JP2004293180A - Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole - Google Patents
Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole Download PDFInfo
- Publication number
- JP2004293180A JP2004293180A JP2003087717A JP2003087717A JP2004293180A JP 2004293180 A JP2004293180 A JP 2004293180A JP 2003087717 A JP2003087717 A JP 2003087717A JP 2003087717 A JP2003087717 A JP 2003087717A JP 2004293180 A JP2004293180 A JP 2004293180A
- Authority
- JP
- Japan
- Prior art keywords
- joint
- reinforced concrete
- precast
- column
- precast reinforced
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、プレキャスト鉄筋コンクリート梁、プレキャスト鉄筋コンクリート梁と柱の接合構造、プレキャスト鉄筋コンクリート梁と柱の接合方法に関する。
【0002】
【従来の技術】
従来より、鉄筋コンクリート造の構造物を構築する際には、プレキャスト鉄筋コンクリート造の柱を構築するとともに、ハーフプレキャスト鉄筋コンクリート造の梁を架け渡し、柱と梁の仕口部にコンクリートを打設して柱と梁の接合した後、床に対してコンクリートを打設して架構を構築する工法が一般に用いられている。このような工法では、柱と梁の仕口部へのコンクリート打設に際し、前記梁の上面で、柱との取り合い部と床との間にコンクリート止めを設置する必要がある。このようなコンクリート止めは、前記梁の上端筋が貫通できる構成を備える必要があるとともに、コンクリート打設後には撤去するか、もしくは捨て型枠として床に埋設されても、構造に不具合を生じないものとする必要があり、作業が繁雑であり、工費削減や工期短縮の妨げとなっていた。
このような中、特許文献1に示すように、上端筋及びあばら筋の上部を露出させたハーフプレキャスト鉄筋コンクリート造の梁について、プレキャストコンクリートの天端面で、柱との取り合い部と床との境界部にあらかじめ突起部を設け、該突起部をコンクリート止めとして利用する構成が考案されている。これにより、コンクリート型枠の設置や撤去等の作業を省略することが可能になるものである。
【0003】
【特許文献1】
特開2001−164688号公報(p4、図1参照)
【0004】
【発明が解決しようとする課題】
しかしながら、特許文献1に示された梁は、上端筋が前記梁の小口面よりも突出する構成となっているため、柱との接合構造は、梁の上端筋及び下端筋の両者が柱の内方に挿入される構成となるとともに、柱の仕口部にはフープ筋を配設する必要があるため、仕口部内の配筋が複雑となる。さらに、柱に対して梁が2方向以上から接合する構成では、梁の上端筋を互いに移動しながら、所定の位置に配筋する等の手間を有することとなり、コンクリート打設に係る煩雑さは解消されるものの、配筋に係る煩雑さを解消することができない。
【0005】
上記事情に鑑み、本発明は、柱と梁の接合に際し、作業性が良く、安価なプレキャスト鉄筋コンクリート梁、プレキャスト鉄筋コンクリート梁と柱の接合構造、及びプレキャスト鉄筋コンクリート梁と柱の接合方法を提供することを目的としている。
【0006】
【課題を解決するための手段】
請求項1記載のプレキャスト鉄筋コンクリート梁は、複数の上端筋及び下端筋よりなる主筋と、複数のあばら筋と、該あばら筋及び主筋を埋設するプレキャストコンクリートを備えてなり、該プレキャストコンクリートの天端面が、上端筋及びあばら筋の上部を露出する高さに形成され、その天端面には、プレキャストコンクリートの端部より所定の離間距離を有する位置に、少なくとも上端筋の配置高さよりも高さを有する立ち上がり部を有するとともに、前記下端筋の端部が、前記プレキャストコンクリートの端部より突出し、前記上端筋の端部が、前記プレキャストコンクリートの端部と立ち上がり部との間に位置することを特徴としている。
【0007】
請求項2記載のプレキャスト鉄筋コンクリート梁は、立ち上がり部に、下部を前記プレキャストコンクリートに固着されて鉛直に立設する板状のラス網が用いられており、板面を前記上端筋と直交するように配されて、該上端筋が板面の網目を貫通していることを特徴としている。
【0008】
請求項3記載のプレキャスト鉄筋コンクリート梁と柱の接合構造は、端部を向かい合わせて隣り合う前記プレキャスト鉄筋コンクリート梁の間に、前記柱が配置されて、該柱の仕口部に、隣り合うプレキャスト鉄筋コンクリート梁に備えられた向かい合う下端筋の端部を連結する継ぎ手が形成されるとともに、隣り合う前記プレキャスト鉄筋コンクリート梁に備えられた向かい合う上端筋どうしを連結する複数の梁筋が配設され、また、該梁筋の端部と前記上端筋の端部に継ぎ手が形成されて、該梁筋と前記上端筋の継ぎ手、及び下端筋の継ぎ手を埋設するように、コンクリートが打設されており、前記梁筋と上端筋の継ぎ手が、前記プレキャスト鉄筋コンクリート梁の内方に形成されることを特徴としている。
【0009】
請求項4記載のプレキャスト鉄筋コンクリート梁と柱の接合方法は、前記柱のx方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込んだ後、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋の端部どうしに継ぎ手を形成した上で、前記柱の仕口部にフープ筋を配設する第1の工程と、前記柱の仕口部を跨ぎx方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成する第2の工程と、前記梁筋と上端筋の継ぎ手を埋設するように、柱の仕口部、及びプレキャスト鉄筋コンクリート梁の上部で前記立ち上がり部と前記柱に囲まれる領域の両者に、コンクリートを打設する第3の工程を備えることを特徴としている。
【0010】
請求項5記載のプレキャスト鉄筋コンクリート梁と柱の接合方法は、第1の工程で、フープ筋を配設する前に、前記柱のy方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込み、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋どうしに継ぎ手を形成し、第2の工程の後、前記柱の仕口部を跨ぎy方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成することを特徴としている。
【0011】
【発明の実施の形態】
本発明のプレキャスト鉄筋コンクリート梁、プレキャスト鉄筋コンクリート梁と柱の接合構造、及びプレキャスト鉄筋コンクリート梁と柱の接合方法を、図1から図6に示す。本発明のプレキャスト鉄筋コンクリート梁は、上端筋及びあばら筋の上部をプレキャストコンクリートより露出する構成とし、該プレキャストコンクリートの上面で端部より所定の離間距離を設けた位置に、立ち上がり部を設けるとともに、前記上端筋の端部がプレキャストコンクリートの端部と立ち上がり部との間に位置する部材長に設定した。
これにより、柱と梁の接合に際し、上端筋に係る継ぎ手をプレキャスト鉄筋コンクリート梁の内方に配置できるため、柱の仕口部における配筋を簡略化できるとともに、立ち上がり部をコンクリート止めとして使用できるため、仕口部へのコンクリートの打設時に、コンクリート型枠の設置及び撤去工程を省略することができ、施工性を向上することができるものである。
【0012】
図1(a)に示すように、プレキャスト鉄筋コンクリート造の梁1は、上端筋2、下端筋3よりなる主筋4と、あばら筋5、及びこれらを埋設するプレキャストコンクリート6により構成されている。前記主筋4は、梁1の長さ方向に延在し、また幅方向に複数が所定の離間間隔をもって平行に配置されており、梁1の上方に位置する上端筋2及び梁1の下方に位置する下端筋3が、鉛直方向で同軸となるように位置決めされている。また、複数のあばら筋5は、前記主筋4に直交し、これらを内包するように所定の離間間隔をもって梁1の長さ方向に複数配置されている。
【0013】
このような構成の梁1は、前記プレキャストコンクリート6がその天端面を、上端筋2及びあばら筋5の上部を露出する高さに形成されており、該天端には、プレキャストコンクリート6の長さ方向の端部から所定の離間距離をもって、前記上端筋2の配置高さよりも高さを有する立ち上がり部7が設置されている。また、該立ち上がり部7には、水平方向に貫通する孔7aが備えられており、該孔7aを上端筋2が貫通する構成となっている。
なお、立ち上がり部7の高さの上限は、後に梁1の上面に形成される床スラブの天端面と同様の高さである。
【0014】
また、該梁1は、前記上端筋2と下端筋3で部材長を違えており、前記下端筋3はプレキャストコンクリート6の部材長より長く、端部が前記プレキャストコンクリート6の端部より長さ方向に突出するよう成形されているが、前記上端筋2はプレキャストコンクリート6の部材長より短く、プレキャストコンクリート6の端部より外方へ突出することなく、内方に納めることの可能な長さに成形されている。このとき、該上端筋2の端部は、プレキャストコンクリート6の端部と前記立ち上がり部7との間に位置している。
【0015】
なお、本実施の形態では、梁1の両端部の近傍に前記立ち上がり部7を備えているが、必ずしもこれにこだわるものではなく、何れか一方に備える構成としても良い。また、該立ち上がり部7には、前記あばら筋5の一部を内包するプレキャストコンクリート6が用いられているが、必ずしもあばら筋5を内包する必要が無く、また、捨て型枠として用いても床に不具合を生じない部材であれば何れの部材を用いても良い。
【0016】
図1(b)に他の部材を用いた立ち上がり部7の例を示す。該梁1は、図1(a)に示したものと同様の構成であるが、前記立ち上がり部7にラス網が用いられている。該ラス網は、網目状の鋼板であり、板面を前記上端筋2と直交する方向に向けて立設され、上部が露出するようにプレキャストコンクリート6に下部を埋設されている。なお、ラス網は、必ずしも下部を埋設する必要はなく、所定位置に固定できれば、何れの方法で固定しても良く、また、脱着可能に設置しても良い。
ここで、該ラス網の露出高さは、プレキャストコンクリート6で製作された立ち上がり部7と同様に、少なくとも前記上端筋2の配置高さよりも高く形成するが、その高さの上限は、後に梁1の上面に形成される床スラブ15の天端面よりも低くなるように形成する。このとき、前記上端筋2は、ラス網の網目を貫通する構成としている。
【0017】
上述する梁1を用いた柱8と梁1の接合構造は、図2に示すように、対をなす前記梁1が、前記柱8を挟んで端部同士を向かい併せるように同一水平軸上に配置されている。対をなす前記梁1の下端筋3は端部を、前記梁1を構成するプレキャストコンクリート6の端部より長さ方向に突出するように形成されているため、その端部どうしが前記柱8の仕口部内で突き合わされており、両者を連結するようにカプラーが嵌合されて、向かい合う下端筋3どうしの継ぎ手9が形成されている。なお、本実施の形態において、該下端筋3の継ぎ手9には、カプラーを用いたが、必ずしもこれにこだわるものではなく、長手方向に隣り合って延在する下端筋3に継ぎ手9を構成できれば、何れを用いても良い。
【0018】
一方、対をなす前記梁1の上端筋2は、前記プレキャストコンクリート6よりも短く形成されているため、端部が柱8の仕口部に突出することはない。そこで、前記柱8の仕口部には、柱8の断面を跨ぐことのできる部材長を有する梁筋11が、前記上端筋2と同様の高さに、平行でかつ上端筋2と同様の離間間隔をもって、前記上端筋2と同数配置されている。該梁筋11は、その両端部各々と前記上端筋2の端部とを前記梁1のプレキャストコンクリート6の天端面上で突き合わされて、両者を連結するようにスリーブが嵌合され、継ぎ手10を形成している。なお、本実施の形態において、該上端筋2と梁筋11の継ぎ手10には、スリーブを用いたが、必ずしもこれにこだわるものではなく、長手方向に隣り合って延在する上端筋2及び梁筋11に継ぎ手10を構成できれば、何れを用いても良い。
これにより、前記柱8の仕口部には、対をなす梁1の下端筋3同士の継ぎ手9が配置されるものの、前記梁筋11が貫通するように配されるのみで、前記上端筋2に係る継ぎ手10が配置されることはない。
【0019】
このような柱8の仕口部には、柱8の主筋8aに直交して複数のフープ筋8bが配設され、前記下端筋3同士の継ぎ手9、及び前記梁筋11と上端筋2の継ぎ手10を埋設するように、柱8の仕口部、及び前記梁1の上部で柱8と前記立ち上がり部7に囲われた領域の両者に、コンクリート12が打設されている。したがって、前記立ち上がり部7を、梁1を構成するプレキャストコンクリート6の上面で、柱8との取り合い部と後に構築する床スラブ15との境界に設置しておくことにより、これを柱8と梁1の接合時、及び床スラブ15の構築時の両工程でコンクリート型枠として利用するものである。なお、本実施の形態では、前記立ち上がり部7を後に構築される床スラブ15の天端と同様の高さに形成していないため、立ち上がり部7の上端部にコンクリート止め13を配置したが、必ずしもこれにこだわるものではなく、立ち上がり部7の上端部を床スラブ15の天端と同様の高さに形成してもよい。
【0020】
上述するように、前記柱8と梁1の接合構造は、前記梁1の上端筋2と梁筋11との継ぎ手が、柱8の仕口部ではなく、前記梁1の端部、つまり柱8との取り合い部に位置するため、柱8の仕口部の配筋を簡略化し作業性を向上できるものである。また、前記梁1の立ち上がり部7を、柱8との取り合い部と床スラブ15との境界に配置しておくことにより、該立ち上がり部7を柱8と梁1を接合構造を構築する際のコンクリート12の打設作業時、及び後に床スラブ15を構築する際のコンクリートの打設作業時の両者に、コンクリート型枠として用いることができるため、作業の繁雑な上端筋2廻りに係るコンクリート型枠の施工を省略することができるものである。
【0021】
なお、図2では、前記柱8の向かい合う両側に、端部を向かい合わせて配置された1対の梁が接合する場合の接合構造を示したが、必ずしもこれにこだわるものではなく、図3に示すように、四角柱の柱8の向かい合う2対の側面各々に、2対の梁を接合しても良い。ただし、この場合には、2対の梁のうち、何れか一方に高低差を設けた上で、前記柱8に接合する。本実施の形態では、図5(b)に示すように、y方向に配置した対をなす梁1を、x方向に配置した対をなす梁1と比較して高く位置するように配置した。このとき、x方向及びy方向に配置した梁1の高低差は、前記y方向及びx方向の両者各々に配置した対をなす梁1の下端筋3どうしの高さ方向の離間間隔hを、コンクリート12を打設した際に必要なかぶり厚を確保できる距離とすれば、何れの高低差を設けても良い。
【0022】
上述するハーフプレキャスト鉄筋コンクリート造の柱8と梁1の接合方法を図4及び図5を用いて詳述する。
まず、第1の工程では、前記柱8のx方向の両側に、端部を向かい合わせるように対をなすプレキャスト鉄筋コンクリート造の梁1を建て込む。このとき、該梁1の下端筋3は、前記柱8の仕口部内に挿入された状態となる。
次に、対をなす該梁1の突き合え下端筋3どうしを連結するように前記カプラーを設置し、図4(a)に示すように、下端筋3どうしの継ぎ手9を形成する。
なお、前記柱8に対してx方向にのみ対をなす梁1を接合する際には、この後、前記柱8の仕口部にフープ筋8bを配設する。
【0023】
上述する第1の工程を終了した後、前記柱8のy方向の両側に、端部を突き合わせるように対をなす梁1を建て込む。このとき、y方向に建て込む対をなす梁1は、x方向に建て込んだ対をなす梁1と比較して、柱8に対する高低差を所定量hだけ設けて高く配置する。
次に、y方向の対をなす該梁1の突き合う下端筋3どうしを連結するように前記カプラー9を設置して下端筋3どうしの継ぎ手9を形成し、図4(b)に示すように、前記柱8の仕口部にフープ筋8bを配設する。
【0024】
第2の工程では、前記柱8の仕口部を跨ぐように、梁1に備えられた上端筋2と同数の梁筋11を、柱8のx方向に、梁1の上端筋2と同様の離間間隔をもって平行に配置し、x方向の対をなす梁1に備えられた上端筋2の端部と、これに突き合う該梁筋11の端部とを連結するようにスリーブを設置し、図4(c)に示すように、梁筋11と上端筋2の継ぎ手10を形成する。なお、前記柱8に対してx方向にのみ対をなす梁1を接合する際には、この後、下記に記載する第3の工程を実施する。
【0025】
上述する第2の工程を終了した後、前記柱8のy方向にも同様に、柱8の仕口部を跨ぐように、梁1に備えられた上端筋2と同数の梁筋11aを配置し、y方向の対をなす梁1に備えられた上端筋2の端部と、これと突き合う該梁筋11の端部とを連結するようにスリーブを設置し、図5(a)に示すように、梁筋11と上端筋2の継ぎ手10を形成する。
【0026】
第3の工程では、前記梁1の上面に備えられた前記立ち上がり部7をコンクリート型枠として、梁筋11と上端筋2の継ぎ手を埋設するように、柱8の仕口部、及び前記梁1の上面で柱8と立ち上がり部7に囲まれる領域の両者にコンクリート12を打設する。
このとき、前記梁1のプレキャストコンクリート6上には側面に沿って、プレキャストコンクリート6の端部と立ち上がり部7との間に、ラス網もしくはベニヤ板等により構成されるコンクリート型枠14を配置しておく。
【0027】
なお、該コンクリート型枠14は、隣り合うX方向の梁1及びy方向の梁1の両者各々に設けられたコンクリート型枠14をあらかじめ一体化させて、図6に示すようにL字型に成型しておいても良い。
また、図6に示すように、前記立ち上がり部7にラス網を備えた梁1と柱8を接合する場合にも、柱8と梁1の接合方法は、上述する方法と同様の工程で実施すればよい。
【0028】
このような方法により、前記柱8の四方に端部を向かい合わせて対をなす2対の梁1とが接合されることとなる。なお、前記柱8の一対の向かい合う側面にのみ対をなす1対の梁1を接合したい場合には、上述する手順のうち、y方向へ対をなす1対の梁1接合に係る手順を省略すれば良い。
【0029】
上述する構成によれば、前記梁1の上部には、立ち上がり部7が備えられていることから、該立ち上がり部7を前記柱8との取り合い部と床15との境界に配置して、該立ち上がり部7を柱8と梁1の接合時、及び床スラブ15の構築時の各々でコンクリートの打設作業に用いるコンクリート型枠として用いることができるため、作業の繁雑な上端筋2廻りに係るコンクリート型枠の設置作業を省略することができ、施工性を向上することができ、工期短縮、工費削減に大きく寄与することが可能となる。
【0030】
また、前記上端筋2の端部が、前記梁1のプレキャストコンクリート6の端部と前記立ち上がり部7との間に位置していることから、該上端筋2に係る継ぎ手10を、梁1の内方に配置することができるため、上端筋2に係る継ぎ手10を容易に形成することが可能で施工性が良く、工費削減、工期短縮に大きく寄与することが可能となる。
【0031】
さらに、前記柱8と梁1の接合構造は、前記柱8の仕口部を跨ぐように梁筋11を配置し、該梁筋11を介して向かい合う上端筋2を連結するため、上端筋2と梁筋11の継ぎ手10が柱8の仕口部ではなく、前記梁1の端部に配置されることから、柱8仕口部の配筋を簡略化でき、作業性が向上するため、工期短縮に大きく寄与することが可能となる。
【0032】
また、上述する構造の梁1と柱8の接合方法は、柱8の仕口部に係る配筋が容易であることから、従来のように柱8の仕口部にフープ筋8bを配置するために上端筋2の位置を移動させる等の作業を省略でき、上端筋2移動の鉄筋工やフープ筋8b配筋の鉄筋工の相番作業が不要となる。さらに、前記立ち上がり部7を有する梁1を用いることにより、作業の繁雑な上端筋2廻りに係るコンクリート型枠の設置作業を省略できるため、工期を短縮することが可能となる。
【0033】
【発明の効果】
請求項1または2に記載のプレキャスト鉄筋コンクリート梁によれば、複数の上端筋及び下端筋よりなる主筋と、複数のあばら筋と、該あばら筋及び主筋を埋設するプレキャストコンクリートを備えてなり、該プレキャストコンクリートの天端面が、上端筋及びあばら筋の上部を露出する高さに形成され、その天端面には、プレキャストコンクリートの端部より所定の離間距離を有する位置に、少なくとも上端筋の配置高さよりも高さを有する立ち上がり部を有するとともに、前記下端筋の端部が、前記プレキャストコンクリートの端部より突出し、前記上端筋の端部が、前記プレキャストコンクリートの端部と立ち上がり部との間に位置する。
もしくは、立ち上がり部に、下部を前記プレキャストコンクリートに固着されて鉛直に立設する板状のラス網が用いられており、板面を前記上端筋と直交するように配されて、該上端筋が板面の網目を貫通している。
これにより、該立ち上がり部を前記柱との取り合い部と床との境界に配置して、該立ち上がり部を柱と梁の接合時、及び床スラブの構築時の各々でコンクリートの打設作業に用いるコンクリート型枠として用いることができるため、型枠に係る作業を省略することができ、施工性を向上することができ、工期短縮、工費削減に大きく寄与することが可能となる。
【0034】
請求項3記載のプレキャスト鉄筋コンクリート梁と柱の接合構造によれば、端部を向かい合わせて隣り合う前記プレキャスト鉄筋コンクリート梁の間に、前記柱が配置されて、該柱の仕口部に、隣り合うプレキャスト鉄筋コンクリート梁に備えられた向かい合う下端筋の端部を連結する継ぎ手が形成されるとともに、隣り合う前記プレキャスト鉄筋コンクリート梁に備えられた向かい合う上端筋どうしを連結する複数の梁筋が配設され、また、該梁筋の端部と前記上端筋の端部に継ぎ手が形成されて、該梁筋と前記上端筋の継ぎ手、及び下端筋の継ぎ手を埋設するように、コンクリートが打設されており、前記梁筋と上端筋の継ぎ手が、前記プレキャスト鉄筋コンクリート梁の内方に形成される。
これにより、上端筋と梁筋の継ぎ手が柱の仕口部ではなく、前記梁の端部に配置されることから、柱仕口部の配筋を簡略化でき、作業性が向上するため、工期短縮に大きく寄与することが可能となる。
【0035】
請求項4または5に記載のプレキャスト鉄筋コンクリート梁と柱の接合方法によれば、前記柱のx方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込んだ後、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋の端部どうしに継ぎ手を形成した上で、前記柱の仕口部にフープ筋を配設する第1の工程と、前記柱の仕口部を跨ぎx方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成する第2の工程と、前記梁筋と上端筋の継ぎ手を埋設するように、柱の仕口部、及びプレキャスト鉄筋コンクリート梁の上部で前記立ち上がり部と前記柱に囲まれる領域の両者に、コンクリートを打設する第3の工程を備える。
もしくは、第1の工程で、フープ筋を配設する前に、前記柱のy方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込み、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋どうしに継ぎ手を形成し、第2の工程の後、前記柱の仕口部を跨ぎy方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成する。
【0036】
これにより、前記柱の仕口部に係る配筋が容易であるため、従来のように柱の仕口部にフープ筋を配置するために上端筋の位置を移動させる、といった作業を省略でき、上端筋移動の鉄筋工やフープ筋配筋の鉄筋工の相番作業が不要となる。さらに、前記立ち上がり部を有する梁を用いることにより、作業の繁雑な上端筋廻りに係るコンクリート型枠の設置作業を省略できるため、工期を大幅に短縮することが可能となる。
【図面の簡単な説明】
【図1】本発明に係るプレキャスト鉄筋コンクリート梁を示す図である。
【図2】本発明に係るプレキャスト鉄筋コンクリート梁を用いた柱と、端部を向かい合う対をなす梁の接合構造を示す図である。
【図3】本発明に係るプレキャスト鉄筋コンクリート梁を用いた、柱と該4面に梁が設けられた場合の接合構造を示す図である。
【図4】本発明に係るプレキャスト鉄筋コンクリート梁を用いた柱と、端部を向かい合う対をなす梁の接合方法を示す図である。
【図5】本発明に係るプレキャスト鉄筋コンクリート梁を用いた、柱と該4面に梁が設けられた場合の接合方法を示す図である。
【図6】本発明に係るプレキャスト鉄筋コンクリート梁を用いた、柱と該4面に梁が設けられた場合の他の接合構造を示す図である。
【符号の説明】
1 梁
2 上端筋
3 下端筋
4 主筋
5 あばら筋
6 プレキャストコンクリート
7 立ち上がり部
7a 孔
8 柱
9 継ぎ手
10 継ぎ手
11 梁筋
12 コンクリート
13 コンクリート止め
14 コンクリート型枠
15 床スラブ[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a precast reinforced concrete beam, a joint structure between a precast reinforced concrete beam and a column, and a method for joining a precast reinforced concrete beam and a column.
[0002]
[Prior art]
Conventionally, when constructing a reinforced concrete structure, a precast reinforced concrete column is constructed, a half-precast reinforced concrete beam is bridged, and concrete is poured into the joint between the column and the beam. After the beam and the beam are joined, a method of casting concrete on the floor to construct a frame is generally used. In such a construction method, it is necessary to install a concrete stopper on the upper surface of the beam between the joint with the column and the floor when concrete is poured into the joint between the column and the beam. Such a concrete stop needs to have a configuration that allows the upper end of the beam to penetrate, and does not cause any trouble in the structure even if the concrete stop is removed or buried on the floor as a discarded formwork. And the work is complicated, which hinders reduction of construction costs and shortening of construction period.
Under such circumstances, as shown in
[0003]
[Patent Document 1]
JP 2001-164688 A (p4, see FIG. 1)
[0004]
[Problems to be solved by the invention]
However, since the beam shown in
[0005]
In view of the above circumstances, the present invention provides a workable, inexpensive precast reinforced concrete beam, a precast reinforced concrete beam-to-column joining structure, and a method of joining a precast reinforced concrete beam-to-column when joining columns and beams. The purpose is.
[0006]
[Means for Solving the Problems]
The precast reinforced concrete beam according to
[0007]
In the precast reinforced concrete beam according to
[0008]
The joint structure between a precast reinforced concrete beam and a column according to
[0009]
5. The method of joining a precast reinforced concrete beam and a column according to claim 4, wherein a pair of precast reinforced concrete beams is erected on both sides of the column in the x-direction so as to abut end portions, and then opposite lower ends of the precast reinforced concrete beam. A first step of arranging a hoop streak in the joint of the pillar after forming a joint between the ends of the muscle, and a strut extending in the x direction across the joint of the pillar. A second step of arranging a plurality of beam reinforcements at the connection part of the joint and forming a joint at an end of the upper reinforcement provided on the end of the beam reinforcement and a pair of precast reinforced concrete beams facing the end; Thirdly, concrete is poured into both the joint portion of the pillar and the upper part of the precast reinforced concrete beam at both the rising portion and the area surrounded by the pillar so as to bury the joint between the bar and the upper bar. It is characterized in that it comprises a step.
[0010]
6. The method of joining a precast reinforced concrete beam and a column according to
[0011]
BEST MODE FOR CARRYING OUT THE INVENTION
FIGS. 1 to 6 show a precast reinforced concrete beam, a joint structure between a precast reinforced concrete beam and a column, and a method for joining a precast reinforced concrete beam and a column according to the present invention. The precast reinforced concrete beam of the present invention has a configuration in which the upper ends of the stirrups and stirrups are exposed from the precast concrete, and at the position where a predetermined distance is provided from the end on the upper surface of the precast concrete, a rising portion is provided, The length of the upper end was set to the length of the member located between the end of the precast concrete and the rising portion.
As a result, when joining the column and the beam, the joint relating to the upper end bar can be arranged inside the precast reinforced concrete beam, so that it is possible to simplify the arrangement of the reinforcement at the joint of the column and to use the rising part as a concrete stopper When the concrete is poured into the connection part, the step of installing and removing the concrete formwork can be omitted, and the workability can be improved.
[0012]
As shown in FIG. 1A, a precast reinforced
[0013]
In the
The upper limit of the height of the rising
[0014]
The
[0015]
In the present embodiment, the rising
[0016]
FIG. 1B shows an example of the rising
Here, the exposed height of the lath net is formed to be higher than at least the arrangement height of the
[0017]
As shown in FIG. 2, the joint structure between the
[0018]
On the other hand, since the upper end bars 2 of the paired
As a result, although the joint 9 between the
[0019]
A plurality of
[0020]
As described above, in the joint structure between the
[0021]
FIG. 2 shows a joint structure in which a pair of beams arranged with their ends facing each other is joined to both sides of the
[0022]
The above-described method of joining the half precast reinforced
First, in a first step, a pair of precast reinforced
Next, the coupler is installed so that the
When the
[0023]
After the above-described first step is completed, a pair of
Next, the
[0024]
In the second step, the same number of the
[0025]
After the above-described second step is completed, the same number of beam bars 11a as the
[0026]
In a third step, the connection portion of the
At this time, on the
[0027]
Note that the
As shown in FIG. 6, when the
[0028]
According to such a method, two pairs of
[0029]
According to the above-described configuration, since the rising
[0030]
Further, since the end of the upper reinforcing
[0031]
Further, in the joint structure between the
[0032]
In addition, in the method of joining the
[0033]
【The invention's effect】
According to the precast reinforced concrete beam according to
Alternatively, in the rising portion, a plate-like lath net having a lower portion fixed to the precast concrete and vertically erected is used, and the plate surface is arranged so as to be orthogonal to the upper end streak, and the upper end streak is It penetrates the mesh on the plate surface.
Thereby, the rising portion is arranged at the boundary between the joint portion with the column and the floor, and the rising portion is used for concrete casting at the time of joining the column and the beam and at the time of constructing the floor slab. Since it can be used as a concrete formwork, work relating to the formwork can be omitted, workability can be improved, and it is possible to greatly contribute to shortening of construction period and reduction of construction cost.
[0034]
According to the joint structure of a precast reinforced concrete beam and a column according to
Thereby, since the joint between the upper end bar and the beam bar is arranged at the end of the beam, not at the joint of the column, the arrangement of the bar at the column joint can be simplified, and the workability is improved. This can greatly contribute to shortening the construction period.
[0035]
According to the method for joining a precast reinforced concrete beam and a column according to
Alternatively, in the first step, before arranging the hoop reinforcement, a pair of precast reinforced concrete beams are erected on both sides of the column in the y direction so as to abut ends thereof, and opposed lower ends of the precast reinforced concrete beams. A joint is formed between the streaks, and after the second step, a plurality of beam streaks are arranged in the joint portion of the column so as to extend in the y direction across the joint portion of the column, A joint is formed at the end of the top bar provided on the section and the opposing pair of precast reinforced concrete beams.
[0036]
Thereby, since the arrangement of the bars related to the joint portion of the pillar is easy, it is possible to omit the operation of moving the position of the upper end muscle in order to arrange the hoop muscle in the joint portion of the pillar as in the related art, This eliminates the need for the rebar work of moving the upper end muscle or the reinforcement work of the hoop reinforcement. Further, by using the beam having the rising portion, it is possible to omit the installation work of the concrete formwork around the upper end muscle, which is complicated work, and it is possible to greatly shorten the construction period.
[Brief description of the drawings]
FIG. 1 is a view showing a precast reinforced concrete beam according to the present invention.
FIG. 2 is a diagram showing a joint structure of a column using a precast reinforced concrete beam according to the present invention and a pair of beams facing each other at an end.
FIG. 3 is a diagram showing a joint structure using a precast reinforced concrete beam according to the present invention when columns and beams are provided on the four surfaces.
FIG. 4 is a view showing a method of joining a column using a precast reinforced concrete beam according to the present invention and a pair of beams facing each other at an end.
FIG. 5 is a view showing a joining method using a precast reinforced concrete beam according to the present invention when columns and beams are provided on four surfaces thereof.
FIG. 6 is a view showing another joint structure using a precast reinforced concrete beam according to the present invention and a column and beams provided on the four surfaces.
[Explanation of symbols]
REFERENCE SIGNS
Claims (5)
該プレキャストコンクリートの天端面が、上端筋及びあばら筋の上部を露出する高さに形成され、その天端面には、プレキャストコンクリートの端部より所定の離間距離を有する位置に、少なくとも上端筋の配置高さよりも高さを有する立ち上がり部を有するとともに、
前記下端筋の端部が、前記プレキャストコンクリートの端部より突出し、
前記上端筋の端部が、前記プレキャストコンクリートの端部と立ち上がり部との間に位置することを特徴とするプレキャスト鉄筋コンクリート梁。Main bars consisting of a plurality of upper bars and lower bars, a plurality of stirrups, comprising precast concrete burying the stirrups and the main bars,
The top end surface of the precast concrete is formed at a height that exposes the upper ends of the upper streaks and stirrups, and at least the upper end streaks are disposed on the top end surface at a position separated by a predetermined distance from the end of the precast concrete. With a rising part having a height higher than the height,
The end of the lower streak protrudes from the end of the precast concrete,
The precast reinforced concrete beam, wherein an end of the upper reinforcing bar is located between an end of the precast concrete and a rising portion.
立ち上がり部に、下部を前記プレキャストコンクリートに固着されて鉛直に立設する板状のラス網が用いられており、板面を前記上端筋と直交するように配されて、該上端筋が板面の網目を貫通していることを特徴とするプレキャスト鉄筋コンクリート梁。The precast reinforced concrete beam according to claim 1,
In the rising portion, a plate-like lath net is used, the lower portion of which is fixed to the precast concrete and vertically erected, and the plate surface is disposed so as to be orthogonal to the upper end streak, and the upper end streak is Precast reinforced concrete beam, characterized by penetrating through the mesh of.
端部を向かい合わせて隣り合う前記プレキャスト鉄筋コンクリート梁の間に、前記柱が配置されて、
該柱の仕口部に、隣り合うプレキャスト鉄筋コンクリート梁に備えられた向かい合う下端筋の端部を連結する継ぎ手が形成されるとともに、隣り合う前記プレキャスト鉄筋コンクリート梁に備えられた向かい合う上端筋どうしを連結する複数の梁筋が配設され、
また、該梁筋の端部と前記上端筋の端部に継ぎ手が形成されて、該梁筋と前記上端筋の継ぎ手、及び下端筋の継ぎ手を埋設するように、コンクリートが打設されており、
前記梁筋と上端筋の継ぎ手が、前記プレキャスト鉄筋コンクリート梁の内方に形成されることを特徴とするプレキャストコンクリート梁と柱の接合構造。A joint structure between the precast reinforced concrete beam and the column according to claim 1 or 2,
The pillar is disposed between the precast reinforced concrete beams adjacent to each other with their ends facing each other,
At the connection part of the pillar, a joint is formed to connect the ends of the lower ends of the opposing precast reinforced concrete beams, and the upper ends of the opposing precast reinforced concrete beams are connected to each other. Multiple beam reinforcements are arranged,
Further, a joint is formed at an end of the beam bar and an end of the upper bar, and concrete is cast so as to bury the joint of the beam bar and the upper bar, and the joint of the lower bar. ,
A joint structure between a precast concrete beam and a column, wherein a joint between the beam reinforcement and an upper reinforcement is formed inside the precast reinforced concrete beam.
前記柱のx方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込んだ後、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋の端部どうしに継ぎ手を形成した上で、前記柱の仕口部にフープ筋を配設する第1の工程と、
前記柱の仕口部を跨ぎx方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成する第2の工程と、
前記梁筋と上端筋の継ぎ手を埋設するように、柱の仕口部、及びプレキャスト鉄筋コンクリート梁の上部で前記立ち上がり部と前記柱に囲まれる領域の両者に、コンクリートを打設する第3の工程を備えることを特徴とするプレキャスト鉄筋コンクリート梁と柱の接合方法。A method for joining a precast reinforced concrete beam and a column according to claim 3,
On both sides of the column in the x direction, a pair of precast reinforced concrete beams are erected so as to abut the ends, and a joint is formed between the ends of the lower end bars facing the precast reinforced concrete beams. A first step of arranging a hoop in a connection part of
A plurality of beam reinforcements were arranged at the column joints so as to extend in the x direction across the column joints, and were provided on a pair of precast reinforced concrete beams facing the ends of the beam reinforcements. A second step of forming a joint at the end of the upper muscle;
A third step of placing concrete in both the joint portion of the column and the upper part of the precast reinforced concrete beam both in the rising portion and the region surrounded by the column so as to bury the joint between the beam reinforcement and the upper end reinforcement. A method for joining a precast reinforced concrete beam and a column, comprising:
第1の工程で、フープ筋を配設する前に、前記柱のy方向の両側に、端部を突き合わせるように対をなすプレキャスト鉄筋コンクリート梁を建て込み、該プレキャスト鉄筋コンクリート梁の向かい合う下端筋どうしに継ぎ手を形成し、
第2の工程の後、前記柱の仕口部を跨ぎy方向に延在するように、柱の仕口部に梁筋を複数配置し、該梁筋の端部とこれと向かい合う対をなすプレキャスト鉄筋コンクリート梁に備えられた上端筋の端部に継ぎ手を形成することを特徴とするプレキャスト鉄筋コンクリート梁と柱の接合方法。The method for joining a precast reinforced concrete beam and a column according to claim 4,
In the first step, before arranging the hoop reinforcing bars, a pair of precast reinforced concrete beams are erected on both sides of the column in the y direction so as to abut end portions, and opposed lower reinforcing bars of the precast reinforced concrete beams. Forming a joint in
After the second step, a plurality of beam streaks are arranged in the joint portion of the pillar so as to extend in the y direction across the joint portion of the pillar, and form a pair facing the end portion of the beam strut. A method for joining a precast reinforced concrete beam and a column, wherein a joint is formed at an end of a top reinforcing bar provided on the precast reinforced concrete beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003087717A JP2004293180A (en) | 2003-03-27 | 2003-03-27 | Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003087717A JP2004293180A (en) | 2003-03-27 | 2003-03-27 | Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004293180A true JP2004293180A (en) | 2004-10-21 |
Family
ID=33402038
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003087717A Withdrawn JP2004293180A (en) | 2003-03-27 | 2003-03-27 | Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004293180A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008115539A (en) * | 2006-10-31 | 2008-05-22 | Okumura Corp | Flat plate construction method |
CN108755949A (en) * | 2018-07-11 | 2018-11-06 | 上海应用技术大学 | Assembly concrete girder and time beam connecting node and construction method |
CN109629748A (en) * | 2019-01-17 | 2019-04-16 | 江西联保工程咨询有限公司 | A kind of prefabricated convex beam and its application method of limited destructing |
CN110512785A (en) * | 2019-09-27 | 2019-11-29 | 福建工程学院 | A kind of end tongue and groove does not go out the unidirectional superimposed sheet of muscle and formwork erecting structure and construction method |
CN114382172A (en) * | 2021-12-27 | 2022-04-22 | 三能集成房屋股份有限公司 | Fully-assembled building and building method thereof |
CN115045440A (en) * | 2022-06-21 | 2022-09-13 | 苏州思萃融合基建技术研究所有限公司 | Prefabricated column component with steel pipe joints at two ends and construction method thereof |
JP7404603B2 (en) | 2019-12-26 | 2023-12-26 | 株式会社竹中工務店 | Column beam joint structure |
-
2003
- 2003-03-27 JP JP2003087717A patent/JP2004293180A/en not_active Withdrawn
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008115539A (en) * | 2006-10-31 | 2008-05-22 | Okumura Corp | Flat plate construction method |
CN108755949A (en) * | 2018-07-11 | 2018-11-06 | 上海应用技术大学 | Assembly concrete girder and time beam connecting node and construction method |
CN109629748A (en) * | 2019-01-17 | 2019-04-16 | 江西联保工程咨询有限公司 | A kind of prefabricated convex beam and its application method of limited destructing |
CN110512785A (en) * | 2019-09-27 | 2019-11-29 | 福建工程学院 | A kind of end tongue and groove does not go out the unidirectional superimposed sheet of muscle and formwork erecting structure and construction method |
CN110512785B (en) * | 2019-09-27 | 2024-05-10 | 福建工程学院 | Unidirectional superimposed sheet with no rib at end rabbet and formwork structure and construction method |
JP7404603B2 (en) | 2019-12-26 | 2023-12-26 | 株式会社竹中工務店 | Column beam joint structure |
CN114382172A (en) * | 2021-12-27 | 2022-04-22 | 三能集成房屋股份有限公司 | Fully-assembled building and building method thereof |
CN115045440A (en) * | 2022-06-21 | 2022-09-13 | 苏州思萃融合基建技术研究所有限公司 | Prefabricated column component with steel pipe joints at two ends and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2006348664A (en) | Connecting method of precast concrete column/beam member | |
JP2004293180A (en) | Precast reinforced concrete beam, joint structure for precast concrete beam and pole, and method of joining precast concrete beam and pole | |
JP6635801B2 (en) | Precast concrete wall joining structure and precast concrete wall joining method | |
JP6636345B2 (en) | RC building and construction method of RC building | |
JP4657993B2 (en) | Beam-column joint structure and construction method thereof | |
KR101880813B1 (en) | A sandwitch pc pannel structure and construction method of structure using thereof | |
JP2004263502A (en) | Work execution method for bridge | |
JP7230317B2 (en) | Column construction method | |
KR20210004289A (en) | Transfer Structure Construction Method Using U-shaped Steel Girder | |
JP2749474B2 (en) | Reverse construction method for underground structures | |
JPH08302808A (en) | Connecting method of large pc wall board | |
JP2003313944A (en) | Construction method for joining precast concrete panel zone with lower column member | |
JP2003041516A (en) | Integral structure of upper and lower parts of continuous girder bridge and method of constructing it | |
JP2004197347A (en) | Construction method of cross girder-integrated concrete floor slab | |
JP2004308316A (en) | Column of precast reinforced concrete construction, and frame structure of structure | |
JPH0420639A (en) | Pc small beam | |
JPS63167825A (en) | Precast concrete beam and building construction method using the same | |
JPH06306931A (en) | Construction of steel frame reinforced concrete structure | |
JP2651322B2 (en) | Construction method of wall type rigid frame structure | |
JP2651321B2 (en) | Anchoring method of beam in wall type rigid frame structure | |
JP2017078258A (en) | Construction method of slab structure | |
JP2023022563A (en) | Concrete wall construction method | |
CN116084576A (en) | Construction method of embedded steel skeleton | |
JP6195463B2 (en) | building | |
JPH0725102U (en) | Frame joint structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20060606 |