ES2726226A1 - PREFABRICATED CONCRETE POST (Machine-translation by Google Translate, not legally binding) - Google Patents

PREFABRICATED CONCRETE POST (Machine-translation by Google Translate, not legally binding) Download PDF

Info

Publication number
ES2726226A1
ES2726226A1 ES201830327A ES201830327A ES2726226A1 ES 2726226 A1 ES2726226 A1 ES 2726226A1 ES 201830327 A ES201830327 A ES 201830327A ES 201830327 A ES201830327 A ES 201830327A ES 2726226 A1 ES2726226 A1 ES 2726226A1
Authority
ES
Spain
Prior art keywords
post
section
concrete
sections
threaded rods
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
ES201830327A
Other languages
Spanish (es)
Other versions
ES2726226B2 (en
Inventor
Fragüet Jesus Montaner
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Structural Concrete and Steel SL
Original Assignee
Structural Concrete and Steel SL
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Structural Concrete and Steel SL filed Critical Structural Concrete and Steel SL
Priority to ES201830327A priority Critical patent/ES2726226B2/en
Publication of ES2726226A1 publication Critical patent/ES2726226A1/en
Application granted granted Critical
Publication of ES2726226B2 publication Critical patent/ES2726226B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/18Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic
    • E04H12/182Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic telescopic
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Abstract

Precast concrete post, especially of high height, for the support of structures, comprising one or more prefabricated concrete sections, joined together where appropriate by removable mechanical joints, and with the possibility of using a removable mechanical joint between the foundation and a thickening as a foot at the lower end of the post. In the case of a single section, a metal structure in support lattice is used to move the post to its location. The section or sections of the post are prefabricated concrete elements, made by self-compacting concrete and metal forging, using a conventional static mold without centrifugation. The invention presented provides the main advantage of allowing high-rise, removable and reusable precast concrete poles to be achieved, with easy transport, lower economic cost and much faster assembly. (Machine-translation by Google Translate, not legally binding)

Description

DESCRIPCIONDESCRIPTION

Poste prefabricado de hormigónPrecast concrete post

La presente memoria descriptiva se refiere, como su título indica, a un poste prefabricada de hormigón, especialmente de gran altura, del tipo de los utilizados especialmente en aeropuertos, grandes aparcamientos, estadios deportivos, etc. para el soporte de estructuras, que comprende una o más secciones prefabricadas de hormigón, unidas entre sí en su caso mediante uniones mecánicas removibles, y con la posibilidad de utilizar una unión mecánica removible entre la cimentación y un regruesamiento a modo de pié en el extremo inferior del poste. Se utiliza, en caso de una única sección, una estructura metálica en celosía de soporte para el desplazamiento del poste hasta su ubicación. La sección o secciones del poste son elementos prefabricados de hormigón, realizados mediante hormigón autocompactante y forjado metálico, utilizando un molde estático convencional sin centrifugado.The present specification refers, as its title indicates, to a prefabricated concrete post, especially of high height, of the type used especially in airports, large car parks, sports stadiums, etc. for the support of structures, comprising one or more prefabricated sections of concrete, joined together where appropriate by removable mechanical joints, and with the possibility of using a removable mechanical joint between the foundation and a foot-like thickening at the end bottom of the post. In the case of a single section, a metal structure in support lattice is used to move the post to its location. The section or sections of the post are prefabricated concrete elements, made by self-compacting concrete and metal forging, using a conventional static mold without centrifugation.

La estructura o estructuras soportadas por este tipo de poste de gran altura pueden ser de iluminación, videovigilancia, fotografía, alarma, instalaciones meteorológicos, medidores de parámetros de contaminación del aire, ahuyentadores de aves, etc..., o una combinación de ellas.The structure or structures supported by this type of high-rise pole can be lighting, video surveillance, photography, alarm, meteorological installations, air pollution parameter meters, bird scarers, etc ..., or a combination of them.

Campo de la invenciónField of the Invention

La invención se refiere al campo de los postes prefabricadas de hormigón, de elevada altura.The invention relates to the field of prefabricated concrete posts, of high height.

Estado actual de la TécnicaCurrent state of the art

En la actualidad es frecuente la utilización de postes de elevada altura para el soporte de estructuras que albergan gran número de elementos técnicos, son muy utilizadas en grandes superficies, como por ejemplo aeropuertos, grandes aparcamientos, centros deportivos, etc... Estos postes son realizados principalmente en hormigón, por su alta resistencia estructural para elevadas alturas, a partir de 25 ó 30 metros.At present, the use of high-rise posts is frequent for the support of structures that house a large number of technical elements, they are widely used in large areas, such as airports, large parking lots, sports centers, etc ... These posts are Made mainly in concrete, due to its high structural strength for high heights, from 25 or 30 meters.

Existen múltiples referencias a este tipo de postes, como por ejemplo podemos encontrar reflejadas en las Patentes EP0561101 “Equipo para la producción de postes cónicos de uso industrial para aplicaciones de iluminación y similares", ES0151929 “Poste para aparatos de iluminación", ES0254993 “Sistema de construcción de postes de hormigón pretensado desmontables" y ES2291053 “Sistema de fabricación y unión de tramos de postes huecos de hormigón armado y/o pretensado", pero estas postes adolecen de una serie de problemas constructivos y económicos.There are multiple references to this type of posts, as for example we can find reflected in Patents EP0561101 "Equipment for the production of conical posts for industrial use for lighting and similar applications", ES0151929 "Post for lighting devices", ES0254993 "System of construction of removable prestressed concrete posts " and ES2291053 " System for manufacturing and joining sections of hollow reinforced and / or prestressed concrete posts ", but these posts suffer from a series of constructive and economic problems.

Los postes necesitan alcanzar idealmente una altura comprendida entre 30 y 50 m. como mínimo para lograr una buena efectividad. Esto origina que, en muchos casos, deben estar compuestas de al menos dos tramos, para permitir su transporte por carretera, que suele estar limitado a 20/25 m. Estos tramos se suelen fabricar, para conseguir una estructura troncocónica hueca, de reducido diámetro y gran altura, mediante moldes giratorios, por centrifugado del hormigón. Estos moldes son muy caros, y difíciles de rentabilizar, lo cual influye en el coste final del producto. Además imponen una serie de requerimientos técnicos, como la imposibilidad de elementos fuera de la estructura troncocónica que se pudieran necesitar, como por ejemplo un pié de hormigón de mayor anchura para el anclaje al suelo. Esto se suele paliar mediante piezas auxiliares metálicas de soporte, que deben añadirse posteriormente al proceso de rotación del hormigón, encareciendo más el coste económico. Un ejemplo clásico de este tipo de construcción mediante moldes giratorios lo encontramos descrito en la Patente ES0262978 “Poste hueco de hormigón armado", en donde podemos comprobar la complejidad de su proceso constructivo.The posts need to ideally reach a height between 30 and 50 m. at least to achieve good effectiveness. This causes that, in many cases, they must be composed of at least two sections, to allow transport by road, which is usually limited to 20/25 m. These sections are usually manufactured, to achieve a hollow truncated conical structure, of reduced diameter and great height, by means of rotating molds, by centrifuging the concrete. These molds are very expensive, and difficult to monetize, which influences the final cost of the product. They also impose a series of technical requirements, such as the impossibility of elements outside the truncated conical structure that may be needed, such as a concrete foot of greater width for anchoring to the ground. This is usually mitigated by auxiliary metal support pieces, which must be added later to the concrete rotation process, making the economic cost more expensive. A classic example of this type of construction by means of rotating molds is found in the patent ES0262978 "Hollow post of reinforced concrete", where we can check the complexity of its construction process.

Por otro lado, los tramos o secciones que componen la altura total del poste necesitan de una unión entre ellas, que se suele hacer, al no poder añadir elementos de conexión o unión durante el proceso de fabricación en molde rotatorio, dejando parte del forjado fuera del hormigón, para así, durante el montaje, proceder a la soldadura entre sí de los forjados de dos secciones consecutivas, a un hormigonado in-situ de dicha unión, con su correspondiente tiempo de fraguado, y un recubrimiento posterior con una tapa decorativa y protectora de la unión. Esto lo podemos encontrar descrito en la Patente ES0192199 “Perfeccionamientos en la construcción de postes de hormigón armado". Esto obliga a un tiempo de trabajo en obra bastante elevado, que a veces es complicado por los especiales requerimientos de seguridad o tiempo de trabajo de algunas instalaciones como aeropuertos. Además presenta el inconveniente de que este tipo de unión no es desmontable sin destrozar parte de la sección, con lo cual no es reutilizable en caso necesario en otra ubicación. On the other hand, the sections or sections that make up the total height of the post need a joint between them, which is usually done, as they cannot add connecting or joining elements during the rotational mold manufacturing process, leaving part of the slab out of the concrete, so, during assembly, proceed to weld each other of the slabs of two consecutive sections, to an in-situ concreting of said joint, with its corresponding setting time, and a subsequent coating with a decorative cover and protective of the union. This can be found described in Patent ES0192199 "Improvements in the construction of reinforced concrete poles." This forces a fairly high work time, which is sometimes complicated by the special safety requirements or working time of some facilities such as airports It also has the disadvantage that this type of union is not removable without destroying part of the section, so it is not reusable if necessary in another location.

Como alternativa a este proceso de unión entre secciones, también se conoce el método descrito en la Patente ES2291053 “Sistema de fabricación y unión de tramos de postes huecos de hormigón armado y/o pretensado”, que consiste en dotar a la parte superior de una sección de un alojamiento troncónico en su interior, en el que se introduce una terminación troncocónica macho en la parte inferior de la siguiente sección, con un adhesivo, resina o cemento de unión, pero presenta el inconveniente de complicar bastante la fabricación de las secciones, además de imposibilitar también el desmontaje posterior en caso necesario.As an alternative to this process of joining between sections, the method described in Patent ES2291053 "System for manufacturing and joining of hollow sections of reinforced and / or prestressed concrete poles" is also known, which consists in providing the upper part with a section of a truncated housing inside, in which a male truncated conical termination is introduced at the bottom of the next section, with an adhesive, resin or bonding cement, but has the disadvantage of complicating the fabrication of the sections quite a bit, in addition to also disabling subsequent disassembly if necessary.

Por último, las Patentes ES0253993 “Un procedimiento de erección de postes de hormigón armado" y US2015322665A1 “Column shoe" muestran algunos ejemplos de uniones mecánicas entre una columna y su soporte, o entre elementos de un poste, que hasta ahora no se han utilizado nunca en la construcción de postes prefabricadas de hormigón debido a que tampoco no es posible su inserción en elementos fabricados en moldes de hormigón por centrifugado.Finally, Patents ES0253993 "A procedure for erection of reinforced concrete posts" and US2015322665A1 "Column shoe" show some examples of mechanical joints between a column and its support, or between elements of a post, which until now have not been used never in the construction of prefabricated concrete posts because it is also not possible to insert them in elements manufactured in concrete molds by centrifugation.

Descripción de la invenciónDescription of the invention

Para solventar la problemática existente en la actualidad en cuanto a la fabricación, montaje y reutilización de postes de hormigón de gran altura, solventando los problemas existentes y mejorando el estado de la técnica actual, se ha ideado el poste prefabricado de hormigón objeto de la presente invención, el cual comprende una o más secciones prefabricadas de hormigón, unidas entre sí mediante uniones mecánicas removibles en caso de varias secciones, estando dotada la sección inferior de un regruesamiento a modo de pié fabricado en el extremo inferior del poste. El poste puede estar soportado sobre una cimentación mediante una unión mecánica removible aplicada entre dicha pieza de cimentación prefabricada y el regruesamiento a modo de pié. Opcionalmente está previsto que el poste pueda ubicarse utilizando cimentación fija convencional.To solve the current problem regarding the manufacture, assembly and reuse of high-rise concrete poles, solving existing problems and improving the state of the art, the precast concrete post object of the present has been devised The invention, which comprises one or more prefabricated sections of concrete, joined together by removable mechanical joints in the case of several sections, the bottom section being provided with a foot-shaped thickening manufactured at the lower end of the post. The post can be supported on a foundation by means of a removable mechanical joint applied between said prefabricated foundation piece and the foot-like thickening. Optionally it is provided that the post can be located using conventional fixed foundation.

Este poste de hormigón se utiliza preferentemente para el soporte de estructuras a gran altura. La estructura o estructuras soportadas por este tipo de poste de gran altura pueden ser de iluminación, videovigilancia, fotografía, alarma, instalaciones meteorológicos, medidores de parámetros de contaminación del aire, ahuyentadores de aves, etc..., o una combinación de ellas.This concrete pole is preferably used for supporting high-rise structures. The structure or structures supported by this type of high-rise pole can be lighting, video surveillance, photography, alarm, meteorological installations, air pollution parameter meters, bird scarers, etc ..., or a combination of them.

La invención también comprende una estructura metálica en celosía, reutilizable, para facilitar el desplazamiento del poste, en caso de estar formada por una única sección. De esta forma, se posibilita el transporte de postes de gran altura en una sola pieza, de más de 30 m. de longitud, sin problemas de roturas.The invention also comprises a metal structure in lattice, reusable, to facilitate the movement of the post, if it is formed by a single section. In this way, it is possible to transport high-rise posts in a single piece, of more than 30 m. in length, without breakage problems.

En caso necesario, mediante la unión de dos, o más secciones de longitudes menores de 30m., típicamente entre 20 y 25 m. más fácilmente transportables en transportes convencionales para elementos de gran longitud, pueden lograrse postes de hormigón prefabricadas de mayor altura todavía, adaptándose a todas las necesidades.If necessary, by joining two, or more sections of lengths less than 30m., Typically between 20 and 25m. more easily transportable in conventional transport for large elements, prefabricated concrete posts of greater height can still be achieved, adapting to all needs.

La sección o secciones del poste son elementos prefabricados de hormigón, realizados mediante hormigón autocompactante y forjado metálico, utilizando un molde estático convencional sin centrifugado. Utilizan preferentemente para el aligeramiento, y para crear el hueco interno, una pluralidad de tubos cilíndricos y piezas de acople rígidos de PVC, que se insertan en el molde antes del vertido del hormigón.The section or sections of the post are prefabricated concrete elements, made by self-compacting concrete and metal forging, using a conventional static mold without centrifugation. They are preferably used for lightening, and to create the internal hollow, a plurality of cylindrical tubes and rigid PVC coupling parts, which are inserted into the mold before concrete pouring.

Es característico de la invención que, como consecuencia de su fabricación de molde estático convencional, es posible que la sección inferior del poste tenga un regruesamiento, a modo de pie, para facilitar la unión con la cimentación, realizado en el mismo material que el resto de la sección y de manera simultánea en el molde. Este pie, preferentemente, adopta la forma una base cilíndrica dotada de una pluralidad de refuerzos inclinados para dotar de rigidez al conjunto, distribuidos radialmente en la parte superior de la base cilíndrica, y está dotado de una pluralidad de perforaciones pasantes verticales, radialmente distribuidas de manera alterna con los refuerzos.It is characteristic of the invention that, as a consequence of its manufacture of conventional static mold, it is possible that the lower section of the post has a thickening, as a foot, to facilitate the union with the foundation, made of the same material as the rest of the section and simultaneously in the mold. This foot preferably takes the form of a cylindrical base provided with a plurality of inclined reinforcements to provide rigidity to the assembly, distributed radially in the upper part of the cylindrical base, and is provided with a plurality of vertical through radially distributed perforations of alternate way with reinforcements.

Las uniones mecánicas removibles pueden realizarse utilizando cualquiera de los distintos tipos de uniones mecánicas removibles existentes en el mercado para elementos prefabricados de hormigón. Está previsto que preferentemente utilicen uniones que comprenden en el extremo superior de cada sección una pluralidad de varillas roscadas, con un disco metálico opcional, y en el extremo inferior de la sección o secciones superiores una pluralidad de piezas metálicas angulares insertas en el hormigón, dotadas en su parte inferior de perforaciones y con una cavidad abierta en la pared de la sección para acceso a la parte superior de la perforación. De esta forma se utilizan tuercas sobre las varillas roscadas para asegurar la parte inferior de las piezas metálicas sobre la parte superior de la otra sección.Removable mechanical joints can be made using any of the different types of removable mechanical joints available on the market for precast concrete elements. It is envisaged that they preferably use joints comprising at the upper end of each section a plurality of threaded rods, with an optional metal disk, and at the lower end of the upper section or sections a plurality of angular metal parts inserted in the concrete, provided in its lower part of perforations and with an open cavity in the wall of the section for access to the upper part of the perforation. In this way nuts are used on the threaded rods to secure the lower part of the metal parts on the upper part of the other section.

Esta poste prefabricada de hormigón que se presenta, incluye asimismo un procedimiento característico de montaje, en el que primero se realiza el transporte de los elementos, luego la preparación de la cimentación, a continuación, en caso necesario, se realiza la unión de la sección inferior con la sección superior, y de las secciones superiores entre sí en caso de haber mas de una, y finalmente se realiza el izado y fijación del poste sobre la cimentación.This prefabricated concrete post that is presented, also includes a characteristic assembly procedure, in which the elements are first transported, then the foundation preparation, then, if necessary, the section joint is made lower with the upper section, and of the upper sections with each other in case there is more than one, and finally the lifting and fixing of the post on the foundation is carried out.

Ventajas de la invenciónAdvantages of the invention

Esta poste prefabricada de hormigón que se presenta aporta múltiples ventajas sobre los disponibles en la actualidad siendo la más importante que las sección o secciones del poste son elementos prefabricados de hormigón, realizados mediante hormigón autocompactante y forjado metálico, utilizando un molde estático convencional sin centrifugado, reduciendo notablemente el coste de fabricación al requerir moldes más sencillos y sin rotación, y permitiendo la inserción de elementos y la realización de regruesamientos a modo de pié como parte integral del poste.This prefabricated concrete post that is presented provides multiple advantages over those currently available, the most important being that the sections or sections of the post are prefabricated concrete elements, made by self-compacting concrete and metal forging, using a conventional static mold without centrifugation, notably reducing the cost of manufacturing by requiring simpler molds without rotation, and allowing the insertion of elements and the realization of footing as an integral part of the post.

La utilización de moldes convencionales estáticos permite además la inserción en las paredes de las secciones del poste de los elementos necesarios para las uniones mecánicas removibles, sin necesidad de operaciones posteriores.The use of conventional static molds also allows the necessary elements for removable mechanical joints to be inserted into the walls of the post sections, without the need for subsequent operations.

Otra importante ventaja es que todas las uniones entre elementos prefabricados son removibles, propiciando el fácil y rápido desmontaje, sin causar daños a el poste, y su reutilización en otra ubicación, en caso necesario. Asimismo, al utilizar uniones mecánicas removibles, se elimina la necesidad de empalmar las secciones mediante soldadura de los forjados, hormigonado, fraguado y recubrimiento, todo ello realizado in-situ en la ubicación del poste y consumiendo mucho tiempo y recursos en un montaje convencional.Another important advantage is that all joints between prefabricated elements are removable, leading to quick and easy disassembly, without causing damage to the post, and its reuse in another location, if necessary. Also, by using removable mechanical joints, the need to splice the sections by welding the slabs, concreting, setting and coating is eliminated, all done in-situ at the location of the post and consuming a lot of time and resources in a conventional assembly.

Otra de las más importantes ventajas a destacar es permitir mediante la unión de dos, o más secciones, de longitud menor de 30m., conseguir postes de hormigón prefabricadas de gran altura, desmontables y reutilizables, transportables mediante procedimientos convencionales, adaptándose a todas las necesidades con un coste económico menor y con un montaje mucho más rápido.Another of the most important advantages to highlight is to allow, by joining two, or more sections, of length less than 30m., To obtain prefabricated concrete posts of great height, removable and reusable, transportable by conventional procedures, adapting to all needs with a lower economic cost and with a much faster assembly.

No debemos dejar de resaltar que la utilización de una estructura de soporte en celosía para la manipulación de del poste, en caso de estar formada por una única sección, facilita enormemente su transporte, permitiendo asimismo el transporte de un poste de 30m. o más de longitud completamente preparado desde la fábrica con el cableado interno, tanto eléctrico como mecánico, ya instalado, facilitando de esta forma aún más su montaje.We must not fail to emphasize that the use of a lattice support structure for the manipulation of the post, if it is formed by a single section, greatly facilitates its transport, also allowing the transport of a 30m post. or more in length, completely prepared from the factory with the internal wiring, both electrical and mechanical, already installed, thus facilitating its assembly even more.

Descripción de las figurasDescription of the figures

Para comprender mejor el objeto de la presente invención, en el plano anexo se ha representado una realización práctica preferencial de un poste prefabricado de hormigón. En dicho plano la figura 1 muestra una vista en alzado de un ejemplo de poste con una única sección, montada sobre su cimentación, con un detalle ampliado del aligeramiento interior, y otro detalle ampliado de la unión entre el pie del extremo inferior de la sección inferior del poste con la cimentación.To better understand the object of the present invention, a preferred practical embodiment of a precast concrete post has been shown in the attached drawing. In said plane Figure 1 shows an elevation view of an example of a pole with a single section, mounted on its foundation, with an enlarged detail of the interior lightening, and another enlarged detail of the joint between the foot of the lower end of the section bottom of the post with the foundation.

En la figura 2 se muestra una vista en alzado de un ejemplo de poste, en una realización alternativa con dos secciones, montada sobre su cimentación, con un detalle ampliado del aligeramiento interior, y otro detalle ampliado de la unión entre el pie del extremo inferior de la sección inferior del poste con la cimentación.Figure 2 shows an elevational view of an example of a pole, in an alternative embodiment with two sections, mounted on its foundation, with an enlarged detail of the interior lightening, and another enlarged detail of the joint between the foot of the lower end of the lower section of the post with the foundation.

En la figura 3 podemos ver una vista en alzado y planta del regruesamiento del extremo inferior del poste.In figure 3 we can see an elevation and plan view of the thickening of the lower end of the post.

En la figura 4 se muestra el detalle de los elementos de un ejemplo de unión mecánica removible, antes de la unión.Figure 4 shows the detail of the elements of an example of removable mechanical joint, before joining.

En la figura 5 se muestra el detalle de los elementos de un ejemplo de unión mecánica removible, una vez completada la unión y aseguradas las secciones entre sí.Figure 5 shows the detail of the elements of an example of removable mechanical joint, once the joint is completed and the sections secured together.

Por último, la figura 6 muestra varias vistas de la estructura metálica en celosía para el transporte del poste, en caso de estar formada por una única sección de gran longitud.Finally, Figure 6 shows several views of the lattice metal structure for the transport of the post, if it is formed by a single section of great length.

Realización preferente de la invenciónPreferred Embodiment of the Invention

La constitución y características del poste prefabricada de hormigón podrán comprenderse mejor con la siguiente descripción hecha con referencia a las figuras adjuntas.The constitution and characteristics of the precast concrete post can be better understood with the following description made with reference to the attached figures.

Según puede apreciarse en la figura 1, se ilustra un ejemplo de realización de poste que comprende As can be seen in Figure 1, an example of a pole embodiment is illustrated comprising

- una sección (1) prefabricadas de hormigón, de sección troncocónica hueca con diámetros notablemente menores que la altura, y- a prefabricated section (1) of concrete, with a hollow conical section with diameters significantly smaller than the height, and

- una cimentación (4) inserta en el suelo (5) y que se relaciona mediante una unión mecánica removible con el extremo inferior de la sección (1) del poste, que cuenta con un regruesamiento a modo de pie, del mismo material que el resto de la sección.- a foundation (4) inserted into the ground (5) and which is related by a removable mechanical connection with the lower end of the section (1) of the post, which has a foot-like thickening, of the same material as the rest of the section.

En la figura 2, se ilustra un ejemplo de realización alternativa de poste que comprendeIn Fig. 2, an example of an alternative embodiment of a pole is illustrated, comprising

- una sección (1) y una sección superior (2), prefabricadas de hormigón, de sección troncocónica hueca con diámetros notablemente menores que la altura, unidas entre sí mediante una unión mecánica removible (3), y- a section (1) and an upper section (2), prefabricated of concrete, with a hollow truncated conical section with diameters markedly smaller than the height, joined together by a removable mechanical joint (3), and

- una cimentación (4) inserta en el suelo (5) y que se relaciona mediante una unión mecánica removible con el extremo inferior de la sección (1) del poste, que cuenta con un regruesamiento a modo de pie, del mismo material que el resto de la sección.- a foundation (4) inserted into the ground (5) and which is related by a removable mechanical connection with the lower end of the section (1) of the post, which has a foot-like thickening, of the same material as the rest of the section.

En ambas realizaciones está previsto que, opcionalmente, el poste pueda ubicarse utilizando cimentación (4) convencional mediante inserción directa del poste en la cimentación (4), sin unión mecánica removible con el extremo inferior de la sección (1) del poste.In both embodiments it is provided that, optionally, the post can be located using conventional foundation (4) by direct insertion of the post into the foundation (4), without removable mechanical connection with the lower end of section (1) of the post.

En la primera realización es característica, tal y como podemos ver en la figura 6, la utilización de una estructura metálica en celosía (29), reutilizable, bajo la cual se suspende el poste formada por una única sección (1), de manera solidaria mediante elementos de fijación (30) durante su desplazamiento. Esta estructura metálica en celosía (29) permite el transporte del poste desde la fábrica con el cableado interno de la sección (1), tanto eléctrico como mecánico, ya instalado, facilitando de esta forma aún más su montaje.In the first embodiment it is characteristic, as we can see in Figure 6, the use of a reusable lattice metal structure (29), under which the post formed by a single section (1) is suspended, in solidarity by means of fixing elements (30) during its movement. This lattice metal structure (29) allows the transport of the post from the factory with the internal wiring of the section (1), both electrical and mechanical, already installed, thus facilitating its assembly even more.

En la segunda realización, con el poste formada por varias secciones (1,2), el transporte se realiza mediante plataformas o semirremolques convencionales para transportes de gran longitud, aunque opcionalmente está previsto que pudiera utilizarse también la estructura metálica en celosía (29), bajo la cual se suspenderían las distintas secciones (1,2) que componen el poste, de manera solidaria mediante elementos de fijación (30) Las secciones del poste (1,2) son elementos prefabricados de hormigón, realizados mediante hormigón autocompactante y forjado metálico, utilizando un molde estático convencional sin centrifugado.In the second embodiment, with the post formed by several sections (1,2), the transport is carried out by means of conventional platforms or semi-trailers for long-distance transport, although it is optionally provided that the lattice metal structure (29) could also be used, under which the different sections (1,2) that make up the post would be suspended, in solidarity with fixing elements (30) The post sections (1,2) are prefabricated concrete elements, made by self-compacting concrete and metal forging , using a conventional static mold without spin.

Tanto en la figura 1 como en la figura 2 podemos apreciar un detalle ampliado en el que se muestra que, tanto la sección (1), como la o las secciones superiores (2), están aligeradas preferentemente mediante la inserción de tubos cilíndricos rígidos de PVC (11), de diámetros decrecientes, relacionados entre sí mediante piezas de acople (12) también de PVC, conformando el hueco interior del poste. Esta inserción de tubos cilíndricos rígidos y piezas de acople de PVC se realiza durante el proceso de fabricación de las secciones del poste, mediante su inserción en el molde antes del vertido de hormigón autocompactante, quedando solidarios con la pared de hormigón.Both in Figure 1 and in Figure 2 we can see an enlarged detail in which it is shown that both the section (1) and the upper section (2) are preferably lightened by the insertion of rigid cylindrical tubes of PVC (11), of decreasing diameters, related to each other by means of coupling pieces (12) also made of PVC, forming the inner hollow of the post. This insertion of rigid cylindrical pipes and PVC coupling parts is carried out during the manufacturing process of the pole sections, by inserting them into the mold before pouring self-compacting concrete, being integral with the concrete wall.

Asimismo, en ambas figuras 1 y 2 podemos apreciar otro detalle ampliado de la unión entre el pie del extremo inferior de la sección (1) del poste con la cimentación (4).Also, in both figures 1 and 2 we can see another enlarged detail of the connection between the foot of the lower end of the section (1) of the post with the foundation (4).

En la figura 3 podemos ver como el regruesamiento del extremo inferior de la sección (1) del poste, adopta la forma de base cilíndrica (13) dotada de una pluralidad de refuerzos (14) inclinados para dotar de rigidez al conjunto, distribuidos radialmente en la parte superior de la base cilíndrica (13), y está dotado de una pluralidad de perforaciones pasantes verticales (15), radialmente distribuidas de manera alterna con los refuerzos (14). Las uniones mecánicas removibles (3) pueden realizarse utilizando cualquiera de los distintos tipos de uniones mecánicas removibles existentes en el mercado para elementos prefabricados de hormigón. En las figuras 4 y 5 se representa una de estas posibilidades, en la que las uniones mecánicas removibles (3) comprendenIn figure 3 we can see how the thickening of the lower end of the section (1) of the post, adopts the shape of a cylindrical base (13) provided with a plurality of inclined reinforcements (14) to provide rigidity to the assembly, distributed radially in the upper part of the cylindrical base (13), and is provided with a plurality of vertical through holes (15), radially distributed alternately with the reinforcements (14). The removable mechanical joints (3) can be made using any of the different types of removable mechanical joints available on the market for precast concrete elements. One of these possibilities is shown in Figures 4 and 5, in which the removable mechanical joints (3) comprise

- en el extremo superior de la sección (1,2) del poste una pluralidad de varillas roscadas (23), radialmente distribuidas e insertas en el hormigón de las paredes, opcionalmente complementadas con un disco metálico (22), solidario con el hormigón de las paredes y atravesado por las varillas roscadas (23) y- at the top end of the section (1,2) of the post a plurality of threaded rods (23), radially distributed and inserted in the concrete of the walls, optionally complemented with a metal disk (22), integral with the concrete of the walls and pierced by threaded rods (23) and

- en el extremo inferior de la sección superior (2) una pluralidad de piezas metálicas (24) en forma de “L” insertas en el hormigón de la pared, dotadas en su parte inferior de perforaciones (25) de dimensiones, posicionamiento y distribución acordes con las varillas roscadas (23), y con una cavidad abierta (26) en la pared de la sección para acceso a la parte superior de la perforación (25), utilizándose tuercas (27) sobre las varillas roscadas (23) para asegurar la parte inferior de las piezas metálicas (24) sobre el disco metálico (22) en su caso, o la parte superior de la sección ubicada debajo.- at the lower end of the upper section (2) a plurality of metal parts (24) in the form of "L" inserted in the concrete of the wall, provided in its lower part with perforations (25) of dimensions, positioning and distribution according to the threaded rods (23), and with an open cavity (26) in the wall of the section for access to the upper part of the perforation (25), using nuts (27) on the threaded rods (23) to ensure the lower part of the metal parts (24) on the metal disk (22) where appropriate, or the upper part of the section located below.

Este poste prefabricada de hormigón que se presenta, incluye asimismo un procedimiento característico de montaje, que comprendeThis prefabricated concrete post that is presented also includes a characteristic assembly procedure, comprising

- una primera fase de transporte de los elementos, - a first phase of transport of the elements,

- una segunda fase de preparación de la cimentación (4),- a second phase of foundation preparation (4),

- una tercera fase opcional de unión de la sección (1) con la sección superior (2) en caso de existir, y de las secciones superiores (2) entre sí en caso de haber mas de una, y- an optional third phase of joining section (1) with the upper section (2) if it exists, and the upper sections (2) with each other if there is more than one, and

- una cuarta fase de izado y fijación del poste sobre la cimentación.- a fourth phase of lifting and fixing the post on the foundation.

La fase de transporte de los elementos se realiza, en caso de estar compuesta de una única sección (1), mediante la utilización de una estructura metálica en celosía (29), reutilizable, bajo la cual se suspende el poste de manera solidaria mediante elementos de fijación (30) durante su desplazamiento, soltándose estos elementos de fijación (30) una vez ubicados los elementos en el suelo junto a su punto de montaje, y retirando la estructura metálica en celosía (29). En caso de estar compuesta por varias secciones (1,2) el transporte se realizará mediante procedimientos convencionales para elementos de gran longitud, como por ejemplo camiones con plataforma, o camiones semirremolques en dos partes que se denominan habitualmente “dollys”.The transport phase of the elements is carried out, in case of being composed of a single section (1), by using a reusable lattice metal structure (29), under which the post is suspended jointly by means of elements of fixing (30) during its movement, releasing these fixing elements (30) once the elements are located on the floor next to their mounting point, and removing the metal structure in lattice (29). In case of being composed of several sections (1,2) the transport will be carried out by conventional procedures for elements of great length, such as trucks with platform, or semi-trailer trucks in two parts that are usually called “dollys”.

La fase de preparación de la cimentación (4) comprende,The foundation preparation phase (4) comprises,

- un paso de excavación en el suelo (5) de la oportuna zanja,- an excavation step in the ground (5) of the appropriate ditch,

- un paso de colocación de una pluralidad de varillas roscadas (6), bien puestas o bien solidarias con una chapa de montaje, radialmente dispuestas, de dimensiones, posicionamiento y distribución acordes con las perforaciones pasantes verticales (15) del regruesamiento a modo de pie de la sección (1) del poste,- a step of placing a plurality of threaded rods (6), either placed or in solidarity with a mounting plate, radially arranged, of dimensions, positioning and distribution in accordance with the vertical through holes (15) of the foot-like thickening of section (1) of the post,

- un paso de vertido de hormigón (9) de relleno. de tal forma que la parte superior de las varillas roscadas (6) quede por encima del nivel superior del hormigón, y- a concrete pouring step (9) of filling. such that the upper part of the threaded rods (6) is above the upper level of the concrete, and

- un paso de fraguado del hormigón (9).- a concrete setting step (9).

La fase opcional de unión de la sección (1) con la sección superior (2), y de las secciones superiores (2) entre sí en caso de haber mas de una, únicamente se realizará en caso de estar el poste compuesta de varias secciones, y comprendeThe optional phase of joining the section (1) with the upper section (2), and the upper sections (2) with each other in case there are more than one, will only be carried out if the post is composed of several sections , and understand

- un paso de inserción del cableado, tanto eléctrico como de cabrestantes, por el interior hueco de las secciones,- one step of inserting the wiring, both electric and winches, through the hollow interior of the sections,

- un paso de alineación de las secciones a unir,- an alignment step of the sections to be joined,

- un paso de empuje del extremo inferior de la sección superior (2) sobre el extremo superior de la sección (1,2), de tal forma que las varillas roscadas (23) atraviesen las perforaciones (25), hasta que el disco metálico (22) en su caso, o la parte superior de la sección, entre en contacto con la parte inferior de las piezas metálicas (24),- a thrust passage from the lower end of the upper section (2) over the upper end of the section (1,2), such that the threaded rods (23) pass through the perforations (25), until the metal disk (22) if applicable, or the upper part of the section, come into contact with the lower part of the metal parts (24),

- un paso de aseguramiento de la unión, mediante el roscado de tuercas (27) sobre las varillas roscadas (23),- a joint securing step, by threading nuts (27) onto the threaded rods (23),

- un paso de colocación de un capuchón plástico de protección (28) y- a step of placing a protective plastic cap (28) and

- un paso de relleno de las cavidades abiertas (26) con material de relleno, preferentemente mortero grout,- a filling step of the open cavities (26) with filling material, preferably grout mortar,

realizándose todos estos pasos con las secciones (1,2) horizontalmente dispuestas en el suelo.performing all these steps with the sections (1,2) horizontally arranged on the floor.

La fase de izado y fijación del poste sobre la cimentación comprende,The lifting and fixing phase of the post on the foundation includes,

- un paso de izado mediante una grúa del poste, o las distintas secciones (1,2) previamente ensambladas, hasta su posicionamiento sobre la parte principal (16) de la pieza de cimentación, - un paso de inserción del cableado eléctrico a través de la conducción hueca (20) hasta la caja de registro (19),- a lifting step by means of a post crane, or the different sections (1,2) previously assembled, until it is positioned on the main part (16) of the foundation piece, - a step of inserting the electrical wiring through the hollow conduit (20) to the register box (19),

- un paso de apoyo de las distintas secciones (1,2) previamente ensambladas, sobre la cimentación, de tal manera que las varillas roscadas (6) atraviesen las perforaciones pasantes verticales (15) del pie de la sección (1) del poste, y- a support step of the different sections (1,2) previously assembled, on the foundation, in such a way that the threaded rods (6) pass through the vertical through holes (15) of the foot of the section (1) of the post, Y

- un paso de aseguramiento de la unión, mediante el roscado de tuercas (7) sobre las varillas roscadas (6).- a joint securing step, by threading nuts (7) onto the threaded rods (6).

Está previsto que, de manera alternativa, pueda realizarse otro procedimiento convencional de montaje, en el que el pié de la sección (1) del poste se inserta directamente en el hueco excavado en el suelo (5) y se vierte el hormigón (9) de relleno, quedando sujeto el poste con el fraguado del hormigón (9).It is envisaged that, alternatively, another conventional assembly procedure may be performed, in which the foot of the section (1) of the post is inserted directly into the hole excavated in the ground (5) and the concrete (9) is poured of filling, subjecting the post with the setting of the concrete (9).

La persona experta en la técnica comprenderá fácilmente que puede combinar características de diferentes realizaciones con características de otras posibles realizaciones, siempre que esa combinación sea técnicamente posible.The person skilled in the art will readily understand that he can combine characteristics of different embodiments with characteristics of other possible embodiments, provided that such combination is technically possible.

Toda la información referida a ejemplos o modos de realización forma parte de la descripción de la invención. All information referring to examples or embodiments is part of the description of the invention.

Claims (1)

REIVINDICACIONES 1 - Poste prefabricado de hormigón, caracterizado porque comprende1 - Precast concrete post, characterized in that it comprises - al menos una sección (1) hueca, de configuración troncocónica y prefabricada en molde estático con hormigón autocompactante y forjado metálico, con diámetros notablemente menores que la altura, que cuenta en su extremo inferior con un regruesamiento a modo de pie, del mismo material que el resto de la sección (1), y- at least one hollow section (1) of truncated conical configuration and prefabricated in static mold with self-compacting concrete and metal slab, with diameters significantly smaller than the height, which at its lower end has a foot-like thickening of the same material than the rest of section (1), and - una estructura metálica en celosía (29), reutilizable, bajo la cual se suspende el poste, en caso de estar compuesta de una única sección (i), de manera solidaria mediante elementos de fijación (30) durante su desplazamiento.- a metal structure in lattice (29), reusable, under which the post is suspended, if it is composed of a single section (i), in solidarity with fixing elements (30) during its movement. 2 - Poste prefabricado de hormigón, según la anterior reivindicación, caracterizado porque el poste comprende además una o varias secciones superiores (2), todas ellas huecas, de sección troncocónica y prefabricadas en molde estático con hormigón autocompactante y forjado metálico, con diámetros notablemente menores que la altura, unidas entre sí y con la sección (1) mediante uniones mecánicas removibles (3).2 - Precast concrete post, according to the preceding claim, characterized in that the post further comprises one or more upper sections (2), all of them hollow, with a truncated conical section and prefabricated in static mold with self-compacting concrete and metal forging, with notably smaller diameters that the height, joined together and with section (1) by removable mechanical joints (3). 3 - Poste prefabricado de hormigón, según cualquiera de las anteriores reivindicaciones, caracterizado porque el regruesamiento a modo de pie del extremo inferior de la sección (1) del poste, adopta la forma de base cilíndrica (13) dotada de una pluralidad de refuerzos (14) inclinados para dotar de rigidez al conjunto, distribuidos radialmente en la parte superior de la base cilindrica (13), y está dotado de una pluralidad de perforaciones pasantes verticales (15), radialmente distribuidas de manera alterna con los refuerzos (14).3 - Precast concrete post, according to any of the preceding claims, characterized in that the foot-like thickening of the lower end of the section (1) of the post, adopts the shape of a cylindrical base (13) provided with a plurality of reinforcements ( 14) inclined to provide rigidity to the assembly, distributed radially in the upper part of the cylindrical base (13), and is provided with a plurality of vertical through holes (15), radially distributed alternately with the reinforcements (14). 4 - Poste prefabricado de hormigón, según cualquiera de las anteriores reivindicaciones, caracterizado porque tanto la sección (1), como la o las secciones superiores (2), están aligeradas mediante una pluralidad de tubos cilindricos rígidos de PVC (11), solidarios con la pared de hormigón debido a su inserción en moldeado previa al vertido de hormigón, de diámetros decrecientes, relacionados entre sí mediante piezas de acople (12) también de PVC, conformando el hueco interior del poste.4 - Precast concrete post, according to any of the preceding claims, characterized in that both the section (1), and the upper section (2), are lightened by a plurality of rigid cylindrical PVC pipes (11), integral with the concrete wall due to its insertion in molded prior to the pouring of concrete, of decreasing diameters, related to each other by means of coupling pieces (12) also of PVC, forming the inner hollow of the post. 5 - Poste prefabricado de hormigón, según cualquiera de las anteriores reivindicaciones, caracterizado porque las uniones mecánicas removibles (3) comprenden5 - Precast concrete post, according to any of the preceding claims, characterized in that the removable mechanical joints (3) comprise - en el extremo superior de la sección (1,2) una pluralidad de varillas roscadas (23), radialmente distribuidas e insertas en el hormigón de las paredes, y- at the upper end of section (1,2) a plurality of threaded rods (23), radially distributed and inserted in the concrete of the walls, and - en el extremo inferior de la sección superior (2) una pluralidad de piezas metálicas (24) en forma de “L” insertas en el hormigón de la pared, dotadas en su parte inferior de perforaciones (25) de dimensiones, posicionamiento y distribución acordes con las varillas roscadas (23), y con una cavidad abierta (26) en la pared de la sección para acceso a la parte superior de la perforación (25), utilizándose tuercas (27) sobre las varillas roscadas (23) para asegurar la parte inferior de las piezas metálicas (24) sobre la parte superior de la sección ubicada debajo.- at the lower end of the upper section (2) a plurality of metal parts (24) in the form of "L" inserted in the concrete of the wall, provided in its lower part with perforations (25) of dimensions, positioning and distribution according to the threaded rods (23), and with an open cavity (26) in the wall of the section for access to the upper part of the perforation (25), using nuts (27) on the threaded rods (23) to ensure the lower part of the metal parts (24) on the upper part of the section located below. 6 - Poste prefabricado de hormigón, según la reivindicación 5, caracterizado porque el extremo superior de la sección (1,2) del poste comprende un disco metálico (22), solidario con el hormigón de las paredes, que es atravesado por las varillas roscadas (23).6 - Precast concrete post, according to claim 5, characterized in that the upper end of the section (1,2) of the post comprises a metal disk (22), integral with the concrete of the walls, which is crossed by the threaded rods (2. 3). 7 - Procedimiento de montaje de un poste prefabricada de hormigón, como el descrita en las anteriores reivindicaciones caracterizado porque comprende7 - Assembly procedure of a prefabricated concrete post, as described in the previous claims characterized in that it comprises - una primera fase de transporte de los elementos,- a first phase of transport of the elements, - una segunda fase de preparación de la cimentación (4),- a second phase of foundation preparation (4), - una tercera fase opcional de unión de la sección (1) con la sección superior (2) en caso de existir, y de las secciones superiores (2) entre sí en caso de haber mas de una, y- an optional third phase of joining section (1) with the upper section (2) if it exists, and the upper sections (2) with each other if there is more than one, and - una cuarta fase de izado y fijación del poste sobre la cimentación (4).- a fourth phase of lifting and fixing the post on the foundation (4). 8 - Procedimiento de montaje de un poste prefabricada de hormigón, según la reivindicación 7, caracterizado porque la fase de transporte de los elementos se realiza,8 - Assembly procedure of a prefabricated concrete post, according to claim 7, characterized in that the transport phase of the elements is carried out, - en caso de estar compuesta de una única sección (1), mediante la utilización de una estructura metálica en celosía (29), reutilizable, bajo la cual se suspende el poste de manera solidaria mediante elementos de fijación (30) durante su desplazamiento, soltándose estos elementos de fijación (30) una vez ubicados los elementos en el suelo junto a su punto de montaje, y retirando la estructura metálica en celosía (29), y- in the case of being composed of a single section (1) , through the use of a reusable lattice metal structure (29), under which the post is suspended jointly by means of fixing elements (30) during its movement, releasing these fasteners (30) once the elements are located on the floor next to their mounting point, and removing the lattice metal structure (29), and - en caso de estar compuesta por varias secciones (1,2) el transporte se realizará mediante procedimientos convencionales para elementos de gran longitud. - in case of being composed of several sections (1,2) the transport will be carried out by means of conventional procedures for elements of great length. 9 - Procedimiento de montaje de un poste prefabricada de hormigón para iluminación de grandes superficies, según cualquiera de las reivindicaciones 7 a la 8, caracterizado porque la fase de preparación de la cimentación (4) comprende,9 - Procedure for assembling a prefabricated concrete post for lighting large areas, according to any of claims 7 to 8, characterized in that the foundation preparation phase (4) comprises, - un paso de excavación en el suelo (5) de la oportuna zanja,- an excavation step in the ground (5) of the appropriate ditch, - un paso de colocación de una pluralidad de varillas roscadas (6), bien puestas o bien solidarias con una chapa de montaje, radialmente dispuestas, de dimensiones, posicionamiento y distribución acordes con las perforaciones pasantes verticales (15) del regruesamiento a modo de pie de la sección (1) del poste,- a step of placing a plurality of threaded rods (6), either placed or in solidarity with a mounting plate, radially arranged, of dimensions, positioning and distribution in accordance with the vertical through holes (15) of the foot-like thickening of section (1) of the post, - un paso de vertido de hormigón (9) de relleno. de tal forma que la parte superior de las varillas roscadas (6) quede por encima del nivel superior del hormigón, y- a concrete pouring step (9) of filling. such that the upper part of the threaded rods (6) is above the upper level of the concrete, and - un paso de fraguado del hormigón (9).- a concrete setting step (9). 10 - Procedimiento de montaje de un poste prefabricada de hormigón, según cualquiera de las reivindicaciones 7 a la 9, caracterizado porque la fase de unión de la sección (1) con la sección superior (2), y de las secciones superiores (2) entre sí en caso de haber mas de una, comprende10 - Assembly procedure of a prefabricated concrete post, according to any of claims 7 to 9, characterized in that the joining phase of the section (1) with the upper section (2), and of the upper sections (2) each other in case there is more than one, understand - un paso de inserción del cableado, tanto eléctrico como de cabrestantes, por el interior hueco de las secciones,- one step of inserting the wiring, both electric and winches, through the hollow interior of the sections, - un paso de alineación de las secciones a unir,- an alignment step of the sections to be joined, - un paso de empuje del extremo inferior de la sección superior (2) sobre el extremo superior de la sección (1,2), de tal forma que las varillas roscadas (23) atraviesen las perforaciones (25), hasta que el disco metálico (22) en su caso, o la parte superior de la sección entre en contacto con la parte inferior de las piezas metálicas (24),- a thrust passage from the lower end of the upper section (2) over the upper end of the section (1,2), such that the threaded rods (23) pass through the perforations (25), until the metal disk (22) if applicable, or the upper part of the section comes into contact with the lower part of the metal parts (24), - un paso de aseguramiento de la unión, mediante el roscado de tuercas (27) sobre las varillas roscadas (23),- a joint securing step, by threading nuts (27) onto the threaded rods (23), - un paso de colocación de un capuchón plástico de protección (28) y- a step of placing a protective plastic cap (28) and - un paso de relleno de las cavidades abiertas (26) con material de relleno, preferentemente mortero grout,- a filling step of the open cavities (26) with filling material, preferably grout mortar, realizándose todos estos pasos con las secciones (1,2) horizontalmente dispuestas en el suelo.performing all these steps with the sections (1,2) horizontally arranged on the floor. 11 - Procedimiento de montaje de un poste prefabricada de hormigón, según cualquiera de las reivindicaciones 7 a la 10, caracterizado porque la fase de izado y fijación del poste sobre la cimentación (4) comprende,11 - Procedure for mounting a prefabricated concrete post, according to any of claims 7 to 10, characterized in that the lifting and fixing phase of the post on the foundation (4) comprises, - un paso de izado mediante una grúa del poste, o las distintas secciones (1,2) previamente ensambladas, hasta su posicionamiento sobre la parte principal (16) de la pieza de cimentación, - un paso de inserción del cableado eléctrico a través de la conducción hueca (20) hasta la caja de registro (19),- a lifting step by means of a post crane, or the different sections (1,2) previously assembled, until it is positioned on the main part (16) of the foundation piece, - a step of inserting the electrical wiring through the hollow conduit (20) to the register box (19), - un paso de apoyo de las distintas secciones (1,2) previamente ensambladas, sobre la cimentación, de tal manera que las varillas roscadas (6) atraviesen las perforaciones pasantes verticales (15) del pie de la sección (1) del poste, y- a support step of the different sections (1,2) previously assembled, on the foundation, in such a way that the threaded rods (6) pass through the vertical through holes (15) of the foot of the section (1) of the post, Y - un paso de aseguramiento de la unión, mediante el roscado de tuercas (7) sobre las varillas roscadas (6). - one step of securing the joint, by threading nuts (7) onto the threaded rods (6).
ES201830327A 2018-04-02 2018-04-02 PREFABRICATED CONCRETE POST Active ES2726226B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ES201830327A ES2726226B2 (en) 2018-04-02 2018-04-02 PREFABRICATED CONCRETE POST

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
ES201830327A ES2726226B2 (en) 2018-04-02 2018-04-02 PREFABRICATED CONCRETE POST

Publications (2)

Publication Number Publication Date
ES2726226A1 true ES2726226A1 (en) 2019-10-02
ES2726226B2 ES2726226B2 (en) 2021-05-28

Family

ID=68063128

Family Applications (1)

Application Number Title Priority Date Filing Date
ES201830327A Active ES2726226B2 (en) 2018-04-02 2018-04-02 PREFABRICATED CONCRETE POST

Country Status (1)

Country Link
ES (1) ES2726226B2 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1434730A1 (en) * 1963-11-12 1970-01-15 Moll Kg Leonhard Process for the production of steel or prestressed concrete masts consisting of several detachably connected parts and multi-part concrete mast produced according to this process
JPH0473381A (en) * 1990-07-13 1992-03-09 Nippon Chikou Kk Independent electric pole and its pole erecting construction
JP2004011210A (en) * 2002-06-05 2004-01-15 Fuji Ps Corp Main tower for wind-power generation facility
WO2011030199A2 (en) * 2009-09-11 2011-03-17 Stefano Knisel Improved foundation for a wind turbine tower
US20130269286A1 (en) * 2010-06-14 2013-10-17 Max Bögl Bauunternehmung GmbH & Co. KG Tower of a Wind Power Plant and Method for Producing a Tower of a Wind Power Plant
ES2476599T3 (en) * 2007-12-12 2014-07-15 Senvion Se Anchorage of a tower of a wind power installation
CN104612455A (en) * 2015-03-04 2015-05-13 陈宝民 Integrated structure of concrete tower drum and foundation of fan
WO2015131174A1 (en) * 2014-02-28 2015-09-03 University Of Maine System Board Of Trustees Hybrid concrete - composite tower for a wind turbine

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1434730A1 (en) * 1963-11-12 1970-01-15 Moll Kg Leonhard Process for the production of steel or prestressed concrete masts consisting of several detachably connected parts and multi-part concrete mast produced according to this process
JPH0473381A (en) * 1990-07-13 1992-03-09 Nippon Chikou Kk Independent electric pole and its pole erecting construction
JP2004011210A (en) * 2002-06-05 2004-01-15 Fuji Ps Corp Main tower for wind-power generation facility
ES2476599T3 (en) * 2007-12-12 2014-07-15 Senvion Se Anchorage of a tower of a wind power installation
WO2011030199A2 (en) * 2009-09-11 2011-03-17 Stefano Knisel Improved foundation for a wind turbine tower
US20130269286A1 (en) * 2010-06-14 2013-10-17 Max Bögl Bauunternehmung GmbH & Co. KG Tower of a Wind Power Plant and Method for Producing a Tower of a Wind Power Plant
WO2015131174A1 (en) * 2014-02-28 2015-09-03 University Of Maine System Board Of Trustees Hybrid concrete - composite tower for a wind turbine
CN104612455A (en) * 2015-03-04 2015-05-13 陈宝民 Integrated structure of concrete tower drum and foundation of fan

Also Published As

Publication number Publication date
ES2726226B2 (en) 2021-05-28

Similar Documents

Publication Publication Date Title
ES2794126T3 (en) Frame structure and method of construction of the same
ES2246734B1 (en) PREFABRICATED MODULAR TOWER.
US3991532A (en) Sign post construction
US3872635A (en) Multi-unit building construction
ES2565411T3 (en) Concrete slab or slab reinforced with casetones
ES2356546B2 (en) A FORGED OR SIMILAR STRUCTURAL ELEMENT LIGHTENED BY WHICH THEY CAN DISCURRATE RECORDABLE FACILITIES.
ES2764468B2 (en) FOUNDATION FOR WIND TOWERS
CN102605858A (en) Building structure and construction method
KR100947852B1 (en) Joint Structure Betweeen Street Lighting Pole and Base
PT2239398E (en) Tower
ES2726226B2 (en) PREFABRICATED CONCRETE POST
KR101750404B1 (en) Structure using same time pouring process for wall and foundation concrete and construction method therefor
US4232495A (en) Precast units for constructing cooling towers and the like
ES2835346B2 (en) Concrete foundation for wind tower and method for its installation
ES2761655B2 (en) Foundation for a wind turbine tower and method of making said foundation
US20060207214A1 (en) Method of constructing multi-storey building balconies
WO2021144416A1 (en) Module of substantially parallelepipedal shape intended to create a modular dwelling, and modular dwelling
KR100996734B1 (en) Foundation assembly for trafic signal support structure and foundation using the same
KR20100101799A (en) Elementary block for supporting of steel pipe
ES1249434U (en) PREFABRICATED FOUNDATION FOR POSTS (Machine-translation by Google Translate, not legally binding)
GB2074211A (en) Suspended roof
ES2288784B1 (en) IMPROVED PREFABRICATED PILLAR SYSTEM.
KR200336491Y1 (en) The fixing device of landlord by city reclaim
KR200257292Y1 (en) The concrete form constructed basic concrete structure of pole in electric railroads
ES2726248A1 (en) PREFABRICATED FOUNDATION FOR POSTS (Machine-translation by Google Translate, not legally binding)

Legal Events

Date Code Title Description
BA2A Patent application published

Ref document number: 2726226

Country of ref document: ES

Kind code of ref document: A1

Effective date: 20191002

FG2A Definitive protection

Ref document number: 2726226

Country of ref document: ES

Kind code of ref document: B2

Effective date: 20210528