JP2006104709A - Pier and construction method thereof - Google Patents

Pier and construction method thereof Download PDF

Info

Publication number
JP2006104709A
JP2006104709A JP2004290415A JP2004290415A JP2006104709A JP 2006104709 A JP2006104709 A JP 2006104709A JP 2004290415 A JP2004290415 A JP 2004290415A JP 2004290415 A JP2004290415 A JP 2004290415A JP 2006104709 A JP2006104709 A JP 2006104709A
Authority
JP
Japan
Prior art keywords
girder
pier
main
conducting
steel pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004290415A
Other languages
Japanese (ja)
Other versions
JP4109664B2 (en
Inventor
Shozo Iwai
省三 岩井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hanshin Kensetsu Co Ltd
Original Assignee
Hanshin Kensetsu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hanshin Kensetsu Co Ltd filed Critical Hanshin Kensetsu Co Ltd
Priority to JP2004290415A priority Critical patent/JP4109664B2/en
Publication of JP2006104709A publication Critical patent/JP2006104709A/en
Application granted granted Critical
Publication of JP4109664B2 publication Critical patent/JP4109664B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Revetment (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a pier which can be constructed in a short period of time, and a construction method of the pier. <P>SOLUTION: Firstly, an abutment 7 is constructed on one bank, and three main girders 4a about twice longer than a span are elongated in a river crossing direction from the abutment 7 in such a manner that the abutment 7 serves as a base point. Next, a material guiding girder 2a is temporarily held in the central section of the main girder 4a (refer to Fig. 6(a)). Subsequently, after the temporarily held girder 2a is fixed, a material guiding girder 2b is temporarily held at the leading end of the main girder 4a, and fixed. Two main girders 4b about twice longer than the span are further elongated in the river crossing direction from the girder 2a in such a manner as to lay astride the girder 2b. A material guiding girder 2c is temporarily held at the leading end of the main girder 4b (refer to Fig. 6(c)). After that, the above operations are repeated. This enables the pier to be constructed in a short period of time. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

この発明は、桟橋およびその施工方法に関する。   The present invention relates to a jetty and a construction method thereof.

従来から、河川や渓谷において、様々な仮設桟橋が利用されている。たとえば、河川において、対岸で工事を行う場合には、一時的な橋として仮設桟橋が構築される。そして、その仮設桟橋を利用することで対岸における工事が円滑に行われる。この種の仮設桟橋が特許文献1に記載されている。
特開2001−115421号公報
Conventionally, various temporary piers are used in rivers and valleys. For example, when construction is performed on the opposite shore in a river, a temporary pier is constructed as a temporary bridge. And the construction on the opposite shore is smoothly performed by using the temporary pier. This type of temporary pier is described in Patent Document 1.
JP 2001-115421 A

上記の仮設桟橋の施工は、まず、仮設桟橋の根元部分から仮設桟橋の架設方向に複数のビームを張り出す。そして、張り出した各ビームの先端部分にそれぞれ仮杭を打設し、打設した各仮杭の上端部によって各ビームを支持する。次いで、支持された各ビームを基盤として、複数の支柱を打設し、各支柱の上部に、横桁、ブレス、主桁、覆工板等を取り付ける。そして、仮設桟橋の架設方向に各ビームを送り出し、その後は、上記工程を繰り返すことで仮設桟橋を構築する。   In the construction of the temporary pier, first, a plurality of beams are projected from the base of the temporary pier in the direction of the temporary pier. Then, temporary piles are placed at the tip portions of the overhanging beams, and the beams are supported by the upper ends of the placed temporary piles. Next, a plurality of pillars are driven using each supported beam as a base, and a horizontal girder, a bracelet, a main girder, a lining plate, etc. are attached to the upper part of each pillar. And each beam is sent out in the construction direction of the temporary pier, and then the above steps are repeated to construct the temporary pier.

ところで、仮設桟橋は、一時的な橋として構築され、それを利用して工事等が行われるものであるため、仮設桟橋が構築されなければ工事等を行うことができない。ゆえに、仮設桟橋は短期間で構築されることが望ましい。
しかしながら、上記の仮設桟橋の構築においては、ビームや仮杭を用いるため、その工程が多くなり、結果として構築するまでの期間が長くなってしまう。
By the way, since a temporary pier is constructed as a temporary bridge and construction is performed using the temporary pier, construction or the like cannot be performed unless the temporary pier is constructed. Therefore, it is desirable that the temporary pier be constructed in a short period of time.
However, in the construction of the above-mentioned temporary pier, since beams and temporary piles are used, the number of processes is increased, and as a result, the period until the construction is increased.

この発明は、かかる背景をもとになされたもので、短期間で構築することのできる桟橋およびその施工方法提供することを目的とする。   The present invention has been made based on such a background, and an object thereof is to provide a pier that can be constructed in a short period of time and a construction method therefor.

上記目的を達成するための請求項1に記載の発明は、架設方向と直交する方向に平行に、かつ、架設方向に一定間隔をあけて設けられた複数の導材桁(2)と、各導材桁を支持するように、上部は導材桁に固定され、下部は地中に打ち込まれた複数の鋼杭(3)と、導材桁と導材桁との間に掛け渡されて架設方向に延びる主桁(4)と、を備え、上記導材桁は、2本の溝形鋼(211)が上記鋼杭を差し込める隙間をあけて平行に連結された上桁(21)を有し、上記鋼杭は、上記導材桁の上桁を構成する2本の溝形鋼の隙間から垂直下方に差し込まれて、下部は地中に打ち込まれ、上部は上記上桁に対して上下に移動しないように固定されていることを特徴とする桟橋(1)である。   The invention described in claim 1 for achieving the above object comprises a plurality of conductive girders (2) provided parallel to a direction orthogonal to the erection direction and at a predetermined interval in the erection direction, The upper part is fixed to the conductive material girder so as to support the conductive material girder, and the lower part is spanned between a plurality of steel piles (3) driven into the ground and between the conductive material girder and the conductive material girder. A main girder (4) extending in the erection direction, and the guide girder is an upper girder (21) connected in parallel with a gap through which the two steel pipes (211) can be inserted. The steel pile is inserted vertically downward from the gap between two channel steels constituting the upper girder of the conductive material girder, the lower part is driven into the ground, and the upper part is against the upper girder The pier (1) is fixed so as not to move up and down.

請求項2に記載の発明は、上記導材桁(2)は、上記上桁(21)の下方で、上記上桁と平行に延びる補助桁(22)と、上記上桁および上記補助桁を連結する複数のブレス(23)とを有し、上記鋼杭(3)は、上記補助桁を経由して差し込まれることを特徴とする請求項1に記載の桟橋(1)である。
なお、括弧内の英数字は、後述の実施形態における対応構成要素を表す。以下、この項において同じ。
The invention according to claim 2 is characterized in that the conductive material beam (2) includes an auxiliary beam (22) extending in parallel with the upper beam below the upper beam (21), the upper beam and the auxiliary beam. The pier (1) according to claim 1, further comprising a plurality of braces (23) to be connected, wherein the steel pile (3) is inserted via the auxiliary girder.
The alphanumeric characters in parentheses represent corresponding components in the embodiments described later. The same applies hereinafter.

これらの構成によれば、桟橋は、導材桁を備えており、その導材桁は、上桁、補助桁およびブレスを有している。たとえば、前もって工場にて導材桁を組立てておき、現場にてその導材桁を用いれば、桟橋を構築するための工程を少なくすることができ、桟橋を短期間で構築できる。
請求項3に記載の発明は、導材桁(2)を用いて桟橋(1)を施工する方法であって、上記導材桁は、2本の溝形鋼(211)が鋼杭(3)を差し込める隙間をあけて平行に連結された上桁(21)を有するものであり、桟橋の根元部分に設けた橋台(7)から、架設方向に第1の主桁(4a)を延ばして、仮杭で先端側を仮保持し、上記第1の主桁のほぼ中央部に、架設方向と直交する方向に平行に設ける第1の導材桁(2a)を水平方向に仮保持し、上記仮保持した第1の導材桁の上桁を構成する2本の溝形鋼の隙間から垂直下方に鋼杭を差し込み、当該差し込んだ鋼杭の下部を地中に打ち込んだ後、その上部を上桁に固定し、さらに、上記第1の主桁の先端部に、上述と同様にして、鋼杭により固定された第2の導材桁(2b)を取り付け、鋼杭で支持された第2の導材桁をまたぎ、上記第1の導材桁から、さらに架設方向前方に向けて延びる第2の主桁(4b)を取り付け、その後、上記第2の導材桁と同様の手順で、複数の導材桁(2c,2d)を順次取り付けていくことを特徴とする桟橋の施工方法である。
According to these structures, the pier is provided with the conducting material girder, and the conducting material girder has the upper girder, the auxiliary girder, and the breath. For example, if a conducting girder is assembled in advance in a factory and the conducting girder is used in the field, the steps for constructing the pier can be reduced, and the pier can be constructed in a short period of time.
Invention of Claim 3 is a method of constructing a pier (1) using a conducting material girder (2), Comprising: As for the said conducting material girder, two channel steels (211) are steel piles (3 ) With the upper girder (21) connected in parallel with a gap for inserting the first main girder (4a) in the erection direction from the abutment (7) provided at the base of the pier. Temporarily hold the tip side with a temporary pile, and temporarily hold the first guide beam (2a) provided parallel to the direction perpendicular to the erection direction at the substantially central portion of the first main beam in the horizontal direction. After inserting the steel pile vertically downward from the gap between the two channel steels constituting the upper girder of the first conducting girder temporarily held above, and driving the lower part of the inserted steel pile into the ground, The upper part is fixed to the upper girder, and a second conductor girder (2b) fixed by a steel pile is attached to the tip of the first main girder in the same manner as described above. The second main girder (4b) extending across the second conducting girder supported by the steel pile and extending from the first conducting girder further forward in the erection direction is attached. The construction method of the jetty is characterized in that a plurality of conducting girders (2c, 2d) are sequentially attached in the same procedure as the conducting girders.

請求項4に記載の発明は、上記導材桁(2)は、上記上桁(21)の下方で、上記上桁と平行に延びる補助桁(22)と、上記上桁および上記補助桁を連結する複数のブレス(23)とを有し、上記鋼杭(3)は、上記補助桁を経由して差し込むことを特徴とする請求項3に記載の桟橋(1)の施工方法である。
これらの方法によれば、桟橋を短期間で構築することができる。たとえば、前もって工場にて導材桁を組立てておき、現場にてその導材桁を用いれば、桟橋を構築するための工程を少なくすることができる。
According to a fourth aspect of the present invention, the guide beam (2) includes an auxiliary girder (22) extending in parallel with the upper girder below the upper girder (21), the upper girder and the auxiliary girder. It has a plurality of braces (23) to connect, and the steel pile (3) is inserted through the auxiliary girder, The construction method of the pier (1) according to claim 3 characterized by things.
According to these methods, the pier can be constructed in a short period of time. For example, if a conductor girder is assembled in advance in a factory and the conductor girder is used in the field, the steps for constructing a pier can be reduced.

また、主桁が、導材桁をまたぐようにして架設方向前方に延ばされるので、桟橋に用いられる主桁の数が少なくなり、桟橋をより短期間で構築することができる。
また、導材桁は、主桁の先端部で仮保持された後に固定されるため、導材桁を仮保持してから固定するまでの時間を短縮することができ、桟橋全体の構築期間を短くすることができる。
Further, since the main girder is extended forward in the erection direction so as to straddle the conductive material girder, the number of main girder used for the pier is reduced, and the pier can be constructed in a shorter period of time.
In addition, since the guide girders are fixed after being temporarily held at the tip of the main girder, it is possible to shorten the time from temporarily holding the guide girders until they are fixed, and the construction period of the entire pier Can be shortened.

以下では、この発明の実施の形態を、添付図面を参照して詳細に説明する。
図1は、この発明の一実施形態にかかる桟橋1を示す平面図であり、図2は、図1の矢印A方向にみた図であり、図3は、図2の矢印B方向にみた図である。
桟橋1は、河川を横断するように構築されており、架設方向が河川横断方向とされ、架設方向と直交する方向が河川の流れの方向とされている。
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a plan view showing a pier 1 according to an embodiment of the present invention, FIG. 2 is a view seen in the direction of arrow A in FIG. 1, and FIG. 3 is a view seen in the direction of arrow B in FIG. It is.
The pier 1 is constructed so as to cross the river, and the installation direction is the river crossing direction, and the direction perpendicular to the installation direction is the river flow direction.

桟橋1には、河川の流れに平行に延び、かつ、河川横断方向に一定間隔をあけて設けられている複数の導材桁2と、各導材桁2を支持している複数の鋼杭3と、各導材桁2間に掛け渡されて河川横断方向に延びる複数の主桁4と、河川の流れに平行に延び、各主桁4をまたぐようにして各主桁4上に設けられている複数の横桁5と、各横桁5上に敷設された複数の覆工板6とが備えられている。   The pier 1 includes a plurality of conductor girders 2 that extend in parallel to the river flow and are provided at regular intervals in the river transverse direction, and a plurality of steel piles that support the respective conductor girders 2. 3, a plurality of main girders 4 extending in the cross-river direction spanning between the respective guide girders 2, and extending on the main girders 4 so as to extend parallel to the river flow and straddle the main girders 4 A plurality of horizontal girders 5 and a plurality of lining plates 6 laid on each of the cross girders 5 are provided.

図4は、導材桁2の構成を詳しく示す図であり、図4(a)は、導材桁2の平面図である。また、図4(b)は、図4(a)の矢印C方向にみた図であり、図4(c)は、図4(b)の矢印D方向にみた図である。
導材桁2には、長尺形状の上桁21と、上桁21の下方で上桁21と平行に延びる長尺形状の補助桁22と、上桁21と補助桁22とを連結する複数のブレス23とが備えられている。
FIG. 4 is a diagram showing in detail the configuration of the conductive material beam 2, and FIG. 4A is a plan view of the conductive material beam 2. 4B is a diagram viewed in the direction of arrow C in FIG. 4A, and FIG. 4C is a diagram viewed in the direction of arrow D in FIG. 4B.
The conductive material girder 2 includes a long upper girder 21, a long auxiliary girder 22 extending below the upper girder 21 in parallel with the upper girder 21, and a plurality of connecting the upper girder 21 and the auxiliary girder 22. The breath 23 is provided.

図5は、上桁21の一部を詳しく示す斜視図であり、溝形鋼211と区画部材212との接合状態が詳しく示されている。
上桁21には、互いに平行を保って延びる長尺形状の一対の溝形鋼211と、一対の溝形鋼211の間に配置され、各溝形鋼211と接合している複数の区画部材212とが備えられている。
FIG. 5 is a perspective view showing a part of the upper girder 21 in detail, and shows the joining state between the channel steel 211 and the partition member 212 in detail.
The upper girder 21 includes a pair of elongated steel bars 211 extending parallel to each other, and a plurality of partition members disposed between the pair of channel steels 211 and joined to the respective steel grooves 211. 212.

溝形鋼211は、断面略コ字状の部材であり、略長方形状の板状の主面211aと、主面211aの幅方向の両端から主面211aと直交する方向に突出する一対のフランジ211bとが備えられている。
区画部材212は、断面略I字状の部材であり、溝形鋼211の主面211aと直交する略矩形状の主面212aと、主面212aの両端に、主面212aと直交するように設けられた一対のフランジ212bとが備えられている。
The grooved steel 211 is a member having a substantially U-shaped cross section, a substantially rectangular plate-shaped main surface 211a, and a pair of flanges that protrude from both ends in the width direction of the main surface 211a in a direction orthogonal to the main surface 211a. 211b.
The partition member 212 is a member having a substantially I-shaped cross section, and has a substantially rectangular main surface 212a orthogonal to the main surface 211a of the channel steel 211, and both ends of the main surface 212a so as to be orthogonal to the main surface 212a. And a pair of flanges 212b provided.

一対の溝形鋼211は、互いのフランジ211bが外側方向を向くようにして、互いの主面211aを対向して並列している。そして、各溝形鋼211の主面211aの内面に各区画部材212のフランジ212bが密着し、主面211aとフランジ212bとがボルトおよびナットなどで固定されることで、各溝形鋼211と各区画部材212とが固定されている。   The pair of channel steels 211 are parallel to each other so that their flanges 211b face outward and their main surfaces 211a face each other. The flange 212b of each partition member 212 is in close contact with the inner surface of the main surface 211a of each channel steel 211, and the main surface 211a and the flange 212b are fixed with bolts, nuts, etc. Each partition member 212 is fixed.

また、区画部材212は、上桁21の長手方向において、2つの区画部材212が所定間隔を保って対をなしており、その間の空間を、鋼杭3が挿入され得る挿入空間213としている。そして、6対の区画部材212が、上桁21の長手方向において、所定間隔を保って配置されている。これにより、主桁21の長手方向において、6つの挿入空間213が所定間隔ごとに形成されている(図4参照)。   The partition member 212 is paired with two partition members 212 in the longitudinal direction of the upper girder 21 at a predetermined interval, and the space between them is an insertion space 213 into which the steel pile 3 can be inserted. Six pairs of partition members 212 are arranged at a predetermined interval in the longitudinal direction of the upper beam 21. Thereby, six insertion spaces 213 are formed at predetermined intervals in the longitudinal direction of the main beam 21 (see FIG. 4).

再び、図4を参照して、補助桁22には、導材桁2の長手方向に延びる一対の長尺形状の補助鋼221が備えられている。
補助鋼221は、断面略L字状であって、上桁21の長さとほぼ同じ長さを有している。そして、一対の補助桁221は、所定間隔を保って対向している。
そして、補助桁22も、上桁21とほぼ同程度の、鋼杭3の挿入空間と、挿入された鋼杭3を固定するための構造を有している。
Referring again to FIG. 4, the auxiliary girder 22 is provided with a pair of elongated auxiliary steels 221 extending in the longitudinal direction of the conductive material girder 2.
The auxiliary steel 221 has a substantially L-shaped cross section and has substantially the same length as the upper girder 21. The pair of auxiliary beams 221 are opposed to each other with a predetermined interval.
And the auxiliary girder 22 also has the structure for fixing the steel pile 3 inserted and the insertion space of the steel pile 3 substantially the same as the upper girder 21.

ブレス23は、長手の棒状の部材であって、2つのブレス23がX字状に組み合わされて対とされ、その対とされたブレス23の上部が上桁21の一方の溝形鋼211の下端に接合され、その下部が補助桁22の一方の補助鋼221の上端に接合されることで、一方の溝形鋼211と一方の補助鋼221とを連結している。そして、導材桁2の長手方向において、5対のブレス23が所定間隔ごとに配置されている。   The brace 23 is a longitudinal bar-like member, and two braces 23 are combined in an X shape to form a pair, and the upper part of the paired brace 23 is formed of one channel steel 211 of the upper girder 21. It is joined to the lower end, and its lower part is joined to the upper end of one auxiliary steel 221 of the auxiliary girder 22, thereby connecting one channel steel 211 and one auxiliary steel 221. In the longitudinal direction of the conductive material beam 2, five pairs of breaths 23 are arranged at predetermined intervals.

また、図4(b)においては図示されないが、同様に、上桁21の他方の溝形鋼211の下端に、対とされたブレス23の上部が接合され、下部が補助桁22の他方の補助鋼221の上端に接合されることで、他方の溝形鋼211と他方の補助鋼221とを連結している。そして、導材桁2の長手方向において、5対のブレス23が所定間隔ごとに配置されている。すなわち、導材桁2は、トラス構造を有している。   Although not shown in FIG. 4B, similarly, the upper part of the paired brace 23 is joined to the lower end of the other grooved steel 211 of the upper girder 21 and the lower part is the other of the auxiliary girder 22. By joining to the upper end of the auxiliary steel 221, the other channel steel 211 and the other auxiliary steel 221 are connected. In the longitudinal direction of the conductive material beam 2, five pairs of breaths 23 are arranged at predetermined intervals. That is, the conducting material girder 2 has a truss structure.

なお、導材桁2は、たとえば、その長さが約12m以内、その高さが約2.4m以内となるようにされている。
再び、図1〜図3を参照して、鋼杭3には、たとえば、H形鋼が用いられている。そして、各導材桁2の6つの挿入空間213に、それぞれ鋼杭3が挿入されている。導材桁2の挿入空間213に挿入された鋼杭3は、その上部が上桁21および補助桁22に、後述の杭固定装置55により固定されており、その下部が河川底に打ち込まれている。これにより、各導材桁2は、鋼杭3によって所定高さに支持されている。
In addition, the conducting material girder 2 has a length of about 12 m or less and a height of about 2.4 m or less, for example.
Again referring to FIGS. 1 to 3, for example, H-section steel is used for the steel pile 3. And the steel pile 3 is inserted in the six insertion spaces 213 of each conducting material girder 2, respectively. The steel pile 3 inserted into the insertion space 213 of the guide girder 2 has its upper part fixed to the upper girder 21 and auxiliary girder 22 by a pile fixing device 55 described later, and its lower part is driven into the river bottom. Yes. Thereby, each conducting material girder 2 is supported at a predetermined height by the steel pile 3.

主桁4には、たとえば、H形鋼が用いられており、各導材桁2間に、5本の主桁4が掛け渡されて固定されている。なお、図1〜図3においては示されないが、各導材桁2間に掛け渡される主桁4は、後述するように、その長さが、支間となる各導材桁2間の長さのほぼ2倍の長さとされている。
横桁5には、たとえば、H形鋼が用いられている。また、横桁5は、各主桁4上に、河川の流れとほぼ平行になるように配置されており、各主桁4に固定されている。そして、複数の横桁5が、河川の横断方向に所定間隔ごとに配置されている。
For example, H-shaped steel is used for the main girder 4, and five main girders 4 are spanned and fixed between the conductive material girders 2. Although not shown in FIG. 1 to FIG. 3, the main girder 4 spanned between the respective conducting girders 2 has a length between the conducting girders 2 serving as a span, as will be described later. Is almost twice as long.
For the cross beam 5, for example, H-section steel is used. Further, the horizontal beam 5 is arranged on each main beam 4 so as to be substantially parallel to the flow of the river, and is fixed to each main beam 4. A plurality of cross beams 5 are arranged at predetermined intervals in the crossing direction of the river.

覆工板6は、平面視略矩形状とされており、複数の覆工板6が横桁5上に敷き詰められている。そして、この覆工板6の上面が、桟橋1の路面とされている。
図6は、桟橋1の施工手順を概略的に示す図である。また、図7,8,9は、クレーン53を用いた作業の仕方を具体的に示す図であり、それぞれ、(a)は側面図、(b)は平面図である。以下、図6〜図9を参照して、桟橋1の施工方法を説明する。なお、図6においては、奥側を前方、手前側を後方として、図7〜図9においては、左側を後方、右側を前方として説明する。
The lining plate 6 has a substantially rectangular shape in plan view, and a plurality of lining plates 6 are spread on the cross beam 5. The upper surface of the lining plate 6 is the road surface of the pier 1.
FIG. 6 is a diagram schematically illustrating the construction procedure of the pier 1. 7, 8, and 9 are views specifically showing how to use the crane 53, and (a) is a side view and (b) is a plan view, respectively. Hereinafter, the construction method of the pier 1 will be described with reference to FIGS. In FIG. 6, the back side is assumed to be the front, the front side is assumed to be the rear, and in FIGS. 7 to 9, the left side is assumed to be the rear and the right side is assumed to be the front.

まず、導材桁2が、たとえば、工場にて前もって組み立てられる。そして、その組み立てられた導材桁2が現場まで搬送される。現場では、桟橋1は、河川を横断するように、一方の岸から他方の岸にかけて掛け渡される。具体的には、まず、一方の岸に、橋台7を構築する。
そして、河川の横断方向前方に仮杭51を打設する。次に、仮杭51に、主桁4を受け止めることのできる仮受け材52を設ける。次いで、クレーン53により、橋台7から、橋台7を基点にして、支間のほぼ2倍の長さを有する3本の主桁4(以下、この主桁4を主桁4aとする)を河川横断方向に延ばして、仮受け材52に掛け渡す。
First, the conductive material beam 2 is assembled in advance at a factory, for example. And the assembled conducting material girder 2 is conveyed to the spot. At the site, the pier 1 is stretched from one shore to the other shore so as to cross the river. Specifically, first, an abutment 7 is constructed on one bank.
And the temporary pile 51 is driven in the cross direction front of a river. Next, the temporary pile 51 is provided with a temporary receiving material 52 that can receive the main girder 4. Next, the crane 53 crosses the river from the abutment 7 to the three main girders 4 (hereinafter, the main girder 4 is referred to as the main girder 4a) having a length approximately twice as long as the span. It extends in the direction and hangs on the temporary receiving material 52.

その後、3本の主桁4aの中央部に、導材桁仮保持部材54を設け、その導材桁仮保持部材54により導材桁2(以下、この導材桁2を導材桁2aとする)を、水平状態を維持するようにして仮保持する(図7(a)参照)。なお、この状態において、導材桁2aは、その長手方向が河川の流れの方向と平行になるようにされており、3本の主桁4aは、河川の流れの方向において、たとえば、両外方および中央に配置されている(図6(a)参照)。   After that, a conducting material girder temporary holding member 54 is provided at the center of the three main girders 4a, and the conducting material girder temporary holding member 54 provides a conducting material girder 2 (hereinafter this conducting girder 2 is referred to as a conducting material girder 2a. Is temporarily held so as to maintain the horizontal state (see FIG. 7A). In this state, the guide beam 2a is arranged such that its longitudinal direction is parallel to the direction of the river flow, and the three main beams 4a are arranged in the direction of the river flow. And in the center (see FIG. 6A).

そして、仮保持した導材桁2aの各挿入空間213にそれぞれ鋼杭3が挿入され、鋼杭3の下部が河川底に打ち込まれる(図7(b)参照)。次に、導材桁2aを水平に保った状態で、導材桁2aから上方に突出する鋼杭3の部分が切り取られ、一部が切り取られた後の鋼杭3の上部が杭固定装置55により導材桁2aに固定される。かかる作業は、作業員により行われる。作業員が上記作業を行い易いように、導材桁2aの前方に、台場56が引掛けられている(図7(a),(b)参照)。   And the steel pile 3 is each inserted in each insertion space 213 of the conducting material girder 2a temporarily hold | maintained, and the lower part of the steel pile 3 is driven into the river bottom (refer FIG.7 (b)). Next, the steel pile 3 protruding upward from the conductive material girder 2a is cut out in a state where the conductive material girder 2a is kept horizontal, and the upper part of the steel pile 3 after the part is cut off is a pile fixing device. By 55, it fixes to the conducting material girder 2a. Such work is performed by a worker. A stand 56 is hooked in front of the guide beam 2a so that the worker can easily perform the above work (see FIGS. 7A and 7B).

これにより、導材桁2aが、水平状態を保って、その長手方向が河川の流れに平行となるようにして固定される。その後、導材桁2aを仮保持していた導材桁仮保持部材54を主桁4aから外し、導材桁2aと主桁4aとを固定し、仮杭51を抜き取る。
次いで、導材桁2aおよび鋼杭3により、長さ方向中央部が固定された主桁4の先端に、次の導材桁2bが導材桁仮保持部材54を用いて仮保持される。そして、クレーン53によって、鋼杭3が打ち込まれ、打ち込まれた鋼杭3と導材桁2bとが鋼杭固定装置55によって固定される(図8(a),(b)参照)。
Thereby, the conducting material girder 2a is fixed so that the longitudinal direction thereof is parallel to the river flow while maintaining the horizontal state. Thereafter, the conductive material girder temporary holding member 54 temporarily holding the conductive material beam 2a is removed from the main beam 4a, the conductive material beam 2a and the main beam 4a are fixed, and the temporary pile 51 is extracted.
Next, the next conductor girder 2 b is temporarily held by the conductor girder 2 a and the steel pile 3 using the conductor girder temporary holding member 54 at the front end of the main girder 4 whose central portion in the length direction is fixed. And the steel pile 3 is driven in by the crane 53, and the driven steel pile 3 and the conducting material girder 2b are fixed by the steel pile fixing device 55 (refer Fig.8 (a), (b)).

その後、3本の主桁4aの間に、橋台7と導材桁2aとをつなぐように、主桁4aの半分の長さの主桁4sが2本掛けられる(図6(b)参照)。そして、橋台7と導材桁2aとの間に横桁5を設け、さらに、横桁5上に覆工板6を敷き詰める(図8(b)参照)(なお、図6においては、図が煩雑になるのを避けるため、横桁5および覆工板6は図示されない)。   Thereafter, between the three main girders 4a, two main girders 4s having a half length of the main girders 4a are hung so as to connect the abutment 7 and the conductive material girders 2a (see FIG. 6B). . And the cross beam 5 is provided between the abutment 7 and the conducting material girder 2a, and also the covering board 6 is spread on the cross beam 5 (refer FIG.8 (b)) (In addition, in FIG. In order to avoid complications, the cross beam 5 and the lining plate 6 are not shown).

次いで、導材桁2aを基点にして、支間のほぼ2倍の長さを有する2本の主桁4(以下、この主桁4を主桁4bとする)を、導材桁2bをまたぐようにして河川横断方向に延ばす。この状態では、各主桁4bは、河川の流れの方向において各主桁4aと交互になるように配置されている。また、河川の横断方向に延ばした主桁4bの先端部に、導材桁2bと同様にして、導材桁2(以下、この導材桁2を導材桁2cとする)を仮保持する(図6(c)参照)。   Next, the two main girders 4 (hereinafter, the main girder 4 is referred to as the main girder 4b) having a length approximately twice as long as the span are spanned across the conducting girder 2b with the conducting girder 2a as a base point. And extend in the river crossing direction. In this state, the main girders 4b are arranged alternately with the main girders 4a in the river flow direction. In addition, the conducting material girder 2 (hereinafter referred to as the conducting material girder 2c) is temporarily held at the tip of the main girder 4b extending in the crossing direction of the river in the same manner as the conducting material girder 2b. (See FIG. 6 (c)).

そして、上述と同様にして、仮保持した導材桁2cの各挿入空間213にそれぞれ鋼杭3を挿入して、鋼杭3の下部を河川底に打ち込むとともに、鋼杭3の上部を導材桁2cに固定することで、導材桁2cを固定する。その後、導材桁2cと、それを仮保持していた主桁4bとを固定する。そして、導材桁2aと導材桁2bとの間に横桁5を設け、さらに、横桁5上に覆工板6を敷き詰める(図9(a),(b)参照)。   Then, in the same manner as described above, the steel piles 3 are inserted into the respective insertion spaces 213 of the temporarily held conducting material girders 2c, the lower portions of the steel piles 3 are driven into the river bottom, and the upper portions of the steel piles 3 are introduced into the conducting material. By fixing to the girder 2c, the conductive material girder 2c is fixed. Thereafter, the conductive material beam 2c and the main beam 4b temporarily holding it are fixed. And the cross beam 5 is provided between the conductive material beam 2a and the conductive material beam 2b, and the covering board 6 is spread on the horizontal beam 5 (refer FIG. 9 (a), (b)).

次いで、主桁4bとほぼ同程度の長さを有する3本の主桁4(以下、この主桁4を主桁4cとする)を、導材桁2cをまたぐようにして、導材桁2bからさらに河川横断方向に延ばす。この状態では、各主桁4cは、河川の流れの方向において各主桁4bと交互になるようにされている。
また、河川の横断方向に延ばした主桁4cの先端部に、導材桁2bと同様にして、導材桁2(以下、この導材桁2を導材桁2dとする)を仮保持する(図6(d)参照)。
Next, the three main girders 4 (hereinafter, the main girders 4 are referred to as main girders 4c) having substantially the same length as the main girders 4b are arranged so as to straddle the conducting girders 2c. It extends in the river crossing direction. In this state, the main girders 4c alternate with the main girders 4b in the river flow direction.
In addition, a conducting girder 2 (hereinafter, this conducting girder 2 is referred to as a conducting girder 2d) is temporarily held at the tip of the main girder 4c extending in the crossing direction of the river in the same manner as the conducting girder 2b. (See FIG. 6D).

そして、上述と同様にして、仮保持した導材桁2dの各挿入空間213にそれぞれ鋼杭3を挿入して、鋼杭3の下部を河川底に打ち込むとともに、鋼杭3の上部を導材桁2dに固定することで、導材桁2dを固定する。その後、導材桁2dと、それを仮保持していた主桁4cとを固定する。そして、導材桁2bと導材桁2cとの間に横桁5を設け、さらに、横桁5上に覆工板6を敷き詰める。   Then, in the same manner as described above, the steel piles 3 are respectively inserted into the insertion spaces 213 of the temporarily held conductor girders 2d, the lower portions of the steel piles 3 are driven into the river bottom, and the upper portions of the steel piles 3 are introduced into the conductor. By fixing the girder 2d, the conductive material girder 2d is fixed. Thereafter, the conductive material beam 2d and the main beam 4c temporarily holding it are fixed. And the cross beam 5 is provided between the conductive material girder 2b and the conductive material beam 2c, and the covering board 6 is spread on the horizontal beam 5.

次いで、主桁4bとほぼ同程度の長さを有する2本の主桁4(以下、この主桁4を主桁4dとする)を、導材桁2dをまたぐようにして、導材桁2cからさらに河川横断方向に延ばし、その先端を対岸に到達させる。この状態では、各主桁4dは、河川の流れの方向において各主桁4cと交互になるようにされている(図6(e)参照)。そして、導材桁2cと導材桁2dとの間に横桁5を設け、さらに、横桁5上に覆工板6を敷き詰める。   Next, two main girders 4 having a length substantially equal to that of the main girders 4b (hereinafter, the main girders 4 are referred to as main girders 4d) are placed across the conducting girders 2d so as to cross the conducting girders 2c. It is further extended in the crossing direction of the river, and its tip reaches the opposite bank. In this state, the main girders 4d alternate with the main girders 4c in the river flow direction (see FIG. 6E). And the cross beam 5 is provided between the conductive material girder 2c and the conductive material beam 2d, and the covering board 6 is spread on the horizontal beam 5.

その後、導材桁2dから対岸に、主桁4dのほぼ半分の長さを有する3本の主桁4tを延ばし、それらの先端を対岸に到達させる。この状態では、各主桁4tは、河川の流れの方向において各主桁4dと交互になるようにされている(図6(f)参照)。そして、導材桁2dと対岸との間に横桁5を設け、さらに、横桁5上に覆工板6を敷き詰めることで、桟橋1が完成する(図1〜図3参照)。   Thereafter, the three main girders 4t having approximately half the length of the main girder 4d are extended from the conducting material girder 2d to the opposite bank, and their tips reach the opposite bank. In this state, the main girders 4t alternate with the main girders 4d in the river flow direction (see FIG. 6F). The pier 1 is completed by providing the cross beam 5 between the guide beam 2d and the opposite bank, and further laying the lining board 6 on the cross beam 5 (see FIGS. 1 to 3).

以上のように、この実施形態では、桟橋1は、導材桁2を備えている。そして、その導材桁2を前もって組立てておき、現場にてその導材桁2を用いれば、桟橋1を構築するための工程を少なくすることができ、桟橋1を短期間で構築できる。
また、桟橋1の構築には、支間のほぼ2倍の長さを有する主桁4a〜4dが用いられるので、桟橋1の構築に用いられる主桁の数が少なくなり、桟橋1をより短期間で構築することができる。
As described above, in this embodiment, the pier 1 is provided with the conductive material beam 2. And if the conducting material girder 2 is assembled in advance and the conducting material girder 2 is used in the field, the steps for constructing the pier 1 can be reduced, and the pier 1 can be constructed in a short period of time.
In addition, since the main girders 4a to 4d having almost twice the length of the span are used for the construction of the jetty 1, the number of main girders used for the construction of the jetty 1 is reduced, and the jetty 1 can be used for a shorter period of time. Can be built with.

また、導材桁2は、主桁4の先端部で仮保持された後に固定されるため、導材桁2を仮保持してから固定するまでの時間を短縮することができ、桟橋1全体の構築期間を短くすることができる。
図10は、導材桁仮保持部材54の構成を詳しく示す図である。
導材桁仮保持部材54には、上下方向に延びる長手の垂直体541と、垂直体541の上部に一体的に設けられた水平体542と、垂直体541の中央部に設けられた当接部材543と、垂直体541の下端に設けられた保持部材544とが備えられている。
Moreover, since the conducting material girder 2 is temporarily fixed at the front end portion of the main girder 4, it is fixed, so the time from temporarily holding the guiding material beam 2 to fixing it can be shortened, and the entire pier 1 can be shortened. The construction period can be shortened.
FIG. 10 is a diagram showing in detail the configuration of the conductive material girder temporary holding member 54.
The temporary girder temporary holding member 54 has a vertically long vertical body 541 extending in the vertical direction, a horizontal body 542 integrally provided on the top of the vertical body 541, and a contact provided at the center of the vertical body 541. A member 543 and a holding member 544 provided at the lower end of the vertical body 541 are provided.

水平体542は、垂直体541と交差するようにされており、垂直体541に設けられた状態で水平方向に延びている。また、水平体542は、その上端および下端にフランジが形成されている。
当接部材543は、垂直体541から、水平方向に所定寸法突出する形状とされている。
The horizontal body 542 intersects with the vertical body 541 and extends in the horizontal direction while being provided on the vertical body 541. Further, the horizontal body 542 has flanges formed at the upper and lower ends thereof.
The contact member 543 has a shape projecting from the vertical body 541 by a predetermined dimension in the horizontal direction.

保持部材544は、断面形状が略コ字状とされており、コ字状の先端部分が下方を向くようにして、垂直体541から水平方向に突出している。
そして、水平体542の上端のフランジを、主桁4の上端のフランジにクランプ55で留めて、導材桁仮保持部材54を主桁4に取り付ける。次いで、その導材桁仮保持部材54の当接部材543および保持部材544に導材桁2を当接させ、さらに、その状態で、導材桁2の上桁21の上部と主桁4の下端のフランジとをクランプ55で留め、また、導材桁2の補助桁22の下部と保持部材544の先端とをクランプ55で留める。
The holding member 544 has a substantially U-shaped cross section, and protrudes in the horizontal direction from the vertical body 541 so that the U-shaped tip portion faces downward.
Then, the flange at the upper end of the horizontal body 542 is fastened to the flange at the upper end of the main girder 4 with a clamp 55, and the conductive material girder temporary holding member 54 is attached to the main girder 4. Next, the guide member 2 is brought into contact with the contact member 543 and the holding member 544 of the guide member temporary holding member 54, and in this state, the upper part of the upper member 21 of the guide member 2 and the main beam 4 The lower end flange is fastened with a clamp 55, and the lower part of the auxiliary girder 22 of the conductive material girder 2 and the tip of the holding member 544 are fastened with the clamp 55.

これにより、導材桁2が垂直状態を維持して主桁4に仮保持される。また、クランプ55を外すことで、容易に導材桁仮保持部材54を取り外すことができる。
この発明は、以上説明した実施形態に限定されるものではなく、請求項記載の範囲内において種々の変更が可能である。
たとえば、上述の説明では、導材桁2は、トラス構造を有しているとしたが、トラス構造を有していないものであってもよい。
Thereby, the conducting material beam 2 is temporarily held by the main beam 4 while maintaining a vertical state. Further, by removing the clamp 55, the guide beam temporary holding member 54 can be easily removed.
The present invention is not limited to the embodiment described above, and various modifications can be made within the scope of the claims.
For example, in the above description, the conductive material beam 2 has a truss structure, but may not have a truss structure.

また、主桁4a〜4dの長さは支間の長さよりも長いものであればよく、たとえば、支間の長さの3倍または4倍であってもよい。
また、桟橋1を構築するための導材桁2および主桁4の数は、上述のものに限られず種々に変更可能である。
また、桟橋1は河川に構築されるものに限られず、たとえば、渓谷に構築されるものであってもよい。
Moreover, the length of the main girders 4a-4d should just be longer than the length of a branch, for example, may be 3 times or 4 times the length of a branch.
Moreover, the number of the conducting material girder 2 and the main girder 4 for constructing the pier 1 is not restricted to the above-mentioned thing, but can be changed variously.
Moreover, the jetty 1 is not restricted to what is built in a river, For example, you may build in a valley.

この発明の一実施形態にかかる桟橋を示す平面図である。It is a top view which shows the jetty concerning one Embodiment of this invention. 図1の矢印A方向にみた図である。It is the figure seen from the arrow A direction of FIG. 図2の矢印B方向にみた図である。It is the figure seen from the arrow B direction of FIG. 導材桁の構成を詳しく示す図である。It is a figure which shows the structure of a conducting material girder in detail. 上桁の一部を詳しく示す斜視図である。It is a perspective view which shows a part of upper girder in detail. 桟橋の施工手順を概略的に示す図である。It is a figure which shows roughly the construction procedure of a pier. 作業開始時におけるクレーンを用いた作業の仕方を示す図である。It is a figure which shows the way of the operation | work using the crane at the time of an operation | work start. 図7に示す状態からさらに作業が進んだ状態における作業の仕方を示す図である。It is a figure which shows the method of the operation | work in the state which the operation | work further advanced from the state shown in FIG. 図8に示す状態からさらに作業が進んだ状態における作業の仕方を示す図である。It is a figure which shows the method of the operation | work in the state which the operation | work further advanced from the state shown in FIG. 導材桁仮保持部材の構成を詳しく示す図である。It is a figure which shows the structure of a conductive material girder temporary holding member in detail.

符号の説明Explanation of symbols

1 桟橋
2 導材桁
2a〜2d 導材桁
3 鋼杭
4 主桁
4a,4b 主桁
7 橋台
21 上桁
22 補助桁
23 ブレス
211 溝形鋼
1 Pier 2 Conductor Girder 2a to 2d Conductor Girder 3 Steel Pile 4 Main Girder 4a, 4b Main Girder 7 Abutment 21 Upper Girder 22 Auxiliary Girder 23 Breath 211 Channel Steel

Claims (4)

架設方向と直交する方向に平行に、かつ、架設方向に一定間隔をあけて設けられた複数の導材桁と、
各導材桁を支持するように、上部は導材桁に固定され、下部は地中に打ち込まれた複数の鋼杭と、
導材桁と導材桁との間に掛け渡されて架設方向に延びる主桁と、を備え、
上記導材桁は、2本の溝形鋼が上記鋼杭を差し込める隙間をあけて平行に連結された上桁を有し、
上記鋼杭は、上記導材桁の上桁を構成する2本の溝形鋼の隙間から垂直下方に差し込まれて、下部は地中に打ち込まれ、上部は上記上桁に対して上下に移動しないように固定されていることを特徴とする桟橋。
A plurality of conductive girders provided in parallel to the direction perpendicular to the erection direction and at regular intervals in the erection direction;
To support each conductor girder, the upper part is fixed to the conductor girder and the lower part is a plurality of steel piles driven into the ground,
A main girder spanned between a conducting girder and a conducting girder and extending in the installation direction,
The conductive material girder has an upper girder in which two channel steels are connected in parallel with a gap into which the steel pile can be inserted.
The steel pile is inserted vertically downward from the gap between the two channel steels constituting the upper girder of the conductive material girder, the lower part is driven into the ground, and the upper part moves up and down with respect to the upper girder A pier characterized by being fixed so that it does not.
上記導材桁は、
上記上桁の下方で、上記上桁と平行に延びる補助桁と、
上記上桁および上記補助桁を連結する複数のブレスとを有し、
上記鋼杭は、上記補助桁を経由して差し込まれることを特徴とする請求項1に記載の桟橋。
The conducting material girder is
An auxiliary girder extending in parallel with the upper girder below the upper girder,
A plurality of braces connecting the upper girder and the auxiliary girder,
The pier according to claim 1, wherein the steel pile is inserted via the auxiliary girder.
導材桁を用いて桟橋を施工する方法であって、
上記導材桁は、2本の溝形鋼が鋼杭を差し込める隙間をあけて平行に連結された上桁を有するものであり、
桟橋の根元部分に設けた橋台から、架設方向に第1の主桁を延ばして、仮杭で先端側を仮保持し、
上記第1の主桁のほぼ中央部に、架設方向と直交する方向に平行に設ける第1の導材桁を水平方向に仮保持し、
上記仮保持した第1の導材桁の上桁を構成する2本の溝形鋼の隙間から垂直下方に鋼杭を差し込み、当該差し込んだ鋼杭の下部を地中に打ち込んだ後、その上部を上桁に固定し、
さらに、上記第1の主桁の先端部に、上述と同様にして、鋼杭により固定された第2の導材桁を取り付け、
鋼杭で支持された第2の導材桁をまたぎ、上記第1の導材桁から、さらに架設方向前方に向けて延びる第2の主桁を取り付け、
その後、上記第2の導材桁と同様の手順で、複数の導材桁を順次取り付けていくことを特徴とする桟橋の施工方法。
It is a method of constructing a pier using a guide girder,
The conductive material girder has an upper girder in which two channel steels are connected in parallel with a gap through which a steel pile can be inserted.
From the abutment provided at the base of the pier, extend the first main girder in the erection direction and temporarily hold the tip side with a temporary pile,
Temporarily holding in a horizontal direction a first conductive material girder provided parallel to a direction orthogonal to the erection direction at a substantially central portion of the first main girder,
Insert the steel pile vertically downward from the gap between the two channel steels that make up the upper girder of the first conducting material temporarily held above, and drive the lower part of the inserted steel pile into the ground. Is fixed to the upper digit,
Furthermore, in the same manner as described above, a second conductive material girder fixed by a steel pile is attached to the tip of the first main girder,
A second main girder extending across the second conducting girder supported by the steel pile and extending forward from the first conducting girder in the erection direction is attached.
Then, the construction method of the pier characterized by attaching a several conducting material girder sequentially in the same procedure as said 2nd conducting material girder.
上記導材桁は、
上記上桁の下方で、上記上桁と平行に延びる補助桁と、
上記上桁および上記補助桁を連結する複数のブレスとを有し、
上記鋼杭は、上記補助桁を経由して差し込むことを特徴とする請求項3に記載の桟橋の施工方法。
The conducting material girder is
An auxiliary girder extending in parallel with the upper girder below the upper girder,
A plurality of braces connecting the upper girder and the auxiliary girder,
The said steel pile is inserted through the said auxiliary girder, The construction method of the pier of Claim 3 characterized by the above-mentioned.
JP2004290415A 2004-10-01 2004-10-01 Pier and its construction method Expired - Fee Related JP4109664B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004290415A JP4109664B2 (en) 2004-10-01 2004-10-01 Pier and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004290415A JP4109664B2 (en) 2004-10-01 2004-10-01 Pier and its construction method

Publications (2)

Publication Number Publication Date
JP2006104709A true JP2006104709A (en) 2006-04-20
JP4109664B2 JP4109664B2 (en) 2008-07-02

Family

ID=36374762

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004290415A Expired - Fee Related JP4109664B2 (en) 2004-10-01 2004-10-01 Pier and its construction method

Country Status (1)

Country Link
JP (1) JP4109664B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6093072A (en) * 1983-10-27 1985-05-24 株式会社東芝 Method of detecting holiday of elevator
JP2014005652A (en) * 2012-06-25 2014-01-16 Nippon Juuki Kensetsu Kk Construction method for pile type pier
JP2015014156A (en) * 2013-07-05 2015-01-22 株式会社横山基礎工事 Pier construction method and pile material guide structure
JP2016199929A (en) * 2015-04-10 2016-12-01 株式会社横山基礎工事 Bridge construction method and column body and guide means used in the same
JP2020041341A (en) * 2018-09-11 2020-03-19 鹿島建設株式会社 Pier structure construction method and pier structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6093072A (en) * 1983-10-27 1985-05-24 株式会社東芝 Method of detecting holiday of elevator
JP2014005652A (en) * 2012-06-25 2014-01-16 Nippon Juuki Kensetsu Kk Construction method for pile type pier
JP2015014156A (en) * 2013-07-05 2015-01-22 株式会社横山基礎工事 Pier construction method and pile material guide structure
JP2016199929A (en) * 2015-04-10 2016-12-01 株式会社横山基礎工事 Bridge construction method and column body and guide means used in the same
JP2020041341A (en) * 2018-09-11 2020-03-19 鹿島建設株式会社 Pier structure construction method and pier structure

Also Published As

Publication number Publication date
JP4109664B2 (en) 2008-07-02

Similar Documents

Publication Publication Date Title
JP2012062664A (en) Precast floor slab and erection method therefor
JP2011032841A (en) Construction method of concrete bridge and moving working device used by method of construction
JP4109664B2 (en) Pier and its construction method
JP2007254974A (en) Prestressed concrete floor slab bridge of composite structure of steel/concrete using shape steel, and construction method of the prestressed concrete floor slab bridge
JP6215037B2 (en) Roof erection method and roof structure
JP6425779B2 (en) Roof structure
KR20100066692A (en) Psc beam connection method for continuous bridge using plat anchorage apparatus
JP2003253620A (en) Cable stayed bridge and its construction method
JP6266246B2 (en) Steel column and footing joint structure and construction method
JP2006265976A (en) Corrugated steel-plate web u component bridge and its construction method
JP4226399B2 (en) How to build a bridge
JP4109594B2 (en) Main girder and frame and construction method of temporary pier using them
JP2001200510A (en) Method for constructing overhangingly erected bridge using corrugated steel plate web
JP2009235835A (en) Bridge construction method
JP2011246989A (en) Railroad construction girder and erection method thereof
JP2003193424A (en) Composite truss bridge and its construction method
JP2022037522A (en) Beam construction method, and beam formwork support structure
JP7157092B2 (en) Construction method of precast concrete structure
KR20180011528A (en) Prestressed Hybrid Composite Girder Utilizing Truss Action
JP3361789B2 (en) Steel plate dowel and concrete filled steel pipe with corrugated stopper
JP2006057253A (en) Construction method for steel sheet pile-combined spread foundation, and steel sheet pile-combined spread foundation
JP2016033318A (en) Assembly-type unit bridge kit
JP6854652B2 (en) Reinforcing bar assembly method and rebar assembly jig
JPS5910441B2 (en) Fixing method for floor slabs
JP2005139628A (en) Method for erecting bridge

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20061010

A131 Notification of reasons for refusal

Effective date: 20080108

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080307

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20080401

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080404

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110411

Year of fee payment: 3

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees