JP2004285711A - Construction method for enlarged tunnel - Google Patents
Construction method for enlarged tunnel Download PDFInfo
- Publication number
- JP2004285711A JP2004285711A JP2003079584A JP2003079584A JP2004285711A JP 2004285711 A JP2004285711 A JP 2004285711A JP 2003079584 A JP2003079584 A JP 2003079584A JP 2003079584 A JP2003079584 A JP 2003079584A JP 2004285711 A JP2004285711 A JP 2004285711A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- lining
- wall
- existing tunnel
- existing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は既設トンネルの一側部を拡幅してその拡幅部に歩道や新たな車線を設ける拡大トンネルの築造方法に関するものである。
【0002】
【従来の技術】
近年、交通量の増加に伴い、車線数の増加や歩道の増設を目的として既設トンネルの断面幅を拡大する工事が行われている。この際、拡大工事中においても一般車両の通行の迂回路を設けることなく、該既設トンネル内を通行路として使用することにより工期の短縮を図ると共に、工事期間中の安定した交通を確保することが提案されている。(例えば、特許文献1参照)。
【0003】
【特許文献1】
特開2000−356090号公報(第2〜4頁、第2、5図)。
【0004】
この特許文献1に記載された既設トンネルの拡幅方法は、築造すべき拡幅トンネルの断面を、既設トンネルに隣接して掘削する先進坑と既設トンネルの断面を含む後進坑とに分け、上記先進坑を掘削すると共にこの先進坑と上記後進坑とを分割する仕切り面に仮支保工としての中壁を構築し、上記先進坑の掘削形成後、上記中壁を残してままで上記後進坑を掘削し、この後進坑の掘削形成後、上記中壁を撤去することにより既設トンネルの断面を拡幅するものである。
【0005】
【発明が解決しようとする課題】
しかしながら、このような既設トンネルの拡幅方法において、上記中壁に最も要求される機能としては、先進坑と後進坑とを順次掘削して拡大トンネルを築造した際に、この拡大トンネルの天端周辺地盤の崩落を防止することにあり、そのため、中壁を拡大トンネルの断面形状の略中央部に施工する必要があるにもかかわらず、上記方法においては、中壁を既設トンネルの覆工体の一側方に施工されているために、先進坑の断面幅が狭くなればなる程、中壁の位置が拡大トンネルの一側部寄りに施工された状態となり、後進坑の掘削の際に拡大トンネルの天端周辺地盤が崩落する虞れがあった。また、上被りが浅い場合、崩落に限らず天端の大きな沈下により、地表面が沈下する虞れもあった。
【0006】
従って、先進坑の断面幅が既設トンネルの断面幅の2倍以上、幅広い場合には上記拡幅方法を採用することができても、先進坑の断面幅が歩道や一車線の幅に等しい、例えば、既設トンネルの半分程度の狭い幅の場合には採用することが困難であるという問題点があった。
【0007】
本発明は上記のような問題点に鑑みてなされたもので、その目的とするところは、既設トンネルの一側部に拡幅トンネル部を掘削、形成する際に、該既設トンネルの覆工体の一側部を拡幅トンネル部との仕切壁の一部に使用して、築造すべき拡大トンネルの天端周辺地盤をこの仕切壁を介して支持し得るようにした拡大トンネルの築造方法を提供するにある。
【0008】
【課題を解決するための手段】
上記目的を達成するために本発明の拡大トンネルの築造方法は、請求項1に記載したように、覆工体で覆工されている既設トンネルを拡幅してアーチ状の拡大トンネルを築造する方法であって、既設トンネルの一側部に沿って該既設トンネルの覆工体の一側部外周面を露出させ且つ高さがこの露出した覆工体一側部の上端よりも高い所定幅の拡幅トンネル部を掘削する第1工程と、この拡幅トンネル部の上端部と上記露出した覆工体の一側部の上端部間に壁体部を施工する第2工程と、この壁体部と拡幅トンネルに露出している上記覆工体部分とによって形成した仕切壁を残して覆工体の上周部側の地盤の掘削と該仕切壁以外の既設トンネルの壁体部分を撤去する第3工程と、仕切壁を撤去する第4工程とからなることを特徴としている。
【0009】
また、請求項2に係る発明は、上記拡大トンネルの築造方法における、拡幅トンネル部の上端部と露出した既設トンネル覆工体の一側部の上端部間に壁体部を施工する第2工程において、該壁体部の下端を既設トンネル覆工体の露出した一側部の上端に連結、支持させると共にその支持部の下方における既設トンネル覆工体の一側内周面側に、既設トンネル内に車両が通行可能な空間を残して既設トンネル覆工体の補強体を施工することを特徴とする。
【0010】
一方、請求項3に係る発明においては、上記拡幅トンネル部の上端部と既設トンネルにおける露出した覆工体の一側部の上端部間に壁体部を施工する第2工程より前に、該壁体部の下端の下方における既設トンネル覆工体の一側部内に、既設トンネル内に車両が通行可能な空間を残して既設トンネル覆工体の補強体を施工し、この補強体の上端部を既設トンネル覆工体の一側部に貫通させておき、第2工程において、該補強体の上端を上記壁体部の下端に一体に連結させることを特徴とする。
【0011】
【作用】
既設のトンネル、例えば、2車線の通行路幅を有する小径の既設トンネルの一側部に既設トンネルの断面幅よりも幅狭い一車線の通行路又は歩道を増設する場合、まず、既設トンネルの一側部に上記一車線分又は歩道の幅に等しい幅を有する拡幅トンネル部を掘削形成する。この際、既設トンネル側においては車両規制を行うことなく自由に通行させる。この拡幅トンネル部は、上記既設トンネルの覆工体における一側部外周面を露出させながら掘削され、且つ、その高さは既設トンネルの上記露出した覆工体の一側部の上方に達する高さ、即ち、築造すべき拡大トンネルの天端近傍部に達する高さとなるように掘削される。従って、拡幅トンネル部の両側掘削壁面における他側壁面の大部分は、上記既設トンネルの露出した覆工体の一側部外周面によって形成された構造となる。
【0012】
そして、上記露出した覆工体を他側壁面としてこの他側壁面に対向している拡幅トンネル部の一側方の掘削壁面を吹き付けコンクリート等によって覆工すると共に、この一側部の上端と上記露出した覆工体の上端間の掘削壁面に吹き付けコンクリート等による壁体部を施工し、この壁体部と拡幅トンネルに露出している上記覆工体部分とによって拡幅トンネル部と既設トンネルとを仕切っている仕切壁を形成する。
【0013】
この際、この壁体部の下端を露出した覆工体の一側部上端外周面に連結、支持させると共にこの支持部の下方における既設トンネル覆工体の一側内周面側に、既設トンネル覆工体の補強体を施工してこの補強体により上記壁体部にかかる土圧等を既設トンネルの覆工体を介して支持させるか、或いは、上記補強体の上端部を既設トンネルの覆工体の一側上端部を貫通させてその上端面で上記壁体部の下端を支持させておくことが望ましい。なお、この場合も、既設トンネルの一側部内に補強体を施工するにもかかわらず、既設トンネル内での車両の通行を妨げないようにする。
【0014】
次いで、上記仕切壁を残して既設トンネル覆工体の上周部側の地盤を掘削する。この際、仕切壁の上部を形成している上記壁体部は、築造すべき拡大トンネルの天端近傍部に設けられた構造としているので、既設トンネル覆工体の上周部側の地盤掘削時には、この壁体部によって拡大トンネルの天端周辺地盤が崩落するのを防止することができる。そして、既設トンネルの上記覆工体部分を解体、撤去すると共に該覆工体の上周部側の地盤を掘削してこの掘削壁面を吹き付けコンクリート等によって覆工する。この作業中においては上記仕切壁を残しておき、この仕切壁によって仕切られた拡幅トンネル部側を車両通行路として使用する。
【0015】
既設トンネルの覆工体における上周部側の地盤の掘削作業や掘削壁面に対する覆工作業、及び、既設トンネルの覆工体部分の撤去作業が全線或いは所定長さ完了した後、上記仕切壁を撤去することによって拡大トンネルを築造するものである。
【0016】
【発明の実施の形態】
次に、本発明の実施の形態を図面について説明すると、図1において、T1は例えば2車線の通行路を設けている小径の既設トンネルであって、本発明の実施の形態においては、この小径の既設トンネルT1の一側部に該既設トンネルT1の断面幅よりも幅狭い一車線分の通行路又は歩道を有する拡幅トンネル部T2を掘削、形成して図6に示すような拡大トンネルTを築造する方法について説明する。まず、拡幅トンネル部T2を掘削、形成する前に既設トンネルT1の覆工体tを補強しておく。
【0017】
この補強作業は、覆工体tの内周面に沿ってアーチ状に湾曲したH形鋼からなる支保工1を既設トンネルT1の長さ方向に所定間隔毎に建込むと共に、隣接する支保工1、1間に対する金網(図示せず)の張設や既設トンネルT1の覆工背面に対する薬液注入処理を行ったのち、拡幅トンネル部T2を掘削する側の覆工体tの一側部以外の覆工体t部分に、既設トンネルT1内から覆工体tの周辺地盤中に向かってロックボルト2、2・・・を放射状に打設し、後述するように覆工体tの周辺地盤を掘削する際において、該周辺地盤が崩壊するのを予め防止した構造としておく。
【0018】
また、既設トンネルT1の一側部内において、覆工体tの一側部内周面の上部と床面一側部との間にH形鋼からなる型枠兼用の補強縦枠材3を既設トンネルT1の長さ方向に一体間隔毎に建て込み、その上下端を覆工体tの一側部内周面の上部と床面一側部とにそれぞれ固着すると共に隣接する補強縦枠材3、3間に矢板4を嵌め込んで型枠を形成し、この型枠と既設トンネルT1の覆工体tの一側部内周面とで囲まれた空間部にコンクリート5を打設、充填して硬化させることにより、既設トンネルT1の一側部に覆工体tの一側部と一体化して該一側部を補強した補強体Aを形成する。なお、この補強体Aは既設トンネルT1内で車両の通行を妨げない通路幅を残して既設トンネルT1の一側部内に施工される。また、この補強体Aの施工作業や上記ロックボルト2、2・・・の打設による覆工体tの補強作業等は夜間において、車両を一時通行止めすることにより行われ、これらの作業終了後は既設トンネルT1内を自由に通行させる。
【0019】
一方、既設トンネルT1の覆工体tの一側部外周面から外側方部に、図2に示すように、この既設トンネルT1の長さ方向に沿って、該既設トンネルT1の断面幅の1/2程度の幅を有し、内部を一車線分の車両の通行路または歩道とするための拡幅トンネル部T2を掘削形成する。この拡幅トンネル部T2の掘削形成は、まず、既設トンネルT1の覆工体tの一側部側の周辺地盤における上半部を掘削する。
【0020】
この際、該上半部の上端部の高さ、即ち、形成すべき拡幅トンネル部T2の上端部Bの高さが覆工体tの天端部よりも高くなるように、且つ、該上端部Bが既設トンネルT1の覆工体tの一側部の上方に位置するように掘削すると共に、この上端部Bから既設トンネルT1側に対して、その覆工体tの一側部上端に向かって斜め下方に傾斜した傾斜掘削壁面B1となるように掘削する一方、該上端部Bから外側下方に向かって円弧状に湾曲した掘削壁面B2となるように掘削する。さらに、上記傾斜掘削壁面B1の下端が既設トンネルT1の覆工体tの一側部上端に達するまで掘削されると、該覆工体tの一側部外周面の上部を露出させながら既設トンネルT1の上半部における下部を図2の仮想線Dに示す位置まで掘削形成する。
【0021】
従って、拡幅トンネル部T2の上半部における上部の断面形状は上端部Bから下方に向かって徐々に幅広くなってあたかも竹の子の先端部の断面形状に等しい形状に形成され、覆工体tの一側部の上部外周面が露出したのちは、この露出面と上記一側方の円弧状掘削壁面B2との間の幅が下方に向かって僅かに幅広くなるように掘削するか、或いは、略等しい幅でもって掘削する。
【0022】
こうして、拡幅トンネル部T2における上端部Bから仮想線Dに達する上半部が掘削されると、その掘削壁面B1、B2にコンクリートを吹き付けて一次吹き付けコンクリート層6を形成したのち、これらの掘削壁面B1、B2にトンネル長さ方向に所定間隔毎にH形鋼よりなる鋼製支保工7a、7bをそれぞれ建て込む。この際、傾斜掘削壁面B1に建て込まれた鋼製支保工7aはその上端を上記円弧状掘削壁面B2側に建て込まれた鋼製支保工7bの上端に一体に連結されると共に下端は拡幅トンネル部T2の覆工体tにおける露出した一側部上端に連結、支持させる。
【0023】
さらに、これらの鋼製支保工7a、7bの建て込み後、二次吹き付けコンクリート層8を設けると共に鋼製支保工7a、7bの長さ方向に所定間隔毎にロックボルト2a、2bをそれぞれ打設することにより、掘削壁面B1、B2からの地盤の崩落を防止した覆工壁体部9A、9Bをそれぞれ形成する。
【0024】
図3は上記傾斜掘削壁面B1側の覆工壁体部9Aを支持した既設トンネルT1における覆工体t部分の拡大断面図であって、既設トンネルT1の一側部内に築造された上記補強体Aの上端上方部における既設トンネル覆工体tの露出している一側部上端に切欠段部10を削成し、この切欠段部10に上記鋼製支保工7aの下端エンドプレート7a’ を当接、受止させ、このエンドプレート7a’ をアンカーボルトとナット11によって切欠段部10に固定、支持させ、上記補強体Aによって補強された既設トンネル覆工体tにおける露出した一側部上端に、上記鋼製支保工7aを有する覆工壁体部9Aを介して拡幅トンネル部T2の上端側地盤を支持させ、該地盤の崩壊を防止した構造としている。そして、上記覆工壁体部9Aと補強体Aにより補強されてこの覆工壁体部9Aを支持している既設トンネル覆工体tの一側部とによって、後述する拡大トンネルTを築造する際における拡幅トンネル部T2に対する仕切壁Eを構成している。
【0025】
次いで、拡幅トンネル部T2において、上記仮想線Dから底面に達するまでの拡幅トンネル部T2の下半部を掘削する。この掘削は既設トンネルT1の覆工体tの一側部側においてはその一側部における覆工体tの下部外周面を露出させながら下端まで掘削する一方、円弧状に湾曲した掘削壁面B2側においては、この掘削壁面B2を下方に延長するようにして上記上半部の幅でもって、或いは、その幅を徐々に広がらせながら掘削する。
【0026】
しかるのち、図2に示すように、この下半部における円弧状に湾曲した掘削壁面B2’ 、即ち、拡幅トンネル部T2の一側掘削壁面にコンクリートを吹き付けて上記一次吹き付けコンクリート層6の下端に連続する一次吹き付けコンクリート層6’を形成したのち、トンネル長さ方向に所定間隔毎に上記上半部側の鋼製支保工7bから連続したH形鋼よりなる鋼製支保工7b’ を建て込み、次いで、上記上半部側の二次吹き付けコンクリート層8の下端に連続する二次吹き付けコンクリート層8’を設けると共に鋼製支保工7b’ の長さ方向(掘削壁面B2’ の円弧長方向) に所定間隔毎にロックボルト2bを打設することにより、掘削壁面B2’ からの地盤の崩落を防止した覆工壁体部9B’ (上記覆工壁体部9Aの下端に連続している)を形成する。
【0027】
このように拡幅トンネル部T2の掘削、及び掘削壁面B1、B2を補強した覆工壁体部9A、9Bの形成が終了すると、図4に示すように、既設トンネルT1の覆工体t一側部に沿って拡幅トンネル部T2内に上端が上記上端部Bに連続し、下端がこの拡幅トンネル部T2の底面他端部に固定した垂直な防護壁12を設置すると共に既設トンネルT1の底部と略面一状となるように掘削された拡幅トンネル部T2の底面に仮舗装13を施工する一方、円弧状に湾曲した覆工壁体部9B、9B’ の内面に防水シート14を張設する。なお、上記防護壁12は拡幅トンネル部T2に面している既設トンネルT1の覆工体tの一側部を隠蔽して拡幅トンネル部T2内を車両が一層安全に走行できるように設けられたものであり、この防護壁12から一車線路の幅を存して拡幅トンネル部T2の一下側覆工壁体部9B’ に沿ってガードレール15をトンネル長さ方向に立設する。
【0028】
こうして、拡幅トンネル部T2内を車両が交互通行可能な状態にしてのち、既設トンネルT1内からこの拡幅トンネル部T2内に車線を変更し、既設トンネルT1側の掘削作業を開始する。この掘削作業は、図5に示すように、上記補強体Aによって補強されている既設トンネルT1の一側覆工体部分と上記覆工壁体部9Aとからなる仕切壁Eを残して、既設トンネルT1の覆工体tの撤去と、仕切壁Eの覆工壁体部9Aで仕切られた既設トンネルT1の覆工体tの上周部側の地盤を掘削することにより行われる。
【0029】
即ち、既設トンネルT1内から、該既設トンネルT1の一側部以外の覆工体tを支保工1の解体後に破砕、撤去して該覆工体上周部側の地盤を露出させたのち、この地盤を適宜な掘削機械を使用してその掘削壁面t1が上記拡幅トンネル部T2の円弧状に湾曲した一側掘削壁面B2の上端からこの掘削壁面B2と略同じ湾曲度でもって該掘削壁面B2を覆工体tの他側部に向かって延長するように掘削し、該掘削壁面T1を覆工体tの他側部下端に連続させるものである。
【0030】
詳しくは、上記仕切壁Eの上部を形成している覆工壁体部9A側が最も上下掘削幅が広くなり、この覆工壁体部9B側から既に撤去している既設トンネルT1の覆工体tの上周部外周面に沿うようにして該既設トンネルT1の覆工体tの他側部に向かうに従って覆工体tとの間の上下掘削幅が徐々に狭くなるように円弧状に掘削し、既設トンネルT1を拡大した空間部Cを形成するものである。なお、既設トンネルT1の覆工体tの撤去時及び地盤の掘削時には、その掘削すべき地盤内に存在しているロックボルト2部分を切除する。
【0031】
こうして、既設トンネルT1の覆工体tの撤去と共にその上周部側の地盤を掘削して拡大空間部Cを形成したのち、この拡大空間部Cの円弧状に湾曲した掘削壁面t1に一次吹き付けコンクリート層16を施工し、次いで、上記拡幅トンネル部T2の一側掘削壁面B2にトンネル長さ方向に所定間隔毎に建て込んでいる各鋼製支保工7bの上端に一端を連続させて、上記掘削壁面t1に同じくH形鋼よりなる支保工7cを順次建て込み、しかるのち、該掘削壁面t1に二次吹き付けコンクリート層17を施工することによって覆工壁面18を形成する。
【0032】
次いで、上記補強体Aによって補強された既設トンネル覆工体tの一側部と壁体部9Aとからなる仕切壁Eを解体、撤去したのち、底面に上記拡幅トンネル部T2の仮舗装13と面一状となるように仮舗装19すると共に、掘削壁面t1に、上記拡幅トンネル部T2の円弧状掘削壁面B2に張設した防水シート14と連続するように防水シート14’ を張設する。この状態にして、上記拡幅トンネル部T2と防護壁12を介して区画されている既設トンネルT1を拡大した拡大トンネル部内で車両の通行を可能にして拡幅トンネル部T2側からこの拡大トンネル部内に車線変更を行う。
【0033】
しかるのち、図6に示すように、拡幅トンネル部T2側から防護壁12を解体、撤去することによって拡大トンネルTを構成し、拡幅トンネル部T2側の掘削壁面B2に張設している防水シート14と拡大トンネル部T’側の掘削壁面t1に張設している防水シート14’ とを接続させると共にこの拡大トンネルT内での車線の位置変更等を行い、さらに、舗装や覆工工事、内装設備工事等を行って拡大トンネルTの築造を終了するものである。
【0034】
なお、以上の実施の形態において、既設トンネルT1の一側方に拡幅トンネル部T2を掘削形成した時に、その上端部Bから既設トンネルT1の覆工体tの一側部上端に向かって施工している覆工壁体部9Aは、図3に示すように、その下端を上記覆工体tの一側部上端に連結、支持させているが、図7に示すように、既設トンネルT1の一側部内に形成している補強体Aにおける補強縦枠材3の上端部を覆工体tの一側部上端を貫通させて覆工体tから外周方に突出させ、その突出上端面に上記覆工壁体部9Aにおける鋼製支保工7aの下端面を突き合わせ状態にしてボルト20により一体に連結した構造としておいてもよい。
【0035】
また、上記実施の形態においては、既設トンネル覆工体tの補強体Aは、補強縦枠材3とコンクリート5とから構成しているが、本発明の既設トンネル覆工体tの補強体はこれに限らず、例えば、補強縦枠材3のみ、或いはコンクリート5のみで形成しておいてもよい。
【0036】
【発明の効果】
以上のように本発明の拡大トンネルの築造方法によれば、請求項1に記載したように、覆工体で覆工されている既設トンネルを拡幅してアーチ状の拡大トンネルを築造する方法であって、既設トンネルの一側部に沿って該既設トンネルの覆工体の一側部外周面を露出させ且つ高さがこの露出した覆工体一側部の上端よりも高い所定幅の拡幅トンネル部を掘削する第1工程と、この拡幅トンネル部の頂部と上記露出した覆工体の一側部の上端部間に壁体部を施工する第2工程と、この壁体部と拡幅トンネルに露出している上記覆工体部分とによって形成した仕切壁を残して覆工体の上周部側の地盤の掘削と該仕切壁以外の既設トンネルの壁体部分を撤去する第3工程と、仕切壁を撤去する第4工程とからなることを特徴とするものであるから、拡幅トンネル部の掘削形成時には既設トンネル内を車両の通行路として使用することができると共にこの拡幅トンネル部の形成後、既設トンネルの拡大作業時においては上記拡幅トンネル部内を車両の通行路として使用することができ、従って、車両の通行を全面的に遮断したり迂回させたりすることなく、拡大トンネルの築造が能率よく行うことができ、工期の短縮を図ることができる。
【0037】
さらに、上記拡幅トンネル部における既設トンネル側の掘削壁面の大部分をこの既設トンネルの露出した覆工体の一側部外周面によって形成しているので、該掘削壁面に対する地盤崩落防止処理等が省略することができて工費の低減と作業能率の向上を図ることができると共に、拡幅トンネル部の最上端と既設トンネルにおける上記露出した覆工体の一側部の上端部間の掘削壁面に壁体部を施工するので、この壁体部を拡幅トンネル部の覆工体側に強固に支持させることができ、その上、この壁体部を設けている掘削壁面は既設トンネルにおける上記露出した覆工体の一側部上方に位置するので、壁体部を築造すべき拡大トンネルの幅方向の中央部、即ち、天端部分に設けることができ、従って、既設トンネルの周辺上方地盤を掘削して拡大トンネルを築造する際に、その天端周辺の地盤をこの壁体部によって確実に支持して地盤の崩落を防止することができる。
【0038】
また、既設トンネルの周辺上方地盤を掘削する際には、上記壁体部と既設トンネルの覆工体における露出した一側部を、拡幅トンネル部側に対する仕切壁として使用して拡幅トンネル部内での車両の通行に支障を及ぼすことなく拡大掘削作業を行うことができるものであり、拡幅トンネル部が一車線、或いは歩道用としての幅狭いトンネル部であって、このトンネル部を既設トンネルの一側部に設けることにより拡大トンネルを築造することができる好適な方法を提供し得るものである。
【0039】
このような拡大トンネル築造方法において、請求項2に係る発明は、上記拡幅トンネル部の頂部と露出した覆工体の一側部の上端部間に壁体部を施工する際に、該壁体部の下端を覆工体の露出した一側部の上端に連結、支持させるので、覆工体の一側部を壁体部の支持体として利用して壁体部と共に上述したように拡幅トンネル部側に対する仕切壁を形成することができ、且つ、拡大トンネルの掘削時における天端周辺の地盤を壁体部を介して既設トンネルの覆工体の一側部に確実に支持させることができる。さらに、その支持部の下方における既設トンネル覆工体の一側内周面側に、既設トンネル内に車両が通行可能な空間を残して既設トンネル覆工体の補強体を施工するので、上記壁体部の支持力が一層強大となり、この壁体部を介しての拡大トンネルの掘削時における天端周辺の地盤崩落を確実に防止することができる。
【0040】
一方、請求項3に係る発明によれば、拡幅トンネル部の上端部と露出した覆工体の一側部の上端部間に壁体部を施工する際に、該壁体部の下端の下方における既設トンネル覆工体の一側部内に、既設トンネル内に車両が通行可能な空間を残して上記既設トンネル覆工体の補強体を施工し、この補強体の上端部を既設トンネル覆工体の一側部を貫通させて上記壁体部の下端に一体に連結させるので、補強体を既設トンネル内における車両通路側に対する仕切部材としての役目と共に壁体部を強固に支持した支持部材として共用させることができ、壁体部を介しての掘削壁面の確実にして安定した支持構造を構成することができる。
【図面の簡単な説明】
【図1】既設トンネルの一側部内に補強壁体部を施工している状態の縦断正面図、
【図2】既設トンネルの一側部に沿って拡幅トンネル部を掘削形成している状態の縦断正面図、
【図3】覆工壁体部の支持構造を示す既設トンネルの一部の拡大縦断正面図、
【図4】拡幅トンネル部内に防護壁等を施工した状態の縦断正面図、
【図5】既設トンネル側を拡大して拡大トンネルを形成している状態の縦断正面図、
【図6】拡大トンネルの縦断正面図、
【図7】覆工壁体部の支持構造の別な形態を示す一部の拡大縦断正面図。
【符号の説明】
T 拡大トンネル
T1 既設トンネル
t 覆工体
T2 拡幅トンネル部
A 補強壁体部
B 拡幅トンネル部の掘削上端部
E 既設トンネル覆工体の補強体
9A 覆工壁体部
1 支保工
2 ロックボルト
3 補強縦枠材
7 鋼製支保工
12 防護壁[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for constructing an enlarged tunnel in which one side of an existing tunnel is widened and a sidewalk or a new lane is provided in the widened portion.
[0002]
[Prior art]
2. Description of the Related Art In recent years, with the increase in traffic volume, construction for increasing the cross-sectional width of an existing tunnel has been performed for the purpose of increasing the number of lanes and increasing the number of sidewalks. At this time, even during the expansion work, the construction time will be shortened by using the existing tunnel as a passageway without providing a detour for general vehicles, and the stable traffic during the construction period will be secured. Has been proposed. (For example, see Patent Document 1).
[0003]
[Patent Document 1]
JP-A-2000-356090 (
[0004]
The method of widening an existing tunnel described in Patent Document 1 divides the cross section of the widening tunnel to be built into an advanced pit excavated adjacent to the existing tunnel and a reverse pit including the cross section of the existing tunnel, And constructing an intermediate wall as a temporary support on a partition surface separating the advanced pit and the reverse pit, and excavating the reverse pit while leaving the intermediate wall after forming the excavation of the advanced pit After the excavation of the backward shaft, the cross section of the existing tunnel is widened by removing the inner wall.
[0005]
[Problems to be solved by the invention]
However, in such a widening method of the existing tunnel, the most required function of the middle wall is to construct an enlarged tunnel by sequentially digging an advanced pit and a reverse pit, and constructing an enlarged tunnel around the top end of the enlarged tunnel. In order to prevent the ground from collapsing, it is necessary to construct the middle wall at the approximate center of the cross-sectional shape of the enlarged tunnel. Because it is constructed on one side, as the section width of the advanced pit becomes narrower, the position of the inner wall is enlarged.It is constructed closer to one side of the tunnel, and it expands when excavating the reverse tunnel. There was a risk that the ground around the top of the tunnel would collapse. In addition, when the top cover is shallow, there is a possibility that the ground surface may sink due to a large sink at the top end as well as the collapse.
[0006]
Therefore, even if the cross-sectional width of the advanced pit is at least twice the cross-sectional width of the existing tunnel and is wide, even if the widening method can be adopted, the cross-sectional width of the advanced pit is equal to the width of the sidewalk or one lane. However, there is a problem that it is difficult to adopt the case where the width is about half as narrow as the existing tunnel.
[0007]
The present invention has been made in view of the above problems, and an object thereof is to excavate and form a widened tunnel portion on one side of an existing tunnel, and to form a lining body of the existing tunnel. Provided is a method of constructing an enlarged tunnel in which one side portion is used as a part of a partition wall with the widened tunnel portion so that the ground around the top end of the enlarged tunnel to be built can be supported through the partition wall. It is in.
[0008]
[Means for Solving the Problems]
To achieve the above object, a method for constructing an enlarged tunnel according to the present invention is a method for constructing an arch-shaped enlarged tunnel by widening an existing tunnel covered with a lining body, as described in claim 1. And an outer peripheral surface of one side of the lining of the existing tunnel is exposed along one side of the existing tunnel, and the height of the predetermined width is higher than the upper end of the one side of the exposed lining. A first step of excavating the widened tunnel, a second step of constructing a wall between the upper end of the widened tunnel and the upper end of one side of the exposed lining, Excavating the ground on the upper peripheral side of the lining body while leaving the partition wall formed by the above-mentioned lining body part exposed to the widening tunnel, and removing the wall part of the existing tunnel other than the partition wall; And a fourth step of removing the partition wall.
[0009]
The invention according to
[0010]
On the other hand, in the invention according to
[0011]
[Action]
When an existing one-lane traffic lane or sidewalk narrower than the cross-sectional width of the existing tunnel is added to one side of the existing tunnel, for example, a small-diameter existing tunnel having a two-lane lane width, the existing tunnel must first be reconstructed. A widened tunnel portion having a width equal to the width of the one lane or the sidewalk is formed in the side portion. At this time, the existing tunnel is allowed to pass freely without restricting the vehicle. The widened tunnel portion is excavated while exposing an outer peripheral surface of one side of the lining body of the existing tunnel, and has a height reaching above one side of the exposed lining body of the existing tunnel. That is, it is excavated so as to reach a height near the top end of the enlarged tunnel to be built. Therefore, most of the other side wall surface of the excavated wall surface on both sides of the widening tunnel portion has a structure formed by the outer peripheral surface of one side of the exposed lining of the existing tunnel.
[0012]
The exposed lining body is used as the other side wall surface, and the excavated wall surface on one side of the widening tunnel portion facing the other side wall surface is laid by spraying concrete or the like. A wall part made of sprayed concrete or the like is constructed on the excavation wall between the upper ends of the exposed lining body, and the widening tunnel part and the existing tunnel are connected by the wall part and the lining part exposed to the widening tunnel. Forming partition walls.
[0013]
At this time, the lower end of the wall portion is connected to and supported by the outer peripheral surface of the upper end of the exposed side of the lining body, and the existing tunnel lining body is provided with the existing tunnel below the supporting portion. Either a reinforced body of the lining is applied and the earth pressure or the like applied to the wall portion is supported by the reinforced body through the lining of the existing tunnel, or the upper end of the reinforcing body is covered with the lining of the existing tunnel. It is desirable to penetrate the upper end of one side of the body and to support the lower end of the wall at the upper end surface. In this case as well, despite the construction of the reinforcing member in one side of the existing tunnel, the traffic of the vehicle in the existing tunnel is not obstructed.
[0014]
Next, the ground on the upper peripheral side of the existing tunnel lining body is excavated while leaving the partition wall. At this time, since the wall portion forming the upper portion of the partition wall is provided near the top end of the enlarged tunnel to be built, the ground excavation on the upper peripheral side of the existing tunnel lining body is performed. At times, the ground can prevent the ground around the top end of the enlarged tunnel from collapsing. Then, the above-mentioned lining body portion of the existing tunnel is dismantled and removed, and the ground on the upper peripheral side of the lining body is excavated. During this operation, the above-mentioned partition wall is left, and the widened tunnel section side partitioned by this partition wall is used as a vehicle passage.
[0015]
After the excavation work of the ground on the upper peripheral side in the lining body of the existing tunnel and the lining work on the digging wall surface, and the removal work of the lining body part of the existing tunnel are completed on the entire line or a predetermined length, the partition wall is removed. By removing it, an enlarged tunnel is built.
[0016]
BEST MODE FOR CARRYING OUT THE INVENTION
Next, an embodiment of the present invention will be described with reference to the drawings. In FIG. 1, T1 is an existing small-diameter tunnel provided with a two-lane traffic path, for example. In one side of the existing tunnel T1, a widened tunnel T2 having a traffic lane or sidewalk for one lane narrower than the cross-sectional width of the existing tunnel T1 is excavated and formed to form an enlarged tunnel T as shown in FIG. The method of building will be described. First, before excavating and forming the widened tunnel portion T2, the lining body t of the existing tunnel T1 is reinforced.
[0017]
In this reinforcing work, the support 1 made of H-shaped steel curved in an arch shape along the inner peripheral surface of the lining body t is erected at predetermined intervals in the length direction of the existing tunnel T1, and the adjacent support After stretching a wire mesh (not shown) between the first and the first and performing a chemical solution injection process on the back surface of the lining of the existing tunnel T1, excluding the one side of the lining body t on the side where the widening tunnel portion T2 is excavated. In the lining body t, the
[0018]
Further, in one side of the existing tunnel T1, a reinforcing
[0019]
On the other hand, as shown in FIG. 2, along the longitudinal direction of the existing tunnel T1, one section of the cross-sectional width of the existing tunnel T1 extends from the outer peripheral surface of one side of the lining body t of the existing tunnel T1 to the outside. A widened tunnel portion T2 having a width of about / 2 and having the inside as a traffic lane or a sidewalk for one lane is formed by excavation. In the excavation of the widened tunnel portion T2, first, the upper half of the surrounding ground on one side of the lining body t of the existing tunnel T1 is excavated.
[0020]
At this time, the height of the upper end of the upper half, that is, the height of the upper end B of the widened tunnel portion T2 to be formed is higher than the top end of the lining body t, and Excavation is performed so that the part B is located above one side of the lining body t of the existing tunnel T1, and from the upper end B to the upper end of one side of the lining body t with respect to the existing tunnel T1. Excavation is performed so as to form an inclined excavation wall surface B1 that is inclined diagonally downward, while excavation is performed so as to form an excavation wall surface B2 that is curved in an arc shape from the upper end portion B outward and downward. Further, when the lower end of the inclined excavation wall B1 is excavated until reaching the upper end of one side of the lining body t of the existing tunnel T1, the existing tunnel is exposed while exposing the upper part of the outer peripheral surface of one side of the lining body t. The lower part of the upper half of T1 is excavated and formed to the position shown by the imaginary line D in FIG.
[0021]
Therefore, the cross-sectional shape of the upper part in the upper half portion of the widening tunnel portion T2 is gradually increased from the upper end portion B downward, and is formed as if the cross-sectional shape is equal to the cross-sectional shape of the tip of the bamboo shoot. After the upper outer peripheral surface of the side portion is exposed, the excavation is performed such that the width between the exposed surface and the one sided arc-shaped excavation wall surface B2 is slightly widened downward, or substantially equal. Excavate with width.
[0022]
When the upper half of the widened tunnel portion T2 reaching the imaginary line D from the upper end portion B is excavated in this way, concrete is sprayed on the excavated wall surfaces B1 and B2 to form a primary sprayed
[0023]
Further, after the steel supports 7a, 7b are erected, a secondary sprayed
[0024]
FIG. 3 is an enlarged cross-sectional view of a lining body t portion of the existing tunnel T1 supporting the
[0025]
Next, in the widening tunnel portion T2, the lower half of the widening tunnel portion T2 from the imaginary line D to the bottom is excavated. In this excavation, on one side of the lining body t of the existing tunnel T1, the digging is performed to the lower end while exposing the lower outer peripheral surface of the lining body t on the one side, and the digging wall B2 side curved in an arc shape. In this case, digging is performed by extending the digging wall B2 downward with the width of the upper half portion or while gradually increasing the width.
[0026]
Thereafter, as shown in FIG. 2, concrete is sprayed on the excavated
[0027]
When the excavation of the widened tunnel portion T2 and the formation of the
[0028]
Thus, after the vehicle is allowed to pass alternately in the widened tunnel portion T2, the lane is changed from the existing tunnel T1 to the widened tunnel portion T2, and the excavation work on the existing tunnel T1 side is started. As shown in FIG. 5, this excavation work is performed while leaving a partition wall E composed of one side lining body part of the existing tunnel T1 reinforced by the reinforcing body A and the
[0029]
That is, from inside the existing tunnel T1, the lining body t other than one side of the existing tunnel T1 is crushed and removed after disassembly of the support 1 to expose the ground on the upper peripheral side of the lining body. Using an appropriate excavating machine, the excavated wall surface t2 of the excavated wall surface t1 is formed from the upper end of the one-side excavated wall surface B2 curved in an arc shape of the widening tunnel portion T2 with substantially the same degree of curvature as the excavated wall surface B2. Is excavated so as to extend toward the other side of the lining body t, and the excavated wall surface T1 is connected to the lower end of the other side of the lining body t.
[0030]
Specifically, the
[0031]
In this way, after removing the lining body t of the existing tunnel T1 and excavating the ground on the upper peripheral side to form the enlarged space C, the primary spraying is performed on the excavated wall surface t1 curved in an arc shape of the enlarged space C. The
[0032]
Next, after separating and removing the partition wall E including one side portion of the existing tunnel lining body t reinforced by the reinforcing member A and the
[0033]
Thereafter, as shown in FIG. 6, the
[0034]
In the above-described embodiment, when the widened tunnel portion T2 is excavated and formed on one side of the existing tunnel T1, construction is performed from the upper end portion B toward the upper end of one side of the lining body t of the existing tunnel T1. The lower end of the
[0035]
In the above embodiment, the reinforcing member A of the existing tunnel lining body t is composed of the reinforcing
[0036]
【The invention's effect】
As described above, according to the method for constructing an enlarged tunnel of the present invention, as described in claim 1, a method of constructing an arch-shaped enlarged tunnel by widening an existing tunnel covered with a lining body. A widening of a predetermined width that exposes an outer peripheral surface of one side of the lining of the existing tunnel along one side of the existing tunnel and has a height higher than an upper end of the one side of the exposed lining; A first step of excavating the tunnel, a second step of constructing a wall between the top of the widened tunnel and an upper end of one side of the exposed lining, and a step of excavating the wall and the widened tunnel Excavating the ground on the upper peripheral side of the lining body while leaving the partition wall formed by the lining body part exposed to the outside, and removing the wall part of the existing tunnel other than the partition wall; And the fourth step of removing the partition wall. When the wide tunnel is excavated, the existing tunnel can be used as a traffic path for the vehicle, and after the wide tunnel is formed, when the existing tunnel is expanded, the wide tunnel is used as a traffic path for the vehicle. Therefore, the construction of the enlarged tunnel can be efficiently performed without completely blocking or bypassing the traffic of the vehicle, and the construction period can be shortened.
[0037]
Furthermore, since most of the excavated wall surface on the existing tunnel side in the widened tunnel portion is formed by the outer peripheral surface of one side of the exposed lining body of the existing tunnel, ground collapsing prevention processing for the excavated wall surface is omitted. The excavation wall between the top end of the widening tunnel and the upper end of one side of the exposed lining in the existing tunnel can be reduced while reducing the construction cost and improving the work efficiency. Since the wall portion is constructed, the wall portion can be firmly supported on the lining side of the widening tunnel portion, and the excavated wall surface on which the wall portion is provided is the exposed lining portion in the existing tunnel. Because it is located above one side of the tunnel, it can be provided at the center in the width direction of the enlarged tunnel where the wall is to be built, that is, at the top end. When construction of the tunnel, it is possible to prevent the collapse of the ground and securely support the ground around the top end by the wall portion.
[0038]
Also, when excavating the ground above the existing tunnel, the exposed side of the wall and the lining of the existing tunnel are used as a partition wall for the widened tunnel and the inside of the widened tunnel is used. Enlarged excavation work can be performed without hindering the passage of vehicles. The widened tunnel is a narrow lane for one lane or sidewalk, and this tunnel is connected to one side of the existing tunnel. It is possible to provide a suitable method by which an enlarged tunnel can be built by providing the part in a part.
[0039]
In such an enlarged tunnel construction method, the invention according to
[0040]
On the other hand, according to the invention according to
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional front view showing a state in which a reinforcing wall is being constructed in one side of an existing tunnel;
FIG. 2 is a longitudinal sectional front view showing a state in which a widening tunnel is excavated along one side of an existing tunnel;
FIG. 3 is an enlarged vertical sectional front view of a part of an existing tunnel showing a support structure of a lining wall portion;
FIG. 4 is a longitudinal sectional front view showing a state in which a protective wall and the like are constructed in the widening tunnel,
FIG. 5 is a longitudinal sectional front view showing a state in which an existing tunnel is enlarged to form an enlarged tunnel;
FIG. 6 is a longitudinal front view of the enlarged tunnel,
FIG. 7 is a partially enlarged longitudinal sectional front view showing another form of the support structure of the lining wall.
[Explanation of symbols]
T Expanding tunnel T1 Existing tunnel t Lining body T2 Widening tunnel part A Reinforcement wall part B Excavation top end of widening tunnel part
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003079584A JP4144702B2 (en) | 2003-03-24 | 2003-03-24 | How to build an enlarged tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003079584A JP4144702B2 (en) | 2003-03-24 | 2003-03-24 | How to build an enlarged tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004285711A true JP2004285711A (en) | 2004-10-14 |
JP4144702B2 JP4144702B2 (en) | 2008-09-03 |
Family
ID=33293657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003079584A Expired - Fee Related JP4144702B2 (en) | 2003-03-24 | 2003-03-24 | How to build an enlarged tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4144702B2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102852533A (en) * | 2012-10-18 | 2013-01-02 | 山东大学 | High-strength three-dimensional support system of yielding type restriction concrete lagging jack |
CN103953351A (en) * | 2014-05-20 | 2014-07-30 | 长安大学 | Existing tunnel down-digging extension construction method without traffic interruption |
JP2016118040A (en) * | 2014-12-19 | 2016-06-30 | 大成建設株式会社 | Tunnel support structure and steel supporting |
CN107956491A (en) * | 2017-10-11 | 2018-04-24 | 中国矿业大学(北京) | One kind is based on the soft rock roadway support method of " steel grating-concrete filled steel tube " |
CN110374608A (en) * | 2019-08-28 | 2019-10-25 | 贵州大学 | The excavation method in vault direction when a kind of existing tunnel is extended |
JP2020084474A (en) * | 2018-11-20 | 2020-06-04 | 株式会社建技調査 | Widening construction method of existing tunnel |
CN112253143A (en) * | 2020-11-27 | 2021-01-22 | 中交路桥建设有限公司 | Structure for rapidly entering hole by adjusting position of tunnel and construction method |
CN114086992A (en) * | 2021-11-18 | 2022-02-25 | 中铁二院重庆勘察设计研究院有限责任公司 | Large-span tunnel expanding excavation construction method under complex geological conditions |
CN117449864A (en) * | 2023-12-22 | 2024-01-26 | 洛阳高飞桥隧机械股份有限公司 | Tunnel widening driving protection construction device and tunnel widening construction method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306680B (en) * | 2013-03-23 | 2015-09-30 | 中铁二院工程集团有限责任公司 | Existing single-track tunnel enlarging is the construction method of multiple track tunnel |
-
2003
- 2003-03-24 JP JP2003079584A patent/JP4144702B2/en not_active Expired - Fee Related
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102852533A (en) * | 2012-10-18 | 2013-01-02 | 山东大学 | High-strength three-dimensional support system of yielding type restriction concrete lagging jack |
CN103953351A (en) * | 2014-05-20 | 2014-07-30 | 长安大学 | Existing tunnel down-digging extension construction method without traffic interruption |
JP2016118040A (en) * | 2014-12-19 | 2016-06-30 | 大成建設株式会社 | Tunnel support structure and steel supporting |
CN107956491B (en) * | 2017-10-11 | 2020-05-12 | 中国矿业大学(北京) | Soft rock roadway supporting method based on steel grating-steel pipe concrete |
CN107956491A (en) * | 2017-10-11 | 2018-04-24 | 中国矿业大学(北京) | One kind is based on the soft rock roadway support method of " steel grating-concrete filled steel tube " |
JP2020084474A (en) * | 2018-11-20 | 2020-06-04 | 株式会社建技調査 | Widening construction method of existing tunnel |
CN110374608A (en) * | 2019-08-28 | 2019-10-25 | 贵州大学 | The excavation method in vault direction when a kind of existing tunnel is extended |
CN110374608B (en) * | 2019-08-28 | 2021-08-31 | 贵州大学 | Method for excavating vault direction during existing tunnel extension |
CN112253143A (en) * | 2020-11-27 | 2021-01-22 | 中交路桥建设有限公司 | Structure for rapidly entering hole by adjusting position of tunnel and construction method |
CN114086992A (en) * | 2021-11-18 | 2022-02-25 | 中铁二院重庆勘察设计研究院有限责任公司 | Large-span tunnel expanding excavation construction method under complex geological conditions |
CN114086992B (en) * | 2021-11-18 | 2024-05-03 | 中铁二院重庆勘察设计研究院有限责任公司 | Large-span tunnel expanding and excavating construction method under complex geological conditions |
CN117449864A (en) * | 2023-12-22 | 2024-01-26 | 洛阳高飞桥隧机械股份有限公司 | Tunnel widening driving protection construction device and tunnel widening construction method |
CN117449864B (en) * | 2023-12-22 | 2024-03-05 | 洛阳高飞桥隧机械股份有限公司 | Tunnel widening driving protection construction device and tunnel widening construction method |
Also Published As
Publication number | Publication date |
---|---|
JP4144702B2 (en) | 2008-09-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101274974B1 (en) | Earth retaining wall and construction method thereof | |
KR101363878B1 (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
KR20130105147A (en) | The construction method of steel-concrete underpass | |
KR20160131410A (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
JP2004285711A (en) | Construction method for enlarged tunnel | |
JP5843413B1 (en) | Lowering method of existing tunnel | |
KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
KR20110096339A (en) | Construction method of undergroud structure using phc pile | |
JP3893056B2 (en) | Construction method of underground structure | |
JP4022687B2 (en) | Construction method for underground structures | |
JP4083334B2 (en) | Underground structure having arch roof and method for constructing the same | |
JP2004169474A (en) | Connecting structure for tunnel cutting and enlarging section | |
JP2000179299A (en) | Large-section tunnel construction method | |
KR100882127B1 (en) | Construction method for installation escalator of subway outside entrance | |
JP2003193494A (en) | Underground hollow structure constructing method and the underground hollow structure | |
JP3930954B2 (en) | Construction method of structure | |
JP4303512B2 (en) | Construction method of large section tunnel | |
KR100753140B1 (en) | Steel pipe roof assembly and the construction method for tunnel using thereof | |
JP3796524B2 (en) | Tunnel widening method and tunnel | |
JP2554507B2 (en) | Underground space construction method | |
JP2813807B2 (en) | How to build an underground tunnel | |
JP4037004B2 (en) | Construction method of underground structure | |
JP2003301454A (en) | Earth retaining wall and construction method for underground structure | |
JP4612356B2 (en) | How to create a slope | |
KR20040034292A (en) | Tunnel structure carried out by double construction method using corrugated steel plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050802 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070629 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080513 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080611 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110627 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110627 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140627 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |