JP2001251095A - Manufacture control system - Google Patents

Manufacture control system

Info

Publication number
JP2001251095A
JP2001251095A JP2000060906A JP2000060906A JP2001251095A JP 2001251095 A JP2001251095 A JP 2001251095A JP 2000060906 A JP2000060906 A JP 2000060906A JP 2000060906 A JP2000060906 A JP 2000060906A JP 2001251095 A JP2001251095 A JP 2001251095A
Authority
JP
Japan
Prior art keywords
component
mounting
parts
time
printed wiring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000060906A
Other languages
Japanese (ja)
Inventor
Masaichi Kobayashi
政一 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2000060906A priority Critical patent/JP2001251095A/en
Publication of JP2001251095A publication Critical patent/JP2001251095A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Installment Of Electrical Components (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a manufacture control system wherein production stop due to arrangement for supplying a surface-mounting component is suppressed to minimum, in a surface-mounting process in which the surface-mounting component is mounted on a printed wiring board (Pt plate) for soldering in many-kind/ small-quantity production system. SOLUTION: A fixed set component deciding means is provided wherein a production plan corresponding component list is generated from a CAD information for Pt plate, a production plan for it, and a component information for components to be use, and a fixed set component is decided based on a production plan corresponding board average and a line operation condition. A fixed set component distributing means is provided wherein a fixed set component among the production plan corresponding component list is sequentially set, initially to a mounter capable of collective set and then to a plurality of mounters after no mounter capable of collective set is available, so that the total mounting time with the mounter is averaged.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、製造管理システム
に係り、特に、多種少量生産体制下で表面実装部品をプ
リント配線基板上に搭載して半田付けする表面実装工程
において、表面実装部品供給の段取り替えによる生産停
止を極少化することが可能な製造管理システムに関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a manufacturing management system, and more particularly to a method for supplying surface mounted components in a surface mounting process of mounting and soldering surface mounted components on a printed wiring board under a small-lot production system. The present invention relates to a production management system capable of minimizing production stoppage due to setup change.

【0002】通信機器や情報処理機器などの電子機器の
製造工程においては、抵抗やコンデンサなどのチップ部
品、デジタル集積回路やアナログ集積回路をパッケージ
に納めたSOP(Small Outline Package)又はQFP
(Quad Flat Package)などの表面実装部品(通常「SM
D」と略記される。これは、「Surface Mount Device」
の頭文字をとった略語である。)をプリント配線基板上
に搭載して半田付けする表面実装工程が主要な工程にな
っている。
2. Description of the Related Art In the manufacturing process of electronic equipment such as communication equipment and information processing equipment, SOP (Small Outline Package) or QFP in which chip parts such as resistors and capacitors, digital integrated circuits and analog integrated circuits are packaged.
(Quad Flat Package) and other surface mount components (usually "SM
D ". This is "Surface Mount Device"
Is an abbreviation that takes the initials of ) Is mounted on a printed circuit board and soldered.

【0003】従って、表面実装工程の合理化と効率化が
通信機器や情報処理機器などの電子機器の製造工程の合
理化と効率化にとって最も重要な課題となる。
[0003] Therefore, rationalization and efficiency of the surface mounting process are the most important issues for rationalization and efficiency improvement of the manufacturing process of electronic devices such as communication devices and information processing devices.

【0004】ここで、表面実装工程には、通常、プリン
ト配線基板の表面の実装工程、即ち、半田ペースト印
刷、表面実装部品の搭載及びリフロー・ソルダリングに
よる半田付けと、プリント配線基板の裏面の実装工程、
即ち、表面実装部品固定のための接着剤塗布、該接着剤
上への表面実装部品の搭載、該接着剤の硬化による表面
実装部品の一時固定、リード付部品のプリント配線基板
上の穴へのリード挿入、フロー・ソルダリングによる半
田付けがある。
[0004] Here, the surface mounting process usually includes a surface mounting process of the printed wiring board, that is, solder paste printing, mounting of surface mounted components and soldering by reflow soldering, and a back surface of the printed wiring board. Mounting process,
That is, applying an adhesive for fixing the surface-mounted component, mounting the surface-mounted component on the adhesive, temporarily fixing the surface-mounted component by curing the adhesive, and attaching the leaded component to the hole on the printed wiring board. There are lead insertion and soldering by flow soldering.

【0005】このうち、リード付部品のリード挿入及び
フロー・ソルダリングは、本発明の対象外である。
[0005] Of these, lead insertion and flow soldering of components with leads are outside the scope of the present invention.

【0006】従って、プリント配線基板の表面における
半田ペースト印刷、表面実装部品の搭載及びリフロー・
ソルダリングによる半田付けと、プリント配線基板の裏
面における表面実装部品固定のための接着剤塗布、該接
着剤上への表面実装部品の搭載、該接着剤の硬化による
表面実装部品の一時固定及びフロー・ソルダリングによ
る半田付けと、これらに付随する作業が本発明による合
理化と効率化の対象となる。
Accordingly, solder paste printing on the surface of a printed wiring board, mounting of surface mount components, and reflow soldering.
Soldering by soldering, applying adhesive for fixing surface mounted components on the back side of the printed wiring board, mounting surface mounted components on the adhesive, temporarily fixing and mounting the surface mounted components by curing the adhesive・ Soldering by soldering and the work associated therewith are objects of rationalization and efficiency improvement according to the present invention.

【0007】さて、種類が限定された特定品種を大量生
産する場合には、決まった部品を継続的に供給すればよ
いので、全てが特定品種向けに最適化されている専用の
製造装置を投入することが合理化と効率化の最適な解に
なる。
[0007] When mass-producing a specific kind of limited type, it is only necessary to continuously supply fixed parts. Therefore, a dedicated manufacturing apparatus, all of which are optimized for the specific kind, is introduced. Is the best solution for rationalization and efficiency.

【0008】しかし、製造すべき製品の品種が多い上に
1種類当たりの製造数が少ない場合、即ち多種少量生産
の場合には専用の製造装置の投入は不可能で、汎用の製
造装置を組み合わせて、製品によって供給する部品を段
取り替えする形態の生産ラインを構成せざるを得ない。
However, if there are many types of products to be manufactured and the number of products per type is small, that is, in the case of small-lot production of many types, it is not possible to put in a dedicated manufacturing apparatus, and it is not possible to combine general-purpose manufacturing apparatuses. Therefore, a production line in which parts supplied by products are changed is inevitable.

【0009】従って、多種少量生産を行なう生産ライン
においては、製品によって供給する部品を段取り替えす
る作業の効率化が製造工程の効率化を左右することにな
る。
[0009] Therefore, in a production line in which various kinds of products are produced in small quantities, the efficiency of the work of changing the parts supplied by the product affects the efficiency of the manufacturing process.

【0010】表面実装ラインは、通常、チップ部品専用
のチップ搭載機と、チップ部品と微細ピッチの多端子を
有するパッケージ部品とを搭載可能な汎用搭載機(異な
る形態の部品を搭載できるという意味で「異形部品搭載
機」又は「異形搭載機」とも呼ばれる。)の2種類の搭
載機で構成される。
A surface mounting line is generally a chip mounting machine dedicated to chip components, and a general-purpose mounting machine capable of mounting chip components and package components having multiple terminals with fine pitches (in the sense that components of different forms can be mounted). It is also called “deformed component mounting machine” or “deformed mounting machine.”).

【0011】そして、多種少量生産形態の典型的な製品
では、1種類のプリント配線ユニット当たり約40種類
の表面実装部品を搭載機付属のパーツ・フィーダーに取
りつけて当該搭載機にセットする必要がある。1種類の
表面実装部品を搭載機付属のパーツ・フィーダーに取り
つけて当該搭載機にセットする(これまで意味の説明な
しに何回か使っているが、これを「段取り替え」又は
「段取り」という。)には約2分/部品種の時間がかか
る。従って、40種類の表面実装部品の段取り替えを作
業者2人で行なうと40分を要することになる。
[0011] Then, in a typical product of various kinds of small-volume production, it is necessary to mount about 40 types of surface mount components per type of printed wiring unit on a parts feeder attached to the mounting machine, and set them on the mounting machine. . Attach one type of surface mount component to the part feeder attached to the mounting machine and set it on the mounting machine. (I have used it several times without explanation of its meaning, but this is called "setup change" or "setup".) .) Takes about 2 minutes / type of part. Therefore, it takes 40 minutes to change the setup of 40 types of surface mount components by two workers.

【0012】しかも、問題なのは、同一種類のプリント
配線ユニットの製造数が多くても少なくても固定的に4
0分の段取り時間がかかるということである。言い換え
れば、製造数が少ないプリント配線ユニットの場合、表
面実装部品の段取り替えに要する時間の方がプリント配
線ユニットに表面実装部品を実装する時間より長くなる
こともあるということである。
Further, the problem is that even if the number of manufactured printed wiring units of the same type is large or
This means that a setup time of 0 minutes is required. In other words, in the case of a printed wiring unit with a small number of manufactures, the time required for the setup change of the surface mounted component may be longer than the time required for mounting the surface mounted component on the printed wiring unit.

【0013】従って、製造数が少ないプリント配線ユニ
ットの場合であっても、表面実装部品の段取り替えに要
する時間を極少化して、多種少量生産ラインの効率を高
めることができる製造管理システムの構築が待たれてい
る。
Therefore, even in the case of a printed wiring unit whose number of production is small, it is possible to construct a production management system capable of minimizing the time required for the changeover of the surface mount components and increasing the efficiency of the production line of various kinds and small quantities. I have been waiting.

【0014】[0014]

【従来の技術】従来、段取り替えに伴う生産停止時間を
極少化すべく、下記の如き工夫がなされていた。
2. Description of the Related Art Heretofore, the following measures have been devised in order to minimize the production stoppage time due to setup change.

【0015】その第一は、パーツ・フィーダーのパーツ
・フィーダー・セット・テーブルへのセットの自動化で
ある。
The first one is to automate the setting of the parts feeder to the parts feeder set table.

【0016】これは、パーツ・フィーダー自動倉庫とパ
ーツ・フィーダー取り付けロボットの導入によるパーツ
・フィーダーのパーツ・フィーダー・セット・テーブル
へのセットの自動化と、そのパーツ・フィーダー・セッ
ト・テーブルを自動で交換する装置から成り、これによ
れば、プリント配線板ユニット製造中に次に必要になる
部品をパーツ・フィーダー・セット・テーブル準備して
おくことによって、製造終了時に自動交換してくれるの
で、ライン停止時間は2分程度に短縮できる。
[0016] This is to automate the setting of the parts feeder to the parts feeder set table by introducing the parts feeder automatic warehouse and the parts feeder mounting robot, and to automatically replace the parts feeder set table. According to this, the parts that will be required next during the manufacture of the printed wiring board unit will be automatically replaced at the end of production by preparing the parts feeder set table, so the line will be stopped The time can be reduced to about 2 minutes.

【0017】最大の長所は省力化の効果が大きいことで
あるが、製造システムが高価な上、特殊な搭載機にしか
適用できないという問題がある。又、同一部品に対して
表面実装中の部品リールと外段取り中の部品リールの2
つのリールが必要になるという問題もある。
The greatest advantage is that the effect of labor saving is great, but there is a problem that the manufacturing system is expensive and can be applied only to a special mounting machine. In addition, for the same component, there are two types: a component reel being surface-mounted and a component reel being set up outside.
There is also a problem that one reel is required.

【0018】第二は、複数の表面実装プリント配線板ユ
ニットの部品パーツ・フィーダーをまとめて準備してお
き、前の製品の製造終了時に1つのパーツ・フィーダー
を交換する方法で、ライン停止時間は約20分である。
The second is a method in which component parts and feeders of a plurality of surface mount printed wiring board units are collectively prepared, and one part and feeder is replaced at the end of the production of the previous product. About 20 minutes.

【0019】長所は、製造数が多い製品と少ない製品を
組み合わせることで全体の搭載時間を長くし、その間に
部品の準備を済まそうとするものであるが、省力化の効
果が少なく、同一部品に対して表面実装中の部品リール
と外段取り中の部品リールの2つのリールが必要になる
という問題がある。
An advantage is that the total mounting time is lengthened by combining a product with a large number of products and a product with a small number of products, and during that time the components are ready to be prepared. On the other hand, there is a problem that two reels, a component reel during surface mounting and a component reel during external setup, are required.

【0020】第三は、外段取りで準備したパーツ・フィ
ーダーをパーツ・フィーダー・セット・テーブル毎一括
交換する方式である。
The third method is a system in which parts feeders prepared in the external setup are exchanged for each part feeder set table.

【0021】これは、別置きのパーツ・フィーダー・セ
ット・テーブルに表面実装部品をセットしてパーツ・フ
ィーダーをセット・テーブル毎一括交換するもので、内
段取り時間は10分程度である。
In this method, a surface mount component is set on a separately placed parts feeder set table, and the parts feeder is replaced collectively for each set table. The internal setup time is about 10 minutes.

【0022】長所は、完全外段取りが可能なことである
が、パーツ・フィーダー・セット・テーブルを一括交換
できる特定の搭載機にしか適用できないという問題があ
り、又、同一部品に対して表面実装中の部品リールと外
段取り中の部品リールの2つのリールが必要になるとい
う問題もある。
An advantage is that complete external setup is possible, but there is a problem that it can only be applied to a specific mounting machine that can replace parts feeder set tables all at once. There is also a problem that two reels, a component reel in the middle and a component reel in the outer setup, are required.

【0023】それに、製造数が極少の場合には外段取り
での部品交換が間に合わず、又、パーク・フィーダー・
セット・テーブルの交換による段取り替えのための生産
停止も無視できない。
In addition, when the number of parts manufactured is very small, parts cannot be replaced in the external setup in time, and the park feeder
Production stoppage due to setup change due to set / table exchange cannot be ignored.

【0024】そこで考え出されたのは、パーツ・フィー
ダー・セット・テーブルへ表面実装部品を固定的にセッ
トする方式である。
What has been devised is a method in which surface mount components are fixedly set on a parts feeder set table.

【0025】これは、使用頻度が高い表面実装部品をパ
ーツ・フィーダー・セット・テーブルに固定的にセット
し、その他の部品は複数のプリント配線板ユニットをま
とめてパーツ・フィーダー・セット・テーブルにセッ
ト、一括交換する方式で、外段取り時間は(固定的にセ
ットする表面実装部品以外の段取り替えを必要とする表
面実装部品の種類数)×2分÷(作業者数)となる。
In this method, frequently used surface mount components are fixedly set on a parts feeder set table, and other components are collectively set on a parts feeder set table with a plurality of printed wiring board units. The external setup time is (the number of types of surface mount components requiring setup change other than the surface mount components to be fixedly set) × 2 minutes ÷ (the number of workers).

【0026】長所は、表面実装部品の交換は固定的にセ
ットする表面実装部品を除いた表面実装部品だけになる
ので、表面実装部品のセット種類数が少なくなって、部
品準備時間を最小化することでロット生産の場合でも部
品準備を間に合わせようとするもので、特に、パーツ・
フィーダーをグループにしてセットする方式や、パーツ
・フィーダー・セット・テーブルを一括交換する方式と
組み合わせることによって、段取り替え時間を更に短縮
することができる。
An advantage is that the replacement of the surface-mounted components is limited to the surface-mounted components excluding the surface-mounted components to be fixedly set, so that the number of set types of the surface-mounted components is reduced and the component preparation time is minimized. Therefore, even in the case of lot production, we try to make preparations for parts in time.
By combining the method of setting the feeders in groups and the method of collectively replacing the parts feeder set table, the setup change time can be further reduced.

【0027】又、同一部品のリールが1つでよいという
利点もある。
Another advantage is that only one reel of the same part is required.

【0028】[0028]

【発明が解決しようとする課題】しかし、パーツ・フィ
ーダー・セット・テーブルへ表面実装部品を固定的にセ
ットする方式にも下記の欠点がある。
However, the system in which the surface mount components are fixedly set on the parts feeder set table has the following disadvantages.

【0029】第一の欠点は、段取り替え時間の極少化に
よる生産停止時間の短縮効果が上がる程度にパーツ・フ
ィーダーの搭載機への固定的なセットを実現するために
は、搭載機の台数を通常の3倍から5倍程度に増やす必
要があるという点である。
The first drawback is that, in order to achieve a fixed set of parts feeders on a mounting machine to the extent that the effect of shortening the production stoppage time by minimizing the setup change time is increased, the number of mounting machines must be reduced. The point is that it is necessary to increase it from about three times to about five times.

【0030】第二の欠点は、固定的にセットする表面実
装部品の最適種類数を客観的又は論理的に決定できない
ことである。
A second drawback is that the optimal number of types of fixedly mounted surface mount components cannot be determined objectively or logically.

【0031】第三の欠点は、部品を固定にセットするた
め複数の搭載機間で搭載時間のバランスをとり難いとい
う点である。
A third disadvantage is that it is difficult to balance the mounting time among a plurality of mounting machines because the parts are set fixedly.

【0032】本発明は、かかる問題点に鑑み、多種少量
生産体制下で表面実装部品をプリント配線板上に搭載し
て半田付けする表面実装工程において、表面実装部品の
段取り替えによる生産停止を極少化することが可能な製
造管理システムを提供することを目的とする。
In view of the above problems, the present invention minimizes production stoppage due to changeover of surface mount components in a surface mounting process of mounting and soldering surface mount components on a printed wiring board under a variety of small production systems. It is an object of the present invention to provide a manufacturing management system that can be made into a computer.

【0033】[0033]

【課題を解決するための手段】まず第一の欠点に対して
は、製造計画を参照して今後製造する製品に適用される
表面実装部品の使用頻度を算出し、最も効果的な表面実
装部品を固定的にセットする部品に決定するという手段
を講ずる。
For the first disadvantage, the frequency of use of surface mount components applied to products to be manufactured in the future is calculated with reference to a manufacturing plan, and the most effective surface mount components are calculated. Means to determine the parts to be fixedly set.

【0034】上記手段により、最も効果的な表面実装部
品を選択して固定的にセットする部品に決定するので、
搭載機の台数を大幅に増やさなくても部品準備作業を短
縮することができる。
By the above means, the most effective surface mount component is selected and determined as a component to be fixedly set.
The component preparation work can be shortened without significantly increasing the number of mounted machines.

【0035】第二の欠点に対しては、部品情報と搭載機
情報をデータベース化し、固定セット部品と段取り部品
の比率に整合して固定セット部品の種類数とセット位置
を決定する手段である。
As for the second disadvantage, there is a means for converting the component information and the mounting machine information into a database and determining the number of types and the set positions of the fixed set components in accordance with the ratio of the fixed set components to the setup components.

【0036】上記手段により、固定セット部品と段取り
部品の比率に整合して固定セット部品の種類数とセット
位置を決定することができるので、固定的にセットする
表面実装部品の最適種類数を客観的に決定することがで
きる。
According to the above-mentioned means, the number of types and the set positions of the fixed set components can be determined in accordance with the ratio between the fixed set components and the setup components. Therefore, the optimal number of the surface mount components to be fixedly set is objectively determined. Can be determined.

【0037】第三の欠点に対しては、固定的にセットす
る表面実装部品を、複数の搭載機間で搭載時間のバラン
スをとって配置する手段である。
As a third disadvantage, there is a means for arranging the surface mounting components to be fixedly set in such a manner that the mounting time is balanced among a plurality of mounting machines.

【0038】上記手段により、固定的にセットする表面
実装部品を、複数の搭載機間で搭載時間のバランスをと
って配置することが可能になる。
According to the above-mentioned means, it becomes possible to arrange the surface mounting components to be fixedly set in a plurality of mounting machines with the mounting time being balanced.

【0039】更に、製品の製造数の分布に合わせて、搭
載機への部品振り分けを特定のプリント配線板を優先し
て行なうか、或る生産計画で使用される全部の部品の使
用数の多い順に振り分けるかを選択する手段、出現頻度
が高い部品を複数の搭載機に重複して振り分け、その部
品を搭載する搭載機の搭載時間のバランスがとれるよう
に選択する手段、段取り部品を製品の搭載完了情報や製
造スケジュールに合わせて動的にセットする手段を講ず
ることにより、表面実装部品供給の段取り替えによる生
産停止を極少化することが可能な製造管理システムを実
現することができる。
Furthermore, in accordance with the distribution of the number of manufactured products, parts are distributed to the mounting machine by giving priority to a specific printed wiring board, or all parts used in a certain production plan are frequently used. A means to select whether to sort in order, a means to assign frequently appearing parts to multiple mounting machines redundantly, and a means to select so that the mounting time of the mounting machine to mount the parts is balanced, and to mount the setup parts to the product By adopting a means for dynamically setting according to the completion information or the manufacturing schedule, it is possible to realize a manufacturing management system capable of minimizing the production stoppage due to the change of the surface mount component supply setup.

【0040】[0040]

【発明の実施の形態】以降、本発明の技術を図面を参照
しながら詳細に説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the technology of the present invention will be described in detail with reference to the drawings.

【0041】図1は、本発明の第一の実施の形態の機能
ブロック図である。
FIG. 1 is a functional block diagram of the first embodiment of the present invention.

【0042】図1において、1は、製造管理システム全
体を制御する中央処理ユニット(図では「CPU」と略
記している。これは「Central Proccesser Unit 」の頭
文字をとった略語である。)、2は、固定セット部品を
合理的に決定する固定セット部品決定手段、3は、固定
セット部品決定手段2によって固定セット部品に決定さ
れた部品を搭載機に合理的に振り分ける固定セット部品
振り分け手段、4は、固定セット部品以外の部品、即
ち、段取り部品の搭載機へのセット位置を合理的に決定
する段取り部品セット位置決定手段、5は、どの部品を
どのパーツ・フィーダーから取ってきてどこに実装する
かを決定する数値制御データ作成手段(図では「NCデ
ータ作成手段」と略記している。「NC」は、「Numeri
cal Control (数値制御)」の頭文字をとった略語であ
る。)、6は、表面実装部品をプリント配線ユニットに
実装するラインを制御する表面実装ライン制御手段であ
る。
In FIG. 1, reference numeral 1 denotes a central processing unit (abbreviated as “CPU” in the figure, which is an abbreviation of “Central Proccesser Unit”) for controlling the entire manufacturing management system. Reference numeral 2 denotes fixed set component determining means for rationally determining fixed set components. Reference numeral 3 denotes fixed set component distribution means for rationally distributing the components determined as fixed set components by the fixed set component determining means 2 to the mounting machine. Reference numeral 4 denotes a part other than the fixed set parts, that is, a set-up part set position determining means for rationally determining the set position of the set-up parts on the mounting machine. Numerical control data creation means for deciding whether or not to implement (in the figure, abbreviated as “NC data creation means”. “NC” means “Numeri
cal Control (numerical control). ) And 6 are surface mounting line control means for controlling a line for mounting the surface mounting components on the printed wiring unit.

【0043】7は、プリント配線ユニットをラインに供
給するローダー、8は、順番に供給されるプリント配線
ユニットに半田ペーストを印刷する半田印刷機、9は、
プリント配線ユニットに接着剤を塗布する接着剤塗布
機、10乃至12は、半田ペースト上又は接着剤の上に
表面実装部品を搭載する部品搭載機、13はリフロー・
ソルダリングによって表面実装部品をプリント配線ユニ
ットに半田付けするリヤロー炉で、ローダー7以降リフ
ロー炉13によって表面実装ラインが構成される。
7 is a loader for supplying a printed wiring unit to a line, 8 is a solder printing machine for printing a solder paste on the sequentially supplied printed wiring units, and 9 is a solder printing machine.
An adhesive applicator for applying an adhesive to the printed wiring unit is a component mounting machine for mounting a surface mount component on a solder paste or an adhesive, and 13 is a reflow machine.
A rear row furnace for soldering the surface mount components to the printed wiring unit by soldering, and a surface mount line is configured by the reflow furnace 13 after the loader 7.

【0044】又、14は、電子計算機による設計情報
(図では「CAD情報」と略記している。「CAD」は
「Computer Aided Design 」の頭文字による略語であ
る。以降、本明細書では一貫してCADを用いることに
する。)、15は、所定時期の生産計画、16は、段取
り部品の情報である段取り部品選択表、17は、全体の
表面実装部品の情報(これを「部品情報」と標記す
る。)、18は、部品搭載機10乃至12の情報(これ
を「搭載機情報」と標記する。)、19は、ラインの稼
働条件(これを「ライン稼働条件」と標記する。)、2
0は、搭載機にセットする全ての表面実装部品のセット
位置情報(これを「部品セット・リスト」と標記す
る。)である。
Numeral 14 denotes design information by a computer (abbreviated as "CAD information" in the figure. "CAD" is an abbreviation of "Computer Aided Design". 15 is a production plan at a predetermined time, 16 is a setup component selection table which is information of setup components, and 17 is information of the entire surface mount component (this is referred to as “component information”). ), 18 is information of the component mounting machines 10 to 12 (this is referred to as “mounting machine information”), and 19 is a line operating condition (this is referred to as “line operating condition”). .), 2
0 is set position information of all the surface mount components to be set on the mounting machine (this is referred to as a “component set list”).

【0045】そして、固定セット部品決定手段2は、C
AD情報14、生産計画15、段取り部品選択表16、
部品情報17、搭載機情報18及びライン稼働条件19
を利用して固定セット部品を決定する。
Then, the fixed set part determining means 2
AD information 14, production plan 15, setup part selection table 16,
Component information 17, mounting machine information 18, and line operating conditions 19
Is used to determine fixed set parts.

【0046】又、固定セット部品振り分け手段3及び段
取り部品セット位置決定手段4は、部品情報17及び搭
載機情報18を利用して固定セット部品の振り分け及び
段取り部品のセット位置を決定し、搭載機別部品セット
・リストを作成する。
The fixed set component distribution means 3 and the setup component set position determination means 4 use the component information 17 and the placement machine information 18 to determine the distribution of fixed set components and the set position of the setup component, and Create a separate parts set list.

【0047】又、数値制御データ作成手段5は、CAD
情報14、生産計画15、段取り部品選択表16、部品
情報17及び固定セット部品振り分け手段3及び段取り
部品セット位置決定手段4で決定された部品セット位置
情報を利用して数値制御データを作成する。
Further, the numerical control data creating means 5 has a CAD
Numerical control data is created using the information 14, the production plan 15, the set-up part selection table 16, the part information 17, and the part set position information determined by the fixed set part allocating means 3 and the set-up part set position determining means 4.

【0048】最後に、表面実装ライン制御手段6は、数
値制御データを利用して表面実装ラインの制御を行な
う。
Finally, the surface mounting line control means 6 controls the surface mounting line using the numerical control data.

【0049】尚、図1において、中太の実線はバスを表
わし、細い実線の矢印は情報の流れを表わし、太い実線
は製造の流れを表わしている。
In FIG. 1, a solid solid line represents a bus, a thin solid arrow represents an information flow, and a thick solid line represents a manufacturing flow.

【0050】本発明の第一の実施の形態においては、ま
ず、固定セット部品決定手段によって固定セット部品の
最適種類数と固定セット部品自体の決定を行ない、次い
で、固定セット部品振り分け手段によって固定セット部
品の搭載機への振り分けを行ない、続いて、段取り部品
セット位置決定手段によって段取り部品の搭載機への振
り分け及びセット位置の決定を行なう。その後、数値制
御データ作成手段によって数値制御データと部品セット
・リストを作成し、最終的に製造に移る。
In the first embodiment of the present invention, first, the optimum set number of fixed set components and the fixed set components themselves are determined by the fixed set component determination means, and then the fixed set components are allocated by the fixed set component distribution means. The parts are distributed to the mounting machines, and subsequently, the set-up parts setting position determining means allocates the prepared parts to the mounting machines and determines the set positions. After that, the numerical control data and the part set list are created by the numerical control data creating means, and finally the production is started.

【0051】以降、本発明の特徴である固定セット部品
決定手段2、固定セット部品振り分け手段3及び段取り
部品セット位置決定手段を中心に、数値制御データ作成
手段及び製造プロセスも含めて説明を進めてゆく。
Hereinafter, the description will proceed focusing on the fixed set component determining means 2, the fixed set component allocating means 3, and the setup component set position determining means, which are features of the present invention, including the numerical control data creating means and the manufacturing process. go.

【0052】図2は、図1の固定セット部品決定手段2
における固定セット部品決定のフローチャートで、固定
セット部品の決定に必要な情報も併せて図示している。
FIG. 2 shows the fixed set part determining means 2 of FIG.
In the flowchart for determining the fixed set part, the information necessary for determining the fixed set part is also shown.

【0053】ここで、中太の実線の矢印は処理の流れを
表わし、細い実線の矢印は情報の流れを表わしている。
Here, solid thick arrows indicate the flow of processing, and thin solid arrows indicate the flow of information.

【0054】又、図3は、CAD情報の例、図4は、部
品情報の例、図5は、搭載機情報の例、図6は、図5の
搭載機情報に対応する表面実装ラインの部品搭載機の配
列例、図7は、段取り部品選択表の例、図8は、生産計
画の例、図9は、ライン稼働条件の例で、図1のフロー
チャートを説明する際の参考資料として図示している。
FIG. 3 shows an example of CAD information, FIG. 4 shows an example of component information, FIG. 5 shows an example of mounting machine information, and FIG. 6 shows a surface mounting line corresponding to the mounting machine information of FIG. FIG. 7 is an example of a set-up component selection table, FIG. 8 is an example of a production plan, and FIG. 9 is an example of a line operating condition, which is used as a reference when explaining the flowchart of FIG. It is illustrated.

【0055】以降、図2の符号に沿って固定セット部品
決定の手順を詳細に説明するが、具体的な説明に入る前
にCAD情報、部品情報、搭載機情報、部品搭載機の配
列、段取り部品選択表、生産計画及びライン稼働条件の
例について概説しておく。
Hereinafter, the procedure for determining the fixed set components will be described in detail along the reference numerals in FIG. 2. Before entering a specific description, CAD information, component information, mounting machine information, arrangement of component mounting machines, setup An example of a parts selection table, a production plan, and line operating conditions will be outlined.

【0056】まず、CAD情報は製品図番毎にまとめら
れている。内、項番は部品番号に対応して振られるが、
プリント配線ユニットへの部品実装位置の基準となる2
つの基準マークも部品として扱われて最初に現れる。そ
して、項番毎に部品名称を表わす部品記号、搭載位置の
X座標とY座標、搭載の向きを示す角度(図では「θ」
と標記している。)、部品の図番、当該部品を実装する
プリント配線ユニットの面(図では「搭載面」と標記し
ている。)を表わす数1又は2、及び、ブロック番号が
記載されている。
First, CAD information is organized for each product drawing number. Of which, item numbers are assigned corresponding to part numbers,
2 which is the reference of the component mounting position on the printed wiring unit
Two fiducial marks also appear as parts and appear first. Then, a component symbol representing a component name for each item number, an X coordinate and a Y coordinate of a mounting position, and an angle indicating a mounting direction (“θ” in the figure)
It is labeled. ), The drawing number of the component, the number 1 or 2 representing the surface of the printed wiring unit on which the component is mounted (indicated as “mounting surface” in the figure), and the block number.

【0057】次に、部品情報は、部品図番毎に部品形状
コード、部品がどのような容器で供給されるかを示す荷
姿、部品の形状やパッケージを示す部品タイプ、部品を
通常の空気中に放置できる許容限界時間を示す湿度ラン
ク、カートリッジ・タイプ、(途中略)、搭載時間及び
段取り時間が記載されている。
Next, the part information includes a part shape code for each part drawing number, a packing style indicating what kind of container the part is supplied in, a part type indicating the shape and package of the part, and a normal air state for the part. A humidity rank indicating a permissible limit time that can be left inside, a cartridge type, (omitted halfway), a mounting time, and a setup time are described.

【0058】次に、搭載機情報は、表面実装らラインを
構成する搭載機の部品セット部(図では「セット部」と
略記している。)毎に、リールをセット可能なチャネル
数(図では「CH」と略記している。これは「CHANNEL
」の頭2文字を使った略語である。尚、以降も図では
「CH」と標記する。)及びトレイをセット可能なチャ
ネル数を記載している。この場合、どの搭載機も2つの
部品セット部を持っているものとしている。
Next, the mounting machine information indicates the number of channels on which reels can be set for each component setting section (abbreviated as "set section" in the figure) of the mounting machine forming the surface mounting line. Is abbreviated as “CH.” This is called “CHANNEL
"Is an abbreviation using the first two letters. In the following, "CH" is also indicated in the figure. ) And the number of channels in which trays can be set. In this case, it is assumed that each mounting machine has two component setting units.

【0059】上記搭載機情報に対応する表面実装ライン
の部品搭載機の配列を図6に示している。
FIG. 6 shows the arrangement of component mounting machines on the surface mounting line corresponding to the mounting machine information.

【0060】次に、段取り部品選択表は、段取り替えを
行なう部品の属性を表す。ここに示す属性のいずれかを
持つ部品は、段取り部品と判断される。
Next, the setup part selection table indicates the attributes of the parts whose setup is to be changed. Components having any of the attributes shown here are determined as setup components.

【0061】次に、生産計画は、製品であるプリント配
線ユニットの図番(製品図番)毎に製造番号、製造数、
部品を製造現場に供給する予定日(出材予定日)及び当
該製品の完成予定日を記載している。
Next, the production plan includes a production number, a production number, and a production number for each drawing number (product drawing number) of a printed wiring unit as a product.
The scheduled date for supplying parts to the manufacturing site (scheduled release date) and the scheduled completion date of the product are described.

【0062】最後に、ライン稼働条件は、グルーピング
する製品数(グルーピング製品数)、段取り作業者数、
部品搭載におけるアンバランス率、複数の部品搭載機へ
の部品の振り分けを基板優先にするか基板平均を優先に
するかの振り分け手法、及び、例えば2交替などの勤務
態様を記載している。
Finally, the line operation conditions include the number of products to be grouped (the number of grouped products), the number of setup workers,
It describes an unbalance rate in component mounting, a method of allocating components to a plurality of component mounting machines by giving priority to a board or averaging a board, and a work mode such as two shifts.

【0063】では、固定セット部品の決定手段の処理に
ついて詳述する。
Now, the processing of the fixed set part determining means will be described in detail.

【0064】S1.生産計画対応使用部品一覧を作成す
る。
S1. Create a list of parts used for production planning.

【0065】最初の処理は、図8の生産計画と図3のC
AD情報とから所定期間内の生産計画にある製品を製造
する際に使用する部品を全てリスト・アップし、それら
の出現回数と使用数を算出する。
The first process consists of the production plan shown in FIG.
From the AD information, all parts used when manufacturing a product in a production plan within a predetermined period are listed up, and the number of appearances and the number of use are calculated.

【0066】次いで、リスト・アップした部品の部品図
番をキーにして図4の部品情報に記載されている部品の
属性情報、即ち、部品形状コード、荷姿、占有チャネル
数、部品タイプ、湿度ランク、カートリッジ・タイプ及
びリード・ピッチを付加する。
Next, the attribute information of the component described in the component information of FIG. 4, that is, the component shape code, the packing style, the number of occupied channels, the component type, and the humidity, using the component drawing number of the listed component as a key. Add rank, cartridge type and lead pitch.

【0067】次いで、リスト・アップした部品を下記の
順位でソーティングする。
Next, the listed parts are sorted in the following order.

【0068】(1)図7の段取り部品選択表に記載され
ている部品属性を持つ部品は固定セットできない部品で
あるので、リスト・アップした部品の後尾に移動する。
(1) Since the parts having the part attributes described in the setup part selection table of FIG. 7 cannot be fixedly set, they are moved to the end of the listed parts.

【0069】(2)上記部品以外の部品について出現回
数が多い順にソーティングする。
(2) Parts other than the above parts are sorted in descending order of appearance frequency.

【0070】上記ソーティングの結果、まず段取り部品
以外の部品が出現回数順に並び、その後に段取り部品が
並ぶことになる。
As a result of the above sorting, first, components other than the set-up components are arranged in the order of appearance frequency, and thereafter, the set-up components are arranged.

【0071】次いで、下記の計算をして生産計画対応使
用部品一覧の列を埋めてゆく。
Next, the following calculation is performed to fill in the columns of the used parts list corresponding to the production plan.

【0072】(3)部品全体の出現回数に対する個々の
部品の出現回数の割合(出現比率:%)を算出し、更
に、上位から順に出現回数の割合の累積(累積出現比
率:%)を算出する。
(3) Calculate the ratio of the number of appearances of each part to the number of appearances of the entire part (appearance ratio:%), and further calculate the accumulation of the ratio of the number of appearances from the top (cumulative appearance ratio:%). I do.

【0073】(4)部品の使用数についても、使用比率
(%)と累積使用比率(%)を算出する。
(4) The usage ratio (%) and the cumulative usage ratio (%) are calculated for the number of parts used.

【0074】(5)上位から順に部品毎の占有チャネル
数の累積(累積チャネル数)を算出する。
(5) Calculate the cumulative number of the occupied channels (accumulated channel number) for each component in order from the top.

【0075】(6)部品毎に、(使用数)×(部品情報
中の部品単体の搭載時間)によって搭載時間を算出す
る。
(6) For each component, the mounting time is calculated by (number of used components) × (mounting time of a single component in the component information).

【0076】(7)部品毎に、(出現回数)×(部品情
報中の段取り時間)によって段取り時間を算出する。
(7) For each component, the setup time is calculated by (the number of appearances) × (the setup time in the component information).

【0077】上記の処理によって、図10の如く、搭載
機番号と部品セット位置(図では単に「セット位置」と
表意している。)を除いて、生産計画対応使用部品一覧
の列が埋められる。但し、図10においては、部品形
状、荷姿、部品タイプ、湿度ランク、パーツ・フィーダ
ー、リード・ピッチ、搭載時間及び段取り時間は詳細な
記載を省略している。
By the above-described processing, as shown in FIG. 10, the columns of the used parts list corresponding to the production plan are filled except for the mounting machine number and the part set position (in the figure, simply referred to as “set position”). . However, in FIG. 10, detailed descriptions of the component shape, packing style, component type, humidity rank, parts feeder, lead pitch, mounting time and setup time are omitted.

【0078】S2.図10の生産計画対応使用部品一覧
中の部品種数(項番に等しい)に対する累積出現比率と
累積使用比率を読み取って固定部品種数とその占有率の
グラフを作成する。
S2. The cumulative appearance ratio and the cumulative usage ratio with respect to the number of component types (equal to the item number) in the list of used components corresponding to the production plan in FIG. 10 are read, and a graph of the number of fixed component types and their occupancy is created.

【0079】これは、図10の項番100、200、3
00、・・・、1000における累積出現比率と累積使
用比率を読み取ってグラフ化すればよい。
This corresponds to item numbers 100, 200, 3 in FIG.
The cumulative appearance ratio and the cumulative use ratio at 00,..., 1000 may be read and graphed.

【0080】例えば、固定部品種数を400種とすれ
ば、生産計画対応使用部品一覧より累積出現比率は73
%、累積使用比率は85%である。
For example, if the number of types of fixed parts is 400, the cumulative appearance ratio is 73 from the list of used parts corresponding to the production plan.
% And the cumulative usage ratio is 85%.

【0081】S3.製品のプリント配線ユニット1枚当
たりの部品数、部品種数、占有チャネル数、製造枚数、
搭載時間及び段取り時間を求める。
S3. The number of parts, the number of parts, the number of occupied channels, the number of products,
Find the mounting time and setup time.

【0082】これは、図8の生産計画と、図3の製品図
番毎のCAD情報を組み併せることによって求めること
ができる。
This can be obtained by combining the production plan shown in FIG. 8 and the CAD information for each product drawing number shown in FIG.

【0083】ステップS1乃至ステップS3が固定部品
決定及び段取り部品最適振り分けの準備処理である。
Steps S1 to S3 are the preparation processing for determining the fixed parts and optimizing the arrangement of the set-up parts.

【0084】S4.図5の搭載機情報に対応させて、搭
載機番号と部品セット・チャネル数の単位で固定セット
部品と段取り部品のチャネル数の組み合わせを作る。
S4. A combination of the number of channels of the fixed set component and the number of setup components is made in units of the mounting machine number and the number of component sets / channels in correspondence with the mounting machine information of FIG.

【0085】この場合、図5の搭載機情報よりリール・
チャネル数は最大800チャネルであるので、固定セッ
ト部品のチャネル数が800チャネルの時には段取り部
品チャネル数は0となり、固定セット部品チャネル数が
0の時には段取り部品チャネル数は800チャネルにな
る。これを、固定セット部品/段取り部品振り分け表の
1行目及び2行目に記載する。
In this case, the reel information is obtained from the mounting machine information shown in FIG.
Since the maximum number of channels is 800, the number of setup component channels is 0 when the number of fixed set component channels is 800, and the number of setup component channels is 800 when the number of fixed set component channels is 0. This is described in the first and second rows of the fixed set component / setup component distribution table.

【0086】S5.上記固定セット部品チャネル数及び
段取り部品チャネル数を、図11の生産計画別基板平均
の占有チャネル数で除算し、それぞれのチャネル数を部
品種数に変換する。
S5. The number of fixed set component channels and the number of setup component channels are divided by the average number of occupied channels for each production plan in FIG. 11, and each channel number is converted into the number of component types.

【0087】この場合、図11の生産計画別基板平均の
占有チャネル数は1.5チャネル/部品である。この除
算結果を固定セット部品/段取り部品振り分け表の3行
目及び4行目に記載する。
In this case, the average number of occupied channels per board in each production plan in FIG. 11 is 1.5 channels / part. The result of the division is described in the third and fourth rows of the fixed set component / setup component distribution table.

【0088】S6.固定セット部品/段取り部品振り分
け表の3行目の固定セット部品種数の場合の、全体部品
種数に対する占有率をグラフ1の累積出現比率から求め
る。
S6. The occupancy rate for the total number of component types in the case of the number of fixed set component types in the third row of the fixed set component / setup component distribution table is determined from the cumulative appearance ratio in graph 1.

【0089】例えば、固定セット部品/段取り部品振り
分け表の3行目で固定セット部品種数が400の時に
は、固定セット部品占有率は73%である。このように
求めた固定セット部品占有率を固定セット部品/段取り
部品振り分け表の5行目に記載する。
For example, when the number of fixed set component types is 400 in the third row of the fixed set component / setup component distribution table, the fixed set component occupancy is 73%. The fixed set component occupancy thus obtained is described in the fifth row of the fixed set component / setup component distribution table.

【0090】又、(図11の生産計画別基板平均の使用
部品種数)×(1−(全体部品種に対する占有率))は
(段取りする部品種数)/(製品)である。
Further, (the number of parts used on the average of the boards by the production plan in FIG. 11) × (1− (the occupation ratio with respect to the whole parts)) is (the number of parts to be set up) / (product).

【0091】例えば、固定セット部品占有率が73%の
時には、400×(1−0.73)=10.8が段取り
部品種数/製品である。このように求めた値を固定セッ
ト部品/段取り部品振り分け表の6行目に記載する。
For example, when the fixed set component occupancy is 73%, 400 × (1−0.73) = 10.8 is the number of setup component types / product. The values thus determined are described in the sixth row of the fixed set component / setup component distribution table.

【0092】S7.固定セット部品/段取り部品振り分
け表の6行目の値で固定セット部品/段取り部品振り分
け表の4行目の段取りセット可能部品種数を除算すれ
ば、同時に何種類の部品を段取り部品セット部にセット
できるかを示すグループ・セット可能製品数が求められ
る。
S7. By dividing the number of parts that can be set up and set up in the fourth row of the fixed set parts / setup parts distribution table by the value of the sixth row of the fixed set parts / setup parts distribution table, how many parts can be simultaneously placed in the setup part set section The number of products that can be set in a group that indicates whether they can be set is determined.

【0093】例えば、固定セット部品チャネル数が70
0の場合、段取りセット可能部品種数が66.7で、段
取り部品種数/製品が9.6であるので、グループ・セ
ット可能製品数は7.0である。このようにして求めた
値を固定セット部品/段取り部品振り分け表の7行目に
記載する。
For example, if the number of fixed set component channels is 70
In the case of 0, the number of settable parts is 66.7 and the number of settable parts / product is 9.6, so the number of group settable products is 7.0. The value thus determined is described in the seventh row of the fixed set component / setup component distribution table.

【0094】S8.グループ・セット基板の連続稼働時
間を下記により求める。
S8. The continuous operation time of the group / set board is obtained as follows.

【0095】即ち、(平均搭載時間/搭載機台数)×
(搭載機アンバランス率)×(平均製造枚数)×(グル
ープ・セット可能製品数)によって求める。例えば、固
定セット部品チャネル数が700の時、平均搭載時間は
3.05分、搭載機台数は4台、搭載機アンバランス率
は2倍、平均製造枚数は6.7枚、グループ・セット可
能製品数は7.0であるから、グループ・セット基板の
連続稼働時間は1.2時間となる。このようにして求め
た値を固定セット部品/段取り部品振り分け表の8行目
に記載する。
That is, (average mounting time / number of mounted machines) ×
It is calculated by (loading machine unbalance rate) x (average number of products manufactured) x (number of products that can be set in a group). For example, when the number of fixed set component channels is 700, the average mounting time is 3.05 minutes, the number of mounted machines is 4, the unbalance rate of mounted machines is double, the average number of manufactured is 6.7, and group setting is possible. Since the number of products is 7.0, the continuous operation time of the group / set board is 1.2 hours. The value thus determined is described in the eighth row of the fixed set component / setup component distribution table.

【0096】S9.同様に、段取り時間を下記によって
計算する。
S9. Similarly, the setup time is calculated by the following.

【0097】即ち、(固定セット部品/段取り部品振り
分け表4行目の段取りセット可能部品種数)×(平均段
取り時間)/作業者数)によって算出する。例えば、固
定セット部品チャネル数が700の時、段取りセット可
能部品種数が66.7、平均段取り時間が2分であるの
で、作業者数2人とすると段取り時間は1.1時間とな
る。このようにして求めた値を固定セット部品/段取り
部品振り分け表の9行目に記載する。
In other words, it is calculated by (fixed set parts / set-up part distribution table, the number of kinds of parts that can be set-up in the fourth row) × (average setup time) / number of workers. For example, when the number of fixed set component channels is 700, the number of parts that can be set up and set is 66.7, and the average setup time is 2 minutes. Therefore, when the number of workers is two, the setup time is 1.1 hours. The value thus determined is described in the ninth row of the fixed set component / setup component distribution table.

【0098】上記の如くして、ステップS4乃至ステッ
プS9によって固定セット部品/段取り部品振り分け表
が完成される。そして、次のチェック・ルーチンによっ
て固定セット部品のチャネル数と段取り部品のチャネル
数を決定する。
As described above, the fixed set component / setup component distribution table is completed through steps S4 to S9. Then, the number of channels of the fixed set component and the number of channels of the setup component are determined by the following check routine.

【0099】S10.連続稼働時間と段取り時間の差が
最大の所を選択する。
S10. Select the place where the difference between continuous operation time and setup time is the largest.

【0100】この場合、固定セット部品チャネル数が7
00の時に、連続稼働時間が1.2時間で段取り時間が
1.1時間となり、差が最大になる。
In this case, the number of fixed set component channels is 7
At 00, the continuous operation time is 1.2 hours and the setup time is 1.1 hours, and the difference is maximum.

【0101】ところで、図11の生産計画別基板平均よ
りグループ・セット図番数は5以上であることが求めら
れており、固定セット部品チャネル数が700の時に生
産計画中のいずれの製品も製造可能であることが必要で
ある。
By the way, the number of group / set figure numbers is required to be 5 or more from the average of the boards by production plan in FIG. 11, and when the number of fixed set component channels is 700, any product in the production plan is manufactured. It needs to be possible.

【0102】そこで、上記解が上記2つの条件を満たす
か否かを判定する。
Therefore, it is determined whether the above solution satisfies the above two conditions.

【0103】S11.グループ・セット可能な基板数が
5以上か否かを判定する。
S11. It is determined whether the number of boards that can be set in a group is 5 or more.

【0104】S12.ステップS11で、グループ・セ
ット可能な基板数が5未満の場合(No)には、段取り
部品セット箇所を1箇所増やして、ステップS11の検
証を再度行なう。
S12. If the number of boards that can be set in a group is less than 5 in step S11 (No), the number of set-up component setting locations is increased by one, and the verification in step S11 is performed again.

【0105】S13.ステップS11で、グループ・セ
ット可能な基板数が5以上の場合(Yes)には、どの
基板の段取り部品もセット可能か否かを判定する。
S13. In step S11, if the number of boards that can be set in the group is 5 or more (Yes), it is determined whether or not the setup components of any boards can be set.

【0106】いずれかのプリント配線板において、段取
り部品セット・チャネル数が不足して全ての段取り部品
をセットすることができない場合(No)には、ステッ
プS12で段取り部品セット箇所を1箇所増やして、ス
テップS11及びステップS13の検証を再度行なう。
If the number of set-up parts and the number of channels are insufficient to set all the set-up parts on any of the printed wiring boards (No), the set-up part set location is increased by one in step S12. , The verification in steps S11 and S13 is performed again.

【0107】ステップS13で、いずれのプリント配線
板の段取り部品をセットすることができる場合(Ye
s)には、固定セット部品が決定され、処理を終了す
る。
In step S13, if any of the setup parts of the printed wiring board can be set (Ye
In s), the fixed set component is determined, and the process ends.

【0108】今の場合、グループ・セット可能製品数は
7であるからステップS11からステップS13に進む
ことができる。そして、ステップS13で全ての基板の
段取り部品が100箇所の段取り部品セット部にセット
可能と判断されれば処理が終了する。
In this case, since the number of products that can be set in a group is 7, the process can proceed from step S11 to step S13. Then, if it is determined in step S13 that the set-up parts of all the boards can be set in the set-up part setting units at 100 locations, the process ends.

【0109】次に、固定セット部品決定手段による処理
結果を踏まえて、固定セット部品をセットする搭載機へ
の振り分けとセット位置の決定を行なう。
Next, based on the processing result by the fixed set component determining means, the fixed set components are distributed to the mounting machines on which the fixed set components are set, and the setting positions are determined.

【0110】図13は、固定部品振り分け手段のフロー
チャートである。以降、図13の符号に沿って固定部品
振り分け手段の処理を説明する。
FIG. 13 is a flowchart of the fixed component distribution means. Hereinafter, the processing of the fixed component distribution unit will be described along the reference numerals in FIG.

【0111】S21.各搭載機の搭載時間を0にセット
した上で、最初に段取り部品全体の搭載時間を算出す
る。
S21. After setting the mounting time of each mounting machine to 0, the mounting time of the entire setup component is calculated first.

【0112】上記の如く、固定セット部品決定手段によ
って固定セット部品のチャネル数が700と決められた
ので、図10の生産計画対応使用部品一覧において、累
積チャネル数が700以降になる部品は段取り部品であ
る。従って、図10の生産計画対応使用部品一覧におい
て、累積チャネル数が700以降になる部品について搭
載時間の和を求めれば段取り部品の搭載時間が求められ
る。
As described above, the number of channels of the fixed set parts is determined to be 700 by the fixed set part determining means. In the list of used parts corresponding to the production plan in FIG. It is. Therefore, in the list of used parts corresponding to the production plan in FIG. 10, if the sum of the mounting times is obtained for the parts having the accumulated channel number of 700 or more, the mounting time of the setup parts is obtained.

【0113】S22.これを段取り部品搭載機の搭載時
間に加算する。
S22. This is added to the mounting time of the setup component mounting machine.

【0114】段取り部品搭載機の搭載時間の初期値が0
にセットされているので、これで段取り部品搭載機に搭
載時間がセットされたことになる。具体的には、上記の
如く段取り部品のチャネル数は100であり、段取り替
えによる生産停止が起こり難いのはラインにおいて後ろ
にある搭載機を段取り部品の搭載機にする場合であるの
で、搭載機No.4に段取り部品をセットすることにし
て、部品セット部はNo.8とする。
The initial value of the mounting time of the setup component mounting machine is 0.
, So the mounting time is now set on the setup component mounting machine. Specifically, as described above, the number of channels of the set-up parts is 100, and the production stoppage due to the setup change is unlikely to occur when the mounting machine located behind in the line is used as the mounter for the set-up parts. No. No. 4 is set to the setup part, and the part setting part is No. 4. 8 is assumed.

【0115】S23.図10の生産計画対応使用部品一
覧の1番目の部品を選択する。
S23. The first part in the list of used parts corresponding to the production plan in FIG. 10 is selected.

【0116】S24.選択した部品をセットするための
チャネルが空いている搭載機があるか否か判定する。
S24. It is determined whether or not there is a mounted machine having a vacant channel for setting the selected component.

【0117】この場合、搭載機No.4の部品セット部
No.8は段取り部品のセット部となっているので、判
定の対象になるのは搭載機No.1乃至搭載機No.3
と搭載機No.4の部品セット部No.7である。
In this case, the loading machine No. No. 4 part setting section No. 4 No. 8 is a set part of the set-up parts, so that the determination target is the mounting machine No. 8. No. 1 to No. Three
And installed machine No. No. 4 part setting section No. 4 7

【0118】S25.ステップS24で、選択した部品
をセットすることが可能な搭載機があると判定された場
合(Yes)には、上記搭載機の内で総搭載時間が最も
少ない搭載機を選択する。
S25. If it is determined in step S24 that there is a mounting machine on which the selected component can be set (Yes), the mounting machine with the shortest total mounting time is selected from the above mounting machines.

【0119】今の場合、固定セット部品の最初の部品を
選択した段階であるので、搭載機No.1乃至搭載機N
o.3のチャネルは空いており、又、搭載時間も0であ
る。従って、搭載機No.1乃至搭載機No.3のいず
れにも図10の生産計画対応使用部品一覧の1番目の部
品振り分けることが可能である。
In this case, since the first part of the fixed set part has been selected, the mounting machine No. 1 to N
o. The channel of No. 3 is empty, and the mounting time is 0. Therefore, the loading machine No. No. 1 to No. 3 can be assigned to the first part in the list of used parts corresponding to the production plan in FIG.

【0120】S26.当該部品をセットすることにした
搭載機に対して搭載時間と占有チャネル数を加算する。
S26. The mounting time and the number of occupied channels are added to the mounting machine on which the component is set.

【0121】S27.図10の生産計画対応使用部品一
覧の搭載機番号の欄に、当該部品をセットすることにし
た搭載機の番号を記入する。
S27. In the column of mounting machine number in the list of used parts corresponding to the production plan in FIG. 10, the number of the mounting machine for which the part is to be set is written.

【0122】S29.図10の生産計画対応使用部品一
覧の次の部品を選択してステップS24にジャンプし
て、選択された部品をセットできる搭載機がなくなるま
で、ステップS24乃至ステップS29を繰り返す。
S29. The next part in the list of used parts corresponding to the production plan shown in FIG. 10 is selected, and the process jumps to step S24. Steps S24 to S29 are repeated until there is no more mounting machine on which the selected part can be set.

【0123】尚、最初は段取り部品をセットされない搭
載機を中心に振り分けが行なわれるが、ステップS24
乃至ステップS29を繰り返すうちに段取り部品をセッ
トする搭載機No.4の部品セット部No.7にも固定
セット部品の振り分けがされるようになる。
At first, the sorting is performed mainly on the mounting machine on which the set-up parts are not set.
After the steps S29 to S29 are repeated, the mounting machine No. for setting up the set-up parts. No. 4 part setting section No. 4 7, the fixed set parts are also sorted.

【0124】S30.ステップS24で、選択された部
品をどの搭載機にもセットできないと判定された場合
(No)には、各搭載機にセットする部品は全て揃った
ことになる。これらの部品を前後の2つのセット部に、
部品数が同じになるように振り分け、セット位置を決め
る。
S30. If it is determined in step S24 that the selected component cannot be set on any of the mounting machines (No), it means that all the components to be set on each mounting machine are complete. Put these parts in the front and rear two sets,
Sort the parts so that they have the same number of parts and determine the set position.

【0125】S31.図10の生産計画対応使用部品一
覧の搭載機番号の欄に、当該部品をセットすることにし
たセット位置の番号を記入する。
S31. In the column of the mounting machine number in the list of used parts corresponding to the production plan in FIG. 10, the number of the set position at which the part is set is entered.

【0126】S32.そして、搭載機毎に固定部品の部
品セット表を作成して処理を終了する。
S32. Then, a component set table of the fixed components is created for each mounting machine, and the process is terminated.

【0127】これで、固定セット部品をセットする搭載
機とセット位置が決まる。この搭載機番号とセット位置
番号は製品のプリント配線ユニットに共通なものであ
る。
With this, the mounting machine on which the fixed set component is set and the setting position are determined. The mounting machine number and the set position number are common to the printed wiring unit of the product.

【0128】次いで、製品のプリント配線ユニット毎に
基板別使用部品一覧を作成してゆき、この中で段取り部
品をセットする搭載機とセット位置を決定してゆく。
Next, a list of parts to be used for each product is created for each printed wiring unit of the product, and a mounting machine on which set-up parts are set and a setting position are determined.

【0129】まず、生産計画にある基板のCAD情報と
部品情報とから生産順に基板別使用部品一覧を作成す
る。
First, a list of used components for each board is created in the order of production from CAD information and component information of boards in the production plan.

【0130】該基板別使用部品一覧のフォーマットは図
14の如くなり、最初に特定の製品図番のプリント配線
ユニットに使用される部品図番、使用数がCAD情報か
らコピーされ、次いで該部品図番をキーにして部品情報
から部品形状以降段取り時間までの部品属性がコピーさ
れ、最後に固定セット部品振り分け手段によって決定さ
れた固定セット部品に関する搭載機番号とセット位置番
号がコピーされる。
The format of the used parts list for each board is as shown in FIG. 14. First, the part drawing number and the number of parts used for the printed wiring unit of a specific product drawing number are copied from the CAD information. The component attributes from the component information to the setup time are copied from the component information using the number as a key, and finally, the mounting machine number and the set position number related to the fixed set component determined by the fixed set component distribution means are copied.

【0131】この状態では段取り部品に関する搭載機番
号とセット位置番号がブランクになっている。そこで、
搭載機番号とセット位置番号の欄がブランクの部品につ
いて搭載機番号とセット位置番号を決定してゆく。
In this state, the mounting machine number and the set position number relating to the setup parts are blank. Therefore,
The mounting machine number and the setting position number are determined for the blank parts in the columns of the mounting machine number and the setting position number.

【0132】上記の例では、段取り部品に振り分けられ
るチャネル数が100であり、搭載機No.4の部品セ
ット部No.8にセットすればよいことが判っているの
で、この場合にはセット位置だけを決定すればよい。
In the above example, the number of channels allocated to the setup components is 100, and No. 4 part setting section No. 4 Since it is known that the setting should be made to 8, in this case, only the setting position needs to be determined.

【0133】しかし、一般的には段取り部品をセットす
る搭載機が複数になることもある。この場合は、生産ラ
インの後ろの搭載機から順に段取り部品の搭載機とし
て、必要なチャネルを振り分ける。そして、どの段取り
部品をどの搭載機に振り分けるかは、固定セット部品振
り分け手段と同様な手順で振りわけてゆけば、段取り部
品に関する搭載機番号とセット位置番号を決めることが
できる。
However, in general, there may be a plurality of mounting machines on which set-up parts are set. In this case, the necessary channels are allocated as the mounting machines for the setup parts in order from the mounting machine behind the production line. Then, which set-up parts are to be assigned to which mounter can be determined by the same procedure as the fixed set part assigning means, so that the set-up part number and the set-up number for the set-up parts can be determined.

【0134】このようにして決められた段取り部品をセ
ットする搭載機番号とセット位置番号を図14の表に付
加すれば、特定図番のプリント配線ユニットについて基
板別使用部品一覧が完成されるので、以下、生産計画中
の次の生産順のプリント配線板ユニットについて同様に
段取り部品の搭載機番号とセット位置番号を決めてゆく
(上記の例では、搭載機番号は決まっているので、セッ
ト位置番号だけを決めればよい。)。
By adding the mounting machine number and the set position number for setting the set-up parts determined in this way to the table of FIG. 14, the list of used parts by board for the printed wiring unit of a specific figure number is completed. In the following, similarly, the mounting machine number and the set position number of the setup parts are determined for the printed wiring board units in the next production order in the production plan (in the above example, since the mounting machine number is fixed, the set position number is determined. You only need to decide on the number.)

【0135】この際、先に段取り部品の搭載機番号とセ
ット位置番号を決めたプリント配線ユニットに使用され
ている部品と同じ部品については、同じ搭載機番号とセ
ット位置番号に決めることにして、重複しての部品セッ
トを回避すると共に部品セット回数の削減を図る。
At this time, for the same parts as those used in the printed wiring unit for which the mounting machine number and the set position number of the set-up parts have been previously determined, the same mounting machine number and the set position number are determined. Avoid redundant component sets and reduce the number of component sets.

【0136】このようにして、段取り部品をセットする
搭載機の部品セット部が全て埋まる前まで段取り部品の
搭載機とセット位置を決めてゆけば、段取り部品をセッ
トする搭載機の部品セット部が全て埋まる前までのプリ
ント配線ユニットのグループ(これが1回の段取りで生
産できるプリント配線ユニットのグループである。)に
対する段取り部品の搭載機番号とセット位置番号を決め
ることができる。
In this way, if the placement machine and the setting position of the setup component are determined until all the component setting sections of the placement machine for setting the setup component are filled, the component setting section of the placement machine for setting the setup component is completed. It is possible to determine the machine number and set position number of the set-up parts for the group of printed wiring units before they are all filled (this is the group of printed wiring units that can be produced in one setup).

【0137】尚、上記では生産計画に上がっているプリ
ント配線ユニットだけを対象にした段取り部品のセット
位置決定の手順を記載したが、当然、当該期に生産が計
画されていない揶揄を含めて段取り部品のセット位置を
決定しておくことも可能である。
In the above description, the procedure for determining the set position of the set-up parts for only the printed wiring units included in the production plan has been described. It is also possible to determine the part setting position.

【0138】そして、固定セット部品振り分け手段の処
理によって完成されている固定セット部品のセット・リ
ストに加えて、段取り部品のセット・リストが完成され
るので、全ての部品のセット・リストが完成される。
The set list of the set-up parts is completed in addition to the set list of the fixed set parts completed by the processing of the fixed set part allocating means, so that the set list of all the parts is completed. You.

【0139】ここで、固定セット部品のセット・リスト
は生産計画に対応して決定されているので、当該生産計
画期間中は固定セット部品のセット・リストは変更され
ないが、段取り部品のセット・リストは1回の段取りに
対応して生産投入されるプリント配線ユニットの全てが
製造完了する度に変更され、単一の固定セット部品のセ
ット・リストと組み合わせて生産が継続される。
Since the set list of the fixed set parts is determined according to the production plan, the set list of the fixed set parts is not changed during the production plan period, but the set list of the setup parts is not changed. Is changed each time all of the printed wiring units produced and supplied in response to one setup are completed, and the production is continued in combination with a single fixed set component set list.

【0140】ここまでが、本発明の特徴である固定セッ
ト部品種の決定と固定セット部品及び段取り部品の振り
分けの技術である。
Up to this point, the technique of determining the fixed set component type and distributing the fixed set component and the setup component, which are the features of the present invention, have been described.

【0141】以降暫くは、固定セット部品種の決定と固
定セット部品及び段取り部品の振り分けに続く数値制御
データの作成と、生産の手順を説明する。
For a while, the procedure of the determination of the fixed set component type, the distribution of the fixed set components and the setup components, the creation of numerical control data, and the production procedure will be described.

【0142】まず数値制御データの作成の手順は次の通
りである。
First, the procedure for creating the numerical control data is as follows.

【0143】まず、CAD情報において部品図番毎に搭
載面を分割する(図3のCAD情報では、既に搭載面を
分割したものを示している。)。
First, the mounting surface is divided for each part drawing number in the CAD information (the mounting information is already divided in the CAD information of FIG. 3).

【0144】上記情報に、部品図番をキーにして固定セ
ット部品振り分け手段及び段取り部品振り分け手段によ
って決定された、固定セット部品と段取り部品の搭載機
番号とセット位置番号をコピーする。
The mounting machine number and the set position number of the fixed set parts and the set-up parts determined by the fixed set part allocating means and the set-up part allocating means are copied to the information by using the part drawing number as a key.

【0145】次いで、搭載機番号別にCAD情報を分割
する。即ち、図3のCAD情報の製品図番、版数の後に
搭載機番号を付して該CAD情報を分割し、部品情報の
部品属性を付加して、搭載機毎の数値制御データに変換
する。該変換の技術は広く適用されている、CAD情報
とCAM情報(ここで「CAM」は「Computer AidedMa
nufacturing 」の頭文字を取った略語で、電子計算機制
御による生産を意味する。)の変換技術であるので、詳
述は省略する。
Next, the CAD information is divided for each mounting machine number. That is, the CAD information is divided by adding the mounting machine number after the product drawing number and the version number of the CAD information in FIG. 3, and the component information of the component information is added to convert the CAD information into numerical control data for each mounting machine. . The conversion technique is widely applied to CAD information and CAM information (where “CAM” is “Computer Aided Ma
Abbreviation for "nufacturing," meaning production under computer control. ), The detailed description is omitted.

【0146】最後に、半田印刷機及び接着材塗布機につ
いても通常の技術によって数値制御データを作成し、生
産ライン全体の数値制御データを完成する。
Finally, numerical control data is created for the solder printing machine and the adhesive coating machine by the usual technique, and the numerical control data for the entire production line is completed.

【0147】これで、生産を開始するための情報が全て
揃ったので、下記の手順で生産を行なう。
Now that all the information for starting production has been prepared, production is performed in the following procedure.

【0148】まず、固定セット部品セット・リストに従
って各搭載機に固定セット部品をセットする。
First, fixed set parts are set in each mounting machine according to the fixed set part set list.

【0149】次いで、最初の製品グループの段取り部品
セット・リストに従って段取り部品を収集、一括交換台
車(パーツ・フィーダー・セット・テーブル)上にセッ
トして搭載機にセットする。
Next, the set-up parts are collected according to the set-up part set list of the first product group, set on a collective exchange trolley (parts feeder set table) and set on the mounting machine.

【0150】次いで、生産するプリント配線板をラック
に入れて、表面実装ラインの先頭設備であるローダーに
投入する。
Next, the printed wiring board to be produced is put in a rack, and put into a loader which is the leading equipment of the surface mounting line.

【0151】プリント配線板がラインを流れてゆく間に
プリント配線板に付与されたIDを各設備が読み取るこ
とにより、自動的にコンベアの幅替え、数値制御データ
の変更を行なって、半田ペースト印刷、固定セット部品
搭載、段取り部品搭載、リフロー半田付けを行なってゆ
く。
Each equipment reads the ID given to the printed wiring board while the printed wiring board flows through the line, automatically changes the width of the conveyor, changes the numerical control data, and prints the solder paste. , Fixed set parts mounting, setup parts mounting, reflow soldering.

【0152】次いで、同一グループを形成する基板を次
々にローダーに投入し、同一グループの基板の製造を継
続する。
Next, the substrates forming the same group are successively put into the loader, and the manufacture of the same group of substrates is continued.

【0153】一方、最初のプリント配線板ユニットの生
産開始と同時に予め作成されている次のグループの段取
り部品セット・リストによって次の段取り部品の収集を
開始する。
On the other hand, at the same time when the production of the first printed wiring board unit is started, the collection of the next set-up parts is started according to the set-up part set list of the next group created in advance.

【0154】そして、最初の製品グループの最後のプリ
ント配線ユニットの部品搭載が完了した時点で、一括交
換台車を交換して搭載機にセットする。これで、次の製
品グループの生産が開始される。
Then, when the components of the last printed wiring unit of the first product group have been mounted, the collective exchange cart is replaced and set on the mounting machine. This starts production of the next product group.

【0155】以降、上記の繰り返しで複数の製品グルー
プの生産が行なわれてゆく。
Thereafter, the production of a plurality of product groups is performed by repeating the above.

【0156】以上詳細に説明した如く、本発明により、
固定セット部品の決定、固定セット部品の搭載機への振
り分けと段取り部品の搭載機への振り分けを合理的に行
なうことができ、段取り待ちのために生産を停止する不
利益を極少化することができる。
As described in detail above, according to the present invention,
Decision of fixed set parts, distribution of fixed set parts to loading machines and distribution of setup parts to loading machines can be performed rationally, minimizing the disadvantage of stopping production due to setup waiting. it can.

【0157】以上で本発明の第一の実施の形態の説明を
終了し、次いで本発明の第二の実施の形態の説明に入
る。
[0157] The description of the first embodiment of the present invention is completed above, and then, the description of the second embodiment of the present invention is started.

【0158】本発明の第二の実施の形態の機能ブロック
図の形は図1と同じであるが、固定セット部品振り分け
手段の処理が異なるので、固定セット部品振り分け手段
についてのみ説明する。
Although the form of the functional block diagram of the second embodiment of the present invention is the same as that of FIG. 1, the processing of the fixed set component allocating means is different, so only the fixed set component allocating means will be described.

【0159】準備的な処理では、まず、生産計画中で製
造番号と出材予定日が異なる同一製品図番の製品をまと
めて製造数を加算し、製造数が多い順にソーティングす
る。
In the preparatory process, first, products having the same product drawing number having different production numbers and scheduled release dates in a production plan are added together and the number of products is added, and the products are sorted in descending order of the number of products.

【0160】そして、各々の製造図番毎に、CAD情報
と部品情報とを用いて、既に説明したのと同様に基板面
別使用部品一覧を作成し、基板面別使用部品一覧上の部
品別に合計搭載時間を算出する。作成されるのが、図1
5に示す本発明の第二の実施の形態の基板面別使用部品
一覧の例である。
Then, for each manufacturing drawing number, using the CAD information and the component information, a list of used components for each board surface is created in the same manner as described above. Calculate the total loading time. Fig. 1
FIG. 9 is an example of a list of parts used according to board surface according to the second embodiment of the present invention shown in FIG.

【0161】上記算出結果に従って、基板面別使用部品
一覧上の部品の順序を合計搭載時間が長い順にソーティ
ングする。
According to the above calculation results, the order of the components on the list of used components by board surface is sorted in the order of the total mounting time.

【0162】一方、図10の生産計画対応使用部品一覧
において、累積チャネル数が700以上になる部品に対
しては、上記の如く固定セット部品のチャネル数が70
0と決められているため、搭載機番号をNo.4とす
る。
On the other hand, in the list of used parts corresponding to the production plan in FIG. 10, for the parts whose cumulative number of channels is 700 or more, the number of channels of the fixed set parts is 70 as described above.
0, so the mounted machine number is No. 4 is assumed.

【0163】そして、下記の手順で固定セット部品を搭
載機へ振り分けてゆく。
Then, the fixed set components are distributed to the mounting machine in the following procedure.

【0164】図16は、本発明の第二の実施の形態にお
ける固定セット部品振り分け手段のフローチャートであ
る。以降、図16の符号に沿って説明する。
FIG. 16 is a flow chart of the fixed set component allocating means according to the second embodiment of the present invention. Hereinafter, description will be made along the reference numerals in FIG.

【0165】S41.製造数が最多の基板面別使用部品
一覧を選択する。
S41. Select the list of parts used by board surface with the largest number of products.

【0166】S42.選択した基板面別使用部品一覧に
おける最初の部品を選択する。
S42. Select the first component in the selected component list for each board surface.

【0167】S43.選択した部品の搭載機番号がブラ
ンクか否かを判定する。
S43. It is determined whether or not the mounting machine number of the selected component is blank.

【0168】搭載機番号がブランクでない場合(No)
には、既に搭載機番号が決まっているのでステップS4
8にジャンプする。尚、最初は当然ブランクである。
When the mounted machine number is not blank (No)
In step S4, the machine number has already been determined.
Jump to 8. It should be noted that the first is a blank.

【0169】S44.ステップS43で、搭載機番号が
ブランクである場合(Yes)には、当該部品をセット
可能な搭載機があるか否かを判定する。
S44. If the mounting machine number is blank in step S43 (Yes), it is determined whether there is a mounting machine on which the component can be set.

【0170】当該部品をセット可能な搭載機がない場合
(No)には、ステップS50にジャンプする。尚、最
初は当然セット可能である。
If there is no mounting machine on which the part can be set (No), the process jumps to step S50. At first, it can be set naturally.

【0171】S45.ステップS24で、当該部品をセ
ット可能な搭載機がある場合(Yes)には、固定セッ
ト部品を搭載する搭載機の中で総搭載時間が最短の搭載
機を選択し、S46.当該搭載機に搭載時間とチャネル
数を加算する。
S45. In step S24, if there is a mounting machine on which the component can be set (Yes), a mounting machine with the shortest total mounting time is selected among the mounting machines on which the fixed set component is mounted, and S46. Add the installation time and the number of channels to the mounted machine.

【0172】S47.生産計画対応使用部品一覧と基板
面別使用部品一覧に搭載機番号を書き込む。
S47. Write the mounting machine number in the list of used parts corresponding to the production plan and the list of used parts by board surface.

【0173】S48.今搭載機に振り分けた部品が基板
面別使用部品一覧における最後の部品か否かを判定す
る。
S48. It is determined whether or not the component distributed to the mounting machine is the last component in the list of used components by board surface.

【0174】最後の部品であると判定された場合(Ye
s)には、ステップS52にジャンプする。
If it is determined that the part is the last part (Ye
In s), the process jumps to step S52.

【0175】S49.ステップS48で、最後の部品で
はないと判定された場合(No)には、ステップS41
で選択した基板面別使用部品一覧における次の部品を選
択し、ステップS43にジャンプする。
S49. If it is determined in step S48 that the component is not the last component (No), the process proceeds to step S41.
Then, the next part in the list of used parts for each board surface selected in is selected, and the process jumps to step S43.

【0176】S50.ステップS44で、選択した部品
をセットすることが可能な搭載機がないと判定された場
合(No)には、各搭載機にセットする部品は全て揃っ
たことになる。これらの部品を前後の2つのセット部
に、部品数が同じになるように振り分け、セット位置を
決める。
S50. If it is determined in step S44 that there is no mounting machine on which the selected component can be set (No), it means that all the components to be set on each mounting machine are complete. These parts are allocated to the two front and rear set parts so that the number of parts is the same, and the set position is determined.

【0177】S51.生産計画対応使用部品一覧と基板
面別使用部品一覧にセット位置番号を書き込んでステッ
プS54に移行する。
S51. The set position number is written in the production plan-compatible part list and the board-part-specific part list, and the flow advances to step S54.

【0178】そして、最終部品になるまでステップS4
3乃至ステップS49を繰り返す。
Step S4 until the final part is obtained.
Steps 3 to S49 are repeated.

【0179】S52.ステップS48で、最後の部品で
あると判定された場合(Yes)には、今固定セット部
品の振り分けを行なった基板が最後の基板であるか否か
を判定する。
S52. If it is determined in step S48 that the board is the last board (Yes), it is determined whether the board on which the fixed set components have been distributed is the last board.

【0180】最後の基盤であると判定された場合(Ye
s)には、ステップS50にジャンプする。
When it is determined that the base is the last base (Ye
In s), the process jumps to step S50.

【0181】S53.ステップS52で、最後の基板で
はないと判定された場合(No)には、製造数が次の規
範面別使用部品一覧を選択してステップS42にジャン
プし、上記の処理を新たに選択された基板について行な
う。
S53. If it is determined in step S52 that the board is not the last board (No), the production number is selected from the next list of reference surface-specific used parts, the process jumps to step S42, and the above processing is newly selected. Perform on the substrate.

【0182】S54.ステップS51の処理の後、搭載
機毎に固定セット部品セット・リストを作成して処理を
終了する。
S54. After the processing in step S51, a fixed set part set list is created for each mounting machine, and the processing ends.

【0183】残された段取り部品の振り分けは既に説明
したのと全く同じであり、以降の処理や生産も既に説明
したのと同じである。
The distribution of the remaining set-up parts is exactly the same as described above, and the subsequent processing and production are the same as already described.

【0184】本発明の第二の実施の形態の利点は、個々
の製品基板毎の搭載時間を考慮して固定セット部品を振
り分けるために、搭載機毎の搭載時間のバランスを改善
できる点である。
An advantage of the second embodiment of the present invention is that the balance of the mounting time for each mounting machine can be improved because the fixed set components are sorted in consideration of the mounting time for each product board. .

【0185】そして、本発明の第一の実施の形態による
か、本発明の第二の実施の形態によるかは、ライン稼働
条件における振り分け手法の指定に従えばよい。
Whether to use the first embodiment of the present invention or the second embodiment of the present invention may be in accordance with the designation of the sorting method in the line operating conditions.

【0186】次に、本発明の第三の実施の形態について
説明する。これも、固定セット部品の振り分けを改善し
たもので、以下のように振り分ける。
Next, a third embodiment of the present invention will be described. This is also an improvement in the distribution of fixed set components, and is distributed as follows.

【0187】生産計画対応使用部品一覧において出現回
数が多い部品を共通部品として、段取り部品のセット部
を除く全ての搭載機の部品セット部に振り分けておく。
In the list of used parts corresponding to the production plan, parts having a large number of appearances are assigned as common parts to the part setting sections of all mounting machines except for the set-up parts setting section.

【0188】そして、上記の振り分け条件を考慮して搭
載機番号とセット位置番号を決定し、既に説明したのと
同様に基板別使用部品一覧を作成する。この際、共通部
品については搭載機番号には全ての搭載機という意味で
0を記入する。これを、図17に示してある。
Then, the mounting machine number and the set position number are determined in consideration of the above-mentioned distribution conditions, and a used component list for each board is created in the same manner as described above. At this time, for the common parts, 0 is written in the mounting machine number to mean all mounting machines. This is shown in FIG.

【0189】次いで、搭載機別に各々の共通部品の搭載
時間とその他の部品の搭載時間も算出する。
Next, the mounting time of each common component and the mounting time of other components are calculated for each mounting machine.

【0190】この結果に基づいて、それぞれの搭載機の
共通部品以外の部品の搭載時間の最大時間を超えないよ
うに共通部品を搭載する搭載機を決定する。
Based on the result, a mounting machine on which the common component is mounted is determined so as not to exceed the maximum mounting time of the components other than the common component of each mounting machine.

【0191】例えば、共通部品が2種で、図18の共通
部品を最適配置した場合の搭載時間に示すような搭載時
間になる場合、No.3の搭載機で共通部品1を搭載す
るようにし、No.4の搭載機で共通部品2の搭載をす
るようにし、No.1とNo.2の搭載機はその他の部
品を搭載するようにすれば、No.1乃至No.4の搭
載機の搭載時間はそれぞれ15.5分、17.5分、1
3分及び11分になり、平準化が達成される。
For example, if there are two types of common parts and the mounting time is as shown in the mounting time when the common parts in FIG. No. 3, the common component 1 is mounted on the mounting machine. No. 4, the common component 2 is mounted on the mounting machine. 1 and No. If the other mounting parts are mounted on the mounting machine of No. 2, 1 to No. The loading times of the four machines were 15.5 minutes, 17.5 minutes, and 1 respectively.
At 3 minutes and 11 minutes, leveling is achieved.

【0192】要するに、出現回数の多い部品を共通部品
として振り分ける場合、固定セット部品のチャネルの自
由度はその分減少する。しかし、出現回数の多い部品の
部品使用数の比率は高いので、共通部品を優先的にセッ
トすることによってセットすべきチャネルを失う部品は
使用部品数比率が非常に低いのが現実である。従って、
使用部品数比率が低い部品を段取り部品に回して段取り
部品の振り分けを行なうようにしても、全体的に見て搭
載機毎の搭載時間は明らかに平準化できる。
In short, when a component having a large number of appearances is assigned as a common component, the degree of freedom of the channel of the fixed set component is reduced accordingly. However, since the ratio of the number of components used is high for components with a large number of appearances, it is a reality that the ratio of the number of used components is very low for components that lose channels to be set by preferentially setting common components. Therefore,
Even if a component having a low used component ratio is turned into a setup component and the setup component is sorted, the mounting time of each mounting machine can be obviously leveled as a whole.

【0193】次に、本発明の第四の実施の形態について
説明する。これは、以下のように段取り部品のセット指
示を出して必要最小限の段取り替えを可能にするもので
ある。
Next, a fourth embodiment of the present invention will be described. This enables a minimum necessary setup change by issuing an instruction to set up the setup parts as described below.

【0194】製造予定の製品(複数も可)について段取
り部品のセット指示を出し、製造完了図番は遅延なく完
了情報を入力する。
A set part setting instruction is issued for a product (a plurality of products to be manufactured), and the completion information is input without delay for the manufacturing completion drawing number.

【0195】そして、次の製造予定図番を入力する時、
次の製造に必要となる部品図番及び現状の段取り部品の
セット状況、製造の完了状況を比較して、必要最小限の
段取り部品のセット指示を出すようにして、上記の処理
を繰り返す。
Then, when inputting the next production plan drawing number,
The above process is repeated by comparing the part drawing number required for the next production, the current set-up state of the set-up parts, and the completion state of the manufacture, and issuing an instruction for setting the minimum necessary set-up parts.

【0196】これにより、随時、必要最小限の段取り替
えをすることができるようになり、段取り時間が少な
い、小回りがきく生産ラインを構築することができる。
As a result, the necessary minimum setup change can be made at any time, and a production line with a short setup time and a small turn can be constructed.

【0197】次いで、本発明の第五の実施の形態につい
て説明する。
Next, a fifth embodiment of the present invention will be described.

【0198】本発明の第五の実施の形態では、下記の手
順により製品の投入順を改善して、総搭載時間を極少化
する。ここでは、製品の種類が10種類ある場合を例に
説明する。そして、各々の搭載機間に30枚程度のプリ
ント配線ユニットのバッファ・ストッカーを設置してあ
るものとする。
In the fifth embodiment of the present invention, the order of product introduction is improved by the following procedure to minimize the total mounting time. Here, a case where there are ten types of products will be described as an example. It is assumed that buffer stockers of about 30 printed wiring units are installed between each mounting machine.

【0199】まず、各々の製品の搭載機別の搭載時間に
製造数量をかけて各々の製品の価値搭載機における総搭
載時間を算出する。これを図19に示してある。
First, the total mounting time of each product in the value mounting machine is calculated by multiplying the mounting time of each product mounting machine by the manufacturing quantity. This is shown in FIG.

【0200】次いで、図19の表の中で下記ルールで製
品の順序を入れ替える。
Next, the order of the products is changed in the table of FIG. 19 according to the following rules.

【0201】即ち、各々の製品の中で搭載機No.4に
おける搭載時間が最長の製品を1番目にする。もし、搭
載機No.4の中で搭載時間が同じ製品がある場合に
は、搭載機No.1乃至No.3における搭載時間が長
い方を1番目とする。
That is, in each product, the loading machine No. The product with the longest mounting time in No. 4 is the first product. If the installed machine No. In the case where there is a product having the same mounting time among the mounting machines No. 4, 1 to No. 3 is the first one with the longer mounting time.

【0202】これは、最終の搭載機である搭載機No.
4における搭載時間が最も長い製品を搭載機No.4に
最初に投入すれば、前にある搭載機が搭載待ちをしなく
て済むという考え方によるものである。
This is the loading machine No. which is the final loading machine.
4 is the product with the longest mounting time. This is based on the idea that if the vehicle is first introduced into the No. 4, it is not necessary for the preceding machine to wait for mounting.

【0203】この場合、製品No3が搭載機No.4に
おいて最長の搭載時間25分であるので、これを1番目
にする。
In this case, the product No. 3 is the mounted machine No. 4, since the longest mounting time is 25 minutes, this is the first.

【0204】次いで、搭載機No.4における搭載時間
の最も短い製品を2番目にする。
Next, the loading machine No. The product with the shortest mounting time in No. 4 is the second product.

【0205】これは、最初に搭載機No.4に最大の負
荷をかけたので、次には搭載機No.4には最小の負荷
をかけて、搭載機No.4と搭載機No.3の間にたま
る搭載待ちプリント配線板を減らすという考え方であ
る。
[0205] This is because the loading machine No. Since the maximum load was applied to No.4, the next step was to mount No. 4 is loaded with the minimum load. 4 and mounted machine No. The idea is to reduce the number of printed wiring boards waiting to be mounted that accumulate between the three.

【0206】この場合、製品No.2が最短搭載時間2
分であるので、製品No,2を2番目にする。
In this case, the product No. 2 is the shortest loading time 2
Product No. 2 is the second product.

【0207】この段階で、各々の搭載機の搭載時間を加
算する。
At this stage, the mounting time of each mounting machine is added.

【0208】次いで、搭載時間が最長の搭載機において
搭載時間が最短の製品を次の順番にする。
Next, in the mounting machine having the longest mounting time, the products having the shortest mounting time are arranged in the following order.

【0209】これも、最大の負荷をかけた搭載機には次
には最小の負荷をかけて、搭載時間の計算時点で最大負
荷の搭載機とその前の搭載機との間の搭載待ちが生じ難
くするという考え方である。
[0209] Again, the smallest load is applied next to the loaded machine with the maximum load, and at the time of the calculation of the loading time, the loading wait between the loaded machine with the maximum load and the preceding loaded machine is waited. The idea is to make it less likely to occur.

【0210】この場合、搭載機No.4がここまでの総
搭載時間が27分で最長であるので、残っている製品の
中で搭載時間が3時間で最短の製品No.6を選択し
て、3番目とする。
In this case, the loading machine No. No. 4 is the longest with a total mounting time of 27 minutes so far, so the product No. 4 with the shortest mounting time of 3 hours among the remaining products. 6 is selected to be the third.

【0211】以降、同様にして、各々の搭載機の搭載時
間を加算し、搭載時間が最長の搭載機において搭載時間
が最短の製品を次の順番にする。
Thereafter, similarly, the mounting time of each mounting machine is added, and the products having the shortest mounting time in the mounting machine having the longest mounting time are arranged in the following order.

【0212】このようにして、投入順を決めた時の搭載
機別総搭載時間は図20の如くなり、累積搭載時間は図
21の如くなる。
In this way, the total mounting time for each mounting machine when the order of loading is determined is as shown in FIG. 20, and the cumulative mounting time is as shown in FIG.

【0213】上記の如く、本発明の第五の実施の形態に
より、搭載機毎の搭載時間を平準化しながら製品の投入
順序を設定することによって、全ての製品に部品を搭載
する時間を短縮することができる。
As described above, according to the fifth embodiment of the present invention, the time for mounting components on all products is reduced by setting the order of product introduction while leveling the mounting time for each mounting machine. be able to.

【0214】[0214]

【発明の効果】本発明の第一の実施の形態によれば、複
数の搭載機への固定セット部品と段取り部品の割合を最
適化で、更に、固定セット部品の搭載機への振り分けを
最適化することができる。
According to the first embodiment of the present invention, the ratio of fixed set parts and setup parts to a plurality of mounting machines is optimized, and the distribution of fixed set parts to the mounting machines is further optimized. Can be

【0215】生産計画対応に生産効率を算出したとこ
ろ、従来の技術では搭載機の稼働率が20%前後であっ
たものが、本発明の第一の実施の形態の適用によって8
0乃至90%の稼働率に改善された。これは、少数品種
を大量生産する場合の稼働率並みのデータである。
When the production efficiency was calculated in accordance with the production plan, the operation rate of the mounted machine was about 20% in the prior art, but was reduced to 8% by applying the first embodiment of the present invention.
The operation rate was improved from 0 to 90%. This is data similar to the operation rate when mass-producing a small number of varieties.

【0216】又、本発明の第二の実施の形態によれば、
個々の製品の搭載時間を考慮して固定セット部品の振り
分けを行なうので搭載時間のバランスを改善できる。
Further, according to the second embodiment of the present invention,
Since the fixed set components are sorted in consideration of the mounting time of each product, the mounting time balance can be improved.

【0217】又、本発明の第三の実施の形態によれば、
出現回数の多い部品を共通部品として搭載機に共通的に
セットすることにより、搭載機間の搭載時間を平準化す
ることができる。
According to the third embodiment of the present invention,
By setting a component with a large number of appearances as a common component in the mounting machine in common, the mounting time between the mounting machines can be equalized.

【0218】又、本発明の第四の実施の形態では、製造
状態を勘案して段取り部品をセットするので、製造中に
必要最小限の段取り替えをすればよくなる。
Further, in the fourth embodiment of the present invention, since the set-up parts are set in consideration of the manufacturing state, it is only necessary to change the necessary minimum set-up during the manufacturing.

【0219】最後に、本発明の第五の実施の形態は、搭
載機の総搭載時間を勘案して製品を投入するので、搭載
機間の搭載時間の更に平準化することができる。
Finally, in the fifth embodiment of the present invention, since the product is introduced in consideration of the total mounting time of the mounting machines, the mounting time between the mounting machines can be further leveled.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の第一の実施の形態の機能ブロック
図。
FIG. 1 is a functional block diagram of a first embodiment of the present invention.

【図2】 固定セット部品決定のフローチャート。FIG. 2 is a flowchart of fixing set component determination.

【図3】 CAD情報の例。FIG. 3 is an example of CAD information.

【図4】 部品情報の例。FIG. 4 is an example of component information.

【図5】 搭載機情報の例。FIG. 5 is an example of mounted device information.

【図6】 表面実装ラインの部品搭載機の配列例。FIG. 6 is an arrangement example of a component mounting machine in a surface mounting line.

【図7】 段取り部品選択表の例。FIG. 7 is an example of a setup part selection table.

【図8】 生産計画の例。FIG. 8 shows an example of a production plan.

【図9】 ライン稼働条件の例。FIG. 9 shows an example of line operating conditions.

【図10】 生産計画対応使用部品一覧の例。FIG. 10 is an example of a used part list corresponding to a production plan.

【図11】 生産計画別基板平均の例。FIG. 11 is an example of a board average for each production plan.

【図12】 固定セット部品/段取り部品振り分け表の
例。
FIG. 12 is an example of a fixed set component / setup component distribution table.

【図13】 本発明の第一の実施の形態における固定セ
ット部品振り分け手段のフローチャート。
FIG. 13 is a flowchart of a fixed set component distribution unit according to the first embodiment of the present invention.

【図14】 本発明の第一の実施の形態の基板別使用部
品一覧の例。
FIG. 14 is an example of a used component list for each board according to the first embodiment of this invention.

【図15】 本発明の第二の実施の形態の基板別使用部
品一覧の例。
FIG. 15 is an example of a list of used components for each board according to the second embodiment of the present invention.

【図16】 本発明の第二の実施の形態における固定セ
ット部品振り分け手段のフローチャート。
FIG. 16 is a flowchart of a fixed set component distribution unit according to the second embodiment of the present invention.

【図17】 本発明の第三の実施の形態の基板別使用部
品一覧の例。
FIG. 17 is an example of a list of used components for each board according to the third embodiment of the present invention.

【図18】 共通部品を最適配置した場合の搭載時間。FIG. 18 shows the mounting time when the common parts are optimally arranged.

【図19】 搭載機別搭載時間[Fig. 19] Mounting time by mounted machine

【図20】 投入順最適化後の搭載機別搭載時間。FIG. 20 shows the mounting time of each mounting machine after the optimization of the loading order.

【図21】 投入順最適化後の累積搭載時間。FIG. 21 shows the cumulative mounting time after the loading order optimization.

【符号の説明】[Explanation of symbols]

1 中央処理ユニット(CPU) 2 固定セット部品決定手段 3 固定セット部品振り分け手段 4 段取り部品セット位置決定手段 5 数値制御データ(NCデータ)作成手段 6 表面実装ライン制御手段 7 ローダー 8 半田印刷機 9 接着剤塗布機 10 部品搭載機 11 部品搭載機 12 部品搭載機 13 リフロー炉 14 CAD情報 15 生産計画 16 段取り部品選択表 17 部品情報 18 搭載機情報 19 ライン稼働条件 20 部品セット・リスト DESCRIPTION OF SYMBOLS 1 Central processing unit (CPU) 2 Fixed set component determination means 3 Fixed set component distribution means 4 Setup component set position determination means 5 Numerical control data (NC data) creation means 6 Surface mounting line control means 7 Loader 8 Solder printing machine 9 Adhesion Dispensing machine 10 Component mounting machine 11 Component mounting machine 12 Component mounting machine 13 Reflow furnace 14 CAD information 15 Production plan 16 Setup parts selection table 17 Parts information 18 Mounting machine information 19 Line operating conditions 20 Parts set list

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 表面実装部品をプリント配線板に実装し
て半田付けする表面実装ラインの製造管理システムであ
って、 プリント配線板ユニットのCAD情報とプリント配線板
ユニットの生産計画及び使用部品に関する部品情報とか
ら生産計画対応使用部品一覧を作成し、生産計画別基板
平均及びライン稼働条件より固定セット部品を決定する
固定セット部品決定手段と、 該生産計画対応使用部品一覧中の固定セット部品を順に
総搭載時間が最短の搭載機にセットし、搭載機の総搭載
時間を平準化する固定セット部品振り分け手段とを備え
ることを特徴とする製造管理システム。
The present invention relates to a production management system for a surface mounting line for mounting and soldering a surface mount component on a printed wiring board, wherein the CAD information of the printed wiring board unit, a production plan of the printed wiring board unit, and a component relating to a used component. A list of used parts corresponding to the production plan is created from the information, and a fixed set part determining means for determining a fixed set part based on a board average and a line operating condition for each production plan, and a fixed set part in the list of used parts corresponding to the production plan in order. A production management system comprising: a fixed set component distribution unit that sets the total mounting time of a mounting machine on the mounting machine having the shortest total mounting time and equalizes the total mounting time of the mounting machine.
【請求項2】 請求項1記載の製造管理システムにおい
て、 上記固定セット部品振り分け手段は、 上記生産計画において製造数の多い製品の順に、各搭載
機の搭載時間を均一に振り分ける手段を備える固定セッ
ト部品振り分け手段であることを特徴とする製造管理シ
ステム。
2. The production management system according to claim 1, wherein said fixed set component distribution means includes means for uniformly distributing the mounting time of each mounting machine in the order of the number of products manufactured in the production plan. A production management system, which is a component distribution unit.
【請求項3】 請求項1又は請求項2のいずれかに記載
の製造管理システムにおいて、 上記生産計画対応使用部品一覧において出現回数が上位
の部品を共通部品として複数の搭載機に共通にセットす
ることを特徴とする製造管理システム。
3. The manufacturing management system according to claim 1, wherein a part having a higher appearance frequency in the list of used parts corresponding to the production plan is set in common to a plurality of mounting machines as a common part. A manufacturing management system characterized by the above.
【請求項4】 請求項1又は請求項2のいずれかに記載
の製造管理システムにおいて、 同時に製造中の複数のプリント配線ユニットについて、
段取り部品のセット状況、プリント配線ユニットの製造
完了状況、次にセットが必要になる段取り部品の図番と
から段取り部品の交換指示を出すことを特徴とする製造
管理システム。
4. The manufacturing management system according to claim 1, wherein the plurality of printed wiring units being manufactured at the same time are:
A production management system, which issues an instruction to replace a set-up component based on a set-up status of a set-up component, a manufacturing completion status of a printed wiring unit, and a figure of a set-up component that needs to be set next.
【請求項5】 請求項1又は請求項2のいずれかに記載
の製造管理システムにおいて、 当初は最後の搭載機での搭載時間が最長のプリント配線
ユニットを投入した後に、最後の搭載機の搭載時間が最
短のプリント配線ユニットを投入し、 以降は、累積搭載時間が最長の搭載機における搭載時間
が最短のプリント配線ユニットを投入することを特徴と
する製造管理システム。
5. The manufacturing management system according to claim 1, wherein the mounting of the last mounting machine is started after a printed wiring unit having the longest mounting time in the last mounting machine is initially supplied. A manufacturing management system characterized in that a printed wiring unit with the shortest time is input, and thereafter, a printed wiring unit with the shortest mounting time in a mounting machine with the longest cumulative mounting time is input.
JP2000060906A 2000-03-06 2000-03-06 Manufacture control system Pending JP2001251095A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000060906A JP2001251095A (en) 2000-03-06 2000-03-06 Manufacture control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000060906A JP2001251095A (en) 2000-03-06 2000-03-06 Manufacture control system

Publications (1)

Publication Number Publication Date
JP2001251095A true JP2001251095A (en) 2001-09-14

Family

ID=18581145

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000060906A Pending JP2001251095A (en) 2000-03-06 2000-03-06 Manufacture control system

Country Status (1)

Country Link
JP (1) JP2001251095A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007067050A (en) * 2005-08-30 2007-03-15 Hitachi High-Tech Instruments Co Ltd Electronic component mounting equipment
JP2009272551A (en) * 2008-05-09 2009-11-19 Panasonic Corp Method of deciding mounting condition
JP2010073958A (en) * 2008-09-19 2010-04-02 Juki Corp Feeder arrangement optimizing method of component mounting device
JP2011154659A (en) * 2010-01-28 2011-08-11 Fujitsu Ltd Case data generating program, method, and device
KR101169869B1 (en) 2009-06-26 2012-07-31 가부시끼가이샤 히다찌 하이테크 인스트루먼츠 Component mounting line design device, computer-readable recording medium, and component mounting system
JP2012520577A (en) * 2009-03-16 2012-09-06 シーメンス アクチエンゲゼルシヤフト How to determine equipment for a fixed table of an automatic mounting machine
JP2017112135A (en) * 2015-12-14 2017-06-22 富士通株式会社 Calculation device, calculation method, and calculation program
WO2017187512A1 (en) * 2016-04-26 2017-11-02 富士通株式会社 Production plan generation device, production plan generation method, and production plan generation program
WO2020012522A1 (en) * 2018-07-09 2020-01-16 株式会社日立製作所 Mounting time leveling device for pick-and-place machine and method for leveling mounting time

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007067050A (en) * 2005-08-30 2007-03-15 Hitachi High-Tech Instruments Co Ltd Electronic component mounting equipment
JP4733473B2 (en) * 2005-08-30 2011-07-27 株式会社日立ハイテクインスツルメンツ Electronic component mounting device and setup change time teaching device
JP2009272551A (en) * 2008-05-09 2009-11-19 Panasonic Corp Method of deciding mounting condition
JP2010073958A (en) * 2008-09-19 2010-04-02 Juki Corp Feeder arrangement optimizing method of component mounting device
JP2012520577A (en) * 2009-03-16 2012-09-06 シーメンス アクチエンゲゼルシヤフト How to determine equipment for a fixed table of an automatic mounting machine
KR101169869B1 (en) 2009-06-26 2012-07-31 가부시끼가이샤 히다찌 하이테크 인스트루먼츠 Component mounting line design device, computer-readable recording medium, and component mounting system
JP2011154659A (en) * 2010-01-28 2011-08-11 Fujitsu Ltd Case data generating program, method, and device
US8700954B2 (en) 2010-01-28 2014-04-15 Fujitsu Limited Common trouble case data generating method and non-transitory computer-readable medium storing common trouble case data generating program
JP2017112135A (en) * 2015-12-14 2017-06-22 富士通株式会社 Calculation device, calculation method, and calculation program
WO2017187512A1 (en) * 2016-04-26 2017-11-02 富士通株式会社 Production plan generation device, production plan generation method, and production plan generation program
JPWO2017187512A1 (en) * 2016-04-26 2018-11-22 富士通株式会社 Manufacturing plan generation apparatus, manufacturing plan generation method, and manufacturing plan generation program
CN109076725A (en) * 2016-04-26 2018-12-21 富士通株式会社 Manufacturing planning generating means, manufacturing planning generation method and manufacturing planning generate program
CN109076725B (en) * 2016-04-26 2020-06-05 富士通株式会社 Manufacturing plan generating device, manufacturing plan generating method, and manufacturing plan generating program
US10921791B2 (en) 2016-04-26 2021-02-16 Fujitsu Limited Production plan generation device, production plan generation method, and production plan
WO2020012522A1 (en) * 2018-07-09 2020-01-16 株式会社日立製作所 Mounting time leveling device for pick-and-place machine and method for leveling mounting time
JPWO2020012522A1 (en) * 2018-07-09 2021-04-01 株式会社日立製作所 Mounting time leveling device for component mounting machine and mounting time leveling method

Similar Documents

Publication Publication Date Title
JP3339779B2 (en) Manufacturing management system with SMT line
US5170554A (en) High mix printed circuit assembly technique
CN109076725B (en) Manufacturing plan generating device, manufacturing plan generating method, and manufacturing plan generating program
CN107114015B (en) Filling of printed circuit boards
CN1846223B (en) Method for optimization of an order for component mounting and apparatus for optimization of an order for component mounting
JP2001251095A (en) Manufacture control system
CN114585982A (en) Configuration support method, learning completion model generation method, program, configuration support system, and operating system
US5980086A (en) Facility operating method
US5371940A (en) Pallet arranging system
JP4335119B2 (en) Operation analysis method and operation analysis system
JP2008004761A (en) Preparation method for group of data for setup
JP4302422B2 (en) Component mounting method and system
JP3946320B2 (en) Tool placement setting method and tool placement setting device for work machine
EP3484255B1 (en) Production plan creation system and production plan creation method
JP2642800B2 (en) Pallet knitting system
JP7249918B2 (en) PRODUCTION PLANNING DEVICE AND COMPONENT MOUNTING SYSTEM WITH THE SAME
JP5500900B2 (en) Electrical circuit assembly method
JPH10335896A (en) Apparatus for mounting electronic component
JP3003869B2 (en) Electronic package manufacturing equipment
JP2006171916A (en) Production planning method
Dillon et al. PCB assembly line setup optimization using component commonality matrices
JP2832318B2 (en) Electronic package manufacturing equipment
JP3042452B2 (en) Reel parts management system
JP2002185200A (en) Method for mounting electronic component
JPH08167796A (en) Electronic parts mounting method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20051108

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060106

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060207

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060331

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060425