JP2001336115A - Rebuilding method of bridge - Google Patents

Rebuilding method of bridge

Info

Publication number
JP2001336115A
JP2001336115A JP2000158067A JP2000158067A JP2001336115A JP 2001336115 A JP2001336115 A JP 2001336115A JP 2000158067 A JP2000158067 A JP 2000158067A JP 2000158067 A JP2000158067 A JP 2000158067A JP 2001336115 A JP2001336115 A JP 2001336115A
Authority
JP
Japan
Prior art keywords
bridge
steel
concrete
pier
abutment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000158067A
Other languages
Japanese (ja)
Inventor
Katsuyoshi Nakanishi
克佳 中西
Takuya Murakami
琢哉 村上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP2000158067A priority Critical patent/JP2001336115A/en
Publication of JP2001336115A publication Critical patent/JP2001336115A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide the rebuilding method of a bridge capable of making an object rebuilding a concrete bridge and a steel bridge, remarkably reducing noise during rebuilding work and a dust amount scattering in a circumstance, and being built in short time in the simple configuration of the rebuilding bridge. SOLUTION: A steel shell 11 having a support part 14 on a lower bridge face side is installed in the bridge axis direction of the bridge P of both the sides of an existing bridge to be filled with concrete 16, after concrete 16 is hardened, the upper structure of the erection bridge is removed, and bridged on the support part 14 of both the steel shells 11 to install a floor slab 20.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、橋梁の架け替え方
法に関すものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for replacing a bridge.

【0002】[0002]

【従来の技術】橋梁は、地震等の災害や老朽化などのた
め、架け替えが必要となる場合がある。この種橋梁の架
け替え工法の一例として、特開2000−17618号
公報に開示された発明がある。この発明に係るコンクリ
ート橋の鋼橋への架替工法は、橋脚上に架設されている
既設のコンクリート製床版の上面に、路面を構成する別
途形成された新設の構成床版を設置するとともに、この
新設鋼製床版の橋軸方向両側部下面と橋脚との間に鋼桁
を設置し、この鋼桁と新設鋼製床版とを固定して鋼橋に
架け替えるようにしたものである。
2. Description of the Related Art Bridges may need to be replaced due to disasters such as earthquakes and aging. As an example of this type of bridge replacement method, there is an invention disclosed in Japanese Patent Application Laid-Open No. 2000-17618. In the method for replacing a concrete bridge according to the present invention with a steel bridge, a newly formed floor slab separately forming a road surface is installed on the upper surface of an existing concrete slab laid on a pier. A steel girder was installed between the lower surface of both sides of the new steel slab in the bridge axis direction and the pier, and the steel girder and the new steel slab were fixed and replaced with a steel bridge. is there.

【0003】そして、このように構成することにより、
災害や老朽化により架け替えが必要になったコンクリー
ト橋の架け替え工事が、騒音や粉塵の影響を抑制でき、
その上交通の遮断期間を従来工法に比べて大幅に短縮す
ることができるとしている。
[0003] Then, with this configuration,
Rebuilding of concrete bridges that needed to be replaced due to disasters and aging can reduce the effects of noise and dust,
In addition, it says that the traffic cutoff period can be significantly reduced compared to the conventional method.

【0004】[0004]

【発明が解決しようとする課題】上記の従来技術におい
ては、工事中の騒音を鋼板によって遮断するようにして
いるため、防音効果が小さく、また、架け替え橋梁の構
造が複雑なため、架け替え工事に長時間を要する。さら
に、架け替えの対象がコンクリート橋に限られるという
問題がある。
In the above-mentioned prior art, the noise during construction is cut off by a steel plate, so that the soundproofing effect is small, and the structure of the replacement bridge is complicated. It takes a long time for construction. Furthermore, there is a problem that the replacement target is limited to the concrete bridge.

【0005】本発明は、上記のような課題を解決するた
めになされたもので、コンクリート橋及び鋼橋を架け替
えの対象とし、架け替え工事中の騒音及び周囲にまき散
らす粉塵量を大幅に低減することができ、その上架け替
え橋梁の構造が簡単で短時間で架け替えることのできる
橋梁の架け替え方法を提供することを目的としたもので
ある。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and is intended to replace concrete bridges and steel bridges, thereby greatly reducing the noise during the replacement work and the amount of dust scattered around. It is another object of the present invention to provide a method for rebuilding a bridge in which the structure of the rebuilt bridge is simple and can be rebuilt in a short time.

【0006】[0006]

【課題を解決するための手段】本発明に係る橋梁の架け
替え方法は、既設橋梁の両側面の橋脚又は橋台上の橋軸
方向に、ほぼU字状断面又は箱状断面で下部の橋面側に
支持部を有する鋼殻を設置して該鋼殻内にコンクリート
を充填し、このコンクリートが硬化したのち前記既設橋
梁の上部構造を撤去し、ついで前記両鋼殻の支持部上に
橋絡して床版を設置するようにしたものである。
According to the present invention, there is provided a method for replacing a bridge, comprising the steps of: providing a substantially U-shaped cross section or a box-shaped cross section on a lower bridge surface in a bridge axis direction on a pier or abutment on both sides of an existing bridge; A steel shell having a supporting portion is installed on the side, concrete is filled in the steel shell, and after the concrete has hardened, the upper structure of the existing bridge is removed, and then a bridge is provided on the supporting portions of the two steel shells. The floor slab was then installed.

【0007】また、上記の既設橋梁の上部構造を撤去し
たのち、既設橋梁に設置した鋼殻の間の橋脚又は橋台上
に所定の間隔でかつ前記鋼殻と同方向に、下部の両側に
支持部を有する1本又は複数本の鋼殻を設置して該鋼殻
内にコンクリートを充填し、コンクリートが硬化したの
ち隣接する鋼殻の支持部上に橋絡して床版を設置するよ
うにしたものである。
Further, after removing the upper structure of the existing bridge, the bridge is supported on both sides of the lower part at a predetermined interval and in the same direction as the steel shell on a pier or abutment between the steel shells installed on the existing bridge. One or more steel shells having a portion are installed, concrete is filled in the steel shell, and after the concrete is hardened, a bridge is bridged on a support portion of an adjacent steel shell to install a floor slab. It was done.

【0008】また、本発明に係る橋梁の架け替え方法
は、既設橋梁の両側面又は橋台上の橋軸方向に、ほぼU
字状断面又は箱型断面で下部の橋面側に支持部を有し内
部にコンクリートが充填された鋼殻を設置し、ついで前
記既設橋梁の上部構造を撤去し、前記両鋼板の支持部上
に橋絡して床版を設置するようにしたものである。
[0008] The method for replacing a bridge according to the present invention is characterized in that both sides of the existing bridge or the direction of the bridge axis on the abutment are substantially U-shaped.
A steel shell filled with concrete inside with a supporting part on the lower bridge surface side in a U-shaped cross section or a box-shaped cross section is installed, then the upper structure of the existing bridge is removed, and The bridge is to be installed on the floor slab.

【0009】また、上記の既設橋梁の上部構造を撤去し
たのち、前記既設橋梁に設置した鋼殻の間の橋脚又は橋
台上に所定の間隔でかつ前記鋼殻と同方向に、下部の両
側に支持部を有し内部にコンクリートが充填された1本
又は複数本の鋼殻を設置し、隣接する鋼殻の支持部上に
橋絡して床版を設置するようにしたものである。
[0009] After removing the upper structure of the existing bridge, on the pier or abutment between the steel shells installed on the existing bridge, at predetermined intervals and in the same direction as the steel shell, on both sides of the lower part. One or more steel shells having a support portion and filled with concrete are installed therein, and a floor slab is installed by bridging on a support portion of an adjacent steel shell.

【0010】さらに、本発明に係る橋梁の架け替え方法
は、架設橋梁の橋脚の間又は橋脚と橋台との間に新橋脚
又は新橋台を建設し、これら新橋脚若しくは新橋台上、
又は新橋脚若しくは新橋台上と既設橋梁の橋脚若しくは
橋台上に、上記いずれかの上部構造を構築するようにし
たものである。
[0010] Further, the bridge replacement method according to the present invention comprises constructing a new pier or a new abutment between piers of an erected bridge or between a pier and an abutment.
Alternatively, any one of the above superstructures is constructed on a new pier or a new abutment and a pier or abutment of an existing bridge.

【0011】[0011]

【発明の実施の形態】[実施の形態1]図1は本発明に
係る架け替え工法により橋梁の上部構造を架け替えた状
態を示す断面図である。図において、Gは地面、Pは地
面G上に建設された既設橋梁の橋脚である。11は橋梁
の両側面の橋軸方向において橋脚P上に支承2を介して
設置された鋼殻で、内部にはコンクリート16が打設さ
れている。20は鋼殻11の下部の橋面側に設けた支持
部14上に橋絡して設置された床版で、これらにより架
け替え後の上部構造10を構成する。以下、図面を用い
て本発明に係る橋梁の架け替え方法の一例を説明する。
[First Embodiment] FIG. 1 is a cross-sectional view showing a state in which the upper structure of a bridge has been replaced by a replacement method according to the present invention. In the figure, G is the ground, and P is the pier of the existing bridge constructed on the ground G. Reference numeral 11 denotes a steel shell installed on the pier P via the bearing 2 in the bridge axis direction on both sides of the bridge, and concrete 16 is cast inside. Reference numeral 20 denotes a floor slab which is installed in a bridge on a support portion 14 provided on a bridge surface side below the steel shell 11, and these constitute the upper structure 10 after replacement. Hereinafter, an example of a bridge replacement method according to the present invention will be described with reference to the drawings.

【0012】図2は本発明に係る架け替え方法を実施す
る前の状態を示す既設橋梁の断面図、図3はその一部の
側面図である。なお、本例は比較的幅の広い既設橋梁の
架け替えについて説明する。図において、Gは地面、P
は地面G上に建設された橋脚(以下の説明では、橋台を
含む)である。3は橋脚P上に支承2を介して立設され
た複数の鋼桁で、その上には床版4が設けられている。
5は床版4の両側に設けた高欄で、これら支承2、鋼桁
3、床版4及び高欄5によって既設橋梁の上部構造1が
構成されている。
FIG. 2 is a cross-sectional view of an existing bridge showing a state before the replacement method according to the present invention is implemented, and FIG. 3 is a side view of a part of the existing bridge. This example describes replacement of a relatively wide existing bridge. In the figure, G is the ground, P
Is a pier (including an abutment in the following description) constructed on the ground G. Reference numeral 3 denotes a plurality of steel girders erected on a pier P via a bearing 2, and a floor slab 4 is provided thereon.
Reference numeral 5 denotes a rail provided on both sides of the floor slab 4. The bearing 2, the steel girder 3, the floor slab 4, and the rail 5 constitute an upper structure 1 of the existing bridge.

【0013】上記のような既設橋梁を架け替えるには、
次の手順による。 (1)各橋桁Pの両端部からやや内側の上面に、1本又
は複数本のアンカーボルトを植設する。 (2)図4に示すように、既設梁の上部構造1の両側に
おいて、橋脚P上に支承2を介してあらかじめ工場で製
作した鋼殻11を設置する。
To replace an existing bridge as described above,
Follow the steps below. (1) One or more anchor bolts are planted on the upper surface slightly inside from both ends of each bridge girder P. (2) As shown in FIG. 4, on both sides of the upper structure 1 of the existing beam, steel shells 11 previously manufactured in a factory are installed on the piers P via the bearings 2.

【0014】この鋼殻11は、図12に示すように、例
えば橋梁のスパンに対応した長さで、所定幅(高さ)の
2枚の鋼板12a,12bを所定の間隔で対向配置し、
鋼板12a,12bの下端部に鋼板12a,12bと同
じ長さで、鋼板12a,12bの間隔より広い幅の鋼板
からなる底板13を接合し、上部が開口されたほぼU字
状に構成したものである。
As shown in FIG. 12, two steel plates 12a and 12b having a length corresponding to, for example, a span of a bridge and a predetermined width (height) are opposed to each other at a predetermined interval, as shown in FIG.
A bottom plate 13 made of a steel plate having the same length as the steel plates 12a and 12b and having a width wider than the interval between the steel plates 12a and 12b is joined to lower ends of the steel plates 12a and 12b to form a substantially U-shape with an open top. It is.

【0015】この底板13は一方の端部を鋼板12a
(又は12b)の側壁と整合させ、したがって他方の端
部を鋼板12b(又は12a)の側壁から突設させて溶
接により一体に接合し、底板13の鋼板12b(又は1
2a)からの突出部により後述の床版の支持部14が形
成される。そして、支持部14には、橋脚Pに植設した
アンカーボルト31に対応する位置にアンカーボルト挿
通穴15aが設けられており、また、後述の床版に対応
してボルト挿通穴15bが設けられている。なお、支持
部14は、橋脚Pに対応する部分以外の部分を破線で示
すように切除して、幅狭に形成してもよい。
The bottom plate 13 has one end portion formed of a steel plate 12a.
(Or 12b), so that the other end protrudes from the side wall of the steel plate 12b (or 12a) and is integrally joined by welding, and the steel plate 12b (or 1
The projecting portion from 2a) forms a floor slab support portion 14 described later. The support portion 14 is provided with an anchor bolt insertion hole 15a at a position corresponding to the anchor bolt 31 planted on the pier P, and is provided with a bolt insertion hole 15b corresponding to a floor slab described later. ing. Note that the support portion 14 may be formed to be narrower by cutting off a portion other than the portion corresponding to the pier P as shown by a broken line.

【0016】上記の説明では、鋼殻11を上部が開口さ
れた断面ほぼU字状に形成した場合を示したが、上部開
口部を鋼板により閉塞して断面箱状に形成してもよい。
なお、この場合は、上記の鋼板に内部にコンクリートを
注入するための注入穴を設けることが必要である。
In the above description, the case where the steel shell 11 is formed to have a substantially U-shaped cross section with an upper opening is shown, but the upper opening may be closed with a steel plate to form a box-shaped cross section.
In this case, it is necessary to provide an injection hole for injecting concrete into the steel plate.

【0017】このように構成した鋼殻11は、図13に
示すように、支承2を介して橋脚P上に設置され、底板
13の支持部14に設けたアンカボルト挿通穴15aを
橋脚Pに植設したアンカーボルト31に挿入し、ナット
で固定して橋脚P上に設置される。この場合、図13に
破線で示すように、橋脚Pと支持部14との間にブロッ
ク状の台座32を介装してもよい。
The steel shell 11 thus configured is installed on the pier P via the bearing 2 as shown in FIG. 13, and the anchor bolt insertion hole 15a provided in the support portion 14 of the bottom plate 13 is connected to the pier P. It is inserted into the planted anchor bolt 31, fixed with a nut, and installed on the pier P. In this case, a block-shaped pedestal 32 may be interposed between the pier P and the support portion 14, as shown by a broken line in FIG.

【0018】(3)ついで、図5に示すように、この鋼
殻11内に現場においてコンクリート16を充填する。 (4)コンクリート16が硬化したのち、図6に示すよ
うに、既設橋梁の上部構造1(支承2、鋼桁3、床版4
及び高欄5)を解体し、撤去する。 (5)そして、後述の鋼殻11aの設置位置に対応して
各橋脚Pの上面に1本又は複数本のアンカーボルト31
を植設する。
(3) Next, as shown in FIG. 5, concrete 16 is filled in the steel shell 11 on site. (4) After the concrete 16 has hardened, as shown in FIG. 6, the superstructure 1 of the existing bridge (support 2, steel girder 3, floor slab 4)
5) and dismantle and remove. (5) Then, one or more anchor bolts 31 are provided on the upper surface of each pier P in accordance with the installation position of the steel shell 11a described later.
To plant.

【0019】(6)次に、図7に示すように、上部構造
1が撤去された鋼殻11の間の空間に、図14に示すよ
うに、底板13を鋼板12a,12bの両側に延設して
支持部14を構成した1本又は複数本の鋼殻11a(図
には2本の場合が示してある。なお、以下、先に設置し
た鋼殻11と合わせて、11と記すことがある。)を、
支承2を介して所定の間隔で、かつ鋼殻11と同方向に
橋脚P上に立設し、あらかじめ橋脚Pに植設したアンカ
ーボルト31にアンカーボルト挿通穴15aを挿入し、
ナットで固定して設置する。 (7)そして、図8に示すように、鋼殻11a内にコン
クリート16を充填する。
(6) Next, as shown in FIG. 7, a bottom plate 13 is extended to both sides of the steel plates 12a and 12b in a space between the steel shells 11 from which the upper structure 1 has been removed, as shown in FIG. One or a plurality of steel shells 11a (in the figure, two cases are shown.) There is.)
Standing on the pier P at predetermined intervals via the bearing 2 and in the same direction as the steel shell 11, the anchor bolt insertion hole 15 a is inserted into the anchor bolt 31 previously implanted in the pier P,
Install with nuts. (7) Then, as shown in FIG. 8, the concrete 16 is filled in the steel shell 11a.

【0020】(8)コンクリート16が硬化したのち、
図9、図10に示すように、各鋼殻11の間において、
隣接する支持部14間を橋絡してプレキャスト床版20
(以下、単に床版という)を設置する。この床版20は
あらかじめ工場で製作されたもので、その幅が隣接する
鋼殻11間の内のり寸法より若干狭く、所定の長さで形
成されており、橋軸方向の両端部には、図15に示すよ
うに、例えば三角形状あるいは台形状の凸部と凹部から
なるせん断接合キー21が形成されており、また、図1
6に示すように、一部又は全部の床版20の幅方向の両
縁部近傍には、上下方向に1個又は複数個のボルト挿通
穴22が設けられていて、その上面側は大径に形成され
ている。
(8) After the concrete 16 has hardened,
As shown in FIGS. 9 and 10, between each steel shell 11,
Bridging between adjacent supports 14 to precast slab 20
(Hereinafter simply referred to as floor slabs). The floor slab 20 is manufactured in advance at a factory, and has a width slightly smaller than an inner dimension between the adjacent steel shells 11 and is formed to have a predetermined length. As shown in FIG. 15, a shear bonding key 21 composed of, for example, a triangular or trapezoidal convex part and a concave part is formed.
As shown in FIG. 6, one or more bolt insertion holes 22 are provided in the vertical direction in the vicinity of both edges in the width direction of some or all of the floor slabs 20, and the upper surface side has a large diameter. Is formed.

【0021】このような床版20を鋼殻11の支持部1
4上に設置するにあたっては、先ず、橋脚Pに対応しな
い部分の支持部14間に橋絡して床版20を設設し、図
16に示すように、床版20に設けたボルト挿通穴22
に上面側から高力ボルト32を挿通し、下部を支持部1
4に設けたボルト挿通穴15bかた突出させてナットで
固定する。このとき、支持部14上にモルタルや弾性材
など23を敷いてもよい。これにより、各鋼殻11は床
版20によって連絡され、かつ強固に固定される。
The floor slab 20 is mounted on the supporting portion 1 of the steel shell 11.
When installing on the floor slab 4, first, a floor slab 20 is installed by bridging between the support portions 14 in a portion not corresponding to the pier P, and as shown in FIG. 22
A high-strength bolt 32 is inserted from the upper surface side into the
4 and is fixed with a nut by projecting from the bolt insertion hole 15b. At this time, a mortar or an elastic material 23 may be laid on the support portion 14. Thereby, each steel shell 11 is connected by the floor slab 20, and is firmly fixed.

【0022】このようにして、橋脚Pの間に順次床版2
0を設置する。そして、最後に橋脚P上のアンカーボル
ト31の支持部14からの突出部を切除し、上記と同様
に隣接する鋼殻11の支持部14上に床版20を設置す
れば、上部構造10が構成される。このときの状態を図
11に示す。なお、橋軸方向に隣接する床版20は、エ
ポキシ樹脂、モルタル等を介してせん断接合キー21に
より接合される。(8)最後に、床版20の上面に、コ
ンクリート等を打設すれば、既設橋梁の架け替え作業を
完了する。なお、上記の説明では、鋼殻11,11aを
橋脚P上に設置したのち内部にコンクリート16を充填
する場合を示したが、あらかじめ工場等でコンクリート
16を充填した鋼殻11,11aを橋脚P上に設置して
もよい。これにより、コンクリート16の硬化に要する
時間を短縮することができる。
In this way, the floor slabs 2 are sequentially placed between the piers P.
Set 0. Finally, the protrusion of the anchor bolt 31 from the support portion 14 on the pier P is cut off, and the floor slab 20 is placed on the support portion 14 of the adjacent steel shell 11 in the same manner as described above. Be composed. FIG. 11 shows the state at this time. The floor slabs 20 adjacent in the bridge axis direction are joined by a shear joining key 21 via epoxy resin, mortar, or the like. (8) Finally, if concrete or the like is cast on the upper surface of the floor slab 20, the work of replacing the existing bridge is completed. In the above description, the steel shells 11 and 11a are set on the pier P and then filled with concrete 16 in the interior. It may be installed on top. Thereby, the time required for hardening the concrete 16 can be shortened.

【0023】[実施例]本実施の形態に係る架け替えた
上部構造の諸元については、対象となる構造物の種類、
規模等により種々の設計が可能であるが、各部の寸法の
一例を挙げれば、次の通りである。鋼殻11は、板厚9
mm、幅(高さ)5m、長さ40mの2枚の鋼板12
a,12bを間隔0.5mを隔てて対向配置し、鋼板1
2a,12bの下端部に、板厚38mm、幅0.80
m、長さ40mの鋼板からなる底板13を、その一方の
端部を一方の側板(例えば12a)の側壁と整合させて
溶接により接合し、他方の側を他方の鋼板12bの側壁
から0.30m突出させて支持部14を形成した。
[Examples] Regarding the specifications of the replaced upper structure according to the present embodiment, the type of the target structure,
Various designs are possible depending on the scale and the like, but examples of the dimensions of each part are as follows. The steel shell 11 has a thickness of 9
mm, width (height) 5 m, length 40 m
a and 12b are arranged to face each other with an interval of 0.5 m.
38mm thickness, 0.80 width at the lower end of 2a, 12b
A bottom plate 13 made of a steel plate having a length of 40 m and a length of 40 m is joined by welding so that one end thereof is aligned with the side wall of one side plate (for example, 12a), and the other side is separated from the side wall of the other steel plate 12b by 0.1 mm. The support part 14 was formed to protrude by 30 m.

【0024】上記のように構成した鋼殻11及び床版2
0を現場に輸送し、既設橋梁の橋脚Pの両端部近傍に鋼
殻11をそれぞれ設置し、鋼殻11内にコンクリート1
6を充填した。コンクリート16が硬化したのち既設橋
梁の上部構造を分解して撤去し、両鋼製11の間におい
て、橋脚P上に互いに4.6m間隔(中心部の間隔)
で、支持部14が両側に設けられた2本の鋼殻11aを
設置し、内部にコンクリート16を充填した。
The steel shell 11 and the floor slab 2 configured as described above
0 to the site, steel shells 11 are respectively installed near both ends of the pier P of the existing bridge, and concrete 1 is placed in the steel shell 11.
6 was charged. After the concrete 16 has hardened, the upper structure of the existing bridge is disassembled and removed, and between the two steels 11, the bridge piers P are separated from each other by 4.6 m (interval at the center).
Then, two steel shells 11a provided with support portions 14 on both sides were installed, and concrete 16 was filled inside.

【0025】そして、コンクリート16が硬化したの
ち、橋脚Pと対応する部分を除く支持部14上に10m
mの厚さでモルタルを敷き、その上に板厚0.3m、幅
4m、長さ2mの床版20を配設し、M22(F10
T)の高力ボルト33をボルト挿通穴22,15bに挿
通し、ナットで固定した。ついで、橋脚P上のアンカー
ボルト31の支持部14からの突出部を除去し、上記と
同様に床版20を設置し、固定した。なお、床版20の
設置にあたっては、橋軸方向に隣接する床版20を、エ
ポキシ樹脂を介してせん断接合キー21により順次接合
して、支持部14に固定した。
After the concrete 16 has hardened, 10 m is placed on the support portion 14 except for the portion corresponding to the pier P.
mortar is laid with a thickness of 0.3 m, a floor slab 20 having a thickness of 0.3 m, a width of 4 m, and a length of 2 m is provided thereon.
T) The high-strength bolt 33 was inserted through the bolt insertion holes 22 and 15b, and fixed with nuts. Next, the protrusion of the anchor bolt 31 on the pier P from the support portion 14 was removed, and the floor slab 20 was installed and fixed in the same manner as described above. When the floor slabs 20 were installed, the floor slabs 20 adjacent in the bridge axis direction were sequentially joined to each other by the shear joining key 21 via an epoxy resin, and were fixed to the support portion 14.

【0026】上記のように構成した本発明に係る橋梁の
架け替え工法によれば、既設橋梁の両側面に高い防音効
果を有するコンクリート充填鋼殻を設置してから、既設
橋梁の上部構造の解体、撤去を行うため、上部構造の撤
去工事中に発生する騒音及び周囲にまき散らす粉塵量を
大幅に低減することができる。
According to the bridge replacement method according to the present invention having the above-described structure, concrete-filled steel shells having a high soundproofing effect are installed on both sides of the existing bridge, and then the upper structure of the existing bridge is dismantled. Since the removal is performed, the noise generated during the removal work of the superstructure and the amount of dust scattered around can be significantly reduced.

【0027】また、新設橋梁の架設に際しては、橋面を
形成する床版を支えるための支持部を有する鋼殻を橋脚
又は橋台上に設置し、ついで鋼殻内にコンクリートを充
填し、コンクリートが硬化したのち鋼殻の支持部上に床
版を設置するようにしたので、コンクリート打設時に型
枠が不要である。さらに、現場でコンクリートを打設す
るため、重量物を運搬、架設しなくてもよい。このよう
に、本発明は高い施工性を有するため、橋梁の架け替え
を短時間で行うことができる。
When a new bridge is erected, a steel shell having a support portion for supporting a floor slab forming a bridge surface is installed on a pier or an abutment, and then the steel shell is filled with concrete. After the hardening, the floor slab is placed on the supporting part of the steel shell, so that a formwork is not required at the time of casting concrete. Furthermore, since concrete is cast on site, it is not necessary to carry or lay heavy objects. As described above, since the present invention has high workability, bridge replacement can be performed in a short time.

【0028】上記発明では、既設橋梁の両側面の橋脚上
に鋼殻11を設置し、既設橋梁の上部構造を撤去したの
ち両鋼殻11の間に1本又は複数本の鋼殻11aを設置
した場合を示したが、橋梁の幅が狭い場合などにおいて
は、図1に示すように、両鋼殻11の間に鋼殻11aを
設置することなく、両鋼殻11の支持部14間に床版2
0を設置してもよい。
In the above invention, steel shells 11 are installed on the piers on both sides of the existing bridge, and after removing the upper structure of the existing bridge, one or more steel shells 11a are installed between the steel shells 11. In the case where the width of the bridge is narrow, for example, as shown in FIG. 1, the steel shell 11a is not provided between the steel shells 11 and the support portions 14 of the steel shells 11 are provided. Floor slab 2
0 may be set.

【0029】[実施の形態2]実施の形態1では、既設
橋梁の橋脚P上に上部構造10を架け替える場合につい
て説明したが、状況によっては既設橋梁の橋脚も損傷し
あるいは老巧化していることがある。本実施の形態は、
このような場合、橋脚Pの間に新たに橋脚(以下、橋台
を含み、新橋脚という)を建設し、この新橋脚上又は新
橋脚と既設橋梁の橋脚上に、実施の形態1に係る上部構
造10を構築するようにしたものである。本実施の形態
によれば、上部構造10のみならず、橋脚Pも架け替え
ることができる。
[Second Embodiment] In the first embodiment, the case where the upper structure 10 is replaced on the pier P of the existing bridge has been described. However, the pier of the existing bridge is damaged or deteriorated depending on the situation. Sometimes. In this embodiment,
In such a case, a new pier (hereinafter, referred to as a new pier including an abutment) is constructed between the piers P, and the upper part according to the first embodiment is placed on the new pier or on the pier of the new pier and the existing bridge. The structure 10 is constructed. According to the present embodiment, not only the upper structure 10 but also the pier P can be replaced.

【0030】[実施の形態3]以下の説明は、本発明の
要部をなす鋼殻及び床版の設置方法の他の実施の形態に
関するものである。図17は架け替え後の上部構造10
を斜め下方からみた斜視図である。本実施の形態は、ほ
ぼU字状断面又は箱型断面の鋼殻11内に、節となるダ
イヤフラム17を長手方向に一定間隔で設けたものであ
る。このように、鋼殻11内にダイヤフラム17を設け
ることにより、鋼殻11とこれに充填したコンクリート
16とを力学的により一体化することができる。
[Embodiment 3] The following description relates to another embodiment of a method of installing a steel shell and a floor slab, which are essential parts of the present invention. FIG. 17 shows the upper structure 10 after replacement.
FIG. 2 is a perspective view of the device viewed from obliquely below. In the present embodiment, diaphragms 17 serving as nodes are provided at regular intervals in the longitudinal direction in a steel shell 11 having a substantially U-shaped cross section or a box-shaped cross section. Thus, by providing the diaphragm 17 in the steel shell 11, the steel shell 11 and the concrete 16 filled therein can be mechanically integrated.

【0031】図18は鋼殻11の他の構造を示すもの
で、図18(a)に示すように、鋼殻11の鋼板12
a,12bの対向する内壁に、上下方向にほぼ等しい間
隔で複数の補剛材18を設けたもので、必要に応じて底
板13の内壁にも補剛材18を設けてもよい。補剛材1
8は、例えば図18(b)に示すように、鋼殻3とほぼ
等しい長さで水平片に複数のコンクリート通過穴19が
設けられた断面L字状の鋼材、又は図18(c)に示す
ように、L字状で短い複数の鋼材からなり、その垂直片
を鋼殻11の内壁に溶接により接合したものである。本
実施の形態によれば、鋼殻11の内壁に複数の補剛材1
8を設けたので、鋼殻11の形状を維持すると共に、鋼
殻11とコンクリート16との一体化をさらに促進する
ことができる。
FIG. 18 shows another structure of the steel shell 11, and as shown in FIG.
A plurality of stiffeners 18 are provided at substantially equal intervals in the vertical direction on the inner walls opposing a and 12b. The stiffeners 18 may be provided on the inner wall of the bottom plate 13 as needed. Stiffener 1
18 is, for example, as shown in FIG. 18 (b), an L-shaped steel material having a length substantially equal to that of the steel shell 3 and a plurality of concrete passage holes 19 provided in a horizontal piece, or FIG. 18 (c). As shown in the figure, a plurality of L-shaped short steel materials are used, and their vertical pieces are joined to the inner wall of the steel shell 11 by welding. According to the present embodiment, a plurality of stiffeners 1
Since the steel shell 11 is provided, the shape of the steel shell 11 can be maintained, and the integration of the steel shell 11 and the concrete 16 can be further promoted.

【0032】図19は鋼殻11の支持部14上への床版
20の取付方法の他の例を示すもので、図19(b)に
示すように、支持部14の上面に複数のスタッドジベル
等の棒状のせん断接合部材35を溶接等により接合する
と共に、図19(c)に示すように、床版20のせん断
接合部材35と対向する位置に、貫通穴24を設けたも
のである。
FIG. 19 shows another example of a method of mounting the floor slab 20 on the support portion 14 of the steel shell 11, and as shown in FIG. A bar-shaped shear joining member 35 such as a dowel is joined by welding or the like, and as shown in FIG. 19C, the through hole 24 is provided at a position facing the shear joining member 35 of the floor slab 20. .

【0033】鋼殻11の支持部14への床版20の敷設
にあたっては、必要に応じて支持部14上にモルタル等
23を敷き、ついで図19(a)に示すように、床版2
0に設けた貫通穴24をせん断接合部材35に嵌合して
支持部14上に載置する。そして、貫通穴24にモルタ
ル又はコンクリート16を流し込んで固化することによ
り、せん断接合部材35と床版20を一体に接合する。
When laying the floor slab 20 on the support portion 14 of the steel shell 11, mortar 23 or the like is laid on the support portion 14 as necessary, and then, as shown in FIG.
The through hole 24 provided on the support portion 14 is fitted to the shear joint member 35. Then, the mortar or concrete 16 is poured into the through holes 24 and solidified, whereby the shear joining member 35 and the floor slab 20 are integrally joined.

【0034】以上、本発明に使用する鋼殻の他の例につ
いて説明したが、これに限定するものではなく、他の構
造のものを用いてもよい。また、鋼殻11の支持部14
への床版20の取付けの他の例について説明したが、そ
の他の適宜の手段により取付けることができる。
The other examples of the steel shell used in the present invention have been described above. However, the present invention is not limited to this, and another steel shell having another structure may be used. Further, the support portion 14 of the steel shell 11
Although another example of the attachment of the floor slab 20 to the slab has been described, it can be attached by other appropriate means.

【0035】[0035]

【発明の効果】本発明に係る橋梁の架け替え方法は、既
設橋梁の両側面の橋脚又は橋台上の橋軸方向に、ほぼU
字状断面又は箱状断面で下部の橋面側に支持部を有する
鋼殻を設置して内部にコンクリートを充填し、このコン
クリートが硬化したのち既設橋梁の上部構造を撤去し
て、両鋼殻の支持部上に橋絡して床版を設置し、あるい
は、上記の既設橋梁の上部構造を撤去したのち、両鋼殻
の間の橋脚又は橋台上に所定に間隔で鋼殻と同方向に、
下部の両側に支持部を有する1本又は複数本の鋼殻を設
置して内部にコンクリートを充填し、コンクリートが硬
化したのち隣接する鋼殻の支持部上に橋絡して床版を設
置するようにしたので、次のような効果を得ることがで
きる。
According to the method for replacing a bridge according to the present invention, the bridge is substantially U-shaped in the direction of the bridge axis on the pier or abutment on both sides of the existing bridge.
A steel shell having a support section on the lower bridge surface side with a U-shaped cross section or a box-shaped cross section is installed, concrete is filled inside, and after this concrete hardens, the upper structure of the existing bridge is removed, and both steel shells are removed. After installing the floor slab by bridging on the support of the above, or after removing the superstructure of the existing bridge, place it on the pier or abutment between both steel shells in the same direction as the steel shell at predetermined intervals. ,
One or more steel shells with supporting parts are installed on both sides of the lower part, concrete is filled inside, and after the concrete is hardened, a bridge is placed on the supporting part of the adjacent steel shell and a floor slab is installed. As a result, the following effects can be obtained.

【0036】既設橋梁の両側面に高い防音効果を有する
コンクリート充填鋼殻を設置してから、既設橋梁の解
体、撤去を行うため、上部構造の解体、撤去工事中に発
生する騒音及び周囲にまき散らす粉塵量を大幅に低減す
ることができる。また、ほぼU字状断面又は箱状断面の
鋼殻内にコンクリートを打設するようにしたので、コン
クリート打設時に型枠が不要であり、さらに、現場でコ
ンクリートを打設するため、重量物を運搬、架設しなく
てもよい。このように、本発明は高い施工性を有するた
め、橋梁の架け替えを短時間で行うことができ、その上
コンクリート橋は勿論、鋼橋の架け替えも行うことがで
きる。
After installing concrete-filled steel shells having high soundproofing effects on both sides of the existing bridge, the existing bridge is dismantled and removed in order to dismantle the superstructure, disperse the noise generated during the removal work and the surrounding area. The amount of dust can be significantly reduced. In addition, since concrete is poured into a steel shell having a substantially U-shaped cross section or box-shaped cross section, no formwork is required at the time of placing concrete. Need not be transported or installed. As described above, since the present invention has high workability, the bridge can be replaced in a short time, and in addition to the concrete bridge, the steel bridge can be replaced.

【0037】また、本発明に係る橋梁の架け替え方法
は、上記の鋼殻にあらかじめコンクリート充填鋼殻を用
いたので、上部構造の解体、撤去工事中に発生する騒音
及び粉塵量を大幅に低減することができると共に、工期
をさらに短縮することができる。
In the bridge replacement method according to the present invention, since concrete-filled steel shells are used in advance for the steel shells, the amount of noise and dust generated during the disassembly and removal work of the upper structure is significantly reduced. And the construction period can be further shortened.

【0038】さらに、本発明に係る橋梁の架け替え方法
は、既設橋梁の橋脚の間又は橋脚と橋台との間に新橋脚
又は新橋台を建設し、これら新橋脚若しくは新橋台上、
又は新橋脚若しくは新橋台上と既設橋梁の橋脚若しくは
橋台上に、上記いずれかの上部構造を構築するようにし
たので、上部構造の架け替えのみならず、橋脚や橋台も
新設することができる。
Further, the method for replacing a bridge according to the present invention includes the steps of: constructing a new pier or a new abutment between piers of an existing bridge or between a pier and an abutment;
Alternatively, since any of the above superstructures is constructed on a new pier or a new abutment and on the pier or abutment of an existing bridge, not only replacement of the superstructure but also a new pier or abutment can be provided.

【図面の簡単な説明】[Brief description of the drawings]

【図1】既設橋梁に本発明により上部構造を架け替えた
状態を示す断面図である。
FIG. 1 is a cross-sectional view showing a state in which an upper structure is replaced on an existing bridge according to the present invention.

【図2】架け替えを行う既設橋梁の断面図である。FIG. 2 is a cross-sectional view of an existing bridge to be replaced.

【図3】図1の一部の側面図である。FIG. 3 is a side view of a part of FIG. 1;

【図4】本発明の実施の形態1に係る橋梁の架け替え手
順の説明図である。
FIG. 4 is an explanatory diagram of a bridge replacement procedure according to the first embodiment of the present invention.

【図5】橋梁の架け替え手順の説明図である。FIG. 5 is an explanatory diagram of a bridge replacement procedure.

【図6】橋梁の架け替え手順の説明図である。FIG. 6 is an explanatory diagram of a bridge replacement procedure.

【図7】橋梁の架け替え手順の説明図である。FIG. 7 is an explanatory diagram of a bridge replacement procedure.

【図8】橋梁の架け替え手順の説明図である。FIG. 8 is an explanatory diagram of a bridge replacement procedure.

【図9】架け替え完了後の断面図である。FIG. 9 is a sectional view after completion of replacement.

【図10】図8の一部の側面図である。FIG. 10 is a side view of a part of FIG. 8;

【図11】図8の斜め下方からみた斜視図である。11 is a perspective view of FIG. 8 as viewed from obliquely below.

【図12】鋼殻の一例の斜視図である。FIG. 12 is a perspective view of an example of a steel shell.

【図13】鋼殻の橋脚への設置の一例の説明図である。FIG. 13 is an explanatory diagram of an example of installation of a steel shell on a pier.

【図14】鋼殻の他の例の斜視図である。FIG. 14 is a perspective view of another example of the steel shell.

【図15】床版の一例の側面図である。FIG. 15 is a side view of an example of the floor slab.

【図16】床版の支持部への取付けの一例の説明図であ
る。
FIG. 16 is an explanatory diagram of an example of attaching a floor slab to a support portion.

【図17】他の例の鋼殻によって架け替えた橋梁を斜め
下方からみた斜視図である。
FIG. 17 is a perspective view of a bridge replaced with a steel shell of another example as viewed obliquely from below.

【図18】鋼殻のさらに別の例の断面図及び補剛材の斜
視図である。
FIG. 18 is a sectional view of still another example of a steel shell and a perspective view of a stiffener.

【図19】床版の支持部への取付けの他の例の説明図で
ある。
FIG. 19 is an explanatory view of another example of attaching the floor slab to the support portion.

【符号の説明】[Explanation of symbols]

1 既設橋梁の上部構造 10 架け替えた橋梁の上部構造 11 鋼殻 14 支持部 16 コンクリート 20 床版 P 橋脚 DESCRIPTION OF SYMBOLS 1 Upper structure of existing bridge 10 Upper structure of bridge which was replaced 11 Steel shell 14 Supporting part 16 Concrete 20 Floor slab P Pier

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 既設橋梁の両側面の橋脚又は橋台上の橋
軸方向に、ほぼU字状断面又は箱形断面で下部の橋面側
に支持部を有する鋼殻を設置して該鋼殻内にコンクリー
トを充填し、このコンクリートが硬化したのち前記既設
橋梁の上部構造を撤去し、ついで前記両鋼殻の支持部上
に橋絡して床版を設置することを特徴とする橋梁の架け
替え方法。
1. A steel shell having a U-shaped cross section or a box-shaped cross section and a supporting portion on a lower bridge surface side is installed in a bridge axis direction on a pier or abutment on both sides of an existing bridge. And filling the concrete with the concrete, and after the concrete has hardened, removing the superstructure of the existing bridge, and then bridging the supporting portions of the two steel shells and installing a floor slab. Replacement method.
【請求項2】 既設橋梁の両側面の橋脚又は橋台上の橋
軸方向に、ほぼU字状断面又は箱状断面で下部の橋面側
に支持部を有する鋼殻を設置して該鋼殻内にコンクリー
トを充填し、このコンクリートが硬化したのち前記既設
橋梁の上部構造を撤去し、ついで、前記既設橋梁に設置
した鋼殻の間の橋脚又は橋台上に所定の間隔でかつ前記
鋼殻と同方向に、下部の両側に支持部を有する1本又は
複数本の鋼殻を設置して該鋼殻内にコンクリートを充填
し、このコンクリートが硬化したのち隣接する鋼殻の支
持部上に橋絡して床版を設置することを特徴とする橋梁
の架け替え方法。
2. A steel shell having a U-shaped cross section or a box-shaped cross section and a supporting portion provided on a lower bridge surface side in a bridge axis direction on a pier or abutment on both sides of an existing bridge. After the concrete is hardened, the superstructure of the existing bridge is removed after the concrete has hardened, and then at a predetermined interval on the pier or abutment between the steel shells installed on the existing bridge and the steel shell. In the same direction, one or more steel shells having support portions on both sides of the lower portion are installed, concrete is filled in the steel shells, and after the concrete is hardened, a bridge is placed on the support portions of the adjacent steel shells. A method of replacing a bridge, characterized by installing a floor slab in entanglement.
【請求項3】 既設橋梁の両側面の橋脚又は橋台上の橋
軸方向に、ほぼU字状断面又は箱形断面で下部の橋面側
に支持部を有し内部にコンクリートが充填された鋼殻を
設置し、ついで前記既設橋梁の上部構造を撤去し、前記
両鋼殻の支持部上に橋絡して床版を設置することを特徴
とする橋梁の架け替え方法。
3. A steel having a substantially U-shaped cross section or a box-shaped cross section having a support portion on the lower bridge surface side and filled with concrete inside in the direction of the bridge axis on the pier or abutment on both sides of the existing bridge. A method for rebuilding a bridge, comprising: installing a shell, removing the upper structure of the existing bridge, and installing a floor slab by bridging the support portions of the steel shells.
【請求項4】 既設橋梁の両側面の橋脚又は橋台上の軸
方向に、ほぼU字状断面又は箱状断面で下部の橋面側に
支持部を有し内部にコンクリートが充填された鋼殻を設
置し、ついで前記既設橋梁の上部構造を撤去し、次に前
記既設橋梁に設置した鋼殻の間の橋脚又は橋台上に所定
の間隔でかつ前記鋼殻と同方向に、下部の両側に支持部
を有し内部にコンクリートが充填された1本又は複数本
の鋼殻を設置し、隣接する鋼殻の支持部上に橋絡して床
版を設置することを特徴とする橋梁の架け替え方法。
4. A steel shell having a substantially U-shaped or box-shaped cross-section and a supporting portion on the lower bridge surface side in the axial direction on the pier or abutment on both sides of the existing bridge and having concrete filled therein. Is installed, then the upper structure of the existing bridge is removed, and then on the pier or abutment between the steel shells installed on the existing bridge at predetermined intervals and in the same direction as the steel shell, on both sides of the lower part Bridge construction characterized in that one or more steel shells having a support portion and filled with concrete are installed therein, and a floor slab is installed by bridging on a support portion of an adjacent steel shell. Replacement method.
【請求項5】 既設橋梁の橋脚の間又は橋脚と橋台との
間に新橋脚又は新橋台を建設し、これら新橋脚若しくは
新橋台上、又は新橋脚若しくは新橋台上と既設橋梁の橋
脚若しくは橋台上に、請求項1,2,3又は4のいずれ
かの上部構造を構築することを特徴とする橋梁の架け替
え工法。
5. A new pier or a new abutment is constructed between the piers of the existing bridge or between the pier and the abutment, and the new pier or the new abutment, or the pier or the abutment of the new pier or the new abutment and the existing bridge. A method for rebuilding a bridge, wherein the upper structure according to any one of claims 1, 2, 3, and 4 is constructed thereon.
JP2000158067A 2000-05-29 2000-05-29 Rebuilding method of bridge Pending JP2001336115A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000158067A JP2001336115A (en) 2000-05-29 2000-05-29 Rebuilding method of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000158067A JP2001336115A (en) 2000-05-29 2000-05-29 Rebuilding method of bridge

Publications (1)

Publication Number Publication Date
JP2001336115A true JP2001336115A (en) 2001-12-07

Family

ID=18662595

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000158067A Pending JP2001336115A (en) 2000-05-29 2000-05-29 Rebuilding method of bridge

Country Status (1)

Country Link
JP (1) JP2001336115A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778662A (en) * 2019-03-14 2019-05-21 中铁第四勘察设计院集团有限公司 Across the rigid flute type beam bridge of shallow tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778662A (en) * 2019-03-14 2019-05-21 中铁第四勘察设计院集团有限公司 Across the rigid flute type beam bridge of shallow tunnel
CN109778662B (en) * 2019-03-14 2024-04-02 中铁第四勘察设计院集团有限公司 Rigid frame groove type beam bridge crossing shallow-buried tunnel

Similar Documents

Publication Publication Date Title
JPH0821196A (en) Structure of floor system for segment type tunnel, and construction of segment type tunnel with precast floor system
JP3844743B2 (en) Box girder bridge structure and its construction method
JP2004092078A (en) Structure and construction method for bridge
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
JP6630399B2 (en) Pca footing
JPH11148110A (en) Continuous girder bridge
JP6425848B1 (en) Bridge replacement method
JP2002194704A (en) Method for constructing girder
KR20040086653A (en) bridge and construction process with integral pier-type mixed abutment
JPH11247109A (en) Constructing method of rigid-framed elevated bridge
JP2004027609A (en) Construction method for subterranean structure and subterranean structure
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP2980567B2 (en) How to replace the bearing device
JP2001336115A (en) Rebuilding method of bridge
JP6630398B2 (en) Pca middle pillar
JPH08120638A (en) Connecting structure of pile and beam and execution method of structure using connecting structure
KR910007423B1 (en) Method for construction p.c - beam on the bridge
JP2579120B2 (en) garage
JP2536376B2 (en) Foundation structure of shed for road protection
JP2000129633A (en) Erection method for bridge floor slab
JPH03199528A (en) Steel frame foundation of construction
KR102273716B1 (en) Soundproof tunnel for existing bridge and its construction method
JP7108108B1 (en) Support structure of temporary piers and update method of bridge superstructure