JP2004263561A - Cast-in-place pile and its work execution method - Google Patents
Cast-in-place pile and its work execution method Download PDFInfo
- Publication number
- JP2004263561A JP2004263561A JP2004193519A JP2004193519A JP2004263561A JP 2004263561 A JP2004263561 A JP 2004263561A JP 2004193519 A JP2004193519 A JP 2004193519A JP 2004193519 A JP2004193519 A JP 2004193519A JP 2004263561 A JP2004263561 A JP 2004263561A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- excavation
- cast
- excavator
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
Description
本発明は、大口径場所打ち杭の支持力を経済的かつ確実に増大させると共に効率的な施工を可能にする場所打ち杭及びその施工法に関する。 The present invention relates to a cast-in-place pile capable of efficiently and economically increasing the supporting capacity of a large-diameter cast-in-place pile and an execution method thereof.
大口径場所打ち杭の形状には、ストレート杭、拡底杭、拡頭杭、テーパ杭、中空杭、突起杭など、これまで多様な形状のものが提案されている。また施工法においても、ベノト工法、リバース工法、アースドリル工法、深礎工法などが施工条件に応じて選択的に使用されている。しかしながら、これまで提案されてきた杭形状は、選択要件が明確でないことや、施工法に課題があることから、ストレート杭が多く用いられてきた。ストレート杭は、施工が比較的容易ではあるが、杭に作用する荷重と杭の断面形状からすると必ずしも合理的とはいえない。また場所打ちストレート杭は、負の摩擦力が発生するような軟弱地盤では実用的な対策がなく、支持力を低減することにより対応していたのが実情である。さらに、場所打ち杭は、施工法から見ても、地盤に孔を空けた後、その中にコンクリートを充填するので、一般的に地盤を緩めやすく、施工の巧拙による地盤のゆるみやスライムの堆積によって、その品質が大きく左右されるのが実情であるため、確実で効率的な施工法の確立が望まれている。 Various types of large diameter cast-in-place piles have been proposed, including straight piles, bottom piles, head piles, tapered piles, hollow piles, and projecting piles. Also, in the construction method, the Benoto method, the reverse method, the earth drill method, the deep foundation method, and the like are selectively used depending on the construction conditions. However, for the pile shapes proposed so far, straight piles have often been used because the selection requirements are not clear and there is a problem in the construction method. Straight piles are relatively easy to construct, but are not always rational in view of the load acting on the piles and the cross-sectional shape of the piles. In addition, cast-in-place straight piles have no practical countermeasures on soft ground where negative frictional force is generated, and they have actually responded by reducing the supporting force. In addition, cast-in-place piles are generally easy to loosen because the hole is drilled in the ground and then filled with concrete. In practice, the quality is greatly influenced by the quality of the product, and it is desired to establish a reliable and efficient construction method.
このようなストレート杭の課題を受けて、特に建築の分野では拡底場所打ち杭が数多く採用されている。拡底場所打ち杭は、ストレート杭と比較すると、負の摩擦力の影響を受けにくい杭ではあるが、スライムの処理や掘削形状検査などのために、ストレート杭以上に余分の時間を要するものである。 In response to such problems of straight piles, many cast-in-place cast-in-place piles have been adopted particularly in the field of construction. Expanded bottom cast-in-place piles are less susceptible to negative friction forces than straight piles, but require extra time to process slime and inspect excavated shapes. .
なお、本願の発明者は、場所打ち杭、拡底杭、テーパ杭及びこれらに関連する技術分野の調査を実施し、本発明の背景技術として該当する下記の特許文献を見つけた。
大口径場所打ち杭には、解決を要する下記の施工上の課題がある。
すなわち、従来の場所打ち杭のスライム処理は確実性に欠けるため、支持力など品質の確保に課題があるとともに、スライム処理のために多くの時間を要していた。また、場所打ち拡底杭にあっては、拡底部分外周のスライム処理が十分に行い難いという特有の課題があった。場所打ち拡底杭では掘削形状検査が行われており、この検査に多くの時間を必要とすることから、その間にスライムの堆積が進んでしまう。コンクリート打設前に行う2次スライムの処理においても、支持力に大きな影響を与える拡底部のスライム処理が、特に鉄筋籠外周部分において殆ど出来ないという課題がある。
Large diameter cast-in-place piles have the following construction issues that need to be resolved.
That is, conventional slime treatment of cast-in-place piles lacks certainty, so there is a problem in securing quality such as supporting force, and much time is required for slime treatment. Further, in the case of the cast-in-place expanded pile, there is a specific problem that it is difficult to sufficiently perform slime treatment on the outer periphery of the expanded portion. Excavation shape inspection is performed on cast-in-place expanded piles, and this inspection requires a lot of time, and slime accumulation proceeds during that time. Even in the treatment of secondary slime performed before placing concrete, there is a problem that slime treatment of the expanded bottom portion, which greatly affects the supporting force, can hardly be performed, particularly in the outer peripheral portion of the reinforced cage.
また場所打ち杭の施工においては、スタンドパイプ、ケーシングパイプまたは外殻鋼管等が使用されているが、これらの設置や撤去のためには、パワージャツキまたはバイブロハンマー、クレーンなど、その作業専用の機械が必要であった。 Also, in the construction of cast-in-place piles, stand pipes, casing pipes, outer shell steel pipes, etc. are used, but for the installation and removal of these, machines dedicated to the work, such as power jacks, vibro hammers, cranes, etc., are used. Was needed.
さらに、地盤の掘削時にテーパ部や拡底部を効率的かつ確実に施工管理するシステムや効率的な掘削形状検査を行うシステムがなかった。 Furthermore, there has been no system for efficiently and surely managing the construction of the tapered portion or the bottom portion when excavating the ground, and no system for performing an efficient excavation shape inspection.
本発明は上記課題を解決し、鉛直荷重、水平荷重、負の摩擦力に対して有利な場所打ち杭を提案するとともに、確実な品質と経済性を有する場所打ち杭の施工法を提案するものである。 The present invention solves the above problems, proposes a cast-in-place pile that is advantageous against vertical loads, horizontal loads, and negative frictional forces, and proposes a method of constructing a cast-in-place pile having reliable quality and economy. It is.
本発明では上記課題を解決するために以下の手段を採用した。
すなわち、請求項1に記載の場所打ち杭の施工法は、拡底杭の軸部の少なくとも一部に下向きに細るテーパ部を有した場所打ち杭の施工法において、拡縮可能なリバース掘削機の掘削ビットの開閉状況から掘削形状が監視画面上で所定値になるように制御可能なシステムを用いて杭軸部から先端の拡底部まで掘削した後、リバース掘削機のドリルパイプを介して掘削ビット先端から拡底部の一部または全部にセメントミルク、モルタルまたはセメント混合物(以下、本明細書中において、単に「セメントミルク等」ということがある)を注入し、リバース掘削機の掘削ビットを地上に引上げた後に、掘削孔内への鉄筋籠の建込み、トレミー管を用いたコンクリートの打設を行って杭体を造成することを特徴とする。
The present invention employs the following means in order to solve the above problems.
In other words, the method for constructing a cast-in-place pile according to claim 1 is a method for constructing a cast-in-place pile having a tapered portion tapering downward in at least a part of the shaft portion of the expanded bottom pile. After drilling from the pile shaft to the bottom of the tip using a system that can control the drilling shape to a predetermined value on the monitoring screen based on the opening and closing status of the bit, the drill bit tip through the drill pipe of the reverse drilling machine Inject cement milk, mortar or cement mixture (hereinafter sometimes simply referred to as “cement milk” etc.) into a part or the whole of the expanded bottom from above and pull up the drill bit of the reverse excavator to the ground. After that, a pile body is constructed by laying a steel cage in the excavation hole and pouring concrete using a tremy tube.
請求項2に記載の場所打ち杭の施工法は、拡底杭の軸部の少なくとも一部に下向きに細るテーパ部を有した場所打ち杭の施工法において、拡縮可能なリバース掘削機の掘削ビットの開閉状況から掘削形状が監視画面上で所定値になるように制御可能なシステムを用いて杭の軸部を掘削した後、拡底部の掘削時には、拡底径の一部を所定の径より細い径で一旦、略最終深度まで一次掘削を行った後、リバース掘削機のドリルパイプを介して掘削ビット先端から拡底部にセメントミルク等を注入し、次に掘削ビットを操作しながら拡底部が所定の形状になるように二次掘削を行うと共に、前記セメントミルク等と掘削土とを攪拌混合した後に、リバース掘削機の掘削ビットを地上に引上げ、掘削孔内への鉄筋籠の建込み、トレミー管を用いたコンクリートの打設を行って杭体を造成することを特徴とする。
The method for constructing a cast-in-place pile according to
請求項3に記載の場所打ち杭の施工法は、拡底杭の軸部の少なくとも一部に下向きに細るテーパ部を有した場所打ち杭の施工法において、拡大可能なアースドリル掘削機の掘削バケットの拡大状況から監視画面上で掘削形状が所定値になるように制御可能なシステムを用いて軸部から最終深度の拡底部までの掘削と孔底のスライム処理を行った後、アースドリル掘削機のケリバーパイプを介して掘削バケット先端から拡底部の一部または全部にセメントミルク等を注入し、前記掘削機の掘削バケットを地上に引上げ、その後、掘削孔内への鉄筋籠の建込み、トレミー管を用いたコンクリートの打設を行って杭体を造成することを特徴とする。
The method for constructing a cast-in-place pile according to
請求項4に記載の場所打ち杭の施工法は、拡底杭の軸部の少なくとも一部に下向きに細るテーパ部を有した場所打ち杭の施工法において、アースドリル掘削機の拡大可能な拡大バケットの開閉状況から監視画面上で掘削形状が所定値になるように制御可能なシステムを用いて軸部の掘削を行った後、拡底部の掘削段階では、拡底径の一部を所定の径より細い径で一旦、略最終深度まで一次掘削を行った後、アースドリル掘削機のケリーバーを介して拡大バケット先端から拡底部にセメントミルク等を注入し、次に掘削ビットを操作しながら拡底部が所定の形状になるように二次掘削を行うと共に、前記セメントミルク等と掘削土とを攪拌混合し、その後、アースドリル掘削機の拡大ビットを地上に引上げ、掘削孔内への鉄筋籠の建込み、トレミー管を用いたコンクリートの打設を行って杭体を造成することを特徴とする。 The method for constructing a cast-in-place pile according to claim 4 is a method for constructing a cast-in-place pile having a tapered portion tapering downward in at least a part of a shaft portion of the expanded bottom pile, wherein an expandable expandable bucket of an earth drill excavator is used. After excavating the shaft using a system that can control the excavation shape to a predetermined value on the monitoring screen from the opening and closing situation, in the excavation stage of the expanded bottom part, a part of the expanded bottom diameter is smaller than the predetermined diameter Once the primary excavation is performed to a nearly final depth with a small diameter, cement milk or the like is injected from the tip of the enlarged bucket through the kelly bar of the earth drill excavator, and then the expanded part is operated while operating the drill bit. While secondary drilling is performed so as to have a predetermined shape, the cement milk or the like and the excavated soil are stirred and mixed, and thereafter, the enlarged bit of the earth drill excavator is pulled up to the ground, and the rebar cage is built in the drill hole. Including, training It characterized in that it construct a pile body performs pouring of concrete using chromatography tube.
請求項1〜4に記載の場所打ち杭の施工法により、上記課題の解決が可能になった。
すなわち、本発明の施工法では、杭の拡底部まで掘削した後に、掘削ビットや掘削バケットを引上げることなくセメントミルク等を注入するので、杭先端にスライムが挟在することがなく、また拡底地盤を緩めることも少ないので、本来の地盤強度に応じた杭の支持力が確保できる。特に、従来困難であった、鉄筋籠外周のスライム処理を確実に行うことができるので、拡底杭にふさわしい支持力を確実に得ることができる。
また杭に下向きのテーパが付いているので、負の摩擦抵抗が発生するような地盤であっても、その下向きの摩擦抵抗を数分の1に低減でき、正の摩擦力に対しても最大数10%増しの摩擦抵抗が期待できる。テーパにより、杭径をほぼ発生する応力に応じた形状にすることができるので、杭のコンクリート量や土砂の掘削量及び残土(産業廃棄物)を低減できる。
セメントミルク等を注入するために、特別な装置を使用せず、掘削ビットを引抜くこと無しに、ケリバーパイプまたはドリルパイプを介して連続的に注入することができるため、セメントミルク等を注入するための所要時間を最小限に抑えることができる。
リバース掘削機による削孔では、杭底部まで掘削した後に通常20分から30分程度、安定液中の土粒子の沈降を待って、最終的な孔底のスライム処理を行うが、本発明ではこのような時間を省くことができる。
孔底のスライム処理を行った後、掘削ビットの引上げ、鉄筋の建込み、トレミー管の建込みまでに孔底に沈降したスライムは、比重の違いからの表面に堆積するが、これは、通常、行われているトレミ−管を利用したスライム処理で除去できる。
また、仮に多少のスライムが残ったり、その後のコンクリートの打設中に溜まったスライムは、コンクリートの打設表面に堆積した状態で地上まで押上げられる。特に、テーパ杭では、削孔上方に行くにしたがって、径が大きくなるために、スライムはスムーズに上昇し、孔壁面とコンクリートとの間に付着することが少ないので支持力の低下を抑止できる。
本発明の施工法では、以上のような作用や効果により、品質と経済性に優れた場所打ち杭の施工が短時間に行える。
According to the construction method of the cast-in-place pile according to claims 1 to 4, the above-mentioned problem can be solved.
That is, in the construction method of the present invention, after excavating to the bottom of the pile, cement milk or the like is injected without raising the drill bit or the drill bucket, so that no slime is interposed at the tip of the pile, and Since the ground is not loosened, the pile support capacity corresponding to the original ground strength can be secured. In particular, since the slime treatment on the outer periphery of the reinforcing bar cage, which has conventionally been difficult, can be reliably performed, it is possible to reliably obtain the supporting force suitable for the expanded pile.
In addition, since the pile has a downward taper, the downward frictional resistance can be reduced to a fraction of that in the ground where negative frictional resistance is generated, and the maximum for positive frictional force. A friction resistance of several tens% can be expected. The taper allows the pile diameter to be substantially shaped according to the generated stress, so that the amount of concrete in the pile, the amount of excavated earth and sand, and the residual soil (industrial waste) can be reduced.
To inject cement milk, etc., because it can be continuously injected through a Keribar pipe or drill pipe without using special equipment and without pulling out a drill bit to inject cement milk, etc. Required time can be minimized.
In the drilling by the reverse excavator, the final slime treatment of the hole bottom is performed after excavation to the bottom of the pile, usually for about 20 to 30 minutes, waiting for the settling of the soil particles in the stabilizing liquid. Time can be saved.
After performing slime treatment on the bottom of the hole, the slime that settled at the bottom of the hole before raising the drill bit, setting up the reinforcing steel, and setting up the tremy pipe accumulates on the surface due to the difference in specific gravity. Can be removed by a slime treatment using a tore tube.
Also, if some slime remains or slime accumulated during the subsequent casting of concrete, the slime is pushed up to the ground while being deposited on the surface of the concrete. In particular, in the tapered pile, the diameter increases as it goes above the drilled hole, so that the slime rises smoothly and adheres little between the hole wall surface and the concrete, so that a decrease in the supporting force can be suppressed.
According to the construction method of the present invention, a cast-in-place pile excellent in quality and economy can be constructed in a short time by the above-described actions and effects.
次に、請求項5に記載の場所打ち杭の施工法は、拡縮可能なリバース掘削機の掘削ビットに、掘削形状計測用の音波送受信機を取付けて、掘削ビットの開閉角度から計測した掘削形状と音波送受信機から計測した掘削形状を同時に検出可能に構成した掘削形状計測システムを用いて、施工した場所打ち杭の形状を、掘削ビット引上げ時に計測することを特徴とする。
本発明の場所打ち杭の施工法では、掘削ビット部分に掘削形状検査測定器を取付け、掘削ビットを地上に引き上げる時に形状検査を実施するので、従来のように掘削ビット引き上げ後、改めて掘削孔内に形状検査測定器を設置し、地上から測定する必要がない。また、重量のある掘削ビットに送受信装置が取付けられているので、掘削後の安定液の動揺の影響を殆ど受けないために計測時間を大幅に短縮できると共に、計測時の揺れや捩れの影響も殆ど受けず、正確な形状検査が可能になる。また、これによる形状測定値と掘削ビットの開閉角度から求めた形状測定値をモニター画面上で比較できるので一層信頼性の高い計測値が得られる。
Next, in the method for constructing a cast-in-place pile according to
In the method of constructing a cast-in-place pile according to the present invention, a drilling shape inspection measuring instrument is attached to the drilling bit portion, and the shape inspection is performed when the drilling bit is lifted to the ground. There is no need to install a shape inspection and measurement device on the ground to measure from the ground. In addition, since the transmitter / receiver is attached to the heavy excavation bit, the measurement time can be greatly reduced because it is hardly affected by the fluctuation of the stable liquid after the excavation. It is hardly received and an accurate shape inspection can be performed. Further, since the measured shape value and the measured shape value obtained from the opening / closing angle of the drill bit can be compared on the monitor screen, a more reliable measured value can be obtained.
請求項6に記載の場所打ち杭の施工法は、スタンドパイプ、ケーシングパイプまたは外殻鋼管の外面の少なくとも一部に螺旋状の治具を取付け、これらパイプまたは鋼管をリバース掘削機またはアースドリル掘削機の駆動軸の回転力を用いて貫入させることを特徴とする。
この場所打ち杭の施工法では、従来の場所打ち杭の施工においては、スタンドパイプ、ケーシングパイプまたは外殻鋼管の設置や撤去のために、パワージャツキまたはバイブロハンマー、クレーンなど、その作業専用の機械が必要であったが、本発明の場所打ち杭の施工法では、掘削機に使用するベースマシンを利用して、スタンドパイプなどの設置、撤去を行うので、工程的にも経済的にも大きな効果が得られる。
The method of constructing a cast-in-place pile according to
In this method of casting cast-in-place piles, in the conventional construction of cast-in-place piles, machines dedicated to the work, such as power jacks, vibratory hammers, and cranes, are used to install and remove stand pipes, casing pipes, or outer steel pipes. Although it was necessary, in the method for constructing a cast-in-place pile according to the present invention, a base machine used for an excavator is used to install and remove a standpipe, etc. Is obtained.
請求項7に記載の場所打ち杭の施工法は、アースドリル掘削機またはリバース掘削機を用いて施工する拡底場所打ち杭の施工法において、掘削後のスライム処理に引続き、掘削機の中空駆動軸を通じてその最先端から孔底にセメントミルク等を注入し、その後、セメントミルク等の上に堆積したスライムを鉄筋籠建込み後、コンクリート打設用のトレミー管を介してポンプやエアーリフトにより地上に回収することを特徴とする。
この場所打ち杭の施工法では、掘削直後の孔底にセメントミルク等を注入することにより、スライムが杭先地盤上に堆積するのを防止するとともに、コンクリート打設直前に行うスライム処理を効果的に行うことができるので杭支持力の確保、不同沈下の防止など杭の品質を高めることができる。
The method of constructing a cast-in-place pile according to claim 7 is a method of constructing a cast-in-place cast-in-place pile using an earth drill excavator or a reverse excavator, following the slime treatment after excavation, the hollow drive shaft of the excavator. Inject cement milk etc. into the hole bottom from the very tip through the top, then build reinforced slime on the cement milk etc., and then use a pump or air lift on the ground via a tremy pipe for concrete placement. It is characterized by being collected.
In this casting method of cast-in-place pile, by injecting cement milk etc. into the bottom of the hole immediately after excavation, slime is prevented from accumulating on the ground at the tip of the pile, and the slime treatment performed immediately before placing concrete is effective. Therefore, the pile quality can be improved, such as securing pile support capacity and preventing uneven settlement.
請求項7の場所打ち杭の施工法では、トレミー管の代りにコンクリートポンプ車のホースを用いて直接、拡底部にセメントミルク等を打設しても良い。 In the construction method of the cast-in-place pile according to claim 7, cement milk or the like may be directly poured into the expanded bottom using a hose of a concrete pump truck instead of the tremy tube.
請求項9に記載の場所打ち杭の施工法は、ケーシング兼用の外殻鋼管の少なくとも一部に螺旋状の治具を取付けたことを特徴とする。この場所打ち杭の施工法では、外殻鋼管が下向きに細るテーパ鋼管であっても良い。 The construction method of the cast-in-place pile according to the ninth aspect is characterized in that a spiral jig is attached to at least a part of the outer shell steel pipe also serving as the casing. In this casting method of cast-in-place piles, the outer shell steel pipe may be a tapered steel pipe that tapers downward.
本発明では、鉛直荷重、水平荷重、負の摩擦力に対して有利な場所打ち杭を提供し、確実な品質と経済性を有する場所打ち杭の施工法を提供することができる。 According to the present invention, it is possible to provide a cast-in-place pile which is advantageous against a vertical load, a horizontal load, and a negative frictional force, and to provide a cast-in-place pile having a certain quality and economy.
以下、図面を参照して本発明について説明するが、本発明はこれに限定されるものではない。本発明の場所打ち杭の施工法は、原則としてリバース工法またはアースドリル工法を用いて行うものであるが、例えば、ベノト工法の最終掘削段階で拡大ビット付きの掘削バケットを用いて拡底杭を施工する場合にも適用可能である。 Hereinafter, the present invention will be described with reference to the drawings, but the present invention is not limited thereto. The method of constructing the cast-in-place pile of the present invention is, in principle, performed using the reverse method or the earth drill method.For example, in the final excavation stage of the Venoto method, the expanded pile is constructed using a drill bucket with an enlarged bit. It is also applicable to the case.
<杭の形状について>
図1は、本発明を適用するテーパ拡底杭の代表的な形状を例示したものである。
図1(a)(b)(c)のテーパ拡底杭は、いずれも杭頭部にストレート部を有し、その下部にテーパ部を有している。杭頭をストレート部としたのは、杭の断面力が大きくなる部分であり、これに対抗するために断面剛性を確保することと、施工時にスタンドパイプを用いるため、この部分は必然的にストレートになる要因もある。将来、テーパ鋼管が商品化された場合には、杭頭からテーパ状に形成された杭の施工も普及する可能性がある。
<About the shape of the pile>
FIG. 1 illustrates a typical shape of a tapered expanded pile to which the present invention is applied.
1 (a), 1 (b) and 1 (c) each have a straight portion at the pile head and a tapered portion at the lower portion. The pile head is a straight part where the section force of the pile increases. To counter this, the section rigidity is secured, and a stand pipe is used during construction. There is also a factor. In the future, if tapered steel pipes are commercialized, the construction of piles formed in a tapered shape from the pile heads may become popular.
図1(a)はテーパ部の下部にストレート部があり、その下部に拡底部がつながっている。このようにテーパ部の下部にストレート部を設けるのは、テーパ部の最大長に限界があり、杭長が長くなると下部にもストレート部を設ける必要があるためである。テーパ部の実用的な勾配は1〜2%と考えられ、この勾配を基にしたテーパ部の最大長は、杭径にもよるが20〜30mが目安となる。テーパ部の勾配が急なほど正の摩擦抵抗を大きく、負の摩擦抵抗を小さくすることが可能であるが、その分、テーパ部の長さは短くなる。
軟弱層の圧密沈下により、杭に負の摩擦抵抗が作用する区間は、なるべくテーパ部とすることが望ましい。しかし、その区間が長くなる場合には、ある程度杭頭ストレート部の径を大きくすることが必要である。図1(c)は、耐震場所打ち杭として設計された杭の形状を示しており、上部には外殻鋼管が設けられており、スタンドパイプを兼ねている。外殻鋼管には螺旋翼、すなわちスパイラルガイドを付けることも可能であり、掘削機駆動軸のトルクで捻込めるような地盤条件であれば、その効果は大きい。
In FIG. 1A, a straight portion is provided below the tapered portion, and an enlarged bottom portion is connected to the lower portion. The reason why the straight portion is provided below the tapered portion is that there is a limit to the maximum length of the tapered portion, and it is necessary to provide the straight portion also at the lower portion when the pile length is long. The practical gradient of the tapered portion is considered to be 1 to 2%, and the maximum length of the tapered portion based on this gradient is approximately 20 to 30 m depending on the pile diameter. The steeper the slope of the tapered portion, the larger the positive frictional resistance and the smaller the negative frictional resistance, but the length of the tapered portion is reduced accordingly.
It is desirable that the section where the negative frictional resistance acts on the pile due to the consolidation settlement of the soft layer be tapered as much as possible. However, when the section becomes long, it is necessary to increase the diameter of the pile head straight portion to some extent. FIG. 1C shows the shape of a pile designed as an earthquake-resistant cast-in-place pile, in which an outer shell steel pipe is provided at the top and also serves as a standpipe. Spiral wings, that is, spiral guides, can be attached to the outer shell steel pipe, and the effect is great if the ground conditions allow the screw to be screwed in with the torque of the driving shaft of the excavator.
このようなテーパ拡底杭には、次のような長所がある。
杭頭部と杭先端部の径を大きくすることにより、水平支持力や鉛直支持力の確保を効果的に行うことができる。杭に発生する断面力に対して経済的な設計ができるので、材工数量を減じることができる。テーパ部を設けたことにより、その部分が正の摩擦抵抗であればより大きく、負の摩擦力であればより小さくなるので、地盤が複雑な場合でも適用性が高く、ストレート杭に比して周辺摩擦抵抗を大きく見積もることができる。拡底杭とすることにより、周面摩擦力よりも信頼性の高い先端支持力の比率を高めることができるとともに、負の摩擦抵抗の影響を軽減できる。テーパ拡底杭の施工上の問題点は通常用いられるストレート杭と殆ど変らない。
Such a tapered expanded pile has the following advantages.
By increasing the diameter of the pile head and the pile tip, it is possible to effectively secure the horizontal support force and the vertical support force. Since economical design can be performed for the section force generated in the pile, the number of materials can be reduced. By providing the tapered part, it is larger if the part is positive frictional resistance and smaller if it is negative frictional force, so it is more applicable even when the ground is complicated, compared to straight piles The peripheral frictional resistance can be largely estimated. By using the expanded bottom pile, the ratio of the tip support force, which is more reliable than the peripheral friction force, can be increased, and the influence of negative friction resistance can be reduced. The problems in the construction of the tapered expanded pile are almost the same as those of the straight pile normally used.
<テーパ杭に作用する摩擦抵抗について>
図2は、杭の周面に発生する摩擦抵抗と、杭と地盤との相対変位量との関係を模式的に示したものである。この図のように杭周に発生する摩擦抵抗は、少なくともその最大値までは相対変位量に応じて大きくなることが知られている。また、同じ相対変位量における正の摩擦抵抗は、負の摩擦抵抗よりも大きくなるとされている。これは地盤条件などにもよるが、ひずみゲージを取付けた同一杭で、鉛直載荷試験と引抜き載荷試験を実施すれば立証することができる。また、テルツアギーの「土質力学」にもこのことは開示されている。図に示すようにテーパ杭は、ストレート杭に比較して正の摩擦領域では摩擦抵抗が大きく、負の摩擦抵抗領域においては摩擦抵抗が小さくなる。この現象や杭の断面力を勘案して杭形状の設計を行うことにより、経済的で信頼性の高い設計を行うことが可能である。更に特定の土層が将来、正の摩擦抵抗区間となるか負の摩擦抵抗区間となるか不明確な場合は、テーパ区間とすることにより、合理的な杭形状とすることができる。
<About frictional resistance acting on tapered pile>
FIG. 2 schematically shows the relationship between the frictional resistance generated on the peripheral surface of the pile and the relative displacement between the pile and the ground. It is known that the frictional resistance generated around the pile as shown in this figure increases with the relative displacement at least up to the maximum value. Further, it is said that the positive frictional resistance at the same relative displacement is larger than the negative frictional resistance. This can be proved by performing a vertical load test and a pull-out load test on the same pile with a strain gauge attached, depending on the ground conditions and the like. This is also disclosed in Tertuagi's "Soil Mechanics". As shown in the figure, the tapered pile has a higher friction resistance in the positive friction region and a smaller friction resistance in the negative friction region as compared with the straight pile. By designing the shape of the pile in consideration of this phenomenon and the sectional force of the pile, it is possible to perform an economical and highly reliable design. Further, when it is unclear whether a specific soil layer will be a positive friction resistance section or a negative friction resistance section in the future, a tapered section can be used to obtain a reasonable pile shape.
次に、本発明の実施例を図面に基づいて詳細に説明する。先にリバース掘削機を用いて本発明を実施する方法について説明する Next, embodiments of the present invention will be described in detail with reference to the drawings. First, a method of implementing the present invention using a reverse excavator will be described.
<1.掘削装置>
最初に、杭の掘削装置構成と機能について説明する。図3は削孔状況を示す図である。図3において、ドリルパイプ10は地上から掘削孔1の内部に延長しており、ドリルパイプ10の下端10aには掘削ユニット20が接続され、地上に突出した上端10bには駆動装置30が接続されている。なお、掘削孔1は、上端にスタンドパイプ2が設けられ、その下方にテーパ状に軸部3が形成され、さらに下方に拡底部4が掘削されるものであり、掘削孔1の内部には安定液5が満たされて孔壁3aの崩壊を防止している。
<1. Drilling equipment>
First, the configuration and function of a pile excavator will be described. FIG. 3 is a diagram showing a drilling situation. In FIG. 3, the
ここで、前記ドリルパイプ10は複数の中空管が接続されたものである。
Here, the
前記掘削ユニット20では、図4に示したように、中空駆動軸21の上端に継手フランジ21a、下端に開口21bを有し、この開口21bの周りにフィッシュテール22aが固定されている。この開口21bは、掘削孔内の泥水の吸込口として用いられると共に、セメントミルク等の排出口としても用いられるものである。また中空駆動軸21の下端には軸部ビット22bが固定され、軸部ビット22bに拡孔ビット22cが枢着され、拡孔ビット22cはリンク部材23により下部クロスヘッド24aに枢着されている。この下部クロスヘッド24aは、中空駆動軸21に沿って上下動可能なように、中空駆動軸21の下端付近に環装されたものである。この下部クロスヘッド24aは油圧ジャッキ24bにより上部クロスヘッド24cに連結されており、この上部クロスヘッド24cは中空駆動軸21に固定されている。したがって、油圧ジャッキ24bを伸張すれば、拡孔ビット22cは図4で実線で描いたように開いて拡大し、逆に油圧ジャッキ24bを収縮すれば、拡孔ビット22cは点線で描いたように閉じて縮小する。また掘削ユニット20を地盤に押付ける力は、掘削ユニット20を吊っているクレーンの吊上げ力を調整し、掘削ユニット20の自重のうち最適量を地山に加えられることにより得られる。
As shown in FIG. 4, the excavating
また前記掘削ユニット20には、上記構成の他に、拡孔ビット開閉量検出器25、超音波形状検出器26、スタビライザ27が設けられ、このスタビライザ27の内部に油圧ユニット28a及び計測装置28bが収納されており、この計測装置28bからはケーブル29が地上まで延びている。なお、計測装置28bからのデータは、ケーブル29に替えて無線で地上まで送るようにしても良い。
拡孔ビット開閉量検出器25は、下部クロスヘッド22の位置を検知することにより、拡孔ビット24の開閉量を検出するものである。超音波形状検出器26は、ここから孔壁に向かって超音波を発信し、その反射波を検出することにより、掘削孔の形状を検出するものであり、発信受信機能も併せ持つものである。スタビライザ27は、削孔径に適合した円形をしており、ドリルパイプ10とともに掘削孔内で回転し、削孔軸がずれないようにガイドするものである。この実施例では軸部の最小削孔径に合わせて、スタビライザー27の径を設定しているが、油圧シリンダ(図示せず)を用いて可変とすることもできる。
The excavating
The hole opening bit opening /
図3に示す前記駆動装置30は、ドリルパイプ10の上端10bに接続されて駆動力を与えるためのケリーバパイプ31と、回転を遮断するためのロータリジョイント32と、ケリーバパイプ31に駆動力を伝達するロータリーテーブル33とから構成されている。
そして、ロータリジョイント32にはスイベル34が連結され、スイベル34にはデリバリーホース35が接続され、このデリバリーホース35がサクションポンプ(図示せず)まで延長している。軸部ビット22b及び拡孔ビット22cによって切削された切削土は、中空駆動軸21の最先端の開口21b(吸込み口)を通じて、ドリルパイプ10内をサクションポンプで安定液と共に吸い上げられて地上に排出される。地上の沈殿槽(図示せず)で土砂と安定液に分離され、安定液は再び孔内に戻される。
このように孔内の安定液は、孔内と地上とを循環しながら切削土砂を地上に搬出する。この安定液の循環によって孔壁には、遮水膜としてのマッドケーキが生成される。この遮水膜やスタンドパイプ2に加えて、地下水位より2m高く保持された孔内水位が、孔壁に20kPaの静水圧を作用させることにより、掘削時の孔壁の保持が達成される。
またスイベル34には、セメントミルク等の注入管36aが開閉バルブ36bと共に設けられており、これにより、安定液の吸込みを停止した状態で、セメントミルク等を注入管36aから送込み、ドリルパイプ10を通して掘削ユニット20の開口21b(排出口)から注入する。
The driving device 30 shown in FIG. 3 is connected to the
A
As described above, the stable liquid in the hole carries out the cutting earth and sand to the ground while circulating between the hole and the ground. By the circulation of the stabilizing solution, mud cake as a water barrier film is generated on the hole wall. In addition to the water blocking film and the
Further, the
以上の構成の掘削ユニット20により杭のストレート部を掘削するときは、所定の削孔径になるように拡孔ビット22cの開閉角度をスタビライザ27内に収納された油圧ポンプ28aを地上から表示部の画面を見ながら操作し、開閉角度を一定に保持しながら所定の深さまで掘削を行う。テーパ−部3や拡底部4を掘削する場合も同様で、表示部の画面上で設計形状を見ながら同一形状に掘削するように油圧ポンプ28aの地上操作により拡孔ビット22cの開閉角度を調整していく。この操作は、電気的な回路を構成することにより自動的に行うこともできる。掘削ユニット20を引上げるときには、拡孔ビット22cを最大限畳んだ状態にして引上げる。拡孔ビット22cを開閉するための動力源となる油圧ポンプ28aは、本実施例では、スタビライザー27内に収納する構成をとったが、これは地上に設置した場合に生じる油圧ホースの処理・養生作業をなくし、トラブルを極力避けるためである。油圧ポンプ28a用の電源および制御ケーブルは、ドリルパイプ10に沿わせて地上まで配線し、ロータリージョイント32と一体化したスリップリング(図示しない)を介して地上に設置された電源や制御器に接続される。
When the straight portion of the pile is excavated by the excavating
図5(a)(b)は、リバース掘削機に用いる別の掘削ユニット40を例示したものである。この掘削ユニット40では、アウターシャフト41の管内にインナーシャフト42が摺動可能に挿設されている。このインナーシャフト42の上端にはフランジ継手42aが設けられ、その下方には駆動モータ42bとウォームギア42cが設けられ、このインナーシャフト42の上端付近に形成されたクロスヘッド42dには連結ロッド43が枢着され、連結ロッド43の下端に拡孔ビット44が枢着されている。拡孔ビット44は、アウターシャフト41の軸方向に突設されたスライドガイド45に沿って下端の軸部ビット46まで摺動可能に形成されている。アウターシャフト41の上端にはスタビライザ47が設けられ、下端には開口41aが設けられている。この開口41aは掘削孔内の泥水の吸込口及びセメントミルク等の排出口として用いられるものであり、開口41a周りにはフィッシュテール48が突設されている。またアウターシャフト41の下端付近には超音波形状検出器49が設置されている。
上記構成の掘削ユニット40では、インナーシャフト42から連結ロッド43で懸垂された拡孔ビット44が駆動モータ42bとウオームギヤ42cによって、傾斜を有したスライドガイド45を滑動することにより、拡孔ビット44が拡大したり縮小する。図5(a)は、掘削ユニット40の径が最も小さな状態を表し、図5(b)は最も大きな状態を示したものである。掘削ユニット40の拡孔ビット44の操作は、上記例の同じく地上の管理装置によってCRT画面を見ながら行えるようになっている。
FIGS. 5A and 5B illustrate another excavating
In the excavating
<2.計測管理装置>
次に、杭を所定の形状に掘削するための計測器の構成について説明する。
図6は計測システムのフロー図である。各検出器からの信号はA/D変換器を介してコンピュータに送られて処理され、その結果を設計値と比較して逐一表示するように構成されている。掘削深度用変位計は、図3に示されるように地上のケリバーパイプ31の突出長さを計測ワイヤーとエンレコーダ6によって計測するものである。ケーバーパイプ31の下部に接続されるドリルパイプ10bは、これを構成する各中空管が掘削の進行に応じて継ぎ足されるので、その度に中空管の本数が入力され、掘削深度用変位計の盛り替えを行う。コンピュータは、これらの情報を演算し、表示部に表示する。拡孔ビット開閉量変位計は、中空駆動軸21に固定されたスタビライザ27と中空駆動軸21を摺動する下部クロスヘッド24aとの伸縮量を測ることにより拡孔ビット22cの開閉角度を測るためのものである。また、図6のドリルパイプ傾斜計は、掘削ユニット20の中空駆動軸21の鉛直度を測るためのものであり、この鉛直度に関するデータは、掘削時の孔曲りや掘削ユニット20の引上げ時に行う孔壁形状計測のデータと合算し、掘削後の孔曲がりを検出するためのデータとして利用する。
掘削孔の形状を確認するため、図4に示すように掘削ユニット20の4方向に取付けられた超音波形状検出器26により、掘削ビット引上げ時に掘削孔の形状を記録する。この超音波形状検出器26の電気信号は、一旦、スタビライザー内の計測部に送られ、それからケーブルもしくは無線で地上に送り処理され、最終的には、ストローク計などと共にコンピュータを介して表示部で表示する。なお、図5の掘削ユニット40を用いた場合にもほぼ同様である。
このようにして収録された計測データは、すべてコンピュータの記録部に集録され、適宜、それらを演算、処理して表示部に表示させるようになっている。クレーン運転手や管理者は、この画面上の表示を見ながら、所定の形状の掘削孔が出来るように操作したり、他の作業員に情報を伝達する。
<2. Measurement management device>
Next, a configuration of a measuring instrument for excavating a pile into a predetermined shape will be described.
FIG. 6 is a flowchart of the measurement system. A signal from each detector is sent to a computer via an A / D converter and processed, and the result is compared with a design value and displayed one by one. The excavation depth displacement meter measures the protruding length of the above-
In order to confirm the shape of the drilling hole, the shape of the drilling hole is recorded when the drilling bit is pulled up by the
The measurement data thus recorded are all collected in a recording unit of a computer, and are calculated, processed, and displayed on a display unit as appropriate. The crane operator or the manager operates the drill hole having a predetermined shape while transmitting the information to other workers while watching the display on the screen.
<3.施工方法>
図7及び図8は、それぞれ本実施例における施工順序を示す図と施工概要を示す図である。これらの工程中、本発明において特徴的な工程は、(4)及び(6)工程である。その他の工程は、通常のリバース式拡底場所打ち杭の工程とほぼ同じである。本発明によるテーパ拡底杭の施工手順を図7及び図8により説明する。
ここでは、(1)工程のスタンドパイプ建込みから(3)工程のリバース掘削機据付まで、及び(9)工程のリバース機撤去から(14)工程のスタンドパイプ引抜きまでは、従来のリバース掘削機による場所打ち杭の施工法とほぼ同じであるため、図7及び図8に記載して説明は省略する。
<3. Construction method>
7 and 8 are a diagram showing a construction order and a diagram showing a construction outline in the present embodiment, respectively. Among these steps, the characteristic steps in the present invention are the steps (4) and (6). The other steps are almost the same as those of the ordinary reverse type cast-in-place pile. The construction procedure of the tapered expanded pile according to the present invention will be described with reference to FIGS.
Here, the conventional reverse excavator is used from the installation of the stand pipe in the process (1) to the installation of the reverse excavator in the process (3), and from the removal of the reverse machine in the process (9) to the removal of the stand pipe in the process (14). Since the method is almost the same as the method of constructing a cast-in-place pile according to the method described in FIGS.
(4)工程 軸部掘削
杭径の変化しないストレート部の掘削については、従来の工法と同じである。拡孔ビットの拡縮幅を一定にした状態で、ケリーバーパイプ31に回転力を与え掘削ユニット20を回転させ、地盤を切削していく。切削した土砂は、吸込み口から安定液と共に地上に排出される。掘削状況は、表示部の画面上で観察でき、掘削ユニット20に取付けた傾斜計による傾斜角が大きな場合には、ビットにかかる推力が大き過ぎることが考えられるので、クレーンの吊荷重を確認する。テーパ部の掘削では、拡孔ビットの開閉量を制御して所定の直径になるように表示部の画面を見ながら、油圧ポンプの電磁弁を操作する。こうしてドリルパイプ10を構成する中空管1本分(ほぼ3m)の掘削が終わったら、ケリーバーパイプ31とその下のドリルパイプ10bを切り離し、その間に新たな中空管を継ぎ足す。このとき、ドリルパイプ10に仮止めしていた電源ケーブルや計測用信号ケーブルも伸ばして再度仮止めする。また、掘削深度用変位計の盛り替えを行い所定の深度となるよう調整する。
(4) Process Shaft excavation Excavation of the straight section where the pile diameter does not change is the same as the conventional method. With the expansion width of the hole expansion bit kept constant, a rotational force is applied to the
(5)工程 拡底部掘削
杭の軸部の掘削が所定の深度に達したら引続き拡底部の掘削工程に入る。拡底部の掘削途中で、ドリルパイプ10に中空管の継ぎ足しが生じないようなパイプ長の選択を行っておく。テーパ部と同様に表示部の画面上の設計形状になるように油圧ポンプの電磁弁を操作しながら掘進する。最大拡底部下端が所定の深度に到達したら掘削完了である。しかし、孔底に溜まった切削ズリをほぼ完全に排出するために、掘削機は、更に10〜20分間程度回転させてスライム処理を行う。このとき拡孔ビットや軸部ビットが地盤に接触しない程度に近付けた状態に引上げておく。地上に排出される安定液にズリやスライムが混入していないことを確認した後、掘削機を完全に停止する。
(5) Process of excavation of bottom portion When the excavation of the shaft of the pile reaches a predetermined depth, the excavation process of the extension portion is continued. During the excavation of the expanded bottom portion, the pipe length is selected so that the hollow pipe does not rejoin the
(6)(7)工程 拡底部セメントミルク等の注入
前工程において掘削孔内のスライム処理を行っている時に、地上ではセメントミルク等の注入のために準備作業を行い、掘削機が停止した後、スイベル34から分岐させたセメントミルク等の注入管36aを通して速やかにセメントミルク等の注入を行う。注入量は少なくとも拡底部4の立上がり部4a以上を目安とする。このとき掘削ユニット20は原則として停止しておく。
セメントミルク等を拡底部4の全体に注入した場合は、後工程の鉄筋籠の設置が所定の深度まで行えることを十分検討しておかなければならない。このように事前に拡底部4の全体にセメントミルク等を充填しておく場合には、鉄筋籠外周のスライムの処理がより容易になるという特長がある。また、先端への注入量が多い場合やコンクリートを注入する場合には、スイベル31を取外し、直接、ドリルパイプ10をトレミー管代わりに使用して注入することもできる。
工程(7)に示すように拡底部4の側壁部を一部残し、セメントミルク等を注入後、2次掘時の掘削土砂とセメントミルクを攪拌混合し、拡底部4の杭体の一部としても良い。しかし、この場合は、拡底部4の土層が、砂質系地盤であることが前提と考えてよい。
(6) (7) Process Injection of cement milk etc. at the bottom of the bottom After the slime treatment in the excavation hole was performed in the previous process, preparation work was performed on the ground for injection of cement milk etc., and after the excavator stopped The cement milk or the like is quickly injected through the
When cement milk or the like is injected into the entire expanded bottom portion 4, it must be sufficiently considered that the reinforcing rod cage can be installed to a predetermined depth in a later process. When cement milk or the like is previously filled in the entire expanded bottom portion 4 in this way, there is a feature that the treatment of the slime on the outer periphery of the reinforcing bar cage becomes easier. In addition, when the injection amount to the tip is large or when concrete is poured, the
As shown in the step (7), a part of the side wall portion of the expanded bottom portion 4 is left, cement milk or the like is injected, and then the excavated earth and sand during the second excavation and the cement milk are stirred and mixed, and a part of the pile body of the expanded bottom portion 4 It is good. However, in this case, it may be considered that the soil layer of the expanded bottom 4 is sandy ground.
(8)工程 掘削ユニット引上げと掘削形状検査
掘削ユニット20の引上げは、拡孔ビットを最小に収縮させた状態で、かつ鉛直になるようにして引上げる。これは拡孔ビットを孔壁に接触させず、孔壁の損傷を防止することと、正確な杭形状測定を行うためである。そのため、ドリルパイプ10の引上げに際しては、台付けワイヤの掛け方に留意し、ゆっくり一定速度で引上げるようにする。
(8) Process Drilling Unit Pulling Up and Excavation Shape Inspection The
<鉄筋籠について>
テーパ部分の鉄筋籠7は、軸方向鉄筋をテーパ状に配置するか、例えばのストレート状の鉄筋籠を階段状に組み合わせたものとする。
<About reinforcing bars>
The reinforcing bar cage 7 in the tapered portion is formed by arranging axial reinforcing bars in a tapered shape or by combining, for example, straight reinforcing bar cages in a stepwise manner.
実施例2では、アースドリル掘削機を用いて本発明を実施する方法について説明する
なお、実施例1と同じ部分については省略する。
In a second embodiment, a method of implementing the present invention using an earth drill excavator will be described. Note that the same parts as those in the first embodiment will be omitted.
<1.掘削装置>
図9では従来装置である拡孔ビット付きアースドリル掘削機50を例示するものであるが、この図に示すケリーバパイプ51の上部のスイベル52やセメントミルク注入管53は、本発明特有の装備である。拡孔ビット付き掘削バケット54の構造は、例えば特開昭58−222287号公報の図20に示されたものがある。すなわち、掘削バケット54の側部の一部を油圧シリンダーで外側に押出しながら掘削バケット54を回転することにより、底部の掘削だけでなく同時に側部の拡孔掘削を行う機能を備えている。そのため、杭のテーパ部を掘削するためには、その深さに応じた拡孔ビットの開閉量を選択すれば良い。このことから本発明を実施するために新たに追加する機能は、ケリバーパイプ51の中空部を利用して、その掘削バケット54の先端からセメントミルクを排出できるような装置を追加するだけで良い。
なお、上記以外の構成としては、ケリーバパイプ51の下端に回転駆動部55が設けられ、さらに下方にロータリージョイント56、ケーブルホース用リール57、スタビライザ58が設けられている。
<1. Drilling equipment>
FIG. 9 illustrates an
As a configuration other than the above, a
<2.計測管理装置>
図9のような市販のアースドリル掘削機50には、運転席で掘削深度や拡孔ビットの拡孔量が管理できる計測管理装置を装備しているので、本発明においてもこの装置を利用した施工管理が可能である。
<2. Measurement management device>
Since a commercially available
<3.施工方法>
図10及び図11は、それぞれ本実施例における施工順序を示す流れ図と、施工の概要図を示したものである。これらの工程中、本発明で特徴的な工程は、(4)工程のテーパ部成形掘削と、(7)工程の拡底部スライム処理およびセメントミルク注入作業である。その他の工程は、通常のアースドリル掘削機による拡底場所打ち杭の施工法と略同じである。
本発明に基づくテーパ拡底杭の施工手順を図10及び図11を参照して説明する。なお、図10と図11の両図面における各工程の番号(1)〜(14)は、同じ工程に同じ番号を付している。以下、本発明において特徴的な工程である(4)工程であるテーパ部整形掘削、(7)工程である拡底部スライム処理及びセメントミルク注入作業を中心に説明する。
<3. Construction method>
FIG. 10 and FIG. 11 are a flowchart showing the construction order in the present embodiment and a schematic diagram of the construction, respectively. Among these steps, the characteristic steps of the present invention are the step (4) of forming and excavating the tapered portion, and the step (7) of expanding the bottom slime and injecting the cement milk. The other steps are almost the same as the construction method of the cast-in-place cast-in-place pile using an ordinary earth drill excavator.
The procedure for constructing the tapered expanded pile according to the present invention will be described with reference to FIGS. 10 and 11. The numbers (1) to (14) of the steps in both FIGS. 10 and 11 denote the same steps with the same numbers. Hereinafter, description will be made focusing on the (4) process of shaping and excavating the tapered portion, which is a characteristic process of the present invention, and the slime treatment and cement milk injection operation of the (7) process.
(4)工程 テーパ部整形掘削
テーパ部の掘削は、掘削バケット54の孔内搬入・搬出の度に、削孔位置の杭径に応じて拡孔ビットの開閉量を調整しながら掘削しても良いが、この方法は能率が悪く、テーパ部の形状の精度も悪くなる。テーパ形状部の精度が悪く、杭表面に凹凸ができると、その部分の摩擦抵抗が大きくなる。これは正の摩擦抵抗が得られる場合には、好ましいことかもしれないが、負の摩擦抵抗が発生する場合には好ましくない。
そのため、テーパ部の掘削は、図11(a)に示した(3)工程のように、ある区間をストレート部と同様に同じ径で掘削する。そして、例えば5m削孔した後に、その区間の掘削開始高さまで掘削バケット54を戻し、拡孔ビットを閉じるように開閉量を調整しながらテーパ状に連続して整形掘削を行うようにする。あまり長い区間連続して整形掘削を行うと、その区間の孔壁に付着したマッドフィルムが一時的に無くなり、孔壁崩壊に繋がる恐れがあるので、この点に留意して整形掘削の区間長さを設定しなければならない。一連の削孔状況は、運転席の表示部の画面上で観察できる。
(4)工程では図9のアースドリル掘削機50が使用されるが、このアースドリル掘削機50は、ケリーバーパイプ51が多段のテレスコピック方式になっているので、途中でケリーバーパイプ51を接続・切離しすることなく40m以上の掘削が可能である。
(4) Process Taper Shaped Excavation Excavation of the tapered portion can be performed by adjusting the opening / closing amount of the drilling bit according to the pile diameter at the drilling position every time the
Therefore, as for the excavation of the tapered portion, as in the step (3) shown in FIG. 11A, a certain section is excavated with the same diameter as the straight portion. Then, after drilling 5 m, for example, the
In the step (4), the
(5)工程 拡底部掘削
杭の軸部の掘削が所定の深度に達ししたら引続き拡底部4の掘削に入る。テーパ部3と同様に、表示部の画面上を見ながら、設計形状になるように油圧ポンプの電磁弁を操作しながら掘進する。最大拡底部下端が所定の深度に到達すれば掘削完了である。
(5) Process Excavation at the bottom When the excavation of the shaft of the pile reaches a predetermined depth, the excavation at the bottom 4 is started. Similarly to the tapered
(7)工程 拡底部セメントミルク注入
所定深度までの掘削が完了しても孔底には切削ズリやスライムが沈降し、この部分の安定液の比重が1.2を超えるような状態になることもある。このような高密度の泥水は、コンクリートの打設に悪影響を与えるので掘削バケット54で汲上げて排出するようにする。掘削後のスライム処理のために専用のバケットを使うこともある。いずれにしても最終段階で排出される泥水の状態を確認してスライム処理を終了する。なお、高濃度の泥水をバケットで排出するのは能率的でないため、ケリーバー51の中空部を利用してエアーリフトやサクションポンプ、水中ポンプなどで排出するのが望ましい。
前工程のスライム処理時に、地上ではセメントミルク注入の準備作業をしておき、スライム処理のための最終時に、掘削バケット54をほぼ孔底に接触させた状態で、ケリバーパイプ51のセメントミルク注入管53から速やかに孔底にセメントミルクの注入を行う。注入量は少なくとも拡底立上がり部以上(図13(a)参照)となるようにする。このとき掘削バケット54の回転は原則として停止しておき、セメントミルクの注入高さに応じて徐々に引上げる。
(7) Process Injection of cement milk at the bottom of the bottom Even if the excavation to the specified depth is completed, cutting waste and slime settle at the bottom of the hole, and the specific gravity of the stable liquid in this part may exceed 1.2. . Since such high-density muddy water has an adverse effect on the concrete placement, the muddy water is pumped up and discharged by the
At the time of slime treatment in the previous step, preparation work for cement milk injection is performed on the ground, and at the end of slime treatment, the cement
(8)工程 掘削形状検査
前述したように例示したアースドリル掘削機50には、掘削時の拡孔ビット開閉量を記録する装置や深度計が装備されており、その際のデータを利用して形状検査結果に代えることができる。
(8) Process Excavation Shape Inspection The
次に、実施例3について説明する。ここでは、場所打ち杭の施工法において使用し得るスタンドパイプ、ケーシングパイプまたは外殻鋼管(以下これらを単に「鋼管」という)の構成や、これら鋼管をリバース掘削機やアースドリル掘削機の駆動軸を使用して実施する方法について説明する。
図12は上記鋼管60の構成を示したものであり、鋼管本体61の先端付近にスパイラルガイド62が固着されている。このスパイラルガイド62は、鋼管60に圧力を加えながら回転させたときに、鋼管60を地盤内へ導き入れるように機能する。このスパイラルガイド62は、鉄板や丸鋼を鋼管本体61に溶接で取付けることにより形成される。鋼管本体61の頭部には取外し自在なキャップ63が取付けられている。このキャップ63と鋼管本体61は、ロックピン64と回転係止治具65により、相互に拘束されている。また、キャップ63の上蓋には掘削機の駆動軸67(ケリーバパイプやドリルロット)と接続するためのヒンジジョイント66が装備されている。このようにヒンジジョイント66にすることにより、鋼管60が水平に置かれた状態であっても両者を接続することができるので、効率的な吊込み作業が可能になる。
次に鋼管60の設置方法について説明する。地盤が軟弱の場合は、図の状態で直接掘削機の駆動軸67のトルクにより鋼管60をねじ込むことも可能であるが、表層地盤が硬質な場合や鋼管60が長い場合には、あらかじめ地盤を数mの深さまで削孔しておき、その中に鋼管60を建込み、そのままねじ込むか、掘削機のトルクが不足する場合には内部掘削を併用しながら所定の深さまで沈設する。鋼管60を引抜く場合は、引張り力を加えながら掘削機の駆動軸を逆転すれば良い。
Next, a third embodiment will be described. Here, the construction of stand pipes, casing pipes or outer shell steel pipes (hereinafter simply referred to as “steel pipes”) that can be used in the method of constructing cast-in-place piles, and the driving shafts of reverse drills and earth drill drills A method of implementing the method will be described.
FIG. 12 shows the configuration of the
Next, a method of installing the
実施例4では図13(a)〜(d)を参照して、場所打ち杭施工時に杭先にスライムが沈殿するのを防止する方法について説明する。大口径場所打ち杭のスライム処理は、通常、掘削終了直後とコンクリート打設直前の2回にわたって行われている。しかしながら、安定液中に浮遊している土粒子が時間の経過とともに孔底に沈降することや掘削後の孔内作業中に機器や鉄筋籠が孔壁に接触して、多少の土塊が落下することは避けられないのが実情である。このため図13(d)に示したように、コンクリート打設直前に、トレミー管70を利用してスライムの回収を行っているが、鉄筋籠71周辺やその外周の孔底72に溜まったスライム73を、充分に回収することは困難である。
本発明は、鉄筋籠外周についても、十分なスライム処理が行える方法を提案するものである。そのため、実施例1及び実施例3でも述べたように、1次スライム処理直後に掘削機の中空駆動軸部を利用して、孔底にセメントミルクを注入しておくことが必要である。その後の、掘削機の回収、掘削形状検査、鉄筋籠の建込み、トレミー管の設置作業などの工程で数時間を要するので、その間に新たなスライムが孔底に沈殿する。スライムは安定液中をゆっくり沈降するので、図13(a)のように、事前に孔底にセメントミルク74を注入しておくことにより、その比重の差や表面張力により、スライム75はセメントミルク74の表面に堆積する。このスライム75を安定液76やセメントミルク74と共にトレミー管70に接続した水中ポンプなどで吸上げて回収する。トレミー管70から離れたスライムもセメントミルクに載ってトレミー管70内に吸込まれ、地上に回収することができるため、スライムの処理後は、図13(b)のように鉄筋籠71の外周77でもスライムの無い状態にできる。そして、更に良いことには、図13(c)に示したように、コンクリート打設開始時のトレミー管先端がセメントミルク等の内部に位置しているので、コンクリート打設開始時に残存するスライム78aは、セメントミルク等やコンクリート等のセメント混合物の表面に堆積した状態で上昇するので、スライムによる悪影響を極めて少ないものにできる。
なお、時間の経過に伴うセメントミルクの分離を避けるため、分離防止剤や流動化剤などの混和剤を添加することが可能である。またセメント量節約のために、フライアッシュや石炭灰を混ぜることも可能である。
Fourth Embodiment With reference to FIGS. 13A to 13D, a method for preventing slime from depositing on a pile tip at the time of cast-in-place pile construction will be described in a fourth embodiment. Slime treatment of large-diameter cast-in-place piles is usually performed twice immediately after excavation and immediately before placing concrete. However, soil particles floating in the stabilizing liquid settle to the bottom of the hole with the passage of time, and during work inside the hole after excavation, equipment and reinforced cages come into contact with the hole wall and some soil mass falls. The fact is that things cannot be avoided. For this reason, as shown in FIG. 13D, slime is collected using the
The present invention proposes a method capable of performing a sufficient slime treatment also on the outer periphery of a reinforcing bar cage. Therefore, as described in the first and third embodiments, it is necessary to inject cement milk into the hole bottom using the hollow drive shaft of the excavator immediately after the primary slime treatment. The process of collecting the excavator, inspecting the excavation shape, building the reinforced cage, and installing the tremy tube requires several hours, during which time new slime is deposited at the bottom of the hole. Since the slime slowly settles in the stabilizing solution, as shown in FIG. 13 (a), by injecting the
In order to avoid separation of the cement milk over time, it is possible to add an admixture such as an antiseparation agent or a fluidizing agent. It is also possible to mix fly ash and coal ash to save cement.
1 掘削孔
2 スタンドパイプ
3 軸部
4 拡底部
5 安定液
10 ドリルパイプ
20 掘削ユニット
21 中空駆動軸
22b 軸部ビット
22c 拡孔ビット
25 拡孔ビット開閉量検出器
26 超音波形状検出器
29 ケーブル
30 駆動装置
31 ケリーバパイプ
40 掘削ユニット
49 超音波形状検出器
44 拡孔ビット
46 軸部ビット
50 アースドリル掘削機
51 ケリーバパイプ
54 掘削バケット
55 回転駆動部
60 鋼管(スタンドパイプ、ケーシングパイプまたは外殻鋼管)
62 スパイラルガイド
DESCRIPTION OF SYMBOLS 1
62 Spiral Guide
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004193519A JP2004263561A (en) | 2004-06-30 | 2004-06-30 | Cast-in-place pile and its work execution method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004193519A JP2004263561A (en) | 2004-06-30 | 2004-06-30 | Cast-in-place pile and its work execution method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004263561A true JP2004263561A (en) | 2004-09-24 |
Family
ID=33128865
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004193519A Pending JP2004263561A (en) | 2004-06-30 | 2004-06-30 | Cast-in-place pile and its work execution method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004263561A (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010185206A (en) * | 2009-02-12 | 2010-08-26 | Tokyu Construction Co Ltd | Foundation construction machine, attachment attached thereto, and foundation construction method |
JP2010281084A (en) * | 2009-06-03 | 2010-12-16 | Ohbayashi Corp | Constructive method of bracing wall, constructive method of pile, bracing wall, pile |
CN102587361A (en) * | 2012-03-27 | 2012-07-18 | 河海大学 | Polymer material grouted wedge precast pile technique |
JP2013147933A (en) * | 2013-05-08 | 2013-08-01 | Ohbayashi Corp | Earth retaining wall construction method, cast-in-place pile construction method, earth retaining wall, and cast-in-place pile |
CN103266603A (en) * | 2013-05-27 | 2013-08-28 | 浙江城建建设集团有限公司 | Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile |
JP2013177808A (en) * | 2013-05-23 | 2013-09-09 | Ohbayashi Corp | Construction method for earth retaining wall, construction method for pile, pile, and boring machine |
CN103437345A (en) * | 2013-08-29 | 2013-12-11 | 上海市机械施工集团有限公司 | Method for construction of diameter-expanding pile on pile top |
CN104343130A (en) * | 2013-07-25 | 2015-02-11 | 五冶集团上海有限公司 | Large-diameter manual hole digging expanded base pile foundation construction method |
JP2017075452A (en) * | 2015-10-13 | 2017-04-20 | 株式会社菅原建設 | Pile construction method and reverse excavation system |
JP2017082416A (en) * | 2015-10-23 | 2017-05-18 | 鹿島建設株式会社 | Tremie pipe structure and pile construction method |
CN107448137A (en) * | 2017-08-18 | 2017-12-08 | 新地能源工程技术有限公司 | A kind of rig that circles round enters the construction method of rock pore-forming |
CN113290636A (en) * | 2021-06-23 | 2021-08-24 | 徐州众磊建材科技有限公司 | Building material forming device |
CN113914301A (en) * | 2020-07-09 | 2022-01-11 | 中国建筑第八工程局有限公司 | Millimeter-level settlement control method in mudstone geological environment |
CN115030142A (en) * | 2022-05-27 | 2022-09-09 | 珠海十字门中央商务区建设控股有限公司 | Pile foundation engineering construction method |
CN117145410A (en) * | 2023-11-01 | 2023-12-01 | 湖南路桥建设集团有限责任公司 | Reverse circulation bored pile construction device and construction method |
Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5214005A (en) * | 1975-06-06 | 1977-02-02 | Takenaka Komuten Co | Method of forming casttin place concrete pile |
JPS55108530A (en) * | 1979-02-14 | 1980-08-20 | Kiso Kogyo Kk | Preventing method for production of precipitate on bottom of excavated hole |
JPS58222287A (en) * | 1982-06-16 | 1983-12-23 | 日立建機株式会社 | Bottom enlarged bit due to earth drill method and bottom enlarged bucket for constructing same |
JPS5934329A (en) * | 1982-08-17 | 1984-02-24 | Fujita Corp | Pile |
JPS6023520A (en) * | 1983-07-18 | 1985-02-06 | Marugo Kiso Kogyo Kk | Deformed cast-in-place pile |
JPS6195197A (en) * | 1984-10-16 | 1986-05-13 | 日立建機株式会社 | Automatic drilling control apparatus |
JPS61186617A (en) * | 1985-02-13 | 1986-08-20 | Konoike Constr Ltd | Method of managing execution of excavation of spread bottom drive-in-place pile |
JPS6286228A (en) * | 1985-10-09 | 1987-04-20 | Tokyu Constr Co Ltd | Penetration of casing and casing for extension |
JPS6319328A (en) * | 1986-07-11 | 1988-01-27 | Nisshin Kiso Kogyo Kk | Method and apparatus for constructing turning-penetrating type large-diameter steel tube |
JPH01299992A (en) * | 1988-05-27 | 1989-12-04 | Nippon Sharyo Seizo Kaisha Ltd | Expanded bottom detecting device for drilling system |
JPH04146324A (en) * | 1990-10-09 | 1992-05-20 | Takenaka Komuten Co Ltd | Execution method for cast-in-place concrete pile |
JPH0525987A (en) * | 1991-07-18 | 1993-02-02 | Kajima Corp | Method and apparatus for measuring shape of underground continuous wall surface |
JPH05179880A (en) * | 1991-12-27 | 1993-07-20 | Haseko Corp | Excavated hole bottom part diameter enlarging bottom-dredging bucket |
JPH06108456A (en) * | 1992-09-30 | 1994-04-19 | Hazama Gumi Ltd | Position measurement apparatus for excavator for underground continuous wall |
JPH09203208A (en) * | 1996-01-26 | 1997-08-05 | Kyoritsu Kensetsu Kk | Concrete placement/compaction device and concrete placement/computation method using the same device |
JP2001214438A (en) * | 2000-02-02 | 2001-08-07 | East Japan Railway Co | Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile. |
JP2001336149A (en) * | 2000-05-26 | 2001-12-07 | Safety Service System:Kk | Taper pile for civil engineering and building work foundation construction, foundation construction equipment therefor, and embedding method therefor |
JP2003003465A (en) * | 2001-06-20 | 2003-01-08 | Norio Moriya | Tapered foundation pile |
JP2003193469A (en) * | 2001-12-28 | 2003-07-09 | Takenaka Komuten Co Ltd | Slime measuring method and its equipment in diameter widening portion in multistage diameter widening cast-in- place concrete pile |
-
2004
- 2004-06-30 JP JP2004193519A patent/JP2004263561A/en active Pending
Patent Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5214005A (en) * | 1975-06-06 | 1977-02-02 | Takenaka Komuten Co | Method of forming casttin place concrete pile |
JPS55108530A (en) * | 1979-02-14 | 1980-08-20 | Kiso Kogyo Kk | Preventing method for production of precipitate on bottom of excavated hole |
JPS58222287A (en) * | 1982-06-16 | 1983-12-23 | 日立建機株式会社 | Bottom enlarged bit due to earth drill method and bottom enlarged bucket for constructing same |
JPS5934329A (en) * | 1982-08-17 | 1984-02-24 | Fujita Corp | Pile |
JPS6023520A (en) * | 1983-07-18 | 1985-02-06 | Marugo Kiso Kogyo Kk | Deformed cast-in-place pile |
JPS6195197A (en) * | 1984-10-16 | 1986-05-13 | 日立建機株式会社 | Automatic drilling control apparatus |
JPS61186617A (en) * | 1985-02-13 | 1986-08-20 | Konoike Constr Ltd | Method of managing execution of excavation of spread bottom drive-in-place pile |
JPS6286228A (en) * | 1985-10-09 | 1987-04-20 | Tokyu Constr Co Ltd | Penetration of casing and casing for extension |
JPS6319328A (en) * | 1986-07-11 | 1988-01-27 | Nisshin Kiso Kogyo Kk | Method and apparatus for constructing turning-penetrating type large-diameter steel tube |
JPH01299992A (en) * | 1988-05-27 | 1989-12-04 | Nippon Sharyo Seizo Kaisha Ltd | Expanded bottom detecting device for drilling system |
JPH04146324A (en) * | 1990-10-09 | 1992-05-20 | Takenaka Komuten Co Ltd | Execution method for cast-in-place concrete pile |
JPH0525987A (en) * | 1991-07-18 | 1993-02-02 | Kajima Corp | Method and apparatus for measuring shape of underground continuous wall surface |
JPH05179880A (en) * | 1991-12-27 | 1993-07-20 | Haseko Corp | Excavated hole bottom part diameter enlarging bottom-dredging bucket |
JPH06108456A (en) * | 1992-09-30 | 1994-04-19 | Hazama Gumi Ltd | Position measurement apparatus for excavator for underground continuous wall |
JPH09203208A (en) * | 1996-01-26 | 1997-08-05 | Kyoritsu Kensetsu Kk | Concrete placement/compaction device and concrete placement/computation method using the same device |
JP2001214438A (en) * | 2000-02-02 | 2001-08-07 | East Japan Railway Co | Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile. |
JP2001336149A (en) * | 2000-05-26 | 2001-12-07 | Safety Service System:Kk | Taper pile for civil engineering and building work foundation construction, foundation construction equipment therefor, and embedding method therefor |
JP2003003465A (en) * | 2001-06-20 | 2003-01-08 | Norio Moriya | Tapered foundation pile |
JP2003193469A (en) * | 2001-12-28 | 2003-07-09 | Takenaka Komuten Co Ltd | Slime measuring method and its equipment in diameter widening portion in multistage diameter widening cast-in- place concrete pile |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010185206A (en) * | 2009-02-12 | 2010-08-26 | Tokyu Construction Co Ltd | Foundation construction machine, attachment attached thereto, and foundation construction method |
JP2010281084A (en) * | 2009-06-03 | 2010-12-16 | Ohbayashi Corp | Constructive method of bracing wall, constructive method of pile, bracing wall, pile |
CN102587361B (en) * | 2012-03-27 | 2014-11-19 | 河海大学 | Polymer material grouted wedge precast pile construction method |
CN102587361A (en) * | 2012-03-27 | 2012-07-18 | 河海大学 | Polymer material grouted wedge precast pile technique |
JP2013147933A (en) * | 2013-05-08 | 2013-08-01 | Ohbayashi Corp | Earth retaining wall construction method, cast-in-place pile construction method, earth retaining wall, and cast-in-place pile |
JP2013177808A (en) * | 2013-05-23 | 2013-09-09 | Ohbayashi Corp | Construction method for earth retaining wall, construction method for pile, pile, and boring machine |
CN103266603A (en) * | 2013-05-27 | 2013-08-28 | 浙江城建建设集团有限公司 | Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile |
CN104343130A (en) * | 2013-07-25 | 2015-02-11 | 五冶集团上海有限公司 | Large-diameter manual hole digging expanded base pile foundation construction method |
CN103437345A (en) * | 2013-08-29 | 2013-12-11 | 上海市机械施工集团有限公司 | Method for construction of diameter-expanding pile on pile top |
JP2017075452A (en) * | 2015-10-13 | 2017-04-20 | 株式会社菅原建設 | Pile construction method and reverse excavation system |
JP2017082416A (en) * | 2015-10-23 | 2017-05-18 | 鹿島建設株式会社 | Tremie pipe structure and pile construction method |
CN107448137A (en) * | 2017-08-18 | 2017-12-08 | 新地能源工程技术有限公司 | A kind of rig that circles round enters the construction method of rock pore-forming |
CN107448137B (en) * | 2017-08-18 | 2023-10-24 | 新地能源工程技术有限公司 | Construction method for rock entering and pore forming of rotary drilling machine |
CN113914301A (en) * | 2020-07-09 | 2022-01-11 | 中国建筑第八工程局有限公司 | Millimeter-level settlement control method in mudstone geological environment |
CN113290636A (en) * | 2021-06-23 | 2021-08-24 | 徐州众磊建材科技有限公司 | Building material forming device |
CN115030142A (en) * | 2022-05-27 | 2022-09-09 | 珠海十字门中央商务区建设控股有限公司 | Pile foundation engineering construction method |
CN117145410A (en) * | 2023-11-01 | 2023-12-01 | 湖南路桥建设集团有限责任公司 | Reverse circulation bored pile construction device and construction method |
CN117145410B (en) * | 2023-11-01 | 2024-02-09 | 湖南路桥建设集团有限责任公司 | Reverse circulation bored pile construction device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5114529B2 (en) | Pile digging method | |
CN104563098B (en) | A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method | |
JP2004263561A (en) | Cast-in-place pile and its work execution method | |
CN110387879B (en) | Concrete cast-in-place pile construction method for hydraulically vibrating and hammering immersed tube | |
CN102720186B (en) | Underwater once pouring method for variable cross-section bored cast-in-place pile | |
JP2009036010A (en) | Method of building subsidence prevention pile and subsidence prevention pile | |
CN105155519A (en) | Rotary-excavating under-reamed bored pile constructing method | |
JP4974364B2 (en) | Pile burying method | |
JP5078511B2 (en) | Embedded pile method using earth drill machine | |
US20090285637A1 (en) | Pile mandrel with extendable reaming members | |
CN113699981A (en) | Construction method for preventing necking of rotary-digging cast-in-place pile in high-fill field | |
CN210105897U (en) | Throw stone layer stock pore-forming auxiliary device | |
CN205444192U (en) | Bridge stake is towards pile driving construction system | |
GB2154630A (en) | Construction method for foundation piling | |
CN115749654A (en) | Hole cleaning equipment for cast-in-place pile and cast-in-place pile hole forming method using same | |
JPH11166231A (en) | Bottom widening existing pile and embedding machine | |
JP2942779B1 (en) | Underground wall construction method | |
JP2002276273A (en) | Rotary driving device for excavation | |
JP3827309B2 (en) | Auxiliary pile method and embedded pile method | |
JP2015096676A (en) | Excavation method of pile hole having expanded head part | |
JP2005240282A (en) | Inner excavation tip enlarged foot protection method of foundation hollow pile and apparatus | |
JP2020169455A (en) | Construction method of soil cement continuous wall | |
CN213358707U (en) | Concrete pouring monitoring device | |
CN114232638B (en) | Anchor supporting structure | |
JP2015183374A (en) | Pile construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040715 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070416 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20081201 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090324 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20090721 |