ITCT20090015A1 - "TIPO PALERMO" ARTIFICIAL GALLERY - Google Patents

"TIPO PALERMO" ARTIFICIAL GALLERY Download PDF

Info

Publication number
ITCT20090015A1
ITCT20090015A1 IT000015A ITCT20090015A ITCT20090015A1 IT CT20090015 A1 ITCT20090015 A1 IT CT20090015A1 IT 000015 A IT000015 A IT 000015A IT CT20090015 A ITCT20090015 A IT CT20090015A IT CT20090015 A1 ITCT20090015 A1 IT CT20090015A1
Authority
IT
Italy
Prior art keywords
double
tunnel
reinforcements
concrete
prefabricated
Prior art date
Application number
IT000015A
Other languages
Italian (it)
Inventor
Mose Monachino
Original Assignee
Mose Monachino
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mose Monachino filed Critical Mose Monachino
Priority to IT000015A priority Critical patent/ITCT20090015A1/en
Publication of ITCT20090015A1 publication Critical patent/ITCT20090015A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Absorbent Articles And Supports Therefor (AREA)
  • Prostheses (AREA)

Description

DESCRIZIONE DESCRIPTION

GALLERIA PREFABBRICATA NATURALE E ARTIFICIALE CON LA TECNICA, A PARATIE PREFABBRICATE, CON IL GETTO IN SITO, E CON ARMATURA CONTINUA TRAMITE GIUNZIONE FILETTATA. PREFABRICATED NATURAL AND ARTIFICIAL TUNNEL WITH THE TECHNIQUE, WITH PREFABRICATED PARTS, WITH THE CAST IN SITE, AND WITH CONTINUOUS REINFORCEMENT THROUGH THREADED JOINT.

TECNICA A CUI L’INVENZIONE FA RIFERIMENTO TECHNIQUE TO WHICH THE INVENTION REFERS

La tecnica a cui l’invenzione della GALLERIA PREFABBRICATA NATURALE E ARTIFICIALE CON LA TECNICA, A PARATIE PREFABBRICATE, CON IL GETTO IN SITO, E CON ARMATURA CONTINUA TRAMITE GIUNZIONE FILETTATA. fa riferimento e la costruzione di Gallerie. The technique to which the invention of the NATURAL AND ARTIFICIAL PREFABRICATED TUNNEL WITH THE TECHNIQUE, WITH PREFABRICATED PARTS, WITH THE CAST IN SITE, AND WITH CONTINUOUS REINFORCEMENT THROUGH THREADED JOINT. refers and the construction of Galleries.

STATO DELLA TECNICA PREESISTENTE NALLA COSTRUZIONE DELLE GALLERIE STATE OF THE PRE-EXISTING TECHNIQUE IN THE CONSTRUCTION OF TUNNELS

la tecnica preesistenti di produzione gallerie naturali e artificiali oggi esistenti sul mercato, che à ̈ la seguente: the pre-existing production technique of natural and artificial tunnels existing on the market today, which is the following:

- Scavo superficiale fino all’altezza dove si monta il solaio della galleria, con le trivelle si creano i fori per i pali di lunghezza alta, messa l’armatura dei pali, viene gettato il calcestruzzo per formare il palo, la stessa esecuzione per l’altro lato. - Surface excavation up to the height where the gallery floor is mounted, with the augers holes are created for the high length poles, the reinforcement of the poles is placed, the concrete is poured to form the pole, the same execution for the other side.

- Poi si preparano le armature delle travi di collegamento, il linea dei pali, quindi completati con il getto del calcestruzzo. - Then the reinforcements of the connecting beams are prepared, the line of the poles, then completed with the casting of concrete.

- Fase di montaggio dell’armatura del tetto della galleria, e quindi completata con il getto del calcestruzzo, - Assembly phase of the tunnel roof reinforcement, and then completed with the casting of concrete,

- Scavo all’interno della galleria fino alla quota del pavimento. - Excavation inside the tunnel up to the level of the floor.

- Pulite tutte le superfici dei pali, gli interstizi tra i pali, - Clean all the surfaces of the posts, the interstices between the posts,

- Scrostati i pali per trovare le armature per saldare i ganci dove collegare i pali con delle parete prefabbricate. - Peel off the poles to find the reinforcement to weld the hooks where to connect the poles with prefabricated walls.

- Mettere l’impermeabilizzazione per tutta la parete. - Apply waterproofing to the entire wall.

- Montare le pareti prefabbricate o montare le armature, montare le relative carpenterie, ed seguire il getto del calcestruzzo - Mount the prefabricated walls or mount the reinforcements, mount the relative carpentry, and follow the casting of the concrete

- Rifiniture delle pareti. - Wall finishing.

- Preparazione del pavimento della galleria, con livellamento - Preparation of the tunnel floor, with leveling

- Preparare e montare le armature del pavimento ed il relativo getto del calcestruzzo. - Prepare and assemble the floor reinforcements and the relative concrete casting.

LATI DEBOLI TROVATI NEL METODO PREESISTENTE SONO: WEAK SIDES FOUND IN THE PRE-EXISTING METHOD ARE:

- Molto pericoloso per gli addetti ai lavori. - Very dangerous for insiders.

- Tempi di realizzazione molto lunghi - Very long production times

- Molto alterabile nel tempo, - Very alterable over time,

DESCRIZIONE BREVE DEL BREVETTO BRIEF DESCRIPTION OF THE PATENT

GALLERIA PREFABBRICATA NATURALE E ARTIFICIALE CON LA TECNICA, A PARATIE PREFABBRICATE, CON IL COMPLETAMENTO DEL GETTO di CALCESTRUZZO IN OPERA, CON ARMATURA CONTINUA DEL GIUNTO PARETE-BASAMENTO, TRAMITE BARRE FILETTATE PREFABRICATED NATURAL AND ARTIFICIAL TUNNEL WITH THE TECHNIQUE, WITH PREFABRICATED BALLS, WITH THE COMPLETION OF THE CONCRETE CAST IN SITE, WITH CONTINUOUS REINFORCEMENT OF THE WALL-BASE JOINT, THROUGH THREADED BARS

La presente Invenzione costituita da una struttura di elementi prefabbricate particolare, e di una tecnologia di montaggio e scavo sequenziale, come di seguito spiegheremo: spianamento pista di lavoro, scavo a diaframma, doppia parete prefabbricata particolare, inserimento delle Parete doppia prefabbricati particolari, unione prefabbricato-prefabbricato tramite staffe metalliche particolari, getto intercapedine dei prefabbricati con calcestruzzi SCC e impermeabile, montaggio delle coppelle antifuoco, montaggio ferri di armatura della copertura, getto del calcestruzzo di completamento della copertura, impermeabilizzare la copertura, ripristinare i luoghi, scavo del vano interno fino a quota del sottofondo (magrone), realizzazione del sottofondo (magrone), smontaggio dei tappi di protezione filettature delle barre di armature, montaggio moncone d’armatura di ripresa, montaggio delle armature del basamento, montaggio degli IDROSTOP, completamento del basamento con getto del calcestruzzo tipo SCC e impermeabile. The present Invention consists of a structure of particular prefabricated elements, and of a sequential assembly and excavation technology, as we will explain below: work track leveling, diaphragm excavation, particular prefabricated double wall, insertion of particular prefabricated double walls, prefabricated union -prefabricated using special metal brackets, hollow space casting of prefabricated structures with SCC and waterproof concrete, assembly of fire-resistant cupels, assembly of reinforcing rods of the roof, casting of the concrete to complete the roof, waterproof the roof, restore the places, excavation of the internal compartment up to at the level of the substrate (lean), construction of the substrate (lean concrete), disassembly of the thread protection caps of the reinforcement bars, assembly of the reinforcement stump, assembly of the base reinforcements, assembly of the IDROSTOPs, completion of the base with casting of concrete SCC type and waterproof.

La presente Invenzione, ha come oggetto una nuova tecnica di realizzazione di galleria, per: galleria artificiale, sottopasso, cavalcavia, galleria per sottopasso fluviale e per sottopassi tecnici ecc. The present invention relates to a new tunnel construction technique for: artificial tunnel, underpass, overpass, tunnel for river underpass and for technical underpasses, etc.

La presente invenzione consiste in una nuova tecnologia per la realizzazione di gallerie semi prefabbricate cosa importante con il getto di calcestruzzo gettato in opera per dare la continuità della struttura, rendendola monolitica, auto impermeabile e completa. The present invention consists of a new technology for the construction of semi prefabricated tunnels, an important thing with the concrete cast on site to give the continuity of the structure, making it monolithic, waterproof and complete.

VANTAGGI DELL’INVENZIONE ADVANTAGES OF THE INVENTION

- Riduzione dei tempi di realizzazione - Reduction of production times

- Più sicurezza agli addetti ai lavori - More safety for professionals

- Più rispetto all’ecologia - More respect to ecology

- Più durabilità dell’opera - More durability of the work

- -

DESCRIZIONE IN DETTAGLIO DI COME VIENE ATTUATA L’INVENZIONE DELLA DETAILED DESCRIPTION OF HOW THE INVENTION OF THE

GALLERIA PREFABBRICATA NATURALE E ARTIFICIALE CON LA TECNICA, A PARATIE PREFABBRICATE, CON IL COMPLETAMENTO DEL GETTO di CALCESTRUZZO IN OPERA, CON ARMATURA CONTINUA DEL GIUNTO PARETE-BASAMENTO, TRAMITE BARRE FILETTATE PREFABRICATED NATURAL AND ARTIFICIAL TUNNEL WITH THE TECHNIQUE, WITH PREFABRICATED BALLS, WITH THE COMPLETION OF THE CONCRETE CAST IN SITE, WITH CONTINUOUS REINFORCEMENT OF THE WALL-BASE JOINT, THROUGH THREADED BARS

Realizzazione della galleria: Spianamento del sito dove realizzare la galleria compreso lo scavo del setto dove inserire la Doppia Parete (10), inserimento della Doppia parete all’interno della sezione realizzata precedentemente con una profondità più lunga dell’altezza della galleria per dare tenuta alla spinta del terreno contro la stessa Doppia Parete (12), Registrazione delle Doppie Parete si posizione sopra la Doppia Parete due portali con martinetto dove collegarsi alla Doppia Parete e tenerla fino in altezza voluta fino all’indurimento del calcestruzzo (11), Montaggio della coppella prefabbricata del tetto montare tutte le armature metalliche e fare il getto del Calcestruzzo (4), dopo che il calcestruzzo ha fatto presa e stagionatura si può iniziare lo scavo all’interno della galleria fino ad una profondità di venti centimetri sotto le filettature di ripresa delle armature tra le parete della galleria e il basamento (19), smontaggio dei perni di guida armature metalliche e cassero metallico di forma del basso rilievo per tenuta belloni (17), Montaggio con avvitamento dei ferri di ripresa armature metalliche nelle boccole filettate giacenti nella Doppia Parete (18), Assemblaggio di tutte le armature dei basamento e tutte le condutture idrici ed elettrici che il progettista ha previsto (20), Getto finale del calcestruzzo del basamento l’opera strutturale e completata. Construction of the tunnel: Leveling of the site where the tunnel is to be built including the excavation of the partition where to insert the Double Wall (10), insertion of the Double wall inside the section previously made with a depth longer than the height of the tunnel to give resistance to the thrust of the ground against the same Double Wall (12), Double Wall Registration is positioned above the Double Wall two portals with jack where to connect to the Double Wall and hold it up to the desired height until the concrete hardens (11), Assembling the prefabricated roof cupella mount all the metal reinforcements and cast the concrete (4), after the concrete has set and cured, it is possible to start excavating inside the tunnel up to a depth of twenty centimeters below the reinforcement threads between the tunnel wall and the base (19), disassembly of the metal reinforcement guide pins iche and metal formwork in the shape of the bas-relief for sealing belloni (17), Assembly with screwing of the reinforcing bars into the threaded bushings lying in the Double Wall (18), Assembly of all the armatures of the base and all the water and electrical pipes that the designer has foreseen (20), Final casting of the concrete of the basement the structural work is completed.

INDUSTRIALIZZAZIONE DELL’INVENZIONE DELLA GALLERIA PREFABBRICATA INDUSTRIALIZATION OF THE INVENTION OF THE PREFABRICATED TUNNEL

NATURALE E ARTIFICIALE CON LA TECNICA, A PARATIE PREFABBRICATE, CON NATURAL AND ARTIFICIAL WITH TECHNIQUE, WITH PREFABRICATED PARTS, WITH

IL COMPLETAMENTO DEL GETTO di CALCESTRUZZO IN OPERA, CON ARMATURA THE COMPLETION OF THE CONCRETE CAST IN SITE, WITH REINFORCEMENT

CONTINUA DEL GIUNTO PARETE- BASAMENTO, TRAMITE BARRE FILETTATE CONTINUE OF THE WALL-BASE JOINT, THROUGH THREADED BARS

La produzione delle Doppia Parete dell’invenzione può avvenire manuale standard, semiautomatica ed automatica la tecnologia e sempre la stessa. Le varie fasi di produzione della Doppia Lastra: 1 preparazione del cassero sia nelle misure sia nella pulitura e oleatura, 2 montaggio delle armature inferiori con distanziatori montaggio delle armature superiori inserimento delle staffe di collegamento delle due armature delle due pareti mettendoli in sospensione, 3 assemblaggio delle staffe filettare di collegamento tra la Doppia Parete ed il basamento 4 Getto del calcestruzzo SCC per un’altezza predeterminata, 5 attesa di tempo di stagionamento fino ad una resistenza del calcestruzzo di kg 200, 6 getto del Calcestruzzo nel secondo cassero viene spianato a questo punto viene ribaltata a 180 gradi facendo immergere le armature della seconda Pare dentro il calcestruzzo ancora fresco, attesa di stagionatura il tempo occorrente fino ad arrivare che il calcestruzzo resista fino a kg 200 cm quadro. 7 sformatura della doppia lastra con i mezzi di sollevamento. The production of the Double Walls of the invention can be done manually as standard, semiautomatic and automatic, the technology is always the same. The various stages of production of the Double Sheet: 1 preparation of the formwork both in the measurements and in the cleaning and oiling, 2 assembly of the lower reinforcements with spacers assembly of the upper reinforcements insertion of the connecting brackets of the two reinforcements of the two walls by putting them in suspension, 3 assembly of the threaded connecting brackets between the Double Wall and the base 4 Casting of SCC concrete for a predetermined height, 5 waiting for curing time up to a concrete resistance of 200 kg, 6 casting of the concrete in the second formwork is leveled to this point is overturned to 180 degrees by immersing the reinforcements of the second Pare into the still fresh concrete, waiting for the necessary time to mature until the concrete is able to withstand up to 200 kg square cm. 7 demoulding of the double slab with lifting means.

Claims (10)

RIVENDICAZIONI 1. Galleria Prefabbricata, comprendente una doppia parete prefabbricata (1) completa di armature metalliche esterne (2), completa anche di tutte le armature portanti sia interni sia esterne (3). CLAIMS 1. Prefabricated tunnel, comprising a double prefabricated wall (1) complete with external metal reinforcements (2), also complete with all internal and external load-bearing reinforcements (3). 2. Galleria Prefabbricata, secondo la rivendicazione 1, le doppie pareti sono tenute solidali con delle staffe tridimensionali che si agganciano e si sovrappongono alle armature portanti verticali delle doppie pareti (5) 2. Prefabricated tunnel, according to claim 1, the double walls are held together with three-dimensional brackets which hook and overlap the vertical load-bearing reinforcements of the double walls (5) 3. Galleria Prefabbricata, secondo la rivendicazione 1-2, le doppie pareti hanno dei dispositivi che permette una giunzione perfetta con le armature di ripresa della stessa con l’armatura dei basamenti (6) composta da una staffa a forma di U che si sovrappone alle armatura della parete esterna (7), di entrambi estremità filettate per la giunzione delle armature dei basamenti (8), di un prolungamento per formare un sperone di tenuta per la realizzazione dei basamenti (9). 3. Prefabricated tunnel, according to claim 1-2, the double walls have devices that allow a perfect junction with the reinforcement of the same with the reinforcement of the bases (6) composed of a U-shaped bracket that is overlaps the armature of the external wall (7), of both threaded ends for joining the armatures of the bases (8), with an extension to form a sealing spur for the construction of the bases (9). 4. Galleria Prefabbricata, secondo le rivendicazioni precedenti lo scavo a sezione per alloggio con doppia parete realizzato con la tecnologia di mantenimento idrico con piastre provvisorie (10). 4. Prefabricated tunnel, according to the preceding claims, the sectional excavation for accommodation with double wall made with the water maintenance technology with temporary plates (10). 5. Galleria Prefabbricata, secondo le rivendicazioni precedenti la registrazione delle doppie pareti avviene con la tecnologia della sospensione aerea tramite una struttura portante (11), la registrazione, guida e collegamento delle armature di giunzione delle doppie lastre à ̈ fatto dalle staffe particolari (12). 5. Prefabricated tunnel, according to the previous claims, the registration of the double walls takes place with the technology of overhead suspension through a bearing structure (11), the registration, guiding and connection of the joining reinforcements of the double slabs is done by the special brackets (12 ). 6. Galleria Prefabbricata, secondo le rivendicazioni precedenti la creazione dello stampo per la formazione del basso rilievo per la tenuta idrica e come copertura dei bulloni tappi per la tenuta pulita le filettature dei giunti (13), bulloni per la tenuta in guida delle armature della doppia lastra con giunzioni per le armature dei basamenti (14). 6. Prefabricated tunnel, according to the preceding claims, the creation of the mold for the formation of the low relief for the water tightness and as a cover of the bolts, caps for the clean sealing of the threads of the joints (13), bolts for the holding in the guide of the reinforcements of the double slab with joints for the base reinforcement (14). 7. Galleria Prefabbricata, secondo le rivendicazioni precedenti la messa appunto di una tecnica di uso di IDROSTOP particolari per la protezione delle armature sia interni sia esterni (17). 7. Prefabricated tunnel, according to the claims preceding the implementation of a particular technique for using IDROSTOP for the protection of both internal and external reinforcements (17). 8. Galleria Prefabbricata, secondo le rivendicazioni precedenti la giunzione delle due armature quelle della doppia parete e quelle dei basamenti avviene con la tecnologia di filettatura (18). 8. Prefabricated tunnel, according to the preceding claims, the joining of the two reinforcements, those of the double wall and those of the bases, takes place with the threading technology (18). 9. Galleria Prefabbricata, secondo le rivendicazioni precedenti la produzione delle doppie pareti può avvenire manuale standard, semiautomatica ed automatica la tecnologia e sempre la stessa. Le varie fasi di produzione della doppia Lastra: preparazione del cassero sia nelle misure sia nella pulitura e oleatura, 2 montaggio delle armature inferiori con distanziatori montaggio delle armature superiori inserimento delle staffe di collegamento delle due armature delle due pareti mettendoli in sospensione, 3 assemblaggio delle staffe filettare di collegamento tra la doppia parete ed il basamento 4 getto del calcestruzzo SCC per un’altezza predeterminata, 5 attesa di tempo di stagionamento fino ad una resistenza del calcestruzzo di kg 200, 6 getto del calcestruzzo nel secondo cassero viene spianato a questo punto viene ribaltata a 180 gradi facendo immergere le armature della seconda pare dentro il calcestruzzo ancora fresco, attesa di stagionatura il tempo occorrente fino ad arrivare che il calcestruzzo resista fino a kg 200 cm quadro. 7 sollevare la doppia lastra con i mezzi di sollevamento. 9. Prefabricated tunnel, according to the preceding claims, the production of the double walls can be carried out by standard manual, semi-automatic and automatic, the technology is always the same. The various stages of production of the double slab: preparation of the formwork both in the measurements and in the cleaning and oiling, 2 assembly of the lower reinforcements with spacers, assembly of the upper reinforcements, insertion of the connecting brackets of the two reinforcements of the two walls, placing them in suspension, 3 assembly of the threaded connecting brackets between the double wall and the base 4 casting of SCC concrete for a predetermined height, 5 waiting for curing time up to a concrete resistance of 200 kg, 6 casting of the concrete in the second formwork is leveled to this point is overturned at 180 degrees by immersing the reinforcements of the second part in the still fresh concrete, waiting for the necessary time to mature until the concrete is resistant up to 200 kg square cm. 7 lift the double slab with the lifting means. 10. Galleria Prefabbricata, secondo le rivendicazioni precedenti la realizzazione della galleria: spianamento del sito dove realizzare la galleria scavo del setto dove inserire la doppia parete (10), inserimento della doppia parete all’interno della sezione realizzata precedentemente con una profondità più lunga dell’altezza della galleria per dare tenuta alla spinta del terreno contro la stessa doppia parete (12), registrazione della doppie parete: si posizione sopra la Doppia Parete due portali con martinetto dove collegarsi alla doppia parete e tenerla fino in altezza voluta fino all’indurimento del calcestruzzo (11), montaggio della coppella prefabbricata del tetto montare tutte le armature metalliche e fare il getto del calcestruzzo (4), dopo che il calcestruzzo ha fatto presa e stagionatura si può iniziare lo scavo all’interno della galleria fino ad una profondità di venti centimetri sotto le filettature di ripresa delle armature tra le parete della galleria e il basamento (19), smontaggio dei perni di guida armature metalliche e cassero metallico di forma del basso rilievo per tenuta belloni (17), montaggio con avvitamento dei ferri di ripresa armature metalliche nelle boccole filettate giacenti nella doppia parete (18), assemblaggio di tutte le armature dei basamento e tutte le condutture idrici ed elettrici che il progettista ha previsto (20), getto finale del calcestruzzo del basamento l’opera strutturale e completata.10. Prefabricated tunnel, according to the claims preceding the construction of the tunnel: leveling of the site where to create the tunnel excavation of the septum where to insert the double wall (10), insertion of the double wall inside the section made previously with a longer depth height of the tunnel to keep the ground thrust against the same double wall (12), registration of the double wall: two portals with jacks are positioned above the Double Wall to connect to the double wall and hold it up to the desired height up to Hardening of the concrete (11), assembly of the prefabricated roof cupboard, mount all the metal reinforcements and cast the concrete (4), after the concrete has set and curing, excavation can begin inside the tunnel up to a depth of twenty centimeters below the reinforcement threads between the tunnel wall and the base chin (19), disassembly of the metal reinforcement guide pins and metal formwork in the form of the low relief for sealing belloni (17), assembly with screwing of the reinforcing bars into the threaded bushings lying in the double wall (18), assembly of all the reinforcement of the basement and all the water and electrical pipes that the designer envisaged (20), the final casting of the basement concrete, the structural work is completed.
IT000015A 2009-12-29 2009-12-29 "TIPO PALERMO" ARTIFICIAL GALLERY ITCT20090015A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
IT000015A ITCT20090015A1 (en) 2009-12-29 2009-12-29 "TIPO PALERMO" ARTIFICIAL GALLERY

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
IT000015A ITCT20090015A1 (en) 2009-12-29 2009-12-29 "TIPO PALERMO" ARTIFICIAL GALLERY

Publications (1)

Publication Number Publication Date
ITCT20090015A1 true ITCT20090015A1 (en) 2011-06-30

Family

ID=48047481

Family Applications (1)

Application Number Title Priority Date Filing Date
IT000015A ITCT20090015A1 (en) 2009-12-29 2009-12-29 "TIPO PALERMO" ARTIFICIAL GALLERY

Country Status (1)

Country Link
IT (1) ITCT20090015A1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004085749A1 (en) * 2003-03-28 2004-10-07 Carlo Chiaves Process for the construction of a segment of an open-air work by prefabricated structural members, and prefabricated structural member related thereto
EP1486618A1 (en) * 2003-06-12 2004-12-15 Etienne Heirwegh Method and means for building a basement

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004085749A1 (en) * 2003-03-28 2004-10-07 Carlo Chiaves Process for the construction of a segment of an open-air work by prefabricated structural members, and prefabricated structural member related thereto
EP1486618A1 (en) * 2003-06-12 2004-12-15 Etienne Heirwegh Method and means for building a basement

Similar Documents

Publication Publication Date Title
CN106013811B (en) A kind of installation method of assembled architecture
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN210685444U (en) Quick leveling, mounting and supporting device for prefabricated external wall panel
CN101555709B (en) Mounting process for composite insulating concrete shear wall
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN206956979U (en) A kind of Linear shear wall with fore-set
CN111173042B (en) Advanced water stop post-cast strip of foundation slab and construction method
CN209854976U (en) Assembled heat preservation brickwork wall
JP2011069151A (en) Concrete panel form
CN112112193B (en) Double-sided superposed pipe gallery side wall with concealed columns and manufacturing method thereof
ITCT20090015A1 (en) "TIPO PALERMO" ARTIFICIAL GALLERY
CN214364434U (en) Assembled constructional column suitable for prefabricated wallboard of frame construction
CN205776780U (en) Integrated assembled type dwelling house system
CN104563281B (en) A kind of prefabricated balcony structure and its construction method
CN212223971U (en) Post-cast strip side-fixing inner-supporting steel plate combined template
CN208201923U (en) A kind of armpit Angle formwork overlapping assembled comprehensive pipe gallery structure
KR101219459B1 (en) The water-storage tank of assembly type and method for constructing thereof
CN112609867A (en) Prefabricated shear wall cavity with three-dimensional efficient connection structure and connection node configuration
CN110847445A (en) Construction method for integrally forming outer wall and bottom plate of cast-in-place concrete structure of structure
CN111005476A (en) Spliced shear wall and construction process thereof
CN111535361A (en) Assembled rail top air duct structure of underground station and construction method thereof
CN111305590A (en) Assembly type low-energy-consumption transformation structure and rapid transformation method for existing building balcony