JP2012202162A - Bridge crane, bridge erection method and bridge removal method - Google Patents

Bridge crane, bridge erection method and bridge removal method Download PDF

Info

Publication number
JP2012202162A
JP2012202162A JP2011069547A JP2011069547A JP2012202162A JP 2012202162 A JP2012202162 A JP 2012202162A JP 2011069547 A JP2011069547 A JP 2011069547A JP 2011069547 A JP2011069547 A JP 2011069547A JP 2012202162 A JP2012202162 A JP 2012202162A
Authority
JP
Japan
Prior art keywords
bridge
girder
leg
crane
moved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2011069547A
Other languages
Japanese (ja)
Other versions
JP5702640B2 (en
Inventor
Toshiyuki Tachikawa
俊之 舘川
Kazuyoshi Maruoka
和義 丸岡
Susumu Nagai
進 永井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SMCTECH CO Ltd
Sumitomo Mitsui Construction Co Ltd
Original Assignee
SMCTECH CO Ltd
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SMCTECH CO Ltd, Sumitomo Mitsui Construction Co Ltd filed Critical SMCTECH CO Ltd
Priority to JP2011069547A priority Critical patent/JP5702640B2/en
Publication of JP2012202162A publication Critical patent/JP2012202162A/en
Application granted granted Critical
Publication of JP5702640B2 publication Critical patent/JP5702640B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a bridge crane capable of minimizing necessity of traffic regulation when erecting a precast girder and then easily executing transfer work to the next erection span.SOLUTION: When erecting a precast girder 14 to an erection span S0, by a bridge crane 110 installed on an upper surface of a bridge pier 12A, in the state of hoisting and supporting the precast girder 14 through a girder hoisting nose 50, it is hoisted and moved to an erection scheduled position in a bridge axis orthogonal direction. At the time, a second leg 140 of the bridge crane 110 comprises a pair of movable legs 140A and 140B. Then, when a hoisting device 150 is moved in the bridge axis orthogonal direction and passes through installation parts of the respective movable legs 140A and 140B, the respective movable legs 140A and 140B are successively moved to an interference evading position at which it is possible to evade interference with the girder hoisting nose 50 hoisted and supported by the hoisting device 150. Thus, the girder hoisting nose 50 is prevented from interfering with both of the movable legs 140A and 140B.

Description

本願発明は、桁の架設または撤去の際に、橋脚の上面に設置した状態で用いられる橋形クレーンに関するものであり、また、これを用いた橋梁架設方法および橋梁撤去方法に関するものである。   The present invention relates to a bridge-type crane that is used in the state of being installed on the upper surface of a bridge pier when a girder is erected or removed, and to a bridge erection method and a bridge removal method using the crane.

従来より、多径間連続橋等の橋梁架設方法として、架設径間の橋軸方向両側に位置する1対の橋脚相互間に、複数の桁を橋軸直交方向に所定間隔をおいて架設する方法が知られている。   Conventionally, as a method of erection of bridges such as multi-span continuous bridges, a plurality of girders are erected at a predetermined interval in the direction perpendicular to the bridge axis between a pair of bridge piers located on both sides of the bridge axis between the installation diameters. The method is known.

このような架設方法としては、移動式クレーンを用いて各桁を直接架設する方法や、架設径間の側方に位置する搬入ヤードに設置された支保工と橋脚とに跨るように設置された片足張出し式の橋形クレーンを用いて架設する方法が一般的である。   As such erection methods, each girder was directly erected using a mobile crane, or installed so as to straddle the support works and bridge piers installed in the carry-in yard located on the side between the erection diameters. A method of erection using a one-leg overhang type bridge crane is common.

一方「特許文献1」には、橋軸方向に延びる架設用ガーダを架設径間に跨るように設置し、この架設用ガーダで桁を吊り支持した状態で、その横取りを行うようにした橋梁架設方法が記載されている。   On the other hand, in “Patent Document 1”, a bridge erection in which a girder for installation extending in the bridge axis direction is installed so as to straddle the erection diameter, and the girder is suspended and supported by the girder for erection, and the bridge is installed. A method is described.

その際、この「特許文献1」に記載された橋梁架設方法においては、1対の橋脚の各々の上面に設置された橋軸直交方向に延びる横取りレールに対して、その長手方向に移動可能な態様で架設用ガーダを設置しておき、この架設用ガーダにより、架設径間の側端位置において複数の桁を順次吊り上げて、その架設予定位置まで橋軸直交方向に移動させて吊り下ろすようにしている。   At that time, in the bridge erection method described in “Patent Document 1”, it is possible to move in the longitudinal direction with respect to a horizontal rail that extends in a direction perpendicular to the bridge axis and is installed on the upper surface of each pair of bridge piers. The installation girder is installed in this manner, and with this installation girder, a plurality of girders are sequentially lifted at the side end positions between the installation diameters, and moved to the planned installation position in the direction perpendicular to the bridge axis and suspended. ing.

特開2009−68249号公報JP 2009-68249 A

移動式クレーンを用いた架設方法では、架設作業中は架設径間が移動式クレーンによって占有されてしまい、また、片足張出し式の橋形クレーンを用いた橋梁架設方法では、搬入ヤードに支保工が設置されてしまうので、架設径間に既設道路が存在するような場合には、長時間にわたって交通を規制する必要がある、という問題がある。   In the construction method using a mobile crane, the construction span is occupied by the mobile crane during the construction work, and in the bridge construction method using a one-foot overhang type bridge crane, the support yard is installed in the carry-in yard. Since it is installed, there is a problem that it is necessary to regulate traffic for a long time when there is an existing road between the spans.

さらに、移動式クレーンを用いた架設方法では、移動式クレーン自体が大型のものとなるので、架設径間の地盤整備や地盤改良を広範囲にわたって行うことが必要となり、架設作業を効率良く行うことができない、という問題もある。   Furthermore, in the construction method using a mobile crane, since the mobile crane itself is large, it is necessary to perform ground maintenance and ground improvement over a wide range of construction spans, and the construction work can be performed efficiently. There is also the problem that it is not possible.

一方、上記「特許文献1」に記載された橋梁架設方法のように、架設用ガーダにより桁を吊り支持した状態で桁の横取りを行うようにすれば、架設径間や搬入ヤードが重機や架設用機材によって長時間占有されてしまうことはなくなるので、架設径間に既設道路が存在するような場合においても、交通規制の必要性を最低限に抑えることが可能となる。しかしながら、このような橋梁架設方法を採用した場合においても、次の架設径間に架設用ガーダを移設する際には、ある程度大型のクレーンを用いることが必要となってしまう、という問題がある。   On the other hand, if the girder is taken with the girder suspended and supported by the girder for erection as in the bridge erection method described in the above-mentioned “Patent Document 1,” the span between the erection spans and the carry-in yard becomes heavy machinery or erection. Since it will not be occupied for a long time by the equipment, even if there is an existing road between the spans, it is possible to minimize the need for traffic regulation. However, even when such a bridge erection method is adopted, there is a problem that it is necessary to use a crane that is large to some extent when the erection girder is moved between the erection diameters.

これに対し、架設径間の橋軸方向両側に位置する1対の橋脚の各々の上面に橋形クレーンを設置し、これら1対の橋形クレーンを用いて両橋脚相互間に桁を架設することができれば、これら各橋形クレーンは上記架設用ガーダに比して軽量であり、また横取りレールの設置が不要であるので、次の架設径間への移設作業を容易に行うことが可能となる。   On the other hand, a bridge crane is installed on the upper surface of each pair of bridge piers located on both sides in the bridge axis direction between the spans, and a girder is installed between the two bridge piers using the pair of bridge cranes. If possible, each of these bridge cranes is lighter than the above girder girder, and it is not necessary to install a side rail. Therefore, it is possible to easily perform the relocation work between the next spans. Become.

しかしながら、各橋脚の上面に通常の橋形クレーンを単に設置しただけでは、次のような問題がある。   However, simply installing a normal bridge crane on the upper surface of each pier has the following problems.

すなわち、一般に、橋形クレーンは、吊り装置が移動可能に設置されたクレーンガーダを第1脚および第2脚で支持する構成となっており、その吊り装置はクレーンガーダの略真下で荷を吊り支持するようになっている。   That is, in general, a bridge crane is configured to support a crane girder in which a suspension device is movably installed by a first leg and a second leg, and the suspension device suspends a load almost directly below the crane girder. It comes to support.

このため、橋脚の上面に設置された橋形クレーンを用いて桁の架設を行う場合には、桁の長手方向端部に桁吊りノーズ(すなわち、桁の長手方向端部からその長手方向に突出する部材)を取り付けておき、この桁吊りノーズを介して桁をクレーンガーダの略真下で吊り支持することが必要となる。しかしながら、このようにした場合には、吊り装置が橋軸直交方向に移動したとき、これに吊り支持された桁吊りノーズが第2脚(または第1脚)に干渉してしまう、という問題がある。   For this reason, when a girder is installed using a bridge crane installed on the upper surface of a bridge pier, a girder nose (that is, projecting in the longitudinal direction from the longitudinal end of the girder at the longitudinal end of the girder) It is necessary to suspend and support the girder almost directly under the crane girder through this girder nose. However, in this case, when the suspension device moves in the direction perpendicular to the bridge axis, there is a problem that the girder nose suspended and supported by the suspension device interferes with the second leg (or the first leg). is there.

一方、橋脚の上面に設置された橋形クレーンを用いた場合において、クレーンガーダの略真下から架設径間側にずれた位置で桁の長手方向端部を直接吊り支持する構成とすれば、上記干渉の問題は生じなくなる。しかしながら、このようにした場合には、橋形クレーンに大きな転倒モーメントが生じてしまうので、これを防止するために大型の橋形クレーンを用いることが必要となり、次の架設径間への移設作業を容易に行うことができるという橋形クレーンの利点を生かすことができなくなってしまう、という問題がある。   On the other hand, in the case of using a bridge crane installed on the upper surface of the pier, if it is configured to directly suspend and support the longitudinal end of the girder at a position shifted from the position directly below the crane girder to the span span, The problem of interference no longer arises. However, in such a case, a large overturning moment is generated in the bridge crane, so it is necessary to use a large bridge crane to prevent this, and the relocation work between the next installation spans There is a problem that it becomes impossible to take advantage of the advantage of the bridge crane that can be easily performed.

このような問題は、1対の橋脚相互間に桁を架設する場合だけでなく、桁を撤去する場合にも同様に発生し得る問題である。   Such a problem may occur not only when a girder is installed between a pair of piers but also when the girder is removed.

本願発明は、このような事情に鑑みてなされたものであって、桁の架設または撤去の際における交通規制の必要性を最低限に抑えた上で、次の架設径間への移設作業を容易に行うことができる橋形クレーンを提供すること、ならびに、この橋形クレーンを用いた橋梁架設方法および橋梁撤去方法を提供することを目的とするものである。   The present invention has been made in view of such circumstances, and the transfer work between the next installation spans is performed after minimizing the necessity of traffic regulation when installing or removing the girders. It is an object of the present invention to provide a bridge crane that can be easily performed, and to provide a bridge erection method and a bridge removal method using the bridge crane.

本願発明は、橋脚の上面に設置した状態で用いられる橋形クレーンを採用した上で、その構成に工夫を施すことにより、上記目的達成を図るようにしたものである。   The present invention is intended to achieve the above object by adopting a bridge-type crane used in a state of being installed on the upper surface of a pier, and by devising the configuration.

すなわち、本願発明に係る橋形クレーンは、
架設径間の橋軸方向両側に位置する1対の橋脚相互間に桁を架設する際、または上記1対の橋脚相互間に架設された桁を撤去する際に、上記1対の橋脚の各々の上面に設置した状態で用いられる橋形クレーンであって、
橋軸直交方向に延びるクレーンガーダと、このクレーンガーダを橋軸直交方向に所定間隔をおいて支持する第1脚および第2脚と、上記クレーンガーダに対して橋軸直交方向に移動可能に設置された状態で、上記桁の長手方向端部に取り付けられた桁吊りノーズを介して上記桁を吊り支持し得るように構成された吊り装置と、を備えた構成となっており、
上記第2脚は、橋軸直交方向に所定間隔をおいて設置された1対の可動脚で構成されており、
これら各可動脚は、上記吊り装置が橋軸直交方向に移動して該可動脚の設置箇所を通過する際、上記吊り装置に吊り支持された上記桁吊りノーズとの干渉を回避可能な干渉回避位置へ移動し得るように構成されている、ことを特徴とするものである。
That is, the bridge crane according to the present invention is
When installing a girder between a pair of bridge piers located on both sides in the bridge axis direction between spans, or when removing a girder built between the pair of bridge piers, A bridge crane used in the state installed on the upper surface of
A crane girder extending in the direction orthogonal to the bridge axis, a first leg and a second leg that support the crane girder at a predetermined interval in the direction orthogonal to the bridge axis, and movably installed in the direction orthogonal to the bridge axis with respect to the crane girder And a suspension device configured to be able to suspend and support the girder via a girder hanging nose attached to the longitudinal end of the girder,
The second leg is composed of a pair of movable legs installed at a predetermined interval in the direction orthogonal to the bridge axis,
These movable legs can avoid interference with the girder nose suspended and supported by the suspension device when the suspension device moves in the direction perpendicular to the bridge axis and passes through the installation location of the movable leg. It is comprised so that it can move to a position, It is characterized by the above-mentioned.

上記1対の橋脚相互間に架設される(または撤去される)「桁」は、単一の桁であってもよいし、複数の桁であってもよい。また、この「桁」の種類は特に限定されるものではなく、例えば、プレキャスト桁や鋼桁等が採用可能である。   The “girder” constructed (or removed) between the pair of piers may be a single girder or a plurality of girder. Moreover, the kind of this "girder" is not specifically limited, For example, a precast girder, a steel girder, etc. are employable.

上記「吊上げ装置」は、クレーンガーダに対して橋軸直交方向に移動可能に設置されたものであれば、桁吊りノーズを吊り支持するための具体的な構成については特に限定されるものではない。   The above-described “lifting device” is not particularly limited as long as it is installed so as to be movable in the direction orthogonal to the bridge axis with respect to the crane girder. .

上記「1対の可動脚」の設置間隔は、桁吊りノーズが両可動脚の間に位置したとき、いずれの可動脚とも干渉しない大きさが確保されていれば、その具体的な値は特に限定されるものではない。   The installation distance of the above-mentioned “one pair of movable legs” is, in particular, a specific value if a size that does not interfere with any of the movable legs is secured when the girder nose is positioned between the two movable legs. It is not limited.

上記各「可動脚」は、干渉回避位置へ移動し得る構成となっていれば、そのための具体的な構成は特に限定されるものではなく、例えば、可動脚の全部または一部が回動運動により干渉回避位置へ移動する構成、あるいは可動脚の全部または一部が伸縮して干渉回避位置へ移動する構成等が採用可能である。   As long as each of the “movable legs” is configured to be able to move to the interference avoidance position, the specific configuration for that purpose is not particularly limited. Therefore, it is possible to adopt a configuration that moves to the interference avoidance position, or a configuration in which all or part of the movable leg expands and contracts to move to the interference avoidance position.

次に、本願発明に係る橋梁架設方法は、本願発明に係る橋形クレーンを用いて、上記架設径間の側方に位置する搬入ヤードに搬入された桁を上記1対の橋脚相互間に架設する方法であって、
上記橋形クレーンを、上記クレーンガーダが上記搬入ヤードの上方位置まで張り出すとともに上記第2脚が上記第1脚に対して上記搬入ヤード側に位置するようにした状態で上記橋脚の上面に設置した後、
上記吊り装置により、上記搬入ヤードに搬入された架設対象となる桁を上記桁吊りノーズが上記橋脚の上面よりも上方に位置する高さまで吊り上げた後、上記吊り装置を上記桁の架設予定位置まで橋軸直交方向に移動させてから、上記桁を上記橋脚上に吊り下ろすことにより、上記桁の架設を行うようにし、
その際、上記吊り装置の橋軸直交方向への移動を、上記第1脚とは反対側に位置する可動脚を上記干渉回避位置へ移動させた状態で開始し、その後、上記吊り装置が上記1対の可動脚の間の位置まで移動した時点で、上記第1脚とは反対側に位置する可動脚を元の位置へ移動させてから上記第1脚側に位置する可動脚を上記干渉回避位置へ移動させ、その後、上記吊り装置を上記架設予定位置まで移動させる、ことを特徴とするものである。
Next, a bridge erection method according to the present invention uses a bridge crane according to the present invention to construct a girder carried in a carry-in yard located on the side between the erection diameters between the pair of piers. A way to
The bridge crane is installed on the upper surface of the bridge pier with the crane girder extending to a position above the carry-in yard and the second leg positioned on the carry-in yard side with respect to the first leg. After
After the lifting device lifts the girders to be erected into the carry-in yard to a height where the girder hanging nose is located above the upper surface of the bridge pier, the hoisting device is moved to the planned erection position of the girders. After moving in the direction perpendicular to the bridge axis, suspend the girder on the pier, so that the girder is installed,
At that time, the suspension device starts to move in the direction perpendicular to the bridge axis in a state where the movable leg located on the opposite side of the first leg is moved to the interference avoidance position. When moving to a position between the pair of movable legs, the movable leg located on the opposite side of the first leg is moved to the original position, and then the movable leg located on the first leg side is interfered with. The suspension device is moved to an avoidance position, and then the suspension device is moved to the planned installation position.

一方、本願発明に係る橋梁撤去方法は、本願発明に係る橋形クレーンを用いて、上記1対の橋脚相互間に架設された桁を上記架設径間の側方に位置する搬出ヤードへ撤去する方法であって、
上記橋形クレーンを、上記クレーンガーダが上記搬出ヤードの上方位置まで張り出すとともに上記第2脚が上記第1脚に対して上記搬出ヤード側に位置するようにした状態で上記橋脚の上面に設置した後、
上記吊り装置により、上記1対の橋脚相互間に架設された撤去対象となる桁を吊り上げた後、上記吊り装置を上記搬出ヤードの上方位置まで橋軸直交方向に移動させてから、上記桁を上記搬出ヤードの撤去予定位置まで吊り下ろすことにより、上記桁の撤去を行うようにし、
その際、上記吊り装置の橋軸直交方向への移動を、上記第1脚側に位置する可動脚を上記干渉回避位置へ移動させた状態で開始し、その後、上記吊り装置が上記1対の可動脚の間の位置まで移動した時点で、上記第1脚側に位置する可動脚を元の位置へ移動させてから上記第1脚とは反対側に位置する可動脚を上記干渉回避位置へ移動させ、その後、上記吊り装置を上記搬出ヤードの上方位置まで移動させる、ことを特徴とするものである。
On the other hand, the method for removing a bridge according to the present invention uses the bridge crane according to the present invention to remove a girder installed between the pair of bridge piers to a carry-out yard located on the side between the installed diameters. A method,
The bridge crane is installed on the upper surface of the bridge pier with the crane girder extending to a position above the carry-out yard and the second leg positioned on the carry-out yard side with respect to the first leg. After
After lifting the girders to be removed between the pair of bridge piers by the lifting device, the lifting device is moved in the direction perpendicular to the bridge axis to the upper position of the unloading yard, and then the girders are moved. The above girder is removed by suspending it to the planned removal position of the carry-out yard.
At that time, the suspension device is moved in the direction perpendicular to the bridge axis in a state where the movable leg located on the first leg side is moved to the interference avoidance position, and then the suspension device is moved to the pair of pairs. When moving to the position between the movable legs, the movable leg located on the first leg side is moved to the original position, and then the movable leg located on the side opposite to the first leg is moved to the interference avoidance position. It is made to move, and the said suspension apparatus is moved to the upper position of the said unloading yard after that.

上記構成に示すように、本願発明に係る橋形クレーンは、橋脚の上面に設置した状態で用いられるようになっているので、架設径間に既設道路が存在するような場合においても、桁の架設または撤去の際における交通規制の必要性を最低限に抑えることができる。   As shown in the above configuration, the bridge crane according to the present invention is used in a state where it is installed on the upper surface of the bridge pier. Therefore, even in the case where an existing road exists between the spans, The need for traffic regulation during installation or removal can be minimized.

また、本願発明に係る橋形クレーンは、このように橋脚の上面に設置した状態で用いられるようになっているが、その吊り装置により、桁の長手方向端部に取り付けられた桁吊りノーズを介して桁を吊り支持する構成となっているので、そのクレーンガーダの略真下において桁吊りノーズを支持することができる。このため、橋形クレーンに転倒モーメントが生じてしまうのを未然に防止することができ、これにより大型の橋形クレーンを用いる必要をなくすことができる。   Further, the bridge crane according to the present invention is used in such a state that it is installed on the upper surface of the bridge pier, but with the suspension device, the beam suspension nose attached to the longitudinal end of the beam is used. Therefore, the nose suspension nose can be supported almost directly below the crane girder. For this reason, it is possible to prevent an overturning moment from being generated in the bridge crane, thereby eliminating the need to use a large bridge crane.

その上で、本願発明に係る橋形クレーンは、その第2脚が橋軸直交方向に所定間隔をおいて設置された1対の可動脚で構成されており、そして、これら各可動脚は、吊り装置が橋軸直交方向に移動して該可動脚の設置箇所を通過する際、吊り装置に吊り支持された桁吊りノーズとの干渉を回避可能な干渉回避位置へ移動し得る構成となっているので、次のような作用効果を得ることができる。   In addition, the bridge crane according to the present invention is composed of a pair of movable legs whose second legs are installed at a predetermined interval in the direction orthogonal to the bridge axis, and each of these movable legs, When the suspension device moves in the direction perpendicular to the bridge axis and passes through the installation position of the movable leg, the suspension device can move to an interference avoidance position that can avoid interference with the girder nose suspended and supported by the suspension device. Therefore, the following effects can be obtained.

すなわち、橋形クレーンの構成として、吊り装置がクレーンガーダの略真下で桁吊りノーズを吊り支持する構成となっているにもかかわらず、この吊り装置が橋軸直交方向に移動したとき、その移動に伴って各可動脚を順次干渉回避位置へ移動させることにより、桁吊りノーズをいずれの可動脚とも干渉させることなく所定位置まで移動させることができる。したがって、橋形クレーンを大型化しなくても、桁の架設または撤去の際に所期の機能を発揮させることができる。そしてこれにより、次の架設径間に橋形クレーンを移動させるのに大型のクレーンを用いる必要をなくすことができる。   That is, when the suspension device moves in the direction perpendicular to the bridge axis even though the suspension device is configured to support and support the girder nose almost directly below the crane girder, the movement of the suspension crane moves Accordingly, by sequentially moving the movable legs to the interference avoidance position, the suspension nose can be moved to a predetermined position without interfering with any of the movable legs. Therefore, even if the bridge crane is not enlarged, the expected function can be exhibited when the girder is installed or removed. This eliminates the need to use a large crane to move the bridge crane between the next spans.

このように本願発明によれば、桁の架設または撤去の際における交通規制の必要性を最低限に抑えた上で、次の架設径間への橋形クレーンの移設作業を容易に行うことができる。また、このように橋形クレーンの移設作業を容易に行うことができることから、その移設の際における交通規制時間についても、これを最小限に抑えることができる。   As described above, according to the present invention, it is possible to easily perform the transfer work of the bridge crane between the next installation diameters while minimizing the necessity of traffic regulation when installing or removing the girders. it can. In addition, since the relocation work of the bridge crane can be easily performed in this way, the traffic regulation time at the time of the relocation can be minimized.

上記構成において、各可動脚の干渉回避位置への移動が回動運動により行われる構成とすれば、その移動を簡単な作業により行うことが可能となる。   In the above configuration, if the movable legs are moved to the interference avoidance position by a rotational motion, the movement can be performed by a simple operation.

その際、1対の可動脚のうち、第1脚とは反対側に位置する可動脚の干渉回避位置への移動が、その上端を支点とする第1脚とは反対側への回動運動により行われるとともに、第1脚側に位置する可動脚の干渉回避位置への移動が、その上端を支点とする第1脚側への回動運動により行われる構成とすれば、干渉回避位置への移動を最も無理なく行うことができ、また、桁吊りノーズを通過させるための上下方向のスペースを最大限に確保することができる。   At that time, the movement of the movable leg located on the opposite side of the first leg to the interference avoidance position of the pair of movable legs turns to the opposite side of the first leg with its upper end as a fulcrum. And the movement of the movable leg located on the first leg side to the interference avoidance position is performed by a rotational movement toward the first leg with its upper end as a fulcrum. Can be moved most easily, and the vertical space for passing the nose suspension nose can be secured to the maximum.

ところで、架設径間の側方に位置する搬入ヤードに搬入された桁を1対の橋脚相互間に桁を架設する際、本願発明に係る橋梁架設方法を採用すれば、次のような作用効果を得ることができる。   By the way, when the bridge erection method according to the present invention is adopted when the girder carried in the carry-in yard located on the side between the erection diameters is erected between the pair of bridge piers, the following effects are obtained. Can be obtained.

すなわち、本願発明に係る橋梁架設方法においては、上記橋形クレーンを、クレーンガーダが搬入ヤードの上方位置まで張り出すとともに第2脚が第1脚に対して搬入ヤード側に位置するようにした状態で橋脚の上面に設置した後、吊り装置により、搬入ヤードに搬入された架設対象となる桁を桁吊りノーズが橋脚の上面よりも上方に位置する高さまで吊り上げた後、吊り装置を桁の架設予定位置まで橋軸直交方向に移動させてから、桁を橋脚上に吊り下ろすことにより、桁の架設を行うようになっているので、搬入ヤードに搬入された桁に対して、桁吊りノーズの取付作業および吊り装置による吊り支持作業を行うだけで、桁の架設作業を開始することができる。したがって、架設径間に既設道路が存在するような場合においても、搬入ヤードへの桁搬入時に一時的に交通規制を行えば足り、このため交通規制時間を最小限に抑えることができる。   That is, in the bridge erection method according to the present invention, the bridge crane is in a state in which the crane girder extends to the upper position of the carry-in yard and the second leg is located on the carry-in yard side with respect to the first leg. After installing it on the upper surface of the pier, the suspension device lifts the girder loaded into the loading yard to a height where the nose suspension nose is positioned above the upper surface of the pier, and then installs the suspension device The girders are installed by moving them in the direction perpendicular to the bridge axis to the planned position, and then hanging the girders on the piers. The girder construction work can be started simply by performing the attachment work and the suspension support work by the suspension device. Therefore, even when there is an existing road between the spans, it is sufficient to temporarily restrict traffic when carrying the girders into the carry-in yard, thereby minimizing the traffic restriction time.

その上で、本願発明に係る橋梁架設方法においては、吊り装置の橋軸直交方向への移動を、第1脚とは反対側に位置する可動脚を干渉回避位置へ移動させた状態で開始し、その後、吊り装置が1対の可動脚の間の位置まで移動した時点で、第1脚とは反対側に位置する可動脚を元の位置へ移動させてから第1脚側に位置する可動脚を干渉回避位置へ移動させ、その後、吊り装置を架設予定位置まで移動させるようになっているので、桁吊りノーズをいずれの可動脚とも干渉させることなく架設予定位置まで移動させることができ、これにより桁の架設を円滑に行うことができる。   In addition, in the bridge erection method according to the present invention, the movement of the suspension device in the direction orthogonal to the bridge axis is started with the movable leg located on the side opposite to the first leg moved to the interference avoidance position. Thereafter, when the suspension device moves to a position between the pair of movable legs, the movable leg located on the side opposite to the first leg is moved to the original position and then the movable leg located on the first leg side is moved. Since the leg is moved to the interference avoidance position and then the suspension device is moved to the planned installation position, the girder nose can be moved to the planned installation position without interfering with any movable legs, Thereby, the girder can be installed smoothly.

一方、1対の橋脚相互間に架設された桁を架設径間の側方に位置する搬出ヤードへ撤去する際、本願発明に係る橋梁撤去方法を採用すれば、次のような作用効果を得ることができる。   On the other hand, when the girder constructed between a pair of bridge piers is removed to the carry-out yard located on the side between the installation spans, if the bridge removing method according to the present invention is employed, the following operational effects are obtained. be able to.

すなわち、本願発明に係る橋梁撤去方法においては、上記橋形クレーンを、クレーンガーダが搬出ヤードの上方位置まで張り出すとともに第2脚が第1脚に対して搬出ヤード側に位置するようにした状態で橋脚の上面に設置した後、吊り装置により、1対の橋脚相互間に架設された撤去対象となる桁を吊り上げた後、吊り装置を搬出ヤードの上方位置まで橋軸直交方向に移動させてから、桁を搬出ヤードの撤去予定位置まで吊り下ろすことにより、桁の撤去を行うようになっているので、搬出ヤードの撤去予定位置まで吊り下ろされた桁に対して、桁吊りノーズの取外し作業および吊り装置の取外し作業を行うだけで桁の撤去作業を完了させることができる。したがって、架設径間に既設道路が存在するような場合においても、搬出ヤードからの桁搬入時に一時的に交通規制を行えば足り、このため交通規制時間を最小限に抑えることができる。   That is, in the bridge removing method according to the present invention, the bridge crane is configured such that the crane girder extends to a position above the carry-out yard and the second leg is located on the carry-out yard side with respect to the first leg. After installing on the upper surface of the pier, lift the girders to be removed between the pair of piers with a suspension device, and then move the suspension device to the upper position of the carry-out yard in the direction perpendicular to the bridge axis. Since the girders are removed by suspending the girders to the planned removal position of the carry-out yard, the removal work of the nose suspension nose is removed from the girders suspended to the planned removal position of the carry-out yard. And the removal work of the girder can be completed only by removing the lifting device. Therefore, even when there is an existing road between the installation diameters, it is only necessary to temporarily restrict traffic when carrying a girder from the carry-out yard, and thus the traffic restriction time can be minimized.

その上で、本願発明に係る橋梁撤去方法においては、吊り装置の橋軸直交方向への移動を、第1脚側に位置する可動脚を干渉回避位置へ移動させた状態で開始し、その後、吊り装置が1対の可動脚の間の位置まで移動した時点で、第1脚側に位置する可動脚を元の位置へ移動させてから第1脚とは反対側に位置する可動脚を干渉回避位置へ移動させ、その後、吊り装置を搬出ヤードの上方位置まで移動させるようになっているので、桁吊りノーズをいずれの可動脚とも干渉させることなく撤去予定位置まで移動させることができ、これにより桁の撤去を円滑に行うことができる。   Then, in the bridge removal method according to the present invention, the movement of the suspension device in the direction orthogonal to the bridge axis is started with the movable leg located on the first leg side moved to the interference avoidance position, and then When the suspension device moves to a position between the pair of movable legs, the movable leg located on the first leg side is moved to the original position, and then the movable leg located on the opposite side of the first leg interferes. Since it is moved to the avoidance position and then the lifting device is moved to the upper position of the carry-out yard, the girder nose can be moved to the planned removal position without interfering with any movable legs. The girder can be removed smoothly.

本願発明の一実施形態に係る橋梁架設方法の概要を示す側面図The side view which shows the outline | summary of the bridge construction method which concerns on one Embodiment of this invention 図1のII部詳細図Detailed view of part II in Fig. 1 図2のIII−III線断面矢視図Sectional view taken along line III-III in FIG. 上記実施形態に係る橋梁架設方法を示す工程図Process drawing showing the bridge erection method according to the above embodiment 本願発明の一実施形態に係る橋梁撤去方法を示す工程図Process drawing which shows the bridge removal method which concerns on one Embodiment of this invention 上記実施形態の変形例に係る橋形クレーンを示す、図2と同様の図The figure similar to FIG. 2 which shows the bridge crane which concerns on the modification of the said embodiment.

以下、図面を用いて、本願発明の実施の形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

まず、本願発明の一実施形態に係る橋梁架設方法について説明する。   First, a bridge construction method according to an embodiment of the present invention will be described.

図1は、本実施形態に係る橋梁架設方法の概要を示す側面図である。また、図2は、図1のII部詳細図であり、図3は、図2のIII−III線断面矢視図である。   FIG. 1 is a side view showing an outline of a bridge erection method according to the present embodiment. 2 is a detailed view of a portion II in FIG. 1, and FIG. 3 is a cross-sectional view taken along the line III-III in FIG.

これらの図に示すように、本実施形態に係る橋梁架設方法の適用対象は、多径間連続橋における架設径間S0の部分である。その際、この架設径間S0は、高速道路のランプウェイ等を構成している部分の架設径間S0であって、その橋軸方向両側に位置する1対の橋脚12A、12B相互間に、3つのプレキャスト桁14が橋軸直交方向に所定間隔をおいて架設されるようになっている。   As shown in these drawings, the application target of the bridge erection method according to the present embodiment is a portion of the span S0 in the multi-span continuous bridge. At this time, the span S0 is the span S0 of the portion constituting the rampway of the highway, and between the pair of bridge piers 12A and 12B located on both sides in the bridge axis direction. Three precast girders 14 are constructed at predetermined intervals in the direction perpendicular to the bridge axis.

そして、本実施形態に係る橋梁架設方法においては、図3に示すように、架設径間S0の側方に位置する搬入ヤードYiに搬入された架設対象となるプレキャスト桁14を吊り上げて、このプレキャスト桁14を1対の橋脚12A、12B相互間に順次架設するようになっている。なお、図3においては、3つのプレキャスト桁14について、その各々の架設予定位置を2点鎖線で示している。   Then, in the bridge erection method according to the present embodiment, as shown in FIG. 3, the precast girder 14 to be erected in the carry-in yard Yi located on the side of the erection span S0 is lifted, and this precast is performed. Girder 14 is constructed in order between a pair of bridge piers 12A and 12B. In FIG. 3, for each of the three precast girders 14, the respective planned installation positions are indicated by two-dot chain lines.

図1に示すように、架設径間S0に対して橋脚12B側に隣接する架設径間S−1においては、3つのプレキャスト桁14の架設が完了しており、また、橋脚12A側に隣接する架設径間S+1においては、架設径間S0の次に架設が行われるようになっている。   As shown in FIG. 1, in the span span S-1 adjacent to the pier 12B side with respect to the span span S0, the three precast girders 14 have been erected, and adjacent to the pier 12A side. In the construction span S + 1, construction is performed next to the construction span S0.

図1に示すように、各橋脚12A、12Bの上端部には、L字形の桁受け部12Aa、12Baがそれぞれ形成されており、一方、各プレキャスト桁14の長手方向の両端部には、逆L字形の凹部14aが形成されている。そして、これら各プレキャスト桁14は、その各凹部14aにおいて各橋脚12A、12Bの桁受け部12Aa、12Baに載置されるようになっている。   As shown in FIG. 1, L-shaped girder receiving portions 12Aa and 12Ba are formed at the upper ends of the piers 12A and 12B, respectively, while the opposite ends of each precast girder 14 in the longitudinal direction are reversed. An L-shaped recess 14a is formed. The precast girders 14 are placed on the girder receiving portions 12Aa and 12Ba of the piers 12A and 12B in the concave portions 14a.

本実施形態においては、1対の橋脚12A、12Bの各々の上面に橋形クレーン110を設置しておき、これら1対の橋形クレーン110を用いて各プレキャスト桁14の架設を行うようになっている。その際、プレキャスト桁14の長手方向の両端部に、その長手方向に突出する桁吊りノーズ50をそれぞれ取り付けておき、これら1対の桁吊りノーズ50を介してプレキャスト桁14を両橋形クレーン110で吊り支持するようになっている。   In the present embodiment, a bridge crane 110 is installed on the upper surface of each of the pair of bridge piers 12A, 12B, and each precast girder 14 is installed using the pair of bridge cranes 110. ing. At that time, girder hanging noses 50 projecting in the longitudinal direction are respectively attached to both ends in the longitudinal direction of the precast girder 14, and the precast girder 14 is connected to the double-bridge crane 110 via the pair of girder hanging noses 50. It is designed to be supported by hanging.

これら各桁吊りノーズ50は、1対のH形鋼52が橋軸直交方向に所定間隔をおいて配置された構成となっている。そして、これら各桁吊りノーズ50は、プレキャスト桁14の上面近傍において橋軸方向に延びるように配置された状態で、プレキャスト桁14の長手方向端部および該長手方向端部から所定距離離れた位置においてプレキャスト桁14に固定されている。その際、各桁吊りノーズ50のプレキャスト桁14の長手方向端部における固定は、両H形鋼52とプレキャスト桁14との間に支持鋼材54を介在させた状態で、下端部がプレキャスト桁14に埋め込まれた左右1対の鋼棒56を用いて行われており、また、その長手方向端部から所定距離離れた位置における固定は、両H形鋼52とプレキャスト桁14との間に支持鋼材58を介在させるともに両H形鋼52の上面に支持鋼材60を配置した状態で、下端部がプレキャスト桁14に埋め込まれた左右1対の鋼棒62を緊張させることにより行われている。   Each girder hanging nose 50 has a configuration in which a pair of H-section steels 52 are arranged at predetermined intervals in a direction perpendicular to the bridge axis. These girder hanging noses 50 are arranged so as to extend in the bridge axis direction in the vicinity of the upper surface of the precast girder 14 and at positions separated from the longitudinal end of the precast girder 14 by a predetermined distance from the longitudinal end. Is fixed to the precast beam 14. At that time, the fixing at the longitudinal end portion of the precast beam 14 of each girder hanging nose 50 is performed with the supporting steel material 54 interposed between the H-shaped steel 52 and the precast beam 14, and the lower end portion of the precast beam 14. A pair of left and right steel rods 56 embedded in the steel plate 56 is used, and the fixing at a position away from the longitudinal end portion by a predetermined distance is supported between both the H-shaped steel 52 and the precast beam 14. This is done by tensioning a pair of left and right steel rods 62 whose lower ends are embedded in the precast girders 14 with the steel material 58 interposed and the support steel material 60 disposed on the upper surfaces of both H-shaped steels 52.

そして、これら各桁吊りノーズ50は、その長手方向の中心位置からその他端部(すなわち支持鋼材54が設置されている端部とは反対側の端部)側に多少ずれた位置において橋形クレーン110に吊り支持されるようになっている。また、これら各桁吊りノーズ50の他端部の上面にはカウンタウェイト64が載置されている。   These girder hanging noses 50 are bridge-type cranes at positions slightly deviated from the center position in the longitudinal direction to the other end (that is, the end opposite to the end where the support steel material 54 is installed). 110 is supported by suspension. A counterweight 64 is placed on the upper surface of the other end of each girder nose 50.

1対の橋形クレーン110は、いずれも同様の構成を有している。そこで、以下においては、一方の橋脚12Aの上面に設置された橋形クレーン110の構成について詳細に説明する。   Each of the pair of bridge cranes 110 has the same configuration. Therefore, in the following, the configuration of the bridge crane 110 installed on the upper surface of one pier 12A will be described in detail.

図2、3に示すように、橋形クレーン110は、橋軸直交方向に延びるクレーンガーダ120と、このクレーンガーダ120を橋軸直交方向に所定間隔をおいて支持する第1脚130および第2脚140と、クレーンガーダ120に対して橋軸直交方向に移動可能に設置された吊り装置150とを備えた構成となっている。   As shown in FIGS. 2 and 3, the bridge crane 110 includes a crane girder 120 extending in a direction orthogonal to the bridge axis, and a first leg 130 and a second leg that support the crane girder 120 at a predetermined interval in the bridge axis orthogonal direction. The leg 140 and the suspension device 150 installed so as to be movable in the direction orthogonal to the bridge axis with respect to the crane girder 120 are provided.

クレーンガーダ120は、橋軸方向に所定間隔をおいて橋軸直交方向に延びる1対のH形鋼120Aと、橋軸直交方向の4箇所において、これらH形鋼120Aを連結するとともに両H形鋼120Aよりも橋軸方向両側へ突出するようにして配置された連結鋼材120Bとで構成されている。そして、各H形鋼120Aの上面には、吊り装置150を橋軸直交方向に移動させるためのレール122がそれぞれ設置されている。   The crane girder 120 connects a pair of H-sections 120A extending in the direction orthogonal to the bridge axis at a predetermined interval in the direction of the bridge axis and the H-sections 120A at four locations in the direction orthogonal to the bridge axis and both H-shapes. It is comprised with the connection steel material 120B arrange | positioned so that it may protrude in the bridge-axis direction both sides rather than steel 120A. And the rail 122 for moving the suspension apparatus 150 to a bridge axis orthogonal direction is each installed in the upper surface of each H-section steel 120A.

第1脚130は、上端部がクレーンガーダ120の橋軸直交方向の一端部の近傍部位に剛結された鉛直材130Aと、上端部がクレーンガーダ120の橋軸直交方向の一端部に剛結されるとともに下端部が鉛直材130Aの下端部に剛結された斜材130Bとで構成されている。   The first leg 130 has a vertical member 130A whose upper end is rigidly connected to a portion in the vicinity of one end of the crane girder 120 in the direction perpendicular to the bridge axis, and whose upper end is rigidly connected to one end of the crane girder 120 in the direction perpendicular to the bridge axis. In addition, the lower end portion is composed of a diagonal member 130B rigidly connected to the lower end portion of the vertical member 130A.

この第1脚130は、鉛直材130Aおよび斜材130Bが橋軸方向に所定間隔をおいて1対配置された構成となっている。その際、1対の鉛直材130Aは、複数の連結鋼材(図示せず)によって互いに連結されている。また、これら各鉛直材130Aの上端部および各斜材130Bの上端部は、クレーンガーダ120の連結鋼材120Bの前端部および後端部の下面において、それぞれクレーンガーダ120に剛結されている。   The first leg 130 has a configuration in which a pair of vertical members 130A and diagonal members 130B are arranged at predetermined intervals in the bridge axis direction. At that time, the pair of vertical members 130A are connected to each other by a plurality of connecting steel members (not shown). Further, the upper end portion of each vertical member 130A and the upper end portion of each diagonal member 130B are rigidly connected to the crane girder 120 on the lower surfaces of the front end portion and the rear end portion of the connecting steel member 120B of the crane girder 120, respectively.

そして、この第1脚130は、橋脚12Aの上面に設置される際には、その鉛直材130Aの下端部にヒンジ部材132が取り付けられた状態で、橋脚12Aの上面に調整コンクリート160を介して載置されるようになっており、さらに図示しないアンカ−等により橋脚12Aに固定されるようになっている。   When the first leg 130 is installed on the upper surface of the pier 12A, the hinge member 132 is attached to the lower end portion of the vertical member 130A and the upper surface of the pier 12A is provided with adjustment concrete 160 via the adjustment concrete 160. It is placed and is further fixed to the pier 12A by an anchor or the like (not shown).

第2脚140は、クレーンガーダ120の橋軸直交方向の他端部から多少その一端部側に離れた位置において、橋軸直交方向に所定間隔をおいて設置された1対の可動脚140A、140Bで構成されている。その際、これら1対の可動脚140A、140Bの設置間隔は、桁吊りノーズ50の橋軸直交方向の幅よりもやや大きい値に設定されている。また、これら1対の可動脚140A、140Bのうち、第1脚130側に位置する可動脚140Bは、もう一方の可動脚140Aおよび第1脚130よりも断面形状が大きい鋼材で構成されている。   The second leg 140 is a pair of movable legs 140A installed at a predetermined interval in the bridge axis orthogonal direction at a position somewhat away from the other end part of the crane girder 120 in the bridge axis orthogonal direction. 140B. At this time, the installation interval between the pair of movable legs 140A and 140B is set to a value slightly larger than the width of the beam suspension nose 50 in the direction perpendicular to the bridge axis. Of the pair of movable legs 140A and 140B, the movable leg 140B positioned on the first leg 130 side is made of a steel material having a larger cross-sectional shape than the other movable leg 140A and the first leg 130. .

可動脚140Aは、その上端を支点として第1脚130とは反対側へ約90°回動し得るように構成されており、また、可動脚140Bは、その上端を支点として第1脚130側へ約90°回動し得るように構成されている。   The movable leg 140A is configured to be able to rotate about 90 ° to the opposite side of the first leg 130 with the upper end as a fulcrum, and the movable leg 140B is on the first leg 130 side with the upper end as a fulcrum. It is configured to be able to rotate about 90 °.

可動脚140Aは、橋軸方向に所定間隔をおいて配置された1対の鉛直材140A1が、橋軸方向に延びるようにして上下3箇所に配置された連結鋼材140A2および襷がけで配置された1対の連結鋼材140A3によって連結された構成となっている。そして、この可動脚140Aは、上記回動を実現するため、その1対の鉛直材140A1の上端部が、ヒンジ部材142Aを介して、クレーンガーダ120の連結鋼材120Bの前端部および後端部の下面に連結されている。   In the movable leg 140A, a pair of vertical members 140A1 arranged at a predetermined interval in the bridge axis direction are arranged by connecting steel members 140A2 arranged in three upper and lower positions and extending to extend in the bridge axis direction. It is the structure connected by one pair of connection steel materials 140A3. In order to realize the above-mentioned rotation, the movable leg 140A has upper ends of the pair of vertical members 140A1 connected to the front end and the rear end of the connecting steel member 120B of the crane girder 120 via the hinge member 142A. Connected to the bottom surface.

可動脚140Bも、橋軸方向に所定間隔をおいて配置された1対の鉛直材140B1が、橋軸方向に延びるようにして上下3箇所に配置された連結鋼材(図示せず)および襷がけで配置された1対の連結鋼材(図示せず)によって連結された構成となっている。そして、この可動脚140Bは、上記回動を実現するため、その1対の鉛直材140B1の上端部が、ヒンジ部材142Bを介して、クレーンガーダ120の連結鋼材120Bの前端部および後端部の下面に連結されている。   The movable leg 140B also includes a connecting steel material (not shown) and a pair of vertical members 140B1 arranged at a predetermined interval in the bridge axis direction and arranged in three places above and below so as to extend in the bridge axis direction. It is the structure connected by one pair of connection steel materials (not shown) arrange | positioned by. In order to realize the above-mentioned rotation, the movable leg 140B has an upper end portion of the pair of vertical members 140B1 connected to the front end portion and the rear end portion of the connecting steel member 120B of the crane girder 120 via the hinge member 142B. Connected to the bottom surface.

そして、これら各可動脚140A、140Bは、橋脚12Aの上面に設置される際には、その鉛直材140A1、140B1の下端部に油圧ジャッキ144A、144Bが取り付けられた状態で、橋脚12Aの上面に調整コンクリート160を介して載置されるようになっている。   When these movable legs 140A and 140B are installed on the upper surface of the pier 12A, the hydraulic jacks 144A and 144B are attached to the lower ends of the vertical members 140A1 and 140B1, and the movable legs 140A and 140B are attached to the upper surface of the pier 12A. It is placed via the adjusting concrete 160.

吊り装置150は、クレーンガーダ120を構成する1対のH形鋼120Aに跨るようにして設置されている。   The suspension device 150 is installed so as to straddle a pair of H-section steel members 120 </ b> A constituting the crane girder 120.

その際、この吊り装置150は、クレーンガーダ120に対して、その連結鋼材120Bよりも橋軸方向両側まで橋軸方向に延びる上部鋼材152と、この上部鋼材152の下面における橋軸方向の2箇所に設置されたころがり機構154と、上部鋼材152の橋軸方向の両端部に吊り支持された1対の電気チェーンブロック156と、これら1対の電気チェーンブロック156に両端部を支持されるようにして橋軸方向に延びる下部鋼材158とを備えた構成となっている。   At this time, the suspension device 150 is provided with respect to the crane girder 120 at two locations in the bridge axis direction on the lower surface of the upper steel material 152 and an upper steel material 152 extending in the bridge axis direction to both sides in the bridge axis direction than the connecting steel material 120B. A pair of electric chain blocks 156 suspended from and supported by both ends of the upper steel member 152 in the direction of the bridge axis, and both ends of the pair of electric chain blocks 156 being supported by the pair of electric chain blocks 156. And a lower steel material 158 extending in the bridge axis direction.

そして、この吊り装置150は、その下部鋼材158の橋軸方向中央において、上下方向に延びる連結鋼材170を介して桁吊りノーズ50を吊り支持するようになっている。その際、この連結鋼材170は、桁吊りノーズ50に対して、その1対のH形鋼52の間に下端部が挿入された状態で連結されるようになっており、これにより桁吊りノーズ50の全幅が1対のH形鋼52の全幅よりも大きくならないようにしている。   The suspension device 150 suspends and supports the girder nose 50 via a connecting steel material 170 extending in the vertical direction at the center of the lower steel material 158 in the bridge axis direction. At this time, the connecting steel material 170 is connected to the girder nose 50 in a state where the lower end portion is inserted between the pair of H-shaped steels 52, thereby the girder nose. The total width of 50 is not made larger than the total width of the pair of H-section steels 52.

また、この吊り装置150は、その1対の電気チェーンブロック156により、桁吊りノーズ50の吊り上げおよび吊り下ろしを行うようになっている。   The suspension device 150 is configured to lift and suspend the girder nose 50 by the pair of electric chain blocks 156.

さらに、この吊り装置150は、その1対のころがり機構154が、クレーンガーダ120における1対のレール122に載置されており、これにより橋軸直交方向に移動し得るようになっている。この移動は、吊り装置150の上部鋼材152とクレーンガーダ120の一端部の上面に設置された固定具124とに両端部が取り付けられた牽引索180を操作することによって行われるようになっている。   Further, the suspension device 150 has a pair of rolling mechanisms 154 mounted on a pair of rails 122 in the crane girder 120 so that the suspension device 150 can move in a direction perpendicular to the bridge axis. This movement is performed by operating the tow rope 180 having both ends attached to the upper steel material 152 of the suspension device 150 and the fixture 124 installed on the upper surface of one end of the crane girder 120. .

本実施形態に係る橋形クレーン110は、橋脚12Aの上面に設置された状態においては、その吊り装置150が橋軸直交方向に移動して各可動脚140A、140Bの設置箇所を通過する際、これら各可動脚140A、140Bが、吊り装置150に吊り支持された桁吊りノーズ50との干渉を回避可能な干渉回避位置へ移動し得る構成となっている、
その際、各可動脚140A、140Bの干渉回避位置へ移動は、回動運動により行われるように構成されている。具体的には、これら1対の可動脚140A、140Bのうち、第1脚130とは反対側に位置する可動脚140Aの干渉回避位置へ移動は、該可動脚140Aの上端を支点とする第1脚130とは反対側への回動運動により行われるようになっており、また、第1脚130側に位置する可動脚140Bの干渉回避位置へ移動は、該可動脚140Bの上端を支点とする第1脚130側への回動運動により行われるようになっている。
When the bridge crane 110 according to the present embodiment is installed on the upper surface of the pier 12A, when the suspension device 150 moves in the direction orthogonal to the bridge axis and passes through the installation locations of the movable legs 140A and 140B, Each of these movable legs 140A, 140B is configured to be able to move to an interference avoidance position that can avoid interference with the girder nose 50 that is suspended and supported by the suspension device 150.
At this time, the movable legs 140A and 140B are configured to move to the interference avoidance position by a rotating motion. Specifically, of the pair of movable legs 140A and 140B, the movable leg 140A located on the opposite side of the first leg 130 moves to the interference avoidance position with the upper end of the movable leg 140A as a fulcrum. The movement of the movable leg 140B located on the first leg 130 side to the interference avoidance position is performed by turning the upper end of the movable leg 140B as a fulcrum. The first leg 130 is rotated by a movement toward the first leg 130 side.

次に、本実施形態に係る橋形クレーン110を用いた橋梁架設方法について、図4に基づいて説明する。   Next, a bridge construction method using the bridge crane 110 according to the present embodiment will be described with reference to FIG.

まず、同図(a)に示すように、橋形クレーン110を、橋脚12A(および12B)の上面において、そのクレーンガーダ120が搬入ヤードYiの上方位置まで張り出すとともに、その第2脚140が第1脚130に対して搬入ヤードYi側に位置する状態で設置する。   First, as shown in FIG. 4A, the bridge girder 110 is extended from the upper surface of the pier 12A (and 12B) to the upper position of the carry-in yard Yi, and the second leg 140 is It installs in the state located in the carrying-in yard Yi side with respect to the 1st leg 130. FIG.

次に、同図(a)に示すように、搬入ヤードYiにトレーラ等により搬入された架設対象となるプレキャスト桁14を、橋形クレーン110の吊り装置150により、同図(b)に示すように、桁吊りノーズ50が橋脚12A(および12B)の上面よりも上方に位置する高さまで吊り上げる。   Next, as shown in FIG. 5A, the precast girder 14 to be installed, which is carried into the carry-in yard Yi by a trailer or the like, is shown in FIG. Further, the girder hanging nose 50 is lifted up to a height located above the upper surface of the pier 12A (and 12B).

その後、同図(b)〜(e)に示すように、吊り装置150をプレキャスト桁14の架設予定位置まで橋軸直交方向に移動させ、そして、同図(e)に示すように、吊り装置150によりプレキャスト桁14を橋脚12A上に吊り下ろす。   Thereafter, the suspension device 150 is moved in the direction perpendicular to the bridge axis to the position where the precast girder 14 is to be erected as shown in FIGS. 150, the precast girder 14 is hung on the pier 12A.

以下、これを繰り返すことにより3つのプレキャスト桁14の架設を行う。   Thereafter, the three precast girders 14 are installed by repeating this.

その際、同図(a)に示すように、プレキャスト桁14を吊り上げる前(または吊り上げた後)に、第1脚130とは反対側に位置する可動脚140Aを干渉回避位置へ移動させておく。そして、同図(b)に示すように、可動脚140Aを干渉回避位置へ移動させた状態で、吊り装置150の橋軸直交方向への移動を開始する。その後、同図(c)に示すように、吊り装置150が1対の可動脚140A、140Bの間の位置まで移動した時点で、可動脚140Aを元の位置へ移動させてから、同図(d)に示すように、第1脚130側に位置する可動脚140Bを干渉回避位置へ移動させ、この状態で、同図(e)に示すように、吊り装置150を架設予定位置まで移動させる。   At that time, before the precast girder 14 is lifted (or after it is lifted), the movable leg 140A located on the side opposite to the first leg 130 is moved to the interference avoidance position, as shown in FIG. . And as shown in the figure (b), the movement to the bridge axis orthogonal direction of the suspension apparatus 150 is started in the state which moved the movable leg 140A to the interference avoidance position. Thereafter, as shown in FIG. 5C, when the suspension device 150 moves to a position between the pair of movable legs 140A and 140B, the movable leg 140A is moved to the original position, and As shown in d), the movable leg 140B located on the first leg 130 side is moved to the interference avoidance position, and in this state, the suspension device 150 is moved to the planned installation position as shown in FIG. .

次に、本実施形態の作用について説明する。   Next, the operation of this embodiment will be described.

本実施形態に係る橋梁架設方法においては、架設径間S0の橋軸方向両側に位置する1対の橋脚12A、12Bの各々の上面に橋形クレーン110を設置した状態で、両橋脚12A、12B相互間に、3つのプレキャスト桁14を橋軸直交方向に所定間隔をおいて架設するようになっているので、架設径間S0に既設道路が存在するような場合においても、これらプレキャスト桁14の架設の際における交通規制の必要性を最低限に抑えることができる。   In the bridge erection method according to the present embodiment, both piers 12A and 12B are provided with the bridge crane 110 installed on the upper surface of each of the pair of piers 12A and 12B located on both sides of the bridge span direction S0 in the bridge axis direction. Since three precast girders 14 are installed at a predetermined interval in the direction perpendicular to the bridge axis between each other, even in the case where an existing road exists in the span span S0, The necessity of traffic regulation when erection can be minimized.

また、本実施形態に係る橋梁架設方法においては、橋形クレーン110が、1対の橋脚12A、12Bの各々の上面に設置された状態で用いられるようになっているが、その際、この橋形クレーン110は、その吊り装置150により、プレキャスト桁14の長手方向端部に取り付けられた桁吊りノーズ50を介してプレキャスト桁14を吊り支持する構成となっているので、そのクレーンガーダ120の略真下において桁吊りノーズ50を支持することができる。このため、橋形クレーン110に転倒モーメントが生じてしまうのを未然に防止することができ、これにより大型の橋形クレーン110を用いる必要をなくすことができる。   Moreover, in the bridge construction method according to the present embodiment, the bridge crane 110 is used in a state where it is installed on the upper surface of each of the pair of piers 12A, 12B. Since the crane 110 is configured to suspend and support the precast beam 14 via the beam hanging nose 50 attached to the longitudinal end portion of the precast beam 14 by the suspension device 150, the crane girder 120 is an abbreviation of the crane girder 120. The nose suspension nose 50 can be supported directly below. For this reason, it is possible to prevent a tipping moment from occurring in the bridge crane 110, thereby eliminating the need to use a large bridge crane 110.

その上で、本実施形態に係る橋形クレーン110は、その第2脚140が橋軸直交方向に所定間隔をおいて設置された1対の可動脚140A、140Bで構成されており、そして、これら各可動脚140A、140Bは、吊り装置150が橋軸直交方向に移動して該可動脚140A、140Bの設置箇所を通過する際、吊り装置150に吊り支持された桁吊りノーズ50との干渉を回避可能な干渉回避位置へ移動し得る構成となっているので、次のような作用効果を得ることができる。   In addition, the bridge crane 110 according to the present embodiment includes a pair of movable legs 140A and 140B in which the second leg 140 is installed at a predetermined interval in the bridge axis orthogonal direction, and These movable legs 140A and 140B interfere with the girder nose 50 suspended and supported by the suspension device 150 when the suspension device 150 moves in the direction perpendicular to the bridge axis and passes through the installation location of the movable legs 140A and 140B. Therefore, the following operation and effect can be obtained.

すなわち、橋形クレーン110の構成として、吊り装置150がクレーンガーダ120の略真下で桁吊りノーズ50を吊り支持する構成となっているにもかかわらず、この吊り装置150が橋軸直交方向に移動したとき、その移動に伴って各可動脚140A、140Bを順次干渉回避位置へ移動させることにより、桁吊りノーズ50をいずれの可動脚140A、140Bとも干渉させることなく所定位置まで移動させることができる。   In other words, the suspension crane 150 moves in the direction orthogonal to the bridge axis even though the suspension device 150 is configured to suspend and support the girder suspension nose 50 almost directly below the crane girder 120. In this case, the movable leg 140A, 140B is sequentially moved to the interference avoidance position along with the movement, so that the girder nose 50 can be moved to a predetermined position without interfering with any of the movable legs 140A, 140B. .

したがって、橋形クレーン110を大型化しなくても、プレキャスト桁14の架設の際に所期の機能を発揮させることができる。そしてこれにより、次の架設径間S+1に橋形クレーン110を移動させるのに大型のクレーンを用いる必要をなくすことができる。   Therefore, even if the bridge crane 110 is not enlarged, the expected function can be exhibited when the precast girder 14 is installed. This eliminates the need to use a large crane to move the bridge crane 110 to the next span S + 1.

このように本実施形態によれば、プレキャスト桁14の架設の際における交通規制の必要性を最低限に抑えた上で、次の架設径間S+1への橋形クレーン110の移設作業を容易に行うことができる。また、このように橋形クレーン110の移設作業を容易に行うことができることから、その移設の際における交通規制時間についても、これを最小限に抑えることができる。   As described above, according to the present embodiment, it is possible to easily move the bridge crane 110 to the next spanning span S + 1 while minimizing the necessity of traffic regulation when the precast girder 14 is erected. It can be carried out. Further, since the transfer work of the bridge crane 110 can be easily performed in this way, the traffic regulation time at the time of the transfer can be minimized.

特に本実施形態においては、1対の可動脚140A、140Bのうち、第1脚130側に位置する可動脚140Bが、もう一方の可動脚140Aおよび第1脚130よりも断面形状が大きい鋼材で構成されているので、プレキャスト桁14の架設の際に橋形クレーン110に作用する荷重に十分耐え得るクレーン構造とした上で、その軽量化を十分に図ることができる。   In particular, in the present embodiment, of the pair of movable legs 140A and 140B, the movable leg 140B positioned on the first leg 130 side is a steel material having a larger cross-sectional shape than the other movable leg 140A and the first leg 130. Since it is configured, the crane structure can sufficiently withstand the load acting on the bridge crane 110 when the precast girder 14 is installed, and the weight can be sufficiently reduced.

しかも本実施形態においては、各可動脚140A、140Bの干渉回避位置への移動が回動運動により行われる構成となっているので、その移動を簡単な作業により行うことが可能となる。   Moreover, in the present embodiment, since the movable legs 140A and 140B are moved to the interference avoidance position by a rotational movement, the movement can be performed by a simple operation.

その際、1対の可動脚140A、140Bのうち、第1脚130とは反対側に位置する可動脚140Aの干渉回避位置への移動が、その上端を支点とする第1脚130とは反対側への回動運動により行われるとともに、第1脚130側に位置する可動脚140Bの干渉回避位置への移動が、その上端を支点とする第1脚130側への回動運動により行われる構成となっているので、干渉回避位置への移動を最も無理なく行うことができ、また、桁吊りノーズ50を通過させるための上下方向のスペースを最大限に確保することができる。   At that time, of the pair of movable legs 140A and 140B, the movement of the movable leg 140A located on the opposite side of the first leg 130 to the interference avoidance position is opposite to that of the first leg 130 having the upper end as a fulcrum. The movable leg 140B located on the first leg 130 side is moved to the interference avoidance position by the pivoting movement toward the first leg 130 with its upper end as a fulcrum. Since it is configured, it is possible to move to the interference avoidance position without any difficulty, and it is possible to secure a maximum vertical space for allowing the girder nose 50 to pass therethrough.

そして、本実施形態に係る橋梁架設方法においては、架設径間S0の側方に位置する搬入ヤードYiに搬入されたプレキャスト桁14を1対の橋脚12A、12B相互間にプレキャスト桁14を架設する際、各橋脚12A、12Bの上面において、橋形クレーン110を、クレーンガーダ120が搬入ヤードYiの上方位置まで張り出すとともに第2脚140が第1脚130に対して搬入ヤードYi側に位置する状態で設置した後、吊り装置150により、搬入ヤードYiに搬入された架設対象となるプレキャスト桁14を桁吊りノーズ50が橋脚12A、12Bの上面よりも上方に位置する高さまで吊り上げた後、吊り装置150をプレキャスト桁14の架設予定位置まで橋軸直交方向に移動させてから、プレキャスト桁14を橋脚12A、12B上に吊り下ろすことにより、プレキャスト桁14の架設を行うようになっているので、搬入ヤードYiに搬入されたプレキャスト桁14に対して、桁吊りノーズ50の取付作業および吊り装置150による吊り支持作業を行うだけで、プレキャスト桁14の架設作業を開始することができる。したがって、架設径間S0に既設道路が存在するような場合においても、搬入ヤードYiへの桁搬入時に一時的に交通規制を行えば足り、このため交通規制時間を最小限に抑えることができる。   And in the bridge construction method concerning this embodiment, the precast girder 14 carried in the carrying-in yard Yi located in the side of construction span S0 is constructed between a pair of bridge piers 12A and 12B. At this time, on the upper surface of each bridge pier 12A, 12B, the bridge girder 110 projects the crane girder 120 to a position above the carry-in yard Yi, and the second leg 140 is located on the carry-in yard Yi side with respect to the first leg 130. After being installed in a state, the suspension device 150 lifts the precast girder 14 to be installed carried into the carry-in yard Yi to a height where the girder nose 50 is positioned above the upper surfaces of the piers 12A and 12B. After the device 150 is moved in the direction perpendicular to the bridge axis to the position where the precast girder 14 is to be installed, the precast girder 14 is moved to the pier 12A. Since the precast girder 14 is constructed by being suspended on 12B, the girder nose 50 is attached to the precast girder 14 carried into the carry-in yard Yi and supported by the suspension device 150. The construction work of the precast girder 14 can be started only by performing the work. Therefore, even when there is an existing road in the span span S0, it is sufficient to temporarily restrict traffic when carrying the girders into the carry-in yard Yi, and thus the traffic regulation time can be minimized.

その上で、本実施形態に係る橋梁架設方法においては、吊り装置150の橋軸直交方向への移動を、第1脚130とは反対側に位置する可動脚140Aを干渉回避位置へ移動させた状態で開始し、その後、吊り装置150が1対の可動脚140A、140Bの間の位置まで移動した時点で、第1脚130とは反対側に位置する可動脚140Aを元の位置へ移動させてから第1脚130側に位置する可動脚140Bを干渉回避位置へ移動させ、その後、吊り装置150を架設予定位置まで移動させるようになっているので、桁吊りノーズ50をいずれの可動脚140A、140Bとも干渉させることなく架設予定位置まで移動させることができ、これによりプレキャスト桁14の架設を円滑に行うことができる。   In addition, in the bridge erection method according to the present embodiment, the movement of the suspension device 150 in the direction perpendicular to the bridge axis is performed by moving the movable leg 140A located on the opposite side of the first leg 130 to the interference avoidance position. After that, when the suspension device 150 moves to a position between the pair of movable legs 140A and 140B, the movable leg 140A located on the side opposite to the first leg 130 is moved to the original position. Then, the movable leg 140B located on the first leg 130 side is moved to the interference avoidance position, and then the suspension device 150 is moved to the planned installation position, so that the girder nose 50 can be moved to any movable leg 140A. , 140B can be moved to the planned installation position without interfering with each other, whereby the precast girder 14 can be installed smoothly.

次に、本願発明の一実施形態に係る橋梁撤去方法について説明する。   Next, a bridge removing method according to an embodiment of the present invention will be described.

図5は、本実施形態に係る橋梁撤去方法を示す工程図である。   FIG. 5 is a process diagram showing a bridge removing method according to the present embodiment.

同図に示すように、本実施形態に係る橋梁撤去方法においては、上記橋形クレーン110を用いて、上記橋梁架設方法とは略逆の手順で、既設橋梁から3つのプレキャスト桁14を順次撤去するようになっている。   As shown in the figure, in the bridge removing method according to the present embodiment, the three precast girders 14 are sequentially removed from the existing bridge using the bridge crane 110 in a procedure substantially opposite to the bridge erection method. It is supposed to be.

なお、以下においては、説明の都合上、架設径間S0に架設された3つのプレキャスト桁14のうち、最後に撤去されるプレキャスト桁14を撤去する工程について説明する。   In the following, for the convenience of explanation, a process of removing the precast girder 14 that is finally removed from among the three precast girders 14 installed in the span span S0 will be described.

まず、撤去を行う前に、同図(a)に2点鎖線で示すように、既設の3つのプレキャスト桁14の上面に配置された床版16を、各プレキャスト桁14毎に3分割しておく。   First, before removing, the floor slab 16 arranged on the upper surface of the existing three precast girders 14 is divided into three for each precast girders 14 as shown by a two-dot chain line in FIG. deep.

そして、同図(a)に示すように、橋形クレーン110を、橋脚12A(および12B)の上面において、そのクレーンガーダ120が搬出ヤードYoの上方位置まで張り出すとともに、その第2脚140が第1脚130に対して搬出ヤードYo側に位置する状態で設置する。   And as shown to the same figure (a), while the crane girder 120 overhangs the bridge crane 110 in the upper surface of the pier 12A (and 12B) to the upper position of the carrying-out yard Yo, the 2nd leg 140 is The first leg 130 is installed in a state of being located on the unloading yard Yo side.

次に、同図(a)に示すように、撤去対象となるプレキャスト桁14(すなわち最後に撤去されるプレキャスト桁14)を、その上面に配置された床版16の一部と共に橋脚12Aから僅かに吊り上げる。   Next, as shown in FIG. 6A, the precast girder 14 to be removed (that is, the precast girder 14 to be removed last) is slightly removed from the pier 12A together with a part of the floor slab 16 arranged on the upper surface thereof. Suspend to.

その後、同図(b)〜(e)に示すように、吊り装置150を搬出ヤードYoの上方位置まで橋軸直交方向に移動させてから、吊り装置150によりプレキャスト桁14を搬出ヤードYoの撤去予定位置まで吊り下ろす。そして、この搬出ヤードYoからプレキャスト桁14をトレーラ等により搬出する。   Thereafter, as shown in FIGS. 5B to 5E, the suspension device 150 is moved in the direction perpendicular to the bridge axis to the upper position of the unloading yard Yo, and then the precast girder 14 is removed by the suspending device 150 from the unloading yard Yo. Suspend to the planned position. Then, the precast girder 14 is unloaded from the unloading yard Yo by a trailer or the like.

その際、同図(a)に示すように、プレキャスト桁14を吊り上げる前(または吊り上げた後)に、第1脚130側に位置する可動脚140Bを干渉回避位置へ移動させておく。そして、同図(b)に示すように、可動脚140Bを干渉回避位置へ移動させた状態で、吊り装置150の橋軸直交方向への移動を開始する。その後、同図(c)に示すように、吊り装置150が1対の可動脚140A、140Bの間の位置まで移動した時点で、可動脚140Bを元の位置へ移動させてから、同図(d)に示すように、第1脚130とは反対側に位置する可動脚140Aを干渉回避位置へ移動させる。そして、同図(e)に示すように、吊り装置150を搬出ヤードYoの上方位置まで移動させてから、プレキャスト桁14を撤去予定位置まで吊り下ろす。   At that time, before the precast girder 14 is lifted (or after it is lifted), the movable leg 140B located on the first leg 130 side is moved to the interference avoidance position, as shown in FIG. And as shown in the figure (b), the movement to the bridge axis orthogonal direction of the suspension apparatus 150 is started in the state which moved the movable leg 140B to the interference avoidance position. Thereafter, as shown in FIG. 5C, when the suspension device 150 moves to a position between the pair of movable legs 140A and 140B, the movable leg 140B is moved to the original position, and As shown in d), the movable leg 140A located on the opposite side of the first leg 130 is moved to the interference avoidance position. And as shown in the figure (e), after moving the suspending apparatus 150 to the upper position of the carrying-out yard Yo, the precast girder 14 is suspended to the removal planned position.

なお、他の2つのプレキャスト桁14についても、以上と同様の工程で撤去を行うことが可能である。   The other two precast girders 14 can be removed by the same process as described above.

次に、本実施形態の作用について説明する。   Next, the operation of this embodiment will be described.

本実施形態に係る橋梁撤去方法においては、既設のプレキャスト桁14を架設径間S0の側方に位置する搬出ヤードYoへ撤去する際、各橋脚12A(および12B)の上面において、橋形クレーン110を、クレーンガーダ120が搬出ヤードYoの上方位置まで張り出すとともに第2脚140が第1脚130に対して搬出ヤードYo側に位置する状態で設置した後、吊り装置150により、撤去対象となるプレキャスト桁14を吊り上げた後、吊り装置150を搬出ヤードYoの上方位置まで橋軸直交方向に移動させてから、プレキャスト桁14を搬出ヤードYoの撤去予定位置まで吊り下ろすことにより、プレキャスト桁14の撤去を行うようになっているので、搬出ヤードYoの撤去予定位置まで吊り下ろされたプレキャスト桁14に対して、桁吊りノーズ50の取外し作業および吊り装置150の取外し作業を行うだけでプレキャスト桁14の撤去作業を完了させることができる。したがって、架設径間S0に既設道路が存在するような場合においても、搬出ヤードYoからの桁搬入時に一時的に交通規制を行えば足り、このため交通規制時間を最小限に抑えることができる。   In the bridge removing method according to the present embodiment, when the existing precast girder 14 is removed to the carry-out yard Yo located on the side of the span span S0, the bridge crane 110 is formed on the upper surface of each pier 12A (and 12B). Is installed in a state where the crane girder 120 extends to the upper position of the unloading yard Yo and the second leg 140 is positioned on the unloading yard Yo side with respect to the first leg 130, and is then removed by the suspension device 150. After the precast girder 14 is lifted, the lifting device 150 is moved in the direction perpendicular to the bridge axis to the position above the carry-out yard Yo, and then the precast girder 14 is suspended to the planned removal position of the carry-out yard Yo. Since it is designed to be removed, the precast girder 14 is suspended to the planned removal position of the unloading yard Yo. Against, it is possible to complete the dismantling of the precast girder 14 by simply performing the removing work of detaching and lifting device 150 digit hanging nose 50. Therefore, even in the case where an existing road exists in the span between spans S0, it is sufficient to temporarily restrict traffic when carrying a girder from the carry-out yard Yo, so that the traffic regulation time can be minimized.

その上で、本実施形態に係る橋梁撤去方法においては、吊り装置150の橋軸直交方向への移動を、第1脚130側に位置する可動脚140Bを干渉回避位置へ移動させた状態で開始し、その後、吊り装置150が1対の可動脚140A、140Bの間の位置まで移動した時点で、第1脚130側に位置する可動脚140Bを元の位置へ移動させてから第1脚130とは反対側に位置する可動脚140Aを干渉回避位置へ移動させ、その後、吊り装置150を搬出ヤードYoの上方位置まで移動させるようになっているので、桁吊りノーズ50をいずれの可動脚140A、140Bとも干渉させることなく撤去予定位置まで移動させることができ、これによりプレキャスト桁14の撤去を円滑に行うことができる。   Then, in the bridge removing method according to the present embodiment, the movement of the suspension device 150 in the direction orthogonal to the bridge axis is started with the movable leg 140B located on the first leg 130 side moved to the interference avoidance position. Thereafter, when the suspension device 150 moves to a position between the pair of movable legs 140A and 140B, the movable leg 140B located on the first leg 130 side is moved to the original position and then the first leg 130 is moved. Since the movable leg 140A located on the opposite side to the position is moved to the interference avoidance position, and then the suspension device 150 is moved to a position above the carry-out yard Yo, the girder nose 50 can be moved to any movable leg 140A. , 140B can be moved to the planned removal position without interfering with each other, whereby the precast girder 14 can be removed smoothly.

なお、上記実施形態においては、その橋梁架設方法および橋梁撤去方法の適用対象が、高速道路のランプウェイ等のように架設径間に3つのプレキャスト桁14が配置される部分である場合について説明したが、高速道路の本線等のように4つ以上のプレキャスト桁14が配置される部分を適用対象とすることも可能である。   In the above embodiment, the case where the application object of the bridge erection method and the bridge removal method is a part where three precast girders 14 are arranged between the erection diameters such as a rampway of an expressway has been described. However, it is also possible to apply a portion where four or more precast girders 14 are arranged, such as a highway main line.

また、架設径間に単一の橋桁を架設する場合あるいは架設径間に架設された単一の橋桁を撤去する場合にも、上記実施形態に係る橋梁架設方法あるいは橋梁撤去方法を採用することが可能である。   Also, when a single bridge girder is installed between the installation diameters or when a single bridge girder installed between the installation diameters is removed, the bridge installation method or the bridge removal method according to the above embodiment may be adopted. Is possible.

次に、上記実施形態に係る橋形クレーン110の変形例について説明する。   Next, a modified example of the bridge crane 110 according to the above embodiment will be described.

図6は、本変形例に係る橋形クレーン210を示す、図2と同様の図である。   FIG. 6 is a view similar to FIG. 2 showing a bridge crane 210 according to this modification.

同図に示すように、この橋形クレーン210の基本的な構成は、上記実施形態に係る橋形クレーン110の場合と同様であるが、橋形クレーン110よりもさらに簡素化された構成となっている。   As shown in the figure, the basic configuration of the bridge crane 210 is the same as that of the bridge crane 110 according to the above embodiment, but is more simplified than the bridge crane 110. ing.

すなわち、この橋形クレーン210においては、その吊り装置250が、単一の電気チェーンブロック256を備えた構成となっている。また、この橋形クレーン210のクレーンガーダ220においては、橋軸直交方向に延びる1対のH形鋼220Aを橋軸直交方向の複数箇所において連結する連結鋼材220Bが、吊り装置250を囲むように配置された構成となっている。   That is, in the bridge crane 210, the suspension device 250 has a single electric chain block 256. Further, in the crane girder 220 of the bridge crane 210, a connecting steel material 220 </ b> B that connects a pair of H-section steels 220 </ b> A extending in the bridge axis orthogonal direction at a plurality of locations in the bridge axis orthogonal direction surrounds the suspension device 250. It is an arranged configuration.

そして、この橋形クレーン210の第2脚240を構成する1対の可動脚のうち、上記実施形態の可動脚140Aに対応する可動脚240Aは、クレーンガーダ220を構成する1対のH形鋼220Aの下端面に上端部がヒンジ部材242Aを介して連結された1対の鉛直材240A1と、この鉛直材240Aに上端部が剛結されるようにして橋軸方向に斜めに延びる1対の斜材240A2と、これら各斜材240A2の下端部と各鉛直材240A1の下端部とを連結する1対の連結鋼材240A3とで構成されている。   Of the pair of movable legs constituting the second leg 240 of the bridge crane 210, the movable leg 240A corresponding to the movable leg 140A of the above embodiment is a pair of H-section steels constituting the crane girder 220. A pair of vertical members 240A1 whose upper ends are connected to the lower end surface of 220A via a hinge member 242A, and a pair of members extending obliquely in the bridge axis direction so that the upper ends are rigidly connected to the vertical members 240A The diagonal member 240A2 is composed of a pair of connecting steel members 240A3 that connect the lower end portions of the diagonal members 240A2 and the lower end portions of the vertical members 240A1.

なお、他方の可動脚(すなわち上記実施形態の可動脚140Bに対応する可動脚)も、その鉛直材の断面形状が鉛直材240A1の断面形状よりも大きいほかは、可動脚240Aと同様の構成となっている。   The other movable leg (that is, the movable leg corresponding to the movable leg 140B in the above embodiment) has the same configuration as that of the movable leg 240A except that the vertical material has a larger cross-sectional shape than the vertical material 240A1. It has become.

本変形例の構成を採用した場合においても、上記実施形態の場合と同様の作用効果を得ることができる。   Even in the case of adopting the configuration of the present modification, it is possible to obtain the same operational effects as in the case of the above embodiment.

また、本変形例に係る橋形クレーン210においては、単一の電気チェーンブロック256が用いられているので、その分だけ上記実施形態に係る橋形クレーン110よりもコストダウンを図ることができる。   Further, in the bridge crane 210 according to this modification, since a single electric chain block 256 is used, the cost can be reduced as much as the bridge crane 110 according to the above embodiment.

なお、上記実施形態および変形例において諸元として示した数値は一例にすぎず、これらを適宜異なる値に設定してもよいことはもちろんである。   In addition, the numerical value shown as a specification in the said embodiment and modification is only an example, and of course, you may set these to a different value suitably.

12A、12B 橋脚
12Aa、12Ba 桁受け部
14 プレキャスト桁
14a 凹部
16 床版
50 桁吊りノーズ
52、120A、220A H形鋼
54、58、60 支持鋼材
56、62 鋼棒
64 カウンタウェイト
110、210 橋形クレーン
120、220 クレーンガーダ
120B、140A2、140A3、170、220B、240A3 連結鋼材
122 レール
124 固定具
130 第1脚
130A、140A1、140B1、240A1 鉛直材
130B、240A2 斜材
132、142A、142B、242A ヒンジ部材
140、240 第2脚
140A、140B、240A 可動脚
144A、144B 油圧ジャッキ
150、250 吊り装置
152 上部鋼材
154 ころがり機構
156、256 電気チェーンブロック
158 下部鋼材
160 調整コンクリート
180 牽引索
S0、S−1、S+1 架設径間
Yi 搬入ヤード
Yo 搬出ヤード
12A, 12B Bridge pier 12Aa, 12Ba Girder receiving part 14 Precast girder 14a Recess 16 Floor slab 50 Girder hanging nose 52, 120A, 220A H-shaped steel 54, 58, 60 Support steel 56, 62 Steel bar 64 Counter weight 110, 210 Bridge type Crane 120, 220 Crane girder 120B, 140A2, 140A3, 170, 220B, 240A3 Connecting steel material 122 Rail 124 Fixing tool 130 First leg 130A, 140A1, 140B1, 240A1 Vertical material 130B, 240A2 Diagonal material 132, 142A, 142B, 242A Hinge Member 140, 240 Second leg 140A, 140B, 240A Movable leg 144A, 144B Hydraulic jack 150, 250 Lifting device 152 Upper steel 154 Rolling mechanism 156, 256 Electric chain blow Click 158 lower steel 160 adjusts concrete 180 tow S0, S-1, S + 1 bridging span Yi loading yard Yo out Yards

Claims (5)

架設径間の橋軸方向両側に位置する1対の橋脚相互間に桁を架設する際、または上記1対の橋脚相互間に架設された桁を撤去する際に、上記1対の橋脚の各々の上面に設置した状態で用いられる橋形クレーンであって、
橋軸直交方向に延びるクレーンガーダと、このクレーンガーダを橋軸直交方向に所定間隔をおいて支持する第1脚および第2脚と、上記クレーンガーダに対して橋軸直交方向に移動可能に設置された状態で、上記桁の長手方向端部に取り付けられた桁吊りノーズを介して上記桁を吊り支持し得るように構成された吊り装置と、を備えた構成となっており、
上記第2脚は、橋軸直交方向に所定間隔をおいて設置された1対の可動脚で構成されており、
これら各可動脚は、上記吊り装置が橋軸直交方向に移動して該可動脚の設置箇所を通過する際、上記吊り装置に吊り支持された上記桁吊りノーズとの干渉を回避可能な干渉回避位置へ移動し得るように構成されている、ことを特徴とする橋形クレーン。
When installing a girder between a pair of bridge piers located on both sides in the bridge axis direction between spans, or when removing a girder built between the pair of bridge piers, A bridge crane used in the state installed on the upper surface of
A crane girder extending in the direction orthogonal to the bridge axis, a first leg and a second leg that support the crane girder at a predetermined interval in the direction orthogonal to the bridge axis, and movably installed in the direction orthogonal to the bridge axis with respect to the crane girder And a suspension device configured to be able to suspend and support the girder via a girder hanging nose attached to the longitudinal end of the girder,
The second leg is composed of a pair of movable legs installed at a predetermined interval in the direction orthogonal to the bridge axis,
These movable legs can avoid interference with the girder nose suspended and supported by the suspension device when the suspension device moves in the direction perpendicular to the bridge axis and passes through the installation location of the movable leg. A bridge crane characterized by being configured to move to a position.
上記各可動脚の上記干渉回避位置への移動が、回動運動により行われるように構成されている、ことを特徴とする請求項1記載の橋形クレーン。   The bridge crane according to claim 1, wherein each movable leg is moved to the interference avoidance position by a rotational motion. 上記1対の可動脚のうち、上記第1脚とは反対側に位置する可動脚の上記干渉回避位置への移動が、該可動脚の上端を支点とする上記第1脚とは反対側への回動運動により行われるとともに、上記第1脚側に位置する可動脚の上記干渉回避位置への移動が、該可動脚の上端を支点とする上記第1脚側への回動運動により行われるように構成されている、ことを特徴とする請求項2記載の橋形クレーン。   Of the pair of movable legs, the movement of the movable leg located on the opposite side of the first leg to the interference avoidance position moves to the opposite side of the first leg with the upper end of the movable leg as a fulcrum. The movement of the movable leg located on the first leg side to the interference avoidance position is performed by the pivoting movement toward the first leg with the upper end of the movable leg as a fulcrum. The bridge crane according to claim 2, wherein the bridge crane is configured as described above. 請求項1〜3いずれか記載の橋形クレーンを用いて、上記架設径間の側方に位置する搬入ヤードに搬入された桁を上記1対の橋脚相互間に架設する方法であって、
上記橋形クレーンを、上記クレーンガーダが上記搬入ヤードの上方位置まで張り出すとともに上記第2脚が上記第1脚に対して上記搬入ヤード側に位置するようにした状態で上記橋脚の上面に設置した後、
上記吊り装置により、上記搬入ヤードに搬入された架設対象となる桁を上記桁吊りノーズが上記橋脚の上面よりも上方に位置する高さまで吊り上げた後、上記吊り装置を上記桁の架設予定位置まで橋軸直交方向に移動させてから、上記桁を上記橋脚上に吊り下ろすことにより、上記桁の架設を行うようにし、
その際、上記吊り装置の橋軸直交方向への移動を、上記第1脚とは反対側に位置する可動脚を上記干渉回避位置へ移動させた状態で開始し、その後、上記吊り装置が上記1対の可動脚の間の位置まで移動した時点で、上記第1脚とは反対側に位置する可動脚を元の位置へ移動させてから上記第1脚側に位置する可動脚を上記干渉回避位置へ移動させ、その後、上記吊り装置を上記架設予定位置まで移動させる、ことを特徴とする橋梁架設方法。
A bridge crane according to any one of claims 1 to 3, wherein a girder carried into a carry-in yard located on the side between the erection diameters is installed between the pair of bridge piers,
The bridge crane is installed on the upper surface of the bridge pier with the crane girder extending to a position above the carry-in yard and the second leg positioned on the carry-in yard side with respect to the first leg. After
After the lifting device lifts the girders to be erected into the carry-in yard to a height where the girder hanging nose is located above the upper surface of the bridge pier, the hoisting device is moved to the planned erection position of the girders. After moving in the direction perpendicular to the bridge axis, suspend the girder on the pier, so that the girder is installed,
At that time, the suspension device starts to move in the direction perpendicular to the bridge axis in a state where the movable leg located on the opposite side of the first leg is moved to the interference avoidance position. When moving to a position between the pair of movable legs, the movable leg located on the opposite side of the first leg is moved to the original position, and then the movable leg located on the first leg side is interfered with. A bridge construction method, wherein the bridge is moved to an avoidance position, and then the suspension device is moved to the planned construction position.
請求項1〜3いずれか記載の橋形クレーンを用いて、上記1対の橋脚相互間に架設された桁を上記架設径間の側方に位置する搬出ヤードへ撤去する方法であって、
上記橋形クレーンを、上記クレーンガーダが上記搬出ヤードの上方位置まで張り出すとともに上記第2脚が上記第1脚に対して上記搬出ヤード側に位置するようにした状態で上記橋脚の上面に設置した後、
上記吊り装置により、上記1対の橋脚相互間に架設された撤去対象となる桁を吊り上げた後、上記吊り装置を上記搬出ヤードの上方位置まで橋軸直交方向に移動させてから、上記桁を上記搬出ヤードの撤去予定位置まで吊り下ろすことにより、上記桁の撤去を行うようにし、
その際、上記吊り装置の橋軸直交方向への移動を、上記第1脚側に位置する可動脚を上記干渉回避位置へ移動させた状態で開始し、その後、上記吊り装置が上記1対の可動脚の間の位置まで移動した時点で、上記第1脚側に位置する可動脚を元の位置へ移動させてから上記第1脚とは反対側に位置する可動脚を上記干渉回避位置へ移動させ、その後、上記吊り装置を上記搬出ヤードの上方位置まで移動させる、ことを特徴とする橋梁撤去方法。
Using the bridge crane according to any one of claims 1 to 3, a method of removing a girder constructed between the pair of bridge piers to a carry-out yard located on a side between the constructed diameters,
The bridge crane is installed on the upper surface of the bridge pier with the crane girder extending to a position above the carry-out yard and the second leg positioned on the carry-out yard side with respect to the first leg. After
After lifting the girders to be removed between the pair of bridge piers by the lifting device, the lifting device is moved in the direction perpendicular to the bridge axis to the upper position of the unloading yard, and then the girders are moved. The above girder is removed by suspending it to the planned removal position of the carry-out yard.
At that time, the suspension device is moved in the direction perpendicular to the bridge axis in a state where the movable leg located on the first leg side is moved to the interference avoidance position, and then the suspension device is moved to the pair of pairs. When moving to the position between the movable legs, the movable leg located on the first leg side is moved to the original position, and then the movable leg located on the side opposite to the first leg is moved to the interference avoidance position. A method for removing a bridge, comprising: moving the suspension device to a position above the carry-out yard.
JP2011069547A 2011-03-28 2011-03-28 Bridge crane, bridge erection method, and bridge removal method Active JP5702640B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011069547A JP5702640B2 (en) 2011-03-28 2011-03-28 Bridge crane, bridge erection method, and bridge removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011069547A JP5702640B2 (en) 2011-03-28 2011-03-28 Bridge crane, bridge erection method, and bridge removal method

Publications (2)

Publication Number Publication Date
JP2012202162A true JP2012202162A (en) 2012-10-22
JP5702640B2 JP5702640B2 (en) 2015-04-15

Family

ID=47183446

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011069547A Active JP5702640B2 (en) 2011-03-28 2011-03-28 Bridge crane, bridge erection method, and bridge removal method

Country Status (1)

Country Link
JP (1) JP5702640B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532744A (en) * 2014-12-05 2015-04-22 山东省路桥集团有限公司 Orbital transfer portal crane matched with movable formwork
JP2016121453A (en) * 2014-12-24 2016-07-07 オリエンタル白石株式会社 Dismantling and removal method of flip-up rotary bridge
JP2017002541A (en) * 2015-06-09 2017-01-05 オリエンタル白石株式会社 Bridge construction method
CN110607756A (en) * 2019-10-15 2019-12-24 合肥正浩机械科技有限公司 Connecting structure of main beam and supporting legs of bridge girder erection machine
CN114890321A (en) * 2022-05-24 2022-08-12 厦门市特种设备检验检测院 Hoisting machine convenient to install and installation method thereof
CN115231450A (en) * 2022-07-11 2022-10-25 山东省公路桥梁建设集团有限公司 Integral hoisting equipment for steel bar framework and using method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5968402A (en) * 1982-10-08 1984-04-18 日本通運株式会社 Gate hang-up machine for constructing pc beam
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JP2000178922A (en) * 1998-12-15 2000-06-27 Ps Corp Erection method and device for extension girder
JP2005155160A (en) * 2003-11-26 2005-06-16 Ishikawajima Harima Heavy Ind Co Ltd Bridge girder temporary supporting pedestal device and construction bent making use thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5968402A (en) * 1982-10-08 1984-04-18 日本通運株式会社 Gate hang-up machine for constructing pc beam
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JP2000178922A (en) * 1998-12-15 2000-06-27 Ps Corp Erection method and device for extension girder
JP2005155160A (en) * 2003-11-26 2005-06-16 Ishikawajima Harima Heavy Ind Co Ltd Bridge girder temporary supporting pedestal device and construction bent making use thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532744A (en) * 2014-12-05 2015-04-22 山东省路桥集团有限公司 Orbital transfer portal crane matched with movable formwork
JP2016121453A (en) * 2014-12-24 2016-07-07 オリエンタル白石株式会社 Dismantling and removal method of flip-up rotary bridge
JP2017002541A (en) * 2015-06-09 2017-01-05 オリエンタル白石株式会社 Bridge construction method
CN110607756A (en) * 2019-10-15 2019-12-24 合肥正浩机械科技有限公司 Connecting structure of main beam and supporting legs of bridge girder erection machine
CN110607756B (en) * 2019-10-15 2020-11-24 合肥正浩机械科技有限公司 Connecting structure of main beam and supporting legs of bridge girder erection machine
CN114890321A (en) * 2022-05-24 2022-08-12 厦门市特种设备检验检测院 Hoisting machine convenient to install and installation method thereof
CN115231450A (en) * 2022-07-11 2022-10-25 山东省公路桥梁建设集团有限公司 Integral hoisting equipment for steel bar framework and using method

Also Published As

Publication number Publication date
JP5702640B2 (en) 2015-04-15

Similar Documents

Publication Publication Date Title
JP5702640B2 (en) Bridge crane, bridge erection method, and bridge removal method
JP6476426B2 (en) Member renewal method using lifting device
EP3152363B1 (en) Method for building a bridge and bridge-building apparatus
KR101287455B1 (en) System and method for launching upper structure of bridege
JP7045936B2 (en) Hanger unit in deck erection machine
JP2010037727A (en) Equipment and method for erecting precast pc plate for floor slab
JP5890060B1 (en) Bridge dismantling method using erection girder
JP5184248B2 (en) Construction method of level crossing
KR101160273B1 (en) Straddle carrier for bridge construction
JP2024074895A (en) Change-over method of floor slab
JP2019214858A (en) Floor slab erection machine
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
JP3655161B2 (en) Bridge removal and erection methods
JP2005023623A (en) Suspension device for suspension scaffold for bridge and suspension scaffold assembling construction method using this device
JPH10195826A (en) Bridge construction method and device thereof
JP3349463B2 (en) How to install additional girder
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
JP5487031B2 (en) Bridge erection method
JP2019173435A (en) Floor system replacement method and floor system replacement device
JP7324626B2 (en) Lifted load moving device, removal method of existing bridge, and installation method of bridge members
JPH10237823A (en) Method for replacing overhead bridge
JP2020204263A (en) Superstructure member conveyance facility and superstructure member conveyance method
JP7421466B2 (en) Concrete slab replacement method
JP6682332B2 (en) Bridge removal method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130919

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140327

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20141021

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20141219

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150217

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150220

R150 Certificate of patent or registration of utility model

Ref document number: 5702640

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250