JP2006326711A - Device for preparing for tool holder changer-operation information - Google Patents

Device for preparing for tool holder changer-operation information Download PDF

Info

Publication number
JP2006326711A
JP2006326711A JP2005150550A JP2005150550A JP2006326711A JP 2006326711 A JP2006326711 A JP 2006326711A JP 2005150550 A JP2005150550 A JP 2005150550A JP 2005150550 A JP2005150550 A JP 2005150550A JP 2006326711 A JP2006326711 A JP 2006326711A
Authority
JP
Japan
Prior art keywords
tool holder
information
tool
magazine
changer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005150550A
Other languages
Japanese (ja)
Inventor
Takashi Senda
孝志 千田
Makoto Totsugi
誠 戸継
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Murata Machinery Ltd
Original Assignee
Murata Machinery Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Murata Machinery Ltd filed Critical Murata Machinery Ltd
Priority to JP2005150550A priority Critical patent/JP2006326711A/en
Publication of JP2006326711A publication Critical patent/JP2006326711A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To prepare efficient carrying-in/out operation information for carrying out tool holders required for early tool preparations to a tool holder magazine at the outside of a working machine by placing in the working machine the tool holders required early in the working machine. <P>SOLUTION: This information preparing device is provided with a ranking means 51 and a changer-operation information-preparing means 52. The ranking means 51 gives ranking information F5 for determining whether each tool holder 7 is placed on the working machine 1 side or on the tool holder magazine 6 side at the outside of the working machine according to a prescribed ranking reference R1 from use tool holder information F1 classified by schedules and plan schedule information FO including the executing order. A changer-operation information-preparing means 52 prepares a changer operation F6 from information 3 and 4 on the tool holders 7 possessed by each of the working machine 1 and the tool holder magazine 6 at the outside of the working machine at present, the plan schedule information F0 and the ranking information F5. The operation information F6 includes which of the tool holders 7 (T01, T02) is carried from the tool holder magazine 6 at the outside of the working machine to the working machine 1 and which of the tool holders 7 (T01, T02) is carried out. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

この発明は、パンチプレス等の板材加工機や、その他の加工機に対して、タレット等の工具ホルダを交換する工具ホルダチェンジャーの搬入搬出の動作情報を作成する工具ホルダチェンジャー動作情報作成装置に関する。   The present invention relates to a tool holder changer operation information creation device for creating operation information of loading and unloading of a tool holder changer for exchanging a tool holder such as a turret for a plate material processing machine such as a punch press and other processing machines.

従来、複数の工具を交換使用可能としたパンチプレスとして、タレット式のものが一般的である。しかし、タレットパンチプレスでは、タレット内に保持できるパンチ工具の種類が限られ、多彩な加工が行えない。
このような課題を解消するものとして、複数のパンチ工具を搭載したタレット形式の工具ホルダを、旋回可能な工具ホルダマガジンの円周方向複数箇所に着脱自在に保持するマルチタレット形式のものが提案されている(例えば、特許文献1)。これは、工具ホルダマガジンの旋回により、希望の工具ホルダを所定の加工位置に割出し、その割り出された工具ホルダを旋回させて工具ホルダ中の希望のパンチ工具をパンチ加工に用いるものである。
Conventionally, a turret type is generally used as a punch press capable of replacing a plurality of tools. However, in the turret punch press, the types of punch tools that can be held in the turret are limited, and various processes cannot be performed.
In order to solve such problems, a multi-turret type tool holder has been proposed in which a turret type tool holder equipped with a plurality of punch tools is detachably held at a plurality of circumferential positions of a rotatable tool holder magazine. (For example, Patent Document 1). In this method, a desired tool holder is indexed to a predetermined processing position by turning the tool holder magazine, and the determined tool holder is turned to use the desired punch tool in the tool holder for punching. .

この形式のパンチプレスは、複数のパンチ工具を搭載する工具ホルダが工具ホルダマガジンに対して交換自在であるため、工具ホルダマガジンの外部に工具ホルダを準備しておき、その工具ホルダを工具ホルダマガジンの工具ホルダと交換することで多数のパンチ工具の使用が可能になる。
また、加工位置に割り出された同じ工具ホルダに搭載されたパンチ工具を使用するときは、工具ホルダマガジン等に比べて小さくて軽量の工具ホルダを旋回させれば良いため、工具割出の時間が短縮でき、効率の良いパンチ加工が行える。
特開2004−237331号公報
In this type of punch press, the tool holder on which a plurality of punch tools are mounted is replaceable with respect to the tool holder magazine. Therefore, a tool holder is prepared outside the tool holder magazine, and the tool holder is attached to the tool holder magazine. Many punch tools can be used by exchanging the tool holder.
Also, when using a punch tool mounted on the same tool holder that is indexed at the machining position, it is only necessary to rotate a tool holder that is smaller and lighter than the tool holder magazine, etc. Can be shortened and efficient punching can be performed.
JP 2004-237331 A

上記マルチタレット形式のパンチプレスは、機内の工具ホルダマガジンに対する工具ホルダの交換装置を備えているが、交換装置までの工具ホルダの運搬は手作業で行う必要があり、効率的ではない。そのため、機内工具ホルダマガジンとは別に、機外工具ホルダマガジン設け、この機外工具ホルダマガジンと機内工具ホルダマガジンとの間で工具ホルダを自動交換する工具ホルダチェンジャーを備えた加工設備を考えた。
しかし、より一層の加工効率の向上のためには、機内工具ホルダマガジンに対する工具ホルダの搬入,搬出を効率的に行う必要があり、その制御形式に工夫が必要となる。
The multi-turret type punch press includes a tool holder exchanging device with respect to an in-machine tool holder magazine. However, it is necessary to carry the tool holder to the exchanging device by hand, which is not efficient. For this reason, a machining facility provided with a tool holder changer provided separately from the in-machine tool holder magazine and provided with an out-of-machine tool holder magazine and automatically changing the tool holder between the out-of-machine tool holder magazine and the in-machine tool holder magazine.
However, in order to further improve the processing efficiency, it is necessary to efficiently carry in and out the tool holder with respect to the in-machine tool holder magazine, and it is necessary to devise the control format.

例えば、従来の工具ホルダチェンジャーを備えた工作機械では、工作機械と工具ホルダチェンジャーとを単一の同じ加工プログラムで制御するものが一般的である。しかし、単一の加工プログラムで上記マルチタレット形式のパンチプレスおよび工具ホルダチェンジャーを制御しようとした場合、パンチプレスで機内に備えていない工具ホルダが必要となったときに、工具ホルダの交換動作を行うことになる。その場合、工具ホルダチェンジャーは、不要な工具ホルダを搬出し、機外工具ホルダマガジンから必要な工具ホルダを搬送してパンチプレスに搬入する一連の動作時間が、加工時間とは別に必要となり、全体の時間が長くかかる。そのため生産性が低下する。   For example, in a machine tool provided with a conventional tool holder changer, a machine tool and a tool holder changer are generally controlled by a single same machining program. However, when trying to control the multi-turret type punch press and tool holder changer with a single machining program, when a tool holder that is not equipped in the machine is required by the punch press, the tool holder can be replaced. Will do. In that case, the tool holder changer requires a series of operation time for unloading the unnecessary tool holder, transporting the necessary tool holder from the external tool holder magazine, and loading it into the punch press. Takes a long time. Therefore, productivity is reduced.

そのため、先の加工スケジュールを考慮して搬入搬出や、工具ホルダに対する工具交換の段取り少ない工具ホルダ搬入搬出の情報を作成することが望まれる。しかし、加工プログラムの工具情報から、効率良い工具ホルダの搬入搬出を人が考えるのは、困難である。また、加工機に保有する工具ホルダは、一つの加工スケジュルーの終了の都度変わるため、人が工具ホルダの搬入搬出の情報を作成するのでは、機械に付きっきりで居ることが必要となり、自動機の場合は不可能である。
そのため、搬入搬出の動作情報を自動で作成することが望まれるが、効率の良い搬入搬出が行える動作情報を作成するための適切な手法の設定が難しい。
For this reason, it is desirable to create information on loading / unloading of the tool holder in consideration of the previous machining schedule, and with less setup for tool replacement with respect to the tool holder. However, it is difficult for a person to consider efficient loading and unloading of the tool holder from the tool information of the machining program. In addition, since the tool holder held in the processing machine changes each time one processing schedule ends, it is necessary for a person to be in the machine to create information on loading and unloading of the tool holder. The case is impossible.
For this reason, it is desirable to automatically create operation information for loading / unloading, but it is difficult to set an appropriate method for creating operation information that enables efficient loading / unloading.

上記の課題は、加工機がマルチタレット形式のパンチプレスである場合につき説明したが、パンチプレス以外であっても、複数の個別工具を搭載した工具ホルダを交換可能に装備する加工機と工具ホルダチェンジャーとを備える加工設備一般において、上記の課題が生じる。   The above-mentioned problem has been described when the processing machine is a multi-turret type punch press. However, even if the processing machine is other than a punch press, a processing machine and a tool holder equipped with a tool holder on which a plurality of individual tools are mounted in an exchangeable manner. In general processing equipment including a changer, the above problem occurs.

この発明の目的は、加工機で早く必要な工具ホルダは加工機に留めておき、早く工具段取りが必要な工具ホルダは機外工具ホルダマガジンに搬出することのできる効率的な搬入搬出の動作情報が作成できる工具ホルダチェンジャー動作情報作成装置を提供することである。   An object of the present invention is to provide an efficient loading / unloading operation information in which a tool holder required early in a processing machine can be fastened to the processing machine, and a tool holder requiring tool setup quickly can be carried out to an external tool holder magazine. Is to provide a tool holder changer operation information creation device.

この発明の構成を実施形態に対応する図5と共に説明する。この発明の工具ホルダチェンジャー動作情報作成装置(50)は、工具(8)を搭載した複数の工具ホルダ(7)を交換可能に装備する加工機(1)と、この加工機(1)外の工具ホルダ(7)を保管する機外工具ホルダマガジン(6)との間で工具ホルダ(7)を自動交換する工具ホルダチェンジャー(3)の動作情報(F6)を作成する工具ホルダチェンジャー動作情報作成装置であって、格付け手段(51)とチェンジャー動作情報作成手段(52)とを備える。
格付け手段(51)は、一連の加工を行う加工単位である加工スケジュール(Sch )で前記加工機(1)が用いる工具ホルダ(7)の識別番号(T01,T02,…,TM11,…)の情報を使用順に含むスケジュール別使用工具ホルダ情報(F1)、および加工スケジュール(Sch )の実行順を設定した実行順情報(F2)を含む計画スケジュール情報(F0)を用いて、所定の格付け基準(R1)に従い、各工具ホルダ(7)につき加工機(1)側に置くか機外工具ホルダマガジン(6)側に置くかの判別のための格付け情報(F5)を付す手段である。
チェンジャー動作情報作成手段(52)は、加工機(1)および機外工具ホルダマガジン(6)がそれぞれ現在保有する工具ホルダの情報(F3,F4)、前記計画スケジュール情報(F0)、および各工具ホルダ(7)の前記格付け情報(F5)から、前記工具ホルダチェンジャー(3)の動作情報(F6)として、どの工具ホルダ(7)を機外工具ホルダマガジン(6)から加工機(1)へ搬入させ、どの工具ホルダ(7)を加工機(1)から機外工具ホルダマガジン(6)へ搬出させるかの搬入搬出の情報(F6)を作成する手段である。
The configuration of the present invention will be described with reference to FIG. 5 corresponding to the embodiment. The tool holder changer operation information creation device (50) of the present invention includes a processing machine (1) equipped with a plurality of tool holders (7) on which a tool (8) is mounted in an exchangeable manner, and an outside of the processing machine (1). Tool holder changer operation information creation for creating operation information (F6) of the tool holder changer (3) for automatically exchanging the tool holder (7) with the external tool holder magazine (6) for storing the tool holder (7) An apparatus comprising a rating means (51) and a changer operation information creating means (52).
The rating means (51) is an identification number (T01, T02,..., TM11,...) Of the tool holder (7) used by the processing machine (1) in a processing schedule (Sch) that is a processing unit for performing a series of processing. By using the scheduled tool holder information (F1) including the information in the order of use and the plan schedule information (F0) including the execution order information (F2) in which the execution order of the machining schedule (Sch) is set, a predetermined rating standard ( According to R1), each tool holder (7) is provided with rating information (F5) for determining whether to place it on the processing machine (1) side or on the outside tool holder magazine (6) side.
The changer operation information creation means (52) includes tool holder information (F3, F4) currently held by the processing machine (1) and the external tool holder magazine (6), the schedule information (F0), and each tool. From the rating information (F5) of the holder (7), as the operation information (F6) of the tool holder changer (3), which tool holder (7) is transferred from the external tool holder magazine (6) to the processing machine (1). It is means for creating loading / unloading information (F6) which is loaded and which tool holder (7) is unloaded from the processing machine (1) to the external tool holder magazine (6).

この構成の工具ホルダチェンジャー動作情報作成装置(50)によると、格付け手段(51)により、スケジュール別使用工具ホルダ情報(F1)、および加工スケジュール(Sch )の実行順を設定した実行順情報(F2)を含む計画スケジュール情報情報(F0)から、所定の格付け基準(R1)に従い、各工具ホルダ(7)につき加工機(1)側に置くか機外工具ホルダマガジン(7)側に置くかの判別のための格付け情報(F5)を付す。スケジュール別使用工具ホルダ情報(F0)は、加工機(1)を制御する加工プログラム(36)であっても、また加工プログラム(36)から必要情報を抽出した情報、あるいは加工プログラム(36)とは別に準備された情報であっても良い。このスケジュール別使用工具ホルダ情報(F1)は、例えば、加工プログラム(36)を先読みすること等で得られる。計画スケジュール情報情報(F0)は、現在以降の情報で良い。
チェンジャー動作情報作成手段(52)は、加工機(1)および機外工具ホルダマガジン(6)がそれぞれ現在保有する工具ホルダ(7)の情報(F3,F4)と、記計画スケジュール情報(F0)の現在以降の情報とを比較することで、搬入または搬出すべき工具ホルダ(7)を判別する。このとき、加工機(1)および機外工具ホルダマガジン(6)に保有できる工具ホルダ(7)の個数は限られているため、工具ホルダ(7)の搬入または搬出数が限られることがある。また、必ずしも加工機(1)内に工具ホルダを満杯にする必要はなく、工具ホルダ(7)を機外に出しておく方が好ましい場合もある。この場合に、どの工具ホルダ(7)を搬出しまたは搬入するかを選択することが必要となる。この選択を、上記格付け情報(F5)に従って行う。
このように、各工具ホルダ(7)につき加工機(1)側に置くか機外工具ホルダマガジン(6)側に置くかの判別のための格付け情報(F5)を付しておくため、その格付けのための格付け基準(R1)を適切に定めておくことで、無駄な搬入搬出を削減でき、また早期に機外に搬出して工具ホルダ(1)に対する手作業による工具交換の段取りを加工中に行えるようにするなど、効率の良い搬入搬出のチェンジャー動作情報(F6)を作成することができる。
According to the tool holder changer operation information creation device (50) having this configuration, the ranking means (51) executes the execution order information (F2) in which the execution tool execution information (F1) by schedule and the execution order of the machining schedule (Sch) are set. ) Including schedule schedule information (F0) including whether each tool holder (7) is placed on the processing machine (1) side or on the outside tool holder magazine (7) side according to a predetermined rating standard (R1) Rating information (F5) for determination is attached. The use tool holder information (F0) by schedule is a machining program (36) for controlling the machining machine (1), information obtained by extracting necessary information from the machining program (36), or a machining program (36). May be information prepared separately. This schedule use tool holder information (F1) is obtained, for example, by pre-reading the machining program (36). The plan schedule information information (F0) may be information after the present.
The changer operation information creation means (52) includes information (F3, F4) on the tool holder (7) currently held by the processing machine (1) and the external tool holder magazine (6), and the schedule information (F0). The tool holder (7) to be carried in or out is discriminated by comparing with the information after the present. At this time, since the number of tool holders (7) that can be held in the processing machine (1) and the external tool holder magazine (6) is limited, the number of tool holders (7) that are carried in or out may be limited. . Moreover, it is not always necessary to fill the tool holder in the processing machine (1), and it may be preferable to leave the tool holder (7) outside the machine. In this case, it is necessary to select which tool holder (7) to carry out or carry in. This selection is performed according to the rating information (F5).
In this way, each tool holder (7) is assigned rating information (F5) for determining whether to place it on the processing machine (1) side or on the outside tool holder magazine (6) side. By appropriately setting the rating standard (R1) for rating, wasteful loading / unloading can be reduced, and the tool holder (1) can be removed from the machine at an early stage and processed for manual tool change setup. Efficient loading / unloading changer operation information (F6) can be created.

この発明において、前記加工機(1)または機外工具ホルダマガジン(6)の保有する少なくとも一つの工具ホルダ(7)が、複数の工具(8)を交換可能に搭載したものであってあっても良い。その場合、前記格付け手段(51)は、前記計画スケジュール情報(F0)、並びに加工機(1)および機外工具ホルダマガジン(6)がそれぞれ現在保有する工具ホルダ(7)の情報(F3,F4)から、直後の加工スケジュール(Sch )で使用する工具ホルダ(7)、および計画スケジュール(F0)で使用されるが工具ホルダ(7)の搭載工具を変更する段取りのない工具ホルダを加工機(1)側へ置く格付けとし、段取りがあり直後の加工スケジュール(Sch )では使用されない工具ホルダ(7)を機外工具ホルダマガジン(1)側へ置く格付けとするものとしても良い。   In the present invention, at least one tool holder (7) possessed by the processing machine (1) or the external tool holder magazine (6) has a plurality of tools (8) mounted thereon in a replaceable manner. Also good. In this case, the rating means (51) includes the schedule information (F0) and information (F3, F4) of the tool holder (7) currently held by the processing machine (1) and the external tool holder magazine (6). ) To a tool holder (7) used in the immediately following machining schedule (Sch) and a tool holder that is used in the planning schedule (F0) but has no setup to change the tool mounted on the tool holder (7) ( The rating may be placed on the 1) side, and the tool holder (7) that is set up and not used in the machining schedule (Sch) immediately after the setup may be placed on the external tool holder magazine (1) side.

工具ホルダ(7)が複数の工具(8)を交換可能に搭載したものである場合、工具ホルダ(7)に対する工具交換の段取りを機外で行うことになる。格付け手段(51)は、計画スケジュール情報(F0)、および加工機(1)および機外工具ホルダマガジン(6)が現在保有する工具ホルダ(7)の情報(F3,F4)を用いることで、段取りの有無が判定できる。
この場合に、格付け手段(51)は、段取りのない工具ホルダ(7)を加工機(1)側へ置き、段取りのある工具ホルダ(7)は機外工具ホルダマガジン(6)側へ置く判定を行うため、段取りのある工具ホルダ(7)は、早く機外工具ホルダマガジン(6)へ搬出することができて、機外での作業者等による工具交換の段取り作業を、加工機(1)の加工中に行うことができ、機械を止めて行う段取りの時間が短縮される。また、直後の加工スケジュール(Sch )で使用する工具ホルダ(7)は、加工機(1)側へ置く格付けを行うため、直後の加工で必要な工具ホルダ(7)は、加工機(1)に留めておくか、または加工機(1)へ搬入されることになり、直後の加工に必要な工具ホルダ(7)を機内に備えておくことができる。
When the tool holder (7) has a plurality of tools (8) mounted so as to be replaceable, the tool replacement for the tool holder (7) is performed outside the machine. The rating means (51) uses the plan schedule information (F0) and the information (F3, F4) of the tool holder (7) currently held by the processing machine (1) and the external tool holder magazine (6), The presence or absence of setup can be determined.
In this case, the rating means (51) determines that the tool holder (7) without setup is placed on the processing machine (1) side, and the tool holder (7) with setup is placed on the outside tool holder magazine (6) side. Therefore, the tool holder (7) having the setup can be quickly carried out to the outside tool holder magazine (6), and the setup work for the tool change by an operator outside the machine can be performed by the processing machine (1). ) Can be carried out during the machining of the machine, and the setup time to be done by stopping the machine is shortened. Further, since the tool holder (7) used in the immediately following machining schedule (Sch) is placed on the machine (1) side, the tool holder (7) necessary for the immediately following machining is the machine (1). Or a tool holder (7) necessary for the immediately subsequent machining can be provided in the machine.

また、この発明の工具ホルダチェンジャー動作情報作成装置(50)は、加工機(1)による加工スケジュール(Sch )の実行毎に、前記格付け手段(51)による格付け、および前記チェンジャー動作情報作成手段(52)による工具ホルダチェンジャー(3)の動作情報(F6)の作成を行うものとしても良い。
加工スケジュール(Sch )が実行される毎に、加工機(1)の保有する工具ホルダ(7)が変わる可能性がある。そのため、加工スケジュール(Sch )が実行される毎に、格付けおよびその格付けに基づく工具ホルダ(7)の搬入搬出の情報(F6)を作成することで、より効率の良い工具ホルダ(7)の搬入搬出が行える。
Further, the tool holder changer operation information creation device (50) of the present invention provides a rating by the rating means (51) and a changer operation information creation means (for each execution of a machining schedule (Sch) by the machine (1). The operation information (F6) of the tool holder changer (3) according to 52) may be created.
Each time the machining schedule (Sch) is executed, the tool holder (7) held by the machining machine (1) may change. Therefore, each time the machining schedule (Sch 2) is executed, a more efficient loading of the tool holder (7) can be performed by creating a rating and information (F 6) of loading / unloading of the tool holder (7) based on the rating. Can be carried out.

この発明の工具ホルダチェンジャー動作情報作成装置は、工具を搭載した複数の工具ホルダを交換可能に装備する加工機と、この加工機外の工具ホルダを保管する機外工具ホルダマガジンとの間で工具ホルダを自動交換する工具ホルダチェンジャーの動作情報を作成する工具ホルダチェンジャー動作情報作成装置であって、一連の加工を行う加工単位である加工スケジュールで前記加工機が用いる工具ホルダの識別番号の情報を使用順に含むスケジュール別使用工具ホルダ情報、および加工スケジュールの実行順を設定した実行順情報を含む計画スケジュール情報を用いて、所定の格付け基準に従い、各工具ホルダにつき加工機側に置くか機外工具ホルダマガジン側に置くかの判別のための格付け情報を付す格付け手段と、加工機および機外工具ホルダマガジンがそれぞれ現在保有する工具ホルダの情報、前記計画スケジュール情報、および各工具ホルダの前記各付け情報から、前記工具ホルダチェンジャーの動作情報として、どの工具ホルダを機外工具ホルダマガジンから加工機へ搬入させ、どの工具ホルダを加工機から機外工具ホルダマガジンへ搬出させるかの搬入搬出の情報を作成するチェンジャー動作情報作成手段、とを備えたものであるため、加工機で早く必要な工具ホルダは加工機に留めておき、早く工具段取りが必要な工具ホルダは機外工具ホルダマガジンに搬出することのできる効率的な搬入搬出の動作情報が作成できる。   The tool holder changer operation information creation device according to the present invention provides a tool between a processing machine equipped with a plurality of tool holders on which a tool is mounted in an exchangeable manner and an external tool holder magazine for storing the tool holder outside the processing machine. A tool holder changer operation information creation device for creating operation information of a tool holder changer for automatically changing a holder, and information on an identification number of a tool holder used by the processing machine in a processing schedule which is a processing unit for performing a series of processing. Use tool holder information by schedule including order of use, and plan schedule information including execution order information that sets the execution order of machining schedules, and place each tool holder on the machine side or an external tool according to a predetermined rating standard Rating means for assigning rating information for determining whether to place on the holder magazine side, processing machine and outside From the information on the tool holders currently held by the tool holder magazine, the schedule information, and the attachment information of each tool holder, as the operation information of the tool holder changer, which tool holder is processed from the external tool holder magazine Changer operation information creating means for creating information on loading / unloading of which tool holder is loaded from the processing machine to the external tool holder magazine. By holding the holder on the processing machine, it is possible to create efficient loading / unloading operation information that enables a tool holder that requires quick tool setup to be carried out to an outside tool holder magazine.

前記加工機または機外工具ホルダマガジンの保有する少なくとも一つの工具ホルダが、複数の工具を交換可能に搭載したものであり、前記格付け手段は、前記計画スケジュール情報、並びに加工機および機外工具ホルダマガジンがそれぞれ現在保有する工具ホルダの情報から、直後の加工スケジュールで使用する工具ホルダ、および計画スケジュールで使用されるが工具ホルダの搭載工具を変更する段取りのない工具ホルダを加工機側へ置く格付けとし、段取りがあり直後の加工スケジュールでは使用されない工具ホルダを機外工具ホルダマガジン側へ置く格付けとするものとした場合は、工具ホルダが複数の工具を搭載したものであって、その搭載工具を交換する段取りが必要な場合に、効率的な搬入搬出の動作情報が作成できる。   The at least one tool holder possessed by the processing machine or the external tool holder magazine is configured such that a plurality of tools can be exchanged, and the rating means includes the plan schedule information, the processing machine, and the external tool holder. Based on the information on the tool holders currently held by each magazine, the tool holder used in the next machining schedule and the tool holder that is used in the planning schedule but has no setup to change the tool holder's loaded tool are placed on the machine side. If the tool holder that is not used in the machining schedule immediately after setup is placed on the external tool holder magazine side, the tool holder is equipped with multiple tools, and Efficient loading / unloading operation information can be created when setup for replacement is required.

加工機による加工スケジュールの実行毎に前記格付け手段による前記格付け、および前記チェンジャー動作情報作成手段による工具ホルダチェンジャーの動作情報の作成を行うものとした場合は、加工スケジュールの実行毎に変わる加工機の工具ホルダ搭載状況に応じて、より効率的な搬入搬出の動作情報が作成できる。   When the rating by the rating unit and the operation information of the tool holder changer by the changer operation information creation unit are created each time the machining schedule is executed by the processing machine, the processing machine changes each time the machining schedule is executed. More efficient loading / unloading operation information can be created according to the tool holder mounting status.

この発明の一実施形態を図1ないし図9と共に説明する。図1は、制御対象となるチェンジャー付き加工設備の平面図である。この加工設備は、加工機であるパンチプレス1と、プリセッター2と、工具ホルダチェンジャー3と、ローダ4とを備える。パンチプレス1は、機内工具ホルダマガジン5を備え、個別工具8を搭載した複数の工具ホルダ7を、機内工具ホルダマガジン5に交換可能に装備するものである。工具ホルダチェンジャー3は、パンチプレス1およびプリセッター2にそれぞれ設けられた機内工具ホルダマガジン5および機外工具ホルダマガジン6の間で工具ホルダ7を自動交換する装置である。   An embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a plan view of a processing facility with a changer to be controlled. This processing equipment includes a punch press 1, which is a processing machine, a presetter 2, a tool holder changer 3, and a loader 4. The punch press 1 includes an in-machine tool holder magazine 5 and is equipped with a plurality of tool holders 7 on which individual tools 8 are mounted so as to be replaceable in the in-machine tool holder magazine 5. The tool holder changer 3 is a device for automatically exchanging the tool holder 7 between an in-machine tool holder magazine 5 and an out-of-machine tool holder magazine 6 provided in the punch press 1 and the presetter 2, respectively.

工具ホルダ7は、図3に示すように、平面形状が円形のタレットであり、一つまたは複数の個別工具8が搭載される。個別工具8は、工具ホルダ7に設けられた貫通孔等からなる工具支持部7a内に、交換自在に搭載される。個別工具8は、パンチ工具またはダイ工具である。パンチ工具およびダイ工具は、上下に対として用いられるものであり、工具ホルダ7は、パンチ工具用のものとダイ工具用のものとが、上下に対として設けられる。図では、パンチ工具用の工具ホルダ7のみを示し、ダイ工具用の工具ホルダは、図示を省略している。   As shown in FIG. 3, the tool holder 7 is a turret having a circular planar shape, and one or a plurality of individual tools 8 are mounted thereon. The individual tool 8 is exchangeably mounted in a tool support portion 7a formed of a through hole or the like provided in the tool holder 7. The individual tool 8 is a punch tool or a die tool. The punch tool and the die tool are used as a pair in the vertical direction, and the tool holder 7 is provided with a punch tool and a die tool as a pair in the vertical direction. In the figure, only the tool holder 7 for the punch tool is shown, and the tool holder for the die tool is not shown.

個別工具8は、パンチ加工する孔形状や寸法が種々異なるものがあり、工具ホルダ7に設けられた複数の工具支持部7aには、それぞれ異なる孔形状,寸法の加工用のものが搭載される。
また、工具ホルダ7は、図2のように工具支持部7aの個数,配置,寸法等の種々異なる複数種類のものが準備される。同じ工具支持部7aに、外径寸法の合う複数種類の個別工具8の搭載が可能であり、各種類の工具ホルダ7の工具支持部7aに、適合可能な任意の個別工具8を搭載して工具ホルダ7の工具編成が行われる。
The individual tools 8 have various shapes and sizes of holes to be punched, and a plurality of tool support portions 7a provided in the tool holder 7 are mounted with processing tools having different hole shapes and sizes, respectively. .
Further, as shown in FIG. 2, a plurality of types of tool holders 7 different in the number, arrangement, dimensions, etc. of the tool support portions 7a are prepared. A plurality of types of individual tools 8 having the same outer diameter can be mounted on the same tool support portion 7a, and any applicable individual tool 8 can be mounted on the tool support portion 7a of each type of tool holder 7. Tool knitting of the tool holder 7 is performed.

機内工具ホルダマガジン5は、水平旋回自在に設けられ、外周部の円周方向複数箇所に、工具ホルダ7を着脱自在に保持する工具ホルダ保持部5aが設けられている。各工具ホルダ保持部5aは、制御上でアドレスM1〜M8が付される。機内工具ホルダマガジン5は、上下に一対のものが同心に設けられ、それぞれパンチ側およびダイ側の工具ホルダ7を保持して同期して旋回するが、図では上側の機内工具ホルダマガジン5のみを示している。   The in-machine tool holder magazine 5 is provided so as to be able to turn horizontally, and a tool holder holding portion 5a for holding the tool holder 7 in a detachable manner is provided at a plurality of locations in the circumferential direction of the outer peripheral portion. Each tool holder holding portion 5a is assigned addresses M1 to M8 for control. The in-machine tool holder magazine 5 is provided with a pair of upper and lower concentric ones, and holds the punch-side and die-side tool holders 7 and rotates in synchronization, but in the figure, only the upper in-machine tool holder magazine 5 is shown. Show.

図1において、パンチプレス1は、工具割出機構として、マガジン割出部と工具ホルダ割出部(いずれも図示せず)とを有する。マガジン割出部は、機内工具ホルダマガジン5の任意の工具ホルダ保持部5aが所定のプレスヘッド位置Qに来るように機内工具ホルダマガジン5を旋回させる機構である。工具ホルダ割出部は、プレスヘッド位置Qにある工具ホルダ7を保持してその工具ホルダ中心回りに旋回させ、工具ホルダ7の任意の個別工具8を所定のパンチ位置Pに割出す機構である。
パンチ位置Pに割り出された個別工具8は、サーボモータ等のパンチ駆動原により、昇降自在なラムを介してパンチ加工のための昇降動作が与えられる。
In FIG. 1, the punch press 1 has a magazine indexing part and a tool holder indexing part (both not shown) as a tool indexing mechanism. The magazine indexing unit is a mechanism for rotating the in-machine tool holder magazine 5 so that an arbitrary tool holder holding part 5a of the in-machine tool holder magazine 5 comes to a predetermined press head position Q. The tool holder indexing unit is a mechanism that holds the tool holder 7 at the press head position Q and rotates it around the center of the tool holder to index an arbitrary individual tool 8 of the tool holder 7 to a predetermined punch position P. .
The individual tool 8 indexed at the punch position P is given a lifting operation for punching by a punch driving source such as a servo motor through a freely movable ram.

パンチプレス1は、テーブル9上の板材Wを直交2軸(X軸,Y軸)方向に移動させる板材送り機構10を有しており、その移動により、板材Wの加工すべき箇所がパンチ位置Pへ移動させられる。板材送り機構10は、Y軸方向に進退するキャリッジ11に、X軸方向に進退可能にクロススライド12を搭載し、板材Wの端部を把持する複数のワークホルダ13を、クロススライド12に取付けたものである。   The punch press 1 has a plate material feeding mechanism 10 that moves the plate material W on the table 9 in the directions of two orthogonal axes (X axis, Y axis). Moved to P. The plate material feeding mechanism 10 has a cross slide 12 mounted on a carriage 11 that moves forward and backward in the Y-axis direction so as to be able to move forward and backward in the X-axis direction, and a plurality of work holders 13 that grip the end portions of the plate material W It is a thing.

ローダ4は、所定の板材載置部14に積載された板材Wを、一枚ずつ吸着等により把持してパンチプレス1のテーブル9上に供給する装置である。ローダ4は、架設レール15上を走行する走行体16に、板材Wを把持する吸着パッド(図示せず)を備えている。   The loader 4 is a device that grips the sheet material W loaded on a predetermined sheet material mounting unit 14 one by one by suction or the like and supplies it onto the table 9 of the punch press 1. The loader 4 includes a suction pad (not shown) that grips the plate material W on the traveling body 16 that travels on the installation rail 15.

プリセッタ2は、機外工具ホルダマガジン6を旋回割出可能に設置したものであり、パンチプレス1の背後に設置されている。プリセッタ2には、機外工具ホルダマガジン6に対して作業者が工具ホルダ7の交換を行うための段取り用交換部17が設けられている。 機外工具ホルダマガジン6は、機内工具ホルダマガジン5と同様に水平旋回自在に設けられ、外周部の円周方向複数箇所に、工具ホルダ7を着脱自在に保持する工具ホルダ保持部6aが設けられている。機外工具ホルダマガジン6も、パンチ工具搭載の工具ホルダ7用のものと、ダイ工具搭載の工具ホルダ7用のものとが、上下に同心に設置され、旋回割出の駆動がマガジン割出手段(図示せず)で行われる。   The pre-setter 2 is provided so that the external tool holder magazine 6 can be pivotally indexed, and is installed behind the punch press 1. The presetter 2 is provided with a setup changer 17 for an operator to change the tool holder 7 with respect to the external tool holder magazine 6. The out-of-machine tool holder magazine 6 is provided so as to be able to turn horizontally similarly to the in-machine tool holder magazine 5, and a tool holder holding portion 6 a for detachably holding the tool holder 7 is provided at a plurality of locations in the circumferential direction of the outer peripheral portion. ing. As for the external tool holder magazine 6, the one for the tool holder 7 equipped with the punch tool and the one for the tool holder 7 equipped with the die tool are installed concentrically up and down, and the rotation index drive is the magazine indexing means. (Not shown).

工具ホルダチェンジャー3は、パンチプレス1の機内工具ホルダマガジン5と、機外工具ホルダマガジン6との間で工具ホルダ7を交換する装置であり、これらマガジン工具5,6の所定の交換用割出位置R,Sで交換を行う。
工具ホルダチェンジャー3は、これら機内工具ホルダマガジン5と機外工具ホルダマガジン6の交換用割出位置R,Sに渡って設けられたガイドレール21と、このガイドレール21に沿って走行する走行体22とを備える。走行体22は、それぞれ工具ホルダ7を保持する2つのチャック23,24が走行方向に並んで設けられている。これら2つのチャック23,24は、いずれか片方のチャック23,24で交換用の工具ホルダ7を保持しておき、空の方のチャック23,24で工具ホルダマガジン5,6から工具ホルダ7を受け取り、上記片方のチャック23,24で保持していた交換用の工具ホルダ7を工具ホルダマガジン5,6に渡す動作を行う。これにより、走行体22の両工具ホルダマガジン5,6間の一度の走行で工具ホルダ7の交換が行える。
The tool holder changer 3 is a device for exchanging the tool holder 7 between the in-machine tool holder magazine 5 of the punch press 1 and the out-of-machine tool holder magazine 6. Exchange at positions R and S.
The tool holder changer 3 includes a guide rail 21 provided over replacement index positions R and S of the in-machine tool holder magazine 5 and the out-of-machine tool holder magazine 6, and a traveling body that travels along the guide rail 21. 22. The traveling body 22 is provided with two chucks 23 and 24 each holding the tool holder 7 side by side in the traveling direction. These two chucks 23 and 24 hold the replacement tool holder 7 with either one of the chucks 23 and 24, and the empty chucks 23 and 24 remove the tool holder 7 from the tool holder magazines 5 and 6. An operation of receiving and transferring the replacement tool holder 7 held by the one chucks 23 and 24 to the tool holder magazines 5 and 6 is performed. As a result, the tool holder 7 can be replaced by a single travel between the tool holder magazines 5 and 6 of the traveling body 22.

なお、走行体22は、チャック23,24を1個のみとし、交換用割出位置R,Sの付近に設けた仮置き台(図示せず)に、交換用の工具ホルダ7を仮置きすることによっても、一度の走行で工具ホルダ7の交換が行える。
また走行体22に設けられる上記チャック23,24は、いずれも各工具ホルダマガジン5,6と同じく、パンチ工具搭載の工具ホルダ7用のものと、ダイ工具搭載の工具ホルダ7用のものとが、上下に並んで設けられている。
The traveling body 22 has only one chuck 23, 24, and temporarily places the replacement tool holder 7 on a temporary placement stand (not shown) provided near the replacement index positions R, S. In this way, the tool holder 7 can be exchanged in a single run.
Also, the chucks 23 and 24 provided on the traveling body 22 are the same as the tool holder magazines 5 and 6, respectively, for the tool holder 7 mounted with the punch tool and for the tool holder 7 mounted with the die tool. , Provided side by side.

つぎに制御系につき説明する。図4に示すように、加工機であるパンチプレス1は加工機制御装置31により、工具ホルダチェンジャー3はチェンジャー制御装置32により、またローダ4はローダ制御装置33によりそれぞれ制御される。加工機制御装置31は、加工プログラム36に従って制御するものであり、チェンジャー制御装置32およびローダ制御装置33は、それぞれ加工プログラム36とは別のプログラムによって制御されるものとしてしている。
加工機制御装置31、チェンジャー制御装置32、およびローダ制御装置33は、物理的には同じコンピュータ等に構成されたものであっても良く、また別のコンピュータ等で構成されたものであっても良い。これら加工機制御装置31、チェンジャー制御装置32、およびローダ制御装置33は、共通の操作盤46によって操作される。
Next, the control system will be described. As shown in FIG. 4, the punch press 1 as a processing machine is controlled by a processing machine control device 31, the tool holder changer 3 is controlled by a changer control device 32, and the loader 4 is controlled by a loader control device 33. The processing machine control device 31 is controlled according to the processing program 36, and the changer control device 32 and the loader control device 33 are controlled by a program different from the processing program 36, respectively.
The processing machine control device 31, the changer control device 32, and the loader control device 33 may be physically configured by the same computer or the like, or may be configured by another computer or the like. good. These processing machine control device 31, changer control device 32, and loader control device 33 are operated by a common operation panel 46.

また、パンチプレス1の近傍には、スケジュール作成装置34が設けられ、上記操作盤46で操作が可能とされている。スケジュール作成装置34は、パンチプレス1から離れた場所に設置された自動プログラミング装置35に、ネットワークを介して接続されている。   A schedule creation device 34 is provided in the vicinity of the punch press 1 and can be operated by the operation panel 46. The schedule creation device 34 is connected to an automatic programming device 35 installed at a location away from the punch press 1 via a network.

加工機制御装置31は、加工プログラム36を演算制御部(図示せず)で解読して実行することで、パンチプレス1を制御するものである。
同図において、加工プログラム36の記述形式の例を、自動プログラミング装置35の図示部分内に示す。
The processing machine control device 31 controls the punch press 1 by decoding and executing the processing program 36 by an arithmetic control unit (not shown).
In the drawing, an example of a description format of the machining program 36 is shown in the illustrated portion of the automatic programming device 35.

加工プログラム36は、基本的には、一つの孔を加工する加工命令60を順次並べて記述したものとされる。加工命令60は、板材Wを移動させる移動命令60aと、工具割出命令60bとを1行に記述したものである。加工機制御装置31は、加工命令60を読み出すと、その移動命令60aで指定された各軸方向の位置へ板材Wを移動させ、工具割出命令60bで指定された個別工具8をパンチ位置Pに割出し、その割り出された個別工具8をパンチ動作させる一連の制御を行う。個別工具8のパンチ位置Pへの割出しは、機内工具ホルダマガジン5の旋回割出し過程と、工具ホルダ7の旋回割出し過程とを含む。同じ工具ホルダ7を続けて使用する場合は、工具ホルダマガジン5の旋回割出は不要であり、その動作は生じない。移動命令60aは、移動の軸方向X,Yを示す文字と移動量または座標値を示す文字、例えば「X−Y−」として示される。   The machining program 36 is basically a description in which machining instructions 60 for machining one hole are arranged side by side. The machining command 60 is a command in which a movement command 60a for moving the plate material W and a tool indexing command 60b are described in one line. When reading the machining command 60, the processing machine control device 31 moves the plate material W to the position in each axial direction specified by the movement command 60a, and moves the individual tool 8 specified by the tool indexing command 60b to the punch position P. A series of control is performed to punch the indexed individual tool 8. The indexing of the individual tool 8 to the punch position P includes a turning indexing process of the in-machine tool holder magazine 5 and a turning indexing process of the tool holder 7. When the same tool holder 7 is continuously used, the swiveling indexing of the tool holder magazine 5 is not necessary and the operation does not occur. The movement command 60a is indicated as a character indicating the axial direction X, Y of movement and a character indicating the movement amount or coordinate value, for example, “XY-”.

工具割出命令60bは、例えば「T0101」等のように、工具ホルダ7の識別番号「T01」に続いて、その工具ホルダ7におけるどの工具支持部7aであるかを指定する番号「01」を記述したものである。   The tool indexing command 60b, for example “T0101”, is followed by an identification number “T01” of the tool holder 7 followed by a number “01” that designates which tool support portion 7a in the tool holder 7 is. It is described.

加工機制御装置31は、保有工具ホルダ記憶手段55を有していて、これに機内工具ホルダマガジン5の各工具ホルダ保持部5aのアドレス「M1,M2,…」と、そのアドレスの工具ホルダ保持部5aに保持されている工具ホルダ7の識別番号とを対応させた情報が記憶されている。保有工具ホルダ記憶手段55の記憶情報は、機内工具ホルダマガジン5の保持する工具ホルダ7が出入りする毎に、その出入りした工具ホルダ7の識別番号に対応した内容に適宜の手段で更新される。   The processing machine control device 31 has retained tool holder storage means 55, which includes the addresses “M1, M2,...” Of each tool holder holding portion 5a of the in-machine tool holder magazine 5 and the tool holder holding of that address. The information which matched the identification number of the tool holder 7 currently hold | maintained at the part 5a is memorize | stored. Each time the tool holder 7 held by the in-machine tool holder magazine 5 enters and exits, the stored information in the retained tool holder storage means 55 is updated by appropriate means to the contents corresponding to the identification number of the tool holder 7 that has entered and exited.

この工具割出命令60bに対して、加工機制御装置31は、保有工具ホルダ記憶手段55から機内工具ホルダマガジン5の工具ホルダ保持部5aのアドレス「M1,M2,…」を認識し、そのアドレスの工具ホルダ保持部5aをプレスヘッド位置Qに旋回割出する指令を出力する。
また、加工機制御装置31は、工具ホルダ7の工具支持部7aの原点位置からの位相角度の情報を、全ての工具ホルダ7につき、その識別番号「T01 ,T02,…」およびこれに続く「01」等の工具支持部7aの指定番号と対応させて記憶した手段(図示せず)を有しており、この記憶内容を用いて、プレスヘッド位置Qの工具ホルダ7を、指定の位相角度に旋回割出させる。
In response to this tool indexing command 60b, the processing machine control device 31 recognizes the address “M1, M2,...” Of the tool holder holding portion 5a of the in-machine tool holder magazine 5 from the retained tool holder storage means 55, and the address. A command to turn and index the tool holder holding portion 5a to the press head position Q is output.
Further, the processing machine control device 31 provides information on the phase angle from the origin position of the tool support 7a of the tool holder 7 for all the tool holders 7 with the identification numbers “T01, T02,. Means (not shown) stored in association with the designated number of the tool support 7a such as “01”, etc., and using this stored content, the tool holder 7 at the press head position Q is moved to the designated phase angle. To turn.

チェンジャー制御装置32は、例えばプログラマブルコントローラからなり、チェンジャー制御プログラム38と、このプログラム38を解読して実行する制御部39とを有する。チェンジャー制御装置32は、チェンジャー動作情報F6を所定の記憶手段(図示せず)に記憶している。
チェンジャー制御プログラム38は、工具ホルダチェンジャー3の動作のうち、どの工具ホルダ7であるかを問わない共通の動作のプログラムを記述したものである。例えば工具ホルダチェンジャー3の走行体22を機内工具ホルダマガジン5および機外工具ホルダマガジン6の交換位置R,S間で走行させる命令や、各交換位置R,Sで、片方のチャック23,24で工具ホルダマガジン5,6の工具ホルダ7を取り出し、もう片方のチャック23,24に保持している工具ホルダ7を工具ホルダマガジン5,6に入れる一連の動作の命令等が記述される。
なお、チェンジャー制御装置32は、機外工具ホルダマガジン6の旋回割出やその他の動作の制御機能を有するものであっても良い。
The changer control device 32 includes, for example, a programmable controller, and includes a changer control program 38 and a control unit 39 that decodes and executes the program 38. The changer control device 32 stores changer operation information F6 in a predetermined storage means (not shown).
The changer control program 38 describes a common operation program regardless of which tool holder 7 the operation of the tool holder changer 3 is. For example, a command for causing the traveling body 22 of the tool holder changer 3 to travel between the replacement positions R and S of the in-machine tool holder magazine 5 and the external tool holder magazine 6, and the chucks 23 and 24 at one of the replacement positions R and S. Instructions for a series of operations for taking out the tool holder 7 of the tool holder magazines 5 and 6 and inserting the tool holder 7 held by the other chucks 23 and 24 into the tool holder magazines 5 and 6 are described.
The changer control device 32 may have a function for controlling the turning index of the external tool holder magazine 6 and other operations.

チェンジャー動作情報F6は、工具ホルダチェンジャー3からパンチプレス1に対して搬入,搬出する工具ホルダ7の識別番号を、搬入搬出に区別し、必要順に設定した情報である。
チェンジャー動作情報F6における前記必要順は、同図では行方向の並びの順としている。すなわち、同図では、識別番号「T09」の工具ホルダ7を搬出し、識別番号「T03」の工具ホルダ7を搬入する動作の次に、識別番号「T10」の工具ホルダ7を搬出し、識別番号「T05」の工具ホルダ7を搬入する動作を行うものとして設定されている。同図では、説明の簡明のために、1行には搬入する工具ホルダ7を一つ、搬出する工具ホルダ7を一つしているが、搬入,搬出とも、1行に複数の工具ホルダ7の識別番号を記述しても良い。その場合、同じ行に記述された複数の工具ホルダ7を同順位で搬出または搬入することを意味する。また、チェンジャー動作情報F6において、搬出だけを行い、搬入を行わない場合は、搬入欄の空欄とされる。搬入だけを行い、搬出を行わない場合は、搬出の欄は空欄とされる。
なお、チェンジャー動作情報F6は、チェンジャー制御装置32の所定の記憶領域にテーブル等で記憶される。
The changer operation information F <b> 6 is information in which the identification number of the tool holder 7 that is carried into and out of the punch press 1 from the tool holder changer 3 is distinguished from carry-in and carry-out and is set in the necessary order.
The necessary order in the changer operation information F6 is the order of arrangement in the row direction in FIG. That is, in the figure, after the operation of unloading the tool holder 7 with the identification number “T09” and loading the tool holder 7 with the identification number “T03”, the tool holder 7 with the identification number “T10” is unloaded and identified. It is set to perform the operation of carrying in the tool holder 7 with the number “T05”. In the figure, for the sake of simplicity of explanation, one tool holder 7 to carry in and one tool holder 7 to carry out are provided in one line, but a plurality of tool holders 7 are provided in one line for both loading and unloading. May be described. In this case, it means that a plurality of tool holders 7 described on the same line are carried out or carried in the same order. Further, in the changer operation information F6, when only carry-out is performed and no carry-in is performed, the carry-in column is blank. When only carrying in and not carrying out, the carrying out column is left blank.
The changer operation information F6 is stored in a predetermined storage area of the changer control device 32 in a table or the like.

チェンジャー制御装置32は、加工機制御装置31の加工プログラム36とは別のチェンジャー制御プログラム38によって動作するものであり、またチェンジャー動作情報F6が設定してあるため、加工プログラム36の実行によるパンチ加工の続行中に、工具ホルダチェンジャー3の動作を進めておくことができる。   The changer control device 32 is operated by a changer control program 38 that is different from the processing program 36 of the processing machine control device 31, and since the changer operation information F6 is set, punching by executing the processing program 36 is performed. During the operation, the operation of the tool holder changer 3 can be advanced.

図4において、自動プログラミング装置35は、素材となる板材Wの寸法情報と、その板材Wのパンチ加工後の形状を示す図形データとが入力されることで、所定の規則(図示せず)に従って加工プログラム36を作成する手段である。作成した加工プログラム36には、ファイル名(図では「001」等と表示)が付される。   In FIG. 4, the automatic programming device 35 receives dimensional information of a plate material W that is a material and graphic data indicating the shape of the plate material W after punching, and thereby follows a predetermined rule (not shown). This is means for creating the machining program 36. The created machining program 36 is given a file name (displayed as “001” or the like in the figure).

スケジュール作成装置34は、自動プログラミング装置35から送られた複数の加工プログラム36を記憶可能とされる。スケジュール作成装置34は、オペレータの入力によって各加工プログラム36を実行する順および加工枚数を定める設定スケジュール作成手段40を有していて、プログラム記憶手段41に、その定められた加工プログラム36の実行順および加工枚数の情報が、加工プログラム36のファイル名と共に記憶される。この記憶情報を、ここでは設定スケジュール情報F0と称す。実行順の情報は、加工プログラム36の並び順であっても良く、また加工プログラム36のファイル名またはその記憶領域のアドレス等に対して付された順位情報であっても良い。   The schedule creation device 34 can store a plurality of machining programs 36 sent from the automatic programming device 35. The schedule creation device 34 has setting schedule creation means 40 for determining the order in which the machining programs 36 are executed and the number of machining by an operator input, and the program storage means 41 stores the set execution order of the machining programs 36. Information on the number of processed pieces and the file name of the processing program 36 are stored. This stored information is referred to herein as setting schedule information F0. The execution order information may be the order in which the machining programs 36 are arranged, or may be order information given to the file name of the machining program 36 or the address of its storage area.

工具ホルダチェンジャー動作情報作成装置50は、上記チェジャー動作情報F6を作成する装置であり、この例ではスケジュール作成装置34に、その一部として設けられている。   The tool holder changer operation information creation device 50 is a device that creates the above-described charger operation information F6. In this example, the tool holder changer operation information creation device 50 is provided as a part of the schedule creation device 34.

図5に示すように、工具ホルダチェンジャー動作情報作成装置50は、格付け手段51およびチェンジャー動作情報作成手段52を有している。
格付け手段51は、一連の加工を行う加工単位である加工スケジュールSch でパンチプレス1が用いる工具ホルダ7の識別番号「T01,T02,…」の情報を使用順に含むスケジュール別使用工具ホルダ情報F1、および加工スケジュールSch の実行順を設定した実行順情報F2を含む計画スケジュール情報F0のうちの現在以降の情報から、所定の格付け基準R1に従い、各工具ホルダ7につきパンチプレス1側に置くか機外工具ホルダマガジン6側に置くかの判別のための格付け情報F5を付す手段である。なお、格付け基準R1は、換言すれば格付け規則である。作成された格付け情報F5は、所定の記憶手段56に記憶される。
計画スケジュール情報F0は、ここでは、図4と共に前述したように、各加工プログラム36を実行する順および加工枚数を定めた情報であるが、図5では、加工プログラム36のうち、格付け手段51で用いる情報をスケジュール別使用工具ホルダ情報F1として図示している。
As shown in FIG. 5, the tool holder changer operation information creation device 50 includes a rating unit 51 and a changer operation information creation unit 52.
The rating means 51 uses by-schedule tool holder information F1 including the information of the identification numbers “T01, T02,...” Of the tool holder 7 used by the punch press 1 in the processing schedule Sch which is a processing unit for performing a series of processing. From the information after the present schedule information F0 including the execution order information F2 that sets the execution order of the machining schedule Sch, each tool holder 7 is placed on the punch press 1 side according to a predetermined rating standard R1 or out of the machine. This is means for attaching rating information F5 for determining whether to place the tool holder magazine 6 or not. The rating standard R1 is a rating rule in other words. The created rating information F5 is stored in a predetermined storage means 56.
Here, as described above with reference to FIG. 4, the planned schedule information F0 is information that defines the order in which the respective machining programs 36 are executed and the number of processed pieces. In FIG. The information to be used is shown as schedule use tool holder information F1.

加工プログラム36において、工具割出命令60b(図4)は、上記のように工具ホルダ7の識別番号「T01」に続いて、その工具ホルダ7におけるどの工具支持部7aであるかを指定する番号「01」を記述したものとされている。この命令60bの記述には、工具ホルダ7の工具支持部7aは示されているが、その工具ホルダ7が各工具ホルダ7aにどの工具番号の工具を搭載したかの情報は記述されていない。パンチプレス1に搬入さされる工具ホルダ7が同じものであっても、その搭載する個別工具8が異なれば、異なる加工がなされる。   In the machining program 36, the tool indexing command 60b (FIG. 4) is a number that designates which tool support portion 7a in the tool holder 7 follows the identification number “T01” of the tool holder 7 as described above. “01” is described. In the description of the command 60b, the tool support portion 7a of the tool holder 7 is shown, but information on which tool number the tool holder 7a has mounted on the tool holder 7a is not described. Even if the tool holder 7 carried into the punch press 1 is the same, if the individual tool 8 to be mounted is different, different processing is performed.

工具ホルダ7の識別番号として、この例では、その器である工具ホルダ7の識別番号「T01」,「T02」,…の他に、工具ホルダ7に搭載した工具8の編成やその編成の作成日等によって区別される内容を示す識別番号として、「TM11」,「TM21」,…等の番号を用いている。この「TM11」の番号における上位桁(上位3桁)の文字「TM1」は、工具ホルダ7の器しとての識別番号「T01」と同じものを示し、下桁(下1桁)の文字「1」が、工具編成込みの区別(その編成の作成日等による内容の区別を含む)を示す。   As an identification number of the tool holder 7, in this example, in addition to the identification numbers “T01”, “T02”,... Numbers such as “TM11”, “TM21”,... Are used as the identification numbers indicating the contents distinguished by the date. The character “TM1” of the upper digit (upper three digits) in the number “TM11” indicates the same as the identification number “T01” as a tool holder 7 character, and the lower digit (lower one digit) character. “1” indicates the distinction of including the tool knitting (including the distinction according to the creation date of the knitting).

この工具編成込みの識別番号「TM11」,「TM21」,…の情報は、加工プログラム36とは別に設けた段取り情報であっても、加工プログラム36に工具割出命令60bとは別に設けた情報であっても、あるいは工具割出命令60bに含まれる情報としても良いが、格付け手段51で用いる計画スケジュール情報F0は、工具編成込みの識別番号「TM11」,「TM21」,…の情報を含むものである。   Even if the information of the identification numbers “TM11”, “TM21”,... Included in the tool knitting is setup information provided separately from the machining program 36, information provided separately from the tool indexing command 60b in the machining program 36. However, the plan schedule information F0 used in the rating means 51 includes information of identification numbers “TM11”, “TM21”,... Included in the tool knitting, although it may be information included in the tool indexing command 60b. It is a waste.

格付け手段51において、計画スケジュール情報F0は、加工プログラム36を先読みすること、つまり加工機制御装置31の実行に先立って読みだすことで認識する。加工プログラム36とは別に段取り情報が準備されている場合は、格付け手段51は、その段取り情報の読み取りを、上記先読みと共に行う。   In the rating means 51, the plan schedule information F0 is recognized by pre-reading the machining program 36, that is, by reading it prior to the execution of the processing machine control device 31. If setup information is prepared separately from the machining program 36, the rating means 51 reads the setup information together with the pre-reading.

また、格付け手段51による格付けは、一つのスケジュールSch の実行毎に行われる。チェンジャー動作情報作成手段52によるチェンジャー動作情報F6の作成についても、一つのスケジュールSch の実行毎に行われる。   Further, the rating by the rating means 51 is performed every time one schedule Sch is executed. Creation of changer operation information F6 by the changer operation information creation means 52 is also performed each time one schedule Sch is executed.

チェンジャー動作情報作成手段52は、パンチプレス1および機外工具ホルダマガジン6がそれぞれ現在保有する工具ホルダの情報F3,F4、前記計画スケジュール情報F0の現在以降の情報、および各工具ホルダ7の前記格付け情報F5から、チェンジャー動作情報F6として、どの工具ホルダ7(T01,T02,…)を機外工具ホルダマガジン6からパンチプレス1へ搬入させ、どの工具ホルダ7(T01,T02,…)をパンチプレス1から機外工具ホルダマガジン6へ搬出させるかの搬入搬出の情報であるチェンジャー動作情報F6を作成する。作成されたチェンジャー動作情報F6は、所定の記憶手段57に記憶させる。   The changer operation information creation means 52 includes tool holder information F3 and F4 currently held by the punch press 1 and the external tool holder magazine 6, information after the present schedule information F0, and the rating of each tool holder 7. From the information F5, as the changer operation information F6, which tool holder 7 (T01, T02,...) Is carried into the punch press 1 from the external tool holder magazine 6 and which tool holder 7 (T01, T02,...) Is punch pressed. Changer operation information F6, which is information about loading / unloading from 1 to the outside tool holder magazine 6, is created. The created changer operation information F6 is stored in a predetermined storage means 57.

パンチプレス1が現在保有する工具ホルダの情報F3は、加工機制御装置31に設けられた保有工具ホルダ記憶手段55(図4)の記憶内容とされる。機外工具ホルダマガジン6の保有工具ホルダ情報F4は、図4では図示を省略したが、加工機制御装置31またはチェンジャー制御装置32に設けられた機外保有工具ホルダ記憶手段54の記憶情報が用いられる。この機外保有工具ホルダ記憶手段54の記憶内容は、加工機制御装置31の保有工具ホルダ記憶手段55と同じく、工具ホルダ7の搬入搬出ごとに更新されるものである。   The tool holder information F3 currently held by the punch press 1 is stored in the held tool holder storage means 55 (FIG. 4) provided in the processing machine control device 31. The stored tool holder information F4 of the external tool holder magazine 6 is omitted from FIG. 4, but the stored information of the externally stored tool holder storage means 54 provided in the processing machine control device 31 or the changer control device 32 is used. It is done. The stored contents of the externally held tool holder storage means 54 are updated every time the tool holder 7 is loaded and unloaded, as with the held tool holder storage means 55 of the processing machine control device 31.

格付け手段51による格付けは、計画スケジュール情報F0と共に、パンチプレス1および機外工具ホルダマガジン6の現在保有工具ホルダ情報F3,F4を用いて行うようにしても良い。   The rating by the rating means 51 may be performed using the currently held tool holder information F3 and F4 of the punch press 1 and the external tool holder magazine 6 together with the plan schedule information F0.

格付け手段51による格付け基準R1の例を説明する。この例では格付け基準R1は、計画スケジュール情報F0の現在以降の情報と、パンチプレス1の現在の保有工具ホルダ情報F3とから、次の3つのランクA〜Cに大別するものとしている。
Aランクはパンチプレス1側へ置くものとするランクであり、直後の加工スケジュールSch で使用する工具ホルダ7、および直後よりも以降の加工スケジュールSch で使用されるが工具ホルダ7の搭載工具8を変更する段取りのない工具ホルダ7について付す。段取りの必要のある工具ホルダ7であっても、直後の加工スケジュールSch で使用する工具ホルダ7はAランクとするが、直後段取りの例外であることのフラグ等の情報を付す。
Bランクは、計画スケジュール情報F0において、現在以降に使用されることのない工具ホルダ7について付す。使用されることのない工具ホルダ7は、パンチプレス1側と機外工具ホルダマガジン6側のどちらにあっても良いからであ。
Cランクは、機外工具ホルダマガジン3側へ置くものとするランクであり、段取りがあり、直後の加工スケジュールSch では使用されない工具ホルダ7について付す。
An example of the rating standard R1 by the rating means 51 will be described. In this example, the rating standard R1 is roughly divided into the following three ranks A to C from the information after the current schedule information F0 and the current tool holder information F3 of the punch press 1.
Rank A is a rank to be placed on the punch press 1 side, and the tool holder 7 used in the immediately following machining schedule Sch and the tool 8 mounted on the tool holder 7 used in the subsequent machining schedule Sch after the immediately following machining schedule Sch. It attaches about the tool holder 7 without the setup to change. Even if the tool holder 7 needs to be set up, the tool holder 7 used in the immediately following machining schedule Sch is A rank, but information such as a flag indicating that it is an exception of the immediately following setup is attached.
The rank B is attached to the tool holder 7 that is not used after the present in the plan schedule information F0. This is because the tool holder 7 that is not used may be on either the punch press 1 side or the external tool holder magazine 6 side.
The C rank is a rank that is placed on the external tool holder magazine 3 side, and is attached to the tool holder 7 that is set up and is not used in the machining schedule Sch immediately after.

AランクおよびCランクは、それぞれ、さらに2つの補助ランクA1,A2,C1,Cb2に分けられる。
A1のランクは、Aランクのうち、直後のスケジュールSch に使用される工具ホルダ7に付いて付す。段取りの必要のある工具ホルダ7であっても、直後のスケジュール Schで使用されるものも、A1ランクとされる。
A2のランクは、Aランクのうち、直後のスケジュールSch では使用されない工具ホルダ7について付す。
C1のランクは、Cランクのうち、最初に使用されるまでに段取りが必要な工具ホルダ7に付いて付す。
C2のランクは、Cランクのうち、最初に使用されるときは段取りが不要であるが、その後に段取りが必要な工具ホルダ7について付す。
The A rank and the C rank are further divided into two auxiliary ranks A1, A2, C1, and Cb2, respectively.
The rank of A1 is attached to the tool holder 7 used for the schedule Sch immediately after the rank A. Even if the tool holder 7 needs to be set up, the tool holder 7 used in the immediately following schedule Sch is also ranked A1.
The rank of A2 is attached to the tool holder 7 that is not used in the schedule Sch immediately after the rank A.
The rank of C1 is attached to the tool holder 7 that needs to be set up before being used for the first time among the ranks C.
The rank of C2 is attached to the tool holder 7 that does not need to be set up when it is used for the first time among the C ranks, but needs to be set up thereafter.

A,Cで区分される同じランク内の工具ホルダ7については、Aランクの場合は、補助ランクA1,A2の順の優先順位とされる。また、Cランクの場合はC1,C2の順の優先順位とされる。同じ補助ランクの場合、Aランクの工具ホルダ7の場合は、以後の加工で使用される順の早いものを上位としている。使用の順は、スケジュール Schの早い順とれ、同じスケジュール Schではそのスケジュール Sch内で早い順とされる。スケジュール Sch内での使用の順は、加工プログラム36等からわかる。Cランクの工具ホルダ7の場合は、以後の加工で使用される順の遅いものを上位としている。なお、補助ランクを設けない場合は、Aランク内の全体、およびCランク内の全体で、使用順に優先順位が上位とされる。   For the tool holders 7 within the same rank divided by A and C, in the case of the A rank, the priority ranks are in the order of the auxiliary ranks A1 and A2. In the case of C rank, the priority order is C1 and C2. In the case of the same auxiliary rank, in the case of the A-rank tool holder 7, the one with the earlier order used in the subsequent machining is ranked higher. The order of use is the fastest order in the schedule Sch, and the same schedule Sch is the fastest order in the schedule Sch. The order of use in the schedule Sch can be understood from the machining program 36 or the like. In the case of the C-rank tool holder 7, the one with the later order used in the subsequent machining is ranked higher. In the case where no auxiliary rank is provided, the order of priority is set higher in the order of use in the whole of the A rank and the whole of the C rank.

チェンジャー動作情報作成手段52における搬入搬出の所定の基準R2としては、次の各基準が設けられている。ここで言う基準は、換言すれば規則である。
(1) 格付けランクがAの工具ホルダ7は、パンチプレス1へ搬入する。ただし、既にパンチプレス1内にその工具ホルダ7がある場合は、搬入の必要がなく、搬入は行わない。
(2) 格付けランクがCの工具ホルダ7は、機外工具ホルダマガジン6へ搬出する。ただし既に機外工具ホルダマガジン6内にその工具ホルダ7がある場合は、搬出の必要がなく、搬出は行わない。
(3) 格付けランクがAで、直後段取りの例外の情報が付されたものは、搬出を行い、機外で工具交換の段取りが行われた後、搬入を行う。
(4) 上記(1) の搬入は、パンチプレス1の保有する工具ホルダ7の個数が、保有可能な個数(同図の例では8個)を超えない範囲で、格付けの優先順(同ランクの場合は使用順による優先順)から行う。
(5) 上記(2) の搬出は、機外工具ホルダマガジン6の保有する工具ホルダ7の個数が、保有可能な個数(同図の例では8個)を超えない範囲で、格付けの優先順(同ランクの場合は使用順による優先順)から行う。
As the predetermined reference R2 for carrying in / out in the changer operation information creating means 52, the following respective standards are provided. In other words, the standard here is a rule.
(1) The tool holder 7 having a rating rank A is carried into the punch press 1. However, when the tool holder 7 is already present in the punch press 1, there is no need to carry in and no carry-in is performed.
(2) The tool holder 7 whose rating rank is C is carried out to the external tool holder magazine 6. However, when the tool holder 7 is already present in the external tool holder magazine 6, it is not necessary to carry out and carry out.
(3) If the rating rank is A and the information on the exception of the setup is added immediately, carry it out and carry it in after setting up the tool exchange outside the machine.
(4) In order to carry in the above (1), the priority order of ranks (same rank) is within the range where the number of tool holders 7 held by the punch press 1 does not exceed the number that can be held (8 in the example in the figure). In the case of, start from the priority order according to the order of use.
(5) The unloading of (2) above is performed in the order of priority of rating within the range where the number of tool holders 7 held in the external tool holder magazine 6 does not exceed the number that can be held (8 in the example in the figure). (In the case of the same rank, the order of priority according to the order of use).

上記構成による格付け情報F5およびチェンジャー動作情報F6の作成例を、具体例と共に説明する。
いま、図6に示すように、スケジュール別使用工具ホルダ情報F1、およびその実行順が設定され、スケジュール Sch1の開始前に、パンチプレス1および機外工具ホルダマガジン6は、図7(A),(B)に示す工具ホルダ7を保有していたとする。また、スケジュール Sch1の開始前に、チェンジャー動作情報F6を作成するとする。
An example of creating rating information F5 and changer operation information F6 with the above configuration will be described together with specific examples.
Now, as shown in FIG. 6, the scheduled tool holder information F1 and the execution order thereof are set, and before the start of the schedule Sch1, the punch press 1 and the external tool holder magazine 6 are shown in FIG. It is assumed that the tool holder 7 shown in (B) is held. Assume that changer operation information F6 is created before the start of schedule Sch1.

この場合、格付け手段51による格付けは次のように成される。工具ホルダT01,T03,T04は、直後のスケジュールであるスケジュール Sch1で使用するため、いずれもAランクとされ、かつそのうちのAaランクとされる。なお、これらの工具ホルダT01,T03,T04の工具編成込みの識別番号はTM11,TM31,TM41であって、図7(A),(B)からわかるように、いずれも段取りの必要がない。
工具ホルダT07,T09、T10は、いずれも、直後のスケジュール Sch1では使用されないが、計画スケジュールF0の全体を通して、現在の工具編成(TM71,TM91,TM101)で使用され、段取りの必要がない。したがって、工具ホルダT07,T09、T10は、ランクAとされ、そのうちのランクA2とされる。
In this case, the rating by the rating means 51 is performed as follows. Since the tool holders T01, T03, and T04 are used in the schedule Sch1 that is the immediately following schedule, all of them are set to the A rank, and are set to the Aa rank. Incidentally, the tool holders T01, T03, and T04 have identification numbers of the tool knitting included in TM11, TM31, and TM41, and as shown in FIGS. 7A and 7B, no setup is required.
None of the tool holders T07, T09, and T10 are used in the immediately following schedule Sch1, but are used in the current tool organization (TM71, TM91, TM101) throughout the planning schedule F0, and no setup is required. Accordingly, the tool holders T07, T09, and T10 are set to rank A, and rank A2 of them.

工具ホルダT02、T04、T08は、図6の枡目中に○印を付したように、工具編成がTM22,TM42,TM82の状態で使用されることがあり、現在の工具編成TM21,TM41,TM81と異なるため、段取りが必要である。このうち、工具ホルダT04は、スケジュール Sch1で使用されるため、先に述べたようにAランクとされる。
他の2つの工具ホルダT02,T08は、Cランクとされる。このうち、工具ホルダT02は、最初に使用されるスケジュール Sch2での工具編成がTM22であって、最初に使用されるスケジュール Sch2までに段取りが必要なため、C1ランクとされる。工具ホルダT08は、最初に使用されるときがスケジュール Sch3であって、このときの工具編成はTM81であり、現在の工具編成TM81と同じである。このため、C2ランクとされる。
工具ホルダT05,T06については、以後の全てのスケジュール Sch1〜4で使用されないため、ランクBである。
The tool holders T02, T04, and T08 may be used in a state where the tool knitting is TM22, TM42, and TM82 as indicated by a circle in FIG. Since it is different from TM81, setup is required. Among these, since the tool holder T04 is used in the schedule Sch1, it is set to A rank as described above.
The other two tool holders T02 and T08 have a C rank. Among these, the tool holder T02 is set to C1 rank because the tool organization in the schedule Sch2 used first is TM22 and the setup is required by the schedule Sch2 used first. When the tool holder T08 is first used, the schedule Sch3 is used, and the tool knitting at this time is TM81, which is the same as the current tool knitting TM81. For this reason, the rank is C2.
The tool holders T05 and T06 are rank B because they are not used in all the subsequent schedules Sch1 to Sch4.

チェンジャー動作情報作成手段52によるチェンジャーを動作情報F6の作成は、次のようになされる。
工具ホルダT01,T04は、いずれもランクAであってパンチプレス1側に置くが、図7の保有ホルダ情報F3からわかるように、いずれも現在はパンチプレス1に保有されているため、移動の必要がなく、そのままの位置とされる。
工具ホルダT03は、ランクAであってパンチプレス1側に置くが、図7の保有ホルダ情報F4からわかるように、現在は機外工具ホルダマガジン6に保有されているため、パンチプレス1へ搬入する。
工具ホルダT02は、ランクCであって、機外工具ホルダマガジン6側に置くが、現在はパンチプレス1に保有されているため、搬出を行う。
The changer operation information generating means 52 generates changer operation information F6 as follows.
The tool holders T01 and T04 are both placed at the rank A and on the punch press 1 side, but as can be seen from the holder information F3 in FIG. There is no need, and the position is left as it is.
Although the tool holder T03 is placed on the punch press 1 side at rank A, it can be loaded into the punch press 1 because it is currently held in the external tool holder magazine 6 as can be seen from the holding holder information F4 in FIG. To do.
The tool holder T02 is rank C and is placed on the external tool holder magazine 6 side, but is currently held in the punch press 1 and is therefore carried out.

工具ホルダT07,T09は、いずれもランクAであり、パンチプレス1側に置くが、現在はパンチプレス1に保有されているため、移動の必要がなく、そのままの位置とされる。
工具ホルダT10は、ランクAであって、パンチプレス1側に置くが、現在は機外工具ホルダマガジン6に保有されているため、搬入を行う。
工具ホルダT05,T06はランクBであるため、移動の必要がなく、現在の位置、つまり工具ホルダT05はパンチプレス1に、工具ホルダ6は機外工具ホルダマガジン6に置いておく。
The tool holders T07 and T09 are both rank A and placed on the punch press 1 side, but are currently held in the punch press 1 and therefore do not need to be moved, and are left in their positions.
The tool holder T10 is rank A and is placed on the punch press 1 side, but is currently held in the external tool holder magazine 6 and is therefore loaded.
Since the tool holders T05 and T06 are rank B, they do not need to be moved, and the current position, that is, the tool holder T05 is placed in the punch press 1 and the tool holder 6 is placed in the external tool holder magazine 6.

このように、搬入を行う工具ホルダ7は、T03,T10であり、搬出を行う工具ホルダ7はT02である(図9)。搬出よりも搬入の個数が1個多いが、パンチプレス1には8個の工具ホルダ7の保有が可能で、現在は5個の保有であるため、工具ホルダ7が1個増えてもまだ2個の余裕があり、図9に示すとおりの搬入搬出のチェンジャー動作情報F6とする。   Thus, the tool holder 7 that carries in is T03 and T10, and the tool holder 7 that carries out is T02 (FIG. 9). Although the number of carry-in is one more than the carry-out, the punch press 1 can hold eight tool holders 7 and currently has five, so even if the tool holder 7 is increased by one, it is still 2 The changer operation information F6 for carrying in / out as shown in FIG.

上記の具体例では、搬入後のパンチプレス1の保有する工具ホルダ7の個数が最大個数の8個を超えることにならなかったが、最大個数を超える場合は、優先順に最大個数まで保有されるように搬入を行う。優先順位は、まず補助ランクA1,A2の順で区別され、同じ補助ランク内であれば、使用の早い順である。補助ランクA1,A2を設定しない場合は、ランクAの全体で使用の早い順である。
また、搬出後の機外工具ホルダマガジン6の保有する工具ホルダ7の個数が最大個数の8個を超えることになる場合は、優先順に最大個数まで保有されるように搬出を行う。優先順位は、使用の遅い順である。ランクCについても、補助ランクを設定する場合は、優先順位はまず補助ランクの順で区別され、同じ補助ランク内であれば、使用の遅い順である。
In the specific example described above, the number of tool holders 7 held by the punch press 1 after loading does not exceed the maximum number of eight, but if the number exceeds the maximum number, the maximum number is held in order of priority. Carry in as follows. The priorities are first distinguished in the order of the auxiliary ranks A1 and A2. If they are within the same auxiliary rank, the order of use is the fastest. When the auxiliary ranks A1 and A2 are not set, the rank A is used in the order of early use.
Further, when the number of tool holders 7 held by the external tool holder magazine 6 after unloading exceeds the maximum number of eight, the unloading is performed so that the maximum number is held in priority order. The priority order is the order of use. As for rank C, when setting an auxiliary rank, priorities are first distinguished in the order of auxiliary ranks. If they are within the same auxiliary rank, the order of use is slow.

この構成の工具ホルダチェンジャー動作情報作成装置50によると、このように、パンチプレス1で早く必要な工具ホルダ7はパンチプレス1内に留めておき、早く工具段取りが必要な工具ホルダは機外工具ホルダマガジン6に搬出することのできる効率的な搬入搬出の動作情報F6が作成される。   According to the tool holder changer operation information creation device 50 having this configuration, the tool holder 7 that is required early in the punch press 1 is retained in the punch press 1 and the tool holder that requires quick tool setup is an external tool. Efficient loading / unloading operation information F6 that can be carried out to the holder magazine 6 is created.

なお、チェンジャー動作情報作成手段52における搬入搬出の所定の基準R2として、上記実施形態では、「(1) 格付けランクがAの工具ホルダ7は、パンチプレス1へ搬入する。」とし、また「(2) 格付けランクがCの工具ホルダ7は、機外工具ホルダマガジン6へ搬出する。」としたが、基準R2のうちのこの部分について、補助ランクA1,A2,C1,C2を設ける場合は、次のように定めても良い。
すなわち、格付けランクがAの工具ホルダ7のうち、A1ランクの工具ホルダ7は、パンチプレス1へ搬入するが、A2ランクの工具ホルダ7は、パンチプレス1と機外工具ホルダマガジン6のいずれにあっても、原則的には搬入搬出を行わない。ただし、C1ランクの工具ホルダ7を搬出すれば、機外工具ホルダマガジン6の保有する工具ホルダ7の個数が保有可能個数(図示の例では8個)を超えることになる場合は、A1ランクの工具ホルダ7は搬入する。
また、格付けランクがCの工具ホルダ7のうち、C1ランクの工具ホルダ7は、機外工具ホルダマガジン6へ搬出するが、C2ランクの工具ホルダ7は、パンチプレス1と機外工具ホルダマガジン6のいずれにあっても、原則的には搬入搬出を行わない。ただし、A1ランクの工具ホルダ7を搬入すれば、パンチプレス1の保有する工具ホルダ7の個数が保有可能個数(図示の例では8個)を超えることになる場合は、C1ランクの工具ホルダ7は搬出する。
In the above embodiment, “(1) the tool holder 7 whose rating rank is A is carried into the punch press 1” as the predetermined reference R2 for carrying in / out in the changer operation information creating means 52, and “( 2) The tool holder 7 whose rating rank is C is carried out to the external tool holder magazine 6. ”However, when the auxiliary ranks A1, A2, C1, and C2 are provided for this portion of the reference R2, It may be determined as follows.
That is, among the tool holders 7 with the rating rank A, the tool holder 7 with the A1 rank is carried into the punch press 1, but the tool holder 7 with the A2 rank is placed in either the punch press 1 or the external tool holder magazine 6. Even if there is, in principle it will not be carried in or out. However, if the C1 rank tool holder 7 is carried out, the number of tool holders 7 held by the external tool holder magazine 6 will exceed the number (8 in the example shown) that can be held. The tool holder 7 is carried in.
In addition, among the tool holders 7 with the rating rank C, the C1 rank tool holder 7 is carried out to the external tool holder magazine 6, while the C2 rank tool holder 7 includes the punch press 1 and the external tool holder magazine 6. In either case, in principle, no loading / unloading is performed. However, if the A1 rank tool holder 7 is carried in and the number of tool holders 7 held by the punch press 1 exceeds the number that can be held (eight in the illustrated example), the C1 rank tool holder 7 is used. Unload.

また、上記実施形態では、補助ランクA1,A2,C1,C2を設けたが、上位ランクと補助ランクは特に区別する必要はなく、全体をA1,A2,B,C1,C2等の同列のランクで格付けを行うようにしても良い。
また、上記実施形態では、加工機がパンチプレス1である場合につき説明したが、この発明における制御対象となる加工機は、パンチプレスに限らず、複数の個別工具を搭載した工具ホルダを交換可能に装備するものであれば良い。
In the above embodiment, the auxiliary ranks A1, A2, C1, and C2 are provided. However, it is not necessary to distinguish the upper rank and the auxiliary rank, and the ranks of the same row such as A1, A2, B, C1, C2, etc. You may make it perform rating by.
Moreover, although the said embodiment demonstrated about the case where a processing machine is the punch press 1, the processing machine used as the control object in this invention is not restricted to a punch press, The tool holder carrying a several separate tool is exchangeable. Anything can be used.

この発明の一実施形態にかかる工具ホルダチェンジャー動作情報作成装置で作成された情報を使用する工具ホルダチェンジャーを備えたチェンジャー付き加工設備の一例を示す平面図である。It is a top view which shows an example of the processing equipment with a changer provided with the tool holder changer which uses the information produced with the tool holder changer operation information creation apparatus concerning one Embodiment of this invention. その機内工具ホルダマガジン、機外工具ホルダマガジン、および工具ホルダチェンジャーを示す拡大平面図である。It is an enlarged plan view showing the in-machine tool holder magazine, the out-of-machine tool holder magazine, and the tool holder changer. その工具ホルダ斜視図である。It is the tool holder perspective view. 同チェンジャー付き加工設備の制御システムの一部を示す概念構成のブロック図である。It is a block diagram of a conceptual structure which shows a part of control system of the processing equipment with the changer. 同工具ホルダチェンジャー動作情報作成装置の概念構成のブロック図と工具ホルダチェンジャーの平面図とを示す説明図である。It is explanatory drawing which shows the block diagram of the conceptual structure of the tool holder changer operation information creation apparatus, and the top view of a tool holder changer. スケジュール別使用工具ホルダ情報の一例の説明図である。It is explanatory drawing of an example of the use tool holder information according to schedule. 機外工具ホルダマガジンの保有工具ホルダ情報の一例、および加工機の保有工具ホルダ情報の一例の説明図である。It is explanatory drawing of an example of the holding tool holder information of an external machine tool holder magazine, and an example of the holding tool holder information of a processing machine. 格付け情報の一例の説明図である。It is explanatory drawing of an example of rating information. チェンジャー動作情報の一例の説明図である。It is explanatory drawing of an example of changer operation information.

符号の説明Explanation of symbols

1…パンチプレス(加工機)
3…工具ホルダチェンジャー
5…機内工具ホルダマガジン
5a…工具ホルダ保持部
6…機外工具ホルダマガジン
6a…工具ホルダ保持部
7…工具ホルダ
8…個別工具
31…加工機制御装置
32…チェンジャー制御装置
34…スケジュール作成装置
36…加工プログラム
38…チェンジャー制御プログラム
50…工具ホルダチェンジャー動作情報作成装置
51…格付け手段
52…チェンジャー動作情報作成手段
54…機外工具ホルダマガジンの保有工具ホルダ記憶手段
55…加工機の保有工具ホルダ記憶手段
60b…工具割出命令
A,B,C…ランク
A1,A2,C1,C2…補助ランク
F0…設定スケジュール情報
F1…スケジュール別使用工具ホルダ情報
F2…実行順情報
F3…加工機の保有工具ホルダ情報
F4…機外工具ホルダマガジンの保有工具ホルダ情報
F5…格付け情報
F6…チェンジャー動作情報
M1,M2,…アドレス
R1…所定の格付けの基準
R2…搬入搬出の基準
Sch …加工スケジュール
T01,T02,…識別番号
TM11,TM21…識別番号
1 ... Punch press (processing machine)
3 ... Tool holder changer 5 ... In-machine tool holder magazine 5a ... Tool holder holder 6 ... Outside tool holder magazine 6a ... Tool holder holder 7 ... Tool holder 8 ... Individual tool 31 ... Machine control device 32 ... Changer control device 34 ... Schedule creation device 36 ... Machining program 38 ... Changer control program 50 ... Tool holder changer operation information creation device 51 ... Rating means 52 ... Changer operation information creation means 54 ... Own tool holder storage tool holder storage means 55 ... Processing machine Owned tool holder storage means 60b ... tool indexing commands A, B, C ... ranks A1, A2, C1, C2 ... auxiliary rank F0 ... setting schedule information F1 ... use tool holder information F2 by schedule ... execution order information F3 ... machining Machine tool holder information F4 ... External tool holder magazine Held tool holder information F5 ... rating information F6 ... changer operation information M1, M2, ... address R1 ... reference reference R2 ... indexer given rating
Sch ... Machining schedule T01, T02, ... Identification numbers TM11, TM21 ... Identification numbers

Claims (3)

工具を搭載した複数の工具ホルダを交換可能に装備する加工機と、この加工機外の工具ホルダを保管する機外工具ホルダマガジンとの間で工具ホルダを自動交換する工具ホルダチェンジャーの動作情報を作成する工具ホルダチェンジャー動作情報作成装置であって、 一連の加工を行う加工単位である加工スケジュールで前記加工機が用いる工具ホルダの識別番号の情報を使用順に含むスケジュール別使用工具ホルダ情報、および加工スケジュールの実行順を設定した実行順情報を含む計画スケジュール情報を用いて、所定の格付け基準に従い、各工具ホルダにつき加工機側に置くか機外工具ホルダマガジン側に置くかの判別のための格付け情報を付す格付け手段と、
加工機および機外工具ホルダマガジンがそれぞれ現在保有する工具ホルダの情報、前記計画スケジュール情報、および各工具ホルダの前記各付け情報から、前記工具ホルダチェンジャーの動作情報として、どの工具ホルダを機外工具ホルダマガジンから加工機へ搬入させ、どの工具ホルダを加工機から機外工具ホルダマガジンへ搬出させるかの搬入搬出の情報を作成するチェンジャー動作情報作成手段、
とを備えた工具ホルダチェンジャー動作情報作成装置。
Operation information of the tool holder changer that automatically changes the tool holder between a processing machine equipped with a plurality of tool holders equipped with tools in an exchangeable manner and an external tool holder magazine for storing the tool holder outside the processing machine. Tool holder changer operation information creation device to be created, which includes tool holder information according to schedule including information on the identification number of the tool holder used by the processing machine in a processing schedule which is a processing unit for performing a series of processing, and processing Rating for determining whether to place each tool holder on the processing machine side or on the outside tool holder magazine side according to a predetermined rating standard using planned schedule information including execution order information that sets the execution order of the schedule A rating means for attaching information;
Which tool holder is used as the operation information of the tool holder changer from the information on the tool holder currently held by the processing machine and the external tool holder magazine, the schedule information, and the attachment information of each tool holder. Changer operation information creation means for creating loading / unloading information as to which tool holder is loaded into the processing machine from the holder magazine and which tool holder is loaded from the processing machine to the external tool holder magazine;
A tool holder changer operation information creation device.
前記加工機または機外工具ホルダマガジンの保有する少なくとも一つの工具ホルダが、複数の工具を交換可能に搭載したものであり、前記格付け手段は、前記計画スケジュール情報、並びに加工機および機外工具ホルダマガジンがそれぞれ現在保有する工具ホルダの情報から、直後の加工スケジュールで使用する工具ホルダ、および計画スケジュールで使用されるが工具ホルダの搭載工具を変更する段取りのない工具ホルダを加工機側へ置く格付けとし、段取りがあり直後の加工スケジュールでは使用されない工具ホルダを機外工具ホルダマガジン側へ置く格付けとするものとした請求項1記載の工具ホルダチェンジャー動作情報作成装置。   The at least one tool holder possessed by the processing machine or the external tool holder magazine is configured such that a plurality of tools can be exchanged, and the rating means includes the plan schedule information, the processing machine, and the external tool holder. Based on the information of the tool holders currently held by the magazine, the tool holder used in the immediately following machining schedule and the tool holder that is used in the planning schedule but has no setup to change the tool holder's loaded tool are placed on the machine side. The tool holder changer operation information creation device according to claim 1, wherein a tool holder that is set up and that is not used in a machining schedule immediately after the setting is placed on the external tool holder magazine side. 加工機による加工スケジュールの実行毎に、前記格付け手段による格付け、および前記チェンジャー動作情報作成手段による工具ホルダチェンジャーの動作情報の作成を行うものとした請求項1または請求項2記載の工具ホルダチェンジャー動作情報作成装置。   The tool holder changer operation according to claim 1 or 2, wherein each time a machining schedule is executed by a processing machine, the rating unit performs rating, and the changer operation information creating unit creates operation information of the tool holder changer. Information creation device.
JP2005150550A 2005-05-24 2005-05-24 Device for preparing for tool holder changer-operation information Pending JP2006326711A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005150550A JP2006326711A (en) 2005-05-24 2005-05-24 Device for preparing for tool holder changer-operation information

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005150550A JP2006326711A (en) 2005-05-24 2005-05-24 Device for preparing for tool holder changer-operation information

Publications (1)

Publication Number Publication Date
JP2006326711A true JP2006326711A (en) 2006-12-07

Family

ID=37548963

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005150550A Pending JP2006326711A (en) 2005-05-24 2005-05-24 Device for preparing for tool holder changer-operation information

Country Status (1)

Country Link
JP (1) JP2006326711A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009056501A (en) * 2007-09-03 2009-03-19 Murata Mach Ltd Tool holder exchange type punch press
US20160103444A1 (en) * 2014-10-08 2016-04-14 Fanuc Corporation Controller for machine tool including automatic tool changer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009056501A (en) * 2007-09-03 2009-03-19 Murata Mach Ltd Tool holder exchange type punch press
US20160103444A1 (en) * 2014-10-08 2016-04-14 Fanuc Corporation Controller for machine tool including automatic tool changer
CN105500087A (en) * 2014-10-08 2016-04-20 发那科株式会社 Controller for machine tool including automatic tool changer

Similar Documents

Publication Publication Date Title
JP2007185686A (en) Apparatus for generating retooling information of punch press
JP4839802B2 (en) Processing machine setup information display device
JP6212905B2 (en) Machine Tools
JPH0317615B2 (en)
CN112720012A (en) Tool rest/tool magazine shared system and method capable of being infinitely expanded for machining center
JP2007144541A (en) Tool information display device of processing machine
US20230103884A1 (en) Machine tool
JP2009297868A (en) Tool rearranging method for tool magazine device, and device for the same
JP2009288998A (en) Changer-equipped working machine control device
JP2006326711A (en) Device for preparing for tool holder changer-operation information
JP4839656B2 (en) Processing equipment control system with changer
JP4301207B2 (en) Tool holder changer control program creation device
JPS63180390A (en) Method and device for manufacturing work from blank, minutely, thin iron plate
EP1229413A1 (en) Multipurpose processing program and nc processing machine using the same
JP4839655B2 (en) Processing equipment control system with changer
JP4301208B2 (en) Tool holder changer control program creation device
JP4797583B2 (en) Processing equipment control system with changer
JP4752329B2 (en) Tool holder changer control program creation device
JP2009297867A (en) Method and device for changing arrangement of tool in tool magazine device
JP2009106983A (en) Device for displaying arrival expectation of tool life of punch press
JP3224274B2 (en) Die selection control device in punch press
JP4507691B2 (en) Tool setup information creation device
JP7203254B1 (en) Machine Tools
JP2007130676A (en) Processing equipment control system having changer
JP4330403B2 (en) Machine Tools

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20080220

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090414

A131 Notification of reasons for refusal

Effective date: 20090421

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090825