JP2000013937A - Control panel renewal method - Google Patents

Control panel renewal method

Info

Publication number
JP2000013937A
JP2000013937A JP10181703A JP18170398A JP2000013937A JP 2000013937 A JP2000013937 A JP 2000013937A JP 10181703 A JP10181703 A JP 10181703A JP 18170398 A JP18170398 A JP 18170398A JP 2000013937 A JP2000013937 A JP 2000013937A
Authority
JP
Japan
Prior art keywords
control panel
panel
relay
temporary
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10181703A
Other languages
Japanese (ja)
Other versions
JP3588793B2 (en
Inventor
Toru Okuda
徹 奥田
Yutaka Enokida
裕 榎田
Atsushi Otani
厚 大谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yaskawa Electric Corp
Original Assignee
Yaskawa Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yaskawa Electric Corp filed Critical Yaskawa Electric Corp
Priority to JP18170398A priority Critical patent/JP3588793B2/en
Publication of JP2000013937A publication Critical patent/JP2000013937A/en
Application granted granted Critical
Publication of JP3588793B2 publication Critical patent/JP3588793B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Feedback Control In General (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method which realizes verification test, corresponding to the actual facilities and renews the facilities without reduction of the operating time of the facilities. SOLUTION: This renewal method changes an existing control panel 1 with a new control panel 2 by the procedures following it, by preferably changing the connection and switching procedures of a relaying panel 7 and a temporary terminal board 9. A temporary control panel 3 similar to the existing control panel 1 is installed to the area near the existing control panel 1, and the relaying panel 7 is provided between these panels. The temporary control panel 3 is operated. Here, the existing control panel 1 is removed, and a new control panel 2 having the temporary terminal board 9 is placed in the same area. The newly installed control panel 2 is operated via the relaying panel 7. The temporary control panel 3 is made to stop, and the temporary control panel 3 and relaying panel 7 are removed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、制御装置を制御盤
によって制御しているとき、活線状態のまま制御盤を新
規のものに更新するという制御盤の更新方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a control panel updating method for updating a control panel to a new one in a hot-line state when a control device is controlled by the control panel.

【0002】[0002]

【従来の技術】従来の多くの制御装置が電力線や信号
線、通信線など多数の配線を介して制御盤によって制御
されている。そのようなシステムが長年使われている
と、新しい制御盤が開発され、操作性や効率、機能等の
点からみて優れている場合は、新しい制御盤と入れ替え
られるというようなことが行われている。そのように、
制御盤を新規のものと入れ替えるときは、概ね次のよう
な手順で更新されていた。 ステップ1:設備を停止する。 ステップ2:既設制御盤と制御装置を接続している配線
を全て外す。 ステップ3:既設制御盤を退避場所に退避させる。 ステップ4:配線を延長し、既設制御盤に接続する。 ステップ5:既設制御盤を一時的に稼動させて動作を確
認する。 ステップ6:当初既設制御盤があった場所に新設制御盤
を設置する。 ステップ7:新設制御盤に模擬回路を接続し、一時的に
稼動させて動作試験をする。 ステップ8:ステップ7で動作が正常であれば、模擬回
路を除去して正規の配線をする。 ステップ9:新設制御盤を稼動させ、動作確認をして更
新を完了する。
2. Description of the Related Art Many conventional control devices are controlled by a control panel via a number of wires such as power lines, signal lines, and communication lines. When such a system has been used for many years, a new control panel has been developed, and if it is superior in terms of operability, efficiency, function, etc., it can be replaced with a new control panel. I have. so,
When the control panel was replaced with a new one, it was generally updated in the following procedure. Step 1: Shut down the equipment. Step 2: Remove all wiring connecting the existing control panel and the control device. Step 3: The existing control panel is evacuated to the evacuation place. Step 4: Extend the wiring and connect to the existing control panel. Step 5: The existing control panel is temporarily operated to check the operation. Step 6: Install a new control panel at the place where the existing control panel was originally located. Step 7: Connect a simulation circuit to the newly installed control panel and temporarily operate it to perform an operation test. Step 8: If the operation is normal in step 7, the simulated circuit is removed and regular wiring is performed. Step 9: Activate the new control panel, confirm the operation, and complete the update.

【0003】[0003]

【発明が解決しようとする課題】ところが、この従来の
方法では次のような問題があった。 (1)模擬回路を使用するため、実際の設備に即した検
証試験をするのに多大な時間を要する。 (2)切替えに際して、設備の停止時間が長くかかり、
稼動時間が減少して実質的なコスト高となっている。
However, this conventional method has the following problems. (1) Since a simulation circuit is used, it takes a lot of time to perform a verification test based on actual equipment. (2) When switching, it takes a long time to stop the equipment,
Uptime has been reduced and costs have been substantially increased.

【0004】[0004]

【課題を解決するための手段】そこで本発明の制御盤更
新方法は、既設制御盤と、その既設制御盤によって制御
される制御装置と、前記既設制御盤と前記制御装置を接
続する多数の配線とで構成する稼働中のシステムにおい
て、次の手順によって前記既設制御盤を新設制御盤に入
れ替えることを特徴としたのである。 ステップ1:既設制御盤と同じ仮設制御盤をその既設制
御盤の近くに設置し、2接点を持つ中継盤をその間に置
く。 ステップ2:前記中継盤の2接点のうち、開いたa接点
の一方の端子に中継ケーブルを接続し、その中継ケーブ
ルの他端を前記既設制御盤に導く。またa接点のもう一
方の端子に別の中継ケーブルを接続し、その中継ケーブ
ルの他端を前記仮設制御盤のI/Oに接続する。 ステップ3:前記既設制御盤が稼働中のまま前記既設制
御盤と制御装置の間の配線と前記中継ケーブルを直スリ
ーブ接続し、前記中継盤のa接点を閉じる。 ステップ4:前記仮設制御盤を稼動させ、前記直スリー
ブ接続部と前記既設制御盤のI/Oの間を切断する。 ステップ5:前記既設制御盤を撤去し、そこに仮端子台
を備えた新設制御盤を設置する。 ステップ6:前記仮端子台の1端子を前記制御装置に接
続し、もう一端子を別の中継ケーブルで前記中継盤の開
いた接点bに接続する。 ステップ7:前記中継盤の接点bを閉じて前記制御装置
の信号を前記新設制御盤に入力する。 ステップ8:前記仮端子台の接続を切替え、前記制御装
置の信号を前記中継盤を経ずして前記新設制御盤に入力
する。 ステップ9:前記中継ケーブルと前記中継盤、前記既設
制御盤を撤去する。 以上の手順を踏むことによって、設備の停止時間と更新
のための作業を最小に保ち、実際の設備に即した確実な
試験をすることができるのである。
Accordingly, a control panel updating method according to the present invention comprises an existing control panel, a control device controlled by the existing control panel, and a large number of wires connecting the existing control panel and the control device. In the operating system configured as above, the existing control panel is replaced with a new control panel by the following procedure. Step 1: Install the same temporary control panel as the existing control panel near the existing control panel, and place a relay panel with two contacts between them. Step 2: A relay cable is connected to one terminal of the open a-contact among the two contacts of the relay panel, and the other end of the relay cable is guided to the existing control panel. Another relay cable is connected to the other terminal of the a contact, and the other end of the relay cable is connected to the I / O of the temporary control panel. Step 3: While the existing control panel is in operation, the wiring between the existing control panel and the control device and the relay cable are connected directly to the sleeve, and the contact a of the relay panel is closed. Step 4: The temporary control panel is operated to disconnect between the straight sleeve connection portion and the I / O of the existing control panel. Step 5: The existing control panel is removed, and a new control panel having a temporary terminal block is installed there. Step 6: One terminal of the temporary terminal block is connected to the control device, and the other terminal is connected to the open contact b of the relay board with another relay cable. Step 7: Close the contact b of the relay board and input the signal of the control device to the new control board. Step 8: The connection of the temporary terminal block is switched, and the signal of the control device is input to the new control panel without passing through the relay panel. Step 9: removing the relay cable, the relay panel, and the existing control panel. By performing the above procedure, the downtime of the equipment and the work for renewal can be kept to a minimum, and a reliable test can be performed according to the actual equipment.

【0005】[0005]

【発明の実施形態】以下、本発明の実施の形態を図に基
づいて説明する。図1は本発明の方法を適用した制御盤
の更新作業の経過を配線状況とともに示す図であり、図
2はその手順を示すフローチャートである。図におい
て、1は取替えようとする既設制御盤、2は新しく取り
入れる新設制御盤、3は移設の過程で使用する仮設制御
盤、4は既設制御盤1のI/O、5は新設制御盤2のI
/O、6は仮設制御盤3のI/O、7は2つの接点を持
つ中継盤、8は2本の配線を接続する直スリーブ接続
部、9は仮端子台、10、14は配線、11は中継ケー
ブル、12、13は伝送ケーブルである。なお図1で
は、配線10をはじめとして全ての線を1本の線で描い
ているが、実際は多数の線が使われて束ねられており、
その全ての線について以下に説明するものと同じように
取り扱う。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a diagram showing the progress of the update work of the control panel to which the method of the present invention is applied, together with the wiring status, and FIG. 2 is a flowchart showing the procedure. In the figure, 1 is an existing control panel to be replaced, 2 is a newly installed control panel, 3 is a temporary control panel used in the process of relocation, 4 is the I / O of the existing control panel 1, and 5 is a new control panel 2. I
I / O 6 is an I / O of the temporary control panel 3, 7 is a relay panel having two contacts, 8 is a straight sleeve connecting portion for connecting two wires, 9 is a temporary terminal block, 10 and 14 are wires, 11 is a relay cable, and 12 and 13 are transmission cables. In FIG. 1, all the lines including the wiring 10 are drawn by one line, but actually, many lines are used and bundled,
All the lines are treated in the same way as described below.

【0006】既設制御盤1と新設制御盤2、仮設制御盤
3はそれぞれ入出力部のI/O4、5、6を介して外部
と接続され、制御信号については信号入出力部の伝送を
介して制御装置と接続されるようになっている。なお、
伝送と制御装置の間の伝送ケーブルの取扱いも、I/O
4、5、6と制御装置の間の配線の取扱いと同じである
ので、以下では簡略化のため説明を省略する。当初の既
設制御盤1はI/O4を介して配線10が接続され、配
線10の他端は図示しない制御装置が接続されており、
配線10と伝送ケーブル12を経由して既設制御盤1が
制御装置を制御している。このようなシステムにおける
制御盤の更新作業は、本発明の方法によると、図2のフ
ローチャートに沿った次の手順によって行われる。 (ステップ1:S1)まず初めに既設制御盤1と同じ仮
設制御盤3を既設制御盤1の近くに設置し、2接点を持
つ中継盤7をその間に置く。 (ステップ2:S2)中継盤7の2接点のうち、開いた
a接点の一方の端子に中継ケーブル11を接続し、その
中継ケーブル11の他端を既設制御盤1に導く。またa
接点のもう一方の端子に別の中継ケーブル11を接続
し、その中継ケーブル11の他端を仮設制御盤3のI/
O6に接続する。(ステップ3:S3)既設制御盤1が
稼働中のまま既設制御盤1と制御装置の間の配線10を
直スリーブ接続し、中継盤7のa接点を閉じる。 (ステップ4:S4)仮設制御盤3を稼動させ、直スリ
ーブ接続部8と既設制御盤1のI/O4の間を切断す
る。 (ステップ5:S5)既設制御盤1を撤去し、仮端子台
9を備えた新設制御盤2を設置する。 (ステップ6:S6)3つの端子を持つ仮端子台9の端
子のうち、中央の端子は新設制御盤2のI/O5に接続
されている。そして、仮端子台9の中央の端子を除く一
方の端子を制御装置に接続し、中央の端子に繋がってい
る他方の端子を中継ケーブル14で中継盤7の開いた接
点bの一方の端子に接続する。接点bの他方の端子は接
点aの一方の端子に接続され、制御装置に繋がってい
る。 (ステップ7:S7)中継盤7の接点bを閉じて制御装
置の信号を新設制御盤2に入力する。そして仮設制御盤
3の動作と比較しながら新設制御盤2の動作をチェック
し、調整作業などを行う。 (ステップ8:S8)仮端子台9の接続を切替え、制御
装置の信号を中継盤7を経ずして新設制御盤2に入力す
る。この状態で新設制御盤2の動作の最終確認をする。
問題があれば、最終調整をする。 (ステップ9:S9)中継ケーブル11と中継盤7、既
設制御盤1を撤去する。以上の手順によって既設制御盤
1を新設制御盤2に置き換えるので、手際良く作業すれ
ば設備の稼動をほとんど停止することなく置換え作業を
進めることができ、稼動停止時間を最小限に抑えること
ができるのである。
The existing control panel 1, the new control panel 2, and the temporary control panel 3 are connected to the outside via I / Os 4, 5, and 6 of input / output units, respectively, and control signals are transmitted via signal input / output units. Connected to the control device. In addition,
Handling of transmission cables between the transmission and the control unit also requires I / O
Since it is the same as the handling of wiring between 4, 5, 6 and the control device, the description is omitted below for simplification. A wiring 10 is connected to the existing existing control panel 1 via an I / O 4, and the other end of the wiring 10 is connected to a control device (not shown).
The existing control panel 1 controls the control device via the wiring 10 and the transmission cable 12. According to the method of the present invention, the update operation of the control panel in such a system is performed by the following procedure according to the flowchart of FIG. (Step 1: S1) First, the same temporary control panel 3 as the existing control panel 1 is installed near the existing control panel 1, and the relay panel 7 having two contacts is placed between them. (Step 2: S2) Of the two contacts of the relay panel 7, the relay cable 11 is connected to one of the open a contacts, and the other end of the relay cable 11 is guided to the existing control panel 1. And a
Another relay cable 11 is connected to the other terminal of the contact, and the other end of the relay cable 11 is connected to the I / O of the temporary control panel 3.
Connect to O6. (Step 3: S3) While the existing control panel 1 is in operation, the wiring 10 between the existing control panel 1 and the control device is directly connected to the sleeve, and the contact a of the relay panel 7 is closed. (Step 4: S4) The temporary control panel 3 is operated to cut off the connection between the straight sleeve connection portion 8 and the I / O 4 of the existing control panel 1. (Step 5: S5) The existing control panel 1 is removed, and the new control panel 2 provided with the temporary terminal block 9 is installed. (Step 6: S6) Of the terminals of the temporary terminal block 9 having three terminals, the center terminal is connected to the I / O 5 of the newly installed control panel 2. Then, one terminal excluding the central terminal of the temporary terminal block 9 is connected to the control device, and the other terminal connected to the central terminal is connected to one terminal of the open contact b of the relay panel 7 with the relay cable 14. Connecting. The other terminal of the contact b is connected to one terminal of the contact a and is connected to the control device. (Step 7: S7) The contact b of the relay panel 7 is closed, and a signal of the control device is input to the new control panel 2. Then, the operation of the new control panel 2 is checked while comparing with the operation of the temporary control panel 3, and adjustment work and the like are performed. (Step 8: S8) The connection of the temporary terminal block 9 is switched, and the signal of the control device is input to the new control panel 2 without passing through the relay panel 7. In this state, the final check of the operation of the new control panel 2 is performed.
If there is a problem, make a final adjustment. (Step 9: S9) The relay cable 11, the relay panel 7, and the existing control panel 1 are removed. Since the existing control panel 1 is replaced with the new control panel 2 by the above-described procedure, the replacement operation can be carried out with almost no stoppage of the operation of the equipment if the work is performed satisfactorily, and the operation stop time can be minimized. It is.

【0007】[0007]

【発明の効果】以上述べたように、本発明によると、従
来に比べ、設備の停止時間を最小に抑えることができ、
設備の更新作業も最小にすることができる。また、実際
の設備に即した試験をするので、試験を確実なものとす
ることができる。したがって、設備更新のためのコスト
を大幅に低減することができ、実用性を高めることがで
きるという効果がある。
As described above, according to the present invention, the downtime of equipment can be minimized as compared with the prior art.
Equipment replacement work can also be minimized. In addition, since the test is performed in accordance with the actual equipment, the test can be made reliable. Therefore, there is an effect that the cost for equipment renewal can be significantly reduced, and the practicability can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の方法を適用した設備の配線状況の経過
を示す図
FIG. 1 is a diagram showing the progress of wiring conditions of equipment to which the method of the present invention is applied.

【図2】本発明の方法の手順を示すフローチャート1
既設制御盤 2 新設制御盤 3 仮設制御盤 4、5、6 I/O 7 中継盤 8 直スリーブ接続部 9 仮端子台 10、14 配線 11 中継ケーブル 12 、13 伝送ケーブル 整理番号 12542
FIG. 2 is a flowchart 1 showing the procedure of the method of the present invention.
Existing control panel 2 New control panel 3 Temporary control panel 4, 5, 6 I / O 7 Relay panel 8 Straight sleeve connection part 9 Temporary terminal block 10, 14 Wiring 11 Relay cable 12, 13 Transmission cable Reference number 12542

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】既設制御盤と、その既設制御盤によって制
御される制御装置と、前記既設制御盤と前記制御装置を
接続する多数の配線とで構成する稼働中のシステムにお
いて、 次の手順によって前記既設制御盤を新設制御盤に入れ替
えることを特徴とする制御盤更新方法。 ステップ1:既設制御盤と同じ仮設制御盤をその既設制
御盤の近くに設置し、2接点を持つ中継盤をその間に置
く。 ステップ2:前記中継盤の2接点のうち、開いたa接点
の一方の端子に中継ケーブルを接続し、その中継ケーブ
ルの他端を前記既設制御盤に導く。またa接点のもう一
方の端子に別の中継ケーブルを接続し、その中継ケーブ
ルの他端を前記仮設制御盤のI/Oに接続する。 ステップ3:前記既設制御盤が稼働中のまま前記既設制
御盤と前記制御装置の間の配線と前記中継ケーブルを直
スリーブ接続し、前記中継盤のa接点を閉じる。 ステップ4:前記仮設制御盤を稼動させ、前記直スリー
ブ接続部と前記既設制御盤のI/Oの間を切断する。 ステップ5:前記既設制御盤を撤去し、そこに仮端子台
を備えた新設制御盤を設置する。 ステップ6:前記仮端子台の1端子を前記制御装置に接
続し、もう一端子を別の中継ケーブルで前記中継盤の開
いた接点bに接続する。 ステップ7:前記中継盤の接点bを閉じて前記制御装置
の信号を前記新設制御盤に入力する。 ステップ8:前記仮端子台の接続を切替え、前記制御装
置の信号を前記中継盤を経ずして前記新設制御盤に入力
する。 ステップ9:前記中継ケーブルと前記中継盤、前記既設
制御盤を撤去する。
An operating system comprising an existing control panel, a control device controlled by the existing control panel, and a number of wires connecting the existing control panel and the control device, comprises the following steps: A control panel updating method, wherein the existing control panel is replaced with a new control panel. Step 1: Install the same temporary control panel as the existing control panel near the existing control panel, and place a relay panel with two contacts between them. Step 2: A relay cable is connected to one terminal of the open a-contact among the two contacts of the relay panel, and the other end of the relay cable is guided to the existing control panel. Another relay cable is connected to the other terminal of the a contact, and the other end of the relay cable is connected to the I / O of the temporary control panel. Step 3: While the existing control panel is in operation, the wiring between the existing control panel and the control device and the relay cable are directly sleeve-connected, and the contact a of the relay panel is closed. Step 4: The temporary control panel is operated to disconnect between the straight sleeve connection portion and the I / O of the existing control panel. Step 5: The existing control panel is removed, and a new control panel having a temporary terminal block is installed there. Step 6: One terminal of the temporary terminal block is connected to the control device, and the other terminal is connected to the open contact b of the relay board with another relay cable. Step 7: Close the contact b of the relay board and input the signal of the control device to the new control board. Step 8: The connection of the temporary terminal block is switched, and the signal of the control device is input to the new control panel without passing through the relay panel. Step 9: removing the relay cable, the relay panel, and the existing control panel.
JP18170398A 1998-06-29 1998-06-29 Control panel update method Expired - Fee Related JP3588793B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18170398A JP3588793B2 (en) 1998-06-29 1998-06-29 Control panel update method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18170398A JP3588793B2 (en) 1998-06-29 1998-06-29 Control panel update method

Publications (2)

Publication Number Publication Date
JP2000013937A true JP2000013937A (en) 2000-01-14
JP3588793B2 JP3588793B2 (en) 2004-11-17

Family

ID=16105388

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18170398A Expired - Fee Related JP3588793B2 (en) 1998-06-29 1998-06-29 Control panel update method

Country Status (1)

Country Link
JP (1) JP3588793B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006234696A (en) * 2005-02-25 2006-09-07 Toshiba Corp Alarm control board updating method for plant, and update test monitoring apparatus
JP2007195368A (en) * 2006-01-20 2007-08-02 Chugoku Electric Power Co Inc:The Switching method of control panel
JP2008196894A (en) * 2007-02-09 2008-08-28 Toshiba Corp Terminal board for control panel test, control panel automatic testing device, and temporary control device
JP2009268232A (en) * 2008-04-24 2009-11-12 Chugoku Electric Power Co Inc:The Control switching method accompanying control panel renewing
JP2011247638A (en) * 2010-05-24 2011-12-08 Toshiba Corp Update method of plant controller
US8404980B2 (en) 2005-09-30 2013-03-26 Fujitsu Semiconductor Limited Relay board and semiconductor device having the relay board
CN107431336A (en) * 2015-04-03 2017-12-01 三菱电机株式会社 The update method of control panel and control panel

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60106307A (en) * 1983-11-10 1985-06-11 三菱電機株式会社 Method of altering control board for plant
JPS62250806A (en) * 1986-04-22 1987-10-31 株式会社東芝 Non-interrupting load changer
JPH03155311A (en) * 1989-11-09 1991-07-03 Toshiba Corp New/old board replacing device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60106307A (en) * 1983-11-10 1985-06-11 三菱電機株式会社 Method of altering control board for plant
JPS62250806A (en) * 1986-04-22 1987-10-31 株式会社東芝 Non-interrupting load changer
JPH03155311A (en) * 1989-11-09 1991-07-03 Toshiba Corp New/old board replacing device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006234696A (en) * 2005-02-25 2006-09-07 Toshiba Corp Alarm control board updating method for plant, and update test monitoring apparatus
JP4679177B2 (en) * 2005-02-25 2011-04-27 株式会社東芝 Plant alarm control panel update method and update test monitoring device
US8404980B2 (en) 2005-09-30 2013-03-26 Fujitsu Semiconductor Limited Relay board and semiconductor device having the relay board
JP2007195368A (en) * 2006-01-20 2007-08-02 Chugoku Electric Power Co Inc:The Switching method of control panel
JP2008196894A (en) * 2007-02-09 2008-08-28 Toshiba Corp Terminal board for control panel test, control panel automatic testing device, and temporary control device
JP2009268232A (en) * 2008-04-24 2009-11-12 Chugoku Electric Power Co Inc:The Control switching method accompanying control panel renewing
JP2011247638A (en) * 2010-05-24 2011-12-08 Toshiba Corp Update method of plant controller
CN107431336A (en) * 2015-04-03 2017-12-01 三菱电机株式会社 The update method of control panel and control panel
CN107431336B (en) * 2015-04-03 2019-07-02 三菱电机株式会社 The update method of control panel and control panel

Also Published As

Publication number Publication date
JP3588793B2 (en) 2004-11-17

Similar Documents

Publication Publication Date Title
JP2008059857A (en) Wiring connection device
JP3588792B2 (en) Control panel update method
JP3588793B2 (en) Control panel update method
US8120210B2 (en) Method and device for line-switching of MEMS matrix and AMDF
JPH03155311A (en) New/old board replacing device
JP2007079932A (en) Equipment operation support system
JP2003345478A (en) Intelligent type device capable of sharing identical user input/output interface by al intelligent type modules
JP3595139B2 (en) Control program test run auxiliary device and control program test run method
JPH05328455A (en) Distributed control system
CN112596480B (en) Double-loop control device, method and system
JPH0739074A (en) Power receiving and transforming facility
JPH07211375A (en) Wiring control device
JPH04329401A (en) Process signal switching device
KR20080009827A (en) Remote control system for cotrolling main power distributor of semiconducor manufacturing equipment
JP2020092545A (en) Connection device
KR100307492B1 (en) Matching apparatus for carrying out the same function in full electronic telephone exchange
JPH10108365A (en) Power distribution system monitor/controller
JPS6043550B2 (en) Communication line control device
JPS6069721A (en) Power source control interface system
JPH0583886A (en) Monitoring and controlling device for power system
JPH11192947A (en) Switching support device for railway signal maintenance system
CN113703423A (en) Vehicle-mounted fault injection equipment, system and control method
JP2019215649A (en) Signal input/output device
JPH06225364A (en) Plant controlling equipment and updating method for the same
JPH0470300A (en) Testing device for electronic interlocking device

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040325

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040726

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040808

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080827

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090827

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090827

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100827

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees