JP2004068596A - Manhole repairing method - Google Patents
Manhole repairing method Download PDFInfo
- Publication number
- JP2004068596A JP2004068596A JP2003349490A JP2003349490A JP2004068596A JP 2004068596 A JP2004068596 A JP 2004068596A JP 2003349490 A JP2003349490 A JP 2003349490A JP 2003349490 A JP2003349490 A JP 2003349490A JP 2004068596 A JP2004068596 A JP 2004068596A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- replacement method
- filler
- frame replacement
- manhole cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Road Paving Structures (AREA)
- Road Repair (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
この発明は、電気、電信、ガス、及び上下水道系等におけるマンホールの補修方法に関する。 The present invention relates to a method for repairing manholes in electricity, telegraph, gas, water and sewage systems, and the like.
従来、電気、電信、ガス、及び上下水道系等におけるマンホール蓋/枠の取替え工事に際しては、平板状のカッター、コアカッター、等で四方形またはカット面がストレートな円版状に切断し、切断部を除去した後、補修部分に補修材を充填し、その後転圧機で転圧作業をして工事終了とするのが通例である。 Conventionally, when replacing manhole covers / frames in electricity, telegraph, gas, water and sewage systems, etc., cut into square plates or circular plates with a straight cut surface using a flat cutter, core cutter, etc. After the part is removed, the repaired part is filled with a repair material, and then the work is finished by compacting work using a rolling machine.
また、開示されている舗装路面開口工法では、「舗装路面を開口予定部の周囲に沿って切断すると共にその切断された柱状舗装版を引上げて取り外す工程を含み、柱状舗装版に1又は2以上のアンカーが埋設され、柱状舗装版は円形、または四角形に切断され、四角形の場合は少なくとも対向する二辺は深さ方向に先細りとなるように切断され」、と記載されている(例えば、特許文献1参照。)。
然しながら、上述の従来例では、四角形に切断する場合は勿論のこと、円形切断の場合でも、前者の場合は四隅と底部全縁に、後者の場合は底部全縁に角張った隅部が発生し(図4(b)参照)、補修材等の充填材を充填しても前記隅部に前記充填材が十分に行き渡らず空隙が生じ、切断部が略垂直な壁面となり、切断部側面の摩擦力のみで支持されているのでずれて沈下し易い為、路面に生じた隙間から雨水等が浸透し易く、沈下を助長し、事故の原因を誘起することとなる。 However, in the above-described conventional example, not only in the case of cutting into a quadrangle but also in the case of circular cutting, angular corners are generated at the four corners and the entire bottom edge in the former case, and at the entire bottom edge in the latter case. (See FIG. 4 (b).) Even when a filler such as a repair material is filled, the filler does not sufficiently spread to the corners to form a gap, the cut portion becomes a substantially vertical wall surface, and the friction on the side surface of the cut portion. Since it is supported only by force, it is easy to settle because it is displaced, so that rainwater or the like easily penetrates through a gap formed on the road surface, which promotes settlement and induces an accident.
また、四角形に切断する場合は、図4(b)に示すように4角部に余分なカットクロス部ができ、その分の補修も含まれることになる。 (4) In the case of cutting into a quadrangle, as shown in FIG. 4 (b), an extra cut cross portion is formed at the quadrangle, and repair for that amount is also included.
上述のように従来工法では、カットクロス部のような余分な補修工事が発生したり、補修工事の際に、後工程で転圧作業をしなければ、経時的に表層部及び路盤部が沈下し、路面に凹凸が発生する虞がある等の不都合な問題があった。 As described above, in the conventional method, extra repair work such as the cut cross section occurs, and if the compaction work is not performed in the post-process at the time of the repair work, the surface layer and the roadbed part will sink over time. However, there are inconveniences such as the possibility of unevenness on the road surface.
然も従来の充填材では、硬化時間も含めて工事期間が余り短縮できないという問題があり、更に騒音公害の点でも改善の余地がある、等々の問題がある。 Natural in a conventional filler, there can not be shortened remainder construction period, including curing time, further there is room for improvement in terms of noise pollution, there is a like problem.
本発明は、上述の状況に鑑みて成されたもので、予定されたマンホール蓋/枠の取替え工事に際して、工事範囲を最小限とし、工事工程及び工事期間を削減/短縮出来るマンホール補修方法を提供することを課題とする。 The present invention has been made in view of the above circumstances, upon replacement work of scheduled manhole cover / frame, the work range is minimized, providing the construction process and reduction / shortening can manhole repair methods construction period The task is to
本発明は、前記課題を解決するため、マンホール補修方法を次の(1)〜(3)のとおりに構成する。 According to the present invention , a manhole repair method is configured as described in the following (1) to (3) in order to solve the above problems.
(1)マンホール蓋のある路面に、該マンホール蓋と同心円で深さ方向に径が狭まる回転円弧状または球面状切り込みを入れる切り込み工程と、
前記切り込み工程で形成された切り込みと前記蓋を受ける蓋受枠との間にある舗装材および前記蓋受枠を除去する除去工程と、
前記除去工程で除去した蓋受枠のあとに新しい蓋受枠を設置する蓋受枠設置工程と、
前記蓋受枠設置工程で設置した蓋受枠と前記切り込みとの間の空間に、表面が前記路面と同じ高さになるまで舗装材を充填する充填工程と、
を備えたマンホール補修方法。
(1) on the road surface with a manhole cover, a step cut add rotation arcuate or spherical switching interrupt size in the depth direction in the manhole cover and concentric narrowing,
A removing step of removing the pavement material and the lid receiving frame between the notch formed in the cutting step and the lid receiving frame receiving the lid ,
A lid receiving frame setting step of installing a new lid receiving frame after the lid receiving frame removed in the removing step,
A filling step of filling a pavement material into a space between the lid receiving frame and the cut provided in the lid receiving frame setting step until the surface is at the same height as the road surface,
Ma Nhoru repair method with a.
(2)前記(1)記載のマンホール補修方法において、
前記新しい蓋受枠は高さ調整部付きアンカーボルトが付属するものであり、前記蓋受枠設置工程において、下桝の上面に、前記アンカーボルトを設置し該蓋受枠の高さを調整するマンホール補修方法。
(2) before SL (1) Manhole repair method according,
The new lid receiving frame are those height adjustment unit with the anchor bolt is included in the cover receiving frame installation process, the upper surface of the lower basins, Ma Nhoru repair to adjust the height of the installed lid receiving frame the anchor bolt How .
(3)前記(1)または(2)記載のマンホール補修方法において、
前記切り込み工程で、前記蓋受枠表面まで切り込むことを特徴とするマンホール補修方法。
(3) before SL (1) or (2) Manhole repair method according,
The manhole repairing method according to claim 1 , wherein in the cutting step, a cut is made up to a surface of the lid receiving frame .
本発明により、予定されたマンホール蓋/枠の取替え工事に際して、工事範囲を最小限とし、工事工程及び工事期間を削減/短縮出来るマンホール補修方法を提供することが出来る。 The present invention, upon replacement work of scheduled manhole cover / frame, the work range is minimized, it is possible to provide the construction process and reduction / short Chijimide comes manhole repair methods construction period.
以下本発明を実施するための最良の形態を、実施例により詳しく説明する。Hereinafter, the best mode for carrying out the present invention will be described in detail with reference to examples.
以下、実施例1である“マンホール補修方法”について説明する。 Hereinafter, the “manhole repair method” of the first embodiment will be described.
図1は、回転円弧状または球面状カッターを有する路面用カッター装置を用いて予定されたマンホール蓋/枠の周囲に回転円弧状または球面状に切り込みを入れた状況の一例を示す説明図、図2(a)は、切込みを入れて分離除去可能とした切断片を除去した後の状況の一例を示す断面説明図、(b)は、切断片の模式的外観斜視図、図3は、マンホール蓋/枠取替え後の最終工程施工状況の一例を示す詳細断面説明図、(a)は路盤材及び調整部材充填時の詳細断面説明図、(b)は表層材充填後の詳細断面説明図、図4は、本発明に係る本工法と従来から行われていた従来工法との比較説明図であり、(a)は本工法の回転円弧状(球面状)切断の場合、(b)は従来工法の四角形(四工程)切断、または円形切断の場合の例、図5(a)は、補強用鉄筋を網目状に配設した場合の状況を示す側断面図、(b)はA部拡大図である。 FIG. 1 is an explanatory view showing an example of a situation where a circular arc or spherical cut is made around a predetermined manhole cover / frame by using a road surface cutter device having a circular arc or spherical cutter. 2 (a) is a cross-sectional explanatory view showing an example of a situation after a cut piece has been cut and made detachable, and FIG. 2 (b) is a schematic external perspective view of the cut piece. FIG. 3 is a manhole. Detailed cross-sectional explanatory view showing an example of the final process construction status after lid / frame replacement, (a) is a detailed cross-sectional explanatory view when the roadbed material and the adjustment member are filled, (b) is a detailed cross-sectional explanatory view after filling the surface layer material, FIGS. 4A and 4B are comparative explanatory views of the present method according to the present invention and a conventional method which has been conventionally performed. FIG. 4A shows a case of a rotary arc (spherical) cutting of the present method, and FIG. Example of square (four process) cutting or circular cutting of the construction method, FIG. 5 ( ) Is a side sectional view showing a situation where the reinforcing rebar is disposed in a network form, (b) is an A-part enlarged view.
本実施例は、特開2001−295216号公報に開示の路面用カッター、または特願2002−60514号出願の路面用カッター装置を用いて施工した場合であって、切断面となる壁面を回転円弧状または球面状に、且つ必要最小限の範囲で切断施工が可能である。 The present embodiment is a case where the road surface cutter disclosed in Japanese Patent Application Laid-Open No. 2001-295216 or the road surface cutter device of Japanese Patent Application No. 2002-60514 is used, and the wall surface serving as a cutting surface is rotated by a rotating circle. Cutting work can be performed in an arc or spherical shape and in a minimum necessary range.
前記装置を用いて、予定されたマンホール蓋/枠の同心円上路面に所定深さの回転円弧状または球面状切り込み1を入れ、取替えを必要とする部分、例えば、蓋及び蓋受枠2′を交換し、切断片を分離除去した後の空間に、予め用意した、例えば、路盤材6となるカルシウム、サルフォ、アルミネート系等の金属系無収縮材を含有するモルタル類からなる自硬性を有する高流動性無収縮充填材を充填し、また路面の表層部に繊維質を含有する表層材8を、余分に盛り上げることをせず、既存の路面に合わせて仕上げればよい。
Using said device, a circular arc or spherical cut 1 of predetermined depth is made on the concentric road surface of the planned manhole cover / frame, and the parts requiring replacement, for example, the cover and the cover receiving frame 2 'are replaced. Then, in the space after the cut pieces are separated and removed, a self-hardening mortar made of a mortar containing a metal-based non-shrinkable material such as calcium, sulfo, or aluminate, which is prepared as the roadbed material 6, for example, is prepared in advance. The
以下、図面を参照して実施例について詳細に説明する。 Hereinafter, embodiments will be described in detail with reference to the drawings.
図1において、a 先ず、交換を必要とする蓋受枠2′の径dが654mmの場合、切断する直径Dは1000mmとし、予め用意した回転円弧状または球面状カッターを備えた路面用カッター装置の車輪角度を設定(ワンタッチ操作)し、装置を360°旋回して回転円弧状または球面状切り込み1を入れ(舗装切断)、b 次いで、図2(b)に示すように疑似円環状(ドーナツ状)の切断片を除去し、図2(a)に示すような疑似円環状(ドーナツ状)の空間を形成させ、旧い蓋受枠2′を取り外した後、下桝3の上面を清掃し、次に、c 高さ調整部付きアンカーボルト5(後施工型アンカーボルト)を設置し(図3(a)、(b)参照)、高さ調整し、新しい蓋受枠2、及び内型枠4を取り付ける。次に、d 路盤材6及び調整部材7を充填し、養生時間(約19分)経過後、e 表層材8を、例えば、厚み50mm(h)に充填し、そして仕上げ作業を行い、表層材8の養生時間約30分で実作業を終了する。
In FIG. 1, a First, when the diameter d of the lid receiving frame 2 'requiring replacement is 654 mm, the diameter D to be cut is 1000 mm, and a road surface cutter device provided with a rotating arc or spherical cutter prepared in advance is used. The wheel angle is set (one-touch operation), and the device is turned 360 ° to make a circular arc or spherical cut 1 (pavement cutting). B Then, as shown in FIG. 2) is removed to form a pseudo annular (doughnut-shaped) space as shown in FIG. 2 (a), the old lid receiving frame 2 'is removed, and the upper surface of the
本実施例では、実際の合計作業時間は2時間14分であった。 で は In this example, the actual total work time was 2 hours and 14 minutes.
路盤材6及び調整部材7は、前述したように、カルシウム、サルフォ、アルミネート系等の金属系無収縮材を含有するモルタル類からなる自硬性を有する高流動性無収縮充填材を使用している。
As described above, the roadbed material 6 and the adjusting
然も本工法では、補修材となる充填材は、短時間で所定強度に硬化するので、施工を開始してから完工するまで、所要の施工合計時間は3時間以内であり(季節及び環境条件によって多少変動あり)、作業時間を従来法と比較して略1/2以下に短縮することが出来る。 Of course, in this method, the filling material that becomes the repair material hardens to a predetermined strength in a short time, so the total required construction time from the start of construction to completion is within 3 hours (seasonal and environmental conditions). The operation time can be reduced to about 1/2 or less as compared with the conventional method.
尚、本工法の最大の特徴は、切断部の壁面を従来の様な柱状ではなく、回転円弧状または球面状切断部1aとすることが出来るので、図4(a)に示すように、補修材(充填材)が、球面状を形成する切断部の摩擦力に加えて求心方向支持力により、例えば、図4(a)に示すように、上方からの圧力、即ち車両等の荷重Pを受ければ受けるほど、充填材と切断部1aの密着性が高まり、従来法での柱状切断壁面のように隙間からの雨水の浸透等による補修部の沈下現象(図4(b)参照)等を防止出来、トラブルを回避して全く安全且つ迅速なマンホール蓋/枠取替え工事を行うことが出来る。 The greatest feature of this method is that the wall of the cut portion can be formed into a rotating arc-shaped or spherical cut portion 1a instead of a columnar shape as in the prior art. Therefore, as shown in FIG. As shown in FIG. 4 (a), for example, as shown in FIG. 4 (a), the material (filler) generates a pressure P from above, that is, a load P of a vehicle or the like, by the centripetal support force in addition to the frictional force of the cut portion forming a spherical shape. The more it is received, the more the adhesion between the filler and the cut portion 1a is increased, and the sinking phenomenon of the repaired portion due to rainwater permeation from a gap or the like (see FIG. 4 (b)) and the like, such as a columnar cut wall in the conventional method, etc. It is possible to perform manhole cover / frame replacement work completely safely and quickly by avoiding troubles and avoiding troubles.
(変形1)
前述の実施例1と異なる点は、高流動性無収縮充填材として、主として金属性骨材を含まない非金属系無収縮材を含むモルタル類を使用する点である。
( Modification 1)
Example 1 differs from the foregoing, a high fluidity non-shrink filler is that it uses a mortar compound containing mainly non-metallic non-shrink materials without metal aggregate.
(変形2)
前述の実施例1と異なる点は、高流動性無収縮充填材を充填する際に、補強用鉄筋を網目状に配設する点である。
( Modification 2)
The difference from the first embodiment is that reinforcing reinforcing bars are arranged in a mesh when filling the highly fluid non-shrinkable filler.
図5(a)、(b)に示すように、高流動性無収縮充填材となる路盤材の内部に所定太さの鉄筋を所定ピッチで網目状に配設することにより、万一周辺の路盤が崩壊しても、影響を受けず、安全を維持することが出来る。 As shown in FIGS. 5 (a) and 5 (b), by arranging reinforcing bars of a predetermined thickness in a mesh at a predetermined pitch inside a roadbed material to be a high-flow non-shrinkage filler, the vicinity of Even if the roadbed collapses, it is not affected and can maintain safety.
尚、前述の実施例1では、高流動性無収縮充填材を指定して用いたが、本工法において、転圧もしくは転圧締め固め工程の必要の無い材料、または手作業程度の加圧操作で済む材料であれば良く、限定するものではない。 In Example 1 described above, it is used to specify the high flow non-shrink filler, in this method, unnecessary material compaction or rolling clamping solidifying step or manually about pressurization operation, Any material can be used, and there is no limitation.
1 回転円弧状または球面状切り込み
1a 回転円弧状または球面状切断部
2、2′ 蓋受枠
3 下桝
4 内型枠
5 高さ調整部付きアンカーボルト(後施工形アンカーボルト)
6 路盤材
7 調整部材
8 表層材
1 Rotating circular or spherical cut 1a Rotating circular or
6
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003349490A JP2004068596A (en) | 2002-04-26 | 2003-10-08 | Manhole repairing method |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002126383 | 2002-04-26 | ||
JP2003349490A JP2004068596A (en) | 2002-04-26 | 2003-10-08 | Manhole repairing method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003097976A Division JP3522268B2 (en) | 2002-04-26 | 2003-04-01 | Frame replacement method including manhole cover |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006119236A Division JP4392001B2 (en) | 2002-04-26 | 2006-04-24 | Manhole cover frame replacement method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004068596A true JP2004068596A (en) | 2004-03-04 |
Family
ID=32032131
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003349490A Pending JP2004068596A (en) | 2002-04-26 | 2003-10-08 | Manhole repairing method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004068596A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006152570A (en) * | 2004-11-25 | 2006-06-15 | Ito Yogyo Co Ltd | Manhole receiving frame with catchment function, substituting method to manhole receiving frame with water catchment function from existing manhole receiving frame, newly arranging method of manhole receiving frame with water catchment function and road pavement structure provided with manhole receiving frame with water catchment function |
JP2010127044A (en) * | 2008-11-28 | 2010-06-10 | Ogawara Cement Kogyo Kk | Method for changing iron cover for manhole and receiving frame thereof |
-
2003
- 2003-10-08 JP JP2003349490A patent/JP2004068596A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006152570A (en) * | 2004-11-25 | 2006-06-15 | Ito Yogyo Co Ltd | Manhole receiving frame with catchment function, substituting method to manhole receiving frame with water catchment function from existing manhole receiving frame, newly arranging method of manhole receiving frame with water catchment function and road pavement structure provided with manhole receiving frame with water catchment function |
JP2010127044A (en) * | 2008-11-28 | 2010-06-10 | Ogawara Cement Kogyo Kk | Method for changing iron cover for manhole and receiving frame thereof |
JP4518521B2 (en) * | 2008-11-28 | 2010-08-04 | 小河原セメント工業株式会社 | How to replace the manhole cover and its receiving frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2004003309A (en) | Manhole lid / frame replacement method | |
KR101075181B1 (en) | Manhole Repairing Structure | |
JP2004068596A (en) | Manhole repairing method | |
JP4392001B2 (en) | Manhole cover frame replacement method | |
JP2001131964A (en) | Pile head processing device for cast-in-plate pile, and pile head processing construction method using same | |
JP2006322138A (en) | Construction method for repairing side ditch | |
KR100374540B1 (en) | Method of Manhole Repair and Used the Method of Equipment | |
KR200316568Y1 (en) | Device for installation of manhole housing | |
KR20100127062A (en) | Construction of manholes method | |
KR100578554B1 (en) | Manhole maintenance method and suppoting device for the method | |
KR100966639B1 (en) | Manhole repair method | |
KR100488401B1 (en) | Execution method for repairing manhole and manhole structure repaired by the same execution method | |
JP3171675U (en) | Anti-sinking floor slab with maneuvering prevention function | |
KR101074759B1 (en) | Repairing method of concrete road | |
KR101075180B1 (en) | Manhole Repairing Method | |
KR960004916B1 (en) | Overlay method for height adjustable manhole | |
JP3171670U (en) | Preventing subsidence around the manhole | |
JP2680555B2 (en) | How to adjust the height of the top surface of the existing manhole | |
JP7021386B1 (en) | How to replace the wall rail | |
KR200306639Y1 (en) | Manhole housing | |
KR102062807B1 (en) | Repair frame for manhole and method of manhole repair using it | |
JP2009024445A (en) | Method of repairing manhole | |
KR100881438B1 (en) | Manhole repairing structure | |
JPH072703Y2 (en) | Manhole structure | |
JP2023041507A (en) | Manhole cover receiving frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20040518 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20040518 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20051027 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20051108 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051114 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051129 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060126 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20060221 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060424 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20060424 |
|
A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20060529 |
|
A912 | Removal of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20060707 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20061027 |