KR101861805B1 - H omitted - Google Patents

H omitted Download PDF

Info

Publication number
KR101861805B1
KR101861805B1 KR1020170109133A KR20170109133A KR101861805B1 KR 101861805 B1 KR101861805 B1 KR 101861805B1 KR 1020170109133 A KR1020170109133 A KR 1020170109133A KR 20170109133 A KR20170109133 A KR 20170109133A KR 101861805 B1 KR101861805 B1 KR 101861805B1
Authority
KR
South Korea
Prior art keywords
frame
guide
casing
frames
ground
Prior art date
Application number
KR1020170109133A
Other languages
Korean (ko)
Inventor
김장환
Original Assignee
(주) 태황건설
김장환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 태황건설, 김장환 filed Critical (주) 태황건설
Priority to KR1020170109133A priority Critical patent/KR101861805B1/en
Application granted granted Critical
Publication of KR101861805B1 publication Critical patent/KR101861805B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

The present invention relates to a structure for constructing a continuous wall including a casing and an H-beam guide, capable of enhancing work efficiency and convenience. To this end, the structure comprises: a first side frame; a second side frame embedded in a position facing the first side frame; a plurality of connection frames spaced apart from each other at predetermined intervals in order to connect between the first and second side frames; a plurality of gap maintaining frames spaced apart from each other at predetermined intervals in order to maintain and support an interval between the first and second side frames; and a plurality of casing guide frames formed on each inner surface of the first and second side frames at predetermined intervals, and guiding an insertion position of a casing, which is installed to bore the ground between spaces where the first and second side frames face each other.

Description

케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물{omitted}Construction for continuous wall installation with casing and H beam guide {omitted}
본 발명은 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물에 관한 것이다. 보다 상세하게는 천공작업이 이루어지는 위치에 소정 간격을 두고 제1 측면프레임과 제2 측면프레임을 가로질러 설치되는 간격유지프레임을 구비함으로써 제1 측면프레임과 제2 측면프레임의 간격을 유지하고 양 측면프레임 간을 지지하여 정확한 위치에 굴착구멍이 형성될 수 있도록 하고, 제1 측면프레임과 제2 측면프레임의 각 내측면에 소정 간격을 두고 다수개 구비되고 단면이 삼각형상으로 형성되는 케이싱가이드프레임을 구비함으로써 케이싱의 인입위치를 정확히 가이드하고 천공 작업 시 케이싱 간의 간섭을 배제할 수 있도록 하며, 제1 측면프레임과 제2 측면프레임에서 내측으로 각각 돌출되어 서로 마주보게 구비되며 서로 마주보는 양측의 단부는 소정의 간극을 형성하는 빔 가이드를 구비함으로써 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 H빔이 인입되는 위치를 가이드하여 H빔을 용이하게 삽입할 수 있도록 하고, 간격유지프레임과 빔 가이드는 시공순서에 따라 선택적으로 착탈이 가능하도록 하여 작업의 효율성 및 편의성을 높일 수 있도록 하는 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물에 관한 것이다. The present invention relates to a structure for continuous wall installation with casing and H beam guide. More particularly, the present invention provides a gap maintaining frame provided across a first side frame and a second side frame at predetermined intervals at a position where a drilling operation is performed, thereby maintaining a gap between the first side frame and the second side frame, A plurality of casing guide frames each having a triangular cross section and spaced apart from each other at predetermined intervals on the inner side surfaces of the first side frame and the second side frame, The first side frame and the second side frame protrude inwardly from the first side frame and the second side frame, respectively, and are opposed to each other. On both ends facing each other, By providing a beam guide for forming a predetermined gap, the first side frame and the second side frame The main beam guides the position where the H beams are introduced between the spaces, so that the H beam can be easily inserted. The gap holding frame and the beam guide can be selectively attached and detached according to the order of construction, thereby enhancing the efficiency and convenience of the work And a structure for continuous wall installation with H beam guide.
일반적으로 구조물을 시공하기 위해서는 구조물의 시공토대가 되는 지반을 일정 깊이로 굴삭하는 터파기 공사를 실시한다. 터파기 공사 시 굴삭된 지반을 통하여 지하수 등이 내부로 침투될 경우 작업 상의 어려움이 발생하게 되고, 구조물의 안정성도에도 악영향을 미치게 된다. In general, in order to construct a structure, a terra cotta work is carried out to excavate the ground, which is the foundation of the structure, to a certain depth. When the groundwater penetrates into the ground through the excavated ground during the earthquake disaster, it is difficult to work and the stability of the structure is adversely affected.
따라서, 터파기 공사 실시 전, 시공토대가 되는 지반의 내부로 흙 또는 지하수 등이 유입되지 않도록 하는 연속벽을 설치할 수 있다. Therefore, it is possible to provide a continuous wall to prevent soil or groundwater from flowing into the ground, which is the foundation of construction before the earthworks construction.
보통, 연속벽은 시공토대가 되는 지반에 일정 깊이로 천공작업을 실시하고, 천공된 공간으로 콘크리트를 타설하여 기둥 형상의 파일을 형성하게 된다. Typically, the continuous wall is pierced to a certain depth on the ground, which is the foundation of the construction, and concrete is poured into the perforated space to form a pillar-shaped pile.
종래의 연속체 시공방식은 소정 직경을 가진 파일공을 연속으로 천공한 후, 천공된 파일공에 콘크리트를 타설하여 연속벽체를 구축하나, 각 파일이 서로 독립적으로 구비되어 파일이 지반에 정확하게 수직으로 형성되지 않으면 연속된 파일 간에 틈이 발생하게 되는 문제점이 있다. 이러한 틈 사이로 지하수 등이 유입되어 구조물의 안정성에도 영향을 미치게 된다. 또한, 띠장을 설치하기 위해 일정한 간격으로 H빔을 설치하는 데, H빔의 방향이 틀어지는 경우가 많이 발생하여 H빔에 띠장을 설치할 경우 홈메우기 작업에 어려움이 있을 뿐만 아니라, 구조적으로 안정성에 악영향을 미치게 된다. In the conventional continuum construction method, continuous piles having a predetermined diameter are successively drilled, concrete is inserted into punched pile holes to form a continuous wall, and each pile is independently provided so that the pile is precisely formed vertically There is a problem that a gap occurs between consecutive files. Groundwater flows into these gaps to affect the stability of the structure. In addition, when the H beam is installed at regular intervals for installing the wrist strap, there are many cases where the direction of the H beam is changed, so that it is difficult to fill the groove when the wrist strap is installed on the H beam, .
따라서, 케이싱에 의해 성형되는 파일 간에 틈이 발생되지 않도록 차수방지 기능을 보강하고, H빔 가이드로 인하여 H빔이 뒤틀리지 않고 일정한 방향으로 설치가 됨으로써 구조물의 강도 및 안전성을 보강할 수 있는 새로운 시공방법이 필요할 것으로 보인다. Therefore, it is possible to reinforce the prevention function for preventing the gap between the files formed by the casing and to prevent the H beams from being twisted due to the H beam guide, and to install the new construction Method seems to be needed.
선행기술문헌 : 등록특허공보 제1674656호(2016.11.09.공고)Prior Art Document: Registration No. 1674656 (issued on September 11, 2016)
본 발명은 상기와 같은 문제점을 해결하기 위해 안출된 것으로, 특히 케이싱의 인입위치를 정확히 가이드하여 천공작업이 이루어지는 위치에 정확하게 굴착구멍을 형성하고, H빔이 인입되는 위치를 정확히 가이드하여 벽체의 지지력을 강화시킬 수 있도록 하고, 시공순서에 따라 선택적으로 착탈이 가능하도록 하여 작업의 효율성 및 편의성을 높일 수 있도록 하는 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 제공하는 데 그 목적이 있다.SUMMARY OF THE INVENTION The present invention has been conceived in order to solve the problems as described above, and it is an object of the present invention to provide a hammering apparatus and a hammering apparatus which accurately guiding an inlet position of a casing to accurately form an excavation hole at a position where a boring operation is performed, And it is an object of the present invention to provide a structure for a continuous wall construction equipped with a casing and an H beam guide for enhancing the efficiency and convenience of the work by making it possible to selectively attach and detach according to the order of construction .
상기 목적을 달성하기 위해 안출된 본 발명에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물은 길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 일 측면에 내설되는 제1 측면프레임; 길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 타측면에 제1 측면프레임과 서로 대응되는 위치에 마주보도록 내설되는 제2 측면프레임; 제1 측면프레임과 제2 측면프레임 간을 연결하기 위해 소정간격 이격되어 다수개 구비되는 연결프레임; 제1 측면프레임과 제2 측면프레임을 가로질러 연결하고, 제1 측면프레임과 제2 측면프레임의 간격을 유지하고 지지하기 위해 소정 간격을 두고 다수개 구비되는 간격유지프레임; 및 제1 측면프레임과 제2 측면프레임의 각 내측면에 소정 간격을 두고 다수개 구비되고, 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 지반의 구멍을 뚫기 위해 설치되는 케이싱이 인입될 위치를 가이드하는 케이싱가이드프레임을 포함할 수 있다. In order to achieve the above object, a structure for a continuous wall construction equipped with a casing and an H beam guide according to the present invention, which is devised to achieve the above object, is disposed at a predetermined length in the longitudinal direction, A first side frame embodied; A second side frame disposed to face the first side frame at a position corresponding to the first side frame, the second side frame being disposed at a predetermined length in the longitudinal direction and on the other side of the ground, A plurality of connection frames spaced apart from each other by a predetermined distance to connect between the first side frame and the second side frame; A plurality of spacing frames connected across the first side frame and the second side frame and spaced apart from each other to maintain and support the spacing between the first side frame and the second side frame; And a plurality of openings formed on the inner side surfaces of the first side frame and the second side frame at predetermined intervals, the casing being provided for piercing the hole of the ground between the first side frame and the second side frame, And a casing guide frame for guiding a position to be moved.
또한, 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 H빔이 내설될 경우, H빔이 삽입될 수 있도록 제1 측면프레임과 제2 측면프레임에서 내측으로 각각 돌출되어 서로 마주보게 구비되며, 서로 마주보는 양측의 단부는 소정의 간극을 형성하는 빔 가이드를 더 포함할 수 있다. When an H beam is inserted between the first side frame and the second side frame, the first side frame and the second side frame protrude inwardly from the first side frame and the second side frame so that the H beam can be inserted. And end portions of opposite sides facing each other may further include a beam guide forming a predetermined gap.
또한, 케이싱가이드프레임은 단면이 삼각형상으로 형성되어 케이싱의 인입위치를 가이드하고, 천공 작업 시 케이싱 간의 간섭을 배제하는 것을 특징으로 할 수 있다. In addition, the casing guide frame may be formed in a triangular shape in section so as to guide the pull-in position of the casing, and to eliminate interference between the casing during the piercing operation.
본 발명에 의하면, 천공작업이 이루어지는 위치에 소정 간격을 두고 제1 측면프레임과 제2 측면프레임을 가로질러 설치되는 간격유지프레임을 구비함으로써 제1 측면프레임과 제2 측면프레임의 간격을 유지하고 지지하여 정확한 위치에 굴착구멍이 형성될 수 있도록 하는 데 그 효과가 있다. According to the present invention, since the interval maintaining frame is provided across the first side frame and the second side frame at a predetermined interval at the position where the drilling operation is performed, the interval between the first side frame and the second side frame is maintained, So that an excavation hole can be formed at an accurate position.
또한, 본 발명에 의하면 제1 측면프레임과 제2 측면프레임에서 내측으로 각각 돌출되어 서로 마주보게 구비되며, 서로 마주보는 양측의 단부는 소정의 간극을 형성하는 빔 가이드를 구비함으로써 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 H빔이 인입되는 위치를 가이드하여 H빔을 용이하게 삽입할 수 있도록 하는 데 그 효과가 있다. According to the present invention, since the beam guides protrude inward from the first side frame and the second side frame and are opposed to each other and both end portions facing each other have a predetermined gap, And the H beam can be easily inserted by guiding the position where the H beam is introduced between the spaces facing each other in the second side frame.
또한, 본 발명에 의하면 제1 측면프레임과 제2 측면프레임의 각 내측면에 소정 간격을 두고 다수개 구비되고, 단면이 삼각형상으로 형성되는 케이싱가이드프레임을 구비함으로써 케이싱의 인입위치를 정확히 가이드하고 천공 작업 시 케이싱 간의 간섭을 배제할 수 있도록 하는 데 그 효과가 있다. In addition, according to the present invention, a plurality of the first and second side frames are provided at predetermined intervals on the inner side surfaces of the first side frame and the second side frame, and the casing guide frame having a triangular cross section is provided, And it is effective to eliminate the interference between the casings in the drilling operation.
또한, 본 발명에 의하면, 간격유지프레임과 빔 가이드는 시공순서에 따라 선택적으로 착탈이 가능하도록 하여 작업의 효율성 및 편의성을 높일 수 있도록 하는 데 그 효과가 있다. Further, according to the present invention, the gap holding frame and the beam guide can be selectively attached and detached according to the order of construction, thereby improving the efficiency and convenience of the work.
도 1은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 사시도,
도 2는 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 평면도,
도 3은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물이 지반에 매설된 상태를 나타낸 도면,
도 4 내지 도 5는 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 케이싱 삽입과정을 도시한 도면,
도 6은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 빔 가이드를 따라 H빔이 삽입되는 상태를 도시한 도면,
도 7은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 이용하여 시공한 연속벽체 결과물을 위에서 바라본 도면,
도 8은 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 위에서 바라본 도면,
도 9는 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물 중 빔 가이드 장치의 사시도, 및
도 10은 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물 중 빔 가이드의 확대도 및 측면도이다.
1 is a perspective view of a structure for a continuous wall installation with a casing and H beam guide according to a preferred embodiment of the present invention,
2 is a plan view of a structure for a continuous wall installation with a casing and H beam guide according to a preferred embodiment of the present invention,
3 is a view illustrating a state in which a structure for continuous wall installation with casings and H beam guides according to a preferred embodiment of the present invention is embedded in the ground;
FIGS. 4 to 5 illustrate a casing inserting process of a structure for a continuous wall installation with a casing and an H beam guide according to a preferred embodiment of the present invention;
6 is a view illustrating a state in which an H beam is inserted along a beam guide of a structure for a continuous wall installation equipped with a casing and an H beam guide according to a preferred embodiment of the present invention,
FIG. 7 is a top view of a continuous wall product constructed using a structure for continuous wall installation with casing and H beam guide according to a preferred embodiment of the present invention,
8 is a top view of a structure for continuous wall installation with a casing and H beam guide according to another preferred embodiment of the present invention,
9 is a perspective view of a beam guiding apparatus in a structure for a continuous wall installation with a casing and H beam guide according to another preferred embodiment of the present invention, and Fig.
10 is an enlarged view and a side view of a beam guide in a structure for a continuous wall construction equipped with a casing and an H beam guide according to another preferred embodiment of the present invention.
이하, 본 발명의 바람직한 실시예를 첨부된 도면들을 참조하여 상세히 설명한다. 우선 각 도면의 구성 요소들에 참조 부호를 부가함에 있어서, 동일한 구성 요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 부호를 가지도록 하고 있음에 유의해야 한다. 또한, 본 발명을 설명함에 있어, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 발명의 요지를 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다. 또한, 이하에서 본 발명의 바람직한 실시예를 설명할 것이나, 본 발명의 기술적 사상은 이에 한정하거나 제한되지 않고 당업자에 의해 변형되어 다양하게 실시될 수 있음은 물론이다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the drawings, the same reference numerals are used to designate the same or similar components throughout the drawings. In the following description of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear. In addition, the preferred embodiments of the present invention will be described below, but it is needless to say that the technical idea of the present invention is not limited thereto and can be variously modified by those skilled in the art.
도 1은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 사시도이고, 도 2는 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 평면도이며, 도 3은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물이 지반에 매설된 상태를 나타낸 도면이고, 도 4 내지 도 5는 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 케이싱 삽입과정을 도시한 도면이며, 도 6은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물의 빔 가이드를 따라 H빔이 삽입되는 상태를 도시한 도면이고, 도 7은 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 이용하여 시공한 연속벽체 결과물을 위에서 바라본 도면이며, 도 8은 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 위에서 바라본 도면이고, 도 9는 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물 중 빔 가이드 장치의 사시도이며, 도 10은 본 발명의 바람직한 또 다른 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물 중 빔 가이드의 확대도 및 측면도이다. FIG. 1 is a perspective view of a structure for a continuous wall installation with a casing and an H beam guide according to a preferred embodiment of the present invention, and FIG. 2 is a perspective view of a continuous wall structure with a casing and H beam guide according to a preferred embodiment of the present invention FIG. 3 is a view showing a state in which a structure for a continuous wall installation with a casing and an H beam guide is embedded in a ground according to a preferred embodiment of the present invention, and FIGS. 4 to 5 are views FIG. 6 is a view illustrating a process of inserting a casing for a continuous wall construction equipped with a casing and an H beam guide according to a preferred embodiment of the present invention. FIG. 7 is a view showing a state where an H beam is inserted along a beam guide of a structure for a continuous wall construction according to a preferred embodiment of the present invention, and FIG. FIG. 8 is a top view of a continuous wall product constructed using a structure for continuous wall installation with an H beam guide, and FIG. 8 is a top view of a continuous wall construction with a casing and H beam guide according to another preferred embodiment of the present invention FIG. 9 is a perspective view of a beam guide apparatus in a structure for a continuous wall installation with a casing and an H beam guide according to another preferred embodiment of the present invention, and FIG. Fig. 6 is an enlarged view and a side view of a beam guide in a structure for continuous wall installation with a casing and H beam guide according to another preferred embodiment; Fig.
도 1 내지 도 10을 참조하면, 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물은 제1 측면프레임(10), 제2 측면프레임(20), 연결프레임(30), 간격유지프레임(40), 케이싱가이드프레임(50), 및 빔 가이드(60)를 포함하여 구성된다. 1 to 10, a structure for a continuous wall installation with a casing and H beam guide according to a preferred embodiment of the present invention includes a first side frame 10, a second side frame 20, A frame 30, a spacing frame 40, a casing guide frame 50, and a beam guide 60.
이하, 제1 측면프레임(10)부터 설명하기로 한다. Hereinafter, the first side frame 10 will be described.
제1 측면프레임(10)은 길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 일 측면에 내설된다. The first side frame 10 is arranged in a predetermined length in the longitudinal direction, and is inserted into one side of the ground which is ripped to a predetermined depth by the terra cotta work.
제1 측면프레임(10)의 외측면 또는 내측면에는 가로 및 세로 방향으로 보강프레임(70)이 다수개 구비되어 제1 측면프레임(10)을 지지할 수도 있다.A plurality of reinforcing frames 70 may be provided on the outer side surface or the inner side surface of the first side frame 10 in the lateral and longitudinal directions to support the first side frame 10.
제2 측면프레임(20)은 길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 타측면에 제1 측면프레임(10)과 서로 대응되는 위치에 마주보도록 내설된다. The second side frame 20 is arranged to have a predetermined length in the longitudinal direction, and is installed to face the other side of the ground exposed to the predetermined depth by the trench construction to correspond to the first side frame 10.
제2 측면프레임(10)의 외측면 또는 내측면에는 가로 및 세로 방향으로 보강프레임(70)이 다수개 구비되어 제2 측면프레임(10)을 지지할 수도 있다.A plurality of reinforcing frames 70 may be provided on the outer side or inner side of the second side frame 10 in the lateral and longitudinal directions to support the second side frame 10.
제1 측면프레임(10) 및 제2 측면프레임(20)은 지반에 내설될 경우 지지력 강화 및 작업공간 확보를 위해 판 형상으로 형성되는 것이 바람직하다. The first side frame 10 and the second side frame 20 are preferably formed in a plate shape for reinforcing the supporting force and securing the work space when the second side frame 20 is installed in the ground.
제1 측면프레임(10) 및 제2 측면프레임(20)은 철 등의 금속재로 형성되는 것이 바람직하다. 여기서, 제1 측면프레임(10) 및 제2 측면프레임(20)의 재질을 한정하는 것은 아니다. The first side frame 10 and the second side frame 20 are preferably made of a metal such as iron. Here, the material of the first side frame 10 and the second side frame 20 is not limited.
연결프레임(30)은 제1 측면프레임(10)과 제2 측면프레임(20) 간을 연결하기 위해 제1 측면프레임(10)과 제2 측면프레임(20)의 각 일측에 소정간격 이격되어 다수개 배치된다. The connection frame 30 is spaced apart from the first side frame 10 and the second side frame 20 by a predetermined distance so as to connect between the first side frame 10 and the second side frame 20, .
연결프레임(30)의 각 양측단부는 내측으로 절곡되어 그 형태가 ㄷ자 형상으로 형성되고, 양측단부가 제1 측면프레임(10) 및 제2 측면프레임(20)의 측면에 각각 체결된다. Each of the opposite ends of the connection frame 30 is bent inward to have a U-shape, and both ends thereof are fastened to the side surfaces of the first side frame 10 and the second side frame 20, respectively.
간격유지프레임(40)은 천공 작업이 이루어지는 지점으로부터 소정 간격을 두고 제1 측면프레임(10)과 제2 측면프레임(20)을 가로질러 설치되어 제1 측면프레임(10)과 제2 측면프레임(20)의 간격을 유지하고 천공 작업 시 제1 측면프레임(10)과 제2 측면프레임(20)이 흔들리지 않고 지지될 수 있도록 하며, 제1 측면프레임(10) 및 제2 측면프레임(20)이 일정 간격을 두고 유지될 수 있도록 한다. The gap holding frame 40 is installed across the first side frame 10 and the second side frame 20 at a predetermined interval from the point where the boring operation is performed and is provided between the first side frame 10 and the second side frame 20 The first side frame 10 and the second side frame 20 can be supported without being shaken while the gap between the first side frame 10 and the second side frame 20 is maintained, So that they can be maintained at regular intervals.
간격유지프레임(40)은 천공작업이 이루어지는 위치마다 선택적으로 장착되며, 제1 측면프레임(10)과 제2 측면프레임(20)으로부터 착탈가능하다. The gap holding frame 40 is selectively mounted at each position where the drilling operation is performed, and is detachable from the first side frame 10 and the second side frame 20.
간격유지프레임(40)의 각 양측단부는 내측으로 절곡되어 단면이 ㄷ자 형상으로 형성되고 양측단부가 제1 측면프레임(10) 및 제2 측면프레임(20)의 각 측면에 체결된다. Each of the opposite end portions of the gap holding frame 40 is bent inward to have a U-shaped cross section and both side ends thereof are fastened to the respective side surfaces of the first side frame 10 and the second side frame 20.
간격유지프레임(40)과 제1 측면프레임(10) 및 제2 측면프레임(20), 연결프레임(30)과 제1 측면프레임(10) 및 제2 측면프레임(20) 간의 체결방식은 볼트체결방식(22)이 이용될 수 있다. 여기서, 간격유지프레임(40)과 제1 측면프레임(10) 및 제2 측면프레임(20) 간의 체결방식을 위의 방식으로 한정하는 것은 아니다.The fastening manner between the gap holding frame 40 and the first side frame 10 and the second side frame 20 and between the connecting frame 30 and the first side frame 10 and the second side frame 20 is a bolt- Scheme 22 can be used. Here, the fastening manner between the gap maintaining frame 40 and the first side frame 10 and the second side frame 20 is not limited in the above-described manner.
케이싱가이드프레임(50)은 제1 측면프레임(10)과 제2 측면프레임(20)의 각 내측면에 소정 간격을 두고 다수개 구비되고, 제1 측면프레임(10)과 제2 측면프레임(20)의 내부공간 사이로 케이싱(52)이 삽입될 위치를 가이드한다. A plurality of casing guide frames 50 are provided on inner side surfaces of the first side frame 10 and the second side frame 20 at predetermined intervals and the first side frame 10 and the second side frame 20 To guide the position where the casing 52 is to be inserted.
케이싱가이드프레임(50)은 단면이 삼각형상으로 형성되어 지반의 구멍을 뚫기 위해 설치되는 케이싱(52)의 인입위치를 가이드하고 천공 작업시 케이싱(52) 간의 간섭을 배제하도록 한다. The casing guide frame 50 is formed in a triangular shape in cross section so as to guide the pulling-in position of the casing 52 installed for piercing the holes of the ground and to eliminate the interference between the casings 52 during the piercing operation.
도 4 내지 도 5와 같이, 케이싱가이드프레임(50)의 단면형상은 케이싱가이드프레임(50)과 케이싱(52)이 접하지 않고, 삼각형상의 꼭지점이 곡면처리되어 케이싱(52)의 인입 및 인출이 용이하도록 구비될 수도 있다. 4 to 5, the cross-sectional shape of the casing guide frame 50 is such that the casing guide frame 50 and the casing 52 are not in contact with each other, the vertexes of the triangle are curved, .
빔 가이드(60)는 제1 측면프레임(10)과 제2 측면프레임(20) 간 마주보는 공간 사이에 H빔(62)이 내설될 경우, H빔(62)이 삽입될 수 있도록 제1 측면프레임(10)과 제2 측면프레임(20)에서 내측으로 각각 돌출되어 서로 마주보게 구비되며 서로 마주보는 양측의 단부는 소정의 간극을 형성한다. When the H beam 62 is inserted between the opposing spaces between the first side frame 10 and the second side frame 20, the beam guide 60 is inserted into the first side surface 10 so that the H beam 62 can be inserted. And protrude inward from the frame 10 and the second side frame 20 so as to be opposed to each other, and both end portions facing each other form a predetermined gap.
도 6을 참조하면, 빔 가이드(60)는 케이싱(52)을 이용하여 천공 작업이 이루어진 후 서로 마주보는 양 빔 가이드(60)의 사이로 H빔(62)을 인입하여 H빔(62)이 정확한 위치에 삽입될 수 있도록 한다. Referring to FIG. 6, after the beam guide 60 is punched using the casing 52, the H beam 62 is drawn through the two beam guides 60 facing each other, So that it can be inserted into the position.
빔 가이드(60)는 H빔(62)이 삽입되는 위치마다 선택적으로 장착되며, 제1 측면프레임(10)과 제2 측면프레임(20)으로부터 착탈가능하다. The beam guide 60 is selectively mounted at each position where the H beam 62 is inserted, and is detachable from the first side frame 10 and the second side frame 20.
빔 가이드(60)는 서로 마주보는 양측의 단부에 형성된 간극 사이로 H빔(62)이 내설되면 제1 측면프레임(10) 및 제2 측면프레임(20)으로부터 탈착하여 H빔(62)이 삽입될 또 다른 위치에 장착될 수 있다. 여기서, 빔 가이드(60)가 삽입되는 횟수 및 간격을 한정하는 것은 아니다.The beam guide 60 is detached from the first side frame 10 and the second side frame 20 and inserted into the H beam 62 when the H beam 62 is inserted between the gaps formed at both ends of the beam guide 60 facing each other It can be mounted at another position. Here, the number and interval of the beam guide 60 are not limited.
도 9 내지 도 10을 참조하면, 빔 가이드(60)는 일측말단에 구비되고 단면이 ㄷ자 형상으로 형성되며 내측면에 빔가이드 완충수단(80)이 착탈방식으로 구비되는 헤드부(90)와, 타측말단에 구비되고 제1 측면프레임(10) 또는 제2 측면프레임(20)의 외측면으로 소정길이 돌출형성되고, 단면이 U자형상으로 형성되는 볼트체결수단(100)과 체결되기 위한 체결수단(150)이 구비되는 체결부(110)와, 헤드부(90)와 체결부(110) 간을 연결하는 연결부(120)를 더 포함하여 구성될 수 있다. 9 to 10, the beam guide 60 includes a head portion 90 provided at one end and formed in a U-shape in cross section and having a beam guide buffering means 80 mounted on the inner side thereof in a detachable manner, And a bolt fastening means (100) provided at the other end and protruding from the outer surface of the first side frame (10) or the second side frame (20) by a predetermined length and having a U- And a connection unit 120 connecting the head unit 90 and the coupling unit 110. The coupling unit 110 may include a coupling unit 110,
체결부(110)의 상부에 결합된 상부부재(미도시)의 간극 사이로 경첩볼트(152) 등을 관통시켜 제1 측면프레임(10) 또는 제2 측면프레임(20)에 결합되도록 한다. The hinge bolt 152 or the like is inserted through the gap of the upper member (not shown) coupled to the upper portion of the coupling portion 110 so as to be coupled to the first side frame 10 or the second side frame 20.
또한, 연결부(120)의 양측면으로부터 헤드부(90)로 연장형성되어 헤드부(90) 및 연결부(120) 간을 지지하고 연결부(120)의 양측면으로부터 체결부(110)로 연장형성되어 헤드부(90) 및 연결부(120) 간을 지지하는 지지부(130)가 더 구비될 수 있다.The head part 90 and the connecting part 120 are extended from both sides of the connecting part 120 to the head part 90 and extend from both sides of the connecting part 120 to the connecting part 110, And a support part 130 for supporting the connection part 90 and the connection part 120 may be further provided.
연결부(120)의 하부에는 제1 측면프레임(10) 또는 제2 측면프레임(20)에 부착된 빔 가이드(60)를 지지하기 위한 브라켓(140)이 더 구비될 수 있다. 여기서, 브라켓(140)의 형상은 'ㄱ'자 형상으로 형성될 수 있으며, 다른 형태로도 대체 가능하다. A bracket 140 may be further provided on the lower portion of the connection part 120 to support the beam guide 60 attached to the first side frame 10 or the second side frame 20. [ Here, the shape of the bracket 140 may be formed in a letter 'A' shape, or may be replaced with another shape.
이하, 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물를 이용하여 시공하는 방법은 다음과 같다.Hereinafter, a method of constructing a continuous wall by using a structure for installing a casing and an H beam guide according to a preferred embodiment of the present invention will be described.
먼저, 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물이 내설될 수 있는 작업공간을 확보하기 위해 터파기 공사를 수행한다. First, a trench construction is performed to secure a work space in which a structure for a continuous wall construction equipped with a casing and H beam guide according to a preferred embodiment of the present invention can be installed.
그 다음, 본 발명의 바람직한 실시예에 따른 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물을 설치한다. Next, a structure for the continuous wall construction equipped with the casing and the H beam guide according to the preferred embodiment of the present invention is installed.
그 다음, 제1 측면프레임(10) 및 제2 측면프레임(20)의 높이에 대응되도록 되메우기를 수행한다. Then, backfilling is performed to correspond to the heights of the first side frame 10 and the second side frame 20.
그 다음, 케이싱가이드프레임(50)의 안내에 따라 케이싱(52)을 인입하고 천공작업을 수행한다. 이 때, 케이싱(52)의 인입순서는 도 4를 참조하면, 첫번째 케이싱가이드프레임, 세번째 케이싱가이드프레임, 다섯번째 케이싱가이드프레임..N번째 케이싱가이드프레임과 같이 홀수에 위치한 케이싱가이드프레임(50)에 케이싱(52)을 인입시켜 천공작업을 먼저 수행한다. 이 때, 간격유지프레임(40)을 설치함으로써 천공작업 중 정확한 위치에 굴착 구멍이 형성되고, 제1 측면프레임(10)과 제2 측면프레임(20)이 일정 간격으로 유지될 수 있도록 한다. Then, according to the guide of the casing guide frame 50, the casing 52 is pulled in and the drilling operation is performed. Referring to FIG. 4, the casing 52 includes a first casing guide frame, a third casing guide frame, a fifth casing guide frame, an Nth casing guide frame, and an odd numbered casing guide frame 50, The casing 52 is pulled in and the drilling operation is performed first. At this time, by providing the gap holding frame 40, an excavation hole is formed at the correct position during the drilling operation, so that the first side frame 10 and the second side frame 20 can be maintained at a predetermined interval.
그 다음, 도 5를 참조하면, 두번째 케이싱가이드프레임, 네번째 케이싱가이드프레임, 여섯번째 케이싱가이드프레임..N+1번째 케이싱가이드프레임과 같이 짝수에 위치한 케이싱가이드프레임(50)에 케이싱(52)을 인입시켜 천공작업을 수행하도록 한다. 이 때, 간격유지프레임(40)을 설치함으로써 천공작업 중 정확한 위치에 굴착 구멍이 형성되고, 제1 측면프레임(10)과 제2 측면프레임(20)이 일정 간격으로 유지될 수 있도록 한다. Next, referring to FIG. 5, a casing 52 is provided on an even numbered casing guide frame 50 such as a second casing guide frame, a fourth casing guide frame, a sixth casing guide frame, and an (N + 1) And the drilling operation is carried out. At this time, by providing the gap holding frame 40, an excavation hole is formed at the correct position during the drilling operation, so that the first side frame 10 and the second side frame 20 can be maintained at a predetermined interval.
천공된 직후에는 글착구멍에 곧바로 콘크리트를 타설한다. Immediately after drilling, concrete is immediately poured into the glue hole.
이 때, 시공하고자 하는 구조물의 지반의 규모에 따라 적정 간격을 두고 H빔을 삽입시킬 수 있으며, H빔이 삽입되는 위치에 빔 가이드(60)를 장착한다. At this time, the H beam can be inserted at an appropriate interval according to the scale of the ground of the structure to be installed, and the beam guide 60 is mounted at the position where the H beam is inserted.
빔 가이드(60)가 장착되면, 서로 마주보는 양 빔 가이드(60)의 사이로 H빔(62)을 인입하여 H빔(62)이 정확한 위치에 삽입될 수 있도록 한다. When the beam guide 60 is mounted, the H beam 62 is pulled in between the opposite beam guides 60 so that the H beam 62 can be inserted at the correct position.
콘크리트 타설 후 제작된 연속벽체 결과물의 단면 형상은, 도 7을 참조하면, 위에서 바라보았을 때, 일부가 겹쳐진 원반형상이 다수개 나열되고, 일체로 형성된다. 이와 같은 형태를 가진 연속벽체 결과물은 지하수 등이 벽체 간의 틈 사이로 스며들지 못하도록 차수를 방지할 수 있다.Referring to Fig. 7, the cross-sectional shape of the continuous wall product produced after concrete pouring is formed integrally with a plurality of disc-shaped patterns partially overlapping each other when viewed from above. This type of continuous wall product can prevent the underground water from entering the gaps between the walls.
이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위 내에서 다양한 수정, 변경 및 치환이 가능할 것이다. 따라서, 본 발명에 개시된 실시예 및 첨부된 도면들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시예 및 첨부된 도면에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다. 본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.It will be apparent to those skilled in the art that various modifications, substitutions and substitutions are possible, without departing from the scope and spirit of the invention as disclosed in the accompanying claims. will be. Therefore, the embodiments disclosed in the present invention and the accompanying drawings are intended to illustrate and not to limit the technical spirit of the present invention, and the scope of the technical idea of the present invention is not limited by these embodiments and the accompanying drawings . The scope of protection of the present invention should be construed according to the following claims, and all technical ideas within the scope of equivalents should be construed as falling within the scope of the present invention.
10 - 제1 측면프레임 20 - 제2 측면프레임
30 - 연결프레임 40 - 간격유지프레임
50 - 케이싱가이드프레임 52 - 케이싱
60 - 빔 가이드 62 - H빔
70 - 보강프레임 80 - 빔가이드 완충수단
90 - 헤드부 100 - 볼트체결수단
110 - 체결부 120 - 연결부
130 - 지지부 140 - 브라켓
150 - 체결수단
10 - first side frame 20 - second side frame
30 - connection frame 40 - spacer frame
50 - casing guide frame 52 - casing
60 - Beam guide 62 - H beam
70 - Reinforcing frame 80 - Beam guide buffering means
90 - Head part 100 - Bolt fastening means
110 - fastening part 120 - connection part
130 - Support 140 - Bracket
150 - fastening means

Claims (3)

  1. 길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 일측면에 내설되는 제1 측면프레임;
    길이방향으로 소정 길이 배치되고, 터파기 공사에 의해 소정 깊이로 파여진 지반의 타측면에 제1 측면프레임과 서로 대응되는 위치에 마주보도록 내설되는 제2 측면프레임;
    제1 측면프레임과 제2 측면프레임 간을 연결하기 위해 소정간격 이격되어 다수개 구비되고, 양단이 내측으로 절곡되어 제1 측면프레임 및 제2 측면프레임의 측면에 각각 체결되는 연결프레임;
    제1 측면프레임과 제2 측면프레임을 가로질러 연결하고, 제1 측면프레임과 제2 측면프레임의 간격을 유지하고 지지하기 위해 소정 간격을 두고 다수개 구비되며, 양단이 내측으로 절곡되어 제1 측면프레임 및 제2 측면프레임의 각 측면에 체결되고, 천공작업이 이루어지는 위치마다 선택적으로 제1 측면프레임 및 제2 측면프레임에 장착되는 간격유지프레임; 및
    제1 측면프레임과 제2 측면프레임의 각 내측면에 소정 간격을 두고 다수개 구비되고, 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 지반의 구멍을 뚫기 위해 설치되는 케이싱이 인입될 위치를 가이드하는 케이싱가이드프레임;
    케이싱을 이용하여 천공작업이 이루어진 후 H 빔이 삽입되는 위치마다 선택적으로 장착되고, 제1 측면프레임과 제2 측면프레임에서 내측으로 각각 돌출되어 서로 마주보게 구비되며, 제1 측면프레임과 제2 측면프레임 간 마주보는 공간 사이에 H 빔이 내설될 수 있도록 하는 빔 가이드
    를 포함하고,
    제1 측면프레임 및 제2 측면프레임은 지반에 내설될 경우 지지력을 강화하고 작업공간을 확보할 수 있도록 판 형상으로 형성되거나, 제1 측면프레임 및 제2 측면프레임의 외측면 또는 내측면에 가로 및 세로 방향으로 보강프레임이 다수개 구비될 수 있는 것
    을 더 포함하며,
    케이싱가이드프레임은 단면이 삼각형상으로 형성되어 케이싱의 인입위치를 가이드하고, 천공 작업 시 케이싱 간의 간섭을 배제하도록 하는 것
    을 더 포함하고,
    빔 가이드는
    일측말단에 구비되고 단면이 ㄷ자 형상으로 형성되며, 내측면에 빔가이드 완충수단이 착탈방식으로 구비되는 헤드부,
    타측말단에 구비되고 제1 측면프레임 또는 제2 측면프레임의 외측면으로 소정길이 돌출형성되고, 단면이 U자형상으로 형성되는 볼트체결수단과 체결되기 위한 체결수단이 구비되는 체결부,
    헤드부와 체결부 간을 연결하는 연결부,
    연결부의 하부에 구비되고, 제1 측면프레임 또는 제2 측면프레임에 부착된 빔 가이드를 지지하기 위한 브라켓
    을 더 포함하는 케이싱 및 H빔 가이드가 장착된 연속벽체시공을 위한 구조물.
    A first side frame disposed at a predetermined length in the longitudinal direction and inserted into one side of the ground which has been ripped to a predetermined depth by a terra cotta work;
    A second side frame disposed to face the first side frame at a position corresponding to the first side frame, the second side frame being disposed at a predetermined length in the longitudinal direction and on the other side of the ground,
    A plurality of connection frames spaced apart from each other by a predetermined distance to connect between the first side frame and the second side frame and being connected to the side surfaces of the first side frame and the second side frame,
    The first side frame and the second side frame are connected to each other across a first side frame and a second side frame. A plurality of the first side frame and the second side frame are spaced apart from each other at a predetermined interval to support and support the first side frame and the second side frame. A spacing frame attached to each side of the frame and the second side frame and selectively mounted to the first side frame and the second side frame for each position where the boring operation is performed; And
    A plurality of openings are provided in the inner side surfaces of the first side frame and the second side frame at predetermined intervals, and a casing installed to drill holes in the ground between the first side frame and the second side frame is inserted A casing guide frame guiding the position;
    A first side frame and a second side frame, the first side frame and the second side frame being protruded inward from the first side frame and facing each other, and the first side frame and the second side A beam guide for allowing the H beam to be interposed between the opposed spaces of the frames
    Lt; / RTI >
    The first side frame and the second side frame may be formed in a plate shape so as to enhance the supporting force and to secure a working space when the first side frame and the second side frame are inserted into the ground, A plurality of reinforcement frames may be provided in the longitudinal direction
    Further comprising:
    The casing guide frame is formed in a triangular shape in section so as to guide the pulling-in position of the casing and to eliminate the interference between the casing in the piercing operation
    Further comprising:
    The beam guide
    A head part provided at one end and formed in a C shape in cross section and having a beam guide buffering means provided on the inner side thereof in a detachable manner,
    A fastening part provided at the other end and protruding from the first side frame or the second side frame by a predetermined length and having a U-shaped cross section and fastening means for fastening,
    A connecting portion connecting the head portion and the fastening portion,
    A bracket for supporting the beam guide attached to the first side frame or the second side frame,
    And an H beam guide. ≪ RTI ID = 0.0 > [0002] < / RTI >
  2. 삭제delete
  3. 삭제delete
KR1020170109133A 2017-08-29 2017-08-29 H omitted KR101861805B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170109133A KR101861805B1 (en) 2017-08-29 2017-08-29 H omitted

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170109133A KR101861805B1 (en) 2017-08-29 2017-08-29 H omitted

Publications (1)

Publication Number Publication Date
KR101861805B1 true KR101861805B1 (en) 2018-05-28

Family

ID=62451373

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170109133A KR101861805B1 (en) 2017-08-29 2017-08-29 H omitted

Country Status (1)

Country Link
KR (1) KR101861805B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101878832B1 (en) * 2018-06-05 2018-07-17 대림산업 주식회사 Tremie Plate Having a Crane Function of Reinforcing Bar and Verticality Maintaining Method for Reinforcing Bar of the Reinforced Concrete Pile Using the Same
KR102022845B1 (en) * 2019-03-21 2019-09-19 (주)제이피이엔씨 Device for pile install distance and maintance of erection and rotating correction and pile rotating correction method using the same
KR102037223B1 (en) * 2019-01-23 2019-10-28 (주) 태황건설 Structures for continuous wall construction with reduced distortion and shaking
KR102097919B1 (en) * 2019-09-23 2020-04-10 (주)제이피이엔씨 Melioration wall and replacement wall mixed retaining wall construction method
KR20210015135A (en) 2019-07-31 2021-02-10 구본민 Pile reinforcement guide device and its construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100858713B1 (en) * 2007-03-19 2008-09-17 (주)써포텍 Apparatus for construction of a earth-protection walls
KR100955753B1 (en) * 2009-09-23 2010-04-30 한일건설주식회사 The method of vertical construction by leaving of the pile in advanced construction
KR101482501B1 (en) * 2014-06-19 2015-01-14 이봉수 Drilling guide system, drilling method and structure installation method using PC pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100858713B1 (en) * 2007-03-19 2008-09-17 (주)써포텍 Apparatus for construction of a earth-protection walls
KR100955753B1 (en) * 2009-09-23 2010-04-30 한일건설주식회사 The method of vertical construction by leaving of the pile in advanced construction
KR101482501B1 (en) * 2014-06-19 2015-01-14 이봉수 Drilling guide system, drilling method and structure installation method using PC pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101878832B1 (en) * 2018-06-05 2018-07-17 대림산업 주식회사 Tremie Plate Having a Crane Function of Reinforcing Bar and Verticality Maintaining Method for Reinforcing Bar of the Reinforced Concrete Pile Using the Same
KR102037223B1 (en) * 2019-01-23 2019-10-28 (주) 태황건설 Structures for continuous wall construction with reduced distortion and shaking
KR102022845B1 (en) * 2019-03-21 2019-09-19 (주)제이피이엔씨 Device for pile install distance and maintance of erection and rotating correction and pile rotating correction method using the same
KR20210015135A (en) 2019-07-31 2021-02-10 구본민 Pile reinforcement guide device and its construction method
KR102097919B1 (en) * 2019-09-23 2020-04-10 (주)제이피이엔씨 Melioration wall and replacement wall mixed retaining wall construction method

Similar Documents

Publication Publication Date Title
KR101302743B1 (en) Phc pile and its using the same soil cement wall construction methode
KR20080026014A (en) Establishment method of soil guard structure
CN107060803B (en) Tunnel construction method by utilizing pipe curtain grouting
WO2010019014A2 (en) Method for constructing a chair-type, self-supported earth retaining wall
KR101691139B1 (en) Construction method using soil retaining wall
KR20090091460A (en) Soil retaining method for two rows pile using earth anchor
KR100882831B1 (en) Reformed sheet plate and the method of installation of the same
KR100782007B1 (en) Construction method of a earth-protection walls
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100851356B1 (en) Retaining wall structure and construnction method of the retaining wall structure
KR101640971B1 (en) Connecting a sheet pile for retaining wall
KR100957599B1 (en) Basement-structure construction method to use temporary earth retaining structure
KR100968048B1 (en) A retaining panel structure and construction method
KR101344096B1 (en) Apparatus of guide casing for a ground excavator
KR101212972B1 (en) Retaining wall using multi reinforcment and construction method thereof
KR101176592B1 (en) Earth retaining wall structure constructing method using prestressed tendon
KR100913569B1 (en) Phc pile for retaining wall
KR20190051361A (en) CIP waterproof reinforcement method
KR101834847B1 (en) Echo-environmental construction method of tunnel portal area using mini pipe-roof
KR101149895B1 (en) Reinforcement block for pillar of tunnel
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
KR101888737B1 (en) Prefabricated shoring structure
KR100939535B1 (en) Guide for execution of underground diaphragm wall
KR100910576B1 (en) Embed anchor and construction method of composite basement wall using the same
KR20150060079A (en) Wall Shoring Structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant