JP2005309643A - Operation state monitoring device, monitoring object device, and program therefor - Google Patents

Operation state monitoring device, monitoring object device, and program therefor Download PDF

Info

Publication number
JP2005309643A
JP2005309643A JP2004123759A JP2004123759A JP2005309643A JP 2005309643 A JP2005309643 A JP 2005309643A JP 2004123759 A JP2004123759 A JP 2004123759A JP 2004123759 A JP2004123759 A JP 2004123759A JP 2005309643 A JP2005309643 A JP 2005309643A
Authority
JP
Japan
Prior art keywords
notification
monitoring
connection
connection notification
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004123759A
Other languages
Japanese (ja)
Inventor
Takeshi Matsuda
丈司 松田
Hiroshi Suzuki
鈴木  寛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2004123759A priority Critical patent/JP2005309643A/en
Publication of JP2005309643A publication Critical patent/JP2005309643A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Computer And Data Communications (AREA)
  • Telephonic Communication Services (AREA)
  • Power Sources (AREA)
  • Debugging And Monitoring (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide an operation state monitoring device for monitoring the operation state of a monitoring object device, capable of further precisely determining the operating state of the monitoring object device. <P>SOLUTION: The monitoring object device 30 has a schedule of "connection report" transmission, and a report center device (the operation state monitoring device) 10 has a schedule of "connection report" confirmation. The report center device 10 monitors the operating state of the monitoring object device 20 by confirming receipt of "connection report" unilaterally transmitted therefrom. The device 30 reports information for its own power supply ON/OFF to the center device 10, and the center device 10 performs start/release of monitoring on the basis of the report. The device 10 automatically restarts the monitoring of the device 30 in a determined condition after releasing the monitoring by power supply OFF of the device 30. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は,保守サービスの対象となる顧客装置とネットワークで接続された保守サービスを行うコールセンターが,顧客装置での障害発生を自動的に監視する技術に関するものであり,特に,顧客装置の稼動状況を監視する稼動状況監視装置,監視対象装置およびそれらのプログラムに関するものである。   The present invention relates to a technology in which a call center that performs a maintenance service connected to a customer device that is a maintenance service target through a network automatically monitors the occurrence of a failure in the customer device. The present invention relates to an operation status monitoring device, a monitoring target device and their programs.

従来から,コールセンターにネットワークで接続された顧客装置に障害が発生した場合に,その顧客装置がコールセンターに自動的に障害情報を送信するといった保守サービスが存在する。このような保守サービスを行う場合において,コールセンター側が顧客装置の稼動状況を知ることは,非常に重要である。これは,顧客装置自体が障害により停止してしまった場合には,その顧客装置が障害通報を送信できなくなり,コールセンター側で十分な保守サービスを提供することができなくなるからである。   Conventionally, when a failure occurs in a customer device connected to the call center via a network, there is a maintenance service in which the customer device automatically transmits failure information to the call center. When performing such a maintenance service, it is very important for the call center side to know the operating status of the customer device. This is because if the customer device itself is stopped due to a failure, the customer device cannot send a failure notification and cannot provide a sufficient maintenance service on the call center side.

従来,コールセンター側が顧客装置の稼動状況を知るための技術として,コールセンターがネットワークで接続されている顧客装置に対して問合せを行い,顧客装置からの応答の有無によって顧客装置の稼動状況を判断するという技術があった。このような技術では,一般にネットワーク接続に専用線が用いられていた。   Conventionally, as a technology for the call center side to know the operating status of customer equipment, the call center makes an inquiry to the customer equipment connected via the network, and determines the operating status of the customer equipment based on whether there is a response from the customer equipment. There was technology. In such technology, a dedicated line is generally used for network connection.

しかし,顧客装置が多くなると,各顧客装置にアクセスする必要のあるコールセンター側の負荷が大きくなるという問題があった。また,ネットワーク接続の中心がインターネットとなった現在,情報セキュリティーの考えが厳しくなってきており,セキュリティー面から見るとあまり好ましくないコールセンター側から顧客装置へのアクセスができなくなってきているという問題があった。   However, as the number of customer devices increases, there is a problem that the load on the call center side that needs to access each customer device increases. In addition, now that the Internet has become the center of network connection, information security has become stricter, and there is a problem that it is not possible to access customer devices from the call center side, which is not very desirable from the security aspect. It was.

このような状況に対し,顧客装置からコールセンターに一方的かつ定期的に電子メール(定期接続通知)を送信し,コールセンターはそのメールを受信することで顧客装置の稼動状況を監視する技術がある。このような技術では,定期接続通知がコールセンターに届かない場合に顧客装置に稼動障害が発生していると判断していた。   In response to such a situation, there is a technology for monitoring the operational status of a customer device by sending an email (periodic connection notification) unilaterally and periodically from the customer device to the call center and receiving the email. In such a technique, it is determined that an operation failure has occurred in the customer device when the periodic connection notification does not reach the call center.

なお,監視対象装置の稼動状況を稼動状況監視装置が監視する従来技術として,例えば,特許文献1,特許文献2,特許文献3,特許文献4などがある。
特開平7−250156号公報 特開平5−22313号公報 特開平10−40192号公報 特公平7−101390号公報
For example, Patent Literature 1, Patent Literature 2, Patent Literature 3, Patent Literature 4 and the like are known as conventional technologies for monitoring the operational status of the monitoring target device.
JP-A-7-250156 Japanese Patent Laid-Open No. 5-22313 Japanese Patent Laid-Open No. 10-40192 Japanese Examined Patent Publication No. 7-101390

前述のように,顧客装置からコールセンターに定期接続通知を送信する技術を用いることにより,定期接続通知がコールセンターに届かない場合に顧客装置に稼動障害が発生していると判断することができる。しかし,顧客が都合によって顧客装置の電源を停止した場合にも定期接続通知が送信されなくなるため,コールセンター側では顧客装置に稼動障害が発生したと誤判断してしまうという問題があった。   As described above, by using a technology for transmitting a regular connection notification from the customer device to the call center, it is possible to determine that an operation failure has occurred in the customer device when the regular connection notification does not reach the call center. However, since the periodic connection notification is not transmitted even if the customer stops the power supply of the customer device due to circumstances, there is a problem that the call center erroneously determines that an operation failure has occurred in the customer device.

このような状況に対し,顧客装置の電源のON/OFF時に,顧客装置がその電源のON/OFFをコールセンターに通知する技術がある(例えば,特許文献3,特許文献4参照)。この技術において,コールセンター側では,顧客装置から電源OFFの通知を受けた場合にその顧客装置に対する監視を停止し,顧客装置から電源ONの通知を受けた場合にその顧客装置に対する監視を再開する。   In such a situation, there is a technique in which the customer apparatus notifies the call center of the ON / OFF of the power supply when the power of the customer apparatus is turned ON / OFF (see, for example, Patent Document 3 and Patent Document 4). In this technique, when the call center receives a power-off notification from a customer device, monitoring for the customer device is stopped, and when the power-on notification is received from the customer device, monitoring for the customer device is resumed.

しかし,顧客装置が電源OFF通知を行って電源をOFFした後に稼動障害が発生し,電源をONすることができないような場合に,コールセンター側ではそのことを認識することができないという問題があった。   However, there is a problem that the call center cannot recognize when an operation failure occurs after the customer's device issues a power OFF notification and the power is turned OFF and the power cannot be turned ON. .

本発明は,上記の問題点の解決を図り,コールセンター側で顧客装置の稼動状況を最適に監視することが可能となる技術を提供することを目的とする。   SUMMARY OF THE INVENTION An object of the present invention is to solve the above-described problems and to provide a technique that can optimally monitor the operating status of a customer device on the call center side.

本発明は,上記の課題を解決するため,正常に稼動している顧客装置は,定期的に“接続通知”をコールセンター側に送信し,コールセンター側は,定期的に“接続通知”の受信を確認することにより顧客装置の稼動を確認することを特徴とする。また,そのために,顧客装置側が“接続通知”を送信するためのスケジュールを備え,コールセンター側が“接続通知”の受信を確認するためのスケジュールを備えることを特徴とする。   In order to solve the above-described problems, the customer apparatus that is operating normally periodically transmits a “connection notification” to the call center side, and the call center side periodically receives the “connection notification”. It is characterized by confirming the operation of the customer device by confirming. For this purpose, the customer apparatus side has a schedule for transmitting a “connection notification”, and the call center side has a schedule for confirming reception of the “connection notification”.

顧客装置側の“接続通知”を送信するためのスケジュールと,コールセンター側の“接続通知”の受信を確認するためのスケジュールは,連携しながらもそれぞれ独立して存在する。顧客装置側でスケジュールに関する情報(接続周期,電源停止期間(電源停止日時,電源復帰日時),電源復帰後チェック間隔など)が設定・更新されると,顧客装置は,その設定された情報の通知(“接続周期設定通知”,“電源停止期間設定通知”,“電源復帰後チェック間隔設定通知”など)をコールセンター側に送信する。顧客装置側では,設定・更新された情報をもとに“接続通知”を送信するためのスケジュールを作成し,コールセンター側では,顧客装置から受信した通知をもとに“接続通知”の受信を確認するためのスケジュールを作成する。   The schedule for transmitting the “connection notification” on the customer apparatus side and the schedule for confirming the reception of the “connection notification” on the call center side exist independently while cooperating. When information related to the schedule (connection period, power outage period (power stop date / time, power return date / time), check interval after power return, etc.) is set and updated on the customer device side, the customer device notifies the set information. (“Connection cycle setting notification”, “Power supply stop period setting notification”, “Check interval setting notification after power recovery”, etc.) are transmitted to the call center side. The customer device creates a schedule for sending a “connection notification” based on the set / updated information, and the call center receives the “connection notification” based on the notification received from the customer device. Create a schedule to check.

このように,顧客装置でのスケジュールの設定・更新は,通知によりコールセンター側に伝えられるため,顧客装置でのスケジュールの変更が容易になる。   As described above, since the setting / update of the schedule in the customer apparatus is transmitted to the call center side by notification, the schedule in the customer apparatus can be easily changed.

また,顧客装置は,自身の状況(電源のON/OFF,異常状態の発生など)を伝えるための通知(“電源ON通知”,“電源OFF通知”,“その他通知”など)をコールセンター側に送信する。コールセンター側では,顧客装置の状況によって,監視を開始したり,監視を解除したりする。   In addition, the customer device sends notifications (“Power ON Notification”, “Power OFF Notification”, “Other Notification”, etc.) to inform the call center of its own status (power ON / OFF, occurrence of abnormal condition, etc.). Send. On the call center side, the monitoring is started or the monitoring is canceled depending on the status of the customer device.

ここで,“接続通知”,スケジュールに関する情報の通知,顧客装置の状況を伝えるための通知などは,顧客装置からコールセンター側に一方的に送信され,顧客装置の稼動状況を確認するためにコールセンター側から顧客装置にアクセスする必要はない。   Here, “connection notification”, notification of information related to the schedule, notification for conveying the status of the customer device, etc. are transmitted unilaterally from the customer device to the call center side, and the call center side confirms the operating status of the customer device. There is no need to access customer equipment from

以上のような本発明の主な特徴を,場合分けしてよりわかりやすく説明すると,以下のようになる。   The main features of the present invention as described above will be described in a more easy-to-understand manner by dividing the cases.

(1)顧客装置は,正常に稼動している場合に,定期的に“接続通知”をコールセンター側に送信する。コールセンター側は,定期的に顧客装置からの“接続通知”があるかを確認し,顧客装置からの定期的な“接続通知”が確認できなかった場合に,その顧客装置に何らかの障害が発生したと判断する。顧客装置は,あらかじめ“接続周期設定通知”を送ることにより,コールセンター側に“接続通知”の送信周期を伝える。   (1) When the customer apparatus is operating normally, it periodically transmits a “connection notification” to the call center side. The call center periodically checks whether there is a “connection notification” from the customer device. If the regular “connection notification” from the customer device cannot be confirmed, a failure has occurred in the customer device. Judge. The customer device transmits a “connection notification” transmission cycle to the call center by sending a “connection cycle setting notification” in advance.

(2)顧客装置は,一時的に電源をOFFするときに,“電源OFF通知”をコールセンター側に送信する。コールセンター側は,顧客装置から“電源OFF通知”を受けると,その顧客装置に対する監視を解除する。その後,あらかじめ定められた条件が満たされると,その顧客装置に対する監視を再開する。例えば,最初の定期的な“接続通知”の確認のタイミングで再び監視を開始し,さらにその次の定期的な“接続通知”の確認のタイミングで顧客装置からの定期的な“接続通知”が確認できなかった場合に,その顧客装置に何らかの障害が発生したと判断する。   (2) When the customer device temporarily turns off the power, the customer device sends a “power off notification” to the call center. When the call center receives a “power OFF notification” from the customer device, the call center cancels the monitoring of the customer device. Thereafter, when a predetermined condition is satisfied, monitoring of the customer device is resumed. For example, the monitoring is started again at the timing of the first periodic “connection notification” confirmation, and then the periodic “connection notification” from the customer device is received at the next periodic “connection notification” confirmation timing. If it cannot be confirmed, it is determined that some trouble has occurred in the customer device.

(3)顧客装置は,OFF状態となっていた電源をONしたときに,“電源ON通知”をコールセンター側に送信する。コールセンター側は,顧客装置から“電源ON通知”を受けると,その顧客装置に対する監視を開始する。監視開始後は,(1)の場合と同様となる。   (3) When the customer apparatus turns on the power supply that has been in the OFF state, the customer apparatus transmits a “power ON notification” to the call center side. When the call center receives a “power ON notification” from the customer device, it starts monitoring the customer device. After the start of monitoring, it is the same as in (1).

(4)顧客装置は,ある期間の稼動を停止する場合に,“電源停止期間設定通知”をコールセンター側に送信する。コールセンター側では,顧客装置から“電源停止期間設定通知”を受けると,その通知が示す電源停止日時にその顧客装置に対する監視を解除し,その通知が示す電源復帰日時にその顧客装置に対する監視を再開する。電源復帰日時から一定時間後に,顧客装置は,“接続通知”をコールセンター側に送信する。監視を再開してから一定時間後に,コールセンター側では,顧客装置からの“接続通知”があるかを確認し(電源復帰後チェック),顧客装置からの“接続通知”が確認できなかった場合に,その顧客装置に何らかの障害が発生したと判断する。顧客装置は,あらかじめ“電源復帰後チェック間隔設定通知”を送ることにより,コールセンター側に監視再開後の“接続通知”の送信時期を伝える。   (4) When the customer apparatus stops operation for a certain period, it transmits a “power supply stop period setting notification” to the call center side. When the call center receives a “power outage period setting notification” from the customer device, the monitoring for the customer device is canceled at the power outage date and time indicated by the notification, and the monitoring for the customer device is resumed at the power recovery date and time indicated by the notification. To do. After a certain time from the power recovery date and time, the customer device sends a “connection notification” to the call center. After a certain time after resuming monitoring, the call center checks whether there is a “connection notification” from the customer device (check after power is restored), and if the “connection notification” from the customer device cannot be confirmed. , It is determined that some trouble has occurred in the customer device. The customer device notifies the call center side of the transmission timing of the “connection notification” after resuming monitoring by sending a “check interval setting notification after power recovery” in advance.

(5)通常の障害通知など,顧客装置の稼動状況に関する通知以外の通知(“その他通知”)を顧客装置から受信すると,コールセンター側は,その顧客装置に対する監視を開始する。監視開始後は,(1)の場合と同様となる。   (5) When a notification (“other notification”) other than the notification regarding the operation status of the customer device, such as a normal failure notification, is received from the customer device, the call center side starts monitoring the customer device. After the start of monitoring, it is the same as in (1).

具体的に,本発明は,監視対象装置(顧客装置)の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置(コールセンター側の装置)であって,監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,接続通知の受信確認を行うためのスケジュールに従って,監視対象装置からの接続通知の受信を確認することにより,監視対象装置の稼動状況を監視する手段とを備え,監視対象装置の稼動状況を監視する手段は,監視対象装置からの接続通知の受信が確認できなかった場合に,監視対象装置に稼動障害が発生していると判断する手段と,監視対象装置が電源を停止することを示す通知である電源OFF通知を受信した場合に,監視対象装置に対する監視を解除し,その後あらかじめ定められた条件が満たされたときに,自動的に監視対象装置に対する監視を再開する手段とを備えることを特徴とする。   Specifically, the present invention relates to an operating status monitoring device (call center side device) in an operating status monitoring system that monitors the operating status of a monitoring target device (customer device), and that the monitoring target device is operating. Monitoring target device by confirming the reception of the connection notification from the monitoring target device according to the means for recording the schedule for confirming the reception of the connection notification and the schedule for checking the reception of the connection notification. Means for monitoring the operational status of the monitored device, and the means for monitoring the operational status of the monitored device is the result of an operational failure occurring in the monitored device when the connection notification from the monitored device cannot be confirmed. The monitoring of the monitoring target device is canceled when the power OFF notification, which is a notification indicating that the monitoring target device stops the power supply, is received. When subsequent predetermined condition is satisfied, automatically, characterized in that it comprises resuming means monitoring for the monitored device.

また,本発明は,監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置であって,監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,接続通知の受信確認を行うためのスケジュールに従って,監視対象装置からの接続通知の受信を確認することにより,監視対象装置の稼動状況を監視する手段とを備え,監視対象装置の稼動状況を監視する手段は,監視対象装置からの接続通知の受信が確認できなかった場合に,監視対象装置に稼動障害が発生していると判断する手段と,監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,電源停止期間設定通知が示す監視対象装置が電源を停止する予定日時に監視対象装置に対する監視を解除し,電源停止期間設定通知が示す監視対象装置が電源を復帰する予定日時に監視対象装置に対する監視を再開する手段とを備えることを特徴とする。   In addition, the present invention is an operation status monitoring device in an operation status monitoring system that monitors the operation status of a monitoring target device, and performs reception confirmation of a connection notification that is a notification indicating that the monitoring target device is operating. And a means for monitoring the operation status of the monitored device by confirming reception of the connection notification from the monitored device according to the schedule for confirming reception of the connection notification. The means for monitoring the operation status of the target device includes a means for determining that an operation failure has occurred in the monitored device when reception of a connection notification from the monitored device cannot be confirmed, Monitoring is performed at the scheduled date and time when the monitoring target device indicated by the power outage period setting notification is stopped when a power outage period setting notice is received, which indicates the period during which Unmonitor for elephants device, characterized in that it comprises resuming means monitoring for the monitored device to the scheduled date and time the monitored device indicated by the power supply stop period setting notification returns the power.

また,本発明は,稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムにおける監視対象装置であって,自身が稼動していることを示す通知である接続通知を稼動状況監視装置に送信するためのスケジュールを記録する手段と,接続通知を送信するためのスケジュールに従って,稼動状況監視装置に接続通知を送信する手段と,自身の電源を停止する期間の予定日時が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を稼動状況監視装置に送信する手段とを備えることを特徴とする。   In addition, the present invention is a monitoring target device in an operating status monitoring system in which the operating status monitoring device monitors the operating status of the monitoring target device, and a connection notification that is a notification indicating that the operating status monitoring device is operating. The means for recording the schedule for sending to the device, the means for sending the connection notification to the operating status monitoring device according to the schedule for sending the connection notification, and the scheduled date and time of the period for shutting down its own power supply are set And a means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device.

以上の各手段による処理は,コンピュータとソフトウェアプログラムとによって実現することができ,そのプログラムをコンピュータ読み取り可能な記録媒体に記録することも,ネットワークを通して提供することも可能である。   The processing by each means described above can be realized by a computer and a software program, and the program can be recorded on a computer-readable recording medium or provided through a network.

本発明により,コールセンター側から顧客装置にアクセスしなくてもコールセンター側で顧客装置の稼動状況を把握することができるようになるため,コールセンター側の負担が軽減されるようになる。   According to the present invention, it becomes possible to grasp the operating status of the customer device on the call center side without accessing the customer device from the call center side, so that the burden on the call center side is reduced.

また,コールセンター側で顧客装置の電源のON/OFFを把握することができるようになるため,稼動障害発生の検出確度が高くなり,コールセンターのサポート員が不要な対応を行わずにすむようになる。   Further, since the call center side can grasp the power ON / OFF of the customer device, the detection accuracy of the operation failure occurrence is increased, and the call center support staff does not need to take unnecessary measures.

また,顧客装置が電源をOFFした後に稼動障害が発生した場合や,電源停止期間中に稼動障害が発生した場合でも,その後にコールセンター側で解除となっていた顧客装置の監視を自動的に再開するため,監視解除中の稼動障害の発生を検出できるようになる。   In addition, even if an operation failure occurs after the customer device is turned off, or if an operation failure occurs during the power outage period, monitoring of the customer device that has been canceled on the call center side is automatically resumed. As a result, it becomes possible to detect the occurrence of an operation failure during cancellation of monitoring.

顧客装置からコールセンター側への通知をもとに稼動障害を検出する方法であるため,セキュリティー上の問題もなくなる。すなわち,コールセンター側から顧客装置にアクセスして稼動状況の情報を収集すると,顧客側が顧客装置内の情報漏洩の不安を抱く場合があるが,本発明では,コールセンター側が直接,顧客装置へアクセスすることはないので,情報漏洩のおそれのようなセキュリティー上の問題が解決される。   Since this is a method of detecting an operation failure based on notification from the customer device to the call center, there is no security problem. That is, when the customer center is accessed from the call center side and the operation status information is collected, the customer side may have anxiety about information leakage in the customer device, but in the present invention, the call center side directly accesses the customer device. This eliminates security problems such as information leakage.

図1は,本発明の実施の形態における稼動状況監視システムの構成例を示す図である。稼動状況監視システムにおいて,コールセンターには,顧客装置の稼動状況や障害の発生を監視する稼動状況監視装置である通報センター装置10と,コールセンターに勤めるサポート員が通報センター装置10からの通報を監視するためのコールセンターシステム20が備えられている。また,通報センター装置10は,障害発生の監視対象となる顧客装置である複数の監視対象装置30に,ネットワーク40を介して接続されている。   FIG. 1 is a diagram showing a configuration example of an operation status monitoring system according to an embodiment of the present invention. In the operating status monitoring system, the call center has a reporting center device 10 that is an operating status monitoring device that monitors the operating status and failure occurrence of customer devices, and a support member who works for the call center monitors reports from the reporting center device 10. A call center system 20 is provided. Further, the reporting center device 10 is connected via a network 40 to a plurality of monitoring target devices 30 that are customer devices to be monitored for failure occurrence.

監視対象装置30は,自身の稼動状況や異常発生状況を通報センター装置10に伝えるための通知を行う。通知方法としては,例えば電子メールを利用することができる。通報センター装置10は,監視対象装置30からの通知状況からその監視対象装置30の状況を判断し,監視対象装置30に何らかの障害があると判断された場合には,その旨をコールセンターシステム20に通報する。サポート員は,コールセンターシステム20で通報センター装置10からの通報を監視し,その通報の内容に合わせて監視対象装置30への対応を行う。   The monitoring target device 30 performs a notification to notify the reporting center device 10 of its own operating status and abnormality occurrence status. As a notification method, e-mail can be used, for example. The reporting center device 10 determines the status of the monitoring target device 30 from the notification status from the monitoring target device 30, and if it is determined that there is some failure in the monitoring target device 30, the notification center device 10 notifies the call center system 20 to that effect. report. The support staff monitors the report from the report center apparatus 10 by the call center system 20, and responds to the monitoring target apparatus 30 in accordance with the contents of the report.

図2は,本実施の形態における監視対象装置から通報センター装置への通知の例を示す図である。監視対象装置30が通報センター装置10に送信する通知には,図2に示すようなものがある。   FIG. 2 is a diagram illustrating an example of notification from the monitoring target device to the notification center device in the present embodiment. The notifications that the monitoring target device 30 transmits to the notification center device 10 include those shown in FIG.

(a)“接続通知”:監視対象装置30が,自らが稼動していることを通報センター装置10に伝えるための通知である。装置ID(監視対象装置を一意に認識するためのID),通知名(この場合は“接続通知”)などの情報を持つ。   (A) “Connection Notification”: Notification for informing the reporting center device 10 that the monitoring target device 30 is operating. It has information such as a device ID (ID for uniquely recognizing a device to be monitored) and a notification name (in this case, “connection notification”).

(b)“接続周期設定通知”:監視対象装置30が,定期的な“接続通知”の送信の周期を通報センター装置10に伝えるための通知である。装置ID,接続周期(定期的な“接続通知”の送信のスケジュール),通知名(この場合は“接続周期設定通知”)などの情報を持つ。   (B) “Connection cycle setting notification”: This is a notification for the monitoring target device 30 to notify the reporting center device 10 of the periodic transmission cycle of the “connection notification”. It has information such as device ID, connection cycle (scheduling schedule for periodic “connection notification”), and notification name (in this case, “connection cycle setting notification”).

(c)“電源停止期間設定通知”:監視対象装置30が,長期に電源を停止する予定がある場合などに,その停止期間を通報センター装置10に伝えるための通知である。装置ID,電源停止日時(電源をOFFする予定日時),電源復帰日時(電源をONする予定日時),通知名(この場合は“電源停止期間設定通知”)などの情報を持つ。   (C) “Power supply stop period setting notification”: This is a notification for notifying the reporting center apparatus 10 of the stop period when the monitoring target device 30 is scheduled to stop the power supply for a long period of time. It has information such as device ID, power supply stop date / time (scheduled power-off date / time), power recovery date / time (scheduled power-on date / time), and notification name (in this case, “power supply stop period setting notification”).

(d)“電源復帰後チェック間隔設定通知”:監視対象装置30が,電源停止期間終了(電源復帰日時)から電源復帰後チェックのための“接続通知”を送信するまでの時間間隔を通報センター装置10に伝えるための通知である。装置ID,電源復帰後チェック間隔(電源復帰日時から電源復帰後チェックのための“接続通知”を送信するまでの時間間隔),通知名(この場合は“電源復帰後チェック間隔設定通知”)などの情報を持つ。   (D) “Check interval setting notification after power recovery”: Notification center indicating the time interval from the end of the power stop period (power recovery date and time) until the monitoring target device 30 transmits a “connection notification” for checking after power recovery This is a notification for transmitting to the device 10. Device ID, check interval after power recovery (time interval from power recovery date and time until “connection notification” is sent to check after power recovery), notification name (in this case “check interval setting notification after power recovery”), etc. With information.

(e)“電源OFF通知”:監視対象装置30が,自らの電源OFFを通報センター装置10に伝えるための通知である。装置ID,通知名(この場合は“電源OFF通知”)などの情報を持つ。監視対象装置30の電源OFF直前に送信される。   (E) “Power OFF Notification”: Notification for the monitoring target device 30 to notify the reporting center device 10 of its own power OFF. It has information such as a device ID and a notification name (in this case, “power off notification”). Sent immediately before the monitoring target device 30 is powered off.

(f)“電源ON通知”:監視対象装置30が,自らの電源ONを通報センター装置10に伝えるための通知である。装置ID,通知名(この場合は“電源ON通知”)などの情報を持つ。監視対象装置30の電源ON直後に送信される。   (F) “Power ON Notification”: This is a notification for the monitoring target device 30 to notify the reporting center device 10 of its own power ON. It has information such as a device ID and a notification name (in this case, “power-on notification”). Sent immediately after the monitoring target device 30 is powered on.

(g)“その他通知”:監視対象装置30が,通報センター装置10に送信する上記(a)〜(f)以外の通知である。例えば,“通常の障害通知”(監視対象装置30が,自らに発生した何らかの障害をセンター装置10に伝えるための通知,装置ID,障害情報(発生した障害に関する情報),通知名(この場合は“通常の障害通知”)などの情報を持つ)などがある。   (G) “Other notifications”: Notifications other than the above (a) to (f) transmitted from the monitoring target device 30 to the notification center device 10. For example, “normal failure notification” (a notification for the monitoring target device 30 to notify the center device 10 of any failure that has occurred to itself, device ID, failure information (information about the failure that has occurred), notification name (in this case) Etc.) with information such as “normal fault notification”).

図3は,本実施の形態における通報センター装置からコールセンターシステムへの通報の例を示す図である。通報センター装置10がコールセンターシステム20に送信する通報には,図3に示すようなものがある。   FIG. 3 is a diagram illustrating an example of a report from the report center apparatus to the call center system in the present embodiment. The notification that the notification center device 10 transmits to the call center system 20 is as shown in FIG.

(a)“稼動障害通報”(“タイムアウト通報”):通報センター装置10が,監視対象装置30の稼動状況に問題があると判断したときに,コールセンターシステム20に送信する通報である。   (A) “Operation failure notification” (“timeout notification”): This notification is transmitted to the call center system 20 when the notification center device 10 determines that there is a problem with the operation status of the monitoring target device 30.

(b)“障害通報”:監視対象装置30に通常の障害が発生した場合に,通報センター装置10がコールセンターシステム20に送信する通報である。   (B) “Failure notification”: A notification transmitted from the notification center device 10 to the call center system 20 when a normal failure occurs in the monitoring target device 30.

図4は,本実施の形態における監視対象装置の構成例を示す図である。監視対象装置30は,接続通知スケジュールDB(データベース)31,接続通知スケジュール設定部32,通知作成・送信部33から構成される。   FIG. 4 is a diagram illustrating a configuration example of the monitoring target device according to the present embodiment. The monitoring target device 30 includes a connection notification schedule DB (database) 31, a connection notification schedule setting unit 32, and a notification creation / transmission unit 33.

接続通知スケジュールDB31には,監視対象装置30が通報センター装置10に“接続通知”を送信するためのスケジュール情報が記録される。接続通知スケジュール設定部32は,接続通知スケジュールDB31の設定・更新が必要な場合にその記録を設定・更新する。通知作成・送信部33は,通報センター装置10に送信する通知を作成し,送信する。   In the connection notification schedule DB 31, schedule information for the monitoring target device 30 to transmit “connection notification” to the notification center device 10 is recorded. The connection notification schedule setting unit 32 sets / updates the record when the connection notification schedule DB 31 needs to be set / updated. The notification creation / transmission unit 33 creates and transmits a notification to be transmitted to the notification center device 10.

図5は,本実施の形態における監視対象装置の接続通知スケジュールDBの構造の例を示す図である。接続通知スケジュールDB31には,接続周期,電源停止期間(電源停止日時,電源復帰日時),電源復帰後チェック間隔,接続通知予定日時の情報が記録される。   FIG. 5 is a diagram showing an example of the structure of the connection notification schedule DB of the monitoring target device in the present embodiment. The connection notification schedule DB 31 records information about a connection cycle, a power supply stop period (power supply stop date and time, power supply return date and time), a check interval after power supply return, and a connection notification scheduled date and time.

接続周期には,定期的に“接続通知”を送信する周期が記録される。接続周期が設定・更新されると,通知作成・送信部33は,“接続周期設定通知”を作成し,通報センター装置10に送信する。   In the connection cycle, a cycle for periodically transmitting a “connection notification” is recorded. When the connection cycle is set / updated, the notification creation / transmission unit 33 creates a “connection cycle setting notification” and transmits it to the notification center device 10.

電源停止期間には,長期に監視対象装置30の電源の停止を行う予定がある場合などに,その電源OFFの予定日時(電源停止日時)と電源ONの予定日時(電源復帰日時)とが記録される。電源停止期間が設定・更新されると,通知作成・送信部33は,“電源停止期間設定通知”を作成し,通報センター装置10に送信する。   In the power stop period, when the power of the monitored device 30 is scheduled to be stopped for a long time, the scheduled power off date and time (power stop date and time) and the scheduled power on date and time (power return date and time) are recorded. Is done. When the power stop period is set / updated, the notification creation / transmission unit 33 creates a “power stop period setting notification” and transmits it to the notification center device 10.

電源復帰後チェック間隔には,電源停止期間終了(電源復帰日時)から電源復帰後チェックのための“接続通知”を送るまでの時間間隔が記録される。電源復帰後チェック間隔は,10〜15分程度である。電源復帰後チェック間隔が設定・更新されると,通知作成・送信部33は,“電源復帰後チェック間隔設定通知”を作成し,通報センター装置10に送信する。   In the check interval after power recovery, the time interval from the end of the power stop period (power recovery date and time) until the “connection notification” for checking after power recovery is sent is recorded. The check interval after power recovery is about 10 to 15 minutes. When the check interval after power recovery is set / updated, the notification creation / transmission unit 33 creates a “check interval setting notification after power recovery” and transmits it to the notification center device 10.

接続通知予定日時には,次回の“接続通知”を送信する予定日時が記録される。接続通知予定日時になると,通知作成・送信部33は,“接続通知”を作成し,通報センター装置10に送信する。接続通知予定日時は,接続通知スケジュール設定部32により自動的に設定される。   In the scheduled connection notification date and time, the scheduled date and time for transmitting the next “connection notification” is recorded. When the scheduled connection notification date / time is reached, the notification creation / transmission unit 33 creates a “connection notification” and transmits it to the notification center device 10. The connection notification scheduled date and time is automatically set by the connection notification schedule setting unit 32.

図6は,本実施の形態における監視対象装置の接続通知予定日時設定処理フローチャートである。監視対象装置30は,(1)“接続通知”送信後,(2)“電源ON通知”送信後,(3)“接続周期設定通知”送信後,(4)“電源停止期間設定通知”送信後,(5)“電源復帰後チェック間隔設定通知”送信後などに,接続通知スケジュール設定部32に対して接続通知予定日時変更命令を出す。   FIG. 6 is a connection notification scheduled date and time setting process flowchart of the monitoring target device according to the present embodiment. The monitoring target device 30 (1) transmits a “connection notification”, (2) transmits a “power ON notification”, (3) transmits a “connection cycle setting notification”, and (4) transmits a “power stop period setting notification”. Then, after sending (5) “check interval setting notification after power return”, a connection notification scheduled date / time change command is issued to the connection notification schedule setting unit 32.

接続通知スケジュール設定部32は,接続通知予定日時変更命令を受けると,まず,接続通知スケジュールDB31の接続周期から,次回の定期的な“接続通知”の送信予定日時Taを算出する(ステップS10)。   When receiving the connection notification scheduled date / time change command, the connection notification schedule setting unit 32 first calculates the scheduled transmission date / time Ta of the next periodic “connection notification” from the connection cycle of the connection notification schedule DB 31 (step S10). .

接続通知スケジュールDB31の電源停止期間の設定があるかを確認し(ステップS11),電源停止期間の設定がなければ,Taを接続通知予定日時として接続通知スケジュールDB31に設定する(ステップS12)。   It is confirmed whether or not the power supply stop period is set in the connection notification schedule DB 31 (step S11). If there is no power supply stop period, Ta is set in the connection notification schedule DB 31 as the connection notification scheduled date and time (step S12).

ステップS11において,電源停止期間の設定があれば,接続通知スケジュールDB31の電源復帰日時に電源復帰後チェック間隔を加えた日時Tbを算出し(ステップS13),TaとTbとを比較する(ステップS14)。   In step S11, if there is a power stop period, a date Tb obtained by adding a check interval after power recovery to the power recovery date in the connection notification schedule DB 31 is calculated (step S13), and Ta and Tb are compared (step S14). ).

ステップS14において,Taの方が早ければ,Taを接続通知予定日時として接続通知スケジュールDB31に設定する(ステップS12)。   In step S14, if Ta is earlier, Ta is set in the connection notification schedule DB 31 as the connection notification scheduled date and time (step S12).

ステップS14において,Tbの方が早ければ,Tbを接続通知予定日時として接続通知スケジュールDB31に設定する(ステップS15)。   In step S14, if Tb is earlier, Tb is set in the connection notification schedule DB 31 as the connection notification scheduled date and time (step S15).

図7は,本実施の形態における監視対象装置の動作をパターン別に整理したものである。監視対象装置30の主な動作を整理すると,以下の通りとなる。   FIG. 7 shows the operation of the monitoring target apparatus according to the present embodiment organized by pattern. The main operations of the monitoring target device 30 are summarized as follows.

(a)接続通知予定日時を経過
接続通知スケジュールDB31の接続通知予定日時を経過した場合には,“接続通知”を通報センター装置10に送信し,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB31の接続通知予定日時を更新する。
(A) Elapsed connection notification scheduled date and time When the connection notification scheduled date and time of the connection notification schedule DB 31 has elapsed, a “connection notification” is transmitted to the reporting center device 10 to newly create the next connection notification scheduled date and time. The connection notification scheduled date / time in the connection notification schedule DB 31 is updated.

(b)電源をON
監視対象装置30の電源をONした場合には,“電源ON通知”を通報センター装置10に送信する。また,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB31の接続通知予定日時を更新する。
(B) Turn on the power
When the monitoring target device 30 is powered on, a “power on notification” is transmitted to the reporting center device 10. In addition, the next scheduled connection notification date and time is newly created, and the connection notification scheduled date and time in the connection notification schedule DB 31 is updated.

(c)電源をOFF
監視対象装置30の電源をOFFする場合には,停止する直前に,“電源OFF通知”を通報センター装置10に送信する。
(C) Power off
When the power of the monitoring target device 30 is turned off, a “power off notification” is transmitted to the reporting center device 10 immediately before stopping.

(d)接続周期,電源停止期間,電源復帰後チェック間隔を設定・変更
接続通知スケジュールDB31の接続周期,電源停止期間,電源復帰後チェック間隔を設定・変更した場合には,それぞれ“接続周期設定通知”,“電源停止期間設定通知”,“電源復帰後チェック間隔設定通知”を通報センター装置10に送信する。また,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB31の接続通知予定日時を更新する。
(D) Setting / changing the connection cycle, power stop period, and check interval after power recovery When the connection cycle, power stop period, and check interval after power recovery in the connection notification schedule DB 31 are set / changed, "Notification", "Power supply stop period setting notification", and "Check interval setting notification after power return" are transmitted to the reporting center apparatus 10. In addition, the next scheduled connection notification date and time is newly created, and the connection notification scheduled date and time in the connection notification schedule DB 31 is updated.

図8は,本実施の形態における通報センター装置の構成例を示す図である。通報センター装置10は,通知受信部11,接続通知スケジュールDB12,接続通知スケジュール設定部13,障害検出部14,通報作成・送信部15から構成される。   FIG. 8 is a diagram illustrating a configuration example of a report center device in the present embodiment. The notification center device 10 includes a notification receiving unit 11, a connection notification schedule DB 12, a connection notification schedule setting unit 13, a failure detection unit 14, and a report creation / transmission unit 15.

通知受信部11は,監視対象装置30からの通知を受信する。接続通知スケジュールDB12には,通報センター装置10が監視対象装置30からの“接続通知”の受信を確認するためのスケジュール情報が記録される。接続通知スケジュール設定部13は,接続通知スケジュールDB12の設定・更新が必要な場合にその記録を設定・更新する。障害検出部14は,監視対象装置30からの“接続通知”の受信状況などをもとに,その装置の稼動状況を判定して稼動障害を検出し,監視対象装置30からの“通常の障害通知”などをもとに,その装置の異常状態の発生を検出する。通報作成・送信部15は,障害検出部14が監視対象装置30の稼動障害を検出すると,“稼動障害通報”を作成し,障害検出部14が監視対象装置30の異常状態の発生を検出すると,“障害通報”を作成し,作成された通報をコールセンターシステム20に送信する。   The notification receiving unit 11 receives a notification from the monitoring target device 30. In the connection notification schedule DB 12, schedule information for the notification center device 10 to confirm reception of “connection notification” from the monitoring target device 30 is recorded. The connection notification schedule setting unit 13 sets / updates the record when the connection notification schedule DB 12 needs to be set / updated. The failure detection unit 14 determines the operation status of the device based on the reception status of the “connection notification” from the monitoring target device 30 and the like, detects the operation failure, and detects “normal failure from the monitoring target device 30. The occurrence of an abnormal state of the device is detected based on the notification. When the failure detection unit 14 detects an operation failure of the monitoring target device 30, the notification creation / transmission unit 15 generates an “operation failure notification”, and when the failure detection unit 14 detects the occurrence of an abnormal state of the monitoring target device 30. , “Fault report” is created, and the created report is transmitted to the call center system 20.

図9は,本実施の形態における通報センター装置の接続通知スケジュールDBの構造の例を示す図である。接続通知スケジュールDB12には,装置ID,接続周期,電源停止期間(電源停止日時,電源復帰日時),電源復帰後チェック間隔,接続通知予定日時,通知未受信フラグ,直前通知名の情報が,監視対象装置30ごとに記録される。   FIG. 9 is a diagram showing an example of the structure of the connection notification schedule DB of the notification center device in the present embodiment. In the connection notification schedule DB 12, information on the device ID, connection cycle, power supply stop period (power supply stop date / time, power supply return date / time), check interval after power return, connection notification scheduled date / time, notification not received flag, and previous notification name are monitored. Recorded for each target device 30.

装置IDには,監視対象装置30を一意に認識するためのIDが記録される。通報センター装置10は,各通知に含まれる装置IDで,どの監視対象装置30から送られた通知であるかを特定する。   In the device ID, an ID for uniquely identifying the monitoring target device 30 is recorded. The reporting center device 10 identifies which monitoring target device 30 is the notification with the device ID included in each notification.

接続周期には,該当監視対象装置30が定期的に“接続通知”を送信する周期が記録される。これは,該当監視対象装置30の接続通知スケジュールDB31の接続周期と同じ情報である。通知受信部11が“接続周期設定通知”を受信すると,接続通知スケジュール設定部13は,接続通知スケジュールDB12の該当監視対象装置30の接続周期を設定・更新する。   In the connection cycle, a cycle in which the corresponding monitoring target device 30 periodically transmits a “connection notification” is recorded. This is the same information as the connection cycle of the connection notification schedule DB 31 of the corresponding monitoring target device 30. When the notification receiving unit 11 receives the “connection cycle setting notification”, the connection notification schedule setting unit 13 sets / updates the connection cycle of the corresponding monitoring target device 30 in the connection notification schedule DB 12.

電源停止期間には,監視対象装置30に長期電源停止の予定がある場合などに,その電源OFFの予定日時(電源停止日時)と電源ONの予定日時(電源復帰日時)とが記録される。これは,該当監視対象装置30の接続通知スケジュールDB31の電源停止期間(電源停止日時,電源復帰日時)と同じ情報である。通知受信部11が“電源停止期間設定通知”を受信すると,接続通知スケジュール設定部13は,接続通知スケジュールDB12の該当監視対象装置30の電源停止期間を設定・更新する。   In the power-off period, when the monitoring target device 30 has a long-term power-off schedule, the power-off scheduled date / time (power-off date / time) and the power-on scheduled date / time (power return date / time) are recorded. This is the same information as the power stop period (power stop date / time, power return date / time) of the connection notification schedule DB 31 of the corresponding monitoring target device 30. When the notification receiving unit 11 receives “power stop period setting notification”, the connection notification schedule setting unit 13 sets / updates the power stop period of the corresponding monitoring target device 30 in the connection notification schedule DB 12.

電源復帰後チェック間隔には,監視対象装置30における電源停止期間終了(電源復帰日時)から電源復帰後チェックのための“接続通知”の送信までの時間間隔が記録される。これは,該当監視対象装置30の接続通知スケジュールDB31の電源復帰後チェック間隔と同じ情報である。通知受信部11が“電源復帰後チェック間隔設定通知”を受信すると,接続通知スケジュール設定部13は,接続通知スケジュールDB12の該当監視対象装置30の電源復帰後チェック間隔を設定・更新する。   In the check interval after power recovery, the time interval from the end of the power stop period (power recovery date and time) in the monitoring target device 30 to the transmission of the “connection notification” for the check after power recovery is recorded. This is the same information as the check interval after power recovery in the connection notification schedule DB 31 of the corresponding monitoring target device 30. When the notification receiving unit 11 receives the “check interval setting notification after power recovery”, the connection notification schedule setting unit 13 sets / updates the check interval after power recovery of the corresponding monitoring target device 30 in the connection notification schedule DB 12.

接続通知予定日時には,次回の“接続通知”の受信を確認する予定日時が記録される。接続通知予定日時になると,障害検出部14は,該当監視対象装置30からの“接続通知”の有無を確認する。接続通知予定日時は,接続通知スケジュール設定部13により自動的に設定される。   In the scheduled connection notification date and time, a scheduled date and time for confirming reception of the next “connection notification” is recorded. When the scheduled connection notification date / time is reached, the failure detection unit 14 checks whether there is a “connection notification” from the relevant monitoring target device 30. The connection notification scheduled date and time is automatically set by the connection notification schedule setting unit 13.

ここで,通報センター装置10の接続通知スケジュールDB12の接続通知予定日時は,該当監視対象装置30の接続通知スケジュールDB31の接続通知予定日時にあらかじめ定められた猶予時間を加えたものとなる。これは,インターネットや電子メールなどの環境によって,監視対象装置30と通報センター装置10との間の通信に,ある程度の時間を要すると考えられるためである。猶予時間は,10分程度が理想的である。   Here, the connection notification scheduled date and time of the connection notification schedule DB 12 of the notification center device 10 is obtained by adding a predetermined grace time to the connection notification scheduled date and time of the connection notification schedule DB 31 of the corresponding monitoring target device 30. This is because it is considered that a certain amount of time is required for communication between the monitoring target device 30 and the notification center device 10 depending on the environment such as the Internet or electronic mail. The grace time is ideally about 10 minutes.

通知未受信フラグには,(1)接続通知スケジュールDB12の接続通知予定日時経過後であって,直前に“電源OFF通知”を受信しており,まだ未受信のフラグが立っていない場合,または,(2)接続通知スケジュールDB12の接続通知予定日時経過後であって,電源停止期間中である場合に,未受信のフラグが立てられる。また,何らかの通知を受信した場合に,未受信のフラグが取り消される。   The notification non-reception flag includes: (1) after the connection notification scheduled date / time of the connection notification schedule DB 12 has elapsed and the “power OFF notification” has been received immediately before, and the unreception flag has not yet been set, or (2) A non-received flag is set when the scheduled connection notification date / time of the connection notification schedule DB 12 has elapsed and the power supply is stopped. In addition, when any notification is received, the unreceived flag is canceled.

直前通知名には,該当監視対象装置30から直前に受信した通知の通知名が記録される。通知受信部11は,何らかの通知を受信すると,接続通知スケジュールDB12の該当監視対象装置30の直前通知名を,受信した通知の通知名で更新する。   In the immediately preceding notification name, the notification name of the notification received immediately before from the corresponding monitoring target device 30 is recorded. When receiving any notification, the notification receiving unit 11 updates the immediately preceding notification name of the relevant monitoring target device 30 in the connection notification schedule DB 12 with the notification name of the received notification.

図10は,本実施の形態における通報センター装置の接続通知予定日時設定処理フローチャートである。通報センター装置10は,(1)“接続通知”受信後,(2)“接続周期設定通知”受信後,(3)“電源停止期間設定通知”受信後,(4)“電源復帰後チェック間隔設定通知”受信後,(5)接続通知スケジュールDB12の接続通知予定日時経過後であって,直前に“電源OFF通知”を受信しており,まだ未受信のフラグが立っていない場合,(6)接続通知スケジュールDB12の接続通知予定日時経過後で,電源停止期間中である場合などに,接続通知スケジュール設定部13に対して接続通知予定日時変更命令を出す。   FIG. 10 is a connection notification scheduled date and time setting process flowchart of the notification center apparatus according to the present embodiment. The notification center device 10 (1) after receiving “connection notification”, (2) after receiving “connection cycle setting notification”, (3) after receiving “power supply stop period setting notification”, (4) “check interval after power recovery” After receiving the “setting notification”, (5) after the scheduled connection notification date / time of the connection notification schedule DB 12 has elapsed, the “power off notification” has been received immediately before, and the unreceived flag has not been set (6 ) A connection notification scheduled date / time change command is issued to the connection notification schedule setting unit 13 after the connection notification scheduled date / time in the connection notification schedule DB 12 elapses and during a power stop period.

接続通知スケジュール設定部13は,接続通知予定日時変更命令を受けると,まず,接続通知スケジュールDB12の接続周期から,該当監視対象装置30の次回の定期的な“接続通知”の送信予定日時Taを算出する(ステップS20)。   When receiving the connection notification scheduled date / time change command, the connection notification schedule setting unit 13 first determines the scheduled transmission date / time Ta of the next periodic “connection notification” of the monitoring target device 30 from the connection cycle of the connection notification schedule DB 12. Calculate (step S20).

接続通知スケジュールDB12の電源停止期間の設定があるかを確認し(ステップS21),電源停止期間の設定がなければ,Taに猶予時間tを加えた日時を接続通知予定日時として接続通知スケジュールDB12に設定する(ステップS22)。   It is confirmed whether or not the power supply stop period is set in the connection notification schedule DB 12 (step S21). Set (step S22).

ステップS21において,電源停止期間の設定があれば,接続通知スケジュールDB12の電源復帰日時に電源復帰後チェック間隔を加えた日時Tbを算出し(ステップS23),TaとTbとを比較する(ステップS24)。   In step S21, if a power stop period is set, a date Tb obtained by adding a check interval after power recovery to the power recovery date in the connection notification schedule DB 12 is calculated (step S23), and Ta and Tb are compared (step S24). ).

ステップS24において,Taの方が早ければ,Taに猶予時間tを加えた日時を接続通知予定日時として接続通知スケジュールDB12に設定する(ステップS22)。また,ステップS24において,Tbの方が早ければ,Tbに猶予時間tを加えた日時を接続通知予定日時として接続通知スケジュールDB12に設定する(ステップS25)。   In step S24, if Ta is earlier, the date and time when grace time t is added to Ta is set in the connection notification schedule DB 12 as the connection notification scheduled date and time (step S22). In step S24, if Tb is earlier, the date / time obtained by adding the grace time t to Tb is set in the connection notification schedule DB 12 as the connection notification scheduled date / time (step S25).

図11は,本実施の形態における稼動状況判定処理フローチャートである。図11の例は,障害検出部14が,監視対象装置30の稼動状況を判定する処理の例である。   FIG. 11 is a flowchart of the operation status determination process in the present embodiment. The example of FIG. 11 is an example of processing in which the failure detection unit 14 determines the operating status of the monitoring target device 30.

障害検出部14は,現在時刻が接続通知スケジュールDB12の接続通知予定日時を経過しているかを確認し(ステップS30),接続通知予定日時を経過している場合には,“接続通知”を受信しているかを確認する(ステップS31)。“接続通知”を受信している場合には,接続通知スケジュール設定部13に接続通知予定日時変更命令を出し(ステップS32),次の接続通知予定日時の経過を待つ。   The failure detection unit 14 checks whether the current time has passed the connection notification scheduled date / time of the connection notification schedule DB 12 (step S30), and receives the “connection notification” if the connection notification scheduled date / time has passed. It is confirmed whether it is (step S31). If “connection notification” is received, a connection notification scheduled date / time change command is issued to the connection notification schedule setting unit 13 (step S32), and the next connection notification scheduled date / time is awaited.

ステップS31において,まだ“接続通知”を受信していない場合には,接続通知スケジュールDB12の電源停止期間で現在電源停止期間中であるかを確認し(ステップS33),電源停止期間中であれば,接続通知スケジュールDB12の通知未受信フラグに未受信のフラグを立てる(ステップS34)。その後,接続通知スケジュール設定部13に接続通知予定日時変更命令を出し(ステップS32),次の接続通知予定日時の経過を待つ(ステップS30)。   In step S31, if the “connection notification” has not been received yet, it is confirmed whether the power supply is stopped during the power supply stop period in the connection notification schedule DB 12 (step S33). Then, a non-reception flag is set in the notification non-reception flag of the connection notification schedule DB 12 (step S34). Thereafter, a connection notification scheduled date / time change command is issued to the connection notification schedule setting unit 13 (step S32), and the next connection notification scheduled date / time is awaited (step S30).

ステップS33において,電源停止期間中でなければ,接続通知スケジュールDB12の直前通知名で直前の通知が“電源OFF通知”であったかを確認し(ステップS35),直前の通知が“電源OFF通知”でなければ,該当監視対象装置30に稼動障害が発生していると判定する(ステップS37)。   In step S33, if it is not during the power supply stop period, it is confirmed whether or not the previous notification is “power OFF notification” with the previous notification name in the connection notification schedule DB 12 (step S35). If not, it is determined that an operation failure has occurred in the relevant monitoring target device 30 (step S37).

ステップS35において,直前の通知が“電源OFF通知”であれば,すでに接続通知スケジュールDB12の通知未受信フラグに未受信のフラグが立っているかを確認し(ステップS36),すでに未受信のフラグが立っていれば,該当監視対象装置30に稼動障害が発生していると判定する(ステップS37)。   In step S35, if the immediately preceding notification is “power OFF notification”, it is confirmed whether an unreceived flag is set in the notification unreceived flag of the connection notification schedule DB 12 (step S36). If standing, it is determined that an operation failure has occurred in the monitoring target device 30 (step S37).

ステップS36において,まだ未受信のフラグが立っていなければ,接続通知スケジュールDB12の通知未受信フラグに未受信のフラグを立てる(ステップS34)。その後,接続通知スケジュール設定部13に接続通知予定日時変更命令を出し(ステップS32),次の接続通知予定日時の経過を待つ(ステップS30)。   In step S36, if an unreceived flag has not yet been set, an unreceived flag is set in the notification unreceived flag of the connection notification schedule DB 12 (step S34). Thereafter, a connection notification scheduled date / time change command is issued to the connection notification schedule setting unit 13 (step S32), and the next connection notification scheduled date / time is awaited (step S30).

図12は,本実施の形態における通報センター装置の動作をパターン別に整理したものである。通報センター装置10の主な動作を整理すると,以下の通りとなる。   FIG. 12 shows the operation of the notification center apparatus according to this embodiment organized by pattern. The main operations of the reporting center device 10 are summarized as follows.

(a)“接続通知”を受信
“接続通知”を受信した場合には,接続通知スケジュールDB12の該当監視対象装置30の通知未受信フラグに未受信のフラグが立っていればそれを取り消す。また,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB12の該当監視対象装置30の接続通知予定日時を更新し,直前通知名に通知名(この場合には,“接続通知”)を記録する。
(A) Receiving “connection notification” When “connection notification” is received, if a non-reception flag is set in the notification non-reception flag of the relevant monitoring target device 30 in the connection notification schedule DB 12, it is canceled. In addition, the next scheduled connection notification date and time is newly created, the connection notification scheduled date and time of the corresponding monitoring target device 30 in the connection notification schedule DB 12 is updated, and the notification name (in this case, “connection notification”) is updated as the previous notification name. Record.

(b)“電源ON通知”,“電源OFF通知”,“その他通知”(“通常の障害通知”など)を受信
“電源ON通知”,“電源OFF通知”,“その他通知”(“通常の障害通知”など)を受信した場合には,接続通知スケジュールDB12の該当監視対象装置30の通知未受信フラグに未受信のフラグが立っていればそれを取り消す。また,接続通知スケジュールDB12の該当監視対象装置30の直前通知名に通知名(この場合には,それぞれ“電源ON通知”,“電源OFF通知”,“その他通知”(“通常の障害通知”など))を記録する。
(B) Receive “Power ON Notification”, “Power OFF Notification”, “Other Notification” (“Normal Failure Notification”, etc.) “Power ON Notification”, “Power OFF Notification”, “Other Notification” (“Normal Notification”) In the case where a notification not received flag is set in the notification not received flag of the relevant monitoring target device 30 in the connection notification schedule DB 12, it is canceled. Also, the notification name (in this case, “power ON notification”, “power OFF notification”, “other notification” (“normal failure notification”, etc., respectively) )) Is recorded.

(c)“接続周期設定通知”,“電源停止期間設定通知”,“電源復帰後チェック間隔設定通知”を受信
“接続周期設定通知”,“電源停止期間設定通知”,“電源復帰後チェック間隔設定通知”を受信した場合には,接続通知スケジュールDB12の該当監視対象装置30の通知未受信フラグに未受信のフラグが立っていればそれを取り消す。また,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB12の該当監視対象装置30の接続通知予定日時を更新し,直前通知名に通知名(この場合には,それぞれ“接続周期設定通知”,“電源停止期間設定通知”,“電源復帰後チェック間隔設定通知”)を記録する。
(C) Receives “connection cycle setting notification”, “power shutdown period setting notification”, “check interval setting notification after power recovery” “connection cycle setting notification”, “power shutdown period setting notification”, “check interval after power recovery” When the “setting notification” is received, if an unreceived flag is set in the notification unreceived flag of the relevant monitoring target device 30 in the connection notification schedule DB 12, it is canceled. In addition, a new connection notification scheduled date and time is newly created, the connection notification scheduled date and time of the relevant monitoring target device 30 in the connection notification schedule DB 12 is updated, and the notification name (in this case, “connection cycle setting”) is updated as the previous notification name. "Notification", "Power supply stop period setting notification", "Check interval setting notification after power recovery") is recorded.

(d)接続通知予定日時を経過
接続通知スケジュールDB12の接続通知予定日時を経過した場合の通報センター装置10の動作は,以下の数パターンに分けられる。
(D) Elapsed connection notification scheduled date and time The operation of the notification center device 10 when the connection notification scheduled date and time of the connection notification schedule DB 12 has elapsed is divided into the following several patterns.

(1)電源停止期間である場合
該当監視対象装置30が電源停止期間中である場合には,接続通知スケジュールDB12の通知未受信フラグに未受信のフラグを立てる。また,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB12の該当監視対象装置30の接続通知予定日時を更新する。
(1) When it is in the power supply stop period When the corresponding monitoring target device 30 is in the power supply stop period, a non-reception flag is set in the notification non-reception flag of the connection notification schedule DB 12. In addition, the next scheduled connection notification date and time is newly created, and the connection notification scheduled date and time of the relevant monitoring target device 30 in the connection notification schedule DB 12 is updated.

(2)電源停止期間ではなく,直前の通知が“電源OFF通知”ではない場合
該当監視対象装置30が電源停止期間中ではなく,接続通知スケジュールDB12の該当監視対象装置30の直前通知名が“電源OFF通知”でない場合には,“稼動障害通報”を作成し,コールセンターシステム20に送信する。
(2) When the notification immediately before is not the “power-off notification” but not the power-off period The relevant monitoring target device 30 is not in the power-off period, and the previous notice name of the relevant monitoring target device 30 in the connection notification schedule DB 12 is “ If it is not “power OFF notification”, an “operation failure notification” is created and transmitted to the call center system 20.

(3)電源停止期間ではなく,直前の通知が“電源OFF通知”であり,未受信のフラグが立っている場合
該当監視対象装置30が電源停止期間中ではなく,接続通知スケジュールDB12の該当監視対象装置30の直前通知名が“電源OFF通知”であり,通知未受信フラグに未受信のフラグが立っている場合には,“稼動障害通報”を作成し,コールセンターシステム20に送信する。
(3) When the previous notification is “power OFF notification” and the unreceived flag is set, not the power stop period, and the corresponding monitoring target device 30 is not in the power stop period and the corresponding monitoring in the connection notification schedule DB 12 If the immediately preceding notification name of the target device 30 is “power OFF notification” and an unreceived flag is set in the notification unreceived flag, an “operation failure notification” is created and transmitted to the call center system 20.

(4)電源停止期間ではなく,直前の通知が“電源OFF通知”であり,未受信のフラグが立っていない場合
該当監視対象装置30が電源停止期間中ではなく,接続通知スケジュールDB12の該当監視対象装置30の直前通知名が“電源OFF通知”であり,通知未受信フラグに未受信のフラグが立っていない場合には,接続通知スケジュールDB12の通知未受信フラグに未受信のフラグを立て,新たに次の接続通知予定日時を作成し,接続通知スケジュールDB12の該当監視対象装置30の接続通知予定日時を更新する。
(4) When the previous notification is “power OFF notification” and the unreceived flag is not set, not the power stop period, and the corresponding monitoring target device 30 is not in the power stop period and the corresponding monitoring in the connection notification schedule DB 12 If the immediately preceding notification name of the target device 30 is “Power OFF notification” and the unreceived flag is not set in the notification unreceived flag, an unreceived flag is set in the notification not-received flag of the connection notification schedule DB 12; A new connection notification scheduled date and time is newly created, and the connection notification scheduled date and time of the monitoring target device 30 in the connection notification schedule DB 12 is updated.

図13は,本実施の形態における接続通知予定日時の変遷の例を示す図である。図13を用いて,監視対象装置30の接続通知スケジュールDB31の接続通知予定日時(図13では,接続通知予定日時(監視対象装置)と記載)の変遷と,通報センター装置10の接続通知スケジュールDB12の該当監視対象装置30の接続通知予定日時(図13では,接続通知予定日時(通報センター装置)と記載)の変遷とを説明する。   FIG. 13 is a diagram illustrating an example of the transition of the connection notification scheduled date and time in the present embodiment. Using FIG. 13, the transition of the connection notification scheduled date and time in the connection notification schedule DB 31 of the monitoring target device 30 (described as the connection notification scheduled date and time (monitoring target device) in FIG. 13), and the connection notification schedule DB 12 of the notification center device 10. The transition of the connection notification scheduled date and time (described in FIG. 13 as the connection notification scheduled date and time (report center device)) in FIG.

なお,接続通知スケジュールDB31,接続通知スケジュールDB12では,接続周期は毎日10時11分に,電源停止日時は2004年4月9日17時に,電源復帰日時は2004年4月13日8時に,電源復帰後チェック間隔は15分に,猶予時間は10分に設定されているものとする。実際に監視対象装置30の電源がOFFされた日時は2004年4月9日16時30分であり,電源がONされた日時は2004年4月13日7時30分であるものとする。   In the connection notification schedule DB 31 and the connection notification schedule DB 12, the connection cycle is 10:11 every day, the power supply stop date is April 9, 17:00, the power recovery date is April 13, 2004, 8:00. It is assumed that the check interval after return is set to 15 minutes and the grace time is set to 10 minutes. It is assumed that the date and time when the power of the monitoring target device 30 is actually turned off is 16:30 on April 9, 2004, and the date and time when the power is turned on is 7:30 on April 13, 2004.

(a)監視対象装置30は,接続通知予定日時(監視対象装置)として設定されている2004年4月8日10時11分に“接続通知”を送信し,接続周期が毎日10時11分であるので,次の接続通知予定日時(監視対象装置)として2004年4月9日10時11分(b)を設定する。   (A) The monitoring target device 30 transmits “connection notification” at 10:11 on April 8, 2004, which is set as the connection notification scheduled date and time (monitoring target device), and the connection cycle is 10:11 every day. Therefore, 10:11 (b) on April 9, 2004 is set as the next connection notification scheduled date and time (monitoring target device).

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月8日10時21分に“接続通知”の受信を確認し,接続周期が毎日10時11分であり,猶予時間が10分であるので,次の接続通知予定日時(通報センター装置)として2004年4月9日10時21分(b)を設定する。   The notification center device 10 confirms the reception of the “connection notification” at 10:21 on April 8, 2004, which is set as the connection notification scheduled date and time (report center device), and the connection cycle is 10:11 every day. Yes, since the grace time is 10 minutes, 10:21 (b) on April 9, 2004 is set as the next connection notification scheduled date and time (report center device).

(b)監視対象装置30は,接続通知予定日時(監視対象装置)として設定されている2004年4月9日10時11分に“接続通知”を送信し,次の接続通知予定日時(監視対象装置)として2004年4月10日10時11分(c)を設定する。   (B) The monitoring target device 30 transmits a “connection notification” at 10:11 on April 9, 2004 set as the connection notification scheduled date and time (monitoring target device), and the next connection notification scheduled date and time (monitoring) As the target device, 10:11 (c) on April 10, 2004 is set.

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月9日10時21分に“接続通知”の受信を確認し,次の接続通知予定日時(通報センター装置)として2004年4月10日10時21分(c)を設定する。   The notification center device 10 confirms the reception of the “connection notification” at 10:21 on April 9, 2004 set as the connection notification scheduled date and time (report center device), and the next connection notification scheduled date and time (report center) Device) is set to 10:21 (c) on April 10, 2004.

その後,2004年4月9日16時30分に,監視対象装置30の電源がOFFされる。   Thereafter, the power of the monitoring target device 30 is turned off at 16:30 on April 9, 2004.

(c)監視対象装置30は,接続通知予定日時(監視対象装置)として設定されている2004年4月10日10時11分にはすでに電源がOFFされた状態である。   (C) The monitoring target device 30 has already been turned off at 10:11 on April 10, 2004, which is set as the scheduled connection notification date (monitoring target device).

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月10日10時21分に“接続通知”の受信が確認できなかったが,電源停止期間中(電源停止日時2004年4月9日17時〜電源復帰日時2004年4月13日8時)であるので,次の接続通知予定日時(通報センター装置)として2004年4月11日10時21分(d)を設定する。   The notification center device 10 could not confirm the reception of the “connection notification” at 10:21 on April 10, 2004, which is set as the scheduled connection notification date (report center device). Since the stop date and time is April 9, 2004, 17:00 to the power supply return date and time, April 13, 2004, 8:00, the next connection notification scheduled date and time (report center device) is April 11, 2004, 10:21 ( d) is set.

(d)監視対象装置30は,電源がOFFされた状態である。   (D) The monitoring target device 30 is in a state where the power is turned off.

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月11日10時21分に“接続通知”の受信が確認できなかったが,電源停止期間中であるので,次の接続通知予定日時(通報センター装置)として2004年4月12日10時21分(e)を設定する。   The notification center device 10 was not able to confirm the reception of “connection notification” at 10:21 on April 11, 2004, which is set as the connection notification scheduled date and time (report center device), but is in a power-off period. Therefore, 10:21 (e) on April 12, 2004 is set as the next connection notification scheduled date and time (report center device).

(e)監視対象装置30は,電源がOFFされた状態である。   (E) The monitoring target device 30 is in a state where the power is turned off.

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月12日10時21分に“接続通知”の受信が確認できなかったが,電源停止期間中であるので,次の接続通知予定日時(通報センター装置)を設定する。このとき,接続周期と猶予時間とから求められる日時は2004年4月13日10時21分であり,電源復帰日時と電源復帰後チェック間隔(15分)と猶予時間とから求められる日時は2004年4月13日8時25分であるので,次の接続通知予定日時(通報センター装置)として時間の早い2004年4月13日8時25分(f)を設定する。   The notification center device 10 was not able to confirm the reception of the “connection notification” at 10:21 on April 12, 2004, which is set as the connection notification scheduled date and time (report center device), but is in a power-off period. Therefore, the next connection notification scheduled date and time (report center device) is set. At this time, the date and time obtained from the connection cycle and the grace time is 10:21 on April 13, 2004, and the date and time obtained from the power recovery date and time, the check interval after power restoration (15 minutes), and the grace time is 2004. Since it is 8:25 on April 13, 2012, 8:25 (f), April 13, 2004, which is earlier in time, is set as the next connection notification scheduled date and time (report center device).

その後,2004年4月13日7時30分に,監視対象装置30の電源がONされ,監視対象装置30は,次の接続通知予定日時(監視対象装置)を設定する。このとき,接続周期から求められる日時は2004年4月13日10時11分であり,電源復帰日時と電源復帰後チェック間隔とから求められる日時は2004年4月13日8時15分であるので,次の接続通知予定日時(監視対象装置)として時間の早い2004年4月13日8時15分(f)を設定する。   Thereafter, at 7:30 on April 13, 2004, the power of the monitoring target device 30 is turned on, and the monitoring target device 30 sets the next connection notification scheduled date and time (monitoring target device). At this time, the date and time obtained from the connection cycle is 10:11 on April 13, 2004, and the date and time obtained from the power return date and time and the check interval after power restoration is April 15th, 2004 and 8:15. Therefore, 8:15 (f), April 13, 2004, which is earlier in time, is set as the next connection notification scheduled date and time (monitoring target device).

(f)監視対象装置30は,接続通知予定日時(監視対象装置)として設定されている2004年4月13日8時15分に“接続通知”を送信し,接続周期が毎日10時11分であるので,次の接続通知予定日時(監視対象装置)として2004年4月13日10時11分(g)を設定する。   (F) The monitoring target device 30 transmits “connection notification” at 8:15 on April 13, 2004 set as the scheduled connection notification date (monitoring target device), and the connection cycle is 10:11 every day. Therefore, 10:11 (g) on April 13, 2004 is set as the next connection notification scheduled date and time (monitoring target device).

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月13日8時25分に“接続通知”の受信を確認し,接続周期が毎日10時11分であり,猶予時間が10分であるので,次の接続通知予定日時(通報センター装置)として2004年4月13日10時21分(g)を設定する。   The notification center device 10 confirms the reception of “connection notification” at 8:25 on April 13, 2004, which is set as the scheduled connection notification date and time (report center device), and the connection cycle is 10:11 every day. Yes, since the grace time is 10 minutes, 10:21 (g) on April 13, 2004 is set as the next connection notification scheduled date and time (report center device).

(g)監視対象装置30は,接続通知予定日時(監視対象装置)として設定されている2004年4月13日10時11分に“接続通知”を送信し,次の接続通知予定日時(監視対象装置)として2004年4月14日10時11分(h)を設定する。   (G) The monitoring target device 30 transmits “connection notification” at 10:11 on April 13, 2004, which is set as the connection notification scheduled date and time (monitoring target device), and the next connection notification scheduled date and time (monitoring) As the target device), 10:11 (h) on April 14, 2004 is set.

通報センター装置10は,接続通知予定日時(通報センター装置)として設定されている2004年4月13日10時21分に“接続通知”の受信を確認し,次の接続通知予定日時(通報センター装置)として2004年4月14日10時21分(h)を設定する。   The notification center device 10 confirms the reception of the “connection notification” at 10:21 on April 13, 2004 set as the connection notification scheduled date and time (report center device), and the next connection notification scheduled date and time (report center) Device) is set to 10:21 (h) on April 14, 2004.

図14は,本実施の形態における稼動状況監視システム全体の動作パターンの例を説明する図である。以下,図14を用いて,稼動状況監視システム全体の主な動作パターンの例を説明する。ここで,監視対象装置30側の接続通知予定日時と通報センター装置10側の接続通知予定日時との間には,本来は猶予時間の分だけずれがあるが,図14ではそのずれを省略している。   FIG. 14 is a diagram for explaining an example of the operation pattern of the entire operation status monitoring system in the present embodiment. Hereinafter, examples of main operation patterns of the entire operation status monitoring system will be described with reference to FIG. Here, there is originally a difference between the connection notification scheduled date and time on the monitoring target apparatus 30 side and the connection notification scheduled date and time on the notification center apparatus 10 side, but the deviation is omitted in FIG. ing.

図14(A)は,監視対象装置30が正常に稼動している場合の例である。接続通知予定日時を経過するごとに,監視対象装置30が“接続通知”を送信し,通報センター装置10がその“接続通知”を確認する。   FIG. 14A shows an example when the monitoring target device 30 is operating normally. Each time the scheduled connection notification date and time elapses, the monitoring target device 30 transmits a “connection notification”, and the notification center device 10 confirms the “connection notification”.

図14(B)は,電源をONした後に,監視対象装置30に稼動障害が発生した場合の例である。監視対象装置30からの“電源ON通知”を受けて,通報センター装置10は,監視対象装置30の監視を開始する。ところが,電源ON後の最初の接続通知予定日時に監視対象装置30からの“接続通知”がなかったため,通報センター装置10は“稼動障害通報”を作成し,それをコールセンターシステム20に送信する。   FIG. 14B shows an example when an operation failure occurs in the monitoring target device 30 after the power is turned on. Upon receiving the “power ON notification” from the monitoring target device 30, the reporting center device 10 starts monitoring the monitoring target device 30. However, since there is no “connection notification” from the monitoring target device 30 at the first connection notification scheduled date and time after the power is turned on, the notification center device 10 creates an “operation failure notification” and transmits it to the call center system 20.

図14(C)は,電源をOFFした後に,監視対象装置30に稼動障害が発生した場合の例である。監視対象装置30からの“電源OFF通知”を受けて,通報センター装置10は,監視対象装置30の監視を解除する。その後,最初の接続通知予定日時に監視対象装置30からの“接続通知”がなかったので,通報センター装置10は監視対象装置30の監視を開始する。ここでは,まだ“稼動障害通報”を作成しない。しかし,次の接続通知予定日時にも監視対象装置30からの“接続通知”がなかったので,通報センター装置10は“稼動障害通報”を作成し,それをコールセンターシステム20に送信する。   FIG. 14C shows an example when an operation failure occurs in the monitoring target device 30 after the power is turned off. Upon receiving the “power OFF notification” from the monitoring target device 30, the reporting center device 10 cancels monitoring of the monitoring target device 30. Thereafter, since there is no “connection notification” from the monitoring target device 30 at the first connection notification scheduled date and time, the reporting center device 10 starts monitoring the monitoring target device 30. Here, the “operation failure notification” is not yet created. However, since there is no “connection notification” from the monitoring target device 30 at the next connection notification scheduled date and time, the notification center device 10 creates an “operation failure notification” and transmits it to the call center system 20.

図14(D)は,“その他通知”を送信した後に,監視対象装置30に稼動障害が発生した場合の例である。監視対象装置30からの“その他通知”を受けて,通報センター装置10は,監視対象装置30の監視を開始する。ところが,“その他通知”受信後の最初の接続通知予定日時に監視対象装置30からの“接続通知”がなかったため,通報センター装置10は“稼動障害通報”を作成し,それをコールセンターシステム20に送信する。   FIG. 14D shows an example in the case where an operation failure occurs in the monitoring target device 30 after transmitting “other notification”. In response to “other notification” from the monitoring target device 30, the reporting center device 10 starts monitoring the monitoring target device 30. However, since there is no “connection notification” from the monitoring target device 30 at the first connection notification scheduled date and time after receiving “other notification”, the notification center device 10 creates an “operation failure notification” and sends it to the call center system 20. Send.

図14(E)は,あらかじめ設定された電源停止期間中に,監視対象装置30に稼動障害が発生した場合の例である。通報センター装置10は,あらかじめ設定された電源停止日時に監視対象装置30の監視を解除する。その後,最初の接続通知予定日時とその次の接続通知予定日時は電源停止期間中であるので,監視対象装置30から“接続通知”がなくても“稼動障害通報”を作成しない。通報センター装置10は,あらかじめ設定された電源復帰日時に監視対象装置30の監視を開始する。その後,接続通知予定日時(電源復帰後チェック)に監視対象装置30からの“接続通知”がなかったため,通報センター装置10は“稼動障害通報”を作成し,それをコールセンターシステム20に送信する。   FIG. 14E shows an example in the case where an operation failure occurs in the monitoring target device 30 during a preset power supply stop period. The reporting center device 10 cancels the monitoring of the monitoring target device 30 at the power stop date and time set in advance. Thereafter, since the first connection notification scheduled date and time and the next connection notification scheduled date and time are during the power supply stop period, even if there is no “connection notification” from the monitoring target device 30, “operation failure notification” is not created. The reporting center device 10 starts monitoring the monitoring target device 30 at the power recovery date and time set in advance. Thereafter, since there is no “connection notification” from the monitoring target device 30 at the scheduled connection notification date and time (check after power recovery), the notification center device 10 creates an “operation failure notification” and transmits it to the call center system 20.

以上,本発明の実施の形態の特徴を列挙すると,以下の通りである。   The features of the embodiment of the present invention are listed as follows.

(付記1)
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置であって,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,
前記接続通知の受信確認を行うためのスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段とを備え,
前記監視対象装置の稼動状況を監視する手段は,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段と,
前記監視対象装置が電源を停止することを示す通知である電源OFF通知を受信した場合に,前記監視対象装置に対する監視を解除し,その後あらかじめ定められた条件が満たされたときに,自動的に前記監視対象装置に対する監視を再開する手段とを備える
ことを特徴とする稼動状況監視装置。
(Appendix 1)
An operational status monitoring device in an operational status monitoring system for monitoring the operational status of a monitored device,
Means for recording a schedule for confirming reception of a connection notification, which is a notification indicating that the monitored device is operating;
Means for monitoring the operating status of the monitored device by confirming reception of the connection notification from the monitored device according to a schedule for confirming reception of the connection notification,
The means for monitoring the operating status of the monitored device is:
Means for determining that an operational failure has occurred in the monitored device when reception of the connection notification from the monitored device has not been confirmed;
When a power-off notification, which is a notification indicating that the monitored device is to be powered off, is received, the monitoring of the monitored device is canceled, and then automatically when a predetermined condition is satisfied An operation status monitoring device comprising: means for resuming monitoring of the monitoring target device.

(付記2)
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置であって,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,
前記接続通知の受信確認を行うためのスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段とを備え,
前記監視対象装置の稼動状況を監視する手段は,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段と,
前記監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,前記電源停止期間設定通知が示す前記監視対象装置が電源を停止する予定日時に前記監視対象装置に対する監視を解除し,前記電源停止期間設定通知が示す前記監視対象装置が電源を復帰する予定日時に前記監視対象装置に対する監視を再開する手段とを備える
ことを特徴とする稼動状況監視装置。
(Appendix 2)
An operational status monitoring device in an operational status monitoring system for monitoring the operational status of a monitored device,
Means for recording a schedule for confirming reception of a connection notification, which is a notification indicating that the monitored device is operating;
Means for monitoring the operating status of the monitored device by confirming reception of the connection notification from the monitored device according to a schedule for confirming reception of the connection notification,
The means for monitoring the operating status of the monitored device is:
Means for determining that an operational failure has occurred in the monitored device when reception of the connection notification from the monitored device has not been confirmed;
When receiving a power supply stop period setting notification, which is a notification indicating a period during which the monitored device stops power, the monitored device at the scheduled date and time when the monitored device indicated by the power supply stop period setting notification stops power supply An operation status monitoring device comprising: means for canceling the monitoring of the monitoring target device, and restarting the monitoring of the monitoring target device at a scheduled date and time when the monitoring target device indicated by the notification of setting of the power stop period returns power.

(付記3)
付記1または付記2に記載の稼動状況監視装置において,
前記監視対象装置からの前記監視対象装置が前記接続通知を送信するためのスケジュールを設定・更新する情報の通知をもとに,前記接続通知の受信確認を行うためのスケジュールを設定・更新する手段を備える
ことを特徴とする稼動状況監視装置。
(Appendix 3)
In the operation status monitoring device described in appendix 1 or appendix 2,
Means for setting / updating a schedule for confirming reception of the connection notification based on notification of information for setting / updating a schedule for the monitoring target device to transmit the connection notification from the monitoring target device An operation status monitoring device comprising:

(付記4)
稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムにおける監視対象装置であって,
自身が稼動していることを示す通知である接続通知を前記稼動状況監視装置に送信するためのスケジュールを記録する手段と,
前記接続通知を送信するためのスケジュールに従って,前記稼動状況監視装置に前記接続通知を送信する手段と,
自身の電源を停止する期間の予定日時が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を前記稼動状況監視装置に送信する手段とを備える
ことを特徴とする監視対象装置。
(Appendix 4)
A monitoring target device in an operating status monitoring system in which the operating status monitoring device monitors the operating status of the monitoring target device;
Means for recording a schedule for transmitting a connection notification, which is a notification indicating that the device is operating, to the operation status monitoring device;
Means for transmitting the connection notification to the operating status monitoring device according to a schedule for transmitting the connection notification;
And a means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device when a scheduled date and time of the power supply stop period is set. Target device.

(付記5)
稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムであって,
前記監視対象装置は,
自身が稼動していることを示す通知である接続通知を前記稼動状況監視装置に送信するためのスケジュールを記録する手段と,
前記接続通知を送信するためのスケジュールに従って,前記稼動状況監視装置に前記接続通知を送信する手段と,
自身の電源を停止する予定期間が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を前記稼動状況監視装置に送信する手段を備え,
前記稼動状況監視装置は,
前記接続通知の受信確認を行うためのスケジュールを記録する手段と,
前記接続通知の受信確認を行うためのスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段とを備え,
前記監視対象装置の稼動状況を監視する手段は,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段と,
前記監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,前記電源停止期間設定通知が示す前記監視対象装置が電源を停止する予定日時に前記監視対象装置に対する監視を解除し,前記電源停止期間設定通知が示す前記監視対象装置が電源を復帰する予定日時に前記監視対象装置に対する監視を再開する手段とを備える
ことを特徴とする稼動状況監視システム。
(Appendix 5)
An operational status monitoring system in which an operational status monitoring device monitors the operational status of a monitored device,
The monitored device is:
Means for recording a schedule for transmitting a connection notification, which is a notification indicating that the device is operating, to the operation status monitoring device;
Means for transmitting the connection notification to the operating status monitoring device according to a schedule for transmitting the connection notification;
A means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device when a scheduled period for stopping its own power supply is set;
The operating status monitoring device is:
Means for recording a schedule for confirming reception of the connection notification;
Means for monitoring the operating status of the monitored device by confirming reception of the connection notification from the monitored device according to a schedule for confirming reception of the connection notification,
The means for monitoring the operating status of the monitored device is:
Means for determining that an operational failure has occurred in the monitored device when reception of the connection notification from the monitored device has not been confirmed;
When receiving a power supply stop period setting notification, which is a notification indicating a period during which the monitored device stops power, the monitored device at the scheduled date and time when the monitored device indicated by the power supply stop period setting notification stops power supply An operation status monitoring system comprising: means for canceling the monitoring of the monitoring target device and resuming monitoring of the monitoring target device at a scheduled date and time when the monitoring target device indicated by the notification of setting of the power stop period returns power.

(付記6)
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置のコンピュータに実行させるためのプログラムであって,
前記コンピュータを,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うための予め設定されたスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段,
前記監視対象装置が電源を停止することを示す通知である電源OFF通知を受信した場合に,前記監視対象装置に対する監視を解除し,その後あらかじめ定められた条件が満たされたときに,自動的に前記監視対象装置に対する監視を再開する手段,
として機能させるための稼動状況監視装置用プログラム。
(Appendix 6)
A program for causing a computer of an operating status monitoring device in an operating status monitoring system to monitor the operating status of a monitored device,
Said computer,
The monitoring is performed by confirming reception of the connection notification from the monitoring target device according to a preset schedule for confirming reception of the connection notification, which is a notification indicating that the monitoring target device is operating. Means for monitoring the operating status of the target device,
Means for determining that an operational failure has occurred in the monitored device when the reception of the connection notification from the monitored device cannot be confirmed;
When a power-off notification, which is a notification indicating that the monitored device is to be powered off, is received, the monitoring of the monitored device is canceled, and then automatically when a predetermined condition is satisfied Means for resuming monitoring of the monitored device;
Program for operating status monitoring device to function as

(付記7)
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置のコンピュータに実行させるためのプログラムであって,
前記コンピュータを,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うための予め設定されたスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段,
前記監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,前記電源停止期間設定通知が示す前記監視対象装置が電源を停止する予定日時に前記監視対象装置に対する監視を解除し,前記電源停止期間設定通知が示す前記監視対象装置が電源を復帰する予定日時に前記監視対象装置に対する監視を再開する手段,
として機能させるための稼動状況監視装置用プログラム。
(Appendix 7)
A program for causing a computer of an operating status monitoring device in an operating status monitoring system to monitor the operating status of a monitored device,
Said computer,
The monitoring is performed by confirming reception of the connection notification from the monitoring target device according to a preset schedule for confirming reception of the connection notification, which is a notification indicating that the monitoring target device is operating. Means for monitoring the operating status of the target device,
Means for determining that an operational failure has occurred in the monitored device when the reception of the connection notification from the monitored device cannot be confirmed;
When receiving a power supply stop period setting notification, which is a notification indicating a period during which the monitored device stops power, the monitored device at the scheduled date and time when the monitored device indicated by the power supply stop period setting notification stops power supply Means for canceling the monitoring of the monitoring target device and restarting the monitoring of the monitoring target device at the scheduled date and time when the monitoring target device indicated by the notification of setting of the power stop period is restored.
Program for operating status monitoring device to function as

(付記8)
稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムにおける監視対象装置のコンピュータに実行させるためのプログラムであって,
前記コンピュータを,
自身が稼動していることを示す通知である接続通知を前記稼動状況監視装置に送信するための予め設定されたスケジュールに従って,前記稼動状況監視装置に前記接続通知を送信する手段,
自身の電源を停止する期間の予定日時が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を前記稼動状況監視装置に送信する手段,
として機能させるための監視対象装置用プログラム。
(Appendix 8)
A program for causing a computer of a monitored device in an operating status monitoring system to monitor the operating status of a monitored device by an operating status monitoring device,
Said computer,
Means for transmitting the connection notification to the operation status monitoring device according to a preset schedule for transmitting a connection notification, which is a notification indicating that the device is operating, to the operation status monitoring device;
Means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device when a scheduled date and time of the power supply stop period is set;
Program for monitoring target devices to function as

本発明の実施の形態における稼動状況監視システムの構成例を示す図である。It is a figure which shows the structural example of the operating condition monitoring system in embodiment of this invention. 本実施の形態における監視対象装置から通報センター装置への通知の例を示す図である。It is a figure which shows the example of the notification from the monitoring object apparatus in this Embodiment to a report center apparatus. 本実施の形態における通報センター装置からコールセンターシステムへの通報の例を示す図である。It is a figure which shows the example of the report from the report center apparatus in this Embodiment to a call center system. 本実施の形態における監視対象装置の構成例を示す図である。It is a figure which shows the structural example of the monitoring object apparatus in this Embodiment. 本実施の形態における監視対象装置の接続通知スケジュールDBの構造の例を示す図である。It is a figure which shows the example of the structure of the connection notification schedule DB of the monitoring object apparatus in this Embodiment. 本実施の形態における監視対象装置の接続通知予定日時設定処理フローチャートである。6 is a connection notification scheduled date and time setting process flowchart of the monitoring target device according to the present embodiment. 本実施の形態における監視対象装置の動作をパターン別に整理したものである。The operation of the monitoring target device in this embodiment is organized by pattern. 本実施の形態における通報センター装置の構成例を示す図である。It is a figure which shows the structural example of the notification center apparatus in this Embodiment. 本実施の形態における通報センター装置の接続通知スケジュールDBの構造の例を示す図である。It is a figure which shows the example of the structure of connection notification schedule DB of the notification center apparatus in this Embodiment. 本実施の形態における通報センター装置の接続通知予定日時設定処理フローチャートである。It is a connection notification scheduled date setting process flowchart of the notification center apparatus in this Embodiment. 本実施の形態における稼動状況判定処理フローチャートである。It is an operation condition determination processing flowchart in the present embodiment. 本実施の形態における通報センター装置の動作をパターン別に整理したものである。The operation of the reporting center device in the present embodiment is organized by pattern. 本実施の形態における接続通知予定日時の変遷の例を示す図である。It is a figure which shows the example of transition of the connection notification scheduled date in this Embodiment. 本実施の形態における稼動状況監視システム全体の動作パターンの例を説明する図である。It is a figure explaining the example of the operation pattern of the whole operation condition monitoring system in this Embodiment.

符号の説明Explanation of symbols

10 通報センター装置
11 通知受信部
12 接続通知スケジュールDB
13 接続通知スケジュール設定部
14 障害検出部
15 通報作成・送信部
20 コールセンターシステム
30 監視対象装置
31 接続通知スケジュールDB
32 接続通知スケジュール設定部
33 通知作成・送信部
40 ネットワーク
10 Report Center Device 11 Notification Receiver 12 Connection Notification Schedule DB
13 Connection Notification Schedule Setting Unit 14 Failure Detection Unit 15 Report Creation / Transmission Unit 20 Call Center System 30 Monitored Device 31 Connection Notification Schedule DB
32 Connection Notification Schedule Setting Unit 33 Notification Creation / Transmission Unit 40 Network

Claims (5)

監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置であって,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,
前記接続通知の受信確認を行うためのスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段とを備え,
前記監視対象装置の稼動状況を監視する手段は,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段と,
前記監視対象装置が電源を停止することを示す通知である電源OFF通知を受信した場合に,前記監視対象装置に対する監視を解除し,その後あらかじめ定められた条件が満たされたときに,自動的に前記監視対象装置に対する監視を再開する手段とを備える
ことを特徴とする稼動状況監視装置。
An operational status monitoring device in an operational status monitoring system for monitoring the operational status of a monitored device,
Means for recording a schedule for confirming reception of a connection notification, which is a notification indicating that the monitored device is operating;
Means for monitoring the operating status of the monitored device by confirming reception of the connection notification from the monitored device according to a schedule for confirming reception of the connection notification,
The means for monitoring the operating status of the monitored device is:
Means for determining that an operational failure has occurred in the monitored device when reception of the connection notification from the monitored device has not been confirmed;
When a power-off notification, which is a notification indicating that the monitored device is to be powered off, is received, the monitoring of the monitored device is canceled, and then automatically when a predetermined condition is satisfied An operation status monitoring device comprising: means for resuming monitoring of the monitoring target device.
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置であって,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うためのスケジュールを記録する手段と,
前記接続通知の受信確認を行うためのスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段とを備え,
前記監視対象装置の稼動状況を監視する手段は,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段と,
前記監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,前記電源停止期間設定通知が示す前記監視対象装置が電源を停止する予定日時に前記監視対象装置に対する監視を解除し,前記電源停止期間設定通知が示す前記監視対象装置が電源を復帰する予定日時に前記監視対象装置に対する監視を再開する手段とを備える
ことを特徴とする稼動状況監視装置。
An operational status monitoring device in an operational status monitoring system for monitoring the operational status of a monitored device,
Means for recording a schedule for confirming reception of a connection notification, which is a notification indicating that the monitored device is operating;
Means for monitoring the operating status of the monitored device by confirming reception of the connection notification from the monitored device according to a schedule for confirming reception of the connection notification,
The means for monitoring the operating status of the monitored device is:
Means for determining that an operational failure has occurred in the monitored device when reception of the connection notification from the monitored device has not been confirmed;
When receiving a power supply stop period setting notification, which is a notification indicating a period during which the monitored device stops power, the monitored device at the scheduled date and time when the monitored device indicated by the power supply stop period setting notification stops power supply An operation status monitoring device comprising: means for canceling the monitoring of the monitoring target device, and restarting the monitoring of the monitoring target device at a scheduled date and time when the monitoring target device indicated by the notification of setting of the power stop period returns power.
稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムにおける監視対象装置であって,
自身が稼動していることを示す通知である接続通知を前記稼動状況監視装置に送信するためのスケジュールを記録する手段と,
前記接続通知を送信するためのスケジュールに従って,前記稼動状況監視装置に前記接続通知を送信する手段と,
自身の電源を停止する期間の予定日時が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を前記稼動状況監視装置に送信する手段とを備える
ことを特徴とする監視対象装置。
A monitoring target device in an operating status monitoring system in which the operating status monitoring device monitors the operating status of the monitoring target device;
Means for recording a schedule for transmitting a connection notification, which is a notification indicating that the device is operating, to the operation status monitoring device;
Means for transmitting the connection notification to the operating status monitoring device according to a schedule for transmitting the connection notification;
And a means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device when a scheduled date and time of the power supply stop period is set. Target device.
監視対象装置の稼動状況を監視する稼動状況監視システムにおける稼動状況監視装置のコンピュータに実行させるためのプログラムであって,
前記コンピュータを,
前記監視対象装置が稼動していることを示す通知である接続通知の受信確認を行うための予め設定されたスケジュールに従って,前記監視対象装置からの前記接続通知の受信を確認することにより,前記監視対象装置の稼動状況を監視する手段,
前記監視対象装置からの前記接続通知の受信が確認できなかった場合に,前記監視対象装置に稼動障害が発生していると判断する手段,
前記監視対象装置が電源を停止する期間を示す通知である電源停止期間設定通知を受信した場合に,前記電源停止期間設定通知が示す前記監視対象装置が電源を停止する予定日時に前記監視対象装置に対する監視を解除し,前記電源停止期間設定通知が示す前記監視対象装置が電源を復帰する予定日時に前記監視対象装置に対する監視を再開する手段,
として機能させるための稼動状況監視装置用プログラム。
A program for causing a computer of an operating status monitoring device in an operating status monitoring system to monitor the operating status of a monitored device,
Said computer,
The monitoring is performed by confirming reception of the connection notification from the monitoring target device according to a preset schedule for confirming reception of the connection notification, which is a notification indicating that the monitoring target device is operating. Means for monitoring the operating status of the target device,
Means for determining that an operational failure has occurred in the monitored device when the reception of the connection notification from the monitored device cannot be confirmed;
When receiving a power supply stop period setting notification, which is a notification indicating a period during which the monitored device stops power, the monitored device at the scheduled date and time when the monitored device indicated by the power supply stop period setting notification stops power supply Means for canceling the monitoring of the monitoring target device and restarting the monitoring of the monitoring target device at the scheduled date and time when the monitoring target device indicated by the notification of setting of the power stop period is restored.
Program for operating status monitoring device to function as
稼動状況監視装置が監視対象装置の稼動状況を監視する稼動状況監視システムにおける監視対象装置のコンピュータに実行させるためのプログラムであって,
前記コンピュータを,
自身が稼動していることを示す通知である接続通知を前記稼動状況監視装置に送信するための予め設定されたスケジュールに従って,前記稼動状況監視装置に前記接続通知を送信する手段,
自身の電源を停止する期間の予定日時が設定されたときに,その電源停止期間を示す通知である電源停止期間設定通知を前記稼動状況監視装置に送信する手段,
として機能させるための監視対象装置用プログラム。
A program for causing a computer of a monitored device in an operating status monitoring system to monitor the operating status of a monitored device by an operating status monitoring device,
Said computer,
Means for transmitting the connection notification to the operation status monitoring device according to a preset schedule for transmitting a connection notification, which is a notification indicating that the device is operating, to the operation status monitoring device;
Means for transmitting a power supply stop period setting notification, which is a notification indicating the power supply stop period, to the operation status monitoring device when a scheduled date and time of the power supply stop period is set;
Program for monitoring target devices to function as
JP2004123759A 2004-04-20 2004-04-20 Operation state monitoring device, monitoring object device, and program therefor Pending JP2005309643A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004123759A JP2005309643A (en) 2004-04-20 2004-04-20 Operation state monitoring device, monitoring object device, and program therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004123759A JP2005309643A (en) 2004-04-20 2004-04-20 Operation state monitoring device, monitoring object device, and program therefor

Publications (1)

Publication Number Publication Date
JP2005309643A true JP2005309643A (en) 2005-11-04

Family

ID=35438389

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004123759A Pending JP2005309643A (en) 2004-04-20 2004-04-20 Operation state monitoring device, monitoring object device, and program therefor

Country Status (1)

Country Link
JP (1) JP2005309643A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009189000A (en) * 2008-02-04 2009-08-20 Gnst:Kk Remote management system of video processing device and its method
JP2009237936A (en) * 2008-03-27 2009-10-15 Toshiba Corp Information collection apparatus, method and program
JP2011181064A (en) * 2010-02-05 2011-09-15 Fujitsu Ltd Information processing apparatus and method
WO2012147176A1 (en) * 2011-04-27 2012-11-01 富士通株式会社 Program, information processing device, and monitoring method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009189000A (en) * 2008-02-04 2009-08-20 Gnst:Kk Remote management system of video processing device and its method
US8102431B2 (en) 2008-02-04 2012-01-24 GNST Co., Ltd System and method for remote management of image processing device
JP2009237936A (en) * 2008-03-27 2009-10-15 Toshiba Corp Information collection apparatus, method and program
JP2011181064A (en) * 2010-02-05 2011-09-15 Fujitsu Ltd Information processing apparatus and method
WO2012147176A1 (en) * 2011-04-27 2012-11-01 富士通株式会社 Program, information processing device, and monitoring method
JPWO2012147176A1 (en) * 2011-04-27 2014-07-28 富士通株式会社 Program, information processing apparatus, and monitoring method

Similar Documents

Publication Publication Date Title
JP2000306147A (en) Remote monitor system, automatic setting device of near end value for life-limited article management in the system, computer readable recording medium with stored automatic setting program
JP2001077965A (en) Image-forming apparatus management system and management method
CN101777951B (en) Method and system for data monitoring
JP2007042145A (en) Operation monitoring device and operation monitoring system
JP2013137704A (en) Equipment management device and equipment management method
JP2005309643A (en) Operation state monitoring device, monitoring object device, and program therefor
JP5322581B2 (en) Station service system
JP5444739B2 (en) Management device, management system, and management program
JP3917797B2 (en) OPERATION MONITORING DEVICE, STORAGE MEDIUM CONTAINING PROGRAM FOR MAKING COMPUTER TO EXECUTE PROCESSING IN THE DEVICE, AND MONITORED DEVICE MONITORED BY THE DEVICE
US10848547B2 (en) Monitoring system and method
JP5623449B2 (en) Report creation apparatus, report creation program, and report creation method
JP2006154991A (en) Information processing system, control method of information processing system, monitoring device, monitoring program, and maintenance program
JP2008134690A (en) Telemeter device
JP2004086520A (en) Monitoring control device and its method
JP2009187428A (en) Security system
JP2009205221A (en) Maintenance management system and maintenance management method
JP2002169706A (en) Monitor system
JP4362440B2 (en) Notification device and method
JP2023090412A (en) Communication system, management device, and terminal
JP2003169180A (en) Work instructing method, work instructing device and work instruction system
JP2006323563A (en) Abnormality detection system, monitor device and monitor company computer
JP2008059531A (en) Computer system failure notification method
JP2005322024A (en) Abnormality information output device, abnormality detection system and abnormality information output method
JP2007114915A (en) Automatic maintenance checking system based on transmission of information from reporting device installed on user side utilizing self-diagnostic checking system
JP2020178297A (en) Information processing device, apparatus, program, and information processing system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090331

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090421

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090825