CN106285000A - Whole spelling template transporter and conveyer method thereof - Google Patents

Whole spelling template transporter and conveyer method thereof Download PDF

Info

Publication number
CN106285000A
CN106285000A CN201610653815.9A CN201610653815A CN106285000A CN 106285000 A CN106285000 A CN 106285000A CN 201610653815 A CN201610653815 A CN 201610653815A CN 106285000 A CN106285000 A CN 106285000A
Authority
CN
China
Prior art keywords
template
channel
side plate
section steel
whole spelling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610653815.9A
Other languages
Chinese (zh)
Inventor
卢国春
赵宗文
闫力
韩应祥
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610653815.9A priority Critical patent/CN106285000A/en
Publication of CN106285000A publication Critical patent/CN106285000A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a kind of whole spelling template transporter and conveyer method thereof, it is for closing building structure internal forwarding whole spelling template, described template transporter includes: slide, and top is arranged with the resettlement groove in order to accommodating described template, and bottom is provided with multiple roller;Spacing side plate, is fixedly arranged on the side of described resettlement groove, is placed in described resettlement groove in order to limit described template bottom;Support side plate, is fixedly arranged on the opposite side of described resettlement groove, is erected to be placed in described resettlement groove in order to support described template;Diagonal support, is supported between described support side plate and described slide obliquely.The present invention solves and uses whole spelling template in enclosed construction at present; cause taking a lot of work when installation, dismounting transfer fee; and after dismounting, need again the technical problem of assembled aluminum alloy pattern plate; reach only to move to transporter hanging mold mechanism after construction location is dismantled by overall for the good template of assembly; next section can be slid onto install, there is the advantages such as convenient and swift, time saving and energy saving.

Description

Whole spelling template transporter and conveyer method thereof
Technical field
The present invention relates to a kind of building template technical field, relate in particular to a kind of transhipment for transporting building template Device and conveyer method thereof.
Background technology
Aluminum alloy pattern plate is a kind of emerging building template Technology, has another name called aluminum alloy mould plate, the building that i.e. aluminium alloy makes Template.Aluminum alloy pattern plate is suitable for body of wall, horizontal floor, pillar, beam, stair, windowsill, the use of the positions such as plate of wafing, and to collar tie beam, structure The secondary structure formwork such as post, anti-bank is the most useful, and have facilitate durable, can the advantages such as the number of turnover is big, solve biography in the past The defect that system template exists, substantially increases efficiency of construction, thus the application in building field is the most extensive.
It should be noted that aluminum alloy pattern plate needs first to be assemblied into whole spelling template in use and installs to be onstructed section again, therefore, When using aluminum alloy pattern plate in the Linear Closed building structure of such as piping lane, it is limited to spatial shape and causes the transhipment of whole spelling template to be stranded Difficulty is significantly increased;Additionally, aluminum alloy pattern plate needs first to dismantle before being transported to next construction section after whole spelling, wait to be transported to next construction section After, more again it is assemblied into whole spelling template.Therefore use the construction of aluminum alloy pattern plate to be clearly present installation in Linear Closed space at present Or remove transhipment and fairly time consuming take a lot of work, and workman's skill is required height, therefore there is a need to improve further.
Summary of the invention
In view of the foregoing, the present invention provides a kind of whole spelling template transporter and conveyer method thereof, to solve to exist at present After using whole spelling template in Linear Closed structure, cause taking a lot of work when installation, dismounting transfer fee, and after dismounting, need again assembled aluminum dipping form The technical problem of plate, reaches only to winch to transporter after construction location is dismantled by overall for aluminum alloy pattern plate good for assembly, Slide onto next section to install, there is the advantages such as convenient and swift, time saving and energy saving.
For achieving the above object, the present invention adopts the technical scheme that a kind of whole spelling template transporter of offer, and it is used for Closing building structure internal forwarding whole spelling template, described template transporter includes: slide, and top is arranged with in order to accommodating institute Stating the resettlement groove of template, bottom is provided with multiple roller;Spacing side plate, is fixedly arranged on the side of described resettlement groove, described in order to limit Template bottom is placed in described resettlement groove;Support side plate, is fixedly arranged on the opposite side of described resettlement groove, in order to support described template It is erected to be placed in described resettlement groove;Diagonal support, is supported between described support side plate and described slide obliquely.
Further improvement is that of the present invention whole spelling template transporter, described slide, have and connect the first T-shaped groove Steel and the second channel-section steel, the described first described resettlement groove of the recessed formation in channel-section steel top, described roller is located at described first channel-section steel and Bottom two channel-section steels;Described diagonal support, two ends are respectively supported between described support side plate and described second channel-section steel.
Further improvement is that of the present invention whole spelling template transporter, described first channel-section steel, there is web and shaping The wing plate of both sides on described web length direction, described web and described two wing plates enclose and set the described resettlement groove of formation;Described Two channel-section steels, one end is connected fixing with a wherein wing plate of described first channel-section steel.
Further improvement is that of the present invention whole spelling template transporter, described slide has the first groove that connection is T-shaped Steel and the second channel-section steel, the described first channel-section steel described resettlement groove of recessed formation;The one of described resettlement groove is located in the weldering of described spacing side plate Side;The opposite side of described resettlement groove is located in the weldering of described support side plate;Described second channel-section steel end is with described first channel-section steel relatively Weldering is located on the bottom, two sides of described support side plate;The two ends of described diagonal support are welded respectively and are located at described support side plate and closely push up At end and the end away from the first channel-section steel of described second channel-section steel.
Further improvement is that of the present invention whole spelling template transporter, the height of described spacing side plate is between described arrangement The degree of depth of groove is to the 1/10 of described form height.
Further improvement is that of the present invention whole spelling template transporter, the height of described support side plate is between form height To form height 1/2.
Further improvement is that of the present invention whole spelling template transporter, defines by described diagonal support top along described Support side plate has one first distance to described slide top, by described diagonal support bottom along described slide top to described support Side plate has a second distance, and described first distance is 2 to 3 with the ratio range of described second distance.
Additionally, present invention simultaneously provides a kind of whole spelling template conveyer method, it is for many within closing building structure Whole spelling template is transported between individual construction section;Described method includes:
By whole spelling template by whole spelling template transporter as the aforementioned construction section after previous construction section is transported to;
At a rear construction section by the guide chain preset, whole spelling template is hung the mould described whole spelling template transporter of removal and carries out Model sheetinstallat;Or, at previous construction section by the guide chain preset, whole spelling template is hung mould to described whole spelling template transporter Carry out template transhipment.
Due to the fact that and have employed above technical scheme so that it is have the advantages that
(1) only winch on slide after assembled good whole spelling template directly need to be dismantled, then slide onto next construction section and enter Row is installed, and reaches convenient and swift, time saving and energy saving beneficial effect.
(2) by template transporter of the present invention, it is not necessary to repeatedly install or remove template, have and workman's skill is wanted Ask low, and relative in the past manually transhipment, have take a short time, artificial less, fast and convenient advantage.
(3) template transporter of the present invention can reuse after one section of construction terminates in next section of construction, or Configure one group at each construction section, launch streamline construction to be formed, increase substantially construction speed, save management cost.
Accompanying drawing explanation
Fig. 1 is the schematic appearance of template transporter of the present invention.
Fig. 2 is to regard schematic diagram in the end of template transporter of the present invention.
Fig. 3 is that template of the present invention coordinates guide chain to carry out hanging the use view of mould.
Reference is as follows with the corresponding relation of parts:
10-template;20-slide;21-the first channel-section steel;211-web;212-wing plate;22-the second channel-section steel;23- Resettlement groove;24-roller;241-connects leg;The spacing side plate of 30-;40-support side plate;50-diagonal support;60-leads Chain;The pre-buried ring of 61-;62-lifting rope;L22The lateral length of the-the second channel-section steel;H30The height of-spacing side plate;H40-support-side The height of plate;A-the first distance;B-second distance.
Detailed description of the invention
For the benefit of the understanding to the present invention, illustrates below in conjunction with drawings and Examples.
Referring to Fig. 1 to Fig. 3, the present invention provides a kind of whole spelling template transporter, builds for closing at such as piping lane etc. Template 10 after the whole spelling of building structure internal forwarding.As shown in Figure 1 and Figure 2, described template transporter includes slide 20, limiting side Plate 30, support side plate 40 and diagonal support 50;And as it is shown on figure 3, template transporter of the present invention can coordinate guide chain further 60 carry out hanging mould operation at template transport process.
As shown in Figure 1, Figure 2, described slide 20 has connection the first T-shaped channel-section steel 21 and the second channel-section steel 22 and is located at described Multiple rollers 24 bottom first channel-section steel 21 and the second channel-section steel 22;Described first channel-section steel 21 has web 211 and forms in institute State the wing plate 212 of both sides on web 21 length direction, described web 211 and described two wing plates 212 to enclose and be set as shape one cross section and take the shape of the letter U Resettlement groove 23, in order to place and the bottom of fixed form 10.
Described second channel-section steel 22 is connected fixing with a wherein wing plate 212 of described first channel-section steel 21.Definition and described second The wing plate 212 that channel-section steel 22 connects is inner side wing plate 212, and another wing plate 212 is outside wing plate 212.On described outside wing plate 212 admittedly It is provided with spacing side plate 30, in order to be further restricted in described resettlement groove 23 template 10 bottom, it is to avoid template 10 is when transhipment Cross described outside wing plate 212 and depart from resettlement groove 23;Support side plate 40, and described it is installed with on described inner side wing plate 212 Between support side plate 40 proximal portion and described second channel-section steel 22 end away from described first channel-section steel 21, there is a diagonal support 50 connect, and described support side plate 40 and described diagonal support 50 are in order to be supported on template 10 stage casing proximal portion, it is ensured that template 10 In upright state in transport process, follow-up connection with guide chain 60 carries out hanging mould operation.
In the present embodiment, the present invention the first channel-section steel the 21, second channel-section steel 22 preferably uses No. 10 channel-section steel (specifications: 100 × 48 × 5.3mm), but it is not limited to this, suitable channel-section steel specification can be selected according to the concrete dimensions of whole spelling template 10.The present invention limits Position side plate 30 and support side plate 40 can use the building board such as steel plate or iron plate, support whole spelling mould to have compared with high structural strength Plate.The angle steel that the corresponding aforementioned channel-section steel specification of diagonal support 50 of the present invention preferably uses specification to be 50 × 50mm, but it is not limited to this, with Group can be connected and consolidate and provide, with described support side plate 40 and the second channel-section steel 22, the Building wood that support side plate 40 stablizes support strength Material comes under the present invention and protects category.
As it is shown in figure 1, indicating template 10 is placed in slide 20 schematic diagram that supported by support side plate 40 (for understanding earth's surface Slide 20, spacing side plate 30, support side plate 40 and the structure of diagonal support 50 are shown, template 10 top are blocked), due to typically The height of whole spelling template is about within 300 centimeters (3 meters are high, about first floor height), therefore, and the limit of template transporter of the present invention The height H of position side plate 3030Preferably the 1/10 of form height, not hinder on the premise of whole spelling template hangs mould operation, simultaneously Ensure that template 10 can be limited on slide 20 in transport process;The height H of described support side plate 4040Preferably template 10 The 1/2 of height, to guarantee that template 10 is obtained in that enough support strengths in transport process.It is preferred that described spacing side plate The height H of 3030Between the degree of depth extremely described template 10 height of described resettlement groove 23 1/10.The height of described support side plate 40 H40Between template 10 height to the 1/2 of template 10 height.
Additionally, support the effect of described support side plate 40, described second channel-section steel 22 to make diagonal support 50 to play Lateral length L22Preferably described support side plate 40 height H401/3;Make described diagonal support 50 and described support side plate 40, Triangle form after second channel-section steel 22 connection, defines described diagonal support 50 top along described support side plate 40 to described cunning Seat 20 tops have one first distance a, and along described slide 20 top, extremely described support side plate 40 has in described diagonal support 50 bottom A second distance b, described first distance a and described second distance b is had to have the ratio range (a:b=2~3) of 2 to 3, it is ensured that The support side plate 40 support strength to whole spelling template.
More specifically, illustrate as a example by whole spelling template 10 height is 280 centimeters, the height of described spacing side plate 30 can be About 30 centimeters high, and the height of described support side plate 40 can be about 150 centimeters high, and the lateral length of described second channel-section steel 22 is permissible It is about 40 centimeters.
In the present embodiment, described roller 24 is articulated in a connection leg 241, and is fixed by described connection leg 241 Group is connected on bottom described slide 20.Specifically, two rollers 24, described second channel-section steel 22 end it are provided with bottom described first channel-section steel 21 Portion is additionally provided with two rollers 24, but the quantity that arranges of described roller 24 is not limited to this, so that slide 20 can be made to carry out template 10 Transporter, and described roller 24 arrange quantity and between spacing can adjust according to the size of whole spelling template to be transported Whole.
In the present embodiment, described spacing side plate 30, described support side plate 40 are installed in described respectively by welding procedure On two wing plate 212 lateral surface of the first channel-section steel 21, the end of described second channel-section steel 22 is installed in described by welding procedure On support side plate 40 bottom, thus it is connected to described first channel-section steel 21, forms first channel-section steel the 21, second channel-section steel 22 and be positioned at support side plate 40 opposite sides faces and by setting with support side plate 40 weldering and be connected.Welding procedure is passed through at the two ends of described diagonal support 50 respectively It is fixedly arranged on described support side plate 40 proximal portion and the end of the second channel-section steel 22.
Being explained above the concrete structure form of the present invention whole spelling template transporter, following description template of the present invention is transported The operational approach of device.
As it is shown on figure 3, template transporter of the present invention can coordinate guide chain 60 to be transported through.Described guide chain 60 includes pre-buried ring 61 and lifting rope 62;Behind the transhipment path confirming template 10, carry out hanging modulo operation at needs by pre-buried ring 61 pre-plugged Close the position above of building structure inner space;Slide 20 is utilized to be transported to below described pre-buried ring 61 whole spelling template, and Make template 10 top be connected with lifting rope 62, whole spelling template can be sling from slide 20 the described resettlement groove of disengaging by guide chain 60 23 carry out model sheetinstallat operation, and effective minimizing carries out the activity duration of model sheetinstallat within the enclosed space;Or, template 10 prepares During dismounting, the template 10 of whole spelling is connected with lifting rope 62, and the whole mould that hangs disposes to the resettlement groove 23 of described slide 20, then profit With slide 20, complete whole spelling template is transported to next construction section use, thus eliminate whole spelling template is dismantled one by one after again It is transported through and the again assembled activity duration.
To sum up, the present invention is by aforementioned whole spelling template transporter, after only need to assembled good whole spelling template directly being dismantled Winch on slide, then slide onto next construction section and install, reach convenient and swift, time saving and energy saving beneficial effect.Additionally, By template transporter of the present invention, it is not necessary to repeatedly install or remove template, have and workman's skill is required low, and relatively In in the past manually transhipment, have take a short time, artificial less, fast and convenient advantage.Furthermore, template transporter of the present invention exists One section of construction can reuse after terminating in next section of construction, or configures one group at each construction section, to form expansion Streamline is constructed, and increases substantially construction speed, saves management cost.
Being described in detail the present invention above in association with drawings and Examples, those skilled in the art can basis The present invention is made many variations example by described above.Thus, some details in embodiment should not constitute limitation of the invention, The present invention by the scope that defines using appended claims as protection scope of the present invention.

Claims (8)

1. a whole spelling template transporter, for closing building structure internal forwarding whole spelling template;It is characterized in that, bag Include:
Slide, top is arranged with the resettlement groove in order to accommodating described template, and bottom is provided with multiple roller;
Spacing side plate, is fixedly arranged on the side of described resettlement groove, is placed in described resettlement groove in order to limit described template bottom;
Support side plate, is fixedly arranged on the opposite side of described resettlement groove, is erected to be placed in described resettlement groove in order to support described template In;
Diagonal support, is supported between described support side plate and described slide obliquely.
Whole spelling template transporter the most according to claim 1, it is characterised in that:
Described slide, has the first T-shaped channel-section steel of connection and the second channel-section steel, the described first described peace of the recessed formation in channel-section steel top Putting groove, described roller is located at bottom described first channel-section steel and the second channel-section steel;
Described diagonal support, two ends are respectively supported between described support side plate and described second channel-section steel.
Whole spelling template transporter the most according to claim 2, it is characterised in that:
Described first channel-section steel, has web and forms in the wing plate of both sides, described web and institute on described web length direction State two wing plates enclose set formation described resettlement groove;
Described second channel-section steel, one end is connected fixing with a wherein wing plate of described first channel-section steel.
Whole spelling template transporter the most according to claim 1, it is characterised in that:
Described slide has the first T-shaped channel-section steel of connection and the second channel-section steel, the described first channel-section steel described resettlement groove of recessed formation; The side of described resettlement groove is located in the weldering of described spacing side plate;The opposite side of described resettlement groove is located in the weldering of described support side plate;Described Second channel-section steel end and described first channel-section steel relatively weld on the bottom, two sides being located at described support side plate;Described diagonal support Two ends weld respectively and be located at described support side plate proximal portion and the end away from the first channel-section steel of described second channel-section steel.
Whole spelling template transporter the most according to any one of claim 1 to 4, it is characterised in that:
The height of described spacing side plate between described resettlement groove the degree of depth to described form height 1/10.
Whole spelling template transporter the most according to any one of claim 1 to 4, it is characterised in that:
The height of described support side plate is between the 1/2 of form height to form height.
Whole spelling template transporter the most according to any one of claim 1 to 4, it is characterised in that:
Define and along described support side plate to described slide top, be there is one first distance by described diagonal support top, by described tiltedly Support support bottom has a second distance along described slide top to described support side plate, described first distance with described second away from From ratio range be 2 to 3.
8. a whole spelling template conveyer method, for transporting whole spelling mould between the multiple construction sections within closing building structure Plate;It is characterized in that, described method includes:
Whole spelling template is turned from previous construction section by the whole spelling template transporter as according to any one of claim 1 to 7 A construction section after being transported to;
At a rear construction section by the guide chain preset, whole spelling template is hung the mould described whole spelling template transporter of removal and carries out template Install;Or, at previous construction section by the guide chain preset, whole spelling template is hung mould to described whole spelling template transporter and carries out Template is transported.
CN201610653815.9A 2016-08-11 2016-08-11 Whole spelling template transporter and conveyer method thereof Pending CN106285000A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610653815.9A CN106285000A (en) 2016-08-11 2016-08-11 Whole spelling template transporter and conveyer method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610653815.9A CN106285000A (en) 2016-08-11 2016-08-11 Whole spelling template transporter and conveyer method thereof

Publications (1)

Publication Number Publication Date
CN106285000A true CN106285000A (en) 2017-01-04

Family

ID=57668228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610653815.9A Pending CN106285000A (en) 2016-08-11 2016-08-11 Whole spelling template transporter and conveyer method thereof

Country Status (1)

Country Link
CN (1) CN106285000A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112576038A (en) * 2020-12-21 2021-03-30 中建一局集团建设发展有限公司 Mould disassembling and transporting system for large template of super high-rise giant column and construction method thereof
CN113700300A (en) * 2021-09-14 2021-11-26 徐亮 Building template quick-release system and multi-layer multiplexing mold closing method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130269284A1 (en) * 2012-04-11 2013-10-17 Fred E. Hovenier Wall lifting, transport and positioning device with roller pins
CN203626266U (en) * 2013-08-08 2014-06-04 中太建设集团股份有限公司 Simple transporter
CN204876593U (en) * 2015-07-03 2015-12-16 南通滨五实业有限公司 Building glass conveyer
CN205172019U (en) * 2015-11-25 2016-04-20 中国建筑第七工程局有限公司 Big shaped steel constructs horizontal migration device
CN105835927A (en) * 2016-04-27 2016-08-10 国网山东省电力公司招远市供电公司 Universal transport vehicle for moving indoor transformation equipment
CN205976511U (en) * 2016-08-11 2017-02-22 中国建筑第八工程局有限公司 Whole template transfer device that pieces together

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130269284A1 (en) * 2012-04-11 2013-10-17 Fred E. Hovenier Wall lifting, transport and positioning device with roller pins
CN203626266U (en) * 2013-08-08 2014-06-04 中太建设集团股份有限公司 Simple transporter
CN204876593U (en) * 2015-07-03 2015-12-16 南通滨五实业有限公司 Building glass conveyer
CN205172019U (en) * 2015-11-25 2016-04-20 中国建筑第七工程局有限公司 Big shaped steel constructs horizontal migration device
CN105835927A (en) * 2016-04-27 2016-08-10 国网山东省电力公司招远市供电公司 Universal transport vehicle for moving indoor transformation equipment
CN205976511U (en) * 2016-08-11 2017-02-22 中国建筑第八工程局有限公司 Whole template transfer device that pieces together

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112576038A (en) * 2020-12-21 2021-03-30 中建一局集团建设发展有限公司 Mould disassembling and transporting system for large template of super high-rise giant column and construction method thereof
CN113700300A (en) * 2021-09-14 2021-11-26 徐亮 Building template quick-release system and multi-layer multiplexing mold closing method

Similar Documents

Publication Publication Date Title
CN110230262B (en) Half-integral hoisting structure and butt joint method for main arch rib of basket type steel pipe arch bridge
CN113235913B (en) Construction equipment and method for hanging, splicing and lifting vertical templates of building
CN103643800A (en) Lifting installation system for buckling restrained supporting member and construction method thereof
CN210858024U (en) Discharging platform with liftable hole part
CN210031910U (en) Movable formwork supporting system for underground comprehensive pipe gallery
CN106285000A (en) Whole spelling template transporter and conveyer method thereof
CN205976511U (en) Whole template transfer device that pieces together
CN106812307B (en) Construction device of reinforced concrete structure
CN212599995U (en) Welding installation equipment for hot-melt welded pipe
CN209353734U (en) For installing the double-track device of curtain wall
CN105781205A (en) In-place guiding device for segmented hoisting and air pairing of heavy tower equipment
CN109594697B (en) Construction method and structure of super high-rise built-in unit glass curtain wall
CN205241086U (en) Template hoist and mount and ann gun carriage of disassembling and using
CN110616706A (en) Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole
CN106437047B (en) A kind of equipment transported for factory building roof plate with installing
CN215717173U (en) Construction equipment for hanging, splicing and lifting vertical templates of building
CN108285085A (en) Pipe installing vertical-horizontal means of transport and transportation resources
CN209906232U (en) Building template lifting device and cross-floor transportation system comprising same
CN210530883U (en) Construction system for horizontal splicing, vertical rotation and combination of circular strip steel lining tunnel
CN210598373U (en) Chimney steel inner tube installing the system
CN110593906B (en) Horizontal splicing vertical rotation combined construction system and method for circular strip steel lining tunnel
CN110388122B (en) Chimney steel inner cylinder installation system and installation method
CN108644471B (en) Pipeline sliding transportation structure system on large-area water area and construction method thereof
CN209403261U (en) Leakage dropping-board installs matching operation equipment
JP2017128907A (en) Jig for installation and covering from weather of lining plate and method for installation of lining plate using the jig

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104

RJ01 Rejection of invention patent application after publication