JP2004068332A - Tension fixing method of temporary cable - Google Patents

Tension fixing method of temporary cable Download PDF

Info

Publication number
JP2004068332A
JP2004068332A JP2002226823A JP2002226823A JP2004068332A JP 2004068332 A JP2004068332 A JP 2004068332A JP 2002226823 A JP2002226823 A JP 2002226823A JP 2002226823 A JP2002226823 A JP 2002226823A JP 2004068332 A JP2004068332 A JP 2004068332A
Authority
JP
Japan
Prior art keywords
temporary
floor slab
cable
cables
tension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002226823A
Other languages
Japanese (ja)
Inventor
Kazushi Nakamura
中村 收志
Kenichi Saito
齋藤 謙一
Hirokazu Fujita
藤田 汎一
Hiroshi Tokiwa
常磐 浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2002226823A priority Critical patent/JP2004068332A/en
Publication of JP2004068332A publication Critical patent/JP2004068332A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To easily and inexpensively fix the tension of a cable in a temporary erection used for erecting a PC bridge and release and removal. <P>SOLUTION: A pair of cables 14, 16 in a temporary structure are arranged in series in an upper floor slab 12 and respective one-side ends 14a, 16a of both serial directional sides are fixed to headers 12a, 12b of the upper floor slab 12 and then the other end 14b of one side temporary cable 14 is bent up to the upper floor slab 12 and fixedly insert to a movable fixing tool 20 and the other end 16b of the other temporary cable 16 is bent up and fixedly inserted in the fixing tool 20. In this condition, tension is guided into both the temporary cables 14, 16 by pulling out the other end 16b of the temporary cable 16. In this way, it is not necessary to conventionally construct a concrete fixing protrusion to the floor slab, nor labor and an expence for arranging rods, and chipping work. Further, the tension fixing for the cables 14, 16 is performed at one time. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本願発明は、PC橋(プレストレストコンクリート橋)を架設する際に用いられる仮設内ケーブルの緊張定着方法に関するものである。
【0002】
【従来の技術】
PC橋を架設する際、その架設時にのみ緊張力を導入して架設完了時には緊張力を解放する、いわゆる仮設内ケーブルが用いられることがある。
【0003】
この仮設内ケーブルの緊張定着は、架設途中のPC橋の床版内に仮設内ケーブルを配置し、その一端部を床版の小口に固定した後、この仮設内ケーブルに緊張力を導入してその他端部を床版の所定位置に定着するようになっている。
【0004】
その際、ケーブル容量が大きい場合には、図7および8(a)に示すように、床版102上にコンクリート製の定着用突起部102aを構築しておき、直列に配置された1対の仮設内ケーブル104の向かい合う端部104aを定着用突起部102aに襷掛けにして緊張定着を行い、架設完了後に定着用突起部102aをはつり取る方式、あるいは、図8(b)に示すように、床版102上にコンクリート製の定着用突起部材106を複数のPC鋼材108によって固定しておき、直列に配置された1対の仮設内ケーブル104の向かい合う端部104aを定着用突起部102aに襷掛けにして緊張定着を行い、架設完了後に定着用突起部材106を撤去する方式が採用されている。
【0005】
【発明が解決しようとする課題】
しかしながら、図8(a)に示す方式は、定着用突起部102aの配筋(鉄筋110等の配置)、打設および架設完了後のはつり作業に多くの手間と費用が掛かってしまい、しかも本体構造物に望ましくないダメージを与えてしまう場合が多い、という問題がある。また、図8(b)に示す方式においても、定着用突起部材106の固定およびその撤去作業に多くの手間と費用が掛かってしまう、という問題がある。
【0006】
本願発明は、このような事情に鑑みてなされたものであって、PC橋を架設する際に用いられる仮設内ケーブルの緊張定着および解放撤去を簡易かつ安価に行うことができる仮設内ケーブルの緊張定着方法を提供することを目的とするものである。
【0007】
【課題を解決するための手段】
本願発明は、可動式の定着具を用いて、直列に配置された1対の仮設内ケーブルに対する緊張定着を一挙に行うようにすることにより、上記目的達成を図るようにしたものである。
【0008】
すなわち、本願発明に係る仮設内ケーブルの緊張定着方法は、
架設途中のPC橋の床版内に仮設内ケーブルを配置するとともに、この仮設内ケーブルの一端部を上記床版の小口に固定した後、この仮設内ケーブルに緊張力を導入して該仮設内ケーブルの他端部を上記床版の所定位置に定着する、仮設内ケーブルの緊張定着方法において、
上記床版内に第1および第2の仮設内ケーブルを直列に配置するとともに、これら各仮設内ケーブルにおける直列方向両側の一端部を上記床版の小口に各々固定した後、上記第1の仮設内ケーブルの他端部を上記床版上へ曲げ上げて可動式の定着具に挿通固定するとともに上記第2の仮設内ケーブルの他端部を上記床版上へ曲げ上げて上記定着具に挿通させ、この状態で上記第2の仮設内ケーブルの他端部を引き出すことにより上記両仮設内ケーブルに緊張力を導入する、ことを特徴とするものである。
【0009】
上記「床版」は、上床版であってもよいし、下床版であってもよい。
【0010】
上記「定着具」は、各仮設内ケーブルを互いに略反対方向に挿通させるように構成され、かつ、緊張力導入の際、床版上において変位し得るように構成されたものであれば、その形状、材質等の具体的構成は特に限定されるものではない。
【0011】
【発明の作用効果】
上記構成に示すように、本願発明に係る仮設内ケーブルの緊張定着方法は、床版内に直列に配置された第1および第2の仮設内ケーブルにおける直列方向両側の各一端部を床版の小口に各々固定した後、第1の仮設内ケーブルの他端部を床版上へ曲げ上げて可動式の定着具に挿通固定するとともに第2の仮設内ケーブルの他端部を床版上へ曲げ上げて上記定着具に挿通させ、この状態で第2の仮設内ケーブルの他端部を引き出すことにより両仮設内ケーブルに緊張力を導入するようになっているので、次のような作用効果を得ることができる。
【0012】
すなわち、従来のように、床版上にコンクリート製の定着用突起部を構築したり、コンクリート製の定着用突起部材を固定する必要がなくなるので、定着用突起部の配筋、打設およびはつり作業、あるいは定着用突起部材の固定および撤去作業も必要なくなる。したがって、そのための手間と費用が不要となり、これにより工期短縮およびコストダウンを図ることができる。
【0013】
また、直列に配置された1対の仮設内ケーブルに対する緊張定着を一挙に行うことができるので、従来のように各仮設内ケーブル毎に緊張定着を行う場合に比して作業工数を半減させることができ、この点においても工期短縮およびコストダウンを図ることができる。
【0014】
このように本願発明によれば、PC橋を架設する際に用いられる仮設内ケーブルの緊張定着および解放撤去を簡易かつ安価に行うことができる。
【0015】
しかも本願発明においては、可動式の定着具を用いているので、従来のように定着用突起部のはつり作業等によって本体構造物に望ましくないダメージを与えてしまうといったおそれをなくすことができる。
【0016】
上記構成において、床版上における定着具の直列方向両側近傍部位に、各仮設内ケーブルの他端部を定着具に案内するための案内治具を配置しておくようにすれば、各仮設内ケーブルおよび定着具に無理な外力が作用しないようにすることができ、これにより緊張定着作業をスムーズに行うことができる。しかも、これら各案内治具は、他の現場での緊張定着作業を行う際にも転用することが可能である。
【0017】
その際、これら各案内治具として、各仮設内ケーブルの他端部を下方から支持する斜面状案内部と、各仮設内ケーブルの他端部の横ずれを防止するための凹溝状案内部とを備えたものを用いるようにすれば、緊張定着作業を一層スムーズに行うことができる。
【0018】
また上記構成において、床版内における各仮設内ケーブルの他端部近傍部位に、上記緊張力導入の際に各仮設内ケーブルに作用する揚力に抵抗するための補強筋を配置しておくようにすれば、仮設内ケーブルの緊張定着の際に床版が破損してしまうおそれをなくすことができる。
【0019】
【発明の実施の形態】
以下、図面を用いて、本願発明の実施の形態について説明する。
【0020】
図1は、本願発明の一実施形態に係る仮設内ケーブルの緊張定着方法の適用対象となるPC橋を示す側面図であり、図2は、図1のII部詳細断面図であり、図3は、図2の要部詳細図である。
【0021】
図1に示すPC橋10は、架設途中(主桁の片持ち張出し施工中)のPC橋であって、その上床版12内に直列に配置された1対の仮設内ケーブル14、16が緊張定着された状態を示す図である。
【0022】
これら仮設内ケーブル14、16の緊張定着作業は、次のようにして行われるようになっている。
【0023】
すなわち、まず、上床版12内に両仮設内ケーブル14、16を橋軸方向に沿って直列に配置する。これら各仮設内ケーブル14、16の配置は、上床版12内に埋設されたシース18に各仮設内ケーブル14、16を挿通させることにより行う。なお、これら各仮設内ケーブル14、16は、複数本(6本)のPC鋼より線で構成されている。
【0024】
そして、これら各仮設内ケーブル14、16における直列方向両側(橋軸方向両側)の一端部14a、16aを、上床版12の小口12a、12bに各々クサビ固定する。一方、各仮設内ケーブル14、16の他端部14b、16bを曲げ上げて、これらを上床版12のケーブル突出口12c、12dから斜め上方へ突出させる。
【0025】
その後、一方の仮設内ケーブル14(第1の仮設内ケーブル)の他端部14bを上床版12上において定着具20に挿通固定(クサビ固定)するとともに、他方の仮設内ケーブル16(第2の仮設内ケーブル)の他端部16bを定着具20に挿通させる。
【0026】
この状態で、仮設内ケーブル16の他端部16bを、定着具20にRチェア22を介して取り付けられたジャッキ24によって引き出すことにより、両仮設内ケーブル14、16に緊張力を導入する。そしてこの緊張力導入が完了した後、仮設内ケーブル16の他端部16bを定着具20にクサビ固定し、Rチェア22およびジャッキ24を撤去し、緊張定着作業を完了させる。
【0027】
上記定着具20は、可動式の鋼製定着具であって、いわゆる襷掛け定着具として構成されている。すなわち、この定着具20は、箱状に形成されており、各仮設内ケーブル14、16を互いに反対方向に挿通させ、その両端面で各仮設内ケーブル14、16の他端部14b、16bを定着するようになっている。
【0028】
この定着具20は可動式であるので、緊張力導入に伴って橋軸方向に変位する。すなわち、図3において、仮設内ケーブル14の緊張によって左方向へ変位しようとし、仮設内ケーブル16の引出しによっても左方向へ変位しようとする。このため最終的には、元の位置(2点鎖線で示す位置)から左方向へ所定量変位した位置で緊張力導入が完了する。
【0029】
このようにして緊張定着された両仮設内ケーブル14、16は、PC橋10の架設が完了した後、緊張力が解放され、上床版12内から撤去される。その際、緊張力の解放は、Rチェア22およびジャッキ24を再び定着具20に取り付けることによって行う。
【0030】
本実施形態においては、上記緊張定着作業を行う際、上床版12上における定着具20の橋軸方向両側に、各仮設内ケーブル14、16の他端部14b、16bを定着具20に案内するための案内治具26を配置しておくようになっている。
【0031】
これら各案内治具26は、鋼製の治具であって、図4に単品でも示すように、上床版12内から上床版12上へ斜めに突出する各仮設内ケーブル14、16の他端部14b、16bを下方から支持する斜面状案内部26aと、各仮設内ケーブル14、16の他端部14b、16bの横ずれを防止するための凹溝状案内部26bとを備えた構成となっている。
【0032】
斜面状案内部26aは、凸曲面状に形成されており、これにより各仮設内ケーブル14、16を所定長にわたって支持するようになっている。また、凹溝状案内部26bは、斜面状案内部26aの斜面上端部においてU字状に形成されている。
【0033】
また本実施形態においては、図2に示すように、上床版12を打設する際、該上床版12内における各仮設内ケーブル14、16の他端部14b、16bの近傍部位(具体的には、上床版12のケーブル突出口12c、12dの橋軸方向両側近傍部位)に、上記緊張力導入の際に各仮設内ケーブル14、16に作用する揚力に抵抗するための補強筋28を配置しておくようになっている。この補強筋28は、各ケーブル突出口12c、12dに対して複数個ずつ(3個ずつ)配置されている。
【0034】
これら各補強筋28は、図2のVa部詳細図である図5(a)およびこの図5(a)のVb−Vb 断面図である図5(b)に示すように、シース18を跨ぐように形成された逆U字状部28aと、この逆U字状部28aの下端部からケーブル突出口12d(12c)側へ向けて水平方向に平行に延びる1対の直線部28bとからなっている。
【0035】
以上詳述したように、本実施形態においては、上床版12内に橋軸方向に沿って直列に配置された1対の仮設内ケーブル14、16における橋軸方向両側の各一端部14a、16aを、上床版12の小口12a、12bに各々固定した後、一方の仮設内ケーブル14の他端部14bを上床版12上へ曲げ上げて可動式の定着具20に挿通固定するとともに、他方の仮設内ケーブル16の他端部16bを上床版12上へ曲げ上げて定着具20に挿通させ、この状態で仮設内ケーブル16の他端部16bを引き出すことにより両仮設内ケーブル14、16に緊張力を導入するようになっているので、次のような作用効果を得ることができる。
【0036】
すなわち、従来のように、床版上にコンクリート製の定着用突起部を構築したり、コンクリート製の定着用突起部材を固定する必要がなくなるので、定着用突起部の配筋、打設およびはつり作業、あるいは定着用突起部材の固定および撤去作業も必要なくなる。したがって、そのための手間と費用が不要となり、これにより工期短縮およびコストダウンを図ることができる。
【0037】
また、直列に配置された1対の仮設内ケーブル14、16に対する緊張定着を一挙に行うことができるので、従来のように各仮設内ケーブル毎に緊張定着を行う場合に比して作業工数を半減させることができ、この点においても工期短縮およびコストダウンを図ることができる。
【0038】
このように本実施形態によれば、PC橋10を架設する際に用いられる仮設内ケーブル14、16の緊張定着および解放撤去を簡易かつ安価に行うことができる。
【0039】
しかも本実施形態においては、可動式の定着具20を用いているので、従来のように定着用突起部のはつり作業等によって本体構造物に望ましくないダメージを与えてしまうといったおそれをなくすことができる。
【0040】
また本実施形態においては、上床版12上における定着具20の橋軸方向両側近傍部位に、各仮設内ケーブル14、16の他端部14b、16bを定着具20に案内するための案内治具26を配置しておくようになっているので、各仮設内ケーブル14、16および定着具20に無理な外力が作用しないようにすることができ、これにより緊張定着作業をスムーズに行うことができる。しかも、これら各案内治具26は、他の現場での緊張定着作業を行う際にも転用することが可能である。
【0041】
その際、本実施形態においては、これら各案内治具26として、上床版12内から上床版12上へ斜めに突出する各仮設内ケーブル14、16の他端部14b、16bを下方から支持する斜面状案内部26aと、各仮設内ケーブル14、16の他端部14b、16bの横ずれを防止するための凹溝状案内部26bとを備えたものを用いているので、緊張定着作業を一層スムーズに行うことができる。
【0042】
また本実施形態においては、上床版12内におけるケーブル突出口12c、12dの橋軸方向両側近傍部位に、上記緊張力導入の際に各仮設内ケーブル14、16に作用する揚力に抵抗するための補強筋28を配置しておくようになっているので、仮設内ケーブル14、16の緊張定着の際に上床版12が破損してしまうおそれをなくすことができる。なお、本実施形態においては、各仮設内ケーブル14、16毎に3個ずつ配置するものとして説明したが、4個以上ずつ配置するようにしてもよいし、2個以下ずつ配置するようにしてもよい。
【0043】
ところで本実施形態においては、主桁の片持ち張出し施工によるPC橋10の架設途中において、その上床版12内に配置される仮設内ケーブル14、16の緊張定着を行う場合について説明したが、これ以外の場合にも本実施形態に係る仮設内ケーブルの緊張定着方法を適用することが可能である。
【0044】
例えば、図6に示すように、押出し工法によるPC橋40の架設途中において、その下床版42内に配置される1対の仮設内ケーブル14、16を緊張定着することも可能である。
【0045】
この場合、同図(a)に示すように、先端部に手延ガーダ44を装着した状態で図示矢印方向へ押し出す際には、仮設内ケーブル14、16を緊張定着した状態に維持しておき、同図(b)に示すように、押出しが完了した後、1対の仮設内ケーブル14、16の緊張力を解放し、これらを下床版42内から撤去するようにすればよい。
【図面の簡単な説明】
【図1】本願発明の一実施形態に係る仮設内ケーブルの緊張定着方法の適用対象となるPC橋を示す側面図
【図2】図1のII部詳細断面図
【図3】図2の要部詳細図
【図4】上記実施形態に使用される案内治具を単品で示す図
【図5】図2のVa部詳細図(a)およびそのVb−Vb 断面図(b)
【図6】上記実施形態の変形例を示す、図1と同様の図
【図7】従来例を示す、図1と同様の図
【図8】上記従来例を示す、図7のVIIIa 部詳細図(a)、および他の従来例を示す(a)と同様の図(b)
【符号の説明】
10 PC橋
12 上床版(床版)
12a、12b 小口
12c、12d ケーブル突出口
14 仮設内ケーブル(第1の仮設内ケーブル)
14a、16a 一端部
14b、16b 他端部
16 仮設内ケーブル(第2の仮設内ケーブル)
18 シース
20 定着具
22 Rチェア
24 ジャッキ
26 案内治具
26a 斜面状案内部
26b 凹溝状案内部
28 補強筋
28a 逆U字状部
28b 直線部
40 PC橋
42 下床版(床版)
44 手延ガーダ
[0001]
TECHNICAL FIELD OF THE INVENTION
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for fixing a tension in a temporary cable used for erection of a PC bridge (prestressed concrete bridge).
[0002]
[Prior art]
When a PC bridge is erected, a so-called temporary cable may be used, in which a tension is introduced only during the erection and the tension is released when the erection is completed.
[0003]
To fix the tension in the temporary cable, place the temporary cable in the floor slab of the PC bridge in the middle of construction, fix one end of the cable to the edge of the floor slab, and then introduce tension into the temporary cable. The other end is fixed at a predetermined position on the floor slab.
[0004]
At this time, when the cable capacity is large, as shown in FIGS. 7 and 8 (a), a concrete fixing protrusion 102a is constructed on the floor slab 102, and a pair of serially arranged fixing protrusions 102a are arranged. The opposite end 104a of the temporary internal cable 104 is crossed over the fixing projection 102a to perform tension fixing, and after the installation is completed, the fixing projection 102a is peeled off, or as shown in FIG. 8B. A concrete fixing projection member 106 is fixed on the floor slab 102 with a plurality of PC steel materials 108, and the opposite ends 104a of a pair of temporary internal cables 104 arranged in series are crossed to the fixing projection 102a. A method is adopted in which the tension fixing is performed by hanging, and after the erection is completed, the fixing projection member 106 is removed.
[0005]
[Problems to be solved by the invention]
However, the method shown in FIG. 8A requires a lot of labor and cost for the rebar arrangement of the fixing protrusions 102a (arrangement of the reinforcing bars 110 and the like), the installation work, and the hanging work after the completion of the installation. There is a problem that the structure is often undesirably damaged. Also, in the method shown in FIG. 8B, there is a problem that much work and cost are required for fixing and removing the fixing projection member 106.
[0006]
SUMMARY OF THE INVENTION The present invention has been made in view of such circumstances, and a tension of a temporary internal cable which can be easily and inexpensively fixed and fixed at a temporary internal cable used when constructing a PC bridge. It is an object to provide a fixing method.
[0007]
[Means for Solving the Problems]
The present invention achieves the above-mentioned object by using a movable fixing device to perform tension fixing on a pair of temporary cables arranged in series at once.
[0008]
That is, the tension fixing method of the temporary internal cable according to the present invention is as follows.
The temporary internal cable is arranged in the floor slab of the PC bridge in the middle of the erection, and one end of the temporary internal cable is fixed to the small opening of the floor slab. In the tension fixing method of the cable in the temporary, fixing the other end of the cable to a predetermined position of the floor slab,
After arranging the first and second temporary internal cables in series in the floor slab and fixing one end of each temporary internal cable on both ends in the series direction to the edge of the floor slab, The other end of the inner cable is bent up onto the floor slab and inserted and fixed in a movable fixing device, and the other end of the second temporary inner cable is bent up onto the floor slab and inserted into the fixing device. In this state, by pulling out the other end of the second temporary internal cable, tension is introduced to both the temporary internal cables.
[0009]
The “floor slab” may be an upper slab or a lower slab.
[0010]
The `` fixing device '' is configured so that each temporary internal cable is inserted in a substantially opposite direction to each other, and is configured to be displaceable on the floor slab when a tension is introduced. The specific configuration such as shape and material is not particularly limited.
[0011]
Operation and Effect of the Invention
As shown in the above configuration, the tension fixing method of the temporary internal cable according to the invention of the present application includes the first and second temporary internal cables arranged in series in the floor slab, each end of both sides in the serial direction of the floor slab. After being fixed to the fore edge, the other end of the first temporary internal cable is bent up onto the floor slab to be inserted and fixed in the movable fixing tool, and the other end of the second temporary internal cable is placed on the floor slab. Bending up and passing through the fixing device, and pulling out the other end of the second temporary cable in this state introduces tension into both the temporary cables. Can be obtained.
[0012]
That is, unlike the related art, there is no need to construct a concrete fixing projection on the floor slab or fix the concrete fixing projection member. Therefore, it is necessary to arrange, fix, and suspend the fixing projection. There is no need for an operation or an operation for fixing and removing the fixing projection member. Therefore, the labor and cost for this are not required, thereby shortening the construction period and reducing the cost.
[0013]
In addition, since tension fixing can be performed at once for a pair of temporary cables arranged in series, the number of work steps can be reduced by half as compared with the conventional case where tension is fixed for each temporary cable. In this regard, the construction period can be shortened and the cost can be reduced.
[0014]
As described above, according to the present invention, it is possible to easily and inexpensively carry out tension fixing, release, and removal of the intra-temporary cable used when constructing the PC bridge.
[0015]
In addition, in the present invention, since the movable fixing tool is used, it is possible to eliminate the possibility that the main body structure is undesirably damaged due to the hanging work of the fixing protrusion as in the related art.
[0016]
In the above configuration, if a guide jig for guiding the other end of each temporary cable to the fixing tool is arranged in the vicinity of both sides of the fixing tool in the serial direction on the floor slab, the inside of each temporary An unreasonable external force can be prevented from acting on the cable and the fixing device, so that the tension fixing operation can be performed smoothly. In addition, each of these guide jigs can be diverted when performing tension fixing work at another site.
[0017]
At this time, as each of these guide jigs, a slope-shaped guide portion for supporting the other end of each temporary internal cable from below, and a groove-shaped guide portion for preventing the other end of each temporary internal cable from laterally shifting. By using the one provided with the above, the tension fixing work can be performed more smoothly.
[0018]
Further, in the above configuration, a reinforcing bar for resisting a lifting force acting on each temporary internal cable at the time of the introduction of the tension is arranged at a position near the other end of each temporary internal cable in the floor slab. This can eliminate the possibility that the floor slab will be damaged when the temporary internal cable is tensioned and fixed.
[0019]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0020]
FIG. 1 is a side view showing a PC bridge to which a method for tensioning and fixing a temporary internal cable according to an embodiment of the present invention is applied. FIG. 2 is a detailed sectional view of a portion II in FIG. 3 is a detailed view of a main part of FIG.
[0021]
The PC bridge 10 shown in FIG. 1 is a PC bridge being erected (during cantilever extension of the main girder), and a pair of temporary cables 14 and 16 arranged in series in the upper floor slab 12 are strained. FIG. 6 is a diagram illustrating a fixed state.
[0022]
The tension fixing work of these temporary internal cables 14 and 16 is performed as follows.
[0023]
That is, first, both the temporary internal cables 14 and 16 are arranged in series in the upper floor slab 12 along the bridge axis direction. The arrangement of these temporary internal cables 14 and 16 is performed by inserting the temporary internal cables 14 and 16 through a sheath 18 embedded in the upper floor slab 12. Each of these temporary internal cables 14 and 16 is composed of a plurality (six) of PC steel strands.
[0024]
Then, one end portions 14a, 16a on both sides in the serial direction (both sides in the bridge axis direction) of the respective temporary internal cables 14, 16 are fixed to the small openings 12a, 12b of the upper floor slab 12 by wedges. On the other hand, the other end portions 14b and 16b of the temporary internal cables 14 and 16 are bent up and are projected obliquely upward from the cable outlets 12c and 12d of the upper floor slab 12.
[0025]
Then, the other end 14b of one temporary internal cable 14 (first temporary internal cable) is inserted and fixed (wedge-fixed) to the fixing device 20 on the upper floor slab 12, and the other temporary internal cable 16 (second internal cable) is fixed. The other end 16 b of the temporary internal cable) is inserted through the fixing device 20.
[0026]
In this state, the other end 16b of the temporary internal cable 16 is pulled out by the jack 24 attached to the fixing device 20 via the R chair 22, thereby introducing tension to both the temporary internal cables 14, 16. After the introduction of the tension is completed, the other end 16b of the temporary internal cable 16 is wedge-fixed to the fixing device 20, the R chair 22 and the jack 24 are removed, and the tension fixing operation is completed.
[0027]
The fixing device 20 is a movable steel fixing device, and is configured as a so-called cross-fixing device. That is, the fixing device 20 is formed in a box shape, and the respective temporary internal cables 14 and 16 are inserted in opposite directions, and the other end portions 14b and 16b of the respective temporary internal cables 14 and 16 are connected at both end surfaces. It has become established.
[0028]
Since the fixing device 20 is movable, it is displaced in the bridge axis direction with the introduction of tension. That is, in FIG. 3, the cable is to be displaced leftward due to the tension of the temporary internal cable 14, and is also displaced leftward when the temporary internal cable 16 is pulled out. Therefore, finally, the introduction of the tension is completed at a position displaced leftward by a predetermined amount from the original position (the position indicated by the two-dot chain line).
[0029]
After the installation of the PC bridge 10 is completed, the tensions of the two temporary cables 14 and 16 thus fixed in tension are released and removed from the upper floor slab 12. At that time, the release of the tension is performed by attaching the R chair 22 and the jack 24 to the fixing device 20 again.
[0030]
In the present embodiment, when performing the above-described tension fixing operation, the other end portions 14b and 16b of the respective temporary internal cables 14 and 16 are guided to the fixing device 20 on both sides in the bridge axis direction of the fixing device 20 on the upper floor slab 12. Guide jig 26 is arranged in advance.
[0031]
Each of these guide jigs 26 is a steel jig, and as shown in FIG. 4 alone, the other end of each of the temporary internal cables 14 and 16 projecting obliquely from inside the upper slab 12 onto the upper slab 12. A configuration having a slope-shaped guide portion 26a for supporting the portions 14b and 16b from below, and a groove-shaped guide portion 26b for preventing the other end portions 14b and 16b of the temporary cables 14 and 16 from laterally shifting. ing.
[0032]
The inclined guide portion 26a is formed in a convex curved shape, and thereby supports the respective temporary internal cables 14, 16 over a predetermined length. Further, the concave groove guide 26b is formed in a U-shape at the upper end of the slope of the slope guide 26a.
[0033]
Further, in the present embodiment, as shown in FIG. 2, when the upper floor slab 12 is driven, portions near the other end portions 14 b and 16 b of the respective temporary internal cables 14 and 16 in the upper floor slab 12 (specifically, In the upper floor slab 12, reinforcing bars 28 for resisting the lift acting on the respective temporary internal cables 14 and 16 at the time of the introduction of the tension are disposed at the cable protrusions 12 c and 12 d of the upper floor slab 12 near the bridge axial direction. It is supposed to keep. A plurality (three) of the reinforcing bars 28 are arranged for each of the cable protrusion ports 12c and 12d.
[0034]
These reinforcing bars 28 straddle the sheath 18 as shown in FIG. 5 (a) which is a detailed view of the Va portion in FIG. 2 and FIG. 5 (b) which is a cross-sectional view taken along line Vb-Vb in FIG. 5 (a). And a pair of linear portions 28b extending horizontally from the lower end of the inverted U-shaped portion 28a toward the cable outlet 12d (12c). ing.
[0035]
As described in detail above, in the present embodiment, one end portions 14a, 16a on both sides in the bridge axis direction of the pair of temporary internal cables 14, 16 arranged in series in the upper floor slab 12 along the bridge axis direction. Are fixed to the edges 12a, 12b of the upper floor slab 12, then the other end 14b of one of the temporary internal cables 14 is bent up onto the upper floor slab 12, and is fixedly inserted into the movable fixing device 20 while the other is fixed. The other end 16b of the temporary internal cable 16 is bent up onto the upper floor slab 12 and inserted into the fixing device 20, and in this state, the other end 16b of the temporary internal cable 16 is pulled out, thereby tensioning the two temporary internal cables 14,16. Since the force is introduced, the following operation and effect can be obtained.
[0036]
That is, unlike the related art, there is no need to construct a concrete fixing projection on the floor slab or fix the concrete fixing projection member. Therefore, it is necessary to arrange, fix, and suspend the fixing projection. There is no need for an operation or an operation for fixing and removing the fixing projection member. Therefore, the labor and cost for this are not required, thereby shortening the construction period and reducing the cost.
[0037]
Further, since the tension and fixing of the pair of temporary cables 14 and 16 arranged in series can be performed all at once, the number of work steps is reduced as compared with the conventional case where the tension and fixing are performed for each temporary cable individually. In this respect, the construction period can be shortened and the cost can be reduced.
[0038]
As described above, according to the present embodiment, tension fixation, release, and removal of the temporary cables 14, 16 used when the PC bridge 10 is erected can be easily and inexpensively performed.
[0039]
In addition, in the present embodiment, since the movable fixing device 20 is used, there is no possibility that the main body structure is undesirably damaged by the hanging operation of the fixing protrusion as in the related art. .
[0040]
Further, in the present embodiment, a guide jig for guiding the other end portions 14b, 16b of the respective temporary internal cables 14, 16 to the fixing device 20 at portions near both sides in the bridge axis direction of the fixing device 20 on the upper floor slab 12. 26 is arranged, it is possible to prevent an unreasonable external force from acting on each of the temporary internal cables 14 and 16 and the fixing device 20, and thus the tension fixing operation can be performed smoothly. . In addition, each of these guide jigs 26 can be diverted when performing tension fixing work at another site.
[0041]
At this time, in the present embodiment, as the respective guide jigs 26, the other end portions 14b, 16b of the respective temporary internal cables 14, 16 projecting obliquely from within the upper floor slab 12 onto the upper floor slab 12 are supported from below. Since the one having the slope-shaped guide portion 26a and the groove-shaped guide portion 26b for preventing the other end portions 14b, 16b of the respective temporary internal cables 14, 16 from laterally shifting is used, the tension fixing work is further improved. It can be done smoothly.
[0042]
Further, in the present embodiment, the upper floor slab 12 is provided with a portion in the vicinity of both sides of the cable protruding ports 12c and 12d in the bridge axis direction in order to resist lift acting on the respective temporary internal cables 14 and 16 at the time of introducing the tension. Since the reinforcing bars 28 are arranged, it is possible to eliminate the possibility that the upper slab 12 is damaged when the temporary internal cables 14 and 16 are fixed in tension. In the present embodiment, it has been described that three cables are provided for each of the temporary cables 14 and 16, but four or more cables may be provided, or two or less cables may be provided. Is also good.
[0043]
By the way, in the present embodiment, the case where the temporary internal cables 14 and 16 arranged in the upper floor slab 12 are tensioned and fixed during the erection of the PC bridge 10 by cantilevering the main girder, In other cases, the tension fixing method of the temporary cable according to the present embodiment can be applied.
[0044]
For example, as shown in FIG. 6, during the construction of the PC bridge 40 by the extrusion method, the pair of temporary cables 14 and 16 arranged in the lower floor slab 42 can be tensioned and fixed.
[0045]
In this case, as shown in FIG. 3A, when pushing out in the direction of the arrow in the drawing with the hand-extended girder 44 attached to the distal end, the temporary internal cables 14 and 16 are maintained in a tension-fixed state. As shown in FIG. 13B, after the extrusion is completed, the tension of the pair of temporary internal cables 14 and 16 may be released, and these may be removed from the lower floor slab 42.
[Brief description of the drawings]
FIG. 1 is a side view showing a PC bridge to which a tension fixing method for a temporary internal cable according to an embodiment of the present invention is applied. FIG. 2 is a detailed sectional view of a portion II in FIG. 1 FIG. FIG. 4 is a diagram showing the guide jig used in the above embodiment as a single item. FIG. 5 is a detailed view of the Va portion in FIG. 2 (a) and a cross-sectional view of the same taken along line Vb-Vb (b).
6 is a view similar to FIG. 1 showing a modification of the above embodiment; FIG. 7 is a view similar to FIG. 1 showing a conventional example; FIG. 8 is a view showing the above conventional example; FIG. (A) and FIG. (B) similar to (a) showing another conventional example.
[Explanation of symbols]
10 PC bridge 12 Upper floor slab (floor slab)
12a, 12b Small mouth 12c, 12d Cable outlet 14 Temporary internal cable (first temporary internal cable)
14a, 16a One end 14b, 16b Other end 16 Temporary internal cable (second temporary internal cable)
18 Sheath 20 Fixing tool 22 R chair 24 Jack 26 Guide jig 26a Slope guide 26b Groove guide 28 Reinforcing bar 28a Inverted U-shaped section 28b Straight section 40 PC bridge 42 Lower deck (floor deck)
44 Tenobu girder

Claims (4)

架設途中のPC橋の床版内に仮設内ケーブルを配置するとともに、この仮設内ケーブルの一端部を上記床版の小口に固定した後、この仮設内ケーブルに緊張力を導入して該仮設内ケーブルの他端部を上記床版の所定位置に定着する、仮設内ケーブルの緊張定着方法において、
上記床版内に第1および第2の仮設内ケーブルを直列に配置するとともに、これら各仮設内ケーブルにおける直列方向両側の一端部を上記床版の小口に各々固定した後、上記第1の仮設内ケーブルの他端部を上記床版上へ曲げ上げて可動式の定着具に挿通固定するとともに上記第2の仮設内ケーブルの他端部を上記床版上へ曲げ上げて上記定着具に挿通させ、この状態で上記第2の仮設内ケーブルの他端部を引き出すことにより上記両仮設内ケーブルに緊張力を導入する、ことを特徴とする仮設内ケーブルの緊張定着方法。
The temporary internal cable is arranged in the floor slab of the PC bridge in the middle of the erection, and one end of the temporary internal cable is fixed to the small opening of the floor slab. In the tension fixing method of the cable in the temporary, fixing the other end of the cable to a predetermined position of the floor slab,
After arranging the first and second temporary internal cables in series in the floor slab and fixing one end of each temporary internal cable on both ends in the series direction to the edge of the floor slab, The other end of the inner cable is bent up onto the floor slab and inserted and fixed in a movable fixing device, and the other end of the second temporary inner cable is bent up onto the floor slab and inserted into the fixing device. And tensioning the two temporary cables by pulling out the other end of the second temporary cable in this state.
上記床版上における上記定着具の上記直列方向両側近傍部位に、上記各仮設内ケーブルの他端部を上記定着具に案内するための案内治具を配置しておく、ことを特徴とする請求項1記載の仮設内ケーブルの緊張定着方法。A guide jig for guiding the other end of each of the temporary internal cables to the fixing tool is disposed at a position near the both sides of the fixing tool in the serial direction on the floor slab. Item 2. The tension fixing method of the temporary internal cable according to Item 1. 上記各案内治具として、上記各仮設内ケーブルの他端部を下方から支持する斜面状案内部と、上記各仮設内ケーブルの他端部の横ずれを防止するための凹溝状案内部とを備えたものを用いる、ことを特徴とする請求項2記載の仮設内ケーブルの緊張定着方法。As each of the guide jigs, a slope-shaped guide portion that supports the other end of each of the temporary cables from below, and a groove-shaped guide portion that prevents the other end of each of the temporary cables from laterally shifting. The tension fixing method for a temporary internal cable according to claim 2, wherein a cable provided is used. 上記床版内における上記各仮設内ケーブルの他端部近傍部位に、上記緊張力導入の際に上記各仮設内ケーブルに作用する揚力に抵抗するための補強筋を配置しておく、ことを特徴とする請求項1〜3いずれか記載の仮設内ケーブルの緊張定着方法。A reinforcing bar for resisting a lift acting on each of the temporary cables at the time of the introduction of the tension is disposed at a position near the other end portion of each of the temporary cables in the floor slab. The tension fixing method for a temporary internal cable according to claim 1.
JP2002226823A 2002-08-05 2002-08-05 Tension fixing method of temporary cable Pending JP2004068332A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002226823A JP2004068332A (en) 2002-08-05 2002-08-05 Tension fixing method of temporary cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002226823A JP2004068332A (en) 2002-08-05 2002-08-05 Tension fixing method of temporary cable

Publications (1)

Publication Number Publication Date
JP2004068332A true JP2004068332A (en) 2004-03-04

Family

ID=32014032

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002226823A Pending JP2004068332A (en) 2002-08-05 2002-08-05 Tension fixing method of temporary cable

Country Status (1)

Country Link
JP (1) JP2004068332A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011190616A (en) * 2010-03-15 2011-09-29 Sumitomo Mitsui Construction Co Ltd Device and method for releasing tensioning force of tendon
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011190616A (en) * 2010-03-15 2011-09-29 Sumitomo Mitsui Construction Co Ltd Device and method for releasing tensioning force of tendon
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge

Similar Documents

Publication Publication Date Title
JP2004116081A (en) Reinforcing construction of existing structure and reinforcing method
JP2009068249A (en) Bridge construction method
JP3957680B2 (en) Assembling method of cable-stayed cable
JP2004068332A (en) Tension fixing method of temporary cable
KR20100066692A (en) Psc beam connection method for continuous bridge using plat anchorage apparatus
JP3608751B2 (en) Temporary fixing method of block in PC precast block method by non-coupler
KR20160029277A (en) Construction Method to Create Multi-span Continuity in PSC Bridges
JP3797560B2 (en) Bridge segment and its construction method
JP2010037833A (en) Bridge extrusion erection construction method
JPH0771007A (en) Temporary fixation method on construction of capital of bridge
JP2807845B2 (en) Construction method of diagonal material for Stypanel Bridge
JP4310379B2 (en) How to build a bridge
JP2011190616A (en) Device and method for releasing tensioning force of tendon
JP2714531B2 (en) How to install diagonal cable
JP2005047233A (en) Prestressed concrete member and its manufacturing method
JP2007126854A (en) Method of arranging reinforcements of reed-screen-shaped reinforcement unit, and reinforcement connection jig for use therein
JPH0860616A (en) Stretching method of cable
KR100442969B1 (en) Method and its devices to strengthen a bridge by external prestressing cable
JPH03151403A (en) Reinforcing method for existing bridge girder
JP2007217883A (en) Floor structure
JP2000120018A (en) Bridge having hollow section and constructing method therefor
JPH07331782A (en) Floor slab made of pc board
JP4000014B2 (en) Tension method of PC cable of bridge
JP3505662B2 (en) Precast concrete beam and method of using the beam
JP2612425B2 (en) Fixing method of unbonded PC steel strand

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050325

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070220

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070515

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070925