JP2002309573A - Mouth pipe of ground anchor and method of forming slit therein - Google Patents

Mouth pipe of ground anchor and method of forming slit therein

Info

Publication number
JP2002309573A
JP2002309573A JP2001113721A JP2001113721A JP2002309573A JP 2002309573 A JP2002309573 A JP 2002309573A JP 2001113721 A JP2001113721 A JP 2001113721A JP 2001113721 A JP2001113721 A JP 2001113721A JP 2002309573 A JP2002309573 A JP 2002309573A
Authority
JP
Japan
Prior art keywords
pipe
slit
mouth
ground
inflow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001113721A
Other languages
Japanese (ja)
Inventor
Takao Kawashima
隆夫 川島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2001113721A priority Critical patent/JP2002309573A/en
Publication of JP2002309573A publication Critical patent/JP2002309573A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To prevent pressurized water and ejected sand from flowing out of the mouth of an anchor hole when a ground anchor is driven into the ground below the level of underground water for the construction of an earth retaining wall or the like. SOLUTION: A plurality of inflow slits 12 are provided in the mid position of a mouth pipe 10 buried into the ground at the back of an earth retaining wall 1 in order to prevent the collapse of the wall of the anchor hole in the ground anchor. Underground water around the mouth pipe 10 is forced into the pipe via the slits 12 and discharged.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はグラウンドアンカー
の口元管及びその表面に地下水を管内に流入させるスリ
ットを形成する方法に係り、特に山留め壁に打設された
グラウンドアンカーの口元管に作用する背面水圧を低減
させて、アンカー孔の口元から噴砂の発生を防止するよ
うにしたグラウンドアンカーの口元管及び同管のスリッ
ト形成方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mouth pipe of a ground anchor and a method of forming a slit on the surface of the pipe to allow groundwater to flow into the pipe, and more particularly to a back face acting on the mouth pipe of a ground anchor installed on a retaining wall. BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mouth pipe of a ground anchor and a method for forming a slit in the pipe, which reduce water pressure to prevent sand from being generated from the mouth of the anchor hole.

【0002】[0002]

【従来の技術】山留め工事において、山留め壁背面に高
い地下水位がある砂質土層をグラウンドアンカー(地盤
アンカーとも称する。)で支保しながら掘削する場合が
ある。この場合、アンカー孔の口元部分に被水噴出に対
する対策を施さないで山留め壁にアンカー孔を削孔する
と、削孔と同時に被圧水と砂とがアンカー孔を逆流して
口元から噴出するおそれがある。この結果、山留め壁背
面の地盤が乱され、背面地盤内に空洞等が生じ、山留め
壁背面の地表面沈下等を招く原因ともなる。
2. Description of the Related Art In earth retaining work, there is a case where a sandy soil layer having a high groundwater level behind a mountain retaining wall is excavated while being supported by a ground anchor (also referred to as a ground anchor). In this case, if the anchor hole is drilled in the retaining wall without taking measures against water spouting at the mouth of the anchor hole, the pressurized water and sand may flow back through the anchor hole and spout from the mouth at the same time as drilling. There is. As a result, the ground behind the retaining wall is disturbed, and a cavity or the like is generated in the rear ground, which may cause a subsidence of the ground surface behind the retaining wall.

【0003】そこで、従来は、口元管と呼ばれるアンカ
ー孔(削孔ロッド径)より一回り大きい直径の鋼管を口
元から所定範囲にわたってアンカー孔内に埋設し、砂の
噴出による孔壁、背面地盤の崩壊を防止していた。ま
た、一般に口元管の効果を高めるために、口元管の山留
空間側の先端には止水ボックスが設けられている。図6
はグラウンドアンカーの止水ボックス50及び口元管5
1部分を拡大して示した部分断面図である。同図に示し
たように、口元管51には、削孔ロッド52の外径より
一回り大きな内径で長さ1〜4m程度の鋼管が用いら
れ、山留め壁53から突出した先端に止水ボックス50
が取り付けられている。止水ボックス50には削孔ロッ
ド52が貫通する孔54が設けられており、この孔54
の周囲にゴムパッキン等の止水部材55が装着され、こ
の部分から地下水が流出するのが防止される。また、ボ
ックス50内の地下水を排水するためにコック55が設
けられている。通常はこのコック55を閉めておくの
で、グラウンドアンカー打設時の止水効果を確保するよ
うになっている。
Therefore, conventionally, a steel pipe having a diameter slightly larger than an anchor hole called a mouth pipe (diameter of a drilled rod) is buried in the anchor hole over a predetermined range from the mouth, and a hole wall formed by jetting sand and a back ground are formed. To prevent collapse. Generally, in order to enhance the effect of the mouth pipe, a water stop box is provided at the tip of the mouth pipe on the yard space side. FIG.
Is the water stop box 50 and the mouth pipe 5 of the ground anchor
It is the fragmentary sectional view which expanded and showed one part. As shown in the figure, a steel pipe having an inner diameter slightly larger than the outer diameter of the drilling rod 52 and having a length of about 1 to 4 m is used as the mouth pipe 51, and a water stop box is provided at the tip protruding from the retaining wall 53. 50
Is attached. The water stop box 50 is provided with a hole 54 through which the drilling rod 52 penetrates.
A water blocking member 55 such as a rubber packing is attached to the surrounding area, and groundwater is prevented from flowing out from this portion. Also, a cock 55 is provided to drain the groundwater in the box 50. Normally, since the cock 55 is closed, the water stopping effect at the time of placing the ground anchor is ensured.

【0004】[0004]

【発明が解決しようとする課題】ところが、削孔時に
は、図7に示したように、止水ボックス50のコック5
5を開いた状態で削孔ロッド52内に削孔水を送って掘
削土の混じった戻り水(泥水)をアンカー孔外に排水す
る必要がある。このとき口元管51の先端51bから流
入した比較的高い水圧の地下水が削孔土砂と混じってコ
ック56から噴出してしまう。このため、止水ボックス
50を用いた場合にも、口元管先端51bの上方地盤に
空洞57が生じやすく、さらに地表面58の沈下を引き
起こすおそれもあった。
At the time of drilling, however, as shown in FIG.
It is necessary to send drilling water into the drilling rod 52 with the hole 5 open to drain return water (muddy water) mixed with excavated soil outside the anchor hole. At this time, the relatively high water pressure of the groundwater flowing from the end 51b of the mouth pipe 51 mixes with the drilling earth and sand and spouts out of the cock 56. For this reason, even when the water stop box 50 is used, the cavity 57 is likely to be formed in the ground above the mouth pipe tip 51b, and there is a possibility that the ground surface 58 may sink.

【0005】その対策として削孔水にセメントを混合
し、水の比重を高めて被圧水とのバランスをとる方法も
講じられている。しかしながら、この場合にも被圧水の
水圧が削孔水の圧力より上回るような深度では十分な成
果が得られなかった。
[0005] As a countermeasure, a method of mixing cement with drilling water and increasing the specific gravity of water to balance with pressurized water has been taken. However, even in this case, sufficient results were not obtained at a depth where the pressure of the pressurized water exceeded the pressure of the drilling water.

【0006】そこで、本発明の目的は上述した従来の技
術が有する問題点を解消し、口元管に排水機能を設け、
口元管位置で被圧水の水圧を下げるようにして口元管先
端からの砂の流入を最小限にしたグラウンドアンカーの
口元管及び同管のスリット形成方法を提供することにあ
る。
Therefore, an object of the present invention is to solve the above-mentioned problems of the prior art and to provide a drainage function in the mouth pipe,
An object of the present invention is to provide a mouth pipe of a ground anchor and a method for forming a slit in the pipe, which minimize the inflow of sand from the tip of the mouth pipe by lowering the pressure of the water to be pressurized at the mouth pipe position.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、本発明はグラウンドアンカーのアンカー孔壁の崩落
防止のために山留め壁近傍の地盤に埋設される口元管で
あって、管中間位置に複数の流入スリットを有し、該流
入スリットを介して管周囲の地下水を管内に流入させる
ようにしたことを特徴とする。
SUMMARY OF THE INVENTION In order to achieve the above object, the present invention relates to a mouth pipe buried in the ground near a retaining wall to prevent the anchor hole wall of a ground anchor from collapsing. , A plurality of inflow slits, and groundwater around the pipe is caused to flow into the pipe through the inflow slit.

【0008】前記流入スリットは、前記口元管を埋設後
にその管の一部を塑性変形させ、あらかじめ管表面に形
成されていたスリットの幅を広げるようにすることが好
ましい。
It is preferable that a part of the inflow slit is plastically deformed after the mouth pipe is buried, so that a width of a slit previously formed on the pipe surface is increased.

【0009】このとき、前記流入スリットは、管頭部に
外力を作用させてスリット位置の管を塑性変形させてス
リット幅を広げるようにすることが好ましい。
At this time, it is preferable that the inflow slit is made to expand the slit width by applying an external force to the pipe head to plastically deform the pipe at the slit position.

【0010】そのスリットの形成方法として、グラウン
ドアンカーのアンカー孔崩落防止のために山留め壁近傍
の地盤の所定深さまで、管中間位置にスリットが形成さ
れた口元管を埋設し、該口元管の管頭部に管変形力を作
用させ、管を前記スリット位置で塑性変形させて前記ス
リットの幅を広げて口元管周囲の地下水を管内に流入さ
せる流入スリットを形成したことを特徴とする。
As a method of forming the slit, a mouth pipe having a slit formed at an intermediate position of the pipe is buried to a predetermined depth of the ground near the retaining wall in order to prevent the anchor hole of the ground anchor from collapsing. A pipe deforming force is applied to the head, the pipe is plastically deformed at the slit position, and the width of the slit is widened to form an inflow slit for allowing groundwater around the mouth pipe to flow into the pipe.

【0011】[0011]

【発明の実施の形態】以下、本発明のグラウンドアンカ
ーの口元管及び同管のスリット形成方法の一実施の形態
について、添付図面を参照して説明する。図1は本発明
による口元管及びこの口元管10に取り付けられた止水
ボックス20の構成を示した拡大断面図である。この口
元管10は、同図に示したように、管表面の中間位置に
管長手方向及び周方向に添って複数本の流入スリット1
2が形成されている。このスリット12は後述するよう
に、あらかじめ口元管10として用いられる円形鋼管の
表面の中間位置に管の長手方向及び周方向に添って複数
本の筋状スリット11をカッタ等の機械加工により形成
し、管を所定位置に打設後、頭部から打撃等の外力を加
えて長手方向に圧縮することにより、管の塑性変形を生
じさせることでスリット幅を広げたものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the mouth pipe of a ground anchor and a method of forming a slit of the pipe according to the present invention will be described below with reference to the accompanying drawings. FIG. 1 is an enlarged cross-sectional view showing the configuration of a mouth pipe according to the present invention and a water stop box 20 attached to the mouth pipe 10. As shown in the figure, the mouth pipe 10 has a plurality of inflow slits 1 at an intermediate position on the pipe surface along the pipe longitudinal direction and circumferential direction.
2 are formed. As will be described later, the slits 12 are formed in advance at a middle position on the surface of a circular steel pipe used as the mouth pipe 10 by machining a plurality of strip-shaped slits 11 along a longitudinal direction and a circumferential direction of the pipe by a cutter or the like. After the pipe is cast at a predetermined position, an external force such as a blow is applied from the head to compress the pipe in the longitudinal direction, thereby causing plastic deformation of the pipe to increase the slit width.

【0012】本実施の形態における、口元管10の打設
時の各寸法(製造寸法)は全長3000〜4000mm
で、全長の中間位置の2000〜3000mmの範囲に筋
状スリット11が形成されている。この筋状スリット1
1の形成範囲は、設定された口元管10の全長、山留め
壁厚等から適宜決定することが好ましい。なお、本明細
書では、管製造時に管表面に切り込み加工等により形成
されたスリットを「筋状スリット」と呼び、管埋設後に
筋状スリットの幅を広げたスリットを「流入スリット」
と呼んで区別して説明する。
In the present embodiment, each dimension (manufacturing dimension) of the mouth tube 10 at the time of driving is 3000 to 4000 mm in total length.
Thus, a streak slit 11 is formed in a range of 2000 to 3000 mm at an intermediate position of the entire length. This streak slit 1
It is preferable that the formation range of 1 is appropriately determined from the set total length of the mouth tube 10, the thickness of the retaining wall, and the like. In the present specification, a slit formed by cutting or the like on a pipe surface during pipe manufacturing is referred to as a “streak slit”, and a slit in which the width of the streak slit is increased after the pipe is embedded is referred to as an “inflow slit”.
And will be described separately.

【0013】この口元管10の施工手順を、図2各図を
参照して説明する。アンカー打設計画に基づき、所定位
置、角度に設定されたアンカー孔を、削孔ロッド2を用
いて削孔するために、口元管10を山留め壁1の所定位
置に所定角度をなすように、図示しないロータリーパー
カッション等の削孔機で所定深さまで埋設する。この口
元管10をガイドとして単位長の削孔ロッド2を複数本
繋いで所定深度までの削孔を行うことができる(図2
(a))。このときアンカー孔の削孔に先立ち、口元管
10の頭部(山留め壁からの突出部先端)を打撃ハンマ
ー(図示せず)で矢印方向に打撃することで、あらかじ
め周面に形成されていた筋状スリット11部分の管が塑
性変形し、スリット幅が広がって、地下水が通過可能な
流入スリット12が形成される(図2(b))。その
後、口元管10の頭部に従来と同様の構成の止水ボック
ス20を取り付け(図2(c))、止水ボックス20を
通じて削孔ロッド2を用いた削孔を行うことができる。
The procedure for installing the mouth pipe 10 will be described with reference to FIGS. Based on the anchoring design, in order to drill an anchor hole set at a predetermined position and angle using the drill rod 2, the mouth pipe 10 is formed at a predetermined angle on the mountain retaining wall 1 at a predetermined angle. It is buried to a predetermined depth by a drilling machine such as a rotary percussion not shown. Using the mouth tube 10 as a guide, a plurality of unit length drilling rods 2 are connected to perform drilling up to a predetermined depth (FIG. 2).
(A)). At this time, prior to the drilling of the anchor hole, the head of the mouth tube 10 (the tip of the protruding portion from the retaining wall) is hit in the direction of the arrow with a hitting hammer (not shown), thereby being formed on the peripheral surface in advance. The pipe in the portion of the streak-shaped slit 11 is plastically deformed, the slit width is widened, and the inflow slit 12 through which the groundwater can pass is formed (FIG. 2B). Thereafter, a water stop box 20 having the same configuration as the conventional one is attached to the head of the mouth pipe 10 (FIG. 2C), and drilling using the drill rod 2 can be performed through the water stop box 20.

【0014】このようにアンカー孔に設置された口元管
10によれば、図3に示したように、地下水位以深に削
孔されたアンカー孔の口元管10に作用する地下水は、
矢印の流線で示したように、口元管10の先端のみでな
く、流入面積の大きな管中間位置の流入スリット12部
分を介して主に口元管10内に流入する。このとき流入
スリット12位置の方が口元管先端10b位置より水深
が浅いため、口元管10内を通って止水ボックス20か
ら排水される地下水の流速が低下し、管先端位置での砂
の移動が弱められる。このため、管内部に取り込まれる
砂量が減少し、止水ボックス20のコック21からの砂
の噴出を押さえることができる。
According to the mouth pipe 10 installed in the anchor hole as described above, as shown in FIG. 3, the groundwater acting on the mouth pipe 10 of the anchor hole drilled deeper than the groundwater level,
As shown by the streamline of the arrow, the water mainly flows into the mouth pipe 10 not only through the tip of the mouth pipe 10 but also through the inflow slit 12 at the middle position of the pipe having a large inflow area. At this time, since the water depth at the position of the inflow slit 12 is shallower than the position of the mouth end 10b of the mouth, the flow velocity of the groundwater drained from the water stop box 20 through the inside of the mouth pipe 10 decreases, and the movement of sand at the end of the tube Is weakened. For this reason, the amount of sand taken into the inside of the pipe is reduced, and the ejection of sand from the cock 21 of the water stop box 20 can be suppressed.

【0015】次に、口元管10の流入スリット12の形
成方法について、図4〜図6を参照して説明する。図4
は本実施の形態で説明した口元管10及びその流入スリ
ット12を示した説明図である。同図に示したように、
口元管10の管表面には管長手方向の所定範囲に管軸方
向に延びる筋状スリット11が全周にわたって形成され
ている。本実施の形態では当初の筋状スリット11は幅
0.5mm、長さ50mm程度に設定され、あらかじめ工場
でカッタ等により切れ目の加工を施すことで形成されて
いる。さらに同図(b)に示したように、口元管10の
頭部10aに打撃を加えると、口元管10はその周囲が
地盤で拘束された状態で管長手方向に圧縮され、各筋状
スリット11位置で管が圧縮され側方に拡径するように
塑性変形し、各スリットの幅が1〜2mm程度に広がる。
なお、口元管10の先端10bは地盤への圧入を容易に
するために周方向に複数の刃31が連続した矢状に仕上
げられている。なお、この流入スリット口のスリット幅
は地下水量、口元管の設置地盤に応じて適宜設定するこ
とが好ましい。
Next, a method of forming the inflow slit 12 of the mouth tube 10 will be described with reference to FIGS. FIG.
FIG. 2 is an explanatory view showing a mouth tube 10 and an inflow slit 12 thereof described in the present embodiment. As shown in the figure,
A streak-like slit 11 extending in the pipe axis direction is formed on the pipe surface of the mouth pipe 10 in a predetermined range in the pipe longitudinal direction over the entire circumference. In the present embodiment, the initial streak-shaped slit 11 is set to have a width of about 0.5 mm and a length of about 50 mm, and is formed by performing a cut processing in advance by a cutter or the like at a factory. When the head 10a of the lip 10 is hit, as shown in FIG. 2B, the lip 10 is compressed in the longitudinal direction of the pipe while its periphery is restrained by the ground, and each of the slits is formed. At 11 positions, the pipe is compressed and plastically deformed so as to expand laterally, and the width of each slit expands to about 1 to 2 mm.
In addition, the tip 10b of the mouth pipe 10 is finished in a sagittal shape in which a plurality of blades 31 are continuous in the circumferential direction to facilitate press-fitting into the ground. It is preferable that the slit width of the inflow slit is appropriately set according to the amount of groundwater and the ground at which the mouth pipe is installed.

【0016】また、流入スリット12を形成する際の作
用力の大小、スリットの大きさ、本数の違いにより、管
の塑性変形量が異なってくるので、あらかじめ作用力と
スリットの大きさ、本数の関係を実験的に求めておくこ
とにより、流入スリット12のスリット面積の総和を制
御することができ、地下水の口元管10内への流入量、
すなわち止水ボックス20からの排水量を適宜調整する
ことが可能となる。また、スリット位置にあらかじめ細
い網目状のストレーナを装着することで砂の流入を確実
に防止することができる。
Further, the amount of plastic deformation of the pipe varies depending on the magnitude of the acting force when forming the inflow slit 12, the size of the slit, and the number of the slits. By determining the relationship experimentally, the sum of the slit areas of the inflow slits 12 can be controlled, and the amount of groundwater flowing into the mouth pipe 10,
That is, the amount of drainage from the water stop box 20 can be appropriately adjusted. In addition, the inflow of sand can be reliably prevented by mounting a thin mesh strainer in advance at the slit position.

【0017】流入スリットの形成方法として、埋設され
た状態の口元管の先端を固定した状態で、頭部に所定の
トルクを作用させ、管体をねじることで筋状スリットの
幅を広げて流入スリットを形成したり、先端が固定され
た口元管の頭部に引張力を作用させ、管をわずかに伸長
させることで、筋状スリットの幅を広げて流入スリット
を形成することも可能である。
As a method for forming the inflow slit, a predetermined torque is applied to the head while the tip of the buried mouth tube is fixed, and the width of the streak-like slit is widened by twisting the tube so that the inflow slit is formed. By forming a slit or applying a tensile force to the head of the mouth tube to which the tip is fixed to slightly expand the tube, it is also possible to increase the width of the streak-like slit to form the inflow slit. .

【0018】また、口元管が比較的容易に地盤内に打設
できるような地盤であって、口元管の打設時に管の軸方
向の座屈等のおそれがない地盤の場合には、口元管の製
造時にあらかじめ流入スリットのスリット幅程度の広幅
のスリットを形成しておき、この流入スリット付きの口
元管を打設することも可能である(図5参照)。この場
合には口元管埋設後のスリット形成作業を省略すること
ができ、従来の問題を同様に解決することができる。
On the other hand, in the case of a ground in which the mouth pipe can be relatively easily driven into the ground, and there is no fear of buckling of the pipe in the axial direction when the mouth pipe is driven, It is also possible to previously form a slit having a width approximately equal to the slit width of the inflow slit at the time of production of the tube, and to cast a mouth tube with this inflow slit (see FIG. 5). In this case, the slit forming operation after the mouth pipe is buried can be omitted, and the conventional problem can be solved similarly.

【0019】[0019]

【発明の効果】以上に述べたように、本発明によれば、
口元管の中間位置で地下水を口元管内に流入させること
で口元管先端からの地下水の急激な流入を抑え、乱され
た砂を伴う地下水の噴出を防止でき、山留め壁背面での
地盤の崩壊を防止できるという効果を奏する。
As described above, according to the present invention,
By injecting groundwater into the mouth pipe at an intermediate position of the mouth pipe, it is possible to suppress the sudden inflow of groundwater from the tip of the mouth pipe, prevent the discharge of groundwater with disturbed sand, and prevent the ground from collapsing behind the retaining wall. This has the effect that it can be prevented.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明によるグラウンドアンカーの口元管の一
実施の形態を示した部分拡大断面図。
FIG. 1 is a partially enlarged sectional view showing one embodiment of a mouth pipe of a ground anchor according to the present invention.

【図2】本発明のグラウンドアンカーの口元管のスリッ
トの形成方法の手順を簡単に示した施工順序図。
FIG. 2 is a construction sequence diagram schematically showing a procedure of a method of forming a slit of a mouth pipe of a ground anchor according to the present invention.

【図3】本発明による口元管を備えたアンカー孔に沿う
地下水の流れを模式的に示した説明図。
FIG. 3 is an explanatory view schematically showing the flow of groundwater along an anchor hole provided with a mouth pipe according to the present invention.

【図4】口元管の流入スリットの形成例を示した斜視
図。
FIG. 4 is a perspective view showing an example of forming an inflow slit of a mouth tube.

【図5】本発明によるグラウンドアンカーの口元管の他
の実施の形態を示した部分拡大断面図。
FIG. 5 is a partially enlarged sectional view showing another embodiment of the mouth pipe of the ground anchor according to the present invention.

【図6】従来の口元管の構成の一例を示した部分拡大断
面図。
FIG. 6 is a partially enlarged sectional view showing an example of the configuration of a conventional mouth tube.

【図7】図6に示した口元管を備えたアンカー孔での地
下水、砂の噴出の状況を模式的に示した説明図。
FIG. 7 is an explanatory view schematically showing the situation of the spouting of groundwater and sand at the anchor hole provided with the mouth pipe shown in FIG. 6;

【符号の説明】[Explanation of symbols]

1 山留め壁 2 削孔ロッド 10 口元管 11 筋状スリット 12 流入スリット 20 止水ボックス 21 コック DESCRIPTION OF SYMBOLS 1 Mountain retaining wall 2 Drilling rod 10 Mouth pipe 11 Streak slit 12 Inflow slit 20 Water stop box 21 Cock

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】グラウンドアンカーのアンカー孔壁の崩落
防止のために山留め壁近傍の地盤に埋設される口元管で
あって、管中間位置に複数の流入スリットを有し、該流
入スリットを介して管周囲の地下水を管内に流入させる
ようにしたことを特徴とするグラウンドアンカーの口元
管。
1. A mouth pipe buried in the ground near a retaining wall for preventing the anchor hole wall of a ground anchor from collapsing, having a plurality of inflow slits at an intermediate position of the pipe, and through the inflow slit. A mouth pipe of a ground anchor, wherein groundwater around the pipe is caused to flow into the pipe.
【請求項2】前記流入スリットは、前記口元管の埋設後
にその管の一部を塑性変形させ、あらかじめ管表面に形
成されていたスリットの幅が広げられたものであること
を特徴とする請求項1に記載のグラウンドアンカーの口
元管。
2. The inflow slit according to claim 1, wherein a part of the mouth pipe is plastically deformed after the mouth pipe is buried, and a width of a slit previously formed on the pipe surface is widened. Item 2. A mouth tube of the ground anchor according to Item 1.
【請求項3】前記流入スリットは、管頭部に外力を作用
させてスリット位置の管を塑性変形させてスリット幅を
広げるようにしたことを特徴とする請求項2記載のグラ
ウンドアンカーの口元管。
3. The mouth pipe of a ground anchor according to claim 2, wherein the inflow slit is formed by applying an external force to the pipe head to plastically deform the pipe at the slit position to widen the slit width. .
【請求項4】グラウンドアンカーのアンカー孔崩落防止
のために山留め壁近傍の地盤の所定深さまで、管中間位
置にスリットが形成された口元管を埋設し、該口元管の
管頭部に管変形力を作用させ、管を前記スリット位置で
塑性変形させて前記スリットの幅を広げて口元管周囲の
地下水を管内に流入させる流入スリットを形成したこと
を特徴とする口元管のスリット形成方法。
4. A pipe having a slit formed at an intermediate position of the pipe is buried up to a predetermined depth of the ground near the retaining wall to prevent the anchor hole of the ground anchor from collapsing, and the pipe is deformed at the pipe head of the pipe. A slit forming method for a mouth pipe, wherein a force is applied to deform the pipe plastically at the slit position, the width of the slit is widened, and an inflow slit for flowing groundwater around the mouth pipe into the pipe is formed.
JP2001113721A 2001-04-12 2001-04-12 Mouth pipe of ground anchor and method of forming slit therein Pending JP2002309573A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001113721A JP2002309573A (en) 2001-04-12 2001-04-12 Mouth pipe of ground anchor and method of forming slit therein

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001113721A JP2002309573A (en) 2001-04-12 2001-04-12 Mouth pipe of ground anchor and method of forming slit therein

Publications (1)

Publication Number Publication Date
JP2002309573A true JP2002309573A (en) 2002-10-23

Family

ID=18964907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001113721A Pending JP2002309573A (en) 2001-04-12 2001-04-12 Mouth pipe of ground anchor and method of forming slit therein

Country Status (1)

Country Link
JP (1) JP2002309573A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011257196A (en) * 2010-06-07 2011-12-22 Nippon Steel Corp Sample for tensile test of tubular material, and tensile test method
JP2020125653A (en) * 2019-02-06 2020-08-20 日特建設株式会社 Mouth pipe, and method using the same
CN115354655A (en) * 2022-01-20 2022-11-18 河南省地质矿产勘查开发局第四地质矿产调查院 Anchoring device for preventing landslide geological disasters
JP7289022B1 (en) * 2023-03-15 2023-06-08 茂 宮古 Mouth canal and mouth canal burying method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011257196A (en) * 2010-06-07 2011-12-22 Nippon Steel Corp Sample for tensile test of tubular material, and tensile test method
JP2020125653A (en) * 2019-02-06 2020-08-20 日特建設株式会社 Mouth pipe, and method using the same
JP7169214B2 (en) 2019-02-06 2022-11-10 日特建設株式会社 Mouth pipe and construction method using it
CN115354655A (en) * 2022-01-20 2022-11-18 河南省地质矿产勘查开发局第四地质矿产调查院 Anchoring device for preventing landslide geological disasters
CN115354655B (en) * 2022-01-20 2024-02-27 河南省地质矿产勘查开发局第四地质矿产调查院 Anchoring device for preventing landslide geological disasters
JP7289022B1 (en) * 2023-03-15 2023-06-08 茂 宮古 Mouth canal and mouth canal burying method

Similar Documents

Publication Publication Date Title
US7854572B2 (en) Piling machine with high-pressure jet spiral bit and its piling method
JP4716134B2 (en) Slope stabilization method
JP2007077803A (en) Screwing-in type steel pipe pile
JP2002309573A (en) Mouth pipe of ground anchor and method of forming slit therein
JP4698398B2 (en) Ground reinforcement pipe and tunnel excavation method using the same
JP4608327B2 (en) The tip structure of a steel pipe pile used in the medium digging method.
JP4928192B2 (en) Construction method of expansion head pile
JP4502730B2 (en) Steel pipe for ground reinforcement
JPH04302693A (en) Excavating engineering method
JP3833165B2 (en) Drain pipe and drain method
JP4341029B2 (en) Pile foundation method
JP2006348478A (en) Peripheral bit of steel pipe
JPH01295913A (en) Constructing method for enlarged bulb of large caliber pile, and its apparatus
KR20190091741A (en) Grouting apparatus for reinforcing tunnel and the manufacture method thereof
JP4916395B2 (en) Drainage pipe set and drainage method
JP2006348564A (en) Construction method of foundation pile and foundation consolidation structure of foundation pile
KR100420493B1 (en) A steel conduit post for ground-making
JPH0629510B2 (en) Concrete pile foundation method and equipment used therefor
JP2582724B2 (en) Drilling equipment for foundation ground
JPH04302694A (en) Excavating engineering method
JPS6136620Y2 (en)
JP2000257062A (en) Steel pipe pile pitching method
JP2007009639A (en) Method of base formation and sidewall protrusion prevention for tunnel support
CN114622548A (en) Bored concrete pile pore-forming construction structure for complex stratum
JPH08319617A (en) Method and equipment for improvement construction of foundation ground