JP2002169938A5 - - Google Patents

Download PDF

Info

Publication number
JP2002169938A5
JP2002169938A5 JP2000366963A JP2000366963A JP2002169938A5 JP 2002169938 A5 JP2002169938 A5 JP 2002169938A5 JP 2000366963 A JP2000366963 A JP 2000366963A JP 2000366963 A JP2000366963 A JP 2000366963A JP 2002169938 A5 JP2002169938 A5 JP 2002169938A5
Authority
JP
Japan
Prior art keywords
work
schedule
worker
information
displaying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000366963A
Other languages
Japanese (ja)
Other versions
JP2002169938A (en
Filing date
Publication date
Application filed filed Critical
Priority to JP2000366963A priority Critical patent/JP2002169938A/en
Priority claimed from JP2000366963A external-priority patent/JP2002169938A/en
Publication of JP2002169938A publication Critical patent/JP2002169938A/en
Publication of JP2002169938A5 publication Critical patent/JP2002169938A5/ja
Pending legal-status Critical Current

Links

Description

【発明の名称】作業担当者のスケジュール管理方法及びスケジュール管理システム [Title of the Invention] Schedule management method for a person in charge and schedule management system

【0001】
【発明の属する技術分野】
本発明は、フィールドで作業する作業担当者の作業実績を管理する作業担当者のスケジュール管理方法及びスケジュール管理システムに関する。
[0001]
Field of the Invention
The present invention relates to a schedule management method and a schedule management system of a worker responsible for managing work performance of a worker who works in the field.

【0005】
【課題を解決するための手段】
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、前記管理コンピュータが、前記作業担当者端末からの作業担当者の識別情報と作業の識別情報と前記作業担当者の作業実績とを含む作業実績データを受け入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、前記記憶部に記憶した作業実績情報に基づいて、前記作業担当者ごとに前記作業の識別情報ごとの作業実績を表示部に表示する段階とを備えた。
[0005]
[Means for Solving the Problems]
The present invention relates to a method of managing a schedule of a worker by using a management computer connected to a worker terminal used by a worker, wherein the management computer is a worker in charge of the work from the worker terminal. Accepting the work record data including the identification information of the worker, the identification information of the work, and the work record of the worker, and storing the work record information in the storage unit based on the work record data; Displaying, on a display unit, the work record for each identification information of the work based on the stored work record information.

【0006】
従って、本発明によれば、作業担当者端末からの作業担当者の作業実績を受入れて記憶することができ、これをもとに各作業担当者について、作業の識別情報ごとの作業実績を出力できる。これにより、作業担当者の作業実績についての情報が洩れなく得られ、作業実績の出力により、作業指示者は、作業担当者のスケジュールの管理をより的確に行うことができる。
[0006]
Therefore, according to the present invention, it is possible to receive and store the work results of the work person in charge from the work person in charge terminal, and based on this, the work results for each work identification information are output for each work person in charge. it can. As a result, the information about the work record of the worker in charge can be obtained without omission, and the output of the work record enables the work instructor to more appropriately manage the schedule of the worker in charge.

【0007】
この作業担当者のスケジュール管理方法において、前記作業実績データは、少なくとも作業開始時刻を含み、前記作業実績を表示部に表示する段階は、少なくとも前記作業開始時刻を含む情報を表示部に表示する。
[0007]
In the schedule management method of the worker, the work record data includes at least a work start time, and displaying the work record on a display unit displays information including at least the work start time on the display unit.

【0008】
これによれば、各作業担当者の作業実績として少なくとも作業開始時刻を出力することが可能となる。
[0008]
According to this, it is possible to output at least the work start time as the work record of each worker.

【0009】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記作業実績データ中の項目について、予め記憶部に記憶された許容されるデータ形式及び値についての条件に基づいて、前記作業実績データ中のデータが、対応する項目について許容されるデータ形式及び値であることを確認する段階と、前記作業実績データ中のデータが、許容されないデータ形式又は値である場合、処理を終了する段階とをさらに備えた。
[0009]
In the schedule management method for a person in charge of work, the management computer is configured to select the items in the work record data based on conditions for acceptable data formats and values stored in the storage unit in advance. C. confirming that the data of the item is an acceptable data format and value for the corresponding item, and terminating the process if the data in the work record data is an unacceptable data format or value Further equipped.

【0010】
これによれば、作業実績データ中の項目のデータ形式又は値が予め定めた許容されるデータ形式又は値でない場合、その作業実績データに基づいて作業実績情報を記憶しないようにすることができる。これにより、適正な作業実績情報を記録でき、作業担当者の作業実績として信頼性の高い情報を出力できる。
[0010]
According to this, when the data format or value of the item in the work performance data is not a predetermined allowable data format or value, it is possible not to store the work performance information based on the work performance data. As a result, appropriate work record information can be recorded, and highly reliable information can be output as the work record of the worker in charge.

【0011】
この作業担当者のスケジュール管理方法において、前記作業実績データは、作業終了時刻を含み、前記作業実績を表示部に表示する段階は、前記記憶部に記憶した作業実績情報の作業担当者の識別情報、作業開始時刻及び作業終了時刻を抽出する段階と、前記作業担当者の識別情報、前記作業開始時刻及び前記作業終了時刻に基づいて、作業担当者ごとに、時間を所定間隔でセルに区切ったフォーマット上に、前記作業開始時刻から前記作業終了時刻までに対応する作業実績を表示する領域を区別して表示する段階とを備えた。
[0011]
In the schedule management method of the worker, the work record data includes a work end time, and when displaying the work record on the display unit, identification information of the worker in the work record stored in the storage unit. Extracting the work start time and the work end time, and based on the identification information of the worker, the work start time, and the job finish time, the time is divided into cells at predetermined intervals for each worker. And displaying, on the format, an area for displaying the work record corresponding to the work start time to the work finish time.

【0012】
これによれば、作業指示者は、作業実績における作業時間を視覚的に容易に把握することができる。
[0012]
According to this, the work instruction person can easily grasp the work time in the work record visually.

【0013】
この作業担当者のスケジュール管理方法において、前記作業実績データは、作業内容に関する情報を含み、前記作業実績を表示する領域を区別して表示する段階は、前記作業実績を表示する領域の内部に前記作業の識別情報を直接又は間接的に示す文字を表示するとともに、前記作業内容に関する情報に応じて、前記作業実績を表示する領域の前記文字及び前記文字の背景の少なくともいずれか一方を区別して表示する。
[0013]
In the schedule management method for a person in charge of work, the work record data includes information related to work content, and the step of displaying the work record separately is displayed in the inside of the area for displaying the work record. Displaying the character directly or indirectly indicating the identification information of the character and at least one of the character of the area for displaying the work result and the background of the character according to the information related to the work content. .

【0014】
これによれば、文字及び表示部の背景の色の少なくともいずれか一方により、作業内容を区別でき、作業指示者は、作業実績の作業内容を容易に把握することができる。
[0014]
According to this, the work content can be distinguished by at least one of the character and the background color of the display unit, and the work instruction person can easily grasp the work content of the work record.

【0015】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記作業実績に対応する移動時間に関する情報を受入れて記憶部に記憶する段階と、その情報を前記記憶部から抽出し、その情報に基づいて前記作業担当者の移動時間を示す情報を表示部に表示する段階とをさらに備えた。
[0015]
In the schedule management method for a person in charge of work, the management computer receives information on movement time corresponding to the work result and stores the information in a storage unit, and extracts the information from the storage unit, based on the information Displaying information indicating the movement time of the worker on the display unit.

【0016】
これによれば、作業指示者は、作業時間に加えてその作業のための移動時間を把握することができる。
[0016]
According to this, the work instruction person can grasp the moving time for the work in addition to the work time.

【0017】
この作業担当者のスケジュール管理方法において、前記作業実績を表示部に表示する段階は、前記作業担当者の作業実績を作業日ごとに表示部に表示する。
[0017]
In the method of managing schedule of a person in charge of work, in the step of displaying the work result on the display unit, the work result of the person in charge of work is displayed on the display unit for each work day.

【0018】
これによれば、作業指示者は、作業日ごとに作業実績を確認することができる。
[0018]
According to this, the work instruction person can confirm the work result for each work day.

【0019】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記作業担当者の識別情報、前記作業の識別情報及び作業開始予定時刻を含む作業予定情報の入力を受入れて記憶部に記憶する段階と、前記表示部に、前記作業予定情報に基づいて、前記作業担当者ごとに作業開始予定時刻を示す情報を含む作業予定を表示する段階とをさらに備えた。
[0019]
In the schedule management method of the worker, the management computer receives input of work schedule information including identification information of the worker, identification information of the work, and scheduled work start time, and stores the input in the storage unit. And displaying, on the display unit, a work schedule including information indicating a scheduled work start time for each worker in charge based on the work schedule information.

【0020】
これによれば、作業予定を管理し、出力することができる。
[0020]
According to this, the work schedule can be managed and output.

【0021】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記作業の識別情報に基づいて前記作業実績に対応する作業予定を特定し、前記表示部に、前記作業実績を対応する前記作業予定と比較可能に表示する段階をさらに備えた。
[0021]
In the schedule management method of the worker, the management computer specifies a work schedule corresponding to the work record based on identification information of the work, and the display unit displays the work schedule corresponding to the work record The method further comprises displaying comparably.

【0022】
これによれば、作業担当者の作業を指示する作業指示者が、作業予定と作業実績とを比較することができる。これにより、作業指示者は、作業担当者の作業予定の変更や新たな作業の追加等についての作業指示を適切に行うことができる。
[0022]
According to this, the work instructioner who instructs the work of the worker can compare the work schedule and the work result. As a result, the work instruction person can appropriately give a work instruction on the change of the work schedule of the work person in charge, the addition of a new work, and the like.

【0023】
この作業担当者のスケジュール管理方法において、前記作業実績を対応する作業予定と比較可能に表示する段階は、前記作業担当者ごとに、作業予定と作業実績とを並べて表示する。
[0023]
In the schedule management method of the worker, in the step of comparably displaying the work result with the corresponding work schedule, the work schedule and the work result are displayed side by side for each worker.

【0024】
これによれば、作業予定と作業実績とが並べて表示されていることで、作業指示者は、これらの比較を視覚的に容易に行うことができ、作業担当者に対して作業指示を適切に行うことができる。
[0024]
According to this, since the work schedule and the work results are displayed side by side, the work instructioner can easily perform the comparison visually and the work instruction can be appropriately given to the work person in charge. It can be carried out.

【0025】
この作業担当者のスケジュール管理方法において、前記作業実績を対応する作業予定と比較可能に表示する段階は、前記作業担当者ごとに作業予定表示欄と作業実績表示欄とを並べて設けた、時間を所定間隔でセルに区切ったフォーマットを用い、前記フォーマット上の作業予定表示欄に前記作業開始予定時刻から作業終了予定時刻までに対応する作業予定を表示する領域を区別して表示するとともに、前記作業実績表示欄に前記作業開始時刻から作業終了時刻までに対応する作業実績を表示する領域を区別して表示する。
[0025]
In the schedule management method of the worker, in the step of displaying the work result comparably to the corresponding work schedule, a time in which a work schedule display field and a work performance display field are arranged side by side for each worker in charge is provided. Using a format divided into cells at predetermined intervals, an area for displaying a work schedule corresponding to the work start scheduled time to the work finish scheduled time is displayed separately in the work schedule display column on the format, and the work record is displayed The display field distinguishes and displays the area in which the work record corresponding to the work start time to the work finish time is displayed.

【0026】
これによれば、作業指示者は、作業予定又は作業実績における作業時間を視覚的に容易に把握することができる。
[0026]
According to this, the work instruction person can easily grasp visually the work time in the work schedule or the work record.

【0027】
この作業担当者のスケジュール管理方法において、前記作業実績データは、作業内容に関する情報及び作業の識別情報を含み、前記作業実績を対応する作業予定と比較可能に表示する段階は、前記作業予定を表示する領域又は前記作業実績を表示する領域の内部に前記作業の識別情報を直接又は間接的に示す文字を表示するとともに、前記作業内容に関する情報に応じて、前記作業予定を表示する領域又は前記作業実績を表示する領域の前記文字及び前記文字の背景の少なくともいずれか一方を区別して表示する。
[0027]
In the schedule management method for a person in charge of work, the work performance data includes information on work content and work identification information, and the step of comparably displaying the work performance with the corresponding work schedule displays the work schedule An area for displaying the work schedule or the work according to the information related to the work content, while displaying a character indicating the identification information of the work directly or indirectly inside the area for displaying the work result or the work record At least one of the character and the background of the character in the area for displaying results is displayed in a differentiated manner.

【0028】
これによれば、所定の表示部内に表示する作業予定又は作業実績を直接又は間接的に示す文字により作業予定又は作業実績を示すことができる。また、文字及び表示部の背景の色の少なくともいずれか一方により作業内容を区別することができる。これにより、作業指示者は、文字及び表示部の背景の色の少なくともいずれか一方により作業予定又は作業実績の作業内容を把握することができる。
[0028]
According to this, it is possible to indicate the work schedule or the work result by the character indicating the work schedule or the work result directly or indirectly displayed in the predetermined display unit. In addition, the work content can be distinguished by at least one of the characters and the background color of the display unit. Thereby, the work instruction person can grasp the work content of the work schedule or the work result by at least one of the character and the background color of the display unit.

【0029】
この作業担当者のスケジュール管理方法において、前記作業予定を表示する段階は、作業が完了か未完了かにより異なる表示を表示する。
[0029]
In the method of managing the schedule of the worker, the step of displaying the work schedule displays different displays depending on whether the work is completed or not completed.

【0030】
これによれば、作業指示者は、作業が完了か未完了かを把握することができる。
[0030]
According to this, the work instruction person can grasp whether the work is completed or not completed.

【0031】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記作業予定に対応する移動時間に関する情報を受入れて記憶部に記憶する段階と、その情報を前記記憶部から抽出し、その情報に基づいて前記作業担当者の移動時間を示す情報を表示部に表示する段階とをさらに備えた。
[0031]
In the method of managing a schedule of a person in charge of work, the management computer receives information on movement time corresponding to the work schedule and stores the information in a storage unit, and extracts the information from the storage unit, based on the information Displaying information indicating the movement time of the worker on the display unit.

【0032】
これによれば、作業予定に対応する移動時間に関する情報の入力を受入れて、これをもとに移動時間の予定を出力することができる。これにより、作業指示者は、作業時間に加えてその作業のための移動時間についての予定をたてることができる。
[0032]
According to this, it is possible to receive the input of the information on the travel time corresponding to the work schedule and to output the travel time schedule based on this. In this way, the work instructor can schedule the movement time for the work in addition to the work time.

【0033】
この作業担当者のスケジュール管理方法において、前記作業実績を対応する作業予定と比較可能に表示する段階は、前記作業担当者ごとの前記作業予定又は前記作業実績を作業日ごとに表示する。
[0033]
In the method of managing schedule of a person in charge of work, the step of comparably displaying the work result with the corresponding work schedule displays the work schedule or the work result of each work person for each work date.

【0034】
これによれば、作業指示者は、作業日ごとに作業予定をたてることができる。
[0034]
According to this, the work instructor can schedule work for each work day.

【0035】
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、前記管理コンピュータが、作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する段階と、前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する段階と、地図を表示部に表示する段階と、前記各作業予定について、作業が完了か未完了かを示す表示を有する作業位置を示す表示を、前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する段階とを備えた。
[0035]
The present invention is a method of managing a schedule of a worker by using a management computer connected to a worker terminal used by a worker, wherein the management computer includes identification information of the worker, the operation of the worker. A work performance data for receiving a work schedule including identification information, work position, and information on work start scheduled time and storing it in a storage unit, and work result data for notifying completion of work including the work identification information from the work person in charge terminal And storing the work record information in the storage unit based on the work record data, confirming whether the work scheduled for each work has been completed or not, and displaying the map And displaying the work position having a display indicating whether the work is completed or not for each of the work schedules based on the latitude / longitude information of the work position. And a step of displaying on a map displayed on the display unit.

【0036】
従って、本発明によれば、地図上の表示により、作業指示者は、作業位置及びその作業が完了又は未完了のいずれであるかを視覚的に確認することができる。これにより、作業指示者は、作業位置と作業が完了か未完了かについての作業状況とにより作業スケジュールを検討することができる。
[0036]
Therefore, according to the present invention, the display on the map enables the work instructor to visually confirm the work position and whether the work is completed or not completed. Thus, the work instructor can review the work schedule based on the work position and the work status as to whether the work is completed or not completed.

【0037】
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、前記管理コンピュータが、作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する段階と、前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する段階と、地図を表示部に表示する段階と、作業が完了していない各作業予定について、作業位置を示す表示を前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する段階とを備えた。
[0037]
The present invention is a method of managing a schedule of a worker by using a management computer connected to a worker terminal used by a worker, wherein the management computer includes identification information of the worker, the operation of the worker. A work performance data for receiving a work schedule including identification information, work position, and information on work start scheduled time and storing it in a storage unit, and work result data for notifying completion of work including the work identification information from the work person in charge terminal And storing the work record information in the storage unit based on the work record data, confirming whether the work scheduled for each work has been completed or not, and displaying the map On the map, the display indicating the work position is displayed on the display unit on the basis of the latitude and longitude information of the work position for each of the stage of displaying on the unit and each work schedule not completed. And a step of displaying.

【0038】
従って、本発明によれば、地図上の表示により、作業指示者は、未完了の作業について作業位置を視覚的に確認することができる。これにより、作業指示者は、未完了の作業について作業スケジュールを検討することができる。
[0038]
Therefore, according to the present invention, the display on the map allows the work instructor to visually confirm the work position for the uncompleted work. Thus, the work instructor can review the work schedule for uncompleted work.

【0039】
この作業担当者のスケジュール管理方法において、前記作業位置を示す表示は、前記作業の識別情報又は作業の対象となる機種を示す文字を有する。
[0039]
In the schedule management method of the worker, the display indicating the work position has characters indicating the identification information of the work or a model to be a target of the work.

【0040】
これによれば、地図上の作業位置を示す表示により、その作業についての作業受付識別子又は機種を把握することができる。これにより、作業指示者は、地図上で作業又は作業に対応する機種を特定することができる。
[0040]
According to this, it is possible to grasp the work reception identifier or the model of the work by the display indicating the work position on the map. Thereby, the work instruction person can specify the work or the model corresponding to the work on the map.

【0041】
この作業担当者のスケジュール管理方法において、前記管理コンピュータが、前記表示部に表示された前記作業位置を示す表示の操作に応じて、その作業についての詳細な情報を表示部に表示する段階をさらに備えた。
[0041]
In the schedule management method of the worker, the management computer further displays, on the display unit, detailed information on the work according to the display operation indicating the work position displayed on the display unit. Equipped.

【0042】
これによれば、作業指示者は、作業位置を示す表示を操作することにより、その作業についての詳細な情報を容易に取得することができる。
[0042]
According to this, the work instruction person can easily acquire detailed information on the work by operating the display indicating the work position.

【0043】
この作業担当者のスケジュール管理方法において、前記作業担当者端末からの作業実績データは、DTMF(DialToneMultiFrequency)により送信されたものである。
[0043]
In the schedule management method of the worker, the work result data from the worker terminal is transmitted by DTMF (DialToneMultiFrequency).

【0044】
これによれば、作業実績データをDTMFにより受付けることができる。これにより、作業担当者は、携帯電話、PHS、公衆電話又は加入電話等のDTMFを発信するプッシュ方式の電話機を用いて、作業実績データを送信することができる。
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、前記管理コンピュータが、前記作業担当者端末からの作業担当者の識別情報と作業の識別情報と前記作業担当者の作業実績とを含む作業実績データを受け入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、前記記憶部に記憶した作業実績情報に基づいて、前記作業担当者ごとに前記作業の識別情報ごとの作業実績を表示部に表示する手段とを備えた。
従って、本発明によれば、作業担当者端末からの作業担当者の作業実績を受入れて記憶することができ、これをもとに各作業担当者について、作業の識別情報ごとの作業実績を出力できる。これにより、作業担当者の作業実績についての情報が洩れなく得られ、作業実績の出力により、作業指示者は、作業担当者のスケジュールの管理をより的確に行うことができる。
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、前記管理コンピュータが、作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する手段と、前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する手段と、地図を表示部に表示する手段と、前記各作業予定について、作業が完了か未完了かを示す表示を有する作業位置を示す表示を、前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する手段とを備えた。
従って、本発明によれば、地図上の表示により、作業指示者は、作業位置及び その作業が完了又は未完了のいずれであるかを視覚的に確認することができる。これにより、作業指示者は、作業位置と作業が完了か未完了かについての作業状況とにより作業スケジュールを検討することができる。
本発明は、作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、前記管理コンピュータが、作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する手段と、前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する手段と、地図を表示部に表示する手段と、作業が完了していない各作業予定について、作業位置を示す表示を前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する手段とを備えた。
従って、本発明によれば、地図上の表示により、作業指示者は、未完了の作業について作業位置を視覚的に確認することができる。これにより、作業指示者は、未完了の作業について作業スケジュールを検討することができる。
[0044]
According to this, it is possible to receive work result data by DTMF. As a result, the worker can transmit work result data using a push-type telephone set such as a mobile phone, PHS, public telephone, subscriber telephone or the like that transmits DTMF.
The present invention is a schedule management system, including a management computer connected to a worker terminal used by a worker, for managing a schedule of a worker, wherein the management computer is from the worker terminal Means for receiving work result data including identification information of a person in charge of work, identification information of a work and work results of the work person, and storing the work result information in a storage unit based on the work result data; And a means for displaying, on the display unit, the work record for each identification information of the work for each worker based on the work record information stored in the storage unit.
Therefore, according to the present invention, it is possible to receive and store the work results of the work person in charge from the work person in charge terminal, and based on this, the work results for each work identification information are output for each work person in charge. it can. As a result, the information about the work record of the worker in charge can be obtained without omission, and the output of the work record enables the work instructor to more appropriately manage the schedule of the worker in charge.
The present invention is a schedule management system, including a management computer connected to a worker terminal used by a worker, for managing a schedule of a worker, wherein the management computer is identification information of the worker. , Means for receiving a work schedule including information on work identification information, work position and work start scheduled time, and storing it in the storage unit, and notifying completion of the work including the work identification information from the worker terminal A unit for receiving work record data and storing the work record information in the storage unit based on the work record data; and a means for confirming whether the work scheduled for each work is completed or not by using the work record information; The latitude of the work position is displayed with a means for displaying a map on the display unit and a work position having a display indicating whether the work is completed or not completed for each of the work schedules. Based on the degree information, and means for displaying on a map displayed on the display unit.
Therefore, according to the present invention, the display on the map enables the work instructor to visually confirm the work position and whether the work is completed or not completed. Thus, the work instructor can review the work schedule based on the work position and the work status as to whether the work is completed or not completed.
The present invention is a schedule management system, including a management computer connected to a worker terminal used by a worker, for managing a schedule of a worker, wherein the management computer is identification information of the worker. , Means for receiving a work schedule including information on work identification information, work position and work start scheduled time, and storing it in the storage unit, and notifying completion of the work including the work identification information from the worker terminal A unit for receiving work record data and storing the work record information in the storage unit based on the work record data; and a means for confirming whether the work scheduled for each work is completed or not by using the work record information; Means for displaying a map on the display unit, and for each work schedule for which work has not been completed, the display indicating the work position is performed based on the latitude and longitude information of the work position. And means for display on a map displayed on the radical 113.
Therefore, according to the present invention, the display on the map allows the work instructor to visually confirm the work position for the uncompleted work. Thus, the work instructor can review the work schedule for uncompleted work.

【0073】
図5に示すように、表示画面57には、地図としての受注マップ58が表示されている。受注マップ58には、当日の作業の位置を示す作業位置を示す表示としての作業表示ボタン59が地図上に表示されている。受注マップ58は指定された日付について表示される。日付の指定は、日付入力ボックス63への入力により行われ、初期設定として当日日付が設定されている。ここでは、「2000/10/02」が設定されている。また、後退ボタン60又は前進ボタ61をクリックすることにより、日付入力ボックス63に表示されている日付が後退又は前進する。一方、カレンダーボタン62をクリックするとカレンダーが表示され、カレンダーに表示されている日付をクリックすることにより、日付が指定される。また、表示設定として、機種名66、受付番号67及び点68についてのラジオ・ボタンが表示されており、作業表示ボタン59には、選択された内容を示す文字が表示される。ここでは、受付番号67が選択されているため、作業表示ボタン59上に受付番号が表示されている。一方、機種名66が選択されると作業表示ボタン59上に機種名が表示され、例えば、受付番号「3883」に対応して、「LP83B」が表示される。また、点68が選択されると作業表示ボタン59が点のみで表示される。作業表示ボタン59上の文字は、作業が未完了の場合は赤色、完了している場合は青色で表示される。一方、点68が選択されている場合は、点のみで表示される作業表示ボタン59は、作業が未完了の場合は赤色、完了している場合は青色で表示される。詳細表示70には、受付情報記憶部15に格納されている受付情報及び顧客情報記憶部16に格納されている顧客情報、予定情報記憶部17に格納されている予定情報及び作業実績情報記憶部18に格納されている作業実績情報により、当日の作業内容についての詳細情報が表示される。詳細表示70は、左右にスクロールさせることにより必要な情報を表示させることができる。ここで、作業表示ボタン59をクリックすると、その作業表示ボタン59に対応する作業内容が最上部に表示される。例えば、受付番号「3883」についての作業表示ボタン59をクリックすると、受付番号「3883」についての詳細情報(機種名「LP83B」及び市町村「上田市」等)が詳細表示70の最上部に表示される。また、再表示ボタン64をクリックすると再表示が行われ、未消化チェックボックス65をチェックして再表示ボタン64をクリックすると、未完了の作業のみが表示される。なお、終了ボタン69をクリックするとこの画面を閉じる。
[0073]
As shown in FIG. 5, the display screen 57 displays an order acceptance map 58 as a map. In the order reception map 58, a work display button 59 as a display showing a work position indicating the position of the work on the current day is displayed on the map. The order map 58 is displayed for the specified date. The designation of the date is performed by inputting to the date input box 63, and the date of the present day is set as an initial setting. Here, "2000/10/02" is set. Also, by clicking the back button 60 or the forward button 61, the date displayed in the date input box 63 is moved backward or forward. On the other hand, when the calendar button 62 is clicked, the calendar is displayed, and the date is specified by clicking the date displayed in the calendar. In addition, as display settings, radio buttons for model name 66, accession number 67, and point 68 are displayed, and on the work display button 59, characters indicating the selected content are displayed. Here, since the reception number 67 is selected, the reception number is displayed on the work display button 59. On the other hand, when the model name 66 is selected, the model name is displayed on the work display button 59, and for example, "LP 83B" is displayed corresponding to the reception number "3883". Further, when the point 68 is selected, the work display button 59 is displayed only by the point. The characters on the work display button 59 are displayed in red when the work is not completed, and in blue when the work is completed. On the other hand, when the point 68 is selected, the operation display button 59 displayed by only the point is displayed in red when the operation is not completed, and in blue when the operation is completed. In the detail display 70, the reception information stored in the reception information storage unit 15, the customer information stored in the customer information storage unit 16, the schedule information stored in the schedule information storage unit 17, and the work record information storage unit The work record information stored in 18 displays detailed information on the work contents of the current day. The detail display 70 can display necessary information by scrolling left and right. Here, when the work display button 59 is clicked, the work content corresponding to the work display button 59 is displayed at the top. For example, when the operation display button 59 for the reception number "3883" is clicked, detailed information (model name "LP83B", the municipality " Ueda City ", etc.) for the reception number "3883" is displayed at the top of the detail display 70. Ru. Further, when the redisplay button 64 is clicked, redisplay is performed, and when the undigested check box 65 is checked and the redisplay button 64 is clicked, only the uncompleted work is displayed. When the end button 69 is clicked, this screen is closed.

【0078】
一方、作業状況の表示更新については、作業実績データの自動受付において作業実績情報記憶部18に格納された作業実績情報及び表示更新情報記憶部23に格納された表示更新情報を用いて行われる。受注マップについては、管理サーバ11は、書込監視ポーリングジョブにより書込監視を所定間隔で行い、作業実績情報の追加がないかどうかを調べる(S609)。作業実績情報の追加がある場合、管理サーバ11は、受注マップ更新ジョブにより、受注マップ(図5に示す受注マップ58)の更新を行う(S610)。スケジュール表についても同様に、管理サーバ11は、書込監視ポーリングジョブにより書込監視を所定間隔で行い、作業実績情報の追加がないかどうかを調べる(S611)。作業実績情報の追加がある場合、管理サーバ11は、スケジュール更新ジョブにより、スケジュール表(図3に示すスケジュール表30)の更新を行う(S612)。
[0078]
On the other hand, the display update of the work status is performed using the work record information stored in the work record information storage unit 18 and the display update information stored in the display update information storage unit 23 in the automatic reception of the work record data. With regard to the order reception map, the management server 11 performs write monitoring at a predetermined interval by the write monitoring polling job, and checks whether there is any addition of work record information (S609). When there is the addition of the work record information, the management server 11 updates the order receiving map (the order receiving map 58 shown in FIG. 5) by the order receiving map update job (S610). Similarly for the schedule table, the management server 11 performs write monitoring at a predetermined interval by the write monitoring polling job, and checks whether there is no addition of work record information ( S611 ). When there is the addition of the work record information, the management server 11 updates the schedule table (the schedule table 30 shown in FIG. 3) by the schedule update job ( S612 ).

Claims (23)

作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、  A method of managing a schedule of a worker by using a management computer connected to a worker terminal used by the worker, the method comprising:
前記管理コンピュータが、  The management computer is
前記作業担当者端末からの作業担当者の識別情報と作業の識別情報と前記作業担当者の作業実績とを含む作業実績データを受け入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、  The work record data including the identification information of the work clerk from the work clerk terminal, the identification information of the work and the work record of the work clerk is accepted, and the work record information is stored in the storage unit based on the work record data Remembering,
前記記憶部に記憶した作業実績情報に基づいて、前記作業担当者ごとに前記作業の識別情報ごとの作業実績を表示部に表示する段階と  Displaying, on a display unit, a work record for each identification information of the work for each of the workers based on the work record information stored in the storage unit;
を備えたことを特徴とする作業担当者のスケジュール管理方法。A method for managing a schedule of a worker, comprising:
請求項1に記載の作業担当者のスケジュール管理方法において、  In the schedule management method for a worker according to claim 1,
前記作業実績データは、少なくとも作業開始時刻を含み、  The work record data includes at least work start time,
前記作業実績を表示部に表示する段階は、少なくとも前記作業開始時刻を含む情報を表示部に表示することを特徴とする作業担当者のスケジュール管理方法。  In the step of displaying the work record on the display unit, information on at least the work start time is displayed on the display unit.
請求項1又は2に記載の作業担当者のスケジュール管理方法において、  In the schedule management method of the worker according to claim 1 or 2,
前記管理コンピュータが、  The management computer is
前記作業実績データ中の項目について、予め記憶部に記憶された許容されるデータ形式及び値についての条件に基づいて、前記作業実績データ中のデータが、対応する項目について許容されるデータ形式及び値であることを確認する段階と、  Regarding items in the work record data, based on conditions for acceptable data types and values stored in the storage unit in advance, data forms and values in the data in the work record data are permitted for the corresponding item Confirming that it is
前記作業実績データ中のデータが、許容されないデータ形式又は値である場合、処理を終了する段階と  Terminating the process if the data in the work record data is an unacceptable data format or value;
をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。A method of managing a schedule of a worker, further comprising:
請求項1〜3のいずれか1つに記載の作業担当者のスケジュール管理方法において、  In the schedule management method of a worker according to any one of claims 1 to 3,
前記作業実績データは、作業終了時刻を含み、  The work record data includes a work end time,
前記作業実績を表示部に表示する段階は、  When displaying the work results on the display unit,
前記記憶部に記憶した作業実績情報の作業担当者の識別情報、作業開始時刻及び作業終了時刻を抽出する段階と、  Extracting the identification information of the worker in the work record information stored in the storage unit, the work start time, and the work end time;
前記作業担当者の識別情報、前記作業開始時刻及び前記作業終了時刻に基づいて、作業担当者ごとに、時間を所定間隔でセルに区切ったフォーマット上に、前記作業開始時刻から前記作業終了時刻までに対応する作業実績を表示する領域を区別して表示する段階と  From the work start time to the work end time on a format in which the time is divided into cells at predetermined intervals for each worker based on the identification information of the worker, the work start time, and the work finish time To distinguish and display the area for displaying the work results corresponding to
を備えたことを特徴とする作業担当者のスケジュール管理方法。A method for managing a schedule of a worker, comprising:
請求項3又は4に記載の作業担当者のスケジュール管理方法において、  In the schedule management method of the worker according to claim 3 or 4,
前記作業実績データは、作業内容に関する情報を含み、  The work record data includes information on work contents,
前記作業実績を表示する領域を区別して表示する段階は、  The step of distinguishing and displaying the area for displaying the work results is:
前記作業実績を表示する領域の内部に前記作業の識別情報を直接又は間接的に示す文字を表示するとともに、前記作業内容に関する情報に応じて、前記作業実績を表示する領域の前記文字及び前記文字の背景の少なくともいずれか一方を区別して表示することを特徴とする作業担当者のスケジュール管理方法。  A character indicating the identification information of the work directly or indirectly is displayed inside the area for displaying the work result, and the characters and characters of the area for displaying the work result according to the information on the work content A method of managing schedule of a worker, characterized by displaying at least one of backgrounds in a distinguished manner.
請求項1〜5のいずれか1つに記載の作業担当者のスケジュール管理方法において、  In the schedule management method of the worker according to any one of claims 1 to 5,
前記管理コンピュータが、  The management computer is
前記作業実績に対応する移動時間に関する情報を受入れて記憶部に記憶する段階と、  Accepting and storing information on the movement time corresponding to the work result in the storage unit;
その情報を前記記憶部から抽出し、その情報に基づいて前記作業担当者の移動時間を示す情報を表示部に表示する段階と  Extracting the information from the storage unit, and displaying information indicating the movement time of the worker in charge on the display unit based on the information;
をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。A method of managing a schedule of a worker, further comprising:
請求項1〜6のいずれか1つに記載の作業担当者のスケジュール管理方法において、  In the method of managing a schedule of a worker according to any one of claims 1 to 6,
前記作業実績を表示部に表示する段階は、前記作業担当者の作業実績を作業日ごとに表示部に表示することを特徴とする作業担当者のスケジュール管理方法。  The step of displaying the work record on the display unit comprises displaying the work record of the worker in charge on the display unit for each work day.
請求項1〜7のいずれか1つに記載の作業担当者のスケジュール管理方法において、  In the method of managing a schedule of a worker according to any one of claims 1 to 7,
前記管理コンピュータが、  The management computer is
前記作業担当者の識別情報、前記作業の識別情報及び作業開始予定時刻を含む作業予定情報の入力を受入れて記憶部に記憶する段階と、  Receiving an input of work schedule information including the identification information of the worker, the identification information of the work, and the scheduled start time of the work, and storing the input in the storage unit;
前記表示部に、前記作業予定情報に基づいて、前記作業担当者ごとに作業開始予定時刻を示す情報を含む作業予定を表示する段階と  Displaying on the display unit a work schedule including information indicating a scheduled work start time for each worker in charge based on the work schedule information;
をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。A method of managing a schedule of a worker, further comprising:
請求項8に記載の作業担当者のスケジュール管理方法において、  The method according to claim 8, wherein:
前記管理コンピュータが、  The management computer is
前記作業の識別情報に基づいて前記作業実績に対応する作業予定を特定し、前記表示部に、前記作業実績を対応する前記作業予定と比較可能に表示する段階をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。  And identifying the work schedule corresponding to the work result based on the identification information of the work, and displaying the work result on the display unit so as to be comparable with the corresponding work schedule. How to manage the schedule of workers.
請求項8又は9に記載の作業担当者のスケジュール管理方法において、  In the schedule management method of a worker according to claim 8 or 9,
前記作業実績を対応する作業予定と比較可能に表示する段階は、前記作業担当者ごとに、作業予定と作業実績とを並べて表示することを特徴とする作業担当者のスケジュール管理方法。  The method for managing a schedule of a worker according to the present invention, wherein the step of displaying the work result comparably with the corresponding work schedule is displaying the work schedule and the work result side by side for each worker.
請求項8〜10のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 8 to 10, wherein
前記作業実績を対応する作業予定と比較可能に表示する段階は、  The step of comparably displaying the work result with the corresponding work schedule is:
前記作業担当者ごとに作業予定表示欄と作業実績表示欄とを並べて設けた、時間を所定間隔でセルに区切ったフォーマットを用い、前記フォーマット上の作業予定表示欄に前記作業開始予定時刻から作業終了予定時刻までに対応する作業予定を表示する領域を区別して表示するとともに、前記作業実績表示欄に前記作業開始時刻から作業終了時刻までに対応する作業実績を表示する領域を区別して表示することを特徴とする作業担当者のスケジュール管理方法。  Using a format in which a work schedule display field and a work performance display field are arranged side by side for each worker in charge and using a format in which time is divided into cells at predetermined intervals, the work schedule from the work start scheduled time on the format An area displaying the work schedule corresponding to the scheduled end time is displayed separately, and an area displaying the work performance corresponding to the work start time to the work end time is displayed separately in the work result display column. A method of managing a schedule of workers according to the present invention.
請求項8〜11のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 8 to 11,
前記作業実績データは、作業内容に関する情報及び作業の識別情報を含み、  The work record data includes information on work contents and work identification information.
前記作業実績を対応する作業予定と比較可能に表示する段階は、  The step of comparably displaying the work result with the corresponding work schedule is:
前記作業予定を表示する領域又は前記作業実績を表示する領域の内部に前記作業の識別情報を直接又は間接的に示す文字を表示するとともに、前記作業内容に関する情報に応じて、前記作業予定を表示する領域又は前記作業実績を表示する領域の前記文字及び前記文字の背景の少なくともいずれか一方を区別して表示することを特徴とする作業担当者のスケジュール管理方法。  A character indicating the identification information of the work directly or indirectly is displayed in the area for displaying the work schedule or the area for displaying the work record, and the work schedule is displayed according to the information related to the work content A method of managing a schedule of a worker according to the present invention, wherein at least one of the character and the background of the character in the region where the work is to be displayed or the region in which the work record is to be displayed is displayed separately.
請求項8〜12のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 8 to 12,
前記作業予定を表示する段階は、作業が完了か未完了かにより異なる表示を表示することを特徴とする作業担当者のスケジュール管理方法。  In the step of displaying the work schedule, a different display is displayed depending on whether the work is completed or not completed.
請求項8〜13のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 8 to 13,
前記管理コンピュータが、  The management computer is
前記作業予定に対応する移動時間に関する情報を受入れて記憶部に記憶する段階と、  Accepting and storing information on the movement time corresponding to the work schedule in a storage unit;
その情報を前記記憶部から抽出し、その情報に基づいて前記作業担当者の移動時間を示す情報を表示部に表示する段階と  Extracting the information from the storage unit, and displaying information indicating the movement time of the worker in charge on the display unit based on the information;
をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。A method of managing a schedule of a worker, further comprising:
請求項8〜14のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 8 to 14,
前記作業実績を対応する作業予定と比較可能に表示する段階は、  The step of comparably displaying the work result with the corresponding work schedule is:
前記作業担当者ごとの前記作業予定又は前記作業実績を作業日ごとに表示することを特徴とする作業担当者のスケジュール管理方法。  A schedule management method of a worker in charge, wherein the work schedule or the work result for each worker is displayed for each work day.
作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、  A method of managing a schedule of a worker by using a management computer connected to a worker terminal used by the worker, the method comprising:
前記管理コンピュータが、  The management computer is
作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する段階と、  Accepting a work schedule including identification information of a worker, work identification information, work position, and information on scheduled work start time, and storing the work schedule in the storage unit;
前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作  Operation notification of completion of work including identification information of the work from the worker terminal 業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、Receiving work performance data and storing work performance information in a storage unit based on the work performance data;
各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する段階と、  Confirming whether the work scheduled for each work has been completed or not by using the work record information;
地図を表示部に表示する段階と、  Displaying the map on the display unit;
前記各作業予定について、作業が完了か未完了かを示す表示を有する作業位置を示す表示を、前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する段階と  Displaying, for each work schedule, a display indicating a work position having a display indicating whether the work is completed or not, on the map displayed on the display unit based on the latitude and longitude information of the work position;
を備えたことを特徴とする作業担当者のスケジュール管理方法。A method for managing a schedule of a worker, comprising:
作業担当者が使用する作業担当者端末に接続された管理コンピュータを用いて作業担当者のスケジュールを管理する方法であって、  A method of managing a schedule of a worker by using a management computer connected to a worker terminal used by the worker, the method comprising:
前記管理コンピュータが、  The management computer is
作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する段階と、  Accepting a work schedule including identification information of a worker, work identification information, work position, and information on scheduled work start time, and storing the work schedule in the storage unit;
前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する段階と、  Receiving work record data for notifying completion of the work including the identification information of the work from the worker terminal, and storing the work record information in the storage unit based on the work record data;
各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する段階と、  Confirming whether the work scheduled for each work has been completed or not by using the work record information;
地図を表示部に表示する段階と、  Displaying the map on the display unit;
作業が完了していない各作業予定について、作業位置を示す表示を前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する段階と  Displaying, for each work schedule whose work has not been completed, a display indicating the work position on the map displayed on the display unit based on the latitude and longitude information of the work position;
を備えたことを特徴とする作業担当者のスケジュール管理方法。A method for managing a schedule of a worker, comprising:
請求項16又は17に記載の作業担当者のスケジュール管理方法において、  In the method of managing a schedule of a worker according to claim 16 or 17,
前記作業位置を示す表示は、前記作業の識別情報又は作業の対象となる機種を示す文字を有することを特徴とする作業担当者のスケジュール管理方法。  The method according to any one of the above, wherein the display indicating the work position includes identification information of the work or characters indicating a model to be a target of the work.
請求項16〜18のいずれか1つに記載の作業担当者のスケジュール管理方法において、  The schedule management method for a worker according to any one of claims 16 to 18,
前記管理コンピュータが、前記表示部に表示された前記作業位置を示す表示の操作に応じて、その作業についての詳細な情報を表示部に表示する段階をさらに備えたことを特徴とする作業担当者のスケジュール管理方法。  A worker in charge further comprising the step of the management computer displaying detailed information about the work on a display unit in response to a display operation indicating the work position displayed on the display unit. Schedule management method.
請求項1〜19のいずれか1つに記載の作業担当者のスケジュール管理方法において、前記作業担当者端末からの作業実績データは、DTMF(Dial Tone Multi Frequency)により送信されたものであることを特徴とする作業担当者のスケジュール管理方法。  The schedule management method for a worker according to any one of claims 1 to 19, wherein the work result data from the worker terminal is transmitted by DTMF (Dial Tone Multi Frequency). The method of schedule management of the person in charge of work characterized. 作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、  A schedule management system for managing a schedule of a worker with a management computer connected to a worker terminal used by the worker, comprising:
前記管理コンピュータが、  The management computer is
前記作業担当者端末からの作業担当者の識別情報と作業の識別情報と前記作業担当者の作業実績とを含む作業実績データを受け入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、  The work record data including the identification information of the work clerk from the work clerk terminal, the identification information of the work and the work record of the work clerk is accepted, and the work record information is stored in the storage unit based on the work record data Means for storing,
前記記憶部に記憶した作業実績情報に基づいて、前記作業担当者ごとに前記作業の識別情報ごとの作業実績を表示部に表示する手段と  A unit for displaying, on a display unit, a work result for each identification information of the work for each of the workers based on the work performance information stored in the storage unit;
を備えたことを特徴とするスケジュール管理システム。The schedule management system characterized by having.
作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、  A schedule management system for managing a schedule of a worker with a management computer connected to a worker terminal used by the worker, comprising:
前記管理コンピュータが、  The management computer is
作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する手段と、  A means for receiving and storing a work schedule including identification information of a worker, work identification information, work position and work start scheduled time in the storage unit;
前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、  A unit that receives work performance data notifying completion of a work including the identification information of the work from the worker terminal and stores the work performance information in the storage unit based on the work performance data;
各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する手段と、  A means for confirming whether the work scheduled for each work has been completed or not using the work record information;
地図を表示部に表示する手段と、  Means for displaying a map on the display unit;
前記各作業予定について、作業が完了か未完了かを示す表示を有する作業位置を示す表示を、前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する手段と  And means for displaying a display indicating a work position having a display indicating whether the work is completed or not for each work schedule on the map displayed on the display unit based on the latitude and longitude information of the work position
を備えたことを特徴とするスケジュール管理システム。The schedule management system characterized by having.
作業担当者が使用する作業担当者端末に接続された管理コンピュータを備えた、作業担当者のスケジュールを管理するスケジュール管理システムであって、  A schedule management system for managing a schedule of a worker with a management computer connected to a worker terminal used by the worker, comprising:
前記管理コンピュータが、  The management computer is
作業担当者の識別情報、作業の識別情報、作業位置及び作業開始予定時刻に関する情報を含む作業予定を受入れて記憶部に記憶する手段と、  A means for receiving and storing a work schedule including identification information of a worker, work identification information, work position and work start scheduled time in the storage unit;
前記作業担当者端末からの前記作業の識別情報を含む作業の完了を通知する作業実績データを受入れて、前記作業実績データに基づいて作業実績情報を記憶部に記憶する手段と、  A unit that receives work performance data notifying completion of a work including the identification information of the work from the worker terminal and stores the work performance information in the storage unit based on the work performance data;
各作業予定の作業が完了か未完了かを前記作業実績情報を用いて確認する手段と、  A means for confirming whether the work scheduled for each work has been completed or not using the work record information;
地図を表示部に表示する手段と、  Means for displaying a map on the display unit;
作業が完了していない各作業予定について、作業位置を示す表示を前記作業位置の緯度経度情報に基づいて、前記表示部に表示した地図上に表示する手段と  And means for displaying, for each work schedule whose work has not been completed, a display indicating the work position on the map displayed on the display unit based on the latitude and longitude information of the work position;
を備えたことを特徴とするスケジュール管理システム。The schedule management system characterized by having.
JP2000366963A 2000-12-01 2000-12-01 Schedule managing method for workers Pending JP2002169938A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000366963A JP2002169938A (en) 2000-12-01 2000-12-01 Schedule managing method for workers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000366963A JP2002169938A (en) 2000-12-01 2000-12-01 Schedule managing method for workers

Publications (2)

Publication Number Publication Date
JP2002169938A JP2002169938A (en) 2002-06-14
JP2002169938A5 true JP2002169938A5 (en) 2004-08-12

Family

ID=18837491

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000366963A Pending JP2002169938A (en) 2000-12-01 2000-12-01 Schedule managing method for workers

Country Status (1)

Country Link
JP (1) JP2002169938A (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005148963A (en) * 2003-11-13 2005-06-09 Hitachi Ltd Schedule and result management device
JP2005222474A (en) * 2004-02-09 2005-08-18 Fuji Xerox Co Ltd Multiplex work support device, multiplex work support method, and program therefor
JP4564783B2 (en) * 2004-05-24 2010-10-20 パナソニック株式会社 Distribution business support system and distribution business support method
JP2007272425A (en) * 2006-03-30 2007-10-18 Mitsubishi Kagaku Media Co Ltd Work status management support system, work status management support method, and program
JP2008159000A (en) * 2006-12-26 2008-07-10 Tpics Systems:Kk Production management system, program for production management, and production management method
JP2009145980A (en) * 2007-12-11 2009-07-02 Toshiba Tec Corp Work schedule management device
JP2009146015A (en) * 2007-12-12 2009-07-02 Hitachi Ltd Server system for schedule management system
JP2010026611A (en) * 2008-07-15 2010-02-04 Sharp Corp Schedule management device, schedule management method, program and recording medium
GB2476111A (en) * 2009-12-11 2011-06-15 Ac Global Systems Ltd Automated response by user radio call tone detection
JP6166114B2 (en) * 2013-07-16 2017-07-19 株式会社セレージャテクノロジー Emergency request system
JP5981607B1 (en) * 2015-05-21 2016-08-31 日本瓦斯株式会社 Gas equipment work management system
WO2017154758A1 (en) 2016-03-09 2017-09-14 日本電気株式会社 Information processing system and information processing method, server device, client, and recording medium on which computer program is stored
JP2021015551A (en) * 2019-07-16 2021-02-12 株式会社Nttドコモ Reservation management system

Similar Documents

Publication Publication Date Title
US8869057B2 (en) Server displaying status of operator using seat layout, terminal for manager, system, and method
US4980910A (en) Portable automatic dialing unit
JP2002169938A5 (en)
CN101261707B (en) Order accounting system and order accounting method
US20050164735A1 (en) Portable electronic apparatus
WO2005076174A2 (en) A device and a method for using an enhanced high priority calendar event
US20040189687A1 (en) Image displaying method, order receiving device, and system having the order receiving device
US20070275766A1 (en) Mobile communication terminal displaying background screen and display method thereof
JP2002169938A (en) Schedule managing method for workers
CN103188396B (en) Device and method for setting time information of affairs to be done in mobile terminals
KR100585793B1 (en) Method for managing other's schedule by phone-book
KR100703274B1 (en) Apparatus and method for managing user database in mobile terminal
JP2005346711A (en) Information providing method
JPH0935192A (en) Delivery navigation device
JP4229430B2 (en) Building specification meeting support system
TWI249121B (en) Portable information terminal and control method
JP2008112416A (en) Time recorder and time recorder system
JP2839258B2 (en) Multi-commodity product ordering system and multifunctional telephone device used in this system
JP2003002203A (en) Diagram data editing information on execution train diagram making, storage medium and diagram data editor
JP2002342540A (en) Work direction management system
JP2784190B2 (en) Sorting device for product information of ordering system in multi-product ordering system
CN107526516A (en) Display control unit
JP2888714B2 (en) Pickup command response system
JP2552188B2 (en) Card terminal
JP3524572B2 (en) Automatic dialing device