JP2004150181A - Work execution method for flexible plate - Google Patents

Work execution method for flexible plate Download PDF

Info

Publication number
JP2004150181A
JP2004150181A JP2002318044A JP2002318044A JP2004150181A JP 2004150181 A JP2004150181 A JP 2004150181A JP 2002318044 A JP2002318044 A JP 2002318044A JP 2002318044 A JP2002318044 A JP 2002318044A JP 2004150181 A JP2004150181 A JP 2004150181A
Authority
JP
Japan
Prior art keywords
reinforcing plate
plate
roadbed
fixing
flexible flat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002318044A
Other languages
Japanese (ja)
Inventor
Fukuji Okada
福貮 岡田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Keeper Co Ltd
Original Assignee
Keeper Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Keeper Co Ltd filed Critical Keeper Co Ltd
Priority to JP2002318044A priority Critical patent/JP2004150181A/en
Publication of JP2004150181A publication Critical patent/JP2004150181A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for quickly work executing a flexible plate. <P>SOLUTION: Since this work execution method for the flexible plate 1 comprises a process for laying reinforcing plates 2, 22 and 32 all over on a roadbed 5 of leveling the ground, a process for fixing the reinforcing plates 2, 22 and 32 and a process for fixing the flexible plate 1 to the reinforcing plates 2, 22 and 32, the flexible plate 1 can be immediately fixed after fixing the reinforcing plates 2, 22 and 32 to the roadbed 5 so that a construction period can be largely shortened. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明が属する技術分野】
本発明は、歩道、プールサイド、ベランダ、遊園地、運動公園等に用いられる可撓性平板の施工方法に関する。
【0002】
【従来の技術】
ゴム平板などの可撓性平板を道路脇の歩道・遊歩道等の路面に敷設する場合、砂利や砂などを敷詰めて、路盤を整備した上に、可撓性平板を直接敷詰めると、可撓性平板に十分な強度がないため、雨水等で路盤が局部的沈下現象を起こした場合、安全な歩行を妨げてしまう虞があった。このため、従来は、路盤の上にコンクリートを打設することで、可撓性平板を補強し、歩行の安全性を確保していた。
【0003】
【発明が解決しようとする課題】
しかしながら、コンクリートを打設する場合、コンクリートが完全に乾くまでに一週間近くかかっており、可撓性平板の施工が遅れ完成までに時間がかかっていた。
【0004】
本発明の目的はこのような従来の欠点を解消し、施工を迅速に行える方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上述の目的を達成するために請求項1記載の発明は、可撓性平板の施工方法であって、整地された路盤に補強プレートを敷詰める工程、補強プレートを固定する工程、可撓性平板を前記補強プレートに固定する工程を有することとした。したがって、請求項1記載の発明によれば、あらかじめ別の場所で作成した補強プレートを路盤に敷詰め固定するので、固定後すぐに可撓性平板を補強プレートに固定することができ、施工期間を大幅に短縮することができる。
【0006】
また、請求項2記載の発明は、補強プレートが透水性を有しているものとした。
したがって、請求項2記載の発明によれば、雨水が補強プレートに留まることがない。
【0007】
さらに、請求項3記載の発明は、前記補強プレートの内部に金属製の芯材を埋設し、全面に一様な貫通孔を設けることとした。これにより、補強プレートの強度を保つことができるので、補強プレートの厚みを薄くすることができ、さらに全面に一様な貫通孔を設けて、補強プレートを軽量化することができ、十分な透水性も確保することができる。
【0008】
また、請求項4記載の発明は、芯材に防錆処理を施すこととした。これにより、芯材が錆びにくくなり、補強プレートの耐久性が向上する。
【0009】
【発明の実施の形態】
本発明の実施の形態を、添付図面を参照しながら説明する。
【0010】
図1には、本願発明の施工方法を用いたものが記載されている。まず、最初に地面4に、砂利や砂を敷詰め、路盤5を固めながら、平坦を出す。次にコンクリート製の補強プレート2を路盤5の上に敷詰める。前記補強プレート2には、4隅に補強プレート2を路盤5に固定するための穴3が開けられており、前記穴3に杭6などを打ちこみ、路盤5に固定する。前記補強プレート2の材質は、人などが歩行した場合、凹まない程度の強度があれば何でも良く、例えば、アスファルト、木材、鉄板、樹脂等でも良い。前記補強プレート2を敷詰めた路盤5に固定した直後に、補強プレート2の上に可撓性平板1を接着剤等にて固定する。前記可撓性平板1は、透水性のあるゴム平板であることが好ましく、例えば、切削ゴム片と樹脂製バインダーとが混合されたパネル等が挙げられる。切削ゴムには、廃タイヤや、廃ゴム等を用いることが好ましい。
【0011】
図2は、本発明の第2の実施例であり、補強プレートを透水性の良い多孔質プレート12としている。図3は、本発明の第2の実施例である多孔質プレートを用いて可撓性平板を施工した実施例を示している。図3に示す施工方法も第1の実施例同様に、平坦化された路盤5の上に多孔質プレート12を敷詰め、固定した後、多孔質プレート12の上に可撓性平板を接着剤等にて固定する。
【0012】
図4には、本発明の第3の実施例である、補強プレートが記載されている。この補強プレート22は、コンクリートからなり、その内部には、網目状の金属製の芯材24が埋設されている。そして、補強プレート22の全面には、円形の貫通孔23が開けられており、路盤への固定、透水性、補強プレート22の軽量化を実現している。また、網目状の芯材24がある程度の補強を担保するので、補強プレート22の厚みを薄くすることができる。また、図5には、本発明の第4の実施例である、補強プレートが記載されている。第4の実施例の補強プレート32は、網目状の芯材34が補強プレート32の中に埋設されており、補強プレート32の全面には、矩形状の貫通孔33が設けられている。この第4の実施例も第3の実施例同様に、芯材34によって補強プレート32を補強しているので、補強プレートに全面に貫通孔33を設けることができ、軽量化および透水性に優れた補強プレートとすることができる。
【0013】
なお、本発明は上記実施例に限定されるものではなく、種々変更実施可能である。例えば補強プレートの路盤への固定は、補強プレートの4隅に穴を開け、そこに杭を打って行っているが、これに限定されず、例えば、補強プレートの裏面に突起等を形成して、路盤の中に食い込ませることで、路盤に固定しても良い。また、可撓性平板の補強プレートへの固定は、接着により行っているが、これに限定されず、例えば、可撓性平板の裏面に突起を設け、補強プレートに該突起と係合する溝を設けて、可撓性平板に設けた突起と補強プレートに設けた溝とを係合することで、補強プレートへ固定手段としても良い。また、平板は、あらかじめ形成されたパネル状のものに限らず、例えば、現場にて切削ゴム片と樹脂製のバインダーの混合物を補強プレートの上に敷設して、ローラーで固めることで平板を形成しても良い。この場合、ローラーで平板を形成すると同時に補強プレートへの固定が行うことができる。
【0014】
【発明の効果】
以上のように、本発明によれば、可撓性平板の施工方法を、整地された路盤に補強プレートを敷詰める工程、補強プレートを固定する工程、可撓性平板を前記補強プレートに固定する工程としたので、補強プレートを路盤に固定した後、直ちに可撓性平板を固定することができ、施工期間が大幅に短縮することが可能となる。また、補強プレートに透水性を持たせたので、雨水が補強プレートに留まることがなくない。さらに、前記補強プレートの内部に金属製の芯材を埋設することで、補強プレートの強度を保つことができ、補強プレートの厚みを薄くしたり、さらに全面に一様な貫通孔を設けることができる。これにより、補強プレートを軽量化することができると同時に十分な透水性を確保することができる。また、芯材に防錆処理を施すことで芯材が錆びにくくなり、補強プレートの耐久性が向上する。
【図面の簡単な説明】
【図1】本発明の第1の実施例である、補強プレートを用施工された路面の断面図。
【図2】本発明の第2の実施例である、補強プレートの斜視図
【図3】本発明の第2の実施例の補強プレートを用いて施工された路面の断面図
【図4】本発明の第3の実施例である補強プレートの正面図
【図5】本発明の第4の実施例である補強プレートの正面図
【符号の説明】
1 可撓性平板
2、22、32 補強プレート
3 穴
4 地面
5 路盤
6 杭
12 多孔質プレート
23、33 排水孔
24、34 芯材
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for constructing a flexible flat plate used for a sidewalk, a poolside, a veranda, an amusement park, a sports park, and the like.
[0002]
[Prior art]
When laying a flexible flat plate such as a rubber flat plate on the side of the road such as a sidewalk or promenade, it is possible to lay gravel or sand, maintain the roadbed, and then directly lay the flexible flat plate. Since the flexible flat plate does not have sufficient strength, when the roadbed causes a local sinking phenomenon due to rainwater or the like, there is a possibility that safe walking may be hindered. For this reason, conventionally, concrete has been cast on a roadbed to reinforce a flexible flat plate and secure walking safety.
[0003]
[Problems to be solved by the invention]
However, when casting concrete, it took nearly one week for the concrete to completely dry, and the construction of the flexible flat plate was delayed and it took time to complete.
[0004]
An object of the present invention is to solve such a conventional disadvantage and to provide a method capable of performing construction quickly.
[0005]
[Means for Solving the Problems]
To achieve the above object, an invention according to claim 1 is a method for constructing a flexible flat plate, comprising the steps of: laying a reinforcing plate on a leveled roadbed; fixing the reinforcing plate; Is fixed to the reinforcing plate. Therefore, according to the first aspect of the present invention, since the reinforcing plate prepared in another place in advance is fixed to the roadbed and fixed, the flexible flat plate can be fixed to the reinforcing plate immediately after fixing, and the construction period Can be greatly reduced.
[0006]
In the invention according to claim 2, the reinforcing plate has water permeability.
Therefore, according to the second aspect of the invention, rainwater does not stay on the reinforcing plate.
[0007]
Further, in the invention according to claim 3, a metal core is buried inside the reinforcing plate, and a uniform through hole is provided on the entire surface. As a result, the strength of the reinforcing plate can be maintained, so that the thickness of the reinforcing plate can be reduced, and furthermore, a uniform through hole is provided on the entire surface, so that the reinforcing plate can be reduced in weight. Nature can also be secured.
[0008]
Further, in the invention according to claim 4, the core material is subjected to rust prevention treatment. Thereby, the core material is less likely to rust, and the durability of the reinforcing plate is improved.
[0009]
BEST MODE FOR CARRYING OUT THE INVENTION
Embodiments of the present invention will be described with reference to the accompanying drawings.
[0010]
FIG. 1 shows an apparatus using the construction method of the present invention. First, gravel or sand is laid on the ground 4 and the roadbed 5 is flattened while hardening. Next, the reinforcing plate 2 made of concrete is laid on the roadbed 5. Holes 3 for fixing the reinforcing plate 2 to the roadbed 5 are formed at four corners of the reinforcing plate 2, and a stake 6 or the like is driven into the hole 3 to be fixed to the roadbed 5. The material of the reinforcing plate 2 may be any material as long as it has a strength not to be depressed when a person or the like walks. For example, asphalt, wood, iron plate, resin and the like may be used. Immediately after fixing the reinforcing plate 2 to the roadbed 5 on which the reinforcing plate 2 is laid, the flexible flat plate 1 is fixed on the reinforcing plate 2 with an adhesive or the like. The flexible flat plate 1 is preferably a rubber flat plate having water permeability, such as a panel in which a cut rubber piece and a resin binder are mixed. It is preferable to use a waste tire, a waste rubber, or the like as the cut rubber.
[0011]
FIG. 2 shows a second embodiment of the present invention, in which a reinforcing plate is a porous plate 12 having good water permeability. FIG. 3 shows an embodiment in which a flexible flat plate is constructed using a porous plate according to a second embodiment of the present invention. In the construction method shown in FIG. 3, similarly to the first embodiment, the porous plate 12 is spread over the flatbed roadbed 5, fixed, and then a flexible flat plate is bonded on the porous plate 12 with an adhesive. Fix with etc.
[0012]
FIG. 4 shows a reinforcing plate according to a third embodiment of the present invention. The reinforcing plate 22 is made of concrete, and has a mesh-shaped metal core 24 embedded therein. A circular through-hole 23 is formed on the entire surface of the reinforcing plate 22 to realize fixing to the roadbed, water permeability, and weight reduction of the reinforcing plate 22. Further, since the mesh-shaped core member 24 secures a certain degree of reinforcement, the thickness of the reinforcing plate 22 can be reduced. FIG. 5 shows a reinforcing plate according to a fourth embodiment of the present invention. In the reinforcing plate 32 of the fourth embodiment, a mesh-shaped core material 34 is embedded in the reinforcing plate 32, and a rectangular through hole 33 is provided on the entire surface of the reinforcing plate 32. In the fourth embodiment, as in the third embodiment, the reinforcing plate 32 is reinforced by the core material 34, so that the through-hole 33 can be provided on the entire surface of the reinforcing plate, and the weight and water permeability are excellent. Reinforcing plate.
[0013]
The present invention is not limited to the above embodiment, but can be variously modified. For example, the fixing of the reinforcing plate to the roadbed is performed by making holes in four corners of the reinforcing plate and hitting a stake therein, but is not limited thereto. It may be fixed to the roadbed by making it go into the roadbed. Further, the fixing of the flexible flat plate to the reinforcing plate is performed by bonding, but is not limited to this. May be provided, and the projection provided on the flexible flat plate may be engaged with the groove provided on the reinforcing plate, so as to serve as a fixing means to the reinforcing plate. In addition, the flat plate is not limited to a pre-formed panel, for example, a mixture of a cut rubber piece and a resin binder is laid on a reinforcing plate at the site, and the flat plate is formed by solidifying with a roller. You may. In this case, it is possible to form the flat plate with the rollers and simultaneously fix the flat plate to the reinforcing plate.
[0014]
【The invention's effect】
As described above, according to the present invention, the method of constructing a flexible flat plate includes the steps of laying a reinforcing plate on a leveled roadbed, fixing the reinforcing plate, and fixing the flexible flat plate to the reinforcing plate. Since the process is performed, the flexible flat plate can be fixed immediately after the reinforcing plate is fixed to the roadbed, and the construction period can be significantly reduced. In addition, since the reinforcing plate has water permeability, rainwater does not stay on the reinforcing plate. Further, by embedding a metal core material inside the reinforcing plate, the strength of the reinforcing plate can be maintained, the thickness of the reinforcing plate can be reduced, and a uniform through hole can be provided on the entire surface. it can. This makes it possible to reduce the weight of the reinforcing plate and at the same time ensure sufficient water permeability. In addition, by subjecting the core material to rust prevention treatment, the core material is less likely to rust, and the durability of the reinforcing plate is improved.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of a road surface according to a first embodiment of the present invention, on which a reinforcing plate is used.
FIG. 2 is a perspective view of a reinforcing plate according to a second embodiment of the present invention; FIG. 3 is a sectional view of a road surface constructed using the reinforcing plate of the second embodiment of the present invention; FIG. FIG. 5 is a front view of a reinforcing plate according to a third embodiment of the present invention. FIG. 5 is a front view of a reinforcing plate according to a fourth embodiment of the present invention.
DESCRIPTION OF SYMBOLS 1 Flexible flat plate 2, 22, 32 Reinforcement plate 3 Hole 4 Ground 5 Subbase 6 Pile 12 Porous plate 23, 33 Drainage hole 24, 34 Core material

Claims (4)

可撓性平板の施工方法であって、整地された路盤に補強プレートを敷詰める工程、補強プレートを固定する工程、可撓性平板を前記補強プレートに固定する工程を有することを特徴とする可撓性平板の施工方法。A method for constructing a flexible flat plate, comprising the steps of: laying a reinforcing plate on a leveled roadbed, fixing a reinforcing plate, and fixing a flexible flat plate to the reinforcing plate. Flexible plate construction method. 前記補強プレートが透水性を有していることを特徴とする請求項1記載の可撓性平板の施工方法2. The method according to claim 1, wherein the reinforcing plate has water permeability. 前記補強プレートは、内部に金属製の芯材を埋設し、全面に一様な貫通孔を設けたものであることを特徴とする請求項1または2記載の可撓性平板の施工方法。The method according to claim 1, wherein the reinforcing plate has a metal core embedded therein and a uniform through-hole provided on the entire surface. 前記芯材には、防錆処理が施されていることを特徴とする請求項3記載の可撓性平板の施工方法。4. The method according to claim 3, wherein the core material is subjected to a rust prevention treatment.
JP2002318044A 2002-10-31 2002-10-31 Work execution method for flexible plate Pending JP2004150181A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002318044A JP2004150181A (en) 2002-10-31 2002-10-31 Work execution method for flexible plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002318044A JP2004150181A (en) 2002-10-31 2002-10-31 Work execution method for flexible plate

Publications (1)

Publication Number Publication Date
JP2004150181A true JP2004150181A (en) 2004-05-27

Family

ID=32461287

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002318044A Pending JP2004150181A (en) 2002-10-31 2002-10-31 Work execution method for flexible plate

Country Status (1)

Country Link
JP (1) JP2004150181A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409244A (en) * 2019-08-23 2019-11-05 中国建筑第七工程局有限公司 A kind of prefabricated road deck of composite bearing and prefabricated pavement construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409244A (en) * 2019-08-23 2019-11-05 中国建筑第七工程局有限公司 A kind of prefabricated road deck of composite bearing and prefabricated pavement construction method

Similar Documents

Publication Publication Date Title
KR101996133B1 (en) Top topping construction method of underground tunnel structure
CN207259891U (en) Reinforcement of Soft Soil Subgrade structure
JP2005264718A (en) Ground foundation reinforcing structure
JP2004150181A (en) Work execution method for flexible plate
KR101961289B1 (en) Palm shell mat, and construction method of palm shell mat
KR101133427B1 (en) Constructing method of slim road pavement with high elasticity and strength using eco friendly water-tightness mega-polymer concrete
CN212582322U (en) Polyurethane-based permeable ecological road
JPH0534299B2 (en)
KR20090058178A (en) Method for installing an artificial turf
JP2782332B2 (en) Permeable pavement board
WO2020230474A1 (en) Water-permeable structure
JP3101756U (en) Sidewalk structure
JPH0892906A (en) Decorative board
JP4515677B2 (en) Artificial grass pavement method
JP4233470B2 (en) Water-permeable pavement and method for reinforcing water-permeable pavement
JP2000136502A (en) Permeable block and manufacture thereof
JP2000190313A (en) Manufacture of water permeable block and water permeable block
KR100556546B1 (en) Slope block building method to use soil nail and its manufacturing method
JP2002356807A (en) Outdoor playground
JPH0885906A (en) Structure of road pavement having water permeability
JP3086219U (en) Underground infiltration porous block with reinforcement abutment
JPH0672431B2 (en) Underground wall and its construction method
JPH0136962Y2 (en)
TWM254465U (en) Structure of environmentally friendly water permeable surface-layering soft mat
JPH04185820A (en) Foundation structure of building