FR2863098A1 - Dismantling of damaged industrial plant, such as nuclear facility, comprises confining and sealing off damaged section and decontaminating via access from undamaged section - Google Patents

Dismantling of damaged industrial plant, such as nuclear facility, comprises confining and sealing off damaged section and decontaminating via access from undamaged section Download PDF

Info

Publication number
FR2863098A1
FR2863098A1 FR0314067A FR0314067A FR2863098A1 FR 2863098 A1 FR2863098 A1 FR 2863098A1 FR 0314067 A FR0314067 A FR 0314067A FR 0314067 A FR0314067 A FR 0314067A FR 2863098 A1 FR2863098 A1 FR 2863098A1
Authority
FR
France
Prior art keywords
damaged
construction
confinement
containment
dismantling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
FR0314067A
Other languages
French (fr)
Other versions
FR2863098B1 (en
Inventor
Gregoire Alexandroff
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to FR0314067A priority Critical patent/FR2863098B1/en
Priority to UA20041008364A priority patent/UA83462C2/en
Publication of FR2863098A1 publication Critical patent/FR2863098A1/en
Application granted granted Critical
Publication of FR2863098B1 publication Critical patent/FR2863098B1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B5/00Operations not covered by a single other subclass or by a single other group in this subclass
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C13/00Pressure vessels; Containment vessels; Containment in general
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21DNUCLEAR POWER PLANT
    • G21D1/00Details of nuclear power plant
    • G21D1/003Nuclear facilities decommissioning arrangements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • High Energy & Nuclear Physics (AREA)
  • General Engineering & Computer Science (AREA)
  • Plasma & Fusion (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The process comprises confining the damaged section (10) of the plant with a structure (30) that covers and seals it, and then decontaminating the damaged section using access from the undamaged section (28) in order to process dangerous materials removed from the damaged section. The decontamination process is carried out with a pressure below atmospheric inside the sealed confinement structure, which can be built at a distance from the damaged section and then moved into place on tracks (32, 34) to cover it.

Description

2863098 12863098 1

La présente invention concerne un procédé de démantèlement d'installations industrielles accidentées dangereuses, ainsi qu'un dispositif de confinement utile pour la mise en oeuvre de ce procédé, et un procédé de fabrication d'un tel dispositif de confinement.  The present invention relates to a method of dismantling hazardous industrial accidents, as well as a containment device useful for implementing this method, and a method of manufacturing such a containment device.

Le procédé de démantèlement selon l'invention ne s'applique que dans le cas où la partie d'installation accidentée à démanteler jouxte une partie d'installation industrielle non accidentée.  The dismantling method according to the invention applies only in the case where the damaged installation part to be dismantled adjoins a non-accident industrial installation part.

Dans la description qui suit de l'invention, on appelle "démantèlement" une opération qui comprend obligatoirement une décontamination, mais qui peut comprendre en outre la destruction de la structure de la partie décontaminée.  In the following description of the invention, the term "dismantling" is understood to mean an operation which necessarily comprises a decontamination, but which may furthermore comprise the destruction of the structure of the decontaminated part.

Bien que l'invention puisse s'appliquer à diverses situations, on décrit l'invention dans son application au démantèlement de la partie accidentée de la centrale nucléaire de Tchernobyl comportant le réacteur n 4.  Although the invention can be applied to various situations, the invention is described in its application to the dismantling of the rugged part of the Chernobyl nuclear power plant comprising reactor No. 4.

On sait que la centrale nucléaire de Tchernobyl comprend quatre réacteurs adjacents par paire. Ainsi, les réacteurs n 3 et 4 partagent une structure commune intermédiaire notamment munie d'une cheminée. Lorsqu'en 1986 le réacteur n 4 a été accidenté, la partie d'installation relative au réacteur n 3 et la structure commune intermédiaire n'ont pas été accidentées et ont continué à fonctionner et à fournir de l'énergie électrique jusqu'en 2000.  The Chernobyl nuclear power plant is known to have four adjacent reactors in pairs. Thus, the reactors No. 3 and 4 share a common intermediate structure including a chimney. When, in 1986, the No. 4 reactor was damaged, the reactor part relating to the No. 3 reactor and the intermediate common structure were not damaged and continued to operate and supply electric power until 2000. .

Etant donné les dangers présentés par l'installation du réacteur n 4, la communauté internationale s'est mobilisée pour trouver une solution contre les risques présentés par cette situation. En l'état actuel des projets, il est envisagé de construire une gigantesque enceinte de confinement destinée à couvrir la protection mise en place d'urgence autour du réacteur n 4, appelée le "sarcophage". Cette enceinte doit être très grande, car il est prévu d'y installer des installations de décontamination et de stockage de déchets, lorsque, après mise en place de l'enceinte de confinement, le démantèlement de l'installation sera 2863098 2 entrepris depuis l'extérieur du sarcophage, notamment à partir de la toiture.  Given the dangers presented by the installation of reactor No. 4, the international community has mobilized to find a solution against the risks presented by this situation. In the current state of the projects, it is envisaged to build a gigantic containment enclosure intended to cover the protection set up urgently around the reactor n 4, called the "sarcophagus". This enclosure must be very large, since it is planned to install decontamination and waste storage facilities, when, after the containment has been put in place, the dismantling of the facility will be undertaken since outside the sarcophagus, especially from the roof.

En l'état actuel des projets, on ne connaît aucun calendrier pour l'exécution de ces opérations de démantè- lement, et on envisage donc de réaliser une enceinte capable de résister pendant un siècle.  In the current state of the projects, no timetable is known for the execution of these dismantling operations, and it is therefore envisaged to build a chamber capable of withstanding for a century.

L'invention concerne un procédé de démantèlement de la partie d'installation accidentée du réacteur n 4 de la centrale de Tchernobyl, susceptible d'être exécuté en quelques années seulement. Plus précisément, selon l'invention, le démantèlement, comprenant la décontamination et le conditionnement des déchets extraits, est réalisé depuis la partie d'installation utilisée pour le réacteur n 3 qui n'est plus utilisé et est en cours de démontage. Cette partie d'installation présente toutes les propriétés nécessaires de protection contre la radioactivité et contre les autres risques, et elle a un volume considérable, bien supérieur au volume nécessaire au logement d'une installation de démantèlement et de stockage temporaire des déchets.  The invention relates to a method for dismantling the accident site of reactor No. 4 at the Chernobyl power station, which can be executed in a few years only. More precisely, according to the invention, the dismantling, including the decontamination and the conditioning of the extracted waste, is carried out from the part of the installation used for the reactor n 3 which is no longer used and is being dismantled. This part of the installation has all the necessary properties of protection against radioactivity and against other risks, and it has a considerable volume, much higher than the volume necessary for the housing of a dismantling installation and temporary storage of waste.

L'accès à la partie d'installation accidentée du réacteur n 4 depuis la partie d'installation utilisée pour le réacteur n 3 est effectué à travers la structure intermédiaire commune aux réacteurs 3 et 4, par perçage d'ouvertures dans les parties robustes existantes de cette structure intermédiaire.  Access to the uneven installation part of the reactor n 4 from the installation part used for the reactor n 3 is carried out through the intermediate structure common to the reactors 3 and 4, by drilling openings in the existing robust parts. of this intermediate structure.

Un avantage primordial de ce procédé est l'augmentation de la sécurité des populations, jusqu'à des distances considérables de la centrale de Tchernobyl. D'abord, puisqu'il n'est pas nécessaire d'accéder à l'intérieur du réacteur accidenté à travers le sarcophage, mais seulement à partir d'une structure résistante qui a déjà fait ses preuves, le risque d'effondrement du sarcophage lors du démantèlement est donc réduit. Ensuite, comme la durée du démantèlement est considérablement raccourcie, le temps pendant lequel le risque existe est lui aussi considérablement réduit.  A major advantage of this process is the increased safety of the populations, up to considerable distances from the Chernobyl power station. First, since it is not necessary to access the interior of the damaged reactor through the sarcophagus, but only from a resistant structure that has already been proven, the risk of collapse of the sarcophagus when dismantling is reduced. Then, as the duration of the dismantling is considerably shortened, the time during which the risk exists is also considerably reduced.

Un autre avantage important est que le coût du démantèlement est considérablement réduit, d'une part puisqu'il n'est pas nécessaire de construire une installation 2863098 3 spécifique, et d'autre part puisque ce démantèlement peut être réalisé très rapidement, étant donné que l'installation existe déjà.  Another important advantage is that the cost of dismantling is considerably reduced, on the one hand because it is not necessary to build a specific installation, and on the other hand since this dismantling can be done very quickly, given that that the installation already exists.

Plus précisément, l'invention concerne un procédé de démantèlement d'une partie d'installation industrielle accidentée dangereuse pour l'homme, qui jouxte une partie d'installation industrielle non accidentée qui a des caractéristiques de protection contre des matières dangereuses; selon l'invention, ce procédé comprend le confinement de la partie accidentée par un dispositif de confinement qui la recouvre de manière pratiquement étanche, et la décontamination de la partie accidentée par accès à celleci depuis la partie non accidentée, avec utilisation des caractéristiques de protection de la partie non accidentée pour le traitement des matières dangereuses retirées de la partie accidentée. Par exemple, les matières dangereuses sont radioactives.  More specifically, the invention relates to a method of dismantling a portion of industrial plant accidentally dangerous to humans, which adjoins a non-uneven industrial plant part that has protection characteristics against hazardous materials; according to the invention, this method comprises the confinement of the damaged part by a confinement device which covers it in a substantially watertight manner, and the decontamination of the damaged part by access to it from the non-damaged part, with use of the protection characteristics the non-accidental part for the treatment of hazardous materials removed from the damaged part. For example, hazardous materials are radioactive.

De préférence, le confinement est réalisé avec un dispositif de confinement qui recouvre la partie accidentée 20 à une grande proximité de celle-ci.  Preferably, the confinement is carried out with a confinement device which covers the rugged part 20 in close proximity to the latter.

Il est avantageux que le dispositif de confinement soit pratiquement étanche, et que l'opération de décontamination soit exécutée alors que le dispositif de confinement est maintenu en dépression.  It is advantageous that the containment device is substantially sealed, and that the decontamination operation is performed while the confinement device is kept in depression.

De préférence, l'accès à la partie accidentée depuis la partie non accidentée est réalisé par perçage d'une structure séparant la partie accidentée de la partie non accidentée.  Preferably, access to the rugged portion from the non-rugged portion is achieved by drilling a structure separating the rugged portion of the non-rugged portion.

Il est avantageux que l'étape de confinement comprenne la construction d'un dispositif de confinement à distance de l'installation, et le déplacement du dispositif de confinement afin qu'il vienne couvrir la partie accidentée, par exemple par roulement sur des rouleaux.  It is advantageous for the confinement step to comprise the construction of a remote confinement device of the installation, and the displacement of the confinement device so that it covers the rugged part, for example by rolling on rollers.

De préférence, le procédé comporte, après le déplace- ment du dispositif de confinement, la création d'une étanchéité entre la partie inférieure du dispositif de confinement et le sol, par exemple par coulée de béton au niveau du sol.  Preferably, the method comprises, after the displacement of the confinement device, the creation of a seal between the lower part of the confinement device and the ground, for example by pouring concrete at ground level.

2863098 4 De préférence, le procédé comporte, après le déplacement du dispositif de confinement, la création d'une étanchéité entre la structure de la partie accidentée et le bord d'une ouverture d'une face du dispositif de confi- nement, par exemple par des dispositifs à guillotine.  Preferably, the method comprises, after the displacement of the confinement device, the creation of a seal between the structure of the damaged part and the edge of an opening of a face of the confinement device, for example by guillotine devices.

Selon un perfectionnement, le procédé comporte en outre, après la décontamination de la partie accidentée, la destruction de la structure de cette partie au moins.  According to an improvement, the method further comprises, after the decontamination of the damaged part, the destruction of the structure of this part at least.

Selon un autre perfectionnement, le procédé comporte en outre une étape de confinement de la nappe phréatique au moins autour de la partie accidentée.  According to another improvement, the method further comprises a step of confining the water table at least around the rugged part.

L'invention concerne aussi un dispositif de confinement d'installation industrielle accidentée dangereuse, notamment utile pour la mise en oeuvre du procédé de démantèlement précité.  The invention also relates to a hazardous accidental industrial installation containment device, particularly useful for the implementation of the aforementioned dismantling process.

Ce dispositif, très utile dans le cas de la centrale de Tchernobyl, a cependant des applications bien plus étendues. En effet, après un accident sur une installation industrielle contenant des matières dangereuses pour l'homme, en particulier des matières radioactives, il peut arriver que la partie accidentée qui est fragilisée rejette dans l'atmosphère, de manière imprévisible, une quantité importante de résidus dangereux pour l'homme, à une concentration très importante, dans une zone plus ou moins étendue autour du site accidenté. Les résidus peuvent se répandre dans l'atmosphère très rapidement dans certaines conditions climatiques. Le problème de l'occurrence d'un tel rejet se pose de façon encore plus importante lors de la phase de démantèlement et de décontamination des sites industriels accidentés contenant des résidus dangereux pour l'homme, car il est alors nécessaire de pratiquer des interventions sur le site même.  This device, very useful in the case of the Chernobyl plant, however, has much wider applications. In fact, after an accident on an industrial installation containing dangerous materials for humans, in particular radioactive materials, it can happen that the damaged part which is weakened releases into the atmosphere, in an unpredictable way, a large quantity of residues. dangerous for humans, at a very high concentration, in a more or less extensive area around the hilly site. The residues can spread in the atmosphere very quickly under certain climatic conditions. The problem of the occurrence of such a discharge is even more important during the phase of dismantling and decontamination of industrial sites with dangerous residues hazardous to humans, because it is then necessary to perform interventions on the site itself.

Lorsqu'il est trop dangereux ou trop difficile de commencer rapidement la décontamination du site accidenté pour éliminer le danger qu'il constitue pour son environ- nement, par exemple dans le cas de l'installation de la centrale nucléaire accidentée de Tchernobyl, pouvant émettre un très fort rayonnement, il peut être indispensable de 2863098 5 confiner provisoirement l'installation. Le dispositif de confinement doit empêcher un rejet accidentel de résidus dangereux pour l'homme et pour l'environnement, et il doit donc être suffisamment étanche sur une durée suffisante pour que les travaux de démantèlement du site accidenté soient terminés. D'une façon générale, il doit pouvoir être construit et installé dans les meilleures conditions de sécurité, tout en permettant un démantèlement de l'installation accidentée dans les meilleures conditions de sécurité.  When it is too dangerous or too difficult to start decontaminating the hilly site quickly to eliminate the danger it poses to the environment, for example in the case of the installation of the Chernobyl accidental nuclear power station, which may emit a very strong radiation, it may be necessary to temporarily 2863098 confine the installation. The containment system shall prevent accidental release of residues hazardous to humans and the environment, and must be sufficiently sealed for a period of time sufficient to complete the decommissioning of the accident site. In a general way, it must be able to be built and installed in the best safety conditions, while allowing a dismantling of the accidental installation in the best safety conditions.

Lors de la construction d'un tel dispositif de confinement, se pose le problème de la sécurité des intervenants. D'une part, il faut que les intervenants travaillent dans une atmosphère protégée contre d'éventuelles émissions dangereuses, qui est très difficile à obtenir complètement dans le cadre d'un chantier de construction, et d'autre part qu'ils aient accès rapidement à des abris qui les protègent totalement contre ces émissions.  During the construction of such a containment device, there is the problem of the safety of the workers. On the one hand, it is necessary that the workers work in an atmosphere protected against possible dangerous emissions, which is very difficult to obtain completely in the framework of a building site, and on the other hand that they have quick access shelters that protect them completely against these emissions.

Il est primordial que le temps qui s'écoule entre le moment où les intervenants sont avertis par un système de veille d'un rejet accidentel depuis l'installation accidentée et le moment où ils accèdent aux abris soit le plus court possible afin que les risques d'exposition à une substance dangereuse soient limités. Pour les mêmes raisons, il est primordial que le temps qui s'écoule entre le moment où les intervenants sont avertis et le moment où les substances dangereuses atteignent le site de construction soit le plus long possible. Dans certains cas, notamment en cas d'explosion de l'installation accidentée, cette durée peut être très courte.  It is essential that the time elapsed between the time when the workers are warned by a system of vigilance of an accidental release from the accidental installation and the moment when they access the shelters is as short as possible so that the risks exposure to a hazardous substance are limited. For the same reasons, it is essential that the time elapsing between the time when the responders are warned and the moment when the dangerous substances reach the construction site is as long as possible. In some cases, especially in case of explosion of the accident facility, this period can be very short.

Il est aussi important que la durée du chantier soit la plus courte possible, pour un nombre constant d'inter-venants, afin que les risques d'exposition du personnel soient limités. Enfin, il est important, pour les mêmes raisons de sécurité, que la durée du chantier de confinement soit la plus courte possible de façon que les risques que l'installation accidentée présente pour son environnement n'existent que pendant la période la plus courte possible.  It is also important that the duration of the project is as short as possible, for a constant number of stakeholders, so that the risks of exposure of the personnel are limited. Finally, it is important, for the same safety reasons, that the duration of the containment work be as short as possible so that the risks that the accidental installation presents for its environment only exist during the shortest possible period. .

2863098 6 On a déjà proposé des dispositifs de confinement préfabriqués à distance du site accidenté, de très grandes dimensions et destinés à recouvrir la totalité des installations accidentées, ces dispositifs étant déplacés ultérieurement sur des chemins de roulement jusqu'à l'emplacement accidenté. Un tel dispositif est envisagé pour confiner la partie accidentée du site nucléaire de Tchernobyl. Cependant, du fait de la taille considérable de ce dispositif de confinement, il faut prévoir de nombreux travaux en hauteur, et rien ne garantit qu'en cas de rejet de matières dangereuses, les intervenants puissent atteindre un abri de protection avant que les émissions de résidus n'atteignent le site de construction.  Pre-fabricated containment devices have been proposed far away from the hilly site, of very large size and intended to cover all of the hilly installations, these devices being subsequently moved on raceways to the hilly site. Such a device is envisaged to confine the rugged part of the Chernobyl nuclear site. However, because of the considerable size of this containment system, it is necessary to plan a lot of work at height, and there is no guarantee that, in the event of release of hazardous materials, the workers can reach a protective shelter before residues do not reach the construction site.

On connaît déjà un procédé de fabrication d'une telle enceinte de confinement sur le lieu du site accidenté, à base exclusivement de moyens robotisés. Cependant, ces moyens ne permettent pas de progresser rapidement, ils sont très coûteux, et surtout ils ne permettent pas de construire une enceinte de confinement suffisamment étanche.  A method of manufacturing such a containment enclosure on the site of the accident site, based exclusively on robotic means, is already known. However, these means do not make it possible to progress quickly, they are very expensive, and especially they do not make it possible to construct a sufficiently watertight enclosure of confinement.

L'invention concerne donc aussi un dispositif de confinement d'une partie d'installation industrielle accidentée, pouvant être préfabriquée à distance de cette partie d'installation accidentée, de très grandes dimensions, suffisantes afin qu'il recouvre la totalité de la partie d'installation accidentée, et qui peut être déplacé sur des chemins de roulement jusqu'au site accidenté.  The invention therefore also relates to a device for confining a damaged industrial installation part, which can be prefabricated at a distance from this part of a damaged installation, of very large size, sufficient to cover the entire part of the uneven installation, which can be moved on rolling tracks to the hilly site.

Plus précisément, l'invention concerne un dispositif de confinement d'une installation industrielle accidentée contenant des résidus dangereux pour l'homme, destinée à être déplacée entre un lieu de construction et un lieu d'utilisation au- dessus de l'installation industrielle accidentée; selon l'invention, le dispositif comporte une ossature et au moins un revêtement, et l'ossature est constituée de modules métalliques disposés en couches horizontales.  More specifically, the invention relates to a device for confining a damaged industrial plant containing residues dangerous to humans, intended to be moved between a place of construction and a place of use above the accident industrial facility ; according to the invention, the device comprises a frame and at least one coating, and the frame consists of metal modules arranged in horizontal layers.

De préférence, les modules métalliques sont formés d'un alliage léger, avantageusement d'aluminium.  Preferably, the metal modules are formed of a light alloy, preferably aluminum.

Dans un mode de réalisation avantageux, le dispositif de confinement a une forme parallélépipédique destinée à 2863098 7 entourer l'installation accidentée, et il possède au moins une ouverture de forme adaptée à la forme de la partie accidentée à couvrir.  In an advantageous embodiment, the confinement device has a parallelepipedal shape intended to surround the accidental installation, and it has at least one aperture of a shape adapted to the shape of the rugged part to be covered.

De préférence, le revêtement assure pratiquement l'étanchéité du dispositif de confinement.  Preferably, the coating substantially seals the containment device.

Dans un mode de réalisation, la partie supérieure du dispositif de confinement forme un toit incliné.  In one embodiment, the upper portion of the containment device forms an inclined roof.

De préférence, le dispositif comporte un dispositif destiné à mettre l'intérieur du dispositif de confinement en surpression lors de la construction du dispositif de confinement.  Preferably, the device comprises a device for putting the inside of the confinement device under overpressure during the construction of the confinement device.

De préférence, le dispositif comporte un dispositif destiné à mettre l'intérieur du dispositif de confinement en dépression lors de l'utilisation.  Preferably, the device comprises a device for putting the inside of the confinement device in depression during use.

Dans un mode de réalisation avantageux, le dispositif comporte des moyens de levage intégrés à une couche d'assise de l'ossature et travaillant en direction verticale afin qu'ils permettent le déplacement en hauteur du dispositif de confinement de la hauteur d'au moins une couche, par exemple des vérins.  In an advantageous embodiment, the device comprises lifting means integrated into a base layer of the framework and working in the vertical direction so that they allow the height of the confinement device to be moved upwards by at least a layer, for example cylinders.

De préférence, le revêtement comporte au moins deux couches de revêtement, l'une à l'intérieur et l'autre à l'extérieur de l'enceinte. Les couches de revêtement comprennent avantageusement chacune au moins un bardage porté par les modules, par exemple aussi formé d'alliage léger. Les couches de revêtement comprennent avantageusement chacune au moins une toile déroulée de haut en bas.  Preferably, the coating comprises at least two coating layers, one inside and one outside the enclosure. The coating layers advantageously comprise at least one cladding carried by the modules, for example also formed of light alloy. The coating layers each advantageously comprise at least one fabric unrolled from top to bottom.

De préférence, le dispositif comporte des câbles de contreventement.  Preferably, the device comprises bracing cables.

De préférence, le dispositif comporte au moins un dispositif intérieur de levage.  Preferably, the device comprises at least one internal lifting device.

De préférence, le dispositif comporte des butons disposés au moins aux coins intérieurs de la face ayant une ouverture.  Preferably, the device comprises buttresses arranged at least at the inner corners of the face having an opening.

De préférence, le dispositif comporte au moins un sas d'accès à l'intérieur du dispositif de confinement.  Preferably, the device comprises at least one access lock inside the containment device.

L'invention concerne aussi un procédé de fabrication d'un dispositif de confinement d'une installation 2863098 8 industrielle accidentée, le dispositif de confinement étant formé de couches horizontales; selon l'invention, le pro-cédé comprend la construction d'une assise munie de moyens de levage et d'une partie supérieure du dispositif de confinement, le levage de la partie supérieure du dispositif de confinement avec les moyens de levage d'une hauteur pratiquement égale à la hauteur d'une couche au moins pour la formation d'un espace au-dessus de l'assise, la construction d'une couche de l'ossature dans cet espace, avec solidarisation de cette couche et de la structure qui la surmonte, puis la répétition des étapes de levage et de construction d'une couche pour la construction d'au moins une couche supplémentaire, jusqu'à la construction de toutes les couches de l'ossature.  The invention also relates to a method of manufacturing a containment device of an accidental industrial installation, the confinement device being formed of horizontal layers; according to the invention, the method comprises the construction of a seat provided with lifting means and an upper part of the confinement device, the lifting of the upper part of the confinement device with the lifting means of a height substantially equal to the height of at least one layer for the formation of a space above the seat, the construction of a layer of the framework in this space, with the joining of this layer and the structure overcoming it, then repeating the steps of lifting and building a layer for the construction of at least one additional layer, until the construction of all layers of the framework.

De préférence, la construction de l'assise et d'une partie supérieure du dispositif de confinement comprend la construction d'un premier bâtiment ayant une hauteur correspondant à au moins quatre couches de l'ossature, ce bâtiment ayant une longueur au moins égale à la largeur du dispositif de confinement à construire et une largeur très inférieure à la longueur de ce dispositif, et la construction progressive de l'assise et de la partie supérieure du dispositif de confinement depuis un petit côté par association de modules dont certains au moins possèdent des vérins.  Preferably, the construction of the seat and an upper part of the confinement device comprises the construction of a first building having a height corresponding to at least four layers of the frame, this building having a length at least equal to the width of the containment device to be constructed and a width much less than the length of this device, and the progressive construction of the seat and the upper part of the confinement device from a short side by association of modules, some of which at least have cylinders.

Dans un mode de réalisation, le procédé comprend en outre, après la construction de la partie supérieure, la construction, autour de cette partie supérieure, d'une galerie de protection ayant une hauteur au moins égale à la hauteur de deux couches.  In one embodiment, the method further comprises, after the construction of the upper part, the construction, around this upper part, of a protection gallery having a height at least equal to the height of two layers.

Dans un autre mode de réalisation avantageux, le procédé est mis en oeuvre à distance de l'installation industrielle accidentée à laquelle il est destiné, et il comporte en outre la construction d'un mur de protection du site de construction ayant une hauteur au moins égale à la hauteur de deux couches d'ossature du côté tourné vers l'installation accidentée.  In another advantageous embodiment, the method is carried out at a distance from the industrial facility it is intended for, and it also comprises the construction of a construction site protection wall having a height at least equal to the height of two layers of framing on the side facing the uneven installation.

De préférence, le procédé comprend, au cours de toute la construction, l'application aux modules de revêtements 2863098 9 assurant une certaine étanchéité à l'ensemble du dispositif en cours de construction, et la mise en légère surpression de l'intérieur du dispositif en cours de construction.  Preferably, the method comprises, throughout the entire construction, the application to the coating modules 2863098 9 ensuring a certain tightness to the entire device under construction, and the slight overpressure of the inside of the device under construction.

Dans un mode de réalisation dans lequel le dispositif de confinement a, dans au moins une face latérale, une ouverture débouchant vers le bas, le procédé comprend avantageusement la construction, dans la partie destinée à former l'ouverture, d'un dispositif amovible assurant l'étanchéité.  In an embodiment in which the confinement device has, in at least one lateral face, an opening opening towards the bottom, the method advantageously comprises the construction, in the part intended to form the opening, of a removable device ensuring sealing.

D'autres caractéristiques et avantages de l'invention seront mieux compris à la lecture de la description qui va suivre d'exemples de réalisation, faite en référence aux dessins annexés sur lesquels: la figure 1 est une vue schématique en perspective d'un 15 dispositif de confinement actuellement envisagé pour le site du réacteur n 4 de la centrale de Tchernobyl; la figure 2 est une vue correspondante en perspective d'un dispositif de confinement selon l'invention et de l'ensemble des parties de la centrale de Tchernobyl conte- nant les réacteurs 3 et 4, permettant la mise en oeuvre du procédé de démantèlement selon l'invention; la figure 3 est une vue en plan indiquant comment peut être mis en place le dispositif de confinement selon l'invention, dans le cadre général du procédé de démantè- lement du réacteur n 4 de la centrale de Tchernobyl; la figure 4 est une vue schématique en élévation latérale et en coupe partielle d'une partie de l'installation représentée sur la figure 3; et les figures 5 à 9 illustrent des étapes successives de la construction du dispositif de confinement qui peut être utilisé pour le réacteur n 4 de la centrale nucléaire de Tchernobyl.  Other features and advantages of the invention will be better understood on reading the following description of embodiments, with reference to the accompanying drawings, in which: FIG. 1 is a diagrammatic perspective view of a containment device currently being considered for the Chernobyl No. 4 reactor site; FIG. 2 is a corresponding perspective view of a containment device according to the invention and of all the parts of the Chernobyl power plant containing the reactors 3 and 4, allowing the implementation of the dismantling process according to FIG. the invention; FIG. 3 is a plan view showing how the containment device according to the invention can be put into place, in the general context of the dismantling process of reactor No. 4 at the Chernobyl power plant; Figure 4 is a schematic side elevation and partial sectional view of a portion of the installation shown in Figure 3; and FIGS. 5 to 9 illustrate successive steps in the construction of the containment device that can be used for reactor No. 4 of the Chernobyl nuclear power plant.

La figure 1 est en vue schématique en perspective de la disposition actuellement préconisée officiellement pour le traitement du problème posé par le réacteur n 4 de la centrale nucléaire de Tchernobyl. Sur la figure 1, la flèche désigne de façon générale la structure hétéroclite (sarcophage) construite juste après l'explosion du réacteur 2863098 10 n 4 pour assurer une protection immédiate. Ce sarcophage est encore actuellement la seule barrière existant autour du réacteur n 4. Ce réacteur n 4 est adjacent à une structure intermédiaire 12 qui comporte une solide structure bâtie 14 qui porte une cheminée 16 d'évacuation destinée non seule-ment au réacteur n 4, mais aussi au réacteur n 3, qui ne figure pas sur la figure 1 qui reproduit un dessin officiel.  Figure 1 is a schematic perspective view of the provision currently officially recommended for the treatment of the problem posed by the reactor No. 4 of the Chernobyl nuclear power plant. In FIG. 1, the arrow generally designates the heteroclite structure (sarcophagus) constructed just after the explosion of the No. 4 reactor to provide immediate protection. This sarcophagus is still the only barrier existing around the reactor No. 4. This reactor No. 4 is adjacent to an intermediate structure 12 which comprises a solid built structure 14 which carries a discharge stack 16 intended not only to the reactor No. 4 , but also to reactor No. 3, which does not appear in FIG. 1, which reproduces an official drawing.

On note aussi sur la figure 1 la présence d'un long bâtiment 18 qui est placé le long des réacteurs n 3 et 4, mais aussi des réacteurs 1 et 2 et qui a donc une grande longueur. Ce bâtiment 18 n'est sérieusement contaminé qu'au droit du réacteur n 4.  Note also in Figure 1 the presence of a long building 18 which is placed along the reactors No. 3 and 4, but also the reactors 1 and 2 and which is therefore of great length. This building 18 is seriously contaminated only at the reactor n 4.

La solution officiellement préconisée comprend, pour le démantèlement de la partie accidentée, la construction d'un dispositif de confinement 20 sous forme d'une grande arche à double paroi, destinée à être construite à distance de la partie accidentée et à être déplacée pour venir couvrir le sarcophage. Cette arche a une très grande largeur et doit aussi avoir une grande longueur, car il est prévu qu'elle puisse couvrir non seulement le sarcophage 10 du réacteur n 4, mais aussi une installation 24 de démantèlement et un dispositif 26 de stockage de matières radio- actives. Ces deux installations 24, 26 sont destinées à être construites à l'intérieur de l'arche 20. Bien entendu, aux deux faces en demi-ellipse, l'arche doit être fermée, d'une part autour du sarcophage et d'autre part jusqu'au sol.  The officially recommended solution includes, for the dismantling of the damaged part, the construction of a containment device 20 in the form of a large double-walled arch, intended to be built at a distance from the damaged part and to be moved to come cover the sarcophagus. This arch has a very large width and must also have a great length, because it is expected that it can cover not only the sarcophagus 10 of the reactor No. 4, but also a dismantling installation 24 and a device 26 for storing radio materials - active. These two installations 24, 26 are intended to be built inside the arch 20. Of course, on both sides in half-ellipse, the arch must be closed, on the one hand around the sarcophagus and on the other share to the ground.

Il est prévu que l'arche 20 doit avoir une durée de vie de l'ordre d'un siècle, ses dimensions sont gigantesques puisqu'elle doit couvrir un volume considérable, et son coût est donc très élevé.  It is expected that the arch 20 must have a lifetime of the order of a century, its dimensions are gigantic because it must cover a considerable volume, and its cost is very high.

La figure 2 est une vue schématique en perspective illustrant la mise en oeuvre du procédé selon l'invention appliqué au démantèlement du réacteur n 4 de la centrale de Tchernobyl. Par rapport à la figure 1, on a ajouté les bâtiments constituant la structure du réacteur 3, comme indiqué par la référence 28. Il s'agit de bâtiments très vastes, dans lesquels le réacteur n 3 a fonctionné jusqu'en l'an 2000 et est actuellement en cours de déchargement.  FIG. 2 is a diagrammatic perspective view illustrating the implementation of the method according to the invention applied to the dismantling of reactor No. 4 of the Chernobyl power station. With respect to FIG. 1, the buildings constituting the structure of the reactor 3, as indicated by the reference 28, have been added. These are very large buildings in which the reactor 3 operated until the year 2000. and is currently unloading.

2863098 11 Cette structure 28 est pratiquement symétrique de celle qui contenait le réacteur n 4 avant son accident, par rapport à la structure centrale 14 qui contient les services partagés par les deux réacteurs. La structure 28 assure une très bonne protection contre la radioactivité et, actuellement, l'intérieur de cette structure constitue la partie la plus sûre contre la radioactivité de tout le voisinage de la partie accidentée.  2863098 11 This structure 28 is substantially symmetrical to that which contained the reactor n 4 before its accident, compared to the central structure 14 which contains the services shared by the two reactors. The structure 28 provides a very good protection against radioactivity and currently the interior of this structure is the safest part against the radioactivity of the whole neighborhood of the rugged part.

Selon l'invention, la structure 28 qui abritait le réacteur n 3 est réutilisée comme installation de démantèlement et de stockage des matières radioactives contenues dans le sarcophage 10. A cet effet, en plus des accès existants, des accès peuvent être créés dans la structure intermédiaire 14, afin que l'intérieur du sarcophage soit atteint. Ce procédé permet donc l'extraction des matières radioactives, et en particulier du combustible du réacteur n 4, par l'intermédiaire de la structure 14.  According to the invention, the structure 28 which housed the reactor No. 3 is reused as a dismantling and storage facility for the radioactive materials contained in the sarcophagus 10. For this purpose, in addition to the existing accesses, accesses can be created in the structure intermediate 14 so that the inside of the sarcophagus is reached. This process therefore allows the extraction of radioactive materials, and in particular fuel from reactor No. 4, via structure 14.

Une caractéristique avantageuse, dans ce procédé, est que la structure qui contenait le réacteur n 4 est symé- trique de la structure 28 contenant le réacteur n 3. De cette manière, une fois des trajets d'accès formés dans la structure intermédiaire 14, il est facile de se référer à la disposition de l'intérieur de la structure 28 pour connaître celle de l'intérieur du sarcophage.  An advantageous characteristic in this process is that the structure which contained the reactor No. 4 is symmetrical with the structure 28 containing the reactor No. 3. In this way, once access paths formed in the intermediate structure 14, it is easy to refer to the arrangement of the interior of the structure 28 to know that of the interior of the sarcophagus.

Bien entendu, le démantèlement doit commencer, pour des raisons de sécurité des populations, par la mise en place d'une structure de confinement, telle qu'indiquée par la référence 30, au-dessus du sarcophage. Ce dispositif de confinement 30 peut être construit à distance, comme décrit dans la suite, et déplacé le long d'un premier chemin de roulement 32, puis d'un second chemin de roulement 34 en direction perpendiculaire. En position intermédiaire, le dispositif de confinement 30 prend la position 36 à laquelle l'ouverture correspondant au sarcophage est dégagée.  Of course, the dismantling must begin, for reasons of public safety, by the establishment of a containment structure, as indicated by reference 30, above the sarcophagus. This containment device 30 can be remotely constructed, as described below, and moved along a first raceway 32, then a second raceway 34 in the perpendicular direction. In the intermediate position, the confinement device 30 takes the position 36 at which the opening corresponding to the sarcophagus is disengaged.

Pendant le démantèlement, une première opération comprend le montage de dispositifs d'extraction par pompage des poussières contenues dans l'atmosphère du sarcophage. Les poussières sont alors conditionnées sous forme de 2863098 12 déchets qui peuvent plus faciles à traiter. Ensuite, le démantèlement comprend l'évacuation des matières pulvérulentes, puis des matières plus grosses qui subissent par exemple un concassage et un broyage. Les matières sont triées, puis conditionnées avant d'être stockées. Ce stockage est un stockage intermédiaire et les déchets sont évacués. Toutes ces opérations d'extraction, de concassage et broyage, de tri et de conditionnement des déchets sont exécutés à l'intérieur de la structure 28.  During the dismantling, a first operation includes mounting extraction devices by pumping dust contained in the atmosphere of the sarcophagus. The dust is then packaged as 2863098 12 waste that can be easier to treat. Then, the dismantling comprises the evacuation of the pulverulent materials, then larger materials which undergo for example a crushing and grinding. The materials are sorted and packaged before being stored. This storage is an intermediate storage and the waste is evacuated. All these operations extraction, crushing and grinding, sorting and packaging of waste are performed inside the structure 28.

Une caractéristique essentielle du procédé selon l'invention est que le sarcophage est conservé tel quel, à l'intérieur du dispositif de confinement;il risque donc peu de s'effondrer et de poser des problèmes supplémentaires de contamination. Non seulement le sarcophage n'est pas détruit, mais encore il peut être couvert, depuis l'intérieur du dispositif de confinement 30, d'un revêtement étanche et léger destiné à constituer une barrière supplémentaire réduisant l'émission potentielle de poussières.  An essential feature of the method according to the invention is that the sarcophagus is kept as it is, inside the confinement device, so it is unlikely to collapse and pose additional problems of contamination. Not only is the sarcophagus not destroyed, but it can also be covered, from inside the containment device 30, with a tight and light coating intended to constitute an additional barrier reducing the potential emission of dust.

Le procédé de démantèlement peut comprendre ultérieu- rement le démantèlement des structures, une fois la radio-activité suffisamment réduite par l'évacuation des matériaux radioactifs.  The dismantling process may further comprise the dismantling of the structures, once the radioactivity is sufficiently reduced by the removal of the radioactive materials.

En outre, il est avantageux qu'un confinement sous-terrain soit aussi formé autour de l'installation, et même autour de l'ensemble de la centrale, pour la protection de la nappe phréatique. Des techniques de fabrication de parois moulées formant une enceinte jusqu'à la nappe phréatique sont bien connues dans la technique et on les décrit pas plus en détail.  In addition, it is advantageous that an underground containment is also formed around the installation, and even around the entire plant, for the protection of the water table. Mold wall forming techniques forming an enclosure up to the water table are well known in the art and are not described in more detail.

On considère maintenant, en référence aux figures 5 à 9, un procédé de construction d'un dispositif de confinement selon l'invention.  We now consider, with reference to Figures 5 to 9, a method of construction of a containment device according to the invention.

La construction débute à un emplacement situé à une distance importante de la partie accidentée, par exemple de l'ordre de 2 km. De cette manière, l'intensité du rayonnement est beaucoup plus réduite qu'à proximité de la partie accidentée. Par exemple, à 2 km, la radioactivité est 100 fois plus faible qu'à 200 m de l'installation accidentée.  The construction begins at a location located at a significant distance from the rugged part, for example of the order of 2 km. In this way, the intensity of the radiation is much smaller than near the rugged part. For example, at 2 km, the radioactivity is 100 times lower than 200 m from the accident site.

2863098 13 La structure 38 est un bâtiment mobile ayant une hauteur égale à environ cinq couches d'ossature, c'est-à-dire à celle de cinq modules utilisés pour la construction du dispositif de confinement. Ce bâtiment 38 a une forme de portique qui peut être fermé et dans lequel est construit un autre bâtiment 40 ayant lui aussi une forme de portique allongé ouvert d'un côté, mais qui peut être fermé de façon étanche par un dispositif amovible.  The structure 38 is a mobile building having a height equal to about five framework layers, that is to say that of five modules used for the construction of the confinement device. This building 38 has a form of gantry which can be closed and in which is built another building 40 having also an elongate gantry shape open on one side, but which can be sealed by a removable device.

A l'aide du premier bâtiment 38, le second bâtiment 40, dont la hauteur correspond à environ quatre modules, est construit sur une longueur correspondant à un peu plus de la largeur que doit avoir le dispositif de confinement terminé, comme représenté sur la figure 5.  Using the first building 38, the second building 40, the height of which corresponds to about four modules, is constructed over a length corresponding to a little more than the width that the completed confinement device must have, as shown in FIG. 5.

La figure 6 indique que, lorsque le second bâtiment mobile 40 a été réalisé, la construction du dispositif de confinement proprement dit commence. Cette construction est réalisée par déplacement progressif du bâtiment 40 sur des chemins de roulement 42. La structure construite 44 est progressivement réalisée et comporte la partie supérieure 46 du dispositif de confinement 30 et une assise comprenant des moyens de levage, tels que des vérins 50 (figure 8). L'assise comprend de préférence, en plus des vérins, des modules analogues à ceux qui sont utilisés pour le reste du dispositif de confinement.  Figure 6 indicates that when the second mobile building 40 has been completed, the construction of the containment device itself begins. This construction is carried out by progressive displacement of the building 40 on the tracks 42. The constructed structure 44 is progressively made and comprises the upper part 46 of the confinement device 30 and a base comprising lifting means, such as cylinders 50 (FIG. Figure 8). The seat preferably comprises, in addition to cylinders, modules similar to those used for the rest of the confinement device.

Lorsque la structure 44 a été construite, le bâtiment 40 est éloigné et n'est plus utilisé. Des galeries 50 de protection formant des abris autour du bas de la structure sont construites. La structure est alors réalisée par couches, au-dessus de l'assise qui a l'épaisseur d'un module et qui contient les vérins. La galerie 50 d'abri a donc une hauteur un peu supérieure à la hauteur de deux modules. La construction s'effectue par couches, avec préparation de l'ouverture 48 qui doit se trouver du côté du sarcophage.  When the structure 44 has been constructed, the building 40 is remote and is no longer used. Protection galleries 50 forming shelters around the bottom of the structure are constructed. The structure is then made in layers, above the seat which has the thickness of a module and which contains the cylinders. The shelter gallery 50 therefore has a height slightly greater than the height of two modules. The construction is done in layers, with preparation of the opening 48 which must be on the side of the sarcophagus.

Les vérins 50, pendant l'opération de construction, sont destinés à soulever la partie supérieure du dispositif de confinement pour former un espace d'une hauteur au moins égale à celle d'un module afin qu'une couche supplémentaire 2863098 14 puisse être construite par insertion de modules. La construction progresse donc depuis le bas.  The cylinders 50, during the construction operation, are intended to lift the upper part of the confinement device to form a space of a height at least equal to that of a module so that an additional layer 2863098 14 can be constructed by inserting modules. Construction is progressing from the bottom.

La totalité des travaux de construction est réalisée à l'extérieur au niveau des abris 50, et à l'intérieur. Les 5 intervenants sont donc toujours abrités.  All construction work is done outside at shelters 50, and inside. The 5 speakers are therefore always sheltered.

La construction comprend la disposition d'un bardage à l'intérieur comme à l'extérieur, et la disposition de toiles à l'intérieur et à l'extérieur, sous forme de deux revêtements. De cette manière, l'ensemble de la structure construite est toujours relativement étanche. Un dispositif de mise en surpression est raccordé et maintient le dispositif de confinementen construction à une légère surpression de manière que, en cas d'incident provoquant le dégagement de poussières et de gaz radioactifs, le personnel travaillant dans l'enceinte comme dans les galeries ne puisse pas être rapidement contaminé.  The construction includes the layout of a cladding inside and outside, and the arrangement of canvases inside and outside, in the form of two coatings. In this way, the entire constructed structure is still relatively watertight. An overpressure device is connected and maintains the containment device under construction at a slight overpressure so that, in the event of an incident causing the release of dust and radioactive gases, the personnel working in the enclosure as in the galleries do not can not be quickly contaminated.

Selon une caractéristique essentielle de l'invention, le personnel travaille toujours à proximité du niveau du sol. Des abris sont présents au sol à tout le pourtour inté- rieur de la structure, si bien que, dès qu'une alerte est donnée, le personnel peut être très rapidement mis à l'abri.  According to an essential characteristic of the invention, the personnel always work near the ground level. Shelters are present on the ground around the interior of the structure, so that as soon as an alert is given, the staff can be quickly put under cover.

Lorsque le dispositif de confinement 30 a été réalisé, il doit être déplacé. A cet effet, il suffit de construire des chemins de roulement 32 en béton de l'emplacement de construction jusqu'à proximité du sarcophage, comme indiqué sur la figure 3. Sur celle-ci, on voit que le chemin de roulement 32 amène le dispositif de confinement jusqu'à proximité du sarcophage, c'est-à-dire à la position 36 indiquée sur la figure 2. A ce moment, l'ouverture qui était restée fermée depuis le lieu de construction est dégagée, et le dispositif de confinement est amené sur le sarcophage. L'étanchéité entre l'ouverture et le sarcophage est obtenue par des dispositifs d'étanchéité à guillotine tels que décrits par exemple dans le brevet français n 2 746 130.  When the containment device 30 has been made, it must be moved. For this purpose, it is sufficient to construct concrete raceways 32 from the construction site to the vicinity of the sarcophagus, as shown in FIG. 3. On the latter, it can be seen that the raceway 32 brings the confinement device near the sarcophagus, that is to say at the position 36 indicated in FIG. 2. At this moment, the opening which had remained closed from the place of construction is disengaged, and the confinement is brought to the sarcophagus. The seal between the opening and the sarcophagus is obtained by guillotine sealing devices as described for example in French Patent No. 2,746,130.

Le déplacement du dispositif de confinement sur les chemins de roulement peut s'effectuer de diverses manières. Un procédé avantageux, qui se rapproche de la technique utilisée pour le déplacement des arches de pont, comprend 2863098 15 l'utilisation de dispositifs fixes 54 disposés soit sur un chemin de roulement 32, 34, soit sur des supports résistants 52 et ayant des rouleaux 56 montés sur un balancier et qui dépassent à la partie supérieure. Ces rouleaux coopèrent de préférence avec un rail 58 formé à la partie inférieure du dispositif de confinement, c'est-à-dire au-dessous de la première couche. Ce rail est incorporé à la construction dès la construction de l'assise qui comporte les vérins. Un tel déplacement permet de tenir compte des dénivelés éventuels du sol par disposition de cales sous les supports 54 de rouleaux.  The displacement of the confinement device on the raceways can be effected in various ways. An advantageous method, similar to the technique used for moving the bridge arches, includes the use of stationary devices 54 arranged either on a raceway 32, 34, or on resilient supports 52 and having rollers. 56 mounted on a beam and protruding at the top. These rollers preferably cooperate with a rail 58 formed in the lower part of the confinement device, that is to say below the first layer. This rail is incorporated in the construction from the construction of the seat that includes the cylinders. Such a displacement makes it possible to take account of the possible unevenness of the ground by arrangement of shims under the supports 54 of rollers.

Un premier avantage de l'invention est que l'ensemble du démantèlement peut être exécuté très prochainement et en un temps réduit grâce à la réutilisation de la structure du réacteur n 3.  A first advantage of the invention is that the entire dismantling can be performed very soon and in a reduced time through the reuse of the structure of the reactor No. 3.

Un second avantage qui découle du premier est la réduction considérable des coûts puisqu'il n'est pas nécessaire de construire une structure spécifique pour le démantèlement. Cette réduction des coûts est accrue parce que le dispositif de confinement peut être plus petit et donc moins coûteux.  A second advantage that stems from the first is the considerable cost reduction since it is not necessary to build a specific structure for dismantling. This cost reduction is increased because the containment device can be smaller and therefore less expensive.

Un troisième avantage, bien plus important que les précédents, est l'augmentation de la sécurité aussi bien des populations (confinement et démantèlement réalisés plus rapidement) que des intervenants (réduction de l'exposition au rayonnement, proximité constante d'abris). Cette augmentation de sécurité permet à son tour, par un effet de synergie, une réduction supplémentaire du temps nécessaire à l'opération (réduction des fréquences de rotation des intervenants, accroissement de leur mobilité) et donc des Coûts.  A third advantage, much more important than the previous ones, is the increase in the safety of both populations (containment and dismantling achieved more quickly) than those involved (reduction of exposure to radiation, constant proximity to shelters). This increase in security in turn allows, by a synergy effect, a further reduction in the time required for the operation (reduction of rotation frequencies of the parties involved, increased mobility) and therefore Costs.

Bien entendu, diverses modifications peuvent être apportées par l'homme de l'art aux procédés et dispositifs qui viennent d'être décrits uniquement à titre d'exemple non limitatif sans sortir du cadre de l'invention.  Of course, various modifications can be made by those skilled in the art to the methods and devices which have just been described by way of non-limiting example without departing from the scope of the invention.

Claims (10)

REVENDICATIONS 1. Procédé de démantèlement d'une partie d'installation industrielle accidentée (10) dangereuse pour l'homme, qui jouxte une partie d'installation industrielle non accidentée (28) qui a des caractéristiques de protection contre des matières dangereuses, caractérisé en ce qu'il comprend: le confinement de la partie accidentée (10) par un dispositif de confinement (30) qui la recouvre de manière pratiquement étanche, et la décontamination de la partie accidentée (10) par accès à celle-ci depuis la partie non accidentée (28), avec utilisation des caractéristiques de protection de la partie non accidentée (28) pour le traitement des matières dangereuses retirées de la partie accidentée (10).  A method of dismantling a portion of a damaged industrial plant (10) dangerous to man, adjacent to a non-uneven industrial plant part (28) which has protective features against hazardous materials, characterized in that it includes: the containment of the damaged part (10) by a containment device (30) which covers it in a substantially watertight manner, and the decontamination of the damaged part (10) by access to it from the non damaged (28), with use of the protection characteristics of the non-damaged part (28) for the treatment of dangerous substances removed from the damaged part (10). 2. Procédé selon la revendication 1, caractérisé en ce que le dispositif de confinement (30) est pratiquement étanche, et l'opération de décontamination est exécutée alors que le dispositif de confinement {30) est maintenu en dépression.  2. Method according to claim 1, characterized in that the confinement device (30) is substantially sealed, and the decontamination operation is performed while the confinement device (30) is kept in depression. 3. Procédé selon l'une des revendications 1 et 2, caractérisé en ce que l'accès à la partie accidentée (10) depuis la partie non accidentée (28) est réalisé par perçage d'une structure (14) séparant la partie accidentée de la partie non accidentée.  3. Method according to one of claims 1 and 2, characterized in that the access to the rugged part (10) from the non-rough part (28) is achieved by drilling a structure (14) separating the damaged part of the non-rugged part. 4. Procédé selon l'une quelconque des revendications 1 à 3, caractérisé en ce que l'étape de confinement comprend la construction d'un dispositif de confinement (30) à distance de la partie accidentée (10), et le déplacement du dispositif de confinement (30) afin qu'il vienne couvrir la partie accidentée (10).  4. Method according to any one of claims 1 to 3, characterized in that the confinement step comprises the construction of a confinement device (30) remote from the damaged portion (10), and the movement of the device containment (30) to cover the damaged portion (10). 5. Dispositif de confinement d'une installation industrielle accidentée contenant des résidus dangereux pour l'homme, destinée à être déplacée entre un lieu de construction et un lieu d'utilisation au-dessus de l'instal- lation industrielle accidentée (10), caractérisé en ce qu'il comporte une ossature et au moins un revêtement, et en ce que l'ossature est constituée de modules métalliques disposés en couches horizontales.  5. Containment device of a damaged industrial installation containing residues dangerous to humans, intended to be moved between a place of construction and a place of use above the industrial accident site (10), characterized in that it comprises a frame and at least one coating, and in that the frame consists of metal modules arranged in horizontal layers. 2863098 17  2863098 17 6. Dispositif selon la revendication 5, caractérisé en ce qu'il comporte un dispositif destiné à mettre l'intérieur du dispositif de confinement (30) en dépression lors de l'utilisation.6. Device according to claim 5, characterized in that it comprises a device for putting the inside of the confinement device (30) in depression during use. 7. Dispositif selon l'une des revendications 5 et 6, caractérisé en ce qu'il comporte des moyens de levage (50) intégrés à une couche d'assise de l'ossature et travaillant en direction verticale afin qu'ils permettent le déplacement en hauteur du dispositif de confinement (30) de la hauteur d'au moins une couche.  7. Device according to one of claims 5 and 6, characterized in that it comprises lifting means (50) integrated with a seat layer of the frame and working in the vertical direction so that they allow the displacement in height of the confinement device (30) the height of at least one layer. 8. Dispositif selon l'une quelconque des revendications 5 à 7, caractérisé en ce que le revêtement comporte au moins deux couches de revêtement, l'une à l'intérieur et l'autre à l'extérieur de l'enceinte.  8. Device according to any one of claims 5 to 7, characterized in that the coating comprises at least two coating layers, one inside and one outside the enclosure. 9. Procédé de fabrication d'un dispositif de confine-ment d'une installation industrielle accidentée (10), le dispositif de confinement (30) étant formé de couches horizontales, caractérisé en ce qu'il comprend la construction d'une assise munie de moyens de levage (50) et d'une partie supérieure (44) du dispositif de confinement (30), le levage de la partie supérieure (44) du dispositif de confinement avec les moyens de levage (50) d'une hauteur pratiquement égale à la hauteur d'une couche au moins pour la formation d'un espace au-dessus de l'assise, la construction d'une couche de l'ossature dans cet espace, avec solidarisation de cette couche et de la structure qui la surmonte, puis la répétition des étapes de levage et de 30 construction d'une couche pour la construction d'au moins une couche supplémentaire, jusqu'à la construction de toutes les couches de l'ossature.  9. A method of manufacturing a device for confinement-ment of a crashed industrial facility (10), the containment device (30) being formed of horizontal layers, characterized in that it comprises the construction of a seat provided lifting means (50) and an upper portion (44) of the containment device (30), lifting the upper portion (44) of the containment device with the lifting means (50) by a height substantially equal to the height of at least one layer for the formation of a space above the seat, the construction of a layer of the framework in this space, with the attachment of this layer and the structure which forms it overcomes and then repeats the steps of lifting and building a layer for the construction of at least one additional layer, until the construction of all layers of the framework. 10. Procédé selon la revendication 9, caractérisé en ce qu'il comprend, au cours de toute la construction, l'application aux modules de revêtements assurant une bonne étanchéité à l'ensemble du dispositif (30) en cours de construction, et la mise en légère surpression de l'intérieur du dispositif (30) en cours de construction.  10. The method of claim 9, characterized in that it comprises, throughout the construction, the application to the coating modules ensuring a good seal to the entire device (30) under construction, and the slight overpressure of the interior of the device (30) under construction.
FR0314067A 2003-12-01 2003-12-01 DISMANTLING METHOD, CONTAINMENT DEVICE AND MANUFACTURING METHOD FOR ACCIDENTAL INDUSTRIAL INSTALLATION Expired - Fee Related FR2863098B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
FR0314067A FR2863098B1 (en) 2003-12-01 2003-12-01 DISMANTLING METHOD, CONTAINMENT DEVICE AND MANUFACTURING METHOD FOR ACCIDENTAL INDUSTRIAL INSTALLATION
UA20041008364A UA83462C2 (en) 2003-12-01 2004-10-15 Method for dismantling damaged industrial installation, shelter object of damaged industrial installation and method for its erection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR0314067A FR2863098B1 (en) 2003-12-01 2003-12-01 DISMANTLING METHOD, CONTAINMENT DEVICE AND MANUFACTURING METHOD FOR ACCIDENTAL INDUSTRIAL INSTALLATION

Publications (2)

Publication Number Publication Date
FR2863098A1 true FR2863098A1 (en) 2005-06-03
FR2863098B1 FR2863098B1 (en) 2006-01-13

Family

ID=34566269

Family Applications (1)

Application Number Title Priority Date Filing Date
FR0314067A Expired - Fee Related FR2863098B1 (en) 2003-12-01 2003-12-01 DISMANTLING METHOD, CONTAINMENT DEVICE AND MANUFACTURING METHOD FOR ACCIDENTAL INDUSTRIAL INSTALLATION

Country Status (2)

Country Link
FR (1) FR2863098B1 (en)
UA (1) UA83462C2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431197A (en) * 2021-06-24 2021-09-24 山西建投五岳建设工程有限公司 Movable combined type canopy and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2334179A1 (en) * 1975-12-03 1977-07-01 Steinmueller Gmbh L & C EVACUATION PROCESS FOR ACTIVE ELEMENTS, ESPECIALLY FOR NUCLEAR POWER PLANTS
DE2638174A1 (en) * 1976-08-25 1978-03-02 Steinmueller Gmbh L & C Dismantling large radioactive power station plant - using mobile equipment in containers assisted by permanent power station ancillary equipment
US5201152A (en) * 1992-07-31 1993-04-13 The Babcock & Wilcox Company Containment device for contaminated building demolition
DE4308797A1 (en) * 1993-03-19 1994-09-22 Heid Gerhard Floating body of variable height
FR2746130A1 (en) * 1996-03-18 1997-09-19 Usinor Sacilor Rapid assembly containment for high risk industrial plant
RU2180764C2 (en) * 1996-09-18 2002-03-20 Владимир Федотович Русинов Refueling machine for nuclear power station reactors
JP2003185779A (en) * 2001-12-20 2003-07-03 Taisei Corp Method of constructing energy facility

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2334179A1 (en) * 1975-12-03 1977-07-01 Steinmueller Gmbh L & C EVACUATION PROCESS FOR ACTIVE ELEMENTS, ESPECIALLY FOR NUCLEAR POWER PLANTS
DE2638174A1 (en) * 1976-08-25 1978-03-02 Steinmueller Gmbh L & C Dismantling large radioactive power station plant - using mobile equipment in containers assisted by permanent power station ancillary equipment
US5201152A (en) * 1992-07-31 1993-04-13 The Babcock & Wilcox Company Containment device for contaminated building demolition
DE4308797A1 (en) * 1993-03-19 1994-09-22 Heid Gerhard Floating body of variable height
FR2746130A1 (en) * 1996-03-18 1997-09-19 Usinor Sacilor Rapid assembly containment for high risk industrial plant
RU2180764C2 (en) * 1996-09-18 2002-03-20 Владимир Федотович Русинов Refueling machine for nuclear power station reactors
JP2003185779A (en) * 2001-12-20 2003-07-03 Taisei Corp Method of constructing energy facility

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
DATABASE WPI Section Ch Week 200235, Derwent World Patents Index; Class K05, AN 2002-314502, XP002282911 *
PATENT ABSTRACTS OF JAPAN vol. 2003, no. 11 5 November 2003 (2003-11-05) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431197A (en) * 2021-06-24 2021-09-24 山西建投五岳建设工程有限公司 Movable combined type canopy and construction method thereof

Also Published As

Publication number Publication date
UA83462C2 (en) 2008-07-25
FR2863098B1 (en) 2006-01-13

Similar Documents

Publication Publication Date Title
EP0466533B1 (en) Process and device for dismantling an irradiated component of a nuclear reactor by cutting up its shell
FR2522350A1 (en) INSTALLATION OF PRESSURIZATION AND FILTRATION, IN PARTICULAR FOR PROTECTING PERSONS FROM THE EFFECTS OF NUCLEAR, BIOLOGICAL OR CHEMICAL WEAPONS
WO2006131661A2 (en) Collapsible building
EP0001367B1 (en) Antiseismic buildings with basements forming an atombomb-proofed shelter
EP2992974B1 (en) Final disposal plant
FR2863098A1 (en) Dismantling of damaged industrial plant, such as nuclear facility, comprises confining and sealing off damaged section and decontaminating via access from undamaged section
FR3075452A1 (en) AUTOMATED INSPECTION ROBOT FOR RADIOACTIVE WASTE STORAGE GALLERIES
EP0212028A1 (en) Transfer method for an object without interruption of confinement
FR2547101A1 (en) DISENGAGING MACHINE OF NUCLEAR REACTORS DISENGAGED
FR3001829A1 (en) Method for storing radiferous waste in geological layer to extract e.g. uranium, involves gradually saturating water to limit water movement to maintain waste in anoxic condition to avoid oxidation of waste and migration of radio elements
FR3007883A1 (en) SYSTEM AND METHOD FOR HANDLING AND CUTTING BOX CONTAINING RADIOACTIVE PRODUCTS
EP0048671B1 (en) Energy production installation comprising several fast neutron nuclear reactors and a fuel element exchange system
FR2972840A1 (en) NUCLEAR PLANT
FR2561692A1 (en) MODULAR PANEL AND DISMANTLING WORKSHOP CONSISTING OF ASSEMBLY OF THESE PANELS
EP0463948B1 (en) Process for dismantling an underground installation with risk of contamination and intervention box
EP2815036A1 (en) Mobile sealed building consisting of a plurality of sections
KR102510544B1 (en) Method for inserting large disposal container and closing temporary opening in radioactive waste surface disposal facility using a construction lift
FR2806828A1 (en) Underwater closing procedure for sleeve containing irradiated fuel uses bell containing cap fixed in place in sleeve end by TIG welder
FR2988899A1 (en) Method for permanently closing container used to store radioactive wastes from nuclear facility, involves filling space between set of radioactive wastes and lid with blocking material through injection opening provided in lid
EP1466673B1 (en) Method for decontaminating and demolishing cowpers
FR2949741A1 (en) Radioactive nuclear waste packets storing and withdrawing method for e.g. factory, involves using transfer carriage to lift stacks of packets for transporting stacks of packets to final storage place
EP1123754A1 (en) Method for decontaminating cowpers
FR3046287A1 (en) CONFINING STORAGE SYSTEM WITH SCREWS OF RADIOACTIVE GAS, SUCH AS TRITIUM
FR2502380A1 (en) Transferring irradiated fuel elements between basins - using evacuable bell which is filled with water when contg. fuel elements
FR2630479A1 (en) Supporting structure made of sections which have dry joints or are flexible, connected via rollers to tensioning cables

Legal Events

Date Code Title Description
ST Notification of lapse

Effective date: 20140829