JP2004156304A - Removal and backfilling construction method for pipe-jacking tunnel - Google Patents

Removal and backfilling construction method for pipe-jacking tunnel Download PDF

Info

Publication number
JP2004156304A
JP2004156304A JP2002322917A JP2002322917A JP2004156304A JP 2004156304 A JP2004156304 A JP 2004156304A JP 2002322917 A JP2002322917 A JP 2002322917A JP 2002322917 A JP2002322917 A JP 2002322917A JP 2004156304 A JP2004156304 A JP 2004156304A
Authority
JP
Japan
Prior art keywords
tube
propulsion
shaft
backfilling
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002322917A
Other languages
Japanese (ja)
Other versions
JP3815731B2 (en
Inventor
Kikuo Ishida
喜久雄 石田
Katsuhiko Yuchi
克彦 有地
Takashi Wakechigai
隆志 輪違
Masaaki Nakano
正明 中野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Kidoh Construction Co Ltd
Sumitomo Mitsui Construction Co Ltd
Original Assignee
IHI Corp
Kidoh Construction Co Ltd
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp, Kidoh Construction Co Ltd, Sumitomo Mitsui Construction Co Ltd filed Critical IHI Corp
Priority to JP2002322917A priority Critical patent/JP3815731B2/en
Publication of JP2004156304A publication Critical patent/JP2004156304A/en
Application granted granted Critical
Publication of JP3815731B2 publication Critical patent/JP3815731B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a removal and backfilling construction method for a pipe-jacking tunnel in which a jacking pipe is removed and backfilling can be carried out without working large compressive force resulting from frictional force working between a ground and the jacking pipe to the jacking pipe constituting the pipe-jacking tunnel. <P>SOLUTION: The construction method is conducted so that the jacking pipes 3 constituting the pipe-jacking tunnel 1 are removed one by one in a sleeve 25, laying the sleeve 25 on the outer periphery of the existing pipe-jacking tunnel 1 to be removed. The pipe-jacking tunnel 1 is removed, and an excavated pit 32 excavated by the sleeve 25 is filled with a backfilling material and the pit is backfilled. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、不要になった推進トンネルを非開削で撤去し、埋め戻す、推進トンネルの撤去・埋め戻し工法に関する。
【0002】
【従来の技術】
社会基盤の整備の進展に伴い、大都市の地下には、さまざまな用途のトンネルが敷設され、特に、幹線道路の地下は各種のトンネルで過密状態になっている。地下利用が進み、新たなトンネルが計画される一方で、老朽化やライフラインの変更によって使用停止や廃棄されるトンネルも急激に増加し、これら既設トンネルを撤去し、埋め戻すことが要望されている。
【0003】
前記使用停止や廃棄されたトンネル、特に、推進トンネルを撤去し、埋め戻しを行なう工法として、推進トンネルを引き抜き、その跡を埋め戻すようにした引き抜き工法がある。この工法は、撤去すべき推進トンネルの両端に立坑を形成し、該立坑の一方を発進立坑、他方を到達立坑とする。発進立坑側の推進トンネルの端部に埋め戻し装置を接続し、到達立坑側に配置された牽引装置で埋め戻し装置を牽引することにより、該埋め戻し装置を介して推進トンネル全体を到達立坑側に引き抜く。そして、埋め戻し装置の発進立坑側に形成される空間に埋め戻し材を充填する、ことにより推進トンネルの撤去・埋め戻しを行う(特許文献1参照)。
【0004】
【特許文献1】
特開2001−262998号公報、(第4−5頁、図1)
【0005】
【発明が解決しようとする課題】
このような推進トンネルの撤去・埋め戻し工法では、推進トンネルの一端に埋め戻し装置を接続し、該埋め戻し装置を牽引することにより、推進トンネルを到達立坑内に引き出す構成であるため、推進トンネルが敷設された地盤と推進トンネルとの間の摩擦力が大きく、牽引時に推進トンネルを構成する推進管に、大きな牽引力(圧縮力)が作用する。しかし、推進トンネルを構成する推進管には、該推進管の許容耐荷力以上の牽引力を作用させることはできない。このため、推進管の健全度合い(老朽化度合い)によっては、該工法を適用できないことがある。
【0006】
前記の事情に鑑み、本発明は、推進トンネルを構成する推進管に大きな牽引力を作用させることなく、推進トンネルを撤去し、埋め戻しが行えるようにした推進トンネルの撤去・埋め戻し工法を提供することを目的とする。
【0007】
【課題を解決するための手段】
請求項1に係る発明は、撤去すべき推進トンネル(1)の両端に発進立坑(6)と到達立坑(7)を形成し、
前記発進立坑(6)から、撤去すべき推進トンネル(1)を構成する推進管列(2)の外周を覆うようにさや管(25)を敷設しつつ、
前記さや管(25)を通して、前記推進管列(2)を構成する推進管(3)を、一本ずつ前記発進立坑(6)へ搬送して撤去し、
前記到達立坑(7)に到達した前記さや管(25)の先端に、埋め戻し装置(65)を接続し、
前記埋め戻し装置(65)を、前記発進立坑側(6)に向けてさや管(25)で掘削した削進穴(32)内を後退させながら、前記埋め戻し装置(65)の後方に形成される空間に埋め戻し材(71)を充填し、前記削進穴(32)の埋め戻しを行うようにした。
【0008】
請求項2に係る発明は、請求項1記載の発明において、前記さや管(25)の先端には削進チューブ(26)が設けられており、該削進チューブ(26)により前記推進トンネル(1)の外周を掘削してさや管(25)を敷設し、
該さや管(25)が前記第2の立坑(7)に到達した後、該第2の立坑(7)内でさや管(25)の先端から前記削進チューブ(26)を切り離すと共に、削進チューブ(26)が切り離されたさや管(25)の先端に前記埋め戻し装置(65)を連結し、
該さや管(25)と埋め戻し装置(65)を前記第1の立坑(6)側へ移動させながら前記削進穴(32)の埋め戻しを行うようにした。
【0009】
請求項3に係る発明は、請求項1記載の発明において、前記第1の立坑(6)内に、前記さや管(25)の敷設手段(10)を設置し、
前記敷設手段(10)により、前記さや管(25)を揺動及び軸心方向に移動駆動することにより、前記第1の立坑(6)側から、該さや管(25)の先端で前記推進トンネル(1)外周を削進させると共に、該さや管(25)を該推進トンネル(1)の外周を覆うように敷設するようにした。
【0010】
請求項4に係る発明は、請求項3記載の発明において、前記埋め戻し装置(65)が連結された前記さや管(25)を、前記さや管(25)の敷設手段(10)により第1の立坑(6)側に引き抜き、前記さや管(25)と共に第1の立坑(6)側へ移動する前記埋め戻し装置(65)の前記第2の立坑(7)側に形成される空間に埋め戻し材(71)を充填して、前記削進穴(32)を埋め戻すようにした。
【0011】
請求項5に係る発明は、請求項3記載の発明において、前記敷設手段(10)によって、前記さや管(25)と該さや管(25)に連結された埋め戻し装置(65)を前記第1の立坑(6)側へ移動させ、該第1の立坑(6)内で該さや管(25)を構成するケーシングチューブ(27)を一本ずつ切離し、切り離されたケーシングチューブ(27)及び埋め戻し装置(65)を地上へ回収するようにした。
【0012】
なお、括弧内の符号等は、図面と対照するためのものであり、これは、発明の理解を容易にするための便宜的なものであって、特許請求の範囲に何ら影響を及ぼすものではない。
【0013】
【発明の効果】
請求項1に係る発明によると、推進トンネルの外周にさや管を敷設し、該さや管を通して推進管列を構成する推進管を一本ずつ撤去し、推進管列を撤去した後、埋め戻しを行うようにしているので、推進管に地盤と推進管との間に作用する摩擦力に起因する牽引力(圧縮力)を作用させることなく、推進トンネルの撤去・埋め戻しを行うことができる。従って、中程度に老朽化した推進トンネルを撤去し、埋め戻しを行うことができる。また、推進トンネルの撤去・埋め戻し工法を適用することができる範囲(推進トンネルの老朽化度合)を拡大することができる。
【0014】
請求項2記載の発明によると、削進チューブと埋め戻し装置とを、さや管の先端に着脱自在に配置するようにしたので、これらの交換作業が容易であり、推進トンネルの撤去・埋め戻し作業の作業性を向上させることができる。
【0015】
請求項3記載の発明によると、推進トンネルの外周を掘削しつつ、その掘削穴内にさや管を敷設するようにしたので、推進トンネルに大きな負荷を作用させることなくさや管の敷設を行うことができる。従って、本発明による推進トンネルの撤去・埋め戻し工法の適用範囲を拡大することができる。
【0016】
請求項4記載の発明によると、強度の大きなさや管を引っ張ることにより埋め戻し装置を第1の立坑側に移動させているので、埋め戻し装置を確実に移動させることができ、作業性を向上させることができる。
【0017】
請求項5記載の発明によると、さや管を引っ張ることによりさや管と該さや管に連結された埋め戻し装置を第1の立坑内に移動させ、該第1の立坑内でさや管を構成するケーシングチューブを切離し、地上へ回収するようにしたので、さや管及び埋め戻し装置を第1の立坑に確実に移動させ、地上に回収することができる。
【0018】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。
【0019】
図1ないし図9は、本発明の実施の形態の一例を示すもので、図1は、本発明による推進トンネルの撤去・埋め戻し工法の立坑形成工程の一例を示す工程図、図2は、本発明による推進トンネルの撤去・埋め戻し工法のさや管敷設工程の一例を示す工程図、図3は、本発明による推進トンネルの撤去・埋め戻し工法の推進管切り離し工程の一例を示す工程図、図4は、本発明による推進トンネルの撤去・埋め戻し工法の推進管撤去工程の一例を示す工程図、図5は、本発明による推進トンネルの撤去・埋め戻し工法の埋め戻し装置の接続工程の一例を示す工程図、図6は、本発明による推進トンネルの撤去・埋め戻し工法の埋め戻し工程の一例を示す工程図、図7は、本発明による推進トンネルの撤去・埋め戻し工法の削進部の一例を示す拡大図、図8は、図2のA−A矢視拡大図、図9は、調心装置の一例を示す拡大図である。
【0020】
図1乃至図4及び図7に示すように、撤去対象となる既設の推進トンネル1は、推進管列2を形成する、相互に直列に接続された複数の推進管3で構成されている。なお、推進トンネル1(推進管列2)を構成する各推進管3の長さL1は、例えば、2.43mに形成されている。
【0021】
本発明による推進トンネル1の撤去・埋め戻しに使用する装置は、推進トンネル1が埋設された地盤5にさや管25を揺動圧入して、前記推進トンネル1の外周の掘削を行うと共に、さや管25を敷設する敷設手段としての揺動式のオールケーシング掘削機10(図2、図4、図5、図6参照)と、掘削時に前記推進トンネル1とさや管25の軸心CT1を一致させる調心装置35(図7、図8、図9参照)と、前記推進トンネル1とさや管25との間の間隙からさや管25内に水や土砂が侵入するのを防止するための妻板装置45(図7、図8参照)と、掘削時に前記推進トンネル1(推進管3)を内側から支え、その破損を防止するリング支保装置50(図7、図8参照)と、推進管列2から推進管3を切り離す際に、推進管3を支持する切離し装置55(図3参照)と、推進管3の切離しと搬送を行う自走台車21(図2、図3、図4参照)と、推進トンネル1が撤去された削進穴32内の埋め戻しを行う埋め戻し装置65(図5、図6参照)と、を有している。
【0022】
また、図示していないが、給水管31(図2参照)を通して掘削部に水を供給する給水装置と、該給水装置から掘削部に供給された水と掘削された土砂を前記妻板装置45に接続された排土管48(図2、図7、図8参照)を介して地上に排出する吸引装置と、埋め戻し材供給管62(図6参照)を通して削進穴32内に埋め戻し材を圧入する埋め戻し材供給装置と、前記オールケーシング掘削機10、さや管25、推進管3、調心装置35、妻板装置45、リング支保装置50、切離し装置55、自走台車21、埋め戻し装置65等の供給、撤去を行うクレーン等を備えている。
【0023】
図2に示すように、揺動式のオールケーシング掘削機10は、駆動部10aと、該駆動部10aによって駆動され、推進トンネル1の周囲を掘削、推進するさや管25と、前記駆動部10aに対して前記さや管25や推進管3、埋め戻し装置65の受け渡しを行うための管受架台20および受台63と、を有している。
【0024】
前記オールケーシング掘削機10の駆動部10aは、前記推進トンネル1の軸心CT1を中心として揺動可能に配置され、その軸心部を貫通する前記さや管25の外周を着脱自在に保持する環状のチャック16を備えている。前記チャック16は、前記推進トンネル1の軸心CT1を中心とする所定の円周上に、その円周方向に所定の間隔で、それぞれ前記軸心CT1と平行な方向に移動可能に配置された複数の圧入フレーム15に固定されている。
【0025】
前記チャック16の外周部には、油圧供給装置12に接続された揺動ジャッキ17が連結され、該揺動ジャッキ17により、該チャック16が軸心CT1を中心として揺動駆動される。また、前記各圧入フレーム15には、ベース11の端面11aに前記推進管列2の軸心CT1を中心とする円周の接線方向に揺動自在に配置され、前記油圧装置12から圧油を供給自在に接続された複数の圧入ジャッキ13が、それぞれ、例えば、球面軸受け(図示せず)を介して揺動自在に連結され、該各圧入ジャッキ13により、各圧入フレーム15が軸心CT1と平行な方向に移動駆動される。
【0026】
即ち、前記圧入ジャッキ13は、前記圧入フレーム15を介して前記チャック16を前記軸心CT1方向に移動させる。また、前記揺動ジャッキ17は、前記チャック16を、前記軸心CT1を中心として所定の角度往復回転(揺動)させるようになっている。
【0027】
前記管受架台20には、図示しない支持台が配置され、該支持台上に前記さや管25や埋め戻し装置65を搭載したとき、該さや管25や埋め戻し装置65と前記推進トンネル1の各軸心CT1が一致するように支持する。また、該管受架台20は、載置されたさや管25と該推進トンネル1の軸心が一致するように設定された原点位置D(図2に実線で示す位置)と、さや管25の接続、切り離しを行う操作位置E(図2に一点鎖線で示す位置)の間で矢印X方向(軸心CT1方向)に移動可能である。また、撤去される前記推進管3を搭載するときには、前記原点位置Dと、前記さや管25と管受架台20の間で推進管3が円滑に移動し得る搬送位置F(図2に二点鎖線で示す位置)との間で矢印X、Z方向に移動可能に構成されている。
【0028】
図2に示すように、前記さや管25は、さや管25の最先端に装着され、前記駆動部10aで揺動駆動され、前記推進トンネル1の外周を掘削する削進チューブ26と、該削進チューブ26の後端に接続され、推進管3の撤去された後の推進トンネル1の外周を覆う複数のケーシングチューブ27とにより構成される。なお、前記削進チューブ26の長さL2は、3m、ケーシングチューブ27の長さL3、L4は、2mと3mに形成されている。そして、削進チューブ26を含め、3mのチューブと2mのチューブを交互に接続して用いる。即ち、例えば3mの削進チューブ26の後に2mのケーシングチューブ27を接続するとその長さは5mになり、略推進管3の2本分の長さ4.86m(2.43m×2)になる。
【0029】
前記削進チューブ26の先端部26aには、所定の間隔で複数のカッタービット28が固定されている。また、該削進チューブ26の後端部には、後続のケーシングチューブ27を接続するための接続部26bが形成されている。また、前記各ケーシングチューブ27の先端部には、前記削進チューブ26もしくは先行するケーシングチューブ27の後端に接続するための接続部27aが形成され、後端部には、後続のケーシングチューブ27を接続するための接続部27bが形成されている。
【0030】
また、前記削進チューブ26には、図8に示すように、その後端部から先端に向けて軸心CT1と平行な給水穴30が形成されている。該給水穴30の後端部には、到達立坑7(図1参照)側から引かれた給水管31(図2参照)が接続され、前記削進チューブ26の内部を通してカッタービット28が取り付けられた先端部に水を供給するようになっている。
【0031】
図2に示すように、前記削進チューブ26とケーシングチューブ27、ケーシングチューブ27とケーシングチューブ27の接続は、図2に示すように、先行する削進チューブ26またはケーシングチューブ27の後端が、前記圧入フレーム15の端面より発進立坑6側に突出した状態で行う。
【0032】
前記接続は、先行する削進チューブ26またはケーシングチューブ27の接続部26bまたは27bに、後続のケーシングチューブ27の接続部27aを嵌合させ、各接続部26bと27a、または接続部27bと27aを貫通する穴にロックピン等を打ち込むことにより行う。なお、各接続部にパテ等を塗布し、水等の侵入を防止するシール部を形成することができる。
【0033】
前記管受架台20上には、自走台車21が移動自在に支持されている。該自走台車21は、該管受架台20上だけでなく、前記さや管25内を前記軸心CT1に沿って移動し、前記推進管列2から推進管3を分離し、分離した推進管3の搬送を行う。また、図3に示すように、自走台車21の一端(推進トンネル1と対向する側の端部)には、連結用のブラケット22と、牽引ロッド23が配置されている。
【0034】
図7及び図8に示すように、発進立坑6(図1、図2参照)側の推進管3の端部には、調心装置35と、妻枠装置45と、リング支保装置50がそれぞれ着脱自在に配置される。
【0035】
図9に示すように、前記調心装置35は、推進管3の端部に嵌合するコの字形のブラケット36と、該ブラケット36に固定された球座37と、該球座37に固定され、前記削進チューブ26の内周面26cと対抗する面に貫通穴38aが形成されたハウジング38を有している。前記球座37とハウジング38で囲まれる空間には、その一部が前記管通穴38aから突出する形で鋼球41が転動自在に支持されている。前記ハウジング38の貫通穴38aの内周面には、貫通穴38aと鋼球41の隙間を覆う形でダストシール40が固定されている。
【0036】
この調心装置35は、推進管3の端部に所定の間隔で3個配置され、削進チューブ26の軸心を、推進トンネル1の軸心CT1と一致させるように、推進管3に対する削進チューブ26の位置を規制する。なお、この調心装置35は、推進管3を発進立坑6へ搬送する際に、推進管3の先端と後端に取り付けることによりの搬送手段(車輪)を兼ねられるようになっている。
【0037】
図8に示すように、前記妻枠装置45は、前記推進管3の端面に固定され、前記削進チューブ26の内周面26cに向けて突出する4分割された妻板46a、46b、46c、46dと、該妻板46a、46b、46c、46dと削進チューブ26の内周面26cとの間の隙間を埋めるゴムパッキン47(図7参照)を有している。
【0038】
図7、図8に示すように、前記妻板46cには、前記到達立坑7(図1参照)から引かれた排土管48が接続されている。この排土管48は、該到達立坑7の外部に配置された吸引装置(図示せず)に接続されている。そして、前記削進チューブ26で掘削され水と混合された土砂を吸引排出する。
【0039】
図7、図8に示すように、リング支保装置50は、前記推進管3の内周面3bと接触する円弧面51aが形成された一対の支保部材51、51と、該支保部材51、51を互いに近接、離間させる方向に移動自在に接続する一対の間隔調整部材52、52(例えば、ターンバックル、両ねじボルト等)とにより構成されている。
【0040】
図3に示すように、前記推進管列2の推進管3の分離部には、切り離し装置55が配置される。該切り離し装置55は、推進管列2側に残る推進管3の滑材注入穴3aに着脱自在に嵌合する複数の支持金具56で支持されたレール57を有している。該レール57には、該レール57に沿って矢印X方向に移動自在なトロリー58が支持されている。該トロリー58には、切り離される推進管3の推進管列2側の滑材注入穴3aに着脱自在に嵌合する吊り金具60が固定されている。なお、切り離される推進管3の自走台車21側の滑材注入穴3aにも、前記牽引ロッド23を接続するために吊り金具60が取付けられる。
【0041】
図5に示すように、到達立坑7側の受台63は、該受台63上に削進チューブ26(図1参照)または、埋め戻し装置65が載置されたとき、削進チューブ26の軸心CT1、埋め戻し装置65の軸心CT1が、さや管25(推進トンネル1)の軸心CT1と一致するように支持する。
【0042】
前記埋め戻し装置65は、一端に接続部66bが形成された円筒状の外殻66と、該外殻66の内周面に沿って所定の間隔で配置された複数の隔壁ジャッキ67と、外殻66の開口部66aを閉塞する形で設けられた、埋め戻し材の注入口68aが形成され、該隔壁ジャッキ67に支持されたテール隔壁68と、該隔壁ジャッキ67に油圧を供給する油圧供給装置70を有している。前記注入口68aは、前記発進立坑6の外部に配置された埋め戻し材供給装置(図示せず)に接続される。
【0043】
本実施の形態による推進トンネルの撤去・埋め戻しは次のようにして行う。まず、図1に示すように、撤去する推進トンネル1の両端に発進立坑(第1の立坑)6と到達立坑(第2の立坑)7を形成する。そして、発進立坑6と到達立坑7の推進トンネル1と接する位置に、発進坑口6aと到達坑口7aを形成する。なお、該発進立坑6及び到達立坑7は、推進トンネル1の敷設時に形成され、その後、メンテナンス用のマンホールとして使用されていた立坑を利用してもよい。
【0044】
図2に示すように、発進立坑6内に、オールケーシング掘削機10と管受架台20を設置する。オールケーシング掘削機10は、チャック16の軸心が推進トンネル1の軸心CT1と一致するように、そのベース11を前記発進坑口6aに取り付ける。また、管受架台20は、前述のように、原点位置Dにあるとき、削進チューブ26、ケーシングチューブ27を載置すると、これら削進チューブ26及びケーシングチューブ27の軸心が推進トンネル1の軸心CT1と一致するように、発進立坑6の底面に設置する。
【0045】
図5に示すように、到達立坑7には、受台63を設置する。該受台63は、削進チューブ26や埋め戻し装置65を載置したとき、それらの軸心がさや管25(推進トンネル1)の軸心CT1と一致するように到達立坑7の底面に設置する。また、到達立坑7の外部に設置された図示しない給水装置に接続された給水管31と吸引装置に接続された排土管48を、図2に示すように、到達立坑7から推進トンネル1を通して発進立坑6側へ向けて、推進管3の長さ(2.43m)と略同じ長さの管を継ぎ足しながら延長し配管する。
【0046】
発進立坑6の管受架台20上に、削進チューブ26を吊り下ろす。管受架台20に削進チューブ26が載置された状態で、オールケーシング掘削機10の圧入ジャッキ13を伸長させ、圧入フレーム15を削進チューブ26の外周に外嵌させる。同時に、管受架台20を発進坑口6a側に移動させて、削進チューブ26の先端がチャック16を貫通し発進坑口6a側に突出するように挿入する。そして、チャック16で削進チューブ26を固定する。
【0047】
この状態で、圧入ジャッキ13を収縮させると共に、揺動ジャッキ17を作動させる。すると、チャック16が発進坑口6a側に移動して、削進チューブ26の先端に固定されたカッタービット28を発進坑口6aに押し付けると共に、軸心CT1を中心として揺動させる。このカッタービット28の揺動と押し付け力によって、発進坑口6aが掘削される。そして、削進チューブ26のカッタービット28が発進坑口6aを貫通すると、削進チューブ26の先端部が推進管3の外周を取り囲む形で推進トンネル1方向、即ち、矢印A方向に推進され、これにより推進管3の周囲の地盤5の掘削が開始される。
【0048】
削進チューブ26による掘削が所定の深さ(調心装置35、妻板装置45の取付けが可能になる深さ、例えば、500mm程度)まで掘削すると、一旦、圧入ジャッキ13及び揺動ジャッキ17を停止させる。そして、削進チューブ26内に露出した推進管3の端部に、リング支保装置50、調心装置35及び妻板装置45を取り付ける。
【0049】
図7、図8に示すように、推進管3の内部に支保部材51、51間の間隔を縮小したリング支保装置50を挿入し、間隔調整部材52を操作して、支保部材51の円弧面51aを推進管3の内周面3cに接触させる。ついで、図9に示すように、推進管3の端部に調心装置35のブラケット36を装着して、鋼球41がリング支保装置50の支保部材51と対応するように位置決めして、図示しない固定部材で固定する。
【0050】
さらに、図7、図8に示すように、推進管3の端面に、ゴムパッキン等のシール部材を介して妻板46a、46b、46c、46dを取付ける。また、削進チューブ26の内周面26cと各妻板46a〜46dとの隙間にゴムパッキン47を配置する。そして、図2に示すように、妻板46cに排土管48を接続すると共に、給水管31を削進チューブ26の給水穴30(図8参照)に接続する。
【0051】
図示しない吸引装置で、排土管48を通して地盤2、推進管3、妻板46a〜46d及び削進チューブ26の内周面26aで囲まれる掘削空間内の土砂を吸引しつつ、図示しない給水装置から給水管31、給水穴30を通して掘削部に水を供給する。
【0052】
この状態で、圧入ジャッキ13と揺動ジャッキ17を作動させ、掘削を再開させる。なお、掘削により発生する土砂は比較的細かい粒子となるので、前記吸引装置で吸引することにより、掘削部に供給された水と共に排出することができる。また、推進管3は、削進チューブ26から調進装置35を介して圧縮力を受けることになるが、その内周面3bをリング支保装置50で支持されているため、該圧縮力によって変形することはなく、破損を防止することができる。
【0053】
なお、圧入ジャッキ13による圧入フレーム15の移動距離、即ち、削進チューブ26の移動距離は、圧入ジャッキ13のストロークにより設定され、削進チューブ26の長さに比べかなり小さくなっている。従って、圧入ジャッキ13のストローク分だけ削進チューブ26が移動したら、チャック16による削進チューブ26の固定を解除し、圧入ジャッキ13を伸長させて、チャック16を図2矢印B方向に後退させる。そして、チャック16で削進チューブ26を再度固定した後、圧入ジャッキ13と揺動ジャッキ17を作動させて、掘削を再開させる。
【0054】
このような操作を繰り返し、図7に二点鎖線で示すように、削進チューブ26の先端が、撤去する推進管3に隣接する推進管3の所定の位置まで掘削したら、圧入ジャッキ13及び揺動ジャッキ17を停止させ、掘削を停止させる。給水管31からの給水を停止させ、所定の時間経過した後、排土管48の吸引を停止させる。なお、給水停止後の吸引時間は、地盤2、推進管3、妻板46a〜46d及び削進チューブ26の内周面26cで囲まれる掘削空間に残る水と土砂を排出するのに必要な時間とする。
【0055】
排土管48による前記掘削空間の土砂の吸引が終了したら、作業者が削進チューブ26内に移動して、まず、給水管31を削進チューブ26から外し、排土管48を妻板46cから外す。ついで、推進管3から妻板46a〜46dを外す。そして、妻板46a〜46dを発進立坑6へ撤去する。
【0056】
図3に示すように、切離し装置55を搬入して、支持金具56を推進管列2側に残る推進管3の滑材注入穴3aに装着し、該支持金具56にレール57を固定する。該レール57に移動自在に支持されたトロリー57に吊り金具60を接続し、該吊り金具60の一端を切り離す推進管3の滑材注入穴3aに装着する。また、切り離される推進管3の他方の滑材注入穴3aにも、牽引用の吊り金具60を取り付ける。
【0057】
ついで、管受架台20を前記搬送位置に移動させ、自走台車21を管受架台20上から削進チューブ26内に移動させる。そして、自走台車21のブラケット22と前記牽引用の吊り金具60を牽引ロッド23で接続する。この状態で、自走台車21を矢印X1方向(発進立坑6側)に移動させると、牽引ロッド23を介して切り離すべき推進管3が、図3に示す矢印X1方向に引っ張られ、推進管列2から切り離される。
【0058】
このとき、切り離された推進管3の推進管列2側(到達立坑7側)の端部は、吊り金具60を介してトロリー58に吊り下げられているので、落下することはない。この状態で、推進管3の切り離された側(推進管列2側)の端部下方に、2個の調心装置35を搬送用の車輪として所定の間隔で取り付ける。
【0059】
図4に示すように、トロリー58と吊り金具60を切り離し、自走台車21を矢印X1方向に走行させて、二点鎖線で示すように、切り離された推進管3を管受架台20上に搬送する。推進管3が管受架台20上に搬出されると、管受架台20は、前記原点位置Dに復帰する。また、自走台車21と推進管3を接続する牽引ロッド23を切り離す。
【0060】
管受架台20上に搬出された推進管3は、発進立坑6の外に配置されたクレーン(図示せず)等で地上に搬出され、撤去される。なお、推進管3に付設された調心装置35と吊り金具60は、発進立坑6内で取外してもよいし、発進立坑6外へ撤去してから取外すようにしてもよい。
【0061】
また、推進管列2の発進立坑6側の端部の推進管3に設置されている切離し装置55を、該推進管3から取外し、発進立坑6側に搬出する。なお、該切離し装置55は、推進管3から取外した状態で、推進管列2内に押し込む形で保管するようにしてもよい。
【0062】
一方、到達立坑7側では、推進管3の一本分の給水管31と排土管48を切離す。切離された給水管31と排土管48は、到達立坑7の外部に設置されたクレーン等で、到達立坑7の外へ搬出する。
【0063】
この状態で、図7、図8に示すように、前記と同様の作業を行い、削進チューブ26内に露出した推進管3の端部に、リング支保装置50、調心装置35及び妻板装置45を取り付ける。そして、妻板46cに排土管48を接続すると共に、図2に示すように、給水管31を削進チューブ26の給水穴30に接続する。
【0064】
図2に示すように、推進管3が発進立坑6から撤去された後、管受架台20上にケーシングチューブ27を吊り下ろす。そして、管受架台20を前記操作位置に移動させ、削進チューブ26の後端の接続部26bに、ケーシングチューブ27の先端の接続部27aを嵌合させる。各接続部26b、27aに形成された貫通穴に図示しないロックピンを打ち込むことにより、削進チューブ26とケーシングチューブ27を接続する。そして、該削進チューブ26の接続部26bとケーシングチューブ27の接続部27aに、防水シール用のパテ等を塗布して接続作業を終了する。
【0065】
このような操作を繰り返すことにより、推進管列2を形成するすべての推進管3を一本ずつ撤去する。削進チューブ26が到達立坑7に到達した後、最後の推進管3が撤去され、全ての推進管3の撤去が終了する。なお、最後の推進管3を撤去するときには、到達立坑7内に切離し装置55を設置し、該推進管3の到達立坑7側の一端を支持させるようにする。
【0066】
削進チューブ26の先端が到達立坑7内に突出し、最後の推進管3を撤去したら、削進チューブ26全体を発進立坑7内に送り込む。このとき、給水管31及び排土管48は、すべて到達立坑7から撤去する。そして、削進チューブ26を後続のケーシングチューブ27から切離し、到達立坑7から外部に設置されたクレーン等で撤去する。
【0067】
削進チューブ26とケーシングチューブ27の切離しは、それらの接続部26b、27aに塗布されたパテを除去し、ロックピンを抜いた後、さや管25を発進立坑6側に移動させることにより行うことができる。
【0068】
図5に示すように、到達立坑7に、該クレーン等で埋め戻し装置65を吊り下げる。埋め戻し装置65が受台63上に載置されたら、前記オールケーシング掘削機10の圧入ジャッキ13を作動させ、さや管25全体を到達立坑7側に移動させて、ケーシングチューブ27の接続部27aを埋め戻し装置65の接続部66bに嵌合させる。この状態で、前記削進チューブ26とケーシングチューブ27の接続と同様に、図示しないロックピンを打ち込みケーシングチューブ27と埋め戻し装置65を接続する。
【0069】
さや管25の一端に埋め戻し装置65を接続した後、発進立坑6側では、オールケーシング掘削機10を作動させ、該さや管25を発進立坑6に引き込む。この操作は、チャック16によるケーシングチューブ27の固定を解除し、圧入ジャッキ13を収縮させる。すると、圧入フレーム15を介してチャック16が発進坑口6a側に移動する。この状態でチャック16によりケーシングチューブ27を固定し、圧入ジャッキ13を伸長させる。すると、圧入フレーム16を介してチャック16が発進坑口6aから離間する方向に移動する。このとき、チャック16に固定されたケーシングチューブ27が、圧入ジャッキ13のストローク分だけ発進立坑6内に引き出される。
【0070】
このような操作を繰り返すことにより、さや管25全体を発進立坑6側に移動させることができる。従って、さや管25の一端に固定された埋め戻し装置65を削進チューブ26で形成した削進穴32内に引き込む。このとき、管受架台20が、その操作位置Eで待機していると、発進坑口6aを貫通していたケーシングチューブ27は、管受架台20上に移動して載置される。
【0071】
図6に示すように、埋め戻し装置65を削進穴32内に引き込むと、オールケーシング掘削機10は、前記と同様の操作で、チャック16を発進坑口6a側へ移動させ、該チャック16でケーシングチューブ27を固定した状態で待機する。この状態で、さや管25から管受架台25上に載置されたケーシングチューブ27を切り離す。この切離し作業は、前後に接続された各ケーシングチューブ27の接続部27a、27bに塗布されたシール材を除去し、前記ロックピンを抜き、各接続部27a、27bの結合を解除した後、管受架台20を前記原点位置Dへ移動させることにより行われる。
【0072】
さや管25から切り離されたケーシングチューブ27は、発進立坑6の外部に設置されたクレーン等で発進立坑6の外部に撤去される。また、発進立坑6の外部に設置された埋め戻し材供給装置(図示せず)に接続された埋め戻し材供給管62を、さや管25の内部を通してテール隔壁68の供給口68aに接続する。
【0073】
埋め戻し装置65全体が削進穴32に引き込まれた状態で、到達立坑7から受台63を撤去する。そして、油圧供給装置70から供給される油圧で隔壁ジャッキ67を伸長させ、テール隔壁68を到達立坑7側に移動させて外殻66の開口66aを覆った状態で、到達立坑7の上部の開口部から埋め戻し材71を投入して、到達立坑7の仮埋め戻しを行う。この仮埋め戻しは、図6に破線で示すように、削進穴32を塞ぎ、該削進穴32内部から埋め戻し力が作用したとき、崩れない程度に行えばよい。また、到達立坑7の仮埋め戻しに代えて、二点鎖線で示すように、到達坑口7aを蓋72で塞ぐようにしてもよい。
【0074】
到達坑口7aを塞いだ状態で、テール隔壁68の注入口68aからテール隔壁68と到達立坑7に投入された埋め戻し材71(または蓋72)の間に所定の圧力で埋め戻し材71を注入しながら、油圧供給装置70を作動させ、隔壁ジャッキ67を収縮させて、テール隔壁68を外殻66内に引き込む。そして、テール隔壁68の移動によって発生する到達立坑7内の埋め戻し材71(または、蓋72)と外殻66及びテール隔壁68で形成される空間に、埋め戻し材71を注入、充填する。
【0075】
テール隔壁68が所定の位置まで移動して停止すると、オールケーシング掘削機10の圧入ジャッキ13が作動して、さや管25と埋め戻し装置65を発進立坑6側に移動させる。同時に、埋め戻し装置65の隔壁ジャッキ67が逆方向に作動して、埋め戻し装置65に対しテール隔壁68を到達立坑7側へ移動させる。従って、テール隔壁68は、発進立坑6側に移動する埋め戻し装置65に対し、それとは逆の到達立坑7側に移動するので、地盤5に対しては、略静止した状態におかれる。
【0076】
すると、埋め戻し装置65の外殻66内に充填され、埋め戻し装置65と共に発進立坑6側へ移動しようとする埋め戻し材71の移動がテール隔壁68によって阻止される。従って、外殻66内に充填された埋め戻し材71は、埋め戻し装置65の移動によって相対的に到達立坑7側へ移動することになり、外殻66内から削進穴32内へ送り出されることになる。そして、注入時に削進穴32と埋め戻し材71の間に介在していた埋め戻し装置65の外殻66が抜けた空間を埋める。
【0077】
前記の操作を繰り返すことにより、さや管25と埋め戻し装置65を発進立坑6側に移動させながら削進穴32内の埋め戻しを行うと共に、さや管25を構成するケーシングチューブ27の撤去を行う。そして、埋め戻し装置65が発進立坑6に到達し、管受架台20上に載置されると、削進穴32の埋め戻しは終了する。
【0078】
なお、削進穴32の埋め戻しがある程度進行したら、削進穴32の埋め戻しと平行して、仮埋め戻し状態になっている到達立坑7の埋め戻しを行う。このとき、到達立坑7の到達坑口7aに蓋72を設置した場合には、該蓋72を撤去して埋め戻しを行う。
【0079】
こうして、埋め戻し装置65が発進立坑6の位置まで引き寄せられ、チャック16により発進立坑6内に引き抜かれたところで、発進立坑6の外部に設置されたクレーン等で、埋め戻し装置65、自走台車21、管受架台20、オールケーシング掘削機10を撤去する。そして、発進立坑6上部開口部から埋め戻し材71を投入して、発進立坑6の埋め戻しを行う。
【0080】
前記の実施の形態によれば、撤去する推進トンネル1に沿ってさや管25を敷設しつつ、さや管25の内部で該推進トンネル1を構成する推進管3を一本ずつ撤去するようにしているので、推進管3(複数の推進管3で構成される推進管列2)と地盤5との間の摩擦力に起因する大きな圧縮力を推進管3に作用させることなく撤去することができる。従って、中程度に老朽化した推進トンネル1であっても、確実に撤去して埋め戻すことができる。
【0081】
また、前記公知技術のように、推進管3(推進管列2)に大きな圧縮力を作用させることがないので、本工法を適用することができる推進トンネル1の範囲(老朽化度合)を拡大することができる。
【図面の簡単な説明】
【図1】本発明による推進トンネルの撤去・埋め戻し工法の立坑形成工程の一例を示す工程図。
【図2】本発明による推進トンネルの撤去・埋め戻し工法のさや管敷設工程の一例を示す工程図。
【図3】本発明による推進トンネルの撤去・埋め戻し工法の推進管切り離し工程の一例を示す工程図。
【図4】本発明による推進トンネルの撤去・埋め戻し工法の推進管撤去工程の一例を示す工程図。
【図5】本発明による推進トンネルの撤去・埋め戻し工法の埋め戻し装置の接続工程の一例を示す工程図。
【図6】本発明による推進トンネルの撤去・埋め戻し工法の埋め戻し工程の一例を示す工程図。
【図7】本発明による推進トンネルの撤去・埋め戻し工法の削進部の一例を示す拡大図。
【図8】図2のA−A矢視拡大図。
【図9】調心装置の一例を示す拡大図。
【符号の説明】
1…推進トンネル
2…推進管列
3…推進管
6…第1の立坑(発進立坑)
7…第2の立坑(到達立坑)
10…敷設装置(オールケーシング掘削機)
25…さや管
27…ケーシングチューブ
32…削進穴
65…埋め戻し装置
71…埋め戻し材
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of removing and backfilling an unnecessary propulsion tunnel without digging and backfilling the propulsion tunnel.
[0002]
[Prior art]
With the progress of social infrastructure development, tunnels for various uses have been laid underground in large cities, and especially underground arterial roads are overcrowded with various types of tunnels. Underground usage is progressing, and new tunnels are planned, while the number of tunnels that are suspended or discarded due to aging and changes in lifelines are rapidly increasing, and it is requested that these existing tunnels be removed and rebuilt. I have.
[0003]
As a method of removing and refilling the suspended or discarded tunnel, in particular, the propulsion tunnel, there is a drawing method in which the propulsion tunnel is pulled out and the trace thereof is backfilled. In this method, shafts are formed at both ends of a propulsion tunnel to be removed, and one of the shafts is a starting shaft and the other is a reaching shaft. By connecting a backfilling device to the end of the propulsion tunnel on the starting shaft side and towing the backfilling device by a traction device arranged on the reaching shaft side, the entire propulsion tunnel is passed through the backfilling device to the reaching shaft side. Pull out. Then, the space formed on the starting shaft side of the backfilling device is filled with a backfill material, thereby removing and backfilling the propulsion tunnel (see Patent Document 1).
[0004]
[Patent Document 1]
JP-A-2001-262998, (page 4-5, FIG. 1)
[0005]
[Problems to be solved by the invention]
In such a removal and backfilling method of the propulsion tunnel, a backfill device is connected to one end of the propulsion tunnel, and the propulsion tunnel is pulled out into the arrival shaft by pulling the backfill device. The frictional force between the ground on which is laid and the propulsion tunnel is large, and a large traction force (compression force) acts on the propulsion pipe constituting the propulsion tunnel during towing. However, a traction force greater than the allowable load capacity of the propulsion tube cannot be applied to the propulsion tube constituting the propulsion tunnel. For this reason, depending on the soundness (degree of aging) of the propulsion pipe, this method may not be applicable.
[0006]
In view of the above circumstances, the present invention provides a method for removing and backfilling a propulsion tunnel in which the propulsion tunnel can be removed and backfilled without exerting a large traction force on a propulsion pipe constituting the propulsion tunnel. The purpose is to:
[0007]
[Means for Solving the Problems]
The invention according to claim 1 forms a starting shaft (6) and a reaching shaft (7) at both ends of a propulsion tunnel (1) to be removed,
From the starting shaft (6), a sheath tube (25) is laid so as to cover the outer periphery of the propulsion tube row (2) constituting the propulsion tunnel (1) to be removed.
Through the sheath pipe (25), the propulsion pipes (3) constituting the propulsion pipe row (2) are transported one by one to the starting shaft (6) and removed,
A backfilling device (65) is connected to the tip of the sheath tube (25) that has reached the reaching shaft (7),
The backfilling device (65) is formed behind the backfilling device (65) while retreating in the cut hole (32) drilled by the sheath pipe (25) toward the starting shaft (6). The space to be filled is filled with a backfill material (71), and the backcut hole (32) is backfilled.
[0008]
According to a second aspect of the present invention, in the first aspect, a cutting tube (26) is provided at a tip of the sheath tube (25), and the propulsion tunnel (26) is provided by the cutting tube (26). 1) Excavating the outer circumference and laying a sheath tube (25)
After the sheath tube (25) reaches the second shaft (7), the cutting tube (26) is cut off from the tip of the sheath tube (25) in the second shaft (7), and Connecting the backfilling device (65) to the tip of the sheath (25) from which the advance tube (26) has been cut off,
The back hole (32) is back-filled while moving the sheath pipe (25) and the back-filling device (65) toward the first shaft (6).
[0009]
According to a third aspect of the present invention, in the first aspect, laying means (10) for the sheath pipe (25) is installed in the first shaft (6),
The laying means (10) swings and moves the sheath pipe (25) in the axial direction, thereby driving the sheath pipe (25) from the first shaft (6) side at the tip of the sheath pipe (25). The outer periphery of the tunnel (1) was cut down, and the sheath (25) was laid so as to cover the outer periphery of the propulsion tunnel (1).
[0010]
According to a fourth aspect of the present invention, in the third aspect of the present invention, the sheath tube (25) to which the backfilling device (65) is connected is firstly laid by means for laying the sheath tube (25). Of the backfilling device (65) that is pulled out to the side of the first shaft (6) and moves together with the sheath tube (25) to the first shaft (6). A backfill material (71) was filled to fill back the cut hole (32).
[0011]
According to a fifth aspect of the present invention, in the third aspect of the present invention, the sheathing tube (25) and the backfilling device (65) connected to the sheathing tube (25) by the laying means (10). 1 to the side of the first shaft (6), and the casing tubes (27) constituting the sheath tube (25) are cut off one by one in the first shaft (6), and the separated casing tubes (27) and The backfilling device (65) was collected on the ground.
[0012]
Note that the reference numerals and the like in parentheses are for the purpose of comparison with the drawings, and are for convenience of understanding of the invention, and do not affect the scope of the claims. Absent.
[0013]
【The invention's effect】
According to the invention of claim 1, a sheath tube is laid on the outer periphery of the propulsion tunnel, the propulsion tubes constituting the propulsion tube row are removed one by one through the sheath tube, and after the propulsion tube row is removed, backfilling is performed. Since it is performed, the propulsion tunnel can be removed and backfilled without applying a traction force (compression force) to the propulsion pipe due to a frictional force acting between the ground and the propulsion pipe. Thus, a moderately aged propulsion tunnel can be removed and backfilled. In addition, the range in which the removal and backfilling method of the propulsion tunnel can be applied (the degree of deterioration of the propulsion tunnel) can be expanded.
[0014]
According to the second aspect of the present invention, since the cutting tube and the backfilling device are removably disposed at the tip of the sheath, the replacement operation thereof is easy, and the propulsion tunnel is removed and backfilled. Workability of work can be improved.
[0015]
According to the invention as set forth in claim 3, since the sheath is laid in the excavation hole while excavating the outer periphery of the propulsion tunnel, it is possible to lay the sheath without applying a large load to the propulsion tunnel. it can. Therefore, the applicable range of the removal and backfilling method of the propulsion tunnel according to the present invention can be expanded.
[0016]
According to the fourth aspect of the present invention, the backfilling device is moved to the first shaft side by pulling the high strength sheath or tube, so that the backfilling device can be reliably moved and the workability is improved. Can be done.
[0017]
According to the invention as set forth in claim 5, the sheath tube is pulled and the sheath tube and the backfilling device connected to the sheath tube are moved into the first shaft, and the sheath tube is formed in the first shaft. Since the casing tube is cut off and collected on the ground, the sheath tube and the backfill device can be reliably moved to the first shaft and collected on the ground.
[0018]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0019]
FIGS. 1 to 9 show an example of an embodiment of the present invention. FIG. 1 is a process diagram showing an example of a shaft forming process of a removal and backfill method of a propulsion tunnel according to the present invention, and FIG. FIG. 3 is a process diagram showing an example of a sheath pipe laying process of the removal and backfill method of the propulsion tunnel according to the present invention, and FIG. 3 is a process diagram showing an example of a propulsion tube separating process of the removal and backfill method of the propulsion tunnel according to the present invention. FIG. 4 is a process diagram showing an example of a propulsion pipe removal process of the propulsion tunnel removal and backfill method according to the present invention, and FIG. 5 is a connection process of a backfill device of the propulsion tunnel removal and backfill method according to the present invention. FIG. 6 is a process diagram showing an example of the process, and FIG. 6 is a process diagram showing an example of a backfilling process of the removal and backfill method of the propulsion tunnel according to the present invention. FIG. 7 is a process of removing and backfilling the propulsion tunnel according to the present invention. Extension showing an example of FIG, 8, A-A arrow view enlarged view of FIG. 2, FIG. 9 is an enlarged view showing an example of alignment tool.
[0020]
As shown in FIGS. 1 to 4 and 7, the existing propulsion tunnel 1 to be removed includes a plurality of propulsion pipes 3 connected in series to form a propulsion pipe row 2. In addition, the length L1 of each propulsion pipe 3 constituting the propulsion tunnel 1 (propulsion pipe row 2) is formed, for example, at 2.43 m.
[0021]
The apparatus used for removing and backfilling the propulsion tunnel 1 according to the present invention is configured to swing-press the sheath 25 into the ground 5 in which the propulsion tunnel 1 is buried, excavate the outer periphery of the propulsion tunnel 1, and The oscillating all-casing excavator 10 (see FIGS. 2, 4, 5, and 6) as a laying means for laying the pipe 25 matches the axial center CT1 of the propulsion tunnel 1 and the sheath pipe 25 during excavation. A centering device 35 (see FIGS. 7, 8 and 9) and a stop plate device for preventing water or earth and sand from entering the sheath tube 25 from the gap between the propulsion tunnel 1 and the sheath tube 25. 45 (see FIGS. 7 and 8), a ring support device 50 (see FIGS. 7 and 8) for supporting the propulsion tunnel 1 (propulsion pipe 3) from the inside during excavation, and preventing breakage thereof, and a propulsion pipe row 2 When the propulsion pipe 3 is separated from the A separating device 55 (see FIG. 3), a self-propelled vehicle 21 (see FIGS. 2, 3 and 4) for separating and transporting the propulsion tube 3, and filling the cutting hole 32 from which the propulsion tunnel 1 has been removed. And a back-filling device 65 (see FIGS. 5 and 6) for performing back-up.
[0022]
Although not shown, a water supply device for supplying water to the excavation unit through the water supply pipe 31 (see FIG. 2), and water supplied from the water supply device to the excavation unit and excavated earth and sand are supplied to the end plate device 45. A suction device that discharges the ground through the connected earth discharging pipe 48 (see FIGS. 2, 7, and 8), and a backfill material in the drilled hole 32 through a backfill material supply pipe 62 (see FIG. 6). The backfill material supply device to be press-fitted, the all-casing excavator 10, the sheath tube 25, the propulsion tube 3, the aligning device 35, the end plate device 45, the ring support device 50, the separating device 55, the self-propelled carriage 21, and the backfill device 65. It is equipped with a crane for supplying and removing the equipment.
[0023]
As shown in FIG. 2, the oscillating all-casing excavator 10 includes a driving unit 10a, a sheath tube 25 driven by the driving unit 10a, excavating and propelling around the propulsion tunnel 1, and a driving unit 10a. On the other hand, it has a tube receiving stand 20 and a receiving stand 63 for transferring the sheath tube 25, the propulsion tube 3, and the backfilling device 65.
[0024]
A drive unit 10a of the all-casing excavator 10 is arranged so as to be swingable about an axis CT1 of the propulsion tunnel 1 and has an annular shape that detachably holds an outer periphery of the sheath 25 passing through the axis. A chuck 16 is provided. The chuck 16 is arranged on a predetermined circumference centered on the axis CT1 of the propulsion tunnel 1 at predetermined intervals in the circumferential direction so as to be movable in a direction parallel to the axis CT1. It is fixed to a plurality of press-fit frames 15.
[0025]
A swinging jack 17 connected to the hydraulic pressure supply device 12 is connected to the outer periphery of the chuck 16, and the chuck 16 is swingably driven about the axis CT <b> 1 by the swinging jack 17. Further, each of the press-fitting frames 15 is disposed on the end face 11a of the base 11 so as to be swingable in a tangential direction of a circumference around the axis CT1 of the propulsion pipe row 2, and pressurized oil from the hydraulic device 12 is provided. A plurality of press-fit jacks 13 connected to be freely supplied are swingably connected via, for example, spherical bearings (not shown), and each press-fit jack 15 causes each press-fit frame 15 to be connected to the shaft center CT1. It is driven to move in parallel directions.
[0026]
That is, the press-in jack 13 moves the chuck 16 in the direction of the axis CT1 via the press-in frame 15. Further, the swinging jack 17 causes the chuck 16 to reciprocate (swing) at a predetermined angle around the axis CT1.
[0027]
A support base (not shown) is disposed on the pipe support base 20. When the sheath tube 25 and the backfilling device 65 are mounted on the support base, the sheath tube 25, the backfilling device 65, and the It supports so that each axis CT1 may correspond. In addition, the tube receiving stand 20 has an origin position D (a position indicated by a solid line in FIG. 2) set so that the axis of the propelled tunnel 1 and the sheathed tube 25 mounted thereon coincide with each other. It is possible to move in the direction of arrow X (direction of axis CT1) between operation positions E (positions indicated by dashed lines in FIG. 2) at which connection and disconnection are performed. When the propulsion tube 3 to be removed is mounted, the original position D and the transfer position F where the propulsion tube 3 can move smoothly between the sheath tube 25 and the tube receiving gantry 20 (two points in FIG. 2). (Positions shown by chain lines) in the directions of arrows X and Z.
[0028]
As shown in FIG. 2, the sheath tube 25 is mounted at the forefront of the sheath tube 25, and is oscillated by the drive unit 10 a to excavate the outer periphery of the propulsion tunnel 1. A plurality of casing tubes 27 are connected to the rear end of the advance tube 26 and cover the outer periphery of the propulsion tunnel 1 after the propulsion tube 3 has been removed. The length L2 of the cutting tube 26 is 3 m, and the lengths L3 and L4 of the casing tube 27 are 2 m and 3 m. In addition, a 3 m tube and a 2 m tube including the cutting tube 26 are alternately used. That is, for example, if a 2 m casing tube 27 is connected after a 3 m cutting tube 26, the length becomes 5 m, which is approximately 4.86 m (2.43 m × 2), which is approximately the length of two propulsion tubes 3. .
[0029]
A plurality of cutter bits 28 are fixed to the tip portion 26a of the cutting tube 26 at predetermined intervals. A connecting portion 26b for connecting a subsequent casing tube 27 is formed at the rear end of the cutting tube 26. Further, a connecting portion 27a for connecting to the cutting tube 26 or the rear end of the preceding casing tube 27 is formed at the front end of each casing tube 27, and the subsequent casing tube 27 is formed at the rear end. Is formed.
[0030]
As shown in FIG. 8, a water supply hole 30 parallel to the axis CT1 is formed in the cutting tube 26 from its rear end to its front end. A water supply pipe 31 (see FIG. 2) drawn from the reaching shaft 7 (see FIG. 1) is connected to a rear end of the water supply hole 30. A cutter bit 28 is attached through the inside of the cutting tube 26. Water is supplied to the tip.
[0031]
As shown in FIG. 2, the connection between the cutting tube 26 and the casing tube 27, and the connection between the casing tube 27 and the casing tube 27 are, as shown in FIG. This is performed in a state where the press-fit frame 15 protrudes toward the starting shaft 6 from the end face.
[0032]
The connection is performed by fitting the connection portion 27a of the subsequent casing tube 27 to the connection portion 26b or 27b of the preceding grinding tube 26 or the casing tube 27, and connecting the connection portions 26b and 27a or the connection portions 27b and 27a. This is performed by driving a lock pin or the like into the through hole. Note that a putty or the like may be applied to each connection portion to form a seal portion for preventing intrusion of water or the like.
[0033]
A self-propelled carriage 21 is movably supported on the tube receiving stand 20. The self-propelled carriage 21 moves along the axis CT1 not only on the tube receiving stand 20 but also in the sheath tube 25, separates the propulsion tube 3 from the propulsion tube row 2, and separates the propulsion tube. 3 is carried out. As shown in FIG. 3, a connection bracket 22 and a tow rod 23 are arranged at one end (the end on the side facing the propulsion tunnel 1) of the self-propelled carriage 21.
[0034]
As shown in FIGS. 7 and 8, at the end of the propulsion pipe 3 on the side of the starting shaft 6 (see FIGS. 1 and 2), a centering device 35, a sprocket device 45, and a ring support device 50 are respectively provided. It is arranged detachably.
[0035]
As shown in FIG. 9, the centering device 35 includes a U-shaped bracket 36 fitted to the end of the propulsion pipe 3, a ball seat 37 fixed to the bracket 36, and a ball seat 37 fixed to the ball seat 37. The cutting tube 26 has a housing 38 in which a through hole 38a is formed on a surface opposing the inner peripheral surface 26c. In a space surrounded by the ball seat 37 and the housing 38, a steel ball 41 is supported rotatably so that a part thereof projects from the pipe through hole 38a. A dust seal 40 is fixed to an inner peripheral surface of the through hole 38 a of the housing 38 so as to cover a gap between the through hole 38 a and the steel ball 41.
[0036]
The three aligning devices 35 are arranged at an end of the propulsion tube 3 at a predetermined interval, and cut the propulsion tube 3 so that the axis of the cutting tube 26 coincides with the axis CT1 of the propulsion tunnel 1. The position of the advance tube 26 is regulated. The centering device 35 can also serve as a transfer means (wheel) by being attached to the front and rear ends of the propulsion tube 3 when the propulsion tube 3 is transferred to the starting shaft 6.
[0037]
As shown in FIG. 8, the end frame device 45 is fixed to an end surface of the propulsion tube 3 and is divided into four divided end plates 46a, 46b, 46c protruding toward an inner peripheral surface 26c of the cutting tube 26. 46d, and rubber packing 47 (see FIG. 7) for filling a gap between the end plates 46a, 46b, 46c, 46d and the inner peripheral surface 26c of the cutting tube 26.
[0038]
As shown in FIGS. 7 and 8, an earth discharging pipe 48 drawn from the reaching shaft 7 (see FIG. 1) is connected to the end plate 46c. The discharging pipe 48 is connected to a suction device (not shown) arranged outside the reaching shaft 7. Then, the earth and sand excavated by the cutting tube 26 and mixed with the water are sucked and discharged.
[0039]
As shown in FIGS. 7 and 8, the ring support device 50 includes a pair of support members 51, 51 having an arcuate surface 51 a contacting the inner peripheral surface 3 b of the propulsion pipe 3, and the support members 51, 51. And a pair of interval adjusting members 52 (for example, turnbuckles, double-threaded bolts, etc.) that are movably connected to each other in the direction of approaching and separating from each other.
[0040]
As shown in FIG. 3, a separating device 55 is disposed at a separation portion of the propulsion pipe 3 of the propulsion pipe row 2. The separating device 55 has a rail 57 supported by a plurality of support fittings 56 which are removably fitted into the lubricating material injection holes 3a of the propulsion tubes 3 remaining on the propulsion tube row 2 side. The rail 57 supports a trolley 58 that is movable in the direction of the arrow X along the rail 57. The trolley 58 is fixed with a suspending fitting 60 which is detachably fitted to the lubricating material injection hole 3a on the propulsion pipe row 2 side of the propulsion pipe 3 to be separated. In addition, a suspension fitting 60 for connecting the tow rod 23 is also attached to the lubricating material injection hole 3a on the self-propelled carriage 21 side of the propulsion pipe 3 to be separated.
[0041]
As shown in FIG. 5, the receiving pedestal 63 on the arrival shaft 7 side is provided with the cutting tube 26 (see FIG. 1) or the backfilling device 65 when the backing device 65 is placed on the receiving pedestal 63. The axis CT1 and the axis CT1 of the backfilling device 65 are supported so as to coincide with the axis CT1 of the sheath 25 (propulsion tunnel 1).
[0042]
The backfilling device 65 includes a cylindrical outer shell 66 having a connection portion 66b formed at one end, a plurality of partition jacks 67 arranged at predetermined intervals along the inner peripheral surface of the outer shell 66, An injection port 68a for a backfill material is formed so as to close the opening 66a of the shell 66, and a tail partition wall 68 supported by the partition jack 67 and a hydraulic pressure supply for supplying hydraulic pressure to the partition jack 67 It has a device 70. The inlet 68a is connected to a backfill material supply device (not shown) arranged outside the start shaft 6.
[0043]
The removal and backfilling of the propulsion tunnel according to the present embodiment is performed as follows. First, as shown in FIG. 1, a starting shaft (first shaft) 6 and a reaching shaft (second shaft) 7 are formed at both ends of the propulsion tunnel 1 to be removed. Then, the starting shaft 6a and the reaching shaft 7a are formed at positions where the starting shaft 6 and the reaching shaft 7 are in contact with the propulsion tunnel 1. Note that the starting shaft 6 and the reaching shaft 7 may be formed when the propulsion tunnel 1 is laid, and thereafter, the shaft used as a manhole for maintenance may be used.
[0044]
As shown in FIG. 2, an all-casing excavator 10 and a pipe receiving stand 20 are installed in the starting shaft 6. The base 11 of the all-casing excavator 10 is attached to the starting well 6a such that the axis of the chuck 16 coincides with the axis CT1 of the propulsion tunnel 1. Further, as described above, when the cutting tube 26 and the casing tube 27 are placed at the origin position D as described above, the axes of the cutting tube 26 and the casing tube 27 are aligned with the propulsion tunnel 1. It is installed on the bottom surface of the starting shaft 6 so as to coincide with the axis CT1.
[0045]
As shown in FIG. 5, the receiving shaft 63 is installed in the reaching shaft 7. The pedestal 63 is installed on the bottom surface of the reaching shaft 7 such that when the cutting tube 26 and the backfilling device 65 are placed, their axes coincide with the axis CT1 of the sheath tube 25 (propulsion tunnel 1). I do. Further, the water supply pipe 31 connected to a water supply device (not shown) installed outside the arrival shaft 7 and the discharging pipe 48 connected to the suction device are started from the arrival shaft 7 through the propulsion tunnel 1 as shown in FIG. Toward the shaft 6, the pipe is extended while adding a pipe having substantially the same length as the propulsion pipe 3 (2.43m).
[0046]
The cutting tube 26 is hung on the tube receiving stand 20 of the starting shaft 6. With the cutting tube 26 placed on the pipe receiving stand 20, the press-in jack 13 of the all-casing excavator 10 is extended, and the press-in frame 15 is fitted around the outer periphery of the cutting tube 26. At the same time, the pipe gantry 20 is moved to the starting well 6a side, and inserted so that the tip of the cutting tube 26 penetrates the chuck 16 and protrudes toward the starting well 6a. Then, the grinding tube 26 is fixed by the chuck 16.
[0047]
In this state, the press-in jack 13 is contracted and the swinging jack 17 is operated. Then, the chuck 16 moves to the starting wellhead 6a side, presses the cutter bit 28 fixed to the tip of the cutting tube 26 against the starting wellhead 6a, and swings around the axis CT1. The starting wellhead 6a is excavated by the swinging and pressing force of the cutter bit 28. When the cutter bit 28 of the cutting tube 26 penetrates the starting well 6a, the tip of the cutting tube 26 is propelled in the direction of the propulsion tunnel 1, that is, in the direction of arrow A, so as to surround the outer periphery of the propulsion pipe 3. As a result, excavation of the ground 5 around the propulsion pipe 3 is started.
[0048]
When the excavation by the excavation tube 26 is excavated to a predetermined depth (a depth at which the centering device 35 and the end plate device 45 can be mounted, for example, about 500 mm), the press-in jack 13 and the oscillating jack 17 are temporarily stopped. Let it. Then, the ring support device 50, the centering device 35, and the end plate device 45 are attached to the end of the propulsion pipe 3 exposed in the cutting tube 26.
[0049]
As shown in FIGS. 7 and 8, the ring support device 50 in which the distance between the support members 51, 51 is reduced is inserted into the propulsion pipe 3, and the space adjusting member 52 is operated to operate the circular arc surface of the support member 51. 51a is brought into contact with the inner peripheral surface 3c of the propulsion pipe 3. Next, as shown in FIG. 9, the bracket 36 of the centering device 35 is attached to the end of the propulsion pipe 3, and the steel ball 41 is positioned so as to correspond to the support member 51 of the ring support device 50. Fix with a fixing member that does not.
[0050]
Further, as shown in FIGS. 7 and 8, the end plates 46a, 46b, 46c and 46d are attached to the end face of the propulsion pipe 3 via a sealing member such as rubber packing. Further, a rubber packing 47 is arranged in a gap between the inner peripheral surface 26c of the cutting tube 26 and each of the end plates 46a to 46d. Then, as shown in FIG. 2, the drain pipe 48 is connected to the end plate 46c, and the water supply pipe 31 is connected to the water supply hole 30 of the cutting tube 26 (see FIG. 8).
[0051]
Water is supplied from a water supply device (not shown) while sucking earth and sand in the excavation space surrounded by the ground 2, the propulsion pipe 3, the end plates 46a to 46d, and the inner peripheral surface 26a of the milling tube 26 by a suction device (not shown). Water is supplied to the excavation part through the pipe 31 and the water supply hole 30.
[0052]
In this state, the press-in jack 13 and the swinging jack 17 are operated to restart the excavation. In addition, since the earth and sand generated by the excavation are relatively fine particles, the earth and the sand can be discharged together with the water supplied to the excavation portion by sucking the soil with the suction device. The propulsion tube 3 receives a compressive force from the cutting tube 26 via the adjusting device 35, but is deformed by the compressive force because the inner peripheral surface 3 b is supported by the ring support device 50. No damage can be prevented.
[0053]
The moving distance of the press-fitting frame 15 by the press-fitting jack 13, that is, the moving distance of the cutting tube 26 is set by the stroke of the press-fitting jack 13, and is considerably smaller than the length of the cutting tube 26. Therefore, when the cutting tube 26 moves by the stroke of the press-in jack 13, the fixing of the cutting tube 26 by the chuck 16 is released, the press-in jack 13 is extended, and the chuck 16 is retracted in the direction of arrow B in FIG. Then, after the grinding tube 26 is fixed again by the chuck 16, the press-in jack 13 and the swinging jack 17 are operated to restart the excavation.
[0054]
This operation is repeated, and as shown by a two-dot chain line in FIG. 7, when the tip of the cutting tube 26 is excavated to a predetermined position of the propulsion pipe 3 adjacent to the propulsion pipe 3 to be removed, the press-in jack 13 and the rocking jack 13 are swung. The moving jack 17 is stopped, and the excavation is stopped. The water supply from the water supply pipe 31 is stopped, and after a predetermined time has elapsed, the suction of the discharging pipe 48 is stopped. The suction time after the water supply is stopped is the time required to discharge water and soil remaining in the excavation space surrounded by the ground 2, the propulsion pipe 3, the end plates 46a to 46d, and the inner peripheral surface 26c of the cutting tube 26. I do.
[0055]
When the suction of the earth and sand from the excavation space by the discharging pipe 48 is completed, the worker moves into the cutting tube 26, first removes the water supply pipe 31 from the cutting tube 26, and removes the discharging pipe 48 from the end plate 46c. Next, the end plates 46a to 46d are removed from the propulsion pipe 3. Then, the end plates 46a to 46d are removed to the starting shaft 6.
[0056]
As shown in FIG. 3, the separating device 55 is carried in, the support fitting 56 is attached to the lubrication hole 3 a of the propulsion pipe 3 remaining on the propulsion pipe row 2, and the rail 57 is fixed to the support fitting 56. A hanging member 60 is connected to a trolley 57 movably supported by the rail 57, and the hanging member 60 is attached to a lubricating material injection hole 3a of the propulsion pipe 3 from which one end of the hanging member 60 is cut off. Also, a hanging metal fitting 60 for towing is attached to the other lubrication hole 3a of the propulsion pipe 3 to be cut off.
[0057]
Then, the pipe receiving stand 20 is moved to the transfer position. F To move the self-propelled carriage 21 from above the tube receiving gantry 20 into the cutting tube 26. Then, the bracket 22 of the self-propelled carriage 21 and the hanging metal fitting 60 for towing are connected by the towing rod 23. In this state, when the self-propelled carriage 21 is moved in the direction of the arrow X1 (toward the starting shaft 6), the propulsion pipe 3 to be cut off is pulled in the direction of the arrow X1 shown in FIG. Disconnected from 2.
[0058]
At this time, the end of the separated propulsion pipe 3 on the propulsion pipe row 2 side (the reaching shaft 7 side) is suspended by the trolley 58 via the suspension fitting 60, and therefore does not drop. In this state, two aligning devices 35 are mounted at predetermined intervals as transport wheels below the end of the propulsion pipe 3 on the separated side (propulsion pipe row 2 side).
[0059]
As shown in FIG. 4, the trolley 58 and the hanging bracket 60 are separated, and the self-propelled truck 21 is caused to travel in the direction of the arrow X <b> 1, and the separated propulsion tube 3 is placed on the tube receiving cradle 20 as indicated by a two-dot chain line. Transport. When the propulsion tube 3 is carried out onto the tube gantry 20, the tube gantry 20 returns to the origin position D. Further, the towing rod 23 connecting the self-propelled carriage 21 and the propulsion pipe 3 is disconnected.
[0060]
The propulsion pipe 3 carried out on the pipe receiving stand 20 is carried out to the ground by a crane (not shown) arranged outside the starting shaft 6 and removed. Note that the centering device 35 and the suspension fitting 60 attached to the propulsion pipe 3 may be removed in the starting shaft 6 or may be removed after being removed from the starting shaft 6.
[0061]
Further, the disconnecting device 55 installed on the propulsion pipe 3 at the end of the propulsion pipe row 2 on the start shaft 6 side is removed from the propulsion tube 3 and carried out to the start shaft 6 side. The separating device 55 may be stored while being detached from the propulsion pipe 3 and pushed into the propulsion pipe row 2.
[0062]
On the other hand, on the reaching shaft 7 side, the water supply pipe 31 for one propulsion pipe 3 and the discharge pipe 48 are separated. The water supply pipe 31 and the discharge pipe 48 that have been separated are carried out of the reaching shaft 7 by a crane or the like installed outside the reaching shaft 7.
[0063]
In this state, as shown in FIGS. 7 and 8, the same operation as described above is performed, and the ring support device 50, the centering device 35, and the end plate device are attached to the end of the propulsion pipe 3 exposed in the cutting tube 26. Attach 45. Then, the drain pipe 48 is connected to the end plate 46c, and the water supply pipe 31 is connected to the water supply hole 30 of the cutting tube 26 as shown in FIG.
[0064]
As shown in FIG. 2, after the propulsion pipe 3 is removed from the starting shaft 6, the casing tube 27 is hung on the pipe receiving stand 20. Then, the tube stand 20 is moved to the operation position. E Then, the connecting portion 27a at the front end of the casing tube 27 is fitted to the connecting portion 26b at the rear end of the cutting tube 26. The cutting tube 26 and the casing tube 27 are connected by driving a lock pin (not shown) into through holes formed in the connection portions 26b and 27a. Then, putty or the like for waterproof sealing is applied to the connection portion 26b of the cutting tube 26 and the connection portion 27a of the casing tube 27, and the connection operation is completed.
[0065]
By repeating such an operation, all the propulsion tubes 3 forming the propulsion tube row 2 are removed one by one. After the cutting tube 26 reaches the arrival shaft 7, the last propulsion pipe 3 is removed, and the removal of all the propulsion pipes 3 is completed. When the last propulsion pipe 3 is removed, a disconnecting device 55 is installed in the arrival shaft 7 so that one end of the propulsion tube 3 on the arrival shaft 7 side is supported.
[0066]
After the tip of the cutting tube 26 projects into the reaching shaft 7 and the last propulsion tube 3 is removed, the entire cutting tube 26 is sent into the starting shaft 7. At this time, the water supply pipe 31 and the discharge pipe 48 are all removed from the arrival shaft 7. Then, the cutting tube 26 is cut off from the subsequent casing tube 27, and is removed from the reaching shaft 7 by a crane or the like installed outside.
[0067]
The cutting tube 26 and the casing tube 27 are separated by removing the putty applied to the connection portions 26b and 27a, removing the lock pin, and moving the sheath tube 25 to the starting shaft 6 side. Can be.
[0068]
As shown in FIG. 5, the backfilling device 65 is suspended from the reaching shaft 7 by the crane or the like. When the backfilling device 65 is placed on the pedestal 63, the press-in jack 13 of the all-casing excavator 10 is operated to move the entire sheath tube 25 to the arrival shaft 7 side, and the connecting portion 27a of the casing tube 27 is connected. It is fitted to the connection part 66b of the backfilling device 65. In this state, similarly to the connection between the cutting tube 26 and the casing tube 27, a lock pin (not shown) is driven to connect the casing tube 27 and the backfilling device 65.
[0069]
After the backfilling device 65 is connected to one end of the sheath tube 25, the all casing excavator 10 is operated on the start shaft 6 side, and the sheath tube 25 is drawn into the start shaft 6. This operation releases the fixation of the casing tube 27 by the chuck 16 and contracts the press-fit jack 13. Then, the chuck 16 moves to the starting well 6a via the press-fit frame 15. In this state, the casing tube 27 is fixed by the chuck 16 and the press-fit jack 13 is extended. Then, the chuck 16 moves through the press-fit frame 16 in a direction away from the starting well 6a. At this time, the casing tube 27 fixed to the chuck 16 is drawn into the starting shaft 6 by the stroke of the press-fit jack 13.
[0070]
By repeating such an operation, the entire sheath pipe 25 can be moved to the starting shaft 6 side. Accordingly, the backfilling device 65 fixed to one end of the sheath tube 25 is drawn into the cutting hole 32 formed by the cutting tube 26. At this time, if the pipe gantry 20 is waiting at the operation position E, the casing tube 27 that has penetrated the starting well 6a is moved to and mounted on the pipe gantry 20.
[0071]
As shown in FIG. 6, when the backfilling device 65 is pulled into the drilled hole 32, the all-casing excavator 10 moves the chuck 16 to the starting well 6 a side by the same operation as described above. It waits with the tube 27 fixed. In this state, the casing tube 27 placed on the tube support 25 is separated from the sheath tube 25. This detaching operation is performed by removing the sealing material applied to the connection portions 27a and 27b of the casing tubes 27 connected before and after, removing the lock pin, releasing the connection of the connection portions 27a and 27b, and then removing the pipe. This is performed by moving the gantry 20 to the origin position D.
[0072]
The casing tube 27 separated from the sheath tube 25 is removed to the outside of the starting shaft 6 by a crane or the like installed outside the starting shaft 6. Further, a backfill material supply pipe 62 connected to a backfill material supply device (not shown) installed outside the starting shaft 6 is connected to the supply port 68 a of the tail partition wall 68 through the inside of the sheath tube 25.
[0073]
With the entire backfilling device 65 retracted into the drilled hole 32, the pedestal 63 is removed from the arrival shaft 7. Then, the partition jack 67 is extended by the hydraulic pressure supplied from the hydraulic pressure supply device 70, and the tail partition 68 is moved to the reaching shaft 7 side to cover the opening 66 a of the outer shell 66, and the upper opening of the reaching shaft 7 is opened. The backfilling material 71 is supplied from the part, and the reaching shaft 7 is temporarily backfilled. This temporary backfill may be performed to such an extent that the backfilling hole 32 is closed and the backfilling force is applied from the inside of the backfilling hole 32, as shown by a broken line in FIG. Further, instead of temporarily backfilling the reaching shaft 7, the reaching shaft 7a may be closed with the lid 72 as shown by a two-dot chain line.
[0074]
With the arrival well 7a closed, the backfill material 71 is injected at a predetermined pressure from the injection hole 68a of the tail bulkhead 68 into the space between the tail bulkhead 68 and the backfill material 71 (or the lid 72) put into the arrival shaft 7. Meanwhile, the hydraulic supply device 70 is operated to contract the partition jack 67, and the tail partition 68 is drawn into the outer shell 66. Then, the backfill material 71 (or the lid 72) in the reaching shaft 7 generated by the movement of the tail partition wall 68, the space formed by the outer shell 66 and the tail partition wall 68 are injected and filled with the backfill material 71.
[0075]
When the tail partition wall 68 moves to a predetermined position and stops, the press-in jack 13 of the all-casing excavator 10 operates to move the sheath tube 25 and the backfilling device 65 to the starting shaft 6 side. At the same time, the partition jack 67 of the backfilling device 65 operates in the reverse direction, and moves the tail partitioning wall 68 toward the reaching shaft 7 with respect to the backfilling device 65. Therefore, the tail partition wall 68 moves toward the arrival shaft 7 opposite to the backfilling device 65 moving toward the starting shaft 6, and thus is kept substantially stationary with respect to the ground 5.
[0076]
Then, the movement of the backfill material 71 that is filled in the outer shell 66 of the backfilling device 65 and moves to the starting shaft 6 side together with the backfilling device 65 is prevented by the tail partition wall 68. Therefore, the backfill material 71 filled in the outer shell 66 moves relatively toward the reaching shaft 7 by the movement of the backfill device 65, and is sent out from the outer shell 66 into the cutout hole 32. Will be. Then, the space where the outer shell 66 of the backfilling device 65 interposed between the cut hole 32 and the backfill material 71 at the time of the injection is filled.
[0077]
By repeating the above operation, the sheath tube 25 and the backfilling device 65 are moved toward the starting shaft 6 to perform backfilling in the cutting hole 32 and the casing tube 27 constituting the sheath tube 25 is removed. . Then, when the backfilling device 65 reaches the starting shaft 6 and is mounted on the tube receiving gantry 20, the backfilling of the drilled holes 32 ends.
[0078]
When the backfilling of the drilled hole 32 proceeds to some extent, the reaching shaft 7 in the temporary backfilled state is backfilled in parallel with the backfilling of the drilled hole 32. At this time, if the lid 72 is installed at the arrival shaft 7a of the arrival shaft 7, the lid 72 is removed and backfilled.
[0079]
In this way, when the backfilling device 65 is drawn to the position of the starting shaft 6 and pulled out into the starting shaft 6 by the chuck 16, the backfilling device 65 and the self-propelled vehicle are moved by a crane or the like installed outside the starting shaft 6. 21, the pipe gantry 20, and the all-casing excavator 10 are removed. Then, the backfill material 71 is supplied from the upper opening of the starting shaft 6 to backfill the starting shaft 6.
[0080]
According to the above embodiment, while the sheath pipe 25 is laid along the propulsion tunnel 1 to be removed, the propulsion pipes 3 constituting the propulsion tunnel 1 are removed one by one inside the sheath pipe 25. Therefore, it is possible to remove the propulsion pipe 3 without applying a large compressive force caused by a frictional force between the propulsion pipe 3 (the propulsion pipe row 2 composed of a plurality of propulsion pipes 3) and the ground 5 to the propulsion pipe 3. . Therefore, even a moderately deteriorated propulsion tunnel 1 can be reliably removed and backfilled.
[0081]
Further, since a large compressive force is not applied to the propulsion pipe 3 (propulsion pipe row 2) as in the above-described known technique, the range (deterioration degree) of the propulsion tunnel 1 to which the present method can be applied is expanded. can do.
[Brief description of the drawings]
FIG. 1 is a process diagram showing an example of a shaft formation process in a removal and backfill method of a propulsion tunnel according to the present invention.
FIG. 2 is a process diagram showing an example of a sheath pipe laying process of the removal and backfilling method of the propulsion tunnel according to the present invention.
FIG. 3 is a process diagram showing an example of a propulsion pipe separating process in the removal and backfilling method of the propulsion tunnel according to the present invention.
FIG. 4 is a process diagram showing an example of a propulsion tube removing process of the removing and backfilling method of the propulsion tunnel according to the present invention.
FIG. 5 is a process diagram showing an example of a connection process of the backfilling device in the propulsion tunnel removing / backfilling method according to the present invention.
FIG. 6 is a process diagram showing an example of a backfilling step of the removal and backfilling method of the propulsion tunnel according to the present invention.
FIG. 7 is an enlarged view showing an example of a cutting section in the removal and backfill method of the propulsion tunnel according to the present invention.
FIG. 8 is an enlarged view taken along the line AA of FIG. 2;
FIG. 9 is an enlarged view showing an example of the centering device.
[Explanation of symbols]
1 ... Propulsion tunnel
2 ... Propulsion pipe row
3. Propulsion pipe
6: First shaft (start shaft)
7: Second shaft (reach shaft)
10 Laying device (all casing excavator)
25 ... sheath tube
27 ... Casing tube
32 ... drilled hole
65 ... Backfilling device
71… Backfill material

Claims (5)

撤去すべき推進トンネルの両端に第1の立坑と第2の立坑を形成し、
前記第1の立坑から、撤去すべき推進トンネルを構成する推進管列の外周を覆うようにさや管を敷設しつつ、
前記さや管を通して、前記推進管列を構成する推進管を、一本ずつ前記第1の立坑へ搬送して撤去し、
前記第2の立坑に到達した前記さや管の先端に、埋め戻し装置を接続し、
前記埋め戻し装置を、前記第1の立坑側に向けてさや管で掘削した削進穴内を移動させながら、前記埋め戻し装置の後方に形成される空間に埋め戻し材を充填し、前記削進穴の埋め戻しを行う、ことを特徴とする、推進トンネルの撤去・埋め戻し工法。
Forming a first shaft and a second shaft at both ends of the propulsion tunnel to be removed,
From the first shaft, while laying a sheath tube so as to cover the outer periphery of the propulsion tube row constituting the propulsion tunnel to be removed,
Through the sheath tube, the propulsion pipes constituting the propulsion pipe row are transported one by one to the first shaft and removed.
A backfilling device is connected to the tip of the sheath tube that has reached the second shaft,
While moving the backfilling device in the drilled hole excavated by the sheath tube toward the first shaft, a backfilling material is filled in a space formed behind the backfilling device, and A method for removing and backfilling a propulsion tunnel, which performs backfilling of holes.
前記さや管の先端には、削進チューブが設けられており、該削進チューブにより前記推進トンネルの外周を掘削してさや管を敷設し、
該さや管が前記第2の立坑に到達した後、該第2の立坑内でさや管の先端から前記削進チューブを切り離すと共に、削進チューブが切り離されたさや管の先端に前記埋め戻し装置を連結し、
該さや管と埋め戻し装置を前記第1の立坑側へ移動させながら前記削進穴の埋め戻しを行う、ことを特徴とする、請求項1記載の推進トンネルの撤去・埋め戻し工法。
At the tip of the sheath tube, a cutting tube is provided, and the cutting tube digs the outer periphery of the propulsion tunnel to lay a sheath tube,
After the sheath tube reaches the second shaft, the cutting tube is separated from the tip of the sheath tube in the second shaft, and the backfilling device is mounted on the tip of the sheath tube from which the cutting tube is separated. Concatenate,
The method for removing and backfilling a propulsion tunnel according to claim 1, wherein backfilling of the drilled hole is performed while moving the sheath tube and the backfilling device toward the first shaft.
前記第1の立坑内に、前記さや管の敷設手段を設置し、
前記敷設手段により、前記さや管を揺動及び軸心方向に移動駆動することにより、前記第1の立坑側から、該さや管の先端で前記推進トンネル外周を削進させると共に、該さや管を該推進トンネルの外周を覆うように敷設する、ことを特徴とする、請求項1又は2記載の推進トンネルの撤去・埋め戻し工法。
In the first shaft, laying means for the sheath tube is installed,
The laying means swings and moves the sheath tube in the axial direction so that the outer periphery of the propulsion tunnel is cut from the first shaft side at the tip of the sheath tube, and the sheath tube is removed. 3. The method for removing and backfilling a propulsion tunnel according to claim 1, wherein the method is laid so as to cover an outer periphery of the propulsion tunnel.
前記埋め戻し装置が連結された前記さや管を、前記さや管の敷設手段により第1の立坑側に引き抜き、前記さや管と共に第1の立坑側へ移動する前記埋め戻し装置の前記第2の立坑側に形成される空間に埋め戻し材を充填して、前記削進穴を埋め戻す、ことを特徴とする、請求項3記載の推進トンネルの撤去・埋め戻し工法。The second shaft of the backfilling device, in which the sheath tube connected to the backfilling device is pulled out to the first shaft side by the sheathing tube laying means and moves to the first shaft side together with the sheathing tube. 4. The method for removing and backfilling a propulsion tunnel according to claim 3, wherein a backfill material is filled in a space formed on the side, and the cut hole is backfilled. 前記敷設手段によって、前記さや管と該さや管に連結された埋め戻し装置を前記第1の立坑側へ移動させ、該第1の立坑内で該さや管を構成するケーシングチューブを一本ずつ切離し、切り離されたケーシングチューブ及び埋め戻し装置を地上へ回収する、ことを特徴とする、請求項3記載の推進トンネルの撤去・埋め戻し工法。The laying means moves the sheath tube and the backfilling device connected to the sheath tube toward the first shaft, and separates the casing tubes constituting the sheath tube one by one in the first shaft. 4. The method for removing and backfilling a propulsion tunnel according to claim 3, wherein the separated casing tube and backfilling device are collected on the ground.
JP2002322917A 2002-11-06 2002-11-06 Promotion tunnel removal / backfill method Expired - Lifetime JP3815731B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002322917A JP3815731B2 (en) 2002-11-06 2002-11-06 Promotion tunnel removal / backfill method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002322917A JP3815731B2 (en) 2002-11-06 2002-11-06 Promotion tunnel removal / backfill method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2005037199A Division JP3822221B2 (en) 2005-02-15 2005-02-15 Propulsion tunnel removal / backfill equipment

Publications (2)

Publication Number Publication Date
JP2004156304A true JP2004156304A (en) 2004-06-03
JP3815731B2 JP3815731B2 (en) 2006-08-30

Family

ID=32802971

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002322917A Expired - Lifetime JP3815731B2 (en) 2002-11-06 2002-11-06 Promotion tunnel removal / backfill method

Country Status (1)

Country Link
JP (1) JP3815731B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009097296A (en) * 2007-10-19 2009-05-07 Sumitomo Mitsui Construction Co Ltd Removing and backfilling apparatus for propulsive tunnel
JP2009097295A (en) * 2007-10-19 2009-05-07 Sumitomo Mitsui Construction Co Ltd Removing and backfilling apparatus for propulsive tunnel
JP2009215790A (en) * 2008-03-11 2009-09-24 Sanwa Kizai Co Ltd Apparatus and construction method for removing and backfilling existing buried pipe
JP2010112037A (en) * 2008-11-05 2010-05-20 Uemura Giken Kogyo Kk Method for removing and restoring underground installation
KR101318667B1 (en) 2013-05-20 2013-10-16 삼강종합건설(주) The steel pipe propulsion system and method for the a movable reaction force member for agriculture waterway

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019940B (en) * 2015-07-24 2018-04-10 金川集团股份有限公司 A kind of method that damaged filling borehole reparation utilizes

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009097296A (en) * 2007-10-19 2009-05-07 Sumitomo Mitsui Construction Co Ltd Removing and backfilling apparatus for propulsive tunnel
JP2009097295A (en) * 2007-10-19 2009-05-07 Sumitomo Mitsui Construction Co Ltd Removing and backfilling apparatus for propulsive tunnel
JP2009215790A (en) * 2008-03-11 2009-09-24 Sanwa Kizai Co Ltd Apparatus and construction method for removing and backfilling existing buried pipe
JP2010112037A (en) * 2008-11-05 2010-05-20 Uemura Giken Kogyo Kk Method for removing and restoring underground installation
KR101318667B1 (en) 2013-05-20 2013-10-16 삼강종합건설(주) The steel pipe propulsion system and method for the a movable reaction force member for agriculture waterway

Also Published As

Publication number Publication date
JP3815731B2 (en) 2006-08-30

Similar Documents

Publication Publication Date Title
CN102889427B (en) Device, system and method for repairing underground pipeline of trenchless pneumatic cracking pipe
BRPI0711069A2 (en) process and device for installation without pipe trenches
JP3815731B2 (en) Promotion tunnel removal / backfill method
JP3822221B2 (en) Propulsion tunnel removal / backfill equipment
JP4931635B2 (en) How to reassemble the excavator
JP4160483B2 (en) Renewal method for existing pipelines
JP7357517B2 (en) Pipe construction method using propulsion method
CN111997649A (en) Tunnel-first post-station underground excavation station segment removal construction method and segment removal tool used by same
JPH05171641A (en) Pipe burying excavator
JP2000145396A (en) Ring cable insertion device for shield segment
JP3616898B2 (en) Method for joining underground structures using propulsion device
CN112709313B (en) Municipal sewage pipeline trenchless construction equipment and method
JP2020139364A (en) Reconstruction method of existing pipeline
KR101495593B1 (en) The excavation equipment
CN102677724A (en) Mechanical steel sleeve installation device and mechanical steel sleeve installation method
JP4409491B2 (en) Tunnel excavation method by tunnel excavator
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP3219746B2 (en) Existing tunnel removal method and shield tunneling machine for removal of existing tunnel
JP2599617B2 (en) Underwater tunnel construction method
JPH09279984A (en) Method for receiving shield machine into arrival shaft and receiving structure for shield machine in arrival shaft
JP4938618B2 (en) Removal tunnel backfilling device
JP4451016B2 (en) Tunnel laying replacement method
JP5072528B2 (en) Removal tunnel backfilling device
JP3703638B2 (en) Construction method of multi-strip pipes for underground cables such as electric power
JPS6280384A (en) Method of replacement construction of residual pipe

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060201

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060214

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060410

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060516

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060602

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3815731

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090616

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 6

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150616

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term