JP2004068332A - Tension fixing method of temporary cable - Google Patents
Tension fixing method of temporary cable Download PDFInfo
- Publication number
- JP2004068332A JP2004068332A JP2002226823A JP2002226823A JP2004068332A JP 2004068332 A JP2004068332 A JP 2004068332A JP 2002226823 A JP2002226823 A JP 2002226823A JP 2002226823 A JP2002226823 A JP 2002226823A JP 2004068332 A JP2004068332 A JP 2004068332A
- Authority
- JP
- Japan
- Prior art keywords
- temporary
- floor slab
- cable
- cables
- tension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本願発明は、PC橋(プレストレストコンクリート橋)を架設する際に用いられる仮設内ケーブルの緊張定着方法に関するものである。
【0002】
【従来の技術】
PC橋を架設する際、その架設時にのみ緊張力を導入して架設完了時には緊張力を解放する、いわゆる仮設内ケーブルが用いられることがある。
【0003】
この仮設内ケーブルの緊張定着は、架設途中のPC橋の床版内に仮設内ケーブルを配置し、その一端部を床版の小口に固定した後、この仮設内ケーブルに緊張力を導入してその他端部を床版の所定位置に定着するようになっている。
【0004】
その際、ケーブル容量が大きい場合には、図7および8(a)に示すように、床版102上にコンクリート製の定着用突起部102aを構築しておき、直列に配置された1対の仮設内ケーブル104の向かい合う端部104aを定着用突起部102aに襷掛けにして緊張定着を行い、架設完了後に定着用突起部102aをはつり取る方式、あるいは、図8(b)に示すように、床版102上にコンクリート製の定着用突起部材106を複数のPC鋼材108によって固定しておき、直列に配置された1対の仮設内ケーブル104の向かい合う端部104aを定着用突起部102aに襷掛けにして緊張定着を行い、架設完了後に定着用突起部材106を撤去する方式が採用されている。
【0005】
【発明が解決しようとする課題】
しかしながら、図8(a)に示す方式は、定着用突起部102aの配筋(鉄筋110等の配置)、打設および架設完了後のはつり作業に多くの手間と費用が掛かってしまい、しかも本体構造物に望ましくないダメージを与えてしまう場合が多い、という問題がある。また、図8(b)に示す方式においても、定着用突起部材106の固定およびその撤去作業に多くの手間と費用が掛かってしまう、という問題がある。
【0006】
本願発明は、このような事情に鑑みてなされたものであって、PC橋を架設する際に用いられる仮設内ケーブルの緊張定着および解放撤去を簡易かつ安価に行うことができる仮設内ケーブルの緊張定着方法を提供することを目的とするものである。
【0007】
【課題を解決するための手段】
本願発明は、可動式の定着具を用いて、直列に配置された1対の仮設内ケーブルに対する緊張定着を一挙に行うようにすることにより、上記目的達成を図るようにしたものである。
【0008】
すなわち、本願発明に係る仮設内ケーブルの緊張定着方法は、
架設途中のPC橋の床版内に仮設内ケーブルを配置するとともに、この仮設内ケーブルの一端部を上記床版の小口に固定した後、この仮設内ケーブルに緊張力を導入して該仮設内ケーブルの他端部を上記床版の所定位置に定着する、仮設内ケーブルの緊張定着方法において、
上記床版内に第1および第2の仮設内ケーブルを直列に配置するとともに、これら各仮設内ケーブルにおける直列方向両側の一端部を上記床版の小口に各々固定した後、上記第1の仮設内ケーブルの他端部を上記床版上へ曲げ上げて可動式の定着具に挿通固定するとともに上記第2の仮設内ケーブルの他端部を上記床版上へ曲げ上げて上記定着具に挿通させ、この状態で上記第2の仮設内ケーブルの他端部を引き出すことにより上記両仮設内ケーブルに緊張力を導入する、ことを特徴とするものである。
【0009】
上記「床版」は、上床版であってもよいし、下床版であってもよい。
【0010】
上記「定着具」は、各仮設内ケーブルを互いに略反対方向に挿通させるように構成され、かつ、緊張力導入の際、床版上において変位し得るように構成されたものであれば、その形状、材質等の具体的構成は特に限定されるものではない。
【0011】
【発明の作用効果】
上記構成に示すように、本願発明に係る仮設内ケーブルの緊張定着方法は、床版内に直列に配置された第1および第2の仮設内ケーブルにおける直列方向両側の各一端部を床版の小口に各々固定した後、第1の仮設内ケーブルの他端部を床版上へ曲げ上げて可動式の定着具に挿通固定するとともに第2の仮設内ケーブルの他端部を床版上へ曲げ上げて上記定着具に挿通させ、この状態で第2の仮設内ケーブルの他端部を引き出すことにより両仮設内ケーブルに緊張力を導入するようになっているので、次のような作用効果を得ることができる。
【0012】
すなわち、従来のように、床版上にコンクリート製の定着用突起部を構築したり、コンクリート製の定着用突起部材を固定する必要がなくなるので、定着用突起部の配筋、打設およびはつり作業、あるいは定着用突起部材の固定および撤去作業も必要なくなる。したがって、そのための手間と費用が不要となり、これにより工期短縮およびコストダウンを図ることができる。
【0013】
また、直列に配置された1対の仮設内ケーブルに対する緊張定着を一挙に行うことができるので、従来のように各仮設内ケーブル毎に緊張定着を行う場合に比して作業工数を半減させることができ、この点においても工期短縮およびコストダウンを図ることができる。
【0014】
このように本願発明によれば、PC橋を架設する際に用いられる仮設内ケーブルの緊張定着および解放撤去を簡易かつ安価に行うことができる。
【0015】
しかも本願発明においては、可動式の定着具を用いているので、従来のように定着用突起部のはつり作業等によって本体構造物に望ましくないダメージを与えてしまうといったおそれをなくすことができる。
【0016】
上記構成において、床版上における定着具の直列方向両側近傍部位に、各仮設内ケーブルの他端部を定着具に案内するための案内治具を配置しておくようにすれば、各仮設内ケーブルおよび定着具に無理な外力が作用しないようにすることができ、これにより緊張定着作業をスムーズに行うことができる。しかも、これら各案内治具は、他の現場での緊張定着作業を行う際にも転用することが可能である。
【0017】
その際、これら各案内治具として、各仮設内ケーブルの他端部を下方から支持する斜面状案内部と、各仮設内ケーブルの他端部の横ずれを防止するための凹溝状案内部とを備えたものを用いるようにすれば、緊張定着作業を一層スムーズに行うことができる。
【0018】
また上記構成において、床版内における各仮設内ケーブルの他端部近傍部位に、上記緊張力導入の際に各仮設内ケーブルに作用する揚力に抵抗するための補強筋を配置しておくようにすれば、仮設内ケーブルの緊張定着の際に床版が破損してしまうおそれをなくすことができる。
【0019】
【発明の実施の形態】
以下、図面を用いて、本願発明の実施の形態について説明する。
【0020】
図1は、本願発明の一実施形態に係る仮設内ケーブルの緊張定着方法の適用対象となるPC橋を示す側面図であり、図2は、図1のII部詳細断面図であり、図3は、図2の要部詳細図である。
【0021】
図1に示すPC橋10は、架設途中(主桁の片持ち張出し施工中)のPC橋であって、その上床版12内に直列に配置された1対の仮設内ケーブル14、16が緊張定着された状態を示す図である。
【0022】
これら仮設内ケーブル14、16の緊張定着作業は、次のようにして行われるようになっている。
【0023】
すなわち、まず、上床版12内に両仮設内ケーブル14、16を橋軸方向に沿って直列に配置する。これら各仮設内ケーブル14、16の配置は、上床版12内に埋設されたシース18に各仮設内ケーブル14、16を挿通させることにより行う。なお、これら各仮設内ケーブル14、16は、複数本(6本)のPC鋼より線で構成されている。
【0024】
そして、これら各仮設内ケーブル14、16における直列方向両側(橋軸方向両側)の一端部14a、16aを、上床版12の小口12a、12bに各々クサビ固定する。一方、各仮設内ケーブル14、16の他端部14b、16bを曲げ上げて、これらを上床版12のケーブル突出口12c、12dから斜め上方へ突出させる。
【0025】
その後、一方の仮設内ケーブル14(第1の仮設内ケーブル)の他端部14bを上床版12上において定着具20に挿通固定(クサビ固定)するとともに、他方の仮設内ケーブル16(第2の仮設内ケーブル)の他端部16bを定着具20に挿通させる。
【0026】
この状態で、仮設内ケーブル16の他端部16bを、定着具20にRチェア22を介して取り付けられたジャッキ24によって引き出すことにより、両仮設内ケーブル14、16に緊張力を導入する。そしてこの緊張力導入が完了した後、仮設内ケーブル16の他端部16bを定着具20にクサビ固定し、Rチェア22およびジャッキ24を撤去し、緊張定着作業を完了させる。
【0027】
上記定着具20は、可動式の鋼製定着具であって、いわゆる襷掛け定着具として構成されている。すなわち、この定着具20は、箱状に形成されており、各仮設内ケーブル14、16を互いに反対方向に挿通させ、その両端面で各仮設内ケーブル14、16の他端部14b、16bを定着するようになっている。
【0028】
この定着具20は可動式であるので、緊張力導入に伴って橋軸方向に変位する。すなわち、図3において、仮設内ケーブル14の緊張によって左方向へ変位しようとし、仮設内ケーブル16の引出しによっても左方向へ変位しようとする。このため最終的には、元の位置(2点鎖線で示す位置)から左方向へ所定量変位した位置で緊張力導入が完了する。
【0029】
このようにして緊張定着された両仮設内ケーブル14、16は、PC橋10の架設が完了した後、緊張力が解放され、上床版12内から撤去される。その際、緊張力の解放は、Rチェア22およびジャッキ24を再び定着具20に取り付けることによって行う。
【0030】
本実施形態においては、上記緊張定着作業を行う際、上床版12上における定着具20の橋軸方向両側に、各仮設内ケーブル14、16の他端部14b、16bを定着具20に案内するための案内治具26を配置しておくようになっている。
【0031】
これら各案内治具26は、鋼製の治具であって、図4に単品でも示すように、上床版12内から上床版12上へ斜めに突出する各仮設内ケーブル14、16の他端部14b、16bを下方から支持する斜面状案内部26aと、各仮設内ケーブル14、16の他端部14b、16bの横ずれを防止するための凹溝状案内部26bとを備えた構成となっている。
【0032】
斜面状案内部26aは、凸曲面状に形成されており、これにより各仮設内ケーブル14、16を所定長にわたって支持するようになっている。また、凹溝状案内部26bは、斜面状案内部26aの斜面上端部においてU字状に形成されている。
【0033】
また本実施形態においては、図2に示すように、上床版12を打設する際、該上床版12内における各仮設内ケーブル14、16の他端部14b、16bの近傍部位(具体的には、上床版12のケーブル突出口12c、12dの橋軸方向両側近傍部位)に、上記緊張力導入の際に各仮設内ケーブル14、16に作用する揚力に抵抗するための補強筋28を配置しておくようになっている。この補強筋28は、各ケーブル突出口12c、12dに対して複数個ずつ(3個ずつ)配置されている。
【0034】
これら各補強筋28は、図2のVa部詳細図である図5(a)およびこの図5(a)のVb−Vb 断面図である図5(b)に示すように、シース18を跨ぐように形成された逆U字状部28aと、この逆U字状部28aの下端部からケーブル突出口12d(12c)側へ向けて水平方向に平行に延びる1対の直線部28bとからなっている。
【0035】
以上詳述したように、本実施形態においては、上床版12内に橋軸方向に沿って直列に配置された1対の仮設内ケーブル14、16における橋軸方向両側の各一端部14a、16aを、上床版12の小口12a、12bに各々固定した後、一方の仮設内ケーブル14の他端部14bを上床版12上へ曲げ上げて可動式の定着具20に挿通固定するとともに、他方の仮設内ケーブル16の他端部16bを上床版12上へ曲げ上げて定着具20に挿通させ、この状態で仮設内ケーブル16の他端部16bを引き出すことにより両仮設内ケーブル14、16に緊張力を導入するようになっているので、次のような作用効果を得ることができる。
【0036】
すなわち、従来のように、床版上にコンクリート製の定着用突起部を構築したり、コンクリート製の定着用突起部材を固定する必要がなくなるので、定着用突起部の配筋、打設およびはつり作業、あるいは定着用突起部材の固定および撤去作業も必要なくなる。したがって、そのための手間と費用が不要となり、これにより工期短縮およびコストダウンを図ることができる。
【0037】
また、直列に配置された1対の仮設内ケーブル14、16に対する緊張定着を一挙に行うことができるので、従来のように各仮設内ケーブル毎に緊張定着を行う場合に比して作業工数を半減させることができ、この点においても工期短縮およびコストダウンを図ることができる。
【0038】
このように本実施形態によれば、PC橋10を架設する際に用いられる仮設内ケーブル14、16の緊張定着および解放撤去を簡易かつ安価に行うことができる。
【0039】
しかも本実施形態においては、可動式の定着具20を用いているので、従来のように定着用突起部のはつり作業等によって本体構造物に望ましくないダメージを与えてしまうといったおそれをなくすことができる。
【0040】
また本実施形態においては、上床版12上における定着具20の橋軸方向両側近傍部位に、各仮設内ケーブル14、16の他端部14b、16bを定着具20に案内するための案内治具26を配置しておくようになっているので、各仮設内ケーブル14、16および定着具20に無理な外力が作用しないようにすることができ、これにより緊張定着作業をスムーズに行うことができる。しかも、これら各案内治具26は、他の現場での緊張定着作業を行う際にも転用することが可能である。
【0041】
その際、本実施形態においては、これら各案内治具26として、上床版12内から上床版12上へ斜めに突出する各仮設内ケーブル14、16の他端部14b、16bを下方から支持する斜面状案内部26aと、各仮設内ケーブル14、16の他端部14b、16bの横ずれを防止するための凹溝状案内部26bとを備えたものを用いているので、緊張定着作業を一層スムーズに行うことができる。
【0042】
また本実施形態においては、上床版12内におけるケーブル突出口12c、12dの橋軸方向両側近傍部位に、上記緊張力導入の際に各仮設内ケーブル14、16に作用する揚力に抵抗するための補強筋28を配置しておくようになっているので、仮設内ケーブル14、16の緊張定着の際に上床版12が破損してしまうおそれをなくすことができる。なお、本実施形態においては、各仮設内ケーブル14、16毎に3個ずつ配置するものとして説明したが、4個以上ずつ配置するようにしてもよいし、2個以下ずつ配置するようにしてもよい。
【0043】
ところで本実施形態においては、主桁の片持ち張出し施工によるPC橋10の架設途中において、その上床版12内に配置される仮設内ケーブル14、16の緊張定着を行う場合について説明したが、これ以外の場合にも本実施形態に係る仮設内ケーブルの緊張定着方法を適用することが可能である。
【0044】
例えば、図6に示すように、押出し工法によるPC橋40の架設途中において、その下床版42内に配置される1対の仮設内ケーブル14、16を緊張定着することも可能である。
【0045】
この場合、同図(a)に示すように、先端部に手延ガーダ44を装着した状態で図示矢印方向へ押し出す際には、仮設内ケーブル14、16を緊張定着した状態に維持しておき、同図(b)に示すように、押出しが完了した後、1対の仮設内ケーブル14、16の緊張力を解放し、これらを下床版42内から撤去するようにすればよい。
【図面の簡単な説明】
【図1】本願発明の一実施形態に係る仮設内ケーブルの緊張定着方法の適用対象となるPC橋を示す側面図
【図2】図1のII部詳細断面図
【図3】図2の要部詳細図
【図4】上記実施形態に使用される案内治具を単品で示す図
【図5】図2のVa部詳細図(a)およびそのVb−Vb 断面図(b)
【図6】上記実施形態の変形例を示す、図1と同様の図
【図7】従来例を示す、図1と同様の図
【図8】上記従来例を示す、図7のVIIIa 部詳細図(a)、および他の従来例を示す(a)と同様の図(b)
【符号の説明】
10 PC橋
12 上床版(床版)
12a、12b 小口
12c、12d ケーブル突出口
14 仮設内ケーブル(第1の仮設内ケーブル)
14a、16a 一端部
14b、16b 他端部
16 仮設内ケーブル(第2の仮設内ケーブル)
18 シース
20 定着具
22 Rチェア
24 ジャッキ
26 案内治具
26a 斜面状案内部
26b 凹溝状案内部
28 補強筋
28a 逆U字状部
28b 直線部
40 PC橋
42 下床版(床版)
44 手延ガーダ[0001]
TECHNICAL FIELD OF THE INVENTION
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for fixing a tension in a temporary cable used for erection of a PC bridge (prestressed concrete bridge).
[0002]
[Prior art]
When a PC bridge is erected, a so-called temporary cable may be used, in which a tension is introduced only during the erection and the tension is released when the erection is completed.
[0003]
To fix the tension in the temporary cable, place the temporary cable in the floor slab of the PC bridge in the middle of construction, fix one end of the cable to the edge of the floor slab, and then introduce tension into the temporary cable. The other end is fixed at a predetermined position on the floor slab.
[0004]
At this time, when the cable capacity is large, as shown in FIGS. 7 and 8 (a), a
[0005]
[Problems to be solved by the invention]
However, the method shown in FIG. 8A requires a lot of labor and cost for the rebar arrangement of the
[0006]
SUMMARY OF THE INVENTION The present invention has been made in view of such circumstances, and a tension of a temporary internal cable which can be easily and inexpensively fixed and fixed at a temporary internal cable used when constructing a PC bridge. It is an object to provide a fixing method.
[0007]
[Means for Solving the Problems]
The present invention achieves the above-mentioned object by using a movable fixing device to perform tension fixing on a pair of temporary cables arranged in series at once.
[0008]
That is, the tension fixing method of the temporary internal cable according to the present invention is as follows.
The temporary internal cable is arranged in the floor slab of the PC bridge in the middle of the erection, and one end of the temporary internal cable is fixed to the small opening of the floor slab. In the tension fixing method of the cable in the temporary, fixing the other end of the cable to a predetermined position of the floor slab,
After arranging the first and second temporary internal cables in series in the floor slab and fixing one end of each temporary internal cable on both ends in the series direction to the edge of the floor slab, The other end of the inner cable is bent up onto the floor slab and inserted and fixed in a movable fixing device, and the other end of the second temporary inner cable is bent up onto the floor slab and inserted into the fixing device. In this state, by pulling out the other end of the second temporary internal cable, tension is introduced to both the temporary internal cables.
[0009]
The “floor slab” may be an upper slab or a lower slab.
[0010]
The `` fixing device '' is configured so that each temporary internal cable is inserted in a substantially opposite direction to each other, and is configured to be displaceable on the floor slab when a tension is introduced. The specific configuration such as shape and material is not particularly limited.
[0011]
Operation and Effect of the Invention
As shown in the above configuration, the tension fixing method of the temporary internal cable according to the invention of the present application includes the first and second temporary internal cables arranged in series in the floor slab, each end of both sides in the serial direction of the floor slab. After being fixed to the fore edge, the other end of the first temporary internal cable is bent up onto the floor slab to be inserted and fixed in the movable fixing tool, and the other end of the second temporary internal cable is placed on the floor slab. Bending up and passing through the fixing device, and pulling out the other end of the second temporary cable in this state introduces tension into both the temporary cables. Can be obtained.
[0012]
That is, unlike the related art, there is no need to construct a concrete fixing projection on the floor slab or fix the concrete fixing projection member. Therefore, it is necessary to arrange, fix, and suspend the fixing projection. There is no need for an operation or an operation for fixing and removing the fixing projection member. Therefore, the labor and cost for this are not required, thereby shortening the construction period and reducing the cost.
[0013]
In addition, since tension fixing can be performed at once for a pair of temporary cables arranged in series, the number of work steps can be reduced by half as compared with the conventional case where tension is fixed for each temporary cable. In this regard, the construction period can be shortened and the cost can be reduced.
[0014]
As described above, according to the present invention, it is possible to easily and inexpensively carry out tension fixing, release, and removal of the intra-temporary cable used when constructing the PC bridge.
[0015]
In addition, in the present invention, since the movable fixing tool is used, it is possible to eliminate the possibility that the main body structure is undesirably damaged due to the hanging work of the fixing protrusion as in the related art.
[0016]
In the above configuration, if a guide jig for guiding the other end of each temporary cable to the fixing tool is arranged in the vicinity of both sides of the fixing tool in the serial direction on the floor slab, the inside of each temporary An unreasonable external force can be prevented from acting on the cable and the fixing device, so that the tension fixing operation can be performed smoothly. In addition, each of these guide jigs can be diverted when performing tension fixing work at another site.
[0017]
At this time, as each of these guide jigs, a slope-shaped guide portion for supporting the other end of each temporary internal cable from below, and a groove-shaped guide portion for preventing the other end of each temporary internal cable from laterally shifting. By using the one provided with the above, the tension fixing work can be performed more smoothly.
[0018]
Further, in the above configuration, a reinforcing bar for resisting a lifting force acting on each temporary internal cable at the time of the introduction of the tension is arranged at a position near the other end of each temporary internal cable in the floor slab. This can eliminate the possibility that the floor slab will be damaged when the temporary internal cable is tensioned and fixed.
[0019]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0020]
FIG. 1 is a side view showing a PC bridge to which a method for tensioning and fixing a temporary internal cable according to an embodiment of the present invention is applied. FIG. 2 is a detailed sectional view of a portion II in FIG. 3 is a detailed view of a main part of FIG.
[0021]
The
[0022]
The tension fixing work of these temporary
[0023]
That is, first, both the temporary
[0024]
Then, one
[0025]
Then, the
[0026]
In this state, the
[0027]
The fixing
[0028]
Since the fixing
[0029]
After the installation of the
[0030]
In the present embodiment, when performing the above-described tension fixing operation, the
[0031]
Each of these guide jigs 26 is a steel jig, and as shown in FIG. 4 alone, the other end of each of the temporary
[0032]
The
[0033]
Further, in the present embodiment, as shown in FIG. 2, when the
[0034]
These reinforcing
[0035]
As described in detail above, in the present embodiment, one
[0036]
That is, unlike the related art, there is no need to construct a concrete fixing projection on the floor slab or fix the concrete fixing projection member. Therefore, it is necessary to arrange, fix, and suspend the fixing projection. There is no need for an operation or an operation for fixing and removing the fixing projection member. Therefore, the labor and cost for this are not required, thereby shortening the construction period and reducing the cost.
[0037]
Further, since the tension and fixing of the pair of
[0038]
As described above, according to the present embodiment, tension fixation, release, and removal of the
[0039]
In addition, in the present embodiment, since the
[0040]
Further, in the present embodiment, a guide jig for guiding the
[0041]
At this time, in the present embodiment, as the respective guide jigs 26, the
[0042]
Further, in the present embodiment, the
[0043]
By the way, in the present embodiment, the case where the temporary
[0044]
For example, as shown in FIG. 6, during the construction of the
[0045]
In this case, as shown in FIG. 3A, when pushing out in the direction of the arrow in the drawing with the hand-extended
[Brief description of the drawings]
FIG. 1 is a side view showing a PC bridge to which a tension fixing method for a temporary internal cable according to an embodiment of the present invention is applied. FIG. 2 is a detailed sectional view of a portion II in FIG. 1 FIG. FIG. 4 is a diagram showing the guide jig used in the above embodiment as a single item. FIG. 5 is a detailed view of the Va portion in FIG. 2 (a) and a cross-sectional view of the same taken along line Vb-Vb (b).
6 is a view similar to FIG. 1 showing a modification of the above embodiment; FIG. 7 is a view similar to FIG. 1 showing a conventional example; FIG. 8 is a view showing the above conventional example; FIG. (A) and FIG. (B) similar to (a) showing another conventional example.
[Explanation of symbols]
10
12a,
14a, 16a One
18
44 Tenobu girder
Claims (4)
上記床版内に第1および第2の仮設内ケーブルを直列に配置するとともに、これら各仮設内ケーブルにおける直列方向両側の一端部を上記床版の小口に各々固定した後、上記第1の仮設内ケーブルの他端部を上記床版上へ曲げ上げて可動式の定着具に挿通固定するとともに上記第2の仮設内ケーブルの他端部を上記床版上へ曲げ上げて上記定着具に挿通させ、この状態で上記第2の仮設内ケーブルの他端部を引き出すことにより上記両仮設内ケーブルに緊張力を導入する、ことを特徴とする仮設内ケーブルの緊張定着方法。The temporary internal cable is arranged in the floor slab of the PC bridge in the middle of the erection, and one end of the temporary internal cable is fixed to the small opening of the floor slab. In the tension fixing method of the cable in the temporary, fixing the other end of the cable to a predetermined position of the floor slab,
After arranging the first and second temporary internal cables in series in the floor slab and fixing one end of each temporary internal cable on both ends in the series direction to the edge of the floor slab, The other end of the inner cable is bent up onto the floor slab and inserted and fixed in a movable fixing device, and the other end of the second temporary inner cable is bent up onto the floor slab and inserted into the fixing device. And tensioning the two temporary cables by pulling out the other end of the second temporary cable in this state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002226823A JP2004068332A (en) | 2002-08-05 | 2002-08-05 | Tension fixing method of temporary cable |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002226823A JP2004068332A (en) | 2002-08-05 | 2002-08-05 | Tension fixing method of temporary cable |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004068332A true JP2004068332A (en) | 2004-03-04 |
Family
ID=32014032
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002226823A Pending JP2004068332A (en) | 2002-08-05 | 2002-08-05 | Tension fixing method of temporary cable |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004068332A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011190616A (en) * | 2010-03-15 | 2011-09-29 | Sumitomo Mitsui Construction Co Ltd | Device and method for releasing tensioning force of tendon |
JP2015151768A (en) * | 2014-02-14 | 2015-08-24 | 株式会社高速道路総合技術研究所 | Change-over method of concrete slab for highway road, and change-over pc slab by the method |
JP2018053496A (en) * | 2016-09-27 | 2018-04-05 | 三井住友建設株式会社 | Bridge girder erection method for multiple span continuous bridge |
-
2002
- 2002-08-05 JP JP2002226823A patent/JP2004068332A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011190616A (en) * | 2010-03-15 | 2011-09-29 | Sumitomo Mitsui Construction Co Ltd | Device and method for releasing tensioning force of tendon |
JP2015151768A (en) * | 2014-02-14 | 2015-08-24 | 株式会社高速道路総合技術研究所 | Change-over method of concrete slab for highway road, and change-over pc slab by the method |
JP2018053496A (en) * | 2016-09-27 | 2018-04-05 | 三井住友建設株式会社 | Bridge girder erection method for multiple span continuous bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2004116081A (en) | Reinforcing construction of existing structure and reinforcing method | |
JP2009068249A (en) | Bridge construction method | |
JP3957680B2 (en) | Assembling method of cable-stayed cable | |
JP2004068332A (en) | Tension fixing method of temporary cable | |
KR20100066692A (en) | Psc beam connection method for continuous bridge using plat anchorage apparatus | |
JP3608751B2 (en) | Temporary fixing method of block in PC precast block method by non-coupler | |
KR20160029277A (en) | Construction Method to Create Multi-span Continuity in PSC Bridges | |
JP3797560B2 (en) | Bridge segment and its construction method | |
JP2010037833A (en) | Bridge extrusion erection construction method | |
JPH0771007A (en) | Temporary fixation method on construction of capital of bridge | |
JP2807845B2 (en) | Construction method of diagonal material for Stypanel Bridge | |
JP4310379B2 (en) | How to build a bridge | |
JP2011190616A (en) | Device and method for releasing tensioning force of tendon | |
JP2714531B2 (en) | How to install diagonal cable | |
JP2005047233A (en) | Prestressed concrete member and its manufacturing method | |
JP2007126854A (en) | Method of arranging reinforcements of reed-screen-shaped reinforcement unit, and reinforcement connection jig for use therein | |
JPH0860616A (en) | Stretching method of cable | |
KR100442969B1 (en) | Method and its devices to strengthen a bridge by external prestressing cable | |
JPH03151403A (en) | Reinforcing method for existing bridge girder | |
JP2007217883A (en) | Floor structure | |
JP2000120018A (en) | Bridge having hollow section and constructing method therefor | |
JPH07331782A (en) | Floor slab made of pc board | |
JP4000014B2 (en) | Tension method of PC cable of bridge | |
JP3505662B2 (en) | Precast concrete beam and method of using the beam | |
JP2612425B2 (en) | Fixing method of unbonded PC steel strand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050325 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070220 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070515 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20070925 |