JP2005076330A - Connection structure of pile and post - Google Patents

Connection structure of pile and post Download PDF

Info

Publication number
JP2005076330A
JP2005076330A JP2003309457A JP2003309457A JP2005076330A JP 2005076330 A JP2005076330 A JP 2005076330A JP 2003309457 A JP2003309457 A JP 2003309457A JP 2003309457 A JP2003309457 A JP 2003309457A JP 2005076330 A JP2005076330 A JP 2005076330A
Authority
JP
Japan
Prior art keywords
pile
column
steel pipe
reinforcing bar
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003309457A
Other languages
Japanese (ja)
Other versions
JP4130393B2 (en
Inventor
Sumio Yanagihara
純夫 柳原
Hiroyoshi Mukai
広吉 向
Hidenobu Shiki
秀信 志岐
Masashige Kashiki
正成 樫木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2003309457A priority Critical patent/JP4130393B2/en
Publication of JP2005076330A publication Critical patent/JP2005076330A/en
Application granted granted Critical
Publication of JP4130393B2 publication Critical patent/JP4130393B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide the connection structure of a pile and a post reducing a bending moment in the connecting section of the pile and the post while easily arranging bars accurately without a congestion in the connection structure of the reinforced concrete-constructed pile and post. <P>SOLUTION: In the reinforced concrete-constructed pile 1 and the post 2, upper and lower sections are connected by steel pipes 3 buried and fixed in the concrete of the pile 1 and the post 2 while the end sections of footing beams 8 are connected at the central sections of the steel pipes 3. The connecting section of the pile 1 and the post 2 is constituted so that the upper end of the bar 1a for the pile 1 and the lower end of the bar 2a for the post 2 are separated without a connection, and the connecting section of the pile 1 and the post 2 is formed on a connecting section 9 connected by a short-pipe section at the central section of the steel pipe 3. The connecting section of the pile 1 and the post 2 is further constituted so that the bending moment on the pile-head section side in the case of the occurrence of an earthquake is reduced by the ductility of the short-pipe section of the steel pipe 3 while the bar arrangement works of the pile 1 and the post 2 are conducted easily and accurately. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明はコンクリート構造物における鉄筋コンクリート造の杭と柱との接続構造に関するものである。   The present invention relates to a connection structure between a reinforced concrete pile and a column in a concrete structure.

コンクリート構造物における基礎としての杭は、常態においては鉛直方向に作用しているコンクリート構造物の荷重を支持しているものであるが、地震発生時には、該杭に上記鉛直力以外に水平力も作用して杭とこの杭上に立設している柱との接合部に大きな曲げモーメントが発生することになる。このため、従来から杭頭部にフーチングを設けてこのフーチングを介して場所打ち鉄筋コンクリート造りの杭と基礎梁とを連結していると共に柱の下端部を基礎梁を貫通した状態でフーチングに連結した耐力構造としているが、このような杭と柱との接続構造では杭と柱との接合部が剛直化して上記曲げモーメントを低減させることができず、その上、配筋量が増大して配筋作業が煩雑化するという問題点がある。   A pile as a foundation in a concrete structure normally supports the load of the concrete structure acting in the vertical direction, but when an earthquake occurs, a horizontal force acts on the pile in addition to the vertical force. As a result, a large bending moment is generated at the joint between the pile and the column standing on the pile. For this reason, a footing is conventionally provided on the pile head, and the cast-in-place reinforced concrete pile and the foundation beam are connected via this footing, and the bottom end of the column is connected to the footing while penetrating the foundation beam. Although it has a load bearing structure, in such a connection structure between a pile and a column, the joint between the pile and the column becomes stiff and the bending moment cannot be reduced. There is a problem that the line work becomes complicated.

一方、上記コンクリート構造物における杭と柱との接合部に発生する曲げモーメントを低減させるために、その接続構造をピン結合に近い柔構造とすることが行われている。即ち、場所打ちコンクリート杭の上端面から構造物の下面(基礎梁)を上方に離間した状態にしてこの構造物の鉄骨鉄筋コンクリート柱における柱鉄骨の下部を杭頭部のコンクリート中に埋設させて杭頭部の上端面と構造体の下面とを該柱鉄骨で連結した構造とすることにより、杭頭部と構造体間の隙間に存在する柱鉄骨の短い長さ部分で曲げモーメントを低下させるように構成している(例えば、特許文献1参照)。   On the other hand, in order to reduce the bending moment generated at the joint between the pile and the column in the concrete structure, the connection structure is made a flexible structure close to pin coupling. That is, with the bottom surface of the structure (foundation beam) spaced apart upward from the upper end surface of the cast-in-place concrete pile, the lower part of the column steel frame in the steel reinforced concrete column of this structure is buried in the pile head concrete. By using a structure in which the upper end surface of the head and the lower surface of the structure are connected by the column steel, the bending moment is reduced at the short length of the column steel existing in the gap between the pile head and the structure. (For example, refer to Patent Document 1).

特開2000−144904号公報(第3〜5頁、第1図)。JP 2000-144904 A (pages 3 to 5, FIG. 1).

しかしながら、上記杭と柱との接続構造によれば、柱鉄骨の下部を杭頭部のコンクリート中に埋設させるものであるから、柱が杭よりも常に小径又は細いコンクリート構造物にしか適用することができず、その上、柱鉄骨を囲繞している柱の鉄筋も柱鉄骨と共に杭頭部のコンクリート内に埋設されているために、この鉄筋の存在によって杭と柱との接合部の剛性が依然として高くなり、曲げモーメントの低減効果が小さいという問題点がある。   However, according to the connection structure between the pile and the column, the lower part of the column steel frame is buried in the concrete of the pile head, so that the column is always applied only to a concrete structure having a smaller diameter or thinner than the pile. In addition, the reinforcement of the column surrounding the column steel is also embedded in the concrete of the pile head together with the column steel, so the presence of this reinforcement increases the rigidity of the joint between the pile and the column. There is a problem that it still becomes high and the effect of reducing the bending moment is small.

また、柱の鉄筋下部と杭頭部の鉄筋との接合箇所での配筋作業が困難であり、特に、杭が円柱形状で柱が角柱形状である場合、円形状に配筋された杭鉄筋と矩形状に配筋された柱鉄筋との接合箇所では、基礎梁鉄筋が交差して配筋され、鉄筋が非常に輻輳しているために、その配筋作業に著しい手間を要するばかりでなく正確に配筋することが難しく、さらに、配筋後のコンリートの打設作業に困難を伴うといった問題点があった。   In addition, it is difficult to place the bar at the joint between the lower part of the column reinforcement and the reinforcement at the head of the pile. Especially when the pile is cylindrical and the column is prismatic, the pile reinforcement is arranged in a circular shape. At the joint between the reinforcing bar and the column reinforcement arranged in a rectangular shape, the foundation beam reinforcement is crossed and the reinforcement is very congested. There is a problem that it is difficult to arrange the bars accurately, and further, the placement work of the concrete after the bar arrangement is difficult.

本発明は上記のような問題点に鑑みてなされたもので、その目的とするところは、杭によってコンクリート構造物の柱を確実に支持させた上で杭と柱との接続部分の曲げモーメントをできる限り小さくすると共に杭と柱とが略同径或いは同じ太さであっても、さらには、杭が円柱形状で柱が角柱形状であっても配筋作業が能率よく正確に行うことができる杭と柱の接続構造を提供するにある。   The present invention has been made in view of the above problems, and the object of the present invention is to reliably support the column of the concrete structure by the pile and then to determine the bending moment of the connecting portion between the pile and the column. Even if the pile and the column are approximately the same diameter or the same thickness as much as possible, and even if the pile is a columnar shape and the column is a prismatic shape, the bar arrangement work can be performed efficiently and accurately. It is in providing the connection structure of a pile and a pillar.

上記目的を達成するために、本発明の杭と柱の接続構造は、請求項1に記載したように、鉄筋コンクリート造の杭と鉄筋コンクリート造の柱とをこれらの杭や柱よりも細い一定長さの鋼管によって一体に接続してなる杭と柱の接続構造であって、上記杭の上端面と柱の下端面との接続部分に上記鋼管の長さ方向の中央部を配した状態でこの鋼管の上部と下部とをそれぞれ上記鉄筋コンクリート造の柱の上端部の横断面中央と杭の下端部の横断面中央とのコンクリート内に埋設状態で固着していると共に、この鋼管を囲繞している上記柱の鉄筋の下端と杭の鉄筋の上端とを連結することなく離間させた構造としている。   In order to achieve the above object, the connection structure of a pile and a column according to the present invention includes a reinforced concrete pile and a reinforced concrete column having a certain length that is narrower than these piles and columns. A pile-column connection structure that is integrally connected by a steel pipe of the above-mentioned steel pipe with a central portion in the length direction of the steel pipe arranged at the connection portion between the upper end surface of the pile and the lower end surface of the column. The upper part and the lower part of the reinforced concrete column are fixed in an embedded state in the concrete at the center of the cross section of the upper end of the reinforced concrete column and the center of the cross section of the lower end of the pile, respectively, and surround the steel pipe. The lower end of the column reinforcing bar and the upper end of the pile reinforcing bar are separated from each other without being connected.

上記請求項1に記載の杭と柱の接続構造において、請求項2に係る発明は、鋼管の長さ方向の中央部側面に下側の梁筋取付用突片が取付けられていると共に中央部より上方の側面に上側の梁筋取付用突片が取付けられてあり、上側の突片に鋼管の上部を囲繞している柱の鉄筋の下端部を挿通させた孔が設けられていると共に、柱の下端部からこの孔を通じて下方に垂下している上記鉄筋の下端を下側の突片上面に受止させてあり、さらに、この下側の突片下面と杭の鉄筋上端面とを連結することなく離間させた構造を有している。   In the connection structure between a pile and a column according to claim 1, the invention according to claim 2 is characterized in that a lower beam reinforcement projecting piece is attached to the side surface of the central part in the length direction of the steel pipe and the central part. The upper beam reinforcement projecting piece is attached to the upper side surface, and the upper projecting piece is provided with a hole through which the lower end of the reinforcing bar of the column surrounding the upper part of the steel pipe is inserted, The lower end of the above-mentioned reinforcing bar hanging down from the lower end of the column through this hole is received by the upper surface of the lower projecting piece, and the lower surface of the lower projecting piece is connected to the upper end surface of the reinforcing bar of the pile. It has a structure that is separated without any.

また、請求項3に係る発明は、上記上側突片に設けられている鉄筋挿通用の孔を、突片の突出端面側に開口している切欠孔に形成していることを特徴とする。   The invention according to claim 3 is characterized in that the reinforcing bar insertion hole provided in the upper protruding piece is formed in a cutout hole opened on the protruding end face side of the protruding piece.

さらに、請求項4に係る発明は、上記鋼管の上下部における柱と杭とに対する挿入、配設長さを等しくしていると共に杭への挿入長さを、地震等による水平力が作用した時に杭からの引抜力に抵抗し得る長さに形成していることを特徴とする。   Further, in the invention according to claim 4, when the horizontal length due to an earthquake or the like is applied, the insertion length to the columns and piles in the upper and lower portions of the steel pipe is equalized and the arrangement length is equalized. It is formed in the length which can resist the pulling-out force from a pile.

請求項5に係る発明は、上記杭が円柱形状で柱が角柱形状であることを特徴とする。   The invention according to claim 5 is characterized in that the pile is cylindrical and the column is prismatic.

請求項1に係る発明によれば、鉄筋コンクリート造の杭の上端部と、この杭に支持されている鉄筋コンクリート造の柱の下端部とは、これらの杭や柱よりも小径又は細い鋼管の上部を柱の下端部のコンクリート内に埋設状態で固着させると共に下部を杭頭部のコンクリート内に埋設状態で固着することにより接続してなるものであるから、この鋼管を介して杭上に柱を強固に接続、支持させた杭と柱との接続構造を構成することができると共に、この鋼管を囲繞している柱の鉄筋の下端と杭の鉄筋の上端とを離間させた状態にして、これらの杭と柱との接続部には杭頭部の上端面から突出している鋼管の中央一定長さ部分のみが存在し、その周囲には杭頭部と柱の下端部間を接続する配筋が存在しない接続構造としているので、この接続部分が靱性を有する柔構造となって地震発生時に該接続部に作用する曲げモーメントを低減させることができると共に配筋量を減少させることができ、配筋等の作業が能率よく行える。   According to the invention which concerns on Claim 1, the upper end part of a reinforced concrete structure pile and the lower end part of the reinforced concrete structure column supported by this pile are the upper part of a steel pipe smaller in diameter or thinner than these piles and a pillar. Since the lower part of the column is fixed in the embedded state in the concrete and the lower part is fixed in the embedded state of the pile head in the embedded state, the column is firmly fixed on the pile via this steel pipe. It is possible to construct a connection structure between a pile and a column that is connected to and supported by the pipe, and the lower end of the column reinforcing bar surrounding the steel pipe is separated from the upper end of the pile reinforcing bar. There is only a central part of the steel pipe protruding from the upper end surface of the pile head at the connection between the pile and the column, and there is a reinforcing bar connecting the pile head and the lower end of the column around it. Since this connection structure does not exist, this connection part Becomes soft structure having a toughness can be reduced reinforcement amount it is possible to reduce the bending moment acting on the connecting portion when the earthquake occurred, perform well working reinforcement and the like efficiency.

上記杭と柱の接続構造において、請求項2に係る発明によれば、柱の下端部と梁とを一体化させている鋼管の長さ方向の中央部側面に下側の梁筋取付用突片が取付けられていると共に中央部より上方の側面に上側の梁筋取付用突片が取付けられているので、これらの上下突片によって鉄筋コンクリート造の梁を造成する際に、その配筋作業が正確な位置に容易に配筋することができ、さらに、上側の突片に鋼管の上部を囲繞している柱の鉄筋の下端部を挿通させた孔が設けられていると共に柱の下端部からこの孔を通じて下方に垂下している上記鉄筋の下端を下側の突片上に受止させているので、鉄筋コンクリート造の柱を造成する際に、その主筋となる配筋作業も水平方向及び上下方向の正確な位置に能率よく行うことができ、柱の主筋下端と杭の主筋上端との離間幅も確実にとることができる。   According to the invention according to claim 2, in the connection structure between the pile and the column, the lower beam reinforcement mounting protrusion is provided on the side surface of the central portion of the steel pipe in which the lower end portion of the column and the beam are integrated. Since the upper beam reinforcement projecting piece is attached to the side surface above the center part with the piece attached, when constructing a reinforced concrete beam with these upper and lower projecting pieces, the reinforcement work is not performed. The bar can be easily arranged at an accurate position, and the upper projecting piece is provided with a hole through which the lower end of the reinforcing bar of the column surrounding the upper part of the steel pipe is inserted and from the lower end of the column Since the lower end of the above-mentioned reinforcing bar hanging down through this hole is received on the lower projecting piece, when constructing a reinforced concrete column, the main reinforcement is also arranged horizontally and vertically. Can be done efficiently in the exact position of the column, under the main bar The separation width between main reinforcement upper end of the pile can also be taken to ensure.

その上、上述したように、柱の鉄筋の下端と杭の鉄筋の上端とは接続することなく離間させているので、柱の鉄筋と杭の鉄筋とは輻輳することなくそれぞれ独立状態で配筋することができるから、特に、杭が円柱形状であって柱が角柱形状に構成する場合にも、上記鋼管として断面四角形状の鋼管を採用し、その矩形枠状に形成した突片に柱の鉄筋を矩形籠状に配筋することによって円形の杭頭上に角柱状の柱を正確に且つ容易に造成することができる。   In addition, as described above, since the lower end of the column reinforcement and the upper end of the pile reinforcement are separated from each other without being connected, the reinforcement of the column reinforcement and the reinforcement of the pile are arranged independently without being congested. In particular, even when the pile has a columnar shape and the column has a prismatic shape, a steel pipe having a quadrangular cross section is adopted as the steel pipe, and the pillar is formed on the projecting piece formed in the rectangular frame shape. By arranging the reinforcing bars in a rectangular basket shape, a prismatic column can be accurately and easily formed on the circular pile head.

さらに、請求項3に係る発明によれば、上記鋼管に周設した上側突片に設けられている鉄筋挿通用の孔を、突片の突出端面に開口している切欠孔に形成しているので、柱の鉄筋の下端部を鋼管の周囲に配筋する際に、上側突片の突出端面側から鉄筋を上記切欠孔内に差し込むことができて、配筋作業が一層、円滑に能率よく行うことができる。   Furthermore, according to the invention which concerns on Claim 3, the hole for reinforcing bar insertion provided in the upper side protrusion piece provided in the periphery of the said steel pipe is formed in the notch hole opened to the protrusion end surface of the protrusion piece. Therefore, when arranging the lower end of the reinforcing bar of the column around the steel pipe, the reinforcing bar can be inserted into the notch hole from the protruding end face side of the upper projecting piece, making the bar arrangement work more smoothly and efficiently. It can be carried out.

また、請求項4に係る発明によれば、鋼管の上下部における柱と杭とに対する挿入、配設長さを等しくしていると共に杭への挿入長さは、地震等による水平力が作用した時に杭からの引抜力に抵抗し得る長さとして、地震発生時に杭と柱との接続部に作用する水平力に対して鋼管の変形量を大きくとることができ、曲げモーメントの一層の低減を図ることができる構造としている。   Moreover, according to the invention which concerns on Claim 4, horizontal force by earthquake etc. acted while the insertion length with respect to the pillar and pile in the upper and lower parts of a steel pipe was made equal, and the arrangement length to a pile was applied. As the length that can sometimes resist the pulling force from the pile, the amount of deformation of the steel pipe can be increased with respect to the horizontal force acting on the connection between the pile and the column when an earthquake occurs, further reducing the bending moment. The structure can be designed.

次に、本発明を実施するための最良の形態について説明すると、高架橋などの場所打ちのコンクリート構造物における鉄筋コンクリート造の杭1と、この杭1上に立設した鉄筋コンクリート造の柱2との接続構造であって、図1に示すように、これらの杭1と柱2とは一定長さを有する鋼管3によって一体に接続した構造を有していると共に、柱2の下端部に梁8を一体に接続させた構造としている。   Next, the best mode for carrying out the present invention will be described. Connection between a reinforced concrete pile 1 in a cast-in-place concrete structure such as a viaduct and a reinforced concrete pillar 2 erected on the pile 1 As shown in FIG. 1, these piles 1 and columns 2 have a structure in which the piles 1 and the columns 2 are integrally connected by a steel pipe 3 having a certain length, and a beam 8 is provided at the lower end of the columns 2. It is a structure that is connected together.

上記杭1と柱2とは、円柱形状であっても角柱形状であってもよいが、本発明の実施の形態においては、杭1は図2に示すように、円柱形状に、柱2はその太さが杭1の径に略等しい角柱形状に形成されている。また、上記鋼管3は杭1の径や柱2の太さよりも細い、即ち、杭1や柱2の断面よりも小断面の横断面矩形状の角管であって、その上部3aを柱2の下端部の横断面中央のコンクリート内に挿入、埋設状態で固着してあり、下部3bを杭頭部における上端部の横断面中央のコンクリート内に挿入、埋設状態で固着していると共に、柱2に挿入している該鋼管3の上部3aの長さと杭1に挿入している該鋼管3の下部3bの長さとを等しくし、且つ地震時に該鋼管3に作用する水平力に対して杭1からの充分な引抜き抵抗を発揮し得る挿入長さにしている。   Although the said pile 1 and the pillar 2 may be a column shape or a prism shape, in the embodiment of the present invention, the pile 1 has a column shape as shown in FIG. The thickness is formed in a prismatic shape substantially equal to the diameter of the pile 1. The steel pipe 3 is a rectangular tube having a rectangular cross section which is thinner than the diameter of the pile 1 and the thickness of the column 2, that is, a smaller cross section than the cross section of the pile 1 and the column 2. The bottom 3b is inserted into the concrete at the center of the cross section at the center of the cross section and fixed in the embedded state, and the lower part 3b is inserted into the concrete at the center of the cross section at the top of the pile head and fixed in the embedded state. The length of the upper part 3a of the steel pipe 3 inserted into the pile 2 is equal to the length of the lower part 3b of the steel pipe 3 inserted into the pile 1, and the pile is applied to the horizontal force acting on the steel pipe 3 during an earthquake. The insertion length can exhibit a sufficient pulling resistance from 1.

さらに、この鋼管3において、柱2の下端部内に埋設している該鋼管3の長さ方向の中央部3cにおける上下端部の四方(前後面と両側面)には、上下方向に一定間隔を存して一対の梁筋取付用突片4、5が周設されている。   Further, in this steel pipe 3, the upper and lower ends of the steel pipe 3 embedded in the lower end portion of the column 2 are spaced at regular intervals in the vertical direction on the four sides (front and rear surfaces and both side surfaces) of the central portion 3c in the longitudinal direction. Thus, a pair of beam reinforcing projections 4 and 5 are provided around.

これらの突片4、5は、鋼管3の四方外周面から水平方向に突設した一定厚みを有する平面矩形状の鋼製板材からなり、上側の各突片4には図2に示すように、上記柱2の周方向(幅方向)に一定間隔毎に並設している縦方向に長い鉄筋2aの下端部を挿通させた孔6を鉄筋2a、2a・・・と同一間隔毎に設けていると共に、柱2の下端部からこれらの各孔6を挿通して下方に垂下している各鉄筋2aの下端は、上記下側の突片5の上面に当接状態で受止されている。   These projecting pieces 4 and 5 are made of a flat rectangular steel plate material having a constant thickness projecting horizontally from the four-side outer peripheral surface of the steel pipe 3, and each upper projecting piece 4 has an upper projecting piece 4 as shown in FIG. , Holes 6 are provided at the same intervals as the reinforcing bars 2a, 2a, etc., through which the lower ends of the longitudinally long reinforcing bars 2a that are arranged in parallel in the circumferential direction (width direction) of the column 2 are arranged at regular intervals. At the same time, the lower ends of the reinforcing bars 2a passing through the holes 6 from the lower end of the column 2 and hanging downward are received in contact with the upper surface of the lower projecting piece 5. Yes.

そして、鋼管3の外周面を囲繞するように配設しているこれらの前後及び両側部の鉄筋列によって断面矩形状の柱2のコンクリート2bの四方外周部に埋設された矩形枠状の主筋を構成している。さらに、各鉄筋2aの下端部は、側面U字状のフック形状に屈曲してなる定着部2cに形成されてあり、この定着部2cは各鉄筋2aを上側突片4の対応する孔6に挿通したのち、鉄筋2aの下端に継手部材7によって連結され、しかるのち、該定着部2cを下側突片5上に受止させている。なお、前後及び両側の上下突片4、5は、鋼管3の周方向に連続した矩形環状板によって形成しておいてもよく、このように形成しておけば、四隅部にも鉄筋2aの挿通用孔を設けておくことができる。   And the rectangular frame-shaped main reinforcement embed | buried under the four-way outer peripheral part of the concrete 2b of the pillar 2 of a rectangular cross section by these reinforcing bar rows of the front and rear sides and both sides which are arrange | positioned so that the outer peripheral surface of the steel pipe 3 may be surrounded It is composed. Further, the lower end of each reinforcing bar 2 a is formed in a fixing portion 2 c that is bent in a side U-shaped hook shape, and this fixing portion 2 c places each reinforcing bar 2 a in a corresponding hole 6 of the upper protruding piece 4. After being inserted, it is connected to the lower end of the reinforcing bar 2a by the joint member 7, and then the fixing portion 2c is received on the lower projecting piece 5. Note that the front and rear and upper and lower upper and lower protrusions 4 and 5 may be formed by a rectangular annular plate that is continuous in the circumferential direction of the steel pipe 3, and if formed in this way, the reinforcing bars 2a are also formed at the four corners. An insertion hole can be provided.

また、上記下側突片5の下面と杭1の上端面との間には、杭1側の鉄筋1aや柱2側の鉄筋2a、及び、梁筋8a' が配設されていなく、杭1の上端と梁8の下面(柱2の下端)とを一体化しているコンクリートによって埋設された鋼管3の中央部における下端の短い長さ部分(以下、短管部3dとする)のみが存在する杭1と柱2との接続部分9が設けられている。なお、この接続部分9における鋼管3の短管部3dの周囲にコンクリートを打設することなく、該短管部3dを露出させておいてもよい。このように、杭1の鉄筋1aの上端部は該杭1のコンクリート1bの上端部内に埋設されてあり、柱2の鉄筋2aの下端は杭1の上端面から上記接続部分9を介して上方に配設されている上記鋼管3の下側突片5上に受止されているので、これらの配筋1a、2aは連結することなく離間している。さらに、地中梁8の上下梁筋8a、8a' もその先端端部を鋼管3の上下突片4、5上に溶接によってそれぞれ一体に固着してあり、下側突片5の下方には梁筋は配設されていない。   Further, between the lower surface of the lower projecting piece 5 and the upper end surface of the pile 1, the reinforcing bar 1a on the pile 1, the reinforcing bar 2a on the column 2 side, and the beam reinforcing member 8a 'are not arranged. There is only a short length portion (hereinafter referred to as a short pipe portion 3d) of the lower end in the central portion of the steel pipe 3 embedded with concrete in which the upper end of 1 and the lower surface of the beam 8 (lower end of the column 2) are integrated. A connecting portion 9 between the pile 1 and the pillar 2 is provided. The short pipe portion 3d may be exposed without placing concrete around the short pipe portion 3d of the steel pipe 3 in the connection portion 9. Thus, the upper end portion of the reinforcing bar 1a of the pile 1 is embedded in the upper end portion of the concrete 1b of the pile 1, and the lower end of the reinforcing bar 2a of the column 2 is located above the upper end surface of the pile 1 via the connecting portion 9 above. The bar arrangements 1a and 2a are separated from each other without being connected to each other. Further, the upper and lower beam bars 8 a and 8 a ′ of the underground beam 8 are also integrally fixed to the upper and lower projecting pieces 4 and 5 of the steel pipe 3 by welding, and below the lower projecting piece 5. There are no beam bars.

従って、鉄筋コンクリート造の杭1の鉄筋1aと鉄筋コンクリート造の柱2の鉄筋2aとは上記鋼管3の短管部3d(接続部分9)を介して上下に離間されていて、互いに交差させたり接続させたりしていないから、特に、配筋が輻輳してその接続作業が困難であった円形状に配設された鉄筋1aを有する円柱形状の杭1と、矩形状に配設された鉄筋2aを有する角柱形状の柱2との施工を極めて簡素化することができると共に精度のよいコンクリート構造物を構築することができる。   Therefore, the reinforcing bar 1a of the reinforced concrete pile 1 and the reinforcing bar 2a of the reinforced concrete column 2 are separated from each other vertically via the short pipe portion 3d (connecting portion 9) of the steel pipe 3, and cross or connect each other. In particular, the column-shaped pile 1 having the reinforcing bars 1a arranged in a circular shape and the reinforcing bars 2a arranged in a rectangular shape were difficult to connect because the bar arrangement was congested. Construction with the prism 2 having a prismatic shape can be greatly simplified and a concrete structure with high accuracy can be constructed.

さらに、柱2の下端部を一体に接続させている地中梁8の下面と杭1の上端面との間には上記接続部分9が設けられていると共に、この接続部分9には杭1と地中梁8とを接続させている上記鋼管3の短管部3dが存在しているので、地震発生時にコンクリート構造物に水平力が作用した場合、杭1や柱2よりも小断面積の鋼管3における杭頭と地中梁8とを連結している杭頭上の上記短管部3dの剛性低減によって杭頭曲げモーメントを小さくすることができるものである。また、杭1の鉄筋1aが地中梁8まで延長、定着していないため、杭頭処理が容易となるばかりでなく、この杭1の鉄筋1aと柱2の鉄筋2aとが離間した状態で別々に配筋されているので、配筋量の減少と共に杭1や柱2、地中梁8の接合部の配筋作業が大幅に改善することができる。   Further, the connecting portion 9 is provided between the lower surface of the underground beam 8 that integrally connects the lower ends of the columns 2 and the upper end surface of the pile 1, and the connecting portion 9 includes the pile 1. Because there is a short pipe part 3d of the steel pipe 3 connecting the steel beam 8 and the underground beam 8, when a horizontal force acts on the concrete structure at the time of the earthquake, the cross-sectional area is smaller than that of the pile 1 and the column 2 In this steel pipe 3, the pile head bending moment can be reduced by reducing the rigidity of the short pipe portion 3d on the pile head connecting the pile head and the underground beam 8. Moreover, since the reinforcing bar 1a of the pile 1 is not extended and settled to the underground beam 8, not only the pile head processing becomes easy, but also the reinforcing bar 1a of the pile 1 and the reinforcing bar 2a of the column 2 are separated. Since the bar arrangement is performed separately, the bar arrangement work of the joint portion of the pile 1, the column 2 and the underground beam 8 can be greatly improved as the amount of the bar arrangement is reduced.

次に、上記杭1と柱2及び地中梁8の施工方法について簡単に説明する。まず、ケーシング工法によって地表から一定深さまで円形の孔(図示せず)を掘削したのち、この孔内に杭1の配筋1aである鉄筋籠11を建て込み、しかるのち、孔内にコンクリートを打設することによって杭1を造成する。杭1の上端面は地表面から一定深さだけ下方に位置している。   Next, the construction method of the said pile 1, the pillar 2, and the underground beam 8 is demonstrated easily. First, after excavating a circular hole (not shown) from the ground surface to a certain depth by the casing method, the reinforcing bar 11 that is the bar arrangement 1a of the pile 1 is built in this hole, and then concrete is put into the hole. The pile 1 is constructed by driving. The upper end surface of the pile 1 is located below the ground surface by a certain depth.

そして、上記打設コンクリートの未硬化中において、地表に上記円筒体の開口端上を跨がるように作業台(図示せず)を架設し、この作業台上から鋼管3を適宜な吊治具(図示せず)を使用して該鋼管3の中心を上記杭1の中心線上に合致させた状態で円筒体内に吊り下ろし、この鋼管3の下部3bを杭頭部の中央部に該鋼管3の下側突片5から短管部3dの長さ部分を残すようにして挿入、埋設させると共に、コンクリートの硬化によって該下部3bを図3に示すように、コンクリート1bと一体に固着させて杭1の上端面中央部から鋼管3の上部3aを垂直状に立設させた状態にする。   Then, while the cast concrete is not hardened, a work table (not shown) is installed on the ground surface so as to straddle the open end of the cylindrical body, and the steel pipe 3 is appropriately suspended from the work table. A tool (not shown) is used to suspend the steel pipe 3 in the cylindrical body with the center of the steel pipe 3 aligned with the center line of the pile 1, and the lower part 3b of the steel pipe 3 is suspended in the center of the pile head. 3 is inserted and embedded so as to leave the length of the short pipe portion 3d from the lower projecting piece 5, and the lower portion 3b is fixed integrally with the concrete 1b by hardening the concrete as shown in FIG. The upper part 3a of the steel pipe 3 is erected vertically from the center of the upper end surface of the pile 1.

次いで、作業台及び円筒体を撤去したのち、地表部に地中梁8の造成用の溝孔(図示せず)を掘削してこの溝孔内の底部と上部とに複数本の梁筋8a、8a' をそれぞれ溝幅方向に小間隔毎に水平状に配設し、その長さ方向の端部を鋼管3の長さ方向の中央部3cにおける上下端から水平状に突設している上記上下突片4、5上に周方向に並設させた状態で載置して溶接により各梁筋8a、8a' の端部を上下突片4、5にそれぞれ固着する。なお、溝孔は鋼管3を中心にしてこの鋼管3の前後面及び両側面から四方に向かって掘削されているが、柱2の造成位置によっては3方或いは2方に向かって地中梁8が造成される場合もあり、この時には当然のことながら、地中梁8が形成されない側に面している鋼管3の前後面或いは側面には上記上下突片4、5は存在しない。   Next, after removing the work table and the cylindrical body, a groove (not shown) for forming the underground beam 8 is excavated on the ground surface, and a plurality of beam bars 8a are formed at the bottom and the upper part in the groove. , 8a 'are horizontally arranged at small intervals in the groove width direction, and the end portions in the length direction are projected horizontally from the upper and lower ends in the central portion 3c in the length direction of the steel pipe 3. The end portions of the beam bars 8a and 8a 'are fixed to the upper and lower projecting pieces 4 and 5 by welding in a state of being juxtaposed in the circumferential direction on the upper and lower projecting pieces 4 and 5, respectively. The slot is excavated from the front and rear surfaces and both side surfaces of the steel pipe 3 in four directions around the steel pipe 3, but depending on the construction position of the column 2, the underground beam 8 is directed in three or two directions. In this case, as a matter of course, the upper and lower protrusions 4 and 5 do not exist on the front and rear surfaces or side surfaces of the steel pipe 3 facing the side where the underground beam 8 is not formed.

また、杭1は上記溝孔の長さ間隔を存して順次、造成されてあり、従って、上下の梁筋8a、8a' はその両端を隣接する杭1、1上に立設している鋼管3の対向する上部突片4、4間上と下部突片5、5間上とに架設状態で配筋される。なお、梁筋列の幅が鋼管3の横幅よりも広い場合には、該梁筋の端部を受止する突片4、5に対して直角に隣接する突片4、5上に固着した梁筋上にその梁筋列の最両端側の梁筋を直交状態で載置させておけばよい。また、上下梁筋8a、8a' には長さ方向に所定間隔毎にフープ筋8bを組み込んでいる。   In addition, the piles 1 are formed sequentially with the length interval of the above-mentioned slot holes, and therefore the upper and lower beam bars 8a, 8a 'are erected on the adjacent piles 1, 1 at both ends. The steel pipe 3 is arranged in a laid state between the upper projecting pieces 4 and 4 and the lower projecting pieces 5 and 5 facing each other. In addition, when the width | variety of the beam reinforcement row | line is wider than the horizontal width of the steel pipe 3, it fixed on the protrusion pieces 4 and 5 which adjoin the right angle with respect to the protrusion pieces 4 and 5 which receive the edge part of this beam reinforcement. The beam bars at the extreme ends of the beam bars may be placed on the beam bars in an orthogonal state. Further, hoop bars 8b are incorporated into the upper and lower beam bars 8a and 8a ′ at predetermined intervals in the length direction.

一方、柱2の主筋を構成する複数本の鉄筋2aを、地上側から垂直状態で上記鋼管3の前後及び両側面に沿うように下ろしてその下端部を上側突片4に設けている各孔6に挿通したのち、その下端にフック形状の定着部2cを継手部材7によって連結し、この定着部2cを下側突片5の上面に当接、受止させる。このように、鋼管3の四方の突片4、5に設けている複数の孔6に鉄筋2aの下端部を挿入してその下端を下側突片5に受止させることにより、該下側突片5から上方の鋼管3の上部と中央部との前後面、及び両側面に沿ってこれらの各面を覆うように並列した鉄筋2aが上方に向かって建て込まれ、鋼管3の周りを囲むように矩形枠状の配筋が施工される。なお、この矩形枠状に配筋された鉄筋2aも、長さ方向に所定間隔毎にフープ筋2dを組み込んでいる。   On the other hand, a plurality of rebars 2a constituting the main reinforcement of the column 2 are lowered from the ground side so as to be along the front and rear and both side surfaces of the steel pipe 3, and the lower ends thereof are provided in the upper projecting piece 4. 6, a hook-shaped fixing portion 2 c is connected to the lower end of the fixing member 2 c by a joint member 7, and the fixing portion 2 c is brought into contact with and received by the upper surface of the lower protruding piece 5. In this way, by inserting the lower end of the reinforcing bar 2a into the plurality of holes 6 provided in the four projecting pieces 4 and 5 of the steel pipe 3 and receiving the lower end on the lower projecting piece 5, the lower side Reinforcing bars 2a arranged in parallel so as to cover the front and rear surfaces of the upper and central portions of the steel pipe 3 above the projecting piece 5 and both side surfaces are built upward, and around the steel pipe 3 A rectangular frame-shaped reinforcement is constructed so as to surround it. The reinforcing bars 2a arranged in a rectangular frame shape also incorporate hoop bars 2d at predetermined intervals in the length direction.

次いで、これらの鉄筋2aや上記梁筋8a、8a' を囲んだ状態で枠組みしてなる型枠内にコンクリートを打設することによって鉄筋コンクリート造の柱2と、この柱2の下端部が一体化している鉄筋コンクリート造の地中梁8とを造成する。この際、地中梁8の下面は鋼管3における下側突片5よりも下方に位置し、且つその下面と上記杭1の上端面とがコンクリートによって一体に接続していると共に下側突片5と杭1側の鉄筋1aの上端間には、この鉄筋1aの上端と柱2側の鉄筋2aの下端間を離間させている接続部分9が形成される。なお、柱2を構成するための上記鉄筋2aは、その下端にフック形状の定着部2cを設けているので、この定着部2cによって柱2と地中梁8との一体化が一層強固に行われる。   Next, concrete is placed in a formwork framed in a state of surrounding the reinforcing bars 2a and the beam reinforcing bars 8a, 8a 'so that the reinforced concrete column 2 and the lower end of the column 2 are integrated. The reinforced concrete underground beam 8 is created. At this time, the lower surface of the underground beam 8 is positioned below the lower projecting piece 5 in the steel pipe 3, and the lower surface and the upper end surface of the pile 1 are integrally connected by concrete and the lower projecting piece. A connecting portion 9 is formed between the upper end of the reinforcing bar 1a on the pile 1 side and the upper end of the reinforcing bar 1a and the lower end of the reinforcing bar 2a on the column 2 side. The reinforcing bar 2a for constituting the pillar 2 is provided with a hook-shaped fixing portion 2c at the lower end thereof, so that the integration of the pillar 2 and the underground beam 8 is further strengthened by the fixing portion 2c. Is called.

以上の実施の形態においては、鋼管3の中央部における上側の突片4には、鉄筋2aの挿入用孔6として、該突片4を上下に貫通した円形の孔を設けているが、図4に示すように、この孔6から突片4の突出端面に通じる平面細長の孔、即ち、突片4の突出端面に開口している切欠孔6Aとしておいてもよい。このような切欠孔6Aによれば、鉄筋2aを上方から挿入することなく、突片4の突出端面側から開口部を通じて横移動させながら切欠孔6Aに挿通状態に配設することができるので、その配筋作業が一層、円滑に行うことができると共に継手部材7を必要とすることなく、該鉄筋2aの下端部をU字状に屈曲させて定着部2cを形成しておくことができる。   In the above embodiment, the upper projecting piece 4 in the central portion of the steel pipe 3 is provided with a circular hole vertically penetrating the projecting piece 4 as the insertion hole 6 for the reinforcing bar 2a. As shown in FIG. 4, a flat and narrow hole extending from the hole 6 to the projecting end surface of the projecting piece 4, that is, a notch hole 6 </ b> A opening in the projecting end surface of the projecting piece 4 may be used. According to such a notch hole 6A, the rebar 2a can be inserted through the notch hole 6A while being laterally moved from the projecting end face side of the projecting piece 4 through the opening without being inserted from above. The reinforcing work can be performed more smoothly, and the fixing portion 2c can be formed by bending the lower end portion of the reinforcing bar 2a into a U shape without requiring the joint member 7.

さらに、このような切欠孔6Aに代えて、図5に示すように、上記突片4を周方向に複数分割した形状に形成し、この分割によって形成された隣接する小突片4a、4a間の空間部6Bに鉄筋2aを外方側から横移動させながら、或いは、上側から挿入することにより配設するように構成しておいてもよい。また、図6に示すように上下突片4、5を周方向に連続した矩形環状板の形状に形成しておき、上側突片4に周方向に所定間隔毎に鉄筋2aの挿通用孔6を設けた構造としておいてもよい。   Further, in place of such a cutout hole 6A, as shown in FIG. 5, the protruding piece 4 is formed in a shape divided into a plurality of parts in the circumferential direction, and between adjacent small protruding pieces 4a, 4a formed by this division. The rebar 2a may be arranged in the space 6B while being laterally moved from the outer side or by being inserted from the upper side. Moreover, as shown in FIG. 6, the upper and lower protrusions 4 and 5 are formed in the shape of a rectangular annular plate that is continuous in the circumferential direction, and the insertion holes 6 for the reinforcing bars 2a are inserted into the upper protrusion 4 at predetermined intervals in the circumferential direction. It may be a structure provided with.

杭と柱及び地中梁との接続構造を示す簡略正面図である。It is a simplified front view which shows the connection structure of a pile, a pillar, and an underground beam. 杭と柱及び地中梁を造成するための配筋状態を示す斜視図である。It is a perspective view which shows the bar arrangement state for creating a pile, a column, and an underground beam. 施工状態を示す簡略正面図である。It is a simplified front view which shows a construction state. 柱の配筋状態の別な実施形態を示す斜視図である。It is a perspective view which shows another embodiment of the bar arrangement state of a column. さらに別な実施形態を示す横断面図である。It is a cross-sectional view which shows another embodiment. 上下突片を矩形環状に形成した場合の斜視図である。It is a perspective view at the time of forming an up-and-down protrusion piece in a rectangular annular shape.

符号の説明Explanation of symbols

1 杭
1a 鉄筋
1b コンクリート
2 柱
2a 鉄筋
2b コンクリート
3 鋼管
3d 短管部
4、5 上下突片
6 鉄筋挿通用孔
8 地中梁
9 接続部分
1 pile
1a Rebar
1b Concrete 2 pillars
2a rebar
2b Concrete 3 Steel pipe
3d Short pipe part 4, 5 Vertical protrusion 6 Rebar insertion hole 8 Underground beam 9 Connection part

Claims (5)

鉄筋コンクリート造の杭と鉄筋コンクリート造の柱とをこれらの杭や柱よりも細い一定長さの鋼管によって一体に接続してなる杭と柱の接続構造であって、上記杭の上端面と柱の下端面との接続部分に上記鋼管の長さ方向の中央部を配した状態でこの鋼管の上部と下部とをそれぞれ上記鉄筋コンクリート造の柱の上端部の横断面中央と杭の下端部の横断面中央とのコンクリート内に埋設状態で固着していると共に、この鋼管を囲繞している上記柱の鉄筋の下端と杭の鉄筋の上端とを連結することなく離間させていることを特徴とする杭と柱の接続構造。   A pile-column connection structure in which a reinforced concrete pile and a reinforced concrete column are connected together by a steel pipe of a certain length that is thinner than these piles and columns. With the center part in the length direction of the steel pipe arranged at the connecting part with the end face, the upper and lower parts of the steel pipe are respectively connected to the center of the cross section of the upper end of the reinforced concrete column and the center of the cross section of the lower end of the pile. And a pile characterized in that it is fixed in the concrete and embedded in the concrete, and the lower end of the reinforcing bar of the column surrounding the steel pipe and the upper end of the reinforcing bar of the pile are separated without being connected, and Column connection structure. 鋼管の長さ方向の中央部側面に下側の梁筋取付用突片が取付けられていると共に中央部より上方の側面に上側の梁筋取付用突片が取付けられてあり、上側の突片に鋼管の上部を囲繞している柱の鉄筋の下端部を挿通させた孔が設けられていると共に、柱の下端部からこの孔を通じて下方に垂下している上記鉄筋の下端を下側の突片上面に受止させてあり、さらに、この下側の突片下面と杭の鉄筋上端面とを連結することなく離間させていることを特徴とする請求項1に記載の杭と柱の接続構造。   A lower beam reinforcement mounting protrusion is attached to the side surface of the central portion in the length direction of the steel pipe, and an upper beam reinforcement attachment protrusion is attached to the side surface above the center portion. Is provided with a hole through which the lower end of the reinforcing bar of the column surrounding the upper part of the steel pipe is inserted, and the lower end of the reinforcing bar hanging downward from the lower end of the column through this hole The connection between the pile and the column according to claim 1, wherein the connection is made to be received on one upper surface, and further, the lower surface of the lower projecting piece and the upper end surface of the reinforcing bar of the pile are separated without being connected. Construction. 上側突片に設けられている鉄筋挿通用の孔は、突片の突出端面側に開口している切欠孔であることを特徴とする請求項2に記載の杭と柱の接続構造。   The connection structure between a pile and a column according to claim 2, wherein the reinforcing bar insertion hole provided in the upper protrusion is a cutout hole opened on the protruding end face side of the protrusion. 鋼管の上下部における柱と杭とに対する挿入、配設長さを等しくしていると共に杭への挿入長さは、地震等による水平力が作用した時に杭からの引抜力に抵抗し得る長さであることを特徴とする請求項1に記載の杭と柱の接続構造。   The length of insertion and installation into the pillar and pile in the upper and lower parts of the steel pipe is equal, and the length of insertion into the pile is the length that can resist the pulling force from the pile when a horizontal force is applied due to an earthquake, etc. The pile-column connection structure according to claim 1, wherein the connection structure is a pile. 杭が円柱形状で柱が角柱形状であることを特徴とする請求項1、請求項2又は請求項4に記載の杭と柱の接続構造。
The pile-column connection structure according to claim 1, wherein the pile has a cylindrical shape and the column has a prismatic shape.
JP2003309457A 2003-09-02 2003-09-02 Pile-column connection structure Expired - Fee Related JP4130393B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003309457A JP4130393B2 (en) 2003-09-02 2003-09-02 Pile-column connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003309457A JP4130393B2 (en) 2003-09-02 2003-09-02 Pile-column connection structure

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2008077218A Division JP4713605B2 (en) 2008-03-25 2008-03-25 Pile-column connection structure

Publications (2)

Publication Number Publication Date
JP2005076330A true JP2005076330A (en) 2005-03-24
JP4130393B2 JP4130393B2 (en) 2008-08-06

Family

ID=34411586

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003309457A Expired - Fee Related JP4130393B2 (en) 2003-09-02 2003-09-02 Pile-column connection structure

Country Status (1)

Country Link
JP (1) JP4130393B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006316579A (en) * 2005-05-16 2006-11-24 Taisei Corp Foundation structure
JP2008082074A (en) * 2006-09-28 2008-04-10 Okumura Corp Joint structure of pile and post
JP2008082073A (en) * 2006-09-28 2008-04-10 Okumura Corp Joint structure of pile and post
JP2014231673A (en) * 2013-05-28 2014-12-11 新日鐵住金株式会社 Pile head structure and construction method for the same
CN110130600A (en) * 2019-06-05 2019-08-16 六合峰(天津)科技股份有限公司 A kind of TCP steel pipe column engraving facing subsection connecting structure and attaching method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006316579A (en) * 2005-05-16 2006-11-24 Taisei Corp Foundation structure
JP4713218B2 (en) * 2005-05-16 2011-06-29 大成建設株式会社 Foundation structure
JP2008082074A (en) * 2006-09-28 2008-04-10 Okumura Corp Joint structure of pile and post
JP2008082073A (en) * 2006-09-28 2008-04-10 Okumura Corp Joint structure of pile and post
JP4708296B2 (en) * 2006-09-28 2011-06-22 株式会社奥村組 Pile-column connection structure
JP4708295B2 (en) * 2006-09-28 2011-06-22 株式会社奥村組 Pile-column connection structure
JP2014231673A (en) * 2013-05-28 2014-12-11 新日鐵住金株式会社 Pile head structure and construction method for the same
CN110130600A (en) * 2019-06-05 2019-08-16 六合峰(天津)科技股份有限公司 A kind of TCP steel pipe column engraving facing subsection connecting structure and attaching method thereof

Also Published As

Publication number Publication date
JP4130393B2 (en) 2008-08-06

Similar Documents

Publication Publication Date Title
KR101058520B1 (en) Earth retaining wall using phc pile and construction method of the same
KR101861805B1 (en) H omitted
JP2002227204A (en) Earth retaining method of excavation section
JP6650257B2 (en) Mountain retaining structure and construction method thereof
KR20200124949A (en) Anchor Tension way sheathing structure and sheathing method of construction
JP2007177517A (en) Earth anchor method
JP4130393B2 (en) Pile-column connection structure
KR102184900B1 (en) Temporary retaining wall structure using circular steel pipe and construction method thereof
KR101999798B1 (en) Buttress retaining wall witt rear-casing and the c0nstruction method therefor
JP4713605B2 (en) Pile-column connection structure
KR102002059B1 (en) Self-supported temporary earth retaining structure and constructoin method of self-supported retaining wall using the same
KR101348339B1 (en) The pressing device of underground strucyure for non-excavation method and its construccting methods thereof
JP6693115B2 (en) Underground construction method
JP2715867B2 (en) Simple underground construction method
JP2014206025A (en) Culvert
JP2018017041A (en) Foundation structure, and foundation construction method for the same
KR100469961B1 (en) Steel reinforcing cage and reinforcing method of construction using steel reinforcing cage and steel fiber concrete for soft ground
JP3208100U (en) Scaffolding device for construction of underground structures
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP7110015B2 (en) Road lining unit for width change
KR20190023372A (en) Non-detachable Tunnel Structure and Method of Construction Thereof
JP3776280B2 (en) Mountain fastening method
JP2005163330A (en) Tool for constructing impact receiving slab, wall surface material for constructing impact receiving slab, and construction method for protective dam body
JP3060195B2 (en) Construction method of steel basement reinforced concrete continuous underground wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050802

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070402

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080325

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080422

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080521

R150 Certificate of patent or registration of utility model

Ref document number: 4130393

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110530

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110530

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140530

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees