HRP20151199T1 - Method for producing a floor mortar wall in the floor - Google Patents

Method for producing a floor mortar wall in the floor Download PDF

Info

Publication number
HRP20151199T1
HRP20151199T1 HRP20151199TT HRP20151199T HRP20151199T1 HR P20151199 T1 HRP20151199 T1 HR P20151199T1 HR P20151199T T HRP20151199T T HR P20151199TT HR P20151199 T HRP20151199 T HR P20151199T HR P20151199 T1 HRP20151199 T1 HR P20151199T1
Authority
HR
Croatia
Prior art keywords
continuous
soil
well
auger
augers
Prior art date
Application number
HRP20151199TT
Other languages
Croatian (hr)
Original Assignee
Bauer Spezialtiefbau Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bauer Spezialtiefbau Gmbh filed Critical Bauer Spezialtiefbau Gmbh
Publication of HRP20151199T1 publication Critical patent/HRP20151199T1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/126Consolidating by placing solidifying or pore-filling substances in the soil and mixing by rotating blades
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B10/00Drill bits
    • E21B10/44Bits with helical conveying portion, e.g. screw type bits; Augers with leading portion or with detachable parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Fluid Mechanics (AREA)
  • Soil Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Building Environments (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Claims (14)

1. Postupak za pravljenje žbukane stijenke na tlu (60) u tlo (50) uređajem za bušenje (10) s najmanje dva kontinuirana pužna svrdla (20) međusobno blisko paralelno smještenih, gdje se najmanje dva kontinuirana pužna svrdla (20) buše u tlo (50), čime se olabavi materijal tla (53), koji se zatim pomiješa u bušotini (52) sa suspenzijom veziva (55) u žbuku za tlo (57), koja se, nakon vađenja najmanje dva kontinuirana pužna svrdla (20), stvrdne u žbukanu stijenku na tlu (60) u bušotini (52), naznačen time što – u prvom koraku se najmanje dva kontinuirana pužna svrdla (20) buše do dubine bušotine, dok se tlo istodobno razmrvi i olabavi (50), gdje olabavljeni materijal tla (54) uglavnom ostaje u bušotini (52), – u drugom koraku najmanje dva kontinuirana pužna svrdla (20) se podigne do međupoložaja (58) u bušotini (52) dok se ulijeva suspenzija veziva (55), gdje između dna bušotine (54) i međupoložaja (58) se dobije donje područje miješanja (56), u kojem se olabavljeni materijal tla (53) pomiješa s ulivenom suspenzijom veziva (55) u žbuku za tlo (57), – u trećem koraku se najmanje dva kontinuirana pužna svrdla (20) spusti u donje područje miješanja (56), te – u četvrtom koraku najmanje jedno kontinuirano pužno svrdlo (20b), koje služi za transportiranje materijala tla (53) iz donjeg područja miješanja (56) u smjeru prema gore, i najmanje jedno kontinuirano pužno svrdlo (20a, 20c), koje služi za transportiranje olabavljenog materijala tla (53) iz gornjeg područja bušotine (59), iznad međupoložaja (58), u donje područje miješanja (56), su pod pogonom u najmanju ruku dok se žbuku za tlo (57) ne transportira iz donjeg područja miješanja (56) do površine tla (51).1. A method for making a plastered wall on the ground (60) in the ground (50) with a drilling device (10) with at least two continuous augers (20) located closely parallel to each other, where at least two continuous augers (20) are drilled into the ground (50), thereby loosening the soil material (53), which is then mixed in the well (52) with a slurry of binder (55) in the soil mortar (57), which, after removing at least two continuous augers (20), hardens into a plastered wall on the ground (60) in a well (52), indicated by the fact that – in the first step, at least two continuous auger drills (20) are drilled to the depth of the well, while the soil is simultaneously crushed and loosened (50), where the loosened soil material (54) mostly remains in the well (52), - in the second step, at least two continuous screw augers (20) are raised to the intermediate position (58) in the well (52) while the binder suspension (55) is poured in, where between the bottom of the well (54) and the intermediate position (58) the lower mixing area is obtained (56), in which the loosened soil material (53) is mixed with a poured binder suspension (55) in the soil mortar (57), - in the third step, at least two continuous screw augers (20) are lowered into the lower mixing area (56), and - in the fourth step, at least one continuous auger (20b), which serves to transport soil material (53) from the lower mixing area (56) in the upward direction, and at least one continuous auger (20a, 20c), which serves to transport of loosened soil material (53) from the upper area of the well (59), above the intermediate position (58), into the lower mixing area (56), are operated at least until the soil mortar (57) is transported from the lower mixing area (56) ) to the ground surface (51). 2. Postupak u skladu s patentnim zahtjevom 1, naznačen time što se upotrebljava uređaj za bušenje (10) s tri međusobno blisko smještena kontinuirana pužna svrdla (20).2. The method according to patent claim 1, characterized in that a drilling device (10) with three closely spaced continuous auger bits (20) is used. 3. Postupak u skladu s patentnim zahtjevom 2, naznačen time što u četvrtom koraku dva vanjska kontinuirana pužna svrdla (20a, 20c) su pod pogonom kako bi se transportirao materijal tla (53) u donje područje miješanja (56), a središnje kontinuirano pužno svrdlo (20b) je pod pogonom kako bi se transportiralo žbuku za tlo (57) iz donjeg područja miješanja (56) u smjeru prema gore.3. The method according to patent claim 2, characterized in that in the fourth step two outer continuous screw augers (20a, 20c) are driven to transport the soil material (53) into the lower mixing area (56), and the central continuous screw the auger (20b) is driven to transport the soil mortar (57) from the lower mixing area (56) in an upward direction. 4. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 3, naznačen time što se u prvom koraku tijekom labavljenja tla (50) ulijeva suspenzija veziva (55) radi podmazivanja kroz najmanje jedno šuplje tijelo (22) kontinuiranog pužnog svrdla (20).4. The method according to any one of the patent claims 1 to 3, characterized in that in the first step during the loosening of the soil (50) a binder suspension (55) is poured for lubrication through at least one hollow body (22) of the continuous screw auger (20). . 5. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 4, naznačen time što se u donjoj polovici bušotine (52) osigura međupoložaj (58).5. The method according to any one of patent claims 1 to 4, characterized in that an intermediate position (58) is provided in the lower half of the well (52). 6. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 5, naznačen time što u prvom koraku, ovisno o smjeru pužnica svrdla (24), gdje su kontinuirana pužna svrdla (20) pod pogonom kako bi ih se bušilo u tlo (50), gdje se mijenja smjer vrtnje u zadanim vremenskim razmacima.6. A method according to any one of claims 1 to 5, characterized in that in the first step, depending on the direction of the auger augers (24), where the continuous auger augers (20) are driven to drill into the ground (50 ), where the direction of rotation changes at given time intervals. 7. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 6, naznačen time što u drugom koraku se brzinu vrtnje i aksijalno gibanje kontinuiranih pužnih svrdla (20) podešava ovisno o dotoku suspenzije veziva (55), tako da se u donjem području miješanja (56) olabavljeni materijal tla (53) i suspenzija veziva (55) lako pomiješa u žbuku za tlo (57).7. The method according to any one of the patent claims 1 to 6, characterized in that in the second step the rotation speed and axial movement of the continuous screw augers (20) are adjusted depending on the inflow of the binder suspension (55), so that in the lower mixing area (56) loosened soil material (53) and binder suspension (55) are easily mixed into the soil mortar (57). 8. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 7, naznačen time što prije ili nakon drugog koraka kontinuirana pužna svrdla (20) su pod rotacijskim pogonom bez aksijalnog gibanja.8. The method according to any one of patent claims 1 to 7, characterized in that before or after the second step, the continuous auger drills (20) are under rotary drive without axial movement. 9. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 8, naznačen time što u trećem koraku se kontinuirana pužna svrdla (20) spuste do dna bušotine (54).9. The method according to any one of patent claims 1 to 8, characterized in that in the third step, the continuous auger drills (20) are lowered to the bottom of the well (54). 10. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 9, naznačen time što u četvrtom koraku se žbuka za tlo (57), transportiranu prema gore, do površine tla (51), transportira natrag, prema donjem području miješanja (56).10. The method according to any one of the patent claims 1 to 9, characterized in that in the fourth step the soil plaster (57), transported upwards to the surface of the soil (51), is transported back towards the lower mixing area (56) . 11. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 10, naznačen time što u bušotini (52) se postigne okomiti kružni tok.11. The method according to any one of patent claims 1 to 10, characterized in that a vertical circular flow is achieved in the well (52). 12. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 11, naznačen time što u četvrtom koraku se prekine ulijevanje suspenzije veziva (55) dok kontinuirana pužna svrdla (20) nastavljaju s vrtnjom radi dodatnog homogeniziranja žbuke za tlo (57) u bušotini (52).12. The method according to any one of patent claims 1 to 11, characterized in that in the fourth step, the pouring of the binder suspension (55) is stopped while the continuous auger drills (20) continue to rotate for additional homogenization of the soil mortar (57) in the borehole (52). 13. Postupak u skladu s bilo kojim od patentnih zahtjeva 1 do 12, naznačen time što kako bi se napravila kontinuirana žbukana stijenka na tlu (60) načini se više međusobno blisko smještenih bušotina (52).13. The method according to any one of the patent claims 1 to 12, characterized in that in order to make a continuous plastered wall on the ground (60), a number of closely spaced wells (52) are made. 14. Uređaj za bušenje s najmanje dva kontinuirana pužna svrdla (20) s rotacijskim pogonom za pravljenje žbukane stijenke na tlu (60), gdje najmanje jedno kontinuirano pužno svrdlo (20) ima središnju šupljinu u tijelu (22) za ulijevanje suspenzije veziva (55) u bušotinu (52), naznačen time što je osigurana kontrola automatske provedbe postupka u skladu s bilo kojim od patentnih zahtjeva 1 do 13.14. Drilling device with at least two continuous auger bits (20) with a rotary drive for making a plaster wall on the ground (60), where at least one continuous auger bit (20) has a central cavity in the body (22) for pouring a binder suspension (55) ) in the well (52), characterized by the fact that control of the automatic implementation of the procedure is provided in accordance with any of the patent claims 1 to 13.
HRP20151199TT 2012-05-25 2015-11-09 Method for producing a floor mortar wall in the floor HRP20151199T1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP12004086.0A EP2666911B1 (en) 2012-05-25 2012-05-25 Method for producing a floor mortar wall in the floor

Publications (1)

Publication Number Publication Date
HRP20151199T1 true HRP20151199T1 (en) 2015-12-04

Family

ID=46384086

Family Applications (1)

Application Number Title Priority Date Filing Date
HRP20151199TT HRP20151199T1 (en) 2012-05-25 2015-11-09 Method for producing a floor mortar wall in the floor

Country Status (5)

Country Link
EP (1) EP2666911B1 (en)
HK (1) HK1187084A1 (en)
HR (1) HRP20151199T1 (en)
HU (1) HUE025973T2 (en)
PL (1) PL2666911T3 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3081699B1 (en) 2015-04-14 2018-01-31 BAUER Spezialtiefbau GmbH Civil engineering device and method for creating a foundation element in the ground
EP4296431A1 (en) * 2022-06-24 2023-12-27 BAUER Spezialtiefbau GmbH Method for laying out and forming a supporting wall in the ground and supporting wall

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4219150C1 (en) 1992-06-11 1993-09-23 Bauer Spezialtiefbau Gmbh, 86529 Schrobenhausen, De Underground mortar column prodn. - by drilling with auger through which hardenable suspension is fed
FR2715177B1 (en) * 1994-01-14 1996-03-01 Sif Improved device for making in place columns of stabilized and compacted soil.
DE10238646B3 (en) 2002-08-23 2004-04-01 Bauer Spezialtiefbau Gmbh Production of water-tight vertical walls used in the production of building foundations comprises forming secondary lamellae in the spaces between the primary lamellae, and forming homogenizing lamellae between the other lamellae
DE102010027607A1 (en) * 2010-07-20 2012-01-26 Bauer Spezialtiefbau Gmbh In-situ manufactured floor mortar slats with geometric representation
EP2423388A1 (en) * 2010-08-30 2012-02-29 Bauer Spezialtiefbau GmbH Method and device for manufacturing a slotted wall

Also Published As

Publication number Publication date
EP2666911A1 (en) 2013-11-27
PL2666911T3 (en) 2016-01-29
HUE025973T2 (en) 2016-05-30
EP2666911B1 (en) 2015-09-23
HK1187084A1 (en) 2014-03-28

Similar Documents

Publication Publication Date Title
CN102704873B (en) Construction equipment of hole drilling/punching cast-in-place pile with self-provided mud pit and mud separating device
CN105649012B (en) Upper-soft lower-hard ground subway station building enclosure drilled pile construction method
CN103806840B (en) One-way spiral half soil compaction drill bit and one-way spiral half Squeezing Soil Pile construction technology
CN104295239A (en) Method for using rotary drilling rig to drill into hard rock stratum
RU2439274C1 (en) Well construction method
HRP20151199T1 (en) Method for producing a floor mortar wall in the floor
CN110847200B (en) Dewatering and draining structure and dewatering and draining method for horizontal sand well of annular foundation pit
CN107268608A (en) Building waste earth-boring stake forming hole method
CN104846820B (en) Hold type screw-type Squeezing Soil Pile pile-forming equipment and bore forming method in a kind of end
CN104400914A (en) Method and device for realizing lateral drilling of blind hole in small-diameter deep hole
CN104563104A (en) Linkage type wall protecting device for pile driving drilling machine and construction method for using linkage type wall protecting device for pile driving drilling machine
CN204608773U (en) Pile work drilling machine coordinated type breast wall apparatus
CN100585091C (en) Rotary squeezing filling pile and pile-forming method therefor
CN103953280B (en) A kind of Road Bridge Pile Foundation water drilling hole-forming device and boring method
CN113931572B (en) Construction method of large-diameter pile foundation of composite stratum and drill bit system
CN205100208U (en) Crowded, reaming reinforced concrete bored concrete pile composite pile of high water spray earth anger
CN101349059A (en) New technique of long screw driller for press pouring reinforced concrete
CN211395715U (en) Dewatering and dewatering structure for horizontal sand well of annular foundation pit
CN109184564A (en) Method for correcting error when oblique rock stratum is met in a kind of rotary drilling rig pore-forming
CN103774645A (en) Cemented soil and concrete composite pile and construction method thereof
CN204419049U (en) Vertical concrete drilling machine bracing or strutting arrangement
CN204357355U (en) Combined screw thread soil compaction pore-forming sand drain drill bit
CN104746511B (en) Quality of pile control method is dug in rotation when a kind of rich water sand bed
CN209162815U (en) A kind of Screw Pile and its construction tool
CN103306277B (en) A kind of construction method utilizing rigid pile to embed Low Intensity Concrete Piles making compound water stop curtain