JP2001105070A - Method of manufacturing cage - Google Patents

Method of manufacturing cage

Info

Publication number
JP2001105070A
JP2001105070A JP28431299A JP28431299A JP2001105070A JP 2001105070 A JP2001105070 A JP 2001105070A JP 28431299 A JP28431299 A JP 28431299A JP 28431299 A JP28431299 A JP 28431299A JP 2001105070 A JP2001105070 A JP 2001105070A
Authority
JP
Japan
Prior art keywords
panel
reinforcing
cage
reinforcing bar
rebar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28431299A
Other languages
Japanese (ja)
Other versions
JP3731408B2 (en
Inventor
Shigeru Sugano
滋 菅野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP28431299A priority Critical patent/JP3731408B2/en
Publication of JP2001105070A publication Critical patent/JP2001105070A/en
Application granted granted Critical
Publication of JP3731408B2 publication Critical patent/JP3731408B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a cage manufacturing method which is efficient and simple in manufacturing the cage without any troublesome works, and excellent in working efficiency, labor cost and material cost. SOLUTION: This cage manufacturing method comprises a reinforcing panel placing process in which a reinforcing panel P is hoisted from an upper part to a panel receiving part RP provided at a place facing each other in each lower part of fixed and movable cage assembly bases 14 and 15, and a lower end of the reinforcing panel P is placed on the panel receiving part RP, a panel fixing process in which the reinforcing panel P placed on the panel receiving part RP in the reinforcing panel placing process is fixed along the cage assembly bases 14 and 15 by an attachable/detachable panel fixing unit TK, and a hoisting jig 16 for hoisting the reinforcing panel P is removed, a bar arranging process in which bars are arranged after adjusting the distance between the reinforcing panels fixed to the cage assembly bases 14 and 15 in the panel fixing process by moving the movable cage assembly base 15, and a carrying process in which a cage hoisting jig 17 is fitted to an upper end of a completed cage 10 through the processes, and the panel fixing piece TK fixing the reinforcing panel P and the cage assembly bases 14 and 15 in the panel fixing process, is removed, and carried to the other.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は鉄筋コンクリート構
造物の構築に際して予め鉄筋籠を製作する鉄筋籠製作方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for manufacturing a reinforced cage in which a reinforced cage is manufactured in advance when constructing a reinforced concrete structure.

【0002】[0002]

【従来の技術】多面的、立体的に土地の有効利用を図っ
て効率的な構造物配置を実現したり、或いはそれにより
既存構造物に干渉しない地下構造物を構築したりと、現
代の建設分野をとりまく環境は従来より更に効率性、緻
密性等が要求され施工に当たっての困難さを増している
のが現状である。この様な状況の中、地下或いは半地下
に建設される、各種タンク類または道路鉄道等の交通機
関といった大規模な鉄筋コンクリート構造物は需要を増
大させており、係る構造物を施工するに際し一般的に採
用される工法として地中連続壁工法等があげられる。こ
の地中連続壁工法は、構造強度、大深度への対応性及び
環境保全性などに優れているが、工法の施工性質上、連
続壁の芯材となる鉄筋籠は予め地上において製作してお
く必要がある。
2. Description of the Related Art Modern construction, such as realization of efficient structure arrangement by effectively utilizing land in a multifaceted and three-dimensional manner, or construction of an underground structure that does not interfere with existing structures. At present, the environment surrounding the field is required to be more efficient and denser than before and the difficulty in construction is increasing. Under such circumstances, large-scale reinforced concrete structures constructed underground or semi-underground, such as various tanks or transportation such as road railways, are increasing demand, and are generally used when constructing such structures. The underground continuous wall method and the like can be cited as a construction method used in the field. This underground diaphragm wall method is excellent in structural strength, adaptability to large depths and environmental preservation, but due to the construction properties of the method, the reinforcing rod cage which becomes the core material of the continuous wall must be manufactured on the ground in advance. Need to be kept.

【0003】この鉄筋籠を製作する従来方法としては、
例えば、該鉄筋籠を構成すべく構造物の曲面形状等に合
わせて組まれた表裏一対の鉄筋パネルのうち一方のパネ
ル表面にシャックル等を介して吊りロッドを適宜間隔に
て取付け、該吊りロッド各上端と連結された吊りビーム
をクレーン等を用いて吊下することで、固定式の鉄筋籠
組立架台に沿って該鉄筋パネルを吊込むものであった。
係る従来方法は、この吊込み作状態を継続したまま、引
き続き移動式鉄筋籠組立架台に対しても他方の鉄筋パネ
ルを前記と同様に吊込み、その後前記固定式鉄筋籠組立
架台に対し移動式鉄筋籠組立架台を鉄筋籠の所定幅にま
で移動接近させるものであった。
[0003] As a conventional method of manufacturing the reinforcing bar cage,
For example, hanging rods are attached at appropriate intervals to the surface of one of a pair of front and back reinforcing bars assembled according to the curved surface shape of the structure or the like to form the reinforcing rod cage through a shackle or the like. By suspending the suspension beam connected to each upper end using a crane or the like, the reinforcing bar panel is suspended along a fixed-type reinforcing bar assembly assembling base.
In such a conventional method, while continuing the hanging operation state, the other reinforcing bar panel is continuously hung on the movable rebar cage assembling base in the same manner as described above, and thereafter, the movable rebar cage assembling base is movable with respect to the fixed rebar cage assembling base. The rebar basket assembling base is moved close to a predetermined width of the rebar basket.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、従来の
鉄筋籠製作方法にあっては、予め複数セット組まれた全
ての鉄筋パネル毎に前述の吊りビームを取付けて、また
実際に鉄筋籠組立架台上で鉄筋籠製作工程に入る表裏一
対の鉄筋パネルを連結桁材により各々の吊りビームを一
体に連結することで固定し作業に臨む必要があった。一
般に限られた領域しか確保できないことが多い施工ヤー
ドにおいて、ただでさえ各種搬送機械や配筋材料等が錯
綜した状況の下、施工ヤードを大きく占有する鉄筋パネ
ルの全てに対して手作業でしか作業を実施できない吊り
ビーム及び連結桁の取付け作業を行うこととなれば、著
しい作業の煩雑性に伴う作業効率の低下と人件費、機材
コスト等の上昇は避けがたいものであった。
However, in the conventional method for manufacturing a reinforcing bar cage, the above-mentioned hanging beam is attached to each of a plurality of reinforcing bar panels assembled in advance, and the reinforcing bar is actually mounted on the reinforcing bar assembly stand. Therefore, it was necessary to fix a pair of front and back reinforcing bars by connecting the respective suspension beams integrally by a connecting girder material and to start work. Generally, in a construction yard where only a limited area can be secured in general, all the reinforcement panels that occupy a large amount in the construction yard only by hand under the situation where various transport machines and reinforcing materials are complicated. If the work of attaching the suspension beam and the connecting girder, which cannot be performed, is to be performed, it is inevitable that the work efficiency is reduced due to the remarkable complexity of the work, and the labor cost and the equipment cost are increased.

【0005】しかも係る吊りビームは鉄筋籠製作終了時
まで一貫使用しなければならないものであったため、大
規模工事において膨大な鉄筋パネルを使用して鉄筋籠製
作を行う場合などでは吊りビームへの初期投資も過大と
なり、更に、作業工程毎に一切転用することも不可能で
あったから作業サイクルタイムを大きく増大させてい
た。
Moreover, since such a hanging beam must be used consistently until the end of the production of the reinforcing bars, when the reinforcing bar is manufactured using a large number of reinforcing panels in a large-scale construction, the initial use of the hanging beams is required. The investment was too large, and furthermore, it was impossible to divert at every work process, so the work cycle time was greatly increased.

【0006】また、前述の固定式鉄筋籠組立架台に対し
移動式鉄筋籠組立架台を鉄筋籠の所定幅にまで移動接近
させる作業を行う際には、表裏一対の鉄筋パネルを吊り
ビームを介して固定している連結桁材と、該連結桁材を
支持する支持梁材とが、両者接合面の摩擦を原因として
円滑に滑動しないことが多く、そのため所定の位置関係
を確保維持できずにその後の微妙な位置調整を施す必要
があった。従って、揺動しやすくかなりの重量物である
鉄筋パネルについて煩雑かつ微妙な位置修正作業を頻繁
に行うことで全体の作業効率も大きく低下することとな
っていた。
[0006] Further, when performing an operation of moving the movable rebar cage assembling base to a predetermined width of the rebar cage with respect to the above-mentioned fixed type rebar cage assembling base, a pair of front and back reinforcing bar panels are connected via a suspension beam. The fixed connecting girder material and the supporting beam material for supporting the connecting girder material often do not slide smoothly due to friction between the joint surfaces thereof, so that a predetermined positional relationship cannot be secured and maintained. Had to be finely adjusted. Therefore, frequent and complicated position correction work is frequently performed on the rebar panel which is easy to swing and is a heavy object, and the overall work efficiency is greatly reduced.

【0007】そこで、本発明はこのような従来の課題に
着目してなされたもので、煩雑な作業を伴うことなく効
率的かつ簡便に鉄筋籠の製作を行うことができ、作業効
率、人件費及び機材コスト等も良好な鉄筋籠製作方法を
提供するものである。
Accordingly, the present invention has been made in view of such a conventional problem, and it is possible to efficiently and easily manufacture a rebar basket without complicated work, thereby improving work efficiency and labor cost. Further, the present invention provides a method of manufacturing a reinforcing rod cage having good equipment costs and the like.

【0008】[0008]

【課題を解決するための手段】この発明は上記目的を達
成するためになされたもので、鉄筋籠を構成すべく略平
面状に組まれた鉄筋パネルを各々吊込んで固定する、固
定式鉄筋籠組立架台と該固定式鉄筋籠組立架台に遠近自
在に移動可能な移動式鉄筋籠組立架台とを備えて鉄筋籠
の製作を行う鉄筋籠製作方法であって、前記固定式及び
移動式鉄筋籠組立架台の各下部において互いに対向する
位置に設けられたパネル受け部に対し、上方より前記鉄
筋パネルを吊込んで該鉄筋パネル下端を前記パネル受け
部に載置する鉄筋パネル載置工程と、係る鉄筋パネル載
置工程により前記パネル受け部上に各々載置された鉄筋
パネルを、脱着自在なパネル固定具により鉄筋籠組立架
台に沿って固定し、続いて鉄筋パネル吊込み用の吊り治
具を取去るパネル固定工程と、該パネル固定工程により
前記両鉄筋籠組立架台に各々固定された鉄筋パネル間距
離を移動式鉄筋籠組立架台の移動により所定の距離に調
整し各種配筋を行う配筋工程と、係る各工程を経て製作
が完了した鉄筋籠の上端に鉄筋籠吊り治具を取付けた
後、前記パネル固定工程において鉄筋パネルと鉄筋籠組
立架台とを固定したパネル固定具を取り外し、他方へと
搬送する搬送工程とからなることを特徴とする。
DISCLOSURE OF THE INVENTION The present invention has been made to achieve the above-mentioned object, and comprises a fixed type reinforcing bar which suspends and fixes reinforcing bar panels which are assembled in a substantially planar shape so as to form a reinforcing bar cage. A method of manufacturing a reinforcing bar cage comprising a basket assembling gantry and a movable reinforcing bar assembling cradle that can be freely moved to and from the fixed reinforcing bar assembling gantry, wherein the fixed and movable reinforcing squirrel cages are provided. A rebar panel mounting step of suspending the rebar panel from above and mounting a lower end of the rebar panel to the panel receiver with respect to a panel receiving portion provided at a position facing each other in each lower portion of the assembly base. The reinforcing bars respectively mounted on the panel receiving portion in the reinforcing bar mounting step are fixed along the reinforcing bar cage assembling stand by a detachable panel fixing tool, and then a hanging jig for hanging the reinforcing bar panel is provided. Panel to remove A fixing step, and a reinforcing arrangement step of adjusting the distance between the reinforcing bars fixed to the two reinforcing cage assemblies to a predetermined distance by moving the movable reinforcing cage assembly base and performing various reinforcing arrangements by the panel fixing step, After attaching the reinforcing cage hanging jig to the upper end of the reinforcing cage that has been manufactured through the respective steps, the panel fixing tool that fixes the reinforcing panel and the reinforcing cage assembly stand in the panel fixing step is removed and transported to the other. And a transporting step.

【0009】[0009]

【発明の実施の形態】以下、本発明の好ましい実施の形
態につき、添付図面を参照して詳細に説明する。図1は
本発明の鉄筋籠製作方法の一例を示す流れ図である。本
実施例においては、例えば地下或いは半地下に建設され
る断面円形の液化ガスタンク等を想定し、その構造物の
側壁部を施工するに際し本発明を採用し施工を行う場合
について示す。地下の掘削領域たる狭小空間にてコンク
リート打設作業等の施工を行う関係上、側壁の配筋構造
たる鉄筋籠10は予め地上において製作しておく必要が
ある。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 is a flowchart showing an example of the method for manufacturing a reinforcing rod cage according to the present invention. In the present embodiment, for example, a liquefied gas tank having a circular cross section constructed underground or semi-underground is assumed, and a case is described in which the present invention is employed to construct the side wall of the structure. In order to carry out concrete casting work and the like in a small space as an underground excavation area, it is necessary to previously manufacture the reinforcing rod cage 10 as a reinforcing structure on the side wall on the ground.

【0010】〜工程1〜 図2〜図11は、本発明の鉄筋籠製作方法の実際手順を
示す説明図である。ここでまずは鉄筋籠10を主に構成
する鉄筋網P(鉄筋パネルとして)を地上の鉄筋加工ヤ
ードYにおいて製作する。この鉄筋網Pは側壁部構造の
内外面にそれぞれ沿った内側鉄筋網P1及び外側鉄筋網
P2の2種があり、所定の配筋図に従って各径の鉄筋を
組み合わせて製作されるものである。係る内外の鉄筋網
P1、P2の配筋作業に先立って、予め鉄筋加工ヤード
Y内において鉄筋網組立架台11を適宜数据え付け、更
に、配筋の終わった内外鉄筋網P1、P2を仮置きする
為の仮置き架台12を設置しておくこととする。この前
準備が完了した後、ヤードY内に鉄筋が運び込まれ、曲
げ加工機等(図示しない)を介して所定形状に整えられ
た鉄筋が前記鉄筋網組立架台11に搬入されるのであ
る。
Step 1 FIGS. 2 to 11 are explanatory views showing the actual procedure of the method of manufacturing a reinforcing rod cage according to the present invention. First, a reinforcing bar net P (as a reinforcing bar panel) mainly comprising the reinforcing bar cage 10 is manufactured in the reinforcing bar processing yard Y on the ground. There are two types of the reinforcing bar network P, an inner reinforcing bar network P1 and an outer reinforcing bar network P2 along the inner and outer surfaces of the side wall structure, respectively, and are manufactured by combining reinforcing bars of different diameters according to a predetermined reinforcing diagram. Prior to the work of arranging the inner and outer rebar networks P1 and P2, a suitable number of rebar network assembling bases 11 are installed in advance in the rebar processing yard Y, and the inner and outer rebar networks P1 and P2 for which rebar arrangement has been completed are temporarily placed. A temporary gantry 12 is set up for this purpose. After the preparation is completed, the rebar is carried into the yard Y, and the rebar having a predetermined shape is carried into the rebar network assembly base 11 via a bending machine or the like (not shown).

【0011】〜工程2〜 上記の工程1に続いて、タンク側壁の円周方向筋CR
(以下円周筋とする)、鉛直方向筋VR(以下鉛直筋と
する)を、鉄筋網組立架台11上の定規材11a(例え
ばH鋼材等)上にクレーン等を用いて載置する。円周筋
CRを適宜間隔に配筋した後、それと直交する鉛直筋V
Rを配筋し鉄筋網Pを完成させる。
Step 2 Continuing from Step 1 described above, the circumferential stripe CR on the tank side wall is used.
A vertical streak VR (hereinafter referred to as a vertical streak) and a vertical streak VR (hereinafter referred to as a vertical streak) are placed on a ruler 11a (for example, H steel) on the reinforcing bar assembly base 11 using a crane or the like. After arranging the circumferential muscle CR at appropriate intervals, the vertical muscle V
R is arranged to complete the reinforcing bar network P.

【0012】鉄筋網Pの組立手順の詳細としては以下の
〜となる。 鉄筋加工ヤードYにて曲げ形状及び鉄筋長等を示した
加工表に従い鉄筋の曲げ加工を行う。 クローラークレーン等で上記加工の終わった鉄筋束T
を吊下し、鉄筋網組立架台11上に載置する。 円周筋CRを定規材11aに従って配筋する(図2参
照)。 鉛直筋VRも同様にクローラクレーン等で架台11上
に載置し、定規材11aに従って配筋を行う(図3参
照)。 円周筋CRと鉛直筋VRとの交差部を1箇所おきに番
線で結束する。 鉄筋網P運搬時の支点となる吊点補強Uボルト(図示
しない)を最上段円周筋と鉛直筋の交差部に固定する。
また吊点補強Uボルトの両側における鉛直筋VRと円周
筋CRの交差箇所の結束は番線で全箇所行う。
The details of the procedure for assembling the reinforcing bar P are as follows. In the rebar processing yard Y, the rebar is bent in accordance with the processing table indicating the bending shape, the rebar length, and the like. Reinforcing bar bundle T finished with the above processing by crawler crane etc.
Is suspended and placed on the reinforcing bar assembly frame 11. The circumferential muscle CR is arranged according to the ruler 11a (see FIG. 2). Similarly, the vertical streak VR is placed on the gantry 11 by a crawler crane or the like, and is arranged according to the ruler 11a (see FIG. 3). The intersection of the circumferential muscle CR and the vertical muscle VR is bound at every other location by a number line. A suspension point reinforcing U bolt (not shown) serving as a fulcrum at the time of transport of the reinforcing bar P is fixed to the intersection of the uppermost circumferential bar and the vertical bar.
Also, binding at the intersections of the vertical streak VR and the circumferential streaks CR on both sides of the suspension point reinforcing U-bolt is performed at all locations along the reference line.

【0013】〜工程3〜 次に、上記の如く完成された鉄筋網Pは横移動用吊治具
13を用いてクローラークレーン等で吊り、鉄筋網仮置
架台12に移動させる(図4参照)。その移動に際して
は鉄筋網Pが移動中に撓みやねじれ等の変形をできるだ
け生じない様に該鉄筋網重心点に玉掛けし吊り上げるこ
とを基本とする。また仮置き高さは例えば1.5m程度
(鉄筋網にして4〜5枚程度)になるように鉄筋網Pを
重ね置くこととする(図5参照)。前記鉄筋網横移動用
吊治具13は特別な構造ではなく、図4中に示す様に鋼
材13aを井桁状に適宜連結し上下面に連結ピース13
b等を付設したものである。
[Step 3] Next, the reinforced wire net P completed as described above is suspended by a crawler crane or the like using the horizontal moving hanging jig 13 and moved to the reinforced wire net temporary mounting base 12 (see FIG. 4). . At the time of the movement, the reinforcement net P is basically slung and lifted at the center of gravity of the reinforcement mesh so that deformation such as bending or twisting does not occur as much as possible during the movement. Further, the reinforcing nets P are laid one on another so that the temporary placement height is, for example, about 1.5 m (about 4 to 5 reinforcing steel nets) (see FIG. 5). The reinforcing jig 13 for lateral movement of the reinforcing bar mesh is not specially structured, and as shown in FIG.
b etc. are added.

【0014】〜工程4〜(鉄筋パネル載置工程及びパネ
ル固定工程) 上述の鉄筋網Pの製作が終われば該鉄筋網Pを各々吊込
み固定し鉄筋籠10の製作を行う訳であるが、係る鉄筋
籠製作の主要装置たる固定式鉄筋籠組立架台14と該固
定式鉄筋籠組立架台14に遠近自在に移動可能な移動式
鉄筋籠組立架台15は施工ヤードY内に既に備わってい
るものとし、更に本発明においては、前記固定式及び移
動式鉄筋籠組立架台14、15の各下部において互いに
対向する位置に鉄筋網受け部RP(パネル受け部)が設
けられているものとする。この様な状況の下、鉄筋籠1
0の製作は以下の要領で行う。
[Step 4] (Reinforcing panel mounting step and panel fixing step) When the above-described production of the reinforcing bar net P is completed, the reinforcing bar nets P are suspended and fixed, and the reinforcing bar cage 10 is manufactured. It is assumed that a fixed reinforced cage assembly base 14 and a movable reinforced cage assembly base 15 which can be freely moved to and from the fixed reinforced cage assembly gantry 14, which are main devices for manufacturing the reinforced cage, are already provided in the construction yard Y. Further, in the present invention, it is assumed that a reinforcing bar net receiving portion RP (panel receiving portion) is provided at a position facing each other at a lower portion of each of the fixed type and movable type reinforcing bar assembly assembling bases 14 and 15. Under such circumstances, rebar basket 1
0 is manufactured in the following manner.

【0015】鉄筋網仮置架台12にて、Uボルト等で補
強された最上段円周筋CR1に鉄筋網建起用吊治具16
を掛け、クローラクレーン等のメインフックF1で吊
る。また鉄筋網建起し時の支点として下段に鋼管C(例
えばφ60mm)を通してサブフックF2で吊り、鉄筋
網Pを建起す。係る鉄筋網建起用吊治具16の構造はH
鋼材にフック用フランジを設けたシンプルなものであり
前記のメインフックF1に上方より吊り上げられつつ鉄
筋網Pを吊下しうる構造強度を備えたものである(図6
参照)。
The reinforcing jig 16 for erection of the reinforcing net is attached to the uppermost circumferential reinforcing bar CR1 reinforced with U bolts or the like on the reinforcing net temporary mounting base 12.
And hang it on a main hook F1 such as a crawler crane. In addition, as a fulcrum at the time of erection of the reinforced mesh, the steel pipe C (for example, φ60 mm) is suspended at the lower stage by the sub hook F2, and the reinforced mesh P is established. The structure of the reinforcing jig 16 for erection of a reinforcing steel net is H
It is a simple one in which a hook flange is provided on a steel material, and has a structural strength capable of suspending the reinforced mesh P while being suspended from above by the main hook F1 (FIG. 6).
reference).

【0016】次に、内外側鉄筋網P1、P2を、固定式
及び移動式双方の鉄筋籠組立架台14,15の内対向面
に沿って前記鉄筋網受け部RPに向けて各々吊込んで、
該鉄筋網P下端を前記鉄筋網受け部RPに載置する(図
7参照)。鉄筋網Pが鉄筋網受け部RPに載置された
ら、該鉄筋網Pに鉄筋網固定金具TK(例えばカーラッ
シング等)を掛けて両組立架台14、15に沿って固定
する。鉄筋網受け部RPは、鋼材を加工連結して鉄筋網
Pの下端面形状と良好な接合性を示すよう図ったもので
あり、鉄筋籠組立架台14、15及び鉄筋網Pのサイズ
や形状に応じて適宜製作されるものである。
Next, the inner and outer rebar nets P1, P2 are respectively suspended toward the rebar net receiving portion RP along the inner facing surfaces of both the fixed type and the movable type rebar cage assembly bases 14, 15,
The lower end of the rebar net P is placed on the rebar net receiving portion RP (see FIG. 7). When the reinforced mesh P is placed on the reinforced mesh receiving portion RP, the reinforced mesh P is hanged on the reinforced mesh fixing bracket TK (for example, car lashing) to be fixed along both the assembly bases 14 and 15. The rebar net receiving portion RP is formed by processing and connecting steel materials so as to show good joining properties with the lower end surface shape of the rebar net P, and the size and shape of the rebar cage assembly bases 14 and 15 and the rebar net P It is manufactured as appropriate.

【0017】〜工程5〜(配筋工程) 次に所定本数のスターラップ筋SRを内側、外側鉄筋網
P1、P2に掛け渡してスターラップ配筋を行う(図8
参照)。スターラップ筋SRの取付け位置は、コンクリ
ート打設時の移動用空間、躯体内配管箇所及び重ね継手
部の機械継手本数の低減を考慮して位置決めを行う。通
常このスターラップ配筋は鉄筋網P下部から上部に向け
て順次行う。係る配筋作業が完了したら、移動式鉄筋籠
組立架台15を側壁設計幅までパワーシリンダー15a
等を用いて図中の矢印方向に移動させる(図9参照)こ
とでスターラップ筋SRと鉄筋網Pとの確実な接合を図
り、その後スターラップ筋SRと内外の鉄筋網P1、P
2とを番線で結束する。更に円周方向、鉛直方向ともに
補強筋を配筋し(図示しない)Uボルト(例えばφ12
mm)で固定すると好適である。
Step 5 to (Reinforcing Step) Next, a predetermined number of stirrup bars SR are laid over the inner and outer rebar networks P1, P2 to perform stirrup reinforcing (FIG. 8).
reference). The mounting position of the stirrup bar SR is determined in consideration of the reduction of the number of mechanical joints in the moving space at the time of placing concrete, the piping location in the building, and the lap joint. Usually, this stirrup reinforcement is sequentially performed from the lower part of the reinforcing bar network P to the upper part. When the rebar arrangement work is completed, the movable rebar cage assembling base 15 is moved to the side wall design width by the power cylinder 15a.
By moving the stirrup bar SR and the reinforcing bar network P with certainty by moving the stirrup bar SR and the reinforcing bar network P by using the like and the like (see FIG. 9), the stirrup bar SR and the inner and outer reinforcing bar networks P1, P
And 2 are connected by a line. Furthermore, reinforcing bars (not shown) are provided in both the circumferential direction and the vertical direction (not shown),
mm).

【0018】〜工程6〜(搬送工程) まず始めに、鉄筋籠10搬送後に行われる鉄筋籠吊り治
具17の取り外し作業に備えて、鉄筋籠10上部に親綱
及び玉掛けロリップを設置する。これは鉄筋籠10上部
に対し作業員等が容易に各種作業が実施できる鉄筋籠組
立架台14、15上において予め高所作業を完了させて
おく観点から行われる作業である。そこで、前記の工程
5において製作完了した鉄筋籠10はその上端に鉄筋籠
吊り治具17を連結し係る鉄筋籠吊り治具17を介して
クローラークレーンで吊下搬送される(図10参照)。
この鉄筋籠吊り治具17は、例えばH鋼材等を適宜組み
合わせて図12に示すような枠構造を形成したものであ
り、その上部面及び下部面にはそれぞれ、クレーン等の
吊り重機とのフック連結を図る上吊りピースUPもしく
は、下方に連結する鉄筋籠10との連結を行う下吊りピ
ースDPが適宜配置されている。鉄筋籠10の搬送先と
しては、図11に示すような例えば鉄筋籠10のサイズ
に応じて適宜間隔を置いたH鋼材18aを適宜根入れ長
にて地中に打設固定した鉄筋籠仮置架台18を設置して
おく。鉄筋籠仮置架台18へ搬送された鉄筋籠10は転
倒防止金具18bを取り付けた後、鉄筋籠吊り治具17
を取り外すこととなる。
Step 6 (Conveying Step) First, in preparation for the work of removing the reinforcing cage hanging jig 17 after the reinforcing cage 10 is transferred, a master rope and a slinging lip are installed on the upper part of the reinforcing cage 10. This is an operation performed from the viewpoint of previously completing high-altitude operations on the reinforcing bar basket assembling bases 14, 15 on which the workers and the like can easily perform various operations on the upper portion of the reinforcing bar cage 10. Then, the reinforcing bar cage 10 completed in the above-mentioned step 5 is connected to a reinforcing bar hanging jig 17 at the upper end thereof and is suspended and conveyed by a crawler crane via the reinforcing bar hanging jig 17 (see FIG. 10).
This rebar cage hanging jig 17 is formed by appropriately combining, for example, H steel material or the like to form a frame structure as shown in FIG. 12, and has an upper surface and a lower surface, each of which has a hook with a lifting heavy machine such as a crane. An upper hanging piece UP for connection or a lower hanging piece DP for connecting to a reinforcing basket 10 connected below is appropriately arranged. As a transport destination of the reinforcing rod cage 10, for example, as shown in FIG. 11, for example, an H steel material 18a that is appropriately spaced according to the size of the reinforcing rod basket 10 is poured into the ground with an appropriate rooting length and fixed temporarily. The gantry 18 is installed. After the rebar cage 10 conveyed to the rebar cage temporary mounting base 18 is attached with the fall prevention fitting 18b, the rebar cage hanging jig 17
Will be removed.

【0019】以上の本発明における各種作業工程を経る
ことで、鉄筋籠製作時における各種機器の転用を有効に
図ることができる為、煩雑な作業を伴うことなく効率的
かつ簡便に鉄筋籠10の製作を行うことができ、結果と
して作業効率、人員コスト、機器コストの全ての面にお
いて大きな改善効果を奏するのである。
Through the various working steps in the present invention, various devices can be effectively diverted at the time of manufacturing the reinforcing rod cage, so that the reinforcing rod basket 10 can be efficiently and simply assembled without complicated work. The production can be performed, and as a result, a great improvement effect can be achieved in all aspects of work efficiency, personnel cost and equipment cost.

【0020】[0020]

【発明の効果】以上詳細に説明したように、本発明の鉄
筋籠製作方法は、鉄筋籠を構成すべく略平面状に組まれ
た鉄筋パネルを各々吊込んで固定する、固定式鉄筋籠組
立架台と該固定式鉄筋籠組立架台に遠近自在に移動可能
な移動式鉄筋籠組立架台とを備えて鉄筋籠の製作を行う
鉄筋籠製作方法であって、前記固定式及び移動式鉄筋籠
組立架台の各下部において互いに対向する位置に設けら
れたパネル受け部に対し、上方より前記鉄筋パネルを吊
込んで該鉄筋パネル下端を前記パネル受け部に載置する
鉄筋パネル載置工程と、係る鉄筋パネル載置工程により
前記パネル受け部上に各々載置された鉄筋パネルを、脱
着自在なパネル固定具により鉄筋籠組立架台に沿って固
定し、続いて鉄筋パネル吊込み用の吊り治具を取去るパ
ネル固定工程と、該パネル固定工程により前記両鉄筋籠
組立架台に各々固定された鉄筋パネル間距離を移動式鉄
筋籠組立架台の移動により所定の距離に調整し各種配筋
を行う配筋工程と、係る各工程を経て製作が完了した鉄
筋籠の上端に鉄筋籠吊り治具を取付けた後、前記パネル
固定工程において鉄筋パネルと鉄筋籠組立架台とを固定
したパネル固定具を取り外し、他方へと搬送する搬送工
程とからなることを特徴とするものである。
As described in detail above, the method for manufacturing a reinforcing bar cage according to the present invention is a method of assembling a fixed reinforcing bar cage in which reinforcing bar panels that are assembled in a substantially planar shape to form a reinforcing bar cage are suspended and fixed. A method of manufacturing a reinforcing bar cage, comprising a gantry and a movable reinforcing bar cage assembly cradle that can be moved to and away from the fixed reinforcing bar cage gantry, wherein the fixed and movable reinforcing bar cage gantry is provided. A reinforcing bar panel mounting step of suspending the reinforcing bar panel from above and mounting the lower end of the reinforcing bar panel to the panel receiving portion with respect to a panel receiving portion provided at a position facing each other at each lower portion of the reinforcing bar panel; The reinforcing bars respectively mounted on the panel receiving portion in the mounting step are fixed along the reinforcing bar assembly base by a detachable panel fixing tool, and then the hanging jig for hanging the reinforcing bar panel is removed. Panel fixing process, Through a panel fixing step, the distance between the reinforcing bars respectively fixed to the two reinforcing bar assembly frames is adjusted to a predetermined distance by moving the movable reinforcing bar assembly frame, and a reinforcing process of performing various bar arrangements, and through the respective processes. After attaching a reinforcing cage hanging jig to the upper end of the completed reinforcing cage, the panel fixing device that fixed the reinforcing bar panel and the reinforcing bar assembly base in the panel fixing step is removed, and the transporting process of transporting the other to the other is performed. It is characterized by becoming.

【0021】したがって本発明によれば、従来の鉄筋籠
製作方法にあるような、全ての鉄筋パネル毎に吊りビー
ムを取付けて、また実際に鉄筋籠組立架台上で鉄筋籠製
作工程に入る表裏一対の鉄筋パネルを連結桁材により各
々の吊りビームを一体に連結することで固定し作業に臨
むといった必要は無くなり、従って、著しい作業の効率
化と人件及び機材に係るコストの縮減とを併せて確実に
図ることが可能となる。
Therefore, according to the present invention, a hanging beam is attached to every reinforcing bar panel as in the conventional method of manufacturing a reinforcing cage, and a pair of front and back sides is actually entered into a reinforcing cage manufacturing process on a reinforcing cage assembly base. It is no longer necessary to fix the reinforcing bars by connecting the respective suspension beams together with the connecting girder material and work on them.Therefore, it is possible to ensure both significant work efficiency and reduction in personnel and equipment costs. It becomes possible to aim at.

【0022】しかも本発明においては吊りビームは鉄筋
籠製作終了時まで一貫使用しなければならないといった
ことはなく、大規模工事において膨大な鉄筋パネルを使
用して鉄筋籠製作を行う場合などでも、吊りビーム製作
の為の初期投資も転用を考慮にいれた最小限に抑制でき
工事全体のコスト抑制に寄与するところが大きい。ま
た、前述の固定式鉄筋籠組立架台に対し移動式鉄筋籠組
立架台を鉄筋籠の所定幅にまで移動接近させる作業を行
う際には、対向する鉄筋パネル同士の位置関係はその後
の修正を待たずに確保維持できるのである。
In addition, in the present invention, the suspension beam does not have to be used until the completion of the production of the reinforcing cage, and even in the case of producing a reinforcing cage using a huge number of reinforcing panels in a large-scale construction, it is possible to use the suspending beam. The initial investment for beam fabrication can be minimized considering the diversion, greatly contributing to cost reduction of the whole construction. In addition, when performing the work of moving the movable rebar cage assembly base to the predetermined width of the rebar cage relative to the fixed rebar cage assembly base described above, the positional relationship between the opposing rebar panels waited for subsequent correction. Can be secured and maintained.

【0023】加えて、地下構造物のみならず地上構造物
の施工に際しても適用することが可能であり広い汎用性
を備える。
In addition, the present invention can be applied to construction of not only underground structures but also above-ground structures, and has wide versatility.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鉄筋籠製作方法の一例を示す流れ図で
ある。
FIG. 1 is a flowchart showing an example of a method for manufacturing a reinforcing bar cage according to the present invention.

【図2】本発明の鉄筋籠製作方法の実際手順のうち、円
周筋配筋作業を示す説明図である。
FIG. 2 is an explanatory view showing a circumferential bar arrangement work in the actual procedure of the reinforcing bar cage manufacturing method of the present invention.

【図3】本発明の鉄筋籠製作方法の実際手順のうち、鉛
直筋配筋作業を示す説明図である。
FIG. 3 is an explanatory diagram showing a vertical reinforcing bar arrangement work in the actual procedure of the reinforcing cage manufacturing method of the present invention.

【図4】本発明の鉄筋籠製作方法の実際手順のうち、横
移動用吊治具取付け作業を示す説明図である。
FIG. 4 is an explanatory view showing an operation of attaching a horizontal moving hanging jig in the actual procedure of the method of manufacturing a reinforcing rod cage according to the present invention.

【図5】本発明の鉄筋籠製作方法の実際手順のうち、鉄
筋網仮置場載置作業を示す説明図である。
FIG. 5 is an explanatory diagram showing a rebar net temporary storage place mounting operation in the actual procedure of the rebar cage manufacturing method of the present invention.

【図6】本発明の鉄筋籠製作方法の実際手順のうち、鉄
筋網建起し作業を示す説明図である。
FIG. 6 is an explanatory diagram showing a reinforcing net construction work in the actual procedure of the reinforcing cage manufacturing method of the present invention.

【図7】本発明の鉄筋籠製作方法の実際手順のうち、鉄
筋籠組立架台への鉄筋籠吊込み作業を示す説明図であ
る。
FIG. 7 is an explanatory view showing, among the actual procedures of the method for manufacturing a reinforcing bar cage according to the present invention, an operation of suspending the reinforcing bar cage on a reinforcing bar assembly frame.

【図8】本発明の鉄筋籠製作方法の実際手順のうち、ス
ターラップ配筋作業を示す説明図である。
FIG. 8 is an explanatory diagram showing a stirrup reinforcing work in the actual procedure of the reinforcing cage manufacturing method of the present invention.

【図9】本発明の鉄筋籠製作方法の実際手順のうち、鉄
筋籠組立架台のスライド拡幅作業を示す説明図である。
FIG. 9 is an explanatory diagram showing a slide widening operation of the reinforcing bar assembly assembling step in the actual procedure of the reinforcing bar basket manufacturing method of the present invention.

【図10】本発明の鉄筋籠製作方法の実際手順のうち、
鉄筋籠組立架台よりの鉄筋籠搬出作業を示す説明図であ
る。
FIG. 10 shows an actual procedure of a method of manufacturing a reinforcing rod cage according to the present invention.
It is explanatory drawing which shows the rebar basket carrying-out operation | work from a rebar basket assembly stand.

【図11】本発明の鉄筋籠製作方法の実際手順のうち、
鉄筋籠の鉄筋籠仮置き架台への搬送固定作業を示す説明
図である。
FIG. 11 shows an actual procedure of a method of manufacturing a reinforcing rod cage according to the present invention.
It is explanatory drawing which shows the conveyance fixing operation of a reinforcement basket to a reinforcement cage temporary installation stand.

【図12】(a)は本発明の鉄筋籠製作において使用す
る鉄筋籠吊り治具の平面図を示し、(b)は同側面図で
ある。
FIG. 12A is a plan view of a reinforcing cage hanging jig used in manufacturing a reinforcing cage of the present invention, and FIG. 12B is a side view of the same.

【符号の説明】[Explanation of symbols]

P 鉄筋網(鉄筋パネル) RP 鉄筋網受け部(鉄筋パネル受け部) TK 鉄筋網固定金具(パネル固定具) 10 鉄筋籠 14 固定式鉄筋籠組立架台 15 移動式鉄筋籠組立架台 16 鉄筋網建起用吊治具(吊込み用吊り治具) 17 鉄筋籠吊り治具 P Reinforcing mesh (reinforcing panel) RP Reinforcing mesh receiving section (reinforcing panel receiving section) TK Reinforcing mesh fixing bracket (panel fixing) 10 Reinforcing cage 14 Fixed reinforcement cage assembly stand 15 Mobile reinforcement cage assembly stand 16 Hanging jig (hanging jig for hanging) 17 Hanging jig for reinforced cage

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋籠を構成すべく略平面状に組まれた
鉄筋パネルを各々吊込んで固定する、固定式鉄筋籠組立
架台と該固定式鉄筋籠組立架台に遠近自在に移動可能な
移動式鉄筋籠組立架台とを備えて鉄筋籠の製作を行う鉄
筋籠製作方法であって、 前記固定式及び移動式鉄筋籠組立架台の各下部において
互いに対向する位置に設けられたパネル受け部に対し、
上方より前記鉄筋パネルを吊込んで該鉄筋パネル下端を
前記パネル受け部に載置する鉄筋パネル載置工程と、係
る鉄筋パネル載置工程により前記パネル受け部上に各々
載置された鉄筋パネルを、脱着自在なパネル固定具によ
り鉄筋籠組立架台に沿って固定し、続いて鉄筋パネル吊
込み用の吊り治具を取去るパネル固定工程と、該パネル
固定工程により前記両鉄筋籠組立架台に各々固定された
鉄筋パネル間距離を移動式鉄筋籠組立架台の移動により
所定の距離に調整し各種配筋を行う配筋工程と、係る各
工程を経て製作が完了した鉄筋籠の上端に鉄筋籠吊り治
具を取付けた後、前記パネル固定工程において鉄筋パネ
ルと鉄筋籠組立架台とを固定したパネル固定具を取り外
し、他方へと搬送する搬送工程とからなることを特徴と
する鉄筋籠製作方法。
1. A fixed rebar cage assembly base and a movable bar that can be freely moved in and out of the fixed rebar cage assembly rack, each of which suspends and fixes a reinforcing bar panel that is assembled in a substantially planar shape so as to form a rebar basket. A method of manufacturing a reinforcing bar cage comprising a reinforcing bar cage assembling base and a panel receiving portion provided at a position facing each other in each lower portion of the fixed and movable reinforcing cage assembly frames. ,
A reinforcing bar panel placing step of suspending the reinforcing bar panel from above and placing the lower end of the reinforcing panel in the panel receiving portion; and a reinforcing bar panel placed on the panel receiving portion by the reinforcing bar panel placing step. A panel fixing step of fixing along the reinforcing cage assembly base with a detachable panel fixing tool, and subsequently removing a hanging jig for hanging the reinforcing bar panels, The fixed reinforcing bar panel distance is adjusted to a predetermined distance by moving the movable reinforcing cage assembly base to perform various reinforcing arrangements, and the reinforcing rod cage is suspended at the upper end of the reinforcing cage completed through the respective steps. A method of manufacturing a reinforcing bar cage, comprising, after attaching a jig, removing a panel fixing tool fixed to the reinforcing bar panel and the reinforcing bar assembly gantry in the panel fixing step and transporting the panel fixing device to the other. .
JP28431299A 1999-10-05 1999-10-05 Reinforcing rod production method Expired - Fee Related JP3731408B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28431299A JP3731408B2 (en) 1999-10-05 1999-10-05 Reinforcing rod production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28431299A JP3731408B2 (en) 1999-10-05 1999-10-05 Reinforcing rod production method

Publications (2)

Publication Number Publication Date
JP2001105070A true JP2001105070A (en) 2001-04-17
JP3731408B2 JP3731408B2 (en) 2006-01-05

Family

ID=17676926

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28431299A Expired - Fee Related JP3731408B2 (en) 1999-10-05 1999-10-05 Reinforcing rod production method

Country Status (1)

Country Link
JP (1) JP3731408B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103350165A (en) * 2013-06-28 2013-10-16 中国一冶集团有限公司 Processing device and method capable of manufacturing reinforcement cages with different diameters

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104358251A (en) * 2014-11-21 2015-02-18 中国十七冶集团有限公司 Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103350165A (en) * 2013-06-28 2013-10-16 中国一冶集团有限公司 Processing device and method capable of manufacturing reinforcement cages with different diameters

Also Published As

Publication number Publication date
JP3731408B2 (en) 2006-01-05

Similar Documents

Publication Publication Date Title
JP2894226B2 (en) Bridge construction method
JP2009108611A (en) Reinforcement erecting tool and reinforcement erecting method
JP2001105070A (en) Method of manufacturing cage
CN216634842U (en) Automatic production system of prefabricated hollow pier
JP3752934B2 (en) Method for constructing annular concrete frame using slip form device
CN216194915U (en) Quick installation mechanism of piping lane prefab
CN215717173U (en) Construction equipment for hanging, splicing and lifting vertical templates of building
CN210530883U (en) Construction system for horizontal splicing, vertical rotation and combination of circular strip steel lining tunnel
CN212101611U (en) Steel structure small component transport vehicle
CN211545652U (en) Prefabricated T roof beam template hoist device
JP4325340B2 (en) How to build a reinforcing bar
CN113445530A (en) Caisson steel bar hoisting and mounting process and hoisting frame
CN113235913A (en) Construction equipment and method for hanging, splicing and lifting building vertical template
CN111410117A (en) Vertical lifting appliance for side mold of prefabricated box girder
CN106285000A (en) Whole spelling template transporter and conveyer method thereof
CN112195802A (en) Variable-section U-shaped hollow thin-wall pier steel bar partition prefabricated jig frame and partition installation method
CN212792823U (en) Shear force wall framework of steel reinforcement is whole prefabricated device
CN110552422A (en) Assembly type underground structure accessory
CN213410185U (en) Prefabricated ligature mould of single-box multi-chamber large-section suspension casting box girder inclined web reinforcing steel bar
CN212024543U (en) Vertical lifting appliance for side mold of prefabricated box girder
CN212865614U (en) Construction device for hoisting small box girder steel reinforcement framework and matching clamping fixture with frame
CN219906683U (en) Integral forming hoisting structure for column steel mould and reinforcement cage
CN210797580U (en) Large-scale round foundation ditch interior lining wall construction system
CN217025056U (en) Large-diameter rainwater and sewage pipe hoisting device
CN217782591U (en) Reusable reinforcing mesh supporting hanger

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040922

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050214

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050920

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051003

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091021

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091021

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101021

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101021

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111021

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111021

Year of fee payment: 6

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121021

Year of fee payment: 7

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121021

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131021

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees