JP3827309B2 - Auxiliary pile method and embedded pile method - Google Patents

Auxiliary pile method and embedded pile method Download PDF

Info

Publication number
JP3827309B2
JP3827309B2 JP2003007376A JP2003007376A JP3827309B2 JP 3827309 B2 JP3827309 B2 JP 3827309B2 JP 2003007376 A JP2003007376 A JP 2003007376A JP 2003007376 A JP2003007376 A JP 2003007376A JP 3827309 B2 JP3827309 B2 JP 3827309B2
Authority
JP
Japan
Prior art keywords
steel pipe
pile
drill
cap
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2003007376A
Other languages
Japanese (ja)
Other versions
JP2004218292A (en
Inventor
春彦 大樂
Original Assignee
有限会社大樂重機
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社大樂重機 filed Critical 有限会社大樂重機
Priority to JP2003007376A priority Critical patent/JP3827309B2/en
Publication of JP2004218292A publication Critical patent/JP2004218292A/en
Application granted granted Critical
Publication of JP3827309B2 publication Critical patent/JP3827309B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、建築現場等における埋め込み杭工法による杭基礎工事の際に用いる補助装置及びこれを用いた埋め込み杭工法に関する。
【0002】
【従来の技術】
建築物の杭基礎の施工法は、以前は専らコンクリート製の既製杭の打ち込みによるものであったが、社会情勢の変化により工事中の騒音や振動が厳しく規制され、今では街中で既製杭の打ち込み工事を見ることは殆どない。現在は、騒音や振動の少ない既製杭の埋め込み杭工法が一般的な街中での杭基礎工事の主流となっている。
【0003】
図5は上記既製杭を用いた従来の埋め込み杭工法を説明する図である。この埋め込み杭工法は、(イ)先ず、前もって杭を埋め込むための垂直な支持層まで達する穴を、クレーン等のベースマシン1によって支えられて垂直に立てられた主柱2(リーダとも称される。)に沿って付設されたガイド支柱に摺動自在に取り付けられたアースオーガ3(原動機)の掘削ドリル4(スクリューオーガ等であり、主柱2の下端で振れ止め防止具5に挿通されて垂直に保持されている。)で掘削し、(ロ)掘削ドリル4を引き抜きした掘削穴6にセメントミルク7(セメントを水で溶かしただけのミルク状のもの)を注入し(以上、オーガー施工という。)、(ハ)その中にコンクリート製又は鋼製の既製杭9をベースマシン1によって建て込み、(ニ)さらにセメント41を混入して前記既製杭9の周りの土を固めて埋め込む、という工法である。
【0004】
また、他の杭基礎工事の施工法として、大規模な杭基礎に適用される場所打ち杭工法がある(例えば、非特許文献1または非特許文献2参照。)。
【0005】
これは前もって現場で杭製作用の穴を掘り、その後、穴に鉄筋を入れてコンクリートを流し込んで鉄筋コンクリート製の杭とするものである。現場で杭を製作するので杭の運搬が不要であり、大規模な建築物を支える大口径の杭を比較的簡単に施工出来るという特徴を有する。反面、予め掘った穴が崩壊するのを防ぐためにケーシング(鞘管)を用いたり、比重の大きい泥水を大量に使用する必要がある。
【0006】
なお、場所打ち杭工法の一つでオールケーシング掘削機によるオールケーシング工法がある。そしてオールケーシング工法に使用する特殊継手付きの鋼管(ケーシングチューブという。)があるが、これは孔壁を保護するためリブ補強した鋼板製の2重構造としてねじれや損傷に対して強く耐久性を持たせた特殊なものである。
【0007】
一般にケーシングはコンクリート杭の穴が崩れないように、穴の中に挿入する円筒のことをいい、通常は鉄板製または鋼管が用いられる。大規模な建築施工では、100t吊りといった大型クレーンを用いてケーシングを回しながら抜き差しするが、このケーシングはせいぜい深さ3m程度までのものであって、それより深い箇所は膨潤させたベントナイト等の比重の大きな泥水を用いながら掘削していくのが通常である。
【0008】
なお、下記特許文献1には、通常の20〜50t吊りクラスのクレーンがベースマシンとして利用できることから現在主流となりつつある吊り下げ式リーダ方式の杭打機が記載されている。
【特許文献1】
特公平2−4732号公報
【非特許文献1】
ACEネットワーク著「建築・土木のことがわかる事典」株式会社西東社、1994年3月25日発行、p.130−131、p.147
【非特許文献2】
大成建設技術開発部著「建築・土木がわかる事典」株式会社日本実業出版社、1991年4月25日初版発行、p.318
【0009】
【発明が解決しようとする課題】
しかしながら、図5に示されるような一般的な建築現場で使用されている20t〜50t吊りのクレーン等のベースマシン1と、主柱2と、アースオーガ3と、これに装備した掘削ドリル4と、を用いて既製杭9を予め掘削した掘削穴6に埋め込むという従来の埋め込み杭工法では、せっかく掘った掘削穴6の壁が掘削ドリル4の引き抜きの際や引き抜き後に崩壊し易く、作業がはかどらないことが頻繁であった。
【0010】
本発明は上記事情に鑑みてなされたものであり、埋め込み杭工法における掘削穴6の壁崩壊を防止して既製杭9の埋め込み作業が効率的に行えるようにするための補助装置及びこの補助装置を用いた新しい効率的な埋め込み杭工法を提供するものである。
【0011】
【課題を解決するための手段】
本発明は、
(1)上端開口部近傍の外周に掛止部が設けられているとともに掘削ドリルが挿通可能な内径を有する鋼管と、前記鋼管の掛止部に係合して鋼管の上端開口部に脱着自在に冠着する掛止機構を備えるとともに吊り下げ式の主柱に設けられたガイド支柱に対して摺動自在とする摺動機構を備え、中央部に前記掘削ドリルが挿通可能な挿通孔を有する略円環状のキャップと、からなることを特徴とする埋め込み杭工法用補助装置を提供することにより、上記課題を達成する。
【0012】
(2)ベースマシンによって垂直に吊り下げられた主柱に付設されたガイド支柱に対して掘削ドリルを装備したアースオーガが摺動自在にワイヤで吊支され、前記ガイド支柱に対して摺動自在とする筒状のモンケンが前記掘削ドリルに挿通されるとともにワイヤで吊支され、前記ガイド支柱に対して摺動自在な略円環状のキャップが前記掘削ドリルに挿通されるとともにワイヤで吊支された状態とする工程と、鋼管を前記掘削ドリルに挿通するとともに前記鋼管の上端開口部に前記キャップを冠着して固定する工程と、前記主柱を鋼管とともに吊り上げて杭打ち箇所に垂直に立て、前記掘削ドリルと前記モンケンと前記キャップを冠着した鋼管とを垂直に保持する工程と、前記アースオーガの掘削ドリルで地中を掘削しつつ前記鋼管の上端に冠着された前記キャップの上面を前記モンケンで叩いて鋼管を地中に打ち込む工程と、前記鋼管の打ち込み終了後に前記掘削ドリルを鋼管から引き抜くとともに前記鋼管内にセメントミルクを注入する工程と、前記鋼管内に既製杭を建て込む工程と、前記鋼管を吊り上げて地中より引き抜く工程と、前記既製杭の回りの前記セメントミルクにセメントを混入して前記既製杭の周りの土を固める工程と、からなることを特徴とする上記(1)に記載の埋め込み杭工法用補助装置を用いた埋め込み杭工法を提供することにより、上記課題を達成する。
【0013】
【発明の実施の形態】
本発明に係る埋め込み杭工法用補助装置とこれを用いた埋め込み杭工法の実施の形態について図面に基づいて説明する。
【0014】
図1は本発明に係る埋め込み杭工法用補助装置の構造を示す斜視図である。
【0015】
図2は本発明に係る埋め込み杭工法用補助装置を用いた杭基礎工事の施工開始状態を示す図である。
【0016】
図3及び図4は本発明に係る埋め込み杭工法の工程の一部を説明するための概念図である。なお、従来技術とほぼ同様な部材は同符号で示す。
【0017】
先ず、本発明の埋め込み杭工法用補助装置は、図1に示されるような支持層まで達する程度の長さ(6m〜12m程度)の鋼管20と鋼製のキャップ10の組み合わせからなるものである。
【0018】
上記鋼管20は、上端開口部22近傍の外周に凸の掛止部21が設けられているとともに掘削ドリル(例えば径450mm)が緩やかに挿通可能な内径Φを有する円筒構造である。本鋼管20の目的は、後述するように掘削穴6の壁崩壊防止用であり、埋め込み杭工法における埋め込み用の掘削穴6の掘削と同時に打ち込まれ、既製杭9を建て込んだ後に吊り上げて地中から引き抜かれる。
【0019】
また、上記キャップ10は略円環状であって、前記鋼管20の掛止部21に係合して鋼管20の上端開口部に脱着自在に冠着する掛止機構11(周面の下側に略等間隔に取り付けられた数個のボルト12で前記鋼管20の掛止部21の凸の下側に掛止される。)を備えるとともに吊り下げ式の主柱に設けられたガイド支柱に対して摺動自在とする摺動機構15を備え、中央部に前記掘削ドリルが緩やかに挿通可能な挿通孔18を有する構造である。その上面は平坦なフランジ13になっている。本キャップ10の目的は、鋼管20を垂直に支持して吊り上げるため及びモンケンによる打ち込みの打撃を和らげて上端開口部22の変形を防止ためである。
【0020】
次に、上記埋め込み杭工法用補助装置であるキャップ10と鋼管20を用いた埋め込み杭工法は、先ず、図2に示されるように、クレーン等のベースマシン1によって垂直に吊り下げられた主柱2に付設されたガイド支柱8に対して掘削ドリル4を装備したアースオーガ3が摺動自在にワイヤで吊支され、前記ガイド支柱8に対して摺動自在とする筒状のモンケン31が前記掘削ドリル4に挿通されるとともにワイヤで吊支され、前記ガイド支柱8に対して摺動自在な略円環状の前記キャップ10が前記掘削ドリル4に挿通されるとともにワイヤで吊支された状態とする工程と、
前記鋼管20を前記掘削ドリル4に挿通するとともに前記鋼管20の上端開口部に前記キャップ10を冠着して固定する工程と、
前記主柱2を鋼管20とともに吊り上げて杭打ち箇所(鋼管20を通す穴が開けられている水平なベース40上)に垂直に立て、前記掘削ドリル4と前記モンケン31と前記キャップ10を冠着した鋼管20とを垂直に保持する工程と、を行って図2に示されるような状態(イ)にする。
【0021】
次に、図3に示されるように、上記状態(イ)から、
(ロ)前記アースオーガ3の掘削ドリル4で地中を掘削しつつ前記鋼管20の上端に冠着された前記キャップ10のフランジ13の上面を前記モンケン31で叩いて鋼管20を地中に打ち込む工程と、
(ハ)前記鋼管20の打ち込み終了後に前記キャップ10を鋼管20から外して前記掘削ドリル4を鋼管20から引き抜くとともに前記鋼管20内にセメントミルク7を注入する工程と、を行う。
【0022】
次に、図4に示されるように、
(ニ)前記鋼管20内に既製杭9をベースマシン1を用いて建て込む工程と、
(ホ)前記鋼管20をベースマシン1で吊り上げて(前記キャップ10を取り付けると作業が簡易となる。)地中より垂直に引き抜く工程と、
(ヘ)前記既製杭9の回りの前記セメントミルク7にセメント41を混入して前記既製杭9の周りの土を固める工程と、からなる一連の工程を行うものである。
【0023】
なお、上記モンケン(drop hammer)とは、杭打ち工事においてウィンチで牽引して落下させて杭を打ち込むのに用いる重錘をいい、本発明に使用される上記モンケンには、中央部に垂直穴を有する所謂「竹輪」に相当する中堀用モンケンが適用できる。また、本発明の工法に適用する上記既製杭9としては、従来の一般的なコンクリート杭の他にプレストレスコンクリート杭(PC杭)や鋼製の杭(H鋼杭その他の鋼材)が適用できる。
【0024】
ところで、本発明に係る鋼管20は掘削穴の壁崩壊防止の作用の点では、場所打ち杭工法のケーシングに似るが、比較的小規模な50t以下のクレーンをベースマシンとして用いる杭基礎工事の埋め込み杭工法に用いられるものであって用途が異なる。またその鋼管20の長さは埋め込む既製杭9の長さ程度(通常は6〜12m程度)であり、その内径Φは、例えば450mmの掘削ドリル4が遊挿される程度の寸法である。そして、場所打ち杭工法のケーシングのように管を回しながら抜くのではなく、モンケン31による打ち込みと管を回さずに直接に吊り上げて引き抜く構成であり、極めて効率的な杭基礎工事が実現するのである。
【0025】
本発明者の試験では、従来は1ベースマシンで1日2本の杭打ちが限度であったのが、本発明の埋め込み杭工法によれば1日5本の杭打ちが可能になることが判った。
【0026】
念のために付言すれば、本発明に係る埋め込み杭工法用補助装置としての鋼管20は中空の「杭」ではなく、掘削穴の壁崩壊を防止するためのものであり、既製杭9を鋼管20内に建て込んで鋼管20内にセメントミルク7を注入した後に引き抜かれるものである。この点で、杭として埋め込まれたままのコンクリート製や鋼製の筒状の杭とは全く異なる。
【0027】
【発明の効果】
本発明に係る埋め込み杭工法用補助装置及びこれを用いた埋め込み杭工法は、上記のように構成されているため、
(1)埋め込み杭工法において、補助装置の鋼管を掘削と同時に打ち込むことによって掘削穴の壁崩壊が防止される。
【0028】
(2)一般的な50t以下のクレーン等のベースマシンを用いた建築現場の杭基礎工事における埋め込み杭工法の施工効率が向上する。
【図面の簡単な説明】
【図1】本発明に係る埋め込み杭工法用補助装置の斜視図である。
【図2】本発明に係る埋め込み杭工法用補助装置を用いた杭基礎工事の施工開始状態を示す図である。
【図3】本発明に係る埋め込み杭工法の工程の一部を説明する図である。
【図4】本発明に係る埋め込み杭工法の工程の一部を説明する図である。
【図5】従来の埋め込み杭工法の工程を説明する図である。
【符号の説明】
1 ベースマシン
2 主柱
3 アースオーガ
4 掘削ドリル
5 振れ止め防止具
6 掘削穴
7 セメントミルク
8 ガイド支柱
9 既製杭
10 キャップ
11 掛止機構
12 ボルト
13 フランジ
15 摺動機構
18 挿通孔
20 鋼管
21 掛止部
22 鋼管の上端開口部
31 モンケン
40 ベース
41 セメント
Φ 鋼管の内径
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an auxiliary device used for pile foundation work by an embedded pile method at a construction site or the like, and an embedded pile method using the auxiliary device.
[0002]
[Prior art]
Previously, the construction method for building pile foundations was exclusively driven by the ready-made concrete piles, but due to changes in social conditions, noise and vibration during construction were severely regulated. I rarely see driving-in work. At present, the built-in pile method of pre-made piles with less noise and vibration is the mainstream of pile foundation work in general towns.
[0003]
FIG. 5 is a diagram for explaining a conventional buried pile method using the above-mentioned ready-made pile. In this embedded pile method, (a) First, a main pillar 2 (also referred to as a leader) is set up in such a way that a hole reaching a vertical support layer for embedding a pile in advance is supported vertically by a base machine 1 such as a crane. .) Is a drilling drill 4 (screw auger or the like) of an earth auger 3 (prime mover) slidably attached to a guide post provided along the center of the main pillar 2 and is inserted into a steady-state prevention device 5. (B) Cement milk 7 (milk-like product in which cement is melted with water) is poured into the excavation hole 6 from which the excavation drill 4 has been pulled out. (Iii) A concrete or steel ready-made pile 9 is built in the base machine 1 and (d) further cement 41 is mixed in to solidify the soil around the ready-made pile 9. No, it is a method that.
[0004]
Moreover, there exists a cast-in-place pile construction method applied to a large-scale pile foundation as another construction method of pile foundation construction (for example, refer nonpatent literature 1 or nonpatent literature 2).
[0005]
This is a method of digging a hole for making a pile in the field in advance, then putting a rebar into the hole and pouring the concrete into a reinforced concrete pile. Since piles are manufactured on site, transport of the piles is unnecessary, and it has the feature that large diameter piles that support large-scale buildings can be constructed relatively easily. On the other hand, it is necessary to use a casing (sheath tube) or to use a large amount of muddy water having a large specific gravity in order to prevent a hole dug in advance from collapsing.
[0006]
One of the cast-in-place pile methods is an all-casing method using an all-casing excavator. And there is a steel pipe with a special joint (referred to as a casing tube) used in the all-casing method, but this is a double structure made of steel plates with rib reinforcement to protect the hole wall, and is highly resistant to twisting and damage. Special.
[0007]
Generally, the casing is a cylinder inserted into the hole so that the hole of the concrete pile does not collapse, and is usually made of iron plate or steel pipe. In large-scale construction work, a large crane such as a 100-ton crane is used to insert and remove the casing while rotating it. This casing is at most about 3 m deep, and the deeper part is the specific gravity of swollen bentonite or the like. It is normal to drill while using large mud.
[0008]
Patent Document 1 below describes a hanging leader type pile driving machine that is currently becoming mainstream because a normal 20 to 50 t crane class crane can be used as a base machine.
[Patent Document 1]
Japanese Patent Publication No. 2-4732 [Non-Patent Document 1]
“Encyclopedia of Architecture and Civil Engineering” by ACE Network, Saitosha Co., Ltd., published on March 25, 1994, p. 130-131, p. 147
[Non-Patent Document 2]
Taisei Construction Technology Development Department, “Encyclopedia of Architecture and Civil Engineering”, Nihon Jitsugyo Publishing Co., Ltd., published April 25, 1991, p. 318
[0009]
[Problems to be solved by the invention]
However, a base machine 1 such as a crane of 20 to 50 tons used at a general construction site as shown in FIG. 5, a main pillar 2, an earth auger 3, and an excavation drill 4 equipped thereon. In the conventional embedded pile construction method in which the ready-made pile 9 is embedded in the excavated hole 6 that has been excavated in advance, the wall of the excavated drill hole 6 is easily collapsed during or after the excavation drill 4 is pulled out, so that the work is very difficult. Not often.
[0010]
The present invention has been made in view of the above circumstances, and an auxiliary device for preventing the wall collapse of the excavation hole 6 in the embedded pile construction method so that the work of embedding the ready-made pile 9 can be performed efficiently and the auxiliary device. A new and efficient embedded pile construction method using
[0011]
[Means for Solving the Problems]
The present invention
(1) A steel pipe having an inner diameter through which an excavation drill can be inserted and a hook part provided on the outer periphery in the vicinity of the upper end opening part, and engageable with the hook part of the steel pipe so as to be detachable from the upper end opening part of the steel pipe And a sliding mechanism that is slidable with respect to a guide column provided on a suspended main column, and has an insertion hole through which the excavation drill can be inserted. The above object is achieved by providing an auxiliary device for an embedded pile method characterized by comprising a substantially annular cap.
[0012]
(2) An earth auger equipped with an excavation drill is slidably supported by a wire on a guide column attached to a main column suspended vertically by a base machine, and is slidable with respect to the guide column. A cylindrical monken is inserted into the excavation drill and suspended by a wire, and a substantially annular cap slidable with respect to the guide column is inserted into the excavation drill and suspended by a wire. A step of inserting the steel pipe into the excavation drill and attaching and fixing the cap to the upper end opening of the steel pipe; and lifting the main pillar together with the steel pipe to stand perpendicular to the pile driving position A step of vertically holding the excavation drill, the monken and the steel pipe fitted with the cap; and excavating the ground with the excavation drill of the earth auger, at the upper end of the steel pipe Striking the upper surface of the attached cap with the monken and driving the steel pipe into the ground; pulling out the drilling drill from the steel pipe after the completion of driving the steel pipe; and injecting cement milk into the steel pipe; and A step of building a ready-made pile inside, a step of lifting the steel pipe and pulling it out of the ground, a step of mixing cement into the cement milk around the ready-made pile and solidifying the soil around the ready-made pile, By providing an embedded pile method using the auxiliary device for embedded pile method described in (1) above, the above-mentioned problem is achieved.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EMBODIMENTS Embodiments of an embedded pile method auxiliary device according to the present invention and an embedded pile method using the same will be described with reference to the drawings.
[0014]
FIG. 1 is a perspective view showing the structure of an auxiliary device for embedded pile construction according to the present invention.
[0015]
FIG. 2 is a diagram showing a construction start state of pile foundation work using the auxiliary device for embedded pile method according to the present invention.
[0016]
3 and 4 are conceptual diagrams for explaining a part of the steps of the embedded pile method according to the present invention. In addition, the substantially same member as a prior art is shown with a same sign.
[0017]
First, the auxiliary device for embedded pile method according to the present invention comprises a combination of a steel pipe 20 and a steel cap 10 having a length (about 6 m to 12 m) that reaches the support layer as shown in FIG. .
[0018]
The steel pipe 20 has a cylindrical structure in which a convex hooking portion 21 is provided on the outer periphery in the vicinity of the upper end opening 22 and an inner diameter Φ into which a drilling drill (for example, a diameter of 450 mm) can be slowly inserted. The purpose of the steel pipe 20 is to prevent the wall collapse of the excavation hole 6 as will be described later, and it is driven simultaneously with excavation of the excavation hole 6 for embedding in the embedded pile construction method. Pulled out from inside.
[0019]
The cap 10 has a substantially annular shape, and engages with a latching portion 21 of the steel pipe 20 so as to be detachably attached to the upper end opening of the steel pipe 20 (on the lower side of the circumferential surface). It is hooked on the lower side of the convex portion of the hooking portion 21 of the steel pipe 20 with several bolts 12 attached at substantially equal intervals.) And a guide column provided on a hanging main column And a sliding mechanism 15 that is slidable, and has an insertion hole 18 through which the excavation drill can be gently inserted. The upper surface is a flat flange 13. The purpose of the cap 10 is to support the steel pipe 20 vertically and lift it, and to soften the hammering by the monken and prevent the upper end opening 22 from being deformed.
[0020]
Next, in the embedded pile method using the cap 10 and the steel pipe 20 as the auxiliary device for the embedded pile method, first, as shown in FIG. 2, the main pillar suspended vertically by the base machine 1 such as a crane. An earth auger 3 equipped with an excavation drill 4 is slidably supported by a wire with respect to a guide column 8 attached to 2, and a cylindrical monken 31 slidable with respect to the guide column 8 is A substantially annular cap 10 that is inserted into the drilling drill 4 and suspended by a wire and slidable with respect to the guide column 8 is inserted into the drilling drill 4 and suspended by a wire. And a process of
Inserting the steel pipe 20 through the excavation drill 4 and fixing the cap 10 to the upper end opening of the steel pipe 20;
The main pillar 2 is lifted together with the steel pipe 20 and vertically placed on a pile driving location (on a horizontal base 40 in which a hole for passing the steel pipe 20 is drilled), and the excavation drill 4, the monken 31 and the cap 10 are crowned. The step of holding the steel pipe 20 vertically is performed to obtain a state (A) as shown in FIG.
[0021]
Next, as shown in FIG.
(B) While excavating the ground with the excavation drill 4 of the earth auger 3, the upper surface of the flange 13 of the cap 10 which is attached to the upper end of the steel pipe 20 is hit with the monken 31 to drive the steel pipe 20 into the ground. Process,
(C) The step of removing the cap 10 from the steel pipe 20 after the driving of the steel pipe 20 and pulling out the drilling drill 4 from the steel pipe 20 and injecting the cement milk 7 into the steel pipe 20 is performed.
[0022]
Next, as shown in FIG.
(D) a step of building the ready-made pile 9 in the steel pipe 20 using the base machine 1;
(E) hoisting the steel pipe 20 with the base machine 1 (the work is simplified when the cap 10 is attached), and pulling it vertically from the ground;
(F) A series of steps consisting of a step of mixing cement 41 into the cement milk 7 around the ready-made pile 9 and solidifying the soil around the ready-made pile 9 is performed.
[0023]
The above-mentioned monken (drop hammer) refers to a weight used for driving a pile by pulling it with a winch in pile driving work, and the monken used in the present invention has a vertical hole in the center. Nakabori monken corresponding to the so-called “bamboo ring” having Moreover, as said ready-made pile 9 applied to the construction method of this invention, a prestress concrete pile (PC pile) and steel piles (H steel pile other steel materials) can be applied besides the conventional general concrete pile. .
[0024]
By the way, the steel pipe 20 according to the present invention is similar to the cast-in-place pile method casing in terms of the effect of preventing the wall collapse of the excavation hole, but embedding pile foundation work using a relatively small 50t or less crane as a base machine. It is used for the pile construction method and its usage is different. The length of the steel pipe 20 is about the length of the prefabricated pile 9 to be embedded (usually about 6 to 12 m), and the inner diameter Φ is such a dimension that the 450 mm excavation drill 4 is loosely inserted, for example. And it is the structure which does not pull out while turning a pipe like the casing of the cast-in-place pile construction method, but is directly lifted and pulled without turning the pipe and turning the pipe, realizing extremely efficient pile foundation work. It is.
[0025]
According to the present inventor's test, it was possible to drive five piles a day according to the embedded pile construction method of the present invention, although it was limited to two piles a day with one base machine. understood.
[0026]
As a precaution, the steel pipe 20 as an auxiliary device for the embedded pile method according to the present invention is not a hollow “pile”, but is intended to prevent the wall of the excavation hole from collapsing. It is built in 20 and poured out after injecting cement milk 7 into the steel pipe 20. In this regard, it is completely different from a concrete or steel cylindrical pile that is embedded as a pile.
[0027]
【The invention's effect】
Since the auxiliary device for embedded pile method according to the present invention and the embedded pile method using the same are configured as described above,
(1) In the embedded pile method, the wall of the excavation hole is prevented by driving the steel pipe of the auxiliary device at the same time as excavation.
[0028]
(2) The construction efficiency of the embedded pile construction method in the pile foundation construction of a construction site using a general base machine such as a crane of 50 tons or less is improved.
[Brief description of the drawings]
FIG. 1 is a perspective view of an auxiliary device for embedded pile construction according to the present invention.
FIG. 2 is a diagram showing a construction start state of pile foundation work using the auxiliary device for embedded pile method according to the present invention.
FIG. 3 is a diagram for explaining a part of the steps of the embedded pile method according to the present invention.
FIG. 4 is a diagram for explaining a part of the embedded pile method according to the present invention.
FIG. 5 is a diagram for explaining a process of a conventional buried pile method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Base machine 2 Main pillar 3 Earth auger 4 Drilling drill 5 Stabilizer 6 Drilling hole 7 Cement milk 8 Guide strut 9 Ready-made pile 10 Cap 11 Latching mechanism 12 Bolt 13 Flange 15 Sliding mechanism 18 Insertion hole 20 Steel pipe 21 Hang Stop 22 Upper end opening 31 of steel pipe Monken 40 Base 41 Cement Φ Inner diameter of steel pipe

Claims (2)

上端開口部近傍の外周に掛止部が設けられているとともに掘削ドリルが挿通可能な内径を有する鋼管と、
前記鋼管の掛止部に係合して鋼管の上端開口部に脱着自在に冠着する掛止機構を備えるとともに吊り下げ式の主柱に設けられたガイド支柱に対して摺動自在とする摺動機構を備え、中央部に前記掘削ドリルが挿通可能な挿通孔を有する略円環状のキャップと、からなることを特徴とする埋め込み杭工法用補助装置。
A steel pipe having an inner diameter through which a drilling drill can be inserted while a latching portion is provided on the outer periphery in the vicinity of the upper end opening,
A sliding mechanism that includes a latching mechanism that engages with a latching portion of the steel pipe and is detachably attached to an upper end opening of the steel pipe and that is slidable with respect to a guide column provided on a hanging main column. An auxiliary device for an embedded pile method, comprising a moving mechanism and a substantially annular cap having an insertion hole through which the excavation drill can be inserted at a central portion.
ベースマシンによって垂直に吊り下げられた主柱に付設されたガイド支柱に対して掘削ドリルを装備したアースオーガが摺動自在にワイヤで吊支され、前記ガイド支柱に対して摺動自在とする筒状のモンケンが前記掘削ドリルに挿通されるとともにワイヤで吊支され、前記ガイド支柱に対して摺動自在な略円環状のキャップが前記掘削ドリルに挿通されるとともにワイヤで吊支された状態とする工程と、
鋼管を前記掘削ドリルに挿通するとともに前記鋼管の上端開口部に前記キャップを冠着して固定する工程と、
前記主柱を鋼管とともに吊り上げて杭打ち箇所に垂直に立て、前記掘削ドリルと前記モンケンと前記キャップを冠着した鋼管とを垂直に保持する工程と、
前記アースオーガの掘削ドリルで地中を掘削しつつ前記鋼管の上端に冠着された前記キャップの上面を前記モンケンで叩いて鋼管を地中に打ち込む工程と、
前記鋼管の打ち込み終了後に前記掘削ドリルを鋼管から引き抜くとともに前記鋼管内にセメントミルクを注入する工程と、
前記鋼管内に既製杭を建て込む工程と、
前記鋼管を吊り上げて地中より引き抜く工程と、
前記既製杭の回りの前記セメントミルクにセメントを混入して前記既製杭の周りの土を固める工程と、からなることを特徴とする請求項1に記載の埋め込み杭工法用補助装置を用いた埋め込み杭工法。
A cylinder in which an earth auger equipped with an excavation drill is slidably supported by a wire to a guide column attached to a main column vertically suspended by a base machine so as to be slidable with respect to the guide column. A ring-shaped monken is inserted into the drilling drill and suspended by a wire, and a substantially annular cap that is slidable with respect to the guide column is inserted into the drilling drill and suspended by a wire; And a process of
Inserting a steel pipe through the excavation drill and fixing the cap to the upper end opening of the steel pipe; and
Hoisting the main pillar together with the steel pipe and standing vertically to the pile driving site, and holding the excavation drill, the monken, and the steel pipe fitted with the cap vertically;
Hitting the upper surface of the cap that is attached to the upper end of the steel pipe with the monken while drilling the ground with the drill drill of the earth auger, and driving the steel pipe into the ground;
Extracting the drilling drill from the steel pipe after the driving of the steel pipe and injecting cement milk into the steel pipe;
Building a ready-made pile in the steel pipe;
Lifting the steel pipe and pulling it out of the ground,
The embedding using the auxiliary device for embedded pile construction method according to claim 1, further comprising: mixing cement into the cement milk around the ready-made pile to solidify the soil around the ready-made pile. Pile method.
JP2003007376A 2003-01-15 2003-01-15 Auxiliary pile method and embedded pile method Expired - Lifetime JP3827309B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003007376A JP3827309B2 (en) 2003-01-15 2003-01-15 Auxiliary pile method and embedded pile method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003007376A JP3827309B2 (en) 2003-01-15 2003-01-15 Auxiliary pile method and embedded pile method

Publications (2)

Publication Number Publication Date
JP2004218292A JP2004218292A (en) 2004-08-05
JP3827309B2 true JP3827309B2 (en) 2006-09-27

Family

ID=32897499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003007376A Expired - Lifetime JP3827309B2 (en) 2003-01-15 2003-01-15 Auxiliary pile method and embedded pile method

Country Status (1)

Country Link
JP (1) JP3827309B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498947A (en) * 2016-11-18 2017-03-15 天津港航工程有限公司 Case cartridge type piling saddle and its construction technology

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5068301B2 (en) * 2009-11-27 2012-11-07 常陽建設株式会社 Gotoku stitch water-proof construction method and tubular member used therefor
CN112554177B (en) * 2021-02-22 2021-05-11 中铁九局集团第四工程有限公司 Construction method of ultra-long small-diameter cast-in-situ bored pile
CN115045271B (en) * 2022-06-28 2024-08-27 中交建筑集团第六工程有限公司 Pile foundation steel pile casing positioning construction process based on pile foundation steel pile casing transportation construction trolley
CN115305895B (en) * 2022-07-18 2024-02-02 中铁三局集团有限公司 Auxiliary device and method for foundation reinforcement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498947A (en) * 2016-11-18 2017-03-15 天津港航工程有限公司 Case cartridge type piling saddle and its construction technology

Also Published As

Publication number Publication date
JP2004218292A (en) 2004-08-05

Similar Documents

Publication Publication Date Title
WO1996018001A1 (en) Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method
CN111851484A (en) Method for cutting off semi-invasive prestressed anchor cable in supporting pile by rotary drilling rig
JP2017223066A (en) Pile construction management method
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
JP5078511B2 (en) Embedded pile method using earth drill machine
JP2004263561A (en) Cast-in-place pile and its work execution method
JP2008014000A (en) Construction method of cast-in-place concrete pile
JP3827309B2 (en) Auxiliary pile method and embedded pile method
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JPH07145616A (en) Cast-in-place concrete piling method
JPH08209686A (en) Pile head processing tool and pile head processing construction method for cast-in-place pile
EP1283307A2 (en) Method of forming enlarged pile heads
CN212405120U (en) Bored concrete pile of construction is executed to underground reinforced concrete structure department
JP2016037706A (en) Pile head reinforcement method for foundation pile
JPH11166231A (en) Bottom widening existing pile and embedding machine
CN113089654A (en) Construction process of hole digging pile in complex soil layer and steel casing for construction
JP2011140765A (en) Method of driving pile
JP6636362B2 (en) Connection structure between bucket and connection casing and backfill method of excavation hole
JP4137173B1 (en) Reinforcing bar construction in cast-in-place pile
JP2004218378A (en) Removing method for existing pile
JPH03257215A (en) Pile constructing method
JP2002242178A (en) Cast-in-place pile method and working scaffold for steel bar cage erection
JP4137172B1 (en) Reinforcing bar construction in cast-in-place pile
JPH0657762A (en) Construction of deep foundation
JP3293796B2 (en) Pile driver

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060601

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060613

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060703

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3827309

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090714

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100714

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100714

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110714

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110714

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120714

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130714

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term