JP2006083686A - Construction method for foundation of column - Google Patents

Construction method for foundation of column Download PDF

Info

Publication number
JP2006083686A
JP2006083686A JP2005179487A JP2005179487A JP2006083686A JP 2006083686 A JP2006083686 A JP 2006083686A JP 2005179487 A JP2005179487 A JP 2005179487A JP 2005179487 A JP2005179487 A JP 2005179487A JP 2006083686 A JP2006083686 A JP 2006083686A
Authority
JP
Japan
Prior art keywords
column
pillar
concrete
foundation
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005179487A
Other languages
Japanese (ja)
Other versions
JP2006083686A5 (en
JP4636409B2 (en
Inventor
Eizo Saito
栄三 斎藤
Koichi Okuno
幸一 奥野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji Autetsuku Kk
Original Assignee
Fuji Autetsuku Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji Autetsuku Kk filed Critical Fuji Autetsuku Kk
Priority to JP2005179487A priority Critical patent/JP4636409B2/en
Publication of JP2006083686A publication Critical patent/JP2006083686A/en
Publication of JP2006083686A5 publication Critical patent/JP2006083686A5/ja
Application granted granted Critical
Publication of JP4636409B2 publication Critical patent/JP4636409B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method for a foundation of a column, which enables sufficient strength to be imparted to the column, subject to a pull-out load and/or overturning moment, such as a column for a cantilever-type car port. <P>SOLUTION: In this construction method for the foundation of the column, firstly, a vertical hole 91 is dug in a position to erect the column, and the column 11 is installed in the vertical hole 91. A connection member 23 with predetermined strength is wound around the column 11, and concrete is placed around the column 11 inside the vertical hole 91, so that the column 11, the connection member 23 and the concrete can be integrated together. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

この発明は、柱の基礎の施工方法に関し、特に、施工が困難な状況において十分な強度を有する柱の設置が可能な柱の基礎の施工方法に関する。   The present invention relates to a column foundation construction method, and more particularly to a column foundation construction method capable of installing a pillar having sufficient strength in a situation where construction is difficult.

従来、隣地との境界の近くに、ガレージの柱や、背の高い目隠しフェンスを設けることがある。この場合のガレージの屋根の柱用の基礎の配置を図9(A)に示す。図9(A)を参照して、隣地との境界50に近い位置にガレージの屋根を施工する場合の基礎73と、柱71と、隣地との境界50との関係が示されている。一方、図10は、境界50の近くにフェンスを構築する場合の、基礎83の施工断面を示す図である。図10を参照して、従来は、深い穴85を掘削し、そこにある程度、栗石84やクラッシャランを転圧し、捨てコンを打ち、その内部に空洞82を有するコンクリートの基礎83を作り、穴85を土で埋め戻す。空洞82の中にフェンスを支持する柱81を垂直に保持し、フェンスを設置する。その後、空洞82にはモルタルが流し込まれて、基礎との一体化がなされる。   Conventionally, a garage column or a tall blindfold fence is often provided near the boundary with the adjacent land. The layout of the foundation for the garage roof pillar in this case is shown in FIG. With reference to FIG. 9 (A), the relationship between the foundation 73, the pillar 71, and the boundary 50 with the adjacent land in the case of constructing a garage roof at a position close to the boundary 50 with the adjacent land is shown. On the other hand, FIG. 10 is a diagram showing a construction cross section of the foundation 83 when a fence is constructed near the boundary 50. Referring to FIG. 10, conventionally, a deep hole 85 is excavated, to which a chestnut 84 or crusher run is rolled to some extent, a thrown away container is struck, and a concrete foundation 83 having a cavity 82 is formed therein. Backfill with soil. A pillar 81 supporting the fence is held vertically in the cavity 82, and the fence is installed. After that, mortar is poured into the cavity 82 to be integrated with the foundation.

図9(B)は、図9(A)において、B−Bで示す部分の矢視図であり、図9(A)に示した隣地との境界近傍部分にカーポートを設ける場合の、従来における、カーポートの支柱を基礎に埋め込む場合の施工状態を示す図である。図9(B)を参照して、従来は、日本の土地事情から、隣地との境界50ぎりぎりにカーポートを設ける場合が多い。この場合に、カーポートの柱71の基礎73に、コンクリートのかぶり厚を確保しようとすると、境界50からその一部(図9(B)においてdで示す部分)が隣地側にはみ出すため、敷地境界内では、コンクリートのかぶり厚が確保できず、その基礎73は、十分な平面上の面積を得ることができない。一方、境界50の反対側のカーポートの位置が決められている場合、かぶり厚dを確保しようとすると、かぶり厚d分だけカーポートとしての有効面積が減る。
図10に示すフェンスの基礎83についても同様で、図10において、境界50ぎりぎりにフェンスの基礎83を設ける場合に、敷地境界内において、フェンスの基礎83に、敷地内でコンクリートのかぶり厚が確保できず、その一部がはみ出し(図10においてdで示す部分)、基礎83は、十分な平面上の面積を得ることができない。
FIG. 9B is an arrow view of the portion indicated by BB in FIG. 9A, and shows a conventional case where a carport is provided in the vicinity of the boundary with the adjacent land shown in FIG. 9A. It is a figure which shows the construction state in the case of embedding the support | pillar of a carport in the foundation. With reference to FIG. 9 (B), conventionally, there are many cases where a carport is provided just at the border 50 with the neighboring land due to the land situation in Japan. In this case, if a concrete cover thickness is to be secured on the foundation 73 of the carport pillar 71, a part thereof (part indicated by d in FIG. 9 (B)) protrudes to the adjacent land side. Within the boundary, the concrete cover thickness cannot be secured, and the foundation 73 cannot obtain a sufficient plane area. On the other hand, when the position of the carport on the opposite side of the boundary 50 is determined, if an attempt is made to secure the cover thickness d, the effective area as the carport is reduced by the cover thickness d.
The same applies to the fence foundation 83 shown in FIG. 10, and in FIG. 10, when the fence foundation 83 is provided at the border 50, the concrete cover thickness is secured on the fence foundation 83 within the site boundary within the site boundary. A part of the base 83 protrudes (a part indicated by d in FIG. 10), and the base 83 cannot obtain a sufficient area on the plane.

上記のように、基礎コンクリートのかぶりを確保せず施工をすると、図10に示すような、背の高いフェンスの基礎を施工した場合、強風時にフェンスが傾いたり、図9に示したカーポートの場合は、屋根に積もった雪の重みでカーポートが倒れるという問題があった。   As described above, when construction is performed without securing the cover of the foundation concrete, when the foundation of a tall fence as shown in FIG. 10 is constructed, the fence tilts during strong winds, or the carport shown in FIG. In this case, there was a problem that the carport collapsed due to the weight of snow on the roof.

上記のように、柱を境界ぎりぎりに設置するときは、片持ち梁形式のカーポートの柱やフェンスの基礎のような、引き抜き荷重および/または転倒モーメントのかかる柱の基礎の施工は、基礎のコンクリートのかぶり厚が確保できないため、困難であるという問題があった。   As described above, when installing a column near the boundary, the foundation of a column subject to a pull-out load and / or tipping moment, such as a cantilever type carport column or a fence foundation, There was a problem that it was difficult because the cover thickness of concrete could not be secured.

この発明は、上記のような従来の課題に鑑みてなされたもので、片持ち梁形式のカーポート用の柱のような、引き抜き荷重および/または転倒モーメントのかかる柱に、十分な強度を持たせることのできる、柱の基礎の施工方法を提供することを目的とする。   The present invention has been made in view of the above-described conventional problems, and has sufficient strength for a column subjected to a pulling load and / or a tipping moment, such as a column for a carport of a cantilever type. It aims at providing the construction method of the foundation of a pillar which can be made.

この発明の他の目的は、片持ち梁形式のカーポート用の柱のような、引き抜き荷重および/または転倒モーメントのかかる柱を簡単に施工できる、柱の基礎の施工方法を提供することを目的とする。   Another object of the present invention is to provide a column foundation construction method capable of easily constructing a column with a pulling load and / or a tipping moment, such as a cantilever type carport column. And

この発明によれば、柱の基礎の施工方法は、柱の立設位置に縦穴を掘削し、縦穴内に柱を設置するステップと、柱の周囲に所定の強度を有する接続部材を巻付けるステップと、縦穴の内部において柱の周囲にコンクリートを打設することにより、柱と接続部材とコンクリートとを一体化するステップとを含む。   According to the present invention, the column foundation construction method includes a step of excavating a vertical hole at a standing position of the column, a step of installing the column in the vertical hole, and a step of winding a connection member having a predetermined strength around the column And integrating the pillar, the connecting member and the concrete by placing concrete around the pillar inside the vertical hole.

好ましくは、接続部材は柱に近接する第1の部分と、柱から離れた位置に延在する、第1の部分と異なる第2の部分とを含む。   Preferably, the connection member includes a first portion proximate to the column and a second portion different from the first portion extending to a position away from the column.

さらに好ましくは、第1の部分と第2の部分とは、相互に対向した位置に延在する。   More preferably, the first portion and the second portion extend at positions facing each other.

なお、接続部材は、ジオグリッド、ベルト、ロープ、金属板、鉄筋、スパイラル筋、かんざし筋のいずれかであってもよい。   Note that the connecting member may be any of a geogrid, a belt, a rope, a metal plate, a reinforcing bar, a spiral line, and a hairpin.

また、ジオグリッドの原織物、ベルト、ロープは、高強度繊維で形成されている。   Geogrid fabrics, belts and ropes are made of high-strength fibers.

この発明によれば、柱の基礎の施工方法は、柱の立設位置に縦穴を掘削し、縦穴内に柱を設置するステップと、柱の周囲に所定の強度を有する接続部材を巻付けるステップと、縦穴の内部において柱の周囲にコンクリートを打設することにより、柱と接続部材とコンクリートとを一体化するステップとを含む。   According to the present invention, the column foundation construction method includes a step of excavating a vertical hole at a standing position of the column, a step of installing the column in the vertical hole, and a step of winding a connection member having a predetermined strength around the column And integrating the pillar, the connecting member and the concrete by placing concrete around the pillar inside the vertical hole.

柱の周囲に所定の強度を有する接続部材を巻付けてコンクリートを打設することにより、柱と強度部材とコンクリートとを一体化するため、杭を用いることなく、柱の基礎の施工方法を提供できる。   By laying concrete with a connecting member with a predetermined strength around the pillar, the pillar, the strength member, and the concrete are integrated to provide a method for constructing the foundation of the pillar without using a pile. it can.

したがって、たとえば、カーポートやフェンスの柱を敷地境界のぎりぎりの位置に設けた場合のように、境界側にコンクリートのかぶり厚が確保しづらい柱についても、安価に施工が可能になる。   Therefore, for example, a pillar for which it is difficult to secure a concrete cover thickness on the boundary side as in the case where a carport or a fence column is provided at a marginal position of the site boundary can be constructed at low cost.

以下、この発明の一実施の形態を図面を参照して説明する。図1(A),(B)は、この発明の一実施の形態における、従来の図9(A)、(B)に対応する図であり、図2は、図1において、II−IIで示す部分の断面図である。ここでは、カーポートの柱を施工する場合について説明するが、背の高いフェンスの柱を施工する場合も同様である。     An embodiment of the present invention will be described below with reference to the drawings. FIGS. 1A and 1B are views corresponding to FIGS. 9A and 9B in the embodiment of the present invention, and FIG. 2 is II-II in FIG. It is sectional drawing of the part shown. Here, the case of constructing a carport pillar will be described, but the same applies to the case of constructing a tall fence pillar.

図1および図2を参照して、柱11の転倒を防止するための杭として、図6に示す鋼管杭21,22を使用する。すなわち、柱11の施工用の縦穴41に、杭頭補強部として、掘削穴42を複式スコップで掘削する。この杭頭補強の掘削穴42に、垂直でなくても良い状態で、一対の鋼管杭21、22を打ち込む。   With reference to FIG. 1 and FIG. 2, the steel pipe piles 21 and 22 shown in FIG. 6 are used as a pile for preventing the fall of the pillar 11. FIG. That is, the excavation hole 42 is excavated in the vertical hole 41 for construction of the pillar 11 as a pile head reinforcement part with a double scoop. A pair of steel pipe piles 21 and 22 is driven into the excavation hole 42 for reinforcing the pile head in a state where it is not necessary to be vertical.

この実施の形態においては、カーポートの柱11に対して、鋼管杭21,22は、隣地境界50の反対側に2本設けられ、カーポートの柱11、鋼管杭21、22は、接続部材23で接続されて、コンクリートを打設することにより、一体化される。このように、鋼管杭21,22を、カーポートの柱11に対して、敷地内に設けることにより、柱の上部の転倒モーメントを、接続部材23を通じて鋼管杭21,22で吸収する。その結果、鋼管杭21,22で、隣地境界50の近傍において、隣地側または敷地内部側へ転倒することなく、柱11を建てることができる。   In this embodiment, two steel pipe piles 21 and 22 are provided on the opposite side of the adjacent land boundary 50 with respect to the carport pillar 11, and the carport pillar 11 and the steel pipe piles 21 and 22 are connecting members. 23, and are integrated by placing concrete. Thus, by providing the steel pipe piles 21 and 22 in the site with respect to the column 11 of the carport, the steel pipe piles 21 and 22 absorb the overturning moment of the upper part of the column through the connecting member 23. As a result, the pillar 11 can be built by the steel pipe piles 21 and 22 in the vicinity of the adjacent land boundary 50 without falling down to the adjacent land side or the site interior side.

図2に示すように、柱11の下部と鋼管杭21、22(図示無し)の上部とが、ジオグリッド(ジオテキスタイル)のような接続部材23で接続されている。なお、鋼管杭21,22には、その中央部に縦筋25が設けられている。柱のかんざし筋33と、鋼管杭のかんざし筋32とを用いて、柱11と鋼管杭21,22とを接続するようにしてもよい。   As shown in FIG. 2, the lower part of the column 11 and the upper part of the steel pipe piles 21 and 22 (not shown) are connected by a connection member 23 such as a geogrid (geotextile). The steel pipe piles 21 and 22 are provided with vertical bars 25 at the center thereof. The column 11 and the steel pipe piles 21, 22 may be connected using the column barb bars 33 and the steel pipe pile barb bars 32.

また、通常はこのような位置に柱11を建てると、隣地境界50側の基礎のコンクリートのかぶり厚を十分確保できないため、コンクリートにクラックが入って問題になるが、この実施の形態のように、柱11と隣地境界50との間に接続部材23を通すことによって、接続部材23とコンクリートとが一体化するため、そのような問題は生じない。   In addition, usually, if the pillar 11 is built at such a position, the concrete cover thickness of the foundation on the adjacent land boundary 50 side cannot be secured sufficiently, so there is a problem that the concrete cracks, but as in this embodiment Since the connecting member 23 and the concrete are integrated by passing the connecting member 23 between the pillar 11 and the adjacent land boundary 50, such a problem does not occur.

なお、ここでは、鋼管杭を2本用いた例について説明したが、これに限らず、鋼管杭は1本でもよい。   In addition, although the example using two steel pipe piles was demonstrated here, not only this but one steel pipe pile may be sufficient.

ここで、ジオグリッドとは、盛土の不等沈下防止等を目的として開発された繊維原織物を樹脂でコーティングしたものであり、繊維原織物としては、ポリエステル繊維、ナイロン繊維、ポリアラミド繊維、ガラス繊維、ビニロン繊維、炭素繊維、ポリアリレート繊維、ポリアセタール繊維等が好ましい。このように合成繊維を用いているため、さびが生じない。なお、ジオグリッドの原織物に使用される繊維としては、上記繊維の高強度繊維が好ましい。このような高強度繊維としては、高分子量ポリエチレン、PET(ポリエチレンテレフタラート)、ナイロン6、ポリアラミド(パラ、メタ)、ガラス、ビニロン、PAN系炭素繊維、ピッチ系炭素繊維、ポリアリレート繊維、ポリアセタール繊維、PPS繊維、ポリイミド繊維、PEEK繊維、フッソ繊維等がある。   Here, the geogrid is a fiber base fabric developed for the purpose of preventing uneven settlement of the embankment with a resin, and the fiber base fabric includes polyester fiber, nylon fiber, polyaramid fiber, glass fiber. Vinylon fiber, carbon fiber, polyarylate fiber, polyacetal fiber and the like are preferable. Since synthetic fibers are used in this way, rust does not occur. In addition, as a fiber used for the raw fabric of geogrid, the high strength fiber of the said fiber is preferable. Such high-strength fibers include high molecular weight polyethylene, PET (polyethylene terephthalate), nylon 6, polyaramid (para, meta), glass, vinylon, PAN-based carbon fiber, pitch-based carbon fiber, polyarylate fiber, and polyacetal fiber. , PPS fiber, polyimide fiber, PEEK fiber, and fluorine fiber.

また、コンクリートの付着等を考慮して、網目の寸法は、10mmから100mm程度が好ましい。   In consideration of adhesion of concrete and the like, the mesh size is preferably about 10 mm to 100 mm.

以上のように、接続部材23で柱11と杭21,22とを抱き込み、コンクリートを打設し、一体化することにより、隣地側基礎コンクリートのかぶり厚がゼロでも、十分な強度が確保できる。   As described above, by embedding the pillar 11 and the piles 21 and 22 with the connecting member 23 and placing and integrating the concrete, sufficient strength can be ensured even when the cover thickness of the adjacent foundation concrete is zero. .

また、接続部材23を構成する繊維は、地中に埋設されるため、紫外線による劣化は生じない上に、必要な強度を計算して繊維量を増すことによって、安全を確保できる。   Moreover, since the fiber which comprises the connection member 23 is embed | buried in the ground, deterioration by an ultraviolet-ray does not arise, but safety | security can be ensured by calculating required intensity | strength and increasing fiber amount.

図3は、図2の変形例を示す図である。図3を参照して、ここでは、ジオグリッドの代わりに、水平方向の上下に離れた、2本以上のベルト、または、ロープ23a、23bで柱11と、一対の鋼管杭21、22(図示無し)とが接続されている。   FIG. 3 is a diagram showing a modification of FIG. Referring to FIG. 3, here, instead of a geogrid, a pillar 11 and a pair of steel pipe piles 21, 22 (illustrated) are separated by two or more belts or ropes 23 a, 23 b separated vertically in the horizontal direction. None) is connected.

ここで、ベルトおよびロープ23a、23bは、上記したジオグリッドの生布に用いられる高強度繊維で制織されたものが好ましい。   Here, the belts and ropes 23a and 23b are preferably woven with high-strength fibers used in the above-described geogrid raw cloth.

なお、この場合も、柱のかんざし筋38と、鋼管杭のかんざし筋32とを用いて、柱11と鋼管杭21,22(図示なし)とを接続するようにしてもよい。   In this case, the column 11 and the steel pipe piles 21 and 22 (not shown) may be connected using the column barb 38 and the steel pipe pile barb 32.

図4は、図1に示した柱11と、鋼管杭21,22との接続関係を示すさらに他の例を示す図である。図4(A)では、柱11に柱のかんざし筋89を通し、それを、鋼管杭21,22のかんざし筋88で接続している。柱のかんざし筋89と鋼管杭のかんざし筋88とは、結束線(図中黒四角で示す)で接続している。   FIG. 4 is a view showing still another example showing the connection relationship between the pillar 11 shown in FIG. 1 and the steel pipe piles 21 and 22. In FIG. 4 (A), the column hairpin 89 is passed through the column 11, and is connected by the hairpin 88 of the steel pipe piles 21 and 22. The column barb bar 89 and the steel pipe pile barb bar 88 are connected by a binding line (indicated by a black square in the figure).

鋼管杭21,22の縦筋25,26は任意の位置に回転可能であるため、これら縦筋25、26を適切な向きに向け、柱11のかんざし筋89とを接続すればより効果的である。   Since the vertical bars 25 and 26 of the steel pipe piles 21 and 22 can be rotated to arbitrary positions, it is more effective if the vertical bars 25 and 26 are oriented in an appropriate direction and connected to the knurled bar 89 of the column 11. is there.

このように、柱11と鋼管杭21,22とが、鋼管杭のかんざし筋88と柱のかんざし筋89とで一体化されることにより、先の実施の形態と同様に、柱の上部の転倒モーメントを、鋼管杭のかんざし筋88を通じて吸収でき、鋼管杭21,22を打ち込むことにより、隣地との境界50の近傍において、隣地側または敷地内部側へ転倒することなく、柱11を建てることができる。   In this way, the column 11 and the steel pipe piles 21 and 22 are integrated by the steel pipe pile barb 88 and the column barb 89, so that the upper part of the column falls down as in the previous embodiment. Moment can be absorbed through the steel pipe pile pin 88, and by driving the steel pipe piles 21 and 22, the pillar 11 can be built in the vicinity of the boundary 50 with the adjacent land without falling to the adjacent land side or the site inside. it can.

なお、図4(A)では、柱11を貫通するかんざし筋89を固定するために、角柱で構成される柱11の内部にモルタル103を流し込んだ状態を示している。このモルタル103は柱11の上部の開口から流し込んでもよいし、かんざし筋89の上部の側面に設けられた図示のない開口部から流し込んでもよい。このようにモルタル103を充填すると、かんざし筋89は柱11の肉厚だけではなく、柱11の断面全体で支持されるとともに、柱11と基礎とが一体化されるため、より好適である。   FIG. 4A shows a state in which the mortar 103 is poured into the column 11 formed of a rectangular column in order to fix the hairpin 89 that penetrates the column 11. The mortar 103 may be poured from the opening at the top of the column 11 or from an opening (not shown) provided on the side surface of the upper part of the hairpin 89. Filling the mortar 103 in this manner is more preferable because the shank bars 89 are supported not only by the thickness of the column 11 but also by the entire cross section of the column 11 and the column 11 and the foundation are integrated.

また、図4(B)では、柱11の境界50側に「コ」の字形のサポート34を設け、これに穴を設けて、この穴を貫通した鉄筋35、36と、鉄筋37とは結束線(図中黒四角で示す)で接続されている。   Further, in FIG. 4B, a “U” -shaped support 34 is provided on the boundary 50 side of the column 11, a hole is provided in the support 34, and the reinforcing bars 35 and 36 penetrating the hole and the reinforcing bar 37 are bonded They are connected by lines (indicated by black squares in the figure).

また、縦筋25,26を鉄筋35、36と接続する、または、鉄筋37と接続すると、より効果的である。   Further, it is more effective to connect the vertical bars 25 and 26 to the reinforcing bars 35 and 36 or to connect the reinforcing bars 37.

図5は、スパイラル状の鉄筋(以下、「スパイラル筋」という)45を示す図である。スパイラル筋45は直径が約2mm〜16mmの鉄筋で形成され、ばねのように多重スパイラルを形成するよう構成されている。したがって、これを広げようとしても容易には広
がらない。スパイラル筋45は、その一端にスパイラルの中心方向に向かって曲げらた部分46を有し、この部分46が柱11の図示の無い穴部に挿入可能である。鋼管杭21、22を打ち込んだ後、柱11の穴部にスパイラル筋の曲げられた部分46を挿入し、スパイラル筋45で柱11の本体、2本の鋼管杭21、22を接続する。鋼管杭21,22の内部に充填剤を充填する。その後、コンクリートおよびモルタルを縦穴41、杭頭補強の掘削穴42に流し込んで全体を一体化して固定する。
FIG. 5 is a diagram showing a spiral reinforcing bar (hereinafter referred to as “spiral bar”) 45. The spiral bar 45 is formed of a reinforcing bar having a diameter of about 2 mm to 16 mm, and is configured to form a multiple spiral like a spring. Therefore, even if it tries to spread this, it does not spread easily. The spiral muscle 45 has a portion 46 bent toward the center of the spiral at one end, and this portion 46 can be inserted into a hole portion (not shown) of the column 11. After the steel pipe piles 21 and 22 are driven, a portion 46 in which a spiral line is bent is inserted into the hole of the column 11, and the main body of the column 11 and the two steel pipe piles 21 and 22 are connected by the spiral line 45. The inside of the steel pipe piles 21 and 22 is filled with a filler. Then, concrete and mortar are poured into the vertical hole 41 and the excavation hole 42 for pile head reinforcement, and the whole is integrated and fixed.

ここで、スパイラル筋45は、一端側にスパイラルの中心方向に向かって曲げられた部分46を有しているが、他端側にもスパイラルの中心方向に向かって曲げられた部分46を有してもよい。   Here, the spiral muscle 45 has a portion 46 bent toward the center of the spiral on one end side, but also has a portion 46 bent toward the center of the spiral on the other end side. May be.

このようにすれば、大容量のコンクリートを使用することなく、少ないコンクリートの量で柱11が鋼管杭21、22と一体化され、強固な基礎を得ることができる。   In this way, the pillar 11 can be integrated with the steel pipe piles 21 and 22 with a small amount of concrete without using large-capacity concrete, and a strong foundation can be obtained.

なお、鋼管杭21,22に充填される充填材としては、無収縮モルタルを使用するのが好ましい。   In addition, it is preferable to use a non-shrink mortar as a filler with which the steel pipe piles 21 and 22 are filled.

また、鋼管杭21,22は、縦穴41と杭頭補強の掘削穴42内部へのコンクリートおよび/またはモルタルの充填は、同時に行なったほうが好ましい。   In addition, it is preferable that the steel pipe piles 21 and 22 are filled with concrete and / or mortar in the inside of the vertical hole 41 and the excavation hole 42 for reinforcing the pile head at the same time.

また、鋼管杭21、22の径が大きい場合は、鋼管杭21,22内への充填材の充填と、縦穴41、杭頭補強の掘削穴42内へのコンクリートおよび/またはモルタルの充填は、同時に行ってもよい。   Moreover, when the diameter of the steel pipe piles 21 and 22 is large, filling of the filling material into the steel pipe piles 21 and 22 and filling of the vertical hole 41 and the excavation hole 42 of the pile head reinforcement with concrete and / or mortar, You may do it at the same time.

なお、図6を参照して、鋼管杭21、22は、頂部が開放され、下端部28が尖塔型を有しており、内部に縦筋を回転自在に支持するための支持部材29が設けられている。図2や3においては、図6に示す支持部材29によって、縦筋25、26が支持されている。施工時には、この鋼管杭21、22の内部にも無収縮モルタルが充填される。   In addition, with reference to FIG. 6, the steel pipe piles 21 and 22 are open at the top, and the lower end 28 has a spire type, and a support member 29 for rotatably supporting the vertical bars is provided therein. It has been. 2 and 3, the vertical bars 25 and 26 are supported by the support member 29 shown in FIG. During construction, the steel pipe piles 21 and 22 are also filled with non-shrink mortar.

また、鋼管杭21,22にはかんざし筋を貫通して保持するためのかんざし筋穴27が設けられている。   Moreover, the steel pipe piles 21 and 22 are provided with a knurled bar hole 27 for penetrating and holding the knurled bar.

図7はこの発明の他の実施の形態を示す図であり、図1で、VII−VIIで示す部分の矢視図である。図7を参照して、この実施の形態においては、カーポートの柱51を取付けた状態で、掘削穴65の下部に連続して、カーポートの柱51を挟んで対称的に2つの杭頭補強の掘削穴66、67を設ける。それぞれの杭頭補強の掘削穴66、67に図1に示した鋼管杭21、22と同様の鋼管杭61,62を打ち込む。カーポートの柱51にはその下部にかんざし筋52,53が取付けられている。一方、鋼管杭61,62にも縦筋63,64と、かんざし筋54、55が取付けられている。縦筋63,64およびかんざし筋54、55のそれぞれの端部は、カーポートの柱51の2本のかんざし筋52,53と交差可能な位置に設けられ、それぞれの交差部は結束線56a、56b、56c、56dで接続される。これによって、カーポートの柱51と、鋼管杭61,62とが結束される。   FIG. 7 is a view showing another embodiment of the present invention, and is a sectional view taken along the line VII-VII in FIG. Referring to FIG. 7, in this embodiment, two pile heads symmetrically sandwiching the carport column 51 continuously with the bottom of the excavation hole 65 in a state where the carport column 51 is attached. Reinforcing drilling holes 66 and 67 are provided. Steel pipe piles 61 and 62 similar to the steel pipe piles 21 and 22 shown in FIG. 1 are driven into the excavation holes 66 and 67 for reinforcing the pile heads. The pin 51 of the carport is provided with knurled bars 52 and 53 at the lower part thereof. On the other hand, longitudinal bars 63 and 64 and hairpins 54 and 55 are also attached to the steel pipe piles 61 and 62. The ends of the vertical bars 63 and 64 and the pinnacles 54 and 55 are provided at positions where they can intersect with the two pinch bars 52 and 53 of the carport column 51, and the crossings are the binding lines 56a, They are connected by 56b, 56c, and 56d. Thereby, the column 51 of the carport and the steel pipe piles 61 and 62 are bound.

なお、この鋼管杭61,62も共に、先の実施の形態と同様に、垂直方向に向けられるのではなく、斜め方向に向けられてもよい。   Both the steel pipe piles 61 and 62 may be directed not in the vertical direction but in the oblique direction, as in the previous embodiment.

この状態で、掘削穴65,66,67にコンクリートを流し込む。その結果、カーポートの柱51の強固な基礎を得ることができる。   In this state, concrete is poured into the excavation holes 65, 66 and 67. As a result, a solid foundation for the carport pillar 51 can be obtained.

上記実施の形態においては、杭として、鋼管杭を用いた例について説明した。しかしながら、杭として、鋼管杭以外にコンクリート杭や樹脂製の杭を用いてもよい。図8は、コンクリート杭75を示す図である。図8を参照して、コンクリート杭は、コンクリート杭本体75と、コンクリート杭本体75の上部に設けられ、鉄製のキャップを埋め込んだ保護具76と、コンクリート杭本体75に埋め込まれたかんざし筋77、78とを含み、その下端部79は尖塔型を有している。図7に示したように、このかんざし筋77,78を、柱に埋め込まれたかんざし筋と結束線で固定することによって、カーポートの柱と一体化する。なお、かんざし筋は1本でもよい。   In the said embodiment, the example which used the steel pipe pile as a pile was demonstrated. However, a concrete pile or a resin pile may be used as the pile in addition to the steel pipe pile. FIG. 8 is a view showing the concrete pile 75. Referring to FIG. 8, the concrete pile includes a concrete pile main body 75, a protector 76 provided with an iron cap embedded in the upper portion of the concrete pile main body 75, and a hairpin 77 embedded in the concrete pile main body 75. 78, and its lower end 79 has a spire shape. As shown in FIG. 7, the knurled muscles 77 and 78 are integrated with the knurled muscles embedded in the pillars by a binding line to be integrated with the carport pillar. In addition, the number of hairpins may be one.

なお、コンクリート杭75を用いた場合でも、先の実施の形態と同様に、この杭75と柱とをジオグリッド等で接続するように構成してもよい。   Even when the concrete pile 75 is used, the pile 75 and the column may be connected by a geogrid or the like as in the previous embodiment.

次にこの発明のさらに他の実施の形態について説明する。図11は、この発明のさらに他の実施の形態を示す図であり、先に示した図1に対応する。図1の実施の形態においては、一対の鋼管杭を設け、柱の下部と鋼管杭とをジオグリッドのような接続部材で接続したが、この実施の形態においては、鋼管杭を使用しない。   Next, still another embodiment of the present invention will be described. FIG. 11 is a diagram showing still another embodiment of the present invention, and corresponds to FIG. 1 described above. In the embodiment of FIG. 1, a pair of steel pipe piles are provided, and the lower part of the column and the steel pipe pile are connected by a connecting member such as a geogrid. However, in this embodiment, the steel pipe pile is not used.

なお、以下の説明においては、各図の(A)は、柱11の立面を示す図であり、(B)は、図(A)において、B-Bで示す矢視図(平面図)である。   In the following description, (A) in each figure is a view showing an elevation of the pillar 11, and (B) is an arrow view (plan view) indicated by BB in FIG. (A). It is.

この出願の発明者は、各種の実験を行ない、柱11の転倒モーメントが小さい条件下では、ジオグリッドのような所定の強度を有する接続部材を用いて、柱の下部と打設するコンクリートとを一体化すれば、鋼管杭のような杭は不要であることを見いだした。以下にこの実施の形態について説明する。   The inventor of this application performs various experiments, and under the condition that the falling moment of the column 11 is small, the connecting member having a predetermined strength such as a geogrid is used to connect the lower portion of the column and the concrete to be placed. We found that piles like steel pipe piles are unnecessary if they are integrated. This embodiment will be described below.

図11(B)を参照して、まず、図1と同様に隣地との境界の所定の位置にカーポート用の柱11を固定する縦穴91を掘削する。掘削した縦穴91の底面をつき固め、捨てコンを打つ。この捨てコンはなくてもよいが、あると、位置決めが容易になる。   Referring to FIG. 11B, first, similarly to FIG. 1, a vertical hole 91 for fixing the carport column 11 is excavated at a predetermined position on the boundary with the adjacent land. Clamp the bottom of the drilled vertical hole 91 and hit the throwing away. This discarding container may not be provided, but if it is present, positioning becomes easy.

次いで、柱11を据え付ける。ここでは図示を省略しているが、柱11およびその上に設けられた屋根が転倒しないように地面から支持する。ここでは、柱として角柱の場合について説明するが、これに限らず、円形や楕円形等であってもよい。   Next, the pillar 11 is installed. Although not shown here, the pillar 11 and the roof provided thereon are supported from the ground so as not to fall down. Here, the case of a prismatic column will be described, but the present invention is not limited to this, and a circular shape, an elliptical shape, or the like may be used.

この状態で、図12(A)、(B)に示すように、柱11の周囲を囲むようにジオグリッドのような任意の形状で配置可能な接続部材23を配置する。ここでは、接続部材23は、一定の幅を有する長手部材であって、接続部23cでその両端を接続している。この状態で縦穴91内にコンクリートを打設して、柱11、接続部材23およびコンクリートを一体化する。   In this state, as shown in FIGS. 12A and 12B, a connecting member 23 that can be arranged in an arbitrary shape such as a geogrid is disposed so as to surround the periphery of the pillar 11. Here, the connecting member 23 is a longitudinal member having a certain width, and both ends thereof are connected by the connecting portion 23c. In this state, concrete is placed in the vertical hole 91 to integrate the column 11, the connecting member 23, and the concrete.

このとき、接続部材23の横方向の上端部および下端部には、柱11を垂直方向に保持する力がかかるため、それらの端部に沿って横方向に多くの糸量が設けられるか、または、端部を多重に折っておくのが好ましい。   At this time, since a force for holding the pillar 11 in the vertical direction is applied to the upper and lower ends in the horizontal direction of the connecting member 23, a large amount of yarn is provided in the horizontal direction along these ends. Alternatively, it is preferable to fold the end portion in multiple.

接続部材23は、柱11の敷地境界線側においては、柱11に近接するように配置する(接続部材の第1の部分23d)。また、その反対側では柱11から間隔を開けて配置する(接続部材の第2の部分23e)。そして、全体に楕円形、または、柱11側において寸法の狭い台形状に配置する。こうすれば、柱11の敷地境界50の反対側において多くのコンクリートを保持して柱11とコンクリートとが一体化される。また、台形のように2つの辺が交わるような形状になるときは、その2辺の交わる部分は、鋭角ではなく、できるだけ大きな半径となるように配置するのが好ましい。   The connecting member 23 is arranged on the site boundary side of the pillar 11 so as to be close to the pillar 11 (first portion 23d of the connecting member). In addition, on the opposite side, it is arranged at a distance from the pillar 11 (second portion 23e of the connecting member). And it arrange | positions in the trapezoid shape with a narrow dimension in the ellipse or the pillar 11 side as a whole. If it carries out like this, many concrete will be hold | maintained on the opposite side of the site | part boundary 50 of the pillar 11, and the pillar 11 and concrete will be integrated. Moreover, when it becomes a shape where two sides intersect like a trapezoid, it is preferable to arrange | position so that the part which the two sides intersect may have not the acute angle but the largest possible radius.

図13は、上記のようにして施工された柱11の縦穴91およびその中に打設されたコンクリート92による保持状態を示す図である。図13を参照して、柱11の下部とコンクリート92とが接続部材23(図12参照)を介して一体化されているため、施工後に荷重がかかって、柱11が11aや、11bのように斜めになったり、転倒することはない。また、屋根を含めた柱11の転倒モーメントは、敷地境界線50側の縦穴91とコンクリート92との接合部で問題なく受けられる。   FIG. 13 is a view showing a holding state by the vertical hole 91 of the column 11 constructed as described above and the concrete 92 placed therein. With reference to FIG. 13, since the lower part of the pillar 11 and the concrete 92 are integrated via the connection member 23 (refer FIG. 12), a load is applied after construction and the pillar 11 is like 11a and 11b. There is no slanting or tipping over. Further, the falling moment of the pillar 11 including the roof can be received without problems at the joint between the vertical hole 91 and the concrete 92 on the site boundary line 50 side.

なお、縦穴91へのコンクリートの打設においては、型枠をすることなく、コンクリートを土に直接接触させるほうが、両者間の付着力から好ましい。また、型枠を使用した場合は、しっかりと穴固めして埋め戻しをする必要がある。   In placing concrete in the vertical hole 91, it is preferable to bring the concrete into direct contact with the soil without forming a mold because of the adhesive force between the two. In addition, when a formwork is used, it is necessary to firmly fill the hole and backfill.

また、ここでは接続部材23としてジオグリッドを用いた場合について説明したが、これに限らず、ある程度の強度があり、軽くて、細くて、施工性のよいものであれば、プラスチックやエンジニアリングプラスチック等であってもよい。   Further, here, the case where a geogrid is used as the connection member 23 has been described. However, the present invention is not limited to this, and any plastic or engineering plastic may be used as long as it has a certain degree of strength, is light, thin, and has good workability. It may be.

次にこの実施の形態の変形例について図14を参照して説明する。図14に示すように、この実施の形態においては、接続部材としてジオグリッドのような所定の幅を有するものではなく、柱11の下部において、上下の2箇所で幅の狭い接続部材93a、93bを使用して柱11とコンクリートとを一体化する。接続部材93a、93bを柱11の敷地境界50の反対側で保持するために、この実施の形態においては、縦穴91の4隅に鉄筋94a〜94dを設け、これらに直交して、これらを取り囲むように逆C字状の鉄筋94e、94fを設け、図14(B)に示すように、柱11と鉄筋94b、94cとを接続部材93aと93bとで接続する。このように接続した後で、縦穴91の内部にコンクリートを打設する。   Next, a modification of this embodiment will be described with reference to FIG. As shown in FIG. 14, in this embodiment, the connecting member does not have a predetermined width like a geogrid, but the connecting members 93a and 93b having a narrow width at two upper and lower portions in the lower part of the column 11. Is used to integrate the pillar 11 and the concrete. In order to hold the connecting members 93a and 93b on the opposite side of the site boundary 50 of the pillar 11, in this embodiment, reinforcing bars 94a to 94d are provided at the four corners of the vertical hole 91, and they are orthogonal to and surround them. In this way, reverse C-shaped reinforcing bars 94e and 94f are provided, and as shown in FIG. 14B, the pillar 11 and the reinforcing bars 94b and 94c are connected by connecting members 93a and 93b. After connecting in this manner, concrete is placed inside the vertical hole 91.

次にこの実施の形態のさらに他の変形例について図15を参照して説明する。図15に示すように、この実施の形態においては、接続部材として上下の2箇所で幅の狭い接続部材を用いる点では先の変形例に似ているが、柱11とコンクリートとを一体化する接続部材は、柱側部材と、コンクリート側部材と、両者を接続する矩形の鉄板97の3つの部材から構成される。   Next, still another modification of this embodiment will be described with reference to FIG. As shown in FIG. 15, in this embodiment, the connecting member is similar to the previous modification in that a connecting member having a narrow width is used at two upper and lower locations, but the column 11 and the concrete are integrated. The connecting member is composed of three members: a column side member, a concrete side member, and a rectangular iron plate 97 that connects the two.

すなわち、柱11の敷地境界50の反対側に柱11に接触するように矩形の鉄板97を設け、鉄板97と接触しない柱11の残りの部分を上下方向に間隔を開けて配置されたUボルト95a,95bで取り囲み、Uボルト95a,95bを鉄板97にナットで固定する。同様に、コンクリート側でも上下方向に間隔を開けて配置されたUボルト96a,96bを設け、Uボルト96a,96bを鉄板97にナットで固定する。ここで、Uボルト96a,96bのU字間の間隔はUボルト95a,95bの間隔よりも広くなっているのが好ましい。   That is, a rectangular iron plate 97 is provided on the opposite side of the site boundary 50 of the pillar 11 so as to be in contact with the pillar 11, and the remaining portion of the pillar 11 that is not in contact with the iron plate 97 is arranged at intervals in the vertical direction. The U bolts 95a and 95b are fixed to the iron plate 97 with nuts. Similarly, U bolts 96a and 96b arranged at intervals in the vertical direction are also provided on the concrete side, and the U bolts 96a and 96b are fixed to the iron plate 97 with nuts. Here, it is preferable that the space | interval between U character of U bolt 96a, 96b is wider than the space | interval of U bolt 95a, 95b.

次にこの実施の形態のさらに他の変形例について図16を参照して説明する。図16に示すように、この実施の形態においては、柱11の下部で、上下に間隔を開けて設けられた2組の鉄筋で構成された接続部材を用いる。上側の接続部材は、柱11の側面を貫通して設けられたかんざし筋98aと、かんざし筋98aの両端部において結束線(またはケーブルバンド、以下同じ)101で結束された鉄筋99a、99bと、鉄筋99a、99bのかんざし筋98aと接続された側の反対側の端部において結束線101で結束された横筋87aとを含む。下側の接続部材も同様の構成を有し、上側の接続部材と下側の接続部材とは、縦方向に設けられた縦筋86a、86bで接続されている。これらの鉄筋の接続は、結束線101で行ってもよいが、溶接で接続してもよい。   Next, still another modification of this embodiment will be described with reference to FIG. As shown in FIG. 16, in this embodiment, a connection member composed of two sets of reinforcing bars provided at a lower portion in the vertical direction at the lower portion of the column 11 is used. The upper connecting member includes a barb 98a provided through the side surface of the column 11, and reinforcing bars 99a and 99b bound by binding wires (or cable bands, hereinafter the same) 101 at both ends of the barb 98a. The reinforcing bars 99a and 99b include transverse bars 87a bound by a binding wire 101 at the end opposite to the side connected to the knurled bars 98a. The lower connecting member has the same configuration, and the upper connecting member and the lower connecting member are connected by vertical bars 86a and 86b provided in the vertical direction. These reinforcing bars may be connected by the binding wire 101 or may be connected by welding.

図16(B)においては、図4(A)と同様に、柱11を貫通するかんざし筋98a,98b(図示なし)
を固定するために、角柱で構成される柱11の内部にモルタル103を流し込んだ状態を示している。
In FIG. 16 (B), like the case of FIG. 4 (A), the pinnacles 98a and 98b (not shown) penetrating the pillar 11 are used.
In order to fix the mortar 103, a state in which the mortar 103 is poured into the pillar 11 constituted by a prism is shown.

なお、最初の実施の形態においては、杭を用いた場合について説明し、この実施の形態においては、杭を用いない場合について説明したが、どの場合に杭を用いるかは、柱にかかる転倒モーメントの大きさにもよるが、柱を支持するコンクリートの重量にも関係する。すなわち、コンクリートの重量が小さいときは、杭が必要となり、コンクリートの重量が大きくなれば、杭は不要となる。   In the first embodiment, the case where a pile is used has been described. In this embodiment, the case where a pile is not used has been described. It depends on the size of the concrete but also on the weight of the concrete that supports the column. That is, when the concrete weight is small, a pile is necessary, and when the concrete weight is large, the pile is unnecessary.

上記実施の形態においては、カーポートの柱や、背の高いフェンスの柱を補強する場合について説明したが、これに限らず、この柱の基礎の施工方法は、道路標識、ガードレール、看板、信号機、電柱、電灯柱、ポール、バスケットゴールの固定等にも利用が可能である。これらの柱において、鋼管杭を用いた場合は、その径は、柱の寸法にもよるが、約30mm〜150mm程度である。   In the above embodiment, the case of reinforcing a carport pillar or a tall fence pillar has been described, but the construction method of the foundation of this pillar is not limited to this, road signs, guardrails, signboards, traffic lights It can also be used to fix utility poles, light poles, poles and basket goals. In these columns, when steel pipe piles are used, the diameter is about 30 mm to 150 mm, although it depends on the dimensions of the columns.

また、上記実施の形態においては、杭として、一対の鋼管杭を用いて柱と接続する場合について説明したが、これに限らず、1本の鋼管杭を用いてもよいし、地盤に応じて、3本以上の杭を用いてもよい。また、鋼管杭に限らず、非鉄金属の管を用いてもよい。   Moreover, in the said embodiment, although the case where it connected with a pillar using a pair of steel pipe pile as a pile was demonstrated, not only this but one steel pipe pile may be used and according to the ground Three or more piles may be used. Moreover, you may use not only a steel pipe pile but a nonferrous metal pipe.

なお、上記実施の形態の形態では、掘削穴にコンクリートを流し込むと記載したが、これは、使用する箇所に応じて、コンクリートまたは/およびモルタルを使用してもよいことを意味する。   In addition, in the form of the said embodiment, although it described describing pouring concrete into a digging hole, this means that concrete or / and mortar may be used according to the location to be used.

上記実施の形態においては、杭の寸法については、特に規定しなかったが、地盤の悪いところでは、通常に比べて、杭を太く、長くすることで対処可能である。   In the said embodiment, although the dimension of the pile was not prescribed | regulated in particular, in the place where the ground is bad, it can cope by making a pile thicker and longer than usual.

上記実施の形態においては、施工用の縦穴に、杭頭補強部として、より深い縦穴を設けた場合について説明したが、これに限らず、縦穴と杭頭補強部とを同一深さの穴としてもよい。   In the said embodiment, although the case where the deeper vertical hole was provided as a pile head reinforcement part in the vertical hole for construction was demonstrated, not only this but a vertical hole and a pile head reinforcement part as a hole of the same depth Also good.

以上、図面を参照してこの発明の実施形態を説明したが、この発明は、図示した実施形態のものに限定されない。図示された実施形態に対して、この発明と同一の範囲内において、あるいは均等の範囲内において、種々の修正や変形を加えることが可能である。   As mentioned above, although embodiment of this invention was described with reference to drawings, this invention is not limited to the thing of embodiment shown in figure. Various modifications and variations can be made to the illustrated embodiment within the same range or equivalent range as the present invention.

この発明の一実施の形態に係る基礎の施工例を示す平面図および立面図である。It is the top view and elevation which show the example of construction of the foundation concerning one embodiment of this invention. 図1においてII−IIで示す部分の断面図である。It is sectional drawing of the part shown by II-II in FIG. 図1においてII−IIで示す部分の他の実施の形態を示す断面図である。It is sectional drawing which shows other embodiment of the part shown by II-II in FIG. 柱と鋼管杭とを一体化させる他の例を示す平面図である。It is a top view which shows the other example which integrates a pillar and a steel pipe pile. スパイラル筋の構成を示す模式図である。It is a schematic diagram which shows the structure of a spiral muscle. 鋼管杭を示す図である。It is a figure which shows a steel pipe pile. 柱と鋼管杭とを一体化させるさらに他の例を示す立面図である。It is an elevation view which shows the further another example which integrates a pillar and a steel pipe pile. コンクリート杭または樹脂製杭を示す図である。It is a figure which shows a concrete pile or a resin pile. 従来の、隣地に隣接している位置にカーポートの基礎を施工する場合の柱と隣地との境界の位置関係を示す図である。It is a figure which shows the conventional positional relationship of the boundary of a pillar and an adjacent place in the case of constructing the foundation of a carport in the position adjacent to an adjacent place. 従来のフェンスを支持する柱の基礎を示す図である。It is a figure which shows the foundation of the pillar which supports the conventional fence. この発明の他の実施の形態に係る基礎の施工例を示す平面図および立面図である。It is the top view and elevation which show the example of construction of the foundation concerning other embodiments of this invention. 図11においてXII−XIIで示す部分の断面図である。It is sectional drawing of the part shown by XII-XII in FIG. 柱の縦穴およびその中に打設されたコンクリートによる保持状態を示す図である。It is a figure which shows the holding | maintenance state by the vertical hole of a pillar, and the concrete cast | cast in it. 他の実施の形態における変形例を示す図である。It is a figure which shows the modification in other embodiment. 他の実施の形態におけるさらなる変形例を示す図である。It is a figure which shows the further modification in other embodiment. 他の実施の形態におけるさらなる変形例を示す図である。It is a figure which shows the further modification in other embodiment.

符号の説明Explanation of symbols

11,51 柱、21,22,61,62 鋼管杭、23,93 接続部材、25,26,63,64 縦筋、28,79 下端部、29 支持部材、41,65,91 縦穴、45 スパイラル筋、52,53,54,55,98 かんざし筋、42,66,67 杭頭補強の掘削穴、94,99 鉄筋、95 Uボルト、97 鉄板。   11, 51 columns 21, 22, 61, 62 steel pipe piles, 23, 93 connecting members, 25, 26, 63, 64 vertical bars, 28, 79 lower end, 29 support members, 41, 65, 91 vertical holes, 45 spirals Reinforcement, 52, 53, 54, 55, 98 Shark reinforce, 42, 66, 67 Pile head reinforcement excavation hole, 94,99 Reinforcement, 95 U bolt, 97 Iron plate.

Claims (5)

柱の立設位置に縦穴を掘削し、前記縦穴内に柱を設置するステップと、
前記柱の周囲に所定の強度を有する接続部材を巻付けるステップと、
前記縦穴の内部において柱の周囲にコンクリートを打設することにより、前記柱と前記接続部材とコンクリートとを一体化するステップとを含む、柱の基礎の施工方法。
Excavating a vertical hole in the standing position of the column, and installing the column in the vertical hole;
Winding a connection member having a predetermined strength around the pillar;
A method for constructing a pillar foundation, comprising: placing concrete around a pillar inside the vertical hole to integrate the pillar, the connecting member, and concrete.
前記接続部材は前記柱に近接する第1の部分と、前記柱から離れた位置に延在する、前記第1の部分と異なる第2の部分とを含む、請求項1に記載の柱の基礎の施工方法。 2. The pillar foundation according to claim 1, wherein the connection member includes a first part proximate to the pillar and a second part different from the first part extending to a position away from the pillar. Construction method. 前記第1の部分と前記第2の部分とは、相互に対向した位置に延在する、請求項2に記載の柱の基礎の施工方法。 The column foundation construction method according to claim 2, wherein the first portion and the second portion extend to positions facing each other. 前記接続部材は、ジオグリッド、ベルト、ロープ、金属板、鉄筋、スパイラル筋、かんざし筋のいずれかを含む、請求項1から3のいずれかに記載の柱の基礎の施工方法。 The said connection member is the construction method of the foundation of the pillar in any one of Claim 1 to 3 containing any of a geogrid, a belt, a rope, a metal plate, a reinforcing bar, a spiral reinforcement, and a knurled line. 前記ジオグリッドの原織物、ベルト、ロープは、高強度繊維である、請求項4に記載の柱の基礎の施工方法。 The column foundation construction method according to claim 4, wherein the geogrid fabric, belt, and rope are high-strength fibers.
JP2005179487A 2004-01-29 2005-06-20 Pillar foundation construction method Expired - Fee Related JP4636409B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005179487A JP4636409B2 (en) 2004-01-29 2005-06-20 Pillar foundation construction method

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2004022024 2004-01-29
JP2004238711 2004-08-18
JP2005179487A JP4636409B2 (en) 2004-01-29 2005-06-20 Pillar foundation construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2005022010A Division JP3833231B2 (en) 2004-01-29 2005-01-28 Pillar foundation construction method

Publications (3)

Publication Number Publication Date
JP2006083686A true JP2006083686A (en) 2006-03-30
JP2006083686A5 JP2006083686A5 (en) 2008-02-21
JP4636409B2 JP4636409B2 (en) 2011-02-23

Family

ID=36162418

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005179487A Expired - Fee Related JP4636409B2 (en) 2004-01-29 2005-06-20 Pillar foundation construction method

Country Status (1)

Country Link
JP (1) JP4636409B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101081840B1 (en) 2011-07-19 2011-11-09 (주)아리산업 Construction method for footway post
KR101102792B1 (en) 2011-02-16 2012-01-05 (주)아리산업 Construction method for footway post
JP2012219567A (en) * 2011-04-12 2012-11-12 Lend Lease Japan Co Ltd Columnar structure and method of installing columnar structure
KR101277755B1 (en) * 2011-10-05 2013-06-24 (주)명원알앤디 How to install the fence strut and the structure of the fence strut
CN112084635A (en) * 2020-08-21 2020-12-15 山东电力工程咨询院有限公司 Overturning stability verification method and system for power transmission pole foundation

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101102792B1 (en) 2011-02-16 2012-01-05 (주)아리산업 Construction method for footway post
JP2012219567A (en) * 2011-04-12 2012-11-12 Lend Lease Japan Co Ltd Columnar structure and method of installing columnar structure
KR101081840B1 (en) 2011-07-19 2011-11-09 (주)아리산업 Construction method for footway post
KR101277755B1 (en) * 2011-10-05 2013-06-24 (주)명원알앤디 How to install the fence strut and the structure of the fence strut
CN112084635A (en) * 2020-08-21 2020-12-15 山东电力工程咨询院有限公司 Overturning stability verification method and system for power transmission pole foundation
CN112084635B (en) * 2020-08-21 2023-09-01 山东电力工程咨询院有限公司 Method and system for overturning stability verification of transmission pole foundation

Also Published As

Publication number Publication date
JP4636409B2 (en) 2011-02-23

Similar Documents

Publication Publication Date Title
JP4335958B2 (en) Simple foundation
US9151070B2 (en) Anchor post
KR101023660B1 (en) Retaining Wall using Anchor and Concrete Panel and its Construction Method
US8708597B2 (en) System and method for increasing roadway width incorporating a reverse oriented retaining wall and soil nail supports
US20090035061A1 (en) Removable Bollard System and Method of Installation
JP4636409B2 (en) Pillar foundation construction method
JP4437169B2 (en) Simple foundation and aggregate of simple foundations
JP4470208B2 (en) Pillar foundation construction method
US20190010727A1 (en) Anchoring device for a fence
JP6114537B2 (en) Rockfall protection device and rockfall protection method
JP2006083683A (en) Construction method for foundation of column
JP6325248B2 (en) Cell structure construction method and cell structure
JP4190360B2 (en) Masonry wall reinforcement structure and method
KR100822265B1 (en) Revetment structure using natural stones and method for constructing revetment structure using the same
KR100458928B1 (en) Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid
JP2006057442A (en) Anti-falling rock fence
KR20180101986A (en) Methods for constructing retaining wall using fastening unit for stiffener
KR100711054B1 (en) A construction method of concrete retaining wall using anchor
JP3828142B1 (en) Steel column pole construction method
KR101782408B1 (en) Methods for constructing retaining wall using fastening unit for stiffener
KR101020217B1 (en) rock construction structure of using anchor and method thereof
CN205617175U (en) Be applied to temporary support structure of widening fast in place
RU2603036C2 (en) Flexible protective concrete pavement and method of its laying
CN115094944A (en) Gabion retaining wall and construction method thereof
JP2024103910A (en) How to Install a Security Fence

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071228

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071228

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20071228

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20080208

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080318

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080519

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080715

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080916

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090106

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090205

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20090313

A912 Removal of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20090403

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100809

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100910

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20101112

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131203

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4636409

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees