JP2006090776A - Method of constructing nuclear reactor building - Google Patents

Method of constructing nuclear reactor building Download PDF

Info

Publication number
JP2006090776A
JP2006090776A JP2004274846A JP2004274846A JP2006090776A JP 2006090776 A JP2006090776 A JP 2006090776A JP 2004274846 A JP2004274846 A JP 2004274846A JP 2004274846 A JP2004274846 A JP 2004274846A JP 2006090776 A JP2006090776 A JP 2006090776A
Authority
JP
Japan
Prior art keywords
central control
construction
control room
reactor building
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004274846A
Other languages
Japanese (ja)
Inventor
Hiroshi Mizuhashi
浩 水橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2004274846A priority Critical patent/JP2006090776A/en
Publication of JP2006090776A publication Critical patent/JP2006090776A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To expedite power reception period and shorten whole plant construction period by responding to work and electric tests in a central control room to the power reception with a marginal process. <P>SOLUTION: In constructing a nuclear power station, the construction of the central control room placed in an upper story and lower body of the central control room lower body is conducted in parallel and the central control room is made a unit system. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、原子力発電所における原子炉建屋の建設工法に係り、特に原子炉建屋の上部階層に配置される中央制御室とその下部に配置される下部躯体との構築を平行して実施し、中央制御室をユニット化することにより原子力発電所建設期間の短縮を図った原子炉建屋の建設工法に関する。   The present invention relates to a construction method of a nuclear reactor building in a nuclear power plant, and in particular, performs a parallel construction of a central control room arranged in the upper hierarchy of the nuclear reactor building and a lower casing arranged in the lower part thereof, The present invention relates to a construction method of a nuclear reactor building that shortens the construction period of a nuclear power plant by unitizing a central control room.

一般に、原子力発電所における原子炉建屋の建設工事においては、床、壁、天井の順に下方から躯体工事を進めて行き、天井工事が完了して一定の養生期間が経過した後に各室内の工事に着手している。従って、上部階になるほど室内の工事着手時期が遅くなっている。   In general, in the construction of nuclear reactor buildings at nuclear power plants, the building work is proceeded from the bottom in the order of floors, walls, and ceilings. Have started. Therefore, the construction start time in the room is delayed toward the upper floor.

この従来の建設工程を図6によって具体的に説明する。図6(A)は建屋構造を示す概略図であり、図6(B)は工事手順を示す説明図である。   This conventional construction process will be specifically described with reference to FIG. FIG. 6A is a schematic diagram showing a building structure, and FIG. 6B is an explanatory diagram showing a construction procedure.

図6(A)に示すように、中央制御室1は、原子炉建屋の上階に例えば周辺に沿う配置で設置されており、中央制御室1の下階には下方から複数の下部躯体2(2a,2b,2c)が積層配置されている。   As shown in FIG. 6 (A), the central control room 1 is installed on the upper floor of the reactor building, for example, along the periphery, and the lower floor of the central control room 1 has a plurality of lower housings 2 from below. (2a, 2b, 2c) are stacked.

そして、下部躯体工事は、図6(B)に示すように、最下階の下部躯体2aから開始され、その後、上階側の下部躯体2b,2cへ順次進められ、各階の養生期間後に室内工事が行われる。中央制御室1の躯体工事が完了した後に、中央制御室1内の電気工事、試験等が行われる。すなわち、従来の建設工法のもとでは、中央制御室1が上階に設置されていることから、下部躯体2の工事が完了した後に中央制御室1の躯体工事を開始している。原子力発電所の建設工事においては、受電時期がクリティカルとなっているため、中央制御室1の躯体工事完了から受電までの室内工事および電気試験は非常に厳しい期間で対応しているのが現状である。   Then, as shown in FIG. 6 (B), the lower housing construction starts from the lower housing 2a on the lowermost floor, and then proceeds to the lower housings 2b and 2c on the upper floor side in order. Construction is carried out. After the construction of the central control room 1 is completed, electrical work, testing, etc. in the central control room 1 are performed. That is, under the conventional construction method, since the central control room 1 is installed on the upper floor, the construction of the central control room 1 is started after the construction of the lower casing 2 is completed. In the construction of nuclear power plants, the timing of power reception is critical, so the interior work and electrical tests from the completion of the central control room 1 to the power reception are handled in a very severe period. is there.

なお、これまでに原子炉建屋の建設期間短縮技術として、中央制御室の二重天井内の照明、ダクト、天井建具までをユニット化する工法が提案されている(特許文献1参照)。ただし、この技術においても、下部躯体工事については最下階の下部躯体から開始され、順に上階側の下部躯体について進められ、最後に中央制御室1の躯体工事が完了し、その後に中央制御室1内の電気工事、試験等が行われる。
特開平10−260284号公報
In the meantime, as a technique for shortening the construction period of the reactor building, there has been proposed a method for unitizing lighting, ducts, and ceiling fittings in the double ceiling of the central control room (see Patent Document 1). However, even in this technology, the lower frame work starts from the lower frame on the lowest floor, proceeds in sequence to the lower frame on the upper floor side, and finally completes the frame work of the central control room 1 and then the central control Electrical work, testing, etc. in room 1 are performed.
JP-A-10-260284

上述したように、従来の建設工法においては、下部躯体の工事が完了した後に中央制御室の躯体工事を開始するため、中央制御室1の躯体工事完了から受電までの室内工事および電気試験は非常に厳しい期間で対応しているのが現状であった。   As described above, in the conventional construction method, since the construction of the central control room is started after the construction of the lower housing is completed, the indoor construction and electrical tests from the completion of the construction of the central control room 1 to the reception of power are very important. The current situation is that we are responding to a severe period.

本発明は、このような事情に鑑みてなされたものであり、受電までの中央制御室内の工事および電気試験を余裕のある工程で対応可能とし、しかも受電時期の前倒しおよびプラント建設全体工期の短縮を図ることができる原子炉建屋の建設工法を提供することを目的とする。   The present invention has been made in view of such circumstances, and enables the construction and electrical tests in the central control room until power reception can be handled with a sufficient process. It aims at providing the construction method of the reactor building which can aim at.

上記の目的を達成するため、請求項1に係る発明では、原子力発電所の原子炉建屋を建設する工法において、前記原子炉建屋の上部階層に配置される中央制御室の躯体と、この中央制御室の下部に配置される下部躯体との構築を異なるエリアで平行して実施し、かつ前記中央制御室は、盤および配線を備えたユニットとして構築することを特徴とする原子炉建屋の建設工法を提供する。   In order to achieve the above object, according to the first aspect of the present invention, in a construction method for constructing a nuclear power plant nuclear reactor building, a central control room housing disposed in an upper hierarchy of the nuclear reactor building, and the central control A construction method for a reactor building characterized in that the construction with the lower housing arranged in the lower part of the room is carried out in parallel in different areas, and the central control room is constructed as a unit having a panel and wiring. I will provide a.

請求項2に係る発明では、前記中央制御室の躯体を構築するエリアで前記中央制御室内の工事および電気試験を完了させ、前記下部躯体の構築が完了した後に、前記下部躯体の上方に前記中央制御室を搭載する原子炉建屋の建設工法を提供する。   In the invention according to claim 2, the construction and electrical test in the central control room are completed in an area for constructing the central control room chassis, and after the construction of the lower chassis is completed, the central control room is located above the lower chassis. Providing a construction method for reactor buildings equipped with control rooms.

請求項3に係る発明では、前記中央制御室の躯体の構築およびその室内工事を行うエリアを前記原子炉建屋の周辺に設定し、前記原子炉建屋の周辺に設けられた大型クレーンまたは前記エリアに設けた仮設の門型クレーンにより、前記中央制御室を前記下部躯体の上方に移動および搭載する原子炉建屋の建設工法を提供する。   In the invention which concerns on Claim 3, the area which constructs the structure of the said central control room, and the indoor construction is set to the periphery of the said reactor building, The large crane provided in the periphery of the said reactor building, or the said area Provided is a construction method for a reactor building in which the central control room is moved and mounted above the lower housing by a temporary portal crane provided.

請求項4に係る発明では、ユニットとして構築した前記中央制御室の室内工事および電気試験期間を、原子力発電所建設のクリティカルとなる受電時期までに終了させる原子炉建屋の建設工法を提供する。   According to a fourth aspect of the present invention, there is provided a construction method for a nuclear reactor building in which the indoor work and electrical test period of the central control room constructed as a unit are completed by a power reception time that is critical for the construction of a nuclear power plant.

請求項5に係る発明では、原子力発電所建設のクリティカルとなる前記受電時期を前倒しすることにより、原子力発電所建設における全体工期を短縮する原子炉建屋の建設工法を提供する。   According to a fifth aspect of the present invention, there is provided a construction method for a reactor building that shortens the entire construction period in the construction of the nuclear power plant by bringing forward the power receiving time that is critical for construction of the nuclear power plant.

本発明によれば、原子炉建屋の上部階層に配置される中央制御室の躯体と、この中央制御室の下部に配置される下部躯体との構築を異なるエリアで平行して実施することにより、中央制御室の躯体工事を早期に開始し、中央制御室の躯体工事を早期に終了させることができる。また、中央制御室は、盤および配線を備えたユニットとして構築することにより、その室内工事および試験も早期に行うことができる。   According to the present invention, by carrying out in parallel in different areas the construction of the central control room housing arranged in the upper hierarchy of the reactor building and the lower housing arranged in the lower part of this central control room, The construction of the central control room can be started early and the construction of the central control room can be completed early. Moreover, the central control room can be constructed as a unit with a panel and wiring, so that the indoor work and tests can be performed at an early stage.

そして、中央制御室の躯体を構築するエリアで中央制御室内の工事および電気試験を完了させ、下部躯体の構築が完了した後に下部躯体の上方に中央制御室を搭載することにより、受電までの工程確保または、原子力発電所建設のクリティカルである受電時期の前倒しが可能となり、全体工期の短縮が図れる。   Then, the construction and electrical tests in the central control room are completed in the area where the central control room chassis is constructed, and after the construction of the lower chassis is completed, the central control room is installed above the lower chassis, and the process up to receiving power It is possible to secure or to advance the power reception period, which is critical for the construction of nuclear power plants, and shorten the overall construction period.

以下、本発明に係る原子炉の建屋建設工法の実施形態について、図1〜図5を参照して説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, an embodiment of a reactor building construction method according to the present invention will be described with reference to FIGS.

図1(A)は建屋建設工法を説明する部分縦断面図であり、図1(B)は図1の平面図である。図2は同工法による手順を示す説明図である。図3は中央制御室の内部構成を示す斜視図である。図4(A),(B)および図5は作用説明図である。   FIG. 1A is a partial longitudinal sectional view for explaining a building construction method, and FIG. 1B is a plan view of FIG. FIG. 2 is an explanatory view showing a procedure according to the construction method. FIG. 3 is a perspective view showing the internal configuration of the central control room. 4 (A), 4 (B) and FIG.

図1(A),(B)に示すように、本実施形態では、原子炉建屋の上部階層に配置される中央制御室の躯体1(以下、「制御室躯体1」という。)と、この中央制御室躯体1の下部に配置される下部躯体2a,2b,2cとの構築が異なるエリアで平行して実施される。すなわち、中央制御室躯体1は、例えば原子炉建屋周辺のエリア11(以下、「中央制御室構築エリア11」という。)で構築され、下部躯体2a,2b,2cは建屋自体の構築エリア12内で従来同様に構築される。   As shown in FIGS. 1A and 1B, in the present embodiment, a central control room housing 1 (hereinafter referred to as “control room housing 1”) disposed in the upper hierarchy of the reactor building, and this. The construction of the lower housings 2a, 2b, 2c arranged in the lower part of the central control room housing 1 is carried out in parallel in different areas. That is, the central control room housing 1 is constructed, for example, in an area 11 around the reactor building (hereinafter referred to as “central control room construction area 11”), and the lower housings 2a, 2b, 2c are in the construction area 12 of the building itself. It is constructed as before.

なお、中央制御室構築エリア11は、例えば原子炉建屋周辺全体に沿って配置されるが、図1(A)では紙面上の左右で対向する部分の中央制御室構築エリア11および中央制御室躯体1のみについて簡略的に示している。また、図1(B)では紙面上の上半分の中央制御室構築エリア11および中央制御室躯体1のみについて簡略的に示している。   The central control room construction area 11 is arranged, for example, along the entire periphery of the reactor building, but in FIG. 1A, the central control room construction area 11 and the central control room housing at the left and right opposing portions on the paper surface. Only 1 is shown in a simplified manner. FIG. 1B shows only the central control room construction area 11 and the central control room housing 1 in the upper half on the paper.

中央制御室構築エリア11には、中央制御室躯体1を下部躯体2c上に搭載するための設備として、走行用レール3と、この走行用レール3上に配置されて構築後の中央制御室躯体1を設置レベルまで吊上げる仮設の門型クレーン4とが設置されている。なお、図示しないが、門型クレーン4に代えて、原子炉建屋の周辺に設けられる大型クレーンを中央制御室躯体1の吊上げ用として適用してもよい。   In the central control room construction area 11, as a facility for mounting the central control room housing 1 on the lower housing 2c, a traveling rail 3 and a central control room housing constructed on the traveling rail 3 after being constructed are constructed. A temporary portal crane 4 for lifting 1 to the installation level is installed. Although not shown, a large crane provided around the reactor building may be used for lifting the central control room housing 1 instead of the portal crane 4.

また、中央制御室構築エリア11において、レール3上には図示省略の台車が搭載され、この台車の上にて中央制御室躯体1が構築される。   Further, in the central control room construction area 11, a cart (not shown) is mounted on the rail 3, and the central control room housing 1 is constructed on the cart.

このような配置設定のもとで、図2に工程図として示すように、中央制御室躯体工事(1)と、中央制御室躯体1の下部に配置される下部躯体工事(2a),(2b),(2c)とが、平行して実施される。なお、各下部躯体工事(2a),(2b),(2c)の終了毎に、所定の養生期間経過後に室内工事が行われる。   Under such an arrangement setting, as shown in FIG. 2 as a process diagram, the central control room housing construction (1) and the lower housing construction (2a), (2b) arranged at the lower part of the central control room housing 1 ), (2c) are performed in parallel. In addition, indoor construction is performed after the predetermined curing period has elapsed at the end of each lower frame construction (2a), (2b), (2c).

中央制御室躯体工事(1)が終了した後には、所定の養生期間経過後に、中央制御室内工事および電気試験およびその他の各種試験が行われる。そして、下部躯体2a,2b,2cの構築が完了した後であって、中央制御室内の工事および電気試験が完了した後に、中央制御室躯体1が最上部の下部躯体2cの上方に、例えば門型クレーン4を適用して搭載される(図1の矢印a参照)。   After the completion of the central control room housing (1), the central control room construction, electrical tests, and other various tests are performed after a predetermined curing period. Then, after the construction of the lower housings 2a, 2b, 2c is completed, and after the construction and electrical tests in the central control room are completed, the central control room housing 1 is placed above the uppermost lower housing 2c, for example, the gate. It is mounted by applying the type crane 4 (see arrow a in FIG. 1).

なお、本実施形態では、中央制御室構築エリア11で構築される中央制御室躯体1が、盤および配線等を備えたユニットとして構築される。図3は、このユニット構造を示している。   In the present embodiment, the central control room housing 1 constructed in the central control room construction area 11 is constructed as a unit including a panel and wiring. FIG. 3 shows this unit structure.

図3に示すように、中央制御室内工事としては、制御盤基礎工事としてコンクリート基礎5、H型鋼6、チァンネルベース7、盤8、中央制御室床9およびケーブル10等の施工が行われる。そして、電気試験を予め実施し、中央制御室ユニットシステムとして、下部躯体2c上に搭載される。   As shown in FIG. 3, as the central control room construction, concrete foundation 5, H-shaped steel 6, channel base 7, panel 8, central control room floor 9, cable 10 and the like are performed as control panel foundation work. And an electrical test is implemented beforehand and it mounts on the lower housing | casing 2c as a central control room unit system.

以上のように、実施形態においては、下部躯体2a,2b,2cと平行して中央制御室躯体1および室内工事、電気試験等が実施可能となる。   As described above, in the embodiment, the central control room housing 1 and the indoor work, electrical tests, and the like can be performed in parallel with the lower housings 2a, 2b, and 2c.

図4(A),(B)は、本発明の実施形態と従来例との建屋建設シーケンスを対比して示したものである。図4(A)に示すように、従来シーケンスにおいては、下部躯体工事(2a),(2b),(2c)および室内工事の終了後に、中央制御室躯体工事(1)が行われ、その後に中央制御室内工事および電気試験が行われていたのに対し、本発明シーケンスでは、下部躯体工事(2a),(2b),(2c)と中央制御室躯体工事(1)、ならびに室内工事および電気試験が平行して行われる。この結果、本実施形態では、中央制御室躯体工事(1)が従来に比して早期に終了し、それにより中央制御室内工事および電気試験等も早期に終了することができる。   4A and 4B show the building construction sequence of the embodiment of the present invention and the conventional example in comparison. As shown in FIG. 4 (A), in the conventional sequence, after completion of the lower housing construction (2a), (2b), (2c) and the indoor construction, the central control room housing construction (1) is performed, and thereafter Whereas the central control room construction and electrical tests were performed, in the sequence of the present invention, the lower frame construction (2a), (2b), (2c) and the central control room cabinet construction (1), as well as the indoor construction and electricity Tests are performed in parallel. As a result, in the present embodiment, the central control room housing construction (1) is completed earlier than in the prior art, whereby the central control room construction and the electrical test can be completed early.

図5は、さらに原子力発電所建設のクリティカルとなる受電までの流れを本実施形態の工程と従来の工程とで比較例示したものである。   FIG. 5 shows a comparative example of the flow until power reception, which is critical for the construction of a nuclear power plant, in the process of this embodiment and the conventional process.

この図5に示すように、従来工程の場合には、下部躯体工事の完了後に、中央制御室躯体工事が行われ、その後に中央制御室内電気工事および電気試験が行われることから、全ての期間の総和となる全期間が終了した後に受電が行われる。   As shown in FIG. 5, in the case of the conventional process, after completion of the lower housing construction, the central control room housing construction is performed, and then the central control room electrical construction work and electrical tests are performed. Power is received after the whole period, which is the sum of, ends.

これに対し、本実施形態では、下部躯体工事と中央制御室躯体工事とが平行して行われ、さらに中央制御室内の電気工事(室内工事)および電気試験も下部躯体工事と平行して行われる。そして、その後の中央制御室躯体の下部躯体への搭載および電気試験が行われた後に、すぐ受電を行うことができる。   On the other hand, in this embodiment, the lower case work and the central control room case work are performed in parallel, and further, the electric work (indoor work) and the electric test in the central control room are also performed in parallel with the lower case work. . Then, power can be received immediately after the subsequent mounting of the central control room housing to the lower housing and electrical testing.

すなわち、本実施形態では、ユニットとして構築した中央制御室の室内工事および電気試験期間を、原子力発電所建設のクリティカルとなる受電時期までに終了させる。また、原子力発電所建設のクリティカルとなる受電時期を前倒しすることにより、原子力発電所建設における全体工期が短縮される工程となっている。   In other words, in the present embodiment, the indoor work and electrical test period of the central control room constructed as a unit are completed by the power reception time that is critical for the construction of the nuclear power plant. In addition, the entire construction period in the construction of the nuclear power plant is shortened by advancing the power reception period that is critical for the construction of the nuclear power plant.

よって、本実施形態によれば、原子力発電所の建設工事に際し、上部階層に設置される中央制御室と中央制御室下部躯体の構築を平行して実施し、中央制御室をユニットシステム化することにより、受電時期の前倒しおよびプラント建設全体工期を短縮することができる。そして、受電までの工程確保またはクリティカルである受電時期の前倒しが可能となり、全体工期の短縮が図れる。   Therefore, according to the present embodiment, in the construction work of the nuclear power plant, the central control room installed in the upper hierarchy and the lower housing of the central control room are constructed in parallel, and the central control room is unitized. As a result, it is possible to advance the power reception period and shorten the entire construction period of the plant construction. In addition, it is possible to secure the process until power reception or to advance the power reception time which is critical, thereby shortening the entire construction period.

また、原子炉建屋周辺に中央制御室のユニットの構築および室内工事を行うエリアを設け、建屋周辺に設けられた大型クレーンまたは構築エリアに設けた仮設の門型クレーンにて、走行レールを介して当該場所まで中央制御室ユニットを搭載および移動可能とすることにより、プラント建設全体工期の短縮を図ることができる。   In addition, there is an area around the reactor building where the central control room unit is built and indoor work is done, and a large crane provided around the building or a temporary portal crane provided in the construction area, via the traveling rail By making it possible to mount and move the central control room unit to the place, the entire construction period of the plant construction can be shortened.

(A)、(B)は、本発明の一実施形態による中央制御室ユニットシステム化および建設工法の概念図。(A), (B) is a conceptual diagram of central control room unit systemization and construction method by one Embodiment of this invention. 本発明の一実施形態による中央制御室ユニットシステム化および建設工法の作業フロー図。The work flow figure of central control room unit systemization and construction method by one Embodiment of this invention. 本発明の一実施形態による中央制御室断面図。The central control room sectional view by one embodiment of the present invention. (A)、(B)は、従来工法と本発明工法のフロー比較図。(A), (B) is a flow comparison figure of the conventional construction method and this invention construction method. 従来工法と本発明工法の工程比較図。The process comparison figure of a conventional construction method and this invention construction method. (A)、(B)は、従来工法による中央制御室ユニットシステム化および建設工法の概念図。(A), (B) is the conceptual diagram of the central control room unit systemization and construction method by a conventional method.

符号の説明Explanation of symbols

1 中央制御室躯体
2 下部躯体
3 レール
4 門型クレーン
5 コンクリート基礎
6 H型鋼
7 チァンネルベース
8 盤
9 ケーブル
10 床
11 中央制御室構築エリア
12 建屋自体の構築エリア
1 Central control room frame 2 Lower frame 3 Rail 4 Portal crane 5 Concrete foundation 6 H-shaped steel 7 Channel base 8 Panel 9 Cable 10 Floor 11 Central control room construction area 12 Building itself construction area

Claims (5)

原子力発電所の原子炉建屋を建設する工法において、前記原子炉建屋の上部階層に配置される中央制御室の躯体と、この中央制御室の下部に配置される下部躯体との構築を異なるエリアで平行して実施し、かつ前記中央制御室は、盤および配線を備えたユニットとして構築することを特徴とする原子炉建屋の建設工法。 In the construction method of a nuclear power plant reactor building, the construction of the central control room housing arranged in the upper hierarchy of the nuclear reactor building and the lower housing arranged in the lower part of the central control room in different areas A construction method for a reactor building, which is performed in parallel, and the central control room is constructed as a unit having a panel and wiring. 前記中央制御室の躯体を構築するエリアで前記中央制御室内の工事および電気試験を完了させ、前記下部躯体の構築が完了した後に、前記下部躯体の上方に前記中央制御室を搭載する請求項1記載の原子炉建屋の建設工法。 The construction of the central control room and an electrical test are completed in an area for constructing the central control room housing, and after the construction of the lower housing is completed, the central control room is mounted above the lower housing. The construction method of the reactor building described. 前記中央制御室の躯体の構築およびその室内工事を行うエリアを前記原子炉建屋の周辺に設定し、前記原子炉建屋の周辺に設けられた大型クレーンまたは前記エリアに設けた仮設の門型クレーンにより、前記中央制御室を前記下部躯体の上方に移動および搭載する請求項2記載の原子炉建屋の建設工法。 An area for constructing the central control room and carrying out the indoor work is set around the reactor building, and a large crane provided around the reactor building or a temporary portal crane provided in the area 3. The construction method of a reactor building according to claim 2, wherein the central control room is moved and mounted above the lower housing. ユニットとして構築した前記中央制御室の室内工事および電気試験期間を、原子力発電所建設のクリティカルとなる受電時期までに終了させる請求項2記載の原子炉建屋の建設工法。 The construction method for a nuclear reactor building according to claim 2, wherein the indoor construction and electrical test period of the central control room constructed as a unit are completed by a power reception time that becomes a critical point for construction of a nuclear power plant. 原子力発電所建設のクリティカルとなる前記受電時期を前倒しすることにより、原子力発電所建設における全体工期を短縮する請求項4載の原子炉建屋の建設工法。 5. The construction method for a reactor building according to claim 4, wherein the construction period of the nuclear power plant is shortened by advancing the power reception time that is critical for the construction of the nuclear power plant.
JP2004274846A 2004-09-22 2004-09-22 Method of constructing nuclear reactor building Pending JP2006090776A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004274846A JP2006090776A (en) 2004-09-22 2004-09-22 Method of constructing nuclear reactor building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004274846A JP2006090776A (en) 2004-09-22 2004-09-22 Method of constructing nuclear reactor building

Publications (1)

Publication Number Publication Date
JP2006090776A true JP2006090776A (en) 2006-04-06

Family

ID=36231921

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004274846A Pending JP2006090776A (en) 2004-09-22 2004-09-22 Method of constructing nuclear reactor building

Country Status (1)

Country Link
JP (1) JP2006090776A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485554A (en) * 2012-06-13 2014-01-01 中国核动力研究设计院 Semi-buried type double-reactor nuclear island plant layout

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485554A (en) * 2012-06-13 2014-01-01 中国核动力研究设计院 Semi-buried type double-reactor nuclear island plant layout

Similar Documents

Publication Publication Date Title
JP2010024649A (en) Seismic strengthening structure and seismic strengthening method for double floor
JP2006090776A (en) Method of constructing nuclear reactor building
JP3027430B2 (en) Construction method of nuclear power plant building, building module and nuclear power plant building
JP5590369B2 (en) Seismic isolation structure of stigma-isolated steel structure
JP6088926B2 (en) Structure reconstruction method
JPS61162679A (en) Construction of nuclear reactor plant
JP5010656B2 (en) Floor construction method for equipment carry-in area at nuclear power plant
JP2015014159A (en) Structure reconstruction method
JP2000201421A (en) Indoor wiring
JPS60168086A (en) Method of assembling reactor housing vessel
JP2017166262A (en) Construction method of anechoic chamber
JP2005097929A (en) Building floor structure of nuclear power plant
JP2007092452A (en) Construction method of multilayer building
JPS62228975A (en) Method of construction of nuclear plant
JPH05113010A (en) Method of installing roof top facility equipment and structure therefor
JPS6157890A (en) Method of construction of housing for nuclear reactor
JP2010133210A (en) Method of manufacturing structure of large video apparatus
JP2016000913A (en) Mounting structure and mounting method
JPH03133896A (en) Installing method for atomic reactor building ceiling crane
JPH0475410A (en) Ceiling wiring board for housing unit
CN112942869A (en) Method for installing multi-layer large-span steel structure
JPS59127517A (en) Method of installing cable tray
KR20020054140A (en) Light-weight wall system
JPH0755240A (en) Duct device
JPS62215743A (en) Method for constructing housing