construction
progress
server
information
site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005164882A
Other languages
Japanese (ja)
Inventor
Hisami Odakura
久視 小田倉
Kunihiko Kudo
邦彦 工藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HIBARA CORP KK
Original Assignee
HIBARA CORP KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HIBARA CORP KK filed Critical HIBARA CORP KK
Priority to JP2005164882A priority Critical patent/JP2006338561A/en
Publication of JP2006338561A publication Critical patent/JP2006338561A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To grasp progress at each stage from a construction plan to completion in real time and to relieve a burden required for communication between each section/person in charge relevant to the construction. <P>SOLUTION: This construction progress management system has a plurality of clients 3, a server 1 connected to all the clients 3 via the Internet 2 and a portable terminal 4 capable of transmitting/receiving character information and image information including construction progress information from each construction site. The server 1 has a construction management data storage means and a construction site photograph storage means. The clients 3 have means for registering input data regarding the construction plan, means for registering character information regarding the progress and site photograph information and means for referring to and displaying the character information and the site photograph information. The portable terminal 4 has a means for transmitting the character information regarding the progress and taken photograph data to the server 1 to register them and a means for referring to the registered progress information. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、各種の工事(各種の作業も含む)に於ける進捗状況をそれぞれを実行するごとに登録手段から写真を含むその情報の入力が行われる工事進捗状況管理システムであって、ネットワークに接続されたサーバによって管理される工事進捗状況を含む工事データが携帯端末によって随時参照可能な、特に大規模工事又は大規模作業等に有効な工事進捗状況管理システムに関するものである。   The present invention is a construction progress status management system in which information including a photograph is input from a registration means each time the progress status in various works (including various works) is executed. The present invention relates to a construction progress management system that is effective for large-scale construction, large-scale work, and the like, in which construction data including construction progress managed by a connected server can be referred to by a mobile terminal as needed.

なお、この場合の「大規模」には地理的に広範な範囲に広がる工事を指すことはもとより、工程数が多岐に渉って従事する事業者も入り組んでいるため煩雑であること、更には工期が長期となりかつ煩雑な工程管理が必要になること等をも包含する意味である。   In this case, “large-scale” refers not only to construction that covers a wide geographical area, but also because it involves complicated operators engaged in various processes, and is complicated. It also means that the construction period is long and complicated process management is required.

道路・トンネル・橋梁・鉄道・港湾・ダム等に於ける土木工事、都市計画や社会基盤整備に関する土木建築工事、大型プラントや工業団地、新規宅地造成に伴う住宅建設等の大規模工事等にあっては、予め竣工時期乃至完成時期が定められていて、それぞれの工程ごとに工程表が作成され、これらを総合的に管理するような工程管理乃至進捗状況管理が求められる。   Civil engineering works on roads, tunnels, bridges, railways, harbors, dams, etc. Therefore, a completion time or completion time is determined in advance, and a process table is created for each process, and process management or progress management is required to comprehensively manage these.

特に大規模工事にあっては、多数の工事業者による共同受注(JV)や工事グループが担当区域を定めて従事することが多く、同時に進行する各業種との取り合いや、相前後する他工事との間の綿密な調整が必要になる。このような調整が十分に行われないと、個々の工程に遅れを生じ易く、結果的に工事全体の遅延を招き、竣工乃至完成時期にも悪影響を与え、極端な場合には、発注者から損害賠償の請求を受けるような最悪の事態の発生もないとは云えない。   Especially for large-scale construction, joint orders (JV) by a large number of contractors and construction groups are often engaged in establishing areas in charge. A thorough adjustment between is required. If such adjustments are not made sufficiently, it is easy to cause delays in individual processes, resulting in delays in the entire construction, and adversely affecting the completion or completion time. It cannot be said that there is no occurrence of the worst situation of receiving a claim for damages.

従来の工程管理には、当該工事の統括部門で作成された工事計画表によって全体の工程管理が行われ、それぞれの担当範囲ごとにネットワーク管理表により工事進捗状況が視覚的に把握可能なように書類や表示パネルなどが使用されて来た。しかしこのような文書乃至タイムチャート等のような書類や、現場事務所等に設置された白板その他の掲示手段への記入や訂正などは煩雑である上、全員が共有しなければならない書類等の資料も工事規模に応じて膨大なものとなり、それぞれに対する徹底が困難であることが指摘されている。このような事情を考慮して、コンピュータシステムを利用して工事計画、工程表、進捗状況等の入力・記録・修正・確認等が可能なシステムが提案されている。   In the conventional process management, the entire process management is performed by the work plan table created by the supervising department of the work concerned, so that the progress of the work can be visually grasped by the network management table for each area in charge. Documents and display panels have been used. However, such documents and documents such as time charts, whiteboards installed at field offices, etc. and other posting means are cumbersome, and documents that all must share It has been pointed out that the amount of materials has become enormous depending on the scale of construction, and it is difficult to thoroughly implement each. In view of such circumstances, a system has been proposed in which a computer system can be used to input / record / modify / confirm construction plans, process schedules, progress, and the like.

特許文献1は、工事担当者が自己の所持する携帯端末装置によりEメールを利用してウェブページを閲覧し、必要な進捗状況の報告を行う工程進捗状況報告システムを開示している。このウェブページでは、それぞれの工事担当者による報告を受けて最新のデータを記憶装置に更新保存する。その結果、複数の工事担当者からの報告忘れや遅延を回避することができるが、従来電話やFAX等によって行っていた内容を単にウェブシステムや携帯端末等を使用して報告の遅延や報告忘れを防止するようにしたものに過ぎない。   Patent Document 1 discloses a process progress report system in which a construction worker browses a web page using an e-mail with a portable terminal device possessed by himself / herself and reports a necessary progress report. In this web page, the latest data is updated and stored in a storage device in response to a report from each construction worker. As a result, it is possible to avoid forgetting and delaying reports from multiple construction personnel, but using a web system or mobile terminal, etc., the contents that were previously done by telephone or fax are simply delayed or forgotten. It is just something that was designed to prevent this.

特許文献2は、多数の作業車両や作業船が従事する大規模工事に於ける広域作業管理システムを開示するもので、各作業車両や作業船にそれぞれ移動体側端末コンピュータを搭載しておき、管理側コンピュータとの間を相互通信可能なパケット通信網によって連係させている。このように移動側コンピュータと管理側コンピュータとの間の連係にパケット通信網を利用する結果、各部の作業が集中するような状況下にあっても、従来型無線電話のような輻輳による通信遅延が回避できるものである。もっともこのシステムは、報告乃至連絡のタイミングを担当者が判断する必要がなく、通信網の制御によって実行するパケット通信網を利用することにより作業管理を行うに過ぎないもので、より高度な判断や制御を行うものではない。   Patent Document 2 discloses a wide-area work management system in large-scale construction where a large number of work vehicles and work ships are engaged, and each work vehicle and work ship is equipped with a mobile terminal computer and is managed. The side computers are linked by a packet communication network capable of mutual communication. As described above, the communication delay due to congestion as in the case of a conventional wireless telephone, even in a situation where the work of each part is concentrated as a result of using the packet communication network to link the mobile computer and the management computer. Can be avoided. However, this system does not require the person in charge to determine the timing of reporting or communication, and only performs work management by using a packet communication network executed by control of the communication network. It does not control.

特許文献3は、現場管理事務所内のLANによって連係された複数のコンピュータを携帯電話網を利用して工事現場に於ける作業員所持の携帯電話と交信可能にしておき、現場管理事務所からの連絡指示を迅速かつ確実に行ない、メッセージ伝達状況の事後的な管理を効率よく行うメッセージ管理システムを開示するものである。   Patent Document 3 discloses that a plurality of computers linked by a LAN in a site management office can communicate with a mobile phone possessed by a worker at a construction site using a mobile phone network. Disclosed is a message management system that promptly and reliably provides contact instructions and efficiently performs subsequent management of message transmission status.

特許文献4は、各現場事務所内に設置されたコンピュータと、本社内に構築されたLAN系統との間をフレームリレー回線網やRAS回線網等によって連係する建設工事進捗管理システムを開示している。ここでは、大規模プラントの工事全体を大概念ごとに区分し、各区分を更に何段階かの小さな概念に区分し、最下位層の区分が作業単位を表わした区分となるように階層状に区分して、各作業単位に対して計画した物量、工数、工事期間等の計画を入力し、更に毎日実行した実績による投入物量や工数を入力し、これらを対比させることにより工事進捗状況を把握するものである。このようにして得られた結果を日付を横軸とし、進捗率を縦軸とする進捗推移曲線を作成して可視化するように構成されたシステムである。   Patent Document 4 discloses a construction progress management system in which a computer installed in each field office and a LAN system built in the head office are linked by a frame relay network or a RAS network. . Here, the entire construction of a large-scale plant is divided into large concepts, each division is further divided into several small concepts, and the hierarchical structure is formed so that the lowest layer division represents a unit of work. Separately, input the planned quantity, man-hours, construction period, etc. for each unit of work, and also input the amount of input and man-hours based on the results performed every day, and compare these to grasp the progress of construction. To do. The system is configured to create and visualize a progress transition curve with the results obtained in this way having the date as the horizontal axis and the progress rate as the vertical axis.

特開2002‐73739号公報Japanese Patent Laid-Open No. 2002-73739 特開2001‐202589号公報JP 2001-202589 A 特開2002‐335574号公報JP 2002-335574 A 特開2004‐94511号公報JP 2004-94511 A

本発明は、複数の業者がそれぞれの業務分野を分担従事する大規模工事の管理システムに於いて、工事計画から完工に至る各段階の進捗状況がリアルタイムで把握可能であり、工事管理者、発注業者、工事担当者、現場監督及び顧客等の間のコミュニケーションに要する負担を軽減することができる、特に大規模工事等に有効な工事進捗状況管理システムを提供することを解決の課題とする。   In the present invention, in a large-scale construction management system in which a plurality of contractors are assigned to each business field, the progress status of each stage from construction planning to completion can be grasped in real time. The problem to be solved is to provide a construction progress status management system that can reduce the burden required for communication among contractors, construction staff, site supervisors, customers, and the like, which is particularly effective for large-scale construction.

本発明の1は、サーバと、該サーバとネットワークを介して接続された複数のクライアント及び携帯端末とを備えた工事進捗状況管理システムであって、
前記サーバは、前記クライアント及び前記携帯端末から入力された工事に関するデータを格納保管する工事管理データ格納手段並びに前記携帯端末から入力された工事現場写真を格納保管する工事現場写真格納手段を備え、
前記クライアントは、工事計画に関する入力情報を前記サーバの工事管理データ格納手段に登録する手段、工事の進捗状況に関する文字情報を前記サーバの工事管理データ格納手段に登録する手段、工事の進捗状況に関する現場写真の画像情報を工事現場写真格納手段に登録する手段、並びに工事の進捗状況に関する文字情報及び現場写真情報をそれぞれ前記サーバの工事管理データ格納手段及び工事現場写真格納手段から読み出して表示する進捗表示手段を備え、
前記携帯端末は、工事の進捗状況情報を前記サーバの工事管理データ格納手段に登録する進捗状況情報登録手段、写真の撮影手段、及び撮影した工事の進捗状況に関する現場写真の画像情報を前記サーバの工事現場写真格納手段に登録する登録手段を備えるものとした工事進捗状況管理システムである。
1 of the present invention is a construction progress management system including a server, and a plurality of clients and mobile terminals connected to the server via a network,
The server comprises construction management data storage means for storing and storing data relating to construction input from the client and the mobile terminal, and construction site photo storage means for storing and storing construction site pictures input from the mobile terminal,
The client includes means for registering input information relating to a construction plan in the construction management data storage means of the server, means for registering character information relating to the progress of construction in the construction management data storage means of the server, and a site relating to the progress of construction. A means for registering the image information of the photo in the construction site photo storage means, and a progress display for reading and displaying the character information and the site photo information relating to the progress of the construction from the construction management data storage means and the construction site photo storage means of the server, respectively. With means,
The portable terminal is configured to register progress status information registration means for registering construction progress status information in the construction management data storage means of the server, photograph photographing means, and image information of a site photograph regarding the progress status of the photographed construction work. A construction progress status management system comprising registration means for registering in construction site photo storage means.

本発明の2は、本発明の1の工事進捗状況管理システムに於いて、前記クライアントに於ける進捗表示手段が、カレンダー機能と連動して作業計画と実際の進捗状況とを同一画面に表示することにより、予め設定されている計画と進捗状況との可視的対比を可能にしたものである。   According to a second aspect of the present invention, in the construction progress management system according to the first aspect of the present invention, the progress display means in the client displays the work plan and the actual progress on the same screen in conjunction with the calendar function. This enables a visual comparison between a preset plan and the progress.

本発明の3は、本発明の1又は2の工事進捗状況管理システムに於いて、前記携帯端末は、対象の工事現場の各段階毎の工事内容を撮影し、それらの現場写真の画像情報を当該の工事を特定する情報と関連付けて前記サーバの工事現場写真格納手段に登録することができるものとしたものである。   According to the third aspect of the present invention, in the construction progress management system according to the first or second aspect of the present invention, the mobile terminal shoots the construction contents at each stage of the target construction site, and displays image information of those site photographs. The server can be registered in the construction site photo storage means of the server in association with information identifying the construction.

本発明の4は、本発明の1、2又は3の工事進捗状況管理システムに於いて、前記携帯端末から工事の進捗状況情報が前記サーバの工事管理データ格納手段に登録された際に、該サーバから予め設定されている携帯端末に対して特定の工事の進捗状況情報が登録されたことを通知するメールが自動送信されることとしたものである。   4 of the present invention is the construction progress status management system according to 1, 2, or 3 of the present invention, wherein when construction progress status information is registered in the construction management data storage means of the server from the portable terminal, A mail notifying that the progress status information of a specific construction has been registered is automatically transmitted from a server to a preset mobile terminal.

本発明の5は、本発明の1、2、3又は4の工事進捗状況管理システムに於いて、前記クライアント及び携帯端末の各々は、それを管理し又は携帯する者に対して許容される範囲内で、前記サーバの工事管理データ格納手段及び工事現場写真格納手段に登録されている工事進捗状況に関するデータを随時参照可能であるようにしたものである。   The fifth aspect of the present invention is the construction progress status management system according to the first, second, third, or fourth aspect of the present invention, wherein each of the client and the portable terminal is an allowable range for a person who manages or carries it. The construction management data storage means and the construction site photo storage means of the server can be referred to data on the construction progress status registered at any time.

本発明の1の工事進捗状況管理システムは、サーバ、ネットワークにより該サーバに連係された複数のクライアント及び複数の携帯端末を備えた工事進捗状況管理システムであり、多数の現場に跨り、或いは多数工程からなる大規模工事等に於ける工事進捗状況に関する文字・グラフ・写真等の情報を、所定権限を有するクライアント及び携帯端末からサーバ内の工事管理データ格納手段及び工事現場写真格納手段に随時登録しておくことができるものである。   A construction progress status management system according to one aspect of the present invention is a construction progress status management system including a server, a plurality of clients and a plurality of portable terminals linked to the server by a network. Information on characters, graphs, photos, etc. related to the progress of construction in large-scale constructions, etc., is registered from time to time to clients with a certain authority and mobile terminals in the construction management data storage means and construction site photo storage means in the server. It can be kept.

サーバの工事管理データ格納手段及び工事現場写真格納手段に登録された工事進捗状況に関する情報は、携帯端末やクライアントからそれを保持する者の権限の範囲で随時読み出されて参照され進捗状況が確認できる。このような本発明の工事進捗状況管理システムを利用する情報の参照確認によれば、従来のような有形の配布資料を実際に手にして確認するとか、現場事務所や本社に掲示された白板や黒板或いはチャート等を確認し、更には電話やFAXを利用するような煩雑さが解消され、迅速かつ随時に精確な工事進捗状況情報の参照確認が可能となる。   Information related to the progress of construction registered in the construction management data storage means and construction site photo storage means of the server is read from time to time within the authority of the person holding the information from the mobile terminal or client, and the progress status is confirmed. it can. According to the reference confirmation of the information using the construction progress management system of the present invention, the tangible handouts as in the past are actually confirmed by hand or the white board posted at the field office or the head office. In addition, the troublesomeness of checking a blackboard, a chart, or the like and using a telephone or FAX is eliminated, and it is possible to quickly and accurately refer to the construction progress status information at any time.

現実の工事等は、気象条件、作業用機材や資材の充足状況、注文主の変更要求、各種工程間の作業タイミングの調整、作業員の手配等のような諸々の事情を受けて、作業工程は変更されることが多い。このようなケースでは、旧版配布資料の回収乃至廃棄が徹底しないことに起因する新旧版混在や、掲示工程表等にあっては訂正時期の確認が遅れるなどの過誤乃至不可抗力の理由により訂正前のデータを正しいものと勘違いするような事態が生じがちであった。   The actual work, etc., depends on various conditions such as weather conditions, work equipment and material satisfaction, orderer's change request, adjustment of work timing between various processes, arrangement of workers, etc. Are often changed. In such a case, it is necessary to correct the old version distribution materials due to inadequate collection or disposal of the old version, or to check the correction time in the posting schedule etc. There was a tendency to misunderstand the data as correct.

しかし本発明の1の工事進捗状況管理システムによれば、工事進捗状況に関する最新の文字・グラフック・写真等の情報が、定時に又は随時に参照確認可能であり、新旧版資料・データ類の混在や確認遅れによる過誤作業の防止乃至修正作業の漏れ等が回避できる。   However, according to the construction progress management system 1 of the present invention, it is possible to refer to and confirm the latest text, graphics, photographs, and other information related to the construction progress on a regular basis or at any time. In addition, it is possible to avoid erroneous work due to confirmation delay or leakage of correction work.

また携帯端末は使用場所の制限は極めて少なく、進捗状況の登録を工事現場から直接に行えるため、前記のように、サーバの工事管理データ格納手段及び工事現場写真格納手段に登録した進捗状況情報を常時容易に最新状態に維持することが可能になる。   In addition, since the portable terminal has very few restrictions on the place of use, and the progress status can be registered directly from the construction site, as described above, the progress status information registered in the construction management data storage means and the construction site photo storage means of the server is stored. It becomes possible to always maintain the latest state easily.

更に本発明の1の工事進捗状況管理システムによれば、サーバに格納保存された工事進捗状況がネットワークを介して伝送されて遠隔地に於いても可視情報としてリアルタイムで把握可能であるばかりでなく、更に印刷された媒体を介して確認可能であることから、所要資材の発注・督促、現工程から次工程へ移行する際に必要になる人員手配、関連企業に対する連絡・指示等の工事管理を適切に実施するための資料が随時確認可能であり、最適の工事進捗に資することが期待できる。   Furthermore, according to the construction progress management system 1 of the present invention, the construction progress stored and stored in the server can be transmitted via the network and can be grasped in real time as visible information even in a remote place. In addition, since it can be confirmed via printed media, it is possible to perform construction management such as ordering / requiring required materials, arranging personnel required when moving from the current process to the next process, and contacting / instructing related companies. Materials for proper implementation can be confirmed at any time, and can be expected to contribute to the optimal construction progress.

本発明の2の工事進捗状況管理システムによれば、前記クライアントに於ける進捗表示手段が、カレンダー機能と連動して作業計画と実際の進捗状況とを同一画面に表示することとしたため、予め設定されている計画と進捗状況との可視的対比が可能であり、正確に状況を判断することができることになる。   According to the construction progress status management system 2 of the present invention, the progress display means in the client displays the work plan and the actual progress status on the same screen in conjunction with the calendar function. A visual comparison between the planned plan and the progress status is possible, and the situation can be judged accurately.

本発明の3の工事進捗状況管理システムによれば、各工事現場に於ける各段階毎の工事内容が現場の携帯端末で撮影され、当該の工事と関連づけてサーバに登録されることになるため、クライアント及び携帯端末を保持する関係者は必要に応じてこれを参照し、各工事現場の進捗状況を正確に把握することができる。   According to the construction progress status management system 3 of the present invention, the construction content at each stage at each construction site is photographed by the portable terminal at the site, and is registered in the server in association with the construction. The parties holding the client and the portable terminal can refer to this information as necessary, and can accurately grasp the progress status of each construction site.

本発明の4の工事進捗状況管理システムによれば、前記携帯端末から工事進捗状況に関する情報が前記サーバに登録されると、予め設定されている携帯端末を保有する関係者はその旨のメールによって、その進捗状況を直ちに認識し、常に現状をリアルタイムで正確に認識することができる。工事管理者のためにこれを設定しておくと、該工事管理者は、クライアントであるパソコン等の設置してある事務所を離れている場合でも、関係の工事の進捗状況をリアルタイムで把握できることになり、好都合である。   According to the construction progress status management system of 4 of the present invention, when information relating to the construction progress status is registered in the server from the portable terminal, the parties holding the preset portable terminal are notified by e-mail to that effect. , It can immediately recognize the progress status and always accurately recognize the current status in real time. If this setting is made for the construction manager, the construction manager can grasp the progress of the related construction in real time even if he / she is away from the office where the client PC is installed. It is convenient.

本発明の5の工事進捗状況管理システムによれば、前記クライアント及び携帯端末のいずれからでも、前記サーバの工事管理データ格納手段及び工事現場写真格納手段に登録されている工事進捗状況に関するデータを随時参照可能であるため、関係者は何時でも自己の権限の範囲内で関係する工事の進捗状況を参照確認することができる。又それぞれ権限の範囲内で参照可能になっているため、無用に関係者外に情報が漏洩する虞もない。   According to the construction progress status management system 5 of the present invention, data relating to the construction progress status registered in the construction management data storage means and the construction site photo storage means of the server from any of the client and the mobile terminal is stored as needed. Since the information can be referred to, the related person can always refer to and confirm the progress of the related work within the scope of his authority. Moreover, since each can be referred to within the scope of authority, there is no possibility that information is unnecessarily leaked outside the parties concerned.

以下、添付図を参照しつつ本発明の好適な実施例に基づいて発明を実施する最良の形態を開示する。   The best mode for carrying out the invention will be described below on the basis of preferred embodiments of the invention with reference to the accompanying drawings.

図1は、実施例の工事進捗状況管理システムの基本構成を示すブロック図で、サーバ1、インターネット(専用ネットワーク等を含む各種ネットワークの何れでもあり得るが、この実施例ではインターネット)2、複数のクライアント3(3−1、3−2、3−3…)、複数の携帯端末4(4−1、4−2、4−3…)から構成される。   FIG. 1 is a block diagram showing the basic configuration of the construction progress management system of the embodiment. The server 1, the Internet (which can be any of various networks including a dedicated network, etc., but the Internet in this embodiment) 2, a plurality of It is comprised from the client 3 (3-1, 3-2, 3-3 ...) and the some portable terminal 4 (4-1, 4-2, 4-3 ...).

サーバ1は、この実施例の工事進捗状況管理システム全体を管理する中心的機能を発揮するもので、システム管理者により管理運用される。サーバ1を構成する構成要素としては、プログラム制御によって所望の処理を行うプロセッサ(CPU)を含む制御部Cと、インターネット2との間で所要データの授受を行うインターフェース部IFと、所要容量並びに構成による記憶部Mを備えている。記憶部Mは、詳細には記憶部M11、12、13、22から構成され、ハードウエア的には、システム構成や規模に応じて必要となる容量の主記憶装置を始め、一時記憶装置、リムーバブルディスクその他の補助記憶装置類を包含している。これらの構成要素を有機的に作用させることにより、機能的には、必要な工事管理データを蓄積しておく工事管理データ格納手段(記憶部M12、13)、工事現場写真格納手段(記憶部M22)及びメール作成及び送信手段を構成する。   The server 1 exhibits a central function for managing the entire construction progress management system of this embodiment, and is managed and operated by a system administrator. The components constituting the server 1 include a control unit C including a processor (CPU) that performs desired processing by program control, an interface unit IF that transmits and receives required data to and from the Internet 2, a required capacity, and a configuration. The storage part M is provided. The storage unit M is composed of storage units M11, 12, 13, and 22 in detail. In terms of hardware, the storage unit M includes a main storage device having a capacity required according to the system configuration and scale, a temporary storage device, and a removable device. Includes disks and other auxiliary storage devices. Functionally, by making these components act organically, construction management data storage means (storage units M12, 13) for storing necessary construction management data, construction site photo storage means (storage unit M22). ) And mail creation and transmission means.

複数のクライアント3(3−1、3−2、3−3…)は、この実施例では一般的なパーソナルコンピュータ(以下パソコン)であり、中央処理装置(CPU)、記憶部M、インターフェースIF等を備えている。   A plurality of clients 3 (3-1, 3-2, 3-3...) Are general personal computers (hereinafter referred to as personal computers) in this embodiment, and include a central processing unit (CPU), a storage unit M, an interface IF, and the like. It has.

また図示していないが、これらのクライアント3であるパソコンの周辺機器としては、入力手段として、キーボード、マウス、スキャナ及びタッチパネル等の全部又は一部が利用され、出力手段として、画面表示のためのディスプレイ(モニタ画面)、ハードコピー形成用のプリンタ又はX−Yプロッタ等の全部又は一部が利用され、更にデータ授受手段として、自装置内のメール作成手段により作成されたメールを送信し、または外部より伝送されたメールを受信するメール作成及び送受信手段を備えている。   Moreover, although not shown in figure, as a peripheral device of the personal computer which is these clients 3, all or part of a keyboard, a mouse | mouth, a scanner, a touch panel, etc. are utilized as an input means, and for screen display as an output means All or a part of a display (monitor screen), a hard copy forming printer, an XY plotter or the like is used, and further, a mail created by a mail creating means in its own apparatus is transmitted as a data transfer means, or E-mail creation and transmission / reception means for receiving e-mail transmitted from outside is provided.

これらの構成要素を、有機的に作用させることにより、工事管理データの登録手段、工事進捗状況を示す情報の登録手段及びその工事現場写真の登録手段、工事進捗状況を示す文字情報乃至グラフィック情報等の表示手段、工事現場写真の表示手段、その他の各データ類のプリントアウト手段、工事管理者、工事担当者及び顧客間のメールの作成手段乃至伝送手段を構成している。   By organically acting these components, construction management data registration means, construction progress information registration means and construction site photo registration means, construction progress text information or graphic information, etc. Display means, construction site photo display means, other data printout means, construction manager, construction staff and customer mail creation means or transmission means.

図1に示した複数の携帯端末4(4−1、4−2、4−3…)は、携帯至便に構成されたモバイルコンピュータが利用可能である他、携帯電話等を利用することができる。この実施例では、プログラム制御により作動する処理装置(CPU)、記憶装置、写真撮影装置CA、各種インターフェースIF、インターネット2に対する無線送受伝送装置等を備えた携帯電話を採用した。   The plurality of portable terminals 4 (4-1, 4-2, 4-3...) Shown in FIG. 1 can use a mobile computer configured as a portable convenience, and can also use a cellular phone or the like. . In this embodiment, a cellular phone provided with a processing device (CPU) that operates by program control, a storage device, a photography apparatus CA, various interface IFs, a wireless transmission / reception device for the Internet 2, and the like is employed.

以上のような構成要素を活用することにより、該携帯端末4は、工事進捗状況の登録手段、工事現場写真撮影手段、現場写真の画像情報の登録乃至伝送手段、メール作成手段及びメール送受信手段等を構成している。   By utilizing the constituent elements as described above, the portable terminal 4 is able to register the construction progress status registration means, the construction site photo shooting means, the registration / transmission means of the image information of the site photos, the mail creation means, the mail transmission / reception means, etc. Is configured.

図1に示した実施例の基本構成のサーバ1、クライアント3及び携帯端末4に於いて、各構成要素の組合わせによって得られる各構成手段は、図2に示すようなものである。   In the server 1, the client 3, and the portable terminal 4 having the basic configuration of the embodiment shown in FIG. 1, each constituent means obtained by combining the constituent elements is as shown in FIG.

以上のような基本構成に於ける各構成要素の機能は以下のように構成する。   The function of each component in the basic configuration as described above is configured as follows.

サーバ1に格納される工事管理データは、複数のクライアント3(3−1、3−2、3−3…)から登録される各々別個の工事に関する工事計画登録データ、各クライアント3(3−1、3−2、3−3…)及び各携帯端末4(4−1、4−2、4−3…)から登録される各工事毎の工事進捗状況情報等が含まれる。   The construction management data stored in the server 1 includes construction plan registration data relating to individual constructions registered from a plurality of clients 3 (3-1, 3-2, 3-3...), And each client 3 (3-1). 3-2, 3-3...) And construction progress status information for each construction registered from each portable terminal 4 (4-1, 4-2, 4-3...).

工事進捗状況情報は、この実施例では、文字情報及び写真情報を包含するものであり、サーバ1に予め格納されているプログラムに従って、その内容に応じて分類、作表又は日程表(カレンダー)との合成による時系列化、或いはグラフィック化等の所要処理を経た情報である。   In this embodiment, the construction progress status information includes text information and photo information. According to the program stored in the server 1 in advance, the construction progress status information is classified, tabulated, or a schedule table (calendar). This is information that has undergone a required process such as time series or graphicization by combining.

以上の工事計画データの登録を行うクライアント3は、各種工事毎の工事管理者の所要部署に設置し、この実施例では、該工事管理者が自己の管理する工事関連情報の登録を行うものとする。工事管理者の管理するクライアント3は、当然、その管理する工事の工事進捗情報の参照を行うこともできる。更に又顧客はその保有するパソコンをクライアント3として用い、これで、関係の工事に関してのみその進捗状況情報の参照を行うことができる。   The client 3 for registering the construction plan data described above is installed in the required department of the construction manager for each construction, and in this embodiment, the construction manager registers the construction related information managed by the construction manager. To do. Naturally, the client 3 managed by the construction manager can refer to the construction progress information of the construction managed. Further, the customer can use the personal computer owned by the customer as the client 3 and can refer to the progress status information only for the related construction.

工事現場で作業を行う工事担当者及び現場監督は、その管理するクライアント3から工事の進捗状況情報の登録を行うことができる。この進捗状況情報には現場写真情報も含み、この場合は、デジタルカメラの画像情報、或いは銀塩フィルムを用いたカメラの画像をスキャナ又はフィルムスキャナ等で読み込んだ画像情報を取り込んで、これを登録することができるものである。   The person in charge of the construction and the site supervisor who performs the work at the construction site can register the progress information of the construction from the client 3 that is managed. This progress information includes on-site photo information. In this case, the digital camera image information or the image information read by the camera using a silver halide film is read by a scanner or a film scanner and registered. Is something that can be done.

また工事現場で作業を行う工事担当者及び現場監督は、携帯端末4(4−1、4−2、4−3…)を携帯し、これによって工事進捗状況に関する工事内容情報の登録、工事現場写真の撮影及びその撮影による画像情報の登録を行うことができる。また工事管理者も携帯端末4(4−1、4−2、4−3…)を携帯し、工事の進捗状況のサーバ1への登録があった際に、その旨のメールをこれで受信できるようになっている。   Moreover, the construction person in charge and the site supervisor who carries out the work at the construction site carry the portable terminal 4 (4-1, 4-2, 4-3...), Thereby registering the construction content information regarding the construction progress, and the construction site. Photographing and registration of image information by photographing can be performed. The construction manager also carries the portable terminal 4 (4-1, 4-2, 4-3...), And when the construction progress status is registered in the server 1, an email to that effect is received by this. It can be done.

これらの携帯端末4(4−1、4−2、4−3…)としては、この実施例では、先に述べたように、携帯電話を採用したものであるから、それ自体が本来有する機能はそのまま使用できるものであることは云うまでもない。   As these portable terminals 4 (4-1, 4-2, 4-3...), In this embodiment, as described above, a cellular phone is adopted, so that the functions inherently included in the portable terminal 4 (4-1, 4-2, 4-3...) Needless to say, can be used as it is.

なお、それぞれのクライアント3(3−1、3−2、3−3…)、携帯端末4(4−1、4−2、4−3…)等に於ける入力データ形態、入力文字数、直接入力か選択入力か、などに関してはシステムを構成するハードウェア及びソフトウェア手段に応じて適宜変更することができ、固定されたものではない。   In addition, each client 3 (3-1, 3-2, 3-3...), Portable terminal 4 (4-1, 4-2, 4-3. The input or selection input can be appropriately changed according to the hardware and software means constituting the system, and is not fixed.

この実施例の工事進捗状況管理システムの基本的操作は以下のように行われ得るようにする。   The basic operation of the construction progress status management system of this embodiment can be performed as follows.

まず、管理部門に於いて工事計画が作成されると、この工事計画に基づいて工事計画登録情報の登録手段を備えたクライアント3から、工事番号、工事件名、予算額、工事開始日、工事期間、工事内容、各工事区間・工事分担ごとの担当企業(業者)等の工事計画情報がサーバ1の工事管理データ格納手段(記憶部M12、13)に登録される。このような工事計画情報には、表組み、タイムチャート、グラフ、写真等を交えて構成することができる。   First, when a construction plan is created in the management department, a construction number, a construction title, a budget amount, a construction start date, a construction period from a client 3 having means for registering construction plan registration information based on this construction plan. The construction plan information of the construction company, the company in charge (worker), etc. for each construction section and construction division is registered in the construction management data storage means (storage units M12, 13) of the server 1. Such construction plan information can be configured with tables, time charts, graphs, photographs and the like.

各工事の各現場からの進捗状況情報は、それぞれの工事工程の現場管理者(工事担当者)の管理下にある携帯端末4(4−1、4−2、4−3…)からサーバ1に伝送され、その工事管理データ格納手段(記憶部M13)に登録される。また該携帯端末4(4−1、4−2、4−3…)で撮影した工事工程の工事内容の写真は、該携帯端末4(4−1、4−2、4−3…)からの要求でサーバ1で作成されて送信されたメールにその画像情報を添付して返送することで送信し、該サーバ1の工事現場写真格納手段(記憶部M22)に登録される。   The progress status information from each site of each construction is sent from the mobile terminal 4 (4-1, 4-2, 4-3...) Under the control of the site manager (construction person) of each construction process to the server 1 And is registered in the construction management data storage means (storage unit M13). In addition, photographs of the construction contents of the construction process photographed by the portable terminal 4 (4-1, 4-2, 4-3...) Are taken from the portable terminal 4 (4-1, 4-2, 4-3...). Is sent by attaching the image information to the mail created and sent by the server 1 and sent back, and is registered in the construction site photo storage means (storage unit M22) of the server 1.

進捗状況情報は、それぞれの現場管理者(工事担当者)が都合によりその管理するクライアント3であるパソコンから登録することも可能で、この場合は、そのクライアント3からサーバ1に伝送され、その工事管理データ格納手段(記憶部M13)に登録される。またデジタルカメラ等で撮影した工事工程の工事内容の写真情報は、該クライアント3からサーバ1に送信し、該サーバ1の工事現場写真格納手段(記憶部M22)に登録することもできる。   The progress status information can also be registered from the personal computer that is the client 3 managed by each site manager (construction person) for convenience. In this case, the progress information is transmitted from the client 3 to the server 1 for the construction. Registered in the management data storage means (storage unit M13). Also, the photo information of the construction contents of the construction process photographed with a digital camera or the like can be transmitted from the client 3 to the server 1 and registered in the construction site photo storage means (storage unit M22) of the server 1.

このような進捗状況情報の登録がサーバ1の工事管理データ格納手段(記憶部M13)に行われると、その旨のメールがサーバ1で作成され、関係の携帯端末4に送信される。なお、この実施例では、この送信は、それを受けたい旨の登録をした携帯端末4(4−1、4−2、4−3…)に対してのみ行われる。通常、当該の工事の工事管理者の携帯端末4−1についてその旨登録する。   When such progress status information is registered in the construction management data storage means (storage unit M13) of the server 1, a mail to that effect is created by the server 1 and transmitted to the related portable terminal 4. In this embodiment, this transmission is performed only to the portable terminals 4 (4-1, 4-2, 4-3...) That have registered that they want to receive it. Usually, the fact is registered for the portable terminal 4-1 of the construction manager of the construction concerned.

工事の進捗状況情報は、この実施例では、クライアント3(3−1、3−2、3−3…)に於いて、当初設定されている工事計画登録情報と工事進捗実績との比較表示がされる。これは工事計画に基づく工事内容を登録された該工事計画に沿って時系列的に配列し、かつ進捗状況もそれに対比できる状態に配列して表示することにより行うものである。そのような情報の加工は、この実施例では、サーバ1で行うものとした。   In this embodiment, the construction progress status information is displayed in the client 3 (3-1, 3-2, 3-3,...) By comparing and displaying the initially set construction plan registration information and the construction progress record. Is done. This is done by arranging the construction contents based on the construction plan in time series according to the registered construction plan and displaying the progress in a state that can be compared with the progress. Such information processing is performed by the server 1 in this embodiment.

なお、これに加えて、当日以降の工事進捗予想、関連する資材並びに人員配置の検討乃至重点投入等に関する間接的又は直接的な対策に関する資料、例えば、グラフ、図表、写真等を交えた資料の作成並びにアクセスしてくる端末に対して公開・伝送等が行えるように形成することもできる。   In addition, in addition to this, materials related to indirect or direct measures related to construction progress forecasts after that day, related materials and examination of personnel assignment or priority input, for example, materials including graphs, diagrams, photographs, etc. It can also be formed so that it can be disclosed and transmitted to a terminal that has been created and accessed.

なおまた、このように処理された各種情報は、工事番号、工事件名、発注者名、建設現場所在地等をキーとしてそれぞれのクライアント3や携帯端末4からインターネット2を介してアクセスすることにより検索可能であり、モニタ画面による可視データ、プリントアウトされたハードコピー、電子媒体を利用する電子データのような適宜形態のデータとして出力可能である。   In addition, various information processed in this way can be searched by accessing each client 3 or mobile terminal 4 via the Internet 2 using the construction number, construction subject, ordering party name, construction site location, etc. as keys. It can be output as data in an appropriate form such as visible data on a monitor screen, printed hard copy, and electronic data using an electronic medium.

以下この実施例の工事進捗状況管理システムを動作に基づいてより詳細に説明する。
図3は、工事工程表を、クライアント3の一つとして使用されるパソコンから登録する際の動作手順を示すフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M14と対応させて表示している。なおこの登録は、工事管理者が管理するパソコン(クライアント3)から行うべきものであり、工事管理者はこのシステムに会員登録することにより、予めID及びパスワードが設定されている。なおまたこのような工事管理者は、現場監督及び自社部署の工事担当者を兼任することも可能である。
Hereinafter, the construction progress management system of this embodiment will be described in more detail based on the operation.
FIG. 3 is a flowchart showing an operation procedure when registering the construction process table from a personal computer used as one of the clients 3. The storage units M11, M12, M13, and M14 of the server 1 to which information is exchanged are shown. Displayed in correspondence. This registration should be performed from a personal computer (client 3) managed by the construction manager, and the construction manager has registered an ID and password in advance by registering as a member in this system. In addition, such a construction manager can also serve as a site supervisor and a person in charge of construction in his department.

クライアント3がこのシステムの所定のURLにアクセスすると、ログイン画面が表示され、ID及びパスワードの入力が要求される。これらを順次入力すると、サーバ1では、記憶部M11から取り込まれたログイン情報に基づき、クライアント3から入力された上記ID及びパスワードと登録情報との比較が行われ、その認証が行われる(ステップS11)。   When the client 3 accesses a predetermined URL of this system, a login screen is displayed, and input of ID and password is requested. When these are sequentially input, the server 1 compares the ID and password input from the client 3 with the registration information based on the login information fetched from the storage unit M11, and performs authentication (step S11). ).

ID及びパスワードの認証が行われると、初期画面が表示され、「マスタ登録」、「工事登録」、「管理機能」及び「顧客登録」のメニューが表示される。このシステムは、当然ながら予め「マスタ登録」をしておかなければ、利用できないので、その登録から始める。   When the ID and password are authenticated, an initial screen is displayed, and menus of “master registration”, “construction registration”, “management function”, and “customer registration” are displayed. Of course, this system cannot be used unless "master registration" is performed in advance, so that registration is started.

クライアント3は、その初期画面のメニュー表示から「マスタ(ヘッダ部)登録」を選択し、その各々の登録事項の登録を行う(ステップS12)。   The client 3 selects “master (header part) registration” from the menu display of the initial screen, and registers each registration item (step S12).

マスタ登録の内容は、この実施例では、「工事種類(進捗管理対象である工事の任意の名称、例えば、基礎工事、外装工事等)」、「工事担当部署(自社)」、その「工事担当者」、「工事担当業者」、その「工事担当者」である。「マスタ登録」を、前記初期画面のメニュー表示の該当するボタンをクリックすることで選択すると、その登録画面が表示され、その中から上記登録項目の選択用のボタンが表示される。各々登録項目のボタンをクリックすると、その入力画面が表示され、それに従ってそれに示された入力項目を入力することになる。入力内容を確認の上、登録ボタンをクリックすると、それらの情報はサーバ1の記憶部M12に格納保存されることになる。   In this embodiment, the contents of the master registration are “construction type (arbitrary name of construction subject to progress management, for example, basic construction, exterior construction, etc.)”, “department in charge (in-house)”, and “ "Contractor", "Construction Contractor", and "Construction Contractor". When “Master Registration” is selected by clicking the corresponding button in the menu display of the initial screen, the registration screen is displayed, and the button for selecting the registration item is displayed. When each registered item button is clicked, its input screen is displayed, and the input item shown therein is input accordingly. When the registration button is clicked after confirming the input contents, the information is stored and saved in the storage unit M12 of the server 1.

なお以上の登録項目の内、「工事担当部署(自社)」の「工事担当者」及び「工事担当業者」の「工事担当者」については、以上に於いて、その携帯する携帯端末4である携帯電話の「電話番号」、「メールアドレス」及び「パスワード」が登録項目として表示されるようになっており、これを登録しておくものとする。「工事担当部署(自社)」の「工事担当者」及び「工事担当業者」の「工事担当者」の各々管理するクライアント3についてもID及びパスワードを登録しておくものとする。   Of the above registered items, the “construction person in charge” of the “department in charge of construction (in-house)” and the “construction person in charge” of the “construction contractor” are the portable terminals 4 carried by the above. The “phone number”, “mail address”, and “password” of the mobile phone are displayed as registration items, and these are registered. It is assumed that IDs and passwords are also registered for the clients 3 managed by the “construction staff” of the “department in charge (in-house)” and the “construction staff” of the “construction contractor”.

以上のマスタ登録に引き続いて、クライアント3は、初期画面のメニュー表示から工事登録中のサブメニューである「工事」及び「工程」を順次選択し、「工事」に関する登録事項及びその工事の「工程」に関する登録事項の登録を行う(ステップS13)。   Subsequent to the above master registration, the client 3 sequentially selects “construction” and “process”, which are submenus under construction registration, from the menu display on the initial screen. Is registered (step S13).

上記工事に関する登録の内容は、この実施例では、工事番号、工事件名、現場監督、工事期間、工程表示開始日及び備考であり、これらの登録項目は、前記工事登録中のサブメニュー「工事」を選択すると、その登録画面が表示され、その中に表示されることになる。その中の各登録項目のボタンをクリックすると、各々その入力画面が表示され、それに従って各登録項目の内容を入力することができる。各々入力画面の表示に従って必要な情報を入力し、確認の上、登録ボタンをクリックすると、それらの情報はサーバ1の記憶部M13に格納保存されることになる。   In this embodiment, the contents of the registration related to the construction are construction number, construction subject, site supervision, construction period, process display start date and remarks. These registration items are submenus “construction” during the construction registration. When is selected, the registration screen is displayed and displayed therein. When the button for each registered item is clicked, the input screen is displayed, and the contents of each registered item can be input accordingly. When necessary information is input in accordance with the display of each input screen, and after confirmation, the registration button is clicked, the information is stored and saved in the storage unit M13 of the server 1.

なお以上の登録項目の内、現場監督については、以上の入力画面に於いて、その携帯する携帯端末4である携帯電話の「電話番号」、「メールアドレス」及び「パスワード」が入力項目として表示されるようになっており、これを入力しておくものとする。   Of the above registration items, for field supervision, the "phone number", "email address" and "password" of the mobile phone that is the mobile terminal 4 to be carried are displayed as input items on the above input screen. It is assumed that this has been entered.

次いで、前記工事登録中のサブメニュー「工程」を選択すると、その登録画面が表示され、表示に従って工程の登録を行う。この実施例では、登録項目は、当該の工程の工事の内容、その開始予定日、終了予定日、工事担当業者であり、上記のように、入力画面の表示に従って必要な情報を入力し、確認の上、登録ボタンをクリックすると、それらの情報はサーバ1の記憶部M13に格納保存されることになる。これを繰り返して、全工程の登録を完了させる。   Next, when the sub-menu “process” during construction registration is selected, its registration screen is displayed, and the process is registered according to the display. In this embodiment, the registered items are the contents of the construction of the relevant process, its scheduled start date, scheduled end date, and construction contractor. As described above, the necessary information is entered and confirmed according to the display on the input screen. When the registration button is clicked, the information is stored and saved in the storage unit M13 of the server 1. This is repeated to complete the registration of all processes.

また以上のマスタ登録及び工事登録に引き続いて、クライアント3は、顧客登録をしておくべきである。初期画面のメニュー表示から「顧客登録」を選択し、当該の顧客関係の工事を検索し、対応する工事と関連づけて、その顧客に関する登録事項の登録を行う(ステップS14)。   Further, following the above master registration and construction registration, the client 3 should perform customer registration. “Customer registration” is selected from the menu display of the initial screen, the relevant customer-related work is searched, and the registered items related to the customer are registered in association with the corresponding work (step S14).

初期画面のメニュー表示から、上記のように、「顧客登録」を選択すると、工事件名検索画面が表示される。この工事件名検索画面では、登録しようとする顧客関連の工事、即ち、該顧客の注文による工事を検索するものであり、検索のための入力項目として、この実施例では、工事番号、工事件名、工事開始予定日、工事終了予定日、現場監督名、工事担当者(自社又は業者)及び進捗状況が表示され、それぞれに入力エリアが近接して表示される。なお前記進捗状況のみは、他の項目で入力エリアが表示される部位に「すべて、未着手、着手、完了」の選択項目が表示され、いずれかを選択するようになっている。これらの各入力項目の全部又は一部の入力をして検索ボタンをクリックすると、複数入力の場合はそれらの入力項目をAND条件として検索が実行される。   When “customer registration” is selected from the menu display on the initial screen as described above, a construction subject search screen is displayed. In this construction subject search screen, a customer-related construction to be registered, that is, a construction based on the customer's order is searched. In this embodiment, as a search input item, a construction number, a construction subject, The scheduled construction start date, scheduled construction end date, site supervision name, construction staff (in-house or contractor), and progress are displayed, and input areas are displayed in close proximity to each other. For the progress status only, a selection item of “all, not started, started, completed” is displayed in a portion where the input area is displayed with other items, and any one of them is selected. When all or some of these input items are input and the search button is clicked, in the case of multiple inputs, the search is executed using those input items as AND conditions.

前記検索が完了すると、ヒットした工事件名のリストが表示される。この実施例では、このリストに、工事件名の外に、工事の開始予定日及び終了予定日、着手日及び完了日、現場監督名、進捗状況の表示項目が表示され、更に末尾に「顧客登録・修正」並びに「メール」のボタンが付設されている。該リストの該当する工事件名末尾の顧客登録・修正ボタンをクリックして該当する工事を選択すると、顧客情報登録・修正画面が表示される。   When the search is completed, a list of hit construction subjects is displayed. In this embodiment, in addition to the construction subject, this list displays the planned start date and planned end date, start date and completion date, on-site supervision name, and progress status display items. -“Modify” and “Mail” buttons are attached. When the customer registration / correction button at the end of the corresponding construction subject in the list is clicked and the corresponding construction is selected, a customer information registration / correction screen is displayed.

この実施例では、上記顧客情報登録・修正画面中に、入力項目として、顧客名、顧客名(仮名)、ユーザーID、パスワード、メールアドレス、電話番号、郵便番号、住所が表示され、各々に近接してそれらを入力するための入力エリアが付設表示される。これらの入力項目の全てに必要情報を入力して、確認の上、登録ボタンをクリックすると、それらの情報は、該当する工事件名と関連づけてサーバ1の記憶部M14に格納保存されることになる。   In this embodiment, a customer name, customer name (kana), user ID, password, e-mail address, telephone number, postal code, and address are displayed as input items on the customer information registration / correction screen. Then, an input area for inputting them is additionally displayed. When necessary information is input to all of these input items, and after confirming, clicking the registration button, the information is stored and stored in the storage unit M14 of the server 1 in association with the corresponding construction subject. .

同様の手順を経て上記顧客情報登録・修正画面にアクセスすれば、登録事項中の誤りが訂正できることは云うまでもない。また前記検索によって得た各工事件名リストの末尾の「メール」のボタンは、以上のようにして顧客入力が完了した後、これをクリックすると、当該の顧客の携帯端末4及びクライアント3に、当該の工事の進捗状況情報にアクセスするための情報がサーバ1から自動的にメールで送信されることになる。このメールは、このボタンをクリックすると、サーバ1が自動的に作成して送信するようになっている。   Needless to say, if the customer information registration / correction screen is accessed through the same procedure, errors in the registered items can be corrected. The button of “mail” at the end of each construction subject list obtained by the search is clicked after the customer input is completed as described above. The information for accessing the progress status information of the construction is automatically transmitted from the server 1 by mail. The server 1 automatically creates and sends this mail when this button is clicked.

図4は、携帯端末(カメラ付き携帯電話)4からの進捗状況情報の登録及び現場写真情報の送信を行う際の手順を示すフロー図で、図3と同様に、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M22と対応させて表示している。   FIG. 4 is a flowchart showing a procedure for registering progress information and transmitting on-site photo information from the mobile terminal (mobile phone with camera) 4, and similarly to FIG. 3, the server 1 to which information is exchanged is shown. Are displayed in correspondence with the storage units M11, M12, M13, and M22.

なおこの進捗状況の入力は、この実施例では、工事現場に所在する担当の現場監督、工事担当者(自社部署)、工事担当者(業者)又はこれらを兼ねる工事管理者がその携帯する携帯端末4又はクライイアント3から行う。前記工事担当者(自社部署及び業者)は、前記マスタ登録の際にその携帯する携帯端末4と共に登録された者であり、前記現場監督は、前記工事登録の際にその携帯する携帯端末4と共に登録された者である。クライアント3についてもID及びパスワードの登録が同時に行われた者である。   In this embodiment, the progress status is input by a portable terminal carried by the site supervisor who is in charge at the construction site, the construction manager (own department), the construction manager (contractor), or the construction manager who also serves as the manager. 4 or from client 3. The person in charge of the construction (in-house department and contractor) is a person who is registered with the portable terminal 4 that is carried at the time of the master registration, and the site supervisor is together with the portable terminal 4 that is carried at the time of the construction registration. It is a registered person. The client 3 is also a person who has registered ID and password at the same time.

ここでは、先に述べたように、携帯端末4による登録に関して説明する。まず前記関係者が携帯端末4によりこのシステムの所定のアドレスにアクセスすると、携帯端末用のログイン画面が表示され、ID及びパスワードの入力が要求される。これらを順次入力すると、サーバ1では、記憶部M11から取り込まれたログイン情報に基づき、携帯端末4から入力された上記ID及びパスワードと登録情報との比較が行われ、その認証が行われる(ステップS21)。   Here, as described above, registration by the portable terminal 4 will be described. First, when the concerned person accesses a predetermined address of this system by the portable terminal 4, a login screen for the portable terminal is displayed, and input of ID and password is requested. When these are sequentially input, the server 1 compares the ID and password input from the portable terminal 4 with the registration information based on the login information fetched from the storage unit M11, and performs authentication (step). S21).

ID及びパスワードの認証が行われると、携帯端末用の初期画面が表示され、アクセスした者が現場監督の場合(ID及びパスワードによって識別される)は、進捗表示、進捗報告及び実算報告のメニューが表示される。工事担当者の場合は、進捗表示及び進捗報告のみのメニューが表示される。   When the ID and password are authenticated, the initial screen for the mobile terminal is displayed. When the person who accesses the site is a field supervisor (identified by the ID and password), a menu for progress display, progress report, and actual report is displayed. Is displayed. In the case of a person in charge of construction, a menu of only progress display and progress report is displayed.

携帯端末4が、その初期画面のメニュー表示から「進捗報告」を選択し、「次へ」の表示をクリックすると、工事選択画面が表示され、記憶部M12から当該の現場監督又は工事担当者の担当する工事件名リストが読み込まれて、該携帯端末4のモニタ画面に表示される。その工事選択画面の表示に従って進捗報告の対象である工事件名を選択し、「次へ」の表示をクリックすると(ステップS22)、工事工程選択画面が表示され、記憶部M13から、選択された工事件名の全工事工程(全工事内容)のリストが読み込まれて同モニタ画面に表示される。その工事工程選択画面の表示に従って進捗報告の対象である工事工程(工事内容)を選択し、「次へ」の表示をクリックすると(ステップS23)、進捗報告画面が表示される。   When the portable terminal 4 selects “progress report” from the menu display of the initial screen and clicks the “next” display, a construction selection screen is displayed, and the relevant site supervisor or construction worker is informed from the storage unit M12. The construction subject list in charge is read and displayed on the monitor screen of the portable terminal 4. According to the construction selection screen display, select the construction subject that is the subject of the progress report and click the “Next” display (step S22) to display the construction process selection screen, and the selected construction from the storage unit M13. A list of all construction processes (contents of all construction) in the subject is read and displayed on the monitor screen. According to the display of the construction process selection screen, the construction process (construction content) that is the subject of the progress report is selected, and when the “next” display is clicked (step S23), the progress report screen is displayed.

進捗報告画面では、進捗状況に関して、それぞれチェック欄付きの「着手」及び「完了」と、写真の「あり」及び「なし」と、問題点の「あり」及び「なし」とが表示され、それぞれいずれかのチェック欄をチェックした上で、「次へ」の表示をクリックすることで当該の工事の当該の工程について進捗状況の報告を行うことができる。現場監督又は工事担当者は、工事現場の状況に適合するそれを選んで、以上の操作をすると、当該の工事の当該の工程についての進捗状況情報が送信され、サーバ1の記憶部M13に追記乃至更新的に格納保存される(ステップS24)。   On the progress report screen, regarding the progress status, “Start” and “Complete” with check boxes, “Yes” and “None” of the photo, and “Yes” and “None” of the problem are displayed respectively. After checking any of the check boxes, clicking the “Next” display can report the progress status of the relevant process of the construction. When the site supervisor or the construction worker selects that which matches the situation of the construction site and performs the above operation, progress status information on the relevant process of the construction is transmitted and added to the storage unit M13 of the server 1 Or it is stored and saved in an updated manner (step S24).

前記進捗状況情報がサーバ1に送信されると、サーバ1では、その情報中の写真の「あり」及び「なし」の内、いずれにチェックが付されていたかが判断され(ステップS25)、「あり」にチェックが付されていた場合は、該サーバ1で写真添付用のメールが作成され、当該の携帯端末4に、これが送信される。現場監督又は工事担当者は、携帯端末4であるカメラ付き携帯電話で撮影した工事現場の写真の画像情報を該メールに添付して返信することによりその登録を行う。サーバ1では、このメールを受信すると、該メールに添付されていた写真画像情報を前記所定の工事件名の所定の工程(工事内容)と関連づけて記憶部M22に格納保存する。当該の工事件名の所定の工程(工事内容)の登録されている記憶部M13にも写真が登録されている旨の登録をする。   When the progress status information is transmitted to the server 1, the server 1 determines which of “Yes” and “No” of the photo in the information is checked (Step S25). "Is checked, a mail for attaching a photo is created by the server 1 and transmitted to the mobile terminal 4. The site supervisor or the construction person in charge performs registration by attaching the image information of the photograph of the construction site taken with the camera-equipped mobile phone, which is the mobile terminal 4, to the e-mail. Upon receiving this mail, the server 1 stores and saves the photographic image information attached to the mail in the storage unit M22 in association with a predetermined process (construction content) of the predetermined construction subject. The fact that a photograph is registered is also registered in the storage unit M13 in which a predetermined process (construction contents) of the construction subject is registered.

前記進捗状況情報がサーバ1に送信された際に、該サーバ1で、その情報中の写真の「あり」及び「なし」の内、「なし」にチェックが付されていたと判断され(ステップS25)た場合は、そのままそのプロセスは終了する。   When the progress status information is transmitted to the server 1, it is determined by the server 1 that “None” is checked among “Yes” and “No” of the photos in the information (step S25). ), The process ends as it is.

なお、図4のフロー図には示されていないが、携帯端末4から進捗状況の報告が行われ、サーバ1がこれを受け取ると、設定がそのようになっていた場合は、該サーバ1は該携帯端末4からの報告に基づいて進捗報告のメールを作成し、当該の工事関連の工事管理者の携帯端末4に該進捗報告のメールを送信する。これによって工事管理者は、事務所にいない場合でも、リアルタイムで特定の工事の特定の工程の進捗状況を知ることができる。   Although not shown in the flowchart of FIG. 4, when the progress status is reported from the mobile terminal 4 and the server 1 receives this, if the setting is such, the server 1 A progress report mail is created based on the report from the portable terminal 4, and the progress report mail is transmitted to the portable terminal 4 of the construction manager related to the construction. As a result, the construction manager can know the progress of a specific process of a specific construction in real time even when not in the office.

なお、以上のメールによる工事管理者に対する進捗報告の設定は、この実施例では、クライアント3がアクセスする初期画面のメニュー表示から「工事登録」中の「工程」に関する登録を選択すると、各工程毎に、工事管理者にメールで進捗報告をするか否かのチェック欄が構成してあり、これにチェックをすることで、報告する旨の設定をすることができるようになっている。   In this embodiment, the progress report is set for the construction manager by e-mail as described above. When registration related to “process” in “construction registration” is selected from the menu display of the initial screen accessed by the client 3, the progress report is set for each process. In addition, a check column for whether or not to report the progress to the construction manager by e-mail is configured, and by checking this, it can be set to report.

図5は、クライアント3からの進捗状況情報の登録及び現場写真情報の送信を行う際の手順を示すフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M22と対応させて表示している。   FIG. 5 is a flowchart showing a procedure for registering progress status information and transmitting on-site photo information from the client 3, and corresponds to the storage units M11, M12, M13, and M22 of the server 1 to which information is exchanged. Is displayed.

これは、工事現場に所在する担当の現場監督、工事担当者(自社部署)、工事担当者(業者)又はこれらを兼ねる工事管理者がその管理するクライイアント3から行う場合について説明するものである。   This is to explain the case where the site supervisor in charge at the construction site, the construction manager (own department), the construction manager (contractor), or the construction manager who also serves as the manager performs from the client 3 managed by the manager. .

まず前記関係者がクライアント3によりこのシステムの所定のURLにアクセスすると、ログイン画面が表示され、ID及びパスワードの入力が要求される。これらを順次入力すると、サーバ1では、記憶部M11から取り込まれたログイン情報に基づき、クライアント3から入力された上記ID及びパスワードと登録情報との比較が行われ、その認証が行われる(ステップS27)。   First, when the related party accesses a predetermined URL of this system by the client 3, a login screen is displayed and input of an ID and a password is requested. When these are sequentially input, the server 1 compares the ID and password input from the client 3 with the registration information based on the login information fetched from the storage unit M11, and performs authentication (step S27). ).

ID及びパスワードの認証が行われると、初期画面が表示され、アクセスした者が現場監督の場合(ID及びパスワードによって識別される)は、進捗表示、進捗報告及び実算報告のメニューが表示される。工事担当者の場合は、進捗表示及び進捗報告のみのメニューが表示される。   When the ID and password are authenticated, an initial screen is displayed. When the person who accesses the site is a field supervisor (identified by the ID and password), a menu of progress display, progress report, and actual report is displayed. . In the case of a person in charge of construction, a menu of only progress display and progress report is displayed.

クライアント3が、その初期画面のメニュー表示から「進捗報告」を選択し、これをクリックすると、工事選択画面が表示され、検索のための入力項目として、この実施例では、工事番号、工事件名、工事開始予定日、工事終了予定日、現場監督名及び工事担当者(自社又は業者)が表示され、それぞれに入力エリアが近接して表示される。これらの各入力項目の全部又は一部の入力をして検索ボタンをクリックすると、複数入力の場合はそれらの入力項目をAND条件として検索が実行される(ステップS28)。   When the client 3 selects “progress report” from the menu display of the initial screen and clicks on it, a construction selection screen is displayed. In this embodiment, the construction number, construction title, The scheduled construction start date, the scheduled construction end date, the name of the site supervisor, and the person in charge of the construction (in-house or contractor) are displayed, and the input areas are displayed close to each other. When all or some of these input items are input and the search button is clicked, in the case of multiple inputs, the search is executed using those input items as AND conditions (step S28).

前記検索が完了すると、工事工程選択画面が表示され、記憶部M13から、選択された工事件名の全工事工程(全工事内容)のリストが読み込まれてモニタ画面に表示される。その工事工程選択画面の表示に従って進捗報告の対象である工事工程(工事内容)を選択し、これをクリックすると(ステップS29)、進捗報告画面が表示される。   When the search is completed, a construction process selection screen is displayed, and a list of all construction processes (all construction contents) of the selected construction subject is read from the storage unit M13 and displayed on the monitor screen. According to the display of the construction process selection screen, the construction process (construction content) that is the subject of the progress report is selected, and when this is clicked (step S29), the progress report screen is displayed.

進捗報告画面では、進捗状況に関して、それぞれ「着手日」及び「完了日」の入力欄と、写真の「あり」及び「なし」のチェック欄と、問題点の「あり」及び「なし」のチェック欄とが表示され、「着手日」及び「完了日」の入力欄には、該当する日付を入力し、問題点の「あり」及び「なし」のチェック欄は、「あり」にチェックすると、その入力欄が表示されるので、該当する内容を入力する。問題点の「なし」にチェックした場合は、当然、入力欄は表示されない。こうして工事進捗状況情報の登録を行うことができる(ステップS30)。   On the progress report screen, regarding the progress status, input fields for “Start Date” and “Completion Date”, “Yes” and “None” check boxes for photos, and “Yes” and “None” checks for problems, respectively. If the check box for “Yes” and “None” for the problem is “Yes”, enter the appropriate date in the “Start date” and “Completion date” fields. The input field will be displayed, so enter the relevant content. If you check “None” for the problem, the entry field will not be displayed. In this way, construction progress status information can be registered (step S30).

前記写真の「あり」及び「なし」のチェック欄の内の前者の欄にチェックすると、写真のありと判断され(ステップS31)、画像登録画面が表示される。案内に従って登録する画像ファイルを指定して画面中の画像登録ボタンをクリックすると、該画像ファイルがサーバ1にアップロードされ、記憶部M22に登録される(ステップS32)。   If the former column of the “Yes” and “No” check boxes for the photo is checked, it is determined that there is a photo (step S31), and an image registration screen is displayed. When an image file to be registered is designated according to the guidance and the image registration button in the screen is clicked, the image file is uploaded to the server 1 and registered in the storage unit M22 (step S32).

更にクライアント3から写真情報のみの登録を行う場合は、以上に述べた、それ以外の情報と共に登録する場合と同様に、ログインし、対象の工事を検索選択し、更にそのリストから特定の工事工程を選択し、これについての進捗報告画面を表示させ、更に該画面中の写真「あり」のチェック欄をチェックして、画像登録画面を表示させて登録することができる。即ち、この後、案内に従って登録する画像ファイルを指定して画面中の画像登録ボタンをクリックし、該画像ファイルをサーバ1にアップロードする。該画像ファイルはサーバ1の記憶部M22に登録されることになる。   Furthermore, when registering only the photo information from the client 3, as in the case of registering together with the other information described above, login, search and select the target construction, and further select a specific construction process from the list. And a progress report screen for this is displayed, and a check box for a photo “present” in the screen is checked, and an image registration screen is displayed for registration. That is, after that, an image file to be registered is designated in accordance with the guidance, an image registration button in the screen is clicked, and the image file is uploaded to the server 1. The image file is registered in the storage unit M22 of the server 1.

図6は、携帯端末4から工事進捗情報の参照を行う場合のフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M22と対応させて表示している。   FIG. 6 is a flowchart when referring to the construction progress information from the mobile terminal 4 and is displayed in correspondence with the storage units M11, M12, M13, and M22 of the server 1 to which information is exchanged.

現場監督又は工事担当者が携帯端末4でこのシステムの所定のアドレスにアクセスすると、前記したように、携帯端末用のログイン画面が表示され、ID及びパスワードの入力が要求され、所定のプロセスを経てその認証が行われる(ステップS41)。   When the site supervisor or construction worker accesses the predetermined address of this system with the portable terminal 4, as described above, the login screen for the portable terminal is displayed, the input of ID and password is requested, and the predetermined process is performed. The authentication is performed (step S41).

ID及びパスワードの認証が行われると、携帯端末用の初期画面が表示され、前記したように、アクセスした者が現場監督である場合は、進捗表示、進捗報告及び実算報告のメニューが表示され、工事担当者の場合は、進捗表示及び進捗報告のみのメニューが表示される。   When the ID and password are authenticated, the initial screen for the mobile terminal is displayed. As described above, when the person who has accessed the site is a field supervisor, the menu of progress display, progress report, and actual report is displayed. In the case of a person in charge of construction, a menu of only progress display and progress report is displayed.

携帯端末4が、その初期画面のメニュー表示から「進捗表示」を選択し、「次へ」の表示をクリックすると、工事選択画面が表示され、記憶部M12から当該の現場監督又は工事担当者の担当する工事件名リストが読み込まれて表示される(ステップS42)。その工事選択画面の表示に従って表示希望の工事件名を選択し、「次へ」の表示をクリックすると、工事工程選択画面が表示され、記憶部M13から、選択された工事件名の全工事工程(全工事内容)のリストが読み込まれて表示される(ステップS43)。全体の表示が画面中に納まらない場合はスクロールして全リストを見ることができるのは云うまでもない。その工事工程選択画面の表示に従って進捗表示の対象である工事工程(工事内容)を選択し、「次へ」の表示をクリックすると、進捗表示画面が表示される(ステップS44)。   When the portable terminal 4 selects “progress display” from the menu display of the initial screen and clicks “next” display, a construction selection screen is displayed, and the relevant site supervisor or construction worker is informed from the storage unit M12. The construction subject list in charge is read and displayed (step S42). Select the desired construction subject to be displayed according to the construction selection screen display, and click “Next” to display the construction process selection screen. From the storage unit M13, all construction processes with the selected construction subject (all A list of construction details is read and displayed (step S43). Needless to say, if the entire display doesn't fit on the screen, you can scroll to see the full list. According to the display of the construction process selection screen, the construction process (construction content) that is the object of progress display is selected, and when the “next” display is clicked, the progress display screen is displayed (step S44).

進捗表示画面では、この実施例では、工事種類、工事担当部署(自社)又は工事担当業者、開始予定日、終了予定日、着手日、完了日、現場監督及び写真の有無の欄が表示される。全ての表示内容が画面中の納まらない場合はスクロールすれば見ることができるのは云うまでもない。   In the progress display screen, in this embodiment, the columns of construction type, construction department (in-house) or construction contractor, scheduled start date, scheduled end date, start date, completion date, on-site supervision, and presence / absence of photographs are displayed. . Needless to say, if all the display content does not fit on the screen, you can scroll to see it.

現場写真がある場合は、写真ありの表示がされており、表示されている「写真を見る」を選択して、「次へ」の表示をクリックすると、進捗状況を示す当該の現場の写真がサーバ1の記憶部M22から読み出されて送信され、該携帯端末4のモニタ画面に表示されることになる(ステップS45)。   If there is an on-site photo, it is displayed with a photo. Select “View Photo” and click “Next” to display a photo of the site that shows the progress. The data is read from the storage unit M22 of the server 1 and transmitted, and displayed on the monitor screen of the portable terminal 4 (step S45).

図7は、クライアント3から工事進捗情報の参照を行う場合のフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M22と対応させて表示している。   FIG. 7 is a flowchart when referring to the construction progress information from the client 3, and is displayed in correspondence with the storage units M11, M12, M13, and M22 of the server 1 to which information is exchanged.

クライアント3がこのシステムの所定のURLにアクセスすると、前記したように、ログイン画面が表示され、ID及びパスワードの入力が要求される。これらを順次入力すると、サーバ1では、記憶部M11から取り込まれたログイン情報に基づき、クライアント3から入力された上記ID及びパスワードと登録情報との比較が行われ、その認証が行われる(ステップS51)。   When the client 3 accesses a predetermined URL of this system, as described above, the login screen is displayed and the input of ID and password is requested. When these are sequentially input, the server 1 compares the ID and password input from the client 3 with the registration information based on the login information fetched from the storage unit M11, and performs authentication (step S51). ).

ID及びパスワードの認証が行われ、これが工事管理者のものであることが確認されると、前記した初期画面が表示され、前記したように、「マスタ登録」、「工事登録」、「管理機能」及び「顧客登録」のメニューが表示される。ID及びパスワードが顧客のものであることが確認されると、当該の顧客の工事件名に関する工事選択画面が表示されることになる。   When the ID and password are authenticated and confirmed that they belong to the construction manager, the initial screen described above is displayed, and as described above, “master registration”, “construction registration”, “management function” ”And“ Customer Registration ”menus are displayed. When it is confirmed that the ID and password belong to the customer, a construction selection screen regarding the construction subject of the customer is displayed.

まず工事管理者である場合について説明する。この場合は、クライアント3が、その初期画面の工事登録中のサブメニュー、「工事」と「工程」とから「工程」を選択し、更に「工程」中の「進捗表示」を選択し、これをクリックすると、工事選択画面が表示され、検索のための入力項目として、この実施例では、工事番号、工事件名、工事開始予定日、工事終了予定日、現場監督名及び工事担当者(自社又は業者)が表示され、それぞれに入力エリアが近接して表示される。これらの各入力項目の全部又は一部の入力をして検索ボタンをクリックすると、複数入力の場合はそれらの入力項目をAND条件として検索が実行される(ステップS52)。   First, the case of being a construction manager will be described. In this case, the client 3 selects “Process” from the sub-menu under construction registration of the initial screen, “Construction” and “Process”, and further selects “Progress display” in “Process”. When is clicked, the construction selection screen is displayed. In this example, the construction number, construction subject, construction start date, construction start date, construction end date, site supervision name and construction person in charge (in-house or (Trader) is displayed, and input areas are displayed in close proximity to each other. When all or some of these input items are input and the search button is clicked, in the case of multiple inputs, the search is executed using those input items as AND conditions (step S52).

前記検索が完了すると、ヒットした工事件名のリストが表示される。この実施例では、このリストに、工事件名の外に、工事の開始予定日及び終了予定日、着手日及び完了日、現場監督名、進捗状況の表示項目が表示され、更に末尾に「進捗表示」ボタンが付設表示される。該リストの該当する工事件名末尾の「進捗表示」ボタンをクリックして該当する工事を選択すると、サーバ1の記憶部13から当該の工事件名に関する進捗状況情報が読み出されて送信され、該クライアント3のモニタ画面で当該の工事件名に関する進捗表示画面が表示されることになる(ステップS53)。   When the search is completed, a list of hit construction subjects is displayed. In this embodiment, in addition to the construction subject, in this list, the planned start date and planned end date, start date and completion date, site supervision name, and progress status display items are displayed. "Button is additionally displayed. When the “progress display” button at the end of the relevant construction subject in the list is clicked and the relevant construction is selected, progress status information relating to the construction subject is read from the storage unit 13 of the server 1 and transmitted. The progress display screen relating to the construction subject is displayed on the monitor screen 3 (step S53).

この進捗表示画面は、この実施例では、図8に示すように、工事番号及び工事件名で工事を特定し、工事内容(工程)を縦に、施工時期を横に配列して、施工予定期間を各々示すと共に、色分けをして進捗状況を示している。黒(斜めクロス状のハッチング)は工事完了、赤(右上がりのハッチング)は工事着手、青(左上がりのハッチング)は工事未着手を表示する。また記号で実績を示しており、「S」は着手日を、「E」は完了日を、それぞれ示しており、「→」はその間の施工日を示している。   In this embodiment, as shown in FIG. 8, this progress display screen identifies the construction by construction number and construction title, arranges the construction content (process) vertically, and arranges the construction time horizontally. In addition, each color is color-coded to indicate the progress. Black (diagonal cross hatching) indicates completion of construction, red (upward hatching) indicates construction start, and blue (upward left hatching) indicates construction not yet started. In addition, the results are indicated by symbols, “S” indicates the start date, “E” indicates the completion date, and “→” indicates the construction date in between.

各工事内容(工程)の表示欄の左端には「詳細」ボタンが表示されており、これを選択してクリックすると、サーバ1の記憶部13から詳細情報が読み出され、これが工事工程詳細表示画面として表示され、当該の工事工程の問題点の有無、写真の有無、及び備考が表示される(ステップS54)。写真がある旨の表示がある場合は、表示されている「画像表示」ボタンをクリックすると、当該の現場の当該の工程の進捗状況を示す写真がサーバ1の記憶部M22から読み出されて送信され、該クライアント3のモニタ画面に表示されることになる(ステップS55)。   A “detail” button is displayed at the left end of the display column of each construction content (process). When this is selected and clicked, detailed information is read from the storage unit 13 of the server 1, and this is the construction process detail display. Displayed as a screen, the presence / absence of problems in the construction process, presence / absence of photographs, and remarks are displayed (step S54). If there is a display indicating that there is a photo, clicking the displayed “image display” button reads out the photo showing the progress of the process at the site from the storage unit M22 of the server 1 and transmits it. Is displayed on the monitor screen of the client 3 (step S55).

図9は、前記ログイン画面で入力したID及びパスワードにより、当該のID及びパスワードが顧客のものであることが確認された場合のフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13、M22と対応させて表示している。   FIG. 9 is a flowchart when the ID and password entered on the login screen are confirmed to belong to the customer. The storage units M11 and M12 of the server 1 to which information is exchanged are shown. , M13, and M22.

この場合は、当該の顧客の工事件名に関する工事選択画面が直ちに表示されることになり、工事件名のリストが表示される。そのリストから該当する工事件名末尾の「進捗表示」ボタンをクリックして該当する工事を選択すると(ステップS56)、サーバ1の記憶部13から当該の工事件名に関する進捗状況情報が読み出されて送信され、該クライアント3のモニタ画面で当該の工事件名に関する進捗表示画面が表示されることになる(ステップS57)。   In this case, a construction selection screen relating to the construction subject of the customer is immediately displayed, and a list of construction subjects is displayed. When the “construction display” button at the end of the relevant construction subject is clicked from the list and the relevant construction is selected (step S56), the progress status information relating to the construction subject is read from the storage unit 13 of the server 1 and transmitted. Then, the progress display screen relating to the construction subject is displayed on the monitor screen of the client 3 (step S57).

この進捗表示画面は、この実施例では、前記し、図8に示すように、工事番号及び工事件名で工事を特定し、工事内容(工程)を縦に、施工時期を横に配列して、施工予定期間を各々示すと共に、色分けをして進捗状況を示している。黒(斜めクロス状のハッチング)は工事完了、赤(右上がりのハッチング)は工事着手、青(左上がりのハッチング)は工事未着手を表示する。また記号で実績を示しており、「S」は着手日を、「E」は完了日を、それぞれ示しており、「→」はその間の施工日を示している。なお各工事内容(工程)の末尾(施工時期の末尾、図示していない)にはメールと記されたボタンが表示される。   In this embodiment, as shown in FIG. 8, the progress display screen specifies the construction by the construction number and the construction title, arranges the construction contents (process) vertically, and arranges the construction time horizontally. Each of the scheduled construction periods is shown, and the progress is shown in different colors. Black (diagonal cross hatching) indicates completion of construction, red (upward hatching) indicates construction start, and blue (upward left hatching) indicates construction not yet started. In addition, the results are indicated by symbols, “S” indicates the start date, “E” indicates the completion date, and “→” indicates the construction date in between. In addition, a button marked as mail is displayed at the end of each construction content (process) (the end of construction time, not shown).

各工事内容(工程)の表示欄の左端には「詳細」ボタンが表示されており、これを選択してクリックすると、サーバ1の記憶部13から詳細情報が読み出され、これが工事工程詳細表示画面として表示され、この場合は、写真の有無及び備考が表示される(ステップS58)。写真がある旨の表示がある場合は、表示されている「画像表示」ボタンをクリックすると、当該の現場の当該の工程の進捗状況を示す写真がサーバ1の記憶部M22から読み出されて送信され、該クライアント3のモニタ画面に表示されることになる(ステップS59)。   A “detail” button is displayed at the left end of the display column of each construction content (process). When this is selected and clicked, detailed information is read from the storage unit 13 of the server 1, and this is the construction process detail display. In this case, the presence / absence of a photograph and remarks are displayed (step S58). If there is a display indicating that there is a photo, clicking the displayed “image display” button reads out the photo showing the progress of the process at the site from the storage unit M22 of the server 1 and transmits it. Is displayed on the monitor screen of the client 3 (step S59).

なお前記メールのボタンをクリックすると、工事担当部署又は工事担当業者に送信するためのメールの作成画面が表示され、これにメッセージを入力して送信操作をすると、これを工事担当部署又は工事担当業者に送信することができる。   Clicking on the email button displays a screen for creating an email to be sent to the construction department or construction contractor. If you enter a message and send it to it, this will be displayed as a construction department or construction contractor. Can be sent to.

図10は、携帯端末4からの実算報告を行う際の手順を示すフロー図で、情報のやり取り対象のサーバ1の記憶部M11、M12、M13と対応させて表示している。   FIG. 10 is a flowchart showing a procedure for performing an actual calculation report from the mobile terminal 4 and is displayed in association with the storage units M11, M12, and M13 of the server 1 to which information is exchanged.

なおこの実算報告は、この実施例では、工事現場に所在する担当の現場監督のみがその携帯する携帯端末4から行うようになっている。   In this embodiment, the actual calculation report is performed only by the on-site supervisor in charge at the construction site from the portable terminal 4 that is carried.

現場監督が携帯端末4で、このシステムの所定のアドレスにアクセスすると、前記したように、携帯端末用のログイン画面が表示され、所定の手順を経て携帯端末4から入力されたID及びパスワードと登録情報との比較が行われ、その認証が行われる(ステップS61)。   When the site director accesses the predetermined address of this system with the portable terminal 4, as described above, the login screen for the portable terminal is displayed, and the ID and password input from the portable terminal 4 through the predetermined procedure are registered. Comparison with the information is performed and the authentication is performed (step S61).

ID及びパスワードの認証が行われると、携帯端末用の初期画面が表示され、この場合は、アクセスした者が現場監督であるから、「進捗表示」、「進捗報告」及び「実算報告」のメニューが表示される。携帯端末4が、その初期画面のメニュー表示から「実算報告」を選択し、「次へ」の表示をクリックすると、実算報告画面が表示され、記憶部M12から当該の現場監督の担当する工事件名リストが読み込まれて表示される。その工事選択画面の表示に従って実算報告の対象である工事件名を選択し、「次へ」の表示をクリックすると(ステップS62)、工事工程選択画面が表示され、記憶部M13から、選択された工事件名の全工事工程(全工事内容)のリストが読み込まれて表示される。その工事工程選択画面の表示に従って実算報告の対象である工事工程(工事内容)を選択し、「次へ」の表示をクリックすると(ステップS63)、実算報告画面が表示される(ステップS64)。   When the ID and password are authenticated, the initial screen for the mobile terminal is displayed. In this case, since the person who has accessed the site is a field supervisor, the “progress display”, “progress report” and “actual report” A menu is displayed. When the portable terminal 4 selects “Actual Report” from the menu display of the initial screen and clicks the “Next” display, the Actual Report screen is displayed, and the field supervisor is in charge of the relevant field supervisor from the storage unit M12. The construction subject list is read and displayed. According to the display of the construction selection screen, the name of the construction subject to the actual report is selected, and when the “next” display is clicked (step S62), the construction process selection screen is displayed and selected from the storage unit M13. A list of all construction processes (contents of all construction) in the construction subject is read and displayed. According to the display of the construction process selection screen, the construction process (construction content) that is the target of the actual report is selected, and when the “next” display is clicked (step S63), the actual report screen is displayed (step S64). ).

実算報告画面では、当該の工事件名の工事内容(工程)に関して、「年月日」の入力欄と「作業人数」の入力欄と、「登録」ボタンとが表示され、それぞれに必要事項を入力して登録ボタンをクリックすると、それらの情報がサーバ1に送信され、その記憶部M13に登録される(ステップS65)。当該の工程の実行された日時及び要した作業人数が登録されることになるわけである。   On the actual report screen, regarding the construction contents (process) of the relevant construction subject, an input field for “Date”, an input field for “Number of workers”, and a “Register” button are displayed. When the user inputs and clicks the registration button, the information is transmitted to the server 1 and registered in the storage unit M13 (step S65). The date and time when the process was executed and the number of workers required are registered.

実施例の工事進捗状況管理システムに於けるハードウエア面からの基本構成を示すブロック図。The block diagram which shows the basic composition from the hardware surface in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於ける機能に基づく基本構成を示すブロック図。The block diagram which shows the basic composition based on the function in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於いて、マスター登録、工事登録及び顧客登録をクライアント(パソコン)から行う際の動作を示すフロー図。The flowchart which shows the operation | movement at the time of performing master registration, construction registration, and customer registration from a client (personal computer) in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於いて、進捗状況を示すデータ及び写真を携帯端末から登録する際の動作を示すフロー図。The flowchart which shows the operation | movement at the time of registering the data and photograph which show a progress from a portable terminal in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於いて、進捗状況を示すデータ及び写真をクライアント(パソコン)から登録する際の動作を示すフロー図。The flowchart which shows the operation | movement at the time of registering the data and photograph which show progress from a client (personal computer) in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於いて、現場監督又は工事担当者がその携帯する携帯端末で進捗状況を参照する際の動作を示すフロー図。In the construction progress management system of an embodiment, a flowchart showing an operation when a site supervisor or a construction worker refers to the progress with a portable terminal carried by the site supervisor. 実施例の工事進捗状況管理システムに於いて、工事管理者がそのクライアントパソコンから進捗状況を参照する際の動作を示すフロー図。FIG. 5 is a flowchart showing an operation when the construction manager refers to the progress status from the client personal computer in the construction progress status management system of the embodiment. 進捗表示画面を示す説明図。Explanatory drawing which shows a progress display screen. 実施例の工事進捗状況管理システムに於いて、顧客がその携帯する携帯端末で自己の依頼した工事の進捗状況を参照する際の動作を示すフロー図。The flowchart which shows the operation | movement at the time of referring the progress of the construction which the customer requested with the portable terminal which the customer carries in the construction progress management system of an Example. 実施例の工事進捗状況管理システムに於いて、現場監督がその携帯する携帯端末で実算報告をする際の動作を示すフロー図。In the construction progress management system of an embodiment, a flow diagram showing an operation when a field supervisor reports an actual calculation with a portable terminal carried by the site supervisor.

符号の説明Explanation of symbols

1 サーバ
2 インターネット
3(3−1、3−2、3−3…) クライアント
4(4−1、4−2、4−3…) 携帯端末
1 Server 2 Internet 3 (3-1, 3-2, 3-3 ...) Client 4 (4-1, 4-2, 4-3 ...) Mobile terminal

Claims (5)

サーバと、該サーバとネットワークを介して接続された複数のクライアント及び携帯端末とを備えた工事進捗状況管理システムであって、
前記サーバは、前記クライアント及び前記携帯端末から入力された工事に関するデータを格納保管する工事管理データ格納手段並びに前記携帯端末から入力された工事現場写真を格納保管する工事現場写真格納手段を備え、
前記クライアントは、工事計画に関する入力情報を前記サーバの工事管理データ格納手段に登録する手段、工事の進捗状況に関する文字情報を前記サーバの工事管理データ格納手段に登録する手段、工事の進捗状況に関する現場写真の画像情報を工事現場写真格納手段に登録する手段、並びに工事の進捗状況に関する文字情報及び現場写真情報をそれぞれ前記サーバの工事管理データ格納手段及び工事現場写真格納手段から読み出して表示する進捗表示手段を備え、
前記携帯端末は、工事の進捗状況情報を前記サーバの工事管理データ格納手段に登録する進捗状況情報登録手段、写真の撮影手段、及び撮影した工事の進捗状況に関する現場写真の画像情報を前記サーバの工事現場写真格納手段に登録する登録手段を備えるものとした工事進捗状況管理システム。
A construction progress management system comprising a server, and a plurality of clients and portable terminals connected to the server via a network,
The server comprises construction management data storage means for storing and storing data relating to construction input from the client and the mobile terminal, and construction site photo storage means for storing and storing construction site pictures input from the mobile terminal,
The client includes means for registering input information relating to a construction plan in the construction management data storage means of the server, means for registering character information relating to the progress of construction in the construction management data storage means of the server, and a site relating to the progress of construction. A means for registering the image information of the photo in the construction site photo storage means, and a progress display for reading and displaying the character information and the site photo information relating to the progress of the construction from the construction management data storage means and the construction site photo storage means of the server, respectively. With means,
The portable terminal is configured to register progress status information registration means for registering construction progress status information in the construction management data storage means of the server, photograph photographing means, and image information of a site photograph regarding the progress status of the photographed construction work. A construction progress status management system comprising registration means for registering in the construction site photo storage means.
前記クライアントに於ける進捗表示手段が、カレンダー機能と連動して作業計画と実際の進捗状況とを同一画面に表示することにより、予め設定されている計画と進捗状況との可視的対比を可能にした請求項1の工事進捗状況管理システム。   The progress display means in the client displays the work plan and the actual progress on the same screen in conjunction with the calendar function, thereby enabling a visual comparison between the preset plan and the progress. The construction progress management system according to claim 1. 前記携帯端末は、対象の工事現場の各段階毎の工事内容を撮影し、それらの現場写真の画像情報を当該の工事を特定する情報と関連付けて前記サーバの工事現場写真格納手段に登録することができるものとした請求項1又は2の工事進捗状況管理システム。   The portable terminal shoots the construction contents of each stage of the target construction site, and registers the image information of those site photos in the construction site photo storage means of the server in association with information specifying the construction. 3. The construction progress status management system according to claim 1 or 2, wherein the construction progress status management system is capable of. 前記携帯端末から工事の進捗状況情報が前記サーバの工事管理データ格納手段に登録された際に、該サーバから予め設定されている携帯端末に対して特定の工事の進捗状況情報が登録されたことを通知するメールが自動送信されることとした請求項1、2又は3の工事進捗状況管理システム。   When construction progress status information is registered in the construction management data storage means of the server from the mobile terminal, specific construction progress status information is registered for the mobile terminal set in advance from the server. The construction progress status management system according to claim 1, 2 or 3, wherein a mail for notifying is automatically transmitted. 前記クライアント及び携帯端末の各々は、それを管理し又は携帯する者に対して許容される範囲内で、前記サーバの工事管理データ格納手段及び工事現場写真格納手段に登録されている工事進捗状況に関するデータを随時参照可能であるようにした請求項1、2、3又は4の工事進捗状況管理システム。   Each of the client and the portable terminal relates to a construction progress status registered in the construction management data storage means and the construction site photo storage means of the server within a range permitted for a person who manages or carries the client terminal. 5. The construction progress status management system according to claim 1, wherein the data can be referred to as needed.
JP2005164882A 2005-06-03 2005-06-03 Construction progress management system Pending JP2006338561A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005164882A JP2006338561A (en) 2005-06-03 2005-06-03 Construction progress management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005164882A JP2006338561A (en) 2005-06-03 2005-06-03 Construction progress management system

Publications (1)

Publication Number Publication Date
JP2006338561A true JP2006338561A (en) 2006-12-14

Family

ID=37559034

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005164882A Pending JP2006338561A (en) 2005-06-03 2005-06-03 Construction progress management system

Country Status (1)

Country Link
JP (1) JP2006338561A (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009193381A (en) * 2008-02-14 2009-08-27 Construction Learned Academy Civil engineering work execution plan preparation support system, civil engineering work execution plan preparation support method, and civil engineering work execution plan preparation support program
JP2010066864A (en) * 2008-09-09 2010-03-25 West Nippon Expressway Co Ltd Information provision system of work situation of road block
JP2011175584A (en) * 2010-02-25 2011-09-08 Gear Nouve Co Ltd Construction site management system, server and digital camera
JP2012242981A (en) * 2011-05-18 2012-12-10 Hitachi-Ge Nuclear Energy Ltd Plant construction process generation support system, plant construction process generation support method, and program
JP2013037684A (en) * 2011-07-14 2013-02-21 Riraito:Kk Work information registration device and work information management system
JP2013109740A (en) * 2011-11-21 2013-06-06 Anabuki College Service:Kk Remote quality control system
JP2013134686A (en) * 2011-12-27 2013-07-08 Maeda Corp Process management system, management terminal, and process management method
JP2014157609A (en) * 2014-03-11 2014-08-28 Anabuki College Service:Kk Remote quality control system
JP2015014927A (en) * 2013-07-05 2015-01-22 株式会社ゴッタライド Construction site management system
JP2016006590A (en) * 2014-06-20 2016-01-14 カシオ計算機株式会社 Information processing device and program
JP2016048543A (en) * 2014-07-30 2016-04-07 明豊ファシリティワークス株式会社 Project progress state management system and computer program
JP2017059033A (en) * 2015-09-17 2017-03-23 Spデザイン株式会社 Information sharing system and information processing server
JP2017182313A (en) * 2016-03-29 2017-10-05 前田建設工業株式会社 Step management device, step management method and step management program
JP2017215878A (en) * 2016-06-01 2017-12-07 大成建設株式会社 Construction information management system
CN109716381A (en) * 2016-08-16 2019-05-03 金英大 Construction and maintenance incorporated management method based on video
CN110503285A (en) * 2018-05-19 2019-11-26 福建省禹澄建设工程有限公司 A kind of municipal works management system
JP2019204423A (en) * 2018-05-25 2019-11-28 ホーチキ株式会社 Fire alarm system
CN112204589A (en) * 2018-06-12 2021-01-08 神钢建机株式会社 Construction management system and construction management method
JP2021163367A (en) * 2020-04-02 2021-10-11 大成建設株式会社 Document creation system for construction site
CN113656864A (en) * 2021-07-27 2021-11-16 天一建设发展有限公司 Building construction method and system based on BIM, computer device and storage medium
CN117391341A (en) * 2023-09-28 2024-01-12 中交广州航道局有限公司 Construction progress management system for offshore sand taking and spreading project

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009193381A (en) * 2008-02-14 2009-08-27 Construction Learned Academy Civil engineering work execution plan preparation support system, civil engineering work execution plan preparation support method, and civil engineering work execution plan preparation support program
JP2010066864A (en) * 2008-09-09 2010-03-25 West Nippon Expressway Co Ltd Information provision system of work situation of road block
JP2011175584A (en) * 2010-02-25 2011-09-08 Gear Nouve Co Ltd Construction site management system, server and digital camera
JP2012242981A (en) * 2011-05-18 2012-12-10 Hitachi-Ge Nuclear Energy Ltd Plant construction process generation support system, plant construction process generation support method, and program
JP2013037684A (en) * 2011-07-14 2013-02-21 Riraito:Kk Work information registration device and work information management system
JP2013109740A (en) * 2011-11-21 2013-06-06 Anabuki College Service:Kk Remote quality control system
JP2013134686A (en) * 2011-12-27 2013-07-08 Maeda Corp Process management system, management terminal, and process management method
JP2015014927A (en) * 2013-07-05 2015-01-22 株式会社ゴッタライド Construction site management system
JP2014157609A (en) * 2014-03-11 2014-08-28 Anabuki College Service:Kk Remote quality control system
JP2016006590A (en) * 2014-06-20 2016-01-14 カシオ計算機株式会社 Information processing device and program
JP2016048543A (en) * 2014-07-30 2016-04-07 明豊ファシリティワークス株式会社 Project progress state management system and computer program
JP2017059033A (en) * 2015-09-17 2017-03-23 Spデザイン株式会社 Information sharing system and information processing server
JP2017182313A (en) * 2016-03-29 2017-10-05 前田建設工業株式会社 Step management device, step management method and step management program
JP2017215878A (en) * 2016-06-01 2017-12-07 大成建設株式会社 Construction information management system
CN109716381A (en) * 2016-08-16 2019-05-03 金英大 Construction and maintenance incorporated management method based on video
CN110503285A (en) * 2018-05-19 2019-11-26 福建省禹澄建设工程有限公司 A kind of municipal works management system
JP2019204423A (en) * 2018-05-25 2019-11-28 ホーチキ株式会社 Fire alarm system
JP7213025B2 (en) 2018-05-25 2023-01-26 ホーチキ株式会社 Fire alarm equipment
JP7483065B2 (en) 2018-05-25 2024-05-14 ホーチキ株式会社 Fire alarm system
CN112204589A (en) * 2018-06-12 2021-01-08 神钢建机株式会社 Construction management system and construction management method
JP2021163367A (en) * 2020-04-02 2021-10-11 大成建設株式会社 Document creation system for construction site
JP7373450B2 (en) 2020-04-02 2023-11-02 大成建設株式会社 Form creation system for construction sites
CN113656864A (en) * 2021-07-27 2021-11-16 天一建设发展有限公司 Building construction method and system based on BIM, computer device and storage medium
CN113656864B (en) * 2021-07-27 2023-10-13 天一建设发展有限公司 Building construction method, system, computer device and storage medium based on BIM
CN117391341A (en) * 2023-09-28 2024-01-12 中交广州航道局有限公司 Construction progress management system for offshore sand taking and spreading project

Similar Documents

Publication Publication Date Title
JP2006338561A (en) Construction progress management system
JP5973095B1 (en) Field worker management system
US20210029171A1 (en) Data processing systems and methods for performing privacy assessments and monitoring of new versions of computer code for privacy compliance
JP4157717B2 (en) Print production support device
US20040210470A1 (en) System and method for project management
US20170161248A1 (en) System and Methods for Benefit Eligibility Verification
US20210097475A1 (en) Networked activity management with media collection and selectable activity insertion
JP2013109740A (en) Remote quality control system
JP6278401B2 (en) Electronic manual distribution and progress management system
US20150269588A1 (en) System and method for managing information and coordinating communication between stakeholders regarding rf safety at radio transmission sites
JP2006252241A (en) Housing construction information system
US20040201622A1 (en) Free-form routing of physical and electronic documents
US20080307321A1 (en) Method and system for construction document management and distribution
JP5579946B1 (en) Remote quality control system
JP7388222B2 (en) Information processing system, system, usage restriction method
US8832196B2 (en) System and method for information management
US20190228418A1 (en) Electronic employment document control system with mobile application
CN1908969B (en) Method and system for remote operation in-site engineering data alteration control and management
JP2006277447A (en) Schedule management system, schedule management method, schedule information management device, and terminal device or the like
KR20150028875A (en) Quality management apparatus and method
US20240020655A1 (en) Method and system for tracking assets
JP7129584B1 (en) CONSTRUCTION WORK MANAGEMENT SYSTEM, CONSTRUCTION WORK MANAGEMENT METHOD AND PROGRAM
JP2002290881A (en) Job site video managing system
US20240037468A1 (en) Method of monitoring project process and outcome
JP6288597B2 (en) Electronic manual distribution and progress management system