FI111405B - Concrete pipe pile and piling method - Google Patents

Concrete pipe pile and piling method Download PDF

Info

Publication number
FI111405B
FI111405B FI982699A FI982699A FI111405B FI 111405 B FI111405 B FI 111405B FI 982699 A FI982699 A FI 982699A FI 982699 A FI982699 A FI 982699A FI 111405 B FI111405 B FI 111405B
Authority
FI
Finland
Prior art keywords
pile
tube
concrete
collar
pile tube
Prior art date
Application number
FI982699A
Other languages
Finnish (fi)
Swedish (sv)
Other versions
FI982699A (en
FI982699A0 (en
Inventor
Jouko Lennart Lehtonen
Original Assignee
Rautaruukki Oyj
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rautaruukki Oyj filed Critical Rautaruukki Oyj
Publication of FI982699A0 publication Critical patent/FI982699A0/en
Priority to FI982699A priority Critical patent/FI111405B/en
Priority to PL365835A priority patent/PL204637B1/en
Priority to EP99961078A priority patent/EP1507928B1/en
Priority to DE69938438T priority patent/DE69938438T2/en
Priority to AT99961078T priority patent/ATE390521T1/en
Priority to PCT/FI1999/001027 priority patent/WO2000036226A2/en
Priority to RU2001119476/03A priority patent/RU2236505C2/en
Priority to AU17816/00A priority patent/AU1781600A/en
Priority to EEP200100272A priority patent/EE04970B1/en
Priority to DK99961078T priority patent/DK1507928T3/en
Publication of FI982699A publication Critical patent/FI982699A/en
Priority to NO20012890A priority patent/NO20012890D0/en
Application granted granted Critical
Publication of FI111405B publication Critical patent/FI111405B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Abstract

The invention relates to tubular piles encased in concrete, which comprise a metal pile tube (2) to be driven into soil, and in the upper end of the said tube an aperture for feeding liquid concrete mass into the pile tube interior (12). The lower end of the pile tube is provided with a pile shoe (1) comprising a longitudinal tip section (3) with uniform broadness and a ferrule (6), the maximum diameter (D1) of which is bigger than the outer diameter (D2) of the pile tube, and flow apertures (7), which are arranged above the lowermost upwards free base (24) of the ferrule and pass through the circumferential surface (23) of the said pile tube extension for the out-flow of concrete mass. The distance (L1) of the pile shoe from the tool tip (10) is at least five times the outer diameter (D2) of the pile tube. The invention also relates to a method for driving the tubular pile into the soil and encasing it in concrete.

Description

111405111405

Betonilla ympäröity putkipaalu ja paalutusmenetelmä - Rörpäle omgiven av betong och pälningsförfarande 5 Keksintö koskee betonilla ympäröitävää putkipaalua, joka käsittää: maaperään pakotettavan metallisen paaluputken; sen yläpäässä aukon/aukkoja juoksevan betonimassan syöttämiseksi paaluputken sisätilaan; ja sen alapäässä alaspäin suippenevan paalukengän, jonka yläosan läpimitta on suurempi kuin paaluputken läpimitta, ja jonka paalukengän alueelle paaluputken alapää aukeaa mainitun betonimassan 10 ulostulon mahdollistamiseksi. Keksintö koskee myös menetelmää putkipaalun pakottamiseksi maaperään ja ympäröimiseksi betonilla, joka putkipaalu käsittää metallisen paaluputken, jonka yläpäässä on aukko/aukkoja ja alapäässä suippeneva paalukenkä, jonka läpimitta on suurempi kuin paaluputken läpimitta, ja jonka paalu-kengän alueelle paaluputken alapää aukeaa.The invention relates to a concrete pile tube comprising: a metal pile tube which is forced into the ground; at its upper end, an aperture (s) for feeding a fluid mass of concrete into the pile tube interior; and at its lower end a tapered pile shoe having an upper portion larger than the diameter of the pile tube and having a pile shoe region open at the lower end of the pile tube to allow the outlet of said concrete mass 10. The invention also relates to a method of forcing a pipe pile into the soil and encircling it with concrete, the pipe pile comprising a metal pile tube having an aperture (s) at its upper end and a pile shoe tapering at the lower end having a diameter greater than the pile tube.

1515

Rakennusten perustusten kantavuutta parannetaan tunnetusti käyttämällä maahan lyötäviä paaluja, jotka uudisrakentamisessa yleensä koostuvat suhteellisen pitkistä teräsbetonipaaluista ja niiden osista. Korjausrakentamisessa eli aikaisemmin rakennettujen talojen tai muiden rakennelmien perustusten tukemiseen käytetään tilan-20 puutteen vuoksi lyhyitä ja jatkettavia paaluja, koska paalutustyö voidaan joutua tekemään rakennuksen sisällä pienissä ja matalissa tiloissa. Paalujen maahan pakottamiseksi taas käytetään tällaisessa tilanteessa keveitä iskuja tai jopa tärytystä, jotta vältettäisiin liiallista tärinää ja siten saataisiin estettyä ympärillä ja päällä olevan rakennuksen vaurioituminen. Paalun pakottamiseksi maahan, voidaan iskukappaletta 25 liikuttaa paaluputken sisällä ylös-alas tai vaihtoehtoisesti voidaan iskut tai täristys kohdistaa paalun yläpäähän. Yleensä perinteinen teräksisen putkipaalun sisätilavuus täytetään paalun maahan pakottamisen jälkeen betonilla. Teräksinen putkipaalu sinänsä on kuvattuun tarkoitukseen edullinen, sillä sitä on helppo jatkaa esimerkiksi hitsaamalla tai sopivan tyyppisellä holkkiliitoksella ja paalun vastus maahan painet-30 taessa on pienempi kuin vaikkapa betonipaalulla johtuen teräspaalun sileästä pinnasta. Jos paalun kärkeä ei saada vietyä kaihoon tai vastaavaan hyvin kantavaan kerrokseen asti, pitää paalun toimia paalun pituudella sijaitseviin maakerroksiin tukeutuvana kitkapaaluna. Tällaisessa tilanteessa on teräspaalun kantavuus sen sileän pinnan vuoksi huono ja betonipaalun kantavuus taas olennaisesti parempi. Tällainen on 35 tilanne esimerkiksi savimaissa, joissa savikerros voi olla erittäin paksu.The load-bearing capacity of the foundations of buildings is known to be improved by using piles, which are usually made up of relatively long reinforced concrete piles and their parts in new construction. Due to the lack of space-20, short and continuous piles are used in renovation construction, ie to support the foundations of previously built houses or other structures, as piling work may have to be done inside the building in small and shallow spaces. Again, to force the piles to the ground, light shocks or even vibrations are used in this situation to avoid excessive vibration and thus prevent damage to the building around and over. To force the pile on the ground, the impact piece 25 may be moved up and down within the pile tube, or alternatively, the impact or vibration may be applied to the top of the pile. Usually, the traditional internal volume of a steel pipe pile is filled with concrete after the pile has been forced to the ground. A steel pipe pile per se is advantageous for the purpose described because it is easy to extend, for example, by welding or by a suitable type of sleeve joint, and the pile resistance when pressed to the ground is less than, say, a concrete pile due to the smooth surface of the steel pile. If the tip of the pile cannot be pushed up to the cataract or similar well-supporting layer, the pile must be considered as a friction pile resting on ground layers along the length of the pile. In such a situation the steel pile has a poor bearing capacity due to its smooth surface and the concrete pile has significantly better load bearing capacity. This is the case, for example, in clay soils where the clay layer may be very thick.

NO-121440 kuvaa stabilointimassan injektointia maahan lyödyn perustuspaalun, joka koostuu muutoin täysin tavanomaisesta betonipintaisesta teräsbetonipaalusta ja 2 111405 siinä olevasta tavallisen tyyppisestä kalliokäijestä [vrt. esim. ruotsalainen standardi SIS 811196; 1972-11-20] sekä paalun teräsbetonin läpi menevästä kanavasta, jonka kautta stabilointimassaa painetaan paalukärjen lähellä olevaan maaperään. Tämä paalu on lyötävä maahan aivan kuten tavanomaiset teräsbetonipaalut, eikä sillä ole 5 pinnan ansiosta pientä vastusta. Yleensä maaperän stabilointiin käytetään kalkkia, mutta tässä tapauksessa betonimassaa, millä luultavasti tarkoitetaan sementtiä, kuten julkaisussa EP-0539 630. Norjalaisen julkaisun paalukengässä on läpimitaltaan oleellisesti paaluputken pään kokoinen pääty ja siitä ulkoneva kapeampi kärkiosa ja tässä ohuessa kärkiosassa kanavat stabilointimassan injektointia varten maaperään. 10 Tarkoituksena on saada paalun kärjen lähellä ja erityisesti sen alapuolella oleva maaperä stabiloitua. Kärkiosan pituudelle annetaan kaava, jonka mukaan pituusmitta L on (R + r)V3 eli kuvassa noin kolme kertaa kärkiosan halkaisija ja likimäärin yhtä suuri kuin paalun halkaisija. Tehokkaasti kantavan alueen saaminen paalun kärjen kohdalle on vaikeaa, koska kantavaksi saatava alue on pinta-alaltaan hyvin 15 rajallinen. Varsinkin jos huonosti kantava maaperä jatkuu kärjen kohdalle kovetetun sementtipitoisen alueen alapuolelle, voi tällaisen kovetetun alueen merkitys olla olematon tai vieläpä haitallinen.NO-121440 describes the injection of stabilizing mass into a ground pile, which is otherwise composed of a conventional concrete reinforced concrete pile and 2 111405 of the usual type of rock walker [cf. e.g. Swedish Standard SIS 811196; And a passage through the reinforced concrete pile through which the stabilizing compound is pressed into the soil near the pile tip. This pile has to be hit with the ground just like normal reinforced concrete piles and has no small resistance due to 5 surfaces. In general, lime is used for soil stabilization, but in this case concrete pulp, which probably means cement, as in EP-0539 630. The pile shoe of the Norwegian publication has a substantially pile tube end and a narrower apex projecting therefrom and a thin tip for grouting. 10 The purpose is to stabilize the soil near the pile tip and especially below it. The length of the tip is given by the formula that the length dimension L is (R + r) V3, that is to say about three times the diameter of the tip and approximately the diameter of the pile. It is difficult to obtain an effective bearing area at the pile tip because the area to be supported is very limited in area. Especially if the poorly bearing soil extends below the cemented area at the tip, the importance of such a hardened area may be non-existent or even detrimental.

EP-0 539 630 kuvaa maaperään ruuvattavan perustuspaalun valmistusmenetelmän, 20 jossa paalun ruuvikärjestä sen edellä menevästä kohdasta syötetään paalua maahan kierrettäessä aluksi veden ja bentoniitin seosta ja sen jälkeen, kun paalun ruuvikärki saavuttaa kantavan maaperäkerroksen, sementin ja veden seosta suurella paineena, joka on suurempi kuin hydrostaattinen paine, minkä jälkeen paalun ruuvimainen kärki sekoittaa voimakkaasti sementin ja maaperän. Sementtiseoksen ajopaine on 25 hyvin suuri, jopa 500 bar - 1000 bar. Tuloksena saadaan paalun alaosan ja kantavan maaperän väliin muodostettua suuriläpimittainen kannattava vyöhyke. Menetelmä on ensinnäkin monimutkainen, koska se edellyttää ensin porausnesteenä veden ja bentoniitin seosta ja siten laitteet kärjestä ulos pakotettavan massan vaihtamiseen. Lisäksi menetelmä vaatii suurikokoiset ja kalliit laitteet sekä paalun maahan ruu-30 vaamiseksi että mainitun suuren paineen saamiseksi. Korjausrakentamisessa tämän tyyppiset koneet ovat useimmiten liian suuria käytettäväksi, koska ne eivät yksinkertaisesti mahdu huone- tai kellaritiloihin. Sekä julkaisun NO-121440 että julkaisun EP-0 539 630 ratkaisut edellyttävät massan syöttämistä erittäin suurella paineella, koska massa tulee ulos maaperään paalun kärjen otsapinnan alapuolelta, missä maa-35 perän vastapaine on suurimmillaan ja jona vastapaine on ylitettävä pumppauspai-neella. Julkaisussa US-4 909 673 on kuvattu injektointimenettely, jossa paaluputkeen on järjestetty suuri määrä injektointireikiä ja paaluputken sisäpuolelta näihin reikiin liitetyt injektointiventtiilit, jolloin saadaan paalun ja maan välistä kitkaa lisät- 3 111405 tyä injektoimalla teräspaalun ulkopinnalle kovettuvaa laastia. Tämäkin menetelmä edellyttää samoin kuin edellä mainittu EP-julkaisu suurten paineiden ja suurikokoisten koneiden käyttöä. Lisäksi rakenne on aivan liian monimutkainen ja kallis käytettäväksi pienimuotoisessa työskentelyssä kuten yksittäisen talon tai vastaavan kanta-5 vuuden lisäämiseksi.EP-0 539 630 discloses a method of making a foundation pile to be screwed into the soil, wherein a pile screw is fed from the upstream position of the pile screw head first to a ground mixture of water and bentonite and after the pile screw reaches a bearing soil, cement and water hydrostatic pressure followed by vigorous mixing of cement and soil by the screw tip of the pile. The cement mixture has a working pressure of 25 very high, up to 500 bar - 1000 bar. As a result, a large diameter profitable zone is formed between the lower part of the pile and the supporting soil. First of all, the process is complicated because it first requires a mixture of water and bentonite as the drilling fluid, and thus the devices for changing the mass forced out. In addition, the method requires large and expensive devices both to pile on the ground and to obtain said high pressure. In renovation construction, these types of machines are often too large to be used because they simply cannot fit into a room or basement. The solutions of both NO-121440 and EP-0 539 630 both require the mass to be fed at very high pressure, since the mass exits the soil below the pile head face, where the back pressure of the soil 35 is at its maximum and the back pressure must be exceeded by pumping pressure. US-4,909,673 describes an injection procedure in which a plurality of injection holes are provided in a pile tube and injection valves connected to these holes from the inside of the pile tube to provide additional pile-to-ground friction by injecting curing mortar on the outer surface of a steel pile. This method also requires the use of high pressures and large machines, as does the aforementioned EP publication. In addition, the structure is far too complicated and expensive to be used in small-scale work such as to increase the load-bearing capacity of a single house or similar.

Edellisistä täysin poikkeava menetelmä on kuvattu julkaisussa FI-30911, joka koskee betonilla ympäröidyn junttapaalun valmistusmenetelmän. Menetelmässä paalu-kengällä, joka on ylöspäin avoin ja jonka yläosan poikkipinta on suurempi kuin 10 paaluvarren poikkipinta, varustettu putkimainen paaluvarsi juntataan maahan ja se-menttivelliä tai ohutta betonia puristetaan onttoa paaluvartta pitkin ja paalukengän kautta maaperän ja paaluvarren väliin paalukengän vaikutuksesta syntyneeseen onteloon. Tässä menetelmässä juoksevaa sementtiä tai betonia siis puristetaan ylhäältä päin samanaikaisesti ja jatkuvasti junttauksen kanssa syntyvään maaperäonteloon 15 pienellä paineella ontelon jatkuvaksi täyttämiseksi. Junttauksen lopussa tiivistetään täytetty onteloilla ylhäältä ja betonin syöttöä jatketaan suuremmalla paineella. Tämä menetelmä saa tosin aikaan kantavan betonikuoren teräksiseen putkipaaluun varsin yksinkertaisin keinoin. Kuvatussa järjestelyssä on kuitenkin huomattavia ongelmia. Pyrittäessä käyttämään kuvatunlaista konstruktiota todetaan, että useimmiten paalu 20 ei etene maaperässä suoraan, vaan pyrkii selvästi kaartumaan, jolloin paaluputkeen saattaa kohdistua niin suuria taivutusvoimia, että paalun eteneminen maaperään pysähtyy tai paalu vieläpä katkeaa. Vaikka julkaisussa mainitaan sementti- tai betoni-massan syöttäminen vain pienellä paineella, vaatii senkin aikaansaaminen moniin työkohteisiin liian suurikokoisia ja/tai kalliita koneita.A completely different process is described in FI-30911, which relates to a process for manufacturing a concrete surrounded train pile. In the method, a tubular pile arm equipped with a pile shoe that is open upwards and has a cross sectional area greater than 10 pile rods is strung to the ground and extruded with cavity or thin concrete from the hollow pile shank and through the pile shoe to the pile shank. Thus, in this process, fluid cement or concrete is pressed from above, simultaneously and continuously, into the soil cavity 15 formed by shunting under low pressure to continuously fill the cavity. At the end of shunting, the filled cavities are sealed from above and the concrete feed is continued at higher pressure. However, this method provides a load-bearing concrete shell for the steel pipe pile by quite simple means. However, there are considerable problems with the arrangement described. In attempting to use such a construction, it will be noted that in most cases, the pile 20 does not proceed directly in the soil, but clearly tends to bend, causing the pile tube to exert so much bending force that the pile advances to the ground or even stops. Although the publication mentions the supply of cement or concrete pulp at only a low pressure, it is also necessary for many applications to be too large and / or expensive.

2525

Keksinnön tavoitteena on siten saada aikaan metallinen, tyypillisesti teräksinen paalu, esimerkiksi putkipaalu, joka olisi sen maaperään ajamisen yhteydessä ulkopinnaltaan ympäröitävissä kovettuvalla massalla, kuten betonilla, ilman monimutkaisia, kalliita ja/tai suurikokoisia laitteita siten, että valmiin betonipintaisen paalun 30 kantavuus olisi vähintään samaa suuruusluokkaa kuin ennalta tehtyjen betonipaalu-jen kantavuus. Keksinnön toisena tavoitteena on saada aikaan metallinen esimerkiksi putkipaalu, jonka maaperään ajamiseen tarvitaan mahdollisimman vähäinen voima, vastaten enintään suoran teräsputkipaalun vaatimaa voimaa maaperässä. Keksinnön kolmantena tavoitteena on metallinen esimerkiksi putkipaalu, joka maa-35 perään pakotettaessa ei ainakaan haitallisessa määrin pyrkisi etenemään suuntaan, joka ei ole suorassa linjassa tarkoitetun suunnan kanssa. Paalun tulisi siis ainakin pääpiirteittäin pysyä suorana. Keksinnön neljäntenä tavoitteena on tällainen paalu, joka olisi rakenteeltaan yksinkertainen ja valmistus- ja käyttökustannuksiltaan edul- 4 111405 linen. Keksinnön viidentenä tavoitteena on sellainen menetelmä metallisen paalun pakottamiseksi maaperään ja ympäröimiseksi betonilla, joka on toteutettavissa ahtaissakin tiloissa ja eri tyyppisissä maaperissä. Vielä keksinnön tavoitteena on tällainen menetelmä, jossa esimerkiksi putkipaalulle saadaan hyvä kantavuus eri tyyppi-5 sissä maaperissä. Keksinnön tarkoituksena on näin ollen luoda paalutusmenetelmä ja paalu, jossa yhdistyy teräksisen putkipaalun helppo asennettavuus ja betonipaalun hyvä tartunta maakerroksiin.It is therefore an object of the invention to provide a metal pile, typically a steel pile, for example a pipe pile, which, when driven into the ground, is surrounded by a curable mass such as concrete without complicated, expensive and / or bulky devices such that the finished concrete pile has than the load-bearing capacity of pre-made concrete piles. Another object of the invention is to provide a metal pile, for example, with a minimum force required to propel the soil, up to a maximum force required by the straight steel pipe pile in the soil. A third object of the invention is a metallic pipe pile, for example, which, when forced to the ground 35, would not, at least adversely, attempt to advance in a direction which is not in a direct line with the direction in question. Thus, at least in principle, the pile should remain straight. A fourth object of the invention is to provide such a pile which is simple in structure and inexpensive in manufacturing and operating costs. A fifth object of the invention is to provide a method of forcing a metal pile into and encircling with concrete, which is feasible in confined spaces and in different types of soil. Yet another object of the invention is to provide such a method which, for example, provides a good load-bearing capacity for the pipe pile in different types of soils. It is therefore an object of the invention to provide a piling method and a pile that combines easy installation of a steel pipe pile with good adhesion of the concrete pile to the ground.

Edellä kuvatut haittapuolet saadaan eliminoitua ja edellä määritellyt tavoitteet toteu-10 tettua keksinnön mukaisella putkipaalulla, jolle on tunnusomaista se, mitä on määritelty patenttivaatimuksen 1 tunnusmerkkiosassa ja keksinnön mukaisella menetelmällä, jolle on tunnusomaista se, mitä on määritelty patenttivaatimuksen 12 tunnusmerkkiosassa.The drawbacks described above can be eliminated and the objectives defined above be achieved by a pipe pile according to the invention, characterized in what is defined in the characterizing part of claim 1 and in a method according to the invention, characterized in that in the characterizing part of claim 12.

15 Yllättäen on nyt todettu, että järjestämällä paalun alapäähän joka alapää edellä paalu työnnetään maahan, sellainen paalukenkä, jossa on läpimitaltaan paaluputken läpimittaa suurempi kaulus ja kauluksesta paalun työntösuuntaan eli alaspäin ulkoneva suhteellisen pitkä kärkiosa ja järjestämällä kovettuvan massan ulostulo paaluputken sisätilasta kauluksen ja paaluputken kontaktikohdan yläpuolella kehällä sijait-20 sevien reikien kautta saadaan paalu lyönneillä ja/tai täristyksellä uppoamaan riittävän suorana maaperään sen laadusta tai laatuvaihteluista riippumatta. Lisäksi on yllättäen todettu, että kovettuva vesipitoinen massa siirtyy tehokkaasti ja nopeasti metallisen paaluputken sisätilasta näiden kehällä olevien reikien kautta kauluksen vaikutuksesta paaluputken ympärille syntyneeseen onteloon pelkästään paalun upo-25 tuslyöntien ja/tai upotustäristyksen vaikutuksesta, jolloin ei ole välttämättä tarpeen käyttää kovettuvan massan syöttöön paaluputken yläpäässä, joka on maanpinnan yläpuolella, lainkaan painetta, vaan massa voidaan yksinkertaisesti kaataa paaluputken sisään. Tämän putkipaalun vaatima voima sen maahan pakottamiseksi on pieni ja valmiin betonilla päällystetyn ja täytetyn putkipaalun kantavuus on erinomainen 30 sen toimiessa kitkapaaluna joko koko pituudeltaan tai ennalta määrätyltä pituuden osaltaan. Lisäksi keksinnön etuna on se, että paaluputken yläpäähän ei ole tarpeen järjestää monimutkaisia välineitä kovettuvan massan syötön ja upotusiskujen tai upotustäristyksen samanaikaisuuden saamiseksi, koska keksinnön mukaan vaiheet tehdään erikseen. Tämän keksinnön mukainen parannettu paalurakenne ja paalujen 35 asentamismenetelmä soveltuu erinomaisesti rakennusten perustusten korjaukseen, mutta ei ole kuitenkaan rajoitettu tähän käyttöön. Keksintöä voidaan käyttää sekä painamalla että tärytyksellä maahan työnnettävissä paalussa.Surprisingly, it has now been found that by providing a pile shoe with a collar having a diameter larger than the pile through holes 20, the pile can be immersed in the soil with enough stroke and / or vibration regardless of its quality or quality variations. Furthermore, it has surprisingly been found that the curing aqueous mass is efficiently and rapidly transferred from the interior of the metal pile tube through these circumferential holes into the cavity formed by the collar around the pile tube solely by the impact and / or , above the ground, no pressure at all, but the mass can simply be poured into the pile tube. The force required by this tubular pile to force it to the ground is low and the load-bearing capacity of the finished concrete-coated and filled tubular pile is excellent when it acts as a friction pile, either over its entire length or for a predetermined length. A further advantage of the invention is that it is not necessary to provide complicated means at the upper end of the pile tube for simultaneous delivery of the curable mass and the dipping strokes or dipping vibrations, since according to the invention the steps are performed separately. The improved pile structure and method of piling 35 in accordance with the present invention are well suited to, but not limited to, repairing the foundations of buildings. The invention can be used both by pressing and by vibrating on a pile that can be pushed to the ground.

5 1114055 111405

Seuraavassa keksintöä selostetaan yksityiskohtaisesti oheisiin piirustuksiin viittaamalla.The invention will now be described in detail with reference to the accompanying drawings.

Kuviot IA - 1H kuvaavat keksinnön mukaisen menetelmän eri vaiheita käytettäessä 5 keksinnön mukaista putkipaalua ja sen pitkällä kärkiosalla varustettua paalukenkää kaaviomaisesti maanpinnan tasoa vastaan kohtisuorassa pystyleikkauksessa.Figures 1A to 1H illustrate various stages of the method of the invention using a pipe pile according to the invention and a pile shoe with a long toe portion in a vertical section perpendicular to the ground plane.

Kuvio 2 kuvaa keksinnön mukaisella paalulla ja menetelmällä saadun valmiin paa-lurakenteen ensimmäistä toteutusmuotoa maaperässä, samassa kuvannossa kuin ku-10 viot IA - 1H.Fig. 2 illustrates a first embodiment of a finished pile structure obtained in a pile and method according to the invention in soil, in the same view as Figs.

Kuvio 3 kuvaa keksinnön mukaisella paalulla ja menetelmällä saadun valmiin paa-lurakenteen toista toteutusmuotoa maaperässä, samassa kuvannossa kuin kuvio 2.Fig. 3 illustrates another embodiment of a finished pile structure obtained in the pile and method according to the invention in soil, in the same view as Fig. 2.

15 Kuvio 4A esittää keksinnön mukaisen paalukengän ensimmäistä toteutusmuotoa liitettynä paaluputkeen pitkittäisleikkauksena pitkin kuvion 4B tasoa I-I.Figure 4A shows a first embodiment of a pile shoe according to the invention connected in longitudinal section along the plane I-I of Figure 4B.

Kuvio 4B esittää keksinnön mukaisen paalukengän ensimmäistä toteutusmuotoa liitettynä paaluputkeen poikkileikkauksena pitkin kuvion 4A tasoa Π-ΙΙ.Fig. 4B shows a first embodiment of a pile shoe according to the invention connected in cross section along the plane Π-ΙΙ of Fig. 4A.

2020

Kuvio 5A esittää keksinnön mukaisen paalukengän toista toteutusmuotoa liitettynä paaluputkeen pitkittäisleikkauksena pitkin kuvion 5B tasoa III-IH.Fig. 5A shows a second embodiment of a pile shoe according to the invention connected to the pile tube in longitudinal section along the plane III-IH of Fig. 5B.

Kuvio 5B esittää keksinnön mukaisen paalukengän toista toteutusmuotoa liitettynä 25 paaluputkeen poikkileikkauksena pitkin kuvion 5A tasoa IV-IV.Fig. 5B shows a second embodiment of a pile shoe according to the invention connected to a pile tube in cross section along the plane IV-IV in Fig. 5A.

Kuvio 6A esittää keksinnön mukaisen paalukengän kolmatta toteutusmuotoa liitettynä paaluputkeen pitkittäisleikkauksena pitkin kuvion 6B tasoa V-V.Fig. 6A shows a third embodiment of a pile shoe according to the invention connected in longitudinal section along the plane V-V in Fig. 6B.

30 Kuvio 6B esittää keksinnön mukaisen paalukengän kolmatta toteutusmuotoa liitettynä paaluputkeen poikkileikkauksena pitkin kuvion 6A tasoa VI-VIFig. 6B shows a third embodiment of a pile shoe according to the invention in cross-sectional view taken along the plane VI-VI in Fig. 6A.

Kuvio 7 esittää keksinnön mukaisen paalukengän neljättä toteutusmuotoa liitettynä paaluputkeen pitkittäisleikkauksena samassa kuvannossa kuin kuviot 4A - 6A.Fig. 7 shows a fourth embodiment of a pile shoe according to the invention connected in longitudinal section to a pile tube in the same view as Figs. 4A-6A.

Kuvio 8A - 8C esittävät keksinnön mukaisia kolmea erilaista liitosta paaluputken osien jatkamiseksi putkipaalun pitkittäisleikkauksina samassa kuvannossa kuin kuviot 4A - 6A ja 7.Figures 8A-8C show three different joints according to the invention for extending portions of a pile tube in longitudinal section of a tube pile in the same view as Figures 4A-6A and 7.

35 6 11140535 6 111405

Keksintö kohdistuu betonilla ympäröitävään putkipaaluun 40, jonka varsi koostuu paaluputkesta, josta yleisesti käytetään viitenumeroa 2. Ainoastaan silloin kun on tarpeen saada paaluputken eri osat tai osuudet erotettua toisistaan käytetään yksilöi-5 vämpiä viitenumerolta 2a, 2b, 2c, 2’ jne. Yleinen viitenumero 2 viittaa kaikkiin näihin. Putkipaalu 40 siis käsittää maaperään pakotettavan tai työnnettävän metallisen, yleensä teräksisestä putkimateriaalista koostuvan, paaluputken 2, joka voi jäljempänä selostettavalla tavalla muodostua yhdestä tai useammasta putkiosasta 2a, 2b, 2c jne. Tässä selostuksessa tarkoitetaan käsitteillä ’’alapää”, ’’alaspäin”, ’’ala-” 10 jne paalun maahan uppoamisen suuntaan osoittavaa tai maahan työnnettävän pään suuntaan sijaitsevaa asemaa ja vastaavasti käsitteillä ’’yläpää”, ’’ylöspäin”, ’’ylä-” maanpinnan puolelle jäävän paalun pään suuntaan tai maanpinnasta ulospäin osoittavan suuntaan sijaitsevaa asemaa. Yleensä paalut 40 ajetaan maahan pystysuorassa tai lähes pystysuorassa asennossa, kuten on näytetty kuvioissa IA - 3, jolloin edellä 15 selostetut suunnat ja puolet ovat itsestään selviä, mutta ne on ymmärrettävä määritel lyllä tavalla, vaikka paalun pituuden keskilinja 31 muodostaisikin horisontaalitasoon tai maanpintaa 32 kuvaavaan tasoon nähden suorasta kulmasta huomattavastikin poikkeavan kulman, joka voi olla kymmeniä kulma-asteita.The invention relates to a concrete pipe pile 40 surrounded by a concrete consisting of a pile tube generally referred to as reference numeral 2. Only when it is necessary to distinguish between different parts or portions of the pile tube are the unique reference numerals 2a, 2b, 2c, 2 'etc. refers to all of these. The pipe pile 40 thus comprises a metal pile tube 2, generally made of steel pipe material, which may be formed or pushed into the ground, which may consist of one or more pipe sections 2a, 2b, 2c, etc. As used herein, "lower end", "downward", " The position of the "bottom" 10 etc pile in the direction of sinking or in the direction of the pushed head and the position of "pile head", "up", "top" of the pile head below or above the ground, respectively. Generally, piles 40 are driven into the ground in a vertical or near-vertical position, as shown in Figures IA-3, whereby the directions and sides described above 15 are self-explanatory, but must be understood in a defined manner even if the centerline 31 of the pile length is horizontal or planar 32 even at a right angle, which can be tens of degrees.

20 Tyypillisesti paaluputki 2 on poikkileikkaukseltaan tavanomaista pyöreää teräsputkea, mutta voidaan tietenkin käyttää poikkileikkaukseltaan toisenlaistakin putkea, kuten neliömäistä, vinoneliön muotoista tai suunnikkaan muotoista putkea. Paalu-putken ulkoläpimitta D2 voi poikkileikkausmuodosta riippumatta olla esimerkiksi välillä 25 mm - 1500 mm, edullisesti välillä vähintään 40 mm ja enintään 300 mm ja 25 tyypillisesti vähintään 50 mm ja enintään 200 mm. Paaluputken 2 seinämäpaksuus voi olla välillä 1 mm - 20 mm riippuen paaluputken ulkoläpimitasta, edullisesti vähintään 3 mm ja enintään 15 mm ja tyypillisesti vähintään 5 mm ja enintään 12 mm. Paaluputken sisäläpimitta on tietenkin seinämäpaksutta vastaavan mitan verran pienempi kuin ulkoläpimitta ja muodostaa paaluputken sisätilan 12, jota pitkin betoni-30 massa B kulkee paaluputken yläpäästä 29 virtausreikiin 7. Paaluputken 2 toisiinsa liitettävien putkiosien 2a, 2b, 2c jne pituudet ovat pienempiä kuin sen tilan korkeus, jonka sisällä putkipaalun 40 ajaminen maahan tapahtuu, jolloin putkiosien 2a, 2b, 2c jne pituudet L2 ovat usein vähintään 0,5 m ja enintään 3 m, tyypillisesti välillä 1 m - 2,5 m. Mikäli tilaa on voidaan tietenkin käyttää pitempiäkin putkiosia, kuten pituu-35 deltaan 6 m tai pitempiäkin putkiosia. Tarvittaessa paaluputken 2 ulkopinnalla on tartuntoja 30, kuten kiinnihitsattuja teräslistan kappaleita tai muulla tavoin tehtyjä muotoja, kovettuneen betonin B ja paaluputken keskinäisen tartunnan parantamiseksi. Vaikka keksinnön tyypillinen ja edullinen käyttökohde on korjausrakentami- 7 111405 sessa jo olemassa olevien rakenteiden, kuten talojen, siltojen, teiden ja muiden kiinteiden rakenteiden perustusten uudelleen tukeminen, voidaan keksinnön mukaista paalua käyttää myös muissa yhteyksissä, kuten uudisrakentamisessa sekä maa-ankkureina ja maanauloina.Typically, the pile tube 2 is a circular steel tube of conventional cross-section, but of course a tube of a different cross-section may be used, such as a square tube, a diamond tube or a parallelepiped tube. The outer diameter D2 of the pile pipe, regardless of its cross-sectional shape, may for example be between 25 mm and 1500 mm, preferably between at least 40 mm and at most 300 mm and typically at least 50 mm and at most 200 mm. The wall thickness of the pile tube 2 may range from 1 mm to 20 mm, depending on the outer diameter of the pile tube, preferably at least 3 mm and at most 15 mm and typically at least 5 mm and at most 12 mm. The inner diameter of the pile tube is of course smaller than the outer diameter and forms the inner space 12 of the pile tube, along which the concrete B mass B passes from the upper end 29 of the pile tube to the flow holes 7. within which the pipe pile 40 is driven into the ground, whereby the lengths L2 of the pipe sections 2a, 2b, 2c etc. are often at least 0.5 m and at most 3 m, typically between 1 m and 2.5 m. Lengths of 35 pipe sections of 6 m or more in length. If necessary, the outer surface of the pile tube 2 has adhesions 30, such as welded pieces of steel strip or otherwise formed, to improve the adhesion between the hardened concrete B and the pile tube. Although a typical and advantageous application of the invention is the reinforcement of foundations of existing structures such as houses, bridges, roads and other fixed structures in renovation, the pile according to the invention can also be used in other contexts, such as new construction, earth anchors and eartheners.

55

Maanpinnan 32 yläpuolelle tai ainakin maanpinnan 32 lähelle jäävän ja siten ulkoiseen tilaan osoittavassa putkipaalun 40 paaluputken 2 yläpäässä on aukko tai aukkoja 29 juoksevan betonimassan syöttämiseksi paaluputken sisätilaan 12. Yksinkertaisimmillaan paaluputken 2 yläpään aukko 29 on vain avoin putken pää, jonka sisälle 10 juokseva betonimassa kaadetaan, kuten kuvioissa IB, ID ja 1G on näytetty. Vaihtoehtoisesti paaluputken yläpäässä voi olla aukko tai aukkoja 29 joko putken kehällä ja/tai putken yläpäässä mahdollisesti käytetyssä, kuvioissa ei esitetyn ja paaluputken päähän paalua maahan ajavaa voimaa F välittävässä, lyöntialustassa. Tällainen lyöntialusta voi muodostua esimerkiksi putkiosien liitoskappaleista 21 tai toisenlai-15 sesta paaluputken päähän kiinnitettävästä ja siitä irrotettavasta kappaleesta, joka suojaa paaluputken päätä vaurioitumiselta ja muodonmuutoksilta ja jakaa siihen kohdistuvan voiman F, jolla putkipaalua 40 pakotetaan maahan, halutulla tavalla paaluputkeen.At the upper end of the pile tube 2 of the pipe pile 40 above ground 32 or at least near the ground 32 and thus indicating an outer space, there is an opening or openings 29 for as shown in Figures IB, ID and 1G. Alternatively, there may be an opening or openings 29 in the upper end of the pile tube, either on the perimeter of the tube and / or on a punching platform imparting a force F on the pile tube, not shown in the figures. Such a punching platform may consist, for example, of pipe member junctions 21 or of another type 15 which is secured to and detached from the pile tube end, which protects the pile tube end from damage and deformation and distributes the force F to force the pile 40 up to the desired pile.

20 Putkipaalun 40 alapäässä sijaitsee keksinnön mukainen alaspäin suippeneva paalu-kenkä 1, jolla on suuri ulkoläpimitta Dl, ja jonka paalukengän 1 alueelle paaluputki ja erityisesti sen sisätila 12 aukeaa mainitun betonimassan B ulostulon mahdollistamiseksi. Keksinnön mukainen paalukenkä 1 koostuu pitkänomaisesta pääasiassa tasapaksusta kärkiosasta 3, jossa on alapäässään työkärki 10 sekä kauluksesta 6, 25 jonka maksimiläpimitta Dl on oleellisesti suurempi kuin paaluputken ulkoläpimitta D2. Kauluksen maksimiläpimitta Dl muodostaa maaperän M ontelon tai tilan T paaluputken ympärille betonia B varten. Paaluputken ympärille pyritään yleensä saamaan jokin ennalta määrätty kerrospaksuus betonia, jonka kerroksen paksuus suuruusluokkaa puolet paalukengän maksimiläpimitan Dl ja paaluputken ulkolä-30 pimitän D2 erotuksesta. Siten betonin haluttu kerrospaksuus Wb saadaan paaluputkea ympäröivän ontelon T säteen suuntaisella paksuudella W, joka saadaan määräämällä ennalta paalukengän maksimiläpimitta Dl suhteessa paaluputken ulkolä-pimittaan eli W = [Dl - D2]/2. Tyypillisesti paaluputken pintaan halutaan betoniker-ros, jonka paksuus on vähintään 5 mm ja enintään 200 mm, yleensä vähintään 15 35 mm ja enintään 100 mm ja edullisesti välillä 30 mm - 50 mm. Tämän teräksistä paaluputkea ympäröivän betonikerroksen nimellinen paksuus Wb ja siten sen synnyttävä kauluksen maksimiläpimitta Dl voidaan myös suhteuttaa paaluputken ulko-läpimittaan D2 järjestämällä maksimiläpimitta Dl noin 1-4 kertaiseksi tai edullisesti 8 111405 1,5 - 2,5 kertaiseksi paaluputken ulkoläpimittaan D2 nähden. On ymmärrettävä, että jos paaluputken 2 ja kauluksen 6 poikkipintojen muodot ovat toisistaan poikkeavia, kuten on laita kuvioiden 5A ja 5B toteutusmuodossa ja kuvioiden 6A ja 6B toteutusmuodossa, vaihtelee laskennallinen paksuus W ja betonin nimellinen paksuus WB 5 paalun eri sivuilla. Samoin on huomattava, että maaperän M laadusta ja laatuvaihte-luista, kuten kerroksellisuudesta tai epähomogeenisuudesta, riippuen vaihtelee be-tonikerroksen todellinen paksuus WB paalun pituussuunnassa eli keskilinjan 31 suunnassa, kuten on näytetty kuvioissa IA - 3.At the lower end of the tube pile 40 is a downwardly tapered pile shoe 1 of the invention having a large outer diameter D1, in which area of the pile shoe 1 opens the pile tube, and in particular its interior 12, to allow the outlet of said concrete mass B. The pile shoe 1 according to the invention consists of an elongated substantially flat tip portion 3 having a working tip 10 at its lower end and a collar 6 with a maximum diameter D1 substantially greater than the outer diameter D2 of the pile tube. The maximum collar diameter D1 forms the soil M cavity or space T around the pile tube for concrete B. It is generally sought to obtain a predetermined layer thickness of concrete around the pile tube, the layer thickness of which is on the order of half the difference between the maximum pile shoe diameter D1 and the pile tube outer diameter D2. Thus, the desired layer thickness Wb of concrete is obtained by the radial thickness W of the cavity T surrounding the pile tube, obtained by predetermining the maximum diameter D1 of the pile shoe relative to the outer diameter of the pile tube, i.e. W = [D1 - D2] / 2. Typically, a concrete layer with a thickness of at least 5 mm and at most 200 mm, generally at least 15 35 mm and at most 100 mm, and preferably between 30 mm and 50 mm, is desired on the pile tube surface. The nominal thickness Wb of this concrete layer surrounding the steel pile tube and thus the maximum collar diameter D1 which it generates can also be proportioned to the outer diameter D2 of the pile tube by providing a maximum diameter D1 of about 1-4 times or preferably 8-11405 1.5-2.5 times outside the pile tube. It will be appreciated that if the cross sections of the pile tube 2 and the collar 6 have different shapes, as is the case with the embodiment of Figures 5A and 5B and with the embodiment of Figures 6A and 6B, the calculated thickness W and the nominal thickness WB 5 on different sides of the pile. Also, it should be noted that, depending on the nature of the soil M and quality variations such as stratification or inhomogeneity, the actual thickness WB of the concrete layer varies in the longitudinal direction of the pile, i.e. the centerline 31, as shown in Figures IA-3.

10 Keksinnön mukainen kaulus voi olla paalun keskilinjan suunnassa oleellisesti tasapaksu, kuten kuviossa 6A. Edullisesti kuitenkin keksinnön mukaisessa kauluksessa 6 on työkärkeä 10 kohti ainakin osittain kapeneva tai suppeneva ulkopinta 8, jollainen on selvästi esitetty kuvioissa 4A, 5A ja 7. Tämä ulkopinta voi siten olla katkaistun kartion muotoinen tai pyramidin muotoinen tai muun kapenevan muodon mu-15 kainen, jolloin sivulinja kuvioita 4A, 5A, 6A ja 7 vastaavissa paalun keskilinjan 31 kautta kulkevissa pitkittäisleikkauksissa voi olla suora, kupera tai kovera käyrä, por-rasviiva terävin tai pyöristetyin kulmin tai muu viiva. Katkaistun kartion tai pyramidin muoto, joko suorilla tai käyrillä sivulinjoilla tai niiden yhdistelmällä, on kuitenkin keksinnön mukaan edullinen, koska sen avulla putkipaalun 40 paaluputken 2 20 ympärille aikaansaatavaan tilaan tai onteloon T rajautuva maakerros tiivistyy tehokkaammin ja oletettavasti pienemmällä paalua maahan ajavalla voimalla F, kuin jos sivulinja ei muodosta työkärkeä kohti oleellisesti kapenevaa muotoa kaulukseen. Siten uskotaan, että kuvioiden 4A, 5A ja 7 toteutusmuodot ovat edullisempia kuin kuvion 6A toteutusmuoto. Kauluksen poikkileikkausmuoto paalun keskilinjaa 31 25 vastaan kohtisuorassa leikkauksessa voi vaihdella laajoissa rajoissa. Poikkileikkausmuoto voi olla soikio tai pyöreä, kuten kuviossa 4B, suorakaide tai neliö, kuten kuviossa 5B, ulkonevilla haaroilla varustettu, kuten kuviossa 6B tai jokin muu yleensä keskilinjan 31 kautta kulkevan yhden tai useamman pitkittäistason suhteen symmetrinen muoto. Siten paalukengän 6 poikkileikkausmuodon ei ole tarpeen olla 30 yhdenmukainen paaluputken 2 poikkileikkausmuodon kanssa. Kuitenkin paalukengän maksimiläpimitan Dl on joka kohdassa paalukengän kehää täytettävä edellä määritellyt ehdot. Esimerkiksi kuviossa 6B on molempien toisistaan poikkeavien maksimiläpimittojen Dl oltava oleellisesti suurempia kuin paaluputken ulkoläpimit-ta. Erityisesti huomautetaan, että tämä kuvattu kauluksen 6 kapeneva muoto on koko 35 paalukengän 1 suippenevasta päämuodosta erillinen itsenäinen piirre.The collar of the invention may be substantially flat in the direction of the centerline of the pile, as shown in Figure 6A. Preferably, however, the collar 6 of the invention has an outer surface 8 at least partially tapered or tapered toward the working tip 10, such as is clearly shown in Figures 4A, 5A and 7. This outer surface may thus be truncated conical or pyramidal or other tapered 4A, 5A, 6A and 7, the longitudinal cuts corresponding to Figures 4A, 5A, 6A and 7, may have a straight, convex or concave curve, a por-grease with sharp or rounded angles or other line. However, the shape of the truncated cone or pyramid, either with straight or curved side lines or a combination thereof, is advantageous according to the invention because it provides a more efficient and presumably lower pile-to-ground force F than the ground or adjacent to the space 20 the lateral line does not form a substantially tapered shape towards the workpiece towards the collar. Thus, it is believed that the embodiments of Figures 4A, 5A and 7 are more advantageous than the embodiment of Figure 6A. The cross-sectional shape of the collar perpendicular to the pile center line 31 25 can vary within wide limits. The cross-sectional shape may be oval or circular, such as in Fig. 4B, rectangular or square, as in Fig. 5B, with protruding branches, such as in Fig. 6B, or any other symmetrical shape generally with respect to one or more longitudinal planes passing through the centerline 31. Thus, the cross-sectional shape of the pile shoe 6 need not be consistent with the cross-sectional shape of the pile tube 2. However, the maximum diameter D1 of the pile shoe at each point of the pile shoe circumference must satisfy the conditions defined above. For example, in Fig. 6B, the two differing maximum diameters D1 must be substantially larger than the outer diameter of the pile tube. In particular, it is noted that this illustrated tapered shape of the collar 6 is separate from the tapered main shape of the entire 35 pile shoe 1.

Keksinnön erityisen piirteen mukaan kauluksen 6 maksimiläpimittaa Dl vastaavan kohdan R etäisyys LI mainitusta työkäqestä 10 on vähintään viisi kertaa paaluput- 9 111405 ken ulkoläpimitta D2, jolloin kauluksen ja työkärjen 10 välissä on pääasiassa tasapaksu kärkiosa 3. Tämän hetkisen käsityksen mukaan tämä kauluksen 6 alapuolelle ulottuva työkäijen ja kauluksen välinen kärkiosa 3, joka ei ole betonimassan ympäröimä kun putkipaalua 40 ajetaan maaperään, ohjaa koko putkipaalua menemään 5 suoraan tukeutuessaan mm. paalun lyöntien tai täristyksen aikana paalukenkää 1 ja erityisesti kärkiosaa 3 tiiviisti ympäröivään maaperään M. Vielä tehokkaampi ohjaus paaluputkelle 2 ja sen putkiosille 2a, 2b jne saadaan jäljestämällä kauluksen mak-similäpimittaa vastaavan kohdan R ja työkärjen välinen mainittu etäisyys LI, eli kärkiosan pituus, niin pitkäksi, että se on vähintään seitsemän ja edullisesti kymme-10 nen kertaa paaluputken ulkoläpimitta D2. Kauluksen 6 kapenevan tai suippenevan ulkopinnan 8 pituus L3 on enintään 40 % ja tyypillisesti alle 30 % kärkiosan 3 pituudesta Ll. Esimerkinomaisesti etäisyys LI on välillä 30 cm - 1 m, yleensä 0,5 m tai enemmän.According to a particular aspect of the invention, the distance L corresponding to the maximum diameter D1 of the collar 6 from said working curve 10 is at least five times the outer diameter D2 of the pile tube, with a substantially flat tip portion 3 between collar and workpiece 10. and the collar tip portion 3, which is not surrounded by concrete mass when the pipe pile 40 is driven into the ground, directs the entire pipe pile to go directly 5, e.g. even more efficient control of the pile tube 2 and its tube portions 2a, 2b, etc. is obtained by following the maximum distance R of the collar corresponding to the maximum diameter of the collar, i.e. the length of the toe portion p1, i.e. that is at least seven, and preferably ten to ten times, the outer diameter D2 of the pile tube. The length L3 of the tapered or tapered outer surface 8 of the collar 6 is not more than 40% and typically less than 30% of the length L1 of the tip portion 3. By way of example, the distance L1 is between 30 cm and 1 m, usually 0.5 m or more.

15 Kärkiosan 3 poikkileikkausmuoto voi vaihdella laajoissa rajoissa, joten se voi olla pyöreä, soikea, kulmikas, tähtimäinen, uumalla varustettu muoto jne., mutta edullisesti keskilinjan 31 kautta kulkevan yhden tai useamman pitkittäistason suhteen symmetrinen muoto. Kärkiosa 3 voi koostu umpimateriaalia olevasta metallitangosta tai metalliputkesta. Tämä kärkiosa 3 muodostuu esimerkiksi paaluputken 2 osuudes-20 ta 2’, kuten kuviossa 7, tai kaulukseen 6 kiinnitetystä putkikappaleesta 11, kuten kuviossa 6A, tai jäljempänä selostettavan liitososan 4 osuudesta 17, tai kauluksessa 6 olevaan syvennykseen kiinnitetystä tankokappaleesta 18. Kuvion 7 toteutusmuodossa siten itse varsinainen paaluputki 2 menee kauluksessa olevan reiän 16 läpi ja kauluksen alapuolelle ulottuva osuus 2’ muodostaa kärkiosan. Kaulus on kiinnitetty 25 tässä tapauksessa paaluputkeen ja siten myös kärkiosaan liitoselimet 15a muodos-r tavilla hitseillä. Kaulus voidaan tietenkin kiinnittää myös kauluksen ja paaluputken läpi menevillä niiteillä, ruuveilla tai pulteilla tai muilla kiinnityskeinoilla. Kuvion 6A toteutusmuodossa putkikappale 11 on työnnetty kauluksesta 6 alaspäin ulkonevan tapin 33 päälle ja tarvittaessa hitsattu kiinni kaulukseen liitoselimet 15a muo-30 dostavilla hitseillä. Kuvion 5A toteutusmuodossa on tankokappale 18 työnnettynä kauluksen syvennykseen 34 ja tarvittaessa hitsattu kiinni kaulukseen liitoselimet 15a muodostavilla hitseillä. Mikäli putkikappale on riittävän tiukka tapin 33 päällä tai tankokappale riittävän tiukka syvennyksessä 34 ei hitsausta tarvita. Edullisesti kärkiosan ulkoläpimitta D3 on enintään yhtä suuri kuin paaluputken ulkoläpimitta D2, 35 mutta joissain tilanteissa voidaan käyttää paksumpaakin kärkiosaa 3, jonka ulkolä pimitta D3 kuitenkin on oleellisesti pienempi kuin kauluksen maksimiläpimitta Dl. Normaalisti kärkiosan ulkoläpimitta D3 on siis pienempi kuin paaluputken läpimitta ja kärkiosan 3 pääasiallinen ulkoläpimitta vaihtelee pituudellaan enintään 30% i 10 111405 kärkiosan ja kauluksen läpimittojen erotuksesta [D1-D3], mutta yleensä enintään 10 % tästä erotuksesta. Pääasiallinen läpimitta otetaan muodosta, jonka antaa yhdistelmä kärkiosaa niistä kohdista, jotka muodostavat kärkiosan poikkileikkauksen kehästä yli puolet. Kärkiosaa on pidettävä oleellisesti tasapaksuna, vaikka siinä olisi-5 kin keskilinjan 31 suuntaisia tukilaippoja 35, kuten katkoviivoilla on esitetty kuviossa 6A, tai vastaavia ja/tai kärkikappaleessa 9 hieman levennetty osuus 36, kuten kuviossa 6A.The cross-sectional shape of the tip portion 3 may vary over a wide range, so that it may be circular, oval, angular, star-shaped, with web, etc., but preferably symmetrical with respect to one or more longitudinal planes passing through the centerline 31. The tip portion 3 may consist of a metal bar or metal tube of solid material. This tip portion 3 consists, for example, of a portion 20 'of the pile tube 2' as shown in FIG. 7, or a tube piece 11 attached to the collar 6, such as FIG. 6A, or a portion 17 of the connecting portion 4 described below. the actual pile tube 2 itself passes through the hole 16 in the collar and the portion 2 'extending below the collar forms the tip portion. In this case, the collar is secured to the pile tube and thus also to the tip portion by welds forming the connecting members 15a. Of course, the collar can also be secured with rivets, screws or bolts or other means of fastening through the collar and the pile tube. In the embodiment of Fig. 6A, the tubular member 11 is pushed downwardly from the collar 6 onto the protruding pin 33 and, if necessary, welded to the collar by welds forming the connecting members 15a. In the embodiment of Figure 5A, the rod piece 18 is inserted into the collar recess 34 and, if necessary, welded to the collar by welds forming the connecting members 15a. If the tube piece is sufficiently tight on the pin 33 or the rod piece is sufficiently tight in the recess 34, no welding is required. Preferably, the outer diameter D3 of the tip portion is at most equal to the outer diameter D2 of the pile tube, but in some cases a thicker tip portion 3 may be used, however, the outer diameter D3 of which is substantially smaller than the maximum collar diameter D1. Normally, the outer diameter D3 of the tip portion is smaller than the diameter of the pile tube, and the major outer diameter of the tip portion 3 varies by up to 30% of the difference between the diameter of the tip portion and collar [D1-D3], but generally up to 10%. The main diameter is taken from the shape given by the combination of the tip portion to the points that make up more than half of the circumference of the tip portion. The tip portion must be considered substantially flat, even if it has support flanges 35 parallel to the centerline 31, as shown by dotted lines in Figure 6A, or the like and / or a slightly widened portion 36 in the tip piece 9, as in Figure 6A.

Lisäksi keksinnön mukaan paalukengässä 1 on virtausreikiä 7, jotka sijaitsevat paa-10 luputkea tai sen jatketta ympäröivän kauluksen 6 alimman ylöspäin vapaan pohjan 24 yläpuolella ja menevät mainitun paalukengän 1 ja/tai paaluputken 2 ja/tai paalu-putken jatkeen kehäpinnan 13, 22, 23 läpi, betonimassan B ulosvirtausta varten. Ylöspäin vapaalla pohjalla tarkoitetaan paalun keskilinjaa vastaan poikittaista pintaa, joka on paaluputken 2 ulkoläpimitan D2 ulkopuolella ja jonka pinta-alaa paalu-15 putken poikkipinta ei rajoita. Tällöin virtausreiät 7 aukeavat paaluputken 2 ulkopuolelle säteittäisissä suunnissa. Kauluksessa voi olla pääpiirteittäin tasainen ylöspäin vapaa pohja 24, kuten kuviossa 6A, mutta edullisesti kauluksessa 6 on ylös nostettu ulkoreuna 25, joka muodostaa paaluputkea 2 tai sen jatketta, kuten liitososaa 4, ympäröivän ylöspäin avoimen syvennyksen 5. Tässä tapauksessa ylöspäin vapaa pohja 20 24 muodostuu syvennyksen 5 pohjasta, kuten kuvioissa 4A, 5A ja 7, jolloin siis pohja 24 yhdistää mainitun kehäpinnan 13, 22, 23 ja kauluksen tai sen ylös nostetun ulkoreunan 25 virtausreikien 7 alapuolella. Kuvioiden toteutusmuodossa pohja 24 on tasomainen, mutta voi olla muunkin muotoinen pinta. Säteettäiset virtausreiät voivat olla pyöreitä tai pitkänomaisia, kuten kuviosta näkyy, ja ne on järjestetty 25 yleensä tasavälisesti mainitulle kehäpinnalle. Virtausreikiä on vähintään kaksi, mutta useimmiten kolme - viisi kappaletta likimain samalla korkeudella. Jos virtausreikiä 7 sijoitetaan useammalle korkeudelle reikien välisten kannasten leventämiseksi, kuten kuvioissa 5A ja 7, voi reikien kokonaismäärä olla suurempi. Virtausreikien yhteenlaskettu poikkipinta-ala on pienempi kuin paaluputken sisätilan 12 30 poikkipinta-ala, jolloin se voi olla alle 90 %, alle 70 %, alle 50 % tai vieläpä suuruusluokkaa 30 % paaluputken sisätilan 12 poikkipinta-alasta. Reikien jokin halkaisija voi esimerkiksi olla 10 mm:stä 100 mm.iin. Kauluksen syvennyksen 5 sisäpuolinen ulkoläpimitta D5 on oleellisesti suurempi kuin seuraavaksi käsiteltävän liitos-osan yläläpimitta D4 tai paaluputken ulkoläpimitta D2, jotta kauluksen ylös 35 nostetun reunan 25 paksuus olisi pieni. Edullisesti virtausreiät 7 sijaitsevat ainakin osittain kauluksen ulkoreunan 25 tasalla tai syvennyksen 5 korkeuden Hl mitalla. Syvennyksen korkeus Hl tässä tarkoitta pohjan 24 ja ylös nostetun reunan 25 välimatkaa. Tällä muotoilulla, jolla betonivirtaukseen V saadaan joko vain pienehkö 11 111405 suunnanmuutos tai loivasti kaareutuva suunnanmuutos, uskotaan tehostettavan juoksevan betonimassan B virtausta paaluputken sisätilasta 12 kauluksen tekemään maaperän M onteloon T paalun maahan lyöntien tai maahan täristyksen aikana. Betoni-massa eli sementtilaasti siis siirtyy ainakin virtausreikien 7 kohdalla ja käsityksen 5 mukaan myös niiden ulkopuolella onteloon T pääosin suunnassa keskeltä ulospäin. Kärkiosa 3, mahdollinen kärkikappale 9 ja kauluksen 6 ulkopinta 8 alhaalta ulkoreunaan 25 saakka tai vastaava muu ulkopinta ovat umpinaisia eli niissä ei ole betonimassaa varten reikiä, vaan laasti B virtaa vain kauluksen yläpuolitse.In addition, according to the invention, the pile shoe 1 has flow holes 7 located above the lowest upwardly free base 24 of the collar 6 surrounding the paa-tube or extension thereof and passing through the peripheral surface 13, 22, 23 of said pile shoe 1 and / or pile tube 2 through, for outflow of concrete mass B. An upwardly free base means a transverse surface facing the center line of the pile, which is outside the outer diameter D2 of the pile tube 2 and whose area is not limited by the cross-section of the pile tube. The flow holes 7 then open outside the pile tube 2 in radial directions. The collar may have a substantially flat upwardly free bottom 24 as shown in Figure 6A, but preferably the collar 6 has an raised upward edge 25 which forms an upwardly open recess 5 surrounding the pile tube 2 or its extension, such as the connecting portion 4. 4A, 5A and 7, wherein bottom 24 thus connects said peripheral surface 13, 22, 23 and the collar or its raised outer edge 25 below the flow holes 7. In the embodiment of the figures, the base 24 is planar but may also have a surface of other shapes. The radial flow holes may be circular or elongated as shown in the figure and are arranged generally equidistant on said circumferential surface. There are at least two, but most often three to five flow holes at approximately the same height. If the flow holes 7 are positioned at more than one height to widen the between-hole bases, as in Figs. 5A and 7, the total number of holes may be greater. The total cross-sectional area of the flow holes is smaller than the cross-sectional area of the inner pile tube 12, whereby it may be less than 90%, less than 70%, less than 50%, or even of the order of 30% of the pile tube interior 12. For example, any of the holes may have a diameter from 10 mm to 100 mm. The inside diameter D5 of the collar recess 5 is substantially larger than the top diameter D4 of the next fitting or the outside diameter D2 of the pile tube, so that the raised edge 25 of the collar 35 is small. Preferably, the flow holes 7 are at least partially located flush with the outer edge 25 of the collar or with the height H1 of the recess 5. The height H1 of the recess here refers to the distance between the base 24 and the raised edge 25. This design, which provides only a slight 11 111405 change of direction or a slight curvature change in the concrete flow V, is believed to enhance the flow of running concrete mass B from the pile tube interior 12 into the collar M cavity T during pile-to-pile or ground vibration. Thus, the concrete mass, i.e. cement mortar, is transferred at least at the flow holes 7 and, according to the notion 5, also outside them into the cavity T, mainly in the direction from the center to the outside. The tip portion 3, the possible tip piece 9 and the outer surface 8 of the collar 6 from the bottom to the outer edge 25 or the like outer surface are solid, i.e. there are no holes for the concrete mass, but mortar B flows only above the collar.

10 Paaluputken mainittu jatke on liitososa 4, joka ulottuu kauluksen yläpuolelta sen alapuolelle ja jonka avulla kaulus 6 yhdistetään paaluputkeen 2, kuten on osoitettu kuviossa 4A. Tätä varten liitososan ylemmän osuuden ulkopuolinen yläläpimitta D4 on suurempi kuin ulkopuolinen alaläpimitta D3. Läpimittojen erolla on liitososaan muodostettu alaspäin osoittava vastepinta 14. Kaulukseen taas on muodostettu lii-15 tososan läpimenoa varten läpimenevä reikä 16. Tällöin liitososan, jonka yläläpimitta D4 on suurempi kuin kauluksen reiän 16 läpimitta D6, vastepinta 14 tukeutuu kauluksen pohjaan 15. Tässä tapauksessa liitososa 4 käsittää yläosassaan sisäpuolisen syvennyksen 26a paaluputken 2 alapään vastaanottamiseksi sekä kanavan 27, joka ulottuu paaluputken sisätilasta 12 vähintään virtausreikien 7 kohdalle, jonka kana-20 van 27 virtauspoikkipinta edullisesti vastaa sisätilan 12 virtauspoikkipintaa. Liitos-osa 4 koostuu joko samasta kappaleesta kuin kärkiosa 3, kuten kuviossa 4A on esitetty, tai vaihtoehtoisesti toisiinsa kiinnitetystä kärkiosasta ja vastekappaleesta. Liitososaan voidaan vaihtoehtoisesti järjestää paaluputken kiinnitystä varten ulkopuolinen syvennys tai uloke vastaavalla tavalla kuin kuviossa 5A on järjestetty kauluksen 25 6 avulla.Said extension of the pile tube is a connecting part 4 which extends from above the collar to below it and which connects the collar 6 to the pile tube 2 as shown in Fig. 4A. For this purpose, the upper upper portion D4 of the upper portion of the joint portion is larger than the outer lower diameter D3. The difference in diameters has a downwardly facing stop surface 14 formed on the joint portion. A collar 15 is provided with a through hole 16 for the passage of the upper portion 16. In this case, the stop surface 14 of the joint portion 16 having a larger diameter D4 than the D6 collar at its upper end comprises an internal recess 26a for receiving the lower end of the pile tube 2 and a channel 27 extending from the inner space 12 of the pile tube at least to the flow holes 7 whose flow section of the channel 20 preferably corresponds to the flow cross section of the inner space 12. The connecting part 4 consists of either the same piece as the tip part 3 as shown in Fig. 4A, or alternatively the tip part and the stop piece attached to each other. Alternatively, the connector may be provided with an external recess or projection for securing the pile tube in a manner similar to that provided in Fig. 5A by the collar 25 6.

Paaluputki 2 voidaan alapäästään kiinnittää joko edellä kuvatulla tavalla liitososan 4 avulla kaulukseen 6 ja kärkiosaan 3 tai suoraan kaulukseen. Paaluputken kiinnitystä varten kaulus käsittää esimerkiksi kuvion 7 toteutusmuodossa läpimenevän reiän 16, 30 jonka läpimitta D6 vastaa kärkiosan ulkoläpimittaa D3, joka tässä tilanteessa on yhtä suuri kuin paaluputken ulkoläpimitta D2, paaluputken läpimenoa varten. Kuvion 5A toteutusmuodossa kauluksessa 6 on ylöspäin osoittavan ulokkeen 19, jonka ulkohal-kaisija D8 on sovitettu vastaanottamaan paaluputken 2 pää. Tämän ulokkeen 19 ja syvennyksen 5 pohjan 24 ylimenokohtaan voidaan lisäksi muotoilla kehämäinen sy-35 vennys 26b varmistamaan paaluputken pään kiinnipysyminen esimerkiksi taivutus-voimia vastaan, vastaavalla tavalla kuin on kuvattu hakijan aikaisemmassa patentissa FI-81415. Kuvion 6A toteutusmuodossa kaulukseen on muodostettu ylöspäin osoittava uloke 19, jossa on kehämäinen syvennys 26a, jonka sisähalkaisija D7 on „ 111405 1. L* sovitettu vastaanottamaan paaluputken 2 pää. Tässäkin tapauksessa kauluksessa 6 on kanavan 27, joka ulottuu paaluputken sisätilasta 12 vähintään virtausreikien 7 kohdalle.At its lower end, the pile tube 2 can be attached to the collar 6 and the tip portion 3, or directly to the collar, by means of the connecting part 4 as described above. For example, in the embodiment of Fig. 7, the collar comprises a through hole 16, 30 having a diameter D6 corresponding to the outer diameter D3 of the tip portion, which in this case is equal to the outer diameter D2 of the pile tube for the pile tube through. In the embodiment of Fig. 5A, the collar 6 has an upwardly extending projection 19 having an outer diameter D8 arranged to receive the end of the pile tube 2. Further, at the transition point of this projection 19 and the bottom 24 of the recess 5, a circumferential groove 26b may be formed to secure the end of the pile tube, for example against bending forces, in a manner similar to that described in the applicant's previous patent FI-81415. In the embodiment of Figure 6A, an upwardly extending projection 19 is formed in the collar with a circumferential recess 26a having an internal diameter D7 of "111405 1. L * adapted to receive the end of the pile tube 2. Again, the collar 6 has a channel 27 extending from the inner space 12 of the pile tube to at least the flow holes 7.

5 Edellä kuvattu kaulus 6 tai liitososa 4 lisäksi käsittävät myös joko ensimmäiset liitoselimet 15a, kuten hitsit kauluksen tai liitososan ja paaluputken välillä, tai toiset liitoselimet 15b, kuten kauluksen tai liitososan ja paaluputken läpi menevät ruuvit, niitit tai pultit, tai kolmannet liitoselimet 15c, kuten aikaisemmassa patentissa FI-81415 kuvattu puristusliitos tai muun tyyppinen puristusliitos tai poikittainen rihlaus 10 paaluputken 2 ja kauluksen 6 tai liitososan 4 välistä tartuntaa varten. Mainitun patentin mukaista puristusliitosta voidaan soveltaa käyttämällä paaluputkea varten koi-raspuolista vastinosaa, kuten kyseisessä julkaisussa, tai käänteistä rakennetta, jossa paaluputken 2 päätä varten on naaraspuolinen vastinosa. Paaluputken 2 pään liittämiseksi kaulukseen 6 tai liitososaan 4 voidaan tietenkin käyttää kuviosta 8A ilme-15 nevää kierreliitosta sovellettuna tähän kohtaan kauluksen tai liitososan ja paaluputken välillä.The collar 6 or connector 4 described above also comprises either first connecting members 15a, such as welds between the collar or connecting member and the pile tube, or second connecting members 15b, such as screws, rivets or bolts passing through the collar or connecting member and pile tube, or a press joint or other type of press joint or transverse rib 10 described in prior patent FI-81415 for engagement between a pile tube 2 and a collar 6 or connector 4. The compression fitting according to said patent can be applied using a male counterpart for the pile tube as in the present publication, or an inverted structure having a female counterpart for the end of the pile tube 2. Of course, for the connection of the end of the pile tube 2 to the collar 6 or to the connecting part 4, a threaded connection shown in Fig. 8A may be used applied at this point between the collar or connecting part and the pile tube.

Paaluputki 2 koostuu, kuten edellä jo on mainittu, useammista putkiosista 2a, 2b, 2c jne. Putkiosat on yhdistetty toisiinsa esimerkiksi liitoskappaleilla 21 tai liitoksilla 20 20. Liitoskappaleet 21 voivat muodostua kuvioiden 8A ja 8B mukaisista holkeista, joiden sisään paaluputken putkiosat työntyvät. Tällainen liitos voidaan tarvittaessa varmentaa ruuveilla tai niiteillä 38 liitoskappaleen ja putkiosan välissä, kuten kuviossa 8A, tai holkkimaisen liitoskappaleen ja putkiosien välisellä hitsillä tai vastaavalla puristusliitoksella kuin hakijan aikaisemmassa patentissa FI-81415 paitsi, että 25 käytetään naaraspuolista vastinosaa eli holkkimaista liitoskappaletta, kuten kuviossa 8B, tai muun tyyppisellä puristusliitoksella tai putkiosissa ja liitoskappaleessa olevilla poikittaisilla rihlauksilla. Vaihtoehtoisesti käytettävä liitos 21 taas koostuu putki-osien 2a ja 2b, 2b ja 2c jne päiden välisestä hitsistä, kuten kuviossa 8C. On sinänsä mahdollista käyttää myös koiraspuoleista liitoskappaletta, joka menee putkiosien si-30 sään, mutta sillä on pienenä haittana se, että paaluputken sisätilan 12 poikkipinta-ala pienenee niiden kohdalla.The pile pipe 2 consists, as already mentioned, of a plurality of pipe sections 2a, 2b, 2c, etc. The pipe sections are interconnected by means of, for example, connecting pieces 21 or connections 20 20. The connecting pieces 21 may consist of sleeves according to Figures 8A and 8B. Such a joint may, if necessary, be secured by screws or rivets between the connector 38 and the pipe member as in Figure 8A, or by a weld or similar compression joint between the hollow joint and the pipe members as in the applicant's prior patent FI-81415 or other types of compression fitting or transverse ribs on pipe sections and fittings. Alternatively, the joint 21 used consists of a weld between the ends of the pipe sections 2a and 2b, 2b and 2c, etc., as in Figure 8C. As such, it is also possible to use a male connecting piece which goes inside the pipe sections, but has the slight disadvantage of reducing the cross-sectional area of the inner space 12 of the pile tube.

Seuraavaksi selostetaan keksinnön mukaista menetelmää putkipaalun pakottamiseksi maaperään M ja ympäröimiseksi betonilla. Paalutuspaikalla tai vaihtoehtoisesti 35 valmistavalla tehtaalla kootaan aluksi keksinnön mukainen paalukenkä mahdollisista osistaan tarvittavilla toimenpiteillä ja kiinnitetään ensimmäiseksi paaluputken 2 maaperään ajettavaan alapäähän paalukenkä 1, jolloin saadaan käyttökelpoinen putkipaalu 40. Tämän jälkeen asetetaan putkipaalu haluttuun kohtaan ja asentoon 13 111405 maaperän M ja sen pinnan 32 suhteen ja ajetaan sitten jaksoittaisella eli pulssimaisella tai muulla vastaavalla voimalla F, jolla on jokin frekvenssi, putkipaalua maaperään M kuvion IA mukaisesti. Laitetta, jolla voima F joko iskuina tai tärinänä saadaan aikaan ei ole kuvioissa esitetty, koska se voi olla mitä tahansa tarkoitukseen 5 sopivaa tyyppiä. Kun putkipaalu on uponnut jonkin ennalta suunnitellun matkan maaperään täytetään paaluputken sisätila 12 juoksevassa muodossa olevalla laastilla eli betonimassalla B, joka koostuu hydraulisesti kovettuvasta sideaineesta, kiviaineksesta täyteaineena sekä vedestä ja mahdollisista lisäaineista. Hydraulisesti kovettuvana sideaineena on tavalHsimmin sementti, mutta myös masuunikuonaa, muuta 10 vastaavaa sideainetta tai niiden yhdistelmää voidaan käyttää. Tässä riittää paaluputken 2 sisätilan 12 täyttäminen ilman painetta, esimerkiksi yksinkertaisesti kaatamalla, kuten kuvioista IB, ID ja 1G näkyy, eikä ole tarvetta yrittää ajaa betonimassaa B ulos virtausrei’ista 7. Seuraavaksi ajetaan mainitulla jaksoittaisella eli pulssimaisella tms. voimalla F putkipaalua syvemmälle maaperään M kuvion 1C mukaisesti, jol-15 loin betonimassa virtaa kuvioon merkittyjen virtausten suunnassa betonimassan juoksevuuden lisääntyessä virtausrei’istä 7 paaluputken 2 sisätilasta sen ympärille ja kenties jossain määrin ylöspäin paalukengän 1 tekemään onteloon T maaperässä. Tämän hetkisen käsityksen mukaan jaksoittainen tai pulssimainen voima F lisää betonimassan eli laastin juoksevuutta tai notkeutta eli betonimassa reagoi tällaiseen 20 käsittelyyn samaan tapaan kuin tiksotrooppiset materiaalit. Tätä virtausta sisätilasta 12 onteloon T ilmeisesti tehostaa paalun alaspäin etenevän liikkeen aikaansaama alipaine onteloon T, samoin kuin se, että betonimassan B virtaukseen V paaluputken sisätilasta onteloon T tarvitaan kokonaan tai osittain vain suuruusluokkaa 90° suunnan muutos, kuten kuvioissa 5A, 6A ja 7, ja/tai loiva säteellä, joka on suuruusluok-25 kaa [D1-D2J/2, tapahtuvalla suunnan muutoksella, kuten kuvioissa 4A, 5A ja 7. Seuraavassa vaiheessa lisätään paaluputken sisätilaan 12 mainittua laastia betoni-massaa B ja jatketaan vuorotellen putkipaalun ajamista edelleen maaperään M jaksoittaisella voimalla ja mainitun betonimassan B lisäämistä paaluputken sisätilaan 12 kuvioiden ID ja IE mukaisesti. Näiden vuorottelevien vaiheiden määrä voi tie-30 tenkin vaihdella.Next, the method according to the invention for forcing a pipe pile into soil M and encapsulating it with concrete will be described. At the piling site or, alternatively, at the manufacturing plant 35, the pile shoe according to the invention is first assembled from any possible parts and first attached to the bottom end of the pile tube 2 to the soil, to provide a usable tube pile 40. The tube pile is then positioned is then driven by a periodic or pulsed or similar force F having a frequency to the pipe pile into the ground M as shown in Figure IA. The device by which the force F, either by impact or vibration, is exerted is not shown in the figures, since it can be of any type suitable for the purpose. After the pipe pile has sunk into the soil for a predetermined distance, the interior of the pile tube 12 is filled with a flowable mortar, i.e. concrete mass B, which consists of a hydraulically curing binder, aggregate as filler and water and any additives. The hydraulically curable binder is usually cement, but blast furnace slag, other 10 or equivalent binders may also be used. Here, it is sufficient to fill the inner space 12 of the pile tube 2 without pressure, for example by simply pouring, as shown in Figs. IB, ID and 1G, without the need to try to push concrete mass B out of the flow holes 7. The following periodic or pulse-like force F is driven 1C, the jet-15 created a concrete mass flowing in the direction of the flows shown in the figure as the fluidity of the concrete mass increases from the flow holes 7 from the interior of the pile tube 2 to the cavity T formed by the pile shoe 1. According to the current understanding, the cyclic or pulsed force F increases the fluidity or pliability of the concrete mass, i.e. the mortar, i.e. the concrete mass reacts to such treatment in the same way as thixotropic materials. This flow from the inner space 12 to the cavity T is apparently enhanced by the downward pressure created by the downward movement of the pile into the cavity T, as well as the flow of concrete mass B from the internal pile tube to the cavity T requires only a 90 degree change of direction. / or gently changing direction with a radius of magnitude 25 [D1-D2J / 2], as in Figures 4A, 5A and 7. In the next step, concrete mortar B is added to the pile tube interior 12 and continued to alternately drive the tube pile to ground M intermittent force and adding said concrete mass B to the pile tube interior 12 as shown in Figs. ID and IE. The number of these alternating phases may, of course, vary on the road-30.

Kun paaluputken ensimmäinen putkiosa 2a on ajettu maaperään ainakin osittain, eli yleensä pääosin, jatketaan ensimmäistä putkiosaa 2a toisella putkiosalla 2b käyttäen aikaisemmin kuvattuja liitoksia 20 tai liitoskappaleita 21 jatkoksen synnyttämiseksi 35 kuvion 1F mukaisesti. Sen jälkeen jatketaan edelleen paaluputken 2 jatkamista uusilla putkiosilla 2c, 2d, 2e jne. sekä vuorotellen mainitun betonimassan B ainakin osittaista lisäämistä paaluputken sisätilaan 12 ja putkipaalun ajamista syvemmälle maaperään jaksoittaisella voimalla F, kuten on näytetty kuvioissa 1 G ja vastaavasti 14 111405 1H. Näitä vaiheita jatketaan kunnes putkipaalun kärkiosa 3 tulee tarkoitetulle syvyydelle SI maaperään M. Menetelmän ensimmäisen toteutusmuodon mukaan jatketaan juoksevan betonimassan lisäystä putkipaalun 40 koko maahan ajamisen ajan ja tarvittaessa suoritetaan vielä paaluputken lopputäyttö, minkä jälkeen annetaan 5 betonimassan B kovettua sekä paaluputken ympärillä että paaluputken 2 sisätilassa 12. Tulokseksi saadaan kuvion 2 mukainen valmis betoniputkipaalu. Menetelmän toisen toteutusmuodon mukaan ajetaan putkipaalua 40 aluksi jaksoittaisella voimalla F maaperään M ilman betonimassan B syöttämistä paaluputken sisätilaan kunnes putkipaalu 40 on tietyllä syvyydellä S2, jonka jälkeen putkipaalun sisätilaan 12 10 syötetään erä, kuten yksi, betonia B ja toteutetaan lyhyt putkipaalun ajaminen voimalla F. Tämä lyhyt maahan vieminen vastaa esimerkiksi sitä ontelon T pituutta, jonka paaluputkessa olevan betonimassan määrä pystyy täyttämään. Tarvittaessa voidaan toteuttaa myös kaksi tai useampaa putkipaalun täyttöä ja kaksi tai useampaa ajovaihetta voimalla F, mikä myös tarkoittaa em. lyhyttä putkipaalun maahan vie-15 mistä, joskin vastaavasti pitempää ontelon T pituutta. Sitten täytetään betonimassasta onteloon näin saadun sulun yläpinnan ja maanpinnan välinen osuus putkipaalun ympärillä kiviaineksella G, kuten hiekalla, soralla tai vastaavalla. Seuraavaksi jatketaan vuorotellen paaluputken sisätilan 12 täyttämistä betonilla B ja putkipaalun ajamista edelleen maaperään M voimalla F, aivan kuten edellä on selostettu. Näitä 20 vaiheita jatketaan kunnes putkipaalun kärkiosa 3 tulee tarkoitetulle syvyydelle SI maaperään M. Viimeiseksi täytetään putkipaalun 12 sisätilan loppuosuus betonilla B. Lopuksi annetaan betonimassan B kovettua sekä paaluputken ympärillä että paaluputken 2 sisätilassa 12, jolloin saadaan kuvion 3 mukainen valmis betoniputkipaalu.After the first tube portion 2a of the pile tube has been run into the soil at least partially, i.e. generally substantially, the first tube portion 2a is extended by a second tube portion 2b using the previously described joints 20 or joints 21 to provide a joint 35 as shown in Figure 1F. Thereafter, the pile tube 2 is further extended with new pipe sections 2c, 2d, 2e, etc., and alternately at least partially injecting said concrete mass B into the pile tube interior 12 and driving the pile deeper into the ground with a periodic force F as shown in Figures 1G and 1411405, respectively. These steps are continued until the tip 3 of the pipe pile reaches the indicated depth S1 in the soil M. According to a first embodiment of the method, the continuous concrete mass is continued while the pipe pile 40 is driven to the ground and further filled with pile tube 12 and 2 of the pile The result is a finished concrete pipe pile as shown in Figure 2. According to another embodiment of the method, the pipe pile 40 is first driven by a periodic force F into the soil M without feeding concrete mass B into the pile tube interior until the pipe pile 40 is at a certain depth S2, followed by a batch of concrete B and a for example, the short introduction corresponds to the length of the cavity T, which can be filled by the amount of concrete mass in the pile tube. If necessary, two or more filling of the tubular pile and two or more driving steps by force F may also be carried out, which also means the aforementioned short introduction of the tubular pile into the ground, albeit correspondingly longer cavity T. The part of the concrete mass between the top surface of the seal thus obtained and the ground surface is then filled with a rock material G, such as sand, gravel or the like, around the pipe pile. Next, the filling of the pile tube interior 12 with concrete B is continued alternately and the tube pile is further driven into the ground M by force F, just as described above. These 20 steps are continued until the tip 3 of the pipe pile reaches the indicated depth S1 in the soil M. Finally, the remainder of the inner space of the pipe pile 12 is filled with concrete B. Finally the concrete mass B is cured both around the pile pipe and inside 12 of the pile pipe 2.

25 :25:

Betonimassaa siis syötetään paaluputken sisätilaan ilman oleellista ylipainetta ja mainittu jaksoittainen tai pulssimainen tms. voima F synnytetään iskuilla ja/tai täris-tyksellä ja sen maksimi on suuruudeltaan sellainen, että paaluputken sisätilassa ilmenee painesysäys, joka tämän hetkisen käsityksen mukaan on vähintään 10 bar ja 30 edullisesti vähintään 15 bar ja jonka kestoaika on enintään 50 ms, yleensä välillä 0,1 ms - 15 ms tyypillisesti välillä 0,1 ms - 10 ms ja edullisesti mahdollisimman lyhyt, kuten alle 5 ms. Jaksoittainen voima siten synnyttää laastia eli betonimassaa injektoivan lyhytkestoisen painesysäyksen, jonka suuruudeksi on koeasennuksessa mitattu olevan alueella 20-50 bar tai sen lähellä. Tehtyjen havaintojen mukaan näyttää 35 siltä, että ontelossa T olevan betonimassan B pinnankorkeus ei ainakaan oleellisesti nouse paalutuksen aikana, vaan pysyy pääpiirteittäin samalla korkeudella niissä vaihtelurajoissa, jotka laastin eli betonimassan lisäyksen ja putkipaalun maahan ajamisen vuorottelu aiheuttaa.The concrete mass is thus fed into the pile tube interior without substantial overpressure and said periodic or pulsed or similar force F is produced by shocks and / or vibrations and has a maximum such that the pile tube interior exhibits a pressure boost of at least 10 bar and at least 15 bar and having a duration of up to 50 ms, usually between 0.1 ms and 15 ms, typically between 0.1 ms and 10 ms, and preferably as short as possible, such as less than 5 ms. The intermittent force thus produces a short-term pressure boost injecting mortar, or concrete mass, measured at or near 20-50 bar during the test installation. According to the observations made 35, it appears that the surface height of the concrete mass B in the cavity T does not at least substantially increase during piling, but stays roughly at the same level within the range of variation caused by alternating mortar or concrete piling.

Claims (15)

15 11140515 111405 1. Betonilla ympäröitävä putkipaalu, joka käsittää: maaperään asetettavan metallisen paaluputken (2); sen yläpäässä aukon/aukkoja (29) juoksevan betonimassan 5 syöttämiseksi paaluputken sisätilaan (12); ja sen alapäässä paalukengän (1), jossa on pitkänomainen pääasiassa tasapaksu kärkiosa (3) sekä yläosassa kaulus (6), jonka läpimitta (Dl) on suurempi kuin paaluputken läpimitta (D2), ja jonka paalukengän alueella on virtausreikiä (7) mainitun betonimassan (B) ulostulon mahdollistamiseksi, tunnettu siitä, että paalukengässä (1) lisäksi: 10. kauluksen (6) maksimiläpimitta (Dl) on oleellisesti suurempi kuin paaluputken ul- koläpimitta (D2) ja kauluksen tätä maksimiläpimittaa vastaavan kohdan (R) etäisyys (LI) kärkiosan (3) työkärjestä (10) on vähintään seitsemän kertaa paaluputken ulko-läpimitta (D2); - kaulus (6) käsittää työkärkeä kohti ainakin osittain kapenevan ulkopinnan (8); ja 15 - kauluksessa (6) on ylös nostettu ulkoreuna (25) muodostaen paaluputkea (2) tai sen jatketta ympäröivän ylöspäin avoimen syvennyksen (5).A pipe pile surrounded by concrete, comprising: a metal pile pipe (2) to be placed in the ground; at its upper end, an aperture (s) (29) for feeding the fluid concrete mass 5 into the pile tube interior (12); and at its lower end a pile shoe (1) having an elongated substantially flat tip portion (3) and a collar (6) at its upper end having a diameter (D1) greater than the pile tube diameter (D2) and having pile shoe region with flow holes (7) B) to allow an outlet, characterized in that in the pile shoe (1), in addition: 10. the maximum diameter (D1) of the collar (6) is substantially larger than the outer diameter (D2) of the pile tube and the distance (L1) (3) the working tip (10) is at least seven times the outer diameter (D2) of the pile tube; - the collar (6) comprises at least a partially tapered outer surface (8) towards the workpiece; and 15 - the outer collar (6) is raised upwardly to form an upwardly opening recess (5) surrounding the pile tube (2) or its extension. 2. Patenttivaatimuksen 1 mukainen betonilla ympäröitävä putkipaalu, tunnettu siitä, että virtausreiät (7) sijaitsevat paaluputkea tai sen jatketta ympäröivän kauluk- 20 sen (6) alimman ylöspäin vapaan pohjan (24) yläpuolella ja menevät mainitun paalukengän ja/tai paaluputken ja/tai paaluputken jatkeen kehäpinnan (13, 22, 23) läpi betonimassan (B) ulosvirtausta varten paalua maaperään pakotettaessa; ja että virtausreiät (7) aukeavat paaluputken (2) ulkopuolelle säteittäisissä suunnissa.Concrete pipe pipe pile according to claim 1, characterized in that the flow holes (7) are located above the lowest upwardly free base (24) of the neck (6) surrounding the pile pipe or its extension and pass through said pile shoe and / or pile pipe and / or pile pipe. passing through the circumferential surface (13, 22, 23) of the extension for outflow of concrete mass (B) when the pile is forced into the ground; and that the flow holes (7) open outside the pile tube (2) in radial directions. 3. Patenttivaatimuksen 1 tai 2 mukainen betonilla ympäröitävä putkipaalu, tun nettu siitä, että paaluputken mainittu jatke on liitososa (4), joka ulottuu kauluksen yläpuolelta sen alapuolelle ja jonka yläläpimitta (D4) on suurempi kuin alaläpimitta mA concrete pipe pile according to claim 1 or 2, characterized in that said extension of the pile pipe is a connecting part (4) which extends above the collar and below it and whose upper diameter (D4) is greater than the lower diameter m. 4. Patenttivaatimuksen 1 tai 3 mukainen betonilla ympäröitävä putkipaalu, tun nettu siitä, että kauluksen syvennyksen (5) ulkoläpimitta (D5) on oleellisesti suurempi kuin mainitun liitososan yläläpimitta (D4) tai paaluputken ulkoläpimitta (D2); ja että virtausreiät (7) sijaitsevat ainakin osittain kauluksen ulkoreunan (25) tasalla tai syvennyksen (5) korkeuden (Hl) mitalla.Concrete-encapsulated pipe pile according to claim 1 or 3, characterized in that the outer diameter (D5) of the collar recess (5) is substantially larger than the upper diameter (D4) of said coupling part or the outer diameter (D2) of the pile pipe; and that the flow holes (7) are at least partially aligned with the outer edge (25) of the collar or with the height (H1) of the recess (5). 5. Patenttivaatimuksen 1 mukainen betonilla ympäröitävä putkipaalu, tunnettu siitä, että kärkiosan ulkoläpimitta (D3) on enintään yhtä suuri kuin paaluputken ulkoläpimitta (D2); että kärkiosa (3) koostuu metallitangosta tai metalliputkesta; ja 35 16 111405 että työkärjen ja kauluksen maksimiläpimittaa vastaavan kohdan (R) välinen mainittu etäisyys (LI) on edullisesti kymmenen kertaa paaluputken ulkoläpimitta (D2).A concrete pipe pile surrounded by claim 1, characterized in that the outer diameter (D3) of the tip portion is at most equal to the outer diameter (D2) of the pile pipe; that the tip part (3) consists of a metal bar or metal tube; and that said distance (L1) between the workpiece and the point (R) corresponding to the maximum diameter of the collar is preferably ten times the outer diameter (D2) of the pile tube. 6. Patenttivaatimuksen 1 mukainen betonilla ympäröitävä putkipaalu, jonka kär-5 kiosa koostuu metalliputkesta, tunnettu siitä, että kärkiosa (3) on työkärjen kohdalla suljettu kärkikappaleella (9); ja että kärkiosa (3) muodostuu joko: paaluputken (2) osuudesta (2’) tai kaulukseen (6) kiinnitetystä putkikappaleesta (11) tai liitososan (4) osuudesta (17).Concrete tubular pile according to claim 1, wherein the tip portion consists of a metal tube, characterized in that the tip portion (3) is closed at the work tip by a tip piece (9); and that the tip portion (3) consists of: a portion (2 ') of the pile tube (2) or a tube piece (11) fixed to the collar (6) or a portion (17) of the connecting portion (4). 7. Patenttivaatimuksen 1 mukainen betonilla ympäröitävä putkipaalu, jonka kär kiosa koostuu metallitangosta, tunnettu siitä, että tämä kärkiosa (3) muodostuu: joko kauluksessa (6) olevaan syvennykseen kiinnitetystä tankokappaleesta (18) tai liitososan (4) osuudesta.Concrete tubular pile according to Claim 1, characterized in that the tip part consists of a metal rod, characterized in that this tip part (3) consists of: either a rod piece (18) fixed to the recess in the collar (6) or a part of the connecting part (4). 8. Patenttivaatimuksen 1 tai 6 mukainen betonilla ympäröitävä putkipaalu, tun nettu siitä, että kaulus lisäksi käsittää joko: - läpimenevän reiän (16), jonka läpimitta (D6) vastaa kärkiosan ulkoläpimittaa (D3) paaluputken tai liitososan läpimenoa varten, tai - ylöspäin osoittavan ulokkeen (19), jonka sisähalkaisija (D7) tai ulkohalkaisija (D8) 20 on sovitettu vastaanottamaan paaluputken (2) pää.Concrete pipe pile according to Claim 1 or 6, characterized in that the collar further comprises: - a through hole (16) having a diameter (D6) corresponding to the outer diameter (D3) of the tip part for passing through the pile tube or connecting part, or (19) having an inner diameter (D7) or an outer diameter (D8) 20 arranged to receive the end of the pile tube (2). 9. Patenttivaatimuksen 3 tai 8 mukainen betonilla ympäröitävä putkipaalu, tunnettu siitä, että liitososa (4) tai vastaavasti kaulus (6) käsittää yläosassaan sisäpuolisen tai ulkopuolisen syvennyksen (26a, 26b) paaluputken (2) alapään vastaanottami- 25 seksi sekä kanavan (27), joka ulottuu paaluputken sisätilasta (12) vähintään virtaus-reikien (7) kohdalle; ja että liitososa (4) käsittää vastepinnan (14), jonka yläläpimitta (D4) on suurempi kuin kauluksen reiän (16) läpimitta (D6) kauluksen pohjaan (15) tukeutumista varten ja liitososa (4) koostuu kärkiosan kanssa yhtenäisestä kappaleesta. 30Concrete tubular pile according to Claim 3 or 8, characterized in that the connecting part (4) or the collar (6) respectively comprises an inner or outer recess (26a, 26b) for receiving the lower end of the pile tube (2) and a channel (27). extending from the interior (12) of the pile tube to at least the flow holes (7); and that the connecting part (4) comprises a stop surface (14) having an upper diameter (D4) larger than the diameter (D6) of the collar hole (16) for supporting the collar bottom (15) and the connecting part (4) consisting of 30 10. Patenttivaatimuksen 8 tai 9 mukainen betonilla ympäröitävä putkipaalu, tunnettu siitä, että kaulus (6) tai liitososa (4) lisäksi käsittävät liitoselimet (15a tai 15b tai 15c) paaluputken (2) ja kauluksen (6) tai liitososan (4) välistä tartuntaa varten.Concrete tubular pile according to Claim 8 or 9, characterized in that the collar (6) or the connecting part (4) additionally comprises connecting members (15a or 15b or 15c) between the pile tube (2) and the collar (6) or the connecting part (4). for. 11. Patenttivaatimuksen 1 mukainen betonilla ympäröitävä putkipaalu, tunnettu siitä, että paaluputki (2) koostuu useammista putkiosista (2a, 2b, 2c jne.) ja niitä yhdistävistä liitoskappaleista (21) tai liitoksista (20); ja että paaluputken (2) ulkopinnalla on tartuntoja (30) betonia varten. 17 111405A concrete pipe pile according to claim 1, characterized in that the pile pipe (2) consists of a plurality of pipe sections (2a, 2b, 2c, etc.) and connecting pieces (21) or joints (20) connecting them; and that the outer surface of the pile tube (2) has grips (30) for concrete. 17 111405 12. Menetelmä putkipaalun pakottamiseksi maaperään (M) ja ympäröimiseksi betonilla, joka putkipaalu käsittää metallisen paaluputken (2), jonka yläpäässä on auk-ko/aukkoja (29) ja alapäässä suippeneva paalukenkä (1), jonka läpimitta (Dl) on suurempi kuin paaluputken läpimitta (D2) ja jonka alueelle paaluputken alapää au- 5 keaa, tunnettu siitä, että se käsittää vaiheina: {A} kiinnitetään paaluputken (2) maaperään ajettavaan alapäähän paalukenkä (1) putkipaalun saamiseksi, joka paalukenkä koostuu: pitkänomaisesta pääasiassa tasapaksusta kärkiosasta (3), jossa on etäisyyden (LI) päässä työkärjestä (10) kaulus (6), joka etäisyys (LI) on vähintään viisi 10 kertaa paaluputken ulkoläpimitta (D2) ja jonka maksimiläpimitta (Dl) on oleellisesti suurempi kuin paaluputken ulkoläpimitta, sekä kauluksen yläpuolelle avautuvista säteittäisistä virtausrei’istä (7); {B} ajetaan jaksoittaisella voimalla putkipaalua maaperään (M); {D} täytetään paaluputken sisätila (12) betonimassalla (B), joka koostuu hydrauli-15 sesti kovettuvasta sideaineesta, kiviaineksesta täyteaineena sekä vedestä; {E} ajetaan jaksoittaisella voimalla putkipaalua syvemmälle maaperään (M), jolloin betonimassaa siirtyy virtausreikien (7) kautta paaluputken (2) ympärille ja ylöspäin paalukengän (1) tekemään onteloon (T) maaperässä; {F} lisätään paaluputken sisätilaan (12) mainittua betonimassaa (B); ja 20 (G) jatketaan vuorotellen putkipaalun ajamista edelleen maaperään (M) jaksoittai sella voimalla ja mainitun betonimassan (B) lisäämistä paaluputken sisätilaan (12).A method of forcing a pipe pile into soil (M) and encircling it with concrete, the pipe pile comprising a metallic pile tube (2) having an aperture (s) at its upper end and a pile shoe (1) tapering at a lower end larger than the pile tube. diameter (D2) and in the region of which the lower end of the pile tube extends, characterized in that it comprises the steps of: {A} securing the lower end of the pile tube (2) to the ground to provide a pile shoe (1) comprising: an elongated substantially flat ) having a collar (6) at a distance (L1) from the workpiece (10) at least five times 10 times the outside diameter of the pile tube (D2) and having a maximum diameter (D1) substantially greater than the outside diameter of the pile tube; radial flow holes (7); {B} driving the pipe pile to the ground (M) by intermittent force; {D} filling the pile tube interior (12) with a concrete mass (B) consisting of a hydraulically curing binder, aggregate as filler and water; {E} is driven by periodic force deeper than the pipe pile into the soil (M), whereby the concrete mass is transferred through flow holes (7) around the pile tube (2) and up into the cavity (T) made by the pile shoe (1) in the soil; {F} adding said concrete mass (B) to the pile tube interior (12); and 20 (G) alternately continuing to drive the tube pile further into the soil (M) with intermittent force and adding said concrete mass (B) to the interior of the pile tube (12). 13. Patenttivaatimuksen 12 mukainen menetelmä, tunnettu siitä, että se käsittää lisävaiheina: 25 {H} maaperään ainakin osittain ajetun ensimmäisen putkiosan (2a) jatkamisen toi sella putkiosalla (2b) käyttäen liitoksia (20) tai liitoskappaleita (21); {1} jatketaan paaluputken jatkamista uusilla putkiosilla (2c, 2d, 2e jne.) sekä vuorotellen putkipaalun ajamista edelleen maaperään jaksoittaisella voimalla ja mainitun betonimassan (B) ainakin osittaista lisäämistä paaluputken sisätilaan (12), kun-30 nes putkipaalun kärkiosa (3) tulee tarkoitetulle syvyydelle (S 1) maaperään (M); ja {J} annetaan betonimassan (B) kovettua sekä paaluputken ympärillä että paaluputken (2) sisätilassa (12) valmiin betoniputkipaalun saamiseksi.A method according to claim 12, characterized in that it further comprises: extending the first tubular section (2a) driven at least partially into the soil by the second tubular section (2b) using joints (20) or connecting pieces (21); {1} continuing to extend the pile tube with new pipe sections (2c, 2d, 2e, etc.) and alternately driving the pipe pile further to the ground with intermittent force and at least partially inserting said concrete mass (B) into the pile tube interior (12); the indicated depth (S 1) in the soil (M); and {J} allowing the concrete mass (B) to cure both around the pile tube and in the interior (12) of the pile tube (2) to produce a finished concrete tube pile. 14. Patenttivaatimuksen 12 mukainen menetelmä, tunnettu siitä, että betonimassaa 35 syötetään paaluputken sisätilaan ilman oleellista ylipainetta; ja että mainittu jaksoittainen voima (F) synnytetään iskuilla ja/tai täristyksellä ja sen maksimi on suuruudeltaan sellainen, että paaluputken sisätilassa ilmenee painesysäys, joka on vähin- 18 111405 tään 10 bar ja edullisesti vähintään 15 bar ja jonka kestoaika on enintään 50 ms, tyypillisesti välillä 0,1 ms -15 ms ja edullisesti mahdollisimman lyhyt.Method according to Claim 12, characterized in that the concrete mass 35 is supplied to the interior of the pile tube without substantial overpressure; and that said intermittent force (F) is produced by shocks and / or vibrations and has a maximum magnitude such that a pressure impulse of at least 18,111,405 at 10 bar and preferably at least 15 bar and with a duration of up to 50 ms, between 0.1 ms and 15 ms and preferably as short as possible. 15. Patenttivaatimuksen 12 mukainen menetelmä, tunnettu siitä, että se lisäksi 5 käsittää tarvittaessa vaiheina: {Cl} jatketaan putkipaalun (40) ajamista edelleen maaperään jaksoittaisella voimalla tietylle syvyydelle (S2); {C2} lisätään erä betonimassaa (B) paaluputken sisätilaan (12) ja ajetaan putkipaalua vastaava matka maaperään; 10 {C3} täytetään betonimassan kerroksen yläpinnan ja maanpinnan välinen osuus putkipaalun ympärillä kiviaineksella (G) tai vastaavalla; ja {C4} jatketaan vuorotellen paaluputken (2) täyttämistä betonimassalla (B) ja ajamista maaperään (M) jaksoittaisella voimalla (F), kunnes putkipaalun kärkiosa (3) tulee tarkoitetulle syvyydelle (SI) maaperään; ja 15 {C5} täytetään paaluputken sisätilan (12) loppuosuus betonilla (B).A method according to claim 12, characterized in that it further comprises, if necessary, the steps of: continuing to drive the tubular pile (40) into the ground with periodic force to a certain depth (S2); {C2} adding a batch of concrete mass (B) to the interior (12) of the pile tube and driving a distance corresponding to the pile tube to the soil; 10 {C3} filling the portion between the top surface of the concrete mass layer and the ground surface around the pipe pile with rock material (G) or the like; and {C4} alternately filling the pile tube (2) with concrete mass (B) and driving it to the soil (M) with periodic force (F) until the tip of the tube pile (3) reaches the specified depth (SI) in the soil; and 15 {C5} filling the remainder of the pile tube interior (12) with concrete (B).
FI982699A 1998-12-14 1998-12-14 Concrete pipe pile and piling method FI111405B (en)

Priority Applications (11)

Application Number Priority Date Filing Date Title
FI982699A FI111405B (en) 1998-12-14 1998-12-14 Concrete pipe pile and piling method
RU2001119476/03A RU2236505C2 (en) 1998-12-14 1999-12-13 Tubular pile enclosed in concrete layer and driving method thereof
EP99961078A EP1507928B1 (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a pile-driving method
DE69938438T DE69938438T2 (en) 1998-12-14 1999-12-13 A CONCRETE ELEMENTS AND PILLAR METHOD EMBEDDED IN CONCRETE
AT99961078T ATE390521T1 (en) 1998-12-14 1999-12-13 A ROUND PILE EMBEDDED IN CONCRETE AND PILE DRIVING METHOD
PCT/FI1999/001027 WO2000036226A2 (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a method for driving the tubular pile into the soil and encasing it in concrete
PL365835A PL204637B1 (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a pile-driving method
AU17816/00A AU1781600A (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a pile-driving method
EEP200100272A EE04970B1 (en) 1998-12-14 1999-12-13 Pipe for concrete pouring and a method for squeezing a pile tube into the soil and pouring it into concrete
DK99961078T DK1507928T3 (en) 1998-12-14 1999-12-13 Tubular pile encased in concrete and a method of piling down piles
NO20012890A NO20012890D0 (en) 1998-12-14 2001-06-12 Tubular pile in concrete, and method of pile driving

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FI982699A FI111405B (en) 1998-12-14 1998-12-14 Concrete pipe pile and piling method
FI982699 1998-12-14

Publications (3)

Publication Number Publication Date
FI982699A0 FI982699A0 (en) 1998-12-14
FI982699A FI982699A (en) 2000-06-15
FI111405B true FI111405B (en) 2003-07-15

Family

ID=8553105

Family Applications (1)

Application Number Title Priority Date Filing Date
FI982699A FI111405B (en) 1998-12-14 1998-12-14 Concrete pipe pile and piling method

Country Status (11)

Country Link
EP (1) EP1507928B1 (en)
AT (1) ATE390521T1 (en)
AU (1) AU1781600A (en)
DE (1) DE69938438T2 (en)
DK (1) DK1507928T3 (en)
EE (1) EE04970B1 (en)
FI (1) FI111405B (en)
NO (1) NO20012890D0 (en)
PL (1) PL204637B1 (en)
RU (1) RU2236505C2 (en)
WO (1) WO2000036226A2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ATE445737T1 (en) * 2006-05-30 2009-10-15 Turun Ammattikorkeakoulu METHOD FOR PRODUCING A SHEET WALL STRUCTURE, SHEET WALL ELEMENT, SHEET WALL STRUCTURE AND USE OF A SHEET WALL STRUCTURE FOR VIBRATION DAMPING
RU2492294C1 (en) * 2011-12-27 2013-09-10 Открытое акционерное общество "Волгомост" Pipe concrete pile with reinforced base and method of its erection
RU2543397C1 (en) * 2013-10-08 2015-02-27 Михаил Федорович Егоров Metal support and its erection method
WO2019169180A1 (en) * 2018-02-28 2019-09-06 Aptim Intellectual Property Holdings, Llc Pressure grouted displacement screw piles
CN109881670B (en) * 2019-03-26 2024-02-02 中国石油大学(北京) Submarine self-disposable recyclable pile shoe of jack-up drilling platform and drilling platform
CN110468830A (en) * 2019-09-10 2019-11-19 河海大学 A kind of rapid anchor ingot stake and construction method
CN113969578A (en) * 2021-12-13 2022-01-25 广州市番禺大石建筑工程有限公司 Sectional type foundation pile and construction method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB796262A (en) * 1956-10-05 1958-06-11 Mueller Ludwig Improvements in or relating to piles
DE1634470A1 (en) * 1965-11-04 1970-10-29 Mueller Ludwig Foundation stake
BE794280A (en) * 1972-06-05 1973-05-16 Mazzalai Quirino DEVICE FOR MAKING FOUNDATIONS ON PILES EXECUTED IN THE SOIL
DE3131559A1 (en) * 1981-08-08 1983-05-05 Brown, Boveri & Cie Ag, 6800 Mannheim Method of producing cast-in-situ piles
GB2234774B (en) * 1989-08-12 1994-01-12 Roxbury Ltd Improvements in or relating to piling methods

Also Published As

Publication number Publication date
AU1781600A (en) 2000-07-03
DE69938438D1 (en) 2008-05-08
PL204637B1 (en) 2010-01-29
EP1507928A2 (en) 2005-02-23
PL365835A1 (en) 2005-01-10
NO20012890L (en) 2001-06-12
ATE390521T1 (en) 2008-04-15
DK1507928T3 (en) 2008-07-21
EE04970B1 (en) 2008-02-15
WO2000036226A2 (en) 2000-06-22
EE200100272A (en) 2002-10-15
FI982699A (en) 2000-06-15
DE69938438T2 (en) 2009-04-09
FI982699A0 (en) 1998-12-14
WO2000036226A3 (en) 2004-11-18
EP1507928B1 (en) 2008-03-26
NO20012890D0 (en) 2001-06-12
RU2236505C2 (en) 2004-09-20

Similar Documents

Publication Publication Date Title
CN112482359B (en) Carrier pile
JPH0612035Y2 (en) Pile driver for concrete foundation piles
RU2270294C1 (en) Bored pile and method for pile erection in karst or soft ground
CN112323777A (en) Hollow precast pile for rock embedding and rock embedding construction method using precast pile
FI111405B (en) Concrete pipe pile and piling method
CN110387886A (en) Civil air defense constructions and installations foundation pit supporting construction and its construction method
JPH039277B2 (en)
RU2319809C1 (en) Method to reinforce existent building and building structure foundation
JP3754506B2 (en) Prestressed concrete pile construction method
RU72986U1 (en) PILE
CN109853534B (en) Construction method of stiffening core pedestal pile
CN111501854A (en) Anti-floating anchor rod structure penetrating through water-rich gravel bottom layer and construction method thereof
CN110886294A (en) PRC (prestressed concrete pipe) pipe pile for deep foundation pit supporting and pile splicing method thereof
CN207160041U (en) Anchor rod type artificial digging pile
CN203559419U (en) Prestressed concrete precast pile
RU85495U1 (en) INJECTOR DESIGN FOR INJECTION PILES
RU2614131C1 (en) Method of arrangement of root pile with controlled widening
KR102199131B1 (en) Permanent type anchor
CN207469230U (en) Drum prefabricated pile supporting construction is adjusted in a kind of cement soil wall interpolation rigidity
RU12149U1 (en) FOUNDATION OF BUILDING, STRUCTURES
KR100429283B1 (en) Construction Method using Precast Concrete for Diaphragm Wall
CN109972611A (en) A kind of base expanding and base expanding type tubular pole and its construction technology
CN215926039U (en) Assembled plate type foundation connected by sleeve
FI111404B (en) Spont wall and its seal
CN214330696U (en) A structure for tunnel cable duct slope punishment

Legal Events

Date Code Title Description
MM Patent lapsed