JP2005240398A - Permeable pavement, and construction method of permeable pavement - Google Patents

Permeable pavement, and construction method of permeable pavement Download PDF

Info

Publication number
JP2005240398A
JP2005240398A JP2004050793A JP2004050793A JP2005240398A JP 2005240398 A JP2005240398 A JP 2005240398A JP 2004050793 A JP2004050793 A JP 2004050793A JP 2004050793 A JP2004050793 A JP 2004050793A JP 2005240398 A JP2005240398 A JP 2005240398A
Authority
JP
Japan
Prior art keywords
binder
water
concrete
base layer
layer concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004050793A
Other languages
Japanese (ja)
Other versions
JP4230382B2 (en
Inventor
Takeyuki Kimijima
健之 君島
Yasunori Suzuki
康範 鈴木
Tetsuo Kobayashi
哲夫 小林
Koichi Matsumoto
公一 松本
Takayoshi Kodama
孝喜 児玉
Wataru Mizuno
渉 水野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Osaka Cement Co Ltd
Kajima Road Co Ltd
Original Assignee
Sumitomo Osaka Cement Co Ltd
Kajima Road Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Osaka Cement Co Ltd, Kajima Road Co Ltd filed Critical Sumitomo Osaka Cement Co Ltd
Priority to JP2004050793A priority Critical patent/JP4230382B2/en
Publication of JP2005240398A publication Critical patent/JP2005240398A/en
Application granted granted Critical
Publication of JP4230382B2 publication Critical patent/JP4230382B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide permeable pavement eliminating causes of a flood and a heat island phenomenon to solve a water problem and a heat problem by securing a sure permeating function in a paved road. <P>SOLUTION: The permeable pavement 1 is constituted by forming a binder part 4 for joining a base course concrete part 2 and a surface layer concrete part 3 both formed of porous concrete and having permeability, at a boundary part 1X of the base course concrete part 2 and surface layer concrete part 3 so as not to block permeating holes 22, 32 opened to the surface of the base course concrete part 2 and the bottom face of the surface layer concrete part 3. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、透水性舗装とその施工方法に関するものである。   The present invention relates to a water-permeable pavement and its construction method.

舗装道路の最も重要な機能は、交通荷重を安全に地盤に伝達するとともに、車両が通行する舗装面が平滑性や滑り抵抗性等の所定機能を所要耐用期間内において維持することにあり、特にコンクリート舗装が、アスファルト舗装よりも初期投資はかかるものの耐久性に優れるという観点から期待されている。   The most important function of paved roads is to transmit traffic load safely to the ground, and to maintain predetermined functions such as smoothness and slip resistance within the required service life of the paved surface on which the vehicle passes. Concrete pavement is expected from the viewpoint of superior durability compared to asphalt pavement, although it requires an initial investment.

近年の都市部では、道路舗装率の増大に伴って水環境や熱環境が著しく変化してきており、様々な問題が発生してきている。例えば、水環境に関しては、地表面の改変によって流域の保水・遊水機能が減少するため、雨水が道路表面を流れ難くなって、特に豪雨時には大量の雨水排水が一気に河川に流入することとなり、洪水の到達時間が早期化するとともに規模が拡大し、水害の危険性が高まる。さらに、雨水の地下浸透が減少するために、地下水位の低下、平常時の河川の流量の減少が生じ、水質の悪化に繋がっている。また、熱環境に関しては、舗装化の進展による地面の保水機能の低下が、地表からの水分蒸散による大気に対する冷却作用の低下を招き、特に都市部においてヒートアイランド現象をもたらす一因ともなっている。   In urban areas in recent years, the water environment and thermal environment have changed remarkably as the road pavement rate increases, and various problems have arisen. For example, with regard to the water environment, the water retention and recreational functions of the basin will decrease due to the change in the ground surface, making it difficult for rainwater to flow on the road surface. The arrival time of the plant will be accelerated and the scale will increase, increasing the risk of flood damage. Furthermore, since the infiltration of rainwater into the ground is reduced, the groundwater level is lowered and the river flow is reduced during normal times, leading to deterioration of water quality. In addition, regarding the thermal environment, the decrease in the water retention function of the ground due to the progress of paving causes a decrease in the cooling effect on the atmosphere due to moisture evaporation from the ground surface, and is also a factor in causing the heat island phenomenon particularly in urban areas.

そこで、上述のような水環境・熱環境に対応でき、且つ従来のコンクリート舗装の問題点を解消するものとして、コンクリート舗装において、表層及び基層をいずれもポーラスコンクリートからなるものとし、表層と基層の一体性を高めた打ち重ね方法が考えられている(例えば、特許文献1参照)。斯かる方法では、従来と同様に締固め機器の能力の限界から必然的に、一層ではなく二層以上の多層構造に打ち重ねを行う必要があるが、多層に亘るポーラスコンクリートを一体化するために、(a)前層(打ち重ねるコンクリート層の直下となる層)に遅延剤を加えたり、打ち重ね時間を長く取るための配合を行う、(b)前層の一部を掻き乱し、その後で締固め機器により一体となるように締め固める、などの工夫が凝らされている。
特開平2002−317403号公報
Therefore, in order to solve the problems of the conventional water and heat environments as described above and to solve the problems of the conventional concrete pavement, in the concrete pavement, both the surface layer and the base layer are made of porous concrete. A stacking method with improved integrity has been considered (see, for example, Patent Document 1). In such a method, as in the conventional case, it is necessary to stack two or more layers instead of one layer due to the limitation of the capacity of the compacting device. However, in order to integrate porous concrete covering multiple layers. In addition, (a) adding a retarder to the previous layer (a layer directly below the concrete layer to be stacked) or blending for a long stacking time, (b) disturbing a part of the previous layer, After that, contrivances such as compaction to be united with a compaction device have been made.
Japanese Patent Laid-Open No. 2002-317403

ポーラスコンクリート舗装に上述の工夫を施した場合、施工をスムーズに行えば基層と表層との一体化は可能である。   When the above-mentioned device is applied to the porous concrete pavement, the base layer and the surface layer can be integrated if the construction is performed smoothly.

ところが、上記の舗装構造は、表層部は乾燥しやすい一方で、基層部以下は乾燥しにくいので、表層・基層コンクリート間には湿度の差やこれに伴う環境温度の差が生じ、乾燥収縮量の差や熱応力の差が生じて両者の界面の付着力が低下し易いという厳しい構造条件を有している。特に表層部の透水係数が基層部の透水係数よりも大きい場合は、基層部以下は一層乾燥しにくい状態となり、表層・基層間が受ける条件は、より過酷なものとなる。   However, in the above pavement structure, the surface layer part is easy to dry, but the base layer part and below are difficult to dry.Therefore, there is a difference in humidity between the surface layer and the base layer concrete, and the resulting environmental temperature difference. There is a strict structural condition that the difference in thermal stress and the difference in thermal stress occur and the adhesive force at the interface between the two tends to decrease. In particular, when the water permeability coefficient of the surface layer portion is larger than the water permeability coefficient of the base layer portion, the portion below the base layer portion is more difficult to dry, and the conditions experienced by the surface layer and the base layer become more severe.

従って、基層と表層との一体化が出来たとしても、所要の付着性能と透水性能を同時に確保するには高度な施行管理が必要であった。   Therefore, even if the base layer and the surface layer can be integrated, a high level of enforcement management is required to ensure the required adhesion performance and water permeability performance at the same time.

すなわち、まず前記(a)の場合、環境温度が高い場合や強風の場合には、前層に遅延剤を加えたり打ち重ね時間を長く取るような配合上の工夫だけでは十分な付着強度が得られず、過大な遅延剤量や不適切な配合であると、付着強度のみならず透水係数も過度に低下する恐れがあって、その効果が環境条件により左右されやすいという問題がある。   That is, in the case of the above (a), when the environmental temperature is high or the wind is strong, sufficient adhesion strength can be obtained only by adding a retarder to the previous layer or taking a long stacking time. However, if the amount of the retarder is excessive or the blending is inappropriate, not only the adhesion strength but also the water permeability coefficient may be excessively lowered, and there is a problem that the effect is easily influenced by environmental conditions.

次に、(b)の場合には、締固め機器の能力が高いことが要求される上に、一体化できる層の厚さが限定され、一部掻き乱した前層の部分が付着の弱点となる場合がある。   Next, in the case of (b), the capability of the compacting device is required to be high, and the thickness of the layer that can be integrated is limited, and the part of the previous layer that has been partially disturbed is a weak point of adhesion. It may become.

そこで本発明は、以上のような問題に鑑みて、真に水環境・熱環境に対応でき、且つ従来の種々のコンクリート舗装の問題点を解消することができる透水性舗装並びにその施工方法を提供することを主たる目的としている。   Therefore, in view of the above problems, the present invention provides a water-permeable pavement that can truly cope with a water environment and a thermal environment, and can solve the problems of various conventional concrete pavements, and a construction method thereof. The main purpose is to do.

すなわち、本発明の透水性舗装は、ポーラスコンクリートからなり透水性を有する基層コンクリート部と、ポーラスコンクリートからなり前記基層コンクリート部の上部に敷設した透水性を有する表層コンクリート部とを具備するものであって、基層コンクリート部の表面と表層コンクリート部の底面との境界部分に、これら基層コンクリート部と表層コンクリート部とを接合するバインダ部を、基層コンクリート部の表面及び表層コンクリート部の底面において開口する透水孔を閉塞しないように形成していることを特徴とするものである。   That is, the water-permeable pavement of the present invention comprises a base layer concrete portion made of porous concrete and having water permeability, and a surface layer concrete portion made of porous concrete and laid on the upper portion of the base layer concrete portion. Permeable water that opens at the boundary between the surface of the base layer concrete portion and the bottom surface of the surface layer concrete portion, the binder portion joining the base layer concrete portion and the surface layer concrete portion at the surface of the base layer concrete portion and the bottom surface of the surface concrete portion The holes are formed so as not to close the holes.

このような構成の舗装であれば、バインダ部を、基層コンクリート部と表層コンクリートとの境界部分に設けているため、ポーラスコンクリート自体の引張強度に匹敵する程度の基層コンクリート部と表層コンクリート部との接合強度を得ることができる。しかも、当該バインダ部は、前記境界部分において開口する透水孔を閉塞しないように形成しているものであるので、舗装構造全体としてのポーラスコンクリートの透水孔に基づく透水性能を発揮して雨水を表層コンクリート部、境界部分、及び基層コンクリート部を通じて土壌中に浸透させることができる。したがって、雨水が舗装表面を一気に流れて洪水や河川の水質悪化を招くという前述の水環境を改善するとともに、土壌中に雨水を保持させることにより乾燥時にはそれを大気中に蒸発させてヒートアイランド現象の解消を図るという熱問題の改善の一助とすることもできる。なお、本発明に斯かる透水性舗装は、基層コンクリート部と表層コンクリート部の二層構造を有するものに限らず、三層以上のコンクリート多層構造を有するものも含まれる。   In the case of pavement having such a configuration, since the binder portion is provided at the boundary portion between the base layer concrete portion and the surface layer concrete, the base layer concrete portion and the surface concrete portion having a degree comparable to the tensile strength of the porous concrete itself. Bonding strength can be obtained. In addition, since the binder portion is formed so as not to block the water-permeable holes that open at the boundary portion, the water-permeable performance based on the water-permeable holes of the porous concrete as the entire pavement structure is exhibited and the rainwater is surfaced. It can be infiltrated into the soil through the concrete part, the boundary part, and the base concrete part. Therefore, in addition to improving the water environment described above, where rainwater flows all over the surface of the pavement, causing flooding and river water quality deterioration, it retains rainwater in the soil and evaporates it into the atmosphere when dry, causing the heat island phenomenon. It can also help to improve the thermal problem of eliminating it. In addition, the water-permeable pavement according to the present invention is not limited to one having a two-layer structure of a base layer concrete portion and a surface layer concrete portion, and one having a concrete multilayer structure of three or more layers is also included.

また、バインダ部は、セメント系無収縮グラウト材からなるものとすることが好ましく、施工作業性、付着強度、耐久性などの面から適しているといえる。   The binder part is preferably made of a cement-based non-shrink grout material, which can be said to be suitable in terms of construction workability, adhesion strength, durability, and the like.

以上のような透水性舗装を構築するための本発明の施工方法は、ポーラスコンクリートからなり透水性を有する基層コンクリートを敷設する基層コンクリート部形成工程と、基層コンクリート部の表面にバインダを塗布するバインダ塗布工程と、基層コンクリート部の表面に開口する透水孔に塗布されたバインダを除去するバインダ部分的除去工程と、このバインダの硬化前に上方からポーラスコンクリートからなり透水性を有する表層コンクリートを敷設する表層コンクリート部形成工程とを含むことを特徴としている。   The construction method of the present invention for constructing the water-permeable pavement as described above includes a base layer concrete portion forming step of laying base layer concrete made of porous concrete and having water permeability, and a binder for applying a binder to the surface of the base layer concrete portion. A coating step, a binder partial removal step for removing the binder applied to the water-permeable holes opened on the surface of the base layer concrete portion, and a surface layer concrete having water permeability made of porous concrete from above before the binder is cured. Including a surface concrete portion forming step.

このような方法で基層コンクリート部の表面に塗布されたバインダを部分的に除去して透水性舗装を施工することによって、基層コンクリート部と表層コンクリート部との境界部分に、透水孔が閉塞していないバインダ部を形成することができる。その結果、上述のような強度面、耐久性にも問題なく、舗装構造全体としてのポーラスコンクリートの透水孔に基づく透水機能も十分に確保して、水環境及び熱環境の有効な対応策となる透水性舗装を施工することができることとなる。   By partially removing the binder applied to the surface of the base layer concrete part in this way and constructing the water permeable pavement, the water permeable holes are blocked at the boundary part between the base layer concrete part and the surface layer concrete part. No binder part can be formed. As a result, there is no problem in strength and durability as described above, and a sufficient water permeability function based on the pores of porous concrete as a pavement structure as a whole is ensured, which is an effective countermeasure for water and thermal environments. A permeable pavement can be constructed.

特に、バインダ塗布工程においては、塗布面を有するローラを用いてバインダの塗布を行い、バインダ部分的除去工程においては、間欠的に毛先を有するブラシを用いてバインダの部分的除去を行うことが、上述のバインダ部を形成するのに有効である。これに対して、バインダを塗布し得る塗布面と間欠的に設けた毛先を有するブラシ部とを有するブラシ付きローラを使用して、バインダ塗布工程とバインダ部分的除去工程とを一工程で同時に行うと、作業時間の短縮化及び施工コストの削減を図ることができる。   In particular, in the binder application process, the binder is applied using a roller having an application surface, and in the binder partial removal process, the binder is partially removed using a brush having a hair tip intermittently. It is effective to form the above-mentioned binder part. On the other hand, using a roller with a brush having an application surface on which a binder can be applied and a brush portion having a hair tip provided intermittently, the binder application step and the binder partial removal step are simultaneously performed in one step. If done, the working time can be shortened and the construction cost can be reduced.

また上述の通り、バインダ部には、セメント系無収縮グラウト材を適用することが極めて有効である。   As described above, it is extremely effective to apply a cement-based non-shrink grout material to the binder portion.

以上に詳述したように、本発明では、ポーラスコンクリートからなる基層コンクリート部と表層コンクリート部との間の境界部分において、それら二層を接合するために設けられるバインダ部をほぼ全面に亘り均一に且つ部分的に設けることによって、透水性舗装を形成するようにしている。そのため、基層コンクリート部の透水孔と表層コンクリート部の透水孔とが連通した状態が実現されることになり、舗装道路の透水機能を確実に得ることができる。その結果、雨水は舗装道路の表面を流れることなく、路盤、路床に浸透・保持されるため、地下水の滋養、植生・地中生態等の改善だけではなく路面温度の低減によるヒートアイランド現象の抑制に効果があり、水問題及び熱問題の解決を好適に図ることが可能である。   As described above in detail, in the present invention, at the boundary portion between the base layer concrete portion made of porous concrete and the surface concrete portion, the binder portion provided for joining the two layers is made almost uniform over the entire surface. And by providing partially, permeable pavement is formed. Therefore, the state where the water-permeable hole of the base layer concrete part and the water-permeable hole of the surface concrete part communicated is realized, and the water-permeable function of the paved road can be obtained with certainty. As a result, rainwater permeates and is retained on the roadbed and roadbed without flowing on the surface of the paved road, so that not only the improvement of groundwater, vegetation and underground ecology, but also the suppression of the heat island phenomenon by reducing the road surface temperature. It is possible to effectively solve the water problem and the heat problem.

以下、本発明の実施形態を、図表を参照して説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

図1に示す本実施形態の透水性舗装1は、基層コンクリート部2と、表層コンクリート部3と、これら基層コンクリート部2及び表層コンクリート部3との境界部分に介在するバインダ部4とから構成したものである。なお、基層コンクリート部2の下層側において土壌である路床との間は、別途に路盤層や路床改良層等を設けていることができるが、本実施形態ではこれら路盤層や路床改良層の存在の有無は問わない。   A water-permeable pavement 1 according to this embodiment shown in FIG. 1 is composed of a base layer concrete part 2, a surface layer concrete part 3, and a binder part 4 interposed at the boundary part between the base layer concrete part 2 and the surface layer concrete part 3. Is. In addition, although a roadbed layer, a roadbed improvement layer, etc. can be separately provided between the base layer concrete part 2 and the roadbed which is soil, in this embodiment, these roadbed layers and roadbed improvement are provided. It does not matter whether or not the layer exists.

基層コンクリート部2は、表面にセメント、混和材、細骨材、水、混和剤(図示省略)と多数の粗骨材21とを混練したものである。この粗骨材21の粒径は、例えば約5〜20mmであり、水/結合材比を例えば20.0〜35.0%としている。そして、斯かる基層コンクリート部2の空隙率を、約10〜15%としている。このような基層コンクリート部2においては、粗骨材21同士の間に空隙が形成されており、この空隙を透水孔22として利用している。   The base layer concrete portion 2 is obtained by kneading cement, an admixture, fine aggregate, water, an admixture (not shown) and a large number of coarse aggregates 21 on the surface. The particle size of the coarse aggregate 21 is, for example, about 5 to 20 mm, and the water / binding material ratio is, for example, 20.0 to 35.0%. And the porosity of such base layer concrete part 2 is about 10 to 15%. In such a base layer concrete part 2, a gap is formed between the coarse aggregates 21, and this gap is used as the water permeable hole 22.

表層コンクリート部3は、基層コンクリート部2と同様に、表面にセメント、混和材、細骨材、水、混和剤(図示省略)と多数の粗骨材31とを混練したものである。この粗骨材31の粒径は、例えば約2.5〜15mmであり、水/結合材比を例えば約20.0〜35.0%としている。そして斯かる表層コンクリート部3の空隙率を、約15〜25%としている。このような表層コンクリート部3においては、粗骨材31同士の間に空隙が形成されており、この空隙を透水孔32として利用している。   Similar to the base layer concrete portion 2, the surface concrete portion 3 is obtained by kneading cement, an admixture, a fine aggregate, water, an admixture (not shown) and a large number of coarse aggregates 31 on the surface. The particle size of the coarse aggregate 31 is, for example, about 2.5 to 15 mm, and the water / binding material ratio is, for example, about 20.0 to 35.0%. And the porosity of the surface concrete part 3 is set to about 15 to 25%. In such a surface concrete portion 3, a gap is formed between the coarse aggregates 31, and this gap is used as the water permeable hole 32.

バインダ部4は、基層コンクリート部2と表層コンクリート部33を結合させるバインダ41から構成されるものである。本実施形態ではバインダ41を、基層コンクリート部2と表層コンクリート部3との境界部分1Xのほぼ全域に亘って塗布しており、その塗布量を、例えば単位面積当たり約1〜2L/m2としている。ただし、バインダ41は、前記境界部分1Xにおいて、基層コンクリート部2の透水孔22と表層コンクリート部3の透水孔32とを完全には塞いでしまわないように塗布されている。ここで、基層コンクリート部2と表層コンクリート部3とがセメント系の材質である場合には、バインダ41として例えばセメントスラリー、セメントモルタル、ポリマーセメントモルタル、セメント系グラウト材、セメント系無収縮グラウト材を適用することが好ましい。バインダ41を舗装道路の施工に用いる際には、比較的広い面積に塗布する際の作業効率の面からは高い流動性が要求され、収縮による接合面の割れを生じることなく長期間の使用に耐えることが条件となるため、先に例示したバインダのなかでも特に、セメント系無収縮グラウト材、例えば住友大阪セメント株式会社製「フィルコンR」を用いることができる。 The binder part 4 includes a binder 41 that joins the base layer concrete part 2 and the surface concrete part 33. In this embodiment, the binder 41 is applied over almost the entire boundary portion 1X between the base layer concrete portion 2 and the surface concrete portion 3, and the amount applied is, for example, about 1 to 2 L / m 2 per unit area. Yes. However, the binder 41 is applied so as not to completely block the water-permeable holes 22 of the base layer concrete portion 2 and the water-permeable holes 32 of the surface concrete portion 3 in the boundary portion 1X. Here, when the base layer concrete portion 2 and the surface concrete portion 3 are cement-based materials, for example, cement slurry, cement mortar, polymer cement mortar, cement-based grout material, or cement-based non-shrink grout material is used as the binder 41. It is preferable to apply. When the binder 41 is used for construction of a paved road, high fluidity is required from the viewpoint of work efficiency when it is applied to a relatively large area, and it can be used for a long time without causing cracks in the joint surface due to shrinkage. Since it is necessary to endure, among the binders exemplified above, a cement-based non-shrink grout material such as “Filcon R” manufactured by Sumitomo Osaka Cement Co., Ltd. can be used.

以下、本実施形態の透水性舗装1の施工方法について説明する。   Hereinafter, the construction method of the water-permeable pavement 1 of this embodiment is demonstrated.

まず、路床や路床改良層若しくは路盤層の上部に、未硬化状態でポーラスコンクリート打設し、締固め機器により敷き均し・締め固め、基層コンクリート部2を形成する(図2(a);基層コンクリート部形成工程)。   First, porous concrete is placed in an uncured state on the upper part of the road bed, the road bed improvement layer or the road bed layer, and the base layer concrete portion 2 is formed by laying and compacting with a compacting device (FIG. 2A); Base layer concrete part formation process).

次に、この基層コンクリート部2の表面にバインダ41を塗布する工程(バインダ塗布工程)と、そのバインダ41を部分的に除去する工程(バインダ部分除去工程)とを行うが、本実施形態では図2(b)に示すようなブラシ付ローラ5を用いてこの二工程を同時に実施することとしている。すなわち、このブラシ付ローラ5は、円筒状の本体50の周面を塗布面51としており、その周面から多数の刷毛を突出させたブラシ部52を形成したものである。このようなブラシ付ローラ5の塗布面51にバインダ41を付着させておき、所定方向(図示例では右側)に本体50を回転させると、一旦バインダ41が基層コンクリート部2の表面に付着するが、その付着したバインダ41はブラシ部52によって剥離させられる。特に、基層コンクリート部2の表面側から透水孔22に侵入したブラシ部52はその透水孔22からバインダ41を掻き出すことになるので、透水孔22のうち少なくとも一部は上方に開放された状態となる(図2(c))。   Next, a process of applying the binder 41 to the surface of the base concrete part 2 (binder application process) and a process of partially removing the binder 41 (binder partial removal process) are performed. These two steps are carried out simultaneously using a roller 5 with a brush as shown in 2 (b). That is, the roller 5 with brush has a peripheral surface of a cylindrical main body 50 as an application surface 51 and a brush portion 52 in which a large number of brushes protrude from the peripheral surface. When the binder 41 is attached to the application surface 51 of the brushed roller 5 and the main body 50 is rotated in a predetermined direction (right side in the illustrated example), the binder 41 once adheres to the surface of the base concrete portion 2. The adhered binder 41 is peeled off by the brush portion 52. In particular, since the brush portion 52 that has entered the water-permeable hole 22 from the surface side of the base concrete portion 2 scrapes the binder 41 from the water-permeable hole 22, at least a part of the water-permeable hole 22 is open upward. (FIG. 2 (c)).

最後に、バインダ41が未硬化の状態でその上方からポーラスコンクリート打設し、締固め機器により締固め機器により敷き均し・締め固め、表層コンクリート部3を形成する(図2(d);基層コンクリート部形成工程)。この状態で、表層コンクリート部3の透水孔32と基層コンクリート部2の透水孔22とが部分的に連通していることになるので(図2(d))、透水性舗装1全体としての透水機能が確保される。   Finally, porous concrete is cast from above in an uncured state of the binder 41, and is spread and compacted by a compacting device with a compacting device to form a surface concrete portion 3 (FIG. 2 (d); base layer Concrete part formation process). In this state, the water-permeable holes 32 of the surface concrete portion 3 and the water-permeable holes 22 of the base layer concrete portion 2 are partially in communication (FIG. 2D), so that the water-permeable pavement 1 as a whole is permeable. Function is secured.

ここで、本実施形態の透水性舗装1について行った付着強度試験と透水試験について説明する。   Here, the adhesion strength test and the water permeability test performed on the water-permeable pavement 1 of the present embodiment will be described.

Figure 2005240398
Figure 2005240398

Figure 2005240398
Figure 2005240398

このような方法により施工される本実施形態の透水性舗装1によれば、共にポーラスコンクリートから構成され透水性を有する基層コンクリート部2と表層コンクリート部3との境界部分1Xにおいて、バインダ部4を当該境界部分1Xに対して部分的にではあるがほぼ全域に亘って設けているため、従来の透水性舗装とほぼ同程度の付着強度を得ることができる。そして、バインダ部41を境界部分1Xにおいて、基層コンクリート部2の透水孔22と表層コンクリート部3の透水孔32の全てを塞いでしまわないように設けているため、透水性舗装1全体としての透水機能を十分に発揮することができる。したがって、雨水を表層コンクリート部3、境界部分1X、及び基層コンクリート部2を通じて土壌中に流し落とすことができることになるため、雨水が舗装表面を一気に流れることなく土壌に保持される。その結果、洪水や河川の水質悪化を招くという問題が生じず水環境の改善に役立つとともに、土壌中に保持された雨水を乾燥時に大気中に蒸散させてヒートアイランド現象を改善することも可能である。   According to the water-permeable pavement 1 of this embodiment constructed by such a method, the binder portion 4 is formed at the boundary portion 1X between the base layer concrete portion 2 and the surface concrete portion 3 both made of porous concrete and having water permeability. Since it is provided over substantially the entire region, although partially, with respect to the boundary portion 1X, it is possible to obtain adhesion strength substantially the same as that of the conventional water-permeable pavement. And since the binder part 41 is provided in the boundary part 1X so as not to block all the water-permeable holes 22 of the base concrete part 2 and the water-permeable holes 32 of the surface concrete part 3, the water permeability of the water-permeable pavement 1 as a whole. The function can be fully demonstrated. Therefore, since rainwater can be poured into the soil through the surface concrete portion 3, the boundary portion 1X, and the base concrete portion 2, the rainwater is held in the soil without flowing at once at the pavement surface. As a result, it is possible to improve the water environment without causing problems such as floods and river water quality deterioration, and it is also possible to improve the heat island phenomenon by transpiration of rainwater retained in the soil into the atmosphere during drying. .

なお、本実施形態に係る透水性舗装1は、一般道路、高速道路の別を問わず適用できるものであるが、舗装道路の全体にこの透水性舗装1を適用しなければならないわけではない。例えば道路の路肩近傍の舗装版端部のような乾燥収縮による反り応力で付着性能が損なわれやすい部位や、特に大荷重が作用しやすい大型車両の車軸位置に対応する部位などにおいては、バインダ部41の部分的除去工程を行わず、透水孔が一部閉塞した状態であっても、当該境界部分1Xのその他の部位にバインダ部分的除去工程を施して透水孔を開口させて、道路全体として透水機能を有していれば十分である。   In addition, although the water-permeable pavement 1 which concerns on this embodiment can be applied regardless of a general road and a highway, it does not necessarily have to apply this water-permeable pavement 1 to the whole paved road. For example, in parts where adhesion performance is likely to be impaired due to warping stress due to drying shrinkage, such as the edge of a pavement near the shoulder of a road, especially in parts corresponding to the axle position of large vehicles where heavy loads are likely to act, the binder part Even if the partial removal step 41 is not performed and the water-permeable hole is partially blocked, the binder partial removal step is performed on the other part of the boundary portion 1X to open the water-permeable hole, and the entire road It is sufficient if it has a water permeability function.

また、上記実施形態では、バインダ塗布工程とバインダ部分除去工程とをブラシ付ローラを用いて同時に行った例を示したが、この二工程は各別に行うことを妨げるものではない。すなわち、基層コンクリート部形成工程の後、その表面にまずバインダの全面塗布を行い、その後にバインダを部分的に除去したとしても、上記実施形態と同等の透水性舗装が得られる。   Moreover, although the example which performed the binder application | coating process and the binder partial removal process simultaneously using the roller with a brush was shown in the said embodiment, these two processes do not prevent performing separately. That is, after the base layer concrete portion forming step, even if the entire surface of the binder is first coated on the surface and then the binder is partially removed, the water-permeable pavement equivalent to the above embodiment can be obtained.

その他、ポーラスコンクリートにアスファルト系のものを適用したり、バインダに無収縮セメント系グラウト材以外のものを適用するなど、基層コンクリート部、表層コンクリート部、バインダ部の組成等、各部の具体的構成についても上記実施形態に限られるものではなく、本発明の趣旨を逸脱しない範囲で種々変形が可能である。   In addition, specific composition of each part such as composition of base layer concrete part, surface concrete part, binder part, such as applying asphalt type thing to porous concrete, applying something other than non-shrinkage cement grout material to binder However, the present invention is not limited to the above embodiment, and various modifications can be made without departing from the spirit of the present invention.

本発明の一実施形態に係る透水性舗装を概略的に示す断面図。Sectional drawing which shows schematically the water-permeable pavement which concerns on one Embodiment of this invention. 同実施形態の施工工程を示す説明図。Explanatory drawing which shows the construction process of the embodiment.

符号の説明Explanation of symbols

1…透水性舗装
2…基層コンクリート部
3…表層コンクリート部
4…バインダ部
5…ブラシ付ローラ
22…透水孔
32…透水孔
41…バインダ
51…塗布面
52…ブラシ部
DESCRIPTION OF SYMBOLS 1 ... Water-permeable pavement 2 ... Base-layer concrete part 3 ... Surface layer concrete part 4 ... Binder part 5 ... Roller with brush 22 ... Water-permeable hole 32 ... Water-permeable hole 41 ... Binder 51 ... Application surface 52 ... Brush part

Claims (6)

ポーラスコンクリートからなり透水性を有する基層コンクリート部と、該基層コンクリート部の上部に敷設されるポーラスコンクリートからなり透水性を有する表層コンクリート部とを具備するものであって、
基層コンクリート部の表面と表層コンクリート部の底面との境界部分に、これら基層コンクリート部と表層コンクリート部とを接合するバインダ部を、基層コンクリート部の表面及び表層コンクリート部の底面において開口する透水孔を閉塞しないように形成していることを特徴とする透水性舗装。
A base layer concrete portion made of porous concrete and having water permeability, and a surface concrete portion having water permeability made of porous concrete laid on top of the base layer concrete portion,
At the boundary between the surface of the base layer concrete part and the bottom surface of the surface layer concrete part, a binder part that joins the base layer concrete part and the surface layer concrete part is provided with a water-permeable hole that opens at the surface of the base layer concrete part and the bottom surface of the surface layer concrete part. A water-permeable pavement characterized by being formed so as not to be blocked.
前記バインダ部は、セメント系無収縮グラウト材をバインダとするものである請求項1記載の透水性舗装。 The water-permeable pavement according to claim 1, wherein the binder portion uses a cement-based non-shrink grout material as a binder. ポーラスコンクリートからなり透水性を有する基層コンクリートを敷設する基層コンクリート部形成工程と、基層コンクリート部の表面にバインダを塗布するバインダ塗布工程と、基層コンクリート部の表面に開口する透水孔に塗布されたバインダを除去するバインダ部分的除去工程と、このバインダの硬化前に上方からポーラスコンクリートからなり透水性を有する表層コンクリートを敷設する表層コンクリート部形成工程とを含むことを特徴とする透水性舗装の施工方法。 Base layer concrete part forming step of laying base layer concrete made of porous concrete and having water permeability, binder application step of applying a binder to the surface of the base layer concrete part, and binder applied to the water permeable holes opened on the surface of the base layer concrete part A method for constructing a water-permeable pavement, comprising: a binder partial removing step of removing a surface layer; and a surface concrete portion forming step of laying a surface layer concrete made of porous concrete and having water permeability before the binder is cured. . バインダ塗布工程において、塗布面を有するローラを用いてバインダの塗布を行い、バインダ部分的除去工程において、間欠的に毛先を有するブラシを用いてバインダの部分的除去を行う請求項3記載の透水性舗装の施工方法。 The water permeable water according to claim 3, wherein the binder is applied using a roller having an application surface in the binder application step, and the binder is partially removed using a brush having a hair tip intermittently in the binder partial removal step. Construction method for pavement. バインダを塗布し得る塗布面と、間欠的に設けた毛先を有するブラシ部とを有するブラシ付ローラを使用して、前記バインダ塗布工程とバインダ部分的除去工程とを一工程で同時に行う請求項3記載の透水性舗装の施工方法。 The binder application step and the binder partial removal step are simultaneously performed in one step by using a roller with a brush having an application surface on which a binder can be applied and a brush portion having a bristles provided intermittently. The construction method of the water-permeable pavement of 3 description. 前記バインダ部に、セメント系無収縮グラウト材をバインダととして適用する請求項3、4又は5記載の透水性舗装の施工方法。 The method for constructing a water-permeable pavement according to claim 3, 4 or 5, wherein a cement-based non-shrink grout material is applied to the binder part as a binder.
JP2004050793A 2004-02-26 2004-02-26 Permeable pavement and construction method of permeable pavement Expired - Fee Related JP4230382B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004050793A JP4230382B2 (en) 2004-02-26 2004-02-26 Permeable pavement and construction method of permeable pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004050793A JP4230382B2 (en) 2004-02-26 2004-02-26 Permeable pavement and construction method of permeable pavement

Publications (2)

Publication Number Publication Date
JP2005240398A true JP2005240398A (en) 2005-09-08
JP4230382B2 JP4230382B2 (en) 2009-02-25

Family

ID=35022418

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004050793A Expired - Fee Related JP4230382B2 (en) 2004-02-26 2004-02-26 Permeable pavement and construction method of permeable pavement

Country Status (1)

Country Link
JP (1) JP4230382B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587346A (en) * 2012-03-26 2012-07-18 苏州工业园区设计研究院股份有限公司 Method for constructing large-sized unreinforced terrace foundation
CN104631268A (en) * 2015-01-20 2015-05-20 重庆科创职业学院 Concrete road pavement structure
JP2016191288A (en) * 2015-03-31 2016-11-10 住友大阪セメント株式会社 Surface treatment method of porous concrete, porous concrete surface-treated by such surface treatment method, and manufacturing method of surface-treated porous concrete
CN106544941A (en) * 2016-10-11 2017-03-29 南京航空航天大学 A kind of porous pavement with purification function
JP2019138146A (en) * 2019-05-20 2019-08-22 住友大阪セメント株式会社 Surface treatment method of paving porous concrete, paving porous concrete surface-treated by the surface treatment method, and manufacturing method of surface-treated paving porous concrete
CN114409437A (en) * 2022-02-20 2022-04-29 太原钢铁(集团)有限公司 Method for preparing water permeable brick by using baking-free aggregate

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535300B (en) * 2011-06-02 2014-07-09 浙江方远建材科技有限公司 Ecotypic water-permeable stratum structure
CN104831599B (en) * 2015-04-23 2017-03-08 江西师范大学 A kind of compound drainage environmental protection ground

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587346A (en) * 2012-03-26 2012-07-18 苏州工业园区设计研究院股份有限公司 Method for constructing large-sized unreinforced terrace foundation
CN104631268A (en) * 2015-01-20 2015-05-20 重庆科创职业学院 Concrete road pavement structure
JP2016191288A (en) * 2015-03-31 2016-11-10 住友大阪セメント株式会社 Surface treatment method of porous concrete, porous concrete surface-treated by such surface treatment method, and manufacturing method of surface-treated porous concrete
CN106544941A (en) * 2016-10-11 2017-03-29 南京航空航天大学 A kind of porous pavement with purification function
CN106544941B (en) * 2016-10-11 2020-02-21 南京航空航天大学 Permeable pavement with purification performance
JP2019138146A (en) * 2019-05-20 2019-08-22 住友大阪セメント株式会社 Surface treatment method of paving porous concrete, paving porous concrete surface-treated by the surface treatment method, and manufacturing method of surface-treated paving porous concrete
CN114409437A (en) * 2022-02-20 2022-04-29 太原钢铁(集团)有限公司 Method for preparing water permeable brick by using baking-free aggregate

Also Published As

Publication number Publication date
JP4230382B2 (en) 2009-02-25

Similar Documents

Publication Publication Date Title
Tennis et al. Pervious concrete pavements
EP2698471B1 (en) Water-permeable and water-absorbing eco-pavement
AM et al. Development of high quality pervious concrete specifications for Maryland conditions.
JP4230382B2 (en) Permeable pavement and construction method of permeable pavement
CN207672358U (en) A kind of environment protection pavement
JP2005315063A (en) Snow melting panel and its manufacturing method, and snow melting roadbed
CN208649826U (en) The pervious asphalt road of Collapsible Loess District
CN108221533A (en) A kind of laying method in backroad face
US10654751B2 (en) Polymer modified cement adhesive for providing high friction surfacing
JP4555460B2 (en) Permeable block pavement and construction method of permeable block pavement
CN105803888A (en) Sponge type road paving structure
KR20020031281A (en) Water Permeable concrete pavement overlaid with waste tire chip composition
JP5091826B2 (en) Floor or road pavement structure
CN102322010B (en) Road surface porous resin seal layer and construction method thereof
CN107974892A (en) A kind of environment protection pavement and its construction method
KR102503458B1 (en) Red illite water permeable pavement material and pavement method using the same
KR20120055303A (en) Mathod for road constructing using water permeable concrete and permeable exposed color aggregates pavement
JP2003147716A (en) Pavement provided with water permeability, water draining capability and water retentivity and its construction method
JP4146964B2 (en) High-performance road structure and its construction method
KR20070120626A (en) Ommited
JP2002250001A (en) Road paving structure and method
CN220352535U (en) Municipal road construction roadbed drainage structure
JP4233470B2 (en) Water-permeable pavement and method for reinforcing water-permeable pavement
JP2001031481A (en) Water-permeable concrete surface plate, draining pavement and paving method
JP7080201B2 (en) Pavement structure and construction method of permeable concrete pavement

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060906

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080801

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080902

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081031

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081202

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081203

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111212

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111212

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121212

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121212

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131212

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees