JP2002146768A - Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge - Google Patents

Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge

Info

Publication number
JP2002146768A
JP2002146768A JP2000349786A JP2000349786A JP2002146768A JP 2002146768 A JP2002146768 A JP 2002146768A JP 2000349786 A JP2000349786 A JP 2000349786A JP 2000349786 A JP2000349786 A JP 2000349786A JP 2002146768 A JP2002146768 A JP 2002146768A
Authority
JP
Japan
Prior art keywords
drain
ground
gantry
piers
improved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2000349786A
Other languages
Japanese (ja)
Inventor
Akihiro Koga
哲泱 古賀
Isamu Mitanbata
勇 三反畑
Haruo Kumamoto
開男 隈本
Kazuo Todoroki
和夫 轟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Corp
Aoyama Kiko Co Ltd
Original Assignee
Hazama Gumi Ltd
Aoyama Kiko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd, Aoyama Kiko Co Ltd filed Critical Hazama Gumi Ltd
Priority to JP2000349786A priority Critical patent/JP2002146768A/en
Publication of JP2002146768A publication Critical patent/JP2002146768A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method and a work structure capable of advantageously conducting an improvement by vacuum consolidation at the points of the term of works and construction cost even in an extremely soft ground. SOLUTION: The work structure has a plurality of scaffold bridges 4 prepared in approximately parallel at regular intervals in a zone to be improved 2, a frame 13 stretched on a pair of the scaffold bridges in a traveling movable manner, a drain driving machine 11 installed onto the frame laterally movably, a plurality of vertical drains 7 driven into a ground to be improved between the scaffold bridges at regular intervals approximately vertically by the drain driving machine, a horizontal drain material 27 laid on the head sections of a plurality of the vertical drains extended up to a ground surface, an airtight sheet 21 covering a plurality of the vertical drain head sections and the horizontal drain material in an airtight manner, and a vacuum pump 40 secured so as to be communicated with the horizontal drain material.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、作業者や施工機械
が容易に立ち入ることができないような軟弱地盤に含ま
れる水を排出することで硬質地盤へ改良する真空圧密ド
レーン改良工法と、その工法を実施するための施工構造
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vacuum consolidation drain improvement method for draining water contained in soft ground which cannot be easily accessed by a worker or construction machine to improve the hardened ground, and a method therefor. A construction structure for implementing the method.

【0002】[0002]

【従来の技術】鉛直ドレーン、水平ドレーン、気密シー
ト、真空ポンプを用いて、軟弱地盤から水分や空気を吸
い上げて排出する真空圧密地盤改良工法が、例えば、特
開2000−54358号公報や特開2000−104
242号公報に開示されている。これらの工法は真空圧
密により軟弱地盤をシステム的に改良する工法である
が、特開2000−54358号公報に記載の工法は、
ドレーン打設機や作業車両などの泥上走行車が走行可能
な程度の軟弱地盤を対象にしており、また特開2000
−104242号公報に記載の工法は、水面下の軟弱地
盤を対象にするものである。
2. Description of the Related Art A vacuum consolidation ground improvement method for sucking and discharging moisture and air from soft ground using a vertical drain, a horizontal drain, an airtight sheet, and a vacuum pump is disclosed in, for example, JP-A-2000-54358 and JP-A-2000-54358. 2000-104
No. 242. These methods are methods for systematically improving soft ground by vacuum consolidation, but the method described in JP-A-2000-54358 is
It is intended for soft ground that can run on a mud such as a drain driving machine or a working vehicle.
The construction method described in JP-A-104242 targets soft ground under water.

【0003】しかしながら、地盤改良を要する軟弱地盤
のなかには、浮体を備えた泥上走行車での作業が困難な
超軟弱地盤もあり、このような地盤では改良対象域を水
で浸して水上施工を要するものであるが、水上施工は施
工条件によっては困難であり、また工期や工費の点から
も有利とは言い難い。
[0003] However, among soft grounds that require ground improvement, there are also ultra-soft grounds that are difficult to work with a muddy vehicle equipped with a floating body. In such grounds, the area to be improved is immersed in water and construction on water is performed. Although it is necessary, underwater construction is difficult depending on construction conditions, and it is hard to say that it is advantageous in terms of construction period and construction cost.

【0004】また浚渫後まもない埋立地などの超軟弱地
盤においては、作業地盤を確保するために、網状シート
である土木安定シートとサンドマットを地盤の全域に敷
設したり、深さ1〜2m程度までの表層土にセメント粉
末を混合して全域を改良することも行なわれている。こ
れらの方法は、いずれも対象地盤の全域に対して実施す
るので多大な費用を要し、そのための工期も長くかかる
という欠点がある。またサンドマットに関しては、近
年、砂の枯渇から材料の調達にも障害が多いのが実情で
ある。
[0004] In addition, in the case of an extremely soft ground such as a landfill just after dredging, in order to secure a working ground, a civil engineering stabilizing sheet and a sand mat, which are net-like sheets, are laid on the entire ground, or at a depth of one to three. It is also practiced to mix cement powder with a surface soil up to about 2 m to improve the entire area. Each of these methods has a drawback in that it requires a great deal of cost since it is carried out over the entire area of the target ground, and that the construction period is long. In addition, regarding sand mats, in recent years, there are many obstacles to the procurement of materials due to the depletion of sand.

【0005】[0005]

【発明が解決しようとする課題】本発明は上記従来技術
の問題点に着目し、これを解決せんとしたものであり、
その課題は、泥上走行車での作業に困難が予想されるよ
うな極めて軟弱な地盤においても、水上施工、全域の表
層土の改良、土木安定シートやサンドマットの全域への
敷設のいずれも要すること無く、対象地盤の真空圧密に
よる改良を工期や工費の点で有利に行なうことができる
工法及び施工構造を提供することにある。
SUMMARY OF THE INVENTION The present invention focuses on the above-mentioned problems of the prior art and attempts to solve them.
The problem is that even on extremely soft ground where it is expected to be difficult to work with vehicles on mud, it is necessary to perform all work on water, improve the surface soil throughout the area, and lay civil engineering stable sheets and sand mats all over the area. It is an object of the present invention to provide a construction method and a construction structure capable of advantageously improving the target ground by vacuum consolidation in terms of construction period and construction cost without necessity.

【0006】[0006]

【課題を解決するための手段】上記課題を解決するため
に、本発明では、軟弱地盤に含まれる水を排出して硬質
地盤へ改良するための地盤改良工法であって、改良対象
域において複数の桟橋を所定間隔でほぼ平行に造成する
工程と、一対の前記桟橋上を走行移動可能な走行手段で
支持された第一の架台を該桟橋間に架け渡し、該第一の
架台上でドレーン打設機を横移動して前記桟橋間の改良
対象地盤中にほぼ鉛直にドレーン材を打設する工程と、
地表面まで延設した複数の鉛直ドレーン頭部に水平排水
材を敷設する工程と、前記水平排水材に連通する管体を
真空ポンプまで延設する工程と、前記複数の鉛直ドレー
ン頭部及び前記水平排水材を気密シートにより気密に被
覆する工程と、前記真空ポンプを稼働して前記鉛直ドレ
ーンから前記水平排水材を介して地上まで水を導いて排
水する工程とを備えることを特徴とする真空圧密ドレー
ン改良工法が提供される。なお、本発明の工法は、河川
改修などのために軟弱地盤にドレーン材を打設し、地盤
改良を行なう場合をも含むものであって、このような場
合、複数の桟橋は河川の流れに沿って両側に平行曲線状
に設けられることもある。
According to the present invention, there is provided a ground improvement method for draining water contained in soft ground to improve the hard ground by providing a plurality of grounds. Forming a pier at predetermined intervals substantially parallel to each other, and bridging a first gantry supported by traveling means capable of traveling on the pair of piers between the piers, and draining the pier on the first gantry. A step of laterally moving the driving machine and driving the drain material substantially vertically into the ground to be improved between the piers;
Laying horizontal drainage material on a plurality of vertical drain heads extending to the ground surface, extending a pipe communicating with the horizontal drainage material to a vacuum pump, the plurality of vertical drain heads and A vacuum, comprising: a step of airtightly covering a horizontal drainage material with an airtight sheet; and a step of operating the vacuum pump to guide water from the vertical drain to the ground through the horizontal drainage material and drain the water. A method for improving the consolidation drain is provided. The construction method of the present invention includes a case where a drain material is cast on soft ground for river improvement and the like, and ground improvement is performed.In such a case, a plurality of piers are connected to the flow of the river. In some cases, it may be provided on both sides along a parallel curve.

【0007】本発明の真空圧密ドレーン改良工法におい
て、一対の前記桟橋上を走行移動可能な走行手段で支持
された第二の架台を該桟橋間に架け渡し、該第二の架台
を前記第一の架台の後工程で走行させて、該第二の架台
上において前記水平排水材の敷設工程、前記管体の真空
ポンプへの延設工程及び気密シートによる被覆工程を行
っても良い。
In the method for improving the vacuum consolidation drain according to the present invention, a second platform supported by a traveling means capable of traveling on a pair of the piers is bridged between the piers, and the second platform is connected to the first pier. And moving the horizontal drainage material, laying the pipe to a vacuum pump, and covering with a hermetic sheet on the second gantry.

【0008】また本発明では、軟弱地盤に含まれる水を
排出して硬質地盤へ改良する施工構造であって、改良対
象域において所定間隔でほぼ平行に造成した複数の桟橋
と、一対の前記桟橋上を走行移動可能に架け渡した架台
と、前記架台上に横移動可能に設けたドレーン打設機
と、該ドレーン打設機により桟橋間の改良対象地盤中に
ほぼ鉛直に所定間隔で打設された複数の鉛直ドレーン
と、地表面まで延設した複数の鉛直ドレーン頭部に敷設
した水平排水材と、前記複数の鉛直ドレーン頭部及び前
記水平排水材を気密に被覆した気密シートと、前記水平
排水材に連通するように設けられた真空ポンプとを備え
ることを特徴とする施工構造が提供される。
According to the present invention, there is provided a construction structure for discharging water contained in soft ground to improve the hard ground, comprising a plurality of piers formed substantially in parallel at predetermined intervals in an area to be improved, and a pair of the piers. A gantry movably mounted on the gantry, a drain laying machine movably mounted on the gantry, and a vertical laying of the drain laying machine into the ground to be improved between the piers at a predetermined interval. A plurality of vertical drains, a horizontal drainage material laid on a plurality of vertical drain heads extending to the ground surface, an airtight sheet airtightly covering the plurality of vertical drain heads and the horizontal drainage material, And a vacuum pump provided to communicate with the horizontal drainage material.

【0009】[0009]

【発明の実施の形態】本発明において、前記ドレーン材
は、地盤内に含まれる水分を上方の水平排水材まで導く
ことができるものであれば良く、例えば、カードボード
系ドレーン材、フレキシブルパイプ系ドレーン材または
サンドドレーンなどを使用することができるが、前記カ
ードボード系ドレーン材は取り扱いや打設が比較的容易
で、かつ経済性に優れているので最適である。
BEST MODE FOR CARRYING OUT THE INVENTION In the present invention, the drain material may be any material that can guide moisture contained in the ground to an upper horizontal drainage material. For example, a cardboard drain material, a flexible pipe material Although a drain material or a sand drain can be used, the cardboard drain material is most suitable because it is relatively easy to handle and cast and is economical.

【0010】また前記水平排水材は通水性があるもので
あれば良く、例えば、塩化ビニール製の有孔管に不織布
などを巻き付けた有孔排水管、ネットを不織布で巻いた
ドレーン材、通水可能な不織布シート、砂、砂利などを
利用可能である。
The horizontal drainage material may be any material having water permeability. For example, a perforated drainage pipe in which a nonwoven fabric is wound around a perforated pipe made of vinyl chloride, a drain material in which a net is wound with a nonwoven fabric, Possible non-woven sheets, sand, gravel, etc. are available.

【0011】前記桟橋は、上端が地上に突出するように
軟弱地盤に打設した脚体に桁を渡した仮設物であり、ド
レーン打設のための架台、水平排水材や気密シート敷設
するための架台、脚体や桁の材料を運搬する架台を支持
するためのものである。ここで、前記脚体としては杭方
式と矢板方式があり、経済性からは杭方式が好ましく、
特に、杭としてH形鋼などの鋼材を使用すれば、杭の地
盤への打ち込みや引き抜きが容易になり、杭頭の加工性
も優れたものになる。杭方式による桟橋の構築方法は、
先に打設した杭の頭部に桁を架け渡し、この桁に軌道を
設ける。ほぼ平行に位置する一対の桟橋の軌道上に架台
を載せて、この架台上にバイブロハンマー等を有する桟
橋架設装置を搭載し、前方の杭の打設と桁の架設を順次
行なうことにより桟橋を構築する。一方、矢板方式は、
脚体の鉛直支持力や水平支持力を確実に確保する必要が
ある場合、改良対象地盤内に薄い透水層が存在する場
合、あるいは地盤改良に伴なう周辺の地盤沈下などの変
状を最小限に収めたい場合に使用することが好ましく、
比較的中小規模の地盤改良で使用されるものである。矢
板方式による桟橋の構築方法の一つとして、矢板の頭部
に沿って移動可能な慣用の圧入式矢板打設機を使用する
ものがあり、改良対象地盤に打設した矢板の頭部に、こ
の圧入式矢板打設機を設置して、移動させながら隣接す
る矢板を順次圧入打設するものである。矢板方式による
他の工法としては、先に打設した矢板の頭部に桁を架け
渡し、この桁に軌道を設け、ほぼ平行に位置する一対の
桟橋の軌道上に架台を載せて、この架台上からバイブロ
ハンマー等を有する桟橋架設装置により行なうこともで
きる。
[0011] The pier is a temporary structure in which a girder is crossed over a leg that is cast on soft ground so that the upper end protrudes above the ground. To support the gantry, the gantry for transporting the material of the legs and the girder. Here, there are a pile system and a sheet pile system as the legs, and a pile system is preferable in terms of economy,
In particular, if a steel material such as an H-section steel is used for the pile, the pile can be easily driven into and pulled out of the ground, and the pile head can be easily machined. The construction method of the pier by the pile method
A girder is spanned over the head of the pile previously set and a track is provided on this girder. A gantry is placed on the track of a pair of piers located substantially in parallel, a pier erection device having a vibratory hammer, etc. is mounted on the pier, and the pier is sequentially constructed by driving a pile in front and erection of a girder. To construct. On the other hand, the sheet pile method
When it is necessary to ensure the vertical and horizontal bearing capacity of the legs, when there is a thin permeable layer in the ground to be improved, or when deformation such as land subsidence due to ground improvement is minimized. It is preferable to use it if you want to
It is used for relatively small and medium-sized ground improvement. As one of the construction methods of the pier by the sheet pile method, there is a method using a conventional press-fitting sheet pile driving machine that can move along the head of the sheet pile, and the head of the sheet pile placed on the ground to be improved, This press-fitting sheet pile driving machine is installed, and adjacent sheet piles are sequentially press-fitted while moving. Another construction method using the sheet pile method is to bridge a girder over the head of the previously piled sheet pile, provide a track on this girder, place the mount on the track of a pair of piers that are located almost in parallel, It can also be carried out by a pier erection device having a vibro hammer or the like from above.

【0012】前記架台は、桟橋上に支点を有するスパン
約10〜20m程度の鋼製梁であり、H形鋼、I形鋼を
主桁としたもの、H形鋼、I形鋼を複数本組合わせたも
の、鋼材をトラス状に組立てたもの、あるいは仮設用の
組立式橋梁などを用いることができる。架台は、支点部
に車輪や無限軌道などの走行手段を有し、ドレーン打設
機などの施工装置はこの架台の上に設けられる。また架
台の走行手段は、電動モーター、エンジン、ウインチな
どが利用できる。さらに、架台は、一つのレーンの施工
が終了すると、大型クレーンや別途の軌道などを利用し
て隣接するレーンに移されて、この隣接するレーンの施
工を行なうものである。
The gantry is a steel beam having a fulcrum on a pier and having a span of about 10 to 20 m and having a main girder made of an H-beam or an I-beam, and a plurality of H-beams or I-beams. A combination, a steel truss assembled in a truss shape, or a temporary assembly type bridge can be used. The gantry has running means such as wheels and endless tracks at a fulcrum, and a construction device such as a drain driving machine is provided on the gantry. In addition, an electric motor, an engine, a winch, or the like can be used as the traveling means of the gantry. Further, when the construction of one lane is completed, the gantry is moved to an adjacent lane using a large crane or a separate track, and performs the construction of the adjacent lane.

【0013】本発明において、少なくとも前記桟橋間の
改良対象地盤上にはシート材、網状材または網状シート
材を敷設しても良く、これにより、前記鉛直ドレーン頭
部の埋没防止、作業者の軟弱地盤中への埋没防止などが
図れるという利点がある。また本発明において、前記真
空ポンプは、鉛直ドレーン、水平排水材などを介して改
良対象地盤内に真空圧を作用させて、地盤の圧密沈下を
促進すると共に地中の水分や空気を、地表まで吸引・排
出する役割を担うものであるが、気密シート下から地表
への水分の排出は、別途、水中ポンプなどを併用して行
なうことも可能である。
In the present invention, a sheet material, a net-like material or a net-like sheet material may be laid at least on the ground to be improved between the piers, whereby the vertical drain head is prevented from being buried, and the worker is soft. There is an advantage that burial in the ground can be prevented. Further, in the present invention, the vacuum pump applies a vacuum pressure to the ground to be improved through a vertical drain, a horizontal drainage material, etc., to promote consolidation settlement of the ground and to release moisture and air from the ground to the surface. Although it plays a role of sucking and discharging, it is also possible to separately discharge water from below the airtight sheet to the surface of the ground using a submersible pump or the like.

【0014】[0014]

【実施例】以下、添付図面に基づいて実施例を説明する
が、本発明はこれに限定されるものではない。図1は本
発明により地盤改良を行なう対象域の平面図である。こ
こで、改良対象地盤は、海岸に沿った道路3aと護岸3
bとにより囲まれた範囲を埋め立てて造成したものであ
り、改良対象域2には複数の桟橋4が所定間隔でほぼ平
行に構築される。図2(a)(b)及び図3は、かかる
埋立造成地盤に本発明の工法を適用した様子を示す平面
図、側面図及び側面図であり、図4〜図7はそれぞれ本
発明の工法に用いる装置の側面図及び正面図である。図
2及び図3において、本発明の施工構造は、改良対象域
2を挟んで所定間隔でほぼ平行に構築した複数の桟橋4
と、一対の桟橋4上に走行移動可能に架け渡した架台1
3と、この架台上に横移動可能に設けたドレーン打設機
11と、ドレーン打設機11により桟橋4,4間の改良
対象地盤2中にほぼ鉛直に所定間隔で打設した複数の鉛
直ドレーン7と、地表面に出た鉛直ドレーン頭部に敷設
した水平排水材としての水平ドレーン材27及び有孔排
水管26と、これら鉛直ドレーン7、有孔排水管26及
び水平ドレーン材27を気密に被覆した気密シート21
と、排水パイプ41、有孔排水管26及び水平ドレーン
材27を介して鉛直ドレーン7に連通する真空ポンプ4
0とを主要部として備え、さらに、桟橋4の上には架台
13を走行させるための軌道が設けられている。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments will be described below with reference to the accompanying drawings, but the present invention is not limited to these embodiments. FIG. 1 is a plan view of a target area in which ground improvement is performed according to the present invention. Here, the ground to be improved is road 3a along the coast and seawall 3
The pier 4 is constructed by reclaiming the area surrounded by b. In the improvement target area 2, a plurality of piers 4 are constructed substantially in parallel at predetermined intervals. FIGS. 2A, 2B, and 3 are a plan view, a side view, and a side view, respectively, showing a state in which the method of the present invention is applied to such a landfill ground. FIGS. It is a side view and a front view of an apparatus used for the present invention. 2 and 3, the construction structure according to the present invention includes a plurality of piers 4 constructed substantially in parallel at predetermined intervals with the improvement target area 2 interposed therebetween.
And a gantry 1 movably mounted on a pair of piers 4
3, a drain driving machine 11 movably provided on the gantry, and a plurality of vertical driving devices which are driven by the drain driving device 11 substantially vertically at predetermined intervals in the ground 2 to be improved between the piers 4 and 4. The drain 7, a horizontal drain material 27 and a perforated drainage pipe 26 laid as a horizontal drainage material laid on the head of the vertical drain that emerges from the ground surface, and the vertical drain 7, the perforated drainage pipe 26, and the horizontal drain material 27 are hermetically sealed. Airtight sheet 21 covered with
And a vacuum pump 4 communicating with the vertical drain 7 via a drain pipe 41, a perforated drain pipe 26 and a horizontal drain material 27.
0 is provided as a main part, and a track for running the gantry 13 is provided on the pier 4.

【0015】図3及び図6において、前記架台13と前
記ドレーン打設機11は施工装置10を構成するものと
して提供され、これ以外に、施工装置10は、網状シー
ト材14が捲回されたドラム14aと作業用足場15と
を備えている。ここで、前記架台13は、その下面に桟
橋4上を走行するための車輪16を有し、上面にドレー
ン打設機11を走行・横移動させるためのレール(図示
せず)が架設方向に延設されている。また前記ドレーン
打設機11は、モータ(図示せず)などにより駆動され
て架台13のレール上を走行する車輪11dがベース版
11cの下面に設けられ、このベース版11cの上にや
ぐら11aがほぼ垂直に立設されてケーシング11bを
上下動可能に支持し、ケーシング11bはやぐら11a
の下端に設けた駆動装置11eにより上下に駆動される
ように構成されている。またベース版11cの上には、
ドレーン材12が捲回されたドラム12aが設けられ、
ドレーン材12はこのドラム12aから捲き出されてケ
ーシング11bの上端から下端まで供給される。
In FIGS. 3 and 6, the gantry 13 and the drain driving machine 11 are provided as constituting a construction apparatus 10, and in addition to this, the construction apparatus 10 has a reticulated sheet material 14 wound thereon. A drum 14a and a work scaffold 15 are provided. Here, the gantry 13 has wheels 16 on its lower surface for traveling on the pier 4, and rails (not shown) for traveling and laterally moving the drain driving machine 11 on its upper surface in the erection direction. It has been extended. The drain driving machine 11 has wheels 11d, which are driven by a motor (not shown) and travel on rails of the gantry 13, provided on a lower surface of a base plate 11c. The casing 11b is erected substantially vertically to support the casing 11b so that it can move up and down.
It is configured to be driven up and down by a driving device 11e provided at the lower end of the. Also, on the base version 11c,
A drum 12a around which the drain material 12 is wound is provided,
The drain material 12 is unwound from the drum 12a and supplied from the upper end to the lower end of the casing 11b.

【0016】かかる施工装置10では、架台13が図3
の矢印M方向に走行しながら網状シート材14をドラム
14aから捲き出して地上面に敷設し、ドレーン打設機
11は架台13上を走行することにより、桟橋4,4間
を図6の矢印S方向に横移動し、順次、ドレーン材12
をケーシング11bとともにほぼ鉛直に改良対象地盤2
に打設することで、網状シート材14を貫通する複数の
鉛直ドレーン7を軟弱地盤中に形成するものである。し
たがって、施工装置10では、桟橋4上を走行移動する
架台13が超軟弱地盤に接地すること無く上方に支持さ
れ、該架台13上をドレーン打設機11が横移動しなが
らドレーン材12を打設するので、改良対象域2に桟橋
4を構築すれば、鉛直ドレーンの打設施工が可能にな
り、従来のように、超軟弱地盤の全域にわたる表層改良
は不要になった。なお、鉛直ドレーンの打設工程は、上
記施工装置10以外にも、ショベル系ベースマシンのア
ームにケーシングや圧入装置を装備したものも利用可能
である。
In the construction apparatus 10, the gantry 13 is
While running in the direction of arrow M, the net-like sheet material 14 is unwound from the drum 14a and laid on the ground surface, and the drain driving machine 11 travels on the gantry 13 to move between the piers 4 and 4 as shown in FIG. Move laterally in the S direction, and sequentially drain material 12
To be improved with the casing 11b almost vertically
, A plurality of vertical drains 7 penetrating the mesh sheet material 14 are formed in the soft ground. Therefore, in the construction apparatus 10, the gantry 13 traveling and moving on the pier 4 is supported upward without touching the ultra-soft ground, and the drain driving machine 11 strikes the drain material 12 while moving laterally on the gantry 13. Therefore, if the pier 4 is constructed in the area 2 to be improved, it becomes possible to perform the construction of a vertical drain, and it is not necessary to improve the surface layer over the entire ultra-soft ground as in the related art. In addition, in addition to the above-described construction apparatus 10, the vertical drain installation step may be performed by using an arm of a shovel base machine equipped with a casing or a press-fitting device.

【0017】次に、図3及び図7に図示した作業架台2
0について説明する。作業架台20は、網状シート材1
4の敷設工程や鉛直ドレーン7の打設工程に続く工程、
例えば、有孔排水管26、水平ドレーン材27及び気密
シート21などの敷設工程を行なうための装置であり、
一対の桟橋4,4間に架け渡される架台23の両端下面
に車輪24が設けられ、この車輪24により桟橋4上を
走行し、架台23の上に水平ドレーン材27を捲回した
ドラム22、気密シート21、有孔排水管などが積載さ
れ、これら水平ドレーン材27などを超軟弱地盤上に敷
設するための作業足場28を備えている。
Next, the work platform 2 shown in FIGS.
0 will be described. The work platform 20 is a net-like sheet material 1
Steps following the laying step of 4 and the placing step of the vertical drain 7,
For example, it is an apparatus for performing a laying process of a perforated drain pipe 26, a horizontal drain material 27, an airtight sheet 21, and the like.
Wheels 24 are provided on the lower surfaces at both ends of a gantry 23 bridged between the pair of piers 4, 4, and the drums 22 run on the pier 4 with the wheels 24 and wind the horizontal drain material 27 on the gantry 23. An airtight sheet 21, a perforated drainage pipe, and the like are loaded thereon, and a work scaffold 28 for laying the horizontal drain material 27 and the like on the extremely soft ground is provided.

【0018】なお、施工装置10及び作業架台20を軌
道17上で走行移動させるための駆動手段としては、電
動モーター、エンジン、ウインチによる引出しなどが利
用可能である。
An electric motor, an engine, a drawer using a winch, or the like can be used as a driving means for moving the construction apparatus 10 and the work platform 20 on the track 17.

【0019】次に、図4を参照して桟橋4と桟橋架設用
クレーン50について説明する。桟橋4は、改良対象地
盤2にH形鋼を一列に打設してなる杭4bと、この杭頭
に一本のH形鋼を架け渡してなる桁4aとから構成さ
れ、これが図4に示したものであるが、これ以外にも、
例えば、杭及び桁を複数列に配置して桁の上に床版を張
ったものを桟橋とすることも可能である。また図示はし
ないが、桁4aの上面には、架台の車輪を導く軌道が設
けられている。
Next, the pier 4 and the crane 50 for pier construction will be described with reference to FIG. The pier 4 is composed of a pile 4b in which H-shaped steel is cast in a row on the ground 2 to be improved, and a girder 4a in which one H-shaped steel is bridged over the pile head. It is shown, but besides this,
For example, a pier may be a pile and a girder arranged in a plurality of rows and a floor slab stretched over the girder. Although not shown, a track for guiding the wheels of the gantry is provided on the upper surface of the spar 4a.

【0020】かかる桟橋4を架設するための装置は、図
2に示したように、一対の桟橋4,4上に架け渡された
架台55,57と、架台55上に設置される桟橋架設用
クレーン50であり、架台55,57はその下面に桟橋
4上を走行するための車輪16を有し、架台57上には
杭材や桁材としてのH形鋼などの資材4’を積載して桟
橋架設用クレーン50を後追い走行させる。ここで、桟
橋架設用クレーン50は、架台55上を横行するための
クローラ53と、このクローラ53上に旋回可能に設け
られたベースマシン52と、このベースマシン52から
起伏操作されるブーム51aと、ブーム51aの先端に
ワイヤーロープ51bを介して懸吊されたバイブロハン
マー51cとから構成され、杭4bとしてのH形鋼はバ
イブロハンマー51cにより把持されて改良対象地盤中
に打設され、この杭4bの上に桁4aとしてのH形鋼が
架け渡される。
As shown in FIG. 2, the apparatus for erection of the pier 4 includes pedestals 55, 57 laid over a pair of piers 4, 4, and a pier installed on the pedestal 55. The cranes 55 and 57 have wheels 16 for traveling on the pier 4 on the lower surface thereof, and the gantry 57 is loaded with materials 4 ′ such as pile materials and H-beams as girder materials. The pier-building crane 50 is driven to follow. Here, the jetty erection crane 50 includes a crawler 53 for traversing on a gantry 55, a base machine 52 rotatably provided on the crawler 53, and a boom 51a which is raised and lowered from the base machine 52. , A vibratory hammer 51c suspended at the tip of a boom 51a via a wire rope 51b, and the H-section steel as the pile 4b is gripped by the vibratory hammer 51c and driven into the ground to be improved. An H-section steel as the spar 4a is bridged over 4b.

【0021】次に、図5を参照して図4とは異なる桟橋
9と桟橋架設装置について説明する。図5において、桟
橋9は、改良対象地盤2に一列に打設してなる矢板9b
と、この頭部に一本のH形鋼を架け渡してなる桁9aと
から構成される。ここでも、桟橋4の場合と同様に、矢
板及び桁を複数列に配置して桁の上に床版を張ったもの
を桟橋とすることも可能であり、図示はしないが、桁9
aの上面には、架台の車輪を導く軌道が設けられてい
る。
Next, a pier 9 and a pier erection apparatus different from those in FIG. 4 will be described with reference to FIG. In FIG. 5, the pier 9 is a sheet pile 9b which is cast in a line on the ground 2 to be improved.
And a girder 9a having one H-shaped steel bridge over the head. Here, as in the case of the pier 4, it is also possible to arrange a sheet pile and a girder in a plurality of rows and put a floor slab on the girder to form a pier.
A track for guiding the wheels of the gantry is provided on the upper surface of a.

【0022】かかる矢板9bを用いた桟橋9を架設する
ための装置としては、慣用の矢板建込みクレーン60と
矢板圧入機62があり、両装置は地中に連設された矢板
の頭部に沿って走行可能、かつ矢板頭部から転倒しない
ように構成されている。ここで、矢板建込みクレーン6
0は、矢板の頭部に沿って走行するベースマシン63
と、このベースマシン63に起伏可能に取り付けられた
ブーム61aと、ブーム61aを起伏させる伸縮シリン
ダー61bと、ブーム61aの先端からワイヤーロープ
61cにより懸吊されたフック61dとから構成されて
いる。一方、架台57は下面に車輪57aを有するもの
であり、先行して構築した一対の桟橋9,9に架け渡さ
れて、矢板や桁材としてのH形鋼などの資材9’を積載
し、矢板建込みクレーン60や矢板圧入機62の両装置
に後追い走行させるものである。桟橋9の架設施工の際
には、架台57に積載された矢板9bを矢板建込みクレ
ーン60により吊り上げて矢板圧入機62に供給し、こ
れにより矢板9bを改良対象地盤に打設する。次に矢板
圧入機62を矢板建込みクレーン60を使って前進させ
た後に、矢板建込みクレーン60を内蔵のシリンダーで
前進させる。このようにして矢板の打設枚数が15枚程
度になったら、連設した矢板9bの頭部に桁9aとして
のH形鋼を架け渡して固定する。次に、架台57を前進
させたのち同様な作業を繰返して桟橋を構築する。
As a device for erection of the pier 9 using the sheet pile 9b, there are a conventional sheet pile crane 60 and a sheet pile press-in machine 62, both of which are mounted on the head of a sheet pile continuously installed in the ground. It is configured to be able to travel along and not to fall from the sheet pile head. Here, sheet pile cranes 6
0 is a base machine 63 running along the head of the sheet pile
And a boom 61a attached to the base machine 63 so as to be able to raise and lower, a telescopic cylinder 61b for raising and lowering the boom 61a, and a hook 61d suspended from the tip of the boom 61a by a wire rope 61c. On the other hand, the gantry 57 has wheels 57a on the lower surface, is bridged over a pair of piers 9, 9 constructed in advance, and loads a material 9 'such as a sheet pile or a H-beam as a girder material. Both the sheet pile building crane 60 and the sheet pile press-in machine 62 make the machine follow-up. When the pier 9 is erected, the sheet pile 9b loaded on the pedestal 57 is lifted by the sheet pile crane 60 and supplied to the sheet pile press-in machine 62, thereby driving the sheet pile 9b into the ground to be improved. Next, after the sheet pile press-in machine 62 is advanced using the sheet pile crane 60, the sheet pile crane 60 is advanced with the built-in cylinder. When the number of sheet piles is about 15 in this way, an H-section steel as the spar 9a is bridged over the head of the continuous sheet piles 9b and fixed. Next, after the gantry 57 is advanced, the same operation is repeated to construct a pier.

【0023】次に、図10は改良構造の断面図であり、
ここでは施工装置10及び作業架台20による施工後の
地盤断面を示した。また図8(a)は本発明による改良
構造の平面図であり、図8(b)は鉛直ドレーン頭部の
詳細を示す拡大平面図である。図8及び図10におい
て、改良構造は、改良対象地盤に所定長離隔してほぼ平
行に造成された桟橋4,4と、桟橋4,4間の改良対象
域2に敷設された網状シート材14と、網状シート材1
4を貫通するように所定間隔でほぼ鉛直に打設された複
数の鉛直ドレーン7と、地表面に敷設された水平ドレー
ン材27及び有孔排水管26と、これら鉛直ドレーン7
の頭部、水平ドレーン材27及び有孔排水管26などの
上を気密に被覆するように敷設された気密シート21
と、有孔排水管26に排水管41を介して接続された真
空ポンプ40とを備える。
FIG. 10 is a sectional view of the improved structure.
Here, the ground cross section after construction by the construction apparatus 10 and the work stand 20 is shown. FIG. 8A is a plan view of the improved structure according to the present invention, and FIG. 8B is an enlarged plan view showing details of a vertical drain head. 8 and 10, the improved structure includes piers 4, 4, which are formed approximately parallel to the ground to be improved at a predetermined distance, and a mesh sheet material 14 laid in the area 2 to be improved between the piers 4, 4. And mesh sheet material 1
4, a plurality of vertical drains 7 laid substantially vertically at predetermined intervals so as to penetrate through the ground 4, a horizontal drain material 27 and a perforated drainage pipe 26 laid on the ground surface, and these vertical drains 7.
Airtight sheet 21 laid so as to airtightly cover the head, horizontal drain material 27 and perforated drain pipe 26, etc.
And a vacuum pump 40 connected to the perforated drain pipe 26 via a drain pipe 41.

【0024】ここで、前記水平ドレーン材27は、ネッ
トを不織布で巻いた幅30cm程度の水平ドレーン材を
使用し、前記気密シート21は二枚の塩化ビニールシー
トを積層してなる厚さ0.5mmのものを使用する。ま
た前記桟橋4は、脚体としての杭4bと、この杭4bの
上に架け渡された桁4aとから構成される。さらに、前
記気密シート21は内部を気密にするために、図9
(a)〜(e)に示すような構造により端部処理がなさ
れる。すなわち、図9(a)は深さ30〜80cmの溝
35a内に気密シート端部21aを入れて泥土35bに
より埋め戻したもの、図9(b)は気密シート端部21
aを上から押え盛土8により押えたもの、図9(c)は
CMC、MC、HEC、グアガムなどの増粘材や糊材を
土砂に添加した流動化ソイル36を気密シート端部21
aの下に流し込んで圧着したもの、図9(d)は気密シ
ート端部21aを工具などにより地盤内に圧入したも
の、図9(e)は土嚢37や水袋を気密シート端部21
aの上に載せたものである。以上、図9(a)〜(e)
は単独で設けるか、あるいは、これら2つ以上を組み合
わせて設けても良い。
Here, the horizontal drain material 27 is a horizontal drain material having a width of about 30 cm in which a net is wound with a non-woven fabric, and the airtight sheet 21 is formed by laminating two vinyl chloride sheets. Use a 5mm one. The pier 4 includes a stake 4b as a leg and a girder 4a bridged over the stake 4b. Further, the airtight sheet 21 is provided with a structure shown in FIG.
The edge processing is performed by the structure shown in FIGS. 9 (a) shows the airtight sheet end 21a inserted into a groove 35a having a depth of 30 to 80 cm and backfilled with mud 35b, and FIG. 9 (b) shows the airtight sheet end 21.
FIG. 9 (c) shows a fluidized soil 36 obtained by adding a thickening material such as CMC, MC, HEC, guar gum or a glue material to earth and sand, and an airtight sheet end 21.
9 (d) shows the airtight sheet end 21a pressed into the ground with a tool or the like, and FIG. 9 (e) shows the sandbag 37 or water bag with the airtight sheet end 21a.
a. As described above, FIGS.
May be provided singly or in combination of two or more.

【0025】以上の図10の実施例に加えて、図11ま
たは図12のように改良構造を構成することも可能であ
る。すなわち、図11は、杭4bを用いて桟橋4を構築
し、桟橋4,4間の改良対象域2に図10と同様な改良
構造を設けることに加え、気密シート21の上に水を貯
留するか、あるいは載荷盛土43を設け、排水管41の
途中にジェットポンプ44を介在させて排水能力を上昇
させたものである。また図12は、矢板9bを用いて桟
橋9を構築し、桟橋9,9間の改良対象域2には図10
と同様な改良構造を設けることに加え、矢板9bにより
囲まれた範囲内には水を貯留したものである。このよう
に矢板9bを用いた場合、たとえ改良対象域2に透水層
70が存在しても、この透水層70は矢板9bにより遮
断されるので、透水層70を介して圧力が低下すること
は防止される。
In addition to the embodiment shown in FIG. 10, an improved structure can be formed as shown in FIG. 11 or FIG. That is, in FIG. 11, the pier 4 is constructed using the piles 4 b, the improvement structure similar to that of FIG. 10 is provided in the improvement target area 2 between the piers 4, 4, and water is stored on the airtight sheet 21. Alternatively, a loading embankment 43 is provided, and the drainage capacity is increased by interposing a jet pump 44 in the middle of the drainage pipe 41. Also, FIG. 12 shows that the pier 9 is constructed using the sheet pile 9b, and the improvement target area 2 between the piers 9 and 9 is shown in FIG.
In addition to providing the same improved structure as above, water is stored in the area surrounded by the sheet pile 9b. When the sheet pile 9b is used as described above, even if the water permeable layer 70 exists in the improvement target area 2, since the water permeable layer 70 is blocked by the sheet pile 9b, the pressure is not reduced through the water permeable layer 70. Is prevented.

【0026】次に、真空圧密ドレーン改良工法について
説明する。最初に、図1に示すように、改良対象域に複
数の桟橋4を所定間隔、例えば14m程度にほぼ平行に
構築する。次に、図6及び図7に示したように、施工装
置10及び作業架台20を隣合う桟橋4,4上に走行可
能に設置することにより、それぞれの架台13、架台2
3を桟橋4,4間に架け渡し、施工装置10を図3の矢
印M方向に走行させながらドラム14aから捲き出した
網状シート材14を地盤上に敷設し、所定位置で施工装
置10の走行を停止する。施工装置10の走行を停止し
たら、ドレーン打設機11を図6の矢印S方向に横移動
させながら鉛直ドレーン7を改良対象地盤2に所定間隔
で打設する。
Next, the method of improving the vacuum consolidation drain will be described. First, as shown in FIG. 1, a plurality of piers 4 are constructed at predetermined intervals, for example, approximately in parallel with each other at a predetermined interval, for example, about 14 m in the improvement target area. Next, as shown in FIGS. 6 and 7, by installing the construction apparatus 10 and the work platform 20 on adjacent piers 4 and 4 so as to be able to travel, the respective platforms 13 and 2
3 is laid between the piers 4 and 4, the netting sheet material 14 unwound from the drum 14a is laid on the ground while the construction apparatus 10 travels in the direction of arrow M in FIG. 3, and the construction apparatus 10 travels at a predetermined position. To stop. When the traveling of the construction device 10 is stopped, the vertical drain 7 is driven into the ground 2 to be improved at predetermined intervals while the drain driving machine 11 is moved laterally in the direction of the arrow S in FIG.

【0027】このように網状シート材14と鉛直ドレー
ン7が設置された改良対象地盤2上に作業架台20を走
行させて、この作業架台20から水平ドレーン材27と
有孔排水管26とを鉛直ドレーン7頭部に連通するよう
に敷設し、これら鉛直ドレーン7頭部、水平ドレーン材
27及び有孔排水管26などの上に気密シート21を捲
き出し、その端部21aに盛土8を積載して改良対象地
盤上を気密に被覆する。
The work platform 20 is run on the ground 2 to be improved on which the mesh sheet material 14 and the vertical drain 7 are installed, and the horizontal drain material 27 and the perforated drain pipe 26 are vertically separated from the work platform 20. The airtight sheet 21 is laid out so as to communicate with the head of the drain 7, the vertical drain 7, the horizontal drain material 27, the perforated drainage pipe 26, etc., and the embankment 8 is loaded on the end 21 a thereof. Airtightly covers the ground to be improved.

【0028】以上のように気密シート21の敷設が終了
したら、有孔排水管26に排水管41を接続し、この排
水管41を真空ポンプ40に接続し、計測器(図示せ
ず)を設置して調整運転を行った後に、本運転を開始す
る。ここで、真空ポンプ40は各レーンごと(各桟橋
4,4間の改良対象地盤2ごと)に設置するか、複数の
レーンまとめて設置しても良いが、1レーンのみで真空
運転を行なう場合には、所定の位置で鉛直ドレーン7の
打設を終了し、気密シート端部21aの気密処理、真空
ポンプ40の設置などを行なった後に、真空運転を開始
する。真空運転により60kPa〜80kPaの真空圧
が改良対象地盤2に作用し、この真空圧は高さ約4〜5
mの盛土荷重に相当するものである。
When the laying of the airtight sheet 21 is completed as described above, the drain pipe 41 is connected to the perforated drain pipe 26, the drain pipe 41 is connected to the vacuum pump 40, and a measuring instrument (not shown) is installed. After performing the adjustment operation, the main operation is started. Here, the vacuum pump 40 may be installed for each lane (for each ground 2 to be improved between the piers 4 and 4) or may be installed collectively for a plurality of lanes. After the installation of the vertical drain 7 at a predetermined position is completed, the airtight treatment of the airtight sheet end 21a, the installation of the vacuum pump 40, and the like are performed, and then the vacuum operation is started. By the vacuum operation, a vacuum pressure of 60 kPa to 80 kPa acts on the ground 2 to be improved, and the vacuum pressure has a height of about 4 to 5 kPa.
m, which corresponds to an embankment load of m.

【0029】また真空運転により排出される地下水は、
図11に示したように気密シート21上に貯留しても良
く、これにより気密性は高まり、気密シート21内部の
真空圧の上昇に貢献する。これは空気よりも水のほうが
粘性係数が約50倍大きため遮断効果が増加するからで
ある。
The groundwater discharged by the vacuum operation is
As shown in FIG. 11, the airtight sheet 21 may be stored on the airtight sheet 21, thereby increasing the airtightness and contributing to an increase in the vacuum pressure inside the airtight sheet 21. This is because water has a viscosity coefficient about 50 times greater than that of air, and the blocking effect increases.

【0030】なお、各桟橋4の周辺地盤に鉛直ドレーン
7を打設せず、気密シート21の被覆も行なわない場
合、直接的に真空圧が作用しない箇所が存在するが、こ
の場合でも地盤の圧密効果が周辺部にも及ぶため、改良
深さの20〜30%程度の平面範囲では改良域と同等に
地盤強度の増加が期待できる。
When the vertical drain 7 is not cast on the ground around each pier 4 and the airtight sheet 21 is not covered, there are some places where the vacuum pressure does not act directly. Since the consolidation effect extends to the peripheral portion, an increase in ground strength can be expected in a plane range of about 20 to 30% of the improved depth, as in the improved area.

【0031】また真空ポンプの稼働後、2週間程度経過
すれば、気密シート上を人が歩ける状態まで地盤強度は
増加し、この頃から気密シート上への盛土も可能になる
ので、必要に応じて気密シート上に盛土を行い作業用道
路を造成することもできる。さらに、気密シートの上に
は真空ポンプを稼働しながら載荷盛土を行なっても良
く、これにより地盤の改良作用が促進されるので強度増
加の面で有利である。
After about two weeks have passed since the operation of the vacuum pump, the ground strength increased until a person could walk on the airtight sheet. At this time, embankment on the airtight sheet became possible. Embankment can be performed on the airtight sheet to create a work road. Further, the embankment may be loaded on the airtight sheet while operating the vacuum pump, and this improves the ground improvement effect, which is advantageous in terms of increasing the strength.

【0032】[0032]

【発明の効果】本発明では、改良対象域に桟橋をほぼ平
行に構築し、その桟橋間に架台を架け渡し、鉛直ドレー
ン、水平排水材、気密シートなどの敷設を行い、気密シ
ートで被覆した改良対象域に真空圧を作用させることに
より、作業員や施工機械が容易に立ち入ることができな
いような超軟弱地盤であっても、従来のように改良対象
地盤の全域に土木安定シート及びサンドマットなどを設
ける必要が無くなり、鉛直ドレーン打設作業などに先立
つ表層地盤上での処理を桟橋のみに限定できるので、従
来工法と比較すると、サンドマットなどの材料・施工費
用の削減が可能になり、サンドマット用の砂の使用も最
小限にできる。
According to the present invention, a pier is constructed substantially parallel to the area to be improved, a gantry is bridged between the piers, a vertical drain, a horizontal drainage material, an airtight sheet, and the like are laid, and covered with an airtight sheet. By applying vacuum pressure to the area to be improved, even if the ground is extremely soft, where workers and construction machines cannot easily enter, the civil engineering stable sheet and sand mat can be applied to the entire area of the ground to be improved as before. It is no longer necessary to provide such equipment, and processing on the surface ground prior to vertical draining work etc. can be limited to only the pier, so that compared to the conventional method, materials and construction costs such as sand mats can be reduced, The use of sand for sand mats can be minimized.

【0033】また鉛直ドレーンの打設から気密シートの
敷設までシステム的に実施することができるので、工程
管理や地盤改良の質の向上が容易であり、作業員の施工
能力の習熟が図れ、安全上も有利である。さらに、気密
シート上に水を貯留したり、盛土を併用することにより
地盤の改良強度を高めることができる。
Further, since the system can be implemented systematically from the installation of the vertical drain to the installation of the airtight sheet, it is easy to improve the quality of the process control and the ground improvement, and the worker's construction ability can be mastered and the safety can be improved. The above is also advantageous. Further, the improvement strength of the ground can be increased by storing water on the airtight sheet or by using embankment together.

【0034】また本発明では、改良対象域に構築した桟
橋上に走行移動可能な架台を架け渡し、この架台上から
施工を行なうので、例えば、桟橋に替えて作業用道路を
設けてここに架台を架け渡す場合に比べると、特に、下
記の3点で有利である。 気密シートは実質的に未改良部分を残すことなく一工
程で敷設できる。 改良深さが概ね12m以下であれば作業用道路よりも
桟橋の工事費用は安い。 数10cmの水深下にある地盤の改良も容易に行なえ
る。
According to the present invention, a movable platform is mounted on a pier constructed in the area to be improved and construction is performed from this pedestal. For example, a work road is provided in place of the pier, and the pedestal is provided here. It is particularly advantageous in the following three points, as compared with the case of bridging. The hermetic sheet can be laid in one step without leaving substantially unmodified parts. If the improvement depth is about 12 m or less, the construction cost of the pier is lower than that of the work road. Improvement of the ground under several tens of centimeters of water is also easy.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明により地盤改良を実施する対象域の平面
図である。
FIG. 1 is a plan view of a target area in which ground improvement is performed according to the present invention.

【図2】(a)(b)は本発明の工法を示す平面図及び
側面図である。
FIGS. 2A and 2B are a plan view and a side view showing a method of the present invention.

【図3】本発明の工法を示す側面図である。FIG. 3 is a side view showing the method of the present invention.

【図4】本発明の工法に用いる桟橋架設用クレーン等を
示す側面図である。
FIG. 4 is a side view showing a pier construction crane and the like used in the construction method of the present invention.

【図5】本発明の工法に用いる矢板建込みクレーン等を
示す側面図である。
FIG. 5 is a side view showing a sheet pile building crane and the like used in the method of the present invention.

【図6】本発明の工法に用いる施工装置の正面図であ
る。
FIG. 6 is a front view of a construction apparatus used in the method of the present invention.

【図7】本発明の工法に用いる作業架台の正面図であ
る。
FIG. 7 is a front view of a work table used in the method of the present invention.

【図8】(a)は本発明による改良構造の平面図であ
り、(b)は鉛直ドレーン頭部の詳細を示す拡大平面図
である。
8 (a) is a plan view of the improved structure according to the present invention, and FIG. 8 (b) is an enlarged plan view showing details of a vertical drain head.

【図9】(a)〜(e)は気密シート端部の気密構造を
示す断面図である。
FIGS. 9A to 9E are cross-sectional views illustrating an airtight structure at an end of an airtight sheet.

【図10】本発明による改良構造の断面図である。FIG. 10 is a sectional view of an improved structure according to the present invention.

【図11】図10とは異なる改良構造を示す断面図であ
る。
FIG. 11 is a sectional view showing an improved structure different from that of FIG. 10;

【図12】図10及び図11とは異なる改良構造を示す
断面図である。
FIG. 12 is a sectional view showing an improved structure different from FIGS. 10 and 11;

【符号の説明】[Explanation of symbols]

2 改良対象域 4,9 桟橋 7 鉛直ドレーン 11 ドレーン打設機 13 架台 21 気密シート 26 有孔排水管(水平排水材) 27 水平ドレーン材(水平排水材) 40 真空ポンプ 2 Area for improvement 4, 9 Pier 7 Vertical drain 11 Drain driving machine 13 Mount 21 Airtight sheet 26 Perforated drain pipe (horizontal drain) 27 Horizontal drain (horizontal drain) 40 Vacuum pump

───────────────────────────────────────────────────── フロントページの続き (72)発明者 三反畑 勇 東京都港区北青山2丁目5番8号 株式会 社間組内 (72)発明者 隈本 開男 東京都港区北青山2丁目5番8号 青山機 工株式会社内 (72)発明者 轟 和夫 東京都港区北青山2丁目5番8号 青山機 工株式会社内 Fターム(参考) 2D043 CA04 CB08 DA03 DA09 DC00 DD01  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Isamu Mitsubata 2-58 Kitaaoyama, Minato-ku, Tokyo Inside the company group (72) Inventor Kaio Kumamoto 2-5-2 Kitaaoyama, Minato-ku, Tokyo No. Aoyama Kiko Co., Ltd. (72) Inventor Kazuo Todoro 2-5-8 Kita-Aoyama, Minato-ku, Tokyo Aoyama Kiko Co., Ltd. F-term (reference) 2D043 CA04 CB08 DA03 DA09 DC00 DD01

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 軟弱地盤に含まれる水を排出して硬質地
盤へ改良するための地盤改良工法であって、 改良対象域において複数の桟橋を所定間隔でほぼ平行に
設置する工程と、一対の前記桟橋上を走行移動可能な走
行手段で支持された第一の架台を該桟橋間に架け渡し、
該第一の架台上でドレーン打設機を横移動して前記桟橋
間の改良対象地盤中にほぼ鉛直にドレーン材を打設する
工程と、地表面まで延設した複数の鉛直ドレーン頭部に
水平排水材を敷設する工程と、前記水平排水材に連通す
る管体を真空ポンプまで延設する工程と、前記複数の鉛
直ドレーン頭部及び前記水平排水材を気密シートにより
気密に被覆する工程と、前記真空ポンプを稼働して前記
鉛直ドレーンから前記水平排水材を介して地上まで水を
導いて排水する工程とを備えることを特徴とする真空圧
密ドレーン改良工法。
1. A ground improvement method for draining water contained in soft ground to improve it into hard ground, comprising the steps of: installing a plurality of piers at predetermined intervals substantially in parallel in an improvement target area; Bridging the first gantry supported by the traveling means capable of traveling on the pier between the piers,
A step of laterally moving a drain driving machine on the first gantry and driving a drain material substantially vertically in the ground to be improved between the piers, and a plurality of vertical drain heads extending to the ground surface; Laying a horizontal drainage material, extending a pipe communicating with the horizontal drainage material to a vacuum pump, and airtightly covering the plurality of vertical drain heads and the horizontal drainage material with an airtight sheet. Operating the vacuum pump to guide and drain water from the vertical drain to the ground via the horizontal drainage material, and drain the water.
【請求項2】 一対の前記桟橋上を走行移動可能な走行
手段で支持された第二の架台を該桟橋間に架け渡し、該
第二の架台を前記第一の架台の後続工程で走行させて、
該第二の架台上において前記水平排水材の敷設工程、前
記管体の真空ポンプへの延設工程及び気密シートによる
被覆工程を行うことを特徴とする請求項1記載の真空圧
密ドレーン改良工法。
2. A second gantry supported by a traveling means capable of traveling on a pair of the piers is bridged between the piers, and the second gantry is caused to travel in a process subsequent to the first gantry. hand,
The method according to claim 1, wherein a step of laying the horizontal drainage material, a step of extending the pipe to a vacuum pump, and a step of covering with a hermetic sheet are performed on the second gantry.
【請求項3】 軟弱地盤に含まれる水を排出して硬質地
盤へ改良する施工構造であって、 改良対象域において所定間隔でほぼ平行に造成した複数
の桟橋と、一対の前記桟橋上に走行移動可能に架け渡し
た架台と、前記架台上に横移動可能に設けたドレーン打
設機と、該ドレーン打設機により前記桟橋間の改良対象
地盤中にほぼ鉛直に所定間隔で打設された複数の鉛直ド
レーンと、地表面まで延設した複数の鉛直ドレーン頭部
に敷設した水平排水材と、前記複数の鉛直ドレーン頭部
及び前記水平排水材を気密に被覆した気密シートと、前
記水平排水材に連通するように設けられた真空ポンプと
を備えることを特徴とする施工構造。
3. A construction structure for draining water contained in soft ground to improve it into hard ground, comprising: a plurality of piers formed substantially in parallel at predetermined intervals in a region to be improved; A gantry movably bridged, a drain laying machine movably provided on the gantry, and a lay-down machine that is laid substantially vertically at predetermined intervals in the ground to be improved between the piers by the drain laying machine. A plurality of vertical drains, a horizontal drainage material laid on a plurality of vertical drain heads extending to the ground surface, an airtight sheet airtightly covering the plurality of vertical drain heads and the horizontal drainage material, and the horizontal drainage And a vacuum pump provided to communicate with the material.
JP2000349786A 2000-11-16 2000-11-16 Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge Withdrawn JP2002146768A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000349786A JP2002146768A (en) 2000-11-16 2000-11-16 Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000349786A JP2002146768A (en) 2000-11-16 2000-11-16 Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge

Publications (1)

Publication Number Publication Date
JP2002146768A true JP2002146768A (en) 2002-05-22

Family

ID=18823125

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000349786A Withdrawn JP2002146768A (en) 2000-11-16 2000-11-16 Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge

Country Status (1)

Country Link
JP (1) JP2002146768A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004040068A1 (en) * 2002-10-31 2004-05-13 Maruyama Kougyo Kabushikikaisha Method and device for improving poor ground

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004040068A1 (en) * 2002-10-31 2004-05-13 Maruyama Kougyo Kabushikikaisha Method and device for improving poor ground
EP1557496A1 (en) * 2002-10-31 2005-07-27 Maruyama Kougyo Kabushiki Kaisha Method and device for improving poor ground
US7198430B2 (en) 2002-10-31 2007-04-03 Maruyama Kougyo Kabushikikaisha Reformation of soft soil and system therefor
EP1557496A4 (en) * 2002-10-31 2011-03-09 Maruyama Kougyo Kabushikikaisha Method and device for improving poor ground

Similar Documents

Publication Publication Date Title
CN101838968B (en) Double track bridge construction process crossing existing railway operational lines
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN102691300B (en) Construction method of foundation pit earthwork
CN102535474B (en) A kind of construction method of deep-foundation pit excavation
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN109024610A (en) A kind of steel sheet pile purlin support system and the foundation ditch construction method using the support system
CN108301440A (en) With waterproof, the underground pipe gallery construction method of drain function
CN104727324B (en) Irregular basement construction method for supporting
CN109113045A (en) A kind of soft-soil foundation treatment method
CN110004934B (en) Excavation construction method for silt foundation pit
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN111218938A (en) Excavation construction method for foundation pit above existing tunnel
JP2002146768A (en) Vacuum consolidated-drained improvement construction method by utilizing scaffold bridge
KR20100016667A (en) Soil improvement method of soft clay using spread method landfill cover soil on the water surface
JP2002173929A (en) Driving method of vertical drain and execution structure therefor
JPS63167805A (en) Vibro-crawler type compactor
CN116180735B (en) Method for closely knit reinforcement of soil slope by vibrating rod
CN212453828U (en) Double-layer raw material yard structure constructed on deep soft soil foundation
CN204356779U (en) Support the deep foundation ditch vertical cut equipment of support form
CN114875925B (en) Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum
CN110965586B (en) Construction method of multi-layer basement structure of municipal road
JP2002105943A (en) Vacuum consolidation drain improvement construction method and its construction structure
Teparaksa Behavior of deep excavations using sheet pile bracing system in soft Bangkok clay
SU960436A1 (en) Method and apparatus for earth-filling narrow-profile structures
KR100513072B1 (en) form defense-water

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20080205