JP2002007655A - System and method for supporting project and recording medium - Google Patents

System and method for supporting project and recording medium

Info

Publication number
JP2002007655A
JP2002007655A JP2000182180A JP2000182180A JP2002007655A JP 2002007655 A JP2002007655 A JP 2002007655A JP 2000182180 A JP2000182180 A JP 2000182180A JP 2000182180 A JP2000182180 A JP 2000182180A JP 2002007655 A JP2002007655 A JP 2002007655A
Authority
JP
Japan
Prior art keywords
project
staff
contents
information storage
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2000182180A
Other languages
Japanese (ja)
Inventor
Yukihiro Igawa
幸広 井川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Creek & River Co Ltd
Original Assignee
Creek & River Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Creek & River Co Ltd filed Critical Creek & River Co Ltd
Priority to JP2000182180A priority Critical patent/JP2002007655A/en
Publication of JP2002007655A publication Critical patent/JP2002007655A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Information Retrieval, Db Structures And Fs Structures Therefor (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a support system for smoothly carrying out a project such as creative production. SOLUTION: Contents such as projects in the past, fields, kinds, the staff and evaluations are stored in a project DB 116 and staff information related to the specialties or abilities of the staff is stored in a staff DB 117. When a novel project is proposed, contents thereof are inputted, similar projects are extracted out of projects registered in the project DB 116 and further, only the project of high evaluation is extracted. A staff template is found from the extracted project, and the staff satisfying the staff template is extracted from the contents of the staff DB 117 and displayed as staff candidates of that project.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、プロジェクトを
円滑に遂行することを支援するシステムと方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a system and a method for assisting in smoothly executing a project.

【0002】[0002]

【従来の技術】クリエイティブな制作活動を行うために
は、その制作条件(時間、資金、制作環境、など)に応
じて、効率的かつ効果的な制作活動を行うための制作ス
タッフの配分が必要となる。
[Prior Art] In order to perform creative production activities, it is necessary to allocate production staff for efficient and effective production activities according to the production conditions (time, funding, production environment, etc.) Becomes

【0003】[0003]

【発明が解決しようとする課題】従来、制作スタッフの
配分は、担当者の経験や勘に基づいて行われており、属
人的で、客観性に欠けるという問題を有する。同様に、
担当者の経験や勘によってのみ、プロジェクトが提案さ
れているという問題がある。
Heretofore, production staff has been distributed based on the experience and intuition of the person in charge, and has the problem of being personal and lacking in objectivity. Similarly,
There is a problem that a project is proposed only based on the experience and intuition of the person in charge.

【0004】この発明は、上記実状に鑑みてなされたも
のであり、クリエイティブな制作などのプロジェクトを
行う場合に、プロジェクトを円滑に遂行することを支援
するシステム及び方法を提供することを目的とする。ま
た、この発明は、任意のプロジェクトを成功させるため
のスタッフの配分、スタッフの評価等を客観的に行うこ
とを可能とすることを目的とする。さらに、この発明
は、既存のプロジェクトから新規のプロジェクトを提案
できるシステム及び方法を提供することを目的とする。
[0004] The present invention has been made in view of the above situation, and has as its object to provide a system and a method for supporting smooth execution of a project when performing a project such as creative production. . Further, another object of the present invention is to make it possible to objectively perform staff allocation, staff evaluation, and the like for making any project successful. Further, another object of the present invention is to provide a system and a method capable of proposing a new project from an existing project.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するべ
く、この発明の第1の観点に係るプロジェクト支援シス
テムは、過去のプロジェクトとその内容を記憶するプロ
ジェクト情報記憶手段と、スタッフに関するスタッフ情
報を記憶するスタッフ情報記憶手段と、新規プロジェク
トの内容を入力する入力手段と、前記入力手段により入
力された内容の新規プロジェクトについて、前記プロジ
ェクト情報記憶手段の内容から、該新規プロジェクトを
実行するために必要とされるスタッフの人員構成を判別
する人員構成判別手段と、前記スタッフ情報記憶手段を
検索して、前記人員構成判別手段により判別された人員
構成を充足するスタッフの組み合わせを提示する手段
と、を備える、ことを特徴とする。
In order to achieve the above object, a project support system according to a first aspect of the present invention comprises: a project information storage unit for storing past projects and their contents; Staff information storage means for storing, input means for inputting the contents of the new project, and, for the new project having the contents inputted by the input means, necessary for executing the new project from the contents of the project information storage means And a means for presenting a combination of staff that satisfies the personnel structure determined by the personnel structure determining means, by searching the staff information storage means, and Comprising.

【0006】この構成によれば、新規プロジェクトの条
件に従って、過去のプロジェクトの実績に基づいて、適
切なスタッフの組み合わせを提案する。従って、経験や
勘に頼らず、客観的なスタッフの割り当てが可能とな
る。
According to this configuration, an appropriate combination of staffs is proposed based on the results of past projects in accordance with the conditions of a new project. Therefore, it is possible to assign an objective staff without depending on experience or intuition.

【0007】前記新規プロジェクトとその構成スタッフ
とを前記プロジェクト情報記憶手段に追加記録する手段
と、前記プロジェクトの終了時に、前記プロジェクトの
評価を前記プロジェクト情報記憶手段に追加記録する手
段と、を配置してもよい。この構成により、プロジェク
ト情報記憶手段の記憶内容は、自己増殖的に増加し、シ
ステムの信頼性がプロジェクトの達成と共に高まる。
Means for additionally recording the new project and its constituent staff in the project information storage means, and means for additionally recording the evaluation of the project in the project information storage means at the end of the project are arranged. You may. With this configuration, the storage contents of the project information storage means increase in a self-proliferating manner, and the reliability of the system increases as the project is completed.

【0008】前記プロジェクトの終了時に、その構成ス
タッフの評価を前記スタッフ情報記憶手段に追加登録す
る手段、を備えてもよい。
[0008] At the end of the project, means for additionally registering the evaluation of the constituent staff in the staff information storage means may be provided.

【0009】さらに、この発明の第2の観点に係るプロ
ジェクト支援システムは、プロジェクトの内容と、該プ
ロジェクトを担当したスタッフに関する情報、及び該プ
ロジェクトの評価を記憶するプロジェクト情報記憶手段
と、プロジェクトの内容とそのプロジェクトを担当する
スタッフの情報とを指定する指定手段と、前記指定手段
により指定されたスタッフが指定されたプロジェクトを
担当した場合のプロジェクトの結果を、前記プロジェク
ト情報記憶手段に記憶されたデータを用いてシミュレー
トするシミュレート手段と、を備える、ことを特徴とす
る。
Further, a project support system according to a second aspect of the present invention comprises: a project information storage means for storing the contents of a project, information on staff in charge of the project, and evaluation of the project; And designating means for designating information on the staff in charge of the project, and the result of the project when the staff designated by the designating means is in charge of the designated project. And simulation means for performing simulation using

【0010】この構成によれば、任意のプロジェクトに
あるスタッフが参加した場合の、プロジェクトの成否な
どを客観的に判別できる。さらに、複数のプロジェクト
について同様シミュレーションを実行することにより、
選択したプロジェクト群についての、そのスタッフの評
価を知ることもできる。
According to this configuration, the success or failure of a project can be objectively determined when a staff member in an arbitrary project participates. In addition, by performing a similar simulation for multiple projects,
You can also see the staff's evaluation of the selected projects.

【0011】前記プロジェクト情報記憶手段は、例え
ば、過去のプロジェクトの分野、種類、規模、期間、ス
タッフの技能、経験、デモグラフィに関する情報、及び
クライアント及びスタッフ自身による評価を対応付けて
記憶する。この場合、前記シミュレート手段は、前記指
定手段により指定されたスタッフが指定されたプロジェ
クトを担当した場合のプロジェクトの結果を、前記プロ
ジェクト情報記憶手段に記憶された過去のプロジェクト
の実例とのマッチングを取ることによりシミュレートす
ることができる。
[0011] The project information storage means stores, for example, the fields, types, scales, and periods of past projects, information on staff skills, experiences, demography, and evaluations by clients and staff themselves in association with each other. In this case, the simulating means matches the result of the project when the staff specified by the specifying means is in charge of the specified project with the actual example of the past project stored in the project information storage means. It can be simulated by taking.

【0012】さらに、この発明の第3の観点に係るプロ
ジェクト支援システムは、プロジェクトと、そのプロジ
ェクトを構成する複数の因子とを、対応付けて記憶する
プロジェクト情報記憶手段と、前記プロジェクト情報記
憶手段に記憶された複数のプロジェクトの因子同士を比
較することにより、関連する因子から構成される新たな
プロジェクトを生成して提示するプロジェクト生成手段
と、を備える、ことを特徴とする。
Further, a project support system according to a third aspect of the present invention includes: a project information storage means for storing a project and a plurality of factors constituting the project in association with each other; Project generating means for generating and presenting a new project composed of related factors by comparing factors of a plurality of stored projects.

【0013】この構成によれば、人間の主観に頼らず
に、新規プロジェクトを提案する事が可能になる。
According to this configuration, it is possible to propose a new project without relying on human subjectivity.

【0014】前記プロジェクト生成手段は、例えば、前
記プロジェクト情報記憶手段に記憶された1又は複数の
プロジェクトの因子を、他のプロジェクトの対応する1
又は複数の因子で置換する処理や、1又は複数のプロジ
ェクトの因子に、他のプロジェクトの1又は複数の因子
を連結する処理を行うことにより、新たなプロジェクト
を生成する。
[0014] The project generation means, for example, compares one or a plurality of project factors stored in the project information storage means with a corresponding one of other projects.
Alternatively, a new project is generated by performing a process of replacing with a plurality of factors or a process of connecting one or a plurality of factors of another project to a factor of one or a plurality of projects.

【0015】前記プロジェクト生成手段は、複数の因子
を特定するための情報を入力する手段と、入力された情
報に対する因子又は因子群を有するプロジェクトを前記
プロジェクト情報記憶手段から検索する手段と、を備え
てもよい。
The project generating means includes means for inputting information for specifying a plurality of factors, and means for searching the project information storage means for a project having a factor or a group of factors for the input information. You may.

【0016】さらに、この発明の第4の観点に係るプロ
ジェクト支援方法は、過去に実施されたプロジェクトと
その内容と担当スタッフに関する情報と該プロジェクト
の評価とを予め対応付けて記憶させておき、新規プロジ
ェクトの内容が提示された場合に、該新規プロジェクト
の内容と記憶されている過去のプロジェクトとを比較
し、成功した過去のプロジェクトの内容から、該新規プ
ロジェクトを実行するために必要とされるスタッフの人
員構成の要件を判別し、予め登録されているスタッフ情
報に基づいて、判別された人員構成要件を充足するスタ
ッフの組み合わせを求めて、提示する、ことを特徴とす
る。
Further, in a project support method according to a fourth aspect of the present invention, a project implemented in the past, its contents, information on staff in charge, and evaluation of the project are stored in association with each other in advance, and a new project is stored. When the contents of the project are presented, the contents of the new project are compared with the stored past projects, and based on the contents of the successful past project, the staff required to execute the new project Is determined, and based on staff information registered in advance, a combination of staff members satisfying the determined staff configuration requirement is obtained and presented.

【0017】さらに、この発明の第5の観点に係るプロ
ジェクト支援方法は、過去のプロジェクトの内容と、該
プロジェクトを担当したスタッフに関する情報、及び該
プロジェクトの評価を予め登録しておき、プロジェクト
の内容とそのプロジェクトを担当するスタッフとが指定
された場合に、指定されたプロジェクトの内容とそのス
タッフとの組み合わせと、登録されている過去のプロジ
ェクトの内容及びスタッフの組み合わせとを比較し、合
致又は類似するプロジェクトに対する評価を判別するこ
とにより、指定されたスタッフが指定されたプロジェク
トを担当した場合のプロジェクトの結果をシミュレート
する、ことを特徴とする。
Further, in the project support method according to the fifth aspect of the present invention, the contents of the past project, information on the staff in charge of the project, and the evaluation of the project are registered in advance, and the contents of the project are registered. When the staff in charge of the project is designated, the combination of the designated project contents and the staff is compared with the registered past project contents and the staff combination, and they are matched or similar. Determining the evaluation of the project to be performed, thereby simulating the result of the project when the designated staff takes charge of the designated project.

【0018】さらに、この発明の第6の観点に係るプロ
ジェクト支援方法は、プロジェクトとそのプロジェクト
を構成する複数の因子とを対応付けて登録し、因子を特
定する因子指定情報を入力して、この因子指定情報に対
応する因子を有するプロジェクトを抽出し、抽出された
1又は複数のプロジェクトの因子を、他のプロジェクト
の因子と比較することにより、関連する因子から構成さ
れる新たなプロジェクトを生成する、ことを特徴とす
る。
Further, in a project support method according to a sixth aspect of the present invention, a project and a plurality of factors constituting the project are registered in association with each other, and factor designating information for specifying the factor is inputted, and A project having a factor corresponding to the factor designation information is extracted, and a factor of one or more extracted projects is compared with a factor of another project to generate a new project including related factors. , Characterized in that.

【0019】上記プロジェクト支援システムは、専用の
装置によらず、通常のコンピュータを利用して実現可能
である。すなわち、コンピュータに上述の各処理を実行
させるためのプログラムを、記録媒体(CD−ROM、
フロッピー(登録商標)ディスク、MO、ROM等)に
記録して配布し、これをコンピュータにインストールし
てOS(オペレーティングシステム)上で動作させるこ
とにより、コンピュータを上記処理システムとして機能
させることができる。
The above-mentioned project support system can be realized by using a normal computer without using a dedicated device. That is, a program for causing a computer to execute each of the above-described processes is stored in a recording medium (CD-ROM,
By recording and distributing it on a floppy (registered trademark) disk, MO, ROM, or the like), installing it on a computer, and operating it on an OS (operating system), the computer can function as the above processing system.

【0020】[0020]

【発明の実施の形態】以下に、図面を参照して、この発
明の実施の形態に係るプロジェクト支援システムについ
て詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a project support system according to an embodiment of the present invention will be described in detail with reference to the drawings.

【0021】(第1の実施の形態)このプロジェクト支
援システムは、外部企業からの委託を受けて、映像、広
告、マルチメディア、ゲームなどの作成を行う、即ち、
クリエイティブな制作活動を行う企業に設置され、任意
のプロジェクトの内容が入力された時に、そのプロジェ
クトを成功させるために適切な人材を抽出して提案する
システムである。このプロジェクト支援システム11
は、図1に示すように、通信制御部111と、処理制御
部112と、記憶部113と、入力処理部114と、表
示処理部115と、プロジェクトDB(データベース)
116と、スタッフDB117と、クライアントDB1
18とを備えている。
(First Embodiment) This project support system creates a video, an advertisement, a multimedia, a game, and the like under a commission from an external company.
This system is installed in a company that performs creative production activities and, when the contents of an arbitrary project are input, extracts and proposes appropriate human resources to make the project successful. This project support system 11
As shown in FIG. 1, a communication control unit 111, a processing control unit 112, a storage unit 113, an input processing unit 114, a display processing unit 115, a project DB (database)
116, staff DB 117, and client DB 1
18 is provided.

【0022】通信制御部111は、処理制御部112の
制御下に、外部装置との間で通信を行う。
The communication control unit 111 communicates with an external device under the control of the processing control unit 112.

【0023】処理制御部112は、入力処理部114か
ら入力されたプロジェクト情報、スタッフ情報、クライ
アント情報をプロジェクトDB116とスタッフDB1
17とにそれぞれ格納する。また、処理制御部112
は、新規プロジェクトが入力された場合に、そのプロジ
ェクトに対応する過去のプロジェクトをプロジェクトD
B116から抽出し、抽出したプロジェクトの人員構成
を判別して、その人員構成に該当するスタッフをスタッ
フDB117から抽出し、得られたスタッフの組み合わ
せを表示処理部115上に提案する。
The processing control section 112 stores the project information, staff information, and client information input from the input processing section 114 into the project DB 116 and the staff DB 1.
17 respectively. The processing control unit 112
When a new project is input, the past project corresponding to the new project is
B116, the staff composition of the extracted project is determined, the staff corresponding to the staff composition is extracted from the staff DB 117, and the obtained combination of staff is proposed on the display processing unit 115.

【0024】記憶部113は、半導体メモリ、磁気ディ
スク記録装置等から構成され、各種の情報やプログラ
ム、例えば、新規プロジェクトに類似する過去のプロジ
ェクトを抽出する処理と、抽出したプロジェクトのスタ
ッフテンプレートに合致するスタッフを抽出する処理と
を実行するためのプログラムを記憶する。
The storage unit 113 is composed of a semiconductor memory, a magnetic disk recording device, and the like, and performs processing for extracting various information and programs, for example, a past project similar to a new project, and matching with a staff template of the extracted project. And a program for executing a process of extracting staff to be executed.

【0025】入力処理部114は、キーボード、ポイン
ティングデバイス、等から構成され、指示やデータを入
力する。
The input processing unit 114 includes a keyboard, a pointing device, and the like, and inputs instructions and data.

【0026】表示処理部115は、ディスプレイ装置、
ビデオメモリ等から構成され、処理制御部112から供
給された画像情報に従った画像を表示して、情報等を提
示(出力)する。
The display processing unit 115 includes a display device,
It is composed of a video memory and the like, displays an image according to the image information supplied from the processing control unit 112, and presents (outputs) information and the like.

【0027】プロジェクトDB116は、過去に実施さ
れた各プロジェクトについて、図2に示すように、
(1)プロジェクトの分野(映画、WEB作成、ゲーム
など)、(2)プロジェクトの種類(企画、編集、撮影
など各分野で請け負った仕事の種類)、(3)プロジェ
クトの請負金額、(4)プロジェクトの期間、(5)ク
ライアント名、(6)クライアントの業種(製造業、食
品業、コンピュータ関係など)、(7)制作物のクオリ
ティ(高い、普通、低い)、(8)その他のプロジェク
トに関する評価項目、(9)参加したスタッフの構成と
その能力(役職、専門、経験、デモフラフィ、資格、な
ど)、(10)スタッフの満足度、(11)クライアン
トの評価などの情報を格納する。
The project DB 116 stores, for each project executed in the past, as shown in FIG.
(1) the field of the project (movie, WEB creation, game, etc.), (2) the type of project (type of work undertaken in each field such as planning, editing, shooting, etc.), (3) the contracted amount of the project, (4) Project duration, (5) Client name, (6) Client's industry (manufacturing, food, computer, etc.), (7) Quality of production (high, medium, low), (8) Other projects It stores information such as evaluation items, (9) composition and capabilities of participating staff members (posts, specialties, experiences, demographics, qualifications, etc.), (10) staff satisfaction, (11) client evaluations, and the like.

【0028】スタッフDB117は、事前に登録された
スタッフについて、スタッフ情報(スタッフコード、氏
名、性別、生年月日、年齢)、住所、連絡先(電話番
号、携帯電話番号、ファクシミリ番号、電子メールアド
レス、緊急連絡先)、職種(事業部、分野、職種、専
門、スタッフレベル)、研修・教育実績、仕事状況(待
機中、連絡中、面接中、スタート待ち、稼働中、他社稼
働中)などの情報を格納する。
The staff DB 117 stores staff information (staff code, name, gender, date of birth, age), address, and contact information (telephone number, mobile phone number, facsimile number, e-mail address) of staff registered in advance. , Emergency contact), occupation (business department, field, occupation, specialty, staff level), training / education record, work status (on standby, contacting, interviewing, waiting for start, operating, operating by other companies) Stores information.

【0029】一方、クライアントDB118は、依頼元
のクライアントに関する情報を格納する。
On the other hand, the client DB 118 stores information relating to the requesting client.

【0030】次に、上記システムの動作について説明す
る。まず、このプロジェクト支援システムによって仕事
の紹介を受けようとする者は、図3に例示するような登
録フォームに必要事項を記入し、このシステムの運用主
体に予め登録する。
Next, the operation of the above system will be described. First, a person who intends to receive an introduction of a job by this project support system fills in a registration form as illustrated in FIG. 3 and registers it in advance with an operating entity of this system.

【0031】運用担当者は、このフォームに登録されて
いる事項を入力処理部114から入力する。処理制御部
112は、入力されたスタッフ情報をスタッフDB11
7に登録する。これらの登録情報は、各登録者の、経験
や技能、デモグラフィを識別するための情報となる。
The operator inputs items registered in this form from the input processing unit 114. The processing control unit 112 stores the input staff information in the staff DB 11
Register to 7. These pieces of registration information serve as information for identifying the experience, skill, and demography of each registrant.

【0032】各登録者は、適宜、自己の仕事の状況をセ
ンタに通知する。例えば、自己の仕事に関する状況(待
機中、連絡中、面接中、スタート待ち、稼働中、他社稼
働中、などの状況)に変化が生じた場合には、その状況
と担当者、期間などを運用主体に通知する。運用担当者
は、これをスタッフDB117に登録する。
Each registrant appropriately notifies the center of the status of his / her work. For example, if there is a change in the status of your job (waiting, contacting, interviewing, waiting for a start, running, running at another company, etc.), manage the status, the person in charge, and the period. Notify the subject. The operation staff registers this in the staff DB 117.

【0033】次に、新たなプロジェクトの依頼を受けて
から、スタッフの割り当てまでの処理を図4のフローチ
ャートを参照して説明する。まず、新たなプロジェクト
の依頼を受けると、このシステムの運用担当者は、その
プロジェクトを分析し、(1)そのプロジェクトの分野
(映画、WEB作成、ゲーム作成など)、(2)プロジ
ェクトの種類(企画、編集、撮影など各分野で請け負っ
た仕事の種類)、(3)プロジェクトの請負金額、
(4)プロジェクトの期間、(5)クライアント名、
(6)クライアントの業種(製造業、食品業、コンピュ
ータ関係など)、(7)制作物のクオリティ(高い、普
通、低い)、(8)その他のプロジェクトに関する評価
項目、などの情報を入力処理部114から入力する(ス
テップS11)。
Next, the processing from receiving a request for a new project to assigning staff will be described with reference to the flowchart of FIG. First, when a request for a new project is received, an operator in charge of the system analyzes the project, and (1) the field of the project (movie, WEB creation, game creation, etc.), (2) the type of project ( Types of work undertaken in various fields, such as planning, editing, photography, etc.), (3) project contracted amount,
(4) Project period, (5) Client name,
(6) Client's business type (manufacturing, food industry, computer related, etc.), (7) Product quality (high, normal, low), (8) other project evaluation items, etc. Input is made from step 114 (step S11).

【0034】処理制御部112は、入力されたプロジェ
クトの内容と、プロジェクトDB116に格納されてい
るプロジェクトの内容とを突き合わせ処理し(マッチン
グを取り)、一致度が基準レベル以上のプロジェクトを
抽出する(ステップS12)。
The processing control section 112 performs a matching process (matching) between the contents of the input project and the contents of the project stored in the project DB 116, and extracts a project having a matching degree equal to or higher than the reference level ( Step S12).

【0035】次に、処理制御部112は、抽出したプロ
ジェクトの評価項目、スタッフ満足度、及びクライアン
ト満足度を参照し、評価が基準レベル以上であるものを
抽出する(ステップS13)。
Next, the processing control unit 112 refers to the extracted project evaluation items, staff satisfaction levels, and client satisfaction levels, and extracts those whose evaluation is equal to or higher than the reference level (step S13).

【0036】ステップS12及びS13の抽出処理によ
り、新規に依頼されたプロジェクトとの一致度が高く、
かつ、成功したプロジェクトがプロジェクトDB116
から抽出される。なお、条件に合致するプロジェクトが
複数存在する場合には、一致度と成功度との総合評価が
最も高いプロジェクトを1つ選択する。
By the extraction processing in steps S12 and S13, the degree of coincidence with the newly requested project is high,
And the successful project is the project DB 116
Extracted from If there are a plurality of projects that match the conditions, one project with the highest overall evaluation of the degree of coincidence and the degree of success is selected.

【0037】次に、処理制御部112は、抽出したプロ
ジェクトの参加者(プロジェクト構成者)の人員構成を
分析し、「スタッフの組み合わせのテンプレート」を抽
出する(ステップS14)。「スタッフの組み合わせの
テンプレート」とは機能や経験、デモグラフィ、他のス
タッフとの相性などでスタッフを一定の枠組みに分類し
たメタ情報である。
Next, the processing control unit 112 analyzes the personnel composition of the extracted project participants (project constituents) and extracts a "template of a combination of staff" (step S14). “Staff combination template” is meta information that classifies staff into a certain framework based on functions, experience, demography, compatibility with other staff, and the like.

【0038】具体的には、このテンプレートは、例え
ば、プロジェクトが、単純に、チーフ(C)1人、サブ
チーフ(SC)2人、スタッフ6人によって遂行された
というような内容だけではなく、チーフがクリエータと
して最高ランクのレベルを有し、かつ、サブチーフとし
ての経験を有し、サブチーフがクリエータとして最高ラ
ンクのレベルを有し、スタッフがそれぞれクリエータと
して平均以上のレベルを有し、さらに、スタッフ内に管
理担当者が一人含まれている、というような情報であ
る。
Specifically, this template is not limited to contents such as, for example, that the project was simply executed by one chief (C), two sub-chiefs (SC), and six staff members. Has the highest rank as a creator and has experience as a sub-chief, the sub-chief has the highest rank as a creator, each staff has a level above average as a creator, and This information indicates that one person in charge of management is included.

【0039】処理制御部112は、抽出したテンプレー
トをもとに、そのテンプレートに合致するような人材の
組み合わせをスタッフDB117から抽出する(ステッ
プS15)。
Based on the extracted template, the processing control unit 112 extracts a combination of human resources that matches the template from the staff DB 117 (step S15).

【0040】例えば、処理制御部112は、テンプレー
トに従って、クリエータとして最高ランクのレベルを有
し、かつ、サブチーフとしての経験を有する人物を抽出
する。そして、仕事状況を確認し、プロジェクトの遂行
期間中に、他の業務の予定が入っていないことを確認し
た上で、チーフ候補として設定する。同様に、クリエー
タとして最高ランクのレベルを備えている人物で、プロ
ジェクトの遂行期間中に、他の業務の予定が入っていな
い人物を、サブチーフ候補として設定する。さらに、ク
リエータとして平均以上のレベルを有し、少なくとも当
初の一定期間プロジェクトを担当できる5人を抽出し
て、スタッフ候補とする。さらに、制作と管理業務との
両方の能力を有する者を、スタッフ候補とする。
For example, the processing control unit 112 extracts a person having the highest rank as a creator and having experience as a sub-chief according to the template. Then, after confirming the work status and confirming that no other work is scheduled during the project execution period, the candidate is set as a chief candidate. Similarly, a person who has the highest rank as a creator and has no other work scheduled during the execution of the project is set as a sub-chief candidate. Furthermore, five staff members who have a level higher than the average as a creator and can be in charge of the project for at least the initial fixed period are extracted as staff candidates. In addition, those who have both production and management capabilities are considered staff candidates.

【0041】処理制御部112は、このようにして抽出
した8人を、スタッフDB117に登録されている情報
と共に表示処理部115に表示する(ステップS1
6)。
The processing control unit 112 displays the eight persons thus extracted together with the information registered in the staff DB 117 on the display processing unit 115 (step S1).
6).

【0042】運用担当者は、表示内容を確認し、抽出さ
れたスタッフ8人が、このプロジェクトの遂行に適切か
否かをさらに、検討し、必要があれば、スタッフを編集
する。
The operator checks the displayed contents, further examines whether the eight extracted staff members are appropriate for the execution of this project, and edits the staff members if necessary.

【0043】運用担当者は、スタッフ候補を確定する
と、各人に連絡を取り、契約手続きなどの処理に移る。
When the staff in charge determines the staff candidates, it contacts each person and proceeds to the processing such as the contract procedure.

【0044】このようにして決定したスタッフでプロジ
ェクトを開始すると、様々な手法でプロジェクトを管理
しながら、プロジェクトを進める。
When the project is started by the staff determined in this way, the project is advanced while managing the project by various methods.

【0045】プロジェクトが終了すると、プロジェクト
の評価を行う。まず、プロジェクトの請負時に、プロジ
ェクトDB116に登録した内容中の、「参加したスタ
ッフ」、「スタッフの満足度」、「クライアントの評
価」などの項目を登録する。これらの情報は、次回のプ
ロジェクト請負時に、スタッフを選択するために参照さ
れる。
When the project is completed, the project is evaluated. First, at the time of contracting a project, items such as “participating staff”, “staff satisfaction”, and “client evaluation” in the contents registered in the project DB 116 are registered. This information will be used to select staff during the next project contract.

【0046】プロジェクトが終了すると、プロジェクト
の評価を行う。まず、運用担当者は、プロジェクトの請
負時に、プロジェクトDB116に登録した内容中の、
「参加したスタッフ」、「スタッフの満足度」、「クラ
イアントの評価」などの項目を登録する。これらの情報
は、次回のプロジェクト請負時に、スタッフを抽出する
ために参照される。
When the project is completed, the project is evaluated. First, the operator in charge of the project, at the time of contracting the project,
Register items such as "participating staff", "staff satisfaction", and "client evaluation". This information will be referred to in the next project contract to extract staff.

【0047】また、運用担当者は、スタッフDB117
の、そのプロジェクトの参加者の欄に、そのプロジェク
トへの参加経験及びその役割を登録する。また、同一プ
ロジェクトの他の参加者との人的関係などについても、
情報が存在する場合には登録する。これらの情報は、次
回、スタッフを抽出する際に参照される。
The operation person in charge is the staff DB 117
In the "Participant of the project" column, register the experience of participating in the project and its role. In addition, regarding personal relationships with other participants in the same project,
If the information exists, register it. These information will be referred to next time when extracting staff.

【0048】以上説明したように、この実施の形態のシ
ステムは、過去のプロジェクトと各スタッフの能力に基
づいて、新たなプロジェクトを実行するために最適なス
タッフの組み合わせを提案する。従って、経験や勘に頼
ったスタッフ配置を行う必要が無く、短時間で適切なス
タッフの割り当てが可能になる。
As described above, the system according to the present embodiment proposes an optimal combination of staff members for executing a new project based on past projects and the capabilities of each staff member. Therefore, there is no need to perform staffing based on experience or intuition, and appropriate staffing can be performed in a short time.

【0049】上記実施の形態においては、新規プロジェ
クトに内容が一致する既存のプロジェクトを抽出した
が、ぴったりマッチングするプロジェクトを検出できな
い場合がある。このような場合には、たとえば、以下の
手法により、比較的一致するプロジェクトを選択し、そ
のプロジェクトからの推測でスタッフ数を決定してもよ
い。
In the above embodiment, an existing project whose contents match the new project is extracted, but a project that exactly matches may not be detected. In such a case, for example, a relatively matching project may be selected by the following method, and the number of staff members may be determined by estimation from the project.

【0050】まず、プロジェクトの分野と種類とに基づ
いて、プロジェクトDB116からプロジェクトを抽出
する。抽出されたプロジェクトの内から、プロジェクト
の金額、期間、制作物のクオリティなどに基づいて、新
規プロジェクトに比較的近接するもの、或いは、相似系
のものを抽出する。新規プロジェクトと抽出したプロジ
ェクトのサイズ及び期間の比較から、総スタッフ数を求
める。プロジェクトのサイズ及び期間により、予め定め
られた基準に従って、チーフ数と、サブチーフ数を決定
し、残りを一般のスタッフとする。
First, a project is extracted from the project DB 116 based on the field and type of the project. From the extracted projects, ones that are relatively close to the new project or similar ones are extracted based on the amount of the project, the period, the quality of the product, and the like. From the comparison of the size and period of the new project and the extracted project, the total number of staff is calculated. The number of chiefs and the number of sub-chiefs are determined according to a predetermined standard according to the size and duration of the project, and the rest will be general staff.

【0051】例えば、請負金額が5千万円未満のプロジ
ェクトについては、チーフ1人、サブチーフ1人とし
て、他を通常のスタッフとし、請負金額が5千万円以上
のプロジェクトについては、チーフ1人、サブチーフ2
人として、他を通常のスタッフとするように設定するこ
とができる。
For example, for a project with a contract amount of less than 50 million yen, one chief and one sub-chief are used, and the others are used as ordinary staff. For a project with a contract amount of 50 million yen or more, one chief person , Sub Chief 2
As a person, you can set others to be regular staff.

【0052】上記システムは、プロジェクトの途中で、
スタッフに欠員が生じた場合に、そのスタッフとほぼ同
様の能力と経験を有するスタッフを、スタッフDB11
7から抽出し、その欠員を埋めるような場合も適用可能
である。
The above system is used during the project
When a staff member is vacant, a staff member having almost the same ability and experience as the staff member is assigned to the staff DB 11.
7, it is also applicable to a case where the vacancy is filled.

【0053】(第2の実施の形態)上記第1の実施の形
態においては、新規プロジェクトに適した人材を抽出・
提案する実施例について説明した。この発明は、この実
施の形態に限定されず、例えば、あるスタッフが、任意
のプロジェクトに適しているか否かを判別するためにも
利用できる。
(Second Embodiment) In the first embodiment, human resources suitable for a new project are extracted and
The proposed embodiment has been described. The present invention is not limited to this embodiment, and may be used, for example, by a certain staff to determine whether or not the staff is suitable for an arbitrary project.

【0054】この場合のシステムの動作を図5を参照し
て説明する。まず、検証対象のスタッフを抽出する(ス
テップS21)。次に、プロジェクトDB116に登録
されている任意のプロジェクトを選択する(ステップS
22)。
The operation of the system in this case will be described with reference to FIG. First, a staff to be verified is extracted (step S21). Next, an arbitrary project registered in the project DB 116 is selected (step S
22).

【0055】次に、そのプロジェクトのスタッフテンプ
レートに、そのスタッフを割り当て、他のスタッフとし
ては、標準的なスタッフ構成(或いは、既に割り当てが
予定されているスタッフ)を割り当てる(ステップS2
3)。
Next, the staff is assigned to the staff template of the project, and a standard staff configuration (or a staff that has already been assigned) is assigned as the other staff (step S2).
3).

【0056】次に、同様のスタッフ構成で、かつ、同様
の内容を有するプロジェクトをプロジェクトDB116
から抽出し、そのプロジェクトが成功したか否か、さら
に、そのコストなどを求める(ステップS24)。他の
プロジェクトのスタッフテンプレートにおいても、同様
の処理を実行する。このような処理を実行することによ
り、選択したプロジェクト群に対するそのスタッフの適
合性を見ることができる。複数のスタッフについて、同
様のシミュレーションを実行することにより、選択した
プロジェクト群に対する各スタッフの格付けを行うこと
ができる。
Next, a project having the same staff composition and the same contents is stored in the project DB 116.
, And whether the project was successful, and its cost, etc. are determined (step S24). The same processing is performed for staff templates of other projects. By executing such a process, the suitability of the staff for the selected project group can be checked. By performing the same simulation for a plurality of staff, each staff can be rated for the selected project group.

【0057】また、あるプロジェクトのスタッフに生じ
た欠員を穴埋めする場合に、第1の実施の形態のシステ
ムで抽出されたスタッフが、そのプロジェクトに本当に
適しているか否かを判別するために使用することも可能
である。
When filling in the vacancies generated in the staff of a certain project, the staff extracted by the system of the first embodiment is used to determine whether or not the staff is really suitable for the project. It is also possible.

【0058】(第3の実施の形態)第1及び第2の実施
の形態においては、プロジェクトとスタッフとの関係に
主眼をおいてこの発明を説明したが、この発明は、上記
実施の形態に限定されない。例えば、プロジェクトDB
116に格納された複数のプロジェクトから新たなプロ
ジェクトを創出するような場合にもこの発明は適用可能
である。以下、複数のプロジェクトに基づいて新たなプ
ロジェクトを創出するシステムに関する第3の実施の形
態について説明する。
(Third Embodiment) In the first and second embodiments, the present invention has been described with a focus on the relationship between the project and the staff. However, the present invention is not limited to the above-described embodiment. Not limited. For example, project DB
The present invention is also applicable to a case where a new project is created from a plurality of projects stored in 116. Hereinafter, a third embodiment relating to a system for creating a new project based on a plurality of projects will be described.

【0059】この実施の形態においては、各プロジェク
トは、そのプロジェクトを構成する複数の因子に分解さ
れ、各プロジェクトとその因子とが対応付けられて、プ
ロジェクトDB116に格納されている。
In this embodiment, each project is decomposed into a plurality of factors constituting the project, and each project is associated with the factor and stored in the project DB 116.

【0060】例えば、新製品Aについて、英文のマニュ
アルを作成するというプロジェクトを考える。このプロ
ジェクトは、例えば、技術者との日本語による打ち合わ
せ→邦文原稿の作成→邦文原稿の校正→邦文原稿の英文
への翻訳→英文マニュアルの校正、といった手順で作成
される。従って、このプロジェクトは、(a)日本語に
よる打ち合わせ、(b)邦文原稿の作成、(c)邦文原
稿の校正、(d)邦文原稿の英文への翻訳、(e)英文
マニュアルの校正、といった因子に区分することができ
る。従って、プロジェクトDB116には、因子(a)
〜(e)を識別する記号も登録されている。
For example, consider a project for creating an English manual for a new product A. This project is created, for example, in the following sequence: a meeting with a technician in Japanese → preparation of a Japanese manuscript → proofreading of a Japanese manuscript → translation of a Japanese manuscript into English → proofreading of an English manual. Therefore, this project consists of (a) meetings in Japanese, (b) preparation of Japanese manuscripts, (c) proofreading of Japanese manuscripts, (d) translation of Japanese manuscripts into English, and (e) proofreading of English manuals. It can be divided into factors. Therefore, the project DB 116 contains the factor (a)
Symbols for identifying (e) are also registered.

【0061】一方、プロジェクトDB116に、邦文で
の技術打ち合わせの後、英文の説明書を直接作成するよ
うなプロジェクトが登録されていたとする。この場合、
プロジェクトの因子は、(f)日本語での技術打ち合わ
せと、(g)英文の説明書の作成というような因子が登
録されている。
On the other hand, it is assumed that a project for directly creating an English manual after a technical meeting in Japanese is registered in the project DB 116. in this case,
Factors of the project are registered, such as (f) technical meeting in Japanese and (g) preparation of an English manual.

【0062】この場合、処理制御部112は、入力処理
部114から指示に従って、この2つのプロジェクトの
因子を比較することにより、マニュアルを作成するプロ
ジェクトの、因子(a)、(b)、(c)、(d)を、
(f)と(g)とで置換できることを判別する。
In this case, the processing control unit 112 compares the factors of the two projects in accordance with an instruction from the input processing unit 114, thereby obtaining the factors (a), (b), (c) of the project for which the manual is created. ), (D)
It is determined that (f) and (g) can be replaced.

【0063】処理制御部112は、(f)日本語による
技術打ち合わせ、(g)英文マニュアルの作成、(e)
英文マニュアルの校正、という因子を持つ新しいプロジ
ェクトを提案する。その場合には、因子(f)、(g)
を達成できるスタッフがスタッフDB117に登録され
ているので、システム自体が提案した新たなプロジェク
トを、実現するためのスタッフを提案することも可能で
ある。
The processing control unit 112 performs (f) a technical meeting in Japanese, (g) creation of an English manual, and (e)
We propose a new project with the factor of proofreading English manuals. In that case, factors (f) and (g)
Is registered in the staff DB 117, and it is also possible to propose a staff for realizing a new project proposed by the system itself.

【0064】なお、理解を容易にするために、具体例を
参照して説明したが、プロジェクトを複数の因子に分解
する手法や、あるプロジェクトの因子を他のプロジェク
トの因子で置換する手法などは任意である。
Although a specific example has been described for easy understanding, a method of decomposing a project into a plurality of factors, a method of replacing a factor of a certain project with a factor of another project, and the like are not described. Optional.

【0065】例えば、あるプロジェクトの終点の1又は
複数の因子と、他のプロジェクトの始点の1又は複数の
因子がほぼ同一の場合に、それら2つのプロジェクトを
連結することにより新たなプロジェクトを生成してもよ
い。
For example, when one or more factors at the end point of one project and one or more factors at the start point of another project are substantially the same, a new project is generated by linking the two projects. You may.

【0066】また、図6に模式的に示すように、あるプ
ロジェクトを構成する1又は複数の因子を、他のプロジ
ェクトの1又は複数の因子で置換することにより、新た
なプロジェクトを構成することも可能である。
Also, as schematically shown in FIG. 6, a new project can be constructed by replacing one or more factors constituting one project with one or more factors of another project. It is possible.

【0067】さらに、プロジェクトDB116に登録す
る因子とキーワードなどを関連付けておき、因子を検索
できるようにしてもよい。この場合、入力処理部114
からキーワードなどの情報が入力されると、処理制御部
112は、入力された情報に対応する因子を有するプロ
ジェクトを検出する。
Further, a factor registered in the project DB 116 may be associated with a keyword or the like so that the factor can be searched. In this case, the input processing unit 114
When information such as a keyword is input from, the processing control unit 112 detects a project having a factor corresponding to the input information.

【0068】次に、処理制御部112は、索出したプロ
ジェクトの因子と、プロジェクトDB116に登録され
ている他のプロジェクトの因子とを比較し、置換又は連
結できるものがあるか否かを判別し、存在する場合に
は、置換や連結を実行する。このような構成とすれば、
注目している分野に関連するプロジェクトを創出するこ
とが可能となる。
Next, the processing control unit 112 compares the factor of the retrieved project with the factor of another project registered in the project DB 116, and determines whether or not there is any one that can be replaced or linked. , If present, perform substitution or concatenation. With such a configuration,
Projects related to the field of interest can be created.

【0069】この実施の形態のプロジェクト支援システ
ム11は、専用の装置によらず、通常のコンピュータを
利用して実現可能である。すなわち、コンピュータに上
述の各処理を実行させるためのプログラムを、記録媒体
(CD−ROM、フロッピーディスク、MO、ROM
等)に記録して配布し、これをコンピュータにインスト
ールしてOS(オペレーティングシステム)上で動作さ
せることにより、コンピュータをシステムとして機能さ
せることができる。
The project support system 11 of this embodiment can be realized by using a normal computer without using a dedicated device. That is, a program for causing a computer to execute each of the above-described processes is stored in a recording medium (CD-ROM, floppy disk, MO, ROM, or the like).
And the like, and distribute it, install it in a computer, and operate it on an OS (operating system), whereby the computer can function as a system.

【0070】[0070]

【発明の効果】以上の説明のように、この発明によれ
ば、プロジェクトを適切に処理遂行することを支援する
システムと方法を提供することができる。
As described above, according to the present invention, it is possible to provide a system and a method for supporting the proper execution of a project.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の実施の形態に係るプロジェクト支援
システムの構成を示す図である。
FIG. 1 is a diagram showing a configuration of a project support system according to an embodiment of the present invention.

【図2】図1に示すプロジェクトDBのデータ構成を示
す図である。
FIG. 2 is a diagram showing a data structure of a project DB shown in FIG.

【図3】スタッフ登録用の登録フォームの一例を示す図
である。
FIG. 3 is a diagram showing an example of a registration form for staff registration.

【図4】スタッフ提案処理の手順を説明するためのフロ
ーチャートである。
FIG. 4 is a flowchart illustrating a procedure of a staff proposal process.

【図5】プロジェクト遂行のシミュレーション処理を説
明するためのフローチャートである。
FIG. 5 is a flowchart for explaining a simulation process of project execution.

【図6】一のプロジェクトの因子を、他のプロジェクト
の因子で置換する処理を模式的に示す図である。
FIG. 6 is a diagram schematically illustrating a process of replacing a factor of one project with a factor of another project.

【符号の説明】[Explanation of symbols]

11 プロジェクト支援システム 111 通信処理部 112 処理制御部 113 記憶部 114 入力処理部 115 表示処理部 116 プロジェクトDB 117 スタッフDB 118 クライアントDB 11 Project Support System 111 Communication Processing Unit 112 Processing Control Unit 113 Storage Unit 114 Input Processing Unit 115 Display Processing Unit 116 Project DB 117 Staff DB 118 Client DB

Claims (14)

【特許請求の範囲】[Claims] 【請求項1】過去のプロジェクトとその内容を記憶する
プロジェクト情報記憶手段と、 スタッフに関するスタッフ情報を記憶するスタッフ情報
記憶手段と、 新規プロジェクトの内容を入力する入力手段と、 前記入力手段により入力された内容の新規プロジェクト
について、前記プロジェクト情報記憶手段の内容から、
該新規プロジェクトを実行するために必要とされるスタ
ッフの人員構成を判別する人員構成判別手段と、 前記スタッフ情報記憶手段を検索して、前記人員構成判
別手段により判別された人員構成を充足するスタッフの
組み合わせを提示する手段と、 を備える、ことを特徴とするプロジェクト支援システ
ム。
1. A project information storage means for storing past projects and their contents; a staff information storage means for storing staff information on staff; an input means for inputting the contents of a new project; For a new project with the contents described above,
A staff structure determining unit for determining the staff structure of the staff required to execute the new project; and a staff that searches the staff information storage unit and satisfies the staff structure determined by the staff structure determining unit. Means for presenting a combination of: a project support system.
【請求項2】前記新規プロジェクトとその構成スタッフ
とを前記プロジェクト情報記憶手段に追加記録する手段
と、 前記プロジェクトの終了時に、前記プロジェクトの評価
を前記プロジェクト情報記憶手段に追加記録する手段
と、 を備える、ことを特徴とする請求項1に記載のプロジェ
クト支援システム。
2. A means for additionally recording the new project and its constituent staff in the project information storage means, and a means for additionally recording the evaluation of the project in the project information storage means at the end of the project. The project support system according to claim 1, comprising:
【請求項3】前記プロジェクトの終了時に、その構成ス
タッフの評価を前記スタッフ情報記憶手段に追加登録す
る手段、 を備える、ことを特徴とする請求項1又は2に記載のプ
ロジェクト支援システム。
3. The project support system according to claim 1, further comprising means for additionally registering the evaluation of the constituent staff in the staff information storage means at the end of the project.
【請求項4】プロジェクトの内容と、該プロジェクトを
担当したスタッフに関する情報、及び該プロジェクトの
評価を記憶するプロジェクト情報記憶手段と、 プロジェクトの内容とそのプロジェクトを担当するスタ
ッフの情報とを指定する指定手段と、 前記指定手段により指定されたスタッフが指定されたプ
ロジェクトを担当した場合のプロジェクトの結果を、前
記プロジェクト情報記憶手段に記憶されたデータを用い
てシミュレートするシミュレート手段と、 を備える、ことを特徴とするプロジェクト支援システ
ム。
4. A project information storage means for storing contents of a project, information on staff in charge of the project, and evaluation of the project, and designation for designating contents of the project and information of staff in charge of the project. Means, and a simulating means for simulating the result of the project when the staff specified by the specifying means is in charge of the specified project, using data stored in the project information storage means. A project support system characterized by the following.
【請求項5】前記プロジェクト情報記憶手段は、過去の
プロジェクトの分野、種類、規模、期間、スタッフの技
能、経験、デモグラフィーに関する情報、及びクライア
ント及びスタッフ自身による評価を対応付けて記憶して
おり、 前記シミュレート手段は、前記指定手段により指定され
たスタッフが指定されたプロジェクトを担当した場合の
プロジェクトの結果を、前記プロジェクト情報記憶手段
に記憶された過去のプロジェクトの実例とのマッチング
を取ることによりシミュレートする手段を、備える、 ことを特徴とする請求項4に記載のプロジェクト支援シ
ステム。
5. The project information storage means stores information on past project fields, types, scales, periods, staff skills, experiences, demography, and evaluations by clients and staff in association with each other. The simulating means matches the result of the project when the staff designated by the designating means is in charge of the designated project with an actual example of a past project stored in the project information storage means. The project support system according to claim 4, further comprising: means for simulating by:
【請求項6】プロジェクトと、そのプロジェクトを構成
する複数の因子とを、対応付けて記憶するプロジェクト
情報記憶手段と、 前記プロジェクト情報記憶手段に記憶された複数のプロ
ジェクトの因子同士を比較することにより、関連する因
子から構成される新たなプロジェクトを生成して提示す
るプロジェクト生成手段と、 を備える、ことを特徴とするプロジェクト支援システ
ム。
6. A project information storage means for storing a project and a plurality of factors constituting the project in association with each other, and comparing the factors of the plurality of projects stored in the project information storage means with each other. And a project generation means for generating and presenting a new project composed of related factors.
【請求項7】前記プロジェクト生成手段は、前記プロジ
ェクト情報記憶手段に記憶された1又は複数のプロジェ
クトの因子を、他のプロジェクトの対応する1又は複数
の因子で置換する処理、又は、1又は複数のプロジェク
トの因子に、他のプロジェクトの1又は複数の因子を連
結する処理、を行うことにより、新たなプロジェクトを
生成する手段を備える、ことを特徴とする請求項6に記
載のプロジェクト支援システム。
7. A process for replacing one or more factors of one or more projects stored in the project information storage with one or more factors corresponding to another project, or one or more of the following: 7. The project support system according to claim 6, further comprising means for generating a new project by performing a process of linking one or a plurality of factors of another project to a factor of another project.
【請求項8】前記プロジェクト生成手段は、複数の因子
を特定するための情報を入力する手段と、入力された情
報に対する因子又は因子群を有するプロジェクトを前記
プロジェクト情報記憶手段から検索する手段と、を備え
る、 ことを特徴とする請求項6又は7に記載のプロジェクト
支援システム。
8. The project generating means includes means for inputting information for specifying a plurality of factors, means for searching a project having a factor or a group of factors for the input information from the project information storage means, The project support system according to claim 6, further comprising:
【請求項9】過去に実施されたプロジェクトとその内容
と担当スタッフに関する情報と該プロジェクトの評価と
を予め対応付けて記憶させておき、 新規プロジェクトの内容が提示された場合に、該新規プ
ロジェクトの内容と記憶されている過去のプロジェクト
とを比較し、成功した過去のプロジェクトの内容から、
該新規プロジェクトを実行するために必要とされるスタ
ッフの人員構成の要件を判別し、 予め登録されているスタッフ情報に基づいて、判別され
た人員構成要件を充足するスタッフの組み合わせを求め
て、提示する、 ことを特徴とする、プロジェクト支援方法。
9. A project executed in the past, its contents, information on staff in charge, and evaluation of the project are stored in association with each other in advance, and when contents of the new project are presented, the contents of the new project are stored. Compare the contents with the past projects that are memorized, and from the contents of successful past projects,
Determine the staffing requirements of the staff required to execute the new project, and find and present a combination of staff that satisfies the determined staffing requirements based on pre-registered staff information. A project support method characterized by:
【請求項10】過去のプロジェクトの内容と、該プロジ
ェクトを担当したスタッフに関する情報、及び該プロジ
ェクトの評価を予め登録しておき、 プロジェクトの内容とそのプロジェクトを担当するスタ
ッフとが指定された場合に、指定されたプロジェクトの
内容とそのスタッフとの組み合わせと、登録されている
過去のプロジェクトの内容及びスタッフの組み合わせと
を比較し、合致又は類似するプロジェクトに対する評価
を判別することにより、指定されたスタッフが指定され
たプロジェクトを担当した場合のプロジェクトの結果を
シミュレートする、 ことを特徴とするプロジェクト支援方法。
10. The contents of a past project, information on the staff in charge of the project, and the evaluation of the project are registered in advance, and when the contents of the project and the staff in charge of the project are designated, , By comparing the combination of the designated project contents and its staff with the registered past project contents and staff combination, and determining the evaluation of a matching or similar project to determine the designated staff Simulating the result of a project when a person is in charge of a specified project.
【請求項11】プロジェクトとそのプロジェクトを構成
する複数の因子とを対応付けて登録し、 因子を特定する因子指定情報を入力して、 この因子指定情報に対応する因子を有するプロジェクト
を抽出し、 抽出された1又は複数のプロジェクトの因子を、他のプ
ロジェクトの因子と比較することにより、関連する因子
から構成される新たなプロジェクトを生成する、 ことを特徴とするプロジェクト支援方法。
11. A project and a plurality of factors constituting the project are registered in association with each other, factor designation information for specifying the factor is input, and a project having a factor corresponding to the factor designation information is extracted. A project support method, comprising: generating a new project composed of related factors by comparing extracted factors of one or more projects with factors of another project.
【請求項12】コンピュータを、 過去のプロジェクトとその内容を記憶するプロジェクト
情報記憶手段、 スタッフに関するスタッフ情報を記憶するスタッフ情報
記憶手段、 新規プロジェクトの内容を入力する入力手段、 前記入力手段により入力された内容の新規プロジェクト
について、前記プロジェクト情報記憶手段の内容から、
該新規プロジェクトを実行するために必要とされるスタ
ッフの人員構成を判別する人員構成判別手段、 前記スタッフ情報記憶手段を検索して、前記人員構成判
別手段により判別された人員構成を充足するスタッフの
組み合わせを提示する手段、 として機能させるためのプログラムを記録したコンピュ
ータ読み取り可能な記録媒体。
12. A computer, comprising: project information storage means for storing past projects and their contents; staff information storage means for storing staff information on staff; input means for inputting the contents of a new project; For a new project with the contents described above,
A staff composition determining means for determining the staff composition of the staff required to execute the new project; searching the staff information storage means to determine a staff composition that satisfies the staff composition determined by the staff composition discriminating means. Means for presenting the combination, a computer-readable recording medium on which a program for causing the combination to function is recorded.
【請求項13】コンピュータを、 プロジェクトの内容と、該プロジェクトを担当したスタ
ッフに関する情報、及び該プロジェクトの評価を記憶す
るプロジェクト情報記憶手段、 プロジェクトの内容とそのプロジェクトを担当するスタ
ッフの情報とを指定する指定手段、 前記指定手段により指定されたスタッフが指定されたプ
ロジェクトを担当した場合のプロジェクトの結果を、前
記プロジェクト情報記憶手段に記憶されたデータを用い
てシミュレートする手段、 として機能させるためのプログラムを記録したコンピュ
ータ読み取り可能な記録媒体。
13. A computer for designating the contents of a project, information on staff in charge of the project, and project information storage means for storing evaluations of the project, the contents of the project and information on staff in charge of the project. Means for simulating, using the data stored in the project information storage means, the result of the project when the staff specified by the specification means is in charge of the specified project. A computer-readable recording medium on which a program is recorded.
【請求項14】コンピュータを、 プロジェクトと、そのプロジェクトを構成する複数の因
子とを、対応付けて記憶するプロジェクト情報記憶手
段、 前記プロジェクト情報記憶手段に記憶された複数のプロ
ジェクトの因子同士を比較することにより、関連する因
子から構成される新たなプロジェクトを生成して提示す
る手段、 として機能させるためのプログラムを記録したコンピュ
ータ読み取り可能な記録媒体。
14. A computer, comprising: a project information storage means for storing a project and a plurality of factors constituting the project in association with each other; comparing factors of the plurality of projects stored in the project information storage means. Means for generating and presenting a new project composed of related factors, whereby a computer-readable recording medium storing a program for causing the program to function as
JP2000182180A 2000-06-16 2000-06-16 System and method for supporting project and recording medium Withdrawn JP2002007655A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000182180A JP2002007655A (en) 2000-06-16 2000-06-16 System and method for supporting project and recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000182180A JP2002007655A (en) 2000-06-16 2000-06-16 System and method for supporting project and recording medium

Publications (1)

Publication Number Publication Date
JP2002007655A true JP2002007655A (en) 2002-01-11

Family

ID=18682991

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000182180A Withdrawn JP2002007655A (en) 2000-06-16 2000-06-16 System and method for supporting project and recording medium

Country Status (1)

Country Link
JP (1) JP2002007655A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003271796A (en) * 2002-03-12 2003-09-26 Ntt Comware Corp Apparatus and method for assisting operation, computer program, and recording medium
JP2003271628A (en) * 2002-03-14 2003-09-26 Toshiba Corp Method and program for supporting accumulation and retrieval of project know-how
JP2004133860A (en) * 2002-10-15 2004-04-30 Ntt Comware Corp Engineer certifying system, and system, method and program for organizing team
JP2005044362A (en) * 2003-07-25 2005-02-17 Sap Ag Dynamic role generator
JP2007122144A (en) * 2005-10-25 2007-05-17 Toyota Motor Corp System and method for supporting selection of project member
JP2007334596A (en) * 2006-06-14 2007-12-27 Hitachi Software Eng Co Ltd Method, system and program for displaying project member association chart
JP2008077569A (en) * 2006-09-25 2008-04-03 Fujitsu Ltd Measure management program, measure management device, and measure management method
JP2013167930A (en) * 2012-02-14 2013-08-29 Nikon Corp Digital data mediation method and server device
KR101945042B1 (en) * 2018-08-28 2019-02-01 주식회사케이티에스솔루션스 Security service matching method and apparatus
WO2019225287A1 (en) * 2018-05-25 2019-11-28 株式会社日立製作所 Business model creation supporting method and business model creation supporting device
JP7043581B1 (en) * 2020-12-25 2022-03-29 株式会社ドワンゴ Creation support device, creation support method, recording medium, and program

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003271796A (en) * 2002-03-12 2003-09-26 Ntt Comware Corp Apparatus and method for assisting operation, computer program, and recording medium
JP2003271628A (en) * 2002-03-14 2003-09-26 Toshiba Corp Method and program for supporting accumulation and retrieval of project know-how
JP2004133860A (en) * 2002-10-15 2004-04-30 Ntt Comware Corp Engineer certifying system, and system, method and program for organizing team
JP4660648B2 (en) * 2003-07-25 2011-03-30 エスアーペー アーゲー Dynamic role generator
JP2005044362A (en) * 2003-07-25 2005-02-17 Sap Ag Dynamic role generator
JP4736713B2 (en) * 2005-10-25 2011-07-27 トヨタ自動車株式会社 Systems and methods to support the selection of project members
JP2007122144A (en) * 2005-10-25 2007-05-17 Toyota Motor Corp System and method for supporting selection of project member
JP2007334596A (en) * 2006-06-14 2007-12-27 Hitachi Software Eng Co Ltd Method, system and program for displaying project member association chart
JP2008077569A (en) * 2006-09-25 2008-04-03 Fujitsu Ltd Measure management program, measure management device, and measure management method
JP2013167930A (en) * 2012-02-14 2013-08-29 Nikon Corp Digital data mediation method and server device
WO2019225287A1 (en) * 2018-05-25 2019-11-28 株式会社日立製作所 Business model creation supporting method and business model creation supporting device
JP2019204418A (en) * 2018-05-25 2019-11-28 株式会社日立製作所 Creation support method for business model and creation support device for business model
JP7059108B2 (en) 2018-05-25 2022-04-25 株式会社日立製作所 Business model creation support method and business model creation support device
US11334838B2 (en) 2018-05-25 2022-05-17 Hitachi, Ltd. Business model generation support method and business model generation support device
KR101945042B1 (en) * 2018-08-28 2019-02-01 주식회사케이티에스솔루션스 Security service matching method and apparatus
JP7043581B1 (en) * 2020-12-25 2022-03-29 株式会社ドワンゴ Creation support device, creation support method, recording medium, and program

Similar Documents

Publication Publication Date Title
Myers Dialectical hermeneutics: a theoretical framework for the implementation of information systems
US20230290459A1 (en) Healthcare profile card indexing system and apparatus
Berntzen et al. A taxonomy of inter-team coordination mechanisms in large-scale agile
US20080091486A1 (en) Program, method, and apparatus for analyzing group work activities in a project
US8560482B2 (en) Avatar-based technical networking system
US20190164107A1 (en) Automated distributed screening of job candidates
US20080092059A1 (en) System and method for online and programmatic planning of events that are attended by persons
US12008317B2 (en) Summarizing information from different sources based on personal learning styles
Konow-Lund et al. Digital innovation during terror and crises
US20170337501A1 (en) System and method for coordinating and controlling production processes and inter-related decision making processes
JP2002007655A (en) System and method for supporting project and recording medium
US20190188624A1 (en) Automated one-to-many scheduling of interviews with candidates
Richter et al. Problems in Agile Global Software Engineering Projects especially within Traditionally Organised Corporations: [An exploratory semi-structured interview study]
Sannholm Translation, teamwork, and technology: The use of social and material scaffolds in the translation process
Edwards et al. How the Alt Text Gets Made: What Roles and Processes of Alt Text Creation Can Teach Us About Inclusive Imagery
JP2004118648A (en) Resource management server, human resource management method and human resource management system
JP2008250556A (en) Workflow management system, workflow management method, and program
CN116741178A (en) Manuscript generation method, device, equipment and storage medium
JP2010256962A (en) Device and program for providing assembly information
Garzone Job advertisements on Linkedin. Generic integrity and evolution
Katz et al. The state of sustainable research software: Results from the workshop on sustainable software for science: Practice and experiences (wssspe5. 1)
JPH11120224A (en) Personnel reshuffle support system
Allwood et al. Usability and database search at the Swedish Employment Service
Sanghera et al. Planning for communication and stakeholder management
Nicholls A small-to-medium-sized conference scheduling heuristic incorporating presenter and limited attendee preferences

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20070904