JP2006316474A - Construction method for concrete retaining wall - Google Patents

Construction method for concrete retaining wall Download PDF

Info

Publication number
JP2006316474A
JP2006316474A JP2005139171A JP2005139171A JP2006316474A JP 2006316474 A JP2006316474 A JP 2006316474A JP 2005139171 A JP2005139171 A JP 2005139171A JP 2005139171 A JP2005139171 A JP 2005139171A JP 2006316474 A JP2006316474 A JP 2006316474A
Authority
JP
Japan
Prior art keywords
separator
slope
jig
retaining wall
concrete retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005139171A
Other languages
Japanese (ja)
Inventor
Tomiji Tomimatsu
富治 冨松
Katsuya Sasaki
克也 佐々木
Akihiko Karasaki
彰彦 唐崎
Kenichi Saito
謙一 齋藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2005139171A priority Critical patent/JP2006316474A/en
Publication of JP2006316474A publication Critical patent/JP2006316474A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Retaining Walls (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To enhance the reliability of construction while reducing construction costs in the construction of a concrete retaining wall for covering a slope. <P>SOLUTION: After a plurality of separator connecting implements 10 with flanges 10a formed at their base ends are temporarily fixed to the slope 2a in a state of being arranged at predetermined intervals among them along the slope 2a of the natural ground 2. Subsequently, mortar 6 is sprayed on the slope 2a, so that the base end of each of the implements 10 can be fixed to the slope 2a. After that, the base end of a separator 20 is connected to the leading end of each of the implements 10; a sheathing board 22 is installed at the leading end of each of the separators 20 in parallel with the slope 2a; and concrete is placed between the sheathing board 22 and the slope 2a. Thus, reaction for countering a tensile force acting on the separator 20 by using pressure acting on the sheathing board 22 from the placed concrete is secured by the implements 10 and the mortar 6. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本願発明は、法面を覆うコンクリート擁壁を構築するコンクリート擁壁構築方法に関するものである。   The present invention relates to a concrete retaining wall construction method for constructing a concrete retaining wall that covers a slope.

従来より、地山等の法面保護を図るための方法として、法面を覆うコンクリート擁壁を構築する方法が知られている。   Conventionally, a method of constructing a concrete retaining wall that covers a slope is known as a method for protecting a slope such as a natural ground.

このコンクリート擁壁構築方法においては、法面と略平行になるように堰板を設置し、この堰板と法面との間にコンクリートを打設することにより、コンクリート擁壁を構築するようになっている。その際、堰板の設置は複数のセパレータを介して行われるが、これら各セパレータには、打設されたコンクリートから堰板に作用する圧力によって所定の張力が作用するので、この張力に対抗するための反力を法面側に受け持たせる必要がある。   In this concrete retaining wall construction method, a concrete retaining wall is constructed by installing a dam plate so as to be substantially parallel to the slope and placing concrete between the dam and the slope. It has become. At that time, the dam plate is installed through a plurality of separators, and a predetermined tension is applied to each of the separators by the pressure acting on the dam plate from the placed concrete. It is necessary to make the reaction force for the slope face.

このため従来、法面にアンカを打ち込んで、このアンカの先端部にセパレータの基端部を連結したり、あるいは、あるいは「特許文献1」に記載されているように、セパレータ自体を法面に打ち込む工夫がなされている。   Therefore, conventionally, an anchor is driven into the slope and the base end of the separator is connected to the tip of the anchor, or the separator itself is used as the slope as described in “Patent Document 1”. The device is devised.

特開平11−210004号公報Japanese Patent Laid-Open No. 11-210004

上記従来のコンクリート擁壁構築方法においては、法面に打ち込まれたアンカあるいはセパレータにより所要の反力を確保するようになっているので、その打込みを法面からある程度の深さの位置に達するまで行う必要がある。   In the conventional concrete retaining wall construction method described above, the required reaction force is secured by the anchor or separator driven into the slope, so that the placement until reaching a position at a certain depth from the slope. There is a need to do.

しかしながら、法面を構成する地盤が軟弱な場合には、相当な深さまで打込みを行う必要があり、このため長尺のアンカあるいはセパレータを用いる必要がある。また、法面を構成する地盤が堅固な場合には、アンカあるいはセパレータの打込みを必要な深さまで行うこと自体が容易ではない。   However, when the ground constituting the slope is soft, it is necessary to drive to a considerable depth. For this reason, it is necessary to use a long anchor or separator. In addition, when the ground constituting the slope is solid, it is not easy to drive the anchor or the separator to the required depth.

したがって、上記従来のコンクリート擁壁構築方法では、施工効率が悪く、このため施工コストが掛かってしまい、また、定量的な施工管理が困難であるため、施工の信頼性を十分に確保することができない、という問題がある。   Therefore, in the conventional concrete retaining wall construction method described above, the construction efficiency is poor, and thus construction costs are required, and quantitative construction management is difficult, so that the construction reliability can be sufficiently secured. There is a problem that it is not possible.

本願発明は、このような事情に鑑みてなされたものであって、法面を覆うコンクリート擁壁を構築する際の施工コスト低減を図るとともに施工の信頼性を高めることができるコンクリート擁壁構築方法を提供することを目的とするものである。   The present invention has been made in view of such circumstances, and a concrete retaining wall construction method capable of reducing the construction cost when constructing a concrete retaining wall covering a slope and enhancing the reliability of construction. Is intended to provide.

本願発明は、従来のアンカの代わりに所定のセパレータ連結用治具を用い、これをモルタル吹付けにより法面に固定するようにし、もって上記目的達成を図るようにしたものである。   In the present invention, a predetermined separator connecting jig is used instead of a conventional anchor, and this is fixed to a slope by spraying mortar, thereby achieving the above object.

すなわち、本願発明に係るコンクリート擁壁構築方法は、
法面を覆うコンクリート擁壁を構築するコンクリート擁壁構築方法において、
基端部にフランジ部が形成された複数のセパレータ連結用治具を、法面に沿って互いに所定間隔をおいて配置した状態で上記法面に仮固定した後、上記法面にモルタルを吹き付けることにより上記各セパレータ連結用治具の基端部を上記法面に固定し、
その後、上記各セパレータ連結用治具の先端部にセパレータの基端部を連結するとともに、これら各セパレータの先端部に堰板を上記法面と略平行になるように設置し、この堰板と上記法面との間にコンクリートを打設する、ことを特徴とするものである。
That is, the concrete retaining wall construction method according to the present invention is:
In the concrete retaining wall construction method of constructing the concrete retaining wall covering the slope,
A plurality of separator coupling jigs having flange portions formed at the base end are temporarily fixed to the slope in a state of being arranged at predetermined intervals along the slope, and then mortar is sprayed on the slope. By fixing the base end portion of each separator connecting jig to the slope,
Thereafter, the base end of the separator is connected to the tip of each separator connecting jig, and a dam plate is installed at the tip of each separator so as to be substantially parallel to the slope, Concrete is placed between the slope and the slope.

上記各「セパレータ連結用治具」は、その基端部にフランジ部が形成されるとともに、その先端部においてセパレータの基端部に連結し得るように構成されたものであれば、その形状、大きさ、材質等の具体的な構成は特に限定されるものではない。   Each of the above “separator connection jigs” has a flange portion formed at the base end portion thereof, and can be connected to the base end portion of the separator at the tip end portion thereof. Specific configurations such as size and material are not particularly limited.

上記各セパレータ連結用治具を法面に「仮固定」するための具体的方法は、この仮固定の後に行われるモルタル吹付けによる法面への固定までの間、セパレータ連結用治具を法面の所定位置に位置決め保持することができるものであれば、特定の方法に限定されるものではない。   A specific method for “temporarily fixing” each of the separator connecting jigs to the slope is to use the separator connecting jigs until fixing to the slope by mortar spraying performed after the temporary fixing. As long as it can be positioned and held at a predetermined position on the surface, it is not limited to a specific method.

上記法面に対する「モルタル」の吹付けは、各セパレータ連結用治具の基端部を法面に固定し得る態様で行われるものであれば、法面の全域に対して行うようにしてもよいし、各セパレータ連結用治具の基端部の近傍領域に対してのみ行うようにしてもよい。   If the "mortar" spraying on the slope is performed in such a manner that the base end portion of each separator coupling jig can be fixed to the slope, it may be performed over the entire slope. Alternatively, it may be performed only in the vicinity of the base end portion of each separator coupling jig.

上記各セパレータ連結用治具の先端部と各セパレータの基端部との「連結」を行うための具体的方法は特に限定されるものではなく、例えばネジ締めや嵌合等による連結が採用可能である。   The specific method for performing the “connection” between the distal end portion of each separator connection jig and the base end portion of each separator is not particularly limited, and for example, connection by screwing or fitting can be employed. It is.

上記構成に示すように、本願発明に係るコンクリート擁壁構築方法においては、基端部にフランジ部が形成された複数のセパレータ連結用治具を、法面に沿って互いに所定間隔をおいて配置した状態で法面に仮固定した後、法面にモルタルを吹き付けることにより各セパレータ連結用治具の基端部を法面に固定し、その後、各セパレータ連結用治具の先端部にセパレータの基端部を連結するとともに、これら各セパレータの先端部に堰板を法面と略平行になるように設置し、この堰板と法面との間にコンクリートを打設するようになっているので、次のような作用効果を得ることができる。   As shown in the above configuration, in the concrete retaining wall construction method according to the present invention, a plurality of separator connecting jigs having a flange portion formed at the base end portion are arranged at predetermined intervals along the slope. In this state, the base end of each separator coupling jig is fixed to the slope by spraying mortar on the slope, and then the separator is fixed to the tip of each separator coupling jig. The base end is connected, and a dam plate is installed at the tip of each separator so as to be substantially parallel to the slope, and concrete is placed between the dam and the slope. Therefore, the following effects can be obtained.

すなわち、法面に仮固定されたセパレータ連結用治具は、モルタル吹付けにより法面に固定されるので、その後、打設されたコンクリートから堰板に作用する圧力によってセパレータに所定の張力が作用しても、この張力に対抗するための反力をセパレータ連結用治具およびモルタルによって確保することができる。   That is, the separator coupling jig temporarily fixed to the slope is fixed to the slope by mortar spraying, and then a predetermined tension is applied to the separator by the pressure acting on the barrier plate from the placed concrete. Even so, a reaction force to counter this tension can be ensured by the separator connecting jig and the mortar.

その際、このセパレータ連結用治具の法面への固定は、該セパレータ連結用治具の仮固定およびモルタル吹付けにより行われるので、従来のようなアンカ等の打込作業に比して法面への固定を簡易に行うことができ、これにより施工効率を高めることができる。   At that time, the fixing of the separator connecting jig to the slope is performed by temporarily fixing the separator connecting jig and spraying the mortar. The fixing to the surface can be easily performed, and thereby the construction efficiency can be increased.

また、セパレータに作用する張力に対抗するための反力を、従来のようにアンカ等の引抜き抵抗力に依存するのではなく、打設されたコンクリートの圧力を利用してセパレータ連結用治具およびモルタルにより確保するようになっているので、定量的な施工管理を行うことができる。   Also, the reaction force to counter the tension acting on the separator does not depend on the pulling resistance force of an anchor or the like as in the prior art, but the separator connecting jig and the like using the pressure of the placed concrete Since it is secured by mortar, quantitative construction management can be performed.

したがって本願発明によれば、法面を覆うコンクリート擁壁を構築する際の施工コスト低減を図ることができ、また、その施工の信頼性を高めることができる。   Therefore, according to this invention, the construction cost at the time of constructing the concrete retaining wall which covers a slope can be aimed at, and the reliability of the construction can be improved.

上記構成において、各セパレータ連結用治具を法面に仮固定するための具体的方法が特に限定されないことは上述したとおりであるが、この仮固定を、法面に棒状部材を予め打ち込んでおくとともに、この棒状部材にセパレータ連結用治具を装着することにより行うようにすれば、セパレータ連結用治具の構成を簡素化した上で、該セパレータ連結用治具の法面への仮固定を確実に行うことができる。   In the above configuration, as described above, the specific method for temporarily fixing each separator coupling jig to the slope is not particularly limited. However, for this temporary fixation, a rod-shaped member is driven in advance on the slope. At the same time, if the separator connecting jig is attached to the rod-shaped member, the configuration of the separator connecting jig is simplified, and the separator connecting jig is temporarily fixed to the slope. It can be done reliably.

あるいは、このようにする代わりに、セパレータ連結用治具に棒状突起部を予め設けておくとともに、この棒状突起部を法面に打ち込むことにより行うようにすれば、必要機材を削減することができる。   Alternatively, instead of doing this, a bar-like projection is provided in advance on the separator coupling jig, and if this rod-like projection is driven into the slope, the necessary equipment can be reduced. .

これらの場合において、法面に対する棒状部材あるいは棒状突起部の打込みは、セパレータ連結用治具の仮固定のために必要な程度に行えば足り、従来のアンカ等のようにコンクリート打設時の引抜き力に対抗するための反力を確保する必要はないので、法面に浅いドリル穴をあけて、このドリル穴に棒状部材あるいは棒状突起部を挿し込むことにより容易に行うことができる。その際、法面を構成する地盤が比較的軟弱であれば、棒状部材あるいは棒状突起部を法面に直接打ち込むことも可能であり、これにより打込み作業を一層容易に行うことができる。   In these cases, it is sufficient that the rod-like member or rod-like protrusion is driven into the slope to the extent necessary for temporary fixing of the separator connecting jig, and it is pulled out when casting concrete like a conventional anchor. Since it is not necessary to secure a reaction force to counteract the force, it can be easily performed by making a shallow drill hole in the slope and inserting a rod-shaped member or rod-shaped protrusion into the drill hole. At that time, if the ground constituting the slope is relatively soft, it is possible to directly drive the rod-shaped member or the rod-shaped protrusion to the slope, thereby making it possible to perform the driving operation more easily.

上記構成において、法面にモルタルを吹き付ける前に、法面にラス金網を張り付けるようにすれば、セパレータに作用する張力に対抗するための反力を、セパレータ連結用治具およびモルタルだけでなく、ラス金網によっても確保することができるので、施工の信頼性を一層高めることができる。   In the above configuration, before the mortar is sprayed on the slope, if a lath wire mesh is attached to the slope, the reaction force against the tension acting on the separator can be applied not only to the separator connecting jig and mortar. Since it can be secured by a lath wire mesh, the construction reliability can be further enhanced.

このように法面にラス金網を張り付けるようにした場合には、各セパレータ連結用治具の法面に対する仮固定を、該セパレータ連結用治具のフランジ部をラス金網に係止することにより行うようにすることも可能である。このようにした場合には、棒状部材あるいは棒状突起部の法面への打込みを不要とすることが可能となり、これにより施工効率を一層高めることができる。その際、ラス金網への係止と法面への打込みとを併用することも可能であり、このようにした場合には施工の信頼性をより一層高めることができる。   When the lath wire mesh is attached to the slope in this way, temporary fixing to the slope of each separator coupling jig is performed by locking the flange portion of the separator coupling jig to the lath wire mesh. It is also possible to do so. In such a case, it becomes possible to eliminate the need to drive the rod-shaped member or the rod-shaped protrusion into the slope, thereby further improving the construction efficiency. At that time, it is possible to use both the locking to the lath wire mesh and the driving to the slope, and in this case, the reliability of construction can be further enhanced.

上記構成において、各セパレータ連結用治具の先端部と各セパレータの基端部との連結方法が特に限定されないことも上述したとおりであるが、各セパレータ連結用治具の先端部にネジ孔を形成しておくとともに、各セパレータの基端部にネジ部を形成しておき、各セパレータの各セパレータ連結用治具に対する連結を、該セパレータをセパレータ連結用治具にネジ締めすることにより行うようにすれば、汎用のセパレータを用いて施工を行うことができ、これにより施工コスト低減効果を高めることができる。   In the above configuration, as described above, there is no particular limitation on the method of connecting the tip end portion of each separator connecting jig and the base end portion of each separator. However, a screw hole is provided at the tip end portion of each separator connecting jig. In addition to forming the threaded portion at the base end of each separator, the separator is connected to each separator connecting jig by screwing the separator to the separator connecting jig. If it makes it, construction can be performed using a general-purpose separator, and thereby the construction cost reduction effect can be enhanced.

上記構成において、各セパレータ連結用治具を、金属板に曲げ加工を施すことにより製作するようにすれば、打設されたコンクリートに埋め込まれて転用が利かないセパレータ連結用治具を低コストで製作することができ、これにより施工コスト低減効果を一層高めることができる。   In the above configuration, if each separator connecting jig is manufactured by bending a metal plate, the separator connecting jig which is embedded in the placed concrete and does not divert can be manufactured at low cost. It can be manufactured, and thereby the construction cost reduction effect can be further enhanced.

以下、図面を用いて、本願発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1は、本願発明の一実施形態に係るコンクリート擁壁構築方法を示す施工現場の側断面図である。また、図2は、図1のII部詳細図であり、図3は、図2のIII-III 線矢視断面詳細図である。   FIG. 1 is a side sectional view of a construction site showing a concrete retaining wall construction method according to an embodiment of the present invention. 2 is a detailed view of a portion II in FIG. 1, and FIG. 3 is a detailed cross-sectional view taken along the line III-III in FIG.

これらの図に示すように、本実施形態に係るコンクリート擁壁構築方法は、地山2の法面2aをもたれ擁壁として覆うコンクリート擁壁4を構築する方法であって、その工程の概要は次のようになっている。   As shown in these drawings, the concrete retaining wall construction method according to the present embodiment is a method of constructing a concrete retaining wall 4 leaning on the slope 2a of the natural ground 2 and covering it as a retaining wall, and the outline of the process is as follows. It is as follows.

すなわち、基端部にフランジ部10aが形成された複数のセパレータ連結用治具10を、地山2の法面2aに沿って互いに所定間隔をおいて配置した状態で法面2aに仮固定した後、法面2aにモルタル6を吹き付けることにより各セパレータ連結用治具10の基端部を法面2aに固定し、その後、各セパレータ連結用治具10の先端部にセパレータ20の基端部を連結するとともに、これら各セパレータ10の先端部に堰板22を法面2aと平行になるように設置し、この堰板22と法面2aとの間にコンクリートを打設するようになっている。   That is, a plurality of separator connecting jigs 10 having a flange portion 10a formed at the base end portion are temporarily fixed to the slope 2a in a state where they are arranged at predetermined intervals along the slope 2a of the natural ground 2. Thereafter, the base end of each separator coupling jig 10 is fixed to the slope 2 a by spraying mortar 6 on the slope 2 a, and then the base end of the separator 20 on the tip of each separator coupling jig 10. In addition, a barrier plate 22 is installed at the tip of each separator 10 so as to be parallel to the slope 2a, and concrete is placed between the barrier plate 22 and the slope 2a. Yes.

その際、各セパレータ連結用治具10としては、治具本体10Aの先端部にナット10Bが溶接されたものを用いるようになっている。   At that time, as each separator connecting jig 10, a jig main body 10 </ b> A having a nut 10 </ b> B welded to the tip is used.

治具本体10Aは、金属板に曲げ加工を施すことにより製作されるようになっている。すなわち、この治具本体10Aは、その先端部においてコ字状に折り曲げられるとともに、この先端部から平行に延びる1対の中間部の基端部において両側へ直角に折り曲げられており、これにより上記1対のフランジ部10aが形成されるようになっている。また、この治具本体10Aの各中間部における基端部近傍部位の両側部には、1対のタブ部10bが内側へ折り曲げられるようにして形成されている。さらに、この治具本体10Aの先端部には、ナット10Bのネジ径よりも大きい貫通孔が形成されている。そして、この治具本体10Aは、その1対の中間部の間隔および1対のタブ部10bの間隔が、棒状部材12の径と略同じ大きさに設定されている。   The jig body 10A is manufactured by bending a metal plate. That is, the jig body 10A is bent in a U-shape at the distal end portion thereof, and is bent at right angles to both sides at the base end portions of a pair of intermediate portions extending in parallel from the distal end portion. A pair of flange portions 10a are formed. Further, a pair of tab portions 10b are formed so as to be bent inward on both sides of the vicinity of the base end portion in each intermediate portion of the jig body 10A. Further, a through hole larger than the screw diameter of the nut 10B is formed at the tip of the jig body 10A. In the jig body 10A, the distance between the pair of intermediate portions and the distance between the pair of tab portions 10b are set to be approximately the same as the diameter of the rod-shaped member 12.

次に、本実施形態に係るコンクリート擁壁構築方法の工程を、図4〜10により詳細に説明する。   Next, the steps of the concrete retaining wall construction method according to the present embodiment will be described in detail with reference to FIGS.

まず、図4に示すように、地山2の法面2aに対して、上下および左右方向に各々所定間隔をおいて複数の浅いドリル穴2bをあけ、これら各ドリル穴2bに棒状部材12を打ち込む。その際、各ドリル穴2bの径は、棒状部材12の径と略同じ大きさに設定しておき、棒状部材12の打込みを容易に行い得るようにしておく。また、棒状部材12として、所定長の異形鋼棒を用い、ドリル穴2bの内壁との密着性を確保するようにする。そして、打ち込まれた棒状部材12は、その先端部を法面2aからある程度突出させるようにしておく。   First, as shown in FIG. 4, with respect to the slope 2a of the natural ground 2, a plurality of shallow drill holes 2b are formed at predetermined intervals in the vertical and horizontal directions, and the rod-like member 12 is formed in each of these drill holes 2b. Type in. At that time, the diameter of each drill hole 2b is set to be approximately the same as the diameter of the rod-shaped member 12, so that the rod-shaped member 12 can be driven easily. In addition, a deformed steel rod having a predetermined length is used as the rod-like member 12 to ensure adhesion with the inner wall of the drill hole 2b. Then, the rod-like member 12 that has been driven in has its tip portion protruded from the slope 2a to some extent.

次に、図5に示すように、各棒状部材12にセパレータ連結用治具10を各々装着し、これにより各セパレータ連結用治具10を法面2aに仮固定する。その際、セパレータ連結用治具10の棒状部材12への装着は、その治具本体10Aの1対の中間部および1対のタブ部10bで囲まれた隙間に棒状部材12を挿入させることにより行う。   Next, as shown in FIG. 5, the separator coupling jigs 10 are respectively attached to the respective rod-like members 12, thereby temporarily fixing the separator coupling jigs 10 to the slope 2a. At that time, the separator connecting jig 10 is attached to the rod-shaped member 12 by inserting the rod-shaped member 12 into a gap surrounded by the pair of intermediate portions and the pair of tab portions 10b of the jig body 10A. Do.

次に、図6に示すように、法面2aにモルタル6を吹き付けることにより、各セパレータ連結用治具10の基端部を法面2aに固定する。このモルタル6の吹付けは、法面2aの全域にわたって略同じ厚さ(例えば50mm程度)で行い、各セパレータ連結用治具10が半分程度埋設されるようにする。このモルタル吹付けの際、各セパレータ連結用治具10における治具本体10Aの先端部に形成された貫通孔およびナット10Bのネジ孔が、モルタルによって不用意に塞がれてしまわないようにするため、ビニルテープ等を各セパレータ連結用治具10の先端部に巻き付けておくことが好ましい。   Next, as shown in FIG. 6, the mortar 6 is sprayed on the slope 2a to fix the base end portion of each separator connecting jig 10 to the slope 2a. The spraying of the mortar 6 is performed with substantially the same thickness (for example, about 50 mm) over the entire area of the slope 2a so that about half of each separator connecting jig 10 is embedded. At the time of this mortar spraying, the through hole formed at the tip of the jig body 10A and the screw hole of the nut 10B in each separator connecting jig 10 are prevented from being inadvertently blocked by the mortar. Therefore, it is preferable to wind a vinyl tape or the like around the tip of each separator coupling jig 10.

その後、同図に示すように、各セパレータ連結用治具10の先端部にセパレータ20の基端部を連結する。その際、このセパレータ20として全ネジボルトを用い、これをセパレータ連結用治具10のナット10Bにネジ締めすることにより、その連結を行う。   Thereafter, as shown in the figure, the base end of the separator 20 is connected to the tip of each separator connecting jig 10. At that time, all the screw bolts are used as the separator 20, and are connected to the nut 10 </ b> B of the separator connecting jig 10 by screwing.

次に、図7に示すように、各セパレータ20の先端部にプラスチックコーン24を連結する。この連結は、プラスチックコーン24の雌ネジ部24aをセパレータ20の先端部にネジ締めすることにより行う。   Next, as shown in FIG. 7, a plastic cone 24 is connected to the tip of each separator 20. This connection is performed by screwing the female screw portion 24 a of the plastic cone 24 to the tip portion of the separator 20.

なお、このようにする代わりに、予めプラスチックコーン24をセパレータ20に連結した状態で、このセパレータ20をセパレータ連結用治具10に連結するようにしてもよい。   Instead of doing this, the separator 20 may be connected to the separator connecting jig 10 in a state where the plastic cone 24 is connected to the separator 20 in advance.

次に、図8に示すように、各プラスチックコーン24の型枠受面に堰板22を当接させて、堰板22を法面2aと平行になるように設置する。その際、堰板22として、適当なサイズの堰板22を複数枚用い、その端面を互いに密接させるようにして配置する。これら各堰板22の設置は、該堰板22に形成された小孔22aにプラスチックコーン24の雄ネジ部24bを挿入させることによって行う。そして、このようにした設置された複数の堰板22に対して、その背面側から複数の縦桟角パイプ26を当接させる。   Next, as shown in FIG. 8, the dam plate 22 is brought into contact with the mold receiving surface of each plastic cone 24, and the dam plate 22 is installed so as to be parallel to the slope 2a. At that time, a plurality of appropriately sized dam plates 22 are used as the dam plates 22, and the end surfaces thereof are arranged in close contact with each other. Each of the barrier plates 22 is installed by inserting the male screw portion 24b of the plastic cone 24 into the small hole 22a formed in the barrier plate 22. Then, a plurality of vertical beam pipes 26 are brought into contact with the plurality of dam plates 22 installed as described above from the back side.

次に、図9に示すように、堰板22の背面側に突出した各プラスチックコーン24の雄ネジ部24bにフォームタイ28の基端部をネジ締めにより連結した後、これら各フォームタイ28の上下両側に横桟丸パイプ30を配置して、これら各フォームタイ28の先端部にクランプ32を挿通させ、このクランプ32で両横桟丸パイプ30を縦桟角パイプ26に押し当てた状態で、ナット34をフォームタイ28に締め付けることにより、各堰板22の設置を完了させる。   Next, as shown in FIG. 9, after connecting the base end portion of the foam tie 28 to the male screw portion 24b of each plastic cone 24 protruding to the back side of the barrier plate 22 by screwing, The horizontal beam pipes 30 are arranged on both the upper and lower sides, the clamps 32 are inserted into the tip portions of the respective foam ties 28, and the both horizontal beam round pipes 30 are pressed against the vertical beam angle pipe 26 by the clamps 32. Then, the installation of each barrier plate 22 is completed by tightening the nut 34 to the foam tie 28.

そして、図10に示すように、法面2aと平行になるように設置された複数の堰板22と法面2aとの間にコンクリートを打設することにより、コンクリート擁壁4を構築する。   Then, as shown in FIG. 10, the concrete retaining wall 4 is constructed by placing concrete between the plurality of barrier plates 22 installed so as to be parallel to the slope 2a and the slope 2a.

その際、打設されたコンクリートから堰板22に作用する圧力により、各セパレータ20には所定の張力が作用するが、打設されたコンクリートの圧力は、法面2aに吹き付けられたモルタル6にも作用するとともに、このモルタル6を介して各セパレータ連結用治具10にも作用するので、これら各セパレータ連結用治具10およびモルタル6によって各セパレータ20の張力に対抗するための反力が確保され、各堰板22は法面2aと平行に設置された状態に維持される。   At that time, a predetermined tension acts on each separator 20 by the pressure acting on the barrier plate 22 from the placed concrete, but the pressure of the placed concrete is applied to the mortar 6 sprayed on the slope 2a. Since this also acts on each separator connecting jig 10 via this mortar 6, a reaction force for countering the tension of each separator 20 is secured by each of these separator connecting jig 10 and mortar 6. Thus, each barrier plate 22 is maintained in a state of being installed in parallel with the slope 2a.

以上詳述したように、本実施形態に係るコンクリート擁壁構築方法においては、基端部にフランジ部10aが形成された複数のセパレータ連結用治具10を、地山2の法面2aに沿って互いに所定間隔をおいて配置した状態で法面2aに仮固定した後、法面2aにモルタル6を吹き付けることにより各セパレータ連結用治具10の基端部を法面2aに固定し、その後、各セパレータ連結用治具10の先端部にセパレータ20の基端部を連結するとともに、これら各セパレータ20の先端部に堰板22を法面2aと平行になるように設置し、この堰板22と法面2aとの間にコンクリートを打設するようになっているので、次のような作用効果を得ることができる。   As described above in detail, in the concrete retaining wall construction method according to the present embodiment, a plurality of separator connecting jigs 10 each having a flange portion 10a formed at the base end portion are provided along the slope 2a of the natural ground 2. After temporarily fixing to the slope 2a in a state of being spaced apart from each other, the base end portion of each separator connecting jig 10 is fixed to the slope 2a by spraying the mortar 6 on the slope 2a, In addition, the base end of the separator 20 is connected to the tip of each separator connecting jig 10, and the barrier plate 22 is installed at the tip of each separator 20 so as to be parallel to the slope 2a. Since concrete is cast between the slope 22 and the slope 2a, the following effects can be obtained.

すなわち、法面2aに仮固定されたセパレータ連結用治具10は、モルタル吹付けにより法面2aに固定されるので、その後、打設されたコンクリートから堰板22に作用する圧力によってセパレータ20に所定の張力が作用しても、この張力に対抗するための反力をセパレータ連結用治具10およびモルタル6によって確保することができる。   That is, the separator coupling jig 10 temporarily fixed to the slope 2a is fixed to the slope 2a by mortar spraying, and then applied to the separator 20 by the pressure acting on the barrier plate 22 from the placed concrete. Even if a predetermined tension is applied, a reaction force to counter this tension can be secured by the separator connecting jig 10 and the mortar 6.

その際、セパレータ連結用治具10の法面2aへの仮固定は、セパレータ連結用治具10の仮固定およびモルタル吹付けにより行われるので、従来のようなアンカ等の打込作業に比して法面2aへの固定を簡易に行うことができ、これにより施工効率を高めることができる。   At that time, the separator fixing jig 10 is temporarily fixed to the slope 2a by temporary fixing of the separator connecting jig 10 and mortar spraying. Thus, the fixing to the slope 2a can be easily performed, thereby improving the construction efficiency.

また、セパレータ20に作用する張力に対抗するための反力を、従来のようにアンカ等の引抜き抵抗力に依存するのではなく、打設されたコンクリートの圧力を利用してセパレータ連結用治具10およびモルタル6により確保するようになっているので、定量的な施工管理を行うことができる。   Further, the reaction force for countering the tension acting on the separator 20 does not depend on the pulling resistance force of an anchor or the like as in the prior art, but the separator connecting jig using the pressure of the placed concrete. Since 10 and the mortar 6 ensure, quantitative construction management can be performed.

したがって本実施形態によれば、地山2の法面2aを覆うコンクリート擁壁4を構築する際の施工コスト低減を図ることができ、また、その施工の信頼性を高めることができる。   Therefore, according to this embodiment, the construction cost at the time of constructing the concrete retaining wall 4 covering the slope 2a of the natural ground 2 can be reduced, and the reliability of the construction can be enhanced.

特に本実施形態においては、各セパレータ連結用治具10の法面2aに対する仮固定を、法面2aに棒状部材12を予め打ち込んでおくとともに、この棒状部材12にセパレータ連結用治具10を装着することにより行うようになっているので、セパレータ連結用治具10の構成を簡素化した上で、該セパレータ連結用治具10の法面2aへの仮固定を確実に行うことができる。   In particular, in the present embodiment, each separator coupling jig 10 is temporarily fixed to the slope 2a, and a rod-shaped member 12 is driven in advance on the slope 2a, and the separator coupling jig 10 is attached to the rod-shaped member 12. Thus, the configuration of the separator connecting jig 10 can be simplified and the temporary fixing of the separator connecting jig 10 to the slope 2a can be reliably performed.

その際、法面2aに対する棒状部材12の打込みは、セパレータ連結用治具10の仮固定のために必要な程度に行えば足り、従来のアンカ等のようにコンクリート打設時の引抜き力に対抗するための反力を確保する必要はないので、法面2aに浅いドリル穴2bをあけて、このドリル穴2bに棒状部材12を打ち込むことにより(あるいは挿し込むことにより)容易に行うことができる。その際、地山2の法面2aを構成する地盤が比較的軟弱であれば、棒状部材12を法面2aに直接打ち込むことも可能であり、これにより打込み作業を一層容易に行うことができる。   At this time, it is sufficient that the rod-like member 12 is driven into the slope 2a to the extent necessary for temporarily fixing the separator connecting jig 10, and the pulling force at the time of concrete pouring is counteracted like a conventional anchor. Therefore, it is not necessary to secure a reaction force for the purpose of drilling, so that a shallow drill hole 2b is formed in the slope 2a and the rod-like member 12 is driven (or inserted) into the drill hole 2b. . At that time, if the ground constituting the slope 2a of the natural ground 2 is relatively soft, it is possible to directly drive the rod-like member 12 into the slope 2a, thereby making it possible to perform the driving work more easily. .

また本実施形態においては、各セパレータ連結用治具10を、治具本体10Aの先端部にナット10Bが溶接された構成としておくとともに、各セパレータ20として全ネジボルトを用い、これら各セパレータ20の各セパレータ連結用治具10に対する連結を、該セパレータ20をセパレータ連結用治具10にネジ締めすることにより行うようになっているので、汎用のセパレータ20を用いて施工を行うことができ、これにより施工コスト低減効果を高めることができる。   Further, in this embodiment, each separator coupling jig 10 is configured such that a nut 10B is welded to the tip of the jig body 10A, and all the screw bolts are used as the separators 20. Since the separator 20 is connected to the separator connecting jig 10 by screwing the separator 20 to the separator connecting jig 10, the general-purpose separator 20 can be used for construction. The construction cost reduction effect can be enhanced.

さらに本実施形態においては、各セパレータ連結用治具10の治具本体10Aを、金属板に曲げ加工を施すことにより製作するようになっているので、打設されたコンクリートに埋め込まれて転用が利かないセパレータ連結用治具10を低コストで製作することができ、これにより施工コスト低減効果を一層高めることができる。   Further, in the present embodiment, the jig body 10A of each separator coupling jig 10 is manufactured by bending a metal plate, so that it can be diverted by being embedded in the placed concrete. The useless separator coupling jig 10 can be manufactured at low cost, and the construction cost reduction effect can be further enhanced.

なお、上記実施形態において、堰板22を設置する前に、鉄筋を適当に組み立てて法面2aに沿って配置しておくことにより、コンクリート擁壁4を鉄筋コンクリート構造とすることも可能である。   In addition, in the said embodiment, before installing the barrier plate 22, it is also possible to make the concrete retaining wall 4 into a reinforced concrete structure by assembling a reinforcing bar appropriately and arrange | positioning along the slope 2a.

また、上記実施形態においては、セパレータ連結用治具10として、治具本体10Aの先端部にナット10Bが溶接されたものを用いるものとして説明したが、治具本体10Aの先端部に直接ネジ孔を形成するようにしてもよく、このようにした場合にはナット10Bの溶接を不要とすることができる。   Moreover, in the said embodiment, although demonstrated as what uses the nut 10B welded to the front-end | tip part of the jig | tool main body 10A as the separator connection jig | tool 10, it is directly screwed in the front-end | tip part of the jig | tool main body 10A. In this case, the nut 10B need not be welded.

次に、上記実施形態の変形例について説明する。   Next, a modification of the above embodiment will be described.

まず、上記実施形態の第1変形例について説明する。   First, a first modification of the above embodiment will be described.

図11は、本変形例に係るコンクリート擁壁構築方法を示す、図5と同様の図である。   FIG. 11 is a view similar to FIG. 5 showing a concrete retaining wall construction method according to this modification.

同図に示すように、本変形例においては、上記実施形態のセパレータ連結用治具10の代わりにセパレータ連結用治具110を用いる点で上記実施形態の場合と異なっているが、それ以外の工程は上記実施形態の場合と同様である。   As shown in the figure, this modification is different from the above embodiment in that a separator connecting jig 110 is used instead of the separator connecting jig 10 of the above embodiment. The process is the same as in the above embodiment.

このセパレータ連結用治具110は、その基端部に環状のフランジ部110aが形成されるとともにその基端部中央に棒状突起部110bが形成される一方、その先端部にセパレータ連結用のネジ孔110cが形成された構成となっており、鋳造等により製作されるようになっている。   The separator connecting jig 110 is formed with an annular flange portion 110a at the base end portion and a rod-like protrusion 110b at the center of the base end portion, and a screw hole for connecting the separator at the tip end portion. 110c is formed and is manufactured by casting or the like.

そして、本変形例においては、各セパレータ連結用治具110の棒状突起部110bを法面2aの各ドリル穴2bに打ち込むことにより(あるいは挿し込むことにより)、各セパレータ連結用治具110の法面2aへの仮固定を行うようになっている。   In this modification, the rod-shaped protrusion 110b of each separator connecting jig 110 is driven (or inserted) into each drill hole 2b of the slope 2a, whereby the method of each separator connecting jig 110 is obtained. Temporary fixing to the surface 2a is performed.

本変形例の方法を採用することにより、上記実施形態の場合のように法面2aに予め棒状部材12を打ち込んでおく必要をなくすことができ、これによりコンクリート擁壁4の構築に必要な機材を削減することができる。   By adopting the method of this modification, it is possible to eliminate the need to drive the bar-shaped member 12 into the slope 2a in advance as in the case of the above-described embodiment, and thus the equipment necessary for the construction of the concrete retaining wall 4 Can be reduced.

なお、本変形例の方法を採用した場合においても、地山2の法面2aを構成する地盤が比較的軟弱であれば、棒状突起部110bを法面2aに直接打ち込むことも可能であり、これにより打込み作業を一層容易に行うことができる。   Even when the method of the present modification is adopted, if the ground constituting the slope 2a of the natural ground 2 is relatively soft, the rod-shaped protrusion 110b can be directly driven into the slope 2a. Thereby, the driving operation can be performed more easily.

次に、上記実施形態の第2変形例について説明する。   Next, a second modification of the above embodiment will be described.

図12は、本変形例に係るコンクリート擁壁構築方法を示す、図3と同様の図である。   FIG. 12 is a view similar to FIG. 3 showing a concrete retaining wall construction method according to this modification.

同図に示すように、本変形例においては、法面2aにモルタル6を吹き付ける前に、法面2aにラス金網40を張り付けるとともに、各セパレータ連結用治具10の法面2aに対する仮固定を、上記実施形態の場合のように法面2aに打ち込まれた棒状部材12にセパレータ連結用治具10を装着する代わりに、セパレータ連結用治具210のフランジ部210aをラス金網40に係止することにより行うようになっている。   As shown in the figure, in this modification, before the mortar 6 is sprayed on the slope 2a, a lath wire mesh 40 is attached to the slope 2a, and each separator connecting jig 10 is temporarily fixed to the slope 2a. Instead of attaching the separator connecting jig 10 to the rod-like member 12 driven into the slope 2a as in the above embodiment, the flange portion 210a of the separator connecting jig 210 is locked to the lath metal mesh 40. To do it.

このため、本変形例においては、セパレータ連結用治具210として、上記実施形態の場合と同様、治具本体210Aの先端部にナット210Bが溶接されたものを用いるようになっているが、その治具本体210Aには、上記実施形態のセパレータ連結用治具10における治具本体10Aの場合のようなタブ部10bは形成されておらず、その分だけ構成が簡素化されている。   For this reason, in this modification, as in the case of the above-described embodiment, the separator coupling jig 210 is such that a nut 210B is welded to the tip of the jig body 210A. The tab portion 10b as in the case of the jig body 10A in the separator coupling jig 10 of the above embodiment is not formed on the jig body 210A, and the configuration is simplified accordingly.

本変形例の方法を採用することにより、セパレータ20に作用する張力に対抗するための反力を、セパレータ連結用治具210およびモルタル6だけでなく、ラス金網40によっても確保することができるので、施工の信頼性を一層高めることができる。また、各セパレータ連結用治具210の法面2aに対する仮固定を、セパレータ連結用治具210のフランジ部210aをラス金網40に係止することにより行うようになっているので、上記実施形態の場合のような棒状部材12の法面2aへの打込みを不要とすることができ、これにより施工効率を一層高めることができる。   By adopting the method of this modification, a reaction force to counter the tension acting on the separator 20 can be secured not only by the separator connecting jig 210 and the mortar 6 but also by the lath metal mesh 40. The construction reliability can be further improved. Further, the temporary fixing of the separator connecting jig 210 to the slope 2a is performed by locking the flange portion 210a of the separator connecting jig 210 to the lath metal mesh 40. It is possible to eliminate the need for driving the rod-like member 12 into the slope 2a as in the case, thereby further improving the construction efficiency.

なお、本変形例において、セパレータ連結用治具210の位置決めをより確実に行うようにするため、結束用鋼線等を用いて治具本体210Aをラス金網40に適宜巻き付けるようにしてもよい。   In this modification, the jig main body 210A may be appropriately wound around the lath metal mesh 40 using a binding steel wire or the like in order to more reliably position the separator coupling jig 210.

また、本変形例のように、各セパレータ連結用治具210をラス金網40に係止するだけでなく、これら各セパレータ連結用治具210を上記実施形態の場合のように法面2aに打ち込まれた棒状部材12に装着するようにすることも可能であり、このようにすることにより施工の信頼性をより一層高めることができる。   Further, as in the present modified example, not only each separator coupling jig 210 is locked to the lath metal mesh 40, but also each separator coupling jig 210 is driven into the slope 2a as in the above embodiment. It is also possible to attach to the rod-shaped member 12 which has been made, and by doing so, the reliability of construction can be further enhanced.

本願発明の一実施形態に係るコンクリート擁壁構築方法を示す施工現場の側断面図Side sectional view of a construction site showing a concrete retaining wall construction method according to an embodiment of the present invention 図1のII部詳細図Detailed view of part II in Fig. 1 図2のIII-III 線矢視断面詳細図Detailed cross-sectional view taken along line III-III in FIG. 上記コンクリート擁壁構築方法の工程図(その1)Process diagram of the concrete retaining wall construction method (Part 1) 上記コンクリート擁壁構築方法の工程図(その2)Process diagram of the concrete retaining wall construction method (Part 2) 上記コンクリート擁壁構築方法の工程図(その3)Process diagram of the concrete retaining wall construction method (Part 3) 上記コンクリート擁壁構築方法の工程図(その4)Process diagram of the concrete retaining wall construction method (Part 4) 上記コンクリート擁壁構築方法の工程図(その5)Process diagram of the concrete retaining wall construction method (Part 5) 上記コンクリート擁壁構築方法の工程図(その6)Process drawing of the concrete retaining wall construction method (Part 6) 上記コンクリート擁壁構築方法工程図(その7)The concrete retaining wall construction method process diagram (Part 7) 上記実施形態の第1変形例を示す、図5と同様の図The same figure as FIG. 5 which shows the 1st modification of the said embodiment. 上記実施形態の第2変形例を示す、図3と同様の図The same figure as FIG. 3 which shows the 2nd modification of the said embodiment.

符号の説明Explanation of symbols

2 地山
2a 法面
2b ドリル穴
4 コンクリート擁壁
6 モルタル
10、110、210 セパレータ連結用治具
10A、210A 治具本体
10B、210B ナット
10a、110a、210a フランジ部
10b タブ部
12 棒状部材
20 セパレータ
22 堰板
22a 小孔
24 プラスチックコーン
24a 雌ネジ部
24b 雄ネジ部
26 縦桟角パイプ
28 フォームタイ
30 横桟丸パイプ
32 クランプ
40 ラス金網
110b 棒状突起部
110c ネジ孔
2 Natural ground 2a Slope 2b Drill hole 4 Concrete retaining wall 6 Mortar 10, 110, 210 Separator connecting jig 10A, 210A Jig body 10B, 210B Nut 10a, 110a, 210a Flange part 10b Tab part 12 Bar-shaped member 20 Separator 22 Barrage 22a Small hole 24 Plastic cone 24a Female thread part 24b Male thread part 26 Vertical beam square pipe 28 Foam tie 30 Horizontal beam round pipe 32 Clamp 40 Lath wire mesh 110b Bar-shaped protrusion 110c Screw hole

Claims (7)

法面を覆うコンクリート擁壁を構築するコンクリート擁壁構築方法において、
基端部にフランジ部が形成された複数のセパレータ連結用治具を、法面に沿って互いに所定間隔をおいて配置した状態で上記法面に仮固定した後、上記法面にモルタルを吹き付けることにより上記各セパレータ連結用治具の基端部を上記法面に固定し、
その後、上記各セパレータ連結用治具の先端部にセパレータの基端部を連結するとともに、これら各セパレータの先端部に堰板を上記法面と略平行になるように設置し、この堰板と上記法面との間にコンクリートを打設する、ことを特徴とするコンクリート擁壁構築方法。
In the concrete retaining wall construction method of constructing the concrete retaining wall covering the slope,
A plurality of separator coupling jigs having flange portions formed at the base end are temporarily fixed to the slope in a state of being arranged at predetermined intervals along the slope, and then mortar is sprayed on the slope. By fixing the base end portion of each separator connecting jig to the slope,
Thereafter, the base end of the separator is connected to the tip of each separator connecting jig, and a dam plate is installed at the tip of each separator so as to be substantially parallel to the slope, A concrete retaining wall construction method characterized by placing concrete between the slopes.
上記各セパレータ連結用治具の上記法面に対する仮固定を、上記法面に棒状部材を予め打ち込んでおくとともに、この棒状部材に上記セパレータ連結用治具を装着することにより行う、ことを特徴とする請求項1記載のコンクリート擁壁構築方法。   The temporary fixing of each separator coupling jig to the slope is performed by driving a rod-shaped member into the slope in advance and attaching the separator coupling jig to the rod-shaped member. The concrete retaining wall construction method according to claim 1. 上記各セパレータ連結用治具の上記法面に対する仮固定を、上記各セパレータ連結用治具に棒状突起部を予め設けておくとともに、この棒状突起部を上記法面に打ち込むことにより行う、ことを特徴とする請求項1記載のコンクリート擁壁構築方法。   Temporarily fixing each separator coupling jig to the slope is performed by previously providing each separator coupling jig with a rod-shaped protrusion and driving the rod-shaped protrusion into the slope. The concrete retaining wall construction method according to claim 1, wherein the concrete retaining wall is constructed. 上記法面にモルタルを吹き付ける前に、上記法面にラス金網を張り付ける、ことを特徴とする請求項1〜3いずれか記載のコンクリート擁壁構築方法。   The method for constructing a concrete retaining wall according to any one of claims 1 to 3, wherein a lath wire mesh is attached to the slope before the mortar is sprayed on the slope. 上記各セパレータ連結用治具の上記法面に対する仮固定を、上記各セパレータ連結用治具のフランジ部を上記ラス金網に係止することにより行う、ことを特徴とする請求項4記載のコンクリート擁壁構築方法。   5. The concrete support according to claim 4, wherein the separator fixing jig is temporarily fixed to the slope by engaging a flange portion of the separator connecting jig with the lath metal mesh. Wall construction method. 上記各セパレータ連結用治具の先端部にネジ孔を形成しておくとともに、上記各セパレータの基端部にネジ部を形成しておき、
上記各セパレータの上記各セパレータ連結用治具に対する連結を、該セパレータを上記セパレータ連結用治具にネジ締めすることにより行う、ことを特徴とする請求項1〜5いずれか記載のコンクリート擁壁構築方法。
While forming a screw hole at the tip of each separator coupling jig, and forming a screw part at the base end of each separator,
The concrete retaining wall construction according to any one of claims 1 to 5, wherein the separator is connected to the separator connecting jig by screwing the separator to the separator connecting jig. Method.
上記各セパレータ連結用治具を、金属板に曲げ加工を施すことにより製作する、ことを特徴とする請求項1〜6いずれか記載のコンクリート擁壁構築方法。   The concrete retaining wall construction method according to any one of claims 1 to 6, wherein each of the separator connecting jigs is manufactured by bending a metal plate.
JP2005139171A 2005-05-11 2005-05-11 Construction method for concrete retaining wall Pending JP2006316474A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005139171A JP2006316474A (en) 2005-05-11 2005-05-11 Construction method for concrete retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005139171A JP2006316474A (en) 2005-05-11 2005-05-11 Construction method for concrete retaining wall

Publications (1)

Publication Number Publication Date
JP2006316474A true JP2006316474A (en) 2006-11-24

Family

ID=37537390

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005139171A Pending JP2006316474A (en) 2005-05-11 2005-05-11 Construction method for concrete retaining wall

Country Status (1)

Country Link
JP (1) JP2006316474A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101730877B1 (en) * 2016-08-17 2017-04-28 지반이엔씨 주식회사 Establishing method for attached wall in slope using the module for fixing in slope

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60130958U (en) * 1984-02-13 1985-09-02 相馬 時男 Tension material installation adjustment hardware for sheet piles
JPS6197446U (en) * 1984-11-30 1986-06-23
JPH01244071A (en) * 1988-03-25 1989-09-28 Mineichi Iwamoto Metal spacer for concrete placement
JPH0687436U (en) * 1993-06-04 1994-12-22 秀行 外山 Temporary frame spacing adjuster

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60130958U (en) * 1984-02-13 1985-09-02 相馬 時男 Tension material installation adjustment hardware for sheet piles
JPS6197446U (en) * 1984-11-30 1986-06-23
JPH01244071A (en) * 1988-03-25 1989-09-28 Mineichi Iwamoto Metal spacer for concrete placement
JPH0687436U (en) * 1993-06-04 1994-12-22 秀行 外山 Temporary frame spacing adjuster

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101730877B1 (en) * 2016-08-17 2017-04-28 지반이엔씨 주식회사 Establishing method for attached wall in slope using the module for fixing in slope

Similar Documents

Publication Publication Date Title
JP5854508B2 (en) Yamato wall support structure
JP2007239437A (en) Tie cable binding device
JP2006316474A (en) Construction method for concrete retaining wall
JP2015134984A (en) Structure and method for joining reinforced concrete beam and reinforced concrete-filled steel pipe column together
JP4659017B2 (en) Anchor bolt
JP2011043025A (en) Method for reinforcing structure using tensional material
JP2011021711A (en) Steel sheet fastener and steel sheet joining method
JP2005133360A (en) Dowel after putting type embedded hardware
JP2010095971A (en) Mounting implement for sheet pile fall prevention fence
JP4844477B2 (en) Synthetic wall structure and its construction method
KR100865991B1 (en) Clamp for a scaffold pipe
JP4421123B2 (en) Construction method of underground outer wall of structure
JP3826348B2 (en) Construction method of composite wall with mountain retaining core and underground outer wall
KR200421375Y1 (en) Casket anchor
JP2010203097A (en) Member for fixing bolt on wall surface, and method for mounting the same
JP4854607B2 (en) Segment joint structure
JP2009162029A (en) Retaining wall
KR20070068991A (en) Bar type anchor
JP2006291535A (en) Pole reinforcing fitting and fixing method for the reinforcing fitting
JP2006257715A (en) Joint structure for steel pipe sheet pile, and method of constructing steel pipe sheet pile
CN215857650U (en) Prefabricated underground continuous wall structure
JP5221748B2 (en) Recessed column base sheath tube
JP6893949B2 (en) Connection structure and connection method between members
JP6460613B1 (en) Separator shaft fixing bracket
JP4277935B1 (en) Steel erection method, steel erection jig

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20071115

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Effective date: 20091127

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20091208

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100406