JP2001239990A - Construction method of launching slipway - Google Patents
Construction method of launching slipwayInfo
- Publication number
- JP2001239990A JP2001239990A JP2000055160A JP2000055160A JP2001239990A JP 2001239990 A JP2001239990 A JP 2001239990A JP 2000055160 A JP2000055160 A JP 2000055160A JP 2000055160 A JP2000055160 A JP 2000055160A JP 2001239990 A JP2001239990 A JP 2001239990A
- Authority
- JP
- Japan
- Prior art keywords
- launching
- ramp
- slipway
- land
- launch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Revetment (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、陸上で製作した防
波堤や護岸用ケーソンなどの大型構造物を進水させる時
に用いる進水斜路の建設工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a launch ramp used when launching a large-scale structure such as a breakwater or a seawall caisson manufactured on land.
【0002】[0002]
【従来の技術】従来、陸上で製作した防波堤や護岸用ケ
ーソンなどの大型構造物を所定の水域に設置する場合、
一つの方法として、上記の防波堤や護岸用ケーソンなど
の大型構造物を陸上から水中に突き出ている進水斜路を
用いて進水させることが行われている。2. Description of the Related Art Conventionally, when installing large structures such as breakwaters and seawall caisson made on land in a predetermined water area,
As one method, a large structure such as the breakwater or the revetment caisson is launched using a launch ramp that protrudes underwater from the land.
【0003】この方法は、図5に示すように、製作後の
防波堤や護岸用ケーソン1をジャッキアップして台車2
に載せた後、進水斜路3に敷設したレール4上を重力を
利用して降下させ、進水させるというものである。In this method, as shown in FIG. 5, a breakwater and a revetment caisson 1 are jacked up and a bogie 2 is made.
Then, it is lowered on the rails 4 laid on the launch ramp 3 using gravity to launch the water.
【0004】従って、進水斜路3やレール4を精度よく
建設したり、敷設しないと、走行中の台車2が脱線した
り、あるいは、台車2の車軸が破損するなどの事故が発
生し、大事に至ることがある。[0004] Therefore, unless the launch ramp 3 and the rails 4 are constructed or laid accurately, an accident may occur such as the truck 2 being derailed or the axle of the truck 2 being damaged. May be reached.
【0005】また、進水斜路3やレール4は、機能上、
陸上Aから水中Bに突き出して建設されるため、進水斜
路3やレール4の先端部分は、水中土木工事となる。こ
のため、進水斜路3やレール4の先端部分を精度よく建
設したり、敷設することが難しい。また、レール4の下
に敷設したレール固定ブロック5の不等沈下や経年によ
る沈下もあることから維持管理も難しい。[0005] In addition, the launch ramp 3 and the rail 4 are functionally
Since it is constructed by projecting from the land A to the underwater B, the tip of the launch ramp 3 and the rail 4 is underwater civil engineering work. For this reason, it is difficult to accurately construct or lay the leading end of the launch ramp 3 or the rail 4. In addition, maintenance is difficult because the rail fixing block 5 laid under the rail 4 has unequal settlement and aging.
【0006】[0006]
【発明が解決しようとする課題】本発明は、かかる従来
の問題を解消するものであり、その目的とするところ
は、陸上から水中に突き出した進水斜路の建設に際し、
建設期間の短縮、進水斜路やレールの建設精度の向上、
維持管理の容易な進水斜路建設工法を提供することにあ
る。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and an object of the present invention is to construct a launch ramp projecting underwater from land.
Shortening the construction period, improving the construction accuracy of launch ramps and rails,
An object of the present invention is to provide a launch slope construction method that is easy to maintain.
【0007】[0007]
【課題を解決するための手段】上記の課題を解決するた
め、本発明の進水斜路建設工法は、陸上から水中に突き
出した進水斜路を建設するに際し、浮体及び浮体上方の
斜路に敷設したレールを有する進水斜路先端部を陸部で
建造した後、該進水斜路先端部を進水斜路陸上部の先端
水域に曳航し、しかる後に、進水斜路先端部の浮体にバ
ラストを張って予め整地されている進水斜路陸上部先端
の水底に着座させることを特徴としている。In order to solve the above-mentioned problems, a launching ramp construction method according to the present invention, when constructing a launching ramp that protrudes into water from the land, is laid on a floating body and a ramp above the floating body. After the tip of the launch ramp with the rail is built at the land, the tip of the launch ramp is towed to the tip water area of the land on the launch ramp, and then a ballast is stretched over the floating body at the tip of the launch ramp. It is characterized in that it is seated on the water floor at the tip of the land on the rising slope, which is previously leveled.
【0008】本工法によれば、進水斜路の先端部分やレ
ールの先端部分の建設工事が陸上土木工事になるため、
進水斜路の建設期間を短縮させることができる。また、
同じ理由により、進水斜路の建設やレールの敷設を精度
よく実施することができる。更に、レール固定ブロック
の不等沈下や経年による沈下も回避できる。According to this construction method, the construction of the leading end of the launch slope and the leading end of the rail is civil engineering work on land.
The construction period of the launch ramp can be shortened. Also,
For the same reason, the construction of the launch ramp and the laying of the rails can be performed accurately. Furthermore, uneven settlement of the rail fixing block and settlement due to aging can be avoided.
【0009】[0009]
【発明の実施の形態】以下、図面を用いて本発明の実施
の形態について説明する。Embodiments of the present invention will be described below with reference to the drawings.
【0010】図1は建造中の進水斜路先端部の説明図、
図2は曳航中の進水斜路先端部の説明図、図3は沈設後
の進水斜路先端部の説明図である。FIG. 1 is an explanatory view of a leading end of a launch ramp during construction.
FIG. 2 is an explanatory diagram of the leading end of the launch ramp during towing, and FIG. 3 is an explanatory diagram of the leading end of the launch ramp after submerging.
【0011】先ず、図1に示すように、ドックゲート1
1で仕切られたドライドック12の中で進水斜路先端部
13を建造する。進水斜路先端部13は、主として、中
空のくさび形のバージ、すなわち、中空のくさび形の浮
体14から成り、その傾斜した上面、つまり、斜路15
には、台車走行用レール4aが敷設されている。このく
さび形の浮体14は、通常、鉄筋コンクリート製である
が、所望により鋼板製としてもよい。First, as shown in FIG.
In the dry dock 12 partitioned by 1, the leading end 13 of the launching ramp is constructed. The launching ramp end portion 13 is mainly composed of a hollow wedge-shaped barge, that is, a hollow wedge-shaped floating body 14, and its inclined upper surface, that is, the ramp 15 is formed.
, A truck running rail 4a is laid. The wedge-shaped floating body 14 is usually made of reinforced concrete, but may be made of a steel plate if desired.
【0012】進水斜路先端部13の完成後、図2に示す
ように、ドライドック12内に注水して進水斜路先端部
13を浮上させ、引き船30によって曳航する。After the completion of the launch ramp 13, the water is injected into the dry dock 12 to float the launch ramp 13 and towed by the tugboat 30, as shown in FIG.
【0013】図3に示すように、進水斜路陸上部23の
延長線上の海底21は、予め、基礎地盤22を盛って整
地されているので、進水斜路陸上部23の先端水域Cに
進水斜路先端部13を曳航したのち、進水斜路先端部1
3の浮体14内に図示しないバラストを張って進水斜路
先端部13を沈め、上記基礎地盤22上に進水斜路先端
部13を着座させる。As shown in FIG. 3, since the seabed 21 on the extension of the land 23 on the launching slope is previously set on the foundation ground 22, it advances to the water area C at the tip of the land 23 on the launching slope. After towing the water ramp end 13, the launch ramp end 1
A ballast (not shown) is stretched in the floating body 14 of the third step, and the leading end 13 of the launching ramp is submerged, and the leading end 13 of the launching ramp is seated on the foundation ground 22.
【0014】そして、進水斜路先端部13におけるレー
ル4aの後端部と、進水斜路陸上部23におけるレール
4bの先端部にわたって側板(不図示)を渡したのち、
側板とレール4a,4bとをボルト・ナット(不図示)
によって固定して連続し、陸上Aから水中Bに突き出し
た進水斜路3aを完成させる。After passing a side plate (not shown) over the rear end of the rail 4a at the leading end 13 of the launching ramp and the leading end of the rail 4b at the land 23 of the launching ramp,
Bolts and nuts (not shown) between side plates and rails 4a and 4b
To complete the launch ramp 3a that protrudes from the land A to the underwater B.
【0015】この進水斜路3aは、防波堤や護岸用ケー
ソンの大型構造物の進水に限らず、例えば、中小の船体
などの進水にも広く適用することができる。The launch ramp 3a is not limited to launching large structures such as breakwaters and seawalls, but can be widely applied to launching small and medium hulls, for example.
【0016】上記工法によれば、進水斜路の先端部分や
レールの先端部分の建設工事が陸上土木工事になるた
め、進水斜路の建設期間を短縮させることができる。ま
た、同じ理由により、進水斜路の建設やレールの敷設を
精度よく実施することができる。更に、レール固定ブロ
ックの不等沈下や経年による沈下も回避できる。According to the above-mentioned construction method, since the construction work of the leading end of the launch ramp and the leading end of the rail is a civil engineering work on land, the construction period of the launch ramp can be shortened. Further, for the same reason, the construction of the launch ramp and the laying of the rail can be performed with high accuracy. Furthermore, uneven settlement of the rail fixing block and settlement due to aging can be avoided.
【0017】上記の進水斜路先端部13は、浮体14と
浮体上面の斜路15が一体的に形成されているが、図4
に示すように、通常のポンツーン(浮体)34上に立設
した多数の支柱35によって斜路15を支える方式の進
水斜路先端部33も考えられる。この時のポンツーン3
4は、鋼板製でもコンクリート製でもよい。レール4a
は、第1番目の例と同様に、斜路15上に敷設されてい
る。In the above-described leading portion 13 of the launching ramp, a floating body 14 and a ramp 15 on the upper surface of the floating body are integrally formed.
As shown in FIG. 2, a leading end 33 of a launching ramp that supports the ramp 15 with a number of columns 35 standing on a normal pontoon (floating body) 34 is also conceivable. Pontoon 3 at this time
4 may be made of steel plate or concrete. Rail 4a
Are laid on the ramp 15 in the same manner as in the first example.
【0018】本方式で建造した進水斜路先端部33は、
移動も可能である。また、レール下に水圧ジャッキ(不
図示)を配置し、斜路傾斜角を調整できる方式も提供可
能である。The leading end 33 of the launching ramp is constructed by this method.
Movement is also possible. It is also possible to provide a system in which a hydraulic jack (not shown) is arranged below the rail to adjust the inclination angle of the ramp.
【0019】また、進水斜路先端部13,33の建造
は、ドライドックに限らず、ドライドック以外の陸部で
行ってもよい。In addition, the construction of the launching slope end portions 13 and 33 is not limited to the dry dock, but may be performed on land other than the dry dock.
【0020】[0020]
【発明の効果】上記のように、本発明によれば、進水斜
路の先端部分やレールの先端部分の建設工事が陸上土木
工事になるため、進水斜路の建設期間を短縮させること
ができるようになった。また、同じ理由により、進水斜
路の建設やレールの敷設を精度よく実施することができ
るようになった。更に、レール固定ブロックの不等沈下
や経年による沈下も回避でき、維持管理が容易になっ
た。As described above, according to the present invention, since the construction work of the leading end of the launch ramp and the leading end of the rail is a civil engineering work on land, the construction period of the launch ramp can be shortened. It became so. For the same reason, the construction of the launch ramp and the laying of the rails can be performed with high precision. Furthermore, uneven settlement of the rail fixing block and settlement due to aging can be avoided, and maintenance and management become easy.
【図1】建造中の進水斜路先端部の説明図である。FIG. 1 is an explanatory view of a leading end of a launch ramp during construction.
【図2】曳航中の進水斜路先端部の説明図である。FIG. 2 is an explanatory view of a leading end of a launch ramp during towing.
【図3】進水斜路先端部を進水斜路陸上部の前方に設置
させた説明図である。FIG. 3 is an explanatory diagram in which a leading end of a launching ramp is installed in front of a land portion of the launching ramp.
【図4】通常のポンツーンを利用した進水斜路先端部の
側面図である。FIG. 4 is a side view of a leading end of a launch ramp using a normal pontoon.
【図5】従来の進水斜路の断面図である。FIG. 5 is a cross-sectional view of a conventional launch ramp.
A 陸上 B 水中 C 進水斜路陸上部の先端水域 3 進水斜路 4a レール 13,33 進水斜路先端部 14,34 浮体 15 斜路 21 進水斜路陸上部先端の水底 23 進水斜路陸上部 A Land Onshore B Underwater C Launching Ramp Top Land Area 3 Launching Ramp 4a Rail 13,33 Launching Ramp Tip 14,34 Floating Structure 15 Ramp 21 Bottom of Launching Ramp Top Ramp 23 Launching Ramp Overland
Claims (1)
設するに際し、浮体及び浮体上方の斜路に敷設したレー
ルを有する進水斜路先端部を陸部で建造した後、該進水
斜路先端部を進水斜路陸上部の先端水域に曳航し、しか
る後に、進水斜路先端部の浮体にバラストを張って予め
整地されている進水斜路陸上部先端の水底に着座させる
ことを特徴とする進水斜路建設工法。When constructing a launch ramp protruding into the water from the land, a launch ramp having a floating body and a rail laid on the ramp above the float is constructed on the land, and then the launch ramp tip is constructed. A tow to the tip water area at the top of the launch ramp, and then ballast the floating body at the tip of the launch ramp to sit on the water floor at the tip of the land at the top of the launch ramp. Water slope construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000055160A JP2001239990A (en) | 2000-03-01 | 2000-03-01 | Construction method of launching slipway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000055160A JP2001239990A (en) | 2000-03-01 | 2000-03-01 | Construction method of launching slipway |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2001239990A true JP2001239990A (en) | 2001-09-04 |
Family
ID=18576323
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000055160A Withdrawn JP2001239990A (en) | 2000-03-01 | 2000-03-01 | Construction method of launching slipway |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2001239990A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008013106A (en) * | 2006-07-07 | 2008-01-24 | Zeniya Kaiyo Service Kk | Towing self-submerge type anchor block and method of retrieving mooring rope attached thereto |
CN103241350A (en) * | 2013-05-07 | 2013-08-14 | 大连中交理工交通技术研究院有限公司 | Self-sliding dropping type flexible slideway of ocean platform |
-
2000
- 2000-03-01 JP JP2000055160A patent/JP2001239990A/en not_active Withdrawn
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008013106A (en) * | 2006-07-07 | 2008-01-24 | Zeniya Kaiyo Service Kk | Towing self-submerge type anchor block and method of retrieving mooring rope attached thereto |
JP4570592B2 (en) * | 2006-07-07 | 2010-10-27 | ゼニヤ海洋サービス株式会社 | Towing self-sinking anchor block and method of collecting mooring lines attached to it |
CN103241350A (en) * | 2013-05-07 | 2013-08-14 | 大连中交理工交通技术研究院有限公司 | Self-sliding dropping type flexible slideway of ocean platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4440527A (en) | Marine structure | |
CN111980067B (en) | Construction method for long-distance conveying of immersed tube by adopting refuting process | |
CN107338760B (en) | Low-tidal-difference harbor section wall caisson wharf structure and construction method thereof | |
JP2001239990A (en) | Construction method of launching slipway | |
CN109518674B (en) | Artificial island segment, assembled artificial island and construction method of assembled artificial island | |
CN113047215B (en) | High stake pier structure of medium plate stake | |
US4290716A (en) | Platform resting on the bottom of a body of water, and method of manufacturing the same | |
CN214737767U (en) | High-pile beam-slab wharf structure with rear support piles | |
CN111321701B (en) | Dock main body backfilling process | |
JPS59145688A (en) | Launching/grounding system for vessel and ocean structure | |
CN216973272U (en) | Staggered caisson wharf with cover plate | |
IE37296B1 (en) | Marine structures | |
CN105648985B (en) | Islands and reefs development & construction method | |
CN218203847U (en) | A connect bank structure for pier approach bridge | |
JP2815492B2 (en) | How to build an underwater foundation | |
KR20150029379A (en) | A system for loading out marine topside facility | |
CN221052503U (en) | Slope type adjustable heavy-load wharf | |
KR100884050B1 (en) | Method for building well foundation of bridge using pontoon | |
JPH0647828B2 (en) | Offshore structure foundation construction method | |
SU91487A1 (en) | The method of construction of the pier piers | |
JP3132846B2 (en) | Construction method of pile type offshore structure | |
US2096185A (en) | Dock construction | |
JPS6134534B2 (en) | ||
JPH0835221A (en) | Construction of large scale floating structure | |
Cochrane et al. | DUBAI DRY DOCK: DESIGN AND CONSTRUCTION. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20070501 |