JP2008297900A - Filling portion and construction method therefor - Google Patents

Filling portion and construction method therefor Download PDF

Info

Publication number
JP2008297900A
JP2008297900A JP2008234361A JP2008234361A JP2008297900A JP 2008297900 A JP2008297900 A JP 2008297900A JP 2008234361 A JP2008234361 A JP 2008234361A JP 2008234361 A JP2008234361 A JP 2008234361A JP 2008297900 A JP2008297900 A JP 2008297900A
Authority
JP
Japan
Prior art keywords
embankment
girder
backfill material
bottom plate
span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008234361A
Other languages
Japanese (ja)
Other versions
JP4937979B2 (en
Inventor
Tadashi Yoshikawa
正 吉川
Takeshi Narahara
健 楢原
Tomoyuki Uo
朋之 宇尾
Kenichi Suzuki
健一 鈴木
Keita Masumoto
恵太 桝本
Nobuhide Sano
演秀 佐野
Moriyuki Shimai
森幸 嶋井
Yutaka Kotaki
裕 小滝
Shinji Muroi
進次 室井
Koichiro Ono
幸一郎 小野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Nippon Steel Engineering Co Ltd
Nippon Steel Bridge Co Ltd
Original Assignee
Kajima Corp
Nippon Steel Engineering Co Ltd
Nippon Steel Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Nippon Steel Engineering Co Ltd, Nippon Steel Bridge Co Ltd filed Critical Kajima Corp
Priority to JP2008234361A priority Critical patent/JP4937979B2/en
Publication of JP2008297900A publication Critical patent/JP2008297900A/en
Application granted granted Critical
Publication of JP4937979B2 publication Critical patent/JP4937979B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a filling portion and a construction method therefor, which enable a construction of the filling portion in a narrow regular working area. <P>SOLUTION: Two rows of T-type precast protecting walls 43 are placed in a planned location of a filling portion 23 to form a base panel 71, where a backfilling material 61 is placed. An L-type precast protecting wall 65 is placed on one edge of the base panel 71 to form a side 73, where backfilling is performed with a backfilling material 67. The L-type precast protecting wall 65 is also placed on the other edge of the base panel 71, where backfilling is performed with the backfilling material 67. Hence the filling portion 23 is constructed. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、盛土部の構築方法、盛土部に関するものである。   The present invention relates to a method for constructing a bank and a bank.

従来、都市部における道路の平面交差は、交通渋滞の大きな原因となっている。そこで、交差部の通過交通と右折左折交通を立体化することにより、通過交通を減速あるいは停止させることなく通過させることが可能となる。従来、オーバーパスの立体交差を短期間で施工する方法がある(例えば、特許文献1参照)。
特願2001−396946号公報
Conventionally, road intersections in urban areas have been a major cause of traffic congestion. Therefore, by making the passing traffic at the intersection and the right turn and left turn traffic three-dimensional, it is possible to pass the passing traffic without decelerating or stopping. Conventionally, there is a method of constructing an overpass solid intersection in a short period of time (see, for example, Patent Document 1).
Japanese Patent Application No. 2001-396946

しかしながら、構造物幅が8.5m以上の片側2車線の立体交差を構築する際には、9〜10m以上の幅の作業帯が必要となる。都市部の道路では昼間の通行制限は難しく、広い常設作業帯が確保できない場合、工法として成立しない。   However, when constructing a solid intersection of two lanes on one side with a structure width of 8.5 m or more, a work zone with a width of 9 to 10 m or more is required. It is difficult to restrict daytime traffic on urban roads, and if a large permanent work zone cannot be secured, it will not be established as a construction method.

本発明は、このような問題に鑑みてなされたもので、その目的とするところは、狭い常設作業帯で施工可能な盛土部の構築方法、盛土部を提供することにある。   This invention is made | formed in view of such a problem, The place made into the objective is to provide the construction method and embankment part of the embankment part which can be constructed in a narrow permanent work zone.

前述した目的を達成するための第1の発明は、2列の先行する側部および底版部を形成する工程(a)と、前記先行する側部の間に第1の埋め戻し材を充填する工程(b)と、前記底版部の片側の縁に第1の本設側部を形成する工程(c)と、前記先行する側部と前記第1の本設側部の間に第2の埋め戻し材を充填する工程(d)と、前記底版部のもう一方の縁に第2の本設側部を形成する工程(e)と、前記先行する側部と前記第2の本設側部の間に第3の埋め戻し材を充填する工程(f)とを具備することを特徴とする盛土部の構築方法である。   The first invention for achieving the above-described object is the step (a) of forming two rows of preceding side portions and bottom plate portions, and the first backfill material is filled between the preceding side portions. A step (b), a step (c) of forming a first permanent side portion at one edge of the bottom plate portion, and a second gap between the preceding side portion and the first permanent side portion. A step (d) of filling a backfill material, a step (e) of forming a second permanent side portion on the other edge of the bottom plate portion, the preceding side portion and the second permanent side And a step (f) of filling a third backfilling material between the portions.

盛土部を構築するための施工ヤードが狭い場合には、工程(c)および工程(d)によって盛土部上に少なくとも2車線を確保した後、工程(e)および工程(f)を行う。施工ヤードが十分な場合には、工程(c)から工程(d)と、工程(e)から工程(f)を並行して行ってもよい。   When the construction yard for constructing the embankment is narrow, after securing at least two lanes on the embankment by the steps (c) and (d), the steps (e) and (f) are performed. When the construction yard is sufficient, the process (c) to the process (d) and the process (e) to the process (f) may be performed in parallel.

2列の先行する側部は、橋軸直角方向の断面が逆T字型またはL字型のプレキャスト部材を2列に並べて形成される。または、矢板を2列に並べて形成してもよい。底版部は、プレキャスト部材や矢板を設置した後、現場打ちコンクリートを打設して形成される。   Two rows of preceding side portions are formed by arranging pre-cast members whose cross-sections in the direction perpendicular to the bridge axis are inverted T-shaped or L-shaped in two rows. Or you may form a sheet pile in 2 rows. The bottom plate portion is formed by placing a precast member and a sheet pile and then placing cast-in-place concrete.

第1の本設側部および第2の本設側部は、橋軸直角方向の断面がL字型のプレキャスト部材を、底版部上に配置して形成される。   The first permanent side portion and the second permanent side portion are formed by disposing a precast member having an L-shaped cross section in the direction perpendicular to the bridge axis on the bottom plate portion.

第1の埋め戻し材、前記第2の埋め戻し材、前記第3の埋め戻し材は、軽量骨材、軽量材とジオテキスタイル、発泡プラスチック等である。埋め戻し材は、人力で設置できるような軽量のものとするのが望ましい。   The first backfill material, the second backfill material, and the third backfill material are lightweight aggregates, lightweight materials and geotextiles, foamed plastics, and the like. The backfill material is preferably lightweight so that it can be installed manually.

第1の発明では、まず、先行する側部および底版部を形成し、先行する側部の間に埋め戻し材を充填する。そして、先行する側部の外側に本設側部を形成し、先行する側部と本設側部の間にも埋め戻し材を充填する。本設側部は、施工場所の条件に応じて、片側ずつ形成してもよいし、両側を並行して形成してもよい。   In the first invention, first, the leading side portion and the bottom plate portion are formed, and the backfill material is filled between the preceding side portions. Then, the main side is formed outside the leading side, and the backfill material is filled between the leading side and the main side. The main side may be formed one side at a time, or both sides may be formed in parallel, depending on the conditions of the construction site.

第2の発明は、第1の発明の盛土部の構築方法を用いて構築された盛土部である。   2nd invention is the embankment part constructed | assembled using the construction method of the embankment part of 1st invention.

本発明によれば、狭い常設作業帯で施工可能な盛土部の構築方法、盛土部を提供できる。   ADVANTAGE OF THE INVENTION According to this invention, the construction method and embankment part of the embankment part which can be constructed with a narrow permanent work zone can be provided.

以下、図面に基づいて、本発明の実施例を詳細に説明する。図1は、道路橋1の平面図、図2は、道路橋1の立面図を示す。図1に示すように、道路橋1は、基礎である支持杭5、フーチング7、側径間桁13、中央径間桁15、橋脚17、橋台19、盛土部23等からなる。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a plan view of the road bridge 1, and FIG. 2 is an elevation view of the road bridge 1. As shown in FIG. 1, the road bridge 1 includes a support pile 5, a footing 7, a side span girder 13, a central span girder 15, a bridge pier 17, an abutment 19, a banking portion 23, and the like.

図3は、道路橋1の構築方法を示すフローチャート、図4は、側径間主桁25を組み立てた状態の平面図、図5は側径間主桁25をジャッキアップする前の状態の立面図を示す。以下に、図3のフローチャートを用いて、道路3(図1)上に道路橋1を構築する方法について説明する。   3 is a flowchart showing a construction method of the road bridge 1, FIG. 4 is a plan view of the side span main girder 25 assembled, and FIG. 5 is a state before the side span main girder 25 is jacked up. A plane view is shown. Below, the method of constructing the road bridge 1 on the road 3 (FIG. 1) is demonstrated using the flowchart of FIG.

図4に示す道路橋1の計画位置37に道路橋1を構築するには、まず、道路3上に確保された夜間作業帯35を使用して、ジャッキ支持杭兼用基礎である支持杭5、フーチング7を構築する(ステップ101)。支持杭5およびフーチング7は、ジャッキである昇降装置27(図5)の支持杭と、橋脚17や橋台19の基礎を兼ねるものである。支持杭5は、地盤11の支持層9まで根入れされる。計画された道路橋1が片側2車線の場合、常設作業帯33の幅は5〜6m程度、夜間作業帯35の幅は12m程度とする。   In order to construct the road bridge 1 at the planned position 37 of the road bridge 1 shown in FIG. 4, first, using the night work zone 35 secured on the road 3, the support pile 5 serving as a jack support pile combined foundation, A footing 7 is constructed (step 101). The support pile 5 and the footing 7 serve as the support pile of the lifting device 27 (FIG. 5) that is a jack and the foundation of the pier 17 and the abutment 19. The support pile 5 is embedded to the support layer 9 of the ground 11. When the planned road bridge 1 has two lanes on one side, the width of the permanent work zone 33 is about 5 to 6 m, and the width of the night work zone 35 is about 12 m.

次に、昇降装置27及び側径間主桁25を設置する(ステップ102)。側径間主桁25は、側径間桁13(図1)の主桁であり、箱桁等とする。側径間主桁25は、架台(図示せず)等の上で組み立てられる。   Next, the elevating device 27 and the side span main girder 25 are installed (step 102). The side span main girder 25 is the main girder of the side span girder 13 (FIG. 1), and is a box girder or the like. The side span main girder 25 is assembled on a frame (not shown) or the like.

昇降装置27は、側径間主桁15のコーナー部に設置された脚29、脚に取り付けられた駆動装置31からなる。脚29は、側径間主桁25の組み立てと並行して、フーチング7上に設置される。側径間主桁25は、駆動装置31を介して脚29に取り付けられる。   The elevating device 27 includes a leg 29 installed at a corner portion of the side span main girder 15 and a driving device 31 attached to the leg. The legs 29 are installed on the footing 7 in parallel with the assembly of the side span main girder 25. The side span main girder 25 is attached to the leg 29 via the drive device 31.

昇降装置27の設置や、側径間主桁25の組み立ては、夜間作業帯35を使用して行われる。昼間には、常設作業帯33内で、側径間主桁の溶接や塗装等が行われる。   Installation of the lifting device 27 and assembly of the side span main girder 25 are performed using the night work zone 35. In the daytime, the side span main girder is welded or painted in the permanent work zone 33.

ステップ102の後、常設作業帯33を使用して、側径間主桁25をジャッキアップする(ステップ103)。駆動装置31は、側径間主桁25を保持しつつ、脚29に沿って昇降可能である。ステップ103では、昇降装置27を用いて、図5の矢印Aに示すように、側径間主桁25を上昇させる。側径間主桁25は、張出部41(図7)を設置した後、その下方で自動車の通行が可能な程度までジャッキアップされる。   After step 102, the side span main girder 25 is jacked up using the permanent work band 33 (step 103). The driving device 31 can move up and down along the legs 29 while holding the side span main beam 25. In step 103, the side span main girder 25 is raised as shown by the arrow A in FIG. After installing the overhang | projection part 41 (FIG. 7), the side span main girder 25 is jacked up to the grade which can pass a motor vehicle under it.

図6は、側径間主桁25に張出部41を設置した状態での平面図、図7は、側径間主桁25の片側に張出部41を設置した状態での断面図、図8は、側径間主桁25の両側に張出部41を設置した状態での断面図を示す。図7、図8は、図6のB−BまたはC−Cに示す位置での断面図である。   6 is a plan view in a state where the overhanging portion 41 is installed on the side span main girder 25, and FIG. 7 is a cross-sectional view in a state where the overhanging portion 41 is installed on one side of the side span main girder 25. FIG. 8 is a cross-sectional view in a state where the overhang portions 41 are installed on both sides of the side span main girder 25. 7 and 8 are cross-sectional views at the positions indicated by BB or CC in FIG.

側径間主桁25をジャッキアップした後、側径間主桁25に張出部41を取り付ける(ステップ105)。張出部41は、夜間に作業帯を利用して、片方ずつ取り付ける。図7に示すように、側径間主桁25の左車線側に張出部41を固定する際には、夜間には常設作業帯33を左車線側に拡幅した夜間作業帯39a(図6)を使用し、側径間主桁25a、側径間主桁25bの左車線側の側部にそれぞれ張出部41a、張出部41bを取り付ける。昼間には常設作業帯33(図6)を使用し、下方の通行に支障のないボルトの本締め、溶接、塗装などの作業を行う。   After jacking up the side span main girder 25, the overhanging portion 41 is attached to the side span main girder 25 (step 105). The overhanging portion 41 is attached one by one using a work zone at night. As shown in FIG. 7, when the overhanging portion 41 is fixed to the left lane side of the side span main girder 25, the night work zone 39a in which the permanent work zone 33 is widened to the left lane side at night (FIG. 6). ) To attach the overhanging portion 41a and the overhanging portion 41b to the left lane side of the side span main girder 25a and the side span main girder 25b, respectively. During the daytime, the permanent work zone 33 (FIG. 6) is used to perform bolt tightening, welding, painting, etc. that do not hinder downward traffic.

同様に、図8に示すように、側径間主桁25の右車線側に張出部41を固定する際には、夜間には常設作業帯33を右車線側に拡幅した夜間作業帯39bを使用し、側径間主桁25a、側径間主桁25bの右車線側の側部にそれぞれ張出部41a、張出部41bを取り付ける。昼間には常設作業帯33(図6)を使用し、下方の通行に支障のないボルトの本締め、溶接、塗装などの作業を行う。   Similarly, as shown in FIG. 8, when the overhanging portion 41 is fixed to the right lane side of the side span main girder 25, the night work zone 39b in which the permanent work zone 33 is widened to the right lane side at night. The overhanging portion 41a and the overhanging portion 41b are attached to the side portions on the right lane side of the side span main girder 25a and side span main girder 25b, respectively. During the daytime, the permanent work zone 33 (FIG. 6) is used to perform bolt tightening, welding, painting, etc. that do not hinder downward traffic.

図9は、中央径間桁15を組み立てた状態での平面図、図10は、中央径間桁15、盛土部43、橋脚17および橋台19を組み立てる工程での立面図、図11は、中央径間桁15を組み立てた状態での断面図を示す。図11は、図10のF−Fによる断面図である。   9 is a plan view in a state where the central span girder 15 is assembled, FIG. 10 is an elevation view in the process of assembling the central span girder 15, the embankment 43, the pier 17 and the abutment 19, and FIG. Sectional drawing in the state which assembled the center span girder 15 is shown. 11 is a cross-sectional view taken along line FF in FIG.

図6、図8に示すように、側径間主桁25の両側に張出部41を固定して側径間桁13を完成させた後、側径間桁13a上に中央径間桁15を設置する(ステップ106)。中央径間桁15を組み立てる際には、夜間に、夜間作業帯35(図4)を使用して、側径間桁13a上に軌条設備49、台車51を設置し、その上に中央径間桁15を設置する。昼間には、常設作業帯33(図4)を使用して、溶接や塗装等の作業を行う。   As shown in FIGS. 6 and 8, after the side span girder 13 is completed by fixing the overhang portions 41 on both sides of the side span main girder 25, the central span girder 15 is placed on the side span girder 13a. Is installed (step 106). When assembling the central span girder 15, at night, using the night work zone 35 (FIG. 4), the rail equipment 49 and the carriage 51 are installed on the side span girder 13a, and the central span is placed thereon. A girder 15 is installed. In the daytime, the permanent work zone 33 (FIG. 4) is used to perform operations such as welding and painting.

中央径間桁15は、中央径間主桁47と張出部53からなる。中央径間桁15の中央径間主桁47と張出部53は、側径間桁13と同様の分割施工、あるいは同時施工のどちらで組み立ててもよい。   The central span girder 15 includes a central span main girder 47 and an overhang portion 53. The central span main girder 47 and the overhanging portion 53 of the central span girder 15 may be assembled by either the same split construction as the side span girder 13 or simultaneous construction.

ステップ106と並行して、側径間桁13の下方で、ステップ101で未施工の残りの杭5およびフーチング7を構築し、続いて、フーチング7上に橋脚17、橋脚19を構築する(ステップ104)。図10、図11に示すように、中央径間桁13の構築と並行して、側径間桁13aの下方では、フーチング7a上に橋台19aを、フーチング7b上に橋脚17aを構築する。また、側径間桁13bの下方では、フーチング7c上に橋脚17bを、フーチング7d上に橋台19bを構築する。ステップ104は、夜間、昼間を通して行われる。   In parallel with step 106, under the side span girder 13, the remaining pile 5 and footing 7 that are not yet constructed are constructed in step 101, and then the pier 17 and the pier 19 are constructed on the footing 7 (step) 104). As shown in FIGS. 10 and 11, in parallel with the construction of the central span girder 13, the abutment 19a is constructed on the footing 7a and the pier 17a is constructed on the footing 7b below the side span girder 13a. Further, below the side span girder 13b, the pier 17b is constructed on the footing 7c, and the abutment 19b is constructed on the footing 7d. Step 104 is performed throughout the day at night.

図12は、橋脚17および橋台19上に側径間桁13を架設した状態での立面図を、図13は、橋脚17上に側径間桁13を架設した状態での断面図を示す。図13は、図12のL−Lによる断面図である。   FIG. 12 is an elevational view in a state where the side span girder 13 is erected on the pier 17 and the abutment 19, and FIG. 13 is a cross-sectional view in a state in which the side span girder 13 is erected on the pier 17. . 13 is a cross-sectional view taken along line LL in FIG.

ステップ104、ステップ106の後、側径間桁13を橋脚17、橋台19上にジャッキダウンする(ステップ107)。図10に示すように、中央径間桁15の組み立て、橋脚17と橋台19の構築を終えた後、昇降装置27を用いて、中央径間桁15を載せた側径間桁13aを矢印Gに示す方向に下降させ、図12に示すように、橋脚17a、橋台19a上に架設する。同様に、側径間桁13bを矢印Gに示す方向に下降させ、橋脚17b、橋台19b上に架設する。   After step 104 and step 106, the side span girder 13 is jacked down on the pier 17 and the abutment 19 (step 107). As shown in FIG. 10, after the assembly of the central span girder 15 and the construction of the pier 17 and the abutment 19 are finished, the side span girder 13a on which the central span girder 15 is placed is indicated by an arrow G using the lifting device 27. And is installed on the pier 17a and the abutment 19a as shown in FIG. Similarly, the side span girder 13b is lowered in the direction indicated by the arrow G, and is installed on the pier 17b and the abutment 19b.

次に、図12の矢印Mに示すように、橋脚17上に中央径間桁15を押出し(または引出し)架設する(ステップ108)。中央径間桁15は、軌条設備49、台車51、多輪台車63等を用いて、図1に示すように、橋脚17aと橋脚17bの間に架設される。なお、昇降装置27は、側径間桁13の架設後、適宜撤去される。ステップ107、ステップ108を行うときには、30時間程度の集中工事期間113(図3)を設け、昼間に夜間作業帯35(図4)と同じくらいの作業帯を確保する。   Next, as shown by an arrow M in FIG. 12, the central span girder 15 is extruded (or pulled out) on the bridge pier 17 (step 108). The center span girder 15 is constructed between the bridge pier 17a and the bridge pier 17b as shown in FIG. 1 using the rail equipment 49, the carriage 51, the multi-wheel carriage 63, and the like. The lifting device 27 is appropriately removed after the side span girder 13 is installed. When performing Step 107 and Step 108, an intensive construction period 113 (FIG. 3) of about 30 hours is provided, and a work zone as large as the night work zone 35 (FIG. 4) is secured in the daytime.

ステップ105からステップ106と並行して、盛土部23のT型プレキャスト擁壁43を設置し(ステップ109)、底版部71の片側の縁に沿ってL型プレキャスト擁壁65を設置する(ステップ110)。   In parallel with Step 105 to Step 106, the T-shaped precast retaining wall 43 of the embankment portion 23 is installed (Step 109), and the L-shaped precast retaining wall 65 is installed along one edge of the bottom plate portion 71 (Step 110). ).

図14は、盛土部23の底版部71を構築した状態での断面図、図15は、底版部71の片側の縁に沿ってL型プレキャスト擁壁65を設置した状態での断面図である。図14は、図9のD−DまたはE−Eに示す位置での断面図、図15は、図10のH−HまたはI−Iに示す位置での断面図である。   FIG. 14 is a cross-sectional view of the embankment portion 23 in a state in which the bottom slab portion 71 is constructed, and FIG. 15 is a cross-sectional view in a state in which an L-shaped precast retaining wall 65 is installed along one edge of the bottom slab portion 71. . 14 is a cross-sectional view at a position indicated by DD or EE in FIG. 9, and FIG. 15 is a cross-sectional view at a position indicated by H-H or II in FIG.

ステップ109、ステップ110は、例えば、ステップ106と並行して行われる。ステップ109では、まず、図14に示すように、道路3の舗装を撤去して地盤11を掘削し、表層改良部21を設ける。そして、表層改良部21上に、断面が逆T字型のプレキャスト部材であるT型プレキャスト擁壁43を2列に並べて配置し、隣り合うT型プレキャスト擁壁43の水平部材42の間に現場打ちコンクリート59を打設して、底版部71を形成する。   Step 109 and step 110 are performed in parallel with step 106, for example. In step 109, first, as shown in FIG. 14, the pavement of the road 3 is removed, the ground 11 is excavated, and the surface layer improvement part 21 is provided. And on the surface improvement part 21, the T type precast retaining wall 43 which is a precast member with a reverse T-shaped cross section is arranged in two rows, and between the horizontal members 42 of the adjacent T type precast retaining walls 43, the site The bottom concrete portion 71 is formed by casting the cast concrete 59.

そして、2列のT型プレキャスト擁壁43の垂直部材44の間に埋め戻し材61を充填し、埋め戻し材61の上に路盤55を設置する。2列のT型プレキャスト擁壁43の垂直部材44は、(先行する)側部として機能する。T型プレキャスト擁壁43の垂直部材44同士の距離は、常設作業帯33の中で施工可能なように、常設作業帯33(図1)の幅より狭いものとする。   Then, the backfill material 61 is filled between the vertical members 44 of the two rows of the T-shaped precast retaining walls 43, and the roadbed 55 is installed on the backfill material 61. The vertical members 44 of the two rows of T-shaped precast retaining walls 43 function as (leading) side portions. The distance between the vertical members 44 of the T-shaped precast retaining wall 43 is narrower than the width of the permanent work band 33 (FIG. 1) so that construction can be performed in the permanent work band 33.

埋め戻し材61には、例えば、軽量骨材、軽量材とジオテキスタイル等を用いる。または、発泡スチロールを用いたEPS工法により埋め戻しを行ってもよい。   For the backfill material 61, for example, a lightweight aggregate, a lightweight material, a geotextile, or the like is used. Or you may backfill by the EPS construction method using a polystyrene foam.

ステップ109では、夜間に夜間作業帯39a、夜間作業帯39b(図6)を使用してT型プレキャスト擁壁43の設置を行う。埋め戻し材61の充填等は、常設作業帯33の外側に覆工盤57を設置した状態で、昼間に常設作業帯33を使用して行うのが好ましい。図14に示すように底版71を構築した後、昼間は、T型プレキャスト擁壁43の両側に、それぞれ2車線が確保される。   In step 109, the T-type precast retaining wall 43 is installed using the night work zone 39a and the night work zone 39b (FIG. 6) at night. The filling of the backfill material 61 is preferably performed using the permanent work band 33 in the daytime with the lining board 57 installed outside the permanent work band 33. After the bottom plate 71 is constructed as shown in FIG. 14, two lanes are secured on both sides of the T-type precast retaining wall 43 in the daytime.

ステップ110では、まず、図15に示すように、底版部71の片側の縁、すなわち2列に設置されたT型プレキャスト擁壁43のうちの一方の水平部材42の上にL型プレキャスト擁壁65を設置する。そして、T型プレキャスト擁壁43とL型プレキャスト擁壁65との間の空間に埋め戻し材67を充填し、その上に路盤55を設置して、舗装工69を行う。   In step 110, first, as shown in FIG. 15, an L-shaped precast retaining wall is placed on one edge of the bottom plate portion 71, that is, on one horizontal member 42 of T-shaped precast retaining walls 43 installed in two rows. 65 is installed. Then, the backfill material 67 is filled in the space between the T-type precast retaining wall 43 and the L-type precast retaining wall 65, and the roadbed 55 is installed thereon, and the pavement 69 is performed.

ステップ110により、盛土部23の片側では、T型プレキャスト部材43の垂直部材44である先行する側部の外側に、本設の側部73が形成される。ステップ110の後、盛土部23の両側にはそれぞれ1車線ずつが、盛土部23の上部には2車線が確保される。   In step 110, on one side of the embankment 23, a permanent side 73 is formed outside the preceding side that is the vertical member 44 of the T-shaped precast member 43. After step 110, one lane is secured on each side of the embankment 23, and two lanes are secured above the embankment 23.

ステップ110の後、底版部71のもう一方の縁に沿ってL型プレキャスト擁壁65を設置し(ステップ111)、盛土部23の埋戻しを行う(ステップ112)。
ステップ111、ステップ112は、例えば、ステップ107、ステップ108と並行して、集中工事期間114中に行われる。
After step 110, an L-shaped precast retaining wall 65 is installed along the other edge of the bottom plate portion 71 (step 111), and the embedding portion 23 is backfilled (step 112).
Steps 111 and 112 are performed during the intensive construction period 114 in parallel with, for example, steps 107 and 108.

図16は、盛土部23の断面図を示す。図16は、図12のJ−JまたはK−Kに示す位置での断面図である。集中工事期間114には、夜間作業帯35(図4)と同等の幅の作業帯が使用できる。この作業帯を使用して、図16に示すように、底版部71のもう一方の縁、すなわちステップ110でL型プレキャスト擁壁65を設置しなかったT型プレキャスト擁壁43の水平部材42の上にもL型プレキャスト擁壁65を設置する。   FIG. 16 shows a cross-sectional view of the embankment 23. 16 is a cross-sectional view at the position indicated by JJ or KK in FIG. During the intensive construction period 114, a work band having the same width as the night work band 35 (FIG. 4) can be used. Using this work band, as shown in FIG. 16, the other edge of the bottom plate portion 71, that is, the horizontal member 42 of the T-type precast retaining wall 43 in which the L-shaped precast retaining wall 65 was not installed in step 110 is used. An L-shaped precast retaining wall 65 is also installed on the top.

ステップ112では、T型プレキャスト擁壁43とステップ111で設置したL型プレキャスト擁壁65との間の空間に埋め戻し材67を充填し、その上に路盤55を設置する。なお、埋め戻し材67として用いる材料や埋め戻し材67の設置方法は、埋め戻し材61と同様である。ステップ111、ステップ112により、盛土部23の両側に、本設の側部73が形成される。   In step 112, the backfill material 67 is filled in the space between the T-shaped precast retaining wall 43 and the L-shaped precast retaining wall 65 installed in step 111, and the roadbed 55 is installed thereon. The material used as the backfill material 67 and the installation method of the backfill material 67 are the same as those of the backfill material 61. By the steps 111 and 112, the main side portions 73 are formed on both sides of the embankment portion 23.

ステップ110、ステップ111で、L型プレキャスト擁壁65の転倒を防止するには、先行して設置したT型プレキャスト擁壁43の水平部材42とL型プレキャスト擁壁65の水平部材64をボルト(図示せず)等で接合する。または、T型プレキャスト擁壁43の垂直部材44とL型プレキャスト擁壁65の垂直部材66をセパレート、タイロッドで連結する。   In steps 110 and 111, in order to prevent the L-shaped precast retaining wall 65 from overturning, the horizontal member 42 of the T-shaped precast retaining wall 43 and the horizontal member 64 of the L-shaped precast retaining wall 65 previously installed are bolts ( (Not shown) or the like. Alternatively, the vertical member 44 of the T-shaped precast retaining wall 43 and the vertical member 66 of the L-shaped precast retaining wall 65 are connected by separate and tie rods.

ステップ105からステップ108までと、ステップ109からステップ112までの工程がそれぞれ終了した後、集中工事期間114を利用して仕上げ工を行う(ステップ113)。ステップ113では、夜間作業帯35(図4)を使用して、盛土部23の舗装工69等を含む、道路橋1の仕上げ工を行い、図1、図2に示す道路橋1を完成する。   After the processes from Step 105 to Step 108 and Step 109 to Step 112 are completed, finishing work is performed using the concentrated work period 114 (Step 113). In step 113, the night work zone 35 (FIG. 4) is used to finish the road bridge 1 including the pavement 69 and the like of the embankment 23, and the road bridge 1 shown in FIGS. 1 and 2 is completed. .

このように、本実施の形態では、側径間桁13を側径間主桁25と張出部41とに分割し、張出部41を夜間に設置するので、張出部41の設置後にその下を通行可能にでき、常設作業帯33が通常より狭い場合にも橋桁を構築できる。また、側径間桁13の完成後は、その上を中央径間桁15の作業ヤードとして使用することができる。側径間主桁25のジャッキアップ後や、側径間桁13の完成後には、これらの下を作業ヤードとして橋脚17や橋台19を構築できる。   As described above, in this embodiment, the side span girder 13 is divided into the side span main girder 25 and the overhang portion 41, and the overhang portion 41 is installed at night. The bridge girder can be constructed even when the permanent work zone 33 is narrower than usual. Further, after the side span girder 13 is completed, it can be used as a work yard for the central span girder 15. After jacking up the side span main girder 25 or completing the side span girder 13, the pier 17 and the abutment 19 can be constructed using the lower side as a work yard.

盛土部23では、T型プレキャスト擁壁43を用いて先行する側部を形成し、L型プレキャスト擁壁65を用いて本設の側部73を片側ずつ形成することで、施工ヤードが狭い場合にも、先行する側部(垂直部材44)の両側や構築されつつある盛土部23の上部に、必要な本数の車線を確保することができる。   In the embankment portion 23, when the construction yard is narrow by forming the leading side portion using the T-shaped precast retaining wall 43 and forming the main side portion 73 one by one using the L-shaped precast retaining wall 65 In addition, a necessary number of lanes can be secured on both sides of the preceding side portion (vertical member 44) and on the upper portion of the embankment portion 23 being constructed.

また、T型プレキャスト擁壁43を用い、T型プレキャスト擁壁43の水平部材42を精度良く設置して底版部71を形成することで、両外側のL型プレキャスト部材65を短時間で設置できる。   Further, by using the T-shaped precast retaining wall 43, the horizontal member 42 of the T-shaped precast retaining wall 43 is accurately installed and the bottom plate portion 71 is formed, so that the outer L-shaped precast members 65 can be installed in a short time. .

さらに、軽量骨材、軽量材とジオテキスタイル、発泡スチロール等の軽量の埋め戻し材61、埋め戻し材67を用いることで、軟弱地盤でも、表層改良部21の施工を簡略化できる。さらに、人出による急速施工が可能で、機械の故障などのリスクを軽減できる。廃材利用の軽量骨材を使用すれば、環境負荷の軽減も可能となる。   Furthermore, by using the lightweight backfill material 61 and backfill material 67 such as lightweight aggregate, lightweight material and geotextile, and polystyrene foam, the construction of the surface layer improvement portion 21 can be simplified even on soft ground. In addition, rapid construction can be performed by people, reducing the risk of machine failure. The use of lightweight aggregate made from waste materials can reduce the environmental burden.

本実施の形態では、短期間で片側2車線の道路橋1を構築できる。   In the present embodiment, the road bridge 1 having two lanes on one side can be constructed in a short period of time.

また、図3では、ステップ105からステップ108と並行して盛土部23の構築を行ったが、盛土部23の構築時期はこれに限らず、必要な作業帯と時間が確保できるときに構築すればよい。   In FIG. 3, the embankment portion 23 is constructed in parallel with steps 105 to 108, but the construction time of the embankment portion 23 is not limited to this, and is constructed when a necessary work zone and time can be secured. That's fine.

さらに、図3では、盛土部23を、ステップ110、ステップ111に示すように、本設の側部を形成するためのL型プレキャスト擁壁65を片側ずつ2段階施工で設置したが、施工ヤードの広さ、資材の運搬・仮置き状況によって、ステップ110とステップ111を並行して行い、両側のL型プレキャスト擁壁65を1段階施工で同時に設置してもよい。   Further, in FIG. 3, the embankment portion 23 is installed in two stages for each side, as shown in steps 110 and 111, in which the L-shaped precast retaining wall 65 for forming the main side portion is installed in one stage. Depending on the size of the material and the transportation / temporary placement of materials, Step 110 and Step 111 may be performed in parallel, and the L-shaped precast retaining walls 65 on both sides may be installed simultaneously in one-stage construction.

本実施の形態では、桁の分割施工方法と、先行する側部を構築する盛土部の施工方法を組み合わせて説明したが、例えば、他の桁の施工方法と、本発明の先行する側部を構築する盛土部の施工方法を組み合わせる場合もある。   In the present embodiment, the girder split construction method and the embankment construction method for constructing the leading side have been described in combination, for example, the other girder construction method and the leading side of the present invention In some cases, the construction method of the embankment part to be constructed is combined.

盛土部23では、T型プレキャスト擁壁43を用いて先行する側部を構築したが、他の部材を用いて先行する側部を構築してもよい。図17、図18は、他の部材を用いて先行する側部を構築した盛土部の断面図を示す。   In the embankment portion 23, the leading side portion is constructed using the T-shaped precast retaining wall 43, but the leading side portion may be constructed using other members. 17 and 18 are cross-sectional views of the embankment portion in which the preceding side portion is constructed using other members.

図17に示す盛土部では、先行する側部を形成する際に、盛土部23のT型プレキャスト擁壁43の代わりに、L型プレキャスト擁壁83が用いられる。2列に並べられたL型プレキャスト擁壁83の間と外側には、場所打ちコンクリート59が打設され、底版部81が形成される。L型プレキャスト部材65は、底版部81の場所打ちコンクリート59上に設置される。   In the embankment shown in FIG. 17, an L-shaped precast retaining wall 83 is used instead of the T-shaped precast retaining wall 43 of the embankment 23 when forming the preceding side portion. Cast-in-place concrete 59 is placed between and outside the L-shaped precast retaining walls 83 arranged in two rows, and a bottom plate portion 81 is formed. The L-shaped precast member 65 is installed on the cast-in-place concrete 59 of the bottom plate portion 81.

図18に示す盛土部では、先行する側部を形成する際に、盛土部23のT型プレキャスト擁壁43の代わりに、矢板87が用いられる。2列に設置された矢板87の間と外側には、場所打ちコンクリート59が打設され、底版部85が形成される。L型プレキャスト部材65は、底版部85の場所打ちコンクリート59上に設置される。   In the embankment shown in FIG. 18, a sheet pile 87 is used instead of the T-type precast retaining wall 43 of the embankment 23 when forming the preceding side part. Cast-in-place concrete 59 is placed between and outside the sheet piles 87 arranged in two rows, and a bottom plate portion 85 is formed. The L-shaped precast member 65 is installed on the cast-in-place concrete 59 of the bottom plate portion 85.

図17、図18に示すように、L型プレキャスト擁壁83や矢板87を用いて先行する側部を形成することにより、盛土部23と同様に、施工ヤードが狭い場合にも、先行する側部の両側や構築されつつある盛土部の上部に、必要な本数の車線を確保することができる。また、軽量骨材、軽量材とジオテキスタイル、発泡スチロール等の軽量の埋め戻し材61、埋め戻し材67や、L型プレキャスト部材65を用いることで、短期間で盛土部を構築できる。   As shown in FIGS. 17 and 18, the leading side is formed by using the L-shaped precast retaining wall 83 and the sheet pile 87, so that the leading side can be used even when the construction yard is narrow, like the embankment portion 23. The necessary number of lanes can be secured on both sides of the section and on the upper part of the embankment being built. Further, by using the lightweight backfill material 61, the backfill material 67, and the L-shaped precast member 65 such as lightweight aggregate, lightweight material and geotextile, and polystyrene foam, the embankment portion can be constructed in a short period of time.

以上、詳細に説明したように、本発明によれば、狭い常設作業帯で施工可能な盛土部の構築方法、盛土部を提供できる。   As described above in detail, according to the present invention, it is possible to provide a method for constructing an embankment that can be constructed in a narrow permanent work zone, and an embankment.

道路橋1の平面図Top view of road bridge 1 道路橋1の立面図Elevated view of road bridge 1 道路橋1の構築方法を示すフローチャートFlow chart showing the construction method of road bridge 1 側径間主桁25を組み立てた状態の平面図Plan view of the state where the side span main girder 25 is assembled 側径間主桁25をジャッキアップする前の状態の立面図Elevated view of the state before jacking up the side span main girder 25 ジャッキアップ後の側径間主桁25に張出部41を設置した状態での平面図A plan view with the overhanging portion 41 installed on the side span main girder 25 after jacking up ジャッキアップ後の側径間主桁25の片側に張出部41を設置した状態での断面図Sectional drawing in the state in which the overhang | projection part 41 was installed in the one side of the side span main girder 25 after jackup ジャッキアップ後の側径間主桁25の両側に張出部41を設置した状態での断面図Sectional drawing in the state where the overhang | projection part 41 was installed in the both sides of the side span main girder 25 after jackup 側径間桁13aの上で中央径間桁15を組み立てた状態の平面図The top view of the state which assembled the center span girder 15 on the side span girder 13a 側径間桁13aの上で中央径間桁15、盛土部43、橋脚17および橋台19を組み立てる工程での立面図Elevated view in the process of assembling the central span girder 15, the embankment 43, the pier 17 and the abutment 19 on the side span girder 13a. 中央径間桁15を組み立てた状態での断面図Sectional view with the center span girder 15 assembled 側径間桁13a、側径間桁13bをジャッキダウンし、橋脚17および橋台19上に側径間桁13を架設した状態での立面図Elevated view with side span girder 13a and side span girder 13b jacked down and side span girder 13 installed on bridge pier 17 and abutment 19 橋脚17上に側径間桁13を架設した状態での断面図Sectional view with side span girder 13 installed on pier 17 盛土部23の底版部を構築した状態での断面図Sectional view in a state where the bottom plate portion of the embankment portion 23 is constructed 底版部71の片側の縁に沿ってL型プレキャスト擁壁65を設置した状態での断面図Sectional drawing in the state which installed the L-shaped precast retaining wall 65 along the edge of the one side of the baseplate part 71 盛土部23の断面図Cross section of embankment 23 他の部材を用いて先行する側部を構築した盛土部の断面図Sectional drawing of the embankment part which built the preceding side part using other members 他の部材を用いて先行する側部を構築した盛土部の断面図Sectional drawing of the embankment part which built the preceding side part using other members

符号の説明Explanation of symbols

1………道路橋
5………支持杭
7………フーチング
9………支持層
11………地盤
13、13a、13b………側径間桁
15………中央径間桁
17、17a、17b………橋脚
19、19a、19b………橋台
23、23a、23b………盛土部
25、25a、25b………側径間主桁
27………昇降装置
41、41a、41b、53………張出部
42、64………水平部材
43、43a、43b、83………T型プレキャスト擁壁
44、66………垂直部材
47………中央径間主桁
59………場所打ちコンクリート
61、67………埋め戻し材
65………L型プレキャスト部材
71、81、85………底版部
73………側部
1 ......... Road bridge 5 ......... Support pile 7 ......... Footing 9 ......... Support layer 11 ......... Ground 13, 13a, 13b ......... Side span girder 15 ......... Center span girder 17, 17a, 17b ...... Abutments 19, 19a, 19b ......... Abutments 23, 23a, 23b ......... Fills 25, 25a, 25b ......... Side span main girder 27 ......... Elevating devices 41, 41a, 41b , 53... Overhang portions 42 and 64... Horizontal members 43, 43 a, 43 b, 83 ... T-shaped precast retaining walls 44 and 66. ... Cast-in-place concrete 61, 67 ... ... Backfill material 65 ... ... L-shaped precast members 71, 81, 85 ... ... Bottom plate part 73 ... ... Side part

Claims (8)

2列の先行する側部および底版部を形成する工程(a)と、
前記先行する側部の間に第1の埋め戻し材を充填する工程(b)と、
前記底版部の片側の縁に第1の本設側部を形成する工程(c)と、
前記先行する側部と前記第1の本設側部の間に第2の埋め戻し材を充填する工程(d)と、
前記底版部のもう一方の縁に第2の本設側部を形成する工程(e)と、
前記先行する側部と前記第2の本設側部の間に第3の埋め戻し材を充填する工程(f)と、
を具備することを特徴とする盛土部の構築方法。
Forming two rows of leading side and bottom plate portions (a);
Filling the first backfill material between the preceding sides (b);
A step (c) of forming a first permanent side portion on one edge of the bottom plate portion;
Filling a second backfill material between the preceding side and the first main side (d);
Forming a second permanent side portion on the other edge of the bottom plate portion (e);
Filling a third backfill material between the preceding side and the second main side (f);
The construction method of the embankment part characterized by comprising.
前記工程(d)の後、盛土部上に少なくとも2車線が確保されることを特徴とする請求項1記載の盛土部の構築方法。   The method for constructing a banking part according to claim 1, wherein at least two lanes are secured on the banking part after the step (d). 前記工程(c)から前記工程(d)と、前記工程(e)から前記工程(f)を並行して行うことを特徴とする請求項1記載の盛土部の構築方法。   The method for constructing an embankment according to claim 1, wherein the steps (c) to (d) and the steps (e) to (f) are performed in parallel. 前記先行する側部は、橋軸直角方向の断面が逆T字型またはL字型のプレキャスト部材を2列に並べて形成されることを特徴とする請求項5記載の盛土部の構築方法。   6. The embankment portion construction method according to claim 5, wherein the preceding side portion is formed by arranging pre-cast members having a reverse T-shaped or L-shaped cross section in a direction perpendicular to the bridge axis in two rows. 前記先行する側部は、矢板を2列に並べて形成されることを特徴とする請求項1記載の盛土部の構築方法。   The method for constructing a banking portion according to claim 1, wherein the preceding side portion is formed by arranging sheet piles in two rows. 前記第1の本設側部および前記第2の本設側部は、橋軸直角方向の断面がL字型のプレキャスト部材を、前記底版部上に配置して形成されることを特徴とする請求項1記載の盛土部の構築方法。   The first permanent side portion and the second permanent side portion are formed by disposing a precast member having a L-shaped cross section in a direction perpendicular to the bridge axis on the bottom plate portion. The construction method of the embankment part of Claim 1. 前記第1の埋め戻し材、前記第2の埋め戻し材、前記第3の埋め戻し材は、軽量骨材、ジオテキスタイル、発泡プラスチック等であることを特徴とする請求項1記載の盛土部の構築方法。   The construction of the embankment portion according to claim 1, wherein the first backfill material, the second backfill material, and the third backfill material are lightweight aggregate, geotextile, foamed plastic, and the like. Method. 請求項1から請求項7のいずれかに記載された盛土部の構築方法により構築されたことを特徴とする盛土部。   The embankment part built by the construction method of the embankment part described in any one of Claims 1-7.
JP2008234361A 2008-09-12 2008-09-12 Construction method of embankment and embankment Expired - Fee Related JP4937979B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008234361A JP4937979B2 (en) 2008-09-12 2008-09-12 Construction method of embankment and embankment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008234361A JP4937979B2 (en) 2008-09-12 2008-09-12 Construction method of embankment and embankment

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003094491A Division JP4233025B2 (en) 2003-03-31 2003-03-31 How to construct a three-dimensional intersection

Publications (2)

Publication Number Publication Date
JP2008297900A true JP2008297900A (en) 2008-12-11
JP4937979B2 JP4937979B2 (en) 2012-05-23

Family

ID=40171658

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008234361A Expired - Fee Related JP4937979B2 (en) 2008-09-12 2008-09-12 Construction method of embankment and embankment

Country Status (1)

Country Link
JP (1) JP4937979B2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03247801A (en) * 1990-02-26 1991-11-06 Nishi Nippon Eng Kk Method for road construction
JPH10266211A (en) * 1997-03-27 1998-10-06 Toa Harbor Works Co Ltd Construction method of lightweight banking
JPH1129948A (en) * 1997-07-10 1999-02-02 Sekisui Plastics Co Ltd Plantable wall surface greening structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03247801A (en) * 1990-02-26 1991-11-06 Nishi Nippon Eng Kk Method for road construction
JPH10266211A (en) * 1997-03-27 1998-10-06 Toa Harbor Works Co Ltd Construction method of lightweight banking
JPH1129948A (en) * 1997-07-10 1999-02-02 Sekisui Plastics Co Ltd Plantable wall surface greening structure

Also Published As

Publication number Publication date
JP4937979B2 (en) 2012-05-23

Similar Documents

Publication Publication Date Title
JP3327191B2 (en) Underground structure and its construction method
KR101344063B1 (en) The construction method of steel-concrete underpass
CN107059667A (en) Door shape assembled armored concrete box culvert and its construction method
JP5015048B2 (en) Expansion method under space of river bridge
JP3586864B2 (en) Underground structure construction method and elevated traffic path
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
JP4406577B2 (en) Digging road
JP4233025B2 (en) How to construct a three-dimensional intersection
JP5915074B2 (en) How to form an underground space under a ground transportation
JP4937979B2 (en) Construction method of embankment and embankment
JP4196267B2 (en) Construction method of multilevel intersection road
JP2005146695A (en) Viaduct structure and method of constructing the same
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP4047660B2 (en) Elevated traffic road foundation structure and elevated traffic road
JP2010168845A (en) Road widening structure
JP2017206882A (en) Method of constructing underground structure
CN111501468A (en) Fabricated road structure and construction process
JP2010168844A (en) Road widening structure
JPH07243269A (en) Method of building underground parking lot
JP2003003420A (en) Supporting member for prefabricated bridge
KR101971554B1 (en) Method constructuring an underground structure using a temporary structure
JP2001207401A (en) Method of constructing grade separated crossing
CN111535104B (en) Road structure around foundation pit support and construction method thereof
KR101109169B1 (en) Method for constructing tunnel using precast concrete panel
JP3854545B2 (en) Box-type transportation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080912

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20100601

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20100601

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110705

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110901

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120207

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120222

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150302

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees