JP2002081083A - Construction method for basement - Google Patents
Construction method for basementInfo
- Publication number
- JP2002081083A JP2002081083A JP2000272789A JP2000272789A JP2002081083A JP 2002081083 A JP2002081083 A JP 2002081083A JP 2000272789 A JP2000272789 A JP 2000272789A JP 2000272789 A JP2000272789 A JP 2000272789A JP 2002081083 A JP2002081083 A JP 2002081083A
- Authority
- JP
- Japan
- Prior art keywords
- basement
- ground
- embankment
- excavation
- original ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は地下室の構築方法に
関する。TECHNICAL FIELD The present invention relates to a method for constructing a basement.
【0002】[0002]
【従来の技術】従来、住居や工場等の地下室を構築する
方法として、図3(a)に示すように、原地盤101
に、構築する地下室102の高さと略同等の深さの根切
りをして堀り103を形成し、該堀り103内に図3
(b)に示すように地下室102を構築する方法が一般
的である。2. Description of the Related Art Conventionally, as a method of constructing a basement such as a house or a factory, as shown in FIG.
At the same time, the excavation 103 is formed by making a root cut at a depth substantially equal to the height of the basement 102 to be constructed.
A method of constructing the basement 102 as shown in FIG.
【0003】[0003]
【発明が解決しようとする課題】前記従来のように、地
下室102の高さと略同等の根切りをすると、地盤の堀
削作業、地下室102の配筋やコンクリート打設などの
作業に労費が嵩む問題がある。As described above, if the root is cut at a height substantially equal to the height of the basement 102, labor for excavating the ground, arranging the reinforcement of the basement 102, and placing concrete is increased. There is a bulky problem.
【0004】特に、掘削により出た土104の量が多く
なり、その処理に要する手間や費用が多くなる。また、
その掘削した多量の土を一時的に敷地内に堆積しておく
場合には、敷地内の他の植物を傷めたり、雨水による崩
れを心配しなければならない。[0004] In particular, the amount of soil 104 excavated by excavation increases, and the labor and cost required for the treatment increase. Also,
If a large amount of excavated soil is temporarily deposited on the premises, other vegetation on the premises must be damaged, or the landslides caused by rainwater must be concerned.
【0005】そこで本発明は、前記の問題を解決する地
下室の構築方法を提供することを目的とするものであ
る。Accordingly, an object of the present invention is to provide a method for constructing a basement which solves the above-mentioned problem.
【0006】[0006]
【課題を解決するための手段】前記の課題を解決するた
めに、請求項1記載の第1の発明は、原地盤上に盛土し
て地盤を嵩上げし、該盛土によって地下室の周囲を被覆
することを特徴とする地下室の構築方法である。According to a first aspect of the present invention, in order to solve the above-described problems, the ground is raised by embankment on an original ground, and the basement is covered with the embankment. This is a method for constructing a basement.
【0007】請求項2記載の第2の発明は、原地盤に根
切りにより浅い堀りを形成して該堀り内に地下室を構築
し、原地盤上に突出した地下室の外周に、前記根切りに
より出た掘削土を盛土して地盤を嵩上げし、該盛土によ
って地下室の周囲を被覆することを特徴とする地下室の
構築方法である。In a second aspect of the present invention, a shallow trench is formed in the original ground by root cutting, and a basement is constructed in the dug, and the root is formed on the outer periphery of the basement protruding above the original ground. This is a method for constructing a basement, characterized in that the ground excavated by cutting is embanked to elevate the ground, and the basement is covered with the embankment.
【0008】請求項3記載の第3の発明は、原地盤上に
地下室を構築し、該地下室の外周に盛土して地盤を嵩上
げし、該盛土によって地下室の周囲を被覆することを特
徴とする地下室の構築方法である。A third aspect of the present invention is characterized in that a basement is constructed on the original ground, the ground is raised by embankment on the outer periphery of the basement, and the periphery of the basement is covered with the embankment. How to build a basement.
【0009】[0009]
【発明の実施の形態】図1及び図2に示す実施例に基い
て本発明の実施の形態について説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described based on the embodiment shown in FIGS.
【0010】図1は第1実施例を示す。FIG. 1 shows a first embodiment.
【0011】先ず、図1(a)に示すように、敷地にお
ける地下室構築場所に、根切りにより比較的浅い堀り1
を形成し、その周囲にドライエリア2や汲み上げポンプ
3を設ける。First, as shown in FIG. 1 (a), a relatively shallow dig 1
Is formed, and a dry area 2 and a pump 3 are provided therearound.
【0012】次で、図1(b)に示すように、前記堀り
1部に地下室4を、鉄筋コンクリートなどで構築する。
地下室4を構築すると、前記のように堀り1が比較的浅
いため、その地下室4のほとんどが原地盤5よりも上方
へ露出する。Next, as shown in FIG. 1 (b), a basement 4 is constructed in a part of the excavation with reinforced concrete or the like.
When the basement 4 is constructed, since the dug 1 is relatively shallow as described above, most of the basement 4 is exposed above the original ground 5.
【0013】次で、前記堀り1部の掘削土6を用いて図
1(b)に示すように前記地下室4の周壁の外周に盛土
7をして地盤嵩上げをし、地下室4の周囲を被覆する。
これにより、地下室4は土で埋設される。Next, as shown in FIG. 1 (b), using the excavated soil 6 of the part of the excavation, an embankment 7 is formed on the outer periphery of the peripheral wall of the basement 4 to raise the ground. Cover.
Thereby, the basement 4 is buried with the soil.
【0014】なお、前記根切りにより出た掘削土6の量
のみでは所定の地盤嵩上げができない場合には、他所か
ら土を運んで地盤嵩上げを行う。In the case where a predetermined ground level cannot be raised only by the amount of the excavated soil 6 generated by the root cutting, the ground is raised by carrying soil from another place.
【0015】また、前記の地盤嵩上げを行う場合には敷
地境界付近に図に示すような擁壁8を設けて行うとよ
い。ただし、地盤嵩上げ量が少ない場合には、擁壁8が
不要の場合もある。When raising the ground, the retaining wall 8 as shown in the figure may be provided near the boundary of the site. However, when the amount of raised ground is small, the retaining wall 8 may not be necessary.
【0016】図中、9は排水溝を示す。In the drawing, reference numeral 9 denotes a drain.
【0017】以上のように、構築された地下室4は,原
地盤5からはほぼ全体が上方へ突出しているが、前記の
ように構築された地下室4の周囲を盛土して被覆するこ
とにより、法規上地下室として適合する。As described above, the constructed basement 4 projects almost entirely upward from the original ground 5, but the surroundings of the basement 4 constructed as described above are filled and covered by embankment. Suitable as a legal basement.
【0018】以上の構築方法によれば、根切りによる堀
り1が比較的浅いため、掘削作業が容易で早期に行え
る。更に、地下室4の構築が原地盤5(地上)近くで行
えるので、その構築作業が容易で早期に行える。更に、
掘削土量が少ないので、その掘削土の一時的な保管も楽
で、かつ、敷地内の他の植物を傷めたり、雨水による崩
れの心配が少なくなる。更に、堀り1の深さも浅いた
め、工事中の作業者の転落による危険性も軽減して安全
性を高めることもできる。また、隣地に対する掘削のた
めの工事騒音や振動障害の影響も少なく、隣地境界線の
近くの作業も楽に行える。According to the above construction method, the excavation work can be performed easily and early because the excavation 1 by root cutting is relatively shallow. Further, since the construction of the basement 4 can be performed near the original ground 5 (the ground), the construction work can be performed easily and early. Furthermore,
Since the amount of excavated soil is small, temporary storage of the excavated soil is also easy, and there is less fear of damaging other plants in the site or collapse due to rainwater. Furthermore, since the depth of the digging 1 is also shallow, the danger of the worker falling down during the construction can be reduced and the safety can be improved. In addition, the influence of construction noise and vibration disturbance for excavation on the adjacent land is small, and work near the boundary of the adjacent land can be performed easily.
【0019】図2は第2実施例を示す。FIG. 2 shows a second embodiment.
【0020】本発明は、図2(a)に示すように、原地
盤5を根切りすることなく、先ず図2(b)に示すよう
に、原地盤5上に地下室4を構築する。次で、前記構築
された地下室4の外周に、他所から運んで来た土を盛土
7して地下室4の外周を盛土7でほぼ被覆する。これに
より地下室4は土で埋設される。なお、必要により前記
と同様に擁壁8を構築する。In the present invention, as shown in FIG. 2A, the basement 4 is first constructed on the original ground 5 without cutting off the original ground 5 as shown in FIG. 2B. Next, on the outer periphery of the constructed basement 4, soil 7 brought from another place is embanked 7, and the outer periphery of the basement 4 is almost covered with the embankment 7. Thereby, the basement 4 is buried with the soil. If necessary, the retaining wall 8 is constructed in the same manner as described above.
【0021】本実施例によれば、根切りを必要としない
ため、前記従来工法に比べて、作業の容易化、工期の短
縮化及び堀り内への作業者の転落防止を図ることができ
る。更に、掘削土の一時的な保管の必要もない。また、
隣地近くで建築でき、騒音振動も少ない。According to the present embodiment, since root cutting is not required, the work can be facilitated, the construction period can be shortened, and the worker can be prevented from falling into the dug compared to the conventional method. . Furthermore, there is no need to temporarily store excavated soil. Also,
It can be built near the neighboring land, and there is little noise and vibration.
【0022】[0022]
【発明の効果】本発明によれば、原地盤上に盛土して地
盤を嵩上げし、該盛土によって地下室の周囲を被覆する
ようにしたので、地下室を構築するための根切りを必要
としないか或いは浅い根切りでよい。そのため、前記従
来のような深い根切りを行うものに比べて、工期の短縮
化、作業の容易化、掘削土の処理問題の解決を図り、更
には、深い堀りによる作業の危険性を回避して作業の安
全性を図ることができる。According to the present invention, the ground is raised by embankment on the original ground, and the surroundings of the basement are covered with the embankment. Alternatively, it may be a shallow root cutting. Therefore, compared with the conventional method of deep root cutting, the construction period is shortened, the work is facilitated, the problem of excavated soil treatment is solved, and the danger of work due to deep excavation is avoided. Work safety.
【図1】本発明の構築方法の第1実施例を示す図。FIG. 1 is a diagram showing a first embodiment of a construction method according to the present invention.
【図2】本発明の構築方法の第2実施例を示す図。FIG. 2 is a diagram showing a second embodiment of the construction method of the present invention.
【図3】従来の構築方法を示す図。FIG. 3 is a diagram showing a conventional construction method.
1 堀り 4 地下室 5 原地盤 7 盛土 1 Drilling 4 Basement 5 Original ground 7 Embankment
Claims (3)
盛土によって地下室の周囲を被覆することを特徴とする
地下室の構築方法。1. A method of constructing a basement, comprising embankment on an original ground to raise the ground, and covering the basement with the embankment.
て該堀り内に地下室を構築し、原地盤上に突出した地下
室の外周に、前記根切りにより出た掘削土を盛土して地
盤を嵩上げし、該盛土によって地下室の周囲を被覆する
ことを特徴とする地下室の構築方法。2. A shallow trench is formed by excision in the original ground to construct a basement in the excavation, and the excavated soil generated by the excision is filled on the outer periphery of the basement protruding above the original ground. A method of constructing a basement, characterized by raising the ground and covering the periphery of the basement with the embankment.
外周に盛土して地盤を嵩上げし、該盛土によって地下室
の周囲を被覆することを特徴とする地下室の構築方法。3. A method for constructing a basement, comprising: constructing a basement on the original ground; embedding the periphery of the basement to raise the ground; and covering the basement with the embankment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000272789A JP2002081083A (en) | 2000-09-08 | 2000-09-08 | Construction method for basement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000272789A JP2002081083A (en) | 2000-09-08 | 2000-09-08 | Construction method for basement |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2002081083A true JP2002081083A (en) | 2002-03-22 |
Family
ID=18758845
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000272789A Pending JP2002081083A (en) | 2000-09-08 | 2000-09-08 | Construction method for basement |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2002081083A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0043057A1 (en) * | 1980-06-27 | 1982-01-06 | NOVELERG Société Anonyme dite: | Air conditioned house |
JPH04111812A (en) * | 1990-08-31 | 1992-04-13 | Bunka Denki:Kk | Underground structure utilizing vaporizing heat of water in soil |
JPH04347217A (en) * | 1991-05-23 | 1992-12-02 | San East:Kk | Construction of building with basement |
JP2750386B2 (en) * | 1989-05-31 | 1998-05-13 | 清水建設株式会社 | Residential land development method |
-
2000
- 2000-09-08 JP JP2000272789A patent/JP2002081083A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0043057A1 (en) * | 1980-06-27 | 1982-01-06 | NOVELERG Société Anonyme dite: | Air conditioned house |
JP2750386B2 (en) * | 1989-05-31 | 1998-05-13 | 清水建設株式会社 | Residential land development method |
JPH04111812A (en) * | 1990-08-31 | 1992-04-13 | Bunka Denki:Kk | Underground structure utilizing vaporizing heat of water in soil |
JPH04347217A (en) * | 1991-05-23 | 1992-12-02 | San East:Kk | Construction of building with basement |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2002115260A (en) | Extension method for basement | |
JP2002081083A (en) | Construction method for basement | |
JP3967473B2 (en) | Construction method of underground structure | |
CN109024702A (en) | Construction method and structure is isolated in contaminated soil | |
CN208996097U (en) | Contaminated soil isolation structure | |
JPH03281826A (en) | Excavation method in cohesive soil ground | |
JPH09209371A (en) | Method for constructing foundation | |
JP2879610B2 (en) | Water stoppage method during pit excavation | |
JP2612763B2 (en) | Basic structure of structure | |
JP2003001212A (en) | Method confining contaminated soil into ground | |
JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
JP2874906B2 (en) | Shaft construction method | |
JPS5838040Y2 (en) | Spring water prevention structure for underground structures | |
JPH02300422A (en) | Construction of underground structure | |
JP2846248B2 (en) | Earth retaining wall and construction method | |
JPH03275812A (en) | Foundation construction method for soft sea bottom ground | |
JP3027685B2 (en) | Earth retaining wall and construction method | |
JP2524537B2 (en) | Foundation structure of underground structure | |
JP3548310B2 (en) | Drilling method | |
JPH0274727A (en) | Construction method of underground structure | |
JPH09221744A (en) | Construction method of earth retaining wall using deep soil mixing consolidation pile and earth retaining wall structure | |
JPS6128772B2 (en) | ||
JPS5991228A (en) | Pit excavation work using caisson | |
JP3525247B2 (en) | How to form a housing foundation | |
JP2576706B2 (en) | How to construct the basement for underground structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070524 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20091001 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20091013 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100406 |