JP2008196894A - Terminal board for control panel test, control panel automatic testing device, and temporary control device - Google Patents

Terminal board for control panel test, control panel automatic testing device, and temporary control device Download PDF

Info

Publication number
JP2008196894A
JP2008196894A JP2007030544A JP2007030544A JP2008196894A JP 2008196894 A JP2008196894 A JP 2008196894A JP 2007030544 A JP2007030544 A JP 2007030544A JP 2007030544 A JP2007030544 A JP 2007030544A JP 2008196894 A JP2008196894 A JP 2008196894A
Authority
JP
Japan
Prior art keywords
control panel
terminal block
test
input
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2007030544A
Other languages
Japanese (ja)
Other versions
JP5379954B2 (en
Inventor
Atsushi Takahashi
淳 高橋
Mutsuro Ashihara
睦郎 足原
Masahiko Kamiyama
雅彦 神山
Koji Nagahisa
宏司 長久
Tomoaki Furukawa
智昭 古川
Akio Kato
秋夫 加藤
Tatsuya Ueji
達哉 上路
Mototsugu Nezu
基嗣 根津
Eikou Hougi
英光 法木
Masateru Hoshino
真輝 星野
Mamoru Kato
守 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2007030544A priority Critical patent/JP5379954B2/en
Publication of JP2008196894A publication Critical patent/JP2008196894A/en
Application granted granted Critical
Publication of JP5379954B2 publication Critical patent/JP5379954B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Abstract

<P>PROBLEM TO BE SOLVED: To provide a terminal board for a nuclear power plant control panel test, a control panel automatic testing device, and a temporary control device, which reduces a time and cost by reducing a work amount during updating, and also reduces an operation risk caused by plant monitoring control function stop. <P>SOLUTION: This terminal board for the control panel test, detachably fixed to a terminal board installed on a control panel when updating a control unit of the control panel, is equipped with: an elongation terminal to be conducted and opened electrically to a terminal of the terminal board; a fixing metal to be fixed to the terminal board; an external apparatus connection cable to be connected to an external apparatus; and an external apparatus interface part. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、制御盤の更新の際に用いられる更新用機器に関し、特に原子力発電所の制御盤の更新の際に用いられる制御盤試験用端子台、制御盤自動試験装置、及び仮設制御装置に関する。   The present invention relates to an updating device used when updating a control panel, and more particularly to a control panel test terminal block, a control panel automatic testing apparatus, and a temporary control apparatus used when updating a control panel of a nuclear power plant. .

原子力発電プラント監視制御システムに使用される制御盤は、定期的に又は機器更新のため、新制御盤に交換されるが、そのための制御盤の更新作業が必要であった。   The control panel used in the nuclear power plant monitoring and control system is replaced with a new control panel periodically or for equipment replacement, but it is necessary to update the control panel.

従来の更新作業において、更新作業中の原子力発電所の監視機能が停止する時間を最小にするために仮設監視装置を用いて更新作業が行われている(特許文献1参照)。   In the conventional update work, the update work is performed using a temporary monitoring device in order to minimize the time during which the monitoring function of the nuclear power plant being updated is stopped (see Patent Document 1).

この仮設監視装置を用いた更新作業の従来例を図10、図11を用いて説明する。
図10、図11は、原子力発電プラント監視制御システムにおけるデジタル制御盤の更新、更新中の機器の監視操作、および入出力信号の確認試験に関する構成図である。
A conventional example of update work using this temporary monitoring device will be described with reference to FIGS.
FIGS. 10 and 11 are configuration diagrams relating to the updating of the digital control panel, the monitoring operation of the device being updated, and the input / output signal confirmation test in the nuclear power plant monitoring and control system.

原子力発電プラントのプロセス量を監視制御するために設置された複数の計測器2はケーブルで端子台12と接続されており、計測器2で検出されたプロセス量は入力信号4として既設制御盤1へ入力される。   A plurality of measuring instruments 2 installed for monitoring and controlling the process quantity of the nuclear power plant are connected to the terminal block 12 by cables, and the process quantity detected by the measuring instrument 2 is used as an input signal 4 for the existing control panel 1. Is input.

端子台12は既設入力ユニット112に接続され、入力信号4は既設入力ユニット112を経由して既設コントローラユニット111へ入力される。既設コントローラユニットでは入力信号4を演算処理するとともに、処理された入力信号4を既設出力ユニット113に出力信号5として出力する。   The terminal block 12 is connected to the existing input unit 112, and the input signal 4 is input to the existing controller unit 111 via the existing input unit 112. The existing controller unit performs arithmetic processing on the input signal 4 and outputs the processed input signal 4 as an output signal 5 to the existing output unit 113.

既設出力ユニット113は端子台12と接続されており、端子台12を経由した出力信号5はケーブルを通して指示計等の表示装置6に表示され、運転員は状態監視を行う。一方、プロセス量の増減操作を行う操作端3に対しては、運転員は操作器7上のスイッチ等により操作を行う。操作器7で入力された操作信号8はケーブルを経由して端子台12へ接続される。   The existing output unit 113 is connected to the terminal block 12, and the output signal 5 passing through the terminal block 12 is displayed on the display device 6 such as an indicator through the cable, and the operator monitors the state. On the other hand, the operator operates the operation end 3 for increasing / decreasing the process amount with a switch or the like on the operation unit 7. The operation signal 8 input from the operation device 7 is connected to the terminal block 12 via a cable.

端子台12は既設入力ユニット112と接続され、操作信号8は既設入力ユニット112を経由して既設コントローラユニット111へ入力される。既設コントローラユニット111では操作信号8により制御演算を実行した後、操作端操作信号9として既設出力ユニット113から出力し、操作端操作信号9は端子台12からケーブルを通して操作端3へ出力され、操作端3が操作される。   The terminal block 12 is connected to the existing input unit 112, and the operation signal 8 is input to the existing controller unit 111 via the existing input unit 112. The existing controller unit 111 executes the control calculation by the operation signal 8 and then outputs the operation end operation signal 9 from the existing output unit 113. The operation end operation signal 9 is output from the terminal block 12 to the operation end 3 through the cable. End 3 is manipulated.

一般に、制御盤の更新を実施する際、ケーブルの解線、接続作業を省略するため、既設制御盤1の筐体と既設制御盤1の端子台12は継続して使用されるが、既設コントローラユニット111、既設入力ユニット112、及び既設出力ユニット113からなる既設の制御ユニット24は撤去され、新設コントローラユニット114、新設入力ユニット115、及び新設出力ユニット116からなる新設の制御ユニット24を設置して更新を行う方式が採用されている。   In general, when the control panel is updated, the casing of the existing control panel 1 and the terminal block 12 of the existing control panel 1 are continuously used in order to omit cable disconnection and connection work. The existing control unit 24 including the unit 111, the existing input unit 112, and the existing output unit 113 is removed, and a new control unit 24 including the new controller unit 114, the new input unit 115, and the new output unit 116 is installed. A method of updating is adopted.

制御ユニットの更新作業中においても、計測器2および操作端3の中にはその運用上連続監視又は操作可能状態の継続が必要な対象機器があり、既設コントローラユニット111、既設入力ユニット112、既設出力ユニット113の撤去中、新設コントローラユニット114、新設入力ユニット115、新設出力ユニット116の設置中、および新設コントローラユニット114、新設入力ユニット115、新設出力ユニット116の確認試験中において、当該制御盤の監視制御機能が失われることがないように更新作業を実施する必要がある。   Even during the updating operation of the control unit, the measuring instrument 2 and the operation end 3 include target devices that need to be continuously monitored for operation or to be continuously operable. The existing controller unit 111, the existing input unit 112, During the removal of the output unit 113, the installation of the new controller unit 114, the new input unit 115, the new output unit 116, and the confirmation test of the new controller unit 114, the new input unit 115, and the new output unit 116, It is necessary to perform update work so that the supervisory control function is not lost.

そのため、図11に示すように仮設監視装置117および仮設操作器118を端子台12の入力信号4、および操作端操作信号9が接続されている端子121へ接続し、入力信号4により計測器2の監視および操作端操作信号9により操作端3の操作を可能としている。また、新設コントローラユニット114、新設入力ユニット115、新設出力ユニット116の確認試験が完了した後、仮設監視装置117および仮設操作器118は取り外し、新設コントローラユニットに切替える。   Therefore, as shown in FIG. 11, the temporary monitoring device 117 and the temporary operating device 118 are connected to the terminal 121 to which the input signal 4 of the terminal block 12 and the operating end operation signal 9 are connected. The operation end 3 can be operated by the monitoring and the operation end operation signal 9. Further, after the confirmation test of the new controller unit 114, the new input unit 115, and the new output unit 116 is completed, the temporary monitoring device 117 and the temporary operation device 118 are removed and switched to the new controller unit.

また、新設コントローラユニット114を既設制御盤1へ設置した後には入出力信号の接続、精度確認が必要である。図11に示すようにアナログ入力確認試験は、試験対象点に対応する端子121へ発生器21を接続し、新設コントローラユニット114に入力される信号を確認して行い、アナログ出力確認試験は新設コントローラユニット114から出力信号を模擬し、試験対象点に対応する端子121へレコーダ22を接続しレコーダ22の指示を確認して行う。   In addition, after the newly installed controller unit 114 is installed on the existing control panel 1, connection of input / output signals and accuracy check are required. As shown in FIG. 11, the analog input confirmation test is performed by connecting the generator 21 to the terminal 121 corresponding to the test target point and confirming the signal input to the new controller unit 114. The analog output confirmation test is performed by the new controller. An output signal is simulated from the unit 114, the recorder 22 is connected to the terminal 121 corresponding to the test target point, and the instruction of the recorder 22 is confirmed.

また、デジタル入力確認試験は試験対象点に対応する端子121を短絡して入力を模擬し、新設コントローラユニット114の信号を確認して行い、デジタル出力確認試験は新設コントローラユニット114から出力信号を模擬し、試験対象点に対応する端子121にランプ23等を接続して行っている。   The digital input confirmation test is performed by short-circuiting the terminal 121 corresponding to the test target point to simulate the input and confirming the signal of the new controller unit 114. The digital output confirmation test is performed by simulating the output signal from the new controller unit 114. Then, the lamp 23 or the like is connected to the terminal 121 corresponding to the test target point.

しかしながら、上記従来の更新作業では、仮設監視装置117および仮設操作器118を設置する際、及びそれらの機器を取り外す際に、端子台12の解線、再接続作業が大量に発生し、この間、連続監視、操作できない期間が発生してしまうという課題があった。また、入出力される信号点数は膨大であるため、試験作業時間も長時間要するという課題もあった。
特開2006−234696号公報
However, in the conventional update work, when the temporary monitoring device 117 and the temporary operation device 118 are installed and when these devices are removed, the terminal block 12 is disconnected and reconnected in large quantities. There was a problem that a period during which continuous monitoring and operation could not be performed occurred. In addition, since the number of input / output signals is enormous, there is a problem that a long test work time is required.
JP 2006-234696 A

上述したように、原子力発電所の制御盤において、制御盤の更新を行う場合、入出力信号の接続および精度確認を実施するが、入出力信号点数は非常に多く、また試験時の信号模擬、及び確認を人間が実施しているため、当該試験にかかる作業量が膨大となり、時間とコストが増大するとともに機能停止期間が増大する。   As described above, in the control panel of a nuclear power plant, when updating the control panel, I / O signal connection and accuracy check are performed, but the number of input / output signals is very large, In addition, since confirmation is performed by a human, the amount of work required for the test is enormous, which increases time and cost and increases the function stop period.

また、原子力発電所においては、その運用上連続監視、操作可能状態の継続が必要な対象機器があり、これらについては制御盤更新の実施期間中仮設装置を接続し、監視操作に対応しているが、この場合においても端子台配線の解線、再接続作業が発生し、切替えのための作業、および機能停止時間が発生してしまう。   In addition, in nuclear power plants, there are target devices that need to be continuously monitored for operation and to be able to be operated. Temporary equipment is connected to these devices during the control panel update period to support monitoring operations. However, even in this case, the terminal block wiring is disconnected and reconnected, and the switching operation and the function stop time occur.

そこで、本発明の目的は、この制御盤の更新作業における上記問題を解決し、更新時の作業量を減らすことで時間とコストを低減し、またプラント監視制御機能停止による運用上のリスクの低減を可能とする制御盤試験用端子台、制御盤自動試験装置、及び仮設制御装置を提供することにある。   Accordingly, an object of the present invention is to solve the above problems in the update work of the control panel, reduce time and cost by reducing the amount of work at the time of update, and reduce operational risk by stopping the plant monitoring control function. It is an object to provide a control panel test terminal block, a control panel automatic test apparatus, and a temporary control apparatus.

上記課題を解決するために、本発明に係る制御盤試験用端子台は、制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台であって、前記制御盤試験用端子台は、前記端子台の端子と電気的に導通、開放する延長端子と、前記端子台に固定されるための固定用金具と、外部機器と接続するための外部機器接続ケーブルと、外部機器インターフェース部と、からなることを特徴とする。   In order to solve the above problems, a control panel test terminal block according to the present invention is a control panel test terminal block that is detachably fixed to a terminal block installed in the control panel when the control unit of the control panel is updated. The control board test terminal block is connected to an extension terminal electrically connected to and open from the terminal block terminal, a fixing bracket to be fixed to the terminal block, and an external device. The external device connecting cable and the external device interface unit.

また、本発明に係る制御盤自動試験装置は、制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台と、前記制御盤試験用端子台と外部機器接続ケーブルを介して接続され新設制御ユニットとの信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い新設コントローラユニットに順次強制的にデータアドレスと模擬データからなる試験信号を入力するとともに、新設コントローラユニットからの模擬出力信号と前記模擬データとを比較することにより、連続して自動的に前記制御ユニットの出力確認試験を行う自動試験装置と、を具備したことを特徴とする。   The control panel automatic test apparatus according to the present invention includes a control panel test terminal block that is detachably fixed to a terminal block installed on the control panel when the control unit of the control panel is updated, and the control panel test An interface board connected to the terminal block via an external device connection cable to input / output signals to / from the new control unit, and the new controller unit is forcibly sequentially forced to the data address and simulated data according to the confirmation order stored in the storage device in advance. And an automatic test device that automatically and continuously performs an output confirmation test of the control unit by comparing the simulated output signal from the newly installed controller unit with the simulated data. It is characterized by that.

また、本発明に係る制御盤自動試験装置は、制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台と、前記制御盤試験用端子台と外部機器接続ケーブルを介して接続され新設制御ユニットとの信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い順次強制的に模擬信号を制御盤試験用端子台を介して新設コントローラユニットに入力するとともに、前記模擬信号と新設コントローラユニットからの模擬入力信号とを比較することにより、連続して自動的に前記制御ユニットの入力確認試験を行う自動試験装置と、を具備したことを特徴とする。   The control panel automatic test apparatus according to the present invention includes a control panel test terminal block that is detachably fixed to a terminal block installed on the control panel when the control unit of the control panel is updated, and the control panel test An interface board connected to the terminal block via an external device connection cable to input / output signals to / from the newly installed control unit, and a simulation signal forcibly forcing the simulated signals in sequence according to the confirmation order stored in the storage device in advance An automatic test apparatus for automatically performing an input confirmation test of the control unit continuously by comparing the simulated signal with the simulated input signal from the newly installed controller unit, It is characterized by comprising.

また、本発明に係る仮設制御装置は、制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台に外部機器接続ケーブルを介して計測器及び操作端との信号の入出力を行うインターフェースボードと、予め記憶装置に記憶されたプログラムに従い計測器からのプロセス信号を取り込み表示する表示器と、操作端の操作信号を入力する入力装置と、を具備し、制御ユニットの更新中においても任意の機器の連続監視/操作可能状態の継続を可能とすることを特徴とする。   In addition, the temporary control device according to the present invention is measured via an external device connection cable to a control panel test terminal block that is detachably fixed to a terminal block installed on the control panel when the control unit of the control panel is updated. An interface board for inputting and outputting signals to and from the operation terminal, a display for acquiring and displaying a process signal from the measuring instrument according to a program stored in advance in a storage device, and an input device for inputting an operation signal at the operation end The continuous monitoring / operation possible state of any device can be continued even during the update of the control unit.

また、本発明に係る仮設制御装置は、制御盤の更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台に外部機器接続ケーブルを介して新設制御ユニット、計測器及び操作端との信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い新設コントローラユニットに順次強制的にデータアドレスと模擬データからなる試験信号を入力するとともに、新設コントローラユニットからの模擬出力信号と前記模擬データとを比較することにより、連続して自動的に前記制御ユニットの出力確認試験を行い、また予め記憶装置に記憶された確認順序に従い順次強制的に模擬信号を制御盤試験用端子台を介して新設コントローラユニットに入力するとともに、前記模擬信号と新設コントローラユニットからの模擬入力信号を比較することにより、連続して自動的に前記制御ユニットの入力確認試験を行う自動試験装置と、予め記憶装置に記憶されたプログラムに従い計測器からのプロセス信号を取り込み表示する表示器と、を具備し、制御ユニットの更新中においても任意の機器の連続監視/操作可能状態の継続を可能とするとともに、連続して自動的に前記制御ユニットの入出力確認試験の実施を可能とすることを特徴とする。   Further, the temporary control device according to the present invention is a newly installed control unit via an external device connection cable to a control panel test terminal block that is detachably fixed to a terminal block installed in the control panel when the control panel is updated, In addition to an interface board that inputs and outputs signals to and from the measuring instrument and the operation end, a test signal consisting of data addresses and simulated data is forcibly input to the new controller unit in accordance with the confirmation order stored in advance in the storage device. By comparing the simulated output signal from the controller unit and the simulated data, the output confirmation test of the control unit is automatically performed continuously, and the simulation is forcibly sequentially performed according to the confirmation order stored in the storage device in advance. The signal is input to the new controller unit via the control panel test terminal block, and the simulation signal and the new controller By comparing the simulated input signals from the unit, the automatic test device that automatically performs the input confirmation test of the control unit continuously, and the process signal from the measuring instrument is captured and displayed according to the program stored in advance in the storage device A display unit that enables continuous monitoring / operation of any device even while the control unit is being updated and automatically performs an input / output confirmation test of the control unit. It is possible to make it possible.

本発明は、上記構成を有する制御盤試験用端子台、制御盤自動試験装置、及び仮設制御装置を採用したことにより、原子力発電所制御盤の更新時の作業量を減らすことで時間とコストを低減し、またプラント監視制御機能停止による運用上のリスクの低減を可能とする。   The present invention employs the control panel test terminal block, the control panel automatic test device, and the temporary control device having the above-described configuration, thereby reducing time and cost by reducing the amount of work when updating the nuclear power plant control panel. It is possible to reduce operational risks by stopping the plant monitoring and control function.

以下、本発明に係る原子力発電所制御盤試験用端子台、制御盤自動試験装置、及び仮設制御装置の実施の形態について、図面を参照して詳細に説明する。   Hereinafter, embodiments of a nuclear power plant control panel test terminal block, a control panel automatic test apparatus, and a temporary control apparatus according to the present invention will be described in detail with reference to the drawings.

(第1の実施の形態)
本発明の第1の実施の形態に係る制御盤試験用端子台10を図1(a)〜(d)を用いて説明する。
図1(a)は制御盤試験用端子台10の断面図、図1(b)は端子台12の断面図、図1(c)は制御盤試験用端子台10が端子台12に固定された状態を示す断面図、及び図1(d)は外部機器インターフェース部104の拡大図である。
(First embodiment)
A control board test terminal block 10 according to a first embodiment of the present invention will be described with reference to FIGS.
1A is a cross-sectional view of the control board test terminal block 10, FIG. 1B is a cross-sectional view of the terminal block 12, and FIG. 1C is the control board test terminal block 10 fixed to the terminal block 12. FIG. 1D is an enlarged view of the external device interface unit 104, and FIG.

制御盤試験用端子台10は、延長端子101と、端子台12に固定するための固定用金具102と、外部機器接続ケーブル103と、外部機器接続インターフェース部104とから構成される。図1(d)に示されるように、外部機器接続インターフェース部104は、切換スイッチ1041と、端子接続部1042と、外部機器接続ケーブル103が接続されるコネクタ接続部1043から構成される。   The control panel test terminal block 10 includes an extension terminal 101, a fixing bracket 102 for fixing to the terminal block 12, an external device connection cable 103, and an external device connection interface unit 104. As shown in FIG. 1D, the external device connection interface unit 104 includes a changeover switch 1041, a terminal connection unit 1042, and a connector connection unit 1043 to which the external device connection cable 103 is connected.

また、制御盤1に設置されている端子台12は、端子121、固定用金具挿入部122、及び信号ケーブルから構成されている。   Further, the terminal block 12 installed in the control panel 1 includes a terminal 121, a fixing bracket insertion portion 122, and a signal cable.

制御盤の更新において、コントローラユニット111、入力ユニット112、及び出力ユニット113からなる既設の制御ユニット24を新規の制御ユニット24に更新する際、制御盤試験用端子台10が固定用金具102により端子台12へ取り付け固定される(図1(c))。   In updating the control panel, when the existing control unit 24 including the controller unit 111, the input unit 112, and the output unit 113 is updated to a new control unit 24, the control panel test terminal block 10 is connected to the fixing bracket 102. It is fixed to the base 12 (FIG. 1 (c)).

そして、新規のコントローラユニット114、入力ユニット115、及び出力ユニット116ユニットからなる制御ユニット24が設置された後、外部機器接続ケーブル103に接続された外部機器から信号が入力されると、この信号は外部機器接続インターフェース部104及び延長端子101を介して端子121へ入力され、入力信号4、出力信号5、操作信号8、操作信号9として操作端3または新設のユニット114〜116へ入力又は出力される。   Then, after the control unit 24 including the new controller unit 114, the input unit 115, and the output unit 116 unit is installed, when a signal is input from an external device connected to the external device connection cable 103, this signal is The signal is input to the terminal 121 via the external device connection interface unit 104 and the extension terminal 101, and is input or output to the operation terminal 3 or the newly installed units 114 to 116 as the input signal 4, the output signal 5, the operation signal 8, and the operation signal 9. The

この時、外部機器から外部機器接続インターフェース部104へ入力される切替指令1044に基づき切替スイッチ1041が端子とコネクタの接続を切替えることにより、任意の端子121に対して信号を入力することが可能となる。同様に、新設コントローラユニット114、計測器2及び操作端3からの出力信号についても、任意の端子を選択して各信号の外部機器への取出しが可能となる。   At this time, the changeover switch 1041 switches the connection between the terminal and the connector based on the changeover command 1044 input from the external device to the external device connection interface unit 104, so that a signal can be input to any terminal 121. Become. Similarly, with respect to the output signals from the newly installed controller unit 114, the measuring instrument 2, and the operation end 3, it is possible to select arbitrary terminals and take out each signal to an external device.

本第1の実施の形態によれば、原子力発電所の制御盤を更新する際、制御盤の端子台12に制御盤試験用端子台10を接続、固定することで、各端子への外部機器の接続および解線を繰り返すことなく、本設ケーブルを接続したままで容易に任意の端子からの信号取り出し、および任意の端子への信号入力が可能となり、更新時の作業量を大幅に低減することができる。これにより、更新にかかる時間、コスト、およびプラント監視制御機能停止による運用上のリスクを大きく低減することが可能となる。   According to the first embodiment, when the control panel of the nuclear power plant is updated, the control panel test terminal block 10 is connected and fixed to the terminal block 12 of the control panel, so that the external device to each terminal Without repetitive connection and disconnection, it is possible to easily retrieve signals from any terminal and input signals to any terminal while the main cable is connected, greatly reducing the amount of work during renewal. be able to. As a result, it is possible to greatly reduce the time, cost, and operational risk due to the stoppage of the plant monitoring control function.

(第2の実施の形態)
本発明の第2の実施の形態に係る制御盤試験用端子台10を図2(a)〜(c)を用いて説明する。
図2(a)は制御盤試験用端子台10の断面図、図2(b)は端子台12の断面図、図2(c)は制御盤試験用端子台10が端子台12に固定された状態を示す断面図である。
(Second Embodiment)
A control board test terminal block 10 according to a second embodiment of the present invention will be described with reference to FIGS.
2A is a cross-sectional view of the control board test terminal block 10, FIG. 2B is a cross-sectional view of the terminal block 12, and FIG. 2C is a view in which the control board test terminal block 10 is fixed to the terminal block 12. It is sectional drawing which shows the state.

第2の実施の形態に係る制御盤試験用端子台10は、圧着式延長端子101Aと、端子台12に固定するための固定用金具102と、外部機器接続ケーブル103と、外部機器接続インターフェース部104とから構成される。延長端子としてバネ機構と端子台に引っ掛ける固定機構を有する圧接式延長端子101Aを用いた点で第1の実施の形態と異なっている。   The control panel test terminal block 10 according to the second embodiment includes a crimp-type extension terminal 101A, a fixing bracket 102 for fixing to the terminal block 12, an external device connection cable 103, and an external device connection interface unit. 104. This embodiment is different from the first embodiment in that a press contact type extension terminal 101A having a spring mechanism and a fixing mechanism hooked on a terminal block is used as the extension terminal.

制御盤の更新時に、制御盤試験用端子台10に端子台12に固定する際、図2(c)に示されるように圧接式延長端子101Aを有し押し込むことによりバネ機構で端子台12の端子121と接触面にて電気的に導通し、また、固定機構によりバネの反発力で端子が抜けることを防止することが可能となるため、外部機器接続ケーブル103と接続された外部機器から外部機器インターフェース部104を介して、信号の操作端3または新設コントローラ114への出力を可能とする。また同様に、新設コントローラ114、計測器2および操作端3からの出力信号の外部機器への取り出しも可能となる。   When the control board is renewed, when the terminal board 12 is fixed to the control board test terminal block 10, as shown in FIG. The terminal 121 is electrically connected to the contact surface, and the fixing mechanism can prevent the terminal from being pulled out by the repulsive force of the spring, so that the external device connected to the external device connection cable 103 can be externally connected. The signal can be output to the operation end 3 or the new controller 114 via the device interface unit 104. Similarly, the output signals from the newly installed controller 114, the measuring instrument 2, and the operation end 3 can be taken out to an external device.

本第2の実施の形態によれば、延長端子としてバネ機構と端子台に引っ掛ける固定機構を有する圧接式延長端子101Aを用いたことにより、制御盤の端子台に制御盤試験用端子台を確実かつ簡便に接続、固定することが可能なり、制御盤更新にかかる時間、コスト、およびプラント監視制御機能停止による運用上のリスクをさらに低減することができる。   According to the second embodiment, by using the press contact type extension terminal 101A having a spring mechanism and a fixing mechanism that hooks on the terminal block as the extension terminal, the control panel test terminal block can be securely connected to the terminal block of the control panel. In addition, it is possible to easily connect and fix, and it is possible to further reduce the time and cost for updating the control panel, and the operational risk due to the suspension of the plant monitoring control function.

(第3の実施の形態)
本発明の第3の実施の形態に係る自動試験装置14を図3、4を用いて説明する。
図3は全体構成図であり、図4(a)はデータベースの概略図、図4(b)は出力確認試験手順図、及び図4(c)は試験結果入力および判定手順図である。
(Third embodiment)
An automatic test apparatus 14 according to a third embodiment of the present invention will be described with reference to FIGS.
3 is an overall configuration diagram, FIG. 4A is a schematic diagram of a database, FIG. 4B is an output confirmation test procedure diagram, and FIG. 4C is a test result input and determination procedure diagram.

この自動試験装置14は、制御盤試験用端子台10と外部機器接続ケーブル103を介して接続され、新設コントローラユニット114との外部信号の入出力を行うインターフェースボード15と、新設コントローラユニット114とネットワーク17で接続され、データベース化されたコントローラ出力確認試験手順が記憶された記憶装置141と、キーボード等外部よりデータの入力可能な入力装置183とから構成される。   The automatic test apparatus 14 is connected to the control panel test terminal block 10 via an external device connection cable 103, and performs an input / output of an external signal to / from the new controller unit 114, a new controller unit 114 and a network. 17, a storage device 141 that stores a controller output confirmation test procedure that is connected to a database and stores an input device 183 that can input data from the outside such as a keyboard.

自動試験装置14は、入力装置183より入力された種別と端子台NOにより記憶装置141に格納されたデータベースから該当するデータのアドレスと模擬データを、データNOごとに模擬データNOに従って、ネットワーク17を介して新設コントローラユニット114へ試験信号142として送信する。   The automatic test apparatus 14 sets the network 17 in accordance with the simulated data NO for each data NO, the address of the corresponding data and the simulated data from the database stored in the storage device 141 by the type and terminal block NO input from the input device 183. To the newly installed controller unit 114 as a test signal 142.

新設コントローラユニットユニット114は送信されたアドレスに従い自身の出力レジスタに順次強制的に模擬信号を書き込み、新設コントローラユニット114からの出力模擬を行う。コントローラユニットからの模擬出力信号143は、新設出力ユニット116を介して端子台12へ出力される。   The new controller unit unit 114 sequentially forcibly writes a simulation signal to its own output register according to the transmitted address, and simulates the output from the new controller unit 114. The simulated output signal 143 from the controller unit is output to the terminal block 12 via the new output unit 116.

自動試験装置14は、インターフェースボード15の入力機能により制御盤試験用端子台10を介して端子台12からの模擬出力信号143を入力し記憶装置141に格納する。模擬出力信号143を入力する場合、制御盤試験用端子台10のいずれの端子から模擬出力信号143が入力されるかは、データベース中の端子台NOとデータNOから判断可能であり、自動試験装置14では記憶装置141に格納した模擬出力信号143の中から、端子台NOとデータNOにより試験対象点に相当するデータを選択し、データベースの当該模擬データと比較し、デジタル信号の場合は一致すること、アナログ信号の場合は模擬出力信号と模擬データとの偏差を計算し偏差の信号フルスパンに対する誤差がデータベースの誤差欄に指定された値以内にあることを確認し、良否を自動判定し、判定結果としてデータベースに格納する(図4(b)及び(c))。   The automatic test apparatus 14 receives the simulated output signal 143 from the terminal block 12 via the control panel test terminal block 10 by the input function of the interface board 15 and stores it in the storage device 141. When the simulated output signal 143 is input, it is possible to determine from which terminal of the control panel test terminal block 10 the simulated output signal 143 is input from the terminal block NO and the data NO in the database. 14, data corresponding to the test target point is selected from the terminal block NO and data NO from the simulated output signal 143 stored in the storage device 141, and compared with the simulated data in the database. In the case of an analog signal, the deviation between the simulated output signal and the simulated data is calculated, and it is confirmed that the error of the deviation with respect to the signal full span is within the value specified in the error column of the database. The result is stored in the database (FIGS. 4B and 4C).

また、試験結果は試験記録としてプリンタ等外部出力可能とする。なお、インターフェースボード15、外部機器接続ケーブル103および制御盤試験用端子台10の組合せを複数設置し、既設制御盤1の端子台12と接続し、データベースに従って順次上記を繰り返して模擬を行うことにより連続して試験を実施することも可能である。   The test results can be output externally as a test record such as a printer. A plurality of combinations of the interface board 15, the external device connection cable 103, and the control panel test terminal block 10 are installed, connected to the terminal block 12 of the existing control panel 1, and the above is sequentially repeated according to the database and simulated. It is also possible to carry out the test continuously.

本第3の実施の形態によれば、原子力発電所の制御盤更新において制御盤試験用端子台と自動試験装置を使用することにより、各端子台への試験装置の接続および解線を繰り返すことなく、連続して自動的にコントローラユニットの出力確認試験を実施することが出来る。これにより更新時の作業量を低減することができ、更新にかかる時間、コストを低減することが可能である。   According to the third embodiment, the connection and disconnection of the test apparatus to each terminal block is repeated by using the control panel test terminal block and the automatic test apparatus in the control panel update of the nuclear power plant. The controller unit's output confirmation test can be automatically executed continuously. Thereby, the amount of work at the time of updating can be reduced, and the time and cost required for updating can be reduced.

(第4の実施の形態)
本発明の第4の実施の形態に係る制御盤試験用端子台10を図5を用いて説明する。
本第4の実施の形態では、制御盤試験用端子台10は複数台配置され、制御盤試験用端子台連結器13により前記複数の制御盤試験用端子台10が連結、固定されている。このように、制御盤試験用端子台連結器13により複数の制御盤試験用端子台10を連結し、既設制御盤1に収納されている複数の端子台12に接続することで、同時に複数の端子台12から任意の端子121を選択し、信号の入力および取出しが可能となる。
(Fourth embodiment)
A control panel test terminal block 10 according to a fourth embodiment of the present invention will be described with reference to FIG.
In the fourth embodiment, a plurality of control panel test terminal blocks 10 are arranged, and the plurality of control panel test terminal blocks 10 are connected and fixed by a control panel test terminal block coupler 13. In this way, a plurality of control panel test terminal blocks 10 are connected by the control panel test terminal block coupler 13 and connected to the plurality of terminal blocks 12 housed in the existing control panel 1, thereby simultaneously An arbitrary terminal 121 can be selected from the terminal block 12, and a signal can be input and taken out.

本第4の実施の形態によれば、原子力発電所の制御盤更新において、制御盤の複数の端子台に同時に制御盤試験用端子台を接続、固定することで、各端子台への外部機器の接続および解線を繰り返すことなく、本設ケーブルを接続したままで容易に複数の任意の端子から同時に信号取り出しおよび信号入力が可能となり、更新時の作業量を低減することが出来る。これにより、更新にかかる時間、コスト、およびプラント監視制御機能停止による運営リスクを低減することが可能である。   According to the fourth embodiment, in updating the control panel of a nuclear power plant, by connecting and fixing a control panel test terminal block to a plurality of terminal blocks of the control panel at the same time, an external device to each terminal block Without repeating connection and disconnection, it is possible to easily take out signals and input signals simultaneously from a plurality of arbitrary terminals while the main cable is connected, thereby reducing the amount of work during updating. Thereby, it is possible to reduce the time required for the update, the cost, and the operational risk due to the stop of the plant monitoring control function.

(第5の実施の形態)
本発明の第5の実施の形態を図3及び図6(a)〜(c)を用いて説明する。
図3は全体構成図であり、図6(a)はデータベースの概念図、図6(b)は出力確認試験手順図及び図6(c)は試験結果入力および判定手順図である。
(Fifth embodiment)
A fifth embodiment of the present invention will be described with reference to FIGS. 3 and 6A to 6C.
FIG. 3 is an overall configuration diagram, FIG. 6A is a conceptual diagram of a database, FIG. 6B is an output confirmation test procedure diagram, and FIG. 6C is a test result input and determination procedure diagram.

図3において、自動試験装置14は、入力装置183より入力された端子台NOにより記憶装置141に格納されたデータベースから該当するデータのアドレスと模擬データを検索し、該当する模擬データを順次インターフェースボード15の該当する端子へ出力し、インターフェースボード15で模擬データを相当する電圧または電流信号に変換し模擬信号144として、外部機器接続ケーブル103および制御盤試験用端子台10を介して既設制御盤1の端子台12に送信する。さらに端子台12に送信された模擬信号144は、新設入力ユニット115より新設コントローラユニット114へ入力される。   In FIG. 3, the automatic test apparatus 14 retrieves the address and simulated data of the corresponding data from the database stored in the storage device 141 by the terminal block NO input from the input device 183, and sequentially stores the corresponding simulated data in the interface board. 15 is output to the corresponding terminal 15, the simulation data is converted into a corresponding voltage or current signal by the interface board 15, and the simulation control signal 144 is provided as the simulation signal 144 via the external device connection cable 103 and the control panel test terminal block 10. To the terminal block 12. Further, the simulation signal 144 transmitted to the terminal block 12 is input from the new input unit 115 to the new controller unit 114.

新設コントローラユニット114は入力された模擬信号と当該入力レジスタの情報を、ネットワーク17を介して自動試験装置14へ送信する。   The new controller unit 114 transmits the input simulation signal and the information of the input register to the automatic test apparatus 14 via the network 17.

自動試験装置14は、新設コントローラユニット114より入力された模擬信号と入力レジスタを記憶装置141に格納する。その後、格納した模擬信号と入力レジスタをデータベースの模擬信号144として出力した模擬データと比較し、アドレスが一致していること、およびデジタル信号の場合は模擬信号が一致すること、アナログ信号の場合は模擬信号と模擬データとの偏差を計算し、偏差の信号フルスパンに対する誤差がデータベースの誤差欄に指定された値以内にあることを確認し、良否を自動判定し、判定結果としてデータベースに格納する(図6(b),(c))。
また、試験結果は試験記録としてプリンタ等外部出力可能とする。なお、インターフェースボード15、外部機器接続ケーブル103および制御盤試験用端子台10の組合せを複数設置し、既設制御盤1の端子台12と接続し、データベースに従って順次上記を繰り返して模擬を行うことにより、入力装置183からの端子台NOの入力を省略し連続して試験を実施することも可能である。
The automatic test apparatus 14 stores the simulation signal and the input register input from the newly installed controller unit 114 in the storage device 141. After that, the stored simulation signal and the input register are compared with the simulation data output as the simulation signal 144 of the database. If the address is the same, and if the digital signal is a simulation signal, the analog signal is the same. The deviation between the simulated signal and the simulated data is calculated, and it is confirmed that the error of the deviation with respect to the signal full span is within the value specified in the error column of the database. FIG. 6 (b), (c)).
The test results can be output externally as a test record such as a printer. A plurality of combinations of the interface board 15, the external device connection cable 103, and the control panel test terminal block 10 are installed, connected to the terminal block 12 of the existing control panel 1, and the above is sequentially repeated according to the database and simulated. It is also possible to omit the input of the terminal block NO from the input device 183 and continuously perform the test.

本第5の実施の形態によれば、原子力発電所の制御盤更新において制御盤試験用端子台と自動試験装置を使用することにより、実施例3の効果に加えて、各端子台への試験装置の接続および解線を繰り返すことなく、連続して自動的にコントローラの入力確認試験を実施することが出来る。これにより更新時の作業量を低減することができ、更新にかかる時間、コストを低減することが可能である。   According to the fifth embodiment, by using the control panel test terminal block and the automatic test equipment in the control panel update of the nuclear power plant, in addition to the effects of Example 3, the test to each terminal block It is possible to automatically and continuously perform an input confirmation test of the controller without repeating the connection and disconnection of the apparatus. Thereby, the amount of work at the time of updating can be reduced, and the time and cost required for updating can be reduced.

(第6の実施の形態)
本発明の第6の実施の形態に係る仮設制御装置18を、図7、8を用いて説明する。図7は全体構成図であり、図8はデータベースの概念図である。
(Sixth embodiment)
A temporary control device 18 according to a sixth embodiment of the present invention will be described with reference to FIGS. FIG. 7 is an overall configuration diagram, and FIG. 8 is a conceptual diagram of a database.

この仮設制御装置18は、制御盤試験用端子台10を既設制御盤1の端子台12へ接続し、制御盤試験用端子台10と外部機器接続ケーブル103で接続され、新設コントローラユニット114との外部信号の入出力を行うインターフェースボード15と、新設コントローラユニット114とネットワーク17で接続され、仮設監視装置117、および仮設操作器118の機能を表示制御するプログラムを記憶した記憶装置141と、操作機器やプロセス値の状態を表示する表示器182とから構成される。   The temporary control device 18 connects the control panel test terminal block 10 to the terminal block 12 of the existing control panel 1, and is connected to the control panel test terminal block 10 by the external device connection cable 103. An interface board 15 for inputting / outputting external signals, a new controller unit 114 connected to the network 17, a storage device 141 storing programs for controlling the functions of the temporary monitoring device 117 and the temporary operating device 118, and an operating device And a display 182 for displaying the state of the process value.

この仮設制御装置18は、インターフェースボード15の入出力機能により制御盤試験用端子台10を介して監視対象である計測器2からの入力信号4を入力し記憶装置141に格納する。記憶装置141には予め指示計等の表示用機器の画面データを格納しておき表示器182に表示可能としておく。記憶装置141に格納された画面データには表示する計測器2のID情報を記録しておき、データベースのIDと一致するデータを、記憶装置141に格納したデータから取り出し表示器182に表示する。   The temporary control device 18 inputs the input signal 4 from the measuring instrument 2 to be monitored via the control panel test terminal block 10 by the input / output function of the interface board 15 and stores the input signal 4 in the storage device 141. The storage device 141 stores screen data of a display device such as an indicator in advance and can be displayed on the display 182. ID information of the measuring instrument 2 to be displayed is recorded in the screen data stored in the storage device 141, and data that matches the ID of the database is extracted from the data stored in the storage device 141 and displayed on the display 182.

また、記憶装置141には予めスイッチ等の操作端3の画面データを格納しておき表示器182に表示可能とするとともに、入力装置183からの入力による操作信号の入力を可能としておく。記憶装置141に格納された画面データには表示する操作端3のID情報を記録しておき、操作のために選択された操作端3のIDとデータベースのIDとを比較し、一致する操作端に該当するインターフェースボード15の出力端子に入力装置183からの弁開/閉等の操作データを出力し、インターフェースボード15の入出力機能により制御盤試験用端子台10を介して操作対象である操作端3へ操作信号9を出力する(図8)。   Further, screen data of the operation end 3 such as a switch is stored in the storage device 141 in advance so that it can be displayed on the display 182 and an operation signal can be input by an input from the input device 183. The screen data stored in the storage device 141 records the ID information of the operation end 3 to be displayed, compares the ID of the operation end 3 selected for the operation with the ID of the database, and matches the operation end 3 The operation data such as valve opening / closing from the input device 183 is output to the output terminal of the interface board 15 corresponding to the above, and the operation to be operated through the control board test terminal block 10 by the input / output function of the interface board 15 An operation signal 9 is output to the end 3 (FIG. 8).

本第6の実施の形態によれば、原子力発電所の制御盤更新において、コントローラ更新中の場合でも、制御盤試験用端子台と仮設制御装置を使用することにより、各端子台への仮設監視装置、仮設操作器の接続および解線を繰り返すことなく、任意の機器の連続監視、操作可能状態継続が可能となる。これにより更新時の作業量を低減することができ、更新にかかる時間、コスト、およびプラント機能停止による運用上のリスクを低減することが可能である。   According to the sixth embodiment, in the control panel update of the nuclear power plant, even when the controller is being updated, the temporary monitoring of each terminal block is performed by using the control panel test terminal block and the temporary control device. Without repeating the connection and disconnection of the device and the temporary operating device, it is possible to continuously monitor any device and continue the operable state. As a result, the amount of work at the time of updating can be reduced, and it is possible to reduce the time, cost, and operational risk due to the stoppage of plant functions.

(第7の実施の形態)
本発明の第7の実施の形態に係る仮設制御装置19を、図9を用いて説明する。
仮設制御装置19は、新設コントローラユニット114とネットワーク17で接続され、計測器2の検出値の表示と操作端3への操作を行うプログラム、およびデータベース化されたコントローラ入出力確認試験手順が記憶された記憶装置141と、操作機器やプロセス値の状態を表示する表示器182とから構成される。
(Seventh embodiment)
A temporary control device 19 according to a seventh embodiment of the present invention will be described with reference to FIG.
The temporary control device 19 is connected to the new controller unit 114 via the network 17 and stores a program for displaying the detected value of the measuring instrument 2 and operating the operation terminal 3, and a controller input / output confirmation test procedure stored in a database. The storage device 141 and a display 182 for displaying the status of the operation device and the process value.

仮設制御装置19は、記憶装置141に記憶されたプログラムを実行することで、任意の計測器2および操作端3との信号の入出力を行い、操作機器やプロセス値の状態を表示器182へ表示し、表示器182から操作端3に対する操作を実施可能する。またデータベース化されたコントローラ入出力確認試験手順を実行することで、第6の実施の形態に示す入出力試験装置と同様に新設コントローラユニット114への入力模擬および出力模擬を行い、記憶装置141に記憶された模擬信号と新設コントローラユニット114からの模擬入力信号、模擬出力信号との比較を行う。   The temporary control device 19 executes a program stored in the storage device 141 to input / output signals to / from an arbitrary measuring instrument 2 and the operation end 3, and display the status of the operation device and the process value to the display 182. It is possible to perform an operation on the operation end 3 from the display 182. Also, by executing the controller input / output confirmation test procedure stored in the database, the input controller and the output simulation to the newly installed controller unit 114 are simulated as in the input / output test apparatus shown in the sixth embodiment, and the storage device 141 is stored. The stored simulation signal is compared with the simulation input signal and simulation output signal from the newly installed controller unit 114.

本第7の実施の形態によれば、原子力発電所の制御盤更新において制御盤試験用端子台と仮設制御装置を使用することにより、コントローラ更新中の場合でも、各端子台への仮設監視装置、仮設操作器の接続および解線を繰り返すことなく、任意の機器の連続監視、操作可能状態継続が可能となる。またコントローラの新設が済んだ場合にも同じ装置を用いて、機器の連続監視、操作可能状態を継続しながら、各端子台への試験装置の接続および解線を繰り返すことなく、連続して自動的にコントローラの入出力確認試験を実施することが出来る。これにより更新時の作業量を低減することができ、更新にかかる時間、コスト、およびプラント機能停止による運用上のリスクを低減することが可能である。   According to the seventh embodiment, by using the control panel test terminal block and the temporary control device in the control panel update of the nuclear power plant, the temporary monitoring device for each terminal block can be used even when the controller is being updated. Thus, it is possible to continuously monitor any device and continue the operable state without repeating connection and disconnection of the temporary operating device. In addition, when a new controller is installed, the same equipment is used to continuously and continuously monitor the equipment, and continuously and automatically without connecting and disconnecting the test equipment to each terminal block. The controller input / output confirmation test can be performed. As a result, the amount of work at the time of updating can be reduced, and it is possible to reduce the time, cost, and operational risk due to the stoppage of plant functions.

図1(a)は本発明の第1の実施の形態の制御盤試験用端子台の断面図、図1(b)は端子台12の断面図、図1(c)は制御盤試験用端子台が端子台12に固定された状態を示す断面図、及び図1(d)は外部機器インターフェース部の拡大図。1A is a cross-sectional view of a control board test terminal block according to the first embodiment of the present invention, FIG. 1B is a cross-sectional view of the terminal block 12, and FIG. 1C is a control board test terminal. Sectional drawing which shows the state in which the stand was fixed to the terminal block 12, and FIG.1 (d) is an enlarged view of an external apparatus interface part. 図2(a)は本発明の第2の実施形態の制御盤試験用端子台の断面図、図2(b)は端子台の断面図、図2(c)は制御盤試験用端子台が端子台に固定された状態を示す断面図。2A is a cross-sectional view of a control board test terminal block according to a second embodiment of the present invention, FIG. 2B is a cross-sectional view of the terminal block, and FIG. 2C is a control board test terminal block. Sectional drawing which shows the state fixed to the terminal block. 本発明の第3、第5の実施の形態の自動試験装置の全体構成図。The whole block diagram of the automatic test apparatus of the 3rd, 5th embodiment of this invention. 図4(a)は本発明の第4の実施の形態に係るデータベースの概念図、図4(b)は出力確認試験手順図及び図4(c)は試験結果入力および判定手順図。FIG. 4A is a conceptual diagram of a database according to the fourth embodiment of the present invention, FIG. 4B is an output confirmation test procedure diagram, and FIG. 4C is a test result input and determination procedure diagram. 本発明の第4の実施の形態に係る制御盤試験用端子台の構成図。The block diagram of the control panel test terminal block which concerns on the 4th Embodiment of this invention. 図6(a)は、本発明の第5の実施の形態に係るデータベースの概念図、図6(b)は出力確認試験手順図及び図6(c)は試験結果入力および判定手順図。FIG. 6A is a conceptual diagram of a database according to the fifth embodiment of the present invention, FIG. 6B is an output confirmation test procedure diagram, and FIG. 6C is a test result input and determination procedure diagram. 本発明の第6の実施の形態に係る仮設制御装置の全体構成図。The whole block diagram of the temporary control apparatus which concerns on the 6th Embodiment of this invention. 本発明の第6の実施の形態に係る仮設制御装置のデータベースの概念図。The conceptual diagram of the database of the temporary control apparatus which concerns on the 6th Embodiment of this invention. 本発明の第7の実施の形態に係る仮設制御装置の全体構成図。The whole block diagram of the temporary control apparatus which concerns on the 7th Embodiment of this invention. 従来の制御盤更新を示す構成図。The block diagram which shows the conventional control panel update. 従来の制御盤更新における、更新中の監視操作および入出力確認試験技術を示す構成図。The block diagram which shows the monitoring operation and input-output confirmation test technique in the update in the conventional control panel update.

符号の説明Explanation of symbols

1…既設制御盤、2…計測器、3…操作端、4…入力信号、5…出力信号、6…表示装置、7…操作器、8…操作信号、9…操作端操作信号、10…制御盤試験用端子台、12…端子台、14…自動試験装置、15…インターフェースボード、17…ネットワーク、18、19…仮設制御装置、21…発生器、22…レコーダ、23…ランプ、24…制御ユニット、101…延長端子、101A…圧接式延長端子、102…固定用金具、103…外部機器接続ケーブル、104…外部機器インターフェース部、1041…切替スイッチ、1042…端子接続部、1043…コネクタ接続部、1044…切替指令、111…既設コントローラユニット、112…既設入力ユニット、113…既設出力ユニット、114…新設コントローラユニット、115…新設入力ユニット、116…新設出力ユニット、117…仮設監視装置、118…仮設操作器、121…端子、122…固定用金具挿入部、141…記憶装置、142…試験信号、143…模擬出力信号、144…模擬信号、145…模擬入力信号、182…表示器、183…入力装置。   DESCRIPTION OF SYMBOLS 1 ... Existing control panel, 2 ... Measuring instrument, 3 ... Operation end, 4 ... Input signal, 5 ... Output signal, 6 ... Display apparatus, 7 ... Operation device, 8 ... Operation signal, 9 ... Operation end operation signal, 10 ... Control board test terminal block, 12 ... terminal block, 14 ... automatic test device, 15 ... interface board, 17 ... network, 18, 19 ... temporary control device, 21 ... generator, 22 ... recorder, 23 ... lamp, 24 ... Control unit 101 ... Extension terminal 101A ... Press-contact type extension terminal 102 ... Fixing bracket 103 ... External device connection cable 104 ... External device interface unit 1041 ... Changeover switch 1042 ... Terminal connection unit 1043 ... Connector connection , 1044 ... switching command, 111 ... existing controller unit, 112 ... existing input unit, 113 ... existing output unit, 114 ... new controller unit 115 ... Newly installed input unit, 116 ... Newly installed output unit, 117 ... Temporary monitoring device, 118 ... Temporary operating device, 121 ... Terminal, 122 ... Fixing bracket insertion part, 141 ... Storage device, 142 ... Test signal, 143 ... Simulated Output signal, 144 ... simulation signal, 145 ... simulation input signal, 182 ... indicator, 183 ... input device.

Claims (7)

制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台であって、前記制御盤試験用端子台は、前記端子台の端子と電気的に導通、開放する延長端子と、前記端子台に固定されるための固定用金具と、外部機器と接続するための外部機器接続ケーブルと、外部機器インターフェース部と、からなることを特徴とする制御盤試験用端子台。   A control panel test terminal block that is detachably fixed to a terminal block installed in the control panel when the control unit of the control panel is updated, the control panel test terminal block being electrically connected to a terminal of the terminal block. An extension terminal that is electrically conductive and open, a fixing bracket for fixing to the terminal block, an external device connection cable for connecting to an external device, and an external device interface section. Control board test terminal block. 前記延長端子は圧着式延長端子からなることを特徴とする請求項1記載の制御盤試験用端子台。   2. The control panel test terminal block according to claim 1, wherein the extension terminal comprises a crimp-type extension terminal. 前記制御盤試験用端子台が複数設置されるとともに、制御盤試験用端子台連結器により連結、固定されていることを特徴とする請求項1又は2記載の制御盤試験用端子台。   3. The control panel test terminal block according to claim 1, wherein a plurality of the control panel test terminal blocks are installed and connected and fixed by a control panel test terminal block coupler. 制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台と、前記制御盤試験用端子台と外部機器接続ケーブルを介して接続され新設制御ユニットとの信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い新設コントローラユニットに順次強制的にデータアドレスと模擬データからなる試験信号を入力するとともに、新設コントローラユニットからの模擬出力信号と前記模擬データとを比較することにより、連続して自動的に前記制御ユニットの出力確認試験を行う自動試験装置と、を具備したことを特徴とする制御盤自動試験装置。   A control panel test terminal block that is detachably fixed to a terminal block installed in the control panel when the control unit of the control panel is updated, and is newly connected to the control panel test terminal block via an external device connection cable. An interface board that inputs and outputs signals to and from the control unit, and a test signal consisting of a data address and simulated data are forcibly input to the new controller unit in accordance with the confirmation order stored in advance in the storage device. A control panel automatic test apparatus, comprising: an automatic test apparatus for automatically and continuously performing an output confirmation test of the control unit by comparing the simulated output signal with the simulated data. 制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台と、前記制御盤試験用端子台と外部機器接続ケーブルを介して接続され新設制御ユニットとの信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い順次強制的に模擬信号を制御盤試験用端子台を介して新設コントローラユニットに入力するとともに、前記模擬信号と新設コントローラユニットからの模擬入力信号とを比較することにより、連続して自動的に前記制御ユニットの入力確認試験を行う自動試験装置と、を具備したことを特徴とする制御盤自動試験装置。   A control panel test terminal block that is detachably fixed to a terminal block installed in the control panel when the control unit of the control panel is updated, and is newly connected to the control panel test terminal block via an external device connection cable. An interface board for inputting / outputting signals to / from the control unit, and forcibly inputting simulation signals to the newly installed controller unit sequentially through the control panel test terminal block in accordance with the confirmation order stored in the storage device in advance. An automatic test device for automatically and continuously performing an input confirmation test of the control unit by comparing a signal with a simulated input signal from a newly installed controller unit . 制御盤の制御ユニットの更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台に外部機器接続ケーブルを介して計測器及び操作端との信号の入出力を行うインターフェースボードと、予め記憶装置に記憶されたプログラムに従い計測器からのプロセス信号を取り込み表示する表示器と、操作端への操作信号を入力する入力装置と、を具備し、制御ユニットの更新中においても任意の機器の連続監視/操作可能状態の継続を可能とすることを特徴とする仮設制御装置。   When the control unit of the control panel is updated, input and output of signals to and from the measuring instrument and operation terminal are performed via the external device connection cable to the control panel test terminal block that is detachably fixed to the terminal block installed on the control panel. An interface board to be performed, a display that captures and displays a process signal from a measuring instrument in accordance with a program stored in advance in a storage device, and an input device that inputs an operation signal to the operation end, and the control unit is being updated In the temporary control device, the continuous monitoring / operation possible state of any device can be continued. 制御盤の更新時に前記制御盤に設置された端子台に脱着可能に固定される制御盤試験用端子台に外部機器接続ケーブルを介して新設制御ユニット、計測器及び操作端との信号の入出力を行うインターフェースボードと、予め記憶装置に記憶された確認順序に従い新設コントローラユニットに順次強制的にデータアドレスと模擬データからなる試験信号を入力するとともに、新設コントローラユニットからの模擬出力信号と前記模擬データとを比較することにより、連続して自動的に前記制御ユニットの出力確認試験を行い、また予め記憶装置に記憶された確認順序に従い順次強制的に模擬信号を制御盤試験用端子台を介して新設コントローラユニットに入力するとともに、前記模擬信号と新設コントローラユニットからの模擬入力信号を比較することにより、連続して自動的に前記制御ユニットの入力確認試験を行う自動試験装置と、予め記憶装置に記憶されたプログラムに従い計測器からのプロセス信号を取り込み表示する表示器と、を具備し、制御ユニットの更新中においても任意の機器の連続監視/操作可能状態の継続を可能とするとともに、連続して自動的に前記制御ユニットの入出力確認試験の実施を可能とすることを特徴とする仮設制御装置。   Input / output of signals to / from newly installed control unit, measuring instrument and operation terminal via control device test terminal block, which is detachably fixed to the terminal block installed on the control panel when the control panel is updated And a test signal consisting of a data address and simulated data sequentially forcibly input to the new controller unit in accordance with the confirmation order stored in the storage device in advance, and the simulated output signal and the simulated data from the new controller unit To automatically and continuously perform the output confirmation test of the control unit according to the confirmation order stored in advance in the storage device, and forcibly send the simulation signal through the control panel test terminal block. Input to the new controller unit and compare the simulated signal with the simulated input signal from the new controller unit An automatic test device that automatically and continuously performs an input confirmation test of the control unit, and a display that captures and displays a process signal from a measuring instrument in accordance with a program stored in advance in a storage device. In addition, it is possible to continuously monitor / operate an arbitrary device even while the control unit is being updated, and to automatically perform an input / output confirmation test of the control unit continuously. Temporary control device.
JP2007030544A 2007-02-09 2007-02-09 Control panel test terminal block, control panel automatic test device, and temporary control device Expired - Fee Related JP5379954B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007030544A JP5379954B2 (en) 2007-02-09 2007-02-09 Control panel test terminal block, control panel automatic test device, and temporary control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007030544A JP5379954B2 (en) 2007-02-09 2007-02-09 Control panel test terminal block, control panel automatic test device, and temporary control device

Publications (2)

Publication Number Publication Date
JP2008196894A true JP2008196894A (en) 2008-08-28
JP5379954B2 JP5379954B2 (en) 2013-12-25

Family

ID=39755990

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007030544A Expired - Fee Related JP5379954B2 (en) 2007-02-09 2007-02-09 Control panel test terminal block, control panel automatic test device, and temporary control device

Country Status (1)

Country Link
JP (1) JP5379954B2 (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010267057A (en) * 2009-05-14 2010-11-25 Toshiba Corp Equipment replacement method of power generation monitoring control system
JP2010267119A (en) * 2009-05-15 2010-11-25 Toshiba Corp Method for updating of input device
US8659205B2 (en) 2007-06-27 2014-02-25 Brooks Automation, Inc. Motor stator with lift capability and reduced cogging characteristics
US8680803B2 (en) 2007-07-17 2014-03-25 Brooks Automation, Inc. Substrate processing apparatus with motors integral to chamber walls
US8803513B2 (en) 2007-06-27 2014-08-12 Brooks Automation, Inc. Multiple dimension position sensor
US8823294B2 (en) 2007-06-27 2014-09-02 Brooks Automation, Inc. Commutation of an electromagnetic propulsion and guidance system
US9024488B2 (en) 2007-06-27 2015-05-05 Brooks Automation, Inc. Robot drive with magnetic spindle bearings
JP2015146291A (en) * 2014-02-04 2015-08-13 株式会社東芝 Terminal block and exchange method of external control unit using the terminal block
WO2016076077A1 (en) * 2014-11-12 2016-05-19 三菱重工業株式会社 Nuclear power plant control system disassembly method and nuclear power plant control system
CN106646024A (en) * 2016-11-03 2017-05-10 谢梦 Rapid line tester
US9752615B2 (en) 2007-06-27 2017-09-05 Brooks Automation, Inc. Reduced-complexity self-bearing brushless DC motor
JP2018066755A (en) * 2017-12-21 2018-04-26 三菱重工業株式会社 Disassembly method of nuclear plant control system and nuclear plant control system
US11002566B2 (en) 2007-06-27 2021-05-11 Brooks Automation, Inc. Position feedback for self bearing motor
RU2782986C1 (en) * 2021-06-07 2022-11-08 Цзянсуская корпорация по ядерной энергетике Control and measuring device of the detector of the neutron and temperature measuring thimble and the method for its detection

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000013936A (en) * 1998-06-22 2000-01-14 Yaskawa Electric Corp Method for control board renewal
JP2000013937A (en) * 1998-06-29 2000-01-14 Yaskawa Electric Corp Control panel renewal method
JP2000098084A (en) * 1998-09-28 2000-04-07 Toshiba Eng Co Ltd Control panel and terminal stage device for reactor power plant
JP2000275389A (en) * 1999-03-29 2000-10-06 Toshiba Eng Co Ltd Central control panel floor structure of reactor power station
JP2000284811A (en) * 1999-03-31 2000-10-13 Omron Corp Terminal mount and electronic apparatus with terminal mount
JP2002257900A (en) * 2001-02-28 2002-09-11 Advantest Corp Conveyance medium for electronic component to be tested, electronic component testing device, and method of testing
JP2006234696A (en) * 2005-02-25 2006-09-07 Toshiba Corp Alarm control board updating method for plant, and update test monitoring apparatus
JP2006344393A (en) * 2005-06-07 2006-12-21 Mitsubishi Electric Corp Terminal block device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000013936A (en) * 1998-06-22 2000-01-14 Yaskawa Electric Corp Method for control board renewal
JP2000013937A (en) * 1998-06-29 2000-01-14 Yaskawa Electric Corp Control panel renewal method
JP2000098084A (en) * 1998-09-28 2000-04-07 Toshiba Eng Co Ltd Control panel and terminal stage device for reactor power plant
JP2000275389A (en) * 1999-03-29 2000-10-06 Toshiba Eng Co Ltd Central control panel floor structure of reactor power station
JP2000284811A (en) * 1999-03-31 2000-10-13 Omron Corp Terminal mount and electronic apparatus with terminal mount
JP2002257900A (en) * 2001-02-28 2002-09-11 Advantest Corp Conveyance medium for electronic component to be tested, electronic component testing device, and method of testing
JP2006234696A (en) * 2005-02-25 2006-09-07 Toshiba Corp Alarm control board updating method for plant, and update test monitoring apparatus
JP2006344393A (en) * 2005-06-07 2006-12-21 Mitsubishi Electric Corp Terminal block device

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9024488B2 (en) 2007-06-27 2015-05-05 Brooks Automation, Inc. Robot drive with magnetic spindle bearings
US11002566B2 (en) 2007-06-27 2021-05-11 Brooks Automation, Inc. Position feedback for self bearing motor
US8659205B2 (en) 2007-06-27 2014-02-25 Brooks Automation, Inc. Motor stator with lift capability and reduced cogging characteristics
US9752615B2 (en) 2007-06-27 2017-09-05 Brooks Automation, Inc. Reduced-complexity self-bearing brushless DC motor
US8803513B2 (en) 2007-06-27 2014-08-12 Brooks Automation, Inc. Multiple dimension position sensor
US8823294B2 (en) 2007-06-27 2014-09-02 Brooks Automation, Inc. Commutation of an electromagnetic propulsion and guidance system
US8680803B2 (en) 2007-07-17 2014-03-25 Brooks Automation, Inc. Substrate processing apparatus with motors integral to chamber walls
JP2010267057A (en) * 2009-05-14 2010-11-25 Toshiba Corp Equipment replacement method of power generation monitoring control system
JP2010267119A (en) * 2009-05-15 2010-11-25 Toshiba Corp Method for updating of input device
JP2015146291A (en) * 2014-02-04 2015-08-13 株式会社東芝 Terminal block and exchange method of external control unit using the terminal block
WO2016076077A1 (en) * 2014-11-12 2016-05-19 三菱重工業株式会社 Nuclear power plant control system disassembly method and nuclear power plant control system
JP2016095164A (en) * 2014-11-12 2016-05-26 三菱重工業株式会社 Disassembly method of nuclear plant control system and nuclear plant control system
CN106646024A (en) * 2016-11-03 2017-05-10 谢梦 Rapid line tester
JP2018066755A (en) * 2017-12-21 2018-04-26 三菱重工業株式会社 Disassembly method of nuclear plant control system and nuclear plant control system
RU2782986C1 (en) * 2021-06-07 2022-11-08 Цзянсуская корпорация по ядерной энергетике Control and measuring device of the detector of the neutron and temperature measuring thimble and the method for its detection

Also Published As

Publication number Publication date
JP5379954B2 (en) 2013-12-25

Similar Documents

Publication Publication Date Title
JP5379954B2 (en) Control panel test terminal block, control panel automatic test device, and temporary control device
JP2012014584A (en) Test apparatus for plant control apparatus
KR20090046463A (en) A device for testing input output module of distribution control system
JP4731300B2 (en) Monitoring control method and its monitoring control system when replacing remote monitoring control device in electric station
JP4679177B2 (en) Plant alarm control panel update method and update test monitoring device
JP2010072924A (en) Surveillance simulation apparatus
JP2013120483A (en) Playback simulation test system
KR100863672B1 (en) Training simulator of distribution automation system and drivig method there of
JP2008242818A (en) Digital controller
US10178450B2 (en) High-speed converter, measurement system, and computer-readable medium
JP5198343B2 (en) How to update the control panel
JP4686615B2 (en) Maintenance device
JP4282516B2 (en) Maintenance device
JP2525867B2 (en) Fault diagnosis device for plant distributed control system
JP2621913B2 (en) Plant operation control device
JPS63281597A (en) Function checking system for distributed control system
JPH04147095A (en) Replacing method for measurement control equipment of central control room of existing nuclear power plant
EP2682611A2 (en) Apparatus for commanding and controlling the functions of an actuator
JP5438417B2 (en) Equipment test system
JPWO2019171583A1 (en) How to operate the digital protection relay device and the digital protection relay device
JP2018151746A (en) Disconnecting terminal switching system
JP3556443B2 (en) Board testing equipment for digital control equipment
KR100817851B1 (en) Method for electronic components error self-diagnostic
JP5017315B2 (en) Device replacement method for power generation monitoring and control system
JP2008026224A (en) Self-diagnostic method for function diagnostic device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090507

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120703

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120831

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130219

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130422

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130903

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130930

LAPS Cancellation because of no payment of annual fees