JP2002297222A - Production management method and production management system - Google Patents

Production management method and production management system

Info

Publication number
JP2002297222A
JP2002297222A JP2001103443A JP2001103443A JP2002297222A JP 2002297222 A JP2002297222 A JP 2002297222A JP 2001103443 A JP2001103443 A JP 2001103443A JP 2001103443 A JP2001103443 A JP 2001103443A JP 2002297222 A JP2002297222 A JP 2002297222A
Authority
JP
Japan
Prior art keywords
time
processing
order
priority
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2001103443A
Other languages
Japanese (ja)
Inventor
Masuhiro Ishitobi
益弘 石飛
Yasushi Ishiyama
康史 石山
Yutaka Murakami
裕 村上
Masahiro Kuga
正浩 空閑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Materials Corp
Original Assignee
Mitsubishi Materials Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Materials Corp filed Critical Mitsubishi Materials Corp
Priority to JP2001103443A priority Critical patent/JP2002297222A/en
Publication of JP2002297222A publication Critical patent/JP2002297222A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a production management method and system capable of making an accurate production schedule in a short time, and predicting the term of delivery of a product suitable for reality. SOLUTION: At the time of preparing a production schedule by making each facility correspond to each process in a situation that a plurality of facilities and a plurality of orders are provided, and that at least one process is included in each order, time is advanced to a point of time when the process which is being processed by any facility ends, and a prescribed process is assigned to the facility whose processing ends by referring to a priority α to be calculated by referring to a priority accessory to the order, the term of delivery, the calculation execution date, and the total time of the unprocessed process, and discrete processing is performed to the process next to the process whose processing ends by selecting a prescribed facility by referring to the total time of the processing waiting processes of each facility from among the facility capable of processing the next process. Thus, the calculating time can be sharply shortened, and a production schedule whose satisfaction level is high can be prepared in response to all the orders.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、生産管理方法及び
生産管理システムに関し、特に、多品種少量生産工場に
おける製品納期の予測に用いて好適な生産管理方法及び
生産管理システムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production management method and a production management system, and more particularly to a production management method and a production management system suitable for use in predicting a product delivery date in a high-mix low-volume production factory.

【0002】[0002]

【従来の技術】工場の生産設備を利用して複数の製品を
生産する場合、生産すべき製品品種毎に数量及び納期、
使用する設備、材料の調達、人員の振り分け等を条件と
して、トータルコストを最小限にする生産スケジュール
を数理計算法に基づき計算する手法が種々提案されてい
る。上記生産スケジュールの立案に際し、少ない品種を
大量に生産する工場では、一般に空きのある設備に順次
注文を振り分けていくことによって最適な解を得ること
ができるため、その計算も簡便なアルゴリズムで処理す
ることができ、短時間で計算を行うことができる。
2. Description of the Related Art When a plurality of products are produced using production equipment of a factory, the quantity and delivery date for each product type to be produced,
Various methods have been proposed for calculating a production schedule that minimizes the total cost based on a mathematical calculation method, on condition that equipment to be used, procurement of materials, distribution of personnel, and the like. In planning the above production schedule, in a factory that produces a large number of small varieties, the optimal solution can generally be obtained by sequentially allocating orders to vacant facilities, and the calculation is also processed by a simple algorithm. Calculation can be performed in a short time.

【0003】しかしながら、多品種少量生産を行う工場
では、各々の注文の納期や処理工程数、処理時間等に大
きな違いがあるために、単純に注文順に設備を割り当て
ることができず、各々の注文に対する納期や工数、使用
する設備、設備の稼働状況等を総合的に勘案して計算を
行う必要がある。そこで、従来は、多数の設備を用いて
多数の注文を処理する場合、設備と注文を要素として全
ての組み合わせを順次計算して、その中で最適な解を選
択する方法や、予め定めた一定の時間間隔毎に設備と注
文をマップ展開して最適解を求めるといった方法がとら
れている(特開平1−109060号公報、特開平2−
185351号公報、特開平5−108649号公報、
特開平5−108661号公報等)。
However, in a factory that performs high-mix low-volume production, there is a great difference in the delivery date of each order, the number of processing steps, the processing time, and the like. It is necessary to calculate in consideration of the delivery date and man-hours, the equipment to be used, the operation status of the equipment, and the like. Therefore, conventionally, when processing a large number of orders using a large number of equipment, all combinations are sequentially calculated using the equipment and the order as elements, and a method of selecting an optimal solution among them and a predetermined constant (See Japanese Patent Application Laid-Open No. 1-109060 and Japanese Patent Application Laid-Open No.
185351, JP-A-5-108649,
JP-A-5-108661, etc.).

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上述し
た従来の生産管理方法では、各アルゴリズムに基づいて
解を得ることはできるが、設備と注文の全ての組み合わ
せに対して計算を行ったり、予め定められた時間間隔毎
にマップ展開して計算を行うために、所要の解を得るた
めの計算に時間がかかってしまうという問題がある。
However, in the above-described conventional production management method, a solution can be obtained based on each algorithm, but a calculation is performed for all combinations of equipment and orders, or a predetermined value is determined. There is a problem that it takes time to perform a calculation to obtain a required solution because the map is developed at each time interval and the calculation is performed.

【0005】また、上記計算方法では、新たな注文が発
生した場合や、注文の納期に変更が生じた場合や、設備
に故障が生じた場合等、生産スケジュールを作り直す必
要が生じた場合に、初めから計算し直さなければなら
ず、時々刻々変化する生産現場の状況に迅速に対応する
ことができなかった。
Further, according to the above calculation method, when it is necessary to re-create the production schedule, for example, when a new order is generated, when the delivery date of the order is changed, or when equipment is broken down, The calculations had to be recalculated from the beginning, and it was not possible to quickly respond to the ever-changing conditions at the production site.

【0006】更に、全ての組み合わせを計算する方法や
マップ展開する方法では、計算は画一的に行われること
が多く、計算上の最適解と現場担当者の考える生産計画
との間にずれが生じることが多く、そのずれを埋めるた
めに計算手法を改良するには多大なシステム変更が求め
られるといった問題もある。
Further, in the method of calculating all combinations and the method of developing a map, the calculation is often performed uniformly, and there is a gap between the optimal solution in calculation and the production plan considered by the site staff. There is also a problem that a great deal of system change is required to improve the calculation method to fill the gap.

【0007】そして上述した問題は、特に多種多様な注
文が数多く存在し、突発注文が多い生産形態において顕
著に現れており、迅速かつ適切な生産スケジュールを提
供できる生産管理方法及び生産管理システムの実現が望
まれている。
[0007] The above-mentioned problem is particularly noticeable in a production mode in which a large number of various orders are present and a lot of sudden orders are provided, and a production management method and a production management system capable of providing a quick and appropriate production schedule are realized. Is desired.

【0008】本発明は、上記問題点に鑑みてなされたも
のであって、その主たる目的は、短時間で正確な生産ス
ケジュールを立案し、現実に即した製品納期の予測が可
能な生産管理方法及び生産管理システムを提供すること
にある。
The present invention has been made in view of the above problems, and a main object of the present invention is to provide a production management method capable of planning an accurate production schedule in a short time and predicting the actual delivery date of a product. And a production management system.

【0009】[0009]

【問題を解決するための手段】上記目的を達成するた
め、本発明の生産管理方法は、1以上の工程における処
理が必要とされる複数の注文を、複数の設備の中で前記
処理が可能な設備に順次振り分けて生産スケジュールを
作成する生産管理方法において、前記複数の設備の各々
に対し、所定の処理が終了する予定時刻を演算し、前記
予定時刻の中で最も早く到来する時刻まで計算上の時間
を進め、該時刻において、前記処理が終了した前記設備
に対して、予め算出した優先度を参照して所定の工程を
振り分けるステップ、及び、前記処理が終了した前記工
程の次の工程に対して、該次工程の処理が可能な設備の
中から待ち状態の工程の処理時間を参照して所定の設備
を選択するステップを順次実行し、前記複数の注文と前
記設備との対応付けを行うものである。
In order to achieve the above object, the production management method of the present invention can process a plurality of orders requiring processing in one or more steps in a plurality of facilities. In the production management method of sequentially allocating to a plurality of facilities and creating a production schedule, for each of the plurality of facilities, a scheduled time at which predetermined processing is completed is calculated, and the calculation is performed until the earliest arrival time among the scheduled times. Advancing the above time, at that time, allocating a predetermined process to the facility for which the process has been completed with reference to a priority calculated in advance, and a process next to the process for which the process has been completed And sequentially executing a step of selecting predetermined equipment with reference to the processing time of the waiting step from among the equipment capable of processing the next step, and associating the plurality of orders with the equipment. Is performed.

【0010】また、本発明の生産管理方法は、1以上の
工程における処理が必要とされる複数の注文を、複数の
設備の中で前記処理が可能な設備に順次振り分けて生産
スケジュールを作成する生産管理方法において、前記注
文における複数の工程間に所定の移行期間を予め設定
し、前記複数の設備の各々に対し、所定の処理が終了す
る予定時刻又は前記移行期間が終了する予定時刻を演算
し、前記予定時刻の中で最も早く到来する時刻まで計算
上の時間を進め、該時刻において、前記処理が終了した
前記設備に対して、予め算出した優先度を参照して所定
の工程を振り分けるステップ、及び、前記処理が終了又
は前記移行期間が終了した前記工程の次の工程に対し
て、該次工程の処理が可能な設備の中から待ち状態の工
程の処理時間を参照して所定の設備を選択するステップ
を順次実行し、前記複数の注文と前記設備との対応付け
を行うものである。
The production management method of the present invention creates a production schedule by sequentially allocating a plurality of orders requiring processing in one or more processes to equipment capable of performing the processing among a plurality of equipment. In the production management method, a predetermined transition period is set in advance between a plurality of processes in the order, and for each of the plurality of facilities, a scheduled time at which a predetermined process ends or a scheduled time at which the transition period ends is calculated. Then, the calculation time is advanced to the earliest arrival time among the scheduled times, and at that time, a predetermined process is distributed to the equipment for which the processing has been completed with reference to a priority calculated in advance. Steps and, for the next step after the step in which the processing has been completed or the transition period has been completed, refer to the processing time of the step in the waiting state from among the equipment capable of performing the processing in the next step. Sequentially performing the step of selecting a predetermined facility, and performs correlation between the plurality of orders and the facilities.

【0011】本発明においては、前記優先度を、少なく
とも、前記注文に付随する優先度と、該注文で定められ
る納期と、計算を実行する日時と、該注文の未処理工程
の総時間とを参照して定める構成とすることができ、前
記注文に付随する優先度をA、該注文で定められる納期
をT1、計算を実行する日時をT2、該注文の未処理工
程を処理するための総時間をT3とした場合、前記優先
度を、A÷(T1−T2)×T3で定義することが好ま
しい。
[0011] In the present invention, the priority is at least a priority associated with the order, a delivery date specified in the order, a date and time when the calculation is performed, and a total time of the unprocessed steps of the order. The priority associated with the order may be A, the delivery date specified in the order may be T1, the date and time when the calculation is performed is T2, and a total for processing the unprocessed steps of the order. When the time is T3, the priority is preferably defined as A ÷ (T1−T2) × T3.

【0012】また、本発明においては、前記振り分け処
理に際して、全ての前記注文の前記優先度を再計算する
構成とすることができる。
Further, in the present invention, the priorities of all the orders may be recalculated during the distribution process.

【0013】また、本発明においては、上記方法で作成
した生産スケジュールのデータを、所定の暗号化方法を
用いた暗号化処理及び分割処理により複数のファイルに
変換し、変換した前記複数のファイルを、インターネッ
ト網を介して接続されるサーバに送信し、該サーバにお
いて前記複数のファイルの集約処理及び復号化処理を行
い、ブラウザで閲覧可能な形式に変換する構成とするこ
ともできる。
Further, in the present invention, the data of the production schedule created by the above method is converted into a plurality of files by encryption processing and division processing using a predetermined encryption method, and the converted plurality of files are converted. Alternatively, the data may be transmitted to a server connected via the Internet network, and the server may perform aggregating processing and decrypting processing of the plurality of files, and convert the plurality of files into a format that can be browsed by a browser.

【0014】また、本発明の生産管理システムは、1以
上の工程における処理が必要とされる複数の注文を、複
数の設備の中で前記処理が可能な設備に順次振り分けて
生産スケジュールを作成する生産管理システムにおい
て、前記複数の設備の各々に対し、所定の処理が終了す
る予定時刻を演算する手段と、前記予定時刻の中で最も
早く到来する時刻まで計算上の時間を進め、該時刻にお
いて、前記処理が終了した前記設備に対して、予め算出
した優先度を参照して所定の工程を振り分ける手段と、
前記処理が終了した前記工程の次の工程に対して、該次
工程の処理が可能な設備の中から待ち状態の工程の処理
時間を参照して所定の設備を選択する手段とを少なくと
も有することをものである。
Further, the production management system of the present invention creates a production schedule by sequentially allocating a plurality of orders requiring processing in one or more processes to facilities capable of performing the processing among a plurality of facilities. In the production management system, for each of the plurality of facilities, a means for calculating a scheduled time at which a predetermined process is completed, and a calculation time is advanced to the earliest time arriving from the scheduled time. Means for allocating a predetermined process to the equipment for which the processing has been completed, with reference to a priority calculated in advance;
At least means for selecting predetermined equipment with reference to the processing time of a waiting step from among equipment capable of performing the processing of the next step with respect to the next step of the step after the completion of the processing. Is the thing.

【0015】また、本発明の生産管理システムは、1以
上の工程における処理が必要とされる複数の注文を、複
数の設備の中で前記処理が可能な設備に順次振り分けて
生産スケジュールを作成する生産管理システムにおい
て、前記注文の複数の工程間に所定の移行期間を設定す
る手段と、所定の処理が終了又は所定の移行期間が終了
する予定時刻を演算する手段と、前記予定時刻の中で最
も早く到来する時刻まで計算上の時間を進め、該時刻に
おいて、前記処理が終了した前記設備に対して、予め算
出した優先度を参照して所定の工程を振り分ける手段
と、前記処理が終了又は前記移行期間が終了した前記工
程の次の工程に対して、該次工程の処理が可能な設備の
中から待ち状態の工程の処理時間を参照して所定の設備
を選択する手段とを少なくとも有するものである。
Further, the production management system of the present invention creates a production schedule by sequentially allocating a plurality of orders that require processing in one or more processes to equipment capable of performing the processing among a plurality of equipment. In the production management system, means for setting a predetermined transition period between a plurality of steps of the order, means for calculating a scheduled time at which a predetermined process ends or a predetermined transition period ends, and A calculation time is advanced to the earliest arrival time, and at that time, means for distributing a predetermined process to the facility for which the processing has been completed with reference to a previously calculated priority, and Means for selecting a predetermined equipment from the equipment that can perform the processing of the next step with reference to the processing time of the waiting step from the equipment that can perform the processing of the next step for the next step after the transition period has ended Those having Kutomo.

【0016】本発明においては、前記生産管理システム
が、少なくとも前記優先度の計算及び前記振り分け処理
を実行する演算処理装置と、製品製造に関与する各々の
部門に設置される端末と、前記端末の情報を管理、記憶
するホストコンピュータとを含み、各々が社内ネットワ
ーク網を介して相互に接続され、前記端末から入力され
た注文情報及び該注文に関する進捗情報が前記ホストコ
ンピュータに記憶され、該ホストコンピュータに記憶さ
れた前記情報が所定の間隔毎に前記演算処理装置に送信
されて生産スケジュールが作成され、該生産スケジュー
ルが前記社内ネットワーク網を介して前記端末の各々に
出力される構成とすることができる。
[0016] In the present invention, the production management system includes an arithmetic processing unit for executing at least the priority calculation and the distribution process, terminals installed in respective departments involved in product manufacturing, A host computer for managing and storing information, each of which is mutually connected via an in-house network, wherein order information input from the terminal and progress information relating to the order are stored in the host computer, and the host computer Is transmitted to the arithmetic processing unit at predetermined intervals to create a production schedule, and the production schedule is output to each of the terminals via the in-house network. it can.

【0017】また、本発明においては、前記生産管理シ
ステムに、更に、前記社内ネットワーク網を介して接続
されるプロキシサーバと、インターネット網を介して接
続されるwebサーバ及び社外の業者に設置される端末
とを含み、前記生産スケジュールのデータが、前記プロ
キシサーバにおいて所定の暗号化方法を用いた暗号化処
理及び分割処理により複数のファイルに変換され、変換
された前記複数のファイルが、インターネット網を介し
て前記webサーバに送信され、該webサーバにおい
て前記複数のファイルの集約処理及び復号化処理が行わ
れた後ブラウザで閲覧可能な形式に変換され、前記社外
の業者に設置される端末で前記生産スケジュールが参照
される構成とすることもできる。
In the present invention, the production management system is further installed in a proxy server connected via the in-house network, a web server connected via the Internet, and a company outside the company. And a terminal, wherein the data of the production schedule is converted into a plurality of files by an encryption process and a division process using a predetermined encryption method in the proxy server, and the plurality of converted files are transmitted through the Internet network. Is transmitted to the web server via the web server, the plurality of files are converted and converted into a format that can be browsed by a browser after the aggregation process and the decryption process are performed on the web server. The production schedule may be referred to.

【0018】このように、本発明は、優先度を注文に付
随する優先度と納期と未処理時間とを参照して定義し、
複数の設備の中で最も早く処理が終了する時点まで時間
を進め、その時点において、処理が終了した設備に対し
て優先度を参照して所定の工程を振り分ける処理、及
び、処理が終了した工程の次の工程に対して、次工程の
処理が可能な設備の中から待ち状態の工程の総処理時間
を参照して所定の設備を選択する処理を繰り返すことに
より、短時間で現実的な生産スケジュールを立案するこ
とができ、更に、各注文の工程間の移行期間を考慮する
ことによって、各々の設備が点在する場合等であって
も、より現実に即した生産スケジュールを立案すること
ができる。
Thus, the present invention defines a priority with reference to the priority associated with the order, the due date and the unprocessed time,
A process in which the process is advanced to a point in time at which processing is completed earliest among a plurality of facilities, and at that time, a process of assigning a predetermined process to the completed facility by referring to the priority, and a process in which the process is completed For the next process, the process of selecting the specified equipment by referring to the total processing time of the waiting process from among the equipment that can process the next process is repeated, thereby realizing a realistic production in a short time. A schedule can be created, and by considering a transition period between processes of each order, a more realistic production schedule can be created even when each equipment is scattered. it can.

【0019】[0019]

【発明の実施の形態】本発明に係る生産管理方法は、そ
の好ましい一実施の形態において、複数の設備(例えば
設備A〜E)と複数の注文(例えば、注文X及び注文
Y)とを有し、各々の注文に対して1以上の工程(例え
ば、工程X1、X2、工程Y1、Y2)が含まれる状況
において、各々の設備と各々の工程とを対応づけて生産
スケジュールを作成するに際し、いずれかの設備で処理
中の工程が終了する時点まで時間を進め、その時点にお
いて、処理が終了した設備に対しては、注文に付随する
優先度と納期と計算を実行する日時と未処理工程の総時
間とを参照して算出される優先度α(例えば、優先度α
=注文に付随する優先度÷(納期−計算を実行する日
時)×未処理工程の総時間)を参照して所定の工程を振
り分け、処理が終了した工程の次の工程に対しては、次
工程の処理が可能な設備の中から、各設備の処理待ちの
工程の総時間を参照して所定の設備を選択するという離
散的な処理を行うことにより、計算時間を大幅に短縮
し、かつ、全ての注文に対して満足度の高い生産スケジ
ュールを作成することができる。
BEST MODE FOR CARRYING OUT THE INVENTION In a preferred embodiment of the production management method according to the present invention, there are provided a plurality of facilities (for example, facilities A to E) and a plurality of orders (for example, order X and order Y). Then, in a situation where one or more processes (for example, processes X1, X2, processes Y1, Y2) are included for each order, when creating a production schedule by associating each facility with each process, Advance the time until the end of the process being processed in any of the facilities, at which point the priority of the order, the delivery date, the date and time when the calculation is performed, and the unprocessed Priority calculated with reference to the total time (for example, priority α
= Priority associated with order ÷ (delivery date-date and time of execution of calculation) x total time of unprocessed process) By performing discrete processing of selecting predetermined equipment with reference to the total time of the processing waiting process of each equipment from among the equipment capable of performing the processing, the calculation time is significantly reduced, and Thus, a production schedule with a high degree of satisfaction can be created for all orders.

【0020】[0020]

【実施例】上記した本発明の実施の形態についてさらに
詳細に説明すべく、本発明の実施例について図面を参照
して説明する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a block diagram showing an embodiment of the present invention;

【0021】[実施例1]まず、本発明の第1の実施例
に係る生産管理方法におけるアルゴリズムについて、図
1及び図2を参照して説明する。図1は、本実施例のア
ルゴリズムを用いた振り分け方法を説明するためのチャ
ート図であり、図2は、本実施例のアルゴリズムを示す
フローチャート図である。
[Embodiment 1] First, an algorithm in a production management method according to a first embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a chart for explaining a sorting method using the algorithm of the present embodiment, and FIG. 2 is a flowchart showing the algorithm of the present embodiment.

【0022】まず、図1を参照して複数の注文に対して
設備を振り分ける手順について説明する。以下の説明に
際し、注文はXとYの2種類とし、注文Xは工程X1、
工程X2の2つの工程からなり、注文Yは、工程Y1と
工程Y2の2つの工程からなるとする。また、工程X1
は設備A又はBのいずれかで処理され、工程X2は設備
C又はDのいずれかで処理され、工程Y1は設備A〜C
のいずれか、工程Y2は設備Dで処理されるものとす
る。また、初期段階(t=0)において、注文XのX1
工程は設備B、注文YのY1工程は設備Aの処理待ちの
キューに入っているものとする。また、設備A〜Dは稼
働しており、設備A、B、Dには注文X、Y以外の注文
が処理待ちのキューに入っており、設備Cには他の注文
は予定されていないとする。なお、以降の説明は、計算
を行う時刻t0に対して計算上の時間を飛び飛びに進め
(t1〜t8)、各時点においてどのような処理が行わ
れるかを示すものである。
First, a procedure for allocating equipment to a plurality of orders will be described with reference to FIG. In the following description, the order is assumed to be of two types, X and Y, and the order X is a process X1,
It is assumed that the order Y includes two steps of a step X2, and the order Y includes two steps of a step Y1 and a step Y2. Step X1
Is processed in either equipment A or B, step X2 is processed in either equipment C or D, and step Y1 is equipment A to C
, The process Y2 is performed by the equipment D. In the initial stage (t = 0), X1 of order X
It is assumed that the process is in facility B, and the process Y1 of order Y is in the queue of facility A waiting for processing. In addition, equipments A to D are operating, equipments A, B, and D have orders other than orders X and Y in a queue waiting to be processed, and equipment C has no other orders scheduled. I do. In the following description, the calculation time is skipped from time t0 at which the calculation is performed (t1 to t8), and what kind of processing is performed at each time point is shown.

【0023】すなわち、本実施例のアルゴリズムは、従
来例のように一定の時間間隔毎に計算を行うのではな
く、設備A〜Dの処理が終了する予定時刻(t1〜t
8)においてのみ振り分け処理を実行することを特徴と
するものである。具体的には、図1の例では、設備Bの
処理が終了する時点t1が最も早く到来するため、計算
上の時刻をt1まで進める。
That is, the algorithm of the present embodiment does not calculate at regular time intervals as in the conventional example, but the scheduled time (t1 to t) at which the processing of the facilities A to D ends.
It is characterized in that the distribution process is executed only in 8). Specifically, in the example of FIG. 1, the time point t1 at which the processing of the facility B ends is the earliest, so the calculation time is advanced to t1.

【0024】そして、t1において、設備Bの処理待ち
のキューに入っている工程があるか否かを調査する。こ
こでは、予め定義したように設備Bの処理待ちのキュー
には注文Xの工程X1と図示しない他の工程が入ってい
るため、設備Bをいずれかの注文を振り分けることにな
るが、その際、判断の条件として各時点において予め計
算した優先度を基準にする。この優先度は、例えば、注
文に付随する優先度(例えば、重要な製品、重要な顧客
からの依頼等)や納期等を単独で指標とすることができ
るが、本実施例では現実的に処理を行うために、注文に
付随する優先度÷(納期−計算を実行する日時)×未処
理工程でのトータル処理時間を優先度αとして用いるこ
とを特徴としている。
Then, at t1, it is checked whether or not there is a process in the queue of the facility B waiting for processing. Here, as previously defined, the queue for processing the facility B includes the process X1 of the order X and other processes (not shown). Therefore, the order is sorted to the facility B. As a condition for the determination, a priority calculated in advance at each time point is used as a reference. The priority can be, for example, the priority (eg, important product, important customer request, etc.) associated with the order, the delivery date, or the like as an index alone. In order to perform the above, the priority associated with the order ÷ (delivery date−the date and time of execution of the calculation) × the total processing time in the unprocessed process is used as the priority α.

【0025】このような優先度αを採用することによっ
て、注文に付随する優先度のみならず、納期が切迫して
いる製品や処理時間が多く残っている製品を優先的に処
理することができ、注文全体として顧客の満足度を高め
ることができる。この例では、注文Xの優先度が最も高
いとして説明すると、図に示すように設備Bの処理が終
了する時点(t1)で注文Xの工程X1が振り分けられ
る。
By adopting such a priority α, not only the priority accompanying the order but also the product whose delivery time is imminent or the product whose processing time is long can be preferentially processed. As a whole, customer satisfaction can be increased as a whole. In this example, assuming that the priority of the order X is the highest, the process X1 of the order X is assigned at the time (t1) when the processing of the facility B ends as shown in the figure.

【0026】その後、次に処理が終了する時点まで計算
上の時間をスキップする。この例では、設備Aの処理が
終了する時点(t2)が最も早いため、計算上の時間を
t2まで進める。その段階で、計算上の納期までの期間
が変化するため、全ての注文の優先度αを再計算し、同
様に設備Aの処理待ちのキューに入っている工程を調べ
る。ここでは、予め定義したように注文Yの工程Y1と
図示しない他の工程が処理待ちのキューに入っている
が、工程Y1の優先度が最も高いとすると、設備Aに工
程Y1が振り分けられることになる。
Thereafter, the calculation time is skipped until the next processing is completed. In this example, the time point (t2) at which the processing of the facility A ends is the earliest, so the calculation time is advanced to t2. At this stage, since the calculated period until the delivery date changes, the priority α of all the orders is recalculated, and similarly, the process in the queue of the facility A waiting for processing is checked. Here, as previously defined, the process Y1 of the order Y and other processes (not shown) are in the processing waiting queue, but if the priority of the process Y1 is the highest, the process Y1 is allocated to the facility A. become.

【0027】t2での振り分け処理が終了したら、設備
Bの工程X1が終了する時点(t3)において、全ての
注文の優先度を再計算した後、振り分け処理を行う。こ
こで工程X1の次工程である工程X2は、設備C及び設
備Dのいずれも使用可能であるが、設備C及び設備Dは
共に他の工程の処理中であるため、工程X2の処理を直
ちに開始することはできない。そこで、いずれかの設備
の処理待ちのキューに入れることになるが、その際、ど
ちらの設備に振り分けるかは、各々の設備の処理待ちの
工程の数やトータルの処理時間等を総合的に勘案して決
定することが好ましい。この例では、予め定義したよう
に設備Dには処理待ちの工程があるため、工程X2を設
備Cの処理待ちのキューに入れている。
When the distribution process at t2 is completed, at the time (t3) when the process X1 of the facility B ends, the priorities of all the orders are recalculated, and then the distribution process is performed. Here, in the step X2 which is the next step of the step X1, any of the equipment C and the equipment D can be used, but since the equipment C and the equipment D are both being processed in other steps, the processing in the step X2 is immediately performed. Can't start. Therefore, the equipment is placed in the queue waiting to be processed by any one of the facilities. At that time, which equipment is to be allocated is determined by taking into account the number of processes waiting to be processed by each facility and the total processing time, etc. It is preferable to determine it. In this example, since the facility D has a process waiting process as defined in advance, the process X2 is put in the process C queue of the device C.

【0028】その後、いずれかの設備で次に処理が終了
する時点(t4)まで計算上の時間を進め、全ての注文
の優先度αを再計算する。ここで、t4において設備C
及び設備Dの処理が終了するが、設備Cには工程X2の
みが処理待ちのキューに入っているため工程X2を振り
分け、設備Dには予め定義したように図示しない他の注
文の工程が処理待ちのキューに入っているため、その工
程を振り分けることになる。
Thereafter, the calculation time is advanced until the next processing (t4) is completed in any of the facilities, and the priority α of all the orders is recalculated. Here, at time t4, facility C
And the processing of the equipment D is completed. However, since only the processing X2 is in the processing waiting queue in the equipment C, the processing X2 is sorted, and the processing of another order (not shown) is processed in the equipment D as defined in advance. Since it is in the waiting queue, the process is distributed.

【0029】次に、いずれかの設備で次に処理が終了す
る時点(t5)まで計算上の時間を進め、全ての注文の
優先度αを再計算する。そして、t5において工程Y2
を振り分けるが、工程Y2の処理が可能な設備Dは他の
工程の処理中であるため、工程Y2を設備Dの処理待ち
のキューに入れる。そして、t6において設備Dにおけ
る他の工程の処理が終了した時点で、設備Dで工程Y2
の処理を開始し、注文X及び注文Yの各工程に対する設
備の振り分け処理を実行する。
Next, the calculation time is advanced until a time (t5) at which one of the facilities ends the next processing, and the priority α of all the orders is recalculated. Then, at step t5, the process Y2
Since the facility D capable of performing the process Y2 is in the process of another process, the process Y2 is put in a queue waiting for the process of the facility D. Then, at the time when the processing of the other process in the facility D is completed at t6, the facility Y performs the process Y2.
Is started, and equipment allocation processing is executed for each step of order X and order Y.

【0030】上記一連の工程をフローチャート図で説明
すると図2に示すようになる。すなわち、ステップS1
01において、全設備の中で処理が最初に終了する時点
まで計算上の時間を進め、ステップS102において、
その時点での優先度αを注文に付随する優先度と納期と
計算を実行する日時と未処理工程の総時間とから計算す
る。そして、ステップS103において、処理が終了し
た設備に対し、優先度αを基準として処理待ちの注文を
振り分け、一の工程の処理が終了した注文の次の工程を
設備の処理待ちのキューに入れる。そして、ステップS
104において、全ての注文の処理が終了したか否かを
判断し、注文が残っている場合にはステップS101に
戻り、同様の手順で全ての工程の振り分けが終了するま
で計算を行う。
The above series of steps will be described with reference to a flowchart shown in FIG. That is, step S1
In step 01, the calculation time is advanced until the processing ends in all the facilities for the first time, and in step S102,
The priority α at that time is calculated from the priority attached to the order, the delivery date, the date and time when the calculation is executed, and the total time of the unprocessed process. Then, in step S103, orders waiting to be processed are allocated to the equipment whose processing has been completed, based on the priority α, and the next process of the order whose processing has been completed in one step is placed in the processing waiting queue of the equipment. And step S
At 104, it is determined whether or not the processing of all the orders has been completed, and if there are any remaining orders, the process returns to step S101, and the calculation is performed in the same procedure until the distribution of all the steps is completed.

【0031】このように、優先度αを製品に付随する優
先度と納期と計算を実行する日時と未処理時間とを参照
して定義し、複数の設備の中で最も早く処理が終了する
時点まで計算上の時間を進め、その時点で、処理が終了
した設備に対して優先度αを参照して工程を振り分け、
一の工程の処理が終了した注文の次の工程を所定の設備
の処理待ちのキューに入れ、その後、次の処理終了時間
まで計算上の時間を進めて注文の優先度αを再計算する
動作を繰り返すことにより、短時間で現実的な生産計画
を立案することができる。
As described above, the priority α is defined with reference to the priority associated with the product, the delivery date, the date and time at which the calculation is executed, and the unprocessed time, and the time at which the processing ends at the earliest among a plurality of facilities. Advance the calculation time up to that point, and at that point, sort the process with reference to the priority α for the equipment that has completed processing,
An operation of placing the next process of an order after the process of one process is completed in a queue of a predetermined facility for processing, and then advancing the calculation time until the next processing end time to recalculate the priority α of the order. , A realistic production plan can be drafted in a short time.

【0032】すなわち、本実施例では、各設備の処理が
終了する時点でのみ離散的に処理を行うため、全ての組
み合わせについて計算して最適解を求める方法や、予め
定められた時間間隔毎にマップ展開して計算する方法に
比べて、計算時間を著しく短くすることができる。ま
た、注文に付随する優先度のみならず納期や未処理時間
を勘案した優先度αによって振り分け判断を行うため、
より実状に沿ったスケジュールを作成することができ
る。
That is, in this embodiment, since the processing is performed discretely only at the time when the processing of each facility is completed, a method of calculating an optimum solution by calculating all combinations or a method of calculating an optimum solution at every predetermined time interval The calculation time can be remarkably shortened as compared with the method of calculating by expanding the map. In addition, in order to make a sorting decision based on the priority α taking into account the delivery date and unprocessed time as well as the priority attached to the order,
A more realistic schedule can be created.

【0033】なお、本実施例では、説明を容易にするた
めに注文を2つ、設備を4つ使用する場合について説明
したが、本発明は上記実施例に限定されるものではな
く、注文数、各注文の工程数、各工程の使用設備、設備
の数等は任意に設定することができるのは明らかであ
る。また、優先度αとして、製品に付随する優先度と納
期と未処理時間のみならず、他の要素、例えば各注文の
処理に必要な工程の数等を勘案して定義することも可能
であり、生産形態に即して適宜定義することができる。
In this embodiment, the case where two orders and four facilities are used has been described for ease of explanation. However, the present invention is not limited to the above embodiment, and the number of Obviously, the number of steps in each order, the equipment used in each step, the number of equipment, and the like can be arbitrarily set. In addition, as the priority α, it is possible to define not only the priority, delivery date and unprocessed time associated with the product, but also other factors, such as the number of steps required for processing each order. , Can be appropriately defined according to the production mode.

【0034】[実施例2]次に、本発明の第2の実施例
に係る生産管理方法におけるアルゴリズムについて、図
3及び図4を参照して説明する。図3は、本実施例のア
ルゴリズムを用いた振り分け方法を説明するためのチャ
ート図であり、図4は、本実施例のアルゴリズムを示す
フローチャート図である。なお、第2の実施例は、次工
程に移る際に移行期間を考慮することを特徴とするもの
であり、他の部分の構成に関しては前記した第1の実施
例と同様である。
[Second Embodiment] Next, an algorithm in a production management method according to a second embodiment of the present invention will be described with reference to FIGS. FIG. 3 is a chart for explaining a sorting method using the algorithm of the present embodiment, and FIG. 4 is a flowchart showing the algorithm of the present embodiment. The second embodiment is characterized in that a transition period is taken into consideration when moving to the next step, and the configuration of other parts is the same as that of the first embodiment.

【0035】まず、図3を参照して複数の注文に対して
設備を振り分ける手順について説明する。以下の説明に
際し、前記した第1の実施例と同様に、注文はXとYの
2種類とし、注文Xは工程X1、工程X2の2つの工程
からなり、注文Yは、工程Y1と工程Y2の2つの工程
からなるとする。また、工程X1は設備A又はBのいず
れかで処理され、工程X2は設備C又はDのいずれかで
処理され、工程Y1は設備A〜Cのいずれか、工程Y2
は設備Dで処理されるものとする。また、各々の工程に
対し、次工程に移行するための移行時間(x1、x2、
y1)を設定し、この移行時間を便宜的に処理するため
の仮想設備Pを設けている。また、初期段階(t=0)
において、注文XのX1工程は設備B、注文YのY1工
程は設備Aの処理待ちのキューに入っているものとし、
設備A、B、Dには注文X、Y以外の注文が処理待ちの
キューに入っており、設備Cには他の注文は予定されて
いないとする。
First, a procedure for distributing equipment to a plurality of orders will be described with reference to FIG. In the following description, as in the first embodiment described above, the order is of two types, X and Y, the order X is composed of two steps, step X1 and step X2, and the order Y is the step Y1 and step Y2. It is assumed that there are two steps. Further, the process X1 is processed in any of the facilities A and B, the process X2 is processed in any of the facilities C and D, and the process Y1 is performed in any of the facilities A to C and the process Y2.
Is to be processed in equipment D. In addition, for each process, the transition time (x1, x2,
y1) is set, and a virtual facility P for processing the transition time for convenience is provided. In the initial stage (t = 0)
It is assumed that the X1 process of the order X is in the facility B and the Y1 process of the order Y is in the queue of the facility A for processing.
Assume that orders other than orders X and Y are queued for processing in equipments A, B, and D, and no other order is scheduled for equipment C.

【0036】前記した第1の実施例と同様に、全設備を
対象として処理が最初に終了する時点を計算する。図3
の例では、設備Bの処理が終わる時点t1が最も早く到
来するため、計算上の時間をt1まで進める。そして、
t1の時点において、前記した実施例と同様に優先度α
を計算した後、設備Bの処理待ちのキューに入っている
工程があるか否かを調査する。この例では、予め定義し
たように注文Xの工程X1と図示しない他の工程が設備
Bの処理待ちのキューに入っており、工程X1の優先度
が最も高いとすると、設備Bの処理が終了する時点(t
1)に設備Bに注文Xの工程X1が振り分けられる。
In the same manner as in the first embodiment, the time when the process ends for all the facilities is calculated first. FIG.
In the example, the time point t1 at which the processing of the facility B ends is the earliest, so the calculation time is advanced to t1. And
At time t1, the priority α is set in the same manner as in the above-described embodiment.
Is calculated, it is checked whether or not there is a process in a queue of the facility B waiting for processing. In this example, as previously defined, the process X1 of the order X and other processes (not shown) are in the queue waiting for the processing of the equipment B, and if the priority of the processing X1 is the highest, the processing of the equipment B ends. Time (t
In step 1), the process X1 of the order X is allocated to the equipment B.

【0037】その後、次に処理が終了する時点まで計算
上の時間をスキップする。この例では、設備Aの処理が
終了する時間(t2)が最も早いため、時間をt2まで
時間を進める。そして、全注文の優先度αを再計算した
後、設備Aの処理待ちのキューに入っている工程を調べ
る。ここでは、予め定義したように注文Yの工程Y1と
他の工程が処理待ちのキューに入っているが、工程Y1
の優先度が最も高いとすると、設備Aに注文Yの工程Y
1が振り分けられる。
Thereafter, the calculation time is skipped until the next processing is completed. In this example, since the time (t2) at which the processing of the facility A ends is the earliest, the time is advanced to t2. Then, after recalculating the priority α of all the orders, the process in the queue of the equipment A waiting for processing is checked. Here, as previously defined, the process Y1 of the order Y and other processes are in a queue waiting to be processed.
If the priority of the order Y is the highest,
1 is sorted.

【0038】t2での処理が終了したら、次に処理が終
了する時点まで計算上の時間をスキップし、全注文の優
先度αを再計算する。この例では、t3において設備C
及びDの処理が終了するが、設備Cには処理待ちのキュ
ーに工程が入っていないため工程待ちの状態とし、設備
Dには予め定義したように他の注文の工程が処理待ちの
キューに入っているため、その工程の処理を開始する。
When the processing at t2 is completed, the calculation time is skipped until the next processing is completed, and the priority α of all orders is recalculated. In this example, at time t3, facility C
And the processing of D is completed. However, since there is no process in the queue waiting for processing in the facility C, the process is put into a waiting state, and the process of another order is placed in the queue waiting for processing in the facility D as defined in advance. Since it is included, the processing of that step is started.

【0039】次に、設備Bの工程X1が終了する時点
(t4)において、注文Xの次工程である工程X2の振
り分けを行うが、本実施例では、より現実的な生産スケ
ジュールを作成するために、工程間の移行時間を考慮し
ている。すなわち、各々の設備は互いに近接した場所に
設置されているとは限らず、離れた敷地、建家に設置さ
れている場合もある。そこで、工程X1から工程X2に
移行するために必要となる時間x1を設定し、工程X1
が終了してもx1の移行期間内は次の工程X2は直ちに
処理を開始しないこととし、工程X2を設備C又は設備
Dのいずれかの処理待ちのキューに入れることとなる
が、その際、各々の設備の処理待ちの工程の数やトータ
ルの処理時間を勘案して決定することが好ましい。この
例では、設備Dには処理待ちの工程があるため、工程X
2を設備Cの処理待ちのキューに入れている。そして、
移行期間x1が終了するt5の時点において設備Cで工
程X2の処理を開始する。
Next, at the time (t4) when the process X1 of the facility B is completed, the process X2, which is the next process of the order X, is allocated. In this embodiment, a more realistic production schedule is created. First, the transition time between processes is taken into account. That is, each facility is not necessarily installed at a place close to each other, and may be installed at a remote site or a building. Therefore, a time x1 required for shifting from the process X1 to the process X2 is set, and the process X1 is set.
Is completed, the next process X2 is not immediately started during the transition period of x1, and the process X2 is placed in a queue waiting for processing of either the facility C or the facility D. It is preferable that the determination be made in consideration of the number of processes waiting to be processed by each facility and the total processing time. In this example, since the equipment D has a process waiting to be processed, the process X
2 is placed in a queue of the facility C waiting for processing. And
At the time t5 when the transition period x1 ends, the process of the process X2 is started in the facility C.

【0040】同様に、いずれかの設備で次に処理が終了
する時点又は移行期間が終了する時点(t6)までスキ
ップし、全注文の優先度αを再計算する。t6において
も同様に移行期間y1内は次工程Y2を直ちに処理する
ことなく、工程Y2を設備Dの処理待ちのキューに入れ
る。そして、t7の時点において、設備Dにおける他の
工程の処理が終了するが、工程Y2は移行期間y1が終
了していないため、ここでは工程Y2の処理は開始せ
ず、移行期間終了後のt8において工程Y2の処理を開
始し、注文X及び注文Yの各工程に対する設備の振り分
け処理を実行する。
Similarly, the process skips until the time when the processing is next finished in any of the facilities or the time when the transition period ends (t6), and recalculates the priority α of all the orders. At t6, similarly, during the transition period y1, the next process Y2 is not immediately processed, and the process Y2 is put in the processing D queue of the equipment D. Then, at the time t7, the processing of the other process in the facility D ends, but in the process Y2, since the transition period y1 has not ended, the process of the process Y2 does not start here, and t8 after the end of the transition period. , The process of the process Y2 is started, and the process of allocating the equipment to each process of the order X and the order Y is executed.

【0041】上記一連の工程をフローチャート図で説明
すると図4に示すようになる。すなわち、ステップS2
01において、全設備の中で処理が最初に終了する時点
又は工程間の移行期間終了する時点まで時間軸を進め、
ステップS202において、その時点での優先度αを注
文に付随する優先度と納期と計算を実行する日時と未処
理工程の総時間とから計算し、ステップS203におい
て、処理が終了した設備に対し、優先度αを基準として
処理待ちの注文を振り分け、一の工程の処理が終了又は
移行期間が終了した注文の次の工程を設備の処理待ちの
キューに入れる。そして、ステップS204において、
全ての注文の処理が終了したか否かを判断し、注文が残
っている場合にはステップS201に戻り、同様の手順
で全ての工程の振り分けが終了するまで計算を行う。
The above series of steps will be described with reference to a flowchart shown in FIG. That is, step S2
In 01, the time axis is advanced to a point in time when the processing is first completed in all the equipments or a point in time when the transition period between processes is completed,
In step S202, the priority α at that time is calculated from the priority associated with the order, the delivery date, the date and time when the calculation is performed, and the total time of the unprocessed process. The orders waiting to be processed are sorted on the basis of the priority α, and the next step of the order for which the processing of one step has been completed or the transition period has been completed is placed in the processing waiting queue of the equipment. Then, in step S204,
It is determined whether or not the processing of all the orders has been completed. If there are any remaining orders, the process returns to step S201, and the calculation is performed by the same procedure until the distribution of all the steps is completed.

【0042】このように、本実施例の生産管理方法にお
けるアルゴリズムによれば、前記した第1の実施例の効
果に加えて、各注文の工程間の移行期間を考慮すること
によって、各々の設備が点在する場合や次工程に移る前
に一定の保管期間を設けた方がよい場合等であっても、
短時間で現実的な生産スケジュールを立案することがで
きる。
As described above, according to the algorithm in the production management method of this embodiment, in addition to the effects of the above-described first embodiment, by taking into account the transition period between the steps of each order, Even if it is better to provide a certain storage period before moving on to the next process, etc.
A realistic production schedule can be formulated in a short time.

【0043】[実施例3]次に、本発明の第3の実施例
に係る生産管理アルゴリズムを用いた生産管理システム
について、図5及び図6を参照して説明する。図5は、
本実施例の生産管理システム全体の概要を示す図であ
り、図6は、本実施例のアルゴリズムを実行する納期予
測システム内の構成を示す図である。
Third Embodiment Next, a production management system using a production management algorithm according to a third embodiment of the present invention will be described with reference to FIGS. FIG.
FIG. 6 is a diagram illustrating an outline of the entire production management system according to the present embodiment, and FIG. 6 is a diagram illustrating a configuration in a delivery date prediction system that executes an algorithm according to the present embodiment.

【0044】本実施例の生産管理システム1は、図5に
示すように、社内LAN7等のネットワーク網を介して
生産管理部門、製造部門、設計部門等の各部門の端末6
が相互に接続されており、製造部門や設計部門等の進捗
情報が生産管理部門の端末6に集められ、ホストコンピ
ュータ5で管理、保存されている。そして、ホストコン
ピュータ5から定期的にデータベース4に進捗情報ファ
イルがダウンロードされ、その情報は前記した第1及び
第2の実施例で示した生産管理アルゴリズムを実行する
納期予測用マシン3に送られる。また、ホストコンピュ
ータ5で管理することが困難な設計部門の製図作成に係
わる進捗情報は納期予想システム2が進捗情報の収集を
行う。
As shown in FIG. 5, the production management system 1 according to the present embodiment has terminals 6 of respective departments such as a production management department, a manufacturing department, and a design department via a network such as an in-house LAN 7.
Are connected to each other, and progress information of the manufacturing department, the design department, and the like are collected at the terminal 6 of the production management department, and are managed and stored by the host computer 5. Then, the progress information file is periodically downloaded from the host computer 5 to the database 4, and the information is sent to the delivery date prediction machine 3 that executes the production management algorithm shown in the first and second embodiments. In addition, the delivery date forecasting system 2 collects progress information on progress information related to drafting of the design department that is difficult to manage by the host computer 5.

【0045】また、図6に示すように、納期予測システ
ム2は、例えば、進捗データ管理システム8と納期計算
システム9とEUC環境整備10とからなり、進捗デー
タ管理システム8は、製造部門の進捗管理を行う製造進
捗データ管理サブシステム8aと、製図作業の進捗管理
を行う設計進捗データ管理サブシステム8bと、加工ル
ートの指定を行う図面分類サブシステム8cとから構成
され、納期計算システム9は、加工ルート、加工時間な
どの基礎データを整備する基礎データサブシステム9a
と、実績から基礎データを抽出するフィードバックサブ
システム9bと、納期計算を行うシミュレーションサブ
システム9cとから構成されている。また、EUC環境
整備10では、進捗データ管理システム8に保持された
進捗データを利用する環境の整備等を行っている。
As shown in FIG. 6, the delivery date prediction system 2 comprises, for example, a progress data management system 8, a delivery date calculation system 9, and an EUC environment maintenance 10, and the progress data management system 8 The system includes a manufacturing progress data management subsystem 8a for managing, a design progress data management subsystem 8b for managing the progress of drafting work, and a drawing classification subsystem 8c for specifying a machining route. Basic data subsystem 9a that prepares basic data such as processing route and processing time
And a feedback subsystem 9b for extracting basic data from actual results, and a simulation subsystem 9c for calculating a delivery date. In the EUC environment maintenance 10, an environment using the progress data stored in the progress data management system 8 is improved.

【0046】上記構成の生産管理システム1の動作につ
いて以下に説明する。まず、顧客から注文を受けると、
その注文は生産管理部門に送られ、注文に関する所定の
項目が登録された後、製造指示が出される。その際、該
注文が新規製品の場合は図面を作成する必要があるた
め、設計部門に指令が渡され、作成された図面は生産管
理部門に戻される。なお、この一連の図面作成作業は設
計進捗データ管理サブシステム8bによって管理され
る。そして、生産管理部門では、新規図面に対して図面
番号を付与し、図面分類サブシステム8cを用いて図面
の分類を行う。
The operation of the production management system 1 having the above configuration will be described below. First, when an order is received from a customer,
The order is sent to the production management department, and after predetermined items related to the order are registered, a production instruction is issued. At this time, if the order is a new product, it is necessary to create a drawing, so a command is passed to the design department, and the created drawing is returned to the production management department. This series of drawing creation work is managed by the design progress data management subsystem 8b. Then, the production management section assigns a drawing number to the new drawing, and classifies the drawing using the drawing classification subsystem 8c.

【0047】次に、図面分類サブシステム8cで分類さ
れた図面に基づいて製造部門に製造指示が出される。指
示を受けた製造部門では、端末6を用いて所定の項目の
入力を行う。ここで、注文の基礎的なデータは例えばバ
ーコードを用いて行うことができ、工程名、使用設備
名、指令番号等が自動的に入力される構成とするとユー
ザにとって便利である。また、各工程での処理開始時
間、終了時間、処理数量等は、製造部門の作業者が直接
入力を行う。
Next, a manufacturing instruction is issued to the manufacturing department based on the drawings classified by the drawing classification subsystem 8c. In the manufacturing department receiving the instruction, the terminal 6 is used to input predetermined items. Here, the basic data of the order can be performed using, for example, a barcode, and it is convenient for the user if the process name, the name of the equipment used, the command number, and the like are automatically input. In addition, the processing start time, end time, processing quantity, and the like in each process are directly input by a worker in the manufacturing department.

【0048】そして、入力されたデータに基づいて、納
期計算システム9において納期の計算が行われる。具体
的には、図面分類サブシステム8cからの製品分類情
報、フィードバックサブシステム9bからの図面番号毎
の実績データ、進捗データサブシステム8a、8bから
の仕掛指令データ、計上済指令データ等を基礎データサ
ブシステム9aが収集し、インターフェース画面を通じ
て各種情報の入力、修正を行った後、シミュレーション
サブシステム9cに送られる。
The delivery date is calculated in the delivery date calculation system 9 based on the input data. Specifically, the basic data includes product classification information from the drawing classification subsystem 8c, actual data for each drawing number from the feedback subsystem 9b, in-process command data from the progress data subsystems 8a and 8b, accounted command data, and the like. After being collected by the subsystem 9a and inputting and correcting various information through the interface screen, the information is sent to the simulation subsystem 9c.

【0049】基礎データサブシステム9aに入力するデ
ータとしては、具体的には工程や設備を定義するデー
タ、工場のカレンダーデータ、設備のカレンダーデー
タ、加工時間データ、加工ルートデータ等が挙げられ
る。ここで、加工時間、加工ルートは、1回製造したも
のについては、図面番号に対応してそれらのデータがホ
ストコンピュータ5に記憶されているため、そのデータ
を用いることができ、新規品に対しては、図面分類サブ
システム8cで割り当てられた分類番号に従って加工ル
ート、使用設備、加工時間が与えられる。なお、加工ル
ート、加工時間については予め定義した情報が陳腐化す
るおそれがあるため、実績情報を反映して常に更新する
必要がある。
The data to be input to the basic data subsystem 9a include, for example, data defining processes and equipment, factory calendar data, equipment calendar data, processing time data, processing route data, and the like. Here, as for the processing time and the processing route, for those manufactured once, since those data are stored in the host computer 5 corresponding to the drawing numbers, the data can be used, and First, a machining route, a used facility, and a machining time are given according to the classification number assigned by the drawing classification subsystem 8c. It should be noted that the processing route and the processing time need to be constantly updated to reflect the performance information because the information defined in advance may become obsolete.

【0050】そして、上記データに基づいて、シミュレ
ーションサブシステム9cにおいて納期の計算が行われ
る。その具体的な方法は前記した第1及び第2の実施例
に記載したとおりであるが、基礎データサブシステム9
aに記憶された設備に関する情報(設備の処理能力、稼
働状況等)、注文に関する情報(納期、所要工程等)及
び優先度αを参照して、全注文に対して各設備の処理終
了時刻、及び移行期間終了時刻において離散的に設備と
注文の対応付けを行う。例えば、仕掛かりの指令数が3
000、設備数が60、各注文に対する平均工程数が5
として3ヶ月から6ヶ月の期間の納期計算を行った場
合、本実施例の生産管理システム1によれば、約30秒
で計算を行うことができる。
Then, the delivery date is calculated in the simulation subsystem 9c based on the above data. The specific method is as described in the first and second embodiments, but the basic data subsystem 9
With reference to the information (equipment processing capacity, operation status, etc.) regarding the equipment stored in a, the information regarding the order (delivery date, required process, etc.) and the priority α, the processing end time of each equipment for all orders, At the end of the transition period, the equipment and the order are discretely associated with each other. For example, if the number of in-process commands is 3
000, 60 equipments, 5 average steps for each order
According to the production management system 1 of the present embodiment, when the delivery date is calculated for a period of 3 to 6 months, the calculation can be performed in about 30 seconds.

【0051】その後、シミュレーション結果は各端末6
でガントチャート形式等によって出力され、この出力結
果に基づいて製品製造が実施される。また、シミュレー
ション結果と実績との間にずれが生じた場合には、デー
タの入力方法、シミュレーション方法、基礎データの修
正を行い、システムの更新を行う。
Thereafter, the simulation result is transmitted to each terminal 6.
The output is performed in a Gantt chart format or the like, and the product is manufactured based on the output result. If there is a difference between the simulation result and the actual result, the data input method, the simulation method, and the basic data are corrected, and the system is updated.

【0052】このように、本実施例の生産管理システム
1によれば、各部門の進捗情報が生産管理部門に集めら
れた後、ホストコンピュータ5に管理、記憶され、納期
予測システム2では、所定の頻度でホストコンピュータ
5から進捗情報を入手し、予め入力された設備情報や優
先度α等を参照して、各設備と各注文との振り分け処理
を離散的に行うことによって短時間で納期予測を出力す
ることができる。従って、工程管理部門では、各部門の
進捗状況を正確に把握することができ、また、製造部門
では、生産状況の変化に迅速に対応したスケジュールの
もとで生産を遂行することができる。
As described above, according to the production management system 1 of the present embodiment, after the progress information of each department is collected by the production management department, it is managed and stored in the host computer 5. The progress information is obtained from the host computer 5 at a frequency of, and the delivery date is predicted in a short time by discretely allocating each equipment to each order by referring to the equipment information and the priority α etc. which are input in advance. Can be output. Therefore, the process management department can accurately grasp the progress of each department, and the manufacturing department can perform production under a schedule that quickly responds to changes in the production status.

【0053】[実施例4]次に、本発明の第4の実施例
に係る生産管理アルゴリズムを用いた生産管理システム
について、図7及び図8を参照して説明する。図7は、
本実施例の生産管理システム全体の概要を示す図であ
り、図8は、生産管理システムにおける処理の流れを模
式的に示す図である。なお、本実施例は、前記した第3
の実施例のシステムで計算した生産計画を外注工場にお
いてもセキュリティを保持しつつ閲覧可能とするシステ
ムについて記載するものである。
[Fourth Embodiment] Next, a production management system using a production management algorithm according to a fourth embodiment of the present invention will be described with reference to FIGS. FIG.
FIG. 8 is a diagram illustrating an outline of the entire production management system according to the present embodiment, and FIG. 8 is a diagram schematically illustrating a processing flow in the production management system. This embodiment is similar to the third embodiment.
This describes a system that allows the production plan calculated by the system of the third embodiment to be viewed while maintaining security at an outsourcing factory.

【0054】本実施例の生産管理システム1は、図7に
示すように、社内LAN7等のネットワーク網を介して
生産管理部門、製造部門、設計部門等の各部門の端末6
及びプロキシサーバ12が相互に接続されている。ま
た、インターネット網18を介してプロキシサーバ12
とwebサーバ14と外注工場の端末15とが接続され
ている。
As shown in FIG. 7, the production management system 1 according to the present embodiment includes terminals 6 of respective departments such as a production management department, a manufacturing department, and a design department via a network such as an in-house LAN 7.
And the proxy server 12 are connected to each other. Also, the proxy server 12 via the Internet network 18
And a web server 14 and a terminal 15 of an outsourcing factory are connected.

【0055】まず、発注側のユーザは前記した第3の実
施例に示した手順で生産スケジュールを立案する。そし
て、その生産管理データを社内LAN7で接続されたプ
ロキシサーバ12に送信する(図8の)。次に、プロ
キシサーバ12はルータ13を介してインターネット網
18に接続し、webサーバ14に生産計画データを送
信する(図8の)。その際、クライアントプログラム
では、送信の成否をwebサーバ14から受け取り、失
敗した場合には再送信を行う。また、プロキシサーバ1
2はデータの送信終了後、webサーバ14に対して複
合化要求を送付する。
First, a user on the ordering side drafts a production schedule according to the procedure shown in the third embodiment. Then, the production management data is transmitted to the proxy server 12 connected via the in-house LAN 7 (FIG. 8). Next, the proxy server 12 connects to the Internet 18 via the router 13 and transmits the production plan data to the web server 14 (FIG. 8). At this time, the client program receives the success or failure of the transmission from the web server 14, and resends the transmission if the transmission fails. Also, proxy server 1
2 sends a decryption request to the web server 14 after the data transmission is completed.

【0056】なお、データの送信に際して、データの秘
匿性を担保するためにデータをそのまま送信するのでは
なく、所定の暗号化技術(例えば、Advanced Encryptio
n Standard Development Effortで2位となったSerpen
t)を用いて暗号化し、更にデータを所定の大きさのフ
ァイルに分割して送信することを特徴としている。ま
た、データ送信の際、添付すべきファイルに加えて、分
割ファイル数、ファイルID等の管理情報を添付するこ
とが好ましい。
When data is transmitted, the data is not transmitted as it is in order to secure the confidentiality of the data, but rather is transmitted using a predetermined encryption technology (for example, Advanced Encryptio).
n Serpen ranked second in Standard Development Effort
The method is characterized in that the data is encrypted using t), and the data is further divided into files of a predetermined size and transmitted. Also, at the time of data transmission, it is preferable to attach management information such as the number of divided files and the file ID in addition to the file to be attached.

【0057】一方、webサーバ14側では暗号化及び
分割されたファイルを受信すると分割ファイル数、ファ
イルID等の管理情報を参照してファイルの集約、復号
化を行い、元の生産管理データに復元した後、ブラウザ
で閲覧可能なHTML形式等に変換する。
On the other hand, when the web server 14 receives the encrypted and divided files, it refers to the management information such as the number of divided files and the file ID to consolidate and decrypt the files and restore the original production management data. After that, the data is converted into an HTML format that can be browsed by a browser.

【0058】また、外注工場の端末15のwebブラウ
ザは、予め指定されたURLにSSL等を用いてアクセ
スし、予め登録されたユーザ名、パスワードを用いてロ
グインすることによって外注側端末15のwebブラウ
ザで発注側のユーザが作成した生産管理データを閲覧、
あるいはダウンロードすることが可能となる(図8の
)。
The web browser of the terminal 15 of the outsourcing factory accesses the URL specified in advance using SSL or the like, and logs in using the user name and password registered in advance, so that the web browser of the terminal 15 on the outsourcing side. Browse production management data created by the ordering user with a browser,
Alternatively, it can be downloaded (FIG. 8).

【0059】このように、本実施例の生産管理システム
1によれば、発注側ユーザが作成した生産管理データ
が、プロキシサーバ12で暗号化、分割処理を施された
後、webサーバ14に送信され、webサーバ14上
で集約、復号化されてブラウザで閲覧可能な形式に変換
され、予め発注側ユーザに登録された外注工場のユーザ
がインターネット網を介して生産管理データの閲覧、ダ
ウンロードを行うことにより、秘匿性を保持しつつ外注
工場のユーザも生産スケジュールを取得することがで
き、製品の製造に外注工場での処理が含まれる場合であ
っても円滑な生産を実現することができる。
As described above, according to the production management system 1 of the present embodiment, the production management data created by the ordering user is encrypted and divided by the proxy server 12 and then transmitted to the web server 14. Then, the data is aggregated and decrypted on the web server 14, converted into a format that can be browsed by the browser, and the user of the outsourcing factory registered in advance as the ordering user browses and downloads the production management data via the Internet network. Thereby, the user of the outsourcing factory can also acquire the production schedule while maintaining confidentiality, and smooth production can be realized even when the production of the product includes the processing in the outsourcing factory.

【0060】なお、上記構成において、発注ユーザ側で
は、生産計画データが自動的に送信される機能や送信さ
れたデータの履歴を確認する機能、送信先のユーザ以外
が送信データを参照不可とする機能、送信データを受信
ユーザが受信したことを確認できる機能等を有すること
が好ましく、また、外注工場側ユーザでは、発注側から
データが送信されたらその旨が電子メールで担当者宛に
通知される機能や送信データの送信履歴が確認できる機
能、送信データを参照したことを通知できる機能等を有
することが好ましい。
In the above configuration, on the ordering user side, the function of automatically transmitting the production plan data, the function of confirming the history of the transmitted data, and the inability of anyone other than the transmission destination user to refer to the transmission data are prohibited. It is preferable to have a function and a function to confirm that the receiving user has received the transmission data.When the data is transmitted from the ordering side, the outsourcing factory side user is notified by e-mail to the person in charge of the transmission. It is preferable to have a function of confirming the transmission history of transmission data, a function of notifying that transmission data has been referenced, and the like.

【0061】[0061]

【発明の効果】以上説明したように、本発明の生産管理
方法及び生産管理システムによれば下記記載の効果を奏
する。
As described above, according to the production management method and the production management system of the present invention, the following effects can be obtained.

【0062】本発明の第1の効果は、優先度αを製品に
付随する優先度と納期と未処理時間とを参照して定義
し、複数の設備の中で最も早く処理が終了する時点まで
計算上の時間を進め、その時点で優先度αを再計算し
て、処理が終了した設備に対して再計算した優先度αを
参照して注文を振り分けるか、又は、一つの処理が終了
した注文の次工程を所定の設備の処理待ちのキューに入
れる作業を繰り返すという離散的に処理を行うことによ
り、短時間で現実的な生産スケジュールを立案すること
ができるということである。
The first effect of the present invention is that the priority α is defined with reference to the priority, delivery date, and unprocessed time associated with the product, and until the point at which the processing ends at the earliest among a plurality of facilities. Advance the calculation time, recalculate the priority α at that time, sort the order with reference to the recalculated priority α for the equipment for which processing has been completed, or complete one processing By performing the discrete processing of repeating the operation of placing the next process of the order in the processing waiting queue of the predetermined equipment, a realistic production schedule can be drafted in a short time.

【0063】また、本発明の第2の効果は、上記構成に
加えて各注文の工程間の移行期間を考慮することによっ
て、各々の設備が点在する場合等であっても、より現実
に即した生産スケジュールを立案することができるとい
うことである。
The second effect of the present invention is that, in addition to the above-described configuration, by considering the transition period between the steps of each order, even when each facility is scattered, etc. This means that a production schedule can be formulated that is in line with it.

【0064】また、本発明の第3の効果は、各部門の進
捗情報がホストコンピュータに管理、記憶され、納期予
測システムでは、所定の頻度でホストコンピュータから
進捗情報を入手し、予め入力された設備情報や優先度α
等を参照して、各設備と各注文との振り分け処理を離散
的に行うことによって短時間で納期予測を出力すること
ができ、工程管理部門では各部門の進捗状況を正確に把
握することが可能となり、製造部門では生産状況の変化
に迅速に対応したスケジュールのもとで生産を遂行する
ことが可能となるということである。
A third effect of the present invention is that the progress information of each department is managed and stored in the host computer, and in the delivery date prediction system, the progress information is obtained from the host computer at a predetermined frequency and input in advance. Equipment information and priority α
By discretely performing the sorting process for each equipment and each order with reference to the etc., it is possible to output a delivery forecast in a short time, and the process management department can accurately grasp the progress of each department. This makes it possible for the manufacturing department to carry out production on a schedule that quickly responds to changes in the production situation.

【0065】また、本発明の第4の効果は、発注側ユー
ザが作成した生産管理データがプロキシサーバで暗号
化、分割処理を施された後webサーバに送信され、w
ebサーバ上で集約、復号化されてブラウザで閲覧可能
な形式に変換され、予め発注側ユーザに登録された外注
工場のユーザがインターネット網を介して生産スケジュ
ールの閲覧、ダウンロードを行うことにより、秘匿性を
保持しつつ外注工場のユーザも生産スケジュールを取得
することができ、製品の製造に外注工場での処理が含ま
れる場合であっても円滑な生産を実現することができる
ということである。
A fourth effect of the present invention is that the production management data created by the ordering user is encrypted and divided by the proxy server, and then transmitted to the web server.
Aggregated and decrypted on the eb server, converted to a format that can be browsed by the browser, and concealed by users of the outsourcing factory registered in advance as the ordering user who browse and download the production schedule via the Internet network. That is, the user of the outsourcing factory can also acquire the production schedule while maintaining the property, and smooth production can be realized even when the production of the product includes the processing in the outsourcing factory.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施例に係る生産管理アルゴリ
ズムを説明するためのチャート図である。
FIG. 1 is a chart for explaining a production management algorithm according to a first embodiment of the present invention.

【図2】本発明の第1の実施例に係る生産管理アルゴリ
ズムの計算手順を示すフローチャート図である。
FIG. 2 is a flowchart illustrating a calculation procedure of a production management algorithm according to the first embodiment of the present invention.

【図3】本発明の第2の実施例に係る生産管理アルゴリ
ズムを説明するためのチャート図である。
FIG. 3 is a chart for explaining a production management algorithm according to a second embodiment of the present invention.

【図4】本発明の第2の実施例に係る生産管理アルゴリ
ズムの計算手順を示すフローチャート図である。
FIG. 4 is a flowchart illustrating a calculation procedure of a production management algorithm according to a second embodiment of the present invention.

【図5】本発明の第3の実施例に係る生産管理システム
全体の概要を示す図である。
FIG. 5 is a diagram illustrating an outline of an entire production management system according to a third embodiment of the present invention.

【図6】本発明の第3の実施例に係る生産管理システム
のアルゴリズムを実行する納期予測システム内の構成を
示す図である。
FIG. 6 is a diagram showing a configuration in a delivery date prediction system that executes an algorithm of a production management system according to a third embodiment of the present invention.

【図7】本発明の第4の実施例に係る生産管理システム
全体の概要を示す図である。
FIG. 7 is a diagram illustrating an outline of an entire production management system according to a fourth embodiment of the present invention.

【図8】本発明の第4の実施例に係る生産管理システム
生産管理システムにおける処理の流れを模式的に示す図
である。
FIG. 8 is a diagram schematically illustrating a processing flow in a production management system according to a fourth embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 生産管理システム 2 納期予想システム 3 納期予測用マシン 4 データベース 5 ホストコンピュータ 6 端末 7 社内LAN 8 進捗データ管理システム 8a 製造進捗データ管理サブシステム 8b 設計進捗データ管理サブシステム 8c 図面分類サブシステム 9 納期計算システム 9a 基礎データサブシステム 9b フィードバックサブシステム 9c シミュレーションサブシステム 10 EUC環境整備 11 プリンタ 12 プロキシサーバ12 13 ルータ 14 webサーバ 15 外注工場の端末 16 ダイアルアップ 17 プリンタ 18 インターネット網 DESCRIPTION OF SYMBOLS 1 Production management system 2 Delivery time forecasting system 3 Delivery time forecasting machine 4 Database 5 Host computer 6 Terminal 7 In-house LAN 8 Progress data management system 8a Manufacturing progress data management subsystem 8b Design progress data management subsystem 8c Drawing classification subsystem 9 Delivery time calculation System 9a Basic data subsystem 9b Feedback subsystem 9c Simulation subsystem 10 EUC environment maintenance 11 Printer 12 Proxy server 12 13 Router 14 Web server 15 Outsourced factory terminal 16 Dial-up 17 Printer 18 Internet network

───────────────────────────────────────────────────── フロントページの続き (72)発明者 石山 康史 東京都文京区小石川1−3−25 大国ビル 三菱マテリアル株式会社システム事業セ ンター内 (72)発明者 村上 裕 東京都文京区小石川1−3−25 大国ビル 三菱マテリアル株式会社システム事業セ ンター内 (72)発明者 空閑 正浩 東京都千代田区大手町1丁目5番1号 三 菱マテリアル株式会社技術・開発本部生産 技術部内 Fターム(参考) 3C100 AA01 AA23 BB03 BB14  ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Yasushi Ishiyama 1-3-25 Koishikawa, Bunkyo-ku, Tokyo Daikoku Building Mitsubishi Materials Corporation System Business Center (72) Inventor Hiroshi Murakami 1-3 Koishikawa, Bunkyo-ku, Tokyo -25 Daikoku Building Mitsubishi Materials Corporation System Business Center (72) Inventor Masahiro Kuga 1-5-1 Otemachi 1-chome, Chiyoda-ku, Tokyo F-term (reference) 3C100 AA01 AA23 BB03 BB14

Claims (13)

【特許請求の範囲】[Claims] 【請求項1】1以上の工程における処理が必要とされる
複数の注文を、複数の設備の中で前記処理が可能な設備
に順次振り分けて生産スケジュールを作成する生産管理
方法において、 前記複数の設備の各々に対し、所定の処理が終了する予
定時刻を演算し、前記予定時刻の中で最も早く到来する
時刻まで計算上の時間を進め、該時刻において、前記処
理が終了した前記設備に対して、予め算出した優先度を
参照して所定の工程を振り分けるステップ、及び、前記
処理が終了した前記工程の次の工程に対して、該次工程
の処理が可能な設備の中から待ち状態の工程の処理時間
を参照して所定の設備を選択するステップを順次実行
し、前記複数の注文と前記設備との対応付けを行うこと
を特徴とする生産管理方法。
1. A production management method for creating a production schedule by sequentially allocating a plurality of orders requiring processing in one or more processes to equipment capable of performing the processing among a plurality of equipment. For each of the facilities, calculate the scheduled time at which the predetermined process is to be completed, advance the calculation time to the earliest time at which the scheduled time is reached, and at that time, for the facility at which the process has been completed. A step of allocating a predetermined process with reference to a priority calculated in advance, and, for a process next to the process in which the process has been completed, waiting in a facility capable of processing the next process. A step of sequentially selecting predetermined equipment with reference to a processing time of a process, and associating the plurality of orders with the equipment.
【請求項2】1以上の工程における処理が必要とされる
複数の注文を、複数の設備の中で前記処理が可能な設備
に順次振り分けて生産スケジュールを作成する生産管理
方法において、 前記注文における複数の工程間に所定の移行期間を予め
設定し、 前記複数の設備の各々に対し、所定の処理が終了する予
定時刻又は前記移行期間が終了する予定時刻を演算し、
前記予定時刻の中で最も早く到来する時刻まで計算上の
時間を進め、該時刻において、前記処理が終了した前記
設備に対して、予め算出した優先度を参照して所定の工
程を振り分けるステップ、及び、前記処理が終了又は前
記移行期間が終了した前記工程の次の工程に対して、該
次工程の処理が可能な設備の中から待ち状態の工程の処
理時間を参照して所定の設備を選択するステップを順次
実行し、前記複数の注文と前記設備との対応付けを行う
ことを特徴とする生産管理方法。
2. A production management method for creating a production schedule by sequentially allocating a plurality of orders requiring processing in one or more processes to equipment capable of performing the processing among a plurality of equipment, wherein: A predetermined transition period is set in advance between a plurality of processes, and for each of the plurality of facilities, a scheduled time at which predetermined processing ends or a scheduled time at which the transition period ends is calculated,
Advancing the calculated time to the earliest arrival time among the scheduled times, and at that time, allocating a predetermined process to the equipment for which the processing has been completed with reference to a previously calculated priority; And, for the next step of the step where the processing is completed or the transition period is completed, predetermined equipment is referred to from among the equipment capable of performing the processing of the next step with reference to the processing time of the step in the waiting state. A step of sequentially executing the selecting step and associating the plurality of orders with the equipment.
【請求項3】前記優先度を、少なくとも、前記注文に付
随する優先度と、該注文で定められる納期と、計算を実
行する日時と、該注文の未処理工程の総時間とを参照し
て定めることを特徴とする請求項1又は2に記載の生産
管理方法。
3. The priority is determined by referring to at least a priority associated with the order, a delivery date specified in the order, a date and time when a calculation is performed, and a total time of unprocessed steps of the order. The production management method according to claim 1, wherein the production management method is determined.
【請求項4】前記注文に付随する優先度をA、該注文で
定められる納期をT1、計算を実行する日時をT2、該
注文の未処理工程を処理するための総時間をT3とした
場合、 前記優先度を、A÷(T1−T2)×T3で定義するこ
とを特徴とする請求項3記載の生産管理方法。
4. A case where the priority associated with the order is A, the delivery date specified in the order is T1, the date and time when the calculation is performed is T2, and the total time for processing the unprocessed steps of the order is T3. 4. The production management method according to claim 3, wherein the priority is defined by A ÷ (T1−T2) × T3.
【請求項5】前記振り分け処理に際して、全ての前記注
文の前記優先度を再計算することを特徴とする請求項3
又は4に記載の生産管理方法。
5. The method according to claim 3, wherein the priority of all the orders is recalculated during the distribution process.
Or the production management method according to 4.
【請求項6】請求項1乃至5のいずれか一に記載の方法
で作成した生産スケジュールのデータを、所定の暗号化
方法を用いた暗号化処理及び分割処理により複数のファ
イルに変換し、変換した前記複数のファイルを、インタ
ーネット網を介して接続されるサーバに送信し、該サー
バにおいて前記複数のファイルの集約処理及び復号化処
理を行い、ブラウザで閲覧可能な形式に変換することを
特徴とする生産管理方法。
6. The production schedule data created by the method according to claim 1 is converted into a plurality of files by encryption processing and division processing using a predetermined encryption method. Transmitting the plurality of files to a server connected via the Internet network, and performing an aggregation process and a decryption process on the plurality of files in the server to convert the plurality of files into a format that can be browsed by a browser. Production control method.
【請求項7】1以上の工程における処理が必要とされる
複数の注文を、複数の設備の中で前記処理が可能な設備
に順次振り分けて生産スケジュールを作成する生産管理
システムにおいて、 前記複数の設備の各々に対し、所定の処理が終了する予
定時刻を演算する手段と、前記予定時刻の中で最も早く
到来する時刻まで計算上の時間を進め、該時刻におい
て、前記処理が終了した前記設備に対して、予め算出し
た優先度を参照して所定の工程を振り分ける手段と、前
記処理が終了した前記工程の次の工程に対して、該次工
程の処理が可能な設備の中から待ち状態の工程の処理時
間を参照して所定の設備を選択する手段とを少なくとも
有することを特徴とする生産管理システム。
7. A production management system for sequentially allocating a plurality of orders requiring processing in one or more processes to equipment capable of performing the processing among a plurality of equipment and creating a production schedule, wherein: Means for calculating a scheduled time at which a predetermined process is to be completed for each of the facilities; and a calculation time advance to the earliest time at which the scheduled process is completed, and at the time, the facility at which the process is completed. Means for allocating a predetermined process with reference to a priority calculated in advance, and waiting for a process next to the process in which the process has been completed from equipment capable of processing the next process. Means for selecting predetermined equipment with reference to the processing time of the step (a).
【請求項8】1以上の工程における処理が必要とされる
複数の注文を、複数の設備の中で前記処理が可能な設備
に順次振り分けて生産スケジュールを作成する生産管理
システムにおいて、 前記注文の複数の工程間に所定の移行期間を設定する手
段と、所定の処理が終了又は所定の移行期間が終了する
予定時刻を演算する手段と、前記予定時刻の中で最も早
く到来する時刻まで計算上の時間を進め、該時刻におい
て、前記処理が終了した前記設備に対して、予め算出し
た優先度を参照して所定の工程を振り分ける手段と、前
記処理が終了又は前記移行期間が終了した前記工程の次
の工程に対して、該次工程の処理が可能な設備の中から
待ち状態の工程の処理時間を参照して所定の設備を選択
する手段とを少なくとも有することを特徴とする生産管
理システム。
8. A production management system for sequentially allocating a plurality of orders requiring processing in one or more processes to a facility capable of performing the processing among a plurality of facilities and creating a production schedule, wherein: Means for setting a predetermined transition period between a plurality of processes; means for calculating a scheduled time at which a predetermined process ends or a predetermined transition period ends; Means for allocating a predetermined process to the facility for which the process has been completed at the time by referring to a priority calculated in advance, and the process in which the process has been completed or the transition period has been completed. Means for selecting predetermined equipment with reference to the processing time of the waiting step from among the equipment capable of processing the next step for the next step. Management system.
【請求項9】前記優先度が、少なくとも、前記注文に付
随する優先度と、該注文で定められる納期と、計算を実
行する日時と、該注文の未処理工程の総時間とを参照し
て定められることを特徴とする請求項7又は8に記載の
生産管理システム。
9. The method according to claim 1, wherein the priority refers to at least a priority associated with the order, a delivery date determined by the order, a date and time when a calculation is performed, and a total time of unprocessed steps of the order. The production management system according to claim 7, wherein the production management system is determined.
【請求項10】前記注文に付随する優先度をA、該注文
で定められる納期をT1、計算を実行する日時をT2、
該注文の未処理工程を処理するための総時間をT3とし
た場合、 前記優先度が、A÷(T1−T2)×T3で定義される
ことを特徴とする請求項9記載の生産管理システム。
10. The priority associated with the order is A, the delivery date specified in the order is T1, the date and time when the calculation is performed is T2,
10. The production management system according to claim 9, wherein when the total time for processing the unprocessed steps of the order is T3, the priority is defined by A ÷ (T1−T2) × T3. .
【請求項11】前記振り分け処理に際して、全ての前記
注文の前記優先度が再計算されることを特徴とする請求
項9又は10に記載の生産管理システム。
11. The production management system according to claim 9, wherein the priority of all the orders is recalculated during the distribution process.
【請求項12】前記生産管理システムが、少なくとも前
記優先度の計算及び前記振り分け処理を実行する演算処
理装置と、製品製造に関与する各々の部門に設置される
端末と、前記端末の情報を管理、記憶するホストコンピ
ュータとを含み、各々が社内ネットワーク網を介して相
互に接続され、 前記端末から入力された注文情報及び該注文に関する進
捗情報が前記ホストコンピュータに記憶され、該ホスト
コンピュータに記憶された前記情報が所定の間隔毎に前
記演算処理装置に送信されて生産スケジュールが作成さ
れ、該生産スケジュールが前記社内ネットワーク網を介
して前記端末の各々に出力されることを特徴とする請求
項7乃至11のいずれか一に記載の生産管理方法。
12. The production management system manages at least an arithmetic processing unit for executing the priority calculation and the distribution process, terminals installed in respective departments involved in product manufacturing, and information on the terminals. , And a host computer for storing the information, each of which is connected to each other via an in-house network, wherein the order information input from the terminal and the progress information regarding the order are stored in the host computer, and stored in the host computer. 8. The method according to claim 7, wherein the information is transmitted to the arithmetic processing unit at predetermined intervals to create a production schedule, and the production schedule is output to each of the terminals via the in-house network. 12. The production management method according to any one of claims 11 to 11.
【請求項13】前記生産管理システムに、更に、前記社
内ネットワーク網を介して接続されるプロキシサーバ
と、インターネット網を介して接続されるwebサーバ
及び社外の業者に設置される端末とを含み、 前記生産スケジュールのデータが、前記プロキシサーバ
において所定の暗号化方法を用いた暗号化処理及び分割
処理により複数のファイルに変換され、変換された前記
複数のファイルが、インターネット網を介して前記we
bサーバに送信され、該webサーバにおいて前記複数
のファイルの集約処理及び復号化処理が行われた後ブラ
ウザで閲覧可能な形式に変換され、前記社外の業者に設
置される端末で前記生産スケジュールが参照されること
を特徴とする請求項12記載の生産管理システム。
13. The production management system further includes a proxy server connected through the in-house network, a web server connected through the Internet, and a terminal installed in an outside company. The data of the production schedule is converted into a plurality of files by the proxy server in an encryption process and a division process using a predetermined encryption method, and the converted files are transferred to the web server via an Internet network.
b, the files are aggregated and decrypted by the web server, and then converted into a format that can be browsed by a browser. 13. The production management system according to claim 12, which is referred to.
JP2001103443A 2001-04-02 2001-04-02 Production management method and production management system Withdrawn JP2002297222A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001103443A JP2002297222A (en) 2001-04-02 2001-04-02 Production management method and production management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001103443A JP2002297222A (en) 2001-04-02 2001-04-02 Production management method and production management system

Publications (1)

Publication Number Publication Date
JP2002297222A true JP2002297222A (en) 2002-10-11

Family

ID=18956505

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001103443A Withdrawn JP2002297222A (en) 2001-04-02 2001-04-02 Production management method and production management system

Country Status (1)

Country Link
JP (1) JP2002297222A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100530005C (en) * 2006-07-12 2009-08-19 矢崎总业株式会社 Block assembly indicating device and block assembly indicating method
CN103455868A (en) * 2012-05-29 2013-12-18 Juki株式会社 Production management system, production management device, and production management method
JP6168205B1 (en) * 2016-07-08 2017-07-26 富士ゼロックス株式会社 Model order management control device, model order management program
WO2024042766A1 (en) * 2022-08-25 2024-02-29 株式会社日立製作所 Progress management system, production execution system, and progress management method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100530005C (en) * 2006-07-12 2009-08-19 矢崎总业株式会社 Block assembly indicating device and block assembly indicating method
CN103455868A (en) * 2012-05-29 2013-12-18 Juki株式会社 Production management system, production management device, and production management method
CN103455868B (en) * 2012-05-29 2018-05-29 Juki株式会社 Production management system, production management device and production management method
JP6168205B1 (en) * 2016-07-08 2017-07-26 富士ゼロックス株式会社 Model order management control device, model order management program
JP2018005840A (en) * 2016-07-08 2018-01-11 富士ゼロックス株式会社 Molded product order acceptance management control device, molded product order acceptance management program
WO2024042766A1 (en) * 2022-08-25 2024-02-29 株式会社日立製作所 Progress management system, production execution system, and progress management method

Similar Documents

Publication Publication Date Title
Helo et al. Cloud manufacturing–scheduling as a service for sheet metal manufacturing
Stecke A hierarchical approach to solving machine grouping and loading problems of flexible manufacturing systems
US7051328B2 (en) Production server architecture and methods for automated control of production document management
US7283971B1 (en) System and method for managing mobile workers
JP4921727B2 (en) Multiple planning session cooperation system using time constraint, method and product
JPH09330861A (en) Method and system for managing work
Liu et al. Improving energy efficiency in discrete parts manufacturing system using an ultra-flexible job shop scheduling algorithm
Meier et al. Resource planning of industrial product-service systems (IPS 2) by a heuristic resource planning approach
Hong et al. Admission control in queue-time loop production-mixed integer programming with Lagrangian relaxation (MIPLAR)
JP2002297222A (en) Production management method and production management system
JP2006018529A (en) Workflow system, method for controlling it, program, and recording medium
US6917843B2 (en) System and method for scheduling production of molds
Manupati et al. Telefacturing based distributed manufacturing environment for optimal manufacturing service by enhancing the interoperability in the hubs
Aribi et al. Multi-Objective Optimization of the Dynamic and Flexible Job Shop Scheduling Problem Under Workers Fatigue Constraints.
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
WO2016132344A2 (en) System and method for transportation scheduling and planning
Vinod et al. Development and analysis of scheduling decision rules for a dynamic flexible job shop production system: a simulation study
US7123976B2 (en) Capacity management system and method
Krishnaiah Chetty et al. Modelling, simulation and scheduling of flexible assembly systems with coloured Petri nets
Alemão et al. Production and maintenance scheduling supported by genetic algorithms
CN113674798B (en) Proteomics data analysis system
Collart An application of mathematical optimization to autoclave packing and scheduling in a composites manufacturing facility
Frantzén A real-time simulation-based optimisation environment for industrial scheduling
Nejad et al. Integrated dynamic process planning and scheduling in flexible manufacturing systems via autonomous agents
JPH08123869A (en) Information processing system

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20080603