JP2002364776A - Gas pipe replacement construction method - Google Patents
Gas pipe replacement construction methodInfo
- Publication number
- JP2002364776A JP2002364776A JP2001168739A JP2001168739A JP2002364776A JP 2002364776 A JP2002364776 A JP 2002364776A JP 2001168739 A JP2001168739 A JP 2001168739A JP 2001168739 A JP2001168739 A JP 2001168739A JP 2002364776 A JP2002364776 A JP 2002364776A
- Authority
- JP
- Japan
- Prior art keywords
- gas
- gas pipe
- pipe
- air
- gas meter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 48
- 238000010926 purge Methods 0.000 claims abstract description 62
- 238000000034 method Methods 0.000 claims abstract description 19
- 238000012360 testing method Methods 0.000 abstract description 42
- 238000011144 upstream manufacturing Methods 0.000 abstract description 23
- 238000005070 sampling Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000002485 combustion reaction Methods 0.000 description 3
- 239000000203 mixture Substances 0.000 description 3
- 238000004458 analytical method Methods 0.000 description 2
- 230000000740 bleeding effect Effects 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 238000012795 verification Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000008034 disappearance Effects 0.000 description 1
- 238000004868 gas analysis Methods 0.000 description 1
- 238000004817 gas chromatography Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Measuring Volume Flow (AREA)
Abstract
(57)【要約】
【課題】ガス管交換工事における安全性を担保しつつ、
集合住宅の各住戸のガス機器の点火試験を簡略化するこ
とができるガス管交換工事方法を提供する。
【解決手段】本発明のガス管交換工事方法では、メイン
管と集合住宅のパイプシャフト内の立管をつなぐ灯外管
の交換後、灯外管とパイプシャフト内の立管との接続位
置に最も近い(最上流)ガスメータ部分だけで空気パー
ジを実施する。最上流のガスメータ部分で空気パージを
実施することにより、集合住宅内のガス管内の残留空気
がほとんどない状態となり、空気パージを実施したガス
メータ以外のガスメータの住戸についての点火試験が不
要となる。
(57) [Abstract] [Problem] While ensuring safety in gas pipe replacement work,
Provided is a gas pipe replacement construction method capable of simplifying an ignition test of gas appliances in each dwelling unit of an apartment house. In a gas pipe replacement method according to the present invention, after a lamp outer tube connecting a main pipe and a standpipe in a pipe shaft of an apartment house is replaced, the gas pipe is replaced at a connection position between the lamp outer pipe and a standpipe in the pipe shaft. The air purge is performed only at the nearest (most upstream) gas meter section. By performing the air purge at the gas meter section at the most upstream, there is almost no residual air in the gas pipe in the apartment house, and the ignition test on the dwelling units of the gas meters other than the gas meter on which the air purge has been performed becomes unnecessary.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、ガス管の交換工事
方法に関し、特に、ガス管の交換後において、取り替え
られた新しいガス管内の空気を抜く空気パージ処理につ
いて、空気パージ後の各住戸内のガス機器の点火試験を
簡略化することができるガス管交換工事方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for replacing gas pipes, and more particularly to an air purge process for removing air from a new gas pipe after replacement of a gas pipe. The present invention relates to a gas pipe replacement construction method capable of simplifying an ignition test of a gas appliance.
【0002】[0002]
【従来の技術】図4は、従来におけるガス交換工事方法
を説明する図である。図4に示されるように、道路の地
下などに埋設されるメイン管1から、灯外管2が地中で
集合住宅10に延び、灯外管2は、集合住宅直下でパイ
プシャフト内の立管3aと接続している。図示される場
合のように、集合住宅に複数のパイプシャフトが配設さ
れている場合は、灯外管2はそれぞれのパイプシャフト
内の立管3aと接続している。各パイプシャフト内の立
管3aからは、集合住宅を構成する複数の住戸それぞれ
に対して、分岐管3bがガスメータMを介して各住戸内
に引き込まれている。2. Description of the Related Art FIG. 4 is a view for explaining a conventional gas exchange construction method. As shown in FIG. 4, a lamp outer tube 2 extends from a main pipe 1 buried underground to a ground to an apartment house 10 under the ground, and the lamp outer pipe 2 is located in a pipe shaft immediately below the apartment house. It is connected to the tube 3a. When a plurality of pipe shafts are provided in an apartment house as shown in the figure, the lamp outer tube 2 is connected to the standing pipe 3a in each of the pipe shafts. From the standing pipe 3a in each pipe shaft, a branch pipe 3b is drawn into each dwelling unit via the gas meter M for each of the plurality of dwelling units constituting the apartment house.
【0003】メイン管1とパイプシャフト内の立管3a
をつなぐ灯外管2については、経年劣化が進んだ場合
に、交換工事を行っている。この灯外管交換工事では、
工事前に、まず、灯外管2を引き込む集合住宅の各住戸
に対して、事前に工事の施工と当日工事完了時点での在
宅をチラシなどで依頼する。そして、工事当日、古い灯
外管2を新しい灯外管2に交換した後、あらかじめ選定
された箇所において、新しい灯外管内の空気を抜く処理
(空気パージ)を実施する。A main pipe 1 and a standpipe 3a in a pipe shaft
When the lamp outer tube 2 connecting the lamps deteriorates over time, replacement work is performed. In this lamp outer tube replacement work,
Prior to the construction, first, a request is made to each dwelling unit of the apartment house into which the lamp outer tube 2 is to be drawn in for the construction in advance and to be at home at the time of completion of the construction on a flyer or the like. Then, on the day of the construction, after replacing the old lamp outer tube 2 with the new lamp outer tube 2, a process (air purge) for bleeding air from the new lamp outer tube is performed at a previously selected location.
【0004】空気パージ箇所Pは、各パイプシャフトご
とに複数箇所選定され、例えば、交換した灯外管2に最
も近い(最上流)ガスメータや最も遠い(最下流)ガス
メータ、その間のガスメータなど複数のガスメータが任
意に選択される。そして、選択された各ガスメータにつ
いて、各パイプシャフト内の立管3aから分岐する分岐
管3bとガスメータMとの接続箇所をはずし、そこから
空気を抜く作業が行われる。その後、全住戸において、
集合住宅内のガス管(パイプシャフト内の立管3a及び
分岐管3bを含む)内の残留空気によるガス機器の燃焼
不良及び立ち消えを防止するために、工事関係者(ガス
会社担当者を含む)が各住戸を訪問し、住戸内のガス機
器の点火試験を行っている。A plurality of air purging points P are selected for each pipe shaft. For example, a plurality of gas meters, such as a gas meter closest (upstream) to the replaced lamp outer tube 2, a gas meter farthest (downstream), and a gas meter therebetween. A gas meter is arbitrarily selected. Then, for each of the selected gas meters, a connection point between the gas pipe M and the branch pipe 3b branched from the standing pipe 3a in each pipe shaft is removed, and the air is removed therefrom. After that, in all dwelling units,
Persons involved in construction work (including gas company personnel) to prevent gas equipment from being burned out and extinguished due to residual air in gas pipes (including the vertical pipe 3a and the branch pipe 3b in the pipe shaft) in the apartment house Visited each dwelling unit and conducted an ignition test of gas appliances in the dwelling unit.
【0005】このとき、不在の住戸については、工事関
係者は、特定の時間まで住人の帰宅を待ち、それ以降
は、「ガス機器使用前のガス会社への連絡、ガス会社に
よる点火試験実施」を依頼するチラシを配付し、ガス会
社の宿直者に業務を引き継ぐ。ガス会社の宿直者は、不
在であった住人から連絡を受けると、随時、点火試験の
ためにその住戸に出動し、全戸についての点火試験を実
施する。[0005] At this time, with regard to the unoccupied dwelling unit, the person in charge of construction waits for the resident to return home until a specific time, and thereafter, "contacts the gas company before using gas appliances, conducts an ignition test by the gas company" Distribute a flyer to request and take over the duties to the duties staff of a gas company. When receiving a notification from a resident who has been absent, the duties worker of the gas company is dispatched to the dwelling unit for an ignition test at any time, and conducts an ignition test for all the units.
【0006】[0006]
【発明が解決しようとする課題】しかしながら、工事当
日の在宅を依頼するチラシを配付しても、実際は不在宅
が相当数あり、特定時間(例えば、工事当日の夜19
時)内に全戸の点火試験を完了することは非常に困難で
あった。従って、不在者宅要員(ガス会社の宿直者)の
負担及びそのコストの増大を招き、また、工事の効率化
を阻害していた。また、近年における生活時間の多様化
により、不在宅者が相当数いることを前提としたガス管
交換工事方法が求められている。However, even if a flyer for requesting to stay at home on the day of construction is distributed, a considerable number of people are not at home and a specific time (for example, 19
It was very difficult to complete the ignition test for all units within (hour). Accordingly, the burden on the absentee housing personnel (nightkeepers of the gas company) and the cost thereof are increased, and the efficiency of construction is hindered. In addition, due to the diversification of life time in recent years, there is a demand for a gas pipe replacement construction method on the premise that a considerable number of absent persons are present.
【0007】そこで、本発明の目的は、ガス管交換工事
における安全性を担保しつつ、集合住宅の各住戸のガス
機器の点火試験を簡略化することができるガス管交換工
事方法を提供することにある。Accordingly, an object of the present invention is to provide a gas pipe replacement construction method capable of simplifying an ignition test of gas appliances in each dwelling unit of an apartment house while securing safety in gas pipe replacement work. It is in.
【0008】[0008]
【課題を解決するための手段】上記目的を達成するため
に、本発明のガス管交換工事方法では、メイン管と集合
住宅のパイプシャフト内の立管をつなぐ灯外管の交換
後、灯外管とパイプシャフト内の立管との接続位置に最
も近い(最上流)ガスメータ部分だけで空気パージを実
施する。In order to achieve the above object, in the gas pipe replacement method according to the present invention, after replacing a lamp outer tube connecting a main pipe and a standing pipe in a pipe shaft of an apartment house, the gas pipe replacement method is performed. The air purge is performed only at the gas meter portion closest to the connection position between the pipe and the standing pipe in the pipe shaft (upstream).
【0009】最上流のガスメータ部分で空気パージを実
施することにより、集合住宅内のガス管内の残留空気が
ほとんどない状態となり、空気パージを実施したガスメ
ータ以外のガスメータの住戸についての点火試験が不要
となる。[0009] By performing the air purge at the most upstream gas meter portion, there is almost no residual air in the gas pipes in the apartment house, and it is not necessary to perform an ignition test on the dwelling units of the gas meters other than the gas purged gas meter. Become.
【0010】例えば、上記目的を達成するための本発明
のガス管交換工事方法は、集合住宅を構成する複数の住
戸それぞれに引き込まれる少なくとも一つの第一のガス
管(パイプシャフト内の立管)と接続し、前記集合住宅
外に延びる第二のガス管(灯外管)を交換するガス管交
換工事方法において、前記第二のガス管を前記第一のガ
ス管から切り離して古いガス管から新しいガス管に交換
し、前記第一のガス管に接続する各住戸ごとの複数のガ
スメータすべてのうち前記新しいガス管に最も近い第一
のガスメータにおける前記第一のガス管との接続部分か
ら、前記新しいガス管内の空気を抜くための空気パージ
を実施することを特徴とする。For example, the gas pipe replacement construction method of the present invention for achieving the above object provides at least one first gas pipe (a standing pipe in a pipe shaft) drawn into each of a plurality of dwelling units constituting an apartment house. And a second gas pipe extending outside the apartment house (light tube), the second gas pipe is separated from the first gas pipe and the old gas pipe is separated from the old gas pipe. Replace with a new gas pipe, from the connection portion with the first gas pipe in the first gas meter closest to the new gas pipe among all the plurality of gas meters for each dwelling unit connected to the first gas pipe, An air purge for removing air in the new gas pipe is performed.
【0011】なお、前記最も近いガスメータの住戸が、
工事当日に不在の場合、工事当日に在宅である住戸のガ
スメータのうちで、前記新しいガス管に最も近いガスメ
ータと前記第一のガス管との接続部分で、前記新しいガ
ス管内の空気を抜くための空気パージが実施される。The nearest unit of the gas meter is:
In the case of absence on the day of the construction, among the gas meters of the dwelling units at home on the day of the construction, at the connection between the gas meter closest to the new gas pipe and the first gas pipe, to bleed the air in the new gas pipe Is performed.
【0012】そして、前記空気パージ実施後、前記最も
近いガスメータに対応する住戸内にあるガス機器の点火
試験については、必ず工事関係者により実施する。[0012] After the air purge is performed, an ignition test of a gas appliance in the dwelling unit corresponding to the nearest gas meter is always performed by a person in charge of construction.
【0013】そして、前記最も近いガスメータ以外のガ
スメータに対応する住戸内にあるガス機器の点火試験に
ついては、当該各住戸の住人に実施してもらうよう依頼
し、工事関係者は実施しない。[0013] Regarding the ignition test of the gas appliance in the dwelling unit corresponding to the gas meter other than the closest gas meter, the resident of each dwelling unit is requested to carry out the ignition test, and the person in charge of construction does not carry out the test.
【0014】または、前記最も近いガスメータ以外のガ
スメータに対応する住戸内にあるガス機器の点火試験に
ついては、特定の時刻が経過するまでに在宅の住戸に対
しては、工事関係者が実施し、特定の時刻が経過しても
不在の住戸に対しては、当該各住戸の住人に依頼するよ
うにしてもよい。[0014] Alternatively, the ignition test of the gas appliances in the dwelling unit corresponding to the gas meter other than the closest gas meter is carried out by a construction-related person for the dwelling unit at home before a specific time has passed. For a dwelling unit that is absent even after a specific time has passed, a request may be made to the resident of each dwelling unit.
【0015】なお、前記集合住宅が複数の第一のガス管
を有する場合、各第一のガス管ごとに、各第一のガス管
に接続する複数のガスメータであって、工事当日に在宅
である住戸のガスメータのうち、前記新しいガス管に最
も近いガスメータと前記第一のガス管との接続部分で、
前記新しいガス管内の空気を抜くための空気パージが実
施される。In the case where the apartment house has a plurality of first gas pipes, each of the first gas pipes has a plurality of gas meters connected to the first gas pipes. In a gas meter of a certain dwelling unit, at a connection portion between the gas meter closest to the new gas pipe and the first gas pipe,
An air purge is performed to remove the air in the new gas pipe.
【0016】また、前記第二のガス管を前記第一のガス
管から切り離す時間が所定時間以上の場合、前記第一の
ガスメータの上階にあるガスメータのうち前記新しいガ
ス管に最も近い第二のガスメータにおける前記第一のガ
ス管との接続部分でも、さらに空気パージを実施するよ
うにしてもよい。When the time for disconnecting the second gas pipe from the first gas pipe is a predetermined time or more, the second gas pipe closest to the new gas pipe among the gas meters on the upper floor of the first gas meter. The air purge may also be performed at the portion of the gas meter connected to the first gas pipe.
【0017】[0017]
【発明の実施の形態】以下、本発明の実施の形態につい
て説明する。しかしながら、本発明の技術的範囲が、本
実施の形態に限定されるものではない。Embodiments of the present invention will be described below. However, the technical scope of the present invention is not limited to the present embodiment.
【0018】図1は、本発明の実施の形態におけるガス
管交換工事方法の概略を説明する図である。本発明の実
施の形態におけるガス管交換工事方法では、メイン管1
と集合住宅10のパイプシャフト内の立管3aをつなぐ
灯外管2の交換後、新しい灯外管2内の空気を抜くため
の空気パージ箇所を、灯外管2とパイプシャフト内の立
管3aとの接続位置に最も近い(最上流)ガスメータ部
分(図1の位置P1)とする。FIG. 1 is a view for explaining an outline of a gas pipe replacement work method according to an embodiment of the present invention. In the gas pipe replacement method according to the embodiment of the present invention, the main pipe 1
After the replacement of the lamp outer tube 2 connecting the pipes 3a in the pipe shaft of the apartment house 10, an air purge point for bleeding air in the new lamp outer tube 2 is set up in the lamp pipe 2 and the pipe in the pipe shaft. A gas meter portion (position P1 in FIG. 1) closest to the connection position with 3a (most upstream).
【0019】発明者らは、以下に詳述するように、最上
流ガスメータMと分岐管3bとの接続部分(以下、ガス
メータ部分という場合ある)から空気パージを実施する
ことにより、それより下流(灯外管からより遠くに離れ
る方向であって、パイプシャフト内の立管3aに沿った
上階方向を含む)の集合住宅内のガス管(パイプシャフ
ト内の立て管3aや分岐管3bを含む)内に空気がほと
んど残留しないことを見いだした。As will be described in detail below, the present inventors carry out air purging from a connection portion (hereinafter, sometimes referred to as a gas meter portion) between the most upstream gas meter M and the branch pipe 3b, so that the air is purged further downstream (hereinafter, referred to as a gas meter portion). Gas pipes (including a vertical pipe 3a and a branch pipe 3b in a pipe shaft) in a collective house of a direction away from the lamp outer pipe and including a direction of an upper floor along a vertical pipe 3a in a pipe shaft. ) Was found to have very little air left.
【0020】そして、このことから、その最上流ガスメ
ータ部分、すなわち、分岐管3bとそのガスメータMと
をはずした箇所だけで空気パージ作業を行い、その後、
その最上流ガスメータの住戸については、工事関係者
(ガス会社担当者)が、必ずガス機器の点火試験を実施
し、それ以外の住戸については、必ずしも工事関係者に
よる点火試験を必要としないガス管交換工事方法を考案
した。From this, an air purge operation is performed only at the most upstream gas meter portion, that is, at a position where the branch pipe 3b and the gas meter M are removed, and thereafter,
For the most upstream gas meter dwelling unit, the person in charge of construction (the person in charge of the gas company) always conducts an ignition test on the gas equipment, and for other dwelling units, gas pipes that do not necessarily require an ignition test by the person in charge of construction. A replacement construction method was devised.
【0021】空気パージを実施したガスメータについて
は、空気パージ実施のために、ガスメータMを分岐管3
bからはずすので、そこからガスメータ内に空気が混入
する可能性があり、そのガスメータMの住戸内でのガス
機器の点火試験が必ず必要である。一方、集合住宅にお
けるそれ以外の住戸のガスメータについては、空気パー
ジを行わず、また、集合住宅内のガス管内の残留空気も
ほとんどないことから、当該他の住戸でのガス機器の立
ち消えの確率がゼロに近いため、チラシなどで、住人自
身により点火試験を依頼することとした。With respect to the gas meter on which the air purge has been performed, the gas meter M is connected to the branch pipe 3 to perform the air purge.
Since it is removed from b, there is a possibility that air may enter the gas meter from there, and an ignition test of the gas appliance in the dwelling unit of the gas meter M is necessarily required. On the other hand, for gas meters of other dwelling units in the apartment complex, the air purge is not performed, and there is almost no residual air in the gas pipes in the apartment complex. Because it is close to zero, the residents decided to request an ignition test using a flyer or the like.
【0022】このように、本発明の実施の形態における
ガス管交換工事方法によれば、灯外管の交換後の空気パ
ージを灯外管に最も近いガスメータ(最上流ガスメー
タ)部分だけで行うことにより、それより下流のガス管
(特に、パイプシャフト内の立管及び分岐管)内の残留
空気がほとんどない状態となることから、複数箇所で空
気パージを実施する必要がなくなり、さらに、最上流ガ
スメータの住戸以外の住戸での工事関係者による点火試
験が不要となる。これにより、工事関係者による点火試
験の負担が大幅に軽減され、工事の効率化、人件費の低
減を図ることができる。As described above, according to the gas pipe replacement method according to the embodiment of the present invention, the air purge after the replacement of the lamp outer tube is performed only at the gas meter (most upstream gas meter) closest to the lamp outer tube. As a result, there is almost no residual air in the gas pipes downstream of the gas pipes (particularly, standing pipes and branch pipes in the pipe shaft), so that it is not necessary to perform air purging at a plurality of locations. There is no need for an ignition test by a person involved in the construction of the gas meter at a dwelling unit other than the dwelling unit. As a result, the burden of the ignition test by the persons involved in the construction is greatly reduced, and the efficiency of the construction and the labor costs can be reduced.
【0023】以下に、本発明の実施の形態のガス管交換
工事方法の空気パージ作業を実施し、全戸で点火試験を
実施したときの調査結果について説明する。A description will be given below of the results of a survey performed when an air purge operation was performed in the gas pipe replacement method according to the embodiment of the present invention and an ignition test was performed on all the units.
【0024】調査内容 (1)対象:原則としてガスメータ数15個以上の鉄筋
系集合住宅 (2)方法:灯外管交換後、各集合住宅の各パイプシャ
フトに対して、最上流のガスメータ部分から空気パージ
を実施した後、全戸について点火試験を実施し、その際
の燃焼炎の状態を観察した。 (3)調査件数:建物数190棟、パイプシャフト数6
60本、ガスメータ数5420個 (4)調査結果Contents of the survey (1) Target: Reinforced apartment house with 15 or more gas meters in principle (2) Method: After replacing the lamp, replace the pipe shaft of each apartment house with the gas meter from the uppermost stream. After performing the air purge, an ignition test was performed on all the houses, and the state of the combustion flame at that time was observed. (3) Number of surveys: 190 buildings, 6 pipe shafts
60, 5420 gas meters (4) Survey results
【0025】[0025]
【表1】 [Table 1]
【0026】(5)検証結果:空気パージのためにガス
メータとガス管とを取り外した住戸では、94.5%の確率
で点火試験時に燃焼炎の立ち消えが観察されたが、それ
以外の取り外さなかったガスメータについては、立ち消
えは皆無であった。このように、空気パージを実施しな
かった大部分のガスメータの住戸については、立ち消え
は発生せず、住人自身による点火試験で十分に安全を担
保できることが確認できた。(5) Verification result: In a dwelling unit from which the gas meter and the gas pipe were removed for air purging, the burning flame was extinguished at the time of the ignition test with a probability of 94.5%, but the other gas meters were not removed. About, there was no disappearance. As described above, most of the gas meter dwelling units for which the air purging was not performed did not go out, and it was confirmed that sufficient safety could be ensured by the ignition test by the residents themselves.
【0027】次に、撤去予定建物を利用したガス分析試
験による調査結果について説明する。Next, the results of a gas analysis test using a building to be removed will be described.
【0028】調査内容 (1)対象:鉄筋4階建て(総戸数24戸、うち1戸は
休止)、灯外管口径50A及び40A (2)内容:図2のガス管図において、パイプシャフト
A、Cについては、交換された灯外管に最も近い最上流
ガスメータ、パイプシャフトBについては、最下流ガス
メータを空気パージ箇所Pに選択し、空気パージを実施
した。空気パージ実施後、図2に示される各サンプリン
グ位置Sからガスをサンプリングして、ガスクロマトグ
ラフィ法によりその組成分析を実施した。また、ガスの
サンプリング後、各住戸で点火試験を実施した。 (3)分析結果:図2の各サンプリング位置に、そこで
サンプリングされたガスの濃度を示した。 (4)検証結果:空気パージ後、図2の各位置でのガス
組成分析結果では、いずれのサンプリング位置でも、ガ
ス濃度は、80%以上あり、正常な燃焼を維持するのに
十分なガス組成であった。ただし、最上流ガスメータで
空気パージを実施したパイプシャフトA、Cにおけるガ
ス濃度は、図示されるように、全サンプリング位置でガ
ス濃度90%であって、さらにほぼ半数が99%以上で
あり、ほとんど残留空気がないことが確認された。これ
に対して、パイプシャフトBにおけるガス濃度は、正常
な燃焼を維持するのに必要な濃度であったが、パイプシ
ャフトA、Cにおけるガス濃度と比較すると低い濃度で
あり、最上流のガスメータで空気パージを実施する方
が、残留空気がより少なくなり、より好ましいことが確
認された。Details of the survey (1) Target: 4-story reinforced steel building (24 units in total, one of which is closed), lamp tube diameters 50A and 40A (2) Contents: Pipe shaft A in the gas pipe diagram of FIG. , C, the most upstream gas meter closest to the replaced lamp outer tube, and for the pipe shaft B, the most downstream gas meter was selected as the air purge point P, and air purging was performed. After the air purge, the gas was sampled from each sampling position S shown in FIG. 2, and the composition was analyzed by gas chromatography. After sampling the gas, an ignition test was performed at each dwelling unit. (3) Analysis result: The concentration of the gas sampled at each sampling position in FIG. 2 is shown. (4) Verification result: After the air purge, the gas composition analysis results at each position in FIG. 2 indicate that the gas concentration is 80% or more at any sampling position, and that the gas composition is sufficient to maintain normal combustion. Met. However, as shown in the figure, the gas concentrations in the pipe shafts A and C for which the air purge was performed by the uppermost stream gas meter were 90% at all sampling positions, and almost half of the gas concentrations were 99% or more. It was confirmed that there was no residual air. On the other hand, the gas concentration in the pipe shaft B was a concentration necessary to maintain normal combustion, but was lower than the gas concentration in the pipe shafts A and C. It was confirmed that the air purge was more preferable because the residual air was smaller.
【0029】上記調査結果から、灯外管の交換後、集合
住宅の各パイプシャフトそれぞれについて、最上流のガ
スメータ部分一箇所で空気パージを実施し、空気パージ
実施後、その最上流ガスメータの住戸でのみ、工事関係
者(ガス会社担当者)による点火試験を実施することと
した。From the above investigation results, after replacing the lamp outer tube, for each pipe shaft of the apartment house, an air purge is performed at one of the gas flow sections at the most upstream position, and after the air purge is carried out, the air is purged at the dwelling unit of the most upstream gas meter. Only for this, an ignition test was conducted by a person in charge of construction (a person in charge of the gas company).
【0030】これにより、ガス会社担当者は、集合住宅
の全戸に対する点火試験を実施が不要となり、安全を担
保しつつ、点火試験工程が簡略化され、工事全体の効率
化、短時間化が図られる。また、全戸に対して、在宅を
依頼する必要がなくなり、住人の負担も軽減することが
できる。This eliminates the need for the gas company staff to conduct an ignition test on all the units in the apartment house, simplifying the ignition test process while ensuring safety, and improving the efficiency and time of the entire construction. Can be In addition, it is not necessary to ask all the units to stay at home, and the burden on residents can be reduced.
【0031】図3は、本発明の実施の形態におけるガス
管交換工事方法の処理フローチャートである。図3にお
いて、まず、ガス管を交換する工事を実施する旨のチラ
シを全戸に対して配付する(S10)。そして、ガス会
社担当者が、あらかじめ、工事当日の在宅状況を聞き取
り調査し(S11)、灯外管の交換後の空気パージ箇所
を決定する(S12)。具体的には、空気パージ実施箇
所は、上述のように、集合住宅のパイプシャフトごと
に、交換される灯外管に最も近い最上流のガスメータ部
分であるが、在宅状況調査において、その最上流ガスメ
ータの住戸の住人が、工事当日に在宅であれば、その最
上流ガスメータを空気パージ箇所に決定する。一般に
は、最上流ガスメータは、集合住宅の一階におけるパイ
プシャフトに隣接する住戸のガスメータとなる。また、
最上流ガスメータの住戸の住人が工事当日に不在の場合
は、在宅する住戸のガスメータうちで灯外管に最も近い
ガスメータを、空気パージ箇所に決定する。FIG. 3 is a processing flowchart of the gas pipe replacement work method according to the embodiment of the present invention. In FIG. 3, first, a leaflet for performing a construction for replacing a gas pipe is distributed to all the houses (S10). Then, the person in charge of the gas company hears and investigates the home situation on the day of the construction in advance (S11), and determines the air purge location after the replacement of the lamp outer tube (S12). Specifically, as described above, the air purge execution point is, for each pipe shaft of an apartment house, the gas flow portion that is closest to the lamp outer tube to be replaced. If the resident of the gas meter's dwelling unit is at home on the day of construction, the most upstream gas meter is determined as the air purge location. Generally, the most upstream gas meter is a gas meter of a dwelling unit adjacent to a pipe shaft on the first floor of an apartment house. Also,
If the resident of the dwelling unit of the most upstream gas meter is absent on the day of the construction, the gas meter closest to the light bulb among the gas meters of the dwelling units at home is determined as the air purge point.
【0032】なお、空気パージ箇所に決定されたガスメ
ータの住戸には、空気パージ実施後、その住戸内で点火
試験を実施する旨を伝えておく。It should be noted that, after the air purge is performed, the fact that an ignition test is to be performed in the dwelling unit is informed to the dwelling unit of the gas meter determined to be the air purging location.
【0033】工事当日、灯外管をメイン管から切り離し
て古い灯外管から新しい灯外管に交換する(S13)。
そして、灯外管の交換後、上記ステップS12で決定し
た空気パージ箇所であるガスメータ部分で空気パージを
実施する(S14)。On the day of construction, the lamp outer tube is cut off from the main tube and replaced with an old lamp outer tube with a new lamp outer tube (S13).
After replacement of the lamp outer tube, air purging is performed at the gas meter portion, which is the air purging location determined in step S12 (S14).
【0034】空気パージ実施後、ステップS15におい
て、空気パージを実施したガスメータの住戸に対して
は、必ず工事関係者による点火試験を実施する必要があ
るので、特定の時刻(例えば工事当日の19時)までは
(S16)、工事関係者であるガス会社担当者が、その
空気パージ実施ガスメータの住戸の住人の在宅を確認し
て(S17)、ガス機器の点火試験を実施する(S1
8)。ステップS11において、事前に空気パージ実施
ガスメータのガス需要者の工事当日の在宅を確認してい
たが、その後の予定変更や急用などで、不在になる可能
性もある。従って、特定時刻を過ぎても、その住人が不
在の場合は、「ガス機器使用前のガス会社への連絡、ガ
ス会社による点火試験実施」を依頼するチラシを配付し
(S19)、工事関係者となるガス会社の宿直者に業務
を引き継ぐ(S20)。ガス会社の宿直者は、不在であ
った住人から連絡を受けると、点火試験のためにその住
戸に出動し、点火試験を実施する。After performing the air purging, in step S15, it is necessary to always perform an ignition test by a person related to the construction of the dwelling unit of the gas meter for which the air purging has been performed. ) To (S16), the person in charge of the gas company, who is a construction-related person, confirms that the resident of the dwelling unit of the air purge execution gas meter is at home (S17), and performs an ignition test of the gas equipment (S1).
8). In step S11, it was confirmed in advance that the gas consumer of the air purge execution gas meter was at home on the day of construction, but it may be absent due to a subsequent schedule change or urgent business. Therefore, if the resident is absent even after the specified time, a flyer for requesting “contacting the gas company before using the gas equipment and conducting an ignition test by the gas company” is distributed (S19), The duties are taken over by the duties of a gas company (S20). When receiving a notification from a resident who has been absent, the night worker of the gas company is dispatched to the dwelling unit for an ignition test and performs an ignition test.
【0035】一方、ステップS15において、空気パー
ジを実施していない他のガスメータの住戸に対しては、
必ずしも、工事関係者による点火試験は必要ないが、図
3の実施の形態では、特定時刻までに在宅している住戸
については(S21、S22)、工事関係者による点火
試験を実施する(S23)。On the other hand, in step S15, for the dwelling units of other gas meters for which air purging has not been performed,
Although an ignition test by a person involved in construction is not necessarily required, in the embodiment of FIG. 3, for a dwelling unit that is at home by a specific time (S21, S22), an ignition test by a person involved in construction is performed (S23). .
【0036】特定時刻を過ぎても不在の住人に対して
は、住人自身による点火試験を依頼するチラシを配付し
(S24)、工事関係者は、点火試験を実施しない。A flyer for requesting an ignition test by the resident is distributed to the resident who is absent even after the specified time (S24), and the person involved in the construction does not carry out the ignition test.
【0037】こうして、特定時刻を過ぎても不在の住人
に対しては、点火試験をする必要がなくなるので、工事
関係者の負担が著しく軽減され、工事コストの低減にも
寄与する。In this way, it is not necessary to perform an ignition test on a resident who is absent even after a specific time, so that the burden on construction personnel is significantly reduced, which also contributes to a reduction in construction costs.
【0038】なお、上記実施の形態において、灯外管2
の交換時においては、通常、古い灯外管をパイプシャフ
ト内の立管3aから切断して切り離してから、パイプシ
ャフト内の立管を新しい灯外管に接続するまで、立管内
に空気が混入するのを防止するために、立管3aの切断
面にはキャップがはめられる。In the above embodiment, the lamp outer tube 2
At the time of replacement, air is usually mixed into the standing lamp until the standing lamp in the pipe shaft is connected to the new standing lamp after the old lamp tube is cut off from the standing tube 3a in the pipe shaft. In order to prevent this, a cap is fitted on the cut surface of the standpipe 3a.
【0039】このとき、古い灯外管の切断に手間取るな
どして、灯外管を切断するのに時間がかかり、パイプシ
ャフト内の立管3aの切断面からの空気の混入が比較的
多いと判断される場合は、すべてのガスメータのうちで
灯外管に最も近いガスメータ部分(すなわち、最上流ガ
スメータ部分)に加えて、さらにその上階において灯外
管に最も近いガスメータ(以下、上流ガスメータとい
う)部分が、別の空気パージ箇所として選択され、空気
パージが実施されてもよい。空気の混入が多い場合は、
空気が上階部分まで達している場合があるからである。At this time, if it takes time to cut the old lamp tube by cutting the old lamp tube, it takes time to cut the lamp tube, and if there is a relatively large amount of air mixed in from the cut surface of the standing tube 3a in the pipe shaft. If it is determined, in addition to the gas meter portion closest to the lamp tube (that is, the most upstream gas meter portion) of all the gas meters, the gas meter closest to the lamp tube on the upper floor (hereinafter referred to as the upstream gas meter) ) Section may be selected as another air purge point and an air purge may be performed. If there is a lot of air,
This is because the air may reach the upper floor.
【0040】上階において空気パージを実施するかどう
かは、例えば、切断時間により判定される。切断時間が
あらかじめ決められた第1の時間より短い場合は、上階
における空気パージを実施する必要はなく、最上流ガス
メータ部分のみで空気パージが実施され、第1の時間以
上の場合に、次の上階部分における上流ガスメータ部分
での空気パージが実施される。Whether or not to perform the air purge on the upper floor is determined by, for example, the cutting time. If the cutting time is shorter than the predetermined first time, it is not necessary to perform the air purging on the upper floor, and the air purging is performed only in the most upstream gas meter portion. An air purge is performed in the upstream gas meter section in the upper floor section.
【0041】さらに、切断時間が第1の時間より長い第
2の時間以上の場合は、さらに多くの空気が混入したと
判断して、更なる上階部分における上流ガスメータ部分
での空気パージが実施されてもよい。すなわち、切断時
間に応じて、最上流ガスメータ部分に限らず、各階の上
流ガスメータ部分で空気パージを実施するかどうかが判
定される。上階においても、上流ガスメータ部分で空気
パージを実施することで、より下流のガスメータ部分で
空気パージする場合と比較して、集合住宅内ガス管内の
残留空気をより少なくすることができ、より高い安全性
を担保することができる。Further, when the cutting time is longer than the second time which is longer than the first time, it is determined that more air has been mixed in, and the air purging in the upstream gas meter portion in the further upper floor portion is performed. May be done. That is, it is determined whether or not to perform the air purge not only at the uppermost stream gas meter section but also at the upstream gas meter section on each floor according to the cutting time. Also on the upper floor, by performing the air purge in the upstream gas meter portion, the residual air in the gas pipe in the apartment house can be reduced and higher than in the case where the air purge is performed in the gas meter portion further downstream. Security can be ensured.
【0042】本発明の保護範囲は、上記の実施の形態に
限定されず、特許請求の範囲に記載された発明とその均
等物に及ぶものである。The scope of protection of the present invention is not limited to the above embodiments, but extends to the inventions described in the claims and their equivalents.
【0043】[0043]
【発明の効果】以上、本発明によれば、集合住宅につい
てのガス管交換工事において、ガス管交換後の空気パー
ジ実施後、全戸について点火試験を実施しなくとも、安
全を担保できる空気パージ箇所を選択するので、工事の
効率化、低コスト化が図られる。また、空気パージを実
施するガスメータの住戸の住人以外に対しては、工事当
日の在宅を依頼する必要がないので、住人の負担を軽減
させることができる。As described above, according to the present invention, in the gas pipe replacement work for an apartment house, after the air purge is performed after the gas pipe replacement, the air purge point can ensure the safety without performing the ignition test for all the units. Is selected, construction efficiency and cost reduction are achieved. In addition, since it is not necessary to request the resident of the gas meter that performs the air purging to be at home on the day of construction, the burden on the resident can be reduced.
【図1】本発明の実施の形態におけるガス管交換工事方
法の概略を説明する図である。FIG. 1 is a diagram schematically illustrating a gas pipe replacement work method according to an embodiment of the present invention.
【図2】建物内のガス管におけるサンプリング位置とそ
のガス濃度を示す図である。FIG. 2 is a diagram showing sampling positions in gas pipes in a building and their gas concentrations.
【図3】本発明の実施の形態におけるガス管交換工事方
法の処理フローチャートである。FIG. 3 is a processing flowchart of a gas pipe replacement construction method according to the embodiment of the present invention.
【図4】従来におけるガス交換工事方法を説明する図で
ある。FIG. 4 is a diagram illustrating a conventional gas exchange construction method.
1 メイン管 2 灯外管 3a 立管 3b 分岐管 M ガスメータ DESCRIPTION OF SYMBOLS 1 Main pipe 2 Lamp outer pipe 3a Standing pipe 3b Branch pipe M Gas meter
───────────────────────────────────────────────────── フロントページの続き (72)発明者 川島 健 東京都港区海岸一丁目5番20号 東京瓦斯 株式会社内 (72)発明者 和久井 幹雄 東京都港区海岸一丁目5番20号 東京瓦斯 株式会社内 (72)発明者 宮本 登 東京都港区海岸一丁目5番20号 東京瓦斯 株式会社内 Fターム(参考) 2F030 CC13 CF13 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Ken Kawashima 1-5-20 Kaigan, Minato-ku, Tokyo Inside Tokyo Gas Co., Ltd. (72) Mikio Wakui 1-5-20 Kaigan, Minato-ku, Tokyo Tokyo Gas Co., Ltd. (72) Inventor Noboru Miyamoto 1-5-20 Kaigan, Minato-ku, Tokyo Tokyo Gas Co., Ltd. F-term (reference) 2F030 CC13 CF13
Claims (4)
引き込まれる第一のガス管と接続し、前記集合住宅外に
延びる第二のガス管を交換するガス管交換工事方法にお
いて、 前記第二のガス管を前記第一のガス管から切り離して古
いガス管から新しいガス管に交換し、 前記第一のガス管に接続する各住戸ごとの複数のガスメ
ータすべてのうち前記新しいガス管に最も近い第一のガ
スメータにおける前記第一のガス管との接続部分で、前
記新しいガス管内の空気を抜くための空気パージを実施
することを特徴とするガス管交換工事方法。1. A gas pipe replacement work method for connecting a first gas pipe drawn into each of a plurality of dwelling units constituting an apartment house and replacing a second gas pipe extending outside the apartment house, The gas pipe is separated from the first gas pipe, and the old gas pipe is replaced with a new gas pipe, and among the plurality of gas meters for each dwelling unit connected to the first gas pipe, the gas pipe closest to the new gas pipe is used. A method of replacing a gas pipe, wherein an air purge for removing air from the new gas pipe is performed at a connection portion of the first gas meter with the first gas pipe.
合、工事当日に在宅である住戸のガスメータのうち、前
記新しいガス管に最も近いガスメータと前記第一のガス
管との接続部分で、前記新しいガス管内の空気を抜くた
めの空気パージを実施することを特徴とするガス管交換
工事方法。2. The gas meter closest to the new gas pipe among the gas meters of dwelling units which are at home on the day of construction, wherein the gas meter closest to the new gas pipe is located on the day of construction. A method of replacing a gas pipe, wherein an air purge for removing air from the new gas pipe is performed at a connection portion with the gas pipe.
一のガス管ごとに、各第一のガス管に接続する複数のガ
スメータであって、工事当日に在宅である住戸のガスメ
ータのうち、前記新しいガス管に最も近いガスメータと
前記第一のガス管との接続部分で、前記新しいガス管内
の空気を抜くための空気パージを実施することを特徴と
するガス管交換工事方法。3. The gas meter according to claim 1, wherein when the apartment house has a plurality of first gas pipes, a plurality of gas meters connected to each first gas pipe are provided for each first gas pipe. Then, among the gas meters of the dwelling units at home on the day of the construction, an air purge for removing air in the new gas pipe is performed at a connection portion between the gas meter closest to the new gas pipe and the first gas pipe. A gas pipe replacement method characterized by the following.
が所定時間以上の場合、前記第一のガスメータの上階に
あるガスメータのうち前記新しいガス管に最も近い第二
のガスメータにおける前記第一のガス管との接続部分で
も、さらに空気パージを実施することを特徴とするガス
管交換工事方法。4. The gas meter on the upper floor of the first gas meter according to any one of claims 1 to 3, wherein the time for disconnecting the second gas pipe from the first gas pipe is a predetermined time or more. A method of replacing a gas pipe, further comprising performing an air purge also at a connection portion of the second gas meter closest to the new gas pipe with the first gas pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001168739A JP3765735B2 (en) | 2001-06-04 | 2001-06-04 | Gas pipe replacement construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001168739A JP3765735B2 (en) | 2001-06-04 | 2001-06-04 | Gas pipe replacement construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002364776A true JP2002364776A (en) | 2002-12-18 |
JP3765735B2 JP3765735B2 (en) | 2006-04-12 |
Family
ID=19010920
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001168739A Expired - Lifetime JP3765735B2 (en) | 2001-06-04 | 2001-06-04 | Gas pipe replacement construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3765735B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005069346A (en) * | 2003-08-22 | 2005-03-17 | Osaka Gas Co Ltd | Air purge method of gas supply facility |
JP2008190915A (en) * | 2007-02-01 | 2008-08-21 | Toho Gas Co Ltd | Method for exchanging gas pipe |
-
2001
- 2001-06-04 JP JP2001168739A patent/JP3765735B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005069346A (en) * | 2003-08-22 | 2005-03-17 | Osaka Gas Co Ltd | Air purge method of gas supply facility |
JP4540317B2 (en) * | 2003-08-22 | 2010-09-08 | 大阪瓦斯株式会社 | Air purge method for gas supply equipment |
JP2008190915A (en) * | 2007-02-01 | 2008-08-21 | Toho Gas Co Ltd | Method for exchanging gas pipe |
Also Published As
Publication number | Publication date |
---|---|
JP3765735B2 (en) | 2006-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
TW569104B (en) | System for servicing and maintaining heat supply equipment | |
CN102740558A (en) | Method for controlling urban lighting facility based on intelligent terminal, intelligent terminal and system | |
O’rourke et al. | Lessons learned from the World Trade Center disaster about critical utility systems | |
TW201320018A (en) | Area monitoring system | |
JP2002364776A (en) | Gas pipe replacement construction method | |
CN109195030B (en) | Intelligent optical broadband fault repairing system based on optical modem alarm | |
CN108756990A (en) | Subway detour ventilating system with shield door and its operation method | |
CN200962683Y (en) | Intelligent radio control street lamp and cable theft prevention system device | |
JP4310768B2 (en) | Customer service server | |
CN208959212U (en) | A kind of fire hydrant and fire-fighting equipment | |
CN102764907A (en) | Indoor gas pipeline gas passing tapper and working method thereof | |
JP5063088B2 (en) | Street light management system | |
CN210159101U (en) | Portable new trend system in workshop of mill | |
CN106369652A (en) | Energy-saving self-control system used for concentrated lampblack exhaust system | |
CN101409886A (en) | Method for associating multimedia message event | |
CN205299089U (en) | City gas management system based on thing networking | |
CN207640870U (en) | A kind of intelligent fire ties system | |
CN208126440U (en) | Operation management system suitable for intelligent building | |
JP4165804B2 (en) | Customer service server | |
Davis | Quantifying post-earthquake water system functionality | |
CN212163798U (en) | High-speed railway tunnel lighting lamp remote monitering system | |
Zuidema et al. | Pantropical tree growth resilience to drought | |
CN109859443A (en) | NB-Iot and WIFI pattern of fusion gas alarm system and method | |
McGeehan et al. | Beneath cities, a decaying tangle of gas pipes | |
CN107454163A (en) | A kind of multiple terminals exhibition item interconnection displaying control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050126 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050802 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051003 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051108 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060124 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060124 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3765735 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100203 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100203 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110203 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120203 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120203 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130203 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140203 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |