GB2520679A - New house service connection chamber - Google Patents

New house service connection chamber Download PDF

Info

Publication number
GB2520679A
GB2520679A GB1320892.1A GB201320892A GB2520679A GB 2520679 A GB2520679 A GB 2520679A GB 201320892 A GB201320892 A GB 201320892A GB 2520679 A GB2520679 A GB 2520679A
Authority
GB
United Kingdom
Prior art keywords
chamber
service
mains
connection chamber
house service
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
GB1320892.1A
Other versions
GB201320892D0 (en
Inventor
Hugh Liddle
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to GB1320892.1A priority Critical patent/GB2520679A/en
Publication of GB201320892D0 publication Critical patent/GB201320892D0/en
Priority to GB1409210.0A priority patent/GB2520784A/en
Publication of GB2520679A publication Critical patent/GB2520679A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/10Installations of electric cables or lines in or on the ground or water in cable chambers, e.g. in manhole or in handhole

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Casings For Electric Apparatus (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

A new house service connection chamber comprises a preformed plastic chamber (2, figure 2) with a removable lid (8, figure 2). The chamber creates an accessible void over mains utility services, such as electricity, gas or water, and may allow house service connections to be formed without repeated excavation in the vicinity of live service lines. The chamber may have knock out or break away panels (4, figure 2) in its walls corresponding with the correct depths and locations for service mains and house connections. The chamber may accommodate varying diameters of service mains and may support the load of pedestrian and light vehicular traffic.

Description

Front Line Construction Ltd Patent ApIication for a New House Service Connection Chamber
Description
Background
This invention relates to the safe connection of statutory services on new build housing developments which typically include electricity, gas, water and communications.
On new build housing developments, mains services are installed and made live in advance of dwelling construction, however individual service connections cannot be made until the dwelling house is constructed and made secure.
Mains services are generally located in development footpaths. Presently, in the interests of site presentation and safe access to building plots, mains service tracks are backfilled and the footpaths part constructed prior to dwelling construction. Consequently, it is necessary to excavate to expose the mains services in order to form the connections for each new house.
Excavation in the vicinity of live services is an extremely hazardous operation due to the possibility of damage to the mains from strikes by tools or plant. The consequences of such strikes are injury or death to operatives through electrocution or explosion.
This operation is made even more hazardous by the failure of utility contractors to lay mains services at the correct line or level. This means that the location of cables or pipes can deviate from their intended position thereby increasing the risk of strikes.
To compound matters, the connection of the individual services is done by different bodies at different times. There can be a considerable lapse of time between these operations and in order to maintain safe site conditions, the excavations are generally backfilled to reduce the risk inherent in having open trenches into which vehicles or people can fall. Therefore the same pits can be excavated two or three times. This re-excavation greatly increases the risk of service strikes.
Service strikes present a huge problem to the house building industry. Numerous initiatives based on procedure and working methods have been tried but most fail due to human error, high cost or adverse impact on other activities.
In order to overcome the hazards described above, the invention comprises a preformed plastic chamber which is designed to create an accessible void over mains services by means of a removable lid. Knockout panels in the walls of the chamber provide routes for new service mains at the correct line and level. The invention therefore fulfils two main functions by: * Allowing access to underground mains services without the need for excavation whilst maintaining safe site conditions * Ensuring that the service mains are installed at the correct line and level.
Advantages The invention offers numerous advantages over the accepted industry method, namely by: Preventing the risk of injury or death to operatives engaged in the connection of new services by removing the requirement to excavate in the vicinity of live service mains.
Preventing the risk of injury or death to operatives engaged in future maintenance, construction or repair in the vicinity of mains services by ensuring that they are laid to the correct line and level.
* Allowing individual service connections to be carried out at different times whilst maintaining safe site conditions.
* Ensuring a cost effective method of achieving new service connections.
DescriDtion The invention will now be described by referring to the accompanying drawings: Figure 1 Recommended mains positions relative to other Utility Apparatus in Footways Figure 2 Cross section through a development footpath illustrating the invention in situ Figure 3 Sketch illustrating the effect of excavation without the correct datum Figure 4 Plan view of invention in situ Figure 5 Side elevation of invention in situ Figure 6 Isometric view of invention As noted above, the invention fulfils two main tasks.
Firstly, it negates the need to excavate in the vicinity of live services in order to provide a service connection to a new property. This is achieved by forming an accessible void over the point of connection using a preformed plastic chamber. Refer to Figure 6 for an illustration of the chamber.
Utility services to new developments are located within either footpaths or shared surface service strips.
Figure 1 shows the recommended arrangement of Utility apparatus in a new footpath by means of cross section. This detail is adopted in Road and Footpath Construction detail drawings on new developments.
The Water, Gas and Electricity mains are generally laid following the construction of the road but before the permanent construction of the footpath.
Figure 2 illustrates the relationship between the footpath construction (Fig 2-1), the service mains and the preformed chamber (Fig 2-2) The chamber is placed on a prepared formation 850mm below the level of the top of the kerb log (Fig 2-3) and set level from front to back and at a gradient corresponding with the footpath side to side.
The walls of the preformed chamber contain knock out panels shown hatched on the drawing (Fig 2-4). The chamber can be installed by one of two methods: Placing the chamber on the formation, breaking out the circular knock out panels and feeding the mains through the holes or * Breaking out the full height knock out panels and placing the chamber over pre-laid mains onto the formation.
The first option is preferable in order to ensure the correct line and level of the services however the second provides the flexibility to allow use of the chamber on a site where mains have already been laid.
Once the chamber has been laid on the formation, the services can be laid.
The chamber is designed to accommodate all of the commonly used cable and pipe scenarios in that: * It is of sufficient depth to accommodate differing bed and surround depths according to the service diameters * Concentric knock out panels are incorporated to allow different service diameters.
(Fig 2-5) * Spare knock out panels are included to allow for additional services -i.e parallel mains.
Once the services have been installed, the service track is carefully backfilled. The sloping walls (Fig 2-6) provide additional strength by spreading load over the surface area of the walls as well as the flange footing (Fig 2-7). This flange footing allows free draining of the chamber during the construction process.
A preformed lid (Fig 2-8) is placed in a recess on the top of the chamber.
The lid and chamber are designed to withstand the load of a temporary footpath construction and foot traffic, thereby allowing safe access over service excavations.
The temporary footpath construction may be removed and access to the service mains gained via the removable lid.
The preformed chamber lid has hand hold cut outs to aid removal and replacement (Fig 2-9) The service connections are achieved by feeding the dwelling service pipes or cables into the chamber through the knock out panels on the walls perpendicular to the mains.
The chamber can be manufactured in a variety of sizes to suit the arrangement of specific plots and distances between house service pipes or cables.
The second function of the invention is to ensure that service mains are laid to the correct line and level.
It is the responsibility of those laying the mains to ensure that they are laid at the correct deptfl and in the correct position relative to the road kerb, however this can be difficult at the early stages of construction.
In practice, the existing ground levels on the footpath solum can vary greatly from the intended design levels. The Utility Contractor would not generally be contracted to reduce these levels and would therefore commence his excavations from the existing ground levels.
This can lead to the main service being laid at the wrong level.
By way of example, Figure 3 illustrates where a contractor has installed an electricity main by digging a track 600mm deep from the existing ground level where the excavation should have been 600mm deep from the finished level. This has the effect of leaving the cable higher than it should be and therefore vulnerable to an inadvertent strike.
The road kerb foundation (Fig 2-1) should be used to determine line and level at this stage, however due to site conditions and commercial pressures those installing the services may not refer to this datum often, if at all. In addition, those responsible for checking the quality of work may find it difficult to determine if they have been installed correctly or not.
The invention provides a means of ensuring correct installation by utilising the road kerb as a datum. When installed level, the chamber provides a predetermined route between plots for the service installer to work to, thereby preventing the deviation in line and level which leads to service strikes.

Claims (6)

  1. SClaims 1. A new house service connection chamber comprising a preformed plastic chamber with a removable lid, designed to create an accessible void over mains utility services for the purpose of forming safe house service connections.
  2. 2. A new house service connection chamber according to claim 1 which prevents the need for excavation in the vicinity of live services in order to carry out house service connections.
  3. 3. A new house service connection chamber which according to preceding claims features knock out panels in its walls corresponding with the correct depths and locations for service mains and house connections.
  4. 4. A new house service connection chamber which according to preceding claims ensures that new mains services are laid to the correct line and level.
  5. 5. A new house service connection chamber which according to preceding claims accommodates varying diameters of service main.
  6. 6. A new house service connection chamber which according to preceding claims supports the load of footpath construction and pedestrian I light vehicular traffic.
GB1320892.1A 2013-11-27 2013-11-27 New house service connection chamber Withdrawn GB2520679A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
GB1320892.1A GB2520679A (en) 2013-11-27 2013-11-27 New house service connection chamber
GB1409210.0A GB2520784A (en) 2013-11-27 2014-05-23 Apparatus for facilitating access to utility services for buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB1320892.1A GB2520679A (en) 2013-11-27 2013-11-27 New house service connection chamber

Publications (2)

Publication Number Publication Date
GB201320892D0 GB201320892D0 (en) 2014-01-08
GB2520679A true GB2520679A (en) 2015-06-03

Family

ID=49918256

Family Applications (2)

Application Number Title Priority Date Filing Date
GB1320892.1A Withdrawn GB2520679A (en) 2013-11-27 2013-11-27 New house service connection chamber
GB1409210.0A Withdrawn GB2520784A (en) 2013-11-27 2014-05-23 Apparatus for facilitating access to utility services for buildings

Family Applications After (1)

Application Number Title Priority Date Filing Date
GB1409210.0A Withdrawn GB2520784A (en) 2013-11-27 2014-05-23 Apparatus for facilitating access to utility services for buildings

Country Status (1)

Country Link
GB (2) GB2520679A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024124312A1 (en) * 2022-12-15 2024-06-20 Fortlev Energia Solar Ltda Arrangement for a two-part underground junction box

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11338524B1 (en) 2018-10-26 2022-05-24 Afl Telecommunications Llc Method of forming a foldable or collapsible plastic and/or composite utility enclosure
US11349281B1 (en) 2018-10-26 2022-05-31 Afl Telecommunications Llc Foldable and/or collapsible plastic/composite utility enclosure
US11374386B2 (en) 2018-10-26 2022-06-28 Afl Telecommunications Llc Foldable and/or collapsible plastic/composite utility enclosure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4163503A (en) * 1978-09-20 1979-08-07 D/FW Plastics, Inc. Lid and housing
GB2248866A (en) * 1990-10-10 1992-04-22 Cable Lan Supply Limited Access chamber/junction box
EP1061183A2 (en) * 1999-06-18 2000-12-20 Swintex Limited Improvements in or relating to underground junction boxes
GB2351751A (en) * 1999-06-18 2001-01-10 Swintex Underground junction boxes
US20040231724A1 (en) * 2003-05-23 2004-11-25 Mahaney Mark B. Configurable valve-electrical box for underground conduit system to distribute water to landscaping
WO2013178644A1 (en) * 2012-05-30 2013-12-05 Peter Savage Limited Ducting chamber ring and module, a ducted chamber and a method of assembling a modular chamber system

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4872575A (en) * 1987-06-30 1989-10-10 Kobilan Errol D Protective housing structure for underground devices
JP2911820B2 (en) * 1996-05-20 1999-06-23 岡部株式会社 Earthquake-resistant connection structure between the cable housing conduit and the measure member
US5770817A (en) * 1996-09-20 1998-06-23 Lo; Jeffrey C. P. Raceway box with replaceable cable and connector receptacles
JP2000204510A (en) * 1999-01-14 2000-07-25 Nsp Corp Temporary paving cover for junction box in electric-wire utility tunnel
JP2005027375A (en) * 2003-06-30 2005-01-27 Takiron Co Ltd Branch handhole
DE202007014465U1 (en) * 2007-10-16 2007-12-20 Frei Netzwerk Ausstattung Gmbh Underfloor bay
DE202009007474U1 (en) * 2009-03-25 2009-10-08 Lic Langmatz Gmbh Underfloor duct arrangement for housing fiber optic cables
BE1019103A3 (en) * 2009-12-04 2012-03-06 Plastic Color Nv BUILT-IN BOX FOR ELECTRIC MATERIAL.
US8138418B2 (en) * 2010-02-10 2012-03-20 Cordelia Lighting, Inc. Electrical junction box

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4163503A (en) * 1978-09-20 1979-08-07 D/FW Plastics, Inc. Lid and housing
GB2248866A (en) * 1990-10-10 1992-04-22 Cable Lan Supply Limited Access chamber/junction box
EP1061183A2 (en) * 1999-06-18 2000-12-20 Swintex Limited Improvements in or relating to underground junction boxes
GB2351751A (en) * 1999-06-18 2001-01-10 Swintex Underground junction boxes
US20040231724A1 (en) * 2003-05-23 2004-11-25 Mahaney Mark B. Configurable valve-electrical box for underground conduit system to distribute water to landscaping
WO2013178644A1 (en) * 2012-05-30 2013-12-05 Peter Savage Limited Ducting chamber ring and module, a ducted chamber and a method of assembling a modular chamber system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024124312A1 (en) * 2022-12-15 2024-06-20 Fortlev Energia Solar Ltda Arrangement for a two-part underground junction box

Also Published As

Publication number Publication date
GB201320892D0 (en) 2014-01-08
GB201409210D0 (en) 2014-07-09
GB2520784A (en) 2015-06-03

Similar Documents

Publication Publication Date Title
US8538225B2 (en) Communications ducting system and method of laying same
KR100748258B1 (en) In the troy line tube in high tension cable underground power line use a conduit line spatial-temporal method
GB2520679A (en) New house service connection chamber
CN109695247B (en) Deep foundation pit temporary pipeline comprehensive arrangement system and construction method
CN108547628B (en) Quick construction method for pipe-jacking working well in upper-soft and lower-hard stratum
EP2957676A1 (en) Telescopic type riser system equipment for digging round pits and its utilization method
Tervydis et al. Horizontal directional drilling pilot bore simulation
US9876337B2 (en) Machine arranged for sawing micro trenches and placing ducts/cables in micro trenches
RU2720893C1 (en) Development method of repair trench for replacement of defect section of pipeline
KR100731957B1 (en) A case for prevention damage of a drain pipe
AU2012101957A4 (en) Piping
CN110761346A (en) Method and tool for rapidly excavating channel
JP7380282B2 (en) Repair structure and method for underground pipelines
WO2006021244A1 (en) Excavating bucket and method for digging using such an excavating bucket
US20240151058A1 (en) Assembled utility pole, pole building method and rebuilding method
CN102661441B (en) A kind of no-dig technique pipeline construction method
JP5729712B1 (en) Earth retaining method and earth retaining unit
CN219604375U (en) Pipeline foundation pit supporting structure
JP6444808B2 (en) Method of installing new equipment in power plant and power plant
KR20090120796A (en) Laying method of water supply and drain on housing complex
JP4630215B2 (en) Relocation method for buried objects
CN111509649A (en) Temporary debugging power supply configuration scheme
KR200412513Y1 (en) A case for prevention damage of a drain pipe
Olatunji et al. Box-Tunneling Saves the Day from Utility Congestion
KR20230163984A (en) Th method of of burying the protection steel pipe horizontally without excavation

Legal Events

Date Code Title Description
WAP Application withdrawn, taken to be withdrawn or refused ** after publication under section 16(1)