digging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
FR8502090A
Other languages
French (fr)
Other versions
FR2560635B2 (en
Inventor
Klemens Finsterwalder
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Walter Bau AG
Original Assignee
Dyckerhoff and Widmann AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from DE19833332242 external-priority patent/DE3332242A1/en
Application filed by Dyckerhoff and Widmann AG filed Critical Dyckerhoff and Widmann AG
Publication of FR2560635A2 publication Critical patent/FR2560635A2/en
Application granted granted Critical
Publication of FR2560635B2 publication Critical patent/FR2560635B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0635Tail sealing means, e.g. used as end shuttering
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L9/00Rigid pipes
    • F16L9/22Pipes composed of a plurality of segments

Abstract

The underground tunnel is for road traffic etc. and is formed using a pasty material to constitute an intermediate layer between the rock and the lining. This layer supports the thrust from the ground and is placed in position during excavation. The intermediate layer is formed in advance of the lining and in the space between the rock and intermediate formwork on the onside, and covering at least the section which is to receive the layer. The lining is formed in-situ by concreting between this intermediate formwork, which is moved as concreting progresses, and internal formwork.

Description

PROCEDE POUR REALISER UNE CAVITE SOUTERRAINE DE FORME TEtBU-
LAIRE, PAR EXEMPLE UN TUNNEL DE CIRCULATION, ET DISPOSITIF
POUR LA MISE EN OEUVRE DE CE PROCEDE.
PROCESS FOR MAKING A SUBTERRANEAN CAVITY OF TEtBU- FORM
MILK, FOR EXAMPLE A TRAFFIC TUNNEL, AND DEVICE
FOR THE IMPLEMENTATION OF THIS PROCESS.

L'invention concerne un procédé pour réaliser une cavité souterraine de forme tubulaire, par exemple un tunnel de circulation, dans lequel, au cours du creusement, une matière pâteuse est introduite en vue de la formation d'une couche intermédiaire entre la roche et le revêtement supportant la poussée de la roche, ainsi qu'un dispositif pour la mise en oeuvre de ce procédé.The invention relates to a method for producing an underground cavity of tubular shape, for example a circulation tunnel, into which, during digging, a pasty material is introduced with a view to the formation of an intermediate layer between the rock and the coating supporting the thrust of the rock, as well as a device for implementing this method.

L'objet du brevet principal n0 84 13645 est une cavité souterraine de forme tubulaire, telle qu'un tunnel de circulation, une conduite tubulaire ou analogue, dans laquelle est disposée entre la surface extérieure du revêtement qui supporte la poussée de la roche et la roche une couche en une matière qui limite, par déformation plastique, la transmission mutuelle de forces lorsqu'il y a des déplacements relatifs entre la roche et le revêtement. Cette couche est avantageusement constituée d'un mélange pâteux formé par un minéral argileux, par exemple de la bentonite et de l'eau, qui est mis en place lors de la progression de la réalisation du revêtement. The subject of main patent No. 84 13645 is an underground cavity of tubular shape, such as a circulation tunnel, a tubular pipe or the like, in which is disposed between the outer surface of the covering which supports the thrust of the rock and the rock a layer of a material which limits, by plastic deformation, the mutual transmission of forces when there are relative displacements between the rock and the coating. This layer advantageously consists of a pasty mixture formed by a clay mineral, for example bentonite and water, which is put in place during the progress of the production of the coating.

Du fait de l'imperméabilité à l'eau de cette couche, on obtient un effet d'étanchéité favorable qui arpour conséquence, pour des conditions normales de la roche, de permettre d'imposer des conditions nettement moins sévères à la limite de la largeur des fissures d'un revêtement de tunnel en béton armé. La conséquence est que même pour une épaisseur relativement faible mais constante de cette couche, il est possible d'économiser partiellement ou même complètement l'armature. Due to the waterproofing of this layer, a favorable sealing effect is obtained which, as a consequence, for normal conditions of the rock, makes it possible to impose much less severe conditions at the limit of the width. cracks in a reinforced concrete tunnel lining. The consequence is that even for a relatively small but constant thickness of this layer, it is possible to partially or even completely save the reinforcement.

L'utilisation de béton non armé pour constituer le revêtement d'un tunnel suppose que la résultante des efforts de cisaillement dans tous les cas de charge s'applique à
L'intérieur de la région centrale de la section. L'importance des moments de' flexion est influencée par le facteur de poussée des terres et par le ballast. Les moments de flexion sont donc d'autant plus faibles que le facteur de poussée des terres se rapproche de 1. La couche, constituée en un minéral argileux et qui est prévue selon le brevet principal entre le revêtement et la roche, présente des propriétés excellentes de glissement et se comporte comme un fluide quand la déformation est empêchée, ce qui fait que le facteur de poussée des terres devient 1. Ceci constitue une autre condition favorable permettant d'utiliser un revêtement de tunnel non armé.
The use of unreinforced concrete to constitute the lining of a tunnel supposes that the result of the shear forces in all load cases applies to
The interior of the central section. The importance of the bending moments is influenced by the earth push factor and by the ballast. The bending moments are therefore lower the closer the earth's push factor is to 1. The layer, made up of a clay mineral and which is provided according to the main patent between the coating and the rock, has excellent properties slip and behaves like a fluid when deformation is prevented, so that the earth push factor becomes 1. This is another favorable condition for using an unarmoured tunnel lining.

L'invention a pour but de proposer une possibilité économique de réalisation d'un revêtement de tunnel non armé comprenant une couche intermédiaire conformément au brevet principal. The object of the invention is to propose an economic possibility of producing an unarmoured tunnel lining comprising an intermediate layer in accordance with the main patent.

Selon l'invention, ce but est atteint du fait que la couche intermédiaire est réalisée en avance par rapport au revêtement dans l'espace intermédiaire compris entre la roche et un coffrage intermédiaire servant de limite interne et recouvrant au moins la section destinée à cette couche préalable, et du fait que le revêtement est réalisé sur place par apport de béton dans la cavité située entre le coffrage intermédiaire qui est entraîné en même temps que progresse le bétonnage et un coffrage interne. According to the invention, this object is achieved because the intermediate layer is produced in advance with respect to the coating in the intermediate space between the rock and an intermediate formwork serving as internal limit and covering at least the section intended for this layer. prior, and the fact that the coating is carried out on site by adding concrete into the cavity located between the intermediate formwork which is driven at the same time as the concreting and an internal formwork progresses.

La couche intermédiaire et le revêtement peuvent être réalisés au cours d'étapes de travail séparées et successives. The intermediate layer and the coating can be produced during separate and successive working steps.

La couche intermédiaire est de préférence réalisée de façon continue en même temps que le creusement.The intermediate layer is preferably carried out continuously at the same time as the digging.

Le concept de l'invention consiste dans le fait de coupler la mise en place de la couche intermédiaire en une ma trière pâteuse à la mise en place du béton du revêtement de manière que la couche intermédiaire soit réalisée avant le revêtement et de prévoir un coffrage entraîné en même temps que progresse le bétonnage pour séparer la couche intermédiaire du,revêtement La mise en place aussi bien de la couche lntermedlaire que du revêtement se fait donc directement à la suite de l'avance du bouclier de creusement, le béton frais du revêtement parvenant le long d'une ligne limite en contact direct avec le matériau de la couche intermédiaire à mesure qu'avance le coffrage intermédiaire. The concept of the invention consists in coupling the installation of the intermediate layer in a pasty material with the installation of the concrete of the covering so that the intermediate layer is produced before the covering and of providing a formwork entrained at the same time as the concreting progresses to separate the intermediate layer from the coating The installation of both the intermediate layer and the coating is therefore done directly following the advance of the digging shield, the fresh concrete of the coating reaching along a boundary line in direct contact with the material of the intermediate layer as the intermediate formwork advances.

L'invention concerne également un dispositif pour la mise en oeuvre de ce procédé. Dans un bouclier de creusement équipé de vérins de creusement et se prolongeant sur le côté qui est à l'opposé du front de taille en une queue ou arrièrebec de bouclier, est moulé,sur le côté intérieur de l'arrièrebec du bouclier, un coffrage frontal de forme annulaire et destiné à la couche intermédiaire, comprenant des ouvertures d'introduction sous pression de la matière pâteuse, le coffrage intermédiaire limitant la couche intermédiaire étant constitué sous forme d'une enveloppe cylindrique, coopérant avec le côté intérieur du coffrage frontal de la couche intermédiaire et comprenant, sur son coté intérieur, un coffrage frontal de forme annulaire destiné au revêtement et qui, pour sa part, est rendu étanche par rapport au coffrage intermédiaire du revêtement. The invention also relates to a device for implementing this method. In a digging shield equipped with digging jacks and extending on the side which is opposite the cutting face in a tail or rear of shield, is molded, on the inside side of the rear of the shield, a formwork frontal of annular shape and intended for the intermediate layer, comprising openings for the introduction under pressure of the pasty material, the intermediate formwork limiting the intermediate layer being constituted in the form of a cylindrical envelope, cooperating with the inner side of the front formwork of the intermediate layer and comprising, on its inner side, an annular formwork intended for the covering and which, for its part, is made watertight relative to the intermediate formwork of the covering.

Le coffrage intermédiaire peut être déplacé par rapport à l'arrière-bec du bouclier et guidé de façon étanche contre le côté intérieur du coffrage frontal de la couche interme- diaire. The intermediate formwork can be moved with respect to the rear beak of the shield and guided in leaktight manner against the inside of the front formwork of the intermediate layer.

Le coffrage frontal de la couche intermédiaire est avantageusement décalé par rapport à l'extrémité de l'arrière- bec du bouclier et le coffrage frontal du revêtement est décalé par rapport à l'extrémité du coffrage intermédiaire. The front formwork of the intermediate layer is advantageously offset with respect to the end of the shield rear spout and the front formwork of the covering is offset with respect to the end of the intermediate formwork.

L'extrémité du coffrage intermédiaire qui fait saillie au-delà du coffrage frontal peut être constitué en forme de coin allant en diminuant en direction de son extrémité; il peut comprendre des fentes orientées en direction longitudinale et/ou être constitué en une matière flexible telle que du caoutchouc, de la matière synthétique ou analogues. The end of the intermediate formwork which projects beyond the front formwork can be made in the form of a wedge, tapering towards its end; it may include slots oriented in the longitudinal direction and / or be made of a flexible material such as rubber, synthetic material or the like.

Le coffrage frontal du revêtement est avantageusement muni d'ouvertures d'introduction sous pression. The front formwork of the covering is advantageously provided with pressurized introduction openings.

Le coffrage intermédiaire peut être soutenu contre le bouclier au moyen d'unités à cylindre et piston et être guidé par glissement contre la surface extérieure du coffrage interne au moyen d'éléments d'écartement. The intermediate formwork can be supported against the shield by means of cylinder and piston units and can be guided by sliding against the external surface of the internal formwork by means of spacers.

Un mode d'exécution de ce dispositif est décrit ciaprès en référence au dessin schématique annexé dans lequel
Figure 1 est une vue en coupe longitudinale de ce dispositif;
Figure 2 est une vue d'un détail de figure 1, à échelle agrandie;
Figure 3 est une vue similaire à celle de la figure 2 mais dans une autre position de fonctionnement;
Figure 4 est une vue en coupe transversale selon la ligne IV-IV de la figure 1, et
Figure 5 est une vue en coupe transversale selon la ligne V-V de la figure 1.
An embodiment of this device is described below with reference to the attached schematic drawing in which
Figure 1 is a longitudinal sectional view of this device;
Figure 2 is a view of a detail of Figure 1, on an enlarged scale;
Figure 3 is a view similar to that of Figure 2 but in another operating position;
Figure 4 is a cross-sectional view along line IV-IV of Figure 1, and
Figure 5 is a cross-sectional view along line VV of Figure 1.

Sur le dessin, l'invention est représentée au moyen d'un dispositif de creusement d'un tunnel à l'aide d'un bouclier. Comme montré à la figure 1, ce dispositif comprend un bouclier de creusement (1) sur le côté frontal duquel sont montés les outils de creusement (2) destinés à l'abattage de la roche ou du terrain. Les matériaux extraits sont transportés, d'une façon connue en soi, à partir d'une chambre d'abat targe (3) éventuellement remplie d'eau ou d'un fluide thixotrope. In the drawing, the invention is represented by means of a device for digging a tunnel using a shield. As shown in Figure 1, this device comprises a digging shield (1) on the front side of which are mounted the digging tools (2) intended for the felling of rock or ground. The extracted materials are transported, in a manner known per se, from a targe abatement chamber (3) possibly filled with water or a thixotropic fluid.

Le bouclier de creusement (1) s'appuie pour avancer au moyen de vérins de creusement (4) contre le coffrage interne (5) du revêtement (6) du tunnel. Le coffrage interne (5) est consti; tué de sections individuelles d'anneaux tubulaires ou cuvelages, qui sont déplacées en fonction de la progressi'on. On utilise alors un élément télescopique (31) qui ne fait pas non plus l'objet de l'invention. The digging shield (1) is pressed to advance by means of digging cylinders (4) against the internal formwork (5) of the lining (6) of the tunnel. The internal formwork (5) is built; killed individual sections of tubular rings or casings, which are moved depending on the progressi'on. A telescopic element (31) is then used which is not the subject of the invention either.

La partie arrière du bouclier de creusement (1) est indiquée par l'arrière-bec (7) du bouclier. Sur le côté intérieur de l'arrière-bec (7) est fixé, à une certaine distance de son extrémité (8), un coffrage frontal de forme annulaire (9) destiné au mélange pâteux d'un minéral.argileux, qui est amené pour former une couche intermédiaire (10) dans l'espace intermédiaire compris entre la roche et le coffrage interne (5). Le coffrage frontal (9) comporte, à cet effet, des ouvertures d'introduction sous pression (12), qui sont raccordées à des conduites tubulaires (13). The rear part of the digging shield (1) is indicated by the rear spout (7) of the shield. On the inner side of the rear spout (7) is fixed, at a certain distance from its end (8), a frontal formwork of annular shape (9) intended for the pasty mixture of a clay mineral, which is brought to form an intermediate layer (10) in the intermediate space between the rock and the internal formwork (5). The front formwork (9) has, for this purpose, pressurized introduction openings (12), which are connected to tubular conduits (13).

A l'intérieur de l'arrière-bec (7) du bouclier se trouve le coffrage interne (14), sous forme d'une enveloppe cylindrique, qui peut être déplacée en direction axiale au moyen de vérins (15) montés sur le bouclier de creusement (I), en s'appuyant contre le coffrage frontal de forme annulaire (9) (figure 2).Le coffrage frontal (9) est de forme courbe sur sa surface périphérique intérieure (16) en vue d'obtenir un meilleur guidage du coffrage intermédiaire#(l4) et d'autoriser de petits mouvements de basculement dans les courbes
Sur le côté intérieur du coffrage intermédiaire (14) se trouve le coffrage frontal de forme annulaire ( destiné au béton du revêtement (6) de telle sorte que le coffrage intermédiaire dépasse du coffrage (17) dans une zone (la). Dans le coffrage frontal (17) sont prévues des ouvertures,d'intro- duction sous pression (19) pour le béton du revêtement (6), qui est amené par des conduites (20).Comme il ressort surtout de la figure 2, le coffrage intermédiaire (14) est maintenu dans la région du coffrage frontal (17) par des, entre- toises (21), qui peuvent se déplacer en glissant sur le coffrage interne. Le joint annulaire situé entre le coffrage frontal (17) et le coffrage interne (5) est rendu étanche par une garniture (22) comparable à une garniture d'arrièrebec de bouclier; l'espace intermédiaire compris entre la garniture (22) et les entretoises peut être rempli'de graisse (23).
Inside the rear spout (7) of the shield is the internal formwork (14), in the form of a cylindrical envelope, which can be moved in the axial direction by means of jacks (15) mounted on the shield. digging (I), pressing against the annular front formwork (9) (Figure 2) .The front formwork (9) is curved on its inner peripheral surface (16) in order to obtain a better guide the intermediate formwork # (l4) and allow small tilting movements in curves
On the inner side of the intermediate formwork (14) is the annular front formwork (intended for the concrete of the covering (6) so that the intermediate formwork protrudes from the formwork (17) in an area (la). Frontal (17) are provided with openings, for introduction under pressure (19) for the concrete of the covering (6), which is brought by conduits (20). As is shown above all in FIG. 2, the intermediate form (14) is held in the region of the front formwork (17) by spacers (21) which can move by sliding over the internal formwork. The annular seal located between the front formwork (17) and the internal formwork (5) is sealed by a lining (22) comparable to a rear shield lining; the intermediate space between the lining (22) and the spacers can be filled with grease (23).

A la figure 4 est une vue en coupe transversale selon la ligne IV-IV de la figure 1, montrant la répartition des ouvertures d'introduction sous pression (12) et (19), respectivement de la matière pâteuse et du béton du revêtement (6). Pour des raisons de clarté, les conduites d'amenée ne sont pas représentées, non plus que les vérins destinés à l'avance du coffrage interne (14) et de l'élément télescopique de poussée (31). In Figure 4 is a cross-sectional view along line IV-IV of Figure 1, showing the distribution of the pressurized introduction openings (12) and (19), respectively of the pasty material and the concrete of the coating ( 6). For reasons of clarity, the supply lines are not shown, nor are the jacks intended for the advance of the internal formwork (14) and of the telescopic thrust element (31).

En fonctionnement du dispositif de creusement, pendant et à la suite de l'avance en direction de la flèche (24) montrée à la figure 2, au moyen des vérins d'avance (4) qui s'appuient dans le sens de la flèche (25) contre le coffrage interne (5), le mélange pâteux de minéral argileux est amené par les conduites (13) dans le sens de la flèche (26) et introduit sous pression par les ouvertures d'introduction sous pression (12) prévues dans le coffrage frontal (9), dans l'espace compris entre la roche (11) et le coffrage intermédiaire (14). Le minéral argileux constitue donc la couche (10) entre la roche (11) et le coffrage intermédiaire (14).Le creusement est arrêté dès que le coffrage frontal (9) parvient en appui contre une butée (27) à l'extrémité intérieure du coffrage intermédiaire (14) La position d'extrémité de la butée est représentée en pointillés à la figure 3. In operation of the digging device, during and following the advance in the direction of the arrow (24) shown in Figure 2, by means of the advance cylinders (4) which bear in the direction of the arrow (25) against the internal formwork (5), the pasty mixture of clay mineral is brought through the pipes (13) in the direction of the arrow (26) and introduced under pressure through the pressure introduction openings (12) provided in the front formwork (9), in the space between the rock (11) and the intermediate formwork (14). The clay mineral therefore constitutes the layer (10) between the rock (11) and the intermediate formwork (14). Digging is stopped as soon as the front formwork (9) comes to rest against a stop (27) at the inner end of the intermediate formwork (14) The end position of the stop is shown in dotted lines in Figure 3.

L'opération suivante est représentée à la figure 3. Le bouclier de creusement (1) étant arrêté, on fait avancer le coffrage intermédiaire (14) au moyen des vérins (15) dans le sens de la flèche (28), par rapport au bouclier (1), et à la suite de l'avance, du béton est simultanément int,roduit# sous pression par les conduites d'amenée (20) (dans le sens de la flèche (30)) et les ouvertures d'introduction sous pression (19) dans l'espace compris entre la couche intermédiaire (10) préalablement réalisée - et le coffrage intermédiaire (5) en vue de former le revêtement (6) du tunnel. The following operation is represented in FIG. 3. The digging shield (1) being stopped, the intermediate formwork (14) is advanced by means of the jacks (15) in the direction of the arrow (28), relative to the shield (1), and following the advance, concrete is simultaneously int, roduit # under pressure by the supply lines (20) (in the direction of the arrow (30)) and the introduction openings under pressure (19) in the space between the intermediate layer (10) previously produced - and the intermediate formwork (5) in order to form the lining (6) of the tunnel.

La zone en débord (18) du coffrage intermédiaire (14) empêche, à l'arrêt, qu'un mélange pâteux encore frais du minéral argileux pénètre dans une cavité quelconque s'étant formée avant l'introduction du béton frais. Pour éviter que le coffrage intermédiaire adhère dans cette région contre le béton qui prend, pendant les durées d'arrêt du bouclier de creusement, par exemple pendant des interruptions du travail, la zone (18) peut être réalisée sous la forme d'un coin de section allant en diminuant en direction de son extrémité, être munie de fentes longitudinales ou encore être constituée en un matériau flexible. Dans la partie restante, il se forme une ligne de séparation relativement régulière (29) entre la couche de minéral argileux (10) et le béton du revêtement (6). La garniture d'étanchéité (22) rend alors l'espace annulaire étanche par rapport au côté extérieur du coffrage interne (5), qui est maintenu constant par les élé ments d'écartement (21). The overhanging zone (18) of the intermediate formwork (14) prevents, when stationary, a pasty mixture, still fresh, of the clay mineral penetrating into any cavity which has formed before the introduction of the fresh concrete. To prevent the intermediate formwork from sticking in this region against the concrete which takes up, during the shutdown times of the digging shield, for example during work interruptions, the zone (18) can be made in the form of a wedge of section going down towards its end, be provided with longitudinal slots or be made of a flexible material. In the remaining part, a relatively regular separation line (29) is formed between the layer of clay mineral (10) and the concrete of the coating (6). The seal (22) then seals the annular space with respect to the external side of the internal formwork (5), which is kept constant by the spacing elements (21).

La figure 5 est une autre vue partielle en coupe transversale du revêtement de tunnel terminé comprenant une couche intermédiaire, avant le retrait du coffrage interne (5).  FIG. 5 is another partial view in cross section of the finished tunnel lining comprising an intermediate layer, before the removal of the internal formwork (5).

Claims (13)

- REVENDICATIONS- CLAIMS 1. Procédé pour réaliser une cavité souterraine de forme annulaire, par exemple un tunnel de circulation, selon l'une des revendications 19 ou 20 du brevet principal, selon lequel une matière pâteuse destinée à la formation d'une#cou- che intermédiaire entre la. roche et le revêtement qui supporte la poussée des terres est mise en place pendant le creusement, caractérisé en ce que la couche intermédiaire (10) est réalisée'en avance par rapport au revêtement (6), dans l'es pace intermédiaire compris entre la roche et un coffrage intermédiaire (14)' servant de limite interne et recouvrant.au moins la section destinée à cette couche préalable, et en ce' que le revêtement (6) est réalisé sur place par apport de béton dans la cavité située entre le coffrage intermédiaire (14) qui est, entraîné en même temps que progresse le bétonnage, et un' coffrage interne (5).  1. Method for producing an annular underground cavity, for example a circulation tunnel, according to one of claims 19 or 20 of the main patent, according to which a pasty material intended for the formation of an intermediate layer between the. rock and the covering which supports the thrust of the earth is put in place during the digging, characterized in that the intermediate layer (10) is produced in advance with respect to the covering (6), in the intermediate space between rock and an intermediate formwork (14) 'serving as an internal boundary and covering. at least the section intended for this preliminary layer, and in that the covering (6) is produced on site by adding concrete into the cavity located between the intermediate formwork (14) which is driven at the same time as concreting progresses, and an internal formwork (5). 2. Procédé selon la revendication 1, caractérisé en ce que la couche intermédiaire (10) et le revêtement (6) sont réalisés au cours d'étapes de travail séparées et successives. 2. Method according to claim 1, characterized in that the intermediate layer (10) and the coating (6) are produced during separate and successive working steps. 3. Procédé selon la revendication 2, caractérisé en ce que la couche intermédiaire (10) est réalisée de façon continue en 'même temps que le creusement. 3. Method according to claim 2, characterized in that the intermediate layer (10) is produced continuously at the same time as the digging. 4. Dispositif pour la mise en oeuvre du procédé'selon l'une quelconque des revendications 1 à 3, comprenant un. 4. Device for implementing the process according to any one of claims 1 to 3, comprising a. bouclier de creusement équipé de vérins de creusement et se prolongeant sur le côté tourné à l'opposé du front de taille par un arriè-re-bec de bouclier, caractérisé en ce qu'il comprend, sur le côté intérieur de l-'arrière-bec (7) du bouclier, un coffrage frontal (9) de forme annulaire et destiné à la couche intermédiaire (10), comprenant des ouvertures d'introduction sous pression (12) de la matière pâteuse, et en ce que le coffrage interméiaire (14) limitant la couche intermédiaire (10) est constitué sous forme d'une enveloppe cylindrique coopérant avec le côté intérieur du coffrage frontal (9) de la couche intermédiaire et comprenant sur son côté intérieur un coffrage frontal (17) de forme annulaire destiné au revêtement (6) qui, de son côté, est rendu étanche par rapport au coffrage intermédiaire (5) du revêtement (6).digging shield fitted with digging jacks and extending on the side turned away from the cutting face by a shield beaker, characterized in that it comprises, on the inner side of the rear -bec (7) of the shield, a front formwork (9) of annular shape and intended for the intermediate layer (10), comprising openings for the introduction under pressure (12) of the pasty material, and in that the intermediate formwork (14) limiting the intermediate layer (10) is in the form of a cylindrical envelope cooperating with the inner side of the front formwork (9) of the intermediate layer and comprising on its inner side a front formwork (17) of annular shape to the covering (6) which, for its part, is sealed relative to the intermediate formwork (5) of the covering (6). 5. Dispositif selon la revendication 4, caractérisé en ce que le coffrage intermédiaire (14) est déplaçable par rapport à l'arrière-bec (7) du bouclier et guidé de façon étanche contre le côté intérieur du coffrage frontal (9) de la couche intermédiaire (10). 5. Device according to claim 4, characterized in that the intermediate formwork (14) is movable relative to the rear spout (7) of the shield and guided in leaktight manner against the inner side of the front formwork (9) of the intermediate layer (10). 6. Dispositif selon l'une qu & conque des revendications 4 et 5, caractérisé en ce que le coffrage frontal (9) de la couche intermédiaire (10) est décalé vers l'arrière par rapport à l'extrémité de l'arrière-bec (8) du bouclier. 6. Device according to any of claims 4 and 5, characterized in that the front formwork (9) of the intermediate layer (10) is offset rearward relative to the end of the rear- beak (8) of the shield. 7. Dispositif selon l'une quelconque des revendications 4 à 6, caractérisé en ce que le coffrage frontal (X7) du re- vêtement (6) est décalé vers l'arrière par rapport à l'extrémité (18) du coffrage intermédiaire (14). 7. Device according to any one of claims 4 to 6, characterized in that the front formwork (X7) of the coating (6) is offset rearward relative to the end (18) of the intermediate formwork ( 14). 8. Dispositif selon la revendication 7, caractérisé en ce que l'extrémité du coffrage intermédiaire (14) qui fait saillie au-delà du coffrage frontal (17) est en forme de coin dont la section diminue en direction de son extrémité. 8. Device according to claim 7, characterized in that the end of the intermediate formwork (14) which projects beyond the front formwork (17) is wedge-shaped, the section of which decreases towards its end. 9. Dispositif selon l'une quelconque des, revendications 7 et 8, caractérisé en ce que l'extrémité; (18) du coffrage intermédiaire (14), qui fait saillie au-delà du coffrage frontal comprend des fentes orientées en direction: longitudinale.  9. Device according to any one of claims 7 and 8, characterized in that the end; (18) of the intermediate formwork (14), which projects beyond the front formwork comprises slots oriented in the direction: longitudinal. 10. Dispositif selon l'une quelconque des rev'en#ica- tions 7 à 9, caractérisé en ce que l'extrémit-e'Ç (i & ); cof- frage intermédiaire, qui fait saillie au-delà du coffrage frontal, est réalisée en une matière flexible; telle que du caoutchouc, de la matière synthétique ou analogues 10. Device according to any one of rev'en # ica- tions 7 to 9, characterized in that the end-e'Ç (i &); intermediate formwork, which projects beyond the front formwork, is made of a flexible material; such as rubber, synthetic material or the like 11. Dispositif selon l'une quelconque des revendications 4 à 10, caractérisé en ce que le coffrage frontal (17) du revêtement (6) est muni d'ouvertures d'introduction sous pression (19). 11. Device according to any one of claims 4 to 10, characterized in that the front formwork (17) of the covering (6) is provided with pressurized introduction openings (19). 12. Dispositif selon l'une quelconque des revendications 4 à 11, caractérisé en ce que le coffrage intermédiaire (14) s'appuie contre le bouclier (1) au moyen de vérins (15). 12. Device according to any one of claims 4 to 11, characterized in that the intermediate formwork (14) bears against the shield (1) by means of jacks (15). 13. Dispositif selon l'une quelconque des revendications 4 à 12, caractérisé en ce que le coffrage intermédiaire (14) est guidé par glissement contre la surface extérieure du coffrage interne (5) au moyen d'entretoises (21)  13. Device according to any one of claims 4 to 12, characterized in that the intermediate formwork (14) is guided by sliding against the external surface of the internal formwork (5) by means of spacers (21)
FR8502090A 1983-09-07 1985-02-14 PROCESS FOR PRODUCING A SUBTERRANEAN TUBULAR CAVITY, FOR EXAMPLE A TRAFFIC TUNNEL, AND DEVICE FOR CARRYING OUT SAID METHOD Expired - Lifetime FR2560635B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE19833332242 DE3332242A1 (en) 1983-09-07 1983-09-07 TUBULAR UNDERGROUND CAVE, LIKE TRAFFIC TUNNEL, PIPELINE OR THE LIKE
DE19843407384 DE3407384A1 (en) 1983-09-07 1984-02-29 Method of producing a tubular underground hollow space, e.g. a traffic tunnel, and apparatus for carrying out the method

Publications (2)

Publication Number Publication Date
FR2560635A2 true FR2560635A2 (en) 1985-09-06
FR2560635B2 FR2560635B2 (en) 1990-01-26

Family

ID=25813786

Family Applications (1)

Application Number Title Priority Date Filing Date
FR8502090A Expired - Lifetime FR2560635B2 (en) 1983-09-07 1985-02-14 PROCESS FOR PRODUCING A SUBTERRANEAN TUBULAR CAVITY, FOR EXAMPLE A TRAFFIC TUNNEL, AND DEVICE FOR CARRYING OUT SAID METHOD

Country Status (2)

Country Link
DE (1) DE3407384A1 (en)
FR (1) FR2560635B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0273104A1 (en) * 1986-12-16 1988-07-06 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Joint pack ring
EP0303775A1 (en) * 1987-08-13 1989-02-22 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Method for making a tunnel by using a driving shield

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3520092A1 (en) * 1985-06-05 1986-12-11 Dyckerhoff & Widmann AG, 8000 München Method of producing a tubular underground hollow space, e.g. a traffic tunnel, and apparatus for carrying out the method
DE3521888A1 (en) * 1985-06-19 1987-01-02 Dyckerhoff & Widmann Ag METHOD FOR PRODUCING A TUBULAR UNDERGROUND CAVITY, e.g. A TUNNEL, TUNNEL OR THE LIKE IN THE SHIELD DRIVING AND DRIVING SHIELD FOR CARRYING OUT THE METHOD
JPS6490399A (en) * 1987-09-30 1989-04-06 Tekken Constr Co Method of lining shield tunnel
DE102019120232A1 (en) * 2019-07-26 2021-01-28 Herrenknecht Aktiengesellschaft Device for a tunnel lining for sealing an annular gap extending in a longitudinal direction, device for installing an inner formwork in an outer formwork with such a device, tunnel boring machine with such a device and tunnel lining arrangement with such a device
GB2595270B (en) 2020-05-20 2022-09-28 Namaya Ltd Systems and methods of constructing intake-output assemblies for water desalination plants
GB2595716A (en) 2020-06-04 2021-12-08 Namaya Ltd Systems assemblies and methods of pipe ramming prefabricated members with a structured layout

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2013757A (en) * 1978-02-07 1979-08-15 Mowlem & Co Ltd J Improvements relating to tunnelling
DE3015210A1 (en) * 1980-04-19 1981-11-05 Bade & Theelen Gmbh, 3160 Lehrte Tunnel and mine gallery driving and concreting machine - has separately extensible following blades round end formwork casing in following shield

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1252227B (en) * 1967-10-19 Dr Ing Paproth &. Co Tiefbau Unternehmung Krefeld Process for the expansion of tunnels to be produced by means of shield jacking
DE1484574A1 (en) * 1964-09-10 1969-05-08 Stump Bohr Ag Method for sealing building structures
BE712437A (en) * 1967-03-22 1968-07-31
DE1965815A1 (en) * 1969-12-30 1971-07-01 Ruhrkohle Ag Procedure for the introduction of an extension of mine spaces
DE2550050C2 (en) * 1975-11-07 1983-12-29 Gewerkschaft Eisenhütte Westfalia, 4670 Lünen Device for driving tunnels or the like. by means of a shoring sign with the introduction of an in-situ concrete lining

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2013757A (en) * 1978-02-07 1979-08-15 Mowlem & Co Ltd J Improvements relating to tunnelling
DE3015210A1 (en) * 1980-04-19 1981-11-05 Bade & Theelen Gmbh, 3160 Lehrte Tunnel and mine gallery driving and concreting machine - has separately extensible following blades round end formwork casing in following shield

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0273104A1 (en) * 1986-12-16 1988-07-06 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Joint pack ring
US4909668A (en) * 1986-12-16 1990-03-20 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Movable sealing assembly for tunneling machines
EP0303775A1 (en) * 1987-08-13 1989-02-22 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Method for making a tunnel by using a driving shield

Also Published As

Publication number Publication date
DE3407384A1 (en) 1985-08-29
FR2560635B2 (en) 1990-01-26

Similar Documents

Publication Publication Date Title
US3994139A (en) Apparatus for and a method of laying a pipe line
FR2560635A2 (en) Underground road tunnel formation system
FR2599400A1 (en) METHOD FOR WATERTIGHT A HYDRAULIC STRUCTURE IN COMPACT CONCRETE OR IN FILLING
BE901814R (en) Underground road tunnel formation system - forms intermediate layer between rock and intermediate formwork before lining
FR2560282A1 (en) PROCESS AND INSTALLATION FOR THE CONTINUOUS COATING OF THE WALL OF A TUNNEL BY CONCRETE ON THE FOOT OF THE WORK
EP0692606B1 (en) Method for lining a tunnel
FR2679295A1 (en) Method and device for in situ concreting of an underground kerf and corresponding cutting blade
FR2579294A1 (en) Device for repairing pipelines in situ, in particular for drainage channels which cannot be visited
FR2635799A1 (en) Method and device for positioning underground ducts.
US4059965A (en) Apparatus for and a method of laying a pipe line
CN211368692U (en) Water stopping device in anchoring construction
FR2584150A1 (en) SYSTEM FOR HANGING AND REMOTELY TENSIONING AN ELONGATED ELEMENT
CA1283785C (en) Ballasting method and device for a continuously laid and buried pipe in a trench with temporarily shored sidewalls
FR3047496A1 (en) METHOD FOR MANUFACTURING AN ANCHOR TIE AND ANCHORING TIE
CN110820737A (en) Water stopping device in anchoring construction
JP3439341B2 (en) Propulsion method
JP3701157B2 (en) Underground joining method of shield excavator
JPH0232438B2 (en)
SU1609892A1 (en) Device for trenchless pipe laying in grounds
BE894870A (en) Method of underground working - has open trench first dug ahead of face and sealed enclosure later covered over
FR2536787A1 (en) METHOD AND DEVICE FOR GALERIE DRILLING FOR THE RENOVATION OF WASTEWATER COLLECTORS
FR2656913A1 (en) Device for cleaning and renovating, in situ, pipelines and ducts which can not be inspected from the inside and equipped, particularly, with a single inspection port
SU1057659A1 (en) Arrangement for laying monolithic concrete pipelineswithout soil removal