EP4032775A1 - String transport system - Google Patents
String transport system Download PDFInfo
- Publication number
- EP4032775A1 EP4032775A1 EP20868100.7A EP20868100A EP4032775A1 EP 4032775 A1 EP4032775 A1 EP 4032775A1 EP 20868100 A EP20868100 A EP 20868100A EP 4032775 A1 EP4032775 A1 EP 4032775A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- track structure
- rail
- level
- cords
- supports
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005096 rolling process Methods 0.000 claims abstract description 9
- 230000013011 mating Effects 0.000 claims abstract description 7
- 230000000284 resting effect Effects 0.000 claims abstract description 6
- 238000006073 displacement reaction Methods 0.000 claims abstract description 5
- 238000010276 construction Methods 0.000 abstract description 3
- 238000011161 development Methods 0.000 abstract description 3
- 238000013461 design Methods 0.000 description 9
- 239000000463 material Substances 0.000 description 9
- 238000013459 approach Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000003989 dielectric material Substances 0.000 description 3
- 230000006872 improvement Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000013016 damping Methods 0.000 description 2
- 238000003912 environmental pollution Methods 0.000 description 2
- 239000012634 fragment Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000012212 insulator Substances 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 238000004026 adhesive bonding Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000000615 nonconductor Substances 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 229920005596 polymer binder Polymers 0.000 description 1
- 239000002491 polymer binding agent Substances 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000000699 topical effect Effects 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61B—RAILWAY SYSTEMS; EQUIPMENT THEREFOR NOT OTHERWISE PROVIDED FOR
- B61B5/00—Elevated railway systems without suspended vehicles
- B61B5/02—Elevated railway systems without suspended vehicles with two or more rails
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61B—RAILWAY SYSTEMS; EQUIPMENT THEREFOR NOT OTHERWISE PROVIDED FOR
- B61B13/00—Other railway systems
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B25/00—Tracks for special kinds of railways
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D18/00—Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D6/00—Truss-type bridges
Definitions
- the present invention relates to the above-ground transport systems of string type with rail track structure related to overpass-type tracks. It can be used in development of both inner-city highways and in construction of intercity and international transport systems.
- the logical solution to improve the existing track structures are the string transport systems by Yunitski.
- Linear transport system by Yunitski which includes at least one vehicle having a drive unit and guided by wheels on at least one rail containing a head and connected to a prestressed longitudinal element mounted on supports located on foundation.
- Prestressed longitudinal element of this transport system is made in the form of at least one string connected by gaskets of variable height with head of each rail along the whole length.
- the rail head is connected to DC or AC electric power source, and the rail is connected to the support by means of electric insulator.
- Rails in the said transport system are connected to each other by means of transverse strips, which are equipped with electric insulators and dampers.
- the supports are rigid and movable, whereas the rail track is connected to the movable support by a mechanism of mutual relative longitudinal displacement, including, for example, with use of a rod, and/or a mechanism for adjusting its position relative to the support and foundation, and/or by means of a damper [1].
- Transport system by Yunitski which includes at least two pretensioned rail cords in the form of load-bearing members enclosed in bodies (casings) with rolling surfaces mating therewith, for vehicles.
- Rail cords form two track structures.
- Loaded and empty vehicles [2] are installed on rail cords of track structures.
- Yunitski which comprises a two-level string trussed track structure mounted on the foundation, resting on intermediate supports; each level whereof is equipped with two rail cords made in the form of prestressed load-bearing members, enclosed in corresponding bodies with mating therewith rolling surfaces for wheeled vehicles and forming a track.
- both rail cords of each track are interconnected in spans between adjacent supports by means of two-level trussed track structure in the form of zigzag-oriented rod elements, forming triangles with lower and upper rail cords and located on the outer sides of those rail cords, wherein at each level of the track structure, left and right rail cords are connected to each other by cross bulkheads installed in junction units of rod elements and rail cords [3].
- a limitation to the wide use of the said transport system is the insufficient rigidity of its track structure, caused by the significant height of the track structure (considering the height of vehicles) relative to the width of its wheel track.
- the dynamic stability of the track structure in spans between the adjacent supports is also limited.
- the object of the invention is to solve the following technical tasks:
- the technical aims are also achieved provided that the distance R, m, between the junction units of rod elements and rail cords of the lower level of the trussed track structure in each span is made multiple of the distance between the supports.
- Tackling the set tasks is also ensured by the fact that the assembly connection of the transverse beam with the support is made in the form of a pivot lever.
- the rail cord is current-carrying with the possibility of connection to a source of electric power of direct or alternating current.
- the inventive string transport system by Yunitski as shown on Figure 1 , comprises two rail cords of lower 3 level mounted on the foundation 1 between the supports 2 (anchored 2a, resting on intermediate 2b ), and two rail cords of upper 4 level of the track structure, arranged above them.
- Anchor supports 2 a may be buildings and structures with specially equipped boarding and loading areas in the form of loading and unloading stations: passenger for passenger routes and cargo for freight routes (not shown on the Figures).
- Rail cords of the lower 3 and upper 4 levels of the track structure are made (see Figs. 1 and 4 ) in the form of prestressed load-bearing members 5 enclosed in the respective bodies 6 (see Fig. 3 ).
- one or more bundles made from high strength steel wire load-bearing elements may be used, either from rods assembled in a single bundle, or dispersed along the cross-section of the cavity (empty space) of the body 6, or one or more standard twisted or untwisted steel ropes, as well as cords, strips, bands or other extended elements made of any high-strength materials.
- the cavities in the body 6 between the elements of the load-bearing member 5 can be filled with a hardening material 7 based on polymer binders, composites, cement mixtures and/or similar hardening materials, which are rigidly connected into one piece by the load-bearing member 5 and the body 6 with its associated rolling surface 8 (see Figs. 1 and 4 ). concreting thereby as a whole the structure of the rail cord.
- the rolling surface 8 may be formed by the surface of the body 6 itself.
- the body 6 of the rail cord 3 and/or 4 may partially serve the functions of the prestressed load-bearing member 5, if it has also been stressed by tensioning during assembling of the structure.
- the rail cords of the lower 3 and upper 4 levels with mating therewith rolling surfaces 8 for the wheeled vehicles 9 and, accordingly, the tracks formed by them are made of an innovative modification - prestressed by tensioning in the longitudinal direction, those rail cords are load-bearing rigid beams of the lower and upper chords of the span arrangement (superstructure) of the two-level trussed track structure.
- FIG. 3 and 4 An image of cross section and fragment of frontal view of the span arrangement of the track structure of the proposed transport system (see Figs. 3 and 4 ) shows that the tracks of its rail cords of lower 3 and upper 4 levels are interconnected in the spans G between adjacent supports 2 into two-level trussed track structure by means of zigzag-oriented rod elements 10 forming triangles with the rail cords of the lower 3 and upper 4 levels.
- the left 3 L (4 L ) and, correspondingly, the right 3 P (4 P ) rail cords are connected to each other by cross bulkheads 11, which are installed in junction units 12 of zigzag-oriented rod elements 10 and rail cords (see Figs. 2 - 4 ), whereby zigzag-oriented rod elements 10 are placed on the outer sides of those rail cords, which ensures the formation of the profile of the two-level trussed track structure with minimal aerodynamic drag and high parameters of its rigidity (including torsional) and dynamic stability in the spans between adjacent supports 2.
- the length S , m, of the cross bulkhead 11 is defined as the distance between the vertical planes A and B of the respective junction units 12 of the zigzag-oriented rod elements 10 with the rail cords of the lower 3 and upper 4 levels of the track structure.
- the structural coupling (connection) of the cross bulkheads 11 to the bodies 6 of rail cords may be accomplished by any of the known methods: welding, riveting, threaded connection, gluing, kinematic engagement - through various guides made integral with mating elements located on the opposite ends of cross bulkheads 11, by attaching those opposite ends of cross bulkheads 11 to internal and/or external surfaces of bodies 6 of rail cords by various combinations of known joint methods (not shown on the Figures).
- Transverse beam 13 is fixed on support 2. It is essential that the transverse beam 13 is movably fastened along the longitudinal axis of the track structure by means of assembly units 14, which in turn are placed in two, respectively, left N and right M , vertical longitudinal planes.
- assembly units 14 which in turn are placed in two, respectively, left N and right M , vertical longitudinal planes.
- an important feature of the proposed transport system is that the rail cords of the lower 3 level of the two-level trussed track structure are connected to each other in the junction units 12 of the zigzag-oriented rod elements 10 by cross bulkheads 11, and fixed on the transverse beams 13 at the locations of those cross bulkheads 11 and the junction units 12 (see Fig. 3 ) by any known method, e.g. welding, or kinematically (not shown on the Figures).
- any of the non-limiting embodiments of the inventive string transport system various non-exclusive embodiments of the cross bulkhead 11 and its connection to the rail cords (in junction units 12) are feasible, one of which is shown on Figs. 3 and 4 .
- the spans G between the adjacent supports are made with a length multiple of the distance R , m, between the adjacent cross bulkheads 11 of the lower 3 level of the track structure, and between the assembly units 14 of the transverse beam 13, by means of (as an embodiment) fixing it in a certain position (in the vertical latitudinal plane W (see Fig.
- cross bulkhead 11 is installed in junction unit 12 of zigzag-oriented rod elements 10 of track structure of lower 3 level and is located along longitudinal axis X of transverse beam 13, whereby vertical planes A and B of arrangement of zigzag-oriented rod elements 10 are shifted relative to assembly units 14 of transverse beam 13 to its center, and distance L , m, from plane A ( B ) the arrangement of zigzag-oriented rod elements 10 of the trussed track structure up to assembly unit 14 of the transverse beam 13 (see Figs.
- Embodiment of the two-level trussed track structure with zigzag-oriented rod elements 10 located on its outer side and the arrangement of cross bulkheads 11 in junction units 12 of zigzag-oriented rod elements 10 of the trussed track structure when the terminal cross bulkhead 11 of the span structure is located and fixed along the longitudinal axis X of the transverse beam 13, for example, pivot-lever secured on the support 2, provides, if observed are the empirically obtained ratios of dimensions of the height H , m, of the trussed track structure, and distance L , m, from the plane of positioning of zigzag-oriented rod elements 10 of the trussed track structure up to corresponding assembly unit 14 of transverse beam 13, favorable redistribution of active loads and internal stresses in all structural elements of the two-level trussed track structure of the string transport system. This leads to a significant increase in the rigidity and dynamic stability of the trussed structure of the span arrangement of the track structure.
- the optimization of the support surface of the track structure plays a significant role, which, in turn, depends on the length K , m, of transverse beam 13, and height H , m, of two-level trussed track structure, defined by the dependencies: 0.02 ⁇ L / H ⁇ 0.5 , and 0.4 ⁇ S / K ⁇ 0.95 ,
- the values specified in the ratio (1) correspond to the optimal range of interdependence between the height H , m, of trussed track structure (and, accordingly, the height of the location of the center of mass of the span arrangement and the value of the support surface of such track structure.
- the ratio (1) is less than 0.02, then the dynamic stability of the span arrangement of the track structure is significantly reduced due to its low torsional rigidity.
- the ratio (1) is more than 0.5, then the material capacity of the entire structure, and therefore the cost of the transport system, are unjustifiably increased.
- the assembly units 14 of the transverse beam 13 are movable, for example, in the form of a pivot lever 15, a decrease in local overstresses in the rail cords of the track structure is attained, caused by temperature deformation and the impact of the wheeled vehicles 9, which, as a result, are redistributed along the entire length of the track of the proposed string transport system.
- the rail cord 3 (4) may be made current-carrying with the possibility of connection to a direct or alternating current electric power source. This will allow to electricize transport services and reduce environmental pollution.
- the rail cords 3 and 4 can be connected to the trussed track structure by means of electrical insulators, as well as that the trussed track structure can be made of an electric insulating (dielectric) material (not shown on the Figures).
- An alternative embodiment of the proposed string transport system is to provide the connection of rail cord 3 (4) with cross bulkhead 11 with electric insulators (not shown on the Figures) for isolating from each other the rail cords in each track, which increases the reliability, safety and efficiency of the entire system.
- cross bulkhead 11 is made of an electric insulating (dielectric) material.
- the cross bulkhead 11 is provided with a damper (not shown on the Figures).
- an electric insulator can be used as a damper.
- the transverse beam 13 may be connected to the string trussed track structure by an electric insulator (not shown).
- the transverse beam 13 may also be made of an electric insulating (dielectric) material.
- transverse beam 13 of the above dimensions pivot-lever connected to the support 2, and the corresponding positioning on the said transverse beam 13 of the cross bulkhead 11 of lower chord of the trussed span structure; through which, as an embodiment, it is connected to the transverse beam 13, and which is also made and installed in the structure in accordance with the parameters indicated above.
- the positioning of the cross bulkheads 11 between the rail cords 3 and 4 of the trussed structure of the span arrangement of the two-level trussed track structure is determined by the terms of request for proposal for the design thereof, according to which alternative versions of the proposed string transport system are possible, one variant of which is the implementation of spans G between adjacent supports 2 of length multiple of the distance R , m, between the junction units 12 of the zigzag-oriented rod elements 10 and the rail cords of the lower 3 level of the track structure.
- the distance R , m, between the junction units 12 of the zigzag-oriented rod elements 10 and the rail cords of the lower 3 level of the trussed track structure in each span G may be a multiple of the distance between the adjacent supports 2.
- trussed structures in various spans G can differ in spacing (not shown on the Figures) in positioning of their structural elements, for example, cross bulkheads 11.
- the construction of the represented string transport system by Yunitski includes installation on the foundation 1 of supports 2 and appropriately arranged and pivot-levered fixation thereon of transverse beams 13 of the specified length K , m, and the subsequent assembly in spans G between adjacent supports 2 of the span arrangements of the two-level trussed string track structure.
- lower and upper chords of this two-level trussed string track structure are constructed, each of them formed by left and right rail cords connected to each other by cross bulkheads 11 uniformly distributed in span G.
- the side faces of the two-level trussed string track structure are made in the form of zigzag-oriented rod elements 10 forming triangles with the rail cords of the lower 3 and upper 4 levels, and the junction units 12 of zigzag-oriented rod elements 10 with cross bulkheads 11 are arranged in respective vertical longitudinal planes A and B .
- the cross bulkheads 11 of the rail cords of the lower level 3 are arranged in a certain way on the transverse beams 13, fixed on those transverse beams 13 by any of the known methods, after which the rail cords 3 and 4 are equipped with wheeled vehicles 9, and the rail cords, which are made current-carrying, are connected to DC or AC electric power source.
- the string transport system by Yunitski of the described structure in the most general case of a variety of alternative embodiments, operates as described below.
- transverse beams 13 made with the above dimensions and properly fixed, increase the support surface of the two-level trussed track structure and reduce the influence of the tipping moment from the side of the rail cord of the upper level 4, when the wheeled vehicle 9 moves along it at its maximum load.
- the claimed arrangement of the string transport system by Yunitski proposed in the present technical approach allows to attain the intended targets and, at the same time, possesses a set of distinguishing features different from the known technical solutions, which meet the criteria of the invention "novelty” and “key distinctive features” (inventive step), which makes it possible to regard the proposed technical approach as inventive one.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Transportation (AREA)
- Railway Tracks (AREA)
- Rod-Shaped Construction Members (AREA)
- Electric Cable Arrangement Between Relatively Moving Parts (AREA)
- Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
Abstract
Description
- The present invention relates to the above-ground transport systems of string type with rail track structure related to overpass-type tracks. It can be used in development of both inner-city highways and in construction of intercity and international transport systems.
- The logical solution to improve the existing track structures are the string transport systems by Yunitski.
- Linear transport system by Yunitski is known, which includes at least one vehicle having a drive unit and guided by wheels on at least one rail containing a head and connected to a prestressed longitudinal element mounted on supports located on foundation. Prestressed longitudinal element of this transport system is made in the form of at least one string connected by gaskets of variable height with head of each rail along the whole length. Hereby, the rail head is connected to DC or AC electric power source, and the rail is connected to the support by means of electric insulator. Rails in the said transport system are connected to each other by means of transverse strips, which are equipped with electric insulators and dampers. Furthermore, in the above-mentioned transport system, the supports are rigid and movable, whereas the rail track is connected to the movable support by a mechanism of mutual relative longitudinal displacement, including, for example, with use of a rod, and/or a mechanism for adjusting its position relative to the support and foundation, and/or by means of a damper [1].
- The disadvantages of such transport system are the insufficient rigidity and dynamic stability of its track structure in the spans between the supports.
- Transport system by Yunitski is known, which includes at least two pretensioned rail cords in the form of load-bearing members enclosed in bodies (casings) with rolling surfaces mating therewith, for vehicles. Rail cords form two track structures. Loaded and empty vehicles [2] are installed on rail cords of track structures.
- The disadvantages of this transport system are the insufficient rigidity and dynamic stability of the second level of its track structure, which especially affects the transportation of massive goods.
- At the current level of transport development, the topical issue becomes the task of elaborating a transport system on the basis of the principles of mechatronics, which is characterized by high speed of movement and load capacity / traffic performance, low cost, zero environmental pollution, negligible need for useful land, while ensuring economy and maximum safety.
- The closest to the proposed technical essence and the achieved positive effect is the well-known string transport system by Yunitski, which comprises a two-level string trussed track structure mounted on the foundation, resting on intermediate supports; each level whereof is equipped with two rail cords made in the form of prestressed load-bearing members, enclosed in corresponding bodies with mating therewith rolling surfaces for wheeled vehicles and forming a track. Hereby, both rail cords of each track are interconnected in spans between adjacent supports by means of two-level trussed track structure in the form of zigzag-oriented rod elements, forming triangles with lower and upper rail cords and located on the outer sides of those rail cords, wherein at each level of the track structure, left and right rail cords are connected to each other by cross bulkheads installed in junction units of rod elements and rail cords [3].
- A limitation to the wide use of the said transport system is the insufficient rigidity of its track structure, caused by the significant height of the track structure (considering the height of vehicles) relative to the width of its wheel track. For the same reason, in this technical solution, the dynamic stability of the track structure in spans between the adjacent supports is also limited.
- The object of the invention is to solve the following technical tasks:
- increasing the rigidity of the track structure;
- increasing the dynamic stability of the track structure in spans between the adjacent supports.
- Technical aims according to the objects of the present invention are achieved by means of the string transport system by Yunitski, comprising two rail cords of the lower level of the track structure and above them two rail cords of the upper level of the track structure mounted on the foundation between the anchor supports resting on the intermediate supports, made in the form of prestressed load-bearing members enclosed in the corresponding bodies with mating therewith rolling surfaces for wheeled vehicles and forming two tracks, interconnected in spans G between adjacent supports by means of two-level trussed track structure in the form of zigzag-oriented rod elements, forming triangles with rail cords of the lower and upper levels and positioned on the outer sides of those rail cords, wherein at each level of the track structure, left and right rail cords are connected to each other by cross bulkheads, installed in junction units of rod elements and rail cords, whereby the rail cords of lower level are fastened on transverse beams between vertical longitudinal planes A and B, passing through junction units of zigzag-oriented rod elements, and whereby the transverse beams are connected to supports by means of assembly units, located in two vertical longitudinal planes N and M with the possibility of displacement along the axis of the track structure, whereas the transverse beams are arranged at conjunction points of corresponding latitudinal planes W passing through junction units and centers of supports, while vertical longitudinal planes A and B, containing junction units, are displaced relative to vertical longitudinal planes N and M, containing assembly units, by distance L, m, defined by the ratio:
whereas the length S, m, of cross bulkhead and the length K, m, of transverse beam between its assembly units, are related by the ratio: - The technical aims are also achieved provided that the distance R, m, between the junction units of rod elements and rail cords of the lower level of the trussed track structure in each span is made multiple of the distance between the supports.
- Tackling the set tasks is also ensured by the fact that the assembly connection of the transverse beam with the support is made in the form of a pivot lever.
- The abovementioned result is also achieved provided that the rail cord is current-carrying with the possibility of connection to a source of electric power of direct or alternating current.
- The abovementioned features characterizing the proposed technical approach are significant, since on the whole, they are sufficient to solve the given technical task and achieve the expected technical result, while each of them separately is required to identify and distinguish the proposed string transport system by Yunitski from similar technical approaches known in the prior art.
- This set of common and distinctive distinguishing features which characterize the claimed arrangement of the string transport system by Yunitski is unknown in the prior art, is new and sufficient in all cases which are covered by the scope of legal protection.
- Hereinafter, the essence of the invention will be explained by a detailed description of the arrangement and operating principle of the string transport system by Yunitski with references to the accompanying drawings (
Figs. 1 - 4 ) showing the following: -
Fig.1 - layout image of string two-level trussed track structure of transport system by Yunitski - general view (embodiment); -
Fig.2 - layout image of string two-level trussed track structure of transport system by Yunitski - top view (embodiment); -
Fig.3 - layout image of cross section of string two-level trussed track structure of transport system by Yunitski (embodiment); -
Fig.4 - layout image of fragment of string two-level trussed track structure of transport system by Yunitski - front view (embodiment). -
- 1 - foundation;
- 2 - support of track structure;
- 2a - anchor support;
- 2b - intermediate support;
- 3 - rail cord of lower level;
- 3L - left rail cord of lower level;
- 3P - right rail cord of lower level;
- 4 - rail cord of upper level;
- 4L - left rail cord of upper level;
- 4P - right rail cord of upper level;
- 5 - prestressed load-bearing member of rail cord;
- 6 - body of rail cord;
- 7 - hardening material;
- 8 - rolling surface of rail cord;
- 9 - wheeled vehicle;
- 9a - wheeled vehicle of rail cord of upper level;
- 9b - wheeled vehicle of rail cord of lower level;
- 10 - zigzag-oriented rod element of two-level string trussed track structure;
- 11 - cross bulkhead between left and right rail cords;
- 12 - junction unit of rod elements and rail cord;
- 13 - transverse beam;
- 14 - assembly unit of transverse beam with support;
- 15 - pivot lever of assembly unit of transverse beam;
- G - span between adjacent supports of transport system;
- A - vertical longitudinal plane (left), passing through junction unit of zigzag-oriented rod element with rail cord;
- B - vertical longitudinal plane (right), passing through junction unit of zigzag-oriented rod element with rail cord;
- N - vertical longitudinal plane (left) of positioning of assembly unit of transverse beam with support;
- M- vertical longitudinal plane (right) of positioning of assembly unit of transverse beam with support;
- W- vertical latitudinal plane passing through junction unit and center of support of transverse beam;
- X- longitudinal axis of transverse beam;
- R, m, - distance between junction units of rod elements and rail cords of lower level;
- L, m, - distance from the plane of positioning of zigzag-oriented rod elements to the positioning of the adjacent plane of assembly units;
- H, m, - height of two-level trussed track structure;
- S, m, - length of cross bulkhead (the distance between the planes of positioning of junction units of zigzag-oriented rod elements with rail cords);
- K, m, - length of cross bulkhead between planes of positioning of assembly units thereof.
- The essence of the invention is as follows in a more detailed description.
- The inventive string transport system by Yunitski, as shown on
Figure 1 , comprises two rail cords of lower 3 level mounted on thefoundation 1 between the supports 2 (anchored 2a, resting on intermediate 2b), and two rail cords of upper 4 level of the track structure, arranged above them. - Additionally, depending on the design option, reinforced concrete, pipe concrete, steel columnar, frame or various other structures of known modifications of supports with their individual design can perform as supports 2 - for example, in the form of towers or columns. Anchor supports 2a may be buildings and structures with specially equipped boarding and loading areas in the form of loading and unloading stations: passenger for passenger routes and cargo for freight routes (not shown on the Figures).
- Rail cords of the lower 3 and upper 4 levels of the track structure are made (see
Figs. 1 and4 ) in the form of prestressed load-bearing members 5 enclosed in the respective bodies 6 (seeFig. 3 ). - As prestressed load-
bearing member 5 of therail cord 3, cross-sectional view of which is shown onFig. 3 , one or more bundles made from high strength steel wire load-bearing elements may be used, either from rods assembled in a single bundle, or dispersed along the cross-section of the cavity (empty space) of thebody 6, or one or more standard twisted or untwisted steel ropes, as well as cords, strips, bands or other extended elements made of any high-strength materials. The cavities in thebody 6 between the elements of the load-bearing member 5 can be filled with a hardeningmaterial 7 based on polymer binders, composites, cement mixtures and/or similar hardening materials, which are rigidly connected into one piece by the load-bearing member 5 and thebody 6 with its associated rolling surface 8 (seeFigs. 1 and4 ). concreting thereby as a whole the structure of the rail cord. - Hereby, the rolling
surface 8 may be formed by the surface of thebody 6 itself. In some cases, thebody 6 of therail cord 3 and/or 4 may partially serve the functions of the prestressed load-bearing member 5, if it has also been stressed by tensioning during assembling of the structure. - Thanks to the fact that the rail cords of the lower 3 and upper 4 levels with mating therewith rolling
surfaces 8 for thewheeled vehicles 9 and, accordingly, the tracks formed by them, are made of an innovative modification - prestressed by tensioning in the longitudinal direction, those rail cords are load-bearing rigid beams of the lower and upper chords of the span arrangement (superstructure) of the two-level trussed track structure. - An image of cross section and fragment of frontal view of the span arrangement of the track structure of the proposed transport system (see
Figs. 3 and4 ) shows that the tracks of its rail cords of lower 3 and upper 4 levels are interconnected in the spans G between adjacent supports 2 into two-level trussed track structure by means of zigzag-orientedrod elements 10 forming triangles with the rail cords of the lower 3 and upper 4 levels. - Hereby, at each level of the track structure, the left 3L (4L) and, correspondingly, the right 3P (4P) rail cords are connected to each other by
cross bulkheads 11, which are installed injunction units 12 of zigzag-orientedrod elements 10 and rail cords (seeFigs. 2 - 4 ), whereby zigzag-orientedrod elements 10 are placed on the outer sides of those rail cords, which ensures the formation of the profile of the two-level trussed track structure with minimal aerodynamic drag and high parameters of its rigidity (including torsional) and dynamic stability in the spans between adjacent supports 2. - At the same time, the length S, m, of the
cross bulkhead 11 is defined as the distance between the vertical planes A and B of therespective junction units 12 of the zigzag-orientedrod elements 10 with the rail cords of the lower 3 and upper 4 levels of the track structure. - The structural coupling (connection) of the
cross bulkheads 11 to thebodies 6 of rail cords, depending on the design option, may be accomplished by any of the known methods: welding, riveting, threaded connection, gluing, kinematic engagement - through various guides made integral with mating elements located on the opposite ends ofcross bulkheads 11, by attaching those opposite ends ofcross bulkheads 11 to internal and/or external surfaces ofbodies 6 of rail cords by various combinations of known joint methods (not shown on the Figures). -
Transverse beam 13 is fixed on support 2. It is essential that thetransverse beam 13 is movably fastened along the longitudinal axis of the track structure by means ofassembly units 14, which in turn are placed in two, respectively, left N and right M, vertical longitudinal planes. At the same time, an important feature of the proposed transport system is that the rail cords of the lower 3 level of the two-level trussed track structure are connected to each other in thejunction units 12 of the zigzag-orientedrod elements 10 bycross bulkheads 11, and fixed on thetransverse beams 13 at the locations of thosecross bulkheads 11 and the junction units 12 (seeFig. 3 ) by any known method, e.g. welding, or kinematically (not shown on the Figures). - In any of the non-limiting embodiments of the inventive string transport system, various non-exclusive embodiments of the
cross bulkhead 11 and its connection to the rail cords (in junction units 12) are feasible, one of which is shown onFigs. 3 and4 . - Via such embodiment of the transport system, the peculiarity of which, unlike the prototype, is that the spans G between the adjacent supports are made with a length multiple of the distance R, m, between the adjacent cross bulkheads 11 of the lower 3 level of the track structure, and between the assembly units 14 of the transverse beam 13, by means of (as an embodiment) fixing it in a certain position (in the vertical latitudinal plane W (see
Fig. 2 ), passing through junction units 12 and center of support 2 of transverse beam 13) of cross bulkhead 11, the corresponding two-level trussed track structure is fastened, wherein cross bulkhead 11 is installed in junction unit 12 of zigzag-oriented rod elements 10 of track structure of lower 3 level and is located along longitudinal axis X of transverse beam 13, whereby vertical planes A and B of arrangement of zigzag-oriented rod elements 10 are shifted relative to assembly units 14 of transverse beam 13 to its center, and distance L, m, from plane A (B) the arrangement of zigzag-oriented rod elements 10 of the trussed track structure up to assembly unit 14 of the transverse beam 13 (seeFigs. 3 and4 ) is defined by the established dependence, - thus, increasing the base of the support surface of the track structure and, as a result, increasing its rigidity and dynamic stability in general, due to damping of longitudinal dynamic forces, the origin of which is due to temperature difference and dynamic loads arising during the movement of the wheeled vehicle 9 along the rail cords 3 and 4. - Embodiment of the two-level trussed track structure with zigzag-oriented
rod elements 10 located on its outer side and the arrangement ofcross bulkheads 11 injunction units 12 of zigzag-orientedrod elements 10 of the trussed track structure, when theterminal cross bulkhead 11 of the span structure is located and fixed along the longitudinal axis X of thetransverse beam 13, for example, pivot-lever secured on the support 2, provides, if observed are the empirically obtained ratios of dimensions of the height H, m, of the trussed track structure, and distance L, m, from the plane of positioning of zigzag-orientedrod elements 10 of the trussed track structure up tocorresponding assembly unit 14 oftransverse beam 13, favorable redistribution of active loads and internal stresses in all structural elements of the two-level trussed track structure of the string transport system. This leads to a significant increase in the rigidity and dynamic stability of the trussed structure of the span arrangement of the track structure. - In achieving the required rigidity and ensuring the dynamic stability of the track structure, the optimization of the support surface of the track structure plays a significant role, which, in turn, depends on the length K, m, of
transverse beam 13, and height H, m, of two-level trussed track structure, defined by the dependencies: - where L, m, - the distance from the plane of positioning of zigzag-oriented
rod elements 10 of trussed track structure tocorresponding assembly units 14 oftransverse beam 13, - S, m, - the length of
cross bulkhead 11, - K, m, - the length of
cross bulkhead 13 between planes N and M of positioning ofassembly units 14 thereof with support 2 (seeFig.3 ). - When resting the
rail cords 3 of the lower level of the two-level trussed track structure on the intermediate support 2b through thetransverse beam 13 and thecross bulkhead 11, the parameters of which are in accordance with the values defined by the ratios (1) and (2), it is possible to guarantee, without any obstacles, the required improvement in the dynamic stability of the track structure without significantly increasing its weight. - The values specified in the ratio (1) correspond to the optimal range of interdependence between the height H, m, of trussed track structure (and, accordingly, the height of the location of the center of mass of the span arrangement and the value of the support surface of such track structure.
- If the ratio (1) is less than 0.02, then the dynamic stability of the span arrangement of the track structure is significantly reduced due to its low torsional rigidity.
- If the ratio (1) is more than 0.5, then the material capacity of the entire structure, and therefore the cost of the transport system, are unjustifiably increased.
- With the ratio (2) less than 0.5, the implementation of the design option becomes difficult without substantial overconsumption of the materials of the track structure.
- If the ratio (2) is more than 0.95, then the dynamic stability of the span arrangement (superstructure) is reduced.
- Increasing the width of the support surface of the two-level trussed track structure from the length S, m, of
cross bulkhead 11 to the length K, m, oftransverse beam 13, ensures the improvement in rigidity and dynamic stability of the trussed structure of the span arrangement in the track structure. Furthermore, the arrangement on the intermediate supports 2b oftransverse beams 13 of length K, m, defined by the ratio (2), allows, in an alternative embodiment, to install, on those intermediate supports 2b, various zones of maintenance of the transport system, for example, emergency passenger evacuation zones (not shown on the Figures). - Thanks to the fact that, as noted above, the
assembly units 14 of thetransverse beam 13 are movable, for example, in the form of apivot lever 15, a decrease in local overstresses in the rail cords of the track structure is attained, caused by temperature deformation and the impact of thewheeled vehicles 9, which, as a result, are redistributed along the entire length of the track of the proposed string transport system. - In any of the non-limiting embodiments of the proposed string transport system, various non-exclusive embodiments of the pivot levers 15 of the
assembly units 14 of thetransverse beam 13 are possible. - In accordance with any of the non-limiting design versions of the track structure of the proposed string transport system, depending on the design option in use, the rail cord 3 (4) may be made current-carrying with the possibility of connection to a direct or alternating current electric power source. This will allow to electricize transport services and reduce environmental pollution.
- It will be apparent to a specialist skilled in the art that, in the present embodiment, the
rail cords - An alternative embodiment of the proposed string transport system is to provide the connection of rail cord 3 (4) with
cross bulkhead 11 with electric insulators (not shown on the Figures) for isolating from each other the rail cords in each track, which increases the reliability, safety and efficiency of the entire system. - It is also advantageous that the
cross bulkhead 11 is made of an electric insulating (dielectric) material. - According to any of the non-limiting embodiments of the track structure, according to the design option, it is advantageous that in connection with the rail cord 3 (and 4), the
cross bulkhead 11 is provided with a damper (not shown on the Figures). - In accordance with the project specification, an electric insulator can be used as a damper.
- Alternatively, the
transverse beam 13 may be connected to the string trussed track structure by an electric insulator (not shown). - The
transverse beam 13 may also be made of an electric insulating (dielectric) material. - A significant effect on increasing the dynamic stability and rigidity of the track structure is ensured by installing of the
transverse beam 13 of the above dimensions, pivot-lever connected to the support 2, and the corresponding positioning on the saidtransverse beam 13 of thecross bulkhead 11 of lower chord of the trussed span structure; through which, as an embodiment, it is connected to thetransverse beam 13, and which is also made and installed in the structure in accordance with the parameters indicated above. - The positioning of the
cross bulkheads 11 between therail cords junction units 12 of the zigzag-orientedrod elements 10 and the rail cords of the lower 3 level of the track structure. In another embodiment, the distance R, m, between thejunction units 12 of the zigzag-orientedrod elements 10 and the rail cords of the lower 3 level of the trussed track structure in each span G may be a multiple of the distance between the adjacent supports 2. - As a result, trussed structures in various spans G can differ in spacing (not shown on the Figures) in positioning of their structural elements, for example, cross bulkheads 11.
- The present invention is not limited to the embodiments described and shown in the drawings, which can be amended, modified and supplemented within the scope protected by the claims.
- In any of the non-limiting embodiments of the proposed track structure and various non-exclusive versions of its design, an increase in the rigidity and dynamic stability of the string track structure in the spans G between adjacent supports is achieved, which is a priority goal of the proposed technical arrangement.
- In the most general case, the construction of the represented string transport system by Yunitski includes installation on the
foundation 1 of supports 2 and appropriately arranged and pivot-levered fixation thereon oftransverse beams 13 of the specified length K, m, and the subsequent assembly in spans G between adjacent supports 2 of the span arrangements of the two-level trussed string track structure. - For this purpose, lower and upper chords of this two-level trussed string track structure are constructed, each of them formed by left and right rail cords connected to each other by
cross bulkheads 11 uniformly distributed in span G. At the same time, the side faces of the two-level trussed string track structure are made in the form of zigzag-orientedrod elements 10 forming triangles with the rail cords of the lower 3 and upper 4 levels, and thejunction units 12 of zigzag-orientedrod elements 10 withcross bulkheads 11 are arranged in respective vertical longitudinal planes A and B. - At the final stage, the
cross bulkheads 11 of the rail cords of thelower level 3 are arranged in a certain way on thetransverse beams 13, fixed on thosetransverse beams 13 by any of the known methods, after which therail cords wheeled vehicles 9, and the rail cords, which are made current-carrying, are connected to DC or AC electric power source. - The string transport system by Yunitski of the described structure, in the most general case of a variety of alternative embodiments, operates as described below.
- During operation of the transport system, during the movement of
wheeled vehicles 9 along the rail cords of the two-level trussed string track structure, as well as due to temperature fluctuations, thanks to pivot lever, with the possibility of longitudinal displacement, installation on supports 2 oftransverse beams 13 of the given length, with a specially made and fastened thereon, two-level trussed string track structure, during its operation there occurs redistribution and damping of active loads of two-level trussed track structure of string transport system. Hereby,transverse beams 13, made with the above dimensions and properly fixed, increase the support surface of the two-level trussed track structure and reduce the influence of the tipping moment from the side of the rail cord of theupper level 4, when thewheeled vehicle 9 moves along it at its maximum load. - As a result, during practical implementation of the invention the following benefits are achieved: increase in the rigidity of the track structure, as well as improvement in its dynamic stability in spans between adjacent supports.
- Thus, the claimed arrangement of the string transport system by Yunitski proposed in the present technical approach allows to attain the intended targets and, at the same time, possesses a set of distinguishing features different from the known technical solutions, which meet the criteria of the invention "novelty" and "key distinctive features" (inventive step), which makes it possible to regard the proposed technical approach as inventive one.
-
- 1. Patent
RU Nº 2080268, IPC B61B5/02, 13/00, E01B25/22, publ. 27.05.1997 - 2. Patent
RU Nº 2475386, IPC B61B 1/00, 3/02, publ. 20.02.2013 - 3. Patent
RU Nº 2520983, IPC B61B5/02,13/00, E01B25/00, publ. 27.06.2014
Claims (4)
- String transport system, comprising two rail cords of the lower level of the track structure and above them two rail cords of the upper level of the track structure, mounted on the foundation between the anchor supports resting on the intermediate supports, made in the form of prestressed load-bearing members enclosed in the corresponding bodies with mating therewith rolling surfaces for wheeled vehicles and forming two tracks, interconnected in spans G between adjacent supports by means of two-level trussed track structure in the form of zigzag-oriented rod elements, forming triangles with rail cords of the lower and upper levels and positioned on the outer sides of those rail cords, wherein at each level of the track structure, left and right rail cords are connected to each other by cross bulkheads installed in junction units of rod elements and rail cords, characterized by that the rail cords of lower level are fastened on transverse beams between vertical longitudinal planes A and B, passing through junction units of zigzag-oriented rod elements, wherein the transverse beams are connected to supports by means of assembly units, located in two vertical longitudinal planes N and M with the possibility of displacement along the axis of the track structure, whereas the transverse beams are arranged at conjunction points of corresponding latitudinal planes W passing through junction units and centers of supports, while vertical longitudinal planes A and B, containing junction units, are displaced relative to vertical longitudinal planes N and M, containing assembly units, by distance L, m, defined by the ratio:
whereby the length S, m, of cross bulkhead, and the length K, m, of transverse beam between assembly units thereof, are related by the ratio: - The system according to claim 1, characterized by that the distance R, m, between the junction units of rod elements and rail cords of the lower level of the trussed track structure in each span G is made multiple of the distance between the supports.
- The system according to claim 1, characterized by that the assembly connection of the transverse beam with the support is made in the form of pivot lever.
- The system according to claim 1, characterized by that the rail cord is current-carrying with the possibility of connection to a source of electric power of direct or alternating current.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EA201900541A EA038766B1 (en) | 2019-09-25 | 2019-09-25 | Yunitsky string-type transport system |
PCT/BY2020/000012 WO2021056090A1 (en) | 2019-09-25 | 2020-11-24 | String transport system |
Publications (2)
Publication Number | Publication Date |
---|---|
EP4032775A1 true EP4032775A1 (en) | 2022-07-27 |
EP4032775A4 EP4032775A4 (en) | 2023-09-06 |
Family
ID=75164727
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP20868100.7A Pending EP4032775A4 (en) | 2019-09-25 | 2020-11-24 | String transport system |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP4032775A4 (en) |
CN (1) | CN115427283B (en) |
EA (1) | EA038766B1 (en) |
WO (1) | WO2021056090A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP3907117A4 (en) * | 2019-01-04 | 2022-10-05 | Yunitski, Anatoli Eduardovich | String transport system |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114808558B (en) * | 2022-04-13 | 2024-08-16 | 山东启和云梭物流科技有限公司 | Composite special-shaped flange rail system |
Family Cites Families (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0224259A (en) * | 1988-07-13 | 1990-01-26 | Toyo Electric Mfg Co Ltd | Push supply device for departure/arrival of automatic circulating ropeway |
FR2701242B1 (en) * | 1993-02-08 | 1995-04-28 | Pomagalski Sa | Transport facility on its own site for several track sections. |
CN1167467A (en) * | 1994-04-08 | 1997-12-10 | Ntl新运输系统股份有限公司 | Line transport system |
AU6289594A (en) | 1994-04-08 | 1995-10-30 | Anatoly Eduardovich Junitsky | Line transport system |
DE19646121A1 (en) * | 1996-11-08 | 1998-05-14 | Rudolf Berger | Cable-guided airship |
RU2224064C1 (en) * | 2002-05-21 | 2004-02-20 | Юницкий Анатолий Эдуардович | Transportation system and method of its building |
JP2006096057A (en) * | 2004-09-28 | 2006-04-13 | Masao Honda | Elevated track transportation, transportation system |
CN101549692A (en) * | 2008-04-01 | 2009-10-07 | 欧淼森 | Light-duty unmanned type electric vehicle and tridimensional electrified traffic lane |
CN101935978B (en) * | 2010-08-16 | 2013-02-13 | 同济大学 | Overhead cable track and special track traveling crane thereof |
CN102463994B (en) * | 2010-11-15 | 2014-11-12 | 盐城海旭数控装备有限公司 | Double-layer double-way rail compatible green transit system |
RU2475386C1 (en) | 2011-08-31 | 2013-02-20 | Анатолий Эдуардович Юницкий | Yunitsky's conveying system and method of configuring string-type conveying system |
RU2520983C2 (en) * | 2011-09-08 | 2014-06-27 | Анатолий Эдуардович Юницкий | Transportation system of yunitsky |
UA71059U (en) * | 2012-03-23 | 2012-06-25 | Семен Моисеевич Месонжник | Elevated frame system of railway transport |
CN104213477A (en) * | 2014-09-22 | 2014-12-17 | 中铁工程设计咨询集团有限公司 | Straddle type single-track double-box rectangular steel-concrete composite track beam structure |
IT201800006234A1 (en) * | 2018-06-12 | 2019-12-12 | ROPE TRANSPORT SYSTEM | |
CN211547106U (en) * | 2020-01-19 | 2020-09-22 | 羿鹏轨道交通开发(上海)有限公司 | Track beam for suspension type monorail transit |
-
2019
- 2019-09-25 EA EA201900541A patent/EA038766B1/en unknown
-
2020
- 2020-11-24 EP EP20868100.7A patent/EP4032775A4/en active Pending
- 2020-11-24 WO PCT/BY2020/000012 patent/WO2021056090A1/en unknown
- 2020-11-24 CN CN202080081946.9A patent/CN115427283B/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP3907117A4 (en) * | 2019-01-04 | 2022-10-05 | Yunitski, Anatoli Eduardovich | String transport system |
Also Published As
Publication number | Publication date |
---|---|
EP4032775A4 (en) | 2023-09-06 |
WO2021056090A1 (en) | 2021-04-01 |
CN115427283B (en) | 2024-06-11 |
EA038766B1 (en) | 2021-10-15 |
EA201900541A1 (en) | 2021-03-31 |
CN115427283A (en) | 2022-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP4032775A1 (en) | String transport system | |
RU2325293C2 (en) | Stringed transportation system of yunitsky and methods of stringed transportation system build-up | |
CN101935978B (en) | Overhead cable track and special track traveling crane thereof | |
EP3560786B1 (en) | Transport system | |
CN109653077B (en) | Three main cable double-tower column suspension bridge | |
RU2475386C1 (en) | Yunitsky's conveying system and method of configuring string-type conveying system | |
CN209907178U (en) | Three-main-cable double-tower-column suspension bridge | |
CN112770955B (en) | You Nici-based transportation system and method of manufacturing and assembling same | |
EP3395637B1 (en) | Communications system | |
EP3907117B1 (en) | String transport system | |
US20220205196A1 (en) | EA Box Girder System | |
CN111094100B (en) | Truss type track structure and guide rail | |
EP3702231B1 (en) | String track structure | |
EP3992049A1 (en) | Transport system | |
CN113957755A (en) | Medium-low speed magnetic levitation traffic combined U-shaped beam structure | |
CN113584962A (en) | Rubber-tyred tramcar double-box steel-concrete combined track beam structure and construction method thereof | |
Yi et al. | Design of a rail–road asymmetrical low-pylon cable-stayed bridge with a main span of 588 m | |
EP4029754A1 (en) | Method of producing an ultra-high-speed transport complex | |
CN111979896B (en) | Groove-shaped combination beam of pre-buried profile steel | |
US20220205194A1 (en) | EA I-U-T Girder System | |
CN115397712A (en) | Transport system | |
Kenter | The elevated metro structure in concrete, UHPC and composite | |
EA044147B1 (en) | UNITSKY TRANSPORT SYSTEM | |
Stetsko | Development of classification for bearing system prestressed structures | |
Shivakumar | Strengthening of existing timber stringer bridges by the addition of steel stringers |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20220421 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
XX | Miscellaneous (additional remarks) |
Free format text: THE FILING DATE OF THE INTERNATIONAL APPLICATION IS WITHIN TWO MONTHS FROM THE DATE OF EXPIRATION OF THE PRIORITY PERIOD (R. 26BIS.3 PCT). |
|
A4 | Supplementary search report drawn up and despatched |
Effective date: 20230803 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E01D 18/00 20060101ALI20230728BHEP Ipc: E01D 6/00 20060101ALI20230728BHEP Ipc: E01B 25/00 20060101ALI20230728BHEP Ipc: B61B 13/00 20060101ALI20230728BHEP Ipc: B61B 5/02 20060101AFI20230728BHEP |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
RAP3 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: UNITSKY, ANATOLI EDUARDOVICH |
|
RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: UNITSKY, ANATOLI EDUARDOVICH |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20240711 |