JP2004293176A - Protective scaffold unit for bridge and protective construction method using it - Google Patents
Protective scaffold unit for bridge and protective construction method using it Download PDFInfo
- Publication number
- JP2004293176A JP2004293176A JP2003087581A JP2003087581A JP2004293176A JP 2004293176 A JP2004293176 A JP 2004293176A JP 2003087581 A JP2003087581 A JP 2003087581A JP 2003087581 A JP2003087581 A JP 2003087581A JP 2004293176 A JP2004293176 A JP 2004293176A
- Authority
- JP
- Japan
- Prior art keywords
- bridge
- protective
- unit
- frame
- rotation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、橋梁に対して、塗装やメンテナンス等の各作業を行う際に使用される防護足場ユニットに関し、特に、その組立や解体を、橋梁脇下の道路の通行規制を行うことなく施工できるようにした橋梁用の防護足場ユニット、及びこれを用いた防護工法に関するものである。
【0002】
【従来の技術】
橋梁に対して、塗装やメンテナンス等の各作業を安全に行うには、当然「足場」が必要であるが、この足場の組み立てや解体は、他の邪魔にならないように行えるものであることも必要である。
【0003】
例えば、一般道路上に高速道路を「橋梁」を利用して建設した場合、この高速道路用橋梁のメンテンナンス作業は、できれば下の一般道路の通行を妨げないようにして行わなければならない。
【0004】
このような一般道路上の高速道路用橋梁に対して、塗装やメンテナンス等の各作業を安全に行う「足場」としては、例えば、特許文献1に記載されているような「橋梁の移動式防護工」、あるいは特許文献2に記載されているような「防護工およびその移動方法」がある。
【0005】
【特許文献1】特開平5−295712号公報、要約及び選択図
【特許文献2】特開2000−74016号公報、要約及び選択図
【0006】
【発明が解決しようとする課題】
特許文献1に記載されている「橋梁の移動式防護工」は、「高所作業における危険度を最小限にすると共に、橋梁下に道路のある場合でも、交通規制に伴う費用を省ける橋梁の移動式防護工を提供する」ことを目的として、図7に示すように、「橋梁の主桁1に沿って予めレール25を取り付けておき、そのレール25上を移動自在なローラ13を上部に仕込んだ治具14を介しておやごパイプ15を吊り下げて吊足場20を組み立てた後、順次、引きだし設置する」ようにしたものである。
【0007】
しかしながら、この特許文献1に記載された方法では、上記特許文献1の段落0009に記載されているように、「主桁1の下フランジ1Aに沿って予めレール25が溶接などで取り付けられている」ようにすることが前提となっているのであり、レール25の溶接作業等は、当該「橋梁の移動式防護工」なしで行わなければならないものとなっている。
【0008】
つまり、橋梁自体のメンテンナンス作業は当該「橋梁の移動式防護工」を使用して行えるが、その組立作業時には高所作業における危険度が減るわけでも、また交通規制をしなくても済むというものではない。
【0009】
また、特許文献2に記載されているような「防護工およびその移動方法」は、「防護工の組み立て及び撤去作業を容易に行うこと」を目的としてなされたもので、図8にも示すように、「橋桁にガイドローラを有する複数の支承手段を取り付ける」ことが前提となっているものであり、この特許文献2に記載されている防護工でも、その組立作業時には危険を伴うと考えられる。
【0010】
それだけでなく、これらの特許文献1及び2に示された防護工では、橋梁の側面(高速道路用の橋梁にあっては道路側に露出している面)でのメンテナンスを行う際には、図6に示したような側板(以下の本発明を構成している回動枠12に該当する部分)の組立や解体は、道路規制を行わないとできない構造になっているのである。
【0011】
そこで、本発明者は、この種の防護工において、その組立作業時及び解体作業時においても、交通規制を全くする必要がないようにするにはどうしたらよいか、について種々検討を重ねてきた結果、本発明を完成したのである。
【0012】
すなわち、本発明の主たる目的とするところは、その組立及び解体作業時においても、交通規制をする必要がなく、しかも本工事の際には安全に作業を行えるようにすることのできる防護足場ユニット、及びこれを使用した防護工法を、簡単な構成によって提供することにある。
【0013】
【課題を解決するための手段】
以上の課題を解決するために、まず、請求項1に掛かる発明の採った手段は、後述する実施の形態の説明中において使用する符号を付して説明すると、
「橋梁20のメンテナンス等の各種作業を行うための防護足場ユニット10であって、
橋梁20の主桁21に吊下されるユニット本体11と、このユニット本体11を構成してる横梁11aの外端に開閉可能に設けた回動枠12とにより構成したことを特徴とする橋梁用の防護足場ユニット10」
である。
【0014】
すなわち、この請求項1に係る防護足場ユニット10は、図6に示すように、完成されたときの基本的構成を従来のものと略同じとなるようにしたものではあるが、その根本的な差異は、橋梁20の主桁21に吊下されるユニット本体11の端部に、回転ヒンジ12aを介して回動枠12を回動自在に設けたことにある。
【0015】
つまり、この防護足場ユニット10は、これを必要個所に運搬したり保管したりする場合には、図1に示すように、回動枠12をユニット本体11上に折り畳んで橋梁20の直下に配置できるものであり、この場合には、橋梁20の直下から外側にははみ出さないようにしたものである。また、この防護足場ユニット10は、橋梁20の直下から外側にははみ出ないものであるから、橋梁20の直下にて作業車40による吊り上げや吊り下げ作業を、道路側にはみ出さないようにしながら行えるものである。
【0016】
この防護足場ユニット10が橋梁20に吊下されれば、その上で橋梁20のメンテンナンス作業が行えるのであり、これが高所作業に拘わらず、当該防護足場ユニット10は作業者の支持を行って安全な作業とするのである。
【0017】
ところで、この防護足場ユニット10を使用して、橋梁20の側面(高速道路用の橋梁にあっては道路側に露出している面)のメンテナンスを行うには、ユニット本体11上に折り畳んでおいた回動枠12を、図3〜図7に示すように、道路上側に回動させるのである。この回動操作は、橋梁20の主桁21に吊下されているユニット本体11上、つまり道路上ではない個所において行えるのであり、その際には道路規制をする必要は全くないのである。
【0018】
なお、回動枠12の回転角度は、図4にも示すように、自由に設定することができるのであり、後述する実施形態のものでは、最大水平状態になるまで、回動可能なものとなっている。勿論、図6に示した状態となるようにすれば、回動枠12によって作業中に物が道路上に落下するようなことがないことはいうまでもない。
【0019】
そして、以上の橋梁20のメンテナンスが済めば、上述したのとは逆の方向で、解体作業を行えばよい。
【0020】
従って、この請求項1に係る防護足場ユニット10は、その組立及び解体作業時においても、交通規制をする必要がなく、しかも本工事の際には安全に作業を行えるようにすることのできる防護足場ユニット、及びこれを使用した防護工法を、簡単な構成によって提供することができるのである。
【0021】
さて、上記課題を解決するために、請求項2に係る発明の採った手段は、上記請求項1に記載の橋梁用の防護足場ユニット10について、
「横梁11aの回動枠12に隣接した部分、及び回動枠12に、チェーンやワイヤ等の索条30を連結するための連結部13を設けたこと」
である。
【0022】
すなわち、この請求項2に係る防護足場ユニット10は、図4にも示すように、回動枠12を回動したときの角度調整や固定を、チェーンやワイヤ等の索条30の連結によって簡単におこなえるようにすることのできる連結部13を、横梁11aの回動枠12に隣接した部分、及び回動枠12に設けたものである。
【0023】
これにより、この請求項2の防護足場ユニット10では、各連結部13間をチェーンやワイヤ等の索条30によって固定化できるものであり、作業中の安全をより一層高めることができるものとなっている。
【0024】
上記課題を解決するために、請求項3に係る発明の採った手段は、上記請求項1または請求項2に記載の橋梁用の防護足場ユニット10について、
「回動枠12の横梁11aに対する連結部分(回転ヒンジ12a)に、当該回動枠12が水平状になったときにその回動を阻止する回転止め固定プレート14を設けたこと」
である。
【0025】
すなわち、この請求項3の防護足場ユニット10は、回動枠12が道路上側に垂れ下がるようなことがあってはならないから、これを阻止するもの、つまり回転止め固定プレート14を、図4及び図5に示すように、回動枠12の横梁11aに対する連結を行っている回転ヒンジ12aに設けたものである。
【0026】
この回転止め固定プレート14の存在によって、図4に示すように、回動枠12の水平状態となったときの回動を阻止することができるのであり、これによって、回動枠が道路上に垂れ下がってしまうことを防止するだけでなく、橋梁20の下面は勿論、側面における作業をより安全に行えるようにするのである。
【0027】
上記課題を解決するために、請求項4に係る発明の採った手段は、
「橋梁20の主桁21に吊下されるユニット本体11と、このユニット本体11を構成してる横梁11aの外端に開閉可能に設けた回動枠12とにより構成した足場ユニット10を、次の各工程の順に組み立て、または次の各工程の逆順で解体するようにしたことを特徴とする防護足場ユニット10を用いた防護工法。
【0028】
(1)回動枠12を折り畳んだ状態にしてある防護足場ユニット10を施工現場に搬入する工程;
(2)この防護足場ユニット10を吊り上げて、主桁21に吊下する工程;
(3)回動枠12を横梁11aに対して回動することにより開放し、横梁11aと回動枠12間を索条30により連結することにより、所定角度で保持する工程」
である。
【0029】
すなわち、この防護工法によれば、上記請求項1〜3のいずれかの防護足場ユニット10を使用したものであり、橋梁20のメンテナンス作業を、道路の封鎖や規制をすることなく行えるのである。
【0030】
【発明の実施の形態】
次に、上記のように構成した各請求項に係る発明を、図面に示した実施の形態である防護足場ユニット10について、これを使用した防護工法とともに説明する。なお、実施形態の防護足場ユニット10は、上記請求項1〜3のいずれかのそれを実質的に含むものである。
【0031】
図1には、本発明に係る防護足場ユニット10を使用する対象であって、高速道路を構成する橋梁20が示してあり、この橋梁20の図示横方向端部の直下から外側に出る部分が一般道路である。勿論、この橋梁20の下面には主桁21が形成してあって、この主桁21により橋梁20の補強がなされているものである。また、この橋梁20は、T字状の橋脚22上に支持されていて、一般道路より高い所に位置するようにしてある。
【0032】
さて、この図1に示した橋梁20の直下には、本発明に係る防護足場ユニット10が、その回動枠12を折り畳んだ状態で運び込まれており、その一般道路側端部は、一般道路内に突出しないように配置してある。この防護足場ユニット10は、図2に示すような作業車40によって、図3に示すように橋梁20の主桁21に吊下されるのである。
【0033】
この防護足場ユニット10は、これを展開すれば図6に示すような形状となるものであり、図1及び図6に示したように、横梁11a等を組み合わせて形成したユニット本体11と、図4及び図5に示したように、このユニット本体11の端部に回転ヒンジ12aを介して回動自在に連結した回動枠12とからなっているものである。
【0034】
また、この防護足場ユニット10を構成している横梁11aの回動枠12に隣接した部分、及び回動枠12には、図4に示したように、チェーンやワイヤ等の索条30を連結するための連結部13が設けてある。
【0035】
さらに、この防護足場ユニット10を構成している回動枠12の横梁11aに対する連結部分、つまり回転ヒンジ12aの近傍には、図4及び図5に示したように、当該回動枠12が水平状になったときにその回動を阻止する回転止め固定プレート14が設けてある。
【0036】
なお、図5中の符号15は接続ピンを示すものであるが、この接続ピン15は、ユニット本体11上に折り畳んだ回動枠12の、ユニット本体11に対する固定を行うものである。
【0037】
【発明の効果】
以上詳述した通り、請求項1〜3に係る発明においては、
「橋梁20のメンテナンス等の各種作業を行うための防護足場ユニット10であって、
橋梁20の主桁21に吊下されるユニット本体11と、このユニット本体11を構成してる横梁11aの外端に開閉可能に設けた回動枠12とにより構成したこと」
に、その主たる構成上の特徴があり、これにより、その組立及び解体作業時においても、交通規制をする必要がなく、しかも本工事の際には安全に作業を行えるようにすることのできる防護足場ユニット10を、簡単な構成によって提供することができるのである。
【0038】
また、請求項4に係る発明においては、上記請求項1〜3の橋梁用の防護足場ユニット10を採用しながら、次の各工程、
(1)回動枠12を折り畳んだ状態にしてある防護足場ユニット10を施工現場に搬入する工程;
(2)この防護足場ユニット10を吊り上げて、主桁21に吊下する工程;
(3)回動枠12を横梁11aに対して回動することにより開放し、横梁11aと回動枠12間を索条30により連結することにより、所定角度で保持する工程の順に組み立て、または次の各工程の逆順で解体するようにしたことにその特徴があり、これにより、橋梁20のメンテナンス作業を、安全に、しかも道路規制を実施することなく、行うことができるのである。
【図面の簡単な説明】
【図1】本発明の防護足場ユニットが使用されるべき橋梁の正面図である。
【図2】同橋梁下に作業車を配置した状態を示す正面図である。
【図3】本発明に係る防護足場ユニットを橋梁の主桁に吊下下状態を示す正面図である。
【図4】図3中のA部の拡大正面図である。
【図5】図4中のb部の拡大正面図である。
【図6】本発明に係る防護足場ユニットであって、その回動枠を回転して展開したときの斜視図である。
【図7】従来技術を示す正面図である。
【図8】別の従来技術を示す側面図である。
【符号の説明】
10 防護足場ユニット
11 ユニット本体
11a 横梁
12 回動枠
12a 回転ヒンジ
13 連結部
14 回転止め固定プレート
15 接続ピン
20 橋梁
21 主桁
22 橋脚
30 索条
40 作業車[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a protective scaffold unit used when performing various operations such as painting and maintenance on a bridge, and in particular, can assemble and disassemble the bridge without restricting the traffic on a road under the bridge. The present invention relates to a protective scaffold unit for a bridge and a protective method using the same.
[0002]
[Prior art]
Naturally, "scaffolding" is necessary to safely perform painting, maintenance, and other work on bridges, but this scaffolding can be assembled and dismantled without obstructing other things. is necessary.
[0003]
For example, when a highway is constructed on a general road using a "bridge", maintenance work on the highway bridge must be performed so as not to hinder the traffic on the general road below if possible.
[0004]
As a "scaffold" for safely performing various operations such as painting and maintenance on such a highway bridge on a general road, for example, a "mobile protection system for a bridge" as described in
[0005]
[Patent Document 1] Japanese Patent Application Laid-Open No. 5-295712, Abstract and Selection Diagram [Patent Document 2] Japanese Patent Application Laid-Open No. 2000-74016, Abstract and Selection Diagram
[Problems to be solved by the invention]
[0007]
However, in the method described in
[0008]
In other words, the maintenance work of the bridge itself can be performed using the "mobile protective work for the bridge", but at the time of the assembling work, the danger of working at heights is reduced, and traffic regulation is not required. is not.
[0009]
In addition, the “protective work and its moving method” as described in
[0010]
In addition, in the protective works disclosed in
[0011]
The inventor of the present invention has been conducting various studies on how to prevent traffic from being required at all during the assembling work and the dismantling work in this kind of protective work. As a result, the present invention has been completed.
[0012]
That is, the main object of the present invention is to provide a protective scaffolding unit that does not need to regulate traffic even during its assembling and disassembling operations, and that can perform safe operations at the time of main construction. And a protection method using the same with a simple configuration.
[0013]
[Means for Solving the Problems]
In order to solve the above problems, first, means adopted by the invention according to
"The
A bridge, comprising: a unit
It is.
[0014]
That is, as shown in FIG. 6, the
[0015]
In other words, when the
[0016]
If the
[0017]
By the way, in order to use the
[0018]
The rotation angle of the
[0019]
Then, after the maintenance of the bridge 20 is completed, the dismantling operation may be performed in the opposite direction to the above.
[0020]
Therefore, the
[0021]
By the way, in order to solve the above-mentioned problem, the means adopted by the invention according to
"A portion of the
It is.
[0022]
That is, in the
[0023]
Thereby, in the
[0024]
In order to solve the above-mentioned problem, means taken by the invention according to
"A connection portion (
It is.
[0025]
That is, the
[0026]
Due to the presence of the rotation
[0027]
Means taken by the invention according to
A
[0028]
(1) a step of carrying the
(2) a step of lifting the
(3) Step of opening the
It is.
[0029]
That is, according to this protective construction method, the
[0030]
BEST MODE FOR CARRYING OUT THE INVENTION
Next, the invention according to each claim configured as described above will be described together with a protection method using the
[0031]
FIG. 1 shows a bridge 20 which is a target to which the
[0032]
By the way, just below the bridge 20 shown in FIG. 1, the
[0033]
When this
[0034]
Further, as shown in FIG. 4, a
[0035]
Further, as shown in FIG. 4 and FIG. 5, the rotating
[0036]
[0037]
【The invention's effect】
As described in detail above, in the invention according to
"The
The
The main structural feature is that, even during the assembling and disassembling work, there is no need to regulate the traffic, and the protective work can be done safely during the construction work. The
[0038]
In the invention according to
(1) a step of carrying the
(2) a step of lifting the
(3) The
[Brief description of the drawings]
FIG. 1 is a front view of a bridge in which a protective scaffold unit of the present invention is to be used.
FIG. 2 is a front view showing a state where a work vehicle is arranged under the bridge.
FIG. 3 is a front view showing a state where the protective scaffold unit according to the present invention is suspended from a main girder of a bridge.
FIG. 4 is an enlarged front view of a portion A in FIG.
FIG. 5 is an enlarged front view of a portion b in FIG.
FIG. 6 is a perspective view of the protective scaffold unit according to the present invention when the rotating frame is rotated and deployed.
FIG. 7 is a front view showing a conventional technique.
FIG. 8 is a side view showing another conventional technique.
[Explanation of symbols]
DESCRIPTION OF
Claims (4)
前記橋梁の主桁に吊下されるユニット本体と、このユニット本体を構成してる横梁の外端に開閉可能に設けた回動枠とにより構成したことを特徴とする橋梁用の防護足場ユニット。A protective scaffolding unit for performing various tasks such as bridge maintenance,
A protective scaffolding unit for a bridge, comprising: a unit main body suspended from a main girder of the bridge; and a rotatable frame provided at an outer end of a cross beam constituting the unit main body so as to be openable and closable.
(1)回動枠を折り畳んだ状態にしてある防護足場ユニットを施工現場に搬入する工程;
(2)この防護足場ユニットを吊り上げて、前記主桁に吊下する工程;
(3)前記回動枠を前記横梁に対して回動することにより開放し、前記横梁と回動枠間を索条により連結することにより、所定角度で保持する工程。Assembling a scaffolding unit composed of a unit main body suspended from a main girder of a bridge and a rotatable frame provided at the outer end of a cross beam that constitutes the main body so as to be openable and closable, in the order of each of the following steps, or A protective construction method using a protective scaffolding unit, which is dismantled in the reverse order of each step.
(1) carrying the protective scaffolding unit with the rotating frame folded into the construction site;
(2) lifting the protective scaffolding unit and suspending it on the main girder;
(3) a step of opening the rotating frame by rotating with respect to the horizontal beam, and holding the horizontal frame at a predetermined angle by connecting the horizontal beam and the rotating frame with a cable;
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003087581A JP2004293176A (en) | 2003-03-27 | 2003-03-27 | Protective scaffold unit for bridge and protective construction method using it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003087581A JP2004293176A (en) | 2003-03-27 | 2003-03-27 | Protective scaffold unit for bridge and protective construction method using it |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004293176A true JP2004293176A (en) | 2004-10-21 |
Family
ID=33401939
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003087581A Ceased JP2004293176A (en) | 2003-03-27 | 2003-03-27 | Protective scaffold unit for bridge and protective construction method using it |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004293176A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101332763B1 (en) | 2011-09-01 | 2013-11-25 | 김진곤 | Working rack of safety net for box type structure |
JP2017141564A (en) * | 2016-02-08 | 2017-08-17 | 公益財団法人鉄道総合技術研究所 | Bridge girder snow prevention structure |
JP2018084086A (en) * | 2016-11-24 | 2018-05-31 | 三井住友建設株式会社 | Bridge inspection device |
CN113699896A (en) * | 2021-10-08 | 2021-11-26 | 中化学交通建设集团有限公司 | Intercommunication bridge construction multiple spot console mode steelframe protector |
-
2003
- 2003-03-27 JP JP2003087581A patent/JP2004293176A/en not_active Ceased
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101332763B1 (en) | 2011-09-01 | 2013-11-25 | 김진곤 | Working rack of safety net for box type structure |
JP2017141564A (en) * | 2016-02-08 | 2017-08-17 | 公益財団法人鉄道総合技術研究所 | Bridge girder snow prevention structure |
JP2018084086A (en) * | 2016-11-24 | 2018-05-31 | 三井住友建設株式会社 | Bridge inspection device |
CN113699896A (en) * | 2021-10-08 | 2021-11-26 | 中化学交通建设集团有限公司 | Intercommunication bridge construction multiple spot console mode steelframe protector |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9528285B2 (en) | Safety barrier netting system with rigid panel net supports and stopper mechanisms | |
JP5601679B2 (en) | Improved fall prevention barrier | |
US20180038122A1 (en) | Safety Barrier Netting System | |
JP6798082B2 (en) | How to replace the main cable of the suspension bridge | |
JP2009091123A (en) | Crane for steel tower | |
JP2004293176A (en) | Protective scaffold unit for bridge and protective construction method using it | |
JP2824684B2 (en) | Bridge pier inspection and repair scaffold | |
KR20110087164A (en) | Apparatus for constructing a bridge by using precast segmental method | |
CN109610800A (en) | A kind of architectural engineering movable altitude faces side safety work device and application method | |
JP2005299111A (en) | Temporary strut and its erection method | |
JP2005023623A (en) | Suspension device for suspension scaffold for bridge and suspension scaffold assembling construction method using this device | |
JP2002356297A (en) | Steel tower constructing crane and steel tower construction method using crane | |
JP6261089B2 (en) | Work gondola | |
KR100997933B1 (en) | Foldable bridge inspection apparatus and the construction method using the same | |
KR100904031B1 (en) | Bridge construction method | |
JP4643648B2 (en) | Bridge erection method | |
JPH09195228A (en) | Build-up trestle for bridge pier reinforcing work and its using method | |
JP2012202162A (en) | Bridge crane, bridge erection method and bridge removal method | |
KR20110006315A (en) | Angle-adjustable support device of pathway for checking bridge safety and pathway apparatus using it | |
JP2809612B2 (en) | Partial work scaffold and method of erection of joint scaffold using this | |
JP3019857U (en) | Suspension bracket for overhanging scaffold | |
JP2004360302A (en) | Suspending device for suspending scaffold for bridge and assembling construction method using this device | |
JP2004316070A (en) | Protection scaffold unit for bridge and protection method using the same | |
JP2004197364A (en) | Timbering | |
KR102491378B1 (en) | Removable Fall Prevention Cradle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060317 |
|
A977 | Report on retrieval |
Effective date: 20080228 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080310 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080509 |
|
RD12 | Notification of acceptance of power of sub attorney |
Effective date: 20080509 Free format text: JAPANESE INTERMEDIATE CODE: A7432 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20080509 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Effective date: 20080701 Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A045 | Written measure of dismissal of application |
Free format text: JAPANESE INTERMEDIATE CODE: A045 Effective date: 20081125 |