JP2004285600A - Connection method of side ditch - Google Patents

Connection method of side ditch Download PDF

Info

Publication number
JP2004285600A
JP2004285600A JP2003076352A JP2003076352A JP2004285600A JP 2004285600 A JP2004285600 A JP 2004285600A JP 2003076352 A JP2003076352 A JP 2003076352A JP 2003076352 A JP2003076352 A JP 2003076352A JP 2004285600 A JP2004285600 A JP 2004285600A
Authority
JP
Japan
Prior art keywords
joint
gutter
bag body
bag
fluid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003076352A
Other languages
Japanese (ja)
Other versions
JP4174358B2 (en
Inventor
Hiroaki Ouchi
弘朗 大内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OUCHI KENSETSU KK
Original Assignee
OUCHI KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OUCHI KENSETSU KK filed Critical OUCHI KENSETSU KK
Priority to JP2003076352A priority Critical patent/JP4174358B2/en
Publication of JP2004285600A publication Critical patent/JP2004285600A/en
Application granted granted Critical
Publication of JP4174358B2 publication Critical patent/JP4174358B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a connection method of a side ditch capable of accurately carrying out work for making a joint in a gap between side ditches at a curved place. <P>SOLUTION: The side ditch 1 providing a slit 1a having a narrow width on the upper part is installed by butting the end face 1b, and the gap S formed between the tow end faces 1b of the side ditch 1 is filled with a joint filler 4 having fluidity to execute the joint. A bag body 6 expanded by pressure of fluid 9 is made to forcibly enter the inside from the slit 1a of the side ditch 1, and the joint filler 4 is filled in a state to close the inside of the gap S with the expanded bag body 6. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】本発明は、上部に細幅のスリットが設けられた側溝の間の隙間に目地を施工する接続工法に係る技術分野に属する。
【0002】
【従来の技術】一般に、現場築造ではなく工場製造の側溝については、端面を突合わせて設置される側溝の間に形成される隙間に施工現場で目地を施工する必要がある。具体的施工としては、モルタル等の流動性を有する目地材料を隙間に充填する工法が採られる。
【0003】
最近、安全対策、製造コストの削減等の要請から、図7,図8に示すように、上部を大きく開放せずに長さ方向に細幅のスリット1aが設けられた側溝1が提供されてきている。スリット1aには、必要に応じて、通水孔付きの金属製,合成樹脂製等の蓋が設置される。
【0004】
このタイプの側溝1では、図8に示すような目地の施工が行われている。即ち、図8(A)に示すように、施工面に敷石2,捨コンクリート3を打設した後に、突合わせられる端面1bの下部に目地材料4を介在させて側溝1を設置する。続いて、図8(B)に示すように、設置された側溝1の端面1bの間に形成された隙間S(下部を除く)に側溝の1の外側から目地材料4を充填する。
【0005】
このとき、側溝1の上部がスリット1aを除いて閉塞されているため、施工作業者が側溝1の内部に手指を差込んだり、側溝1の内部を目視確認することができないため、施工作業者の経験技術に頼って目地を施工せざるを得ない。従って、図8(B)に示すように、側溝1の端面1bに沿った正確な目地を施工することが困難で、目地のシール性が不充分であったり、目地が側溝1の端面1bを超えて内部にまで突出して側溝1の通水性が阻害されてしまうという施工不良を引起こしている現況にある。この施工不良は、長さが通常2m程度に設計された直状の側溝1が屈曲配置されて隙間Sが扇形に拡開されることになるカーブ箇所で特に顕著になる。
【0006】
このため、上部に細幅のスリットが設けられた側溝1の間の隙間Sに目地を正確に施工する技術の開発が要請されている。
【0007】
従来、目地の施工に係る技術としては、例えば、以下に記載のものが知られている。
【特許文献1】特開平7−127119号公報。
特許文献1には、側溝の端面に係止溝を設けておき、側溝の端面の突合わせの際に帯状の水膨張性止水材を介在させる側溝の接続工法が記載されている。
【0008】
特許文献1に係る側溝の接続工法は、側溝の突合わせの後の水掛けや側溝の設置後の試験通水で水膨張性止水材を膨張させ、膨張した水膨張性止水材で側溝の隙間を充填して目地を完成させる。
【0009】
【発明が解決しようとする課題】特許文献1に係る側溝の接続工法では、図7に示すように隙間が扇形に拡開されている場合、膨張する水膨張性止水材が拡開側に拡がりやすくなるため、側溝の間の隙間に目地を正確に施工することができなくなるという問題点がある。
【0010】
本発明は、このような問題点を考慮してなされたもので、カーブ箇所で側溝の間の隙間に目地を正確に施工することができる側溝の接続工法を提供することを課題とする。
【0011】
【課題を解決するための手段】前述の課題を解決するため、本発明に係る側溝の接続工法は、次のような手段を採用する。
【0012】
即ち、請求項1では、上部に細幅のスリットが設けられた側溝が端面を突合わせて設置され、側溝の端面の間に形成された隙間に流動性を有する目地材料を充填して目地を目地を施工する側溝の接続工法において、側溝のスリットから内部に流体の圧力で膨張する袋体を侵入させ、膨張させた袋体で前記隙間の内側を閉鎖した状態で目地材料を充填することを特徴とする。
【0013】
この手段では、膨張した袋体が隙間の内側を閉塞するため、側溝の外側から充填された目地材料の端面を超えた内側への突出が阻止される。
【0014】
また、請求項2では、請求項1の側溝の接続工法において、袋体は流体が供給,排出されるホースが接続されることを特徴とする。
【0015】
この手段では、接続されたホースによる流体の供給,排出で袋体が膨張,収縮される。
【0016】
また、請求項3では、請求項1または2の側溝の接続工法において、袋体は目地の施工の後に収縮されて側溝のスリットから引出されることを特徴とする。
【0017】
この手段では、袋体が使用後に側溝から回収されて再使用される。
【0018】
また、請求項4では、請求項1または2の側溝の接続工法において、袋体は水溶性の材料で形成され目地の施工の後に側溝の内部に残置されることを特徴とする。
【0019】
この手段では、袋体が使用後に側溝に残置されて使捨てされる。
【0020】
【発明の実施の形態】以下、本発明に係る側溝の接続工法の実施の形態を図1〜図6に基づいて説明する。
【0021】
図1〜図3は、本発明に係る側溝の接続工法の実施の形態(1)を示すものである。
【0022】
この実施の形態は、前述の図8に示した工法を基本として構成されている。
【0023】
即ち、図1(A)に示すように、施工面に敷石2,捨コンクリート3を打設した後に、突合わせられる端面1bの下部に目地材料4を介在させて、上部の長さ方向に細幅のスリット1aが設けられた側溝1を設置する。
【0024】
続いて、図1(B)に示すように、側溝1のスリット1a(隙間S近くの)から内部にホース5が接続された袋体6を侵入させる。ホース5には、図2(A)に示すように、バルブ7,流体供給源8が接続されている。バルブ7は、三方切換バルブからなる。流体供給源8は、空気ポンプ,水ポンプ,工事車両のエンジン(排気ガス)等の流体9を供給するものが選択される。ホース5は、袋体6の側溝1のスリット1aからの侵入や後述の各操作を容易にするとともに、袋体6に対する流体9の供給,回収を確実にする。袋体6は、気体(空気,排気ガス),液体(水)等の流体9の圧力で膨張するゴム材等からなる。
【0025】
続いて、図2(B)に示すように、流体供給源8からホース5,バルブ7を介して袋体6に流体9が供給される。この結果、図1(C)に示すように、袋体6が膨張して側溝1の内部の壁面に張付くことになる。従って、膨張した袋体6は、隙間Sの内側を閉塞する。
【0026】
続いて、図1(D)に示すように、設置された側溝1の端面1bの間に形成された隙間S(下部を除く)に側溝の1の外側から目地材料4を充填する。このとき、膨張した袋体6が隙間Sの内側を閉塞しているため、かなり強引に充填を実施して空隙等の未充填部分の形成を避けるようにしても、目地材料4が端面1bを超えて側溝1の内部にまで突出することはない。従って、側溝1の間の隙間Sに目地を正確に施工することができる。この作用,効果については、隙間Sが扇形に拡開されることになるカーブ箇所に側溝1が設置された場合でも同様である。なお、目地材料4の充填の際には、流体供給源8からの流体9の供給を停止して、バルブ7を切換えて流体9の排出を阻止しておけば、袋体6の膨張を維持することができる。
【0027】
この後、袋体6の膨張を維持して目地材料4を養生する。
【0028】
そして、図2(C)に示すように、袋体6からホース5,バルブ7を介して流体9を排出(自然排出)する。この結果、図1(E)に示すように、袋体6が収縮することになる。収縮した袋体6は、図3に示すように、ホース5によって側溝1のスリット1aから引出される。この袋体6は、施工コスト低減のため他の隙間Sで再使用される。
【0029】
図4は、本発明に係る側溝の接続工法の実施の形態(2)を示すものである。
【0030】
この実施の形態では、前述の実施の形態(1)のバルブ7に加負圧調整機能を備え、袋体6から流体9の排出の際にバルブ7に流体供給源8から流体9を供給するように構成している。
【0031】
この実施の形態によると、袋体6から排出される流体9が流体供給源8から供給される流体9で加圧されて加速されるため、急速に袋体6を収縮させることができる。また、袋体6が長時間の膨張で収縮機能を低下させた場合に、袋体6を強制的に収縮させるのに有効である。
【0032】
図5は、本発明に係る側溝の接続工法の実施の形態(3)を示すものである。
【0033】
この実施の形態では、前述の実施の形態(1),(2)の袋体6を水溶性(目地材料4の水分では溶解しない)の材料で形成し、目地の施工の後に側溝1の内部に残置されるように構成している。
【0034】
この実施の形態によると、膨張したままの袋体6を側溝1のスリット1aでホース5から引きちぎって離脱させることで、袋体6の回収作業を省略することができる。なお、側溝1の内部に残置された袋体6は、試験通水の際等に溶解される消失する。
【0035】
図6は、本発明に係る側溝の接続工法の実施の形態(4)を示すものである。
【0036】
この実施の形態では、袋体6の内部に流体9を発生させるカプセル10を内蔵させている。そして、カプセル10には、操作紐11が接続されている。なお、袋体6には、側溝1のスリット1aからの引下げ,引上げのための吊紐12が接続されている。
【0037】
カプセル10としては、気体からなる流体9を圧縮収納したボンベ類や、異なる薬品類を混合させて気体を発生させるもの等が選択される。操作紐11は、ボンベ類のコックや薬品類の混合遮断壁の破壊等を操作することになる。
【0038】
この実施の形態によると、流体9の供給,回収のため大掛かりの設備が不要になる。
【0039】
【発明の効果】以上のように、本発明に係る側溝の接続工法は、膨張した袋体が隙間の内側を閉塞し、側溝の外側から充填された目地材料の端面を超えた内側への突出が阻止されるため、カーブ箇所で側溝の間の隙間に目地を正確に施工することができる効果がある。
【0040】
さらに、請求項2として、接続されたホースによる流体の供給,排出で袋体が膨張,収縮されるため、袋体の操作が容易になるとともに、袋体に対する流体の供給,回収が確実になる効果がある。
【0041】
さらに、請求項3として、袋体が使用後に側溝から回収されて再使用されるため、施工コストが低減される効果がある。
【0042】
さらに、請求項4として、袋体が使用後に側溝に残置されて使捨てされるため、袋体の回収のための手間が不要になる効果がある。
【図面の簡単な説明】
【図1】本発明に係る側溝の接続工法の実施の形態(1)の工程の断面図であり、(A)〜(E)の順に工程順が示されている。
【図2】図1に接続される装置構成の回路図であり、(A)に基本構成が示され(B),(C)に異なる動作への切換えが示されている。
【図3】図1(E)に続く工程の断面図である。
【図4】本発明に係る側溝の接続工法の実施の形態(2)の実施のための装置構成の回路図である。
【図5】本発明に係る側溝の接続工法の実施の形態(3)を示す最終の工程の断面図である。
【図6】本発明に係る側溝の接続工法の実施の形態(4)を示す要部の正面図である。
【図7】一般的な工場製造タイプの側溝のカーブ箇所での設置例を示す平面図である。
【図8】図7の一般的な目地の施工の断面図であり、(A),(B)の順に施工順が示されている。
【符号の説明】
1 側溝
1a スリット
1b 端面
4 目地材料
6 袋体
9 流体
S スリット
[0001]
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention belongs to a technical field related to a connection method for joining joints in gaps between side grooves provided with narrow slits on an upper portion.
[0002]
2. Description of the Related Art Generally, in the case of a gutter manufactured at a factory instead of a site, it is necessary to construct a joint at a construction site in a gap formed between the gutters which are installed with their end faces abutting each other. As a concrete construction, a construction method of filling a gap with a joint material having fluidity such as mortar is employed.
[0003]
Recently, due to demands for safety measures, reduction of manufacturing cost, and the like, as shown in FIGS. 7 and 8, a side groove 1 provided with a narrow slit 1a in a length direction without greatly opening an upper portion has been provided. ing. The slit 1a is provided with a lid made of metal, synthetic resin, or the like having a water passage hole as necessary.
[0004]
In this type of gutter 1, joints are constructed as shown in FIG. That is, as shown in FIG. 8 (A), after the cobblestones 2 and the concrete 3 are cast on the construction surface, the gutter 1 is installed with the joint material 4 interposed below the butted end face 1b. Subsequently, as shown in FIG. 8B, a joint material 4 is filled into the gap S (excluding the lower portion) formed between the end surfaces 1 b of the installed side grooves 1 from outside the side grooves 1.
[0005]
At this time, since the upper part of the gutter 1 is closed except for the slit 1a, the construction worker cannot insert his / her fingers into the gutter 1 or visually check the inside of the gutter 1; We have to rely on our experience to build joints. Therefore, as shown in FIG. 8 (B), it is difficult to construct an accurate joint along the end face 1b of the gutter 1 and the sealing property of the joint is inadequate, or the joint has an end face 1b of the gutter 1. It is in the present situation which is causing the poor construction that it protrudes to the inside beyond that and impedes the water permeability of the gutter 1. This poor construction is particularly remarkable in a curved portion where the straight side groove 1 designed to have a length of about 2 m is bent and arranged so that the gap S expands in a fan shape.
[0006]
For this reason, there is a demand for the development of a technique for accurately joining joints in the gap S between the side grooves 1 provided with a narrow slit at the top.
[0007]
2. Description of the Related Art Conventionally, for example, the following technology is known as a technology related to joint construction.
[Patent Document 1] JP-A-7-127119.
Patent Literature 1 describes a method of connecting side grooves in which a locking groove is provided on an end face of a side groove and a band-shaped water-swellable water-stopping material is interposed when the end faces of the side grooves are abutted.
[0008]
The gutter connection method according to Patent Literature 1 is to expand the water-swellable water-stopping material by watering after abutment of the gutters or by test water passing after the installation of the gutters, and the gutter is expanded by the expanded water-swellable water-stopper Fill the gap to complete the joint.
[0009]
In the gutter connection method according to Patent Literature 1, when the gap is expanded in a fan shape as shown in FIG. There is a problem that the joints cannot be accurately constructed in the gaps between the side grooves because they are easily spread.
[0010]
The present invention has been made in view of such a problem, and an object of the present invention is to provide a gutter connection method capable of accurately applying joints to gaps between gutters at a curved portion.
[0011]
Means for Solving the Problems In order to solve the above-mentioned problems, a method for connecting a side groove according to the present invention employs the following means.
[0012]
That is, in claim 1, a side groove provided with a narrow slit at an upper portion is installed with the end faces abutting each other, and a gap formed between the end faces of the side grooves is filled with a flowable joint material to fill the joint. In the connection method of the gutter for constructing the joint, injecting the bag body that expands by the pressure of the fluid into the inside from the slit of the gutter, filling the joint material with the expanded bag body closing the inside of the gap. Features.
[0013]
In this means, since the inflated bag closes the inside of the gap, the filled joint material is prevented from protruding inward beyond the end face from outside the side groove.
[0014]
According to a second aspect of the present invention, in the method of connecting the side grooves according to the first aspect, the bag is connected to a hose through which fluid is supplied and discharged.
[0015]
In this means, the bag body is expanded and contracted by the supply and discharge of the fluid by the connected hose.
[0016]
According to a third aspect of the present invention, in the method of connecting a gutter according to the first or second aspect, the bag body is contracted after the joint is constructed and pulled out from the slit of the gutter.
[0017]
In this means, the bag is recovered from the gutter after use and reused.
[0018]
According to a fourth aspect of the present invention, in the method of connecting a gutter according to the first or second aspect, the bag body is formed of a water-soluble material, and is left inside the gutter after construction of the joint.
[0019]
With this means, the bag is left in the gutter after use and is thrown away.
[0020]
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing an embodiment of a gutter connecting method according to the present invention; FIG.
[0021]
1 to 3 show an embodiment (1) of a gutter connection method according to the present invention.
[0022]
This embodiment is configured based on the method shown in FIG.
[0023]
That is, as shown in FIG. 1 (A), after setting a paving stone 2 and a rubble concrete 3 on a construction surface, a joint material 4 is interposed at a lower portion of an abutted end surface 1b to narrow the upper portion in a longitudinal direction. A side groove 1 provided with a slit 1a having a width is installed.
[0024]
Subsequently, as shown in FIG. 1 (B), the bag 6 to which the hose 5 is connected enters the inside through the slit 1a (near the gap S) of the side groove 1. As shown in FIG. 2A, a valve 7 and a fluid supply source 8 are connected to the hose 5. The valve 7 comprises a three-way switching valve. The fluid supply source 8 is selected to supply a fluid 9 such as an air pump, a water pump, and an engine (exhaust gas) of a construction vehicle. The hose 5 facilitates intrusion of the side groove 1 of the bag body 6 from the slit 1a and operations described later, and also ensures supply and recovery of the fluid 9 to and from the bag body 6. The bag 6 is made of a rubber material or the like that expands under the pressure of a fluid 9 such as gas (air, exhaust gas) and liquid (water).
[0025]
Subsequently, as shown in FIG. 2B, the fluid 9 is supplied from the fluid supply source 8 to the bag body 6 via the hose 5 and the valve 7. As a result, as shown in FIG. 1C, the bag body 6 expands and sticks to the inner wall surface of the side groove 1. Therefore, the inflated bag 6 closes the inside of the gap S.
[0026]
Subsequently, as shown in FIG. 1 (D), a joint material 4 is filled into the gap S (excluding the lower part) formed between the end surfaces 1 b of the installed side grooves 1 from outside the side grooves 1. At this time, since the inflated bag body 6 closes the inside of the gap S, the joint material 4 covers the end face 1b even if the filling is performed very forcibly to avoid the formation of an unfilled portion such as a void. It does not protrude to the inside of the side groove 1 beyond. Therefore, the joint can be accurately constructed in the gap S between the side grooves 1. This operation and effect are the same even when the side groove 1 is installed at a curved portion where the gap S is expanded in a fan shape. In addition, when filling the joint material 4, if the supply of the fluid 9 from the fluid supply source 8 is stopped and the valve 7 is switched to prevent the discharge of the fluid 9, the expansion of the bag body 6 is maintained. can do.
[0027]
Thereafter, the joint material 4 is cured while maintaining the expansion of the bag 6.
[0028]
Then, as shown in FIG. 2C, the fluid 9 is discharged from the bag body 6 via the hose 5 and the valve 7 (natural discharge). As a result, the bag 6 contracts as shown in FIG. The contracted bag body 6 is pulled out of the slit 1a of the side groove 1 by the hose 5, as shown in FIG. This bag 6 is reused in another gap S to reduce the construction cost.
[0029]
FIG. 4 shows an embodiment (2) of a gutter connection method according to the present invention.
[0030]
In this embodiment, the valve 7 of the above-described embodiment (1) is provided with a function of adjusting the applied pressure and the negative pressure, and supplies the fluid 9 from the fluid supply source 8 to the valve 7 when the fluid 9 is discharged from the bag body 6. It is configured as follows.
[0031]
According to this embodiment, since the fluid 9 discharged from the bag 6 is pressurized and accelerated by the fluid 9 supplied from the fluid supply source 8, the bag 6 can be rapidly contracted. Further, it is effective for forcibly contracting the bag body 6 when the bag body 6 has reduced the contraction function due to long-term inflation.
[0032]
FIG. 5 shows an embodiment (3) of a gutter connection method according to the present invention.
[0033]
In this embodiment, the bag 6 of the above-described embodiments (1) and (2) is formed of a water-soluble (not dissolved by the moisture of the joint material 4) material, and after the joint is applied, the inside of the gutter 1 is formed. Is configured to be left behind.
[0034]
According to this embodiment, the bag 6 as it is inflated is torn off from the hose 5 by the slit 1a of the side groove 1, and the work of collecting the bag 6 can be omitted. Note that the bag body 6 left inside the side groove 1 is dissolved and disappears when the test water is passed.
[0035]
FIG. 6 shows an embodiment (4) of the gutter connection method according to the present invention.
[0036]
In this embodiment, a capsule 10 for generating a fluid 9 is built in the bag 6. An operation string 11 is connected to the capsule 10. The bag 6 is connected to a hanging string 12 for pulling down and raising the side groove 1 from the slit 1a.
[0037]
As the capsule 10, a cylinder that compresses and stores a fluid 9 made of gas, a capsule that mixes different chemicals to generate a gas, and the like are selected. The operation cord 11 is used to operate a cock of a cylinder or a destruction of a mixing / blocking wall of chemicals.
[0038]
According to this embodiment, a large-scale facility for supplying and recovering the fluid 9 becomes unnecessary.
[0039]
As described above, in the gutter connection method according to the present invention, the expanded bag closes the inside of the gap and projects from the outside of the gutter to the inside beyond the end face of the filled joint material. Is prevented, so that there is an effect that the joint can be accurately constructed in the gap between the side grooves at the curved portion.
[0040]
Furthermore, the bag is expanded and contracted by the supply and discharge of the fluid by the connected hose, so that the operation of the bag is facilitated and the supply and recovery of the fluid to and from the bag are ensured. effective.
[0041]
Furthermore, since the bag is recovered from the side gutter after use and reused, the construction cost is advantageously reduced.
[0042]
Furthermore, since the bag is left in the side groove after use and is thrown away, there is an effect that the labor for collecting the bag is not required.
[Brief description of the drawings]
FIG. 1 is a sectional view of a step of an embodiment (1) of a gutter connection method according to the present invention, in which the order of steps is shown in the order of (A) to (E).
FIG. 2 is a circuit diagram of a device configuration connected to FIG. 1, wherein (A) shows a basic configuration, and (B) and (C) show switching to a different operation.
FIG. 3 is a sectional view of a step following FIG. 1 (E).
FIG. 4 is a circuit diagram of an apparatus configuration for carrying out an embodiment (2) of a gutter connection method according to the present invention.
FIG. 5 is a sectional view of a final step showing an embodiment (3) of a gutter connection method according to the present invention.
FIG. 6 is a front view of a main part showing an embodiment (4) of a gutter connection method according to the present invention.
FIG. 7 is a plan view showing an example of installation at a curved portion of a gutter of a general factory manufacturing type.
8 is a cross-sectional view of the construction of the general joint of FIG. 7, in which the construction order is shown in the order of (A) and (B).
[Explanation of symbols]
Reference Signs List 1 side groove 1a slit 1b end face 4 joint material 6 bag body 9 fluid S slit

Claims (4)

上部に細幅のスリットが設けられた側溝が端面を突合わせて設置され、側溝の端面の間に形成された隙間に流動性を有する目地材料を充填して目地を施工する側溝の接続工法において、側溝のスリットから内部に流体の圧力で膨張する袋体を侵入させ、膨張させた袋体で前記隙間の内側を閉鎖した状態で目地材料を充填することを特徴とする側溝の接続工法。Gutters provided with narrow slits at the top are installed with their end faces abutting each other, and in a gutter connection method of filling joints having fluidity into gaps formed between the end faces of the gutters and constructing the joints. A joint method for connecting the side grooves, wherein a bag body which is inflated by the pressure of the fluid is made to enter into the inside from the slit of the side groove, and the joint material is filled with the inflated bag body closing the inside of the gap. 請求項1の側溝の接続工法において、袋体は流体が供給,排出されるホースが接続されることを特徴とする側溝の接続工法。2. The side groove connecting method according to claim 1, wherein the bag is connected to a hose through which fluid is supplied and discharged. 請求項1または2の側溝の接続工法において、袋体は目地の施工の後に収縮されて側溝のスリットから引出されることを特徴とする側溝の接続工法。3. The method of connecting gutters according to claim 1, wherein the bag body is contracted after the joint is applied and pulled out from the slit of the gutter. 請求項1または2の側溝の接続工法において、袋体は水溶性の材料で形成され目地の施工の後に側溝の内部に残置されることを特徴とする側溝の接続工法。3. The gutter connection method according to claim 1, wherein the bag body is formed of a water-soluble material, and is left inside the gutter after construction of the joint.
JP2003076352A 2003-03-19 2003-03-19 Side groove connection method Expired - Fee Related JP4174358B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003076352A JP4174358B2 (en) 2003-03-19 2003-03-19 Side groove connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003076352A JP4174358B2 (en) 2003-03-19 2003-03-19 Side groove connection method

Publications (2)

Publication Number Publication Date
JP2004285600A true JP2004285600A (en) 2004-10-14
JP4174358B2 JP4174358B2 (en) 2008-10-29

Family

ID=33291434

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003076352A Expired - Fee Related JP4174358B2 (en) 2003-03-19 2003-03-19 Side groove connection method

Country Status (1)

Country Link
JP (1) JP4174358B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017082530A (en) * 2015-10-30 2017-05-18 ケイコン株式会社 Coupling installation method for precast circular water channel
JP2021055431A (en) * 2019-09-30 2021-04-08 三ツ星ベルト株式会社 Method of laying waterproof sheet

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017082530A (en) * 2015-10-30 2017-05-18 ケイコン株式会社 Coupling installation method for precast circular water channel
JP2021055431A (en) * 2019-09-30 2021-04-08 三ツ星ベルト株式会社 Method of laying waterproof sheet
JP7186155B2 (en) 2019-09-30 2022-12-08 三ツ星ベルト株式会社 Waterproof sheet laying method

Also Published As

Publication number Publication date
JP4174358B2 (en) 2008-10-29

Similar Documents

Publication Publication Date Title
KR101657058B1 (en) Double inflatable grouting equipment and the grouting method using the same
KR100668130B1 (en) Feeding device of agent for reinforcing foundation
JP2006322285A (en) Construction method and device for closing borehole
JP2004285600A (en) Connection method of side ditch
KR102011365B1 (en) Packer module for soil nail and method for pressed grouting and constructing concrete panel using the same
JP4219747B2 (en) Civil engineering bag
JP2002146717A (en) Settlement repair method for concrete paving slab
JP4070592B2 (en) Method of injecting water-stopping material for steel pipe joints
JPH11513086A (en) Novel sewage wall, method of forming the sewage wall, and members used therefor
CA2944351C (en) Apparatus and method for plugging a pipe
JP4330929B2 (en) Water stop device and water stop method
JP4916395B2 (en) Drainage pipe set and drainage method
JP3177908B2 (en) Starting method of shield excavator
JP5295038B2 (en) Water draining method
JP6837364B2 (en) How to repair the culvert drainage pipe confluence drainage mass
KR102430894B1 (en) Pressure curtain with multi-wing for filling tube in underground disused pipe and underground disused pipe filling method using the same
JPH0514835B2 (en)
JPH01215512A (en) Back-filling technique of heating, pressurizing and expanding rigid tube lining
JP2004257055A (en) Driving method for steel sheet pile
JP2006057405A (en) Water cutoff method
JP2000273859A (en) Chemical grouting method
JP2009102837A (en) Inter-structure sealing bag
JP2005146550A (en) Filling device, covering member, and method for driving pile material by using them
JPH1113985A (en) Buried pipe repairing method
KR100645010B1 (en) Manhole for watertight coupling and method for coupling pipe by using them

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060315

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071228

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080717

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080818

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110822

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110822

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110822

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120822

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120822

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140822

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees