JP2008180082A - Construction method of wall structure having permanent anchor and wall structure having permanent anchor - Google Patents

Construction method of wall structure having permanent anchor and wall structure having permanent anchor Download PDF

Info

Publication number
JP2008180082A
JP2008180082A JP2008066386A JP2008066386A JP2008180082A JP 2008180082 A JP2008180082 A JP 2008180082A JP 2008066386 A JP2008066386 A JP 2008066386A JP 2008066386 A JP2008066386 A JP 2008066386A JP 2008180082 A JP2008180082 A JP 2008180082A
Authority
JP
Japan
Prior art keywords
anchor
wall structure
fixing member
concrete
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008066386A
Other languages
Japanese (ja)
Other versions
JP4333801B2 (en
Inventor
Tadashi Kaneko
正 金子
Toshimi Sudo
敏己 須藤
Tomio Moriwaki
登美夫 森脇
Yukihiro Kanzaka
幸弘 勘坂
Hirokazu Taira
浩和 平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2008066386A priority Critical patent/JP4333801B2/en
Publication of JP2008180082A publication Critical patent/JP2008180082A/en
Application granted granted Critical
Publication of JP4333801B2 publication Critical patent/JP4333801B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Retaining Walls (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To construct a wall structure having a permanent anchor installed in the ground without using a temporary anchor. <P>SOLUTION: A soldier pile 10 is installed, and then an anchor fixing member 12 composed of reinforced concrete is constructed on the soldier pile 10. A slant type permanent anchor 14 is installed and tensed with excavating the ground inside the solder pile 10, and fixed to the anchor fixing member 12. The processes are repeated. After the installation work of the permanent anchor 14 is completed, concrete for the wall structure 16 is placed and integrated with the anchor fixing member 12. In another embodiment, the anchor fixing member is made of steel, and is embedded in concrete for integration. In this case, after concrete is placed, the permanent anchor 14 is released from tension, and tensed again. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、永久アンカーが施工された壁構造の構築方法および永久アンカーが施工された壁構造に関する。   The present invention relates to a wall structure construction method in which a permanent anchor is constructed and a wall structure in which a permanent anchor is constructed.

例えば傾斜地に建物外壁や擁壁などの壁構造を構築する場合、斜め型の仮設アンカーを用いた山留め工事を行ってから壁の構築工事を行うのが一般的である(例えば特許文献1を参照)。この特許文献1に記載された仮設アンカーでは、山留め用鋼材を打ち込んだ後、鋼棒からなるアースアンカーを傾斜地の地盤へ斜めに埋め込み、このアースアンカーの端部を止体によって山留め用鋼材に定着している。   For example, when building a wall structure such as a building outer wall or retaining wall on an inclined land, it is common to perform a mountain construction using an oblique temporary anchor and then perform a wall construction work (see, for example, Patent Document 1) ). In the temporary anchor described in this Patent Document 1, after mounting a steel material for mountain retaining, an earth anchor made of a steel rod is obliquely embedded in the ground of an inclined ground, and the end of this earth anchor is fixed to the steel material for mountain retaining by a stopper. is doing.

これに対して、特許文献2には、山留め杭に斜め型の永久アンカーを施工し、この永久アンカーに土圧を負担させることにより、仮設アンカーを用いることなく構築物を構築する工法が開示されている。この工法では、構築物を上部より一段ずつ構築し、各段の構築が終了する毎に永久アンカーを施工して土圧を負担させるようにしている。
特開昭62−63722号公報 特開平5−202527号公報
On the other hand, Patent Document 2 discloses a construction method for constructing a structure without using a temporary anchor by constructing an oblique permanent anchor on a pile pile and applying earth pressure to the permanent anchor. Yes. In this construction method, a structure is constructed one by one from the top, and a permanent anchor is constructed every time construction of each stage is completed, so that earth pressure is borne.
JP-A-62-63722 JP-A-5-202527

しかし、仮設アンカーを用いることなく工事を行うことは、斜め型永久アンカーの構築後にその下を根切りする際に、山留め杭のみに土圧を負担させることであり、根切り深さが大きくなると山留め杭の変形も増大してしまうため実用的でない。したがって、従来、傾斜地に壁構造を構築する場合、仮設アンカーを用いざるを得なかった。   However, the construction without using a temporary anchor is to load earth pressure only on the pile pile when rooting under the oblique permanent anchor, and when the root cutting depth increases. It is not practical because the deformation of the pile pile will increase. Therefore, conventionally, when constructing a wall structure on an inclined land, a temporary anchor has to be used.

上記特許文献1に開示されるような斜め型の仮設アンカーを用いて壁構造の構築工事を行う場合、仮設アンカーや山留め用鋼材を再利用するために、壁構造を構築しながら仮設アンカーを取り外していき、山留用鋼材も解体して除去するのが通常である。しかし、仮設アンカー等を撤去してしまうと、壁構造には大きな土圧が作用する。そこで、壁構造がそのような土圧に耐えられるよう、構築した壁に永久アンカーを施工することが考えられる。   When constructing a wall structure using an oblique temporary anchor as disclosed in Patent Document 1, the temporary anchor is removed while the wall structure is being constructed in order to reuse the temporary anchor and the steel for retaining the mountain. It is normal to dismantle and remove steel for steel. However, if a temporary anchor or the like is removed, a large earth pressure acts on the wall structure. Therefore, it is conceivable to construct a permanent anchor on the constructed wall so that the wall structure can withstand such earth pressure.

図24は、仮設アンカーを用いた山留めを行ったうえで、永久アンカーを用いて壁構造を構築する構成を示す断面図であり、図25は、図24の左側から見た正面図である。これらの図面を参照して壁構造の施工手順を説明すると、先ず、山留め杭50を打設し、この山留め杭50の内側(図16における左側)の地盤を根切りする。根切り深さが最上段の仮設アンカー施工位置まで達すると、鋼製の腹起こし52を山留め杭50に取り付け、この腹起こし52に仮設アンカー定着固定用の台座54を固定する。そして、最上段の仮設アンカー56aを施工して、台座54に定着固定する。以後、最下段の仮設アンカー56cまで、このような根切りと仮設アンカー56の施工とを繰り返す。   FIG. 24 is a cross-sectional view showing a configuration in which a wall structure is constructed using a permanent anchor after mountain mounting using a temporary anchor, and FIG. 25 is a front view seen from the left side of FIG. The construction procedure of the wall structure will be described with reference to these drawings. First, the pile retaining pile 50 is placed, and the ground inside the pile retaining pile 50 (left side in FIG. 16) is rooted. When the root cutting depth reaches the uppermost temporary anchor construction position, a steel erection 52 is attached to the pile pile 50, and a pedestal 54 for fixing the temporary anchor is fixed to the erection 52. Then, the uppermost temporary anchor 56 a is constructed and fixed to the base 54. Thereafter, such root cutting and construction of the temporary anchor 56 are repeated up to the lowermost temporary anchor 56c.

仮設アンカー56の工事が終わると床付を行う。そして、床コンクリート58を打設し、この床コンクリート58から上方へ壁構造60を打設しながら、仮設アンカー56を下から順に撤去していく。すなわち、図16および図17の例では、最下段の仮設アンカー56c、腹起こし52、台座54を撤去してから床コンクリート58を打設し、次段の仮設アンカー56b等を撤去してから壁構造60の最下部を打設し、更に、最上段の仮設アンカー56a等を撤去してから、壁構造60の残りの部分を打設する。また、壁構造60の打設を行いながら、斜め型の永久アンカー62の施工も行う。こうして壁構造60の構築が完了する。   When the construction of the temporary anchor 56 is completed, flooring is performed. Then, the floor concrete 58 is placed, and the temporary anchor 56 is sequentially removed from the bottom while placing the wall structure 60 upward from the floor concrete 58. That is, in the example of FIG. 16 and FIG. 17, the bottom temporary anchor 56c, the flank 52, and the pedestal 54 are removed and then the floor concrete 58 is placed, and the next temporary anchor 56b and the like are removed before the wall. The lowermost portion of the structure 60 is driven, and the uppermost temporary anchor 56a and the like are removed, and then the remaining portion of the wall structure 60 is driven. In addition, while the wall structure 60 is driven, the oblique permanent anchor 62 is also constructed. Thus, the construction of the wall structure 60 is completed.

以上説明したように、図24および図25に示す工事では、仮設アンカー56等の施工や撤去の作業が必要となり、施工コストが増大すると共に工事が長期化してしまう。さらに、山留め杭50と壁構造60との間の空間が狭いため、仮設撤去作業は極めて行い難い。しかも、仮設アンカー56等の撤去作業または外壁型枠作業などは、壁構造60や永久アンカー62の施工と並行して行わねばならないため作業が輻輳し、作業効率が悪くなってしまう。   As described above, in the construction shown in FIGS. 24 and 25, the construction and removal of the temporary anchor 56 and the like are required, which increases the construction cost and lengthens the construction. Furthermore, since the space between the mountain retaining pile 50 and the wall structure 60 is narrow, temporary removal work is extremely difficult. In addition, the removal work of the temporary anchor 56 or the like or the outer wall formwork work must be performed in parallel with the construction of the wall structure 60 and the permanent anchor 62, so the work is congested and work efficiency is deteriorated.

また、仮設アンカー56と永久アンカー62の両方を施工するためアンカー施工本数が増大し、この点でもコスト増および工事の長期化を招くと共に、効率的なアンカーの配置計画を行うのが難しいという問題もある。   In addition, since both the temporary anchor 56 and the permanent anchor 62 are constructed, the number of anchor constructions increases, which also increases the cost and lengthens the construction, and makes it difficult to perform efficient anchor placement planning. There is also.

本発明は上記の点に鑑みてなされたものであり、仮設のアンカーや腹起こしを用いることなく地盤内に壁構造を構築できるようにすることを目的とする。   This invention is made | formed in view of said point, and it aims at enabling it to construct | assemble a wall structure in the ground, without using a temporary anchor and a raising.

上記の目的を達成するため、請求項1に記載された発明に係る永久アンカーが施工された壁構造の構築方法は、山留めを打設し、該山留めの内側の地盤を根切りして、アンカーを定着固定するためのアンカー定着部材を前記山留めに構築すると共に、斜め型のアンカーを打設し、当該アンカーを前記アンカー定着部材に定着固定した後、壁構造のコンクリートを前記アンカー定着部材と一体となるように打設することを特徴とする。   In order to achieve the above object, a method for constructing a wall structure in which a permanent anchor according to the first aspect of the present invention is constructed is a method in which a anchor is placed, a ground inside the anchor is rooted, An anchor fixing member for fixing and fixing an anchor is constructed on the mountain stop, an oblique anchor is placed, the anchor is fixed and fixed to the anchor fixing member, and then a concrete wall is integrated with the anchor fixing member. It is characterized by being placed so that

本発明によれば、アンカー定着部材を山留めに構築し、このアンカー定着部材にアンカーを定着固定するので、根切り時の土圧をこのアンカーで確実に負担できる。また、壁構造のコンクリートをアンカー定着部材と一体となるように打設するので、上記アンカーを永久アンカーとして用いることができる。したがって、本発明によれば、仮設アンカーを用いることなく、永久アンカーのみで土圧を負担しながら、壁構造を構築できる。また、アンカー定着部材は腹起こしとして機能するので、仮設の腹起こしを用いることも不要となる。なお、本発明における壁構造として、例えば、建物外壁、建物ドライエリアの外壁、傾斜地盤に設けられる擁壁等がある。   According to the present invention, the anchor fixing member is constructed in a mountain stop, and the anchor is fixedly fixed to the anchor fixing member, so that the earth pressure at the time of root cutting can be reliably borne by the anchor. Moreover, since the concrete having a wall structure is cast so as to be integrated with the anchor fixing member, the anchor can be used as a permanent anchor. Therefore, according to the present invention, a wall structure can be constructed while bearing earth pressure only with a permanent anchor without using a temporary anchor. Further, since the anchor fixing member functions as an erection, it is not necessary to use a temporary erection. Examples of the wall structure in the present invention include a building outer wall, an outer wall of a building dry area, and a retaining wall provided on an inclined ground.

また、請求項2に記載された発明は、請求項1記載の方法において、前記アンカーは複数段に設けられ、上段側から下段側へ各段ごとに、地盤の根切り、前記アンカー定着部材の構築、および、前記アンカーの打設と定着固定を行って、全段のアンカーの施工が完了した後、前記壁構造のコンクリートを打設することを特徴とする。   According to a second aspect of the present invention, in the method according to the first aspect, the anchors are provided in a plurality of stages, and the ground is rooted from the upper stage side to the lower stage side for each stage. After the construction, the anchor placement and fixing, and the construction of all the anchors are completed, the wall structure concrete is placed.

また、請求項3に記載された発明は、請求項1または2記載の方法において、前記壁構造は鉄筋コンクリート造であり、前記アンカー定着部材を、鉄筋コンクリートにより構築することを特徴とする。   According to a third aspect of the present invention, in the method of the first or second aspect, the wall structure is reinforced concrete, and the anchor fixing member is constructed of reinforced concrete.

また、請求項4に記載された発明は、請求項3記載の方法において、前記壁構造のコンクリートを打設する前に、前記アンカー定着部材の鉄筋と、前記壁構造の鉄筋とを接合することを特徴とする。このようにすれば、壁構造とアンカー定着部材との一体性をより強固にして、壁構造の強度向上を図ることができる。   According to a fourth aspect of the present invention, in the method according to the third aspect, before the concrete having the wall structure is placed, the reinforcing bar of the anchor fixing member and the reinforcing bar of the wall structure are joined. It is characterized by. In this way, the integrity of the wall structure can be enhanced by further strengthening the integrity of the wall structure and the anchor fixing member.

また、請求項5に記載された発明は、前記壁構造は鉄骨コンクリート造であり、前記アンカー定着部材を鉄骨コンクリートにより構築することを特徴とする。   Further, the invention described in claim 5 is characterized in that the wall structure is a steel concrete structure, and the anchor fixing member is constructed of steel concrete.

また、請求項6に記載された発明は、前記壁構造は鉄骨鉄筋コンクリート造であり、前記アンカー定着部材を鉄骨鉄筋コンクリートにより構築することを特徴とする。   According to a sixth aspect of the present invention, the wall structure is a steel reinforced concrete structure, and the anchor fixing member is constructed of a steel reinforced concrete.

また、請求項7に記載された発明は、請求項3または4記載の方法において、前記山留めの前記アンカー定着部材が構築される部位に、根切り部の内方へ突出する突出部材を設け、前記アンカー定着部材のコンクリートを、前記突出部材が前記アンカー定着部材内へ埋め込まれるように打設することを特徴とする。このようにすれば、山留めに設けられた突出部材がアンカー定着部材に埋め込まれることで、アンカー定着部材と山留めとの一体化を図ることができる。   The invention described in claim 7 is the method according to claim 3 or 4, wherein a projecting member projecting inward of the root cutting portion is provided at a site where the anchor fixing member of the mountain fixing is constructed, The concrete of the anchor fixing member is placed so that the protruding member is embedded in the anchor fixing member. In this way, the projecting member provided on the mountain retaining member is embedded in the anchor fixing member, so that the anchor fixing member and the mountain retaining member can be integrated.

また、請求項8に記載された発明は、請求項1〜7のうち何れか1項記載の方法において、前記壁構造の外周面と根切りされた地盤の内側面との間の空間に砕石を設置すると共に、前記壁構造にその内側面と外側面との間を貫通する水抜き管を設けることを特徴とする。このようにすれば、地盤内の水を、砕石および水抜き管を介して、壁構造の内側へ排出させることができる。   The invention described in claim 8 is the method according to any one of claims 1 to 7, wherein the crushed stone is formed in a space between the outer peripheral surface of the wall structure and the inner surface of the ground which has been rooted. And a water drain pipe penetrating between the inner side surface and the outer side surface of the wall structure. If it does in this way, the water in a ground can be discharged | emitted inside a wall structure via a crushed stone and a drain pipe.

また、請求項9に記載された発明は、請求項8記載の方法において、前記山留めへの前記アンカー定着部材の構築部位の上部位置に通水性を有する保持板を取り付けて当該保持板の上に前記砕石を設置し、前記アンカー定着部材にはその上下を貫通する水抜き管を設けることを特徴とする。このようにすれば、地盤から砕石に滲み出した水を、アンカー定着部材の水抜き管を介して下段の砕石に導くことができ、地盤の水抜きをより効果的に行うことができる。   Further, the invention described in claim 9 is the method according to claim 8, wherein a holding plate having water permeability is attached to an upper position of a construction site of the anchor fixing member to the mountain stopper and is mounted on the holding plate. The crushed stone is installed, and the anchor fixing member is provided with a drain pipe that penetrates the anchor fixing member. If it does in this way, the water which exuded to the crushed stone from the ground can be guide | induced to the crushed stone of a lower stage through the drain pipe of an anchor fixing member, and the water of a ground can be drained more effectively.

また、請求項10に記載された発明は、請求項1〜9のうち何れか1項記載の方法において、前記アンカー定着部材を鋼材により構成したことを特徴とする。このようにすれば、アンカー定着部材をコンクリートに埋め殺すだけで、コンクリートとの一体化を図ることができるので、コンクリートとアンカー定着部材とを一体化させるための工程を簡単化できる。   The invention described in claim 10 is the method according to any one of claims 1 to 9, wherein the anchor fixing member is made of a steel material. In this way, since the integration with the concrete can be achieved simply by burying the anchor fixing member in the concrete, the process for integrating the concrete and the anchor fixing member can be simplified.

また、請求項11に記載された発明は、請求項1〜10のうち何れか1項記載の方法において、前記アンカーを前記アンカー定着部材へ定着した後、その張力を緩める工程と、前記壁構造のコンクリートの打設後に再緊張する工程と、を含むことを特徴とする。このようにすれば、アンカーの張力を緩めることにより、壁構造のコンクリートに土圧の一部を負担させることができ、その後、アンカーを再緊張することで、壁構造のコンクリートとアンカー定着部材をより強固に一体化させることができる。   The invention described in claim 11 is the method according to any one of claims 1 to 10, wherein after fixing the anchor to the anchor fixing member, the step of releasing the tension, and the wall structure And re-tensioning after placing the concrete. In this way, by relaxing the tension of the anchor, a part of earth pressure can be borne by the concrete of the wall structure, and then the concrete of the wall structure and the anchor fixing member are re-tensioned. It can be integrated more firmly.

また、請求項12に記載された発明に係る永久アンカーが施工された壁構造は、地盤に打設された山留めに、アンカーを定着固定するためのアンカー定着部材が構築され、該アンカー定着部材にアンカーが定着固定されていると共に、壁構造のコンクリートが前記アンカー定着部材と一体となるように打設されていることを特徴とする。   Further, in the wall structure in which the permanent anchor according to the invention described in claim 12 is constructed, an anchor fixing member for fixing and fixing the anchor is constructed on a mountain stopper placed on the ground, and the anchor fixing member is attached to the anchor fixing member. The anchor is fixedly fixed, and the concrete of the wall structure is placed so as to be integrated with the anchor fixing member.

また、請求項13に記載された発明は、請求項12記載の壁構造において、前記アンカー定着部材は、コンクリート部材または鋼材により構成されていることを特徴とする。   According to a thirteenth aspect of the present invention, in the wall structure of the twelfth aspect, the anchor fixing member is made of a concrete member or a steel material.

本発明によれば、仮設のアンカーや腹起こしを用いることなく地盤内に永久アンカーが施工された壁構造を構築することができる。   According to the present invention, it is possible to construct a wall structure in which a permanent anchor is constructed in the ground without using a temporary anchor or an upset.

図1は、本発明の一実施形態である壁構造の構築工事により構築された鉄筋コンクリート造の壁構造を示す断面図であり、図2は、図1の壁構造を同図中左側からみた正面図である。また、図3は、図2おける永久アンカー施工部分を示す(図2のIII部)拡大正面図であり、図4は図1のIV−IV断面図であり、図5は図1のV−V断面図である。   FIG. 1 is a cross-sectional view showing a reinforced concrete wall structure constructed by construction work of a wall structure according to an embodiment of the present invention, and FIG. 2 is a front view of the wall structure of FIG. FIG. 3 is an enlarged front view (part III in FIG. 2) showing the permanent anchor construction part in FIG. 2, FIG. 4 is a sectional view taken along line IV-IV in FIG. 1, and FIG. It is V sectional drawing.

これらの図面に示すように、本実施形態における構築物は、概略、山留め杭10と、山留め杭10に取り付けられたアンカー定着部材12と、アンカー定着部材12に定着固定された斜め型の永久アンカー14と、アンカー定着部材12と一体に打設された壁構造16と、この壁構造16と一体の床部18とにより構成される。壁構造16は、例えば、建物外壁、ドライエリア部の外壁、あるいは、擁壁などである。なお、図1では、3段の永久アンカー14(上から順に、永久アンカー14a,14b,14c)を設けた場合を示しているが、永久アンカー14の段数はこれに限らない。   As shown in these drawings, the structure according to the present embodiment is roughly composed of a pile pile 10, an anchor fixing member 12 attached to the pile pile 10, and an oblique permanent anchor 14 fixed to the anchor fixation member 12. And a wall structure 16 that is integrally formed with the anchor fixing member 12 and a floor portion 18 that is integral with the wall structure 16. The wall structure 16 is, for example, a building outer wall, an outer wall of a dry area, or a retaining wall. Although FIG. 1 shows a case where three stages of permanent anchors 14 (in the order from the top, permanent anchors 14a, 14b, 14c) are shown, the number of stages of permanent anchors 14 is not limited to this.

山留め杭10は例えばH型鋼からなり、壁構造16の外壁面に沿って複数本が地盤に打設されている。また、アンカー定着部材12は鉄筋コンクリート製部材であり、上記複数本の山留め杭10に跨って水平方向に梁状に延びている。したがって、アンカー定着部材12は、永久アンカー14の張力を山留め杭10へ伝達する腹起こしとしての役割も有している。   The pile retaining pile 10 is made of, for example, H-shaped steel, and a plurality of piles are placed on the ground along the outer wall surface of the wall structure 16. The anchor fixing member 12 is a reinforced concrete member and extends in a beam shape in the horizontal direction across the plurality of piled piles 10. Therefore, the anchor fixing member 12 also has a role as an abdomen that transmits the tension of the permanent anchor 14 to the pile pile 10.

また、本実施形態では、山留め杭10と壁構造16との間の空間に砕石22を充填すると共に、壁構造16に水抜き管24を埋設し、さらに、アンカー定着部材12に水抜き管26を埋設することにより、地盤から壁構造16の内側へ地盤の水抜きを行えるようにしている。ただし、地盤の水抜きを行う必要がない場合はこれらの構成は不要であり、壁構造16が山留め杭10に密着するようにコンクリートを打設すればよい。   In the present embodiment, the space between the pile pile 10 and the wall structure 16 is filled with the crushed stone 22, the drainage pipe 24 is embedded in the wall structure 16, and the drainage pipe 26 is embedded in the anchor fixing member 12. By burying, the ground can be drained from the ground to the inside of the wall structure 16. However, when it is not necessary to drain the ground, these configurations are unnecessary, and concrete may be placed so that the wall structure 16 is in close contact with the pile pile 10.

図6〜図15は、上記図1〜図5に示す壁構造の構築工程を示す図である。図6に示すように、先ず、山留め杭10を打設し、所定深さ(最上段の永久アンカー14aの打設位置底部)まで根切りを行う。そして、山留め杭10の側面に例えばアングル材等を用いて砕石保持板28を取り付け、さらに、砕石保持板28の先端から上方に延びる砕石止めとなる波型鋼板30を取り付けて、この波型鋼板30と根切りした地盤側面との間の空間に砕石22を充填する。砕石保持板28は例えば網目状に構成されるなどして、各段の砕石22の水は、直下のアンカー定着部材12の水抜き管26を通って下段の砕石22へ抜けることができるようになっている。なお、波型鋼管30の、壁構造16に設けられた水抜き管24の端部に対向する位置には穴が開けられており、この穴を通って砕石22内の水が水抜き管24へ流れ出せるようになっている。 6-15 is a figure which shows the construction process of the wall structure shown in the said FIGS. 1-5. As shown in FIG. 6, first, the pile pile 10 is driven and rooted to a predetermined depth (bottom position of the uppermost permanent anchor 14a). Then, a crushed stone holding plate 28 is attached to the side surface of the mountain retaining pile 10 using, for example, an angle material, and further, a corrugated steel plate 30 that is a crushed stone stop extending upward from the tip of the crushed stone retaining plate 28 is attached. The crushed stone 22 is filled in the space between 30 and the ground side of the ground. For example, the crushed stone holding plate 28 is configured in a mesh shape, so that the water of the crushed stone 22 in each stage can pass through the drain pipe 26 of the anchor fixing member 12 directly below to the crushed stone 22 in the lower stage. It has become. It should be noted that a hole is formed in the corrugated steel pipe 30 at a position facing the end of the drain pipe 24 provided in the wall structure 16, and the water in the crushed stone 22 passes through the hole to drain the water 24. To be able to flow out.

次に、図7に示すように、根切り部底面のアンカー定着部材12の構築位置に捨てコンクリート31を打設すると共に、山留め杭10のフランジ面に、突出部材としてのスタッド32を溶接する。また、アンカー定着部材12を打設するための型枠を配置して、永久アンカー14の施工用のガイド管34および上記水抜き管26を設置する。そして、ガイド管34の周囲にらせん鉄筋35を配筋すると共にアンカー定着部材12の鉄筋を配筋し、型枠内にコンクリートを打設する。その際、アンカー定着部材12の鉄筋をその上面から突出させ、さらに、その下面からも鉄筋が捨てコンクリート31を貫通して突出し先端が地盤へ埋め込まれるように配筋する。このようにアンカー定着部材12から上下に突出する鉄筋の端部には、好ましくは、後述する壁構造16の鉄筋との接合を簡単に行なえるようにねじ鉄筋接合が施されている。   Next, as shown in FIG. 7, the discarded concrete 31 is placed at the construction position of the anchor fixing member 12 on the bottom surface of the root cutting portion, and the stud 32 as a protruding member is welded to the flange surface of the retaining pile 10. Further, a formwork for placing the anchor fixing member 12 is disposed, and the guide pipe 34 for constructing the permanent anchor 14 and the drain pipe 26 are installed. Then, the reinforcing bars 35 are arranged around the guide tube 34 and the reinforcing bars of the anchor fixing member 12 are arranged, and concrete is placed in the mold. At this time, the reinforcing bars of the anchor fixing member 12 are protruded from the upper surface, and further, the reinforcing bars are disposed from the lower surface so as to pass through the concrete 31 and be embedded in the ground. In this way, the ends of the reinforcing bars projecting up and down from the anchor fixing member 12 are preferably threaded reinforcing bars so that they can be easily joined to the reinforcing bars of the wall structure 16 described later.

次に、図8に示すように、永久アンカー14を打設する。永久アンカー14の打設は、ガイド管34の内側から支持盤に達するまで斜め方向に削孔して、この孔の底までシース管に挿通されたアンカー鋼材36を挿入し、グラウト材を注入することによりアンカー鋼材36を地盤に固定するという周知の工法で行うことができる。そして、グラウト材の養生後、図9に示すように、アンカー鋼材36を緊張し、定着金具38でアンカー定着部材12に定着固定する。   Next, as shown in FIG. 8, the permanent anchor 14 is driven. The permanent anchor 14 is formed by drilling in an oblique direction from the inside of the guide tube 34 until reaching the support plate, inserting the anchor steel material 36 inserted through the sheath tube to the bottom of the hole, and injecting the grout material. Thus, it can be performed by a known method of fixing the anchor steel material 36 to the ground. Then, after curing the grout material, as shown in FIG. 9, the anchor steel material 36 is tensioned and fixed to the anchor fixing member 12 by the fixing metal fitting 38.

なお、以上の説明では、アンカー定着部材12の構築後に永久アンカー14を打設するものとしたが、永久アンカー14を打設した後、アンカー定着部材12を構築し、これに永久アンカー14を定着固定するようにしてもよい。   In the above description, the permanent anchor 14 is driven after the anchor fixing member 12 is constructed. However, after the permanent anchor 14 is driven, the anchor fixing member 12 is constructed, and the permanent anchor 14 is fixed thereto. It may be fixed.

次に、図10に示すように、次段の永久アンカー14bの深さまで根切りを行い、上記図6〜図9と同様の工程により施工を行う。このような工程を最下段の永久アンカー14cまで繰り返す(図11)。   Next, as shown in FIG. 10, root cutting is performed to the depth of the permanent anchor 14b of the next stage, and construction is performed by the same processes as in FIGS. Such a process is repeated up to the lowermost permanent anchor 14c (FIG. 11).

最下段の永久アンカー14cまで施工した後、更に、床部18の打設深さまで根切りを継続し、根切り完了後、壁構造16および床部18の配筋を行う。その際、壁構造16の鉄筋を、上述のようにアンカー定着部材12の上下から突出して配筋された鉄筋へ例えばねじ込み式に接合することで、壁構造16とアンカー定着部材12との強固な一体性を確保できるようにしている。   After construction up to the lowermost permanent anchor 14c, the root cutting is continued to the placement depth of the floor 18 and after the root cutting is completed, the wall structure 16 and the floor 18 are arranged. At this time, the reinforcing members of the wall structure 16 and the anchor fixing member 12 are joined by, for example, screwing the reinforcing bars of the wall structure 16 to the reinforcing bars protruding from above and below the anchor fixing member 12 as described above. The unity is ensured.

壁構造16および床部18の配筋後、図12に示すように、床部18のコンクリートを打設し、さらに、最下段のアンカー定着部材12の高さまで壁構造16のコンクリートを打設する。その際、予め型枠内に水抜き管24を設置しておく。コンクリートの打設後、最下段の永久アンカー14のアンカー鋼材36の張力を測定し、必要があればアンカー鋼材36を再度緊張する。そして、一つ上段のアンカー定着部材12まで、上記と同様にして壁構造16のコンクリートを打設し、当該アンカー定着部材12に定着固定すべき永久アンカー14bのアンカー鋼材36を必要に応じて緊張する。このような壁構造16の打設作業を最上段のアンカー定着部材12まで繰り返し(図13〜図14を参照)、さらに、壁の最上部のコンクリート16aを打設することで(図15を参照)、図1に示す壁構造の構築が完了する。 After bar arrangement of the wall structure 16 and the floor 18, as shown in FIG. 12, the concrete of the floor 18 is cast, and further the concrete of the wall structure 16 is cast to the height of the anchor fixing member 12 at the lowest level. . At that time, a drain pipe 24 is installed in the mold in advance. Concrete after casting to measure the tension of the anchor steel 36 of the lowermost permanent anchor 14 c, again tensioning the anchor steel 36 if necessary. Then, the concrete of the wall structure 16 is placed in the same manner as described above up to the upper anchor fixing member 12, and the anchor steel material 36 of the permanent anchor 14b to be fixed and fixed to the anchor fixing member 12 is tensioned as necessary. To do. By repeating the placement work of the wall structure 16 up to the anchor fixing member 12 at the uppermost stage (see FIGS. 13 to 14), the concrete 16a at the uppermost part of the wall is further placed (see FIG. 15). ), The construction of the wall structure shown in FIG. 1 is completed.

以上説明したように、本実施形態によれば、山留め杭10に構築したアンカー定着部材12に永久アンカー14を定着固定するので、根切り時に地盤の土圧を永久アンカー14で確実に負担することができる。また、永久アンカー14を施工しながら、壁構造16のコンクリートを、永久アンカー14が定着固定されたアンカー定着部材12と一体となるように打設することにより、仮設アンカーや仮設腹起こしを用いることなく壁構造16を構築することができる。さらに、アンカー定着部材12が山留め杭10の腹起こしとしても機能するので、別途仮設の腹起こしを用いることも不要である。そして、このアンカー定着部材12が壁構造16の一部として一体化されるため、仮設アンカーを用いた場合のように、仮設アンカーや腹起こしの撤去作業が全く不要となり、工期短縮および工事コストの低減を図ることができる。   As described above, according to the present embodiment, the permanent anchor 14 is fixedly fixed to the anchor fixing member 12 constructed on the pile pile 10, so that the earth pressure of the ground is surely borne by the permanent anchor 14 at the time of root cutting. Can do. Further, while constructing the permanent anchor 14, by placing the concrete of the wall structure 16 so as to be integrated with the anchor fixing member 12 to which the permanent anchor 14 is fixed and fixed, a temporary anchor or a temporary belly is used. Wall structure 16 can be constructed without. Furthermore, since the anchor fixing member 12 functions also as the erection of the piled pile 10, it is not necessary to use a temporary erection. Since the anchor fixing member 12 is integrated as a part of the wall structure 16, there is no need to remove the temporary anchor or the erection as in the case where the temporary anchor is used. Reduction can be achieved.

また、仮設アンカーの施工が不要となることで、アンカー本数の総数も少なくなり、この点でも、工期短縮およびコスト低減を図ることができる。さらに、アンカー本数が少なくなることで効果的なアンカーの配置計画も行い易くなるため、構築した壁構造16の品質向上を図ることもできる。   Moreover, since the construction of temporary anchors is not required, the total number of anchors is reduced, and in this respect, the construction period can be shortened and the cost can be reduced. Furthermore, since the number of anchors is reduced, it becomes easy to perform effective anchor arrangement planning, so that the quality of the constructed wall structure 16 can be improved.

また、本実施形態では、アンカー定着部材12を鉄筋コンクリートで構成し、その鉄筋コンクリートを壁構造16の鉄筋と接合することで、アンカー定着部材12と壁構造16との強固な一体性を確保することができる。このため、設計上、アンカー定着部材12を壁構造16の一部とみなせるようになり、壁構造16を一体のコンクリートで構築した場合と同様の高い強度を得ることができる。   Further, in the present embodiment, the anchor fixing member 12 is made of reinforced concrete, and the reinforced concrete is joined to the reinforcing bar of the wall structure 16, thereby ensuring strong integrity between the anchor fixing member 12 and the wall structure 16. it can. For this reason, the anchor fixing member 12 can be regarded as a part of the wall structure 16 in design, and the same high strength as when the wall structure 16 is constructed of integral concrete can be obtained.

さらに、本実施形態では、山留め杭10と壁構造16との間に砕石22を設置すると共に、アンカー定着部材12および壁構造16に水抜き管24,26を設けることで、地盤からの水抜きを行うことができる。すなわち、地盤内の水は砕石22を通過して壁構造16の水抜き管24から壁の内側へ排出され、また、アンカー定着部材12で上下に分断された各段の砕石22の水は、アンカー定着部材12の水抜き管26通って下段の砕石22へ移動できるので、砕石22による水抜きはより効果的に行われる。したがって、本実施形態によれば、壁構造16の外壁面にかかる水圧を緩和することができる。   Furthermore, in this embodiment, while installing the crushed stone 22 between the retaining pile 10 and the wall structure 16, and providing the drainage pipes 24 and 26 in the anchor fixing member 12 and the wall structure 16, the water is drained from the ground. It can be performed. That is, the water in the ground passes through the crushed stone 22 and is discharged from the drain pipe 24 of the wall structure 16 to the inside of the wall, and the water of the crushed stone 22 at each stage divided vertically by the anchor fixing member 12 is Since it can move to the crushed stone 22 in the lower stage through the drain pipe 26 of the anchor fixing member 12, the drainage by the crushed stone 22 is performed more effectively. Therefore, according to this embodiment, the water pressure applied to the outer wall surface of the wall structure 16 can be relaxed.

なお、上記実施形態では、山留めとしてH型鋼からなる山留め杭10を用い、この山留め杭10に構築したアンカー定着部材12を腹起こしとしても機能させる構成としたが、本発明における山留めはこれに限らず、例えば鋼管矢板壁、柱列山留壁、連続地中壁などの山留め工法に用いることもできる。   In addition, in the said embodiment, it was set as the structure which uses the mountain retaining pile 10 which consists of H-shaped steel as a mountain retaining, and made the anchor fixing member 12 constructed | assembled to this mountain retaining pile 10 function also as a belly, However, The mountain retaining in this invention is not restricted to this. For example, it can also be used for a mountain fastening method such as a steel pipe sheet pile wall, a pillar row retaining wall, a continuous underground wall, or the like.

また、上記実施形態では、壁構造16が鉄筋コンクリート造であるものとして、これに対応してアンカー定着部材12も鉄筋コンクリートにより構築し、両者の鉄筋を接合することにより一体性を高めるものとした。しかしながら、本発明はこれに限らず、例えば、壁構造16が鉄骨コンクリート造である場合はアンカー定着部材12も鉄骨コンクリートで構成し、壁構造16が鉄骨鉄筋コンクリートである場合はアンカー定着部材12も鉄骨鉄筋コンクリートで構成することにより、アンカー定着部材12と壁構造16との一体化を図る構成とすることも可能である。   Moreover, in the said embodiment, the wall structure 16 shall be reinforced concrete structure, the anchor fixing member 12 was also constructed | assembled by reinforced concrete corresponding to this, and the integrity was improved by joining both reinforcing bars. However, the present invention is not limited to this. For example, when the wall structure 16 is made of steel concrete, the anchor fixing member 12 is also made of steel concrete. When the wall structure 16 is steel reinforced concrete, the anchor fixing member 12 is also steel frame. By constituting the reinforced concrete, the anchor fixing member 12 and the wall structure 16 can be integrated.

次に、本発明の第2の実施形態について説明する。図16は、本実施形態において構築される鉄筋コンクリート造の壁構造を示す断面図である。なお、本実施形態において、上記第1実施形態と同様の構成部分には同一の符号を付してその説明を省略する。
図16に示す如く、本実施形態では、上記第1実施形態のアンカー定着部材12に代えて、鉄骨部材からなるアンカー定着部材100を設けている。図17は、本実施形態のアンカー定着部材100およびその周辺部を拡大して示す断面図であり、また、図18は、図17における左側からみた正面図である。
Next, a second embodiment of the present invention will be described. FIG. 16 is a cross-sectional view showing a reinforced concrete wall structure constructed in the present embodiment. In the present embodiment, the same components as those in the first embodiment are denoted by the same reference numerals, and the description thereof is omitted.
As shown in FIG. 16, in this embodiment, an anchor fixing member 100 made of a steel member is provided in place of the anchor fixing member 12 of the first embodiment. FIG. 17 is an enlarged cross-sectional view showing the anchor fixing member 100 and its peripheral portion according to the present embodiment, and FIG. 18 is a front view seen from the left side in FIG.

図17および図18に示す如く、アンカー定着部材100は、概略、補強リブ材102、斜め支持材104、腹起こし材106等により構成されている。補強リブ材102は、例えばH型鋼等の鋼材であり、その上下フランジ102a、102bおよびウエブ102cが山留め杭10に対して垂直となるように、山留め杭10に溶接されている。補強リブ材102の下フランジ102bの下面には補強材103が溶接されている。   As shown in FIGS. 17 and 18, the anchor fixing member 100 is roughly composed of a reinforcing rib member 102, an oblique support member 104, a bellows member 106, and the like. The reinforcing rib member 102 is a steel material such as H-shaped steel, for example, and is welded to the pile pile 10 so that the upper and lower flanges 102 a and 102 b and the web 102 c are perpendicular to the pile pile 10. A reinforcing member 103 is welded to the lower surface of the lower flange 102b of the reinforcing rib member 102.

補強リブ材102の上フランジ102aの上側には、斜め支持材104が設けられている。斜め支持材104は、下側の端面104aが斜めに切断されたH型鋼等の鋼材により構成されており、この端面104aが補強リブ材102の上フランジ102aの上面に溶接されている。また、斜め支持材104の斜め下側のフランジ104cには、水平方向に延びる補強材105が溶接されている。この補強材105は例えば断面がC型の鋼材により構成されている。 An oblique support member 104 is provided on the upper side of the upper flange 102 a of the reinforcing rib member 102. The diagonal support member 104 is made of a steel material such as H-shaped steel whose lower end surface 104a is cut obliquely, and this end surface 104a is welded to the upper surface of the upper flange 102a of the reinforcing rib member 102. In addition, a reinforcing material 105 extending in the horizontal direction is welded to the flange 104 c on the oblique lower side of the oblique support member 104. The reinforcing material 105 is made of, for example, a steel material having a C-shaped cross section.

斜め支持材104の上側の端面104cには、保持プレート107が溶接されており、この保持プレート107により腹起こし材106が保持されている。腹起こし材106は、例えば、H型鋼を縦2段に重ねてボルト結合してなる鉄骨材106aを2本平行に並べて構成されており、複数本の山留め杭10に跨って水平方向に延びている。これら鉄骨材106aは水平方向に所定間隔で設けられた接続プレート108により互い接続されている。そして、腹起こし材106の、隣接する山留め杭10の中間部に永久アンカー14が定着されている。なお、後述するように、本実施形態では、永久アンカー14を、コンクリート打設前に腹起こし材106の上部フランジ106aに定着し、コンクリート打設後に再緊張して腹起こし材106の下部フランジ106bに定着するようにしており、図17では、コンクリート打設前の定着位置を実線で、コンクリート打設後の定着位置を破線で夫々示している。 A holding plate 107 is welded to the upper end surface 104 c of the diagonal support member 104, and the erection material 106 is held by the holding plate 107. The bellows member 106 is composed of, for example, two steel frames 106a formed by stacking H-shaped steel in two vertical stages and bolted together, and extends horizontally across a plurality of piles 10. Yes. These steel frames 106a are connected to each other by connection plates 108 provided at predetermined intervals in the horizontal direction. And the permanent anchor 14 is being fixed to the intermediate part of the pile pile 10 which adjoins the belly raising material 106. FIG. As will be described later, in this embodiment, the permanent anchor 14 is fixed to the upper flange 106a of the bellows member 106 before placing the concrete, and is re-tensioned after the concrete is placed, and the lower flange 106b of the belly member 106 is re-tensioned. In FIG. 17, the fixing position before placing concrete is indicated by a solid line, and the fixing position after placing concrete is indicated by a broken line.

図19〜図23は、本実施形態における壁構造の構築工程を示す図である。先ず、図19に示すように、山留め杭10を打設して最上段の永久アンカー14の位置まで根切りを行った後、山留め杭10に補強リブ材102を溶接し、さらに、補強リブ材102に斜め支持材104を溶接して、腹起こし材106を取り付けること等によりアンカー定着部材100を構築する。次に、永久アンカー14を斜め方向に打設した後、アンカー鋼材36を緊張し、台座110により腹起こし材106の上部フランジ106aに定着固定する。また、波型鋼板30を設置して、補強リブ材102の上側の波型鋼板30と根切りした地盤側面との間の空間に砕石22を充填する。   19-23 is a figure which shows the construction process of the wall structure in this embodiment. First, as shown in FIG. 19, after the pile retaining pile 10 is driven and rooted to the position of the uppermost permanent anchor 14, the reinforcing rib member 102 is welded to the retaining pile 10, and the reinforcing rib member is further provided. The anchor fixing member 100 is constructed by welding the diagonal support member 104 to 102 and attaching the belly raising member 106 or the like. Next, after the permanent anchor 14 is driven in an oblique direction, the anchor steel material 36 is tensioned and fixedly fixed to the upper flange 106 a of the stomach member 106 by the pedestal 110. Moreover, the corrugated steel sheet 30 is installed, and the crushed stone 22 is filled in the space between the corrugated steel sheet 30 on the upper side of the reinforcing rib member 102 and the ground side surface.

次に、図20に示すように、次段の永久アンカー14bの深さまで根切りを行い、上記図19の場合と同様にして、アンカー定着部材100の構築および永久アンカー14の施工を行う。このような工程を最下段の永久アンカー14cまで繰り返す(図21)。   Next, as shown in FIG. 20, rooting is performed to the depth of the permanent anchor 14b in the next stage, and the anchor fixing member 100 is constructed and the permanent anchor 14 is constructed in the same manner as in FIG. Such a process is repeated up to the lowermost permanent anchor 14c (FIG. 21).

最下段の永久アンカー14cまで施工した後、更に、床部18の打設深さまで根切りを継続し、根切り完了後、壁構造16および床部18の鉄筋を配筋して、図22に示すように、最下段のアンカー定着部材100の高さ(腹起こし材106がコンクリートから露出する程度の高さ)まで壁構造16のコンクリートを打設する。なお、壁構造16の鉄筋は、一段上のコンクリートの鉄筋と重ね継手を行える長さ分だけ、コンクリートの打設高さより上方の位置まで配筋しておく。コンクリートの打設後、最下段の永久アンカー14のアンカー鋼材36の張力をいったん開放した後、再緊張して、台座112により腹起こし材106の下部フランジ106bに定着する。このようにアンカー鋼材36の張力をいったん開放することにより、打設した壁構造16のコンクリートが地盤の土圧の一部を負担することとなる。これにより、壁構造16とアンカー定着部材100との一体性が強化されると共に、土圧を壁構造16とアンカー定着部材100とでほぼ同様に受けることとなり、壁構造16の設計が行い易くなる。なお、上記の説明では、永久アンカー14の2度目の緊張時(本設時)には、最初の緊張時(仮設時)から定着位置を腹起こし材106の下部フランジ106bへ下げることで、仮設時にアンカー鋼材36の定着位置に生じた凹みが本設後のアンカー鋼材36に残らないようにしている。ただし、そのような凹みがアンカー鋼材36の強度に影響を与えることはないので、仮設時と本設時とで同じ位置にて永久アンカー14を定着するようにしてもよい。 After construction to the lowermost permanent anchor 14c, the root cutting is continued to the placement depth of the floor 18 and after the root cutting is completed, the reinforcing bars of the wall structure 16 and the floor 18 are arranged, and FIG. As shown, the concrete of the wall structure 16 is driven up to the height of the anchor fixing member 100 at the lowest level (the height at which the belly raising member 106 is exposed from the concrete). It should be noted that the reinforcing bars of the wall structure 16 are arranged up to a position above the concrete placement height by a length that allows lap joints to be reinforced with the concrete reinforcing bars on the upper level. After placing the concrete, the tension of the anchor steel material 36 of the lowermost permanent anchor 14 c is once released and then re-tensioned to be fixed to the lower flange 106 b of the erection material 106 by the pedestal 112. As described above, once the tension of the anchor steel material 36 is released, the concrete of the wall structure 16 that has been placed bears a part of the earth pressure of the ground. As a result, the integrity of the wall structure 16 and the anchor fixing member 100 is strengthened, and earth pressure is received in the wall structure 16 and the anchor fixing member 100 in substantially the same manner, so that the wall structure 16 can be easily designed. . In the above description, when the permanent anchor 14 is in the second tension (at the time of permanent installation), the fixing position is lowered to the lower flange 106b of the material 106 from the first tension (at the time of temporary installation), thereby temporarily setting the permanent anchor 14. In some cases, the dent generated at the fixing position of the anchor steel material 36 does not remain in the anchor steel material 36 after the main installation. However, since such a dent does not affect the strength of the anchor steel material 36, the permanent anchor 14 may be fixed at the same position during temporary installation and during permanent installation.

次に、図23に示すように、一段上のアンカー定着部材100まで壁構造16のコンクリートを打設し、その際、永久アンカー14の再緊張が済んだ下段のアンカー定着部材100はコンクリートに埋め殺す。そして、上記と同様にして、アンカー鋼材36の張力をいったん開放した後、再緊張して定着固定する。このような壁構造16の打設および永久アンカーの再緊張の作業を最上段のアンカー定着部材12まで繰り返し、さらに、壁の最上部のコンクリートを打設することで、図16に示す壁構造の構築が完了する。   Next, as shown in FIG. 23, the concrete of the wall structure 16 is placed up to the anchor fixing member 100 on the upper level, and the anchor fixing member 100 on the lower level after the permanent anchor 14 has been re-tensioned is buried in the concrete. kill. Then, in the same manner as described above, after the tension of the anchor steel material 36 is once released, it is re-tensioned and fixed. The operation of placing the wall structure 16 and the re-tensioning of the permanent anchor is repeated up to the anchor fixing member 12 at the uppermost stage, and further, the concrete at the uppermost part of the wall is placed, so that the wall structure shown in FIG. Construction is complete.

以上説明したように、本実施形態では、アンカー定着部材100を鋼材で構成し、この鋼材を壁構造16のコンクリートに埋め殺すことで、アンカー定着部材100と壁構造16のコンクリートとを一体化するようにしている。このため、上記第1実施形態のようにアンカー定着部材12の鉄筋と壁構造16の鉄筋とを接合するための作業が不要となるので、その分、工数を減らすことができる。また、壁構造16のコンクリートを打設した後、永久アンカー14の張力をいったん解放して再緊張することで、アンカー定着部材100と壁構造16との一体性をより強化なものとすることができる。   As described above, in this embodiment, the anchor fixing member 100 is made of a steel material, and the steel material is buried in the concrete of the wall structure 16 so that the anchor fixing member 100 and the concrete of the wall structure 16 are integrated. I am doing so. For this reason, since the operation | work for joining the reinforcing bar of the anchor fixing member 12 and the reinforcing bar of the wall structure 16 like the said 1st Embodiment becomes unnecessary, a man-hour can be reduced by that much. In addition, after placing the concrete of the wall structure 16, the tension between the anchor anchor member 100 and the wall structure 16 may be further strengthened by releasing the tension of the permanent anchor 14 and re-tensioning. it can.

なお、上記の説明では、壁構造16のコンクリートを各段のアンカー定着部材100の高さまで打設した後、永久アンカー14の張力を解放して再緊張するものとしたが、これに限らず、先に永久アンカー14の張力を解放した後、壁構造16のコンクリートを打設し、コンクリート打設後に再緊張するようにしてもよい。   In the above description, the concrete of the wall structure 16 is placed up to the height of the anchor fixing member 100 at each stage, and then the tension of the permanent anchor 14 is released and re-tensioned. After releasing the tension of the permanent anchor 14 first, the concrete of the wall structure 16 may be placed and re-tensioned after placing the concrete.

また、本実施形態のように永久アンカー14を再緊張する工法は、上記第1実施形態の場合に適用することもできる。すなわち、上記第1実施形態においても、アンカー定着部材12と一体に壁構造16のコンクリートを打設した状態(例えば図12に示す状態)で、当該アンカー定着部材12に定着した永久アンカー14の張力をいったん開放した後、再緊張させるのである。このようにすれば、張力を開放した時点で、土圧がアンカー定着部材12と共に壁構造16のコンクリートでも負担されるようになり、その後、永久アンカー14を再緊張することで、壁構造16とアンカー定着部材12との一体性をより強固にすることができる。   Further, the construction method for re-tensioning the permanent anchor 14 as in the present embodiment can be applied to the case of the first embodiment. That is, also in the first embodiment, the tension of the permanent anchor 14 fixed to the anchor fixing member 12 in a state where the concrete of the wall structure 16 is cast integrally with the anchor fixing member 12 (for example, the state shown in FIG. 12). Once you release it, re-tension it. In this way, when the tension is released, earth pressure is borne by the concrete of the wall structure 16 together with the anchor fixing member 12, and then the permanent anchor 14 is re-tensioned, The integrity with the anchor fixing member 12 can be further strengthened.

本発明の一実施形態である壁構造の構築工事により構築された鉄筋コンクリート造の壁構造を示す断面図である。It is sectional drawing which shows the wall structure of the reinforced concrete structure constructed | assembled by the construction of the wall structure which is one Embodiment of this invention. 図1の壁構造を同図中左側からみた側面図である。It is the side view which looked at the wall structure of FIG. 1 from the left side in the figure. 図2おける永久アンカー施工部分を示す拡大側面図である。It is an enlarged side view which shows the permanent anchor construction part in FIG. 図1のIV−IV断面図である。It is IV-IV sectional drawing of FIG. 図1のV−V断面図である。It is VV sectional drawing of FIG. 本実施形態における壁構造の構築工程を示す図(その1)である。It is a figure (the 1) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その2)である。It is a figure (the 2) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その3)である。It is a figure (the 3) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その4)である。It is FIG. (The 4) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その5)である。It is FIG. (5) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その6)である。It is FIG. (6) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その7)である。It is a figure (the 7) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その8)である。It is FIG. (The 8) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その9)である。It is FIG. (9) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その10)である。It is FIG. (10) which shows the construction process of the wall structure in this embodiment. 本発明の第2の実施形態において構築される鉄筋コンクリート造の壁構造を示す断面図ある。It is sectional drawing which shows the wall structure of the reinforced concrete structure constructed | assembled in the 2nd Embodiment of this invention. 本実施形態のアンカー定着部材およびその周辺部を拡大して示す断面図である。It is sectional drawing which expands and shows the anchor fixing member of this embodiment, and its peripheral part. 図17における左側からみた正面図である。It is the front view seen from the left side in FIG. 本実施形態における壁構造の構築工程を示す図(その1)である。It is a figure (the 1) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その2)である。It is a figure (the 2) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その3)である。It is a figure (the 3) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その4)である。It is FIG. (The 4) which shows the construction process of the wall structure in this embodiment. 本実施形態における壁構造の構築工程を示す図(その5)である。It is FIG. (5) which shows the construction process of the wall structure in this embodiment. 仮設アンカーを用いた山留を行ったうえで、永久アンカーを用いて壁構造を構築した構成を示す断面図である。It is sectional drawing which shows the structure which constructed | assembled the wall structure using the permanent anchor, after performing the mountain retention using the temporary anchor. 図24の左側から見た正面図である。It is the front view seen from the left side of FIG.

符号の説明Explanation of symbols

10 山留め杭
12 アンカー定着部材
14(14a,14b,14c) 永久アンカー
16 壁構造
22 砕石
24,26 水抜き管
28 砕石保持板
32 スタッド
100 アンカー定着部材
102 補強リブ材
104 斜め支持材
106 腹起こし材
DESCRIPTION OF SYMBOLS 10 Mountain retaining pile 12 Anchor fixing member 14 (14a, 14b, 14c) Permanent anchor 16 Wall structure 22 Crushed stone 24, 26 Drain pipe 28 Crushed stone holding plate 32 Stud 100 Anchor fixing member 102 Reinforcement rib material 104 Diagonal support material 106 Belly raising material

図24は、仮設アンカーを用いた山留めを行ったうえで、永久アンカーを用いて壁構造を構築する構成を示す断面図であり、図25は、図24の左側から見た正面図である。これらの図面を参照して壁構造の施工手順を説明すると、先ず、山留め杭50を打設し、この山留め杭50の内側(図24における左側)の地盤を根切りする。根切り深さが最上段の仮設アンカー施工位置まで達すると、鋼製の腹起こし52を山留め杭50に取り付け、この腹起こし52に仮設アンカー定着固定用の台座54を固定する。そして、最上段の仮設アンカー56aを施工して、台座54に定着固定する。以後、最下段の仮設アンカー56cまで、このような根切りと仮設アンカー56の施工とを繰り返す。 FIG. 24 is a cross-sectional view showing a configuration in which a wall structure is constructed using a permanent anchor after mountain mounting using a temporary anchor, and FIG. 25 is a front view seen from the left side of FIG. The construction procedure of the wall structure will be described with reference to these drawings. First, the pile retaining pile 50 is placed, and the ground inside the pile retaining pile 50 (left side in FIG. 24 ) is rooted. When the root cutting depth reaches the uppermost temporary anchor construction position, a steel erection 52 is attached to the pile pile 50, and a pedestal 54 for fixing the temporary anchor is fixed to the erection 52. Then, the uppermost temporary anchor 56 a is constructed and fixed to the base 54. Thereafter, such root cutting and construction of the temporary anchor 56 are repeated up to the lowermost temporary anchor 56c.

仮設アンカー56の工事が終わると床付を行う。そして、床コンクリート58を打設し、この床コンクリート58から上方へ壁構造60を打設しながら、仮設アンカー56を下から順に撤去していく。すなわち、図24および図25の例では、最下段の仮設アンカー56c、腹起こし52、台座54を撤去してから床コンクリート58を打設し、次段の仮設アンカー56b等を撤去してから壁構造60の最下部を打設し、更に、最上段の仮設アンカー56a等を撤去してから、壁構造60の残りの部分を打設する。また、壁構造60の打設を行いながら、斜め型の永久アンカー62の施工も行う。こうして壁構造60の構築が完了する。 When the construction of the temporary anchor 56 is finished, flooring is performed. Then, the floor concrete 58 is placed, and the temporary anchor 56 is sequentially removed from the bottom while placing the wall structure 60 upward from the floor concrete 58. That is, in the example of FIGS. 24 and 25 , the bottom temporary anchor 56c, the erection 52, and the pedestal 54 are removed, then the floor concrete 58 is placed, and the next temporary anchor 56b and the like are removed before the wall. After the lowermost portion of the structure 60 is driven and the uppermost temporary anchor 56a and the like are removed, the remaining portion of the wall structure 60 is driven. In addition, while the wall structure 60 is driven, the oblique permanent anchor 62 is also constructed. Thus, the construction of the wall structure 60 is completed.

以上説明したように、図24および図25に示す工事では、仮設アンカー56等の施工や撤去の作業が必要となり、施工コストが増大すると共に工事が長期化してしまう。さらに、山留め杭50と壁構造60との間の空間が狭いため、仮設撤去作業は極めて行い難い。しかも、仮設アンカー56等の撤去作業または外壁型枠作業などは、壁構造60や永久アンカー62の施工と並行して行わねばならないため作業が輻輳し、作業効率が悪くなってしまう。   As described above, in the construction shown in FIGS. 24 and 25, the construction and removal of the temporary anchor 56 and the like are required, which increases the construction cost and lengthens the construction. Furthermore, since the space between the mountain retaining pile 50 and the wall structure 60 is narrow, temporary removal work is extremely difficult. In addition, the removal work of the temporary anchor 56 or the like or the outer wall formwork work must be performed in parallel with the construction of the wall structure 60 and the permanent anchor 62, so the work is congested and work efficiency is deteriorated.

上記の目的を達成するため、請求項1に記載された発明は山留めを打設し、該山留めの内側の地盤を根切りして、アンカーを定着固定するためのアンカー定着部材を前記山留めに構築すると共に、斜め型のアンカーを打設し、当該アンカーを前記アンカー定着部材に定着固定した後、壁構造のコンクリートを前記アンカー定着部材と一体となるように打設する永久アンカーが施工された壁構造の構築方法であって、
前記アンカー定着部材を複数段に構築して、各段のアンカー定着部材に、緊張したアンカーを定着し、
前記アンカー定着部材の最下段から最上段へ向けて段毎に、前記壁構造のコンクリートを、前記アンカー定着部材の、前記アンカーの定着位置よりも低い位置まで打設する第1の工程と、アンカー定着部材に定着されたアンカーを再緊張する第2の工程とを行った後、前記壁構造の最上部のコンクリートを打設することを特徴とする。
To achieve the above object, the invention described in claim 1, and Da設the earth retaining, the inner ground of該山fastened to Excavation, anchor fixing member for fixing securing the anchor to the earth retaining In addition to the construction, a permanent anchor was constructed in which an oblique anchor was placed, the anchor was fixedly fixed to the anchor fixing member, and then the wall structure concrete was integrated with the anchor fixing member . A method for building a wall structure,
The anchor fixing member is constructed in a plurality of stages, and a tensioned anchor is fixed on each stage of the anchor fixing member.
A first step of placing concrete of the wall structure from the lowest level of the anchor fixing member to the uppermost level to a position lower than the anchor fixing position of the anchor fixing member; After the second step of re-tensioning the anchor fixed to the fixing member, the uppermost concrete of the wall structure is placed .

また、請求項2に記載された発明は、請求項1記載の方法において、前記アンカー定着部材の段毎に、前記第1の工程の後、前記第2の工程の前に前記アンカーの張力を緩める工程を行い、前記第2の工程で前記アンカーを再緊張するAccording to a second aspect of the present invention, in the method of the first aspect, the tension of the anchor is increased after the first step and before the second step for each step of the anchor fixing member. A loosening step is performed, and the anchor is re-tensioned in the second step .

また、請求項3に記載された発明は、請求項1又は2に記載の構築方法により構築された、永久アンカーが施工された壁構造であるMoreover, the invention described in claim 3 is a wall structure constructed by the construction method according to claim 1 or 2 and provided with a permanent anchor .

壁構造16および床部18の配筋後、図12に示すように、床部18のコンクリートを打設し、さらに、最下段のアンカー定着部材12の高さまで壁構造16のコンクリートを打設する。その際、予め型枠内に水抜き管24を設置しておく。コンクリートの打設後、最下段の永久アンカー14のアンカー鋼材36を再度緊張する。そして、一つ上段のアンカー定着部材12まで、上記と同様にして壁構造16のコンクリートを打設し、当該アンカー定着部材12に定着固定すべき永久アンカー14bのアンカー鋼材36を再緊張する。このような壁構造16の打設作業を最上段のアンカー定着部材12まで繰り返し(図13〜図14を参照)、さらに、壁の最上部のコンクリート16aを打設することで(図15を参照)、図1に示す壁構造の構築が完了する。 After bar arrangement of the wall structure 16 and the floor 18, as shown in FIG. 12, the concrete of the floor 18 is cast, and further the concrete of the wall structure 16 is cast to the height of the anchor fixing member 12 at the lowest level. . At that time, a drain pipe 24 is installed in the mold in advance. Concrete after casting, tensioned anchor steel 3 6 of the lowermost permanent anchor 14 c again. Then, the concrete of the wall structure 16 is placed in the same manner as described above to the upper anchor fixing member 12, and the anchor steel material 36 of the permanent anchor 14b to be fixed and fixed to the anchor fixing member 12 is re- tensioned. By repeating the placement work of the wall structure 16 up to the anchor fixing member 12 at the uppermost stage (see FIGS. 13 to 14), the concrete 16a at the uppermost part of the wall is further placed (see FIG. 15). ), The construction of the wall structure shown in FIG. 1 is completed.

さらに、本実施形態では、山留め杭10と壁構造16との間に砕石22を設置すると共に、アンカー定着部材12および壁構造16に水抜き管24,26を設けることで、地盤からの水抜きを行うことができる。すなわち、地盤内の水は砕石22を通過して壁構造16の水抜き管24から壁の内側へ排出され、また、アンカー定着部材12で上下に分断された各段の砕石22の水は、アンカー定着部材12の水抜き管26通って下段の砕石22へ移動できるので、砕石22による水抜きはより効果的に行われる。したがって、本実施形態によれば、壁構造16の外壁面にかかる水圧を緩和することができる。
Furthermore, in this embodiment, while installing the crushed stone 22 between the retaining pile 10 and the wall structure 16, and providing the drainage pipes 24 and 26 in the anchor fixing member 12 and the wall structure 16, the water is drained from the ground. It can be performed. That is, the water in the ground passes through the crushed stone 22 and is discharged from the drain pipe 24 of the wall structure 16 to the inside of the wall, and the water of the crushed stone 22 at each stage divided vertically by the anchor fixing member 12 is Since it can move to the crushed stone 22 of the lower stage through the drain pipe 26 of the anchor fixing member 12, the drainage by the crushed stone 22 is performed more effectively. Therefore, according to this embodiment, the water pressure applied to the outer wall surface of the wall structure 16 can be relaxed.

Claims (13)

山留めを打設し、該山留めの内側の地盤を根切りして、アンカーを定着固定するためのアンカー定着部材を前記山留めに構築すると共に、斜め型のアンカーを打設し、当該アンカーを前記アンカー定着部材に定着固定した後、壁構造のコンクリートを前記アンカー定着部材と一体となるように打設することを特徴とする永久アンカーが施工された壁構造の構築方法。 An anchor fixing member for anchoring and fixing the anchor is constructed in the mountain retaining by setting up the anchor, rooting the ground inside the anchor, and forming an oblique anchor, and fixing the anchor to the anchor A method for constructing a wall structure on which a permanent anchor is constructed, characterized in that after fixing and fixing to a fixing member, concrete having a wall structure is placed so as to be integrated with the anchor fixing member. 前記アンカーは複数段に設けられ、上段側から下段側へ各段ごとに、地盤の根切り、前記アンカー定着部材の構築、および、前記アンカーの打設と定着固定を行って、全段のアンカーの施工が完了した後、前記壁構造のコンクリートを打設することを特徴とする請求項1記載の方法。 The anchors are provided in a plurality of stages. For each stage from the upper stage side to the lower stage side, ground anchorage, construction of the anchor fixing member, and placement and fixing of the anchor are performed, and anchors in all stages are provided. The method according to claim 1, wherein the concrete of the wall structure is placed after the construction of is completed. 前記壁構造は鉄筋コンクリート造または鉄骨鉄筋コンクリート造であり、前記アンカー定着部材を、鉄筋コンクリートにより構築することを特徴とする請求項1または2記載の方法。 3. The method according to claim 1, wherein the wall structure is reinforced concrete or steel reinforced concrete, and the anchor fixing member is constructed of reinforced concrete. 前記壁構造のコンクリートを打設する前に、前記アンカー定着部材の鉄筋と、前記壁構造の鉄筋とを接合することを特徴とする請求項3記載の方法。 4. The method according to claim 3, wherein the reinforcing bar of the anchor fixing member and the reinforcing bar of the wall structure are joined before placing the concrete of the wall structure. 前記壁構造は鉄骨コンクリート造であり、前記アンカー定着部材を鉄骨コンクリートにより構築することを特徴とする請求項1または2記載の方法。 The method according to claim 1, wherein the wall structure is made of steel concrete, and the anchor fixing member is constructed of steel concrete. 前記壁構造は鉄骨鉄筋コンクリート造であり、前記アンカー定着部材を鉄骨鉄筋コンクリートにより構築することを特徴とする請求項1または2記載の方法。 3. The method according to claim 1, wherein the wall structure is a steel reinforced concrete structure, and the anchor fixing member is constructed of steel reinforced concrete. 前記山留めの前記アンカー定着部材が構築される部位に、根切り部の内方へ突出する突出部材を設け、前記アンカー定着部材のコンクリートを、前記突出部材が前記アンカー定着部材内へ埋め込まれるように打設することを特徴とする請求項3または4記載の方法。 A projecting member projecting inward of the root cutting portion is provided at a site where the anchor fixing member of the mountain fastening is constructed, and the concrete of the anchor fixing member is embedded in the anchor fixing member. The method according to claim 3 or 4, characterized in that it is cast. 前記壁構造の外周面と根切りされた地盤の内側面との間の空間に砕石を設置すると共に、前記壁構造にその内側面と外側面との間を貫通する水抜き管を設けることを特徴とする請求項1〜7のうち何れか1項記載の方法。 Installing crushed stone in a space between the outer peripheral surface of the wall structure and the inner side surface of the ground, and providing a drainage pipe penetrating between the inner side surface and the outer side surface of the wall structure; 8. A method according to any one of the preceding claims. 前記山留めへの前記アンカー定着部材の構築部位の上部位置に通水性を有する保持板を取り付けて当該保持板の上に前記砕石を設置し、前記アンカー定着部材にはその上下を貫通する水抜き管を設けることを特徴とする請求項8記載の方法。 A holding plate having water permeability is attached to the upper position of the construction site of the anchor fixing member to the mountain stopper, and the crushed stone is installed on the holding plate, and the anchor fixing member has a drain pipe penetrating therethrough. 9. The method of claim 8, wherein: 前記アンカー定着部材を、鋼材により構成したことを特徴とする請求項1または2記載の方法。 3. The method according to claim 1, wherein the anchor fixing member is made of a steel material. 前記アンカーを前記アンカー定着部材へ定着した後、その張力を緩める工程と、
前記壁構造のコンクリートの打設後に再緊張する工程と、を含むことを特徴とする請求項1〜10のうち何れか1項記載の方法。
After fixing the anchor to the anchor fixing member, releasing the tension;
The method according to any one of claims 1 to 10, comprising the step of re-tensioning after placing the concrete of the wall structure.
地盤に打設された山留めに、アンカーを定着固定するためのアンカー定着部材が構築され、該アンカー定着部材にアンカーが定着固定されていると共に、壁構造のコンクリートが前記アンカー定着部材と一体となるように打設されていることを特徴とする永久アンカーが施工された壁構造。 An anchor fixing member for fixing and fixing an anchor is constructed on a mountain anchor placed on the ground. The anchor is fixed and fixed to the anchor fixing member, and the wall structure concrete is integrated with the anchor fixing member. A wall structure in which a permanent anchor is constructed. 前記アンカー定着部材は、コンクリート部材または鋼材により構成されていることを特徴とする請求項12記載の壁構造。 The wall structure according to claim 12, wherein the anchor fixing member is made of a concrete member or a steel material.
JP2008066386A 2003-02-05 2008-03-14 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction Expired - Fee Related JP4333801B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008066386A JP4333801B2 (en) 2003-02-05 2008-03-14 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2003028080 2003-02-05
JP2003028080 2003-02-05
JP2008066386A JP4333801B2 (en) 2003-02-05 2008-03-14 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003151592A Division JP4123058B2 (en) 2003-02-05 2003-05-28 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction

Publications (2)

Publication Number Publication Date
JP2008180082A true JP2008180082A (en) 2008-08-07
JP4333801B2 JP4333801B2 (en) 2009-09-16

Family

ID=39653406

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2008066387A Expired - Fee Related JP4433066B2 (en) 2003-02-05 2008-03-14 Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,
JP2008066386A Expired - Fee Related JP4333801B2 (en) 2003-02-05 2008-03-14 Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP2008066387A Expired - Fee Related JP4433066B2 (en) 2003-02-05 2008-03-14 Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,

Country Status (1)

Country Link
JP (2) JP4433066B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763502A (en) * 2019-01-25 2019-05-17 西北大学 A kind of environmentally protective comprehensive processing method of high steep Loess Landslide

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061705B (en) * 2011-01-11 2011-10-05 凌德祥 Timbering wall of built-in prestressed reinforced concrete rectangular pile and construction method thereof
CN102409682B (en) * 2011-11-25 2014-01-15 北京市第三建筑工程有限公司 Pre-stressed anchor rod type steel internal support structure of continuous arched slope protection piles and construction method of pre-stressed anchor rod type steel internal support structure
CN102518147B (en) * 2011-11-28 2013-12-25 湖南大学 Anchoring and retaining structure for reducing support height of existing overhigh retaining wall
CN104141310B (en) * 2013-05-07 2017-04-26 上海市政工程设计研究总院(集团)有限公司 Method for constructing assembly type pre-stress fish-belly sill internal support system
CN103321210A (en) * 2013-06-08 2013-09-25 郭红标 Prestressed anchor cable sheet-pile wall
CN103334421A (en) * 2013-07-05 2013-10-02 郭红标 Pre-stressed anchor cable slab-pile wall
CN103343532B (en) * 2013-07-05 2015-05-13 郭红标 Pre-stressed anchor cable pile-slab wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763502A (en) * 2019-01-25 2019-05-17 西北大学 A kind of environmentally protective comprehensive processing method of high steep Loess Landslide

Also Published As

Publication number Publication date
JP2008150947A (en) 2008-07-03
JP4333801B2 (en) 2009-09-16
JP4433066B2 (en) 2010-03-17

Similar Documents

Publication Publication Date Title
JP4333801B2 (en) Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction
KR100571102B1 (en) Device of Innovative Prestressed Scaffolding System for Improving Workability
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
JP2009097176A (en) Banking structure and its construction method
KR101780370B1 (en) Composite structure using shear connector made of anchor and socket shoe
KR101494132B1 (en) Self reliance type sheathing structure
JP4123058B2 (en) Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction
JP4211491B2 (en) Method for constructing wall structure with permanent anchor, wall structure constructed by this method
KR200385376Y1 (en) Form system for construction of underground slab
KR200370107Y1 (en) Forms for edge girder construction
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR100808939B1 (en) wire-reinforced structure for underground pre-scaffolding system
JP3603130B2 (en) Root-wound reinforcement structure for column bases such as steel columns
KR200383309Y1 (en) Form system for construction of underground slab
KR101787366B1 (en) A Retaining wall using Precast pile and Construction method thereof
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
JP2016044494A (en) Construction method of foundation
KR200370135Y1 (en) Forms for edge girder construction
KR102065941B1 (en) Method for constructing soil retaining wall structure using h-pile
JPH08302689A (en) Construction method for skeleton of underground exterior wall
KR102607848B1 (en) method for constructing self-supporting soil barrier with enhanced tension force transferring capability
KR102607850B1 (en) bracket assembly for constructing self-supporting soil barrier with enhanced tension force transferring capability
JP4373899B2 (en) Attached foundation and construction method of attached foundation
KR100662774B1 (en) Steel beam joint attachment
KR102652914B1 (en) Reinforced soil retaining wall block fixing device

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080501

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20081007

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081201

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090602

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090615

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120703

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120703

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120703

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees