JP2007204219A - Construction method of elevator shaft building - Google Patents

Construction method of elevator shaft building Download PDF

Info

Publication number
JP2007204219A
JP2007204219A JP2006025039A JP2006025039A JP2007204219A JP 2007204219 A JP2007204219 A JP 2007204219A JP 2006025039 A JP2006025039 A JP 2006025039A JP 2006025039 A JP2006025039 A JP 2006025039A JP 2007204219 A JP2007204219 A JP 2007204219A
Authority
JP
Japan
Prior art keywords
foundation
building
floor
floor panel
landing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006025039A
Other languages
Japanese (ja)
Other versions
JP4336682B2 (en
Inventor
Takamitsu Inagaki
孝光 稲垣
Minoru Kinoshita
実 木下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WATAHAN TECHNOS KK
Original Assignee
WATAHAN TECHNOS KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WATAHAN TECHNOS KK filed Critical WATAHAN TECHNOS KK
Priority to JP2006025039A priority Critical patent/JP4336682B2/en
Publication of JP2007204219A publication Critical patent/JP2007204219A/en
Application granted granted Critical
Publication of JP4336682B2 publication Critical patent/JP4336682B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of an elevator shaft building making excavation construction to the minimum, making most of construction to safe ground work, shortening the time necessary for completion at a high dimensional accuracy and making trouble of resident minimum. <P>SOLUTION: PC foundation 1 made of reinforced concrete manufactured in a factory is subjected to caisson at an installation place of the shaft building to construct a foundation. A building body 22 previously integrally assembled to a box shape and having a main pillar material 33 projected downward from four corners at a lower end is hung down on the PC foundation 1 and the main pillar material 33 and a steel column head 2 are connected. A plurality of floor panels 23 for connecting an end of platforms B of each story and the building body 22 are prepared. The floor panels 23 corresponding to the platforms B of the respective stories are hung down from an upper part of the building body 22 by a hanging support member 24 having turn buckles 29, 32 and height positions of the respective floor panels 23 are adjusted by the turn buckles 29, 32. Thereby, the platforms B of the respective stories and the building body 22 are connected by the floor panels 23. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

この発明は、既存建物へ付設されるエレベータにおける昇降路建物、すなわちエレベータシャフトの構築方法に関する。   The present invention relates to a hoistway building in an elevator attached to an existing building, that is, an elevator shaft construction method.

4〜5階建ての既存中低層集合住宅には、エレベータが設置されていないものがある。一方、高齢化が急速に進みつつある現代社会では、バリアフリー化に対する要求が大きく、既存の中低層住宅でもエレベータを設置することが強く望まれている。しかし、1,2階の居住者にとって、エレベータの設置は大きなメリットがなく、したがって、工事に伴う騒音や工事期間中の生活の障害が大きな苦痛に感じられ、また設置費用の居住者負担が求められることもあることから、工事の同意、承認が得にくく、また工事に対する苦情が生じやすいという問題点がある。   Some existing mid- and low-rise apartments with 4 to 5 floors do not have an elevator. On the other hand, in the modern society where the aging is rapidly progressing, there is a great demand for barrier-free, and it is strongly desired to install an elevator even in the existing low-rise housing. However, for residents on the 1st and 2nd floors, the installation of elevators has no great merit. Therefore, the noise associated with the construction and the obstacles to living during the construction are felt very painful, and the residents are required to pay the installation costs. Therefore, there is a problem that it is difficult to obtain consent and approval of the construction, and it is easy to make a complaint about the construction.

そこで、従来より、既存の建物の外部階段室にエレベータを付設する工法が種々提案されている。いずれも、設置費用をできるだけ安く抑え、工事中の居住者の生活への負担を最小限にするために、工事期間を短縮することを目的としている。   Therefore, various methods for attaching an elevator to an external staircase in an existing building have been proposed. Both aim to shorten the construction period in order to keep the installation cost as low as possible and minimize the burden on the lives of residents during construction.

例えば、特許文献1には、外部エレベータの地下ピット部が、地面を掘削した根切り部に設置される構造において、地下ピット部を鉄骨フレームを一体的に組立ててなる鉄骨フレームピットとし、この鉄骨フレームピット部とエレベータ本体部の鉄骨架構とを一体に設けて、最上階部屋根から鉄骨フレームピット部までを工場製作の外部エレベータユニットとし、これを現場打ちコンクリートにより構築された基礎の上に、クレーン等で吊り上げて設置する外部エレベータの構築方法が記載されている。この方法では、エレベータシャフトのピット部が鉄骨構造でユニット化され、現場への運搬が容易となり、現場では、必要に応じて、このピット部に工場製作のプレキャスト板を張るだけで工事が終了するから、施工期間を従来に比べて短縮化できるという。しかし、この方法においても、基礎部分は、掘削部への現場打ちコンクリートで構成される。
特開2004−244208号公報
For example, Patent Document 1 discloses a structure in which an underground pit portion of an external elevator is installed at a root cutting portion excavated from the ground, and the underground pit portion is a steel frame pit formed by integrally assembling a steel frame. The frame pit part and the steel frame of the elevator main body part are provided integrally, and from the top floor roof to the steel frame pit part is an external elevator unit manufactured at the factory, and this is built on the foundation built with cast-in-place concrete, A method for constructing an external elevator that is lifted and installed by a crane or the like is described. In this method, the pit part of the elevator shaft is unitized with a steel frame structure, which makes it easy to transport to the site. At the site, the construction is completed by simply attaching a factory-prepared precast plate to the pit part as necessary. Therefore, it is said that the construction period can be shortened compared to the conventional method. However, even in this method, the foundation portion is made of cast-in-place concrete to the excavation part.
Japanese Patent Laid-Open No. 2004-244208

上記従来の工法においては、基礎部分が現場打ちコンクリートで施工されるため、以下のような問題点がある。(1)設置面積に対して、作業空間を含めより大面積の掘削工事を必要とする。(2)このため、大量の掘削土が発生しその処理に難渋する。(3)掘削壁面の養生の必要性がある。(4)環境の劣悪な地下での長時間の危険な作業を強いられる。(5)長期のコンクリート及び第三者に対する養生が必要である。(6)短期間で高い寸法精度を出すのが困難である。また上記従来の工法においては、昇降路建物と既存建物の階段とを接続する際の高さ調整については何ら考慮されていない。工場製作の外部エレベータユニットとして構成される昇降路建物を基礎上に接続して構築する場合には、既存建物との高さ調整に多くの手数と時間を要することになるという問題点がある。
したがって、この発明は、基礎部を工場生産によるプレキャストコンクリート(PC)化し、潜函工法により現場に埋設することにより、掘削工事を最小限に止め、大部分の工事を安全な地上作業とし、高い寸法精度を出しながら、工期を短縮して居住者の障害を最小限に止めることができるエレベータ用昇降路建物の構築方法を提供することを課題とする。
In the above-mentioned conventional construction method, the foundation part is constructed with cast-in-place concrete, so there are the following problems. (1) Excavation work of a larger area including the work space is required for the installation area. (2) For this reason, a large amount of excavated soil is generated and it is difficult to process it. (3) There is a need to cure the excavated wall. (4) It is forced to perform dangerous work for a long time in the underground where the environment is poor. (5) Long-term concrete and curing for third parties are necessary. (6) It is difficult to achieve high dimensional accuracy in a short period of time. Moreover, in the said conventional construction method, the height adjustment at the time of connecting a hoistway building and the staircase of the existing building is not considered at all. When a hoistway building configured as a factory-made external elevator unit is connected to the foundation, it requires a lot of work and time to adjust the height of the existing building.
Therefore, the present invention makes the foundation part precast concrete (PC) by factory production and embeds it in the site by the submerged method, minimizing excavation work, making most of the work safe ground work, and high dimensions It is an object of the present invention to provide an elevator hoistway building construction method capable of shortening the construction period and minimizing the occupant's obstacle while improving accuracy.

この出願の発明においては、上記課題を解決するため、既存建物の階段Aに隣接して、当該既存建物の外部に、エレベータ用の昇降路建物を構築する方法であって、以下の工程を含むものを提供する。すなわち、(1)予め工場にて製作された鉄筋コンクリート製、無底箱形で、上部の四隅に鉄骨柱頭を突出させたPC基礎1を用意する工程、(2)PC基礎1を昇降路建物21の構築場所に潜函させて地盤に固定することによって基礎を構築する工程、(3)予め箱形に一体に組み立てられ、PC基礎1の鉄骨柱頭2に接続できるように下端の四隅から下方へ主柱材33を突出させた昇降路用の建物本体22を用意する工程、(4)構築されたPC基礎1の上に、建物本体22を吊り下ろして、建物本体の主柱材33とPC基礎の鉄骨柱頭2とを接続する工程、(5)各階の踊り場Bの端部と建物本体22とを接続するための複数の床パネル23を用意する工程、(6)建物本体22の上部から各階の踊り場Bに対応する床パネル23をターンバックル29,32を有する吊支部材24にて吊り、各床パネル23の高さ位置をターンバックル29,32にて調整することにより、各階の踊り場Bと建物本体22との間を床パネル23で接続する工程を含む。   In the invention of this application, in order to solve the above-mentioned problem, a method for constructing a hoistway building for an elevator on the outside of the existing building adjacent to the staircase A of the existing building, which includes the following steps Offer things. That is, (1) a step of preparing a PC foundation 1 made of a reinforced concrete made in advance in a factory and having a bottomless box shape with steel column heads protruding at the upper four corners, and (2) a PC foundation 1 for a hoistway building 21 (3) It is assembled in advance in a box shape and is connected to the steel stigma 2 of the PC foundation 1 so that it can be connected downward to the bottom corners. Step of preparing the hoistway building main body 22 from which the column material 33 protrudes, (4) The building main body 22 is suspended on the constructed PC foundation 1, and the main column material 33 and the PC foundation of the building main body are suspended. (5) preparing a plurality of floor panels 23 for connecting the end of landing B on each floor and the building body 22; (6) connecting each floor from the top of the building body 22; The floor panel 23 corresponding to the landing B The floor panel 23 is suspended between the landing B on each floor and the building main body 22 by suspending by the suspension support member 24 having the buckles 29, 32 and adjusting the height position of each floor panel 23 by the turn buckles 29, 32. A step of connecting with.

この出願の発明においては、以下のような効果を有する。(1)PC基礎を用いるので、基礎の寸法精度と品質を向上させることができる。(2)潜函工法の採用により狭小地での施工が可能となり、(3)掘削土の発生を従来に比して減少させることができると共に、(4)悪環境の地下作業を減少させることができ、(5)既存建物との高さ調整が容易であることとも相まって、工期を大幅に短縮できる。(6)梁材と油圧ジャッキを用いたレベル調整方法の採用により、地上からの作業のみで、安全かつ容易に、レベル調整を行うことができ、(7)PC基礎の位置決めの精度を大幅に向上させることができる等の効果を有する。   The invention of this application has the following effects. (1) Since the PC foundation is used, the dimensional accuracy and quality of the foundation can be improved. (2) Adoption of the submersible construction method enables construction in a narrow area, (3) the generation of excavated soil can be reduced as compared to the conventional, and (4) underground work in adverse environments can be reduced. (5) Coupled with the ease of height adjustment with the existing building, the construction period can be greatly shortened. (6) By adopting a level adjustment method using beam materials and hydraulic jacks, level adjustment can be performed safely and easily only from work on the ground. (7) Significant positioning accuracy of PC foundation It has the effect that it can be improved.

図面を参照してこの発明の実施の形態を説明する。図1は本発明に係るエレベータ用昇降路建物の側面図、図2は本発明に係るエレベータ用昇降路建物の正面図、図3は本発明におけるPC基礎の施工過程を示す断面図、図4は同平面図、図5は本発明の工法に用いるPC基礎の斜視図、図6は本発明におけるPC基礎の施工過程を示す一部の拡大断面図、図7は矩形枠とガイド部材の拡大断面図、図8乃至図15は本発明におけるPC基礎の施工課程を順を追って示す断面図、図16は本発明の昇降路建物の一部の正面図、図17は昇降路建物を構成する鉄骨架構の側面図、図18は昇降路建物を構成する鉄骨架構の正面図、図19は鉄骨架構における吊り梁部の側面図、図20(A)は鉄骨架構における床パネル付近の平面図、(B)は同側面図である。   Embodiments of the present invention will be described with reference to the drawings. 1 is a side view of an elevator hoistway building according to the present invention, FIG. 2 is a front view of the elevator hoistway building according to the present invention, and FIG. 3 is a cross-sectional view showing a construction process of a PC foundation according to the present invention. Is a perspective view of the PC foundation used in the construction method of the present invention, FIG. 6 is a partial enlarged sectional view showing the construction process of the PC foundation in the present invention, and FIG. 7 is an enlarged view of the rectangular frame and the guide member. FIG. 8 to FIG. 15 are sectional views showing the construction process of the PC foundation in the present invention in order, FIG. 16 is a front view of a part of the hoistway building of the present invention, and FIG. 17 constitutes the hoistway building. FIG. 18 is a front view of the steel frame constituting the hoistway building, FIG. 19 is a side view of the suspension beam portion in the steel frame, and FIG. 20 (A) is a plan view of the vicinity of the floor panel in the steel frame. (B) is the side view.

図1,図2に示すエレベータ用昇降路建物21を構築する場合に、この発明の工法においては、まず予め工場にて製作された鉄筋コンクリート製のPC基礎1を昇降路建物21の設置場所に潜函させることにより基礎を構築する。図5に示すように、PC基礎1は、無底の箱形で、上部の四隅に鉄骨柱頭2を突出させてなる。鉄骨柱頭2は、H形鋼材からなり、昇降路建物の本体22の主柱材33にボルト・ナットで接続可能な接続部2aを有する。PC基礎1は、例えば、約2,200mm四方、高さ約1,800mm、重量約10t程度に構成され、下端縁部には、自重による潜函を容易にするため、鉄板で被覆された刃先が形成される。また、PC基礎1の内側下部には、後記耐圧盤15の鉄筋と接続するための接続金具(図示せず)が埋め込まれている。PC基礎1は、工場にて製作され、トラックで現場へ搬送される。   When the elevator hoistway building 21 shown in FIGS. 1 and 2 is constructed, in the construction method of the present invention, first, a reinforced concrete PC foundation 1 manufactured in advance in a factory is hidden in the installation place of the hoistway building 21. To build a foundation. As shown in FIG. 5, the PC foundation 1 has a bottomless box shape, and has steel stigmas 2 projecting from the upper four corners. The steel stigma 2 is made of an H-shaped steel material, and has a connecting portion 2a that can be connected to the main pillar material 33 of the main body 22 of the hoistway building with bolts and nuts. For example, the PC foundation 1 is about 2,200mm square, about 1,800mm in height, and about 10t in weight, and the lower edge is formed with a cutting edge covered with an iron plate to facilitate submerging due to its own weight. The In addition, a connection fitting (not shown) for connecting to a reinforcing bar of a pressure-resistant panel 15 described below is embedded in the inner lower portion of the PC foundation 1. The PC foundation 1 is manufactured at a factory and transported to the site by a truck.

基礎の構築工事は以下のように行われる。まず、図8に示すように、昇降路建物21の設置場所の所要位置に鋼管杭3を打設する。次いで、設置場所の地盤をPC基礎1の潜函面積(底面積)よりもやや広く(例えば周囲に約300mmずつ)、かつ基礎底盤14(図12)を形成する深さ(例えば約2,000mm)より浅く(例えば約700mm)掘削し、養生パネル16で山留して、先行掘地盤4を形成する。また、この先行掘地盤4の外周側を例えば幅100mm、深さ100mm程度に掘削して溝4aを形成する。   The foundation construction work is carried out as follows. First, as shown in FIG. 8, the steel pipe pile 3 is driven in the required position of the installation place of the hoistway building 21. As shown in FIG. Next, the ground of the installation site is slightly larger than the hidden area (bottom area) of the PC foundation 1 (for example, about 300 mm around the circumference) and from the depth (for example, about 2,000 mm) for forming the foundation bottom board 14 (FIG. 12). A shallow excavation (for example, about 700 mm) is carried out, and the pre-excavated ground 4 is formed by mountain cutting with a curing panel 16. Further, the groove 4a is formed by excavating the outer peripheral side of the preceding ground 4 to a width of about 100 mm and a depth of about 100 mm, for example.

次いで、図9に示すように、先行掘地盤4上に、PC基礎の潜函位置を包囲するように、鋼製の矩形枠5を水平に配置し、先行掘地盤4上に配置された矩形枠5の外周に、先行コンクリート6を打設し、当該先行コンクリート6上に基準レベル面6aを形成する。先行コンクリート6の強度確保のために、例えば4週間程度の養生期間をおく。先行コンクリート6は、溝4a内において垂直断面が拡大されており、十分な水平方向の耐力を有する。   Next, as shown in FIG. 9, a steel rectangular frame 5 is horizontally arranged on the preceding excavation ground 4 so as to surround the submerged position of the PC foundation, and the rectangular frame disposed on the preceding excavation ground 4. A preceding concrete 6 is placed on the outer periphery of 5, and a reference level surface 6 a is formed on the preceding concrete 6. In order to secure the strength of the preceding concrete 6, for example, a curing period of about 4 weeks is set. The preceding concrete 6 has an enlarged vertical section in the groove 4a and has sufficient horizontal strength.

ここで、図4,図7を参照して、矩形枠5の構造を説明する。矩形枠5は、互いに両端部においてボルト・ナットにより接続・分離可能に構成される4つの枠材5a,5b,5c,5d(図4)からなり、施工現場において矩形の枠に組み立てられる。各枠材5a,5b,5c,5dは、図7に示すように、先行掘地盤4上に載置される接地片51と、PC基礎の外周に平行に所定の間隔を置いて対向するように配置される起立片52と、接地片51と平行に対向する上部片53とを具備する。先行コンクリート6を打設する工程において、矩形枠5が、先行コンクリート6の内側の型枠として使用され、上部片53が先行コンクリート6の基準レベル面6aと面一となる。各枠材5a,5b,5c,5dには、3カ所ずつガイド取付板7が固着される。ガイド取付板7は、上部片53の上面に溶着され、基準レベル面6aの上に載る位置に配置される。ガイド取付板7は、枠材の延長直交方向のボルト挿通用長孔7aを有する。   Here, the structure of the rectangular frame 5 will be described with reference to FIGS. The rectangular frame 5 is composed of four frame members 5a, 5b, 5c, and 5d (FIG. 4) that can be connected and separated by bolts and nuts at both ends, and is assembled into a rectangular frame at a construction site. As shown in FIG. 7, the frame members 5a, 5b, 5c, and 5d are opposed to the grounding piece 51 placed on the preceding excavated ground 4 with a predetermined interval in parallel to the outer periphery of the PC foundation. And an upper piece 53 that faces the ground piece 51 in parallel. In the step of placing the preceding concrete 6, the rectangular frame 5 is used as a mold inside the preceding concrete 6, and the upper piece 53 is flush with the reference level surface 6 a of the preceding concrete 6. Each frame member 5a, 5b, 5c, 5d has three guide mounting plates 7 fixed thereto. The guide mounting plate 7 is welded to the upper surface of the upper piece 53 and is disposed at a position on the reference level surface 6a. The guide mounting plate 7 has a long hole 7a for inserting a bolt in an extending orthogonal direction of the frame member.

施工方法に戻る。次いで、図10、図7に示すように、矩形枠5のガイド取付板7上に、ボルト・ナット9でガイド部材8を取り付ける。図示の実施例(図7)において、ガイド部材8は、アングル鋼材からなる取付部材8aの起立片にキャスター8bを固着してなる。これと相前後して、PC基礎1をクレーンで吊り、図11に示すように、矩形枠5の内側の先行掘地盤4上にPC基礎1を配置する。この際、矩形枠5の内側とPC基礎1の外側面との間に所定の間隔(例えば約30mm)を置くよう位置調整する。このとき、長孔7aに対するボルト・ナット9の位置を変更することにより、ガイド部材8の位置を調整し、矩形枠5とPC基礎1との間に上記所定間隔が形成される位置において車輪がPC基礎1の外側面に接触するようにガイド部材8を固定する。   Return to the construction method. Next, as shown in FIGS. 10 and 7, the guide member 8 is attached to the guide attachment plate 7 of the rectangular frame 5 with bolts and nuts 9. In the illustrated embodiment (FIG. 7), the guide member 8 is formed by fixing casters 8b to an upright piece of an attachment member 8a made of angle steel. Before and after this, the PC foundation 1 is suspended by a crane, and the PC foundation 1 is placed on the preceding excavation ground 4 inside the rectangular frame 5 as shown in FIG. At this time, the position is adjusted so that a predetermined interval (for example, about 30 mm) is placed between the inside of the rectangular frame 5 and the outside surface of the PC foundation 1. At this time, the position of the guide member 8 is adjusted by changing the position of the bolt / nut 9 with respect to the long hole 7a, and the wheel is located at the position where the predetermined interval is formed between the rectangular frame 5 and the PC base 1. The guide member 8 is fixed so as to contact the outer surface of the PC foundation 1.

次いで、図12に示すように、先行掘地盤4上に配置されたPC基礎1の内側の地盤を順次掘削して徐々にPC基礎1を自重で潜函させ、基準レベルまで潜函したところで基礎底盤14を形成する。潜函の過程でPC基礎1は傾くので、ガイド部材8が側面に接してこれを案内する。このとき、ガイド部材8を介して矩形枠5に水平方向の力が作用する。先行掘地盤4の溝4aにより垂直方向の断面積を拡大された先行コンクリート6が、この水平力に有効に対抗する。   Next, as shown in FIG. 12, the ground inside the PC foundation 1 arranged on the preceding excavation ground 4 is sequentially excavated, and the PC foundation 1 is gradually submerged by its own weight. Form. Since the PC foundation 1 is tilted during the submergence process, the guide member 8 contacts the side surface and guides it. At this time, a horizontal force acts on the rectangular frame 5 via the guide member 8. The preceding concrete 6 whose sectional area in the vertical direction is enlarged by the groove 4a of the preceding excavated ground 4 effectively counters this horizontal force.

次いで、図13に示すように、レベル調整装置10を用いてPC基礎1を所定の設計位置に正確に位置決めする。   Next, as shown in FIG. 13, the level adjusting device 10 is used to accurately position the PC foundation 1 at a predetermined design position.

レベル調整装置10について説明する。レベル調整装置10は、PC基礎の各一対の鉄骨柱頭2,2間に架設される梁材11と、この梁材11と先行コンクリートの基準レベル面6aとの間に挿入される油圧ジャッキ12とを具備する。図示の実施例において、梁材11は、PC基礎1の外側へ張り出した両端の下部に垂直下方へ延出するように固着された束材13を具備する。梁材11は、下面の所定位置に、鉄骨柱頭2を構成するH形鋼材のフランジの外側面に当接するブラケット11aを有する。このブラケット11aは、鉄骨柱頭2の接続部2aに形成されたボルト挿通孔に対応するボルト挿通孔を有し、鉄骨柱頭2にボルト・ナットで接続可能に構成される。   The level adjusting device 10 will be described. The level adjusting device 10 includes a beam member 11 installed between each pair of steel stigmas 2 and 2 on a PC foundation, and a hydraulic jack 12 inserted between the beam member 11 and a reference level surface 6a of preceding concrete. It comprises. In the illustrated embodiment, the beam member 11 includes a bundle member 13 fixed so as to extend vertically downward to the lower part of both ends projecting to the outside of the PC foundation 1. The beam member 11 has a bracket 11 a that is in contact with the outer surface of the flange of the H-shaped steel member constituting the steel stigma 2 at a predetermined position on the lower surface. The bracket 11a has a bolt insertion hole corresponding to a bolt insertion hole formed in the connection portion 2a of the steel stigma 2 and is configured to be connectable to the steel stigma 2 with bolts and nuts.

施工方法に戻る。束材13の下端と先行コンクリート6の基準レベル面6aとの間に、油圧ジャッキ12を挿入し、油圧ジャッキ12を地上で操作して、PC基礎の鉄骨柱頭2のレベルを設計値に精度よく合わせるように位置決めする。PC基礎の位置決め完了後、矩形枠5からガイド部材8を撤去し、鋼管杭3の先端部を処理した後、PC基礎1内の基礎底盤14上に、図14に示すように、鉄筋を配筋してコンクリートを打設することにより耐圧盤15を形成する。鉄筋は、PC基礎1に予め埋め込まれている接続金具と接続する。   Return to the construction method. The hydraulic jack 12 is inserted between the lower end of the bundle 13 and the reference level surface 6a of the preceding concrete 6, and the hydraulic jack 12 is operated on the ground so that the level of the steel foundation 2 of the PC foundation is accurately set to the design value. Position to match. After the positioning of the PC foundation is completed, the guide member 8 is removed from the rectangular frame 5, the tip of the steel pipe pile 3 is processed, and then the reinforcing bars are arranged on the foundation bottom 14 in the PC foundation 1 as shown in FIG. The pressure platen 15 is formed by striking and placing concrete. The rebar is connected to a connection fitting embedded in the PC foundation 1 in advance.

1週間程度養生して耐圧盤15の強度が確保された後、レベル調整用の梁材11、束材13、油圧ジャッキ12を撤去し、図15に示すように、PC基礎1の周りを埋め戻す。以上で基礎工事が完了する。   After curing for about one week and ensuring the strength of the pressure-resistant panel 15, the beam material 11, the bundle material 13, and the hydraulic jack 12 for level adjustment are removed, and the PC foundation 1 is buried as shown in FIG. return. This completes the foundation work.

図1,2,16に示すように、エレベータの昇降路建物21は、建物本体22と、床パネル23と、吊支部材24とを具備する。昇降路建物21は、既存建物の階段Aにおける3,4,5階の各階の踊り場Bの端部に、床パネル23を介して出入り口32を接続するように、当該既設建物の外部に構築される。   As shown in FIGS. 1, 2, and 16, the elevator hoistway building 21 includes a building body 22, a floor panel 23, and a suspension member 24. The hoistway building 21 is constructed outside the existing building so that the entrance / exit 32 is connected to the end of the landing B on each of the third, fourth, and fifth floors of the staircase A of the existing building through the floor panel 23. The

建物本体22は、例えば予め工場にて一体の箱形に組み立てられて、現場に搬送され、予め現場に構築されたPC基礎1上にクレーンで吊り下ろされ、ボルト・ナットで接続される。   For example, the building main body 22 is assembled in advance in an integrated box shape at a factory, transported to the site, suspended on a PC foundation 1 previously constructed on the site by a crane, and connected by bolts and nuts.

建物本体22と各階の踊り場Bの端部とは、床パネル3により接続される。吊支部材24は、床パネル23を、高さ位置を調整可能に、建物本体22に吊り止める。   The building body 22 and the end of the landing B on each floor are connected by the floor panel 3. The suspension member 24 suspends the floor panel 23 from the building body 22 so that the height position can be adjusted.

建物本体22には、最上部付近に位置して、既存建物の階段A側へ向かって張り出す吊り梁25が設けられると共に、各階の踊り場Bに対応する高さ位置において床パネル3のエレベータ側の端部を支持する床パネル受け部材26が設けられる。   The building body 22 is provided with a suspension beam 25 that is located near the top and projects toward the stairs A side of the existing building, and at the height side corresponding to the landing B on each floor, on the elevator side of the floor panel 3. A floor panel receiving member 26 is provided to support the end of the floor panel.

吊支部材24は、建物本体の吊り梁25と最上階の床パネル23とをターンバックル29を介して高さ位置調整可能に結合する上下一対のねじ棒27,28と、その下方の各上下階の床パネル23,23間をターンバックル32を介して高さ位置調整可能に結合する上下一対のねじ棒30,31とを具備する。   The suspension support member 24 includes a pair of upper and lower screw rods 27 and 28 that couple the suspension beam 25 of the building body and the floor panel 23 on the uppermost floor via a turnbuckle 29 so that the height position can be adjusted, and the upper and lower portions of the upper and lower screw rods 27 and 28. A pair of upper and lower screw rods 30 and 31 are connected between the floor panels 23 and 23 of the floor via a turnbuckle 32 so that the height position can be adjusted.

一般に、建物本体2を一体のものとして工場で組み立てる場合には、構築現場において、踊り場Bとの接続のための位置調整に手間取るが、この実施形態においては、ねじ棒27・28,30・31とターンバックル29,32の調整により、床パネル23の高さ位置を任意に変更することで、位置合わせ作業を迅速に行うことができる。   In general, when the building body 2 is assembled as a unit at a factory, it takes time to adjust the position for connection to the landing B at the construction site. In this embodiment, the screw rods 27, 28, 30, 31 are used. By adjusting the turnbuckles 29 and 32, the height position of the floor panel 23 is arbitrarily changed, so that the alignment operation can be performed quickly.

図17,18に示すように、建物本体2は、H形鋼材からなる四隅の主柱材33を梁34と腹材35で接続して箱形に一体に組まれた鉄骨架構36を具備する。   As shown in FIGS. 17 and 18, the building body 2 includes a steel frame 36 integrally formed in a box shape by connecting main pillar members 33 at four corners made of an H-shaped steel member with beams 34 and abdominal members 35.

鉄骨架構36の最上部付近に位置して、既存建物の階段A側へ向かって左右両側から突出するように接続部材37が設けられる(図19)。吊り梁25は、この接続部材37の先端にボルト・ナットにて現場で接続される。接続部材37は、床パネル受け部材26と同じ突出寸法を有し、運搬時の安定性を確保し、また運搬時に一部に過度の負荷がかからないようになっている。   A connection member 37 is provided so as to protrude from both the left and right sides toward the stairs A side of the existing building, located near the uppermost part of the steel frame 36 (FIG. 19). The suspension beam 25 is connected to the tip of the connection member 37 at the site using bolts and nuts. The connecting member 37 has the same projecting dimensions as the floor panel receiving member 26, ensures stability during transportation, and does not apply an excessive load to a part during transportation.

床パネル受け部材26は、正面側左右一対の主柱材33の所要高さ位置に、工場にて予め固着される。   The floor panel receiving member 26 is fixed in advance at a required height position of the pair of left and right main pillar members 33 on the front side.

図20に示すように、床パネル23は、既存建物の踊り場Bに向く一端側の左右に、上下からねじ棒28,30(30,31)を螺合することができる垂直方向のねじ筒38が埋設され、他端側には、床パネル受け部材26との間を所要の高さ調整用スペーサ39を介してボルト40にて接続するための垂直方向のボルト挿通孔21が設けられている。   As shown in FIG. 20, the floor panel 23 has a vertical screw cylinder 38 in which screw rods 28, 30 (30, 31) can be screwed from above and below on the left and right sides of one end facing the landing B of the existing building. The other end side is provided with a vertical bolt insertion hole 21 for connecting the floor panel receiving member 26 with a bolt 40 via a required height adjusting spacer 39. .

例えば、工場で一体に組み立てられた建物本体22は、トラック等で建設現場に搬送され、現場において吊り梁25が接続される。建物本体22は、クレーンで吊り上げられ、予め構築されているPC基礎1の上に降ろされ、主柱材33の下端部を鉄骨柱頭2に接続することにより自立する。   For example, the building body 22 assembled integrally in a factory is transported to a construction site by a truck or the like, and a suspension beam 25 is connected to the site. The building body 22 is lifted by a crane, lowered onto the PC foundation 1 constructed in advance, and becomes independent by connecting the lower end portion of the main column member 33 to the steel stigma 2.

各階の踊り場Bの端部と建物本体22の各床パネル受け部材26とを接続するため、床パネル23が取り付けられる。建物本体22の吊り梁25と最上階の踊り場Bに接続される床パネル23は、ターンバックル29を介して上下一対のねじ棒27,28にて結合される。床パネル23の高さ位置は、ターンバックル29にて調整され、最上階の踊り場Bと建物本体22の対応する床パネル受け部材26との間が床パネル23で接続される。それよりの下方の階における床パネル23は、それぞれ、その直上の階の床パネル23とターンバックル32を介して上下一対のねじ棒30,31にて結合される。当該床パネル23の高さ位置はターンバックル32にて調整され、踊り場Bと建物本体22の対応する床パネル受け部材26との間が床パネル23で接続される。その後、手摺り、壁板等が付設され、昇降路建物21が完成する。   A floor panel 23 is attached to connect the end of the landing B on each floor and each floor panel receiving member 26 of the building body 22. The suspension beam 25 of the building main body 22 and the floor panel 23 connected to the landing B on the uppermost floor are coupled with a pair of upper and lower screw rods 27 and 28 via a turnbuckle 29. The height position of the floor panel 23 is adjusted by the turnbuckle 29, and the floor panel 23 is connected between the landing B on the top floor and the corresponding floor panel receiving member 26 of the building body 22. The floor panel 23 on the floor below it is coupled with a pair of upper and lower screw rods 30 and 31 via the floor panel 23 and turnbuckle 32 on the floor immediately above. The height position of the floor panel 23 is adjusted by the turnbuckle 32, and the floor panel 23 connects between the landing B and the corresponding floor panel receiving member 26 of the building body 22. Thereafter, handrails, wall boards and the like are attached, and the hoistway building 21 is completed.

この発明は、例えば、4〜5階建ての既存の現住集合住宅の階段に接続するように、後付で外部エレベータの昇降路建物を構築するために採用することができ、これにより、工期を大幅に短縮することができる。   This invention can be employed to build a hoistway building for an external elevator on a retrofit, for example, so as to connect to the existing staircase of an existing dwelling house of 4 to 5 stories, thereby reducing the construction period. It can be greatly shortened.

エレベータ用昇降路建物の側面図である。It is a side view of the hoistway building for elevators. エレベータ用昇降路建物の正面図である。It is a front view of the hoistway building for elevators. 基礎の施工過程を示す断面図である。It is sectional drawing which shows the construction process of a foundation. 基礎の施工過程を示す平面図である。It is a top view which shows the construction process of a foundation. PC基礎の斜視図である。It is a perspective view of PC foundation. 基礎の施工過程を示す一部の拡大断面図である。It is a partial expanded sectional view which shows the construction process of a foundation. 矩形枠とガイド部材の拡大断面図である。It is an expanded sectional view of a rectangular frame and a guide member. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 基礎の施工過程を順を追って示す断面図である。It is sectional drawing which shows the construction process of a foundation later on. 昇降路建物の一部の正面図である。It is a front view of a part of hoistway building. 昇降路建物を構成する鉄骨架構の側面図である。It is a side view of the steel frame which comprises a hoistway building. 昇降路建物を構成する鉄骨架構の正面図である。It is a front view of the steel frame which comprises a hoistway building. 鉄骨架構における吊り梁部の側面図である。It is a side view of the suspension beam part in a steel frame. (A)は鉄骨架構における床パネル付近の平面図、(B)は同側面図である。(A) is a plan view of the vicinity of the floor panel in the steel frame, and (B) is a side view thereof.

符号の説明Explanation of symbols

1 PC基礎
2 鉄骨柱頭
2a 接続部
3 鋼管杭
4 先行掘地盤
4a 溝
5 矩形枠
5a 枠材
5b 枠材
5c 枠材
5d 枠材
51 接地片
52 起立片
53 上部片
6 先行コンクリート
6a 基準レベル面
7 ガイド取付板
7a 長孔
8 ガイド部材
8a 起立片
8b キャスター
9 ボルト・ナット
10 レベル調整装置
11 レベル調整用梁材
11a ブラケット
12 油圧ジャッキ
13 束材
14 基礎底盤
15 耐圧盤
16 養生パネル
21 昇降路建物
22 建物本体
23 床パネル
24 吊支部材
25 吊り梁
26 床パネル受け部材
27 ねじ棒
28 ねじ棒
29 ターンバックル
30 ねじ棒
31 ねじ棒
32 ターンバックル
33 主柱材
34 梁
35 腹材
36 鉄骨架構
37 接続部材
38 ねじ筒
39 調整用スペーサ
40 ボルト
41 ボルト挿通孔
42 出入り口
A 既存建物の階段
B 踊り場
DESCRIPTION OF SYMBOLS 1 PC foundation 2 Steel stigma 2a Connection part 3 Steel pipe pile 4 Prior excavation ground 4a Groove 5 Rectangular frame 5a Frame material 5b Frame material 5c Frame material 5d Frame material 51 Standing piece 52 Standing piece 53 Upper piece 6 Prior concrete 6a Reference level surface 7 Guide mounting plate 7a Long hole 8 Guide member 8a Standing piece 8b Caster 9 Bolt / nut 10 Level adjusting device 11 Level adjusting beam 11a Bracket 12 Hydraulic jack 13 Bundling material 14 Base bottom 15 Pressure plate 16 Curing panel 21 Hoistway building 22 Building body 23 Floor panel 24 Suspension support member 25 Suspension beam 26 Floor panel receiving member 27 Screw rod 28 Screw rod 29 Turnbuckle 30 Screw rod 31 Screw rod 32 Turnbuckle 33 Main pillar material 34 Beam 35 Abdominal material 36 Steel frame 37 Connecting member 38 Screw cylinder 39 Adjustment spacer 40 Bolt 41 Bolt insertion hole 42 Entrance / exit A Stage B landing

Claims (3)

既存建物の階段に隣接して、当該既存建物の外部に、エレベータ用の昇降路建物を構築する方法であって、
予め工場にて製作された鉄筋コンクリート製、無底箱形で、上部の四隅に鉄骨柱頭を突出させたPC基礎を用意する工程と、
前記PC基礎を昇降路建物の構築場所に潜函させて地盤に固定することによって基礎を構築する工程と、
予め箱形に一体に組み立てられ、前記PC基礎の鉄骨柱頭に接続できるように下端の四隅から下方へ突出する主柱材を具備する昇降路用の建物本体を用意する工程と、
構築された前記PC基礎の上に、前記建物本体を吊り下ろして、建物本体の主柱材とPC基礎の鉄骨柱頭とを接続する工程と、
前記各階の踊り場の端部と前記建物本体とを接続するための複数の床パネルを用意する工程と、
前記建物本体の上部から前記各階の踊り場に対応する前記床パネルをターンバックルを有する吊支部材にて吊り、各床パネルの高さ位置をターンバックルにて調整することにより、各階の踊り場と建物本体との間を床パネルで接続する工程と、を含むことを特徴とするエレベータ用昇降路建物の構築方法。
A method of constructing a hoistway building for an elevator outside the existing building adjacent to the stairs of the existing building,
A step of preparing a PC foundation made of reinforced concrete made in advance in a factory, in a bottomless box shape, with steel pillars protruding at the upper four corners,
Building the foundation by immersing the PC foundation in the construction site of the hoistway building and fixing it to the ground;
Preparing a building body for a hoistway, which is assembled in advance in a box shape and includes main pillar members projecting downward from the four corners of the lower end so as to be connected to the steel foundation of the PC foundation;
Hanging the building body on the constructed PC foundation and connecting the main pillar material of the building body and the steel foundation of the PC foundation;
Preparing a plurality of floor panels for connecting the end of the landing on each floor and the building body;
Hanging the floor panel corresponding to the landing on each floor from the upper part of the building body with a suspension member having a turnbuckle, and adjusting the height position of each floor panel with the turnbuckle, A method of constructing a hoistway building for an elevator, comprising a step of connecting the main body with a floor panel.
既存建物の階段に隣接して、当該既存建物の外部に、エレベータ用の昇降路建物を構築する方法であって、
予め工場にて製作された鉄筋コンクリート製、無底箱形で、上部の四隅に鉄骨柱頭を突出させたPC基礎を用意する工程と、
昇降路建物の構築場所の地盤を前記PC基礎の底面積よりも広く掘削して先行掘地盤を形成する工程と、
前記先行掘地盤上に、前記PC基礎を潜函させる位置を包囲するように、鋼製の矩形枠を水平に配置する工程と、
前記先行掘地盤上の前記矩形枠の外周に、先行コンクリートを打設し、当該先行コンクリート上に基準レベル面を形成する工程と、
前記矩形枠の内側に所定の間隔を置いて、前記先行掘地盤上に、前記PC基礎を配置する工程と、
前記矩形枠の所要位置に、前記PC基礎を設計位置へ潜函させるための複数のガイド部材を、PC基礎の四囲に転接するように固定する工程と、
前記PC基礎の内側の地盤を基礎底盤となる位置まで掘削して、PC基礎を基準レベルまで潜函させる工程と、
前記PC基礎の各一対の鉄骨柱頭間に、PC基礎の外側へ張り出すレベル調整用の梁材を架設する工程と、
前記梁材と前記先行コンクリートの基準レベル面との間に、油圧ジャッキを挿入する工程と、
前記油圧ジャッキを操作して、前記PC基礎の鉄骨柱頭のレベルを設計値に合わせて位置決めする工程と、
前記PC基礎の位置決め完了後、前記矩形枠から前記ガイド部材を撤去する工程と、
所定位置に潜函された前記PC基礎内の基礎底盤上に、鉄筋を配筋してコンクリートを打設することにより耐圧盤を形成する工程と、
前記耐圧盤の強度確保後、前記レベル調整用の梁材と前記油圧ジャッキを撤去する工程と、
前記PC基礎の周りを埋め戻す工程と、
予め箱形に一体に組み立てられ、前記PC基礎の鉄骨柱頭に接続できるように下端の四隅から下方へ突出する主柱材を具備する昇降路用の建物本体を用意する工程と、
構築された前記PC基礎の上に、前記建物本体を吊り下ろして、建物本体の主柱材とPC基礎の鉄骨柱頭とを接続する工程と、
前記各階の踊り場の端部と前記建物本体とを接続するための複数の床パネルを用意する工程と、
前記建物本体の上部から前記各階の踊り場に対応する前記床パネルをターンバックルを有する吊支部材にて吊り、各床パネルの高さ位置をターンバックルにて調整することにより、各階の踊り場と建物本体との間を床パネルで接続する工程と、を含むことを特徴とするエレベータ用昇降路建物の構築方法。
A method of constructing a hoistway building for an elevator outside the existing building adjacent to the stairs of the existing building,
A step of preparing a PC foundation made of reinforced concrete made in advance in a factory, in a bottomless box shape, with steel pillars protruding at the upper four corners,
A step of excavating the ground of the construction site of the hoistway building wider than the bottom area of the PC foundation to form a preceding excavated ground;
A step of horizontally arranging a steel rectangular frame on the preceding excavated ground so as to surround a position where the PC foundation is hidden;
Placing the preceding concrete on the outer periphery of the rectangular frame on the preceding excavated ground, and forming a reference level surface on the preceding concrete;
Placing the PC foundation on the preceding excavated ground at a predetermined interval inside the rectangular frame;
Fixing a plurality of guide members for submerging the PC foundation to a design position at a required position of the rectangular frame so as to make rolling contact with the four sides of the PC foundation;
Excavating the ground inside the PC foundation to a position to become the foundation bottom, and submerging the PC foundation to a reference level;
A step of laying beam members for level adjustment projecting outside the PC foundation between each pair of steel stigma of the PC foundation;
Inserting a hydraulic jack between the beam material and the reference level surface of the preceding concrete;
Operating the hydraulic jack to position the PC foundation steel stigma according to the design value; and
A step of removing the guide member from the rectangular frame after the positioning of the PC foundation is completed;
Forming a pressure-resistant platen by placing reinforcing bars and placing concrete on the foundation bottom plate in the PC foundation submerged in a predetermined position;
After securing the strength of the pressure platen, removing the beam material for level adjustment and the hydraulic jack,
Backfilling around the PC foundation;
Preparing a building body for a hoistway, which is assembled in advance in a box shape and includes main pillar members projecting downward from the four corners of the lower end so as to be connected to the steel foundation of the PC foundation;
Hanging the building body on the constructed PC foundation and connecting the main pillar material of the building body and the steel foundation of the PC foundation;
Preparing a plurality of floor panels for connecting the end of the landing on each floor and the building body;
Hanging the floor panel corresponding to the landing on each floor from the upper part of the building body with a suspension member having a turnbuckle, and adjusting the height position of each floor panel with the turnbuckle, A method of constructing a hoistway building for an elevator, comprising a step of connecting the main body with a floor panel.
前記建物本体が、前記階段の最上部の踊り場より上方に位置して前記既存建物へ向かって張り出す位置に設けられた吊り梁と、前記階段における各階の踊り場に対応する高さ位置に設けられた床パネル受け部材と、前記PC基礎の鉄骨柱頭に接続できるように下端の四隅から下方へ突出する主柱材とを具備し、
前記各階の踊り場の端部と前記建物本体の各床パネル受け部材とを接続するための複数の床パネルを用意する工程と、
前記建物本体の吊り梁と最上階の踊り場に接続される前記床パネルとをターンバックルを介して上下一対のねじ棒にて結合し、当該床パネルの高さ位置をターンバックルにて調整し、最上階の踊り場と建物本体の対応する前記床パネル受け部材との間を床パネルで接続する工程と、
上階の踊り場に接続される前記床パネルと当該踊り場の下階の踊り場に接続される前記床パネルとをターンバックルを介して上下一対のねじ棒にて結合し、下階の踊り場に接続される床パネルの高さ位置をターンバックルにて調整し、下階の踊り場と建物本体の対応する前記床パネル受け部材との間を床パネルで接続する工程と、を含むことを特徴とする請求項2に記載のエレベータ用昇降路建物の構築方法。
The building body is provided at a height corresponding to the landing on each floor in the staircase, and a suspension beam provided at a position protruding above the uppermost landing on the stairs and projecting toward the existing building. A floor panel receiving member and a main column member projecting downward from the four corners of the lower end so as to be connected to the steel foundation of the PC foundation,
Preparing a plurality of floor panels for connecting the end of the landing on each floor and each floor panel receiving member of the building body;
Combine the suspension beam of the building body and the floor panel connected to the landing on the top floor with a pair of upper and lower screw rods via a turnbuckle, and adjust the height position of the floor panel with the turnbuckle. Connecting a floor panel between the landing on the top floor and the corresponding floor panel receiving member of the building body;
The floor panel connected to the landing on the upper floor and the floor panel connected to the landing on the lower floor of the landing are connected with a pair of upper and lower screw rods via a turnbuckle to be connected to the landing on the lower floor. Adjusting the height position of the floor panel with a turnbuckle, and connecting the lower floor landing area and the corresponding floor panel receiving member of the building body with the floor panel. Item 3. A method for constructing an elevator hoistway building according to Item 2.
JP2006025039A 2006-02-01 2006-02-01 Construction method of elevator hoistway building Expired - Fee Related JP4336682B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006025039A JP4336682B2 (en) 2006-02-01 2006-02-01 Construction method of elevator hoistway building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006025039A JP4336682B2 (en) 2006-02-01 2006-02-01 Construction method of elevator hoistway building

Publications (2)

Publication Number Publication Date
JP2007204219A true JP2007204219A (en) 2007-08-16
JP4336682B2 JP4336682B2 (en) 2009-09-30

Family

ID=38484015

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006025039A Expired - Fee Related JP4336682B2 (en) 2006-02-01 2006-02-01 Construction method of elevator hoistway building

Country Status (1)

Country Link
JP (1) JP4336682B2 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015048573A (en) * 2013-08-29 2015-03-16 住友林業株式会社 Ring-shaped wall positioning method using liner plate
CN107842034A (en) * 2017-12-04 2018-03-27 三洋电梯(珠海)有限公司 A kind of the fast and safe construction system and rapid constructing method on elevator hoistways basis
CN108360840A (en) * 2018-03-26 2018-08-03 北京筑福建筑事务有限责任公司 It is a kind of that elevator structure and its construction method are added using prefabricated plate
CN109184150A (en) * 2018-10-29 2019-01-11 张云天 A kind of existing multi-storey building of cold district installs the prefabricated assembled hoistway of elevator and its construction method additional
CN109208936A (en) * 2018-11-02 2019-01-15 中国建筑局(集团)有限公司 A kind of existing building elevator shaft structure, which adds, builds structure and its construction method
CN109941868A (en) * 2019-04-16 2019-06-28 陶新宇 A kind of load-bearing pillar and elevator frame
JP2019173319A (en) * 2018-03-27 2019-10-10 旭化成ホームズ株式会社 Elevator pit, construction method and building for elevator pit
CN110485557A (en) * 2019-09-12 2019-11-22 潍坊达福嘉建筑配套工程有限公司 A kind of steel construction elevator quick assembled type vestibule
CN111270867A (en) * 2020-01-21 2020-06-12 山东大学 Novel roof steel truss suspension assembly type elevator structure and construction method thereof
CN112942887A (en) * 2021-02-04 2021-06-11 广东世纪达建设集团有限公司 Construction method for additionally building new corridor below old corridor in old building
CN116675088A (en) * 2023-06-16 2023-09-01 杭州西奥电梯现代化更新有限公司 Attached elevator
CN116771155A (en) * 2023-06-16 2023-09-19 杭州西奥电梯现代化更新有限公司 Attached elevator, elevator construction device and construction method thereof

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015048573A (en) * 2013-08-29 2015-03-16 住友林業株式会社 Ring-shaped wall positioning method using liner plate
CN107842034A (en) * 2017-12-04 2018-03-27 三洋电梯(珠海)有限公司 A kind of the fast and safe construction system and rapid constructing method on elevator hoistways basis
CN107842034B (en) * 2017-12-04 2024-01-05 三洋电梯(珠海)有限公司 Quick safety construction system and quick construction method for elevator shaft foundation
CN108360840A (en) * 2018-03-26 2018-08-03 北京筑福建筑事务有限责任公司 It is a kind of that elevator structure and its construction method are added using prefabricated plate
JP2019173319A (en) * 2018-03-27 2019-10-10 旭化成ホームズ株式会社 Elevator pit, construction method and building for elevator pit
CN109184150A (en) * 2018-10-29 2019-01-11 张云天 A kind of existing multi-storey building of cold district installs the prefabricated assembled hoistway of elevator and its construction method additional
CN109208936A (en) * 2018-11-02 2019-01-15 中国建筑局(集团)有限公司 A kind of existing building elevator shaft structure, which adds, builds structure and its construction method
CN109941868A (en) * 2019-04-16 2019-06-28 陶新宇 A kind of load-bearing pillar and elevator frame
CN110485557A (en) * 2019-09-12 2019-11-22 潍坊达福嘉建筑配套工程有限公司 A kind of steel construction elevator quick assembled type vestibule
CN111270867A (en) * 2020-01-21 2020-06-12 山东大学 Novel roof steel truss suspension assembly type elevator structure and construction method thereof
CN112942887A (en) * 2021-02-04 2021-06-11 广东世纪达建设集团有限公司 Construction method for additionally building new corridor below old corridor in old building
CN116675088A (en) * 2023-06-16 2023-09-01 杭州西奥电梯现代化更新有限公司 Attached elevator
CN116771155A (en) * 2023-06-16 2023-09-19 杭州西奥电梯现代化更新有限公司 Attached elevator, elevator construction device and construction method thereof
CN116675088B (en) * 2023-06-16 2024-03-12 杭州西奥电梯现代化更新有限公司 Attached elevator
CN116771155B (en) * 2023-06-16 2024-04-02 杭州西奥电梯现代化更新有限公司 Attached elevator, elevator construction device and construction method thereof

Also Published As

Publication number Publication date
JP4336682B2 (en) 2009-09-30

Similar Documents

Publication Publication Date Title
JP4336682B2 (en) Construction method of elevator hoistway building
JP4336681B2 (en) Elevator shaft foundation construction method and PC foundation and level adjustment beam material used therefor
KR100746551B1 (en) The system and construction method to build apartment
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
KR100676193B1 (en) Steel-frame stair structure
JP5003253B2 (en) RC beam construction method
JP2536249B2 (en) Lift-down underground structure construction method
JP2009030259A (en) Skeleton construction method using steel frame of multistory parking space
KR102338956B1 (en) Modular rammed earth wall construction equipment and method embedding modular steel structure
KR102211218B1 (en) A Construction Method for Pre-Constructing Staircase and Constructing Materials Used therein
JP6418683B2 (en) Temporary support method
JP6138719B2 (en) Construction method of seismic reinforcement structure
JP2023008012A (en) Method of constructing additional elevator shaft for mid-rise residential building
JP2613417B2 (en) Construction method of underground structure
CN216810238U (en) Cast-in-place post column base connection structure of steel mould
JP7275793B2 (en) Position adjusting device and method for adjusting position of structural column
KR100762421B1 (en) Support system of steel stair preceding construction method
JP4064837B2 (en) Housing construction method and housing
JP3345395B2 (en) Elevator tower construction method
JP4122924B2 (en) Seismic isolation method for existing structures
JP3287816B2 (en) Building interior stairs
JP3567387B2 (en) How to build an underground skeleton
JP2023102967A (en) Construction method of structure and structure
JP2761526B2 (en) How to build structures
JP2683878B2 (en) Precast staircase structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090217

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090225

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090413

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20090527

Free format text: JAPANESE INTERMEDIATE CODE: A01

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090629

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 3

Free format text: PAYMENT UNTIL: 20120703

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees