KR100513072B1 - form defense-water - Google Patents

form defense-water Download PDF

Info

Publication number
KR100513072B1
KR100513072B1 KR10-2002-0053652A KR20020053652A KR100513072B1 KR 100513072 B1 KR100513072 B1 KR 100513072B1 KR 20020053652 A KR20020053652 A KR 20020053652A KR 100513072 B1 KR100513072 B1 KR 100513072B1
Authority
KR
South Korea
Prior art keywords
water
box
construction
euroform
eurofoam
Prior art date
Application number
KR10-2002-0053652A
Other languages
Korean (ko)
Other versions
KR20020077305A (en
Inventor
권형석
Original Assignee
권형석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 권형석 filed Critical 권형석
Priority to KR10-2002-0053652A priority Critical patent/KR100513072B1/en
Publication of KR20020077305A publication Critical patent/KR20020077305A/en
Application granted granted Critical
Publication of KR100513072B1 publication Critical patent/KR100513072B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/04Flat foundations in water or on quicksand
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0001Rubbers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0009PE
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0032Steel; Iron in sheet form, i.e. bent or deformed plate-material

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

현재 건설분야의 토공사 및 기초공사에 관한 공법들은 많다. 흙막이공법 , 물막이 공법, 흙막이+물막이 공법등 다양한 공법이 있으며, 우리는 이러한 공법들을 이용하여 지금까지 많은 공사를 진행해왔다. 이러한 공법을 적용하는 것은 기술자의 몫이며 이에 수반되는 토질의 성분, 지하수 유무, 굴토깊이, 공사장의 규모, 공사비, 공사기간 등 주변여건을 감안하여 결정하되 안전성과 경제성 모두를 만족시키는 공법이 가장 바람직할 것이다.At present, there are many construction methods for earthwork and foundation work in construction field. There are various methods such as earthquake method, water block method, earth block + water block method, and we have been doing a lot of construction so far using these methods. It is up to the engineer to apply such a method, which is determined by considering the environmental conditions such as soil composition, groundwater presence, pit depth, size of construction site, construction cost, and construction period, but it is most desirable to have a method that satisfies both safety and economic efficiency. something to do.

기존의 공법으로는 강널 말뚝 공법, 각종 지하 연속벽 공법, 각종 화학적 공법, 차수공법등 여러가지가 있으며, 대부분은 흙막이와 물막이를 겸용으로 사용하는 방식이며, 물막이라 할지라도 고가이며 대규모이다.Conventional methods include steel sheet pile method, various underground continuous wall method, various chemical methods, and order method. Most of them use soil and water barriers, and even water barriers are expensive and large scale.

이에 본 공법은 기존의 대규모 건물에 쓰이는 여러 가지 공법에 차별을 두고, 소규모 구조물에 물막이 공법을 적용함으로써, 시공성향상과 원가절감, 공기단축, 환경 미파괴 등 건설업이 해결해야될 여러가지의 과제를 조금이나마 해소하고져 한다. 유로폼을 이용한 물막이 공법은 유로폼을 하나의 박스형으로짜서 물속에 담근 후 물을 막는 방법으로, 이 방법을 사용함에 있어서 해결해야할 것은 도2)유로폼과 유로폼사이의 틈으로부터 물이 유입되는 것을 막고, 도3)기존의 유로폼과 철판등을 응용하여 보다 깊은곳까지 물막이를 하는 방법, 도4.5)유로폼으로 만든 박스를 물속에 설치하고, 박스의 인발시 안전하며 파손되지 않게 하는 방법, 도6)바닥에서 올라오는 물을 차단하고 도7)박스속의 물을 제거하였을때 부력으로부터 박스가 떠오르는 것을 막는 것이 문제이다. 이런 문제를 해결하기 위해서 아래 도면2)와 같이 유로폼과 유로폼 사이에 고무 팽창 지수재(1cm*2cm)를 설치하고 유로폼을 조립하여 박스를 물속에 담그면 유로폼이 물속에 있는 동안 고무 팽창 지수재는 물속에서 팽창작용을 하여 유로폼의 조인트에서 물이 침투되는 것을 막아준다.Therefore, this method differentiates from various methods used in existing large-scale buildings, and by applying the water barrier method to small-scale structures, the construction industry needs to solve various problems such as improvement of construction efficiency, cost reduction, reduction of air, and destruction of environment. I should get rid of it. The water blocking method using the Eurofoam is a method of squeezing the Eurofoam into a box shape to immerse it in water and preventing water. The problem to be solved in this method is to prevent water from flowing in the gap between the Eurofoam and the Eurofoam. 3) Applying existing Eurofoam and iron plate, etc. to close the water deeper, Fig. 4.5) Installing a box made of Eurofoam in water and safe and not breaking when pulling out of the box, Fig. 6) From the bottom It is a problem to block the rising water and to prevent the box from rising from buoyancy when the water in the box is removed. To solve this problem, install rubber expansion index material (1cm * 2cm) between euroform and euroform as shown in the figure 2) and assemble the Eurofoam into the box to immerse the box in the water while the rubber foam is in the water. It expands to prevent water from penetrating the joint of the eurofoam.

도면3)과 같이 유로폼 뒷면의 철재에 앵글을 보강하여 박스의 설치/ 인발시 유로폼의 파손을 막아주며, 하부에 철판을 일정한 깊이만큼 보강하여 보다 깊은곳까지(1.5m) 작업을 가능하게 하였으며, 유로폼 내부에 PE필름 및 비닐 천막 등을 설치하여 박스 인발시 박리제의 역할을 하게 한다. 도면4.5)는 앵글과 각목 등으로 보강된 박스를 물속에 안전하게 설치하는 것이다. 도면6)와 같이 바닥에서 올라오는 물의 수압은 펌프카의 호스를 이용하여 버림콘크리트를 타설함으로써 막을 수 있다. 도면7)는 버림콘크리트 타설 후 박스속의 물을 제거함으로써 박스가 부력으로 떠오르는 것을 방지하기 위해 1차 되메우기를 실시하여 부력을 줄인다.As shown in Fig. 3, the angle is reinforced to the steel on the back of the Euroform to prevent the damage of the Euroform during installation / drawing of the box, and the steel plate is reinforced to a certain depth at the bottom to enable the work to a deeper depth (1.5m). PE film and vinyl tents are installed inside the Euroform to act as a release agent during box drawing. Figure 4.5) is to install a box reinforced with angles and squares in water safely. As shown in Fig. 6, the water pressure of the water coming from the bottom can be prevented by casting the discarded concrete using the hose of the pump car. Figure 7 is to reduce the buoyancy by performing a first backfill to prevent the box rises to buoyancy by removing the water in the box after casting concrete.

따라서 본 공법에서 설명하는 주요 의도는 지상에서만 쓰이는 유로폼을 고무팽창 지수재와 결합시켜 물막이 재료로 사용함으로써 소규모 공사나 공장 공사의 기초 및 기계기초공사, 해안 매립지 공사등에 유용하게 이용하고자 한다. 이런한 공법의 출현으로 건물의 규모와 공사비, 공기 등 각각에 맞는 맞춤형 토공사/기초공사공법을 적절하게 사용하여 시공성향상과 공기단축, 원가절감을 이루고자 한다.Therefore, the main intention of this method is to use the Eurofoam, which is used only on the ground, in combination with the rubber expansion index material, and to use it as a water barrier material, which is useful for small-scale construction, factory construction, mechanical foundation work, and coastal landfill construction. With the advent of such construction methods, we will use the customized earthwork / base construction methods appropriate for each building size, construction cost, air, etc. to achieve construction improvement, air reduction, and cost reduction.

Description

유로폼을 이용한 물막이 공법{form defense-water}Form defense-water method using Euroform

본 공법은 간단한 시공방법 및 재료로 물막이를 하는 공법으로, 현재 우리가 사용하는 흙막이 및 물막이 공법은 많다. 하지만 이 공법들은 대부분 고가이면서 많은 공기를 요하며, 대부분 흙막이와 물막이를 겸용하는 공법들이다. 대규모 공사나 공간이 넓은 곳에서는 공기나 금액이 크기 때문에 기존의 공법이 효율적이며, 공기단축/ 원가절감면에서 우수성을 나타낼 수 있다. 하지만 대규모공사가 있으면 소규모 공사도 있는 법이다. 소규모 공사는 대규모 공사보다 활발하게 진행되고 있고 앞으로도 계속 진행될 것이며, 해안 매립지의 공장 건축 등도 많이 이루어지리라 생각된다. 우리가 공사를 하면서 지하수위를 알고 공사하는 경우도 있을 것이고, 영세한 자본으로 사전 검토를 하지 않고 공사를 진행하다가 물을 만나는 경우도 많다.This method is a method of closing the water with a simple construction method and materials, the soil barrier and water barrier method we currently use a lot. However, these methods are mostly expensive and require a lot of air, and most of them are a combination of soil and water barriers. In large-scale construction or a large space, the existing method is efficient because of the large amount of air or money, and can show superiority in terms of air reduction / cost reduction. But if there is a large construction, there is a small construction. Small-scale construction is more active than large-scale construction, and will continue in the future, and the construction of factories in coastal landfills will also take place. Sometimes we know the groundwater level while we are doing the construction, and often meet the water while doing the construction without preliminary examination with small capital.

삭제delete

삭제delete

이때, 지하수위가 깊거나 구조체의 면적이 넓은 곳은 기존의 흙막이 및 물막이 공법을 써야 되지만, 구조체의 하부가 수면에서 1-1.5m되고, 구조체의 면적이 좁은곳(가로*세로가 5m*5m이하)에서 일반적 공법들은 고비용이며 공기단축에 도움이 되지 않는다고 생각된다. 구조체의 규모는 작고 흙막이는 필요없으며, 단순히 물막이만 필요한 조건에서, 불필요한 흙막이 공법을 써가며, 공기/ 비용 등을 소모해야 하는가?At this time, where the groundwater level is deep or the area of the structure is large, the existing soil and water barrier method should be used, but the lower part of the structure is 1-1.5m from the surface of the water, and the area of the structure is narrow (width * length is 5m * 5m). In the following, general methods are considered to be expensive and not conducive to air shortening. Is the structure small in size and does not require a clogging, and is it necessary to use an unnecessary clogging and consume air / cost in a condition where only a clogging is needed?

또,일반적 공법은 중장비 투입, 자재운반 및 적재장소 확보, 적재장소 확보로 인한 타 공정의 작업에 지장을 초래할 수 있고, 인발 후 자재의 신속한 처리 및 인발 장비의 확보 등 실제 물막이 공사 시간보다 부수적인 면에서의 시간 및 작업공간, 비용이 많이 소요된다. 이러한 면을 조금이나마 개선하고 비록 제한된 공간에서 쓰이는 기술이지만 저비용, 공기단축, 작업공간의 확보, 무소음 작업으로 민원이 야기되는 것을 차단하여, 환경 보존, 타 공정에 영향을 미치지 않는다는 것 등이 본 공법의 특징이라 하겠다.In addition, the general construction method may interfere with the operation of other processes due to the input of heavy equipment, material transportation and loading place, and securing the loading place, and it is more incidental than the actual construction time such as rapid processing of material after drawing and securing drawing equipment. In terms of time, work space and cost. Although this technique is slightly improved and used in a limited space, it is possible to prevent environmental complaints and other processes by preventing civil complaints due to low cost, shortening of air space, securing a working space, and noiseless operation. It will be called a feature.

본 공법은 대,소규모에 관계없이 쓰이고 있는 기존의 공법의 불합리적인면을 해소하기 위해 시공성 향상, 공기단축, 원가 절감, 현실성, 환경보호 측면, 품질면등 현재 건설에서 대두되고 있는 가장 현실적인 면을 여러 가지 측면에서 개선하고자 한다. 이제 공법에도 맞춤식 공법이 개발되어 그 규모와 장소에 맞는 공사방법, 비용, 작업공기, 작업의 특성에 맞는 공법 등을 채택하여 건축의 질적 향상과 원가 절감 등을 향상시켜야 한다. 본 공법은 현장내에서 사용하는 자재(유로폼)로써 작업이 가능하며, 철판등을 용접하여 작업할수도 있으며, 유로폼과 철판을 함께 사용하여 작업할 수 있는 응용성을 가진다. 본 공법은 유로폼을 사용하는 것을 기본으로하고, 여기에 철판등을 보강하여 수위의 깊이에따라 응용이 가능하며, 좁은 공간에서 간단하게 형틀(박스)을 만들 수 있고, 만든 박스를 터파기한 곳에 그대로 앉힘으로써 기존의 공법보다 시공성 면에서 간단함을 알 수 있다. 한쪽에서 터파기 하는 동안 옆 공간에서 형틀작업을 하여 터파기 완료 후 박스를 삽입시키는 방법이며 별도의 띠장은 필요 없고, 각목을 이용한 가새, 형틀변형 방지 버팀목 등의 간단한 조치로 작업이 진행되므로 공기 단축 면에서 우수하다. 작업에 있어서 자재는 현장의 유로폼을 사용하며, 형틀 보강에 필요한 앵글, 고무 팽창 지수재, PE필름 또는 비닐 천막, 약간의 모래, 각목, 양수기등 건설 현장에서 일반적으로 쓰이는 자재로 별도로 구입이 필요하지 않으며, 장비는 터파기용 백호, 유로폼의 삽입과 인발에 필요한 카고크레인등이 전부이므로 타 공법과 비교하여 원가 절감면에서 우수하다. 이 방법의 기본원리를 이용하여 해안 매립지의 공장 기계기초 및 공장기초, 소규모 작업현장의 기초공사등에 적용하면 즉시 실행될 수 있는 공법이라 생각된다. 모래의 살포(바닥면)로 박스하부로부터 불순물이 빠져나가 물을 오염시키는 것을 제거하였으며, 특별한 소음이 없으므로 소음공해로 야기되는 민원이 발생하지 않는 장점이 있다. 구조체의 품질면에서도 타 공법과 비교하여 떨어짐이 없다고 생각된다. 특별한 자재가 필요하지 않기 때문에 현장에서 깊이 1-1.5m이하의 물을 만나는 경우가 발생하더라도, 쉽게 해결할 수 있을 것이라 생각된다.This method is designed to solve the unreasonable aspect of the existing method, regardless of the size of small and large, to improve the constructability, reduce the air, reduce the cost, realistic, environmental protection, and quality. There are many ways to improve. Now, the customized method must be developed in the construction method, and the construction quality, cost, working air, and construction method suitable for the characteristics of the work must be adopted to improve the quality of the construction and cost reduction. This method can work with materials (eurofoam) used in the field, it can work by welding steel plate, etc., and it has the applicability to work by using Euroform and iron plate together. This method is based on the use of Euroform, and it is possible to apply it according to the depth of water level by reinforcing steel plates, etc., and to make a simple box (box) in a narrow space, and to keep the box made as it is. By sitting, it can be seen that the construction is simpler than the existing construction method. It is a method of inserting a box after the completion of the excavation by inserting a box after the excavation is done in the space next to the excavation from one side. Excellent in terms of The material used in the work uses the Euroform on site, and it is commonly used in construction sites such as angles, rubber expansion index materials, PE film or vinyl tents, some sand, wood, water pumps, etc. It is excellent in terms of cost reduction compared to other methods because equipment is all about backhoe for dig, cargo crane required for insertion and drawing of Euroform. Using the basic principles of this method, it can be applied immediately to plant machinery foundations and factory foundations of coastal landfills and foundation works of small-scale work sites. The spraying of sand (bottom surface) removes impurities from the bottom of the box to contaminate the water, and there is no special noise, so there are no complaints caused by noise pollution. In terms of the quality of the structure, it is considered that there is no drop compared with other methods. Since no special materials are needed, it is thought that it would be easy to solve the problem of encountering water with a depth of 1-1.5m or less.

본 공법 적용시 유의 사항은 구조물의 너비가 5m*5m이하일 경우만 사용가능하며, 기존의 유로폼으로는 수면에서 1m이하로 구조물이 내려가는 곳에서만 사용 가능하다. 단, 유로폼 뒷면의 철재에 철판을 용접하여 사용하면, 보다 깊은곳까지 작업이 가능하다. 시공불량으로 인한 수질 오염에 대한 대비를 해야되며(모래살포등), 수압 및 부력에 대한 기본적 지식이 요구된다. 터파기 공사로 인한 주변건물의 피해가 예상되는 지역에서는 사용하지 못하며, 소음이 없으므로 이로 인한 민원은 없을 것이라 생각된다.Cautions for the application of this method can be used only when the width of the structure is 5m * 5m or less, and it can be used only where the structure goes down 1m or less from the surface with the existing Euroform. However, if the steel plate is welded to the steel on the back of the Euroform, work can be made deeper. Water pollution due to poor construction should be prepared (such as sand spray), and basic knowledge of water pressure and buoyancy is required. It can not be used in areas where damage to surrounding buildings due to trench construction is expected, and there is no noise because there is no noise.

이하 첨부된 도면에 의해 상세히 설명하면 다음과 같다.Hereinafter, described in detail by the accompanying drawings as follows.

도1.에서와 같이 정확한 측량으로 구조물의 하부라인(line)을 지표면에 표시하고 터파기를 실시한다. 이때 터파기 하부의 폭은 구조물의 크기보다 좌우로1m정도 여유 있게(구조물3m*3m면 하부폭은 5m*5m)작업하고, 구조물1)의 하부깊이가 수면에서 900mm이면 터파기는 수면에서 1100mm-1200mm정도로 작업하며 가능한 물 속은 수평으로 정지작업을 한다. 바닥의 200mm-300mm여유는 모래살포4) 및 버림 콘크리트13) 타설을 위한 여유 깊이다. 모래살포는 바닥의 레벨(level)을 맞추는 역할뿐만 아니라 박스내부의 버림 콘크리트 타설시 오염물이 밖으로 유출되어 수질오염을 방지하는 역할을 한다.As shown in Fig. 1, the bottom line of the structure is displayed on the surface of the structure by an accurate measurement, and the trench is carried out. At this time, the width of the lower part of the trench should be about 1m more than the size of the structure (the width of the lower surface of the structure is 3m * 3m and 5m * 5m) .If the lower depth of the structure 1) is 900mm from the water surface, the trench is 1100mm- Work around 1200mm and stop as horizontally as possible. The 200mm-300mm margin of the floor is the depth for sand spraying4) and cast concrete13). Sand spraying not only serves to match the level of the floor, but also prevents water pollution when contaminants are spilled out when casting concrete inside the box.

터파기와 동시에 옆의 공터에서 유로폼5)을 이용하여 도2.3.4와 같이 물속에 설치하기 위한 박스 작업을 한다.At the same time as the trench, the box work for installation in water as shown in Fig.

도2.와 같이 유로폼과 유로폼 사이에 고무 팽창 지수재6)를 넣어 형틀을 조립하며, 유로폼이 물속에 설치되었을 때 고무 팽창 지수재6)는 물과 접하게 되며 시간이 지남에 따라 그 부피가 팽창하여 유로폼과 유로폼의 조립으로 생긴 틈을 막아준다.Put the rubber expansion index member 6) between the euroform and the euroform as shown in Figure 2. When the foam is installed in water, the rubber expansion index member 6) comes into contact with water and its volume expands over time To prevent gaps caused by the assembly of the Euroform and the Euroform.

도3.은 유로폼 뒷면의 철재에 박스 보강용 앵글7)을 용접하여 박스 설치 및 인발시 박스가 손상되지 않도록 한다. 보다 깊은 곳의 작업을 위해 보강용 철판8)을 용접하여 유로폼이 가지고 있는 깊이의 제한에 대한 단점을 보완하여 깊이의 변화10)에 대한 응용성을 가질 수 있다.(유로폼 사용깊이는900mm-1000이며, 철판 보완시 사용깊이는 1500mm까지 가능.) PE필름또는 비닐천막9)은 박스의 인발시 박리제 역할을 하는 것으로 박스 설치시 작업하거나 도7.에서와 같이 양수 후 설치하여도 무방하다.Figure 3 is to weld the box reinforcement angle (7) to the steel on the back of the euroform so that the box is not damaged when the box is installed and drawn. By welding the reinforcing plate 8) for deeper work, it can be applied to the change of depth 10 by supplementing the disadvantage of the limitation of the depth of the euroform. (Eurofoam use depth is 900mm-1000 It can be up to 1500mm in depth when iron plate is supplemented.) PE film or vinyl curtain 9) acts as a release agent during the drawing of the box.

도4.와 같이 박스의 크기는 구조체보다 좌우로 유로폼을 1장씩(600mm또는 300mm) 더 붙여 시공시 외압이나 충격에 의해 박스가 약간 움직여도 여유폭이 있음으로 시공성을 양호하게 한다. 각각의 모서리에 가새11)와 형틀변형 방지 버팀목12)을 설치하여 박스 삽입시 변형되지 않도록 한다.As shown in Fig. 4, the size of the box is one more (600 mm or 300 mm) of the euro foam to the left and right than the structure, so that there is a margin even if the box is slightly moved due to external pressure or impact during construction, thereby improving the workability. Brace 11) and frame deformation prevention support 12) are installed at each corner to prevent deformation when inserting the box.

앵글7)을 박스주위로 돌려 설치하여 박스를 보강하면서 크레인으로 박스를 삽입하거나 인발할 때 형틀의 파손을 막아준다. 이러한 작업을 통하여 하나의 우물통을 만든다.Rotate the angle 7) around the box to reinforce the box and prevent the mold from being damaged when the box is inserted or removed by the crane. This work creates a well.

도5.와 같이 밖에서 만들어진 박스는 크레인으로 인양하여 물 속으로 들어가게 된다. 이때 4명은 각각의 모서리에 설치된 로프를 잡고 박스가 안전하게 설치될 수 있도록 하며, 1명은 트랜싯이나 지상에 표시된 구조물의 하부선을 보고 정확한 위치에 설치될 수 있도록 지시한다.The box made outside as shown in Fig. 5 is lifted by a crane to enter the water. At this time, four people grasp the rope installed at each corner so that the box can be installed safely. One person is instructed to be installed in the correct position by looking at the bottom line of the structure marked on the transit or ground.

박스가 수평이 되지 않았을 경우 장비를 이용하여 그 부위를 정지 작업한 후 다시 설치한다.If the box is not level, use the equipment to stop the area and reinstall it.

도6.은 설치된 박스내부에 버림 콘크리트13)를 타설하는 것으로 타설전 바닥에 와이어 메쉬를 설치한 후 콘크리트를 타설 하여도 좋은 효과를 볼 수 있을 것이라 생각된다. 콘크리트 강도는 180kg/cm2이상을 사용하며 가급적이면 210-240kg/cm2을 사용하면 보다 안전하게 작업할 수 있다. 슬럼프는 10cm이하로 한다. 타설은 펌프카로 하는 것을 원칙으로 하며, 호스를 물 속에 담그고 타설함과 동시에 줄자나 스타프를 가지고 콘크리트의 두께를 체크하여 한곳에 많은양이 타설되지 않도록 한다. 박스 상부에 설치한 앵글7)을 좀더 보강하여 사람이 걸어 다니면서 깊이를 측정할 수도 있다. 양생은 타설 후 최소 4-5일이 경과되어야 하며, 일주일정도 양생하면 확실한 후속시공이 가능하다. 그렇지 않고 내부의 물을 펌핑하면 수압 및 부력으로 바닥의 콘크리트가 파손되어 물막이가 되지 않는다. 이때는 파손 부위를 찾아 콘크리트를 타설하여 다시 양생 시켜야 하는데 완벽한 물막이는 되지 않는다. 그러므로, 성급한 양수작업은 지양하고, 적당한 콘크리트 두께를 유지하는 것이 중요하다.Fig. 6 is to cast the discarded concrete 13 in the installed box, it is thought that the concrete may be good after placing the wire mesh after installing the wire mesh on the floor before placing. The concrete strength is 180kg / cm 2 or more and preferably 210-240kg / cm 2 for safer working. Slump should be less than 10cm. In principle, pump cars should be used for pumping. Soak hoses in water and place them at the same time. Check the thickness of the concrete with a tape measure or staff to avoid placing a large amount in one place. The angle 7) installed on the upper part of the box can be further reinforced to allow the person to walk and measure the depth. Curing should be at least 4-5 days after pouring, and if it is cured for a week, it can be surely followed. Otherwise, if the water inside is pumped, the concrete at the bottom is damaged by water pressure and buoyancy, and it does not become a water block. At this time, find the damaged part and put concrete to cure again, but it is not a perfect water block. Therefore, it is important to avoid hasty pumping operations and to maintain adequate concrete thickness.

도7.은 박스 내부의 물을 양수기15)로 펌핑하는 단계로 1차로 되메우기16)를 실시한 후 양수기로 물을 제거한다. 되메우기시 돌이 박스에 부딪히거나 충격등으로 인하여 박스와 콘크리트의 접착에 이상이 생기지 않도록 주의하며, 되메우기 높이는 박스의 하부가 200mm-300mm정도 묻히게 한다. 되메우기 작업은 내 외부의 수압을 줄여주고 부력으로부터 박스가 떠오르는 것을 방지하는 역할을 한다. 양수 작업시 양수기는 작은 것을 사용하며, 큰 양수기로 물을 한번에 많이 빼는 것은 수압차로 인하여 콘크리트에 무리를 줄 수 있음으로 피해야한다. 바닥의 이물질 제거17)는 필히 해야하며, 콘크리트 위의 레이탄스17)를 제거할 때 골고루 제거해야한다. 바닥콘크리트 외곽으로 물길을 만들어 한곳에 양수기를 설치하면 미세한 물이 나오더라도 작업에 지장을 받지 않는다.Figure 7 is the step of pumping the water in the box to the pump 15) after the first backfill 16) to remove the water to the pump. When backfilling, care should be taken to prevent abnormality in the adhesion between the box and the concrete due to impacts on the box or impacts. Backfilling reduces water pressure inside and outside and prevents the box from rising from buoyancy. When pumping, use a small water pump, and draining a lot of water with a large water pump at once should be avoided because it can strain the concrete due to the hydraulic pressure difference. Debris removal from the floor17 must be done and evenly removed when removing Leytans17 on concrete. If you build a waterway outside the floor concrete and install a water pump in one place, it will not interfere with the work even if fine water comes out.

도8.과 같이 물막이가 성공적으로 끝나면 기초철근 배근 및 콘크리트타설18)을 한다. 위 도3에서 서술한 바와 같이 PE필름 및 비닐 천막(박리제 역활)을 이때 시공하여도 무방하다. 기초의 구조물이 커져도 상관이 없으면 별도로 기초 형틀을 설치하지 않고 박스를 기초 형틀로 사용할 수 있다. 기초 형틀을 설치하고자 할 때는 박스 자체가 기초보다 좌우로 60cm의 여유 폭을 가지고 있음으로 작업을 하는데는 지장이 없다.As shown in Fig. 8, when the water barrier is successfully completed, the foundation reinforcement and concrete placement 18 are performed. As described in Figure 3 above, PE film and vinyl tent (releasant role) may be constructed at this time. If the structure of the foundation does not matter, it is possible to use the box as the foundation frame without installing the foundation frame separately. When installing the foundation frame, the box itself has a width of 60cm left and right than the foundation, so there is no problem to work.

도9.는 1차옹벽 콘크리트타설20)로 타설 높이는 수면보다 200mm-300mm정도 높게 타설하여 2차되메우기22)후에 지면에서 작업이 가능하게 한다.Fig. 9 is the first retaining wall concrete placing 20) the height of the cast is 200mm-300mm higher than the water surface to enable the work on the ground after the second backfill 22).

도10.은 2차되메우기22)와 박스인발23)작업으로 인발시 박스내부에 PE필름 및 비닐 천막9)등이 있음으로 천천히 1/3정도 인발 후 되메우기를 실시하고 이를 반복 작업하여 인발함으로써 하나의 구조체를 완성한다.Fig. 10 shows the PE film and the plastic tent 9) inside the box when drawing by the second backfill 22) and the box drawing 23). Complete the structure of.

이상에서 상술한 바와 같이 본 공법은 현장에서 빠른 시간내에 수급이 가능한 자재와 장비를 사용함으로써 시간과 비용을 최대한으로 줄이면서 작업의 능률을 극대화하는 방법이며, 품질과 환경면에서도 피해를 주지 않고 작업이 마무리되는 공법이다.As described above, this method is a method of maximizing work efficiency while minimizing time and cost by using materials and equipment that can be supplied quickly and on-site in the field. This is the finishing method.

유로폼을 지상에서만 쓰이는 재료가 아니라 유로폼과 유로폼의 조인트 부위에 고무 팽창 지수재를 설치함으로써 물막이의 재료로도 사용하여 자재의 폭넓은 이용과 이로 인해 시간적, 공간적 절약 및 원가절감에도 많은 도움을 줄 것이다.Eurofoam is not only used on the ground but also rubber expansion index material is installed at the joint part of Eurofoam and Eurofoam, so it can be used as a material of water barrier, which will help a wider use of materials and thereby save time, space and cost. .

의도적으로 이러한 공법을 쓰는 경우도 있겠지만, 공사를 하다가 예상치 못한 물을 만나는 경우에 본 공법은 상당한 효과를 볼 수 있을 것이며, 보다 빠른 대처 능력으로 공기단축과 원가절감, 시공성향상 등의 효과를 볼 수 있다. 특별한 장비나 자재가 없으므로 공간적 여유를 확보할 수 있으며, 이로 인해 주변 부대공사에 지장을 주지 않음으로써, 여러면에서 상당한 이익을 볼 수 있다고 생각된다. "땅속의 물" 이제는 그 깊이와 면적에 맞는 맞춤형 물막이 공법을 적용하여 불필요한 인력, 공기, 비용, 소음 등을 줄임으로써 보다 나은 건설 환경을 만들 수 있다고 생각된다.Although this method may be used intentionally, if the construction meets unexpected water, the method may have a significant effect, and it will be able to reduce the air, reduce costs, and improve construction efficiency with faster response. have. Since there is no special equipment or materials, space can be secured, and it is considered that there is considerable benefit in many ways by not disturbing surrounding subsidiary works. "Water in the ground" It is now thought to be possible to create a better construction environment by reducing the unnecessary manpower, air, cost, and noise by applying a tailored barrier method for its depth and area.

도1)은 터파기시 구조체와 터파기 면적 및 깊이, 수위의 상태를 나타내는 평면 및 단면도1) is a plan view and a cross-sectional view showing the state of the structure, the trench area and depth, and the water level during the trench

도2)는 유로폼 사이에 고무 팽창 지수재를 삽입한 후 고무가 팽창된 것을 나타내는 평면도2) is a plan view showing that the rubber is inflated after inserting the rubber expansion index material between the euro-foam

도3)는 박스를 응용하거나 보강하기 위한 단면도3 is a cross-sectional view for applying or reinforcing a box

도4)는 도2.3을 통하여 만들어진 박스의 평면도Figure 4 is a plan view of the box made through Figure 2.3

도5)는 만들어진 박스를 물 속에 담그는 과정을 도시한 측면도Figure 5 is a side view showing the process of dipping the box made in water

도6)은 펌프카를 이용한 버림 콘크리트 타설 과정을 도시한 측면도Figure 6 is a side view showing the process of casting concrete thrown away using a pump car

도7)은 양생 후 되메우기 및 양수하는 과정을 도시한 측면도Figure 7 is a side view showing the process of backfilling and pumping after curing

도8)은 기초 콘크리트를 타설하는 과정을 도시한 측면도Figure 8 is a side view showing the process of pouring the foundation concrete

도9)는 1차 옹벽 콘크리트를 타설하는 과정을 도시한 측면도Figure 9 is a side view showing the process of pouring the primary retaining wall concrete

도10)은 2차되메우기 및 유로폼(박스)을 인발하는 과정을 도시한 측면도FIG. 10 is a side view illustrating a process of drawing a second backfill and a euroform (box); FIG.

*도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

1.구조체 2.터파기 상부 라인(line) 3.터파기 바닥라인(line) 4.모래살포1. Structure 2. Dig top line 3. Dig bottom line 4. Sand spray

5.유로폼 6.고무 팽창 지수재 6-1.물과 접촉하여 고무가 팽창된 상태5. Euro foam 6. Rubber expansion index 6-1. Rubber in contact with water

7.박스 보강용 앵글 8.유로폼의 깊이변화를 위해 응용한 보강 철판7. Angle of box reinforcement 8. Reinforcement steel plate applied for depth change of euro foam

9.PE필름 또는 비닐천막 10.보강 철판을 이용한 깊이의 변화9.PE film or vinyl curtain 10. Depth change using reinforced steel sheet

11.가새 12.형틀 변형 방지 버팀목 13.버림 콘크리트 타설11.Brace 12.Form deformation prevention crutch 13. Cast concrete pouring

14.양수작업으로 인한 수위변화 15.양수기 16.1차 되메우기14.Water level change due to pumping work 15.16.1 backfilling of water pump

17.바닥 이물질제거(레이탄스 등) 18.기초철근 및 콘크리트 타설17.Removal of foreign substances on the floor (Raytans, etc.) 18.Placement of foundation reinforcement and concrete

19.옹벽철근 20.1차 옹벽 콘크리트 타설 21.박스 인발19.Retaining wall reinforcement 20.1 tea retaining wall concrete pouring 21.Box drawing

22.2차 되메우기(석분 및 혼합석) 23.방수등 기타 작업22.2nd backfill (stone powder and mixed stone) 23.Other operations such as waterproofing

Claims (2)

수면이하의 소규모 구조물에 있어 건축공사에서 유용하게 사용되는 유로폼(5)과 유로폼사이에 고무 수팽창 지수재(6)를 사용하여 지상에서 우물통박스를 제작하여 보강앵글(7)로 박스의 파손을 막는 통상의 제1공정이 포함되는 우물통 시공방법에 있어서,Breakage of the box with a reinforcement angle (7) by making a well box on the ground using a rubber water expansion index material (6) between the Euroform (5) and the Euroform, which is useful in construction work in small-scale structures below the surface of water. In the well construction method including a normal first step of preventing the 상기 1공정후 크레인을 이용하여 유로폼(5)으로 제작된 우물통을 설치하는 제2공정과;A second step of installing a well bucket made of a flow path 5 using the crane after the first step; 우물통내부에 해당 높이의 버림콘크리트(13)를 타설하는 제 3공정과;A third step of pouring the discarded concrete 13 of the corresponding height into the well bucket; 수압과 부력으로 인한 우물통 및 바닥 버림콘크리트(13)의 파손을 막기위한 주변 되메우기(16) 작업을 하는 제 4공정과;A fourth step of performing a peripheral backfill 16 operation to prevent breakage of the well bucket and the bottom cast concrete 13 due to water pressure and buoyancy; 상기 되메우기(16)후 양생기간을 걸쳐 우물통내부의 물을 양수기(15)를 사용하여 제거한후 바닥의 이물질제거(17)와 우물통내부에 필름(9)설치 작업 후 기초 및 옹벽 철근을 배근하여 콘크리트 타설(18)을 차례로 행하는 제 5공정과:After the refilling (16) through the curing period to remove the water in the well container using the water pump (15) and then remove the foreign matter in the bottom (17) and inside the well After the installation of the film (9), the fifth step of performing concrete pouring (18) in sequence by reinforcing the foundation and retaining wall reinforcement: 구조체의 콘크리트 양생후 해당 우물통 박스를 인발(21)하고 2차 되메우기(22)를 실시하는 제 6공정;A sixth step of drawing out the well box 21 after the concrete curing of the structure and performing a second backfill 22; 으로 이루어진 것을 특징으로 하는 유로폼을 이용한 물막이 시공방법.Water barrier construction method using the euro foam, characterized in that consisting of. 1항에 있어서, 유로폼이 가지고있는 깊이에 대한 단점을 보강하여 보다 깊은 곳까지 작업을 할 수 있도록 유로폼의 뒷면 철재에 철판을 설치하는 것이 부가된 것을 특징으로 하는 물막이 시공 방법.The method of claim 1, wherein installing a steel plate on the back side of the euroform so as to work deeper by reinforcing the disadvantage of the depth of the euroform.
KR10-2002-0053652A 2002-09-03 2002-09-03 form defense-water KR100513072B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0053652A KR100513072B1 (en) 2002-09-03 2002-09-03 form defense-water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0053652A KR100513072B1 (en) 2002-09-03 2002-09-03 form defense-water

Publications (2)

Publication Number Publication Date
KR20020077305A KR20020077305A (en) 2002-10-11
KR100513072B1 true KR100513072B1 (en) 2005-09-07

Family

ID=27728175

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0053652A KR100513072B1 (en) 2002-09-03 2002-09-03 form defense-water

Country Status (1)

Country Link
KR (1) KR100513072B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105986570B (en) * 2015-02-03 2018-07-13 五冶集团上海有限公司 The Construction of High Pressure Jet Grouting Pile method of sealing is sealed as ground-connecting-wall interface external reinforcement

Also Published As

Publication number Publication date
KR20020077305A (en) 2002-10-11

Similar Documents

Publication Publication Date Title
JP6010070B2 (en) Temporary closing method for existing underwater structures
CN109630127B (en) Construction method of ultra-deep shield vertical shaft for water-rich weak stratum
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
CN113235601A (en) Deep foundation pit construction risk control structure and method for collapsible loess adjacent building
CN112064751A (en) Deep groove construction method for drainage pipeline
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
JP3423394B2 (en) Underwater frame structure
CN112281888A (en) Excavation supporting method for foundation pit caisson
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN110512649B (en) Underground excavation construction method for additionally arranging basement and communication channel structure under existing building
CN111535298A (en) Seepage-proofing construction method for underground diaphragm wall
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
KR100513072B1 (en) form defense-water
CN215165200U (en) Low pile cap buttress combination formula dock wall structure
KR100257083B1 (en) Dry method or rubber gasket apparatus of a pier of a bridge
CN114837088A (en) Construction method of bearing platform on highway
KR200224758Y1 (en) Structure of caisson soil protection four concret caisson
CN106988337A (en) A kind of reinforcement means for being used to reduce bar shaped shallow foundation house differential settlement
CN111677012A (en) Pipe jacking working well structure for sandy soil layer and construction method thereof
CN111155429A (en) Construction method for bridge sand blowing island building in still water deep water area
CN216689436U (en) Prefabricated wallboard convenient to installation
CN115404888B (en) Deep foundation pit bottom water treatment method for finished main body structure
CN113356221B (en) Polluted foundation pit supporting and rapid excavation construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20100816

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee