JP2002363979A - Pile construction method - Google Patents
Pile construction methodInfo
- Publication number
- JP2002363979A JP2002363979A JP2001177130A JP2001177130A JP2002363979A JP 2002363979 A JP2002363979 A JP 2002363979A JP 2001177130 A JP2001177130 A JP 2001177130A JP 2001177130 A JP2001177130 A JP 2001177130A JP 2002363979 A JP2002363979 A JP 2002363979A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- hollow
- soil cement
- hollow pile
- footing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地上に建つ構造物
からの荷重を地盤に伝えるフーチングやフーチング梁な
どの下方に造成され、特にフーチングやフーチング梁な
どとの接続が容易なように、杭頭内部に鉄筋などのフー
チング接続用部材を挿入・固定するための空洞部を有す
る杭を施工するための杭の施工方法に関するものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a footing or footing beam for transmitting a load from a structure built on the ground to the ground, and particularly to a pile for easy connection with a footing or footing beam. The present invention relates to a pile construction method for constructing a pile having a cavity for inserting and fixing a footing connection member such as a reinforcing bar inside a head.
【0002】[0002]
【従来技術】近年、地上に建つ構造物を支持する基礎杭
として、ソイルセメントの中に鋼管を沈設して造成され
る鋼管ソイルセメント杭が採用されている。また、この
種の鋼管ソイルセメント杭の杭頭部と地上に建つ構造物
の基礎の一部として造成されるフーチングやフーチング
梁とを接合する方法として、鋼管ソイルセメント杭の杭
頭部に鉄筋などのフーチング接続用部材を突設し、この
フーチング接続用部材を介して鋼管ソイルセメント杭の
杭頭部とフーチングやフーチング梁とを一体的に接合す
る方法が採用されている。2. Description of the Related Art In recent years, a steel pipe soil cement pile formed by depositing a steel pipe in soil cement has been adopted as a foundation pile for supporting a structure built on the ground. In addition, as a method of joining the pile head of this type of steel pipe soil cement pile and the footing or footing beam created as a part of the foundation of the structure built on the ground, reinforcing steel etc. And a footing or footing beam is integrally joined to the pile head of the steel pipe soil cement pile via the footing connection member.
【0003】この場合、フーチング接続用部材は一般
に、鋼管ソイルセメント杭の杭頭部の鋼管内に挿入し、
その周囲にコンクリートを充填することで鋼管ソイルセ
メント杭の杭頭部に固定されているが、杭頭部の鋼管内
はソイルセメントで充填されているため、コンクリート
を充填するに際しては、あらかじめ杭頭部まで充填され
た鋼管内のソイルセメントを所定の深さまで除去する必
要がある。In this case, the footing connecting member is generally inserted into a steel pipe at the pile head of a steel pipe soil cement pile,
It is fixed to the pile head of the steel pipe soil cement pile by filling concrete around it, but since the steel pipe at the pile head is filled with soil cement, before filling concrete, the pile head is It is necessary to remove the soil cement in the steel pipe filled to a predetermined depth to a predetermined depth.
【0004】しかし、鋼管内の半ば硬化したソイルセメ
ントを完全に取り除くには相当の時間と費用を要し、杭
内部に付着したソイルセメントを完全に取り除くことは
非常に困難である。However, it takes a considerable amount of time and cost to completely remove the semi-hardened soil cement in the steel pipe, and it is very difficult to completely remove the soil cement attached to the inside of the pile.
【0005】このため、杭頭部の鋼管内にソイルセメン
トがどうしても残り易く、この残ったソイルセメントが
杭とコンクリートとの一体化を妨げる大きな要因とな
り、これに伴う様々な問題が提起されていた。For this reason, soil cement tends to remain in the steel pipe at the head of the pile, and the remaining soil cement is a major factor hindering the integration of the pile with the concrete, and various problems have been raised. .
【0006】具体的には、杭頭部の鋼管内、特に鋼管の
内側部にソイルセメントが残存していると、例えば地震
力などの外力によって上部構造物と杭間にせん断力が作
用した際にソイルセメントがコンクリートより早く破壊
する。このため、フーチング接続用部材が杭頭部にコン
クリートで強固に固定されていても、非常に耐力の低い
接続部にならざるを得なかった。More specifically, if soil cement remains in the steel pipe at the head of the pile, especially inside the steel pipe, when a shear force acts between the superstructure and the pile due to an external force such as seismic force, for example. Soil cement breaks down faster than concrete. For this reason, even if the footing connection member is firmly fixed to the pile head with concrete, it has to be a connection part with extremely low proof stress.
【0007】このような問題は、地中に鋼管を杭として
直接埋設した後、鋼管杭の杭頭部に詰まった土砂などを
除去する場合においても、鋼管の内側に土砂などが付着
することにより起こっていた。[0007] Such a problem is caused by the fact that soil and the like adhere to the inside of the steel pipe even when the soil and the like clogged at the pile head of the steel pipe pile are removed after the steel pipe is directly buried as a pile in the ground. Was happening.
【0008】ところで、これまで、杭頭部の鋼管内にソ
イルセメントが残存しない鋼管ソイルセメント杭を施工
するための杭の施工方法として、例えば特開平11−7
1574号公報に開示するような杭の施工方法が知られ
ている。[0008] By the way, as a method of constructing a steel pipe soil cement pile in which no soil cement remains in the steel pipe at the pile head, for example, Japanese Unexamined Patent Publication No.
A pile construction method disclosed in Japanese Patent No. 1574 is known.
【0009】本工法は、例えば図5に図示するように、
地中20内に形成したソイルセメント21内に杭として
鋼管22を沈設する前に、鋼管22の上端部内側にあら
かじめ鋼管22より小径の短管23を取付金具24を介
し、後から取り外しできるようにねじ24aによって取
り付けておくというものである。In this method, for example, as shown in FIG.
Before the steel pipe 22 is laid as a pile in the soil cement 21 formed in the underground 20, a short pipe 23 having a smaller diameter than the steel pipe 22 can be detached from the inside of the upper end of the steel pipe 22 in advance via the mounting bracket 24. Is attached to the device by screws 24a.
【0010】こうすることで、ソイルセメント20内に
鋼管22を上端部まで沈設した際、鋼管22の上端部分
においては、ソイルセメント20は鋼管22より小径の
短管23内に上昇し、鋼管22の内側には流入しない。
また、短管23内のソイルセメント21は硬化後、短管
23とともに除去することができる。By doing so, when the steel pipe 22 is sunk to the upper end in the soil cement 20, the soil cement 20 rises into the short pipe 23 having a smaller diameter than the steel pipe 22 at the upper end of the steel pipe 22, and Does not flow inside the
After hardening, the soil cement 21 in the short pipe 23 can be removed together with the short pipe 23.
【0011】[0011]
【発明が解決しようとする課題】しかし、この方法を採
用するには、図示するように特殊な内部構造の鋼管22
を杭として用意する必要があり、加工などの点で高コス
トとなる等の課題があった。However, in order to adopt this method, as shown in the drawing, a steel pipe 22 having a special internal structure is used.
There is a problem that it is necessary to prepare a stake as a pile, which increases the cost in terms of processing and the like.
【0012】本発明は、以上の課題を解決するためにな
されたもので、特に上述するような特殊構造の鋼管など
を用いないで、既製中空杭の杭頭部の内側にソイルセメ
ントや土砂などの残存を少なくすることができ、しかも
鋼管のみならず他の既製中空杭にも適用できる杭の施工
方法を提供することを目的とする。The present invention has been made in order to solve the above-mentioned problems, and in particular, without using a steel pipe having a special structure as described above, a soil cement, earth and sand, etc. are provided inside a pile head of a prefabricated hollow pile. It is an object of the present invention to provide a pile construction method which can reduce the remaining of piles and can be applied not only to steel pipes but also to other ready-made hollow piles.
【0013】[0013]
【課題を解決するための手段】請求項1記載の杭の施工
方法は、フーチングの下方にソイルセメントと複数の中
空杭とで造成される杭の施工方法において、最上段の中
空杭を所定の位置まで沈設できる深さを有するソイルセ
メントが存在しているとともに、前記ソイルセメント内
に最上段の中空杭を除く中空杭が沈設されている状態
で、前記中空杭内のソイルセメントを中空杭上端から少
なくとも中空杭外径のほぼ10倍程度に相当する深さま
で除去し、次に前記最上段の中空杭を接続し、この最上
段の中空杭をその杭頭部が前記フーチングの下端面より
上方に残存する位置まで前記ソイルセメント内に沈設す
ることを特徴とするものである。According to a first aspect of the present invention, there is provided a method of constructing a pile comprising a soil cement and a plurality of hollow piles below a footing. While the soil cement having a depth capable of sinking to the position is present and the hollow pile except the uppermost hollow pile is sunk in the soil cement, the soil cement in the hollow pile is removed from the top of the hollow pile. From at least a depth corresponding to at least about 10 times the outer diameter of the hollow pile, and then connect the uppermost hollow pile, and put the uppermost hollow pile above the lower end face of the footing. The soil cement is settled in the soil cement to a position where the soil cement remains.
【0014】請求項2記載の杭の施工方法は、フーチン
グの下方にソイルセメントと複数の中空杭とで造成され
る杭の施工方法において、ソイルセメントを形成しつつ
最上段の中空杭を除く中空杭を前記ソイルセメント内に
必要に応じて互いに接続しながら沈設し、次に前記中空
杭の下方に少なくとも前記最上段の中空杭の沈設長さに
相当する深さまでソイルセメントをさらに形成するとと
もに、前記中空杭内のソイルセメントを中空杭上端から
少なくとも中空杭外径のほぼ10倍程度に相当する深さ
まで除去し、次に前記最上段の中空杭を接続し、この最
上段の中空杭をその杭頭部が前記フーチングの下端面よ
り上方に残存する位置まで前記ソイルセメント内に沈設
することを特徴とするものである。According to a second aspect of the present invention, in the method for constructing a pile formed by soil cement and a plurality of hollow piles below the footing, a hollow excluding the uppermost hollow pile while forming the soil cement. Piles are sunk in the soil cement while being connected to each other as necessary, and then the soil cement is further formed below the hollow pile to at least a depth corresponding to the sunk length of the uppermost hollow pile, The soil cement in the hollow pile is removed from the upper end of the hollow pile to a depth corresponding to at least about 10 times the outer diameter of the hollow pile, and then the uppermost hollow pile is connected. The pile head is sunk in the soil cement to a position where the pile head remains above the lower end surface of the footing.
【0015】請求項3記載の杭の施工方法は、フーチン
グの下方にソイルセメントと複数の中空杭とで造成され
る杭の施工方法において、ソイルセメントを所定の深さ
まで形成し、次に最上段の中空杭を除く中空杭を前記ソ
イルセメント内に必要に応じて互いに接続しながら沈設
し、次に前記中空杭内のソイルセメントを中空杭上端か
ら少なくとも中空杭外径のほぼ10倍程度に相当する深
さまで除去し、次に前記最上段の中空杭を接続し、この
最上段の中空杭をその杭頭部が前記フーチングの下端面
より上方に残存する位置まで前記ソイルセメント内に沈
設することを特徴とするものである。According to a third aspect of the present invention, in the method for constructing a pile formed by soil cement and a plurality of hollow piles below the footing, the soil cement is formed to a predetermined depth, and then the uppermost step is formed. The hollow piles except for the hollow piles are sunk while being connected to each other in the soil cement as required, and then the soil cement in the hollow piles is at least about 10 times the outer diameter of the hollow piles from the upper end of the hollow piles. And then connecting the uppermost hollow pile, and sinking the uppermost hollow pile into the soil cement until the pile head remains above the lower end surface of the footing. It is characterized by the following.
【0016】上記いずれの杭の施工方法においても、最
上段の中空杭を沈設した後、最上段の中空杭内にフーチ
ング接続用部材として鉄筋などを建て込み、続いてコン
クリートを充填することにより、杭頭部に鉄筋などのフ
ーチング接続用部材を確実に固定することができる。こ
の場合、コンクリートは最上段の中空杭内に鉄筋などの
フーチング接続用部材を挿入した後すぐに、あるいは時
間をおいて後から充填してもよい。In any of the pile construction methods described above, after the uppermost hollow pile is laid, a reinforcing bar or the like is erected as a footing connecting member in the uppermost hollow pile, and then concrete is filled. A footing connection member such as a reinforcing bar can be securely fixed to the pile head. In this case, the concrete may be filled immediately after the footing connecting member such as a reinforcing bar is inserted into the uppermost hollow pile, or after a while.
【0017】本発明の杭の施工方法は、特に最上段の中
空杭をその中にソイルセメントが全く充填されない状態
でソイルセメント内に沈設できることで、最上段の中空
杭内に鉄筋などのフーチング接続用部材を容易に挿入で
き、またコンクリートも充分な量を確実に充填できて、
フーチング接続用部材を杭頭部に確実に固定できること
を特徴とするものである。The method for constructing a pile according to the present invention is particularly advantageous in that the uppermost hollow pile can be settled in the soil cement without being filled with soil cement at all. Components can be easily inserted and concrete can be filled in a sufficient amount,
The footing connection member can be securely fixed to the pile head.
【0018】また、杭頭部内に杭とコンクリートとの一
体化を妨げるようなソイルセメントが残存しない構造と
なるので、杭頭部にフーチング接続用部材を建て込んだ
後からコンクリートを充填することで、杭頭部にフーチ
ング接続用部材を一体的に固定でき、非常に耐力の高い
フーチング接続部を形成できることを特徴とするもので
ある。In addition, since the pile head has a structure in which soil cement that prevents the integration of the pile and the concrete does not remain in the pile head, concrete is filled after the footing connecting member is installed in the pile head. Thus, the footing connection member can be integrally fixed to the pile head, and a footing connection portion having extremely high proof stress can be formed.
【0019】さらに、中空杭として特に鋼管を採用する
ことで、杭内部の損傷を考慮することなくソイルセメン
トの除去作業を行なうことができるだけでなく、ソイル
セメントと鋼管が一体化された鋼管ソイルセメント杭を
造成することができる。Further, by adopting a steel pipe as the hollow pile, not only the soil cement can be removed without considering the damage inside the pile, but also the steel pipe soil cement in which the soil cement and the steel pipe are integrated. Piles can be created.
【0020】請求項4記載の杭の施工方法は、フーチン
グの下方に複数の中空杭で造成される杭の施工方法にお
いて、オーガーで地盤を掘削しつつ最上段の中空杭を除
く中空杭を必要に応じて互いに接続しながら掘削孔に建
て込み、次に前記中空杭の下方を前記最上段の中空杭を
建て込む長さに相当する深さまで前記オーガーにてさら
に掘削し、その下端に根固め部を形成し、次に前記オー
ガーを回収すると共に前記中空杭内の掘削土を中空杭上
端から少なくとも中空杭外径のほぼ10倍程度に相当す
る深さまで除去し、次に最上段の中空杭を接続し、かつ
この最上段の中空杭をその杭頭部が前記フーチングの下
端面より上方に残存する位置まで地中に建て込むことを
特徴とするものである。According to a fourth aspect of the present invention, in the method for constructing a pile formed by a plurality of hollow piles below the footing, a hollow pile excluding the uppermost hollow pile while excavating the ground with an auger is required. And then excavating the lower part of the hollow pile with the auger to a depth corresponding to the length in which the uppermost hollow pile is to be installed, and bolstering the lower end thereof. Part is formed, and then the auger is collected and excavated soil in the hollow pile is removed from the upper end of the hollow pile to a depth corresponding to at least about 10 times the outer diameter of the hollow pile. And the uppermost hollow pile is buried underground to a position where the pile head remains above the lower end surface of the footing.
【0021】請求項5記載の杭の施工方法は、フーチン
グの下方に複数の中空杭で造成される杭の施工方法にお
いて、地中に最上段の中空杭を除く中空杭を必要に応じ
て互いに接続しながら建て込み、次に前記中空杭内の土
を中空杭上端から少なくとも中空杭外径のほぼ10倍程
度の深さまで除去し、次に最上段の中空杭を接続し、か
つこの最上段の中空杭をその杭頭部が前記フーチングの
下端面より上方に残存する位置まで建て込むことを特徴
とするものである。According to a fifth aspect of the present invention, in the method for constructing a pile formed by a plurality of hollow piles below the footing, the hollow piles except for the uppermost hollow pile may be connected to each other as needed. Then, the soil in the hollow pile is removed from the upper end of the hollow pile to a depth of at least about 10 times the outer diameter of the hollow pile, and then the uppermost hollow pile is connected. Is built up to a position where the pile head remains above the lower end surface of the footing.
【0022】特に、請求項5記載の杭の施工方法は、地
中に中空杭を直接建て込む杭の施工方法であり、この場
合の中空杭として特に鋼管を採用した場合、鋼管の外周
に例えば蝶旋状の翼などを設け、回転させて直接地盤に
埋設することができる。In particular, the method for constructing a pile according to claim 5 is a method for constructing a pile in which a hollow pile is directly buried in the ground. A helical wing or the like can be provided and rotated to be directly buried in the ground.
【0023】また、請求項4記載の施工方法のように中
空杭内にオーガーを建て込み、オーガーで地盤を掘削し
ながら中空杭を降下させて施工する場合においても、さ
らに請求項5記載の施工方法のように中空杭を地中に回
転、打ち込みあるいは押し込むことにより直接建て込ん
で施工する場合においても、鋼管は捻りに強いことから
好ましく、さらに鋼管の場合、杭頭部では外周部が鋼管
となり、その中にコンクリートが充填された構造となる
ため、水平応力に対して耐力の非常に大きな杭を造成で
きる。Also, in the case where the auger is built in the hollow pile and the hollow pile is lowered while excavating the ground with the auger as in the construction method according to the fourth aspect, the construction according to the fifth aspect is further performed. Even when the hollow pile is directly erected by rotating, driving or pushing it into the ground as in the method, the steel pipe is preferable because it is resistant to twisting, and in the case of steel pipe, the outer periphery of the pile head becomes a steel pipe at the pile head. Since the structure is filled with concrete, a pile having a very high proof stress against horizontal stress can be formed.
【0024】[0024]
【発明の実施の形態】発明の実施の形態1.以下に本発
明の実施の形態について図面を用いて説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiment 1 of the Invention Hereinafter, embodiments of the present invention will be described with reference to the drawings.
【0025】図1(a)〜(h)は、中空杭1の下方に
ソイルセメント2を柱状に連続して形成しつつ、ソイル
セメント2内に中空杭1を沈設することによって、ソイ
ルセメント2と中空杭1とが一体化された杭を施工する
方法に、本発明の杭の施工法を適用した1例を示す工程
を順に示した図である。FIGS. 1 (a) to 1 (h) show that the soil cement 2 is continuously formed in a column shape below the hollow pile 1 and the hollow pile 1 is deposited in the soil cement 2 so that the soil cement 2 is formed. It is the figure which showed the process which shows one example which applied the pile construction method of this invention to the method of constructing the pile which integrated the hollow pile 1 with the hollow pile 1 in order.
【0026】 最初に、セメントミルク吐出口を備え
た掘削・攪拌ヘッド3を有するロツド4を中空杭1内に
挿入し、かつ掘削・攪拌ヘッド3を中空杭1の下端に突
出させて図(a)に図示するすような状態にセットす
る。First, a rod 4 having a drilling / mixing head 3 having a cement milk discharge port is inserted into the hollow pile 1, and the drilling / mixing head 3 is projected from the lower end of the hollow pile 1 (FIG. ) Is set as shown in FIG.
【0027】 次に、ロッド4を介して掘削・攪拌ヘ
ッド3を回転させながら中空杭1とともに地中に押し込
み、掘削・攪拌ヘッド3で地盤を掘削しながらセメント
ミルク吐出口から吐出されたセメントミルクと掘削土と
を攪拌・混合してソイルセメント2を掘進方向に柱状に
連続して形成する。同時に、造成される杭の長さに応じ
て必要があれば複数の中空杭1を接続しながら継ぎ足
す。なお、この場合の中空杭1として鋼管を使用する場
合、中空杭どうしは溶接によって接合してもい。また中
空杭1は回転させることなく、ソイルセメント2内に単
に押し込んで沈設してもよい。さらに、この場合の掘削
・攪拌ヘッド3とロツド4の構造は、ソイルセメント2
を形成できるものであればどのような装置でもよい。Next, the excavating / stirring head 3 is pushed into the ground together with the hollow pile 1 while rotating through the rod 4, and the excavating / stirring head 3 excavates the ground while extruding the cement milk from the cement milk discharge port. And the excavated soil are stirred and mixed to form the soil cement 2 continuously in a columnar shape in the direction of excavation. At the same time, if necessary according to the length of the pile to be formed, a plurality of hollow piles 1 are connected and added. When a steel pipe is used as the hollow pile 1 in this case, the hollow piles may be joined by welding. Further, the hollow pile 1 may be simply pushed into the soil cement 2 without being rotated, without being rotated. Further, in this case, the structure of the excavation / stirring head 3 and the rod 4 is
Any device can be used as long as it can form the device.
【0028】 こうして最上段の中空杭1(以下「上
端杭1a」という)を残して複数の中空杭1を地中に連
続して沈設し、上端杭1a(図面では鋼管杭の例を示
す)を接続する位置まで中空杭1を複数沈設し終えた
ら、中空杭1の沈設を停止する。In this way, a plurality of hollow piles 1 are continuously laid in the ground except for the uppermost hollow pile 1 (hereinafter referred to as “upper pile 1a”), and the upper pile 1a (an example of a steel pipe pile is shown in the drawing). When the plurality of hollow piles 1 have been laid down to the position where they are to be connected, the laying of the hollow piles 1 is stopped.
【0029】 次に、地中に沈設された中空杭1の下
方に、上端杭1aを沈設する長さに相当する深さまでソ
イルセメント2をさらに柱状に連続して形成し、そして
ソイルセメント2の下端部に根固め部5を形成する。こ
の状態を(b)に示す。この場合のソイルセメント2
は、ロツド4を介して掘削・攪拌ヘッド3を回転させな
がら地中に押し込み、掘削・攪拌ヘッド3で地盤を掘削
しながらセメントミルク吐出口から吐出されたセメント
ミルクと掘削土とを攪拌・混合することにより形成す
る。また、根固め部5はソイルセメント2の下端部分で
高濃度のセメントミルクを吐出することにより形成す
る。Next, below the hollow pile 1 submerged in the ground, a soil cement 2 is further continuously formed in a columnar shape to a depth corresponding to the length in which the upper pile 1a is submerged. A bolster 5 is formed at the lower end. This state is shown in FIG. Soil cement 2 in this case
Is pushed into the ground while rotating the excavating / mixing head 3 via the rod 4, and while excavating the ground with the excavating / mixing head 3, the cement milk discharged from the cement milk discharge port and the excavated soil are mixed and mixed. It forms by doing. The root consolidation part 5 is formed by discharging high-concentration cement milk at the lower end of the soil cement 2.
【0030】 次に、図(c),(d)に図示するよ
うに、中空杭1内を掘削・攪拌ヘッド3が通過できるよ
うに、土の掘削や攪拌に用いた掘削・攪拌ヘッド3の翼
を折り畳んで縮閉し、そして中空杭1内を引き上げてロ
ッド4を地上に回収する。Next, as shown in FIGS. 3 (c) and 3 (d), the excavation / agitation head 3 used for excavation and agitation of the soil is moved so that the excavation / agitation head 3 can pass through the hollow pile 1. The wings are folded and closed, and the hollow pile 1 is pulled up and the rod 4 is collected on the ground.
【0031】 次に、図(e)に図示するように、続
いて施工される上端杭1aの杭上端からの深さが杭の外
径のほぼ10倍程度に相当する深さHを超える位置まで
中空杭1内のソイルセメント2を除去する。この場合の
ソイルセメントを除去する方法としては、これまでと同
様にソイルセメント内に中空杭を沈設した後、杭頭部の
杭内からソイルセメントを除去する際に適用されてき
た、従来のソイルセメントの除去方法を適用してよい。Next, as shown in FIG. 5E, a position where the depth from the pile upper end of the upper pile 1a to be subsequently constructed exceeds the depth H corresponding to about 10 times the outer diameter of the pile. Until the soil cement 2 in the hollow pile 1 is removed. As a method of removing soil cement in this case, a conventional soil which has been applied to remove soil cement from the pile at the pile head after laying a hollow pile in the soil cement as before. A method for removing cement may be applied.
【0032】 次に、深さHを超える位置まで中空杭
1内のソイルセメント2を除去し終えたら、図(f)に
図示するように中空杭1の上端部に上端杭1aを溶接な
どで接続する。Next, after removing the soil cement 2 in the hollow pile 1 to a position exceeding the depth H, the upper end pile 1 a is welded to the upper end of the hollow pile 1 as shown in FIG. Connecting.
【0033】 次に、上端杭1aを必要ならば回転さ
せながらソイルセメント2内に沈降させる。この場合、
上端杭1aは杭頭部がフーチングの下端面より上方に残
存する位置まで沈降させ、かつ最下段の中空杭1の下端
部を根固め部5内に挿入する。この状態を図(g)に示
す。なお、上端杭1aの下端部に内蓋6を設けてもよ
く、この場合の蓋6は上端杭1aを沈設する際に空気抵
抗を受けないように空気抜き用の小穴を有するものが望
ましい。このように施工することで、図(g)に図示す
るように、後からコンクリートを充填する上端杭1a内
は、ソイルセメントが全く存在しない状態になってい
る。Next, the upper pile 1 a is settled in the soil cement 2 while rotating if necessary. in this case,
The upper pile 1a is settled to a position where the pile head remains above the lower end surface of the footing, and the lower end of the lowermost hollow pile 1 is inserted into the rooting portion 5. This state is shown in FIG. An inner lid 6 may be provided at the lower end of the upper pile 1a. In this case, the lid 6 desirably has a small hole for venting air so as not to receive air resistance when the upper pile 1a is laid. By constructing in this manner, as shown in FIG. 9G, the inside of the upper end pile 1a to be filled with concrete later is in a state where no soil cement is present.
【0034】 次に、上端杭1aの頭部内にフーチン
グ接続用部材として鉄筋7を挿入・固定し、続いて上端
杭1a内にコンクリート8を充填する。なお、この場合
の内蓋6は鉄筋7やコンクリート8が下方に落ちないよ
うにする受け部材の役割を果たすことができる。この状
態を(h)に示す。Next, a reinforcing bar 7 is inserted and fixed as a footing connection member in the head of the upper end pile 1a, and then, concrete 8 is filled in the upper end pile 1a. In this case, the inner lid 6 can function as a receiving member for preventing the reinforcing bar 7 and the concrete 8 from falling down. This state is shown in FIG.
【0035】発明の実施の形態2.図2(a)〜(h)
は、ソイルセメント2を柱状に連続して形成した後、ソ
イルセメント2内に中空杭1を沈設することによって、
ソイルセメント2と中空杭1とが一体化された杭を施工
する杭の施工方法に、本発明の施工法を適用した1例を
示す工程を順に示す図である。Embodiment 2 of the Invention FIG. 2 (a) to (h)
Is formed by continuously forming the soil cement 2 in a columnar shape, and then depositing the hollow pile 1 in the soil cement 2.
It is a figure which shows in order the process which shows one example which applied the construction method of this invention to the construction method of the pile which constructs the pile which integrated the soil cement 2 and the hollow pile 1.
【0036】 最初に、中空杭の全長を建て込む長さ
に相当する深さまでソイルセメント2を柱状に連続して
形成し、そしてその下端部に根固め部5を形成する。こ
の状態を図(b)に示す。ソイルセメント2を形成する
には、セメントミルク吐出口を備えた掘削・攪拌ヘッド
3を有するロツド4を使用し、図(a)に図示するよう
に、ロッド4介して掘削・攪拌ヘッド3を回転させなが
ら地中に押し込み、かつ掘削・攪拌ヘッド3で地盤を掘
削しながらセメントミルク吐出口から吐出されたセメン
トミルクと掘削土とを攪拌・混合する。また、根固め部
5はソイルセメント2の下端部分で特に高濃度のセメン
トミルクを吐出することにより形成する。なお、この場
合の掘削・攪拌ヘッド3およびロッド4の構造などにつ
いては、ソイルセメント2を形成できるものであればど
のような構造であってもよい。First, the soil cement 2 is continuously formed in a columnar shape to a depth corresponding to the length in which the entire length of the hollow pile is to be built, and a rooting portion 5 is formed at the lower end thereof. This state is shown in FIG. To form the soil cement 2, a rod 4 having a drilling / mixing head 3 having a cement milk discharge port is used, and the drilling / mixing head 3 is rotated via a rod 4 as shown in FIG. The cement milk discharged from the cement milk discharge port and the excavated soil are agitated and mixed while being pushed into the ground while excavating the ground with the excavation and agitation head 3. The root consolidation part 5 is formed at the lower end of the soil cement 2 by discharging particularly high-concentration cement milk. The structure of the excavation / stirring head 3 and the rod 4 in this case may be any structure as long as the soil cement 2 can be formed.
【0037】 次に、ソイルセメント2の形成が完了
したなら、掘削・攪拌ヘッド3を有するロツド4を回収
する。この状態を図(c)に示す。なお、以上の説明で
は、掘削・攪拌ヘッド3で掘進する際にセメントミルク
を吐出してソイルセメント2を形成したが、セメントミ
ルクを吐出しないで掘進し、掘削・攪拌ヘッド3を引き
上げる際に攪拌翼の上方の吐出口からセメントミルクを
吐出しつつ、掘削・攪拌ビット3を回転してセメントミ
ルクと掘削土とを攪拌・混合してソイルセメント2を形
成してもい。Next, when the formation of the soil cement 2 is completed, the rod 4 having the excavation / stirring head 3 is recovered. This state is shown in FIG. In the above description, when excavating with the excavating / stirring head 3, the cement milk is discharged to form the soil cement 2. However, when excavating without discharging the cement milk, the excavating / stirring head 3 is stirred up. The soil cement 2 may be formed by rotating the excavation / stirring bit 3 to stir / mix the cement milk and the excavated soil while discharging the cement milk from the discharge port above the wing.
【0038】 次に、図(d)に図示するように、ソ
イルセメント2内に中空杭1(要すれば複数の中空杭を
接続した状態のもの。図面では鋼管杭の例を示す。)を
沈設(例えば、杭を回転させながら埋設)する。この場
合、中空杭1として鋼管を使用する場合、杭どうしは溶
接によって接合してもい。また中空杭1は回転させるこ
となく、ソイルセメント2内に単に押し込んで沈設して
もよい。Next, as shown in FIG. 4D, a hollow pile 1 (a state in which a plurality of hollow piles are connected if necessary. An example of a steel pipe pile is shown in the drawing) is shown in a soil cement 2. Submerging (for example, burying while rotating the pile). In this case, when a steel pipe is used as the hollow pile 1, the piles may be joined by welding. Further, the hollow pile 1 may be simply pushed into the soil cement 2 without being rotated, without being rotated.
【0039】 次に、図(e)に示すように、上端杭
1aの杭上端からの深さが杭外径のほぼ10倍程度に相
当する深さHを超える位置まで中空杭1内のソイルセメ
ント2を除去する。なお、この場合のソイルセメントを
除去する方法としては、これまでと同様にソイルセメン
ト内に中空杭を沈設した後、杭頭部の杭内からソイルセ
メントを除去する際に適用されてきた、従来のソイルセ
メントの除去方法を適用することができる。Next, as shown in FIG. 4E, the soil in the hollow pile 1 is extended to a position where the depth from the upper end of the upper end pile 1a exceeds the depth H corresponding to about 10 times the outer diameter of the pile. The cement 2 is removed. As a method of removing soil cement in this case, the same method has been used to remove soil cement from the pile at the top of the pile after setting a hollow pile in the soil cement as before. The method of removing the soil cement can be applied.
【0040】 次に、深さHを超える位置まで中空杭
1内のソイルセメント2を除去し終えたら、図(f)に
図示するように中空杭1の上端部に上端杭1aを溶接な
どで接続する。そして、中空杭1aを必要ならば回転さ
せながらソイルセメント2内に沈降させる。この場合、
上端杭1aは杭頭部がフーチングの下端面より上方に残
存する位置まで沈降させ、かつ最下段の中空杭1の下端
部を根固め部5内に挿入する。この状態を図(g)に示
す。なお、この場合も上端杭1aの下端部に内蓋6を設
けるのが望ましい。このように施工することで、図
(g)に図示するように、後からコンクリートを充填す
る上端杭1a内は、ソイルセメントが全く存在しない状
態になっている。Next, after the soil cement 2 in the hollow pile 1 has been removed to a position exceeding the depth H, the upper pile 1a is welded to the upper end of the hollow pile 1 as shown in FIG. Connecting. Then, the hollow pile 1a is settled in the soil cement 2 while rotating if necessary. in this case,
The upper pile 1a is settled to a position where the pile head remains above the lower end surface of the footing, and the lower end of the lowermost hollow pile 1 is inserted into the rooting portion 5. This state is shown in FIG. Also in this case, it is desirable to provide the inner lid 6 at the lower end of the upper pile 1a. By constructing in this manner, as shown in FIG. 9G, the inside of the upper end pile 1a to be filled with concrete later is in a state where no soil cement is present.
【0041】 次に、上端杭1aの頭部内にフーチン
グ接続用部材として鉄筋7を挿入・固定し、続いて中空
杭1a内にコンクリート8を充填する。この状態を
(h)に示す。Next, a reinforcing bar 7 is inserted and fixed as a footing connection member in the head of the upper end pile 1 a, and then the hollow pile 1 a is filled with concrete 8. This state is shown in FIG.
【0042】発明の実施の形態3.図3(a)〜(h)
は、中空杭1にスクリューオーガー9を通し、このスク
リューオーガー9で掘削しながら掘削孔に中空杭1を建
て込んで杭を施工する杭の施工方法に、本発明の杭の施
工法を適用した1例を示す工程を順に示す図である。Embodiment 3 of the Invention FIG. 3 (a) to (h)
Applied the pile construction method of the present invention to a pile construction method in which a screw auger 9 is passed through a hollow pile 1 and the pile is constructed by embedding the hollow pile 1 in an excavation hole while excavating with the screw auger 9. It is a figure which shows the process which shows an example in order.
【0043】 最初に、中空杭1内にスクリューオー
ガー9を通し、図(a)に図示するような状態にセット
する。First, the screw auger 9 is passed through the hollow pile 1 and set in a state as shown in FIG.
【0044】 次に、スクリューオーガー9を回転さ
せ、中空杭1とともに地中に押し込み、スクリューオー
ガー9で地盤を掘り進む。また、地盤の掘削と並行し
て、造成される杭の長さに応じて必要ならば複数の中空
杭1を接続しながら継ぎ足す。なお、この場合の中空杭
1として鋼管を使用する場合、杭どうしは溶接によって
接合してもよい。また中空杭1は回転させながら掘削孔
内に押し込んで沈設してもよく、また回転させないで単
に押し込んで沈設してもよい。Next, the screw auger 9 is rotated and pushed into the ground together with the hollow pile 1, and the ground is dug by the screw auger 9. In parallel with the excavation of the ground, a plurality of hollow piles 1 are connected and added if necessary according to the length of the pile to be formed. When a steel pipe is used as the hollow pile 1 in this case, the piles may be joined by welding. Further, the hollow pile 1 may be pushed into the excavation hole while rotating, and may be sunk, or may be simply pushed without being rotated and sunk.
【0045】 次に、こうして上端杭1aを残して複
数の中空杭1を掘削孔内に沈設し、上端杭1a(図面で
は鋼管杭の例を示す)を接続する位置まで複数の中空杭
1を沈設し終えたら、中空杭1の沈設を停止する。Next, the plurality of hollow piles 1 are sunk in the excavation hole, leaving the upper pile 1a, and the plurality of hollow piles 1 are connected to a position where the upper pile 1a (an example of a steel pipe pile is shown in the drawing). When the settlement is completed, the settlement of the hollow pile 1 is stopped.
【0046】 次に、地中に沈設された中空杭1の下
方に、さらに連続する掘削孔を上端杭1aを沈設する長
さに相当する深さまで形成する。そして、掘削孔の下端
部分において、スクリューオーガー9の先端部から高濃
度のセメントミルクを吐出しつつ、スクリューオーガー
9を回転してセメントミルクと掘削土とを攪拌・混合す
ることにより根固め部5を形成する。そしてその後、図
(c)、(d)に図示するように、スクリューオーガー
9を地上に回収する。Next, a further continuous excavation hole is formed below the hollow pile 1 submerged in the ground to a depth corresponding to the length of submerging the upper pile 1a. At the lower end of the drilling hole, the screw auger 9 is rotated while the cement milk and the excavated soil are agitated and mixed while discharging high-concentration cement milk from the tip of the screw auger 9 to thereby fix the root consolidation portion 5. To form After that, the screw auger 9 is collected on the ground as shown in FIGS.
【0047】 次に、図(e)に図示するように、上
端杭1aの杭上端からの深さが杭外径のほぼ10倍程度
に相当する深さHを超える位置まで中空杭1内の掘削土
を除去する。この場合の掘削土を除去する方法として
は、これまでと同様に地中に中空杭を沈設した後、杭頭
部の杭内から掘削土を除去する際に適用されてきた、従
来の掘削土の除去方法を適用してよい。Next, as shown in FIG. 5E, the hollow pile 1 is moved to a position where the depth from the upper end of the upper end pile 1 a exceeds a depth H corresponding to about 10 times the outer diameter of the pile. Remove excavated soil. As a method of removing excavated soil in this case, a conventional excavated soil, which has been applied when removing excavated soil from the pile at the head of the pile after burying a hollow pile in the ground as before, May be applied.
【0048】 次に、深さHを超える位置まで中空杭
1内の掘削土を除去し終えたら、図(f)に示すように
中空杭1の上端部に上端杭1aを溶接などで接続する。
そして、上端杭1aを必要ならば回転させながら掘削土
内に沈降させる。この場合、上端杭1aは杭頭部がフー
チングの下端面より上方に残存する位置まで沈降させ、
かつ最下段の中空杭1の下端部を根固め部5内に挿入す
る。この状態を図(g)に示す。なお、この場合も上端
杭1aの下端部に内蓋6を設けるのが望ましい。このよ
うに施工することで、図(g)に図示するように、後か
らコンクリートを充填する上端杭1a内は、掘削土が全
く存在しない状態になっている。なお、上記の例では中
空杭内の掘削土を除去したが、スクリューオーガー9に
よる掘削時にセメントミルクを吐出してセメントミルク
と掘削土を混合・攪拌したソイルセメントとした場合
は、中空杭内のソイルセメントを除去すれば、内壁がソ
イルセメントに接触しない状態で上端杭1aを沈設する
ことができるので、コンクリート8を充填する上端杭1
aの内壁をソイルセメントが存在しないものとすること
ができる。Next, after removing the excavated soil in the hollow pile 1 to a position exceeding the depth H, the upper pile 1a is connected to the upper end of the hollow pile 1 by welding or the like as shown in FIG. .
The upper pile 1a is settled in the excavated soil while rotating if necessary. In this case, the upper pile 1a is settled to a position where the pile head remains above the lower end face of the footing,
In addition, the lower end of the lowermost hollow pile 1 is inserted into the foundation 5. This state is shown in FIG. Also in this case, it is desirable to provide the inner lid 6 at the lower end of the upper pile 1a. By constructing in this manner, as shown in FIG. 9G, the inside of the upper end pile 1a to be filled with concrete later has no excavated soil. In the above example, the excavated soil in the hollow pile was removed. However, when excavating with the screw auger 9, cement milk was discharged to mix and agitate the cement milk and excavated soil to obtain soil cement. If the soil cement is removed, the upper pile 1a can be laid without the inner wall in contact with the soil cement.
The inner wall of a may be free of soil cement.
【0049】 次に、上端杭1aの頭部内にフーチン
グ接続用部材として鉄筋7を挿入・固定し、続いて上端
杭1a内にコンクリート8を充填する。この場合も、上
端杭1aの下端部に内蓋6を取り付ける。この状態を
(h)に示す。Next, a reinforcing bar 7 is inserted and fixed as a footing connection member in the head of the upper end pile 1a, and then, the concrete 8 is filled in the upper end pile 1a. Also in this case, the inner lid 6 is attached to the lower end of the upper end pile 1a. This state is shown in FIG.
【0050】発明の実施の形態4.図4(a)〜(f)
は、中空杭1を地中に直接建て込んで施工する杭の施工
方法に、本発明の杭の施工方法を適用した例を示す図で
ある。Embodiment 4 of the Invention FIG. 4 (a) to (f)
FIG. 3 is a diagram showing an example in which the pile construction method of the present invention is applied to a pile construction method in which a hollow pile 1 is directly buried in the ground and constructed.
【0051】 最初に、地中に中空杭1を図(a)に
図示するように沈設する。沈設方法は打撃工法や押し込
み工法でもよいが、杭の先端に掘削刃となるような刃を
設けたり、螺旋羽根を設けたりして、回転により沈設し
やすくした中空杭を採用すれば、騒音問題もなく望まし
い。その点で中空杭としては鋼管が好ましい。First, the hollow pile 1 is laid underground as shown in FIG. The submersion method may be a striking method or a push-in method. Not desirable. In that respect, a steel pipe is preferable as the hollow pile.
【0052】 次に、図(b)に図示するように、上
端杭1aを接続する位置まで中空杭1を沈設したなら、
図(c)に図示するように、上端杭1aの杭上端からの
深さが杭外径のほぼ10倍程度に相当する深さHを超え
る位置まで杭内に入り込んだ土を除去する。この場合の
土を除去する方法としては、これまでと同様に地中に中
空杭を沈設した後、杭頭部の杭内から土を除去する際に
適用されてきた、従来の土の除去方法を適用してよい。Next, as shown in FIG. 5B, when the hollow pile 1 is laid down to a position where the upper end pile 1a is connected,
As shown in FIG. (C), the soil that has entered the pile is removed to a position where the depth of the upper end pile 1a from the upper end of the pile exceeds a depth H corresponding to approximately 10 times the outer diameter of the pile. As a method of removing soil in this case, a conventional soil removal method that has been applied when soil is removed from inside the pile at the head of the pile after burying a hollow pile in the ground as before. May be applied.
【0053】 次に、上記の深さHを超える位置まで
中空杭1内の土を除去したら、図(d)に図示するよう
に上端杭1aを溶接などで接続し、そして必要ならば上
端杭1aを回転させながら地盤中に沈降させる。このよ
うに施工することで、上端杭1a内は、土が全く存在し
ない状態になっている。Next, after the soil in the hollow pile 1 is removed to a position exceeding the depth H, the upper pile 1a is connected by welding or the like as shown in FIG. Settle into the ground while rotating 1a. With this construction, the inside of the upper end pile 1a is in a state where no soil is present.
【0054】 次に、上端杭1aの頭部内にフーチン
グ接続用部材として鉄筋7を挿入・固定し、続いて中空
杭1a内にコンクリート8を充填する。この状態を
(f)に示す。Next, a reinforcing bar 7 is inserted and fixed as a footing connecting member in the head of the upper end pile 1a, and then the hollow pile 1a is filled with concrete 8. This state is shown in FIG.
【0055】以上、図1から図4を用いて本発明の杭の
施工方法の実施の形態の例を説明したが、通常の杭の施
工に使用される矢蛸を用いて、上端杭の頭部を地表面か
ら下方に位置させることもできる。The example of the embodiment of the pile construction method according to the present invention has been described above with reference to FIGS. 1 to 4. The part may be located below the ground surface.
【0056】[0056]
【発明の効果】本発明は以上説明したとおりであり、特
に最上段の中空杭をその中にソイルセメントや土などが
全く充填されない状態で施工できることで、最上段の中
空杭内に鉄筋などのフーチング接続用部材を容易に挿入
でき、またコンクリートも充分な量を確実に充填できる
ため、フーチング接続部材を杭頭部に確実に固定でき
る。The present invention has been described above, and in particular, since the uppermost hollow pile can be constructed without any soil cement or soil being filled therein, the reinforcing pile or the like is provided in the uppermost hollow pile. Since the footing connecting member can be easily inserted, and a sufficient amount of concrete can be surely filled, the footing connecting member can be securely fixed to the pile head.
【0057】また、中空杭内に残存したソイルセメント
や土などでコンクリートと中空杭との一体性が妨げられ
ることもないので、杭頭部にフーチング接続用部材を一
体的に固定でき、非常に耐力の高いフーチング接続部を
形成できる。Further, since the integrity of the concrete and the hollow pile is not hindered by soil cement or soil remaining in the hollow pile, the footing connecting member can be integrally fixed to the pile head. A footing connection with high proof stress can be formed.
【0058】さらに、中空杭として特に鋼管を採用する
ことで、杭内部の損傷を考慮することなくソイルセメン
トや土などの除去作業を行なうことができ、またソイル
セメントを併用した場合、ソイルセメントと鋼管とが一
体化された鋼管ソイルセメント杭を造成することができ
る。Furthermore, by adopting a steel pipe as the hollow pile, it is possible to remove soil cement and soil without taking into account damage to the inside of the pile. A steel pipe soil cement pile integrated with a steel pipe can be formed.
【0059】また、杭として鋼管を使用したときの杭頭
部は、外周部が鋼管となり、その中へコンクリートを充
填することにより、中詰めされた鋼管とコンクリートが
複合された構造となり、水平応力に対して耐力の大きな
構造となる。When a steel pipe is used as a pile, the pile head has a structure in which the outer peripheral portion is a steel pipe, and concrete is filled therein, thereby forming a structure in which the middle-filled steel pipe and concrete are combined, and the horizontal stress is reduced. This results in a structure with a large proof stress.
【図1】(a)〜(h)は、本発明に係る杭の施工方法
の一例を工程順に示した図である。1 (a) to 1 (h) are views showing an example of a pile construction method according to the present invention in the order of steps.
【図2】(a)〜(h)は、本発明の杭を施工する方法
の一例を工程順に示した図である。FIGS. 2A to 2H are views showing an example of a method of constructing a pile according to the present invention in the order of steps.
【図3】(a)〜(h)は、本発明の杭を施工する方法
の一例を工程順に示した図である。FIGS. 3A to 3H are views showing an example of a method for constructing a pile according to the present invention in the order of steps.
【図4】(a)〜(f)は、本発明の杭を施工する方法
の一例を工程順に示した図である。FIGS. 4A to 4F are views showing an example of a method for constructing a pile according to the present invention in the order of steps.
【図5】従来の施工方法の一例を示す杭頭部の断面図で
ある。FIG. 5 is a sectional view of a pile head showing an example of a conventional construction method.
1 中空杭 1a 上端杭(最上段の中空杭) 2 ソイルセメント 3 掘削・攪拌ヘッド 4 ロツド 5 根固め部 6 内蓋 7 鉄筋(フーチング接続用部材) 8 コンクリート DESCRIPTION OF SYMBOLS 1 Hollow pile 1a Upper end pile (hollow pile at the top) 2 Soil cement 3 Excavation / stirring head 4 Rod 5 Root fixing part 6 Inner lid 7 Reinforcing bar (footing connection member) 8 Concrete
Claims (5)
数の中空杭とで造成される杭の施工方法において、最上
段の中空杭を所定の位置まで沈設できる深さを有するソ
イルセメントが存在しているとともに、前記ソイルセメ
ント内に最上段の中空杭を除く中空杭が沈設されている
状態で、前記中空杭内のソイルセメントを中空杭上端か
ら少なくとも中空杭外径のほぼ10倍程度に相当する深
さまで除去し、次に前記最上段の中空杭を接続し、この
最上段の中空杭をその杭頭部が前記フーチングの下端面
より上方に残存する位置まで前記ソイルセメント内に沈
設することを特徴とする杭の施工方法。In a method for constructing a pile formed by soil cement and a plurality of hollow piles below a footing, there is a soil cement having a depth capable of sinking an uppermost hollow pile to a predetermined position. At the same time, in a state where the hollow piles except the uppermost hollow pile are laid in the soil cement, the soil cement in the hollow pile is moved from the upper end of the hollow pile to a depth corresponding to at least about 10 times the outer diameter of the hollow pile. Then, the uppermost hollow pile is connected, and the uppermost hollow pile is sunk in the soil cement until the pile head remains above the lower end surface of the footing. Pile construction method.
数の中空杭とで造成される杭の施工方法において、ソイ
ルセメントを形成しつつ最上段の中空杭を除く中空杭を
前記ソイルセメント内に必要に応じて互いに接続しなが
ら沈設し、次に前記中空杭の下方に少なくとも前記最上
段の中空杭の沈設長さに相当する深さまでソイルセメン
トをさらに形成するとともに、前記中空杭内のソイルセ
メントを中空杭上端から少なくとも中空杭外径のほぼ1
0倍程度に相当する深さまで除去し、次に前記最上段の
中空杭を接続し、この最上段の中空杭をその杭頭部が前
記フーチングの下端面より上方に残存する位置まで前記
ソイルセメント内に沈設することを特徴とする杭の施工
方法。2. A method for constructing a pile formed by soil cement and a plurality of hollow piles below a footing, wherein a hollow pile excluding the uppermost hollow pile is formed in the soil cement while forming the soil cement. The soil cement is further laid down while being connected to each other, and then soil cement is further formed below the hollow pile to at least a depth corresponding to the laid length of the uppermost hollow pile, and the soil cement in the hollow pile is hollowed out. At least approximately 1 mm outside diameter of hollow pile from pile top
The soil cement is removed to a depth corresponding to about 0 times, and then the uppermost hollow pile is connected, and the uppermost hollow pile is connected to the soil cement until the pile head remains above the lower end surface of the footing. Construction method of pile characterized by being settled in.
数の中空杭とで造成される杭の施工方法において、ソイ
ルセメントを所定の深さまで形成し、次に最上段の中空
杭を除く中空杭を前記ソイルセメント内に必要に応じて
互いに接続しながら沈設し、次に前記中空杭内のソイル
セメントを中空杭上端から少なくとも中空杭外径のほぼ
10倍程度に相当する深さまで除去し、次に前記最上段
の中空杭を接続し、この最上段の中空杭をその杭頭部が
前記フーチングの下端面より上方に残存する位置まで前
記ソイルセメント内に沈設することを特徴とする杭の施
工方法。3. A method for constructing a pile formed by soil cement and a plurality of hollow piles below a footing, wherein the soil cement is formed to a predetermined depth, and then the hollow pile excluding the uppermost hollow pile is removed. If necessary, sunk into the soil cement while connecting to each other, and then remove the soil cement in the hollow pile from the upper end of the hollow pile to a depth corresponding to at least about 10 times the outer diameter of the hollow pile. A method for constructing a pile, comprising connecting an uppermost hollow pile and sinking the uppermost hollow pile into the soil cement to a position where the pile head remains above a lower end surface of the footing.
される杭の施工方法において、オーガーで地盤を掘削し
つつ最上段の中空杭を除く中空杭を必要に応じて互いに
接続しながら地中に建て込み、次に前記中空杭の下方を
前記最上段の中空杭を建て込む長さに相当する深さまで
前記オーガーにてさらに掘削し、かつその下端に根固め
部を形成し、次に前記オーガーを回収すると共に前記中
空杭内の掘削土を中空杭上端から少なくとも中空杭外径
のほぼ10倍程度に相当する深さまで除去し、次に最上
段の中空杭を接続し、この最上段の中空杭をその杭頭部
が前記フーチングの下端面より上方に残存する位置まで
地中に建て込むことを特徴とする杭の施工方法。4. A method of constructing a pile formed by a plurality of hollow piles below a footing, wherein the ground pile is excavated with an auger while connecting the hollow piles except the uppermost hollow pile to each other as necessary. And then further excavating the lower part of the hollow pile with the auger to a depth corresponding to the length in which the uppermost hollow pile is to be built, and forming a stiffening part at the lower end thereof, and then forming The auger is collected and the excavated soil in the hollow pile is removed from the upper end of the hollow pile to a depth corresponding to at least about 10 times the outer diameter of the hollow pile, and then the uppermost hollow pile is connected. A method for constructing a pile, wherein the hollow pile is buried underground to a position where the pile head remains above the lower end surface of the footing.
される杭の施工方法において、地中に最上段の中空杭を
除く中空杭を必要に応じて互いに接続しながら建て込
み、次に前記中空杭内の土を中空杭上端から少なくとも
中空杭外径のほぼ10倍程度の深さまで除去し、次に最
上段の中空杭を接続し、かつこの最上段の中空杭をその
杭頭部が前記フーチングの下端面より上方に残存する位
置まで地中に建て込むことを特徴とする杭の施工方法。5. A method of constructing a pile formed by a plurality of hollow piles below a footing, wherein the hollow piles other than the uppermost hollow pile are connected to each other as needed and are erected underground. The soil in the hollow pile is removed from the upper end of the hollow pile to a depth of at least about 10 times the outer diameter of the hollow pile, and then the uppermost hollow pile is connected. A pile construction method, wherein the pile is buried underground to a position that remains above a lower end surface of the footing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001177130A JP4475845B2 (en) | 2001-06-12 | 2001-06-12 | Pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001177130A JP4475845B2 (en) | 2001-06-12 | 2001-06-12 | Pile construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002363979A true JP2002363979A (en) | 2002-12-18 |
JP4475845B2 JP4475845B2 (en) | 2010-06-09 |
Family
ID=19018023
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001177130A Expired - Lifetime JP4475845B2 (en) | 2001-06-12 | 2001-06-12 | Pile construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4475845B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008274688A (en) * | 2007-05-02 | 2008-11-13 | Asahi Kasei Construction Materials Co Ltd | Buried device |
CN104018493A (en) * | 2014-06-20 | 2014-09-03 | 宁波鸿晨建设有限公司 | Double-shaft air-injection rotary jet type stirring pile machine and method for forming pile by using pile machine |
CN108265709A (en) * | 2016-11-28 | 2018-07-10 | 林友富 | A kind of construction technology of project pile deflection prevention structure used on soft soil foundation |
-
2001
- 2001-06-12 JP JP2001177130A patent/JP4475845B2/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008274688A (en) * | 2007-05-02 | 2008-11-13 | Asahi Kasei Construction Materials Co Ltd | Buried device |
CN104018493A (en) * | 2014-06-20 | 2014-09-03 | 宁波鸿晨建设有限公司 | Double-shaft air-injection rotary jet type stirring pile machine and method for forming pile by using pile machine |
CN104018493B (en) * | 2014-06-20 | 2015-12-23 | 宁波鸿晨建设有限公司 | Biaxial Compressive gas rotary ejection type mixing pile machine and utilize the method for this machine pile |
CN108265709A (en) * | 2016-11-28 | 2018-07-10 | 林友富 | A kind of construction technology of project pile deflection prevention structure used on soft soil foundation |
Also Published As
Publication number | Publication date |
---|---|
JP4475845B2 (en) | 2010-06-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5265500B2 (en) | Pile digging method, foundation pile structure | |
JP2002155530A (en) | Embedding method and tip metal fitting of existing pile | |
JP2003147782A (en) | Foundation structure for constructing new building on existing basement and its construction method | |
JP2003119775A (en) | Construction of foundation pile | |
JPS5985028A (en) | Steel pipe pile and laying work thereof | |
JP2002061178A (en) | Method of burying existing pile with protrusion in pile installation by inner excavation and foundation pile structure | |
JPH02289718A (en) | Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill | |
JP4872561B2 (en) | Construction method of ready-made piles | |
JP2002363979A (en) | Pile construction method | |
JP2005282063A (en) | Composite field preparation pile, its construction method and device for preparing composite field preparation pile | |
JP2790038B2 (en) | Reinforcement method of existing pile foundation building | |
JP2005139900A (en) | Burying method for ready-made pile, foundation pile structure, and ready-made pile | |
JPH09324422A (en) | Cast-in-place compound pile and building method therefor | |
JP3586839B2 (en) | In-situ formed concrete pile and its forming method | |
JP2000144727A (en) | Construction method of footing pile | |
JP2000154540A (en) | Bored pile, its work execution method, work execution device, and existing pile for bored pile | |
JPS61254716A (en) | Setting of in-place concrete pile | |
JP4054903B2 (en) | Method of burying ready-made piles, foundation pile structure and ready-made piles | |
JP4688214B2 (en) | Concrete foundation method | |
JP2001090060A (en) | Driving method for pile and constructing method for cut- off wall using the method | |
JP2006348637A (en) | Construction method of cast-in-place pile and cast-in-place pile structure | |
JP2002371550A (en) | Construction method of soil cement composite precast pile | |
JP2001011874A (en) | Construction method for structural stud using precast pile | |
JP2004204517A (en) | Pile burying method | |
JP2971045B2 (en) | Casting method of bottom concrete in propulsion method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20080423 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20100304 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100309 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100309 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130319 Year of fee payment: 3 |