JP2005083179A - Main beam, frame and construction method for temporary pier using them - Google Patents

Main beam, frame and construction method for temporary pier using them Download PDF

Info

Publication number
JP2005083179A
JP2005083179A JP2003320253A JP2003320253A JP2005083179A JP 2005083179 A JP2005083179 A JP 2005083179A JP 2003320253 A JP2003320253 A JP 2003320253A JP 2003320253 A JP2003320253 A JP 2003320253A JP 2005083179 A JP2005083179 A JP 2005083179A
Authority
JP
Japan
Prior art keywords
main frame
main
steel pile
frames
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003320253A
Other languages
Japanese (ja)
Other versions
JP4109594B2 (en
Inventor
Shozo Iwai
省三 岩井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hanshin Kensetsu Co Ltd
Original Assignee
Hanshin Kensetsu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hanshin Kensetsu Co Ltd filed Critical Hanshin Kensetsu Co Ltd
Priority to JP2003320253A priority Critical patent/JP4109594B2/en
Publication of JP2005083179A publication Critical patent/JP2005083179A/en
Application granted granted Critical
Publication of JP4109594B2 publication Critical patent/JP4109594B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a main beam and a frame for constructing a temporary pier in a short term, and a construction method for a temporary pier using them. <P>SOLUTION: First, a plurality of frames are manufactured at a factory and transported to a construction site by, for instance, a truck. At the work site, the plurality of frames is combined into a plurality of main frames 7. At their installation site, these main frames 7 are overhung and erected, then steel piles 3 are driven into the sea bottom where these frames are installed, and then the main frames 7 and steel piles 3 are fixed. This process is repeated to construct a temporary pier. This work method can simplify work at the upper pier structure and omit the work of measurements, etc. at the lower structure. So, a large reduction in construction period becomes possible. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

この発明は、主桁およびフレームとそれらを用いた仮設桟橋の施工方法に関する。   The present invention relates to a main girder and a frame and a construction method of a temporary pier using them.

従来から、渓谷や河川等において様々な仮設桟橋が利用されている。たとえば、渓谷や河川の対岸で工事を行う場合等に一時的に橋が必要となるからである。この場合、まず、仮設桟橋が構築され、この仮設桟橋を利用して工事が行われることとなる。急な傾斜や水中での構築作業は困難を伴うが、仮設桟橋が構築されない限り工事を行うことはできないので、仮設桟橋は短期間で構築されることが望まれている。しかし、その一方で、仮設桟橋は当然に、橋としての安全性は確保されなければならない。よって、仮設桟橋は、一定の範囲内で強固に据え付けられ、かつ、短期間で構築されなければならないといえる。   Conventionally, various temporary piers are used in valleys and rivers. This is because, for example, a bridge is required temporarily when construction is performed on the opposite bank of a valley or river. In this case, a temporary pier is first constructed, and construction is performed using the temporary pier. Although steep inclines and underwater construction work are difficult, construction work cannot be performed unless a temporary pier is constructed, so it is desired that the temporary pier be constructed in a short period of time. However, on the other hand, the safety of the temporary pier must be secured as a matter of course. Therefore, it can be said that the temporary pier must be firmly installed within a certain range and constructed in a short period of time.

そこで、現在、たとえば特許文献1のように、仮設桟橋の一部をパネル化しておき、現場において組立て作業を行う技術が提案されている。
特開平10−46523号公報
Therefore, as in Patent Document 1, for example, a technique has been proposed in which a part of the temporary jetty is panelized and the assembly work is performed on site.
Japanese Patent Laid-Open No. 10-46523

しかしながら、上記従来技術では、仮設桟橋に用いられる基礎杭を設置底面深くまで打込む施工方法であり、基礎杭を設置底面深くに打込むための機械と時間が必要となるため手間がかかるといった問題がある。また、パネルを基礎杭から延びるワイヤーによって保持しながら施行するため、パネルをワイヤーで保持するための作業が必要となり、手間がかかるといった問題もある。   However, in the above prior art, it is a construction method for driving the foundation pile used for the temporary pier deep into the installation bottom, and it takes time and effort because it requires a machine and time to drive the foundation pile deep into the installation bottom. There is. Moreover, since it enforces, hold | maintaining a panel with the wire extended from a foundation pile, the operation | work for holding a panel with a wire is needed, and there also exists a problem that it takes an effort.

この発明は、かかる技術背景のもとになされたものであり、極めて短期間での仮設桟橋の構築を可能とする主桁およびフレームとそれらを用いた仮設桟橋の施工方法を提供することを目的とする。   The present invention has been made based on such a technical background, and an object thereof is to provide a main girder and a frame capable of constructing a temporary pier in an extremely short period of time, and a method of constructing a temporary pier using them. And

上記目的を達成するための請求項1記載の発明は、一対の溝形鋼(11)が所定の間隔で配置されて橋の長さ方向に延びる主桁(1)であって、上記一対の溝形鋼は、その長さ方向に所定間隔ごとに鋼杭固定装置(12,13,14)が備えられており、上記鋼杭固定装置は、上記一対の溝形鋼が一定の間隔を保つように仮保持するとともに、後に鋼杭を挿入することができる空間(14)を区画していることを特徴とする主桁である。   In order to achieve the above object, the invention according to claim 1 is a main girder (1) in which a pair of channel steel (11) is arranged at a predetermined interval and extends in the length direction of the bridge, The grooved steel is provided with steel pile fixing devices (12, 13, 14) at predetermined intervals in the length direction, and the pair of grooved steels keeps a constant interval in the steel pile fixing device. The main girder is characterized by partitioning a space (14) into which a steel pile can be inserted later while being temporarily held.

なお、括弧内の英数字は、後述の実施形態における対応構成要素などを表す。以下、この項において同じ。
この発明によれば、主桁は、鋼杭固定装置を有するので、一対の溝形鋼の間隔を所定に保ちつつ、鋼杭が挿入され得る空間を区画することができる。よって、主桁を製作することが鋼杭固定装置の製作を兼ねることになるので、効率的な主桁であるといえる。
The alphanumeric characters in parentheses indicate corresponding components in the embodiments described later. The same applies hereinafter.
According to this invention, since the main girder has the steel pile fixing device, it is possible to partition the space in which the steel pile can be inserted while maintaining a predetermined distance between the pair of channel steels. Therefore, it can be said that the main girder is an efficient main girder because it also serves to manufacture the steel pile fixing device.

なお、鋼杭固定装置は、たとえば、一対の溝形鋼の間に一対の区画部材を挟み、取り外し可能なスペーサーを介してボルトとナットで仮締めすることで形成されている。
これにより、鋼杭の断面積よりもわずかにスペーサーの分だけ大きな空間を区画することができる。また、その空間に鋼杭を挿入した後、ボルトとナットの仮締めを緩めてスペーサーを取り外し、さらに、ボルトとナットで本締めすることで、鋼杭と主桁とを固定することができる。
The steel pile fixing device is formed, for example, by sandwiching a pair of partition members between a pair of channel steels and temporarily fastening them with bolts and nuts via a removable spacer.
Thereby, a space slightly larger than the cross-sectional area of the steel pile can be defined by the spacer. Moreover, after inserting a steel pile into the space, the bolt and nut can be temporarily tightened to remove the spacer, and further tightened with the bolt and nut to fix the steel pile and the main girder.

請求項2記載の発明は、橋の幅方向に延びる所定長さの横桁(2)が、請求項1記載の主桁(1)の長さ方向に直交する方向に突出するように、主桁の左右両側または左右片側に所定数備えられたことを特徴とするフレーム(4,5,6)である。
この発明によれば、フレームは、主桁の左右両側または左右片側に所定数の横桁を備えているので、そのフレームを組み合わせることで、容易に所望の大きさのフレームを作成することができる。
The invention according to claim 2 is characterized in that the main beam (2) having a predetermined length extending in the width direction of the bridge protrudes in a direction perpendicular to the length direction of the main beam (1) according to claim 1. It is a frame (4, 5, 6) characterized in that a predetermined number is provided on the left and right sides or the left and right sides of the beam.
According to the present invention, the frame is provided with a predetermined number of horizontal girders on both the left and right sides or the left and right sides of the main girder, so that a frame having a desired size can be easily created by combining the frames. .

請求項3記載の発明は、仮設桟橋の施工方法であって、請求項2記載のフレーム(4,5,6)を工場で複数製作する工程と、現場において、上記製作された複数のフレームの横桁(2)同士を組み合わせて第1および第2のメインフレーム(7)を製作する工程と、目的の設置場所で、第1のメインフレームを所定の高さで水平に固定する工程と、第2のメインフレームの後端と上記固定された第1のメインフレームの先端とを連結する工程と、上記第2のメインフレームの複数の鋼杭固定装置(12,13,14)の空間(14)にそれぞれ鋼杭(3)を挿入し、各鋼杭を設置底面に打込む工程と、各鋼杭と第2のメインフレームとを固定する工程と、を含み、上記各鋼杭と第2のメインフレームとを固定する工程の後は、上記第2のメインフレームと同様の手順で複数のメインフレームを順次固定していくことを特徴とする仮設桟橋の施工方法である。   The invention described in claim 3 is a method for constructing a temporary pier, wherein a plurality of frames (4, 5, 6) according to claim 2 are manufactured in a factory, and the plurality of manufactured frames are on-site. A step of manufacturing the first and second main frames (7) by combining the cross beams (2), and a step of fixing the first main frame horizontally at a predetermined height at a target installation location; A step of connecting the rear end of the second main frame and the front end of the fixed first main frame, and a space of the plurality of steel pile fixing devices (12, 13, 14) of the second main frame ( 14) including inserting each steel pile (3) and driving each steel pile into the installation bottom, and fixing each steel pile and the second main frame, After the step of fixing the second main frame, the second method is performed. A method of constructing the temporary pier, characterized by successively fixing a plurality of mainframe down frame and the same procedure.

この発明によれば、フレームは工場で製作し、現場においてフレームを組み合わせてメインフレームを製作する。よって、効率的にメインフレームを製作することができる。また、メインフレームが設置された後に、メインフレームに形成された空間に鋼杭が挿入され、鋼杭とメインフレームとが固定される。よって、鋼杭は、メインフレームに形成された空間に挿入されることで打込み場所が定められるので、鋼杭の打込み場所を予め測量等を行って詳細に定めておく必要がなく、施工時間の短縮を図ることができる。   According to the present invention, the frame is manufactured at the factory, and the main frame is manufactured by combining the frames at the site. Therefore, the main frame can be manufactured efficiently. Further, after the main frame is installed, the steel pile is inserted into the space formed in the main frame, and the steel pile and the main frame are fixed. Therefore, because the steel pile is inserted into the space formed in the main frame, the driving place is determined, so it is not necessary to measure the driving position of the steel pile in advance to determine in detail, the construction time Shortening can be achieved.

なお、第1のメインフレームを固定する工程では、たとえば、仮受け台や仮柱を用いて所定の高さで水平に固定される。
請求項4記載の発明は、上記第2のメインフレーム(7)は、その後端が第1のメインフレーム(7)の先端に連結されて片持ち状態に張り出し架設されることを特徴とする請求項3記載の仮設桟橋の施工方法である。
In the step of fixing the first main frame, for example, the first main frame is fixed horizontally at a predetermined height using a temporary cradle or a temporary pillar.
The invention according to claim 4 is characterized in that the rear end of the second main frame (7) is connected to the front end of the first main frame (7) so as to extend in a cantilever state. It is the construction method of the temporary pier of claim | item 3.

この発明によれば、メインフレームは片持ち状態に張り出し架設されるので、メインフレームをワイヤー等で保持するといった作業が不要となり、施工時間を飛躍的に短縮することができる。
請求項5記載の発明は、上記各鋼杭(3)を設置底面に打込む工程は、各鋼杭が地盤の支持層に達すると打込みを終了することを特徴とする請求項3または4記載の仮設桟橋の施工方法である。
According to the present invention, since the main frame is extended and installed in a cantilever state, the work of holding the main frame with a wire or the like is not necessary, and the construction time can be dramatically shortened.
The invention according to claim 5 is characterized in that the step of driving each steel pile (3) into the installation bottom surface ends the driving when each steel pile reaches the support layer of the ground. This is a temporary pier construction method.

この発明によれば、各鋼杭の設置底面への打込みは地盤の支持層に達すると終了するので、掘削機等の機械を必要とせず、各鋼杭の設置底面への打込みを極めて短時間で行うことができる。また、掘削機等で地盤を掘る必要がないので地盤の硬さに影響されない。   According to the present invention, since the driving of each steel pile to the installation bottom surface is completed when the ground reaches the support layer of the ground, a machine such as an excavator is not required, and the driving of each steel pile to the installation bottom surface is extremely short. Can be done. Further, since it is not necessary to dig the ground with an excavator or the like, it is not affected by the hardness of the ground.

以下では、この発明の実施の形態を、添付図面を参照して詳細に説明する。
図1は、主桁1および横桁2を示した斜視図である。主桁1および横桁2は仮設桟橋の骨組みを担うものである。主桁1は、所定方向に延びる一対の溝形鋼11を備えている。溝形鋼11は、所定方向に延びる主面111と、主面111の幅方向の両側の端辺から主面111に直交する方向に突出する一対のフランジ112とで構成される断面略コ字形の鋼材である。それぞれの溝形鋼11は、互いのフランジ112が外側に突出するように主面111を対向させられて並列させられている。また、並列させられた一対の溝形鋼11の間には、一対の断面略コ字形の区画部材12が箱形空間14を区画するように主桁1の長さ方向に所定間隔離されて備えられている。さらに、一方の溝形鋼11と区画部材12との間にスペーサー13が挟まれ、区画部材12およびスペーサー13を介して双方の溝形鋼11にボルトが挿通させられナットで締め付けられることで主桁1が構成されている。
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a perspective view showing a main beam 1 and a horizontal beam 2. The main girder 1 and the horizontal girder 2 bear the framework of the temporary pier. The main girder 1 includes a pair of channel steels 11 extending in a predetermined direction. The grooved steel 11 has a substantially U-shaped cross section including a main surface 111 extending in a predetermined direction and a pair of flanges 112 protruding in a direction orthogonal to the main surface 111 from both side edges of the main surface 111 in the width direction. It is a steel material. Each channel steel 11 is arranged in parallel with the main surface 111 facing each other such that the flanges 112 protrude outward. A pair of substantially U-shaped section members 12 are separated by a predetermined distance in the length direction of the main girder 1 so as to partition the box-shaped space 14 between the pair of channel steels 11 arranged in parallel. Is provided. Further, a spacer 13 is sandwiched between one grooved steel 11 and the partition member 12, and a bolt is inserted into both the grooved steel 11 through the partition member 12 and the spacer 13 and tightened with a nut. Digit 1 is configured.

なお、後述のように、施工前は、主桁1はボルトとナットで仮締めされて構成されており、施工において仮締めを緩めることでスペーサー13が取り外される。箱形空間14は、施工時に、断面略H形の鋼杭3が挿入されるための空間であり、スペーサー13が用いられることで、施工前は、鋼杭3の断面積よりもわずかに大きな断面積を有する空間として保持されている。具体的には、鋼杭3は、幅300ミリ、長さ300ミリの略H形の断面積を有している。また、幅300ミリ、長さ305ミリの断面積を有する箱形空間14が、厚さ4.5ミリのスペーサー13が用いられることで、幅304.5ミリ、長さ305ミリの断面積を有する空間とされている。そして、鋼杭3が挿入された後は、スペーサー13が取り外され、ボルトとナットで本締めされることで主桁1と鋼杭3とが固定される。なお、鋼杭3、スペーサー13、箱形空間14の大きさは、上記のものに限られず種々の変更が可能である。   As will be described later, before construction, the main girder 1 is temporarily tightened with bolts and nuts, and the spacer 13 is removed by loosening the temporary tightening during construction. The box-shaped space 14 is a space for inserting the steel pile 3 having a substantially H-shaped section at the time of construction, and is slightly larger than the cross-sectional area of the steel pile 3 before the construction by using the spacer 13. It is held as a space having a cross-sectional area. Specifically, the steel pile 3 has a substantially H-shaped cross-sectional area having a width of 300 mm and a length of 300 mm. The box-shaped space 14 having a cross-sectional area of 300 mm in width and 305 mm in length has a cross-sectional area of 304.5 mm in width and 305 mm in length by using the spacer 13 having a thickness of 4.5 mm. It is supposed to have a space. And after the steel pile 3 is inserted, the spacer 13 is removed and the main girder 1 and the steel pile 3 are fixed by carrying out final fastening with a volt | bolt and a nut. In addition, the magnitude | size of the steel pile 3, the spacer 13, and the box-shaped space 14 is not restricted to said thing, A various change is possible.

また、溝形鋼11の一方または双方の箱形空間14近辺に(図1においては溝形鋼11の一方)、主桁1の長さ方向と直交する方向に延びる横桁2が備えられている。横桁2は、所定方向に延びる主面21と、主面21の幅方向の両側の端辺に主面21を挟むようにして主面21の端辺から突出する一対のフランジ22とで構成される断面略I字形の鋼材であり、溝形鋼11に溶接されて備えられている。主桁1と横桁2との組み合わせによって、後述のように種々のフレームが製作される。   Further, a cross beam 2 extending in a direction perpendicular to the length direction of the main beam 1 is provided in the vicinity of one or both of the box-shaped spaces 14 of the groove steel 11 (one of the groove steel 11 in FIG. 1). Yes. The cross beam 2 includes a main surface 21 extending in a predetermined direction, and a pair of flanges 22 protruding from the end sides of the main surface 21 so as to sandwich the main surface 21 between both ends of the main surface 21 in the width direction. It is a steel material having a substantially I-shaped cross section and is welded to the grooved steel 11. Depending on the combination of the main beam 1 and the horizontal beam 2, various frames are manufactured as described later.

図2は、フレーム4,5,6を示す概略平面図である。フレーム4,5,6は、主桁1および横桁2を種々に組み合わせて製作される。フレーム4,5,6はそれぞれ一本の主桁1を備えており、ぞれぞれの主桁1の左端付近および中央付近にそれぞれ箱形空間14が形成されている。フレーム4は、それぞれの箱形空間14から手前側に延びるように横桁2を2本備えている。また、フレーム5は、それぞれの箱形空間14から奥側および手前側に延びるように横桁2を4本備えている。さらに、フレーム6は、それぞれの箱形空間14から奥側に延びるように横桁2を2本備えている。フレーム4,5,6は、それぞれ、その長さがおよそ10メートル程度と、幅が2メートル程度とされる。   FIG. 2 is a schematic plan view showing the frames 4, 5, 6. The frames 4, 5, 6 are manufactured by variously combining the main beam 1 and the horizontal beam 2. Each of the frames 4, 5, 6 includes a main girder 1, and a box-shaped space 14 is formed near the left end and the center of each main girder 1. The frame 4 includes two cross beams 2 extending from the respective box-shaped spaces 14 to the front side. Further, the frame 5 includes four cross beams 2 so as to extend from the respective box-shaped spaces 14 to the back side and the front side. Further, the frame 6 includes two cross beams 2 extending from the respective box-shaped spaces 14 to the back side. Each of the frames 4, 5, and 6 has a length of about 10 meters and a width of about 2 meters.

フレーム4,5,6は、通常、工場で製作されるので、上記の大きさとしておくことで、たとえば、トラックによって、工場から現場に搬送することができる。
図3は、メインフレーム7を示す概略図であり、(a)は平面図、(b)は正面図、(c)は側面図である。フレーム4,5,6が奥側から順に並べられ、それぞれの横桁2同士が連結されることでメインフレーム7が製作される。横桁2同士の連結は、上下方向および水平方向から4枚の継ぎ目板8を、連結される横桁2のそれぞれの端部をまたいで覆わせ、さらに、それぞれの継ぎ目板8を介してボルトとナットで横桁2を締め付けることによって行われる。なお、横桁2同士の連結は、横桁2同士が連結されるものであればよい。たとえば、溶接により連結されるものでもよく、その連結方法は上記のものに限られない。また、メインフレーム7は、フレーム4,5,6の組み合わせで種々の変更が可能であり、たとえば、フレーム5を省いたものであってもよいし、フレーム5を2個以上用いたものであってもよい。
Since the frames 4, 5, and 6 are usually manufactured in a factory, the above-described size allows the frames 4, 5, and 6 to be transported from the factory to the site by, for example, a truck.
3A and 3B are schematic views showing the main frame 7, wherein FIG. 3A is a plan view, FIG. 3B is a front view, and FIG. 3C is a side view. Frames 4, 5, and 6 are arranged in order from the back side, and the main frames 7 are manufactured by connecting the cross beams 2 to each other. For the connection between the cross beams 2, the four seam plates 8 from the top and bottom and the horizontal direction are covered across the ends of the cross beams 2 to be connected, and the bolts are connected via the joint plates 8. And tightening the cross beam 2 with a nut. In addition, the connection of the cross beams 2 should just be what connects the cross beams 2 mutually. For example, it may be connected by welding, and the connecting method is not limited to the above. Further, the main frame 7 can be variously changed by combining the frames 4, 5, and 6, for example, the frame 5 may be omitted, or two or more frames 5 may be used. May be.

以下、メインフレーム7を用いた仮設桟橋の施工方法を説明する。
図4は、メインフレーム7を用いた仮設桟橋の施工順序を示す図であり、その順序は(a)→(b)→(c)となる。まず、フレーム4,5,6が工場で複数製作されて、たとえば、トラックで現場に搬送される。さらに、現場において、前述のように、フレーム4,5,6が組み合わされて複数のメインフレーム7が製作される。
Hereinafter, the construction method of the temporary pier using the main frame 7 is demonstrated.
FIG. 4 is a diagram showing the construction order of the temporary pier using the main frame 7, and the order is (a) → (b) → (c). First, a plurality of frames 4, 5, and 6 are manufactured at a factory, and transported to the site by, for example, a truck. Further, as described above, a plurality of main frames 7 are manufactured by combining the frames 4, 5, and 6 at the site.

まず、目的の設置場所のうち、仮設桟橋の後端となる場所に、製作されたメインフレーム7のうち、第1メインフレーム7が、その長さ方向が仮設桟橋の長さ方向となるようにして設置される。第1メインフレーム7の設置は、たとえば、図示しない仮受け台を用いて所定の高さで水平に保持され、後述の第2メインフレーム7と同様に、箱形空間14に、鋼杭3が挿入されて設置底面に打込まれ、さらに、鋼杭3と第1メインフレーム7とが固定されることで行われる。なお、第1メインフレーム7の固定は、第1メインフレーム7が所定の高さで水平に固定されるものであればよく、種々の変更が可能である。たとえば、鋼杭3のかわりに仮柱が用いられて固定されてもよい。   First of all, the first main frame 7 of the manufactured main frames 7 is placed at the rear end of the temporary pier among the target installation locations so that the length direction of the first main frame 7 is the length direction of the temporary pier. Installed. The installation of the first main frame 7 is, for example, held horizontally at a predetermined height using a temporary cradle (not shown), and the steel pile 3 is placed in the box-shaped space 14 in the same manner as the second main frame 7 described later. The steel pile 3 and the first main frame 7 are fixed by being inserted and driven into the installation bottom surface. The first main frame 7 may be fixed as long as the first main frame 7 is fixed horizontally at a predetermined height, and various changes can be made. For example, instead of the steel pile 3, a temporary column may be used and fixed.

つづいて、第2メインフレーム7が、クレーンで吊り上げられ、第2メインフレーム7の後端と既設された第1メインフレーム7の先端とが連結される(図2(a)参照)。連結方法については後述する。第1メインフレーム7に連結された第2メインフレーム7は、その後端のみが連結され、連結された後は、クレーンからはずされ、いわゆる片持ち状態を維持して水平に張り出し架設される。   Subsequently, the second main frame 7 is lifted by a crane, and the rear end of the second main frame 7 is connected to the tip of the existing first main frame 7 (see FIG. 2A). The connection method will be described later. Only the rear end of the second main frame 7 connected to the first main frame 7 is connected. After the connection, the second main frame 7 is removed from the crane, and is stretched horizontally while maintaining a so-called cantilever state.

その後、水平に張り出し架設された第2メインフレーム7の各箱形空間14に、クレーンによって順に断面略H形の鋼杭3が垂直に挿入される。挿入された各鋼杭3は、たとえば、バイブロハンマーによって設置底面に打込まれる(図2(b)参照)。なお、各鋼杭3の設置底面への打込みは、その先端が地盤の支持層に達するまで打込まれるものであればよい。よって、掘削機等の機械を必要としないので、鋼杭3の設置底面への打込みは極めて短時間で行うことができる。また、掘削機等で地盤を掘る必要がないので、地盤が硬い場合であっても容易に設置できる。さらに、鋼杭3は、第2メインフレーム7の箱形空間14に垂直に挿入されることで打込み場所が定められるので、鋼杭3の打込み場所を予め測量等を行って詳細に定めておく必要がなく、施工時間の短縮を図ることができる。   Thereafter, the steel piles 3 having a substantially H-shaped cross section are sequentially inserted vertically into the box-shaped spaces 14 of the second main frame 7 extending horizontally. Each inserted steel pile 3 is driven into the installation bottom by, for example, a vibro hammer (see FIG. 2B). The steel pile 3 may be driven into the installation bottom surface as long as the tip reaches the support layer of the ground. Therefore, since a machine such as an excavator is not required, the steel pile 3 can be driven into the installation bottom surface in a very short time. Further, since it is not necessary to dig the ground with an excavator or the like, it can be easily installed even when the ground is hard. Further, since the steel pile 3 is inserted into the box-shaped space 14 of the second main frame 7 perpendicularly, the driving place is determined, so that the driving position of the steel pile 3 is determined in advance by performing surveying or the like. There is no need, and construction time can be shortened.

設置底面に打込まれた鋼杭3の上端であって、第2メインフレーム7の上方に突出する部分は切断される。全ての鋼杭3の上端が切断された後、第2メインフレーム7の高さが調整される。高さの調整方法については後述する。第2メインフレーム7が位置決めされると、前述のように、主桁1の仮締めが緩められてスペーサー13が取り外され、さらに、ボルトとナットで本締めされて、第2メインフレーム7と各鋼杭3とが固定される。そして、第2メインフレーム7上に覆工板9が敷き並べられる(図2(c)参照)。   A portion of the upper end of the steel pile 3 driven into the installation bottom surface and protruding above the second main frame 7 is cut. After the upper ends of all the steel piles 3 are cut, the height of the second main frame 7 is adjusted. A method for adjusting the height will be described later. When the second main frame 7 is positioned, the temporary tightening of the main girder 1 is loosened and the spacer 13 is removed as described above, and is further tightened with bolts and nuts. The steel pile 3 is fixed. Then, the lining plate 9 is laid on the second main frame 7 (see FIG. 2C).

その後は、第2メインフレーム7と同様の順序で複数のメインフレーム7が順に設置されていく。すなわち、メインフレーム7が水平に張り出し架設された後に、鋼杭3が設置底面に垂直に打込まれ、その後、メインフレーム7と鋼杭3とが固定されるという工程が反復されることで、仮設桟橋が構築されることになる。
図5は、メインフレーム7同士の連結状態を詳しく示す図であり、(a)は平面図、(b)は正面図、(c)は水平方向に切断した断面図である。仮設桟橋の構築は、上記のように、複数のメインフレーム7が順に張り出し架設されることによって行われる。メインフレーム7の張り出し架設は、既設のメインフレーム7の先端に、架設されるメインフレーム7の後端が連結されることによって行われ、より詳しくは、既設のメインフレーム7の各主桁1の先端と、架設されるメインフレーム7の各主桁1の後端とが、仮設桟橋の長さ方向に連接するようにして連結される。
Thereafter, a plurality of main frames 7 are sequentially installed in the same order as the second main frame 7. That is, after the main frame 7 is horizontally extended and installed, the steel pile 3 is driven vertically to the bottom of the installation, and then the process of fixing the main frame 7 and the steel pile 3 is repeated, A temporary pier will be constructed.
5A and 5B are diagrams showing in detail the state of connection between the main frames 7, wherein FIG. 5A is a plan view, FIG. 5B is a front view, and FIG. 5C is a cross-sectional view cut in the horizontal direction. As described above, the construction of the temporary pier is performed by extending a plurality of main frames 7 in order. The overhanging construction of the main frame 7 is performed by connecting the rear end of the main frame 7 to be installed to the front end of the existing main frame 7, and more specifically, each main girder 1 of the existing main frame 7. The front end and the rear end of each main girder 1 of the main frame 7 to be installed are connected so as to be connected in the length direction of the temporary pier.

以下に、具体的な連結方法を、1本の主桁1を例にとって説明する。
まず、既設の主桁1に架設される主桁1が連接される。そして、既設側の各溝形鋼11の主面111と、架設側の各溝形鋼11の主面111とが、水平方向から2枚の継ぎ目板10で挟まれて覆われ、継ぎ目板10を介して各主面111がボルトとナットで締め付けられる。さらに、連接部分が上方向から継ぎ目板15で、下方向から継ぎ目板16で覆われ、継ぎ目板15および16を介して溝形鋼11の上下のフランジ112がそれぞれボルトとナットで締め付けられる。このとき、継ぎ目板15の部分のみが本締めされ、継ぎ目板10および16の部分は溝形鋼11に対してわずかに遊びがもたせられて仮締めされている。また、下側のフランジ112の先端および後端には図示しない半円形の切欠が、継ぎ目板16には図示しない孔が形成されており、この切欠および孔に、下方に向かって緩やかなテーパー形状とされるピン17が嵌入される。これにより、後述のように、張り出し架設された主桁1の水平を保つことが可能となる。
Hereinafter, a specific connection method will be described by taking one main beam 1 as an example.
First, the main girder 1 installed on the existing main girder 1 is connected. And the main surface 111 of each existing channel steel 11 and the main surface 111 of each channel steel 11 on the installation side are sandwiched and covered by the two seam plates 10 from the horizontal direction. Each main surface 111 is tightened with a bolt and a nut via Further, the connecting portion is covered with the joint plate 15 from above and the joint plate 16 from below, and the upper and lower flanges 112 of the channel steel 11 are tightened with bolts and nuts via the joint plates 15 and 16, respectively. At this time, only the portion of the joint plate 15 is finally tightened, and the portions of the joint plates 10 and 16 are temporarily tightened with slight play with respect to the channel steel 11. Further, a semicircular notch (not shown) is formed at the front end and the rear end of the lower flange 112, and a hole (not shown) is formed in the joint plate 16, and the notch and the hole are gradually tapered downward. A pin 17 is inserted. Thereby, as will be described later, it is possible to keep the main girder 1 laid overhanging horizontally.

既設側の全ての主桁1に対して架設側の全ての主桁1の後端が連結されると、メインフレーム7は、その後端の連結のみを支持力として張り出し架設される。張り出し架設されたメインフレーム7は、継ぎ目板10および16が各主桁1に対してわずかに遊びがもたせられて仮締めされているので、連結部分を中心としてわずかに上下に変位し得る。ピン17が下方に押し込まれるように押さえられると、架設側の各主桁1(各溝形鋼11)の下側の各フランジ112に、主桁1の長さ方向に向かう力が加えられる。そして、継ぎ目板15が本締めされているので、各主桁1には、その本締め部分を中心として上方向に向かう回転力が付与され、メインフレーム7全体として上方向に変位し得る。すなわち、張り出し架設されたメインフレーム7に、重力に抗して上方向への力を付与することができるので、張り出し架設時のメインフレーム7の水平を保つことができる。   When the rear ends of all the main girders 1 on the erection side are connected to all the main girders 1 on the existing side, the main frame 7 is stretched and erected with only the connection at the rear end as a supporting force. The overhanging main frame 7 can be slightly displaced up and down around the connecting portion because the joint plates 10 and 16 are temporarily fastened with a slight play with respect to the main girders 1. When the pin 17 is pressed so as to be pushed downward, a force in the length direction of the main girder 1 is applied to each flange 112 on the lower side of each main girder 1 (each grooved steel 11) on the installation side. Since the seam plate 15 is finally tightened, each main girder 1 is given a rotational force directed upward with the main tightening portion as a center, and can be displaced upward as the entire main frame 7. That is, since an upward force can be applied against the main frame 7 that is erected, the main frame 7 can be kept horizontal during the erection.

ピン17によって、メインフレーム7が水平に架設された後、各箱形空間14には、鋼杭3が垂直に挿入される。さらに、鋼杭3は、メインフレーム7の上方に突出する部分が切断されて、杭頭押さえ部材18が備えられる。杭頭押さえ部材18は、断面略コ字形の部材であり、杭頭押さえ部材18から各溝形鋼11の上側のフランジ112にボルトが挿通される。このとき、フランジ112を挟むようにボルトを通して一対のナットが備えられる。この一対のナットが種々に締められることで、ナットを介してフランジ112に上下方向への力が付与される。よって、主桁1(メインフレーム7)全体として上下方向に一定範囲内で変位し得る。これにより、張り出し架設された後、メインフレーム7の高さを調整することができる。   After the main frame 7 is installed horizontally by the pins 17, the steel piles 3 are inserted vertically into the box-shaped spaces 14. Further, the steel pile 3 is provided with a pile head pressing member 18 by cutting a portion protruding above the main frame 7. The pile head holding member 18 is a member having a substantially U-shaped cross section, and a bolt is inserted from the pile head holding member 18 to the upper flange 112 of each channel steel 11. At this time, a pair of nuts are provided through bolts so as to sandwich the flange 112. When the pair of nuts are tightened in various ways, a vertical force is applied to the flange 112 via the nuts. Accordingly, the main girder 1 (main frame 7) as a whole can be displaced within a certain range in the vertical direction. Thereby, after overhanging construction, the height of the main frame 7 can be adjusted.

なお、メインフレーム7は、水平に張り出し架設され、鋼杭3の打込みが終了した後に高さが調整されればよく、それを達成するための構成は上記のものに限らず種々の変更が可能である。
高さが定められたメインフレーム7は、その後、前述のように、鋼杭3と固定される。鋼杭3とメインフレーム7とが固定された後、仮締めされていた継ぎ目板10および16の部分が本締めされる。これにより、メインフレーム7が設置底面に対して固定される。
In addition, the main frame 7 is extended horizontally and it is sufficient that the height is adjusted after the driving of the steel pile 3 is finished. The configuration for achieving the main frame 7 is not limited to the above, and various modifications are possible. It is.
After that, the main frame 7 having a predetermined height is fixed to the steel pile 3 as described above. After the steel pile 3 and the main frame 7 are fixed, the joint plates 10 and 16 that have been temporarily tightened are finally tightened. Thereby, the main frame 7 is fixed to the installation bottom surface.

図6は、仮設桟橋の完成図である。この実施形態では、3個のメインフレーム7が順に固定され、その上部に覆工板9が備えられて、仮設桟橋が構築されている。なお、仮設桟橋には、必要に応じてタイロッドが備えられてもよい。
通常、仮設桟橋の施工は、桁等を設置する上部工と杭等を設置する下部工とに分けられる。この発明では、仮設桟橋の施工は、仮設桟橋の桁がフレーム4,5,6として分割されて工場で製作され、現場で、フレーム4,5,6を組み合わせてメインフレーム7が製作される。そして、複数のメインフレーム7が上記のように順に張り出し架設され、各鋼杭3と固定されることで行われる。すなわち、上部工を行った後に下部工を行うことを反復する施工であり、この発明での上部工は、メインフレーム7を張り出し架設することによって行われるので、上部工の作業を単純なものにすることができる。また、下部工は、張り出し架設されているメインフレーム7の各箱形空間14にそれぞれ鋼杭3を挿入し、各鋼杭3を地盤に打込むことで行われるので、下部工を先行する施工方法と比べると、下部工での測量等の作業を省くことができる。よって、工期の飛躍的な短縮が可能となり、効率的な施行方法であるといえる。また、下部工は、各鋼杭3の設置底面への打ち込みにおいて、掘削機等の地盤を掘削するための機械を必要としないので、機械の搬入が困難な場所であっても仮設桟橋を構築することができる。
FIG. 6 is a completed drawing of the temporary pier. In this embodiment, three main frames 7 are fixed in order, and a cover plate 9 is provided on the upper part to construct a temporary pier. The temporary pier may be provided with a tie rod as necessary.
Usually, the construction of the temporary pier is divided into an upper work for installing girders and a lower work for installing piles and the like. In the present invention, the temporary pier is constructed by dividing the temporary pier girder as frames 4, 5, 6 at the factory, and the main frame 7 is manufactured by combining the frames 4, 5, 6 at the site. Then, a plurality of main frames 7 are overhanging in order as described above and fixed to each steel pile 3. That is, it is a construction that repeats the sub work after the super work, and the super work in the present invention is performed by extending the main frame 7 so that the work of the super work is simplified. can do. In addition, the substructure is carried out by inserting the steel piles 3 into the box-shaped spaces 14 of the overhanging main frame 7 and driving each steel pile 3 into the ground. Compared with the method, it is possible to omit the work such as surveying in the substructure. Therefore, the construction period can be drastically shortened, which can be said to be an efficient enforcement method. In addition, since the substructure does not require a machine for excavating the ground such as an excavator when driving each steel pile 3 into the installation bottom surface, a temporary pier can be constructed even in places where it is difficult to carry in the machine. can do.

この発明は、以上説明した実施形態に限定されるものではなく、請求項記載の範囲内において種々の変更が可能である。   The present invention is not limited to the embodiment described above, and various modifications can be made within the scope of the claims.

主桁および横桁を示した斜視図である。It is the perspective view which showed the main beam and the horizontal beam. フレームを示す概略平面図である。It is a schematic plan view which shows a frame. メインフレームの構成を示す概略図である。It is the schematic which shows the structure of a main frame. メインフレームを用いた仮設桟橋の施工順序を示す図である。It is a figure which shows the construction order of the temporary pier using a main frame. メインフレーム同士の連結状態を詳しく示す図である。It is a figure which shows the connection state of main frames in detail. 仮設桟橋の完成図である。It is a completed drawing of a temporary pier.

符号の説明Explanation of symbols

1 主桁
2 横桁
3 鋼杭
4 フレーム
5 フレーム
6 フレーム
7 メインフレーム
11 溝形鋼
12 区画部材
13 スペーサー
14 箱形空間
1 Main Girder 2 Horizontal Girder 3 Steel Pile 4 Frame 5 Frame 6 Frame 7 Main Frame 11 Groove Steel 12 Partition Member 13 Spacer 14 Box-shaped Space

Claims (5)

一対の溝形鋼が所定の間隔で配置されて橋の長さ方向に延びる主桁であって、
上記一対の溝形鋼は、その長さ方向に所定間隔ごとに鋼杭固定装置が備えられており、
上記鋼杭固定装置は、上記一対の溝形鋼が一定の間隔を保つように仮保持するとともに、後に鋼杭を挿入することができる空間を区画していることを特徴とする主桁。
A pair of channel steel is a main girder arranged at a predetermined interval and extending in the length direction of the bridge,
The pair of channel steels are provided with steel pile fixing devices at predetermined intervals in the length direction,
The main girder characterized in that the steel pile fixing device tentatively holds the pair of channel steels so as to maintain a constant interval and defines a space into which the steel pile can be inserted later.
橋の幅方向に延びる所定長さの横桁が、請求項1記載の主桁の長さ方向に直交する方向に突出するように、主桁の左右両側または左右片側に所定数備えられたことを特徴とするフレーム。   A predetermined number of horizontal girders extending in the width direction of the bridge are provided on the left and right sides or one side of the main girder so as to protrude in a direction perpendicular to the length direction of the main girder according to claim 1. A frame characterized by. 仮設桟橋の施工方法であって、
請求項2記載のフレームを工場で複数製作する工程と、
現場において、上記製作された複数のフレームの横桁同士を組み合わせて第1および第2のメインフレームを製作する工程と、
目的の設置場所で、第1のメインフレームを所定の高さで水平に固定する工程と、
第2のメインフレームの後端と上記固定された第1のメインフレームの先端とを連結する工程と、
上記第2のメインフレームの複数の鋼杭固定装置の空間にそれぞれ鋼杭を挿入し、各鋼杭を設置底面に打込む工程と、
各鋼杭と第2のメインフレームとを固定する工程と、を含み、
上記各鋼杭と第2のメインフレームとを固定する工程の後は、上記第2のメインフレームと同様の手順で複数のメインフレームを順次固定していくことを特徴とする仮設桟橋の施工方法。
A temporary pier construction method,
Producing a plurality of frames according to claim 2 in a factory;
A step of producing first and second main frames by combining the cross beams of the plurality of produced frames at the site;
Fixing the first main frame horizontally at a predetermined height at a desired installation location;
Connecting the rear end of the second main frame and the front end of the fixed first main frame;
Inserting steel piles into the spaces of the plurality of steel pile fixing devices of the second main frame, and driving each steel pile into the installation bottom;
Fixing each steel pile and the second main frame,
After the step of fixing the steel piles and the second main frame, a temporary pier construction method characterized by sequentially fixing a plurality of main frames in the same procedure as the second main frame. .
上記第2のメインフレームは、その後端が第1のメインフレームの先端に連結されて片持ち状態に張り出し架設されることを特徴とする請求項3記載の仮設桟橋の施工方法。   4. The construction method for a temporary pier according to claim 3, wherein the second main frame has a rear end connected to a front end of the first main frame and is stretched in a cantilever state. 上記各鋼杭を設置底面に打込む工程は、各鋼杭が地盤の支持層に達すると打込みを終了することを特徴とする請求項3または4記載の仮設桟橋の施工方法。   The method of constructing a temporary pier according to claim 3 or 4, wherein the step of driving each steel pile to the installation bottom surface ends the driving when each steel pile reaches the support layer of the ground.
JP2003320253A 2003-09-11 2003-09-11 Main girder and frame and construction method of temporary pier using them Expired - Fee Related JP4109594B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003320253A JP4109594B2 (en) 2003-09-11 2003-09-11 Main girder and frame and construction method of temporary pier using them

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003320253A JP4109594B2 (en) 2003-09-11 2003-09-11 Main girder and frame and construction method of temporary pier using them

Publications (2)

Publication Number Publication Date
JP2005083179A true JP2005083179A (en) 2005-03-31
JP4109594B2 JP4109594B2 (en) 2008-07-02

Family

ID=34418948

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003320253A Expired - Fee Related JP4109594B2 (en) 2003-09-11 2003-09-11 Main girder and frame and construction method of temporary pier using them

Country Status (1)

Country Link
JP (1) JP4109594B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007247359A (en) * 2006-03-20 2007-09-27 Fudo Tetra Corp Temporary scaffold for waterside work
CN102733306A (en) * 2012-02-14 2012-10-17 四川川交路桥有限责任公司 Construction method for prefabricating and installing straining beam of water pier of bridge in reservoir area
CN102877414A (en) * 2012-09-28 2013-01-16 中铁四局集团第一工程有限公司 Universal triangular basket and bracket mounting structure and construction method thereof
CN102995562A (en) * 2012-09-10 2013-03-27 中铁十六局集团第五工程有限公司 High-accuracy control method of construction of large temporary steel structure slideway platform of steel truss girder
JP2016199929A (en) * 2015-04-10 2016-12-01 株式会社横山基礎工事 Bridge construction method and column body and guide means used in the same
CN109024236A (en) * 2018-08-24 2018-12-18 中国建筑局(集团)有限公司 Steel trestle and construction method thereof
CN109468938A (en) * 2019-01-11 2019-03-15 湖南金海钢结构有限公司 A kind of assembled large span circular ring shape steel structure footbridge and its installation method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007247359A (en) * 2006-03-20 2007-09-27 Fudo Tetra Corp Temporary scaffold for waterside work
CN102733306A (en) * 2012-02-14 2012-10-17 四川川交路桥有限责任公司 Construction method for prefabricating and installing straining beam of water pier of bridge in reservoir area
CN102995562A (en) * 2012-09-10 2013-03-27 中铁十六局集团第五工程有限公司 High-accuracy control method of construction of large temporary steel structure slideway platform of steel truss girder
CN102877414A (en) * 2012-09-28 2013-01-16 中铁四局集团第一工程有限公司 Universal triangular basket and bracket mounting structure and construction method thereof
CN102877414B (en) * 2012-09-28 2015-02-18 中铁四局集团第一工程有限公司 Universal triangular basket and bracket mounting structure and construction method thereof
JP2016199929A (en) * 2015-04-10 2016-12-01 株式会社横山基礎工事 Bridge construction method and column body and guide means used in the same
CN109024236A (en) * 2018-08-24 2018-12-18 中国建筑局(集团)有限公司 Steel trestle and construction method thereof
CN109468938A (en) * 2019-01-11 2019-03-15 湖南金海钢结构有限公司 A kind of assembled large span circular ring shape steel structure footbridge and its installation method

Also Published As

Publication number Publication date
JP4109594B2 (en) 2008-07-02

Similar Documents

Publication Publication Date Title
JP2008014083A (en) Construction method of pier
JP4109594B2 (en) Main girder and frame and construction method of temporary pier using them
JP2016528406A (en) Beam connection structure of temporary retaining works for earth retaining
KR101428540B1 (en) Soundproof walls basis structure
JP3850785B2 (en) Caisson laying method using main foundation pile
JP6266246B2 (en) Steel column and footing joint structure and construction method
JP5951375B2 (en) Steel tower reinforcement structure
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP4362824B2 (en) Reverse strike method
JP2007247225A (en) Continuous girder structure formed of a plurality of simple girder bridges, and construction method
JP2006183286A (en) Connection structure of corrugated steel web for corrugated steel web u-shaped component bridge
JPH05179647A (en) Supporting structure for earth retaining wall
JPS63280153A (en) Underground inverted lining method
JP2933582B1 (en) Bridge pier reinforcement method
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
KR102550128B1 (en) Demolition and new construction method of underground retaining wall using H-beam technology to which tensile stress is applied
JP2900840B2 (en) How to build underground structures
JP2020076277A (en) Method for constructing earth retaining wall
JP2757209B2 (en) Cut-and-joint underground construction method using synthetic steel beams
JP2516118B2 (en) Concrete block for offshore construction
KR102503595B1 (en) Energy reduction underground retaining wall demolition method
JP5461627B2 (en) Steel tower reinforcement method
JP7032737B2 (en) How to install FC plate fixing member and box structure
JP3457440B2 (en) Building construction method using earth anchor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060522

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080108

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080307

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080401

A61 First payment of annual fees (during grant procedure)

Effective date: 20080404

Free format text: JAPANESE INTERMEDIATE CODE: A61

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110411

Year of fee payment: 3

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees