JP2001059346A - Transfer method for column - Google Patents

Transfer method for column

Info

Publication number
JP2001059346A
JP2001059346A JP11235513A JP23551399A JP2001059346A JP 2001059346 A JP2001059346 A JP 2001059346A JP 11235513 A JP11235513 A JP 11235513A JP 23551399 A JP23551399 A JP 23551399A JP 2001059346 A JP2001059346 A JP 2001059346A
Authority
JP
Japan
Prior art keywords
column
existing
pillar
existing column
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11235513A
Other languages
Japanese (ja)
Inventor
Daisuke Ozaki
大輔 尾崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP11235513A priority Critical patent/JP2001059346A/en
Publication of JP2001059346A publication Critical patent/JP2001059346A/en
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To rationally and economically perform column transferring works by connecting joint plates provided in the side face of a reinforcing post erected in parallel to an existing column at a horizontal transfer distance apart therefrom to the existing column, arranging a PC steel in the reinforcing post, waiting the hardening of the filled concrete, and removing a defective part of the existing column. SOLUTION: A reinforcing post 2 provided with joint plates 5 with such a dimension as presetting a horizontal transfer distance S therein in its side faces of the top end and the bottom end is erected along an existing column 1 between a slab 3 and an underground beam 4 and the ends of the joint plates 5 are connected to the side face of the existing column 1 by welding, etc. The provision of the joint plates 5 can facilitate the retaining of the existing column 1 and the reinforcing post 2 in a prescribed separated interval. The end of a PC steel 6 prearranged inside the reinforcing post 2 is fixed to the slab 3 and the reinforcement of the underground beam 4, so that the PC steel 6 is tensioned. Filler concrete is placed in the reinforcing post 2, and after hardening it and prestressing the post by the PC steel 6, a removal part 1a, or a defect of the existing column 1 is removed. This rationalized work process enables the efficient and economical construction taking account of the safety.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は既設柱の移設方法に
関する。
The present invention relates to a method for relocating an existing pillar.

【0002】[0002]

【従来の技術】増改築工事等に伴い、既設柱の位置が支
障となり柱の移設を行う場合がある。このような場合、
既設柱の上下には既設のスラブや床が存在しているた
め、柱の移設工事の障害物となり能率的、経済的な施工
を行うことが困難であった。
2. Description of the Related Art With the extension and remodeling work, there is a case where the position of an existing pillar is hindered and the pillar is relocated. In such a case,
Since existing slabs and floors exist above and below the existing columns, they have become obstacles to the relocation of the columns, making it difficult to perform efficient and economical construction.

【0003】従来、既設のスラブと床の間に新設柱を構
築する場合、 柱が鉄筋コンクリートの場合 既設のスラブや床の鉄筋を斫り出し、新設柱鉄筋を溶接
して組立て、スラブ下に空間を残して形枠を組み、スラ
ブ下の空間からコンクリート打設し、形枠解体後スラブ
下の空間部にコンクリート充填したり、又は柱のコンク
リート打設全体をコンクリート圧入により行う。 柱が鋼管柱の場合 既設のスラブや床の鉄筋を斫り出し、新設鋼管柱と溶接
して組立てる。
Conventionally, when a new pillar is constructed between an existing slab and a floor, when the pillar is made of reinforced concrete, the reinforcing steel of the existing slab or the floor is cut out, and the new pillar reinforcing steel is welded and assembled to leave a space under the slab. Concrete form is poured from the space under the slab, and concrete is filled into the space under the slab after dismantling the formwork. When the pillar is a steel pipe pillar The existing slab and the reinforcing bar of the floor are cut out and welded with the new steel pipe pillar to assemble.

【0004】しかし前記従来の方法によると作業工程が
輻輳し、能率的、経済的な施工を行うことが困難であ
り、かつ安全な作業が行えないという問題があった。
[0004] However, according to the conventional method, there is a problem that the work steps are congested, it is difficult to carry out efficient and economical construction, and safe work cannot be performed.

【0005】[0005]

【発明が解決しようとする課題】本発明は前記問題点を
解決するため、合理的で経済的な施工を行い、かつ安全
な作業が行える柱の移設方法を提供することを目的とす
る。
SUMMARY OF THE INVENTION An object of the present invention is to provide a method of relocating a pillar which can perform a reasonable and economical construction and can perform a safe operation in order to solve the above-mentioned problems.

【0006】[0006]

【課題を解決するための手段】本発明は、接合板を側面
に備えた添え柱を、既設柱と水平移設距離をあけて平行
に立設し、既設柱に接合板を連結させ、添え柱内にPC
鋼材を配置し、添え柱内にコンクリートを充填し、PC
鋼材を緊張して充填コンクリートが硬化後、既設柱の支
障部分を撤去することを特徴とする、柱の移設方法であ
る。
SUMMARY OF THE INVENTION According to the present invention, a supporting column having a joining plate on a side surface is erected in parallel with an existing column at a horizontal transfer distance, and the joining plate is connected to the existing column. PC in
Placing steel material, filling concrete in the supporting pillar, PC
This is a method of relocating a column, which comprises removing a hindrance portion of an existing column after the filled concrete is hardened by tensioning a steel material.

【0007】[0007]

【発明の実施の形態1】以下に、移設する柱が鋼管柱の
場合の一例について説明する。
[Embodiment 1] An example in which the column to be relocated is a steel pipe column will be described below.

【0008】<イ>既設柱 図1は、既設柱1に沿って添え柱2を平行に立設し、既
設柱1の支障部分1aを撤去した状態を示す側面図であ
り、図2はその斜視図である。既設柱1はたとえば鋼管
柱からなり、スラブ3と地中梁4の間に立設して固定し
ている。増改築工事等に伴い、既設柱1の中間部が支障
部分1aとなる。そのため既設柱1の位置を、支障にな
らない位置まで水平移設距離Sだけ移動させスラブ3を
支持しなければならない。
<A> Existing Pillar FIG. 1 is a side view showing a state in which the supporting pillar 2 is erected in parallel along the existing pillar 1 and the obstruction portion 1a of the existing pillar 1 is removed, and FIG. It is a perspective view. The existing column 1 is made of, for example, a steel tube column, and is erected and fixed between the slab 3 and the underground beam 4. Along with the extension and remodeling work, the middle part of the existing pillar 1 becomes the obstacle 1a. Therefore, the slab 3 must be supported by moving the position of the existing column 1 by a horizontal transfer distance S to a position where it does not cause any trouble.

【0009】<ロ>添え柱 添え柱2は移設する柱そのものであり、中空状の鋼管パ
イプである。添え柱2の側面には、前記水平移設距離S
を満足する寸法を有する接合板5が溶接等により予め取
付けてある。添え柱2の長さは、既設柱1の支障部分1
aとなる長さと、添え柱2を既設柱1に接合する接合板
5の寸法を加えた長さとする。添え柱2の断面は、既設
柱1に対応する断面強度以上を有すればよく、添え柱2
の設置本数及び断面形状等は任意に決定できる。図2
は、一本の既設柱1に対し二本の添え柱2で補強し、支
障にならない位置まで水平移動量Sだけ移動した状態を
示す斜視図である。
<B> Attached Pillar The attached pillar 2 is a pillar itself to be relocated, and is a hollow steel pipe. The horizontal transfer distance S
Is previously attached by welding or the like. The length of the supporting pillar 2 is the obstacle 1 of the existing pillar 1.
The length is a length obtained by adding the length of “a” and the dimension of the joining plate 5 that joins the auxiliary pillar 2 to the existing pillar 1. The cross section of the supporting column 2 may have a sectional strength corresponding to that of the existing column 1 or more.
The number and the cross-sectional shape of the can be determined arbitrarily. FIG.
FIG. 5 is a perspective view showing a state in which one existing pillar 1 is reinforced by two auxiliary pillars 2 and moved by a horizontal movement amount S to a position where no hindrance occurs.

【0010】<ハ>接合板 接合板5はたとえば短冊形の鋼板プレートである。接合
板5は添え柱2の上端と下端の側面に、予め溶接等によ
り取付けてある。接合板5を介して既設柱1の側面と添
え柱2の側面を溶接等により連結する。
<C> Joining Plate The joining plate 5 is, for example, a strip-shaped steel plate. The joining plate 5 is attached to the upper and lower side surfaces of the supporting column 2 by welding or the like in advance. The side surface of the existing column 1 and the side surface of the supporting column 2 are connected by welding or the like via the joining plate 5.

【0011】<ニ>PC鋼材 PC鋼材6は添え柱2内に打設された充填コンクリート
7にプレストレスを導入するための緊張用鋼材である。
添え柱2内に、設計上必要とされる本数を予め配置して
おき、PC鋼材6の両端部はスラブ3と地中梁4の鉄筋
等に固定する。
<D> PC steel material PC steel material 6 is a tension steel material for introducing prestress into the filled concrete 7 cast in the supporting column 2.
The number required for design is previously arranged in the supporting column 2, and both ends of the PC steel material 6 are fixed to the slab 3 and the reinforcing steel of the underground beam 4.

【0012】[0012]

【作用】以下に、本発明の作用を説明する。The operation of the present invention will be described below.

【0013】<イ>添え柱の建込み、連結 添え柱2をスラブ3と地中梁4の間に建込む。既設柱1
に沿って立設する添え柱2の離間間隔は、既設柱1の立
設位置から支障にならない水平移設距離Sだけ移動した
位置とする。添え柱4の上端と下端の側面には、予め水
平移設距離Sを考慮した寸法の接合板5が設けてある。
そのため、既設柱1に沿って添え柱2を立設し、接合板
5の端部を既設柱1の側面に接触させることにより、既
設柱1と添え柱2を所定の離間間隔に保つことができ
る。接合板5の端部を既設柱1の側面に接触後、溶接等
により連結する。
<A> Installation and connection of side pillars The side pillars 2 are built between the slab 3 and the underground beam 4. Existing pillar 1
Is set at a position shifted from the standing position of the existing column 1 by a horizontal transfer distance S that does not cause any trouble. On the side surfaces of the upper end and the lower end of the supporting column 4, a joining plate 5 having a dimension considering the horizontal transfer distance S is provided in advance.
Therefore, the supporting pillar 2 is erected along the existing pillar 1, and the end of the joining plate 5 is brought into contact with the side surface of the existing pillar 1, thereby maintaining the existing pillar 1 and the supporting pillar 2 at a predetermined distance. it can. After the end of the joining plate 5 comes into contact with the side surface of the existing column 1, it is connected by welding or the like.

【0014】<ロ>PC鋼材の緊張 添え柱2の中空内部には予めPC鋼材6を配置してお
く。前記添え柱2の建込み、連結作業時にPC鋼材6の
端部をスラブ3、地中梁4の鉄筋に固定し、PC鋼材5
を緊張する。PC鋼材6の緊張は、プレテンション方式
又はポストテンション方式のいずれの方式であってもよ
い。
<B> Tension of PC steel material PC steel material 6 is arranged in the hollow inside of the supporting column 2 in advance. The end of the PC steel material 6 is fixed to the slab 3 and the reinforcing bar of the underground beam 4 during the work of installing and connecting the attached pillar 2, and the PC steel material 5 is fixed.
Nervous. The tension of the PC steel material 6 may be either a pretension type or a post tension type.

【0015】<ハ>コンクリートの充填 添え柱2内に充填コンクリート7を打設する。充填コン
クリート7の打設作業は、プレテンション方式又はポス
トテンション方式のいずれであるかにより、PC鋼材6
の緊張作業と充填コンクリート7の打設作業の施工順序
を変えなければならない。コンクリートの打設作業はポ
ンプ圧送等従来方法により行う。
<C> Filling of concrete Filled concrete 7 is cast into the supporting pillar 2. Depending on whether a pretensioning method or a posttensioning method is used for placing concrete 7, PC steel 6
The work order of the tensioning work and the placing work of the filled concrete 7 must be changed. The concrete placing operation is performed by a conventional method such as pumping.

【0016】<ニ>既設柱の撤去 充填コンクリート7が硬化し、PC鋼材6によるプレス
トレスが充填コンクリート7に導入完了後、既設柱1の
支障となる撤去部分1aを撤去する。撤去部分1aは従
来方法により撤去する。支障とならない既設柱1の残置
部分は、そのまま接合板5により添え柱2に連結した状
態のままとしておく。既設柱1の残置部分の変形を抑止
するため、撤去部分1aの撤去に先立ち、残置部分にコ
ンクリートを注入して補強しておく。
<D> Removal of Existing Column After the concrete 7 has hardened and the prestress by the PC steel 6 has been introduced into the concrete 7, the removed portion 1 a that hinders the existing column 1 is removed. The removal part 1a is removed by a conventional method. The remaining portion of the existing pillar 1 that does not hinder is left as it is connected to the supporting pillar 2 by the joining plate 5 as it is. Before the removal of the removed portion 1a, concrete is poured into the remaining portion to reinforce the remaining portion of the existing pillar 1 before the removal of the remaining portion.

【0017】[0017]

【発明の実施の形態2】図3は他の実施形態を示す側面
図である。本実施形態においては、既設柱1の支障とな
る撤去部分1aが長く、撤去部分1aの上端はスラブ3
の下面に接近した位置となっている。そのため、添え柱
2の建込み、連結に際しては、スラブ3内に埋没してい
る既設柱1の周辺コンクリートを斫り出して露出させ、
既設柱1の露出部分に接合板5を連結する。PC鋼材6
の緊張、充填コンクリート7の打設は前記実施の形態1
と同様であるので説明を省略する。柱の移設作業が終了
後、既設柱1の露出部分はコンクリート等を充填して修
復する。
Second Embodiment FIG. 3 is a side view showing another embodiment. In the present embodiment, the removed portion 1a that interferes with the existing column 1 is long, and the upper end of the removed portion 1a is
It is a position close to the lower surface of. Therefore, at the time of building and connecting the supporting column 2, the concrete around the existing column 1 buried in the slab 3 is cut out and exposed.
The joining plate 5 is connected to the exposed portion of the existing column 1. PC steel 6
Of the concrete and the placing of the filled concrete 7 are as described in the first embodiment.
Therefore, the description is omitted. After the relocation of the columns is completed, the exposed portions of the existing columns 1 are repaired by filling them with concrete or the like.

【0018】[0018]

【発明の実施の形態3】図4はさらに他の実施形態を示
す側面図である。本実施形態においては、既設柱1の支
障となる撤去部分1aがさらに長く、撤去部分1aの上
端はスラブ3の下面に接近し、撤去部分1aの下端は地
中梁4の上面に接近した位置となっている。添え柱2の
設置位置が既設柱1から離れ、添え柱2の下端が地中梁
4又は杭8から外れるため、PC鋼材6の固定、緊張作
業が行えない場合がある。そのため、添え柱2の建込
み、連結に際しては、既設の杭8及び地中梁4の拡幅工
事を行う。既設柱1を支持している地中梁4及び杭8
を、移設する柱(添え柱2)の設置位置までコンクリー
ト打設して拡幅する。拡幅コンクリート9は、地中梁4
及び杭8とたとえばアンカー10により一体化させる。
PC鋼材6の上端はスラブ3の鉄筋に固定し、PC鋼材
6の下端はたとえばアンカー10に固定させ、PC鋼材
6の緊張作業を行なう。添え柱2の設置位置関係によ
り、地中梁4及び杭8の拡幅工事を行わなくてもよい場
合(実施の形態1又は実施の形態2)、又は地中梁4か
杭8のいずれかを拡幅工事を行う場合等が発生するが、
前述方法の応用であり説明を省略する。
Third Embodiment FIG. 4 is a side view showing still another embodiment. In the present embodiment, the removed portion 1a that is an obstacle to the existing column 1 is longer, the upper end of the removed portion 1a approaches the lower surface of the slab 3, and the lower end of the removed portion 1a approaches the upper surface of the underground beam 4. It has become. Since the installation position of the supporting column 2 is separated from the existing column 1 and the lower end of the supporting column 2 is separated from the underground beam 4 or the pile 8, the fixing and tensioning work of the PC steel material 6 may not be performed. For this reason, when installing and connecting the supporting pillars 2, the existing piles 8 and the underground beams 4 are widened. Underground beam 4 and pile 8 supporting existing column 1
Is concretely cast to the installation position of the pillar to be relocated (attachment pillar 2) and widened. The widening concrete 9 is the underground beam 4
And the stake 8 by, for example, an anchor 10.
The upper end of the PC steel 6 is fixed to the reinforcing bar of the slab 3, and the lower end of the PC steel 6 is fixed to, for example, an anchor 10, and the PC steel 6 is tensioned. When it is not necessary to perform the widening work of the underground beam 4 and the pile 8 depending on the installation positional relationship of the auxiliary pillar 2 (Embodiment 1 or 2), or either the underground beam 4 or the pile 8 When widening work is performed,
This is an application of the above-described method, and the description is omitted.

【0019】[0019]

【発明の効果】本発明は以上説明したようになるから、
次のような効果を得ることができる。 <イ>PC鋼材を配置した添え柱を構築する方法とした
ので、合理的な作業工程により能率的、経済的な施工を
行うことができる。 <ロ>添え柱の側面には、既設柱からの水平移設距離を
満足する寸法を有する接合板が溶接等により予め取付け
てあるため、既設柱と添え柱を所定の離間間隔で容易に
保つことができる。 <ハ>接合板を介して既設柱と添え柱を連結する方法と
したので、既設柱の断面強度に応じた添え柱を複数本設
置でき、柱の移設方法の自由度が増大する。 <ニ>既設の杭及び地中梁を拡幅補強し、PC鋼材を配
置した添え柱を構築する方法としたので、既設柱からの
水平移設距離の範囲が増大する。 <ホ>柱の移設作業が輻輳することなく、安全な作業が
行える。 <ヘ>添え柱は、拡幅部分のアンカーに固定したPC鋼
材を緊張して構築する方法としたので、構造的に確実な
施工を行うことができる。
Since the present invention has been described above,
The following effects can be obtained. <A> Since the method of constructing the supporting pillars on which the PC steel materials are arranged is adopted, efficient and economical construction can be performed by a rational work process. <B> Since a joining plate having dimensions that satisfy the horizontal transfer distance from the existing pillar is previously attached to the side surface of the supporting pillar by welding or the like, the existing pillar and the supporting pillar can be easily maintained at a predetermined spacing. Can be. <C> Since the existing column and the auxiliary column are connected via the joining plate, a plurality of auxiliary columns corresponding to the cross-sectional strength of the existing column can be installed, and the degree of freedom in the method of transferring the column is increased. <D> The method of widening and reinforcing the existing piles and underground beams and constructing the auxiliary pillar on which the PC steel material is arranged increases the range of the horizontal transfer distance from the existing pillar. <E> Safe work can be performed without congestion in the column relocation work. <F> Since the supporting pillar is constructed by tensioning the PC steel material fixed to the anchor of the widened portion, it is possible to perform structurally reliable construction.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明による柱の移設方法の側面図。FIG. 1 is a side view of a method for relocating a pillar according to the present invention.

【図2】同上斜視図。FIG. 2 is a perspective view of the same.

【図3】他の実施形態を示す側面図。FIG. 3 is a side view showing another embodiment.

【図4】さらに他の実施形態を示す側面図。FIG. 4 is a side view showing still another embodiment.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】接合板を側面に備えた添え柱を、既設柱と
水平移設距離をあけて平行に立設し、 既設柱に接合板
を連結させ、 添え柱内にPC鋼材を配置し、 添え柱内にコンクリートを充填し、 PC鋼材を緊張して充填コンクリートが硬化後、既設柱
の支障部分を撤去することを特徴とする、 柱の移設方法。
1. A supporting column having a joining plate on a side surface is erected in parallel with an existing column at a horizontal transfer distance, a joining plate is connected to the existing column, and a PC steel material is arranged in the supporting column. A method of relocating a pillar, comprising filling concrete in a supporting pillar, tensioning a PC steel material, and curing the filled concrete, and removing a hindrance of an existing pillar.
JP11235513A 1999-08-23 1999-08-23 Transfer method for column Pending JP2001059346A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11235513A JP2001059346A (en) 1999-08-23 1999-08-23 Transfer method for column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11235513A JP2001059346A (en) 1999-08-23 1999-08-23 Transfer method for column

Publications (1)

Publication Number Publication Date
JP2001059346A true JP2001059346A (en) 2001-03-06

Family

ID=16987111

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11235513A Pending JP2001059346A (en) 1999-08-23 1999-08-23 Transfer method for column

Country Status (1)

Country Link
JP (1) JP2001059346A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100739449B1 (en) * 2006-06-12 2007-07-16 쌍용건설 주식회사 Method for installation of new column in remodeling apartment house
JP2018044307A (en) * 2016-09-12 2018-03-22 センクシア株式会社 Method of reinforcing existing column

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100739449B1 (en) * 2006-06-12 2007-07-16 쌍용건설 주식회사 Method for installation of new column in remodeling apartment house
JP2018044307A (en) * 2016-09-12 2018-03-22 センクシア株式会社 Method of reinforcing existing column

Similar Documents

Publication Publication Date Title
KR20020086506A (en) Composite structural framing system
KR200381303Y1 (en) Form system for joint between retaining wall and slab of basement floor
JP3700102B2 (en) Building basic structure
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
KR200372315Y1 (en) Moving-fabricated supporting bracket structure of downward construction system
JP2006112179A (en) Bridge girder installing method
JP2001059346A (en) Transfer method for column
JPH06212691A (en) Construction of building
JP3400364B2 (en) A method for joining columns and beams made of precast concrete.
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
JP2959325B2 (en) Construction method of steel frame reinforced concrete structure
JPH06129114A (en) Repairing method for existing column strip structure
JPH10227010A (en) Steel form with main reinforcement for bridge floor panel and bridge floor panel construction method using it
KR20210004289A (en) Transfer Structure Construction Method Using U-shaped Steel Girder
JPH10110498A (en) Half-precast floor slab and construction method of hollow flat slab making use thereof
JP2002332691A (en) Joint construction between column and beam
JP7231523B2 (en) Concrete building and its construction method
JP3275017B2 (en) Method of manufacturing caisson using precast member
JP2864906B2 (en) Precast wall joining method
JPH1150538A (en) Building and method for constructing the same
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP2749474B2 (en) Reverse construction method for underground structures
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH06264691A (en) Supporting frame for repairing existing column row structure
JPH1113015A (en) Arch slab type viaduct, and its execution method